Page 1

OFFICIAL 
___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board 
On:  20 November 2025
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Contract Authorisation Report for Thistle Primary School Main Works
Contract 
___________________________________________________________________
1. Summary 
1.1. Renfrewshire Council has a requirement to build the new Thistle Primary
school (“new school”) in Dargavel Village, Bishopton (the “Project”). The
new school will have capacity for c800 pupils as well as facilities for
Community Use, including a full-size flood-lit 3G playing field. 
1.2. Hub West Scotland Limited (“HWS”) was identified as the recommended
procurement route to market under the approved terms of the Territory
Partnering Agreement (TPA). Design development has taken place in
partnership with HWS since October 2023. The current design and market
testing position represents comprehensive design proposals that meet our
expectations, a robust cost plan that aligns with the agreed budget
parameters and delivery programme that supports the Council's strategic
priorities and anticipated timelines. 
1.3. The Advanced Works Contract, approved at the Finance, Resources and
Customer Services Policy Board meeting on 11 September 2025, which
comprises of carrying out targeted civil engineering and services
preparatory works commencing November 2025, should be completed by
mid-January 2026. At the Finance, Resources and Customer Services
Policy Board meeting on 11 September 2025, it was advised that a further
report would be brought to a future board to seek approval of the award of
the Main Works Contract.

Page 2

OFFICIAL
1.4. Formal approvals are now required to progress the Project to ensure the
Project deadline is met; Finance, Resources and Customer Services
Policy Board approval is requested for a Main Works Contract with HWS,
who will wholly sub-contract all of these works to BAM Construction
Limited. 
___________________________________________________________________ 
2. Recommendations 
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
2.1. Authorises the Head of Corporate Governance to enter into a Design and
Build Development Agreement (DBDA) for Thistle Primary School Main
Works Contract with Hub West Scotland Limited (Registered Company
SC381561). Please note, for the purposes of contractual clarity this will be
by way of amendment and reinstatement of the Advance Works Contract
(i.e. the Advance Works contract will be varied to include the Main Works
phase). Please also note that HWS will wholly subcontract all these
Advance Works under this Contract to BAM Construction Limited
(Registered Company 02379469). 
2.2. Authorises the award of the Main Works Contract for £35,130,451.00
excluding VAT, to Hub West Scotland Limited (“the Contract Sum”).
Please note, this sum is inclusive of the sum of £3,894,263.40 that was
approved for the Advance Works by the Finance, Resources and
Customer Services Policy Board on 11 September 2025. 
2.3. Authorises a contingency spend of £1,756,522.55 in relation to the Main
Works Contract, which equates to 5% of the Contract Sum. 
2.4. Authorises a total Approved Contract Value for the Main Works Contract
of £36,886,973.55 (which is the total of the Contract Sum plus the
contingency spend). 
2.5. Authorises the acceptance of a Limitation on Hub West Scotland Limited’s
Liability for uninsured losses up to the value of the Contract Sum for the
Main Works Contract. To note: this is the market standard position. 
2.6. Notes that construction associated with the Main Works Contract is
anticipated to commence in February 2026 and be completed by June
2027 to facilitate the new school becoming operational by August 2027 for
the 2027/28 academic year.

Page 3

OFFICIAL
2.7. Authorise the acceptance of a Limitation of Liability on Design Consultants
to the sums referred to in 3.3 below on an each and every claim basis
except for claims relating to pollution, contamination, and asbestos, where
the limit will be in the annual aggregate. To note: this is the market
standard position.
_________________________________________________________
3. Background 
3.1  The key Renfrewshire Council (Council) critical success factor is that the
Project must be complete by June 2027 in order that the school will be
operational for pupils by the new term in August 2027. Main Works are
programmed to commence in early February 2026 and complete by June
2027. 
3.2 The Main Works Contract will comprise construction of a new three storey
primary school building for a c800 pupils and include facilities for
community use such as a full size 3G pitch and community garden space.
The Main Contract Works include all construction elements including steel
frame, roof, building façades, interior finishes, landscaping, playgrounds,
carparks and paths required to deliver an educational facility. 
3.3 As part of this Contract, the limitation of liability of HWS’s Sub-Consultants
shall be limited to the sums referred to in the table below on an each and
every claim basis except for claims relating to pollution, contamination and
asbestos where those limits will be in the annual aggregate. These figures
reflect standard market position. The limits noted below reflect the
Enabling Works position with exception of sub-limited £250,000 in
aggregate for Asbestos (JM Architects Limited). 
Legal Entity Value Terms Sub Limit 
JM Architects
Limited
£10m  any one occurrence  Asbestos: £250,000 in the
aggregate
ERZ Ltd  £5m any one claim or
series of claims
arising from the
same originating
cause
Defence costs in addition but in the
aggregate in respect of Pollution
and Contamination claims
Digital Guerrilla
Consultancy Ltd 
£2m any one claim
unlimited in the
period of Insurance
N/A

Page 4

OFFICIAL
Legal Entity Value Terms Sub Limit 
Carbon Futures
(Consultancy)
Limited
£5m  each and every
claim or loss,
excluding defence
costs
N/A
Spacezero (North)
Limited
£10m any one claim N/A
Rybka Ltd £10m any one claim
excluding costs and
expenses
Fire Safety: £10,000,000 in the
aggregate including costs and
expenses in respect of Fire Safety
Pollution: £1,000,000 in the
aggregate inclusive of defence
costs
Asbestos: £250,000 in the
aggregate inclusive of defence
costs
Jeremy Gardner
Associates Ltd
t/a Jensen Hughes 
£10m per occurrence and
aggregate
No fire/combustibility exclusion
included in the Professional
Indemnity Policy
Sandy Brown Ltd £5m any one claim Pollution:  £5,000,000 in the
annual aggregate
Asbestos: £2,000,000 in the
annual aggregate
AECOM Limited  £10m any one claim N/A
Currie & Brown UK
Limited
£10m any one claim N/A 
3.4 The Council provided HWS with a Community Benefit Outcome Menu that
targets 150 points for a Project of this overall value. The Outcome Menu
was also replicated onto the SFT themes, outcomes and measures
(TOMs) system as part of the HWS tender process. BAM Construction
Limited committed to achieving 680 points on the Community Benefit
Outcome Menu and £10.4m worth of Social, Local Economic Value
through the SFT TOMs menu. The Community Benefits will be delivered
as part of the Advance Works Contract and continue through until overall
Project completion.
___________________________________________________________________

Page 5

OFFICIAL
Implications of the Report 
1. Financial – The cost for this Main Works Contract of £36,886,973.55 
(which is the total of the Contract Sum plus the contingency spend)
excluding VAT, will be met through the Capital – General Services
budget. The limits of liability are as detailed within paragraph 3.3. 
2. HR & Organisational Development – None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable.
• Our Renfrewshire is well - supporting the wellness and resilience
of our citizens and communities. 
Place - Demonstrating that Renfrewshire is a great place to grow up, it
is a place of opportunity for those that live and work here.   
Economy:
- Improving lives and securing wellbeing through a stronger, inclusive
and sustainable economy, being creative, imaginative and linking
opportunities to enhance the benefits for Renfrewshire. 
- Matching the skills developed in Renfrewshire with the opportunities
available in Renfrewshire and equipping all children and young
people to achieve success in life. 
Green: 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
- Ensuring our journey to net zero is a just transition with climate
justice and fairness at the heart, finding opportunities to challenge
inequalities in new green ways as we tackle the climate crisis.
- Integrating climate considerations into our long term strategic and
financial planning as an organisation 
- Boosting our green economy, creating good green jobs that are
sustainable for the future.

Page 6

OFFICIAL
Living Our Values:
- Leading positively through transition and change. 
- Delivering best value for our citizens and customers. 
4. Legal - The procurement exercise to establish the ability of the Council
to enter into a contract with Hub West Scotland has been conducted in
accordance with the Procurement Regulations. 
5. Property/Assets - The Council’s investment in its learning estate offers
the opportunity for a place-based approach to local outcomes and
integrating local services to support communities. The new school will
have capacity for c800 pupils as well as facilities for Community Use
including a full-size Flood-lit 3G playing field. 
6. Information Technology – None directly arising from this report 
7. Equality & Human Rights – None directly arising from this report 
8. Health & Safety – None directly arising from this report 
9. Procurement – Hub West Scotland is a joint-venture organisation
which is owned by both the public and private sectors. 
10. Risk – A Risk Register has been produced for the Project and will be
managed and maintained throughout the Project lifetime. 
11. Privacy Impact – None directly arising from this report 
12. Climate Risk – None directly arising from this report 
13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights. 
14. Cosla Policy Position – None directly arising from this report.
_______________________________________________________
List of Background Papers 
(a) Learning Estate Update – on 14 March 2023 to Education and
Children’s Services Policy Board
(b) Learning Estate Update – on 23 May 2023 to Education and
Children’s Services Policy Board

Page 7

OFFICIAL
(c) Contract Authorisation Report: New Primary School in Dargavel,
Enabling Works Contract and approval for Pre-Construction
Consultant Fees – on 13 February 2025 to Finance, Resources and
Customer Services Policy Board 
(d) Contract Authorisation Report: New Primary School in Dargavel,
Advanced Works Contract on 11 September 2025 to Finance,
Resources and Customer Services Policy Board
______________________________________________________________
Author:           Joanna Tannock, Interim Strategic Category Manager, 0141 487 1534,
joanna.tannock@renfrewshire.gov.uk