Page 1

OFFICIAL 
___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board
On:  20 November 2025
___________________________________________________________________
Report by: The Director of Finance and Resources and the Chief Executive
Services 
___________________________________________________________________
Heading: Contract Authorisation Report for Erskine Civic Plaza (RC-CPU-25-
007)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract for Erskine Civic Plaza (RC-CPU-25-007) to Covanburn
Contracts Limited. 
1.2 The recommendation to award the Contract follows a procurement
exercise conducted in accordance with the Renfrewshire Council’s
Standing Orders Relating to Contracts for a below Regulated (Works)
Contract using the below Regulated value Open Procedure. 
1.3 A Contract Strategy was approved by the Interim Corporate
Procurement Manager on 13 August 2025 and Head of Economy &
Development Services on 12 August 2025.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

OFFICIAL
2.1 Authorises the Head of Corporate Governance to award a Works
Contract in the form of NEC3 Engineering and Construction Short
Contract April 2013 incorporating the additional and amended ‘Z’
clauses, for Erskine Civic Plaza (RC-CPU-25-007) to Covanburn
Contracts Limited (Co. no. SC263761):
2.2  Authorises the award of the Total of the Prices of £494,881.21
excluding VAT. 
2.3  Authorises a contingency spend of £98,976.24 excluding VAT which
equates to 20% of the Total of the Prices.
2.4  Authorises a total Approved Contract Value of £593,857.45 excluding
VAT (which is the Total of the Prices plus the contingency spend).
2.5 Note that the starting date is anticipated to be 5 January 2026, and the
completion date is 22 weeks from the starting date.  If there is a change
to these dates then, the actual dates will be as stated in the Award
Schedule to the Council’s Letter of Acceptance to Covanburn Contracts
Limited.
______________________________________________________
3. Background
3.1 This procurement exercise is for the appointment of a contractor to
carry out the construction of a multi-functional civic plaza within Erskine
Town Centre, with associated soft landscaping, lighting and street
furniture. The project will create a new active route and new blue/green
habitats.
3.2 A Prior Information Notice (PIN) was issued on the Public Contracts
Scotland portal on 10 July 2025 to advertise the opportunity in advance
of the issue of the Contract Notice.  
3.3                 The Contract Notice was published on the Public Contracts Scotland
advertising portal on 14 August 2025 with tender documentation
available for downloading from Public Contracts Scotland – Tender
portal from this date. 
3.4 During the live tender period, 31 organisations expressed an interest in
the tender.  By the closing date set for return of electronic tender
submissions, 12pm on 11 September 2025, 5 organisations submitted
a response, 9 organisations declined to respond, and 17 organisations
did not respond.

Page 3

OFFICIAL
3.5 In accordance with the Renfrewshire Council’s Standing Orders relating
to Contracts, standing order 11.5, each Tenderer was required to
complete a Single Procurement Document Scotland (SPD) to be
submitted as part of their tender submission. All 5 SPDs were
evaluated against a pre-determined set of Criteria in the SPD by
representatives from the following Council services: Chief Executive
Service (Economy & Development Services), the Corporate Procurement
Unit, Corporate Risk and Corporate Health & Safety.
3.6  1 tender submission failed to submit a completed Contractor’s Offer by
the tender deadline. Another tender submission failed to comply with
the information and instructions in the ITT and was deemed Abnormally
Low. Both tender submissions were deemed non-compliant and
excluded from the procurement process. The remaining 3 tender
submissions complied with the minimum selection criteria of the SPD
and each Tender Submission was further evaluated against the Award
Criteria of 60% Quality and 40% Price.
3.7 The scores relative to the Award Criteria for each of the 3 tender
submissions are noted below:
Tenderer Name Price Score
(40%)
Quality
Score (60%)
Total Score
(100%)
Covanburn Contracts
Limited 40.00% 55.50% 95.50%
Landscapes and
Contracts Limited 34.79% 49.75% 84.54%
JH Civil Engineering
Limited 15.31% 48.00% 63.31% 
3.8 The evaluation of tender submissions received identified that the
submission by Covanburn Contracts Limited is the most economically
advantageous tender.
3.9 The form of Contract is NEC3 Engineering and Construction Short
Contract April 2013 incorporating the additional and amended ‘Z’
clauses.
3.10 The Contract is being part funded by the UK Government's Shared
Prosperity Fund and Scottish Government's Place Based Investment
Programme.
3.11 Community benefits were requested as part of the tender and
Covanburn Contracts Limited have offered the following community
benefits:

Page 4

OFFICIAL
Community Benefit Outcome Description  No of
People /
Activity
Work Experience Placement for an individual 16+
years of age
1
Work Experience Placement for an individual in full
time education
2
Commitment to ensure that supply chain
opportunities are prioritised for Renfrewshire based
businesses
1
Financial Support for a Social Enterprise or other
approved community initiative
2
Non-financial support for a Social Enterprise or other
approved community initiative
1
___________________________________________________________________
Implications of the Report
1. Financial - The Approved Contract Value of £593,857.45 for the      
22-week Contract will be met through 3 sources: 
• Renfrewshire Council Capital funds £243,857.45
• Shared Prosperity Fund (UK Government) £200,000
• Place Based Investment Programme (Scottish Government)
£150,000 
The £200,000.00 Shared Prosperity Fund allocation requires to be
spent by the end of March 2026.
After consultation, the Council’s Neighbourhood Services department
has confirmed that no significant additional resource is required for
ongoing maintenance of the project.  The first year of maintenance
costs have been included in Covanburn Contracts Limited approved
contract value.  
2. HR & Organisational Development - None directly arising from this
report. 
3. Community/Council Planning –  
Place - working together to enhance wellbeing across communities
• Adopting a 'place shaping' approach to developing our communities
- working together to maximise our collective impact and influence
across economic, social, physical, cultural and environmental policies
and practices.

Page 5

OFFICIAL
• Demonstrating that Renfrewshire is a great place to grow up, it's a
place of opportunity for those that live and work here, and it's a
brilliant place for a day out.
Green - leading Renfrewshire to Net Zero
• Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
• Integrating climate considerations into our long term strategic and
financial planning as an organisation. 
Living our Values - making a difference together
• Ensuring Renfrewshire Council delivers Best Value for our citizens
and customers, that we are a well governed, effective organisation. 
4. Legal - This procurement exercise was carried out as an Open
Procedure for a below Regulated value works contract in accordance
the Council’s Standing Orders relating to Contracts. 
5. Property/Assets - Delivery of the works will return a long-term area of
vacant and derelict land to a positive use for the local community. 
6. Information Technology - None directly arising from this report. 
7. Equality & Human Rights - None directly arising from this report.
8. Health & Safety – Covanburn Contracts Limited health and safety
submissions have been evaluated by the Corporate Health and Safety
team and met the Council’s requirements regarding health and safety.
9. Procurement – The procurement procedures outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency and modern Government.
10. Risk - Covanburn Contracts Limited insurances have been assessed
and evaluated to confirm that they have met the requirements
regarding insurable risk.
11. Privacy Impact - None directly arising from this report.
12. Climate Risk– The Scottish Government Sustainability Test was
carried out and the risks associated with this has been assessed as
High Risk. Mitigations to address this high risk are that the project will
include enhanced landscaping, biodiversity and climate resilience.

Page 6

OFFICIAL
Covanburn Contracts Limited have developed a Carbon Reduction
Plan that aims to reduce their emissions in line with the Scottish
Government’s targets that includes the reduction of carbon emissions,
waste minimisation and implementation of recycling innovation; all of
which will be considered throughout the lifetime of the Contract.
13. Children’s Rights – None directly arising from this report.
14. Cosla Policy Position – None directly arising from this report.
_________________________________________________________
List of Background Papers - None 
__________________________________________________________________ 
Author:           Louise Bishop, Procurement Adviser -
louise.bishop@renfrewshire.gov.uk