Report - Notification of Correction to Report – External Works - Ferguslie Green Line Neighbourhood Centre

Renfrewshire Council · 13 February 2025
Back to Finance, Resources and Customer Services Policy Board — 13 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board
On:  13 February 2025
___________________________________________________________________
Report by: Director of Finance and Resources and the Chief Executive Services
___________________________________________________________________
Heading: Notification of Correction to Report – External Works - Ferguslie Green
Line Neighbourhood Centre – (RC-CPU-24-026)
___________________________________________________________________
1. Summary
1.1 The purpose of this report is to notify the Finance, Resources and
Customer Services Policy Board of an evaluation error in the Contract
for External Works, Ferguslie Green Line – Neighbourhood Centre
recommended for award at the Finance, Resources and Customer
Services Policy Board on 11 December 2024. 
_______________________________________________________________ 
2. Recommendations
The Finance, Resources and Customer Services Policy Board are
asked to note that: 
2.1 Following recommendations to make awards at the Finance,
Resources and Customer Services Policy Board on 11 December
2024, one technical evaluation error was identified. This error had an
impact on the scoring of one tenderer and revision to the ranking for the
tenderers placed second to fifth as provided in the Appendix 1 to this
report.  
2.3 This modification does not change the position of the tenderer
recommended for award at the 11 December 2024 Finance, Resources
and Customer Services Policy Board.

Page 2

The External Works Ferguslie Green Line – Neighbourhood Centre
(RC-CPU-24-026) Contract was awarded to P1 Solutions Ltd on 19
December 2024.
________________________________________________________
3. Background
3.1 The Contract for External Works, Ferguslie Green Line –
Neighbourhood Centre, reference RC-CPU-24-026 was approved at
the Finance, Resources and Customer Services Policy board on 11
December 2024. This report identifies an error in the details provided in
this report.
3.2 A technical evaluation error has been identified and this error impacted
the score and ranking of Mackenzie Construction Limited. In the report
presented to the Policy Board on 11 December 2024, Mackenzie
Construction Limited had been ranked at fourth place however, once
identified and the error corrected, their ranking improved to second
place.  All other Tenderer scores remain unchanged by correcting this
error. 
3.3 This error does not change the recommendation to award the Contract
to P1 Solutions Ltd. 
3.4 The revised ranking achieved by each Tenderer and the corrected
values for the Mackenzie Construction Limited are as set out in
Appendix 1 (attached to this report).
___________________________________________________________________
Implications of the Report
1. Financial – there are no financial implications arising directly from this
report. 
2. HR & Organisational Development – None arising directly from this
report. 
3. Community/Council Planning – None arising directly from this report.  
4. Legal - None arising directly from this report.   
5. Property/Assets – None arising directly from this report. 
6. Information Technology - None directly arising from this report.
7. Equality & Human Rights - None directly arising from this report.

Page 3

8. Health & Safety – None arising directly from this report. 
9. Procurement – The Corporate Procurement Unit noted a technical
error in the Contract for External Works, Ferguslie Green Line –
Neighbourhood Centre recommended for award at the Finance,
Resources and Customer Services Policy Board on 11 December
2024.
10. Risk – None directly arising from this report.
11. Privacy Impact - None directly arising from this report.
12. Climate Risk – None directly arising from this report
13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights.
14. Cosla Policy Position – No COSLA Policy Position implications have
arisen or are anticipated.
_______________________________________________________
List of Background Papers 
(a)  Report by the Director of Finance and Resources to the Finance,
Resources and Customer Services Policy Board on the 11 December
2024: Contract Award: External Works Ferguslie Green Line –
Neighbourhood Centre (RC-CPU-24-026) 
___________________________________________________________________ 
Author:           Aileen Ross, Procurement Adviser, aileen.ross@renfrewshire.gov.uk

Page 4

Appendix 1 – Evaluation Scoring 
Tenderer Price
(40%)
Quality
(60%)
Total
(100%)
P1 Solutions Ltd 40.00% 47.25% 87.25%
MacKenzie Construction Limited  32.52% 50.00% 82.52%
Landscapes and Contracts Limited 38.27% 41.25% 79.52%
Landcare Solutions (Scotland) Limited 37.13% 33.75% 70.88%
JH Civil Engineering Limited 27.16% 34.25% 61.41%