CAR for the Design, supply and installation of Lagoon Active Play

Renfrewshire Council · 20 November 2025
Back to Finance, Resources and Customer Services Policy Board — 20 November 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

OFFICIAL 
___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board 
On:  20 November 2025
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Contract Authorisation Report for the Design, supply and installation of
Lagoon Active Play (RC-CPU-25-139)
___________________________________________________________________
1. Summary 
1.1. The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Delivery
Agreement (“Contract”) for the design, supply and installation of Lagoon
Active Play (RC-CPU-25-139) to Alliance Leisure Services Limited
(Registered Company Number 02723797). 
1.2. The recommendation to award this Contract follows a procurement
exercise conducted in accordance with the terms of the Leisure
Development Partner for the UK Leisure Framework 2022-2026 and
Renfrewshire Council’s Standing Orders relating to Contracts for an above
Threshold Mixed Contract. 
1.3. A Contract Strategy endorsed by Renfrewshire Leisure Limited trading as
OneRen (“OneRen”), the Council’s tenant, was approved by the Head of
Facilities Management and Property Services and the Interim Corporate
Procurement Manager in October 2025. 
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

OFFICIAL
2.1. Authorises the Head of Corporate Governance to award a Contract to
Alliance Leisure Services Limited (Registered Company Number
02723797) (“Alliance”), made following a direct appointment under the
Leisure Development Partner for the UK Leisure Framework 2022-2026.
Please note that Alliance will wholly subcontract the requirements through
the following arrangements: 
• Contract Administrator, Quantity Surveyor and project management to
Axiom Project Services Limited (Registered Company Number
SC358148);
• Principal Designer (CDM) to ABT Safety Limited (Registered Company
Number SC453051); 
• Architect to Construction Design Architects Limited (Registered
Company Number SC352990);
• Design, supply and installation of the play equipment to Play Revolution
Limited (Registered Company Number 06548374; and
• The minor building works and associated design to Thomas Johnstone
Limited (Registered Company Number SC136445). 
2.2. Authorises the Total Approved Contract value of £956,000.00 excluding
VAT (which is the total of the cost plan and includes allowance for the
Council (Client) risk). 
2.3. Authorises the Contract will commence on 8 December 2025. Building
works are anticipated to commence in April 2026 and take 15 weeks to
complete. In the event the Contract does not commence on 8 December
2025, the Contract shall run from the actual commencement date
confirmed in the Contract.   
2.4. Authorises the acceptance of a limitation on Alliance’s total liability for
insurable risk at the level of insurance maintained (£5m in the aggregate)
and a limitation of liability for uninsured losses up to the Delivery
Manager’s Fee (up to 2% of the Approved Contract Value). This is a
market position and dictated by the terms of the Framework Agreement. 
2.5. Authorises the acceptance of a limitation of liability for total insurable risk
for Sub-Consultants and the Building Contractor to the sums referred to in
3.8 below. Note, these are market position(s) and dictated by the terms of
the Framework Agreement.

Page 3

OFFICIAL
2.6. Note Alliance is required to provide the Council with Collateral Warranties
for each of the sub-contractors and sub-consultants with design
responsibility.
_________________________________________________________
3. Background 
3.1. Lagoon Leisure Centre, located in the heart of Paisley, is the flagship
leisure centre of OneRen and caters for various sporting activities and
events including swimming, fitness, aerobics and dance. 
3.2. In 2021, as part of the Council’s cultural infrastructure programme,
OneRen on behalf of the Council entered into an Access Agreement with
Alliance Leisure Services Limited (“Alliance”) in accordance with the
Leisure Development Partner for the UK Leisure Framework 2022-2026
(“the Framework”) procedures, to review options for the Lagoon Leisure
Centre’s facilities focusing on the large six-court sports hall. The aim of
the review was to consider options for converting this sports hall, which
would complement the Council’s investment in cultural infrastructure in
Paisley town centre, increase physical activity levels, promote social
cohesion of the community, and support OneRen to sustainably deliver
leisure services into the future. 
3.3. As part of the Access Agreement, Alliance have prepared a RIBA Stage 4
detailed design and cost plan based on converting the large six-court
sports hall into a state-of-the-art Active Play facility, creating an inclusive
offering for all ages including provision for children with additional support
needs (ASN). 
3.4. In accordance with the Framework call off procedures, the next stage
following completion of the RIBA Stage 4 report is for the Council to enter
into a Development Agreement (“Contract”) with Alliance as the
Development Manager to undertake the design, supply and installation of
an active play facility in the Lagoon Leisure Centre’s existing large six
court sports hall. 
3.5. The Contract includes the creation of a reception area for the family active
play area as well as a café and seating area which will be centrally
located with a good view of the 4 key play zones: 
• Baby/Toddler Soft Play 
• Adventure Zone (Junior Zone)
• TAG Active Arena
• Gymnastics area/multipurpose area suitable for ASN

Page 4

OFFICIAL
The store currently located in the hall will also be split to provide a Party
Room and a Store as part of the Contract. 
3.6. In considering use of this Framework for the Delivery Agreement phase of
the project, the Council’s CPU assessed this as a speculative Framework
in accordance with the Guidance issued in SPPN 03/2017. A risk
assessment was therefore carried out on the recommendation to use this
Framework as opposed to alternative options such as open tender or
restricted procedure and it was concluded that while other route options
may limit the Council’s exposure to potential procurement risk, the
Framework is the only route available that allows the Council to utilise the
work carried out by Alliance to date, including the RIBA Stage 4 design,
benefit from the expertise and experience of a leisure sector expert and
access to their robust and experienced supply chain, allowing
procurement of the works in time for site works to commence in Spring
2026. 
3.7. The recommendation to use the Framework and directly appoint Alliance
to progress the design, supply and installation of Lagoon Active Play has
been approved by the Interim Corporate Procurement Manager and the
Head of Property and Facilities Management as the route presenting the
best value approach. 
3.8. As part of this Contract, the total limitation of liability of Alliance’s Sub-
Consultants shall be the amounts in the aggregate referred to in the table
below.  These figures reflect standard market position. 
Nature of Consultant
/ Contractor Name Proposed PI
Limit
Architect Construction Design Architects £1m
M&E Consultant Wallace Whittle Limited £1m
Structural Engineer Struer Consulting Engineers
Limited £1m
Employer’s Agent / 
Project Manager /
Quantity Surveyor
Axiom Project Services Limited £1m
Principal Designer
CDM ABT Safety Limited £2m 
Building Contractor Thomas Johnstone Limited £2m

Page 5

OFFICIAL
3.9. The Council provided Alliance with a Community Benefit Outcome Menu
that targets 30 points for a Project of this nature and overall value. On
appointment, the Building Contractor will commit to delivering Community
Benefits and will work with the Council and Alliance to deliver to deliver
these in line with the Council’s community benefit policies.
__________________________________________________________________
Implications of the Report 
1. Financial – The total Approved Contract value is £956,000.00 (which is
the Delivery Agreement Fee consisting of the Contract Sum, Equipment
Supplier Price, Consultant Fees and Client Risk allowance) excluding
VAT for the Contract period stated at 2.3 above, will be met through the
Capital – General Services budget. The limits of liability are as detailed
within paragraph 3.8.   
2. HR & Organisational Development – None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable.
• Our Renfrewshire is well - supporting the wellness and resilience
of our citizens and communities. 
Place - Demonstrating that Renfrewshire is a great place to grow up, it
is a place of opportunity for those that live and work here.   
Economy:
- Improving lives and securing wellbeing through a stronger, inclusive
and sustainable economy, being creative, imaginative and linking
opportunities to enhance the benefits for Renfrewshire. 
Living Our Values:
- Leading positively through transition and change. 
- Delivering best value for our citizens and customers. 
4. Legal - As identified at 3.6 there are risks entering into a speculative
Framework. This is a public sector Framework which has been created
for use by all public sector bodies in the UK. As noted above there are
limited routes available for these specialised services. The Framework
has been created by Denbighshire Leisure Limited and therefore the
Council will require to conform with the Public Contracts Regulations

Page 6

OFFICIAL
2015 rather than the Scottish Public Contracts (Scotland) Regulations
2015 as part of this Contract.
In accordance with Regulation 33 of these Regulations, the Council will
require to accept the conditions as laid out by the Framework. The
Director of Finance and Resources and the Head of Corporate
Governance have been consulted during the process to date. 
5. Property/Assets - The Council’s investment in Lagoon Leisure Centre
offers the opportunity for a place-based approach to local outcomes
and integrating local services to support communities. The refurbished
sport centre will allow OneRen to offer a range of family focussed
activities for all age groups including children and young people with
additional support needs to Renfrewshire communities. 
As the works require to be undertaken in the Lagoon Leisure Centre
while the building remains operational, the Council and OneRen will
enter into Minutes of Agreement relating to the Property Agreement
and Lease as well as works licences and licences to occupy. 
6. Information Technology – None directly arising from this report 
7. Equality & Human Rights – An Equality impact assessment (EQIA)
has been developed to inform the proposals for re-design in the Lagoon
Leisure Centre, and impacted groups have been identified. The
proposals for redesign centre on creation of an active play facility
suitable and accessible for all children and young people including
those with additional support needs. The dedicated play zone as part of
the service offering has been designed with consideration to the
particular inequalities that may be faced by someone with additional
support needs and their family/ carer, particularly barriers to
participating in active play, including the provision of a sensory zone.
OneRen will continue to develop the provision for the active play facility
cognisant of potential inequalities for those with ASN, and develop a
fee structure mindful of families / young people facing barriers due to
income level. 
8. Health & Safety – None directly arising from this report 
9. Procurement – The appointment of Alliance Leisure Services Limited
through the Framework has been conducted in accordance with the
Council’s Standing Orders relating to Contract and assessment of the
Framework as noted in 3.6 of this Report.

Page 7

OFFICIAL
10. Risk – A Risk Register has been produced for the Project and will be
managed and maintained throughout the Project lifetime. 
The works will be insured by the Building Contractor and the Council is
satisfied Thomas Johnstone Limited’s insurance arrangements meet
the Council’s requirements regarding insurable risk.   
The Lagoon Leisure Centre will continue to be insured by OneRen for
the duration of the works and obligations for this will be confirmed
between the Council and OneRen in the Minute of Agreement for the
Lease and Property Agreement. 
11. Privacy Impact – None directly arising from this report 
12. Climate Risk – None directly arising from this report 
13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights. 
14. Cosla Policy Position – None directly arising from this report.
_______________________________________________________
List of Background Papers
None
___________________________________________________________________
Author:           Rebecca Park, Strategic Category Manager,