Report - New Primary School in Dargavel

Renfrewshire Council · 13 February 2025
Back to Finance, Resources and Customer Services Policy Board — 13 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board 
On:  13 February 2025
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Contract Authorisation Report: New Primary School in Dargavel,
Enabling Works Contract and approval for Pre-Construction
Consultant Fees
___________________________________________________________________
1. Summary 
1.1. Renfrewshire Council has a requirement to build a new primary school in
Dargavel Village, Bishopton. The new school will have capacity for a
minimum of 800 pupils as well as facilities for Community Use including a
full-size Flood-lit 3G playing field. 
1.2. Hub West Scotland (HWS) Limited was identified as the recommended
procurement route to market under the approved terms of the Territory
Partnering Agreement (TPA). Design development has taken place in
partnership with Hub West Scotland since October 2023, culminating in
submission of Hub West Scotland Limited Stage 1 report on 18 December
2024 confirming that the project is on budget and that the forecast
programme for delivery is achievable. 
1.3. Formal approvals are now required to progress the project to ensure the
project deadline is met; Finance, Resources and Customer Services
Policy Board approval is requested for an Enabling Works contract with
Hub West Scotland Limited, who will wholly sub-contract all these works
to BAM Construction Limited and for the Finance, Resources and
Customer Service Policy Board to also approve the payment of Pre-
Construction Consultant fees to Hub West Scotland Limited to allow them
to pay their professional consultant team.

Page 2

1.4. It should be noted that further approvals will be sought from a future
Finance, Resources and Customer Service Policy board to enter into
Advance Works and Main Works Contracts with Hub West Scotland
Limited, who will wholly sub-contract each of these contracts to BAM
Construction Limited. 
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
2.1. Authorises the Head of Corporate Governance to enter into a Design and
Build Development Agreement (DBDA) for Enabling Works with Hub West
Scotland Limited. Please note that Hub West Scotland Limited will wholly
subcontract all these Enabling Works under this contract to BAM
Construction Limited. 
2.2. Authorise the award of the Enabling Works Contract for £2,354,023.00
exclusive of VAT to Hub West Scotland Limited. 
2.3. Authorise a contingency spend of £353,103.45in relation to the Enabling
Works Contract which equates to 15% of the Contract Sum. 
2.4. Authorise a total Approved Contract Value for Enabling Works of
£2,707,126.45 (which is the total of the Contract Sum plus the
contingency spend). 
2.5. Authorise the acceptance of a Limitation on Hub West Scotland Limited’s
Liability for uninsured losses up to the value of the Contract Sum for the
Enabling Works Contract. This is the market standard position. 
2.6. Note the Enabling Works Contract is anticipated to commence in early
March 2025 and be completed by late October 2025. 
2.7. Authorise the spend of £2,228,624 to Hub West Scotland Limited for them
to pay their various Pre-Construction Consultant Fees which will be
incurred in advance of entering into the Design and Build Development
Agreement associated with the Main Works Contract. 
2.8. Authorise a contingency spend of £334,293.60 in relation to the Pre-
Construction Consultant Fees which equates to 15% of the Contract Sum.

Page 3

2.9. Authorise a total Approved Contract Value for Pre-Construction
Consultant Fees of £2,562,917.60 (which is the total of the Contract Sum
plus the contingency spend). 
2.10. Authorise the acceptance of a Limitation of Liability on Design Consultants
Pre-Construction Development (Pre-Construction Consultants) to the
sums referred to in 3.19 on an each and every claim basis except for
claims relating to pollution and contamination and asbestos where the
limit will be in the annual aggregate. This is the market standard position. 
2.11. Note that a further report will be brought to a future Finance, Resources
and Customer Services Policy Board to seek approval of the award of an
Advance Works Contract and award of a Main Works Contract to Hub
West Scotland Limited noting that these will both also be wholly sub-
contracted to BAM Construction Limited. 
_________________________________________________________
3. Background
Enabling Works 
3.1. Renfrewshire Council (RC) is looking to build a primary school in Dargavel
on a site that has been purchased from BAE Systems (BAE) and requires
the school to be delivered for May 2027 to allow familiarisation / fit-out
over the school summer holidays and for the school to be ready for pupils
from the new Term in August 2027. 
3.2. RC undertook extensive consultation to gauge public opinion and
determine a preferred site for the new school. The chosen site lies
southwest of Bishopton, with plot E1 formally confirmed as the location for
the new school on 23 May 2024. The plot forms part of a wider
regeneration project by BAE Systems following the decommissioning of
the former Royal Ordnance Factory Bishopton. 
The site has been purchased from BAE by RC. The brownfield site (Plot E1) has
been remediated by BAE to a residential construction specification. The next stage in
the site preparation process is for civil engineering works comprising of the
installation of vertical drainage and fill material. These works are defined as
‘Enabling Works. 
3.3. After advice from RC officers on appropriate procurement routes, it was
proposed that the use of Hub West Scotland Limited (HWS) as a project
delivery partner would be the most appropriate procurement route for a
project of this nature. This recommendation was reported to the Education
and Children’s Services Policy Board in May 2024.

Page 4

3.4. RC entered into a Territory Partnering Agreement (TPA) with HWS on 27
April 2012. A New Project Request (a HWS Governance requirement)
was submitted by RC for the overarching Dargavel Primary School Project
(Project) to HWS and which was accepted by the HWS Board in January
2024. Appointing a contractor as early as possible in the Project was vital
due to the complexity of the Project and to develop design options during
the Feasibility Stage. 
3.5. HWS approached their Tier 1 Primary Contractor supply chain and 4
organisations were asked to confirm their interest to tender the Project
and were also requested to submit capability statements. As part of HWS
procurement methodology financial checks using project value versus
organisation turnover, Dun & Bradstreet and Credit-Safe check reports
were compiled for each organisation to further validate their suitability for
the Project. 
3.6. All 4 organisations met the due diligence requirements and on 19
February 2024 the 4 organisations were sent an Invitation to Tender (ITT).
By the closing date, 15 March 2024 all four organisations (now known as
tenderers) submitted a completed ITT. Both HWS and members of RC
evaluated the Quality element (based on 70%) and HWS evaluated the
pricing element (based on 30%). 
3.7. The 4 tenderers attended in person interviews on 26 March 2024 and
presented to a panel consisting of members from HWS and members
from RC’s Corporate Procurement Unit and Property Services. 
3.8. Following the evaluation of the 4 bids received BAM Construction Limited
(BAM) were identified by HWS as the most economically advantageous
tenderer. 
3.9. Whilst progressing through the design stages of the Project, HWS, BAM
and RC identified that there was a requirement to undertake early civil
engineering works to facilitate the site preparation ahead of the Main
Works Contract. RC are now seeking authority from the Finance,
Resources and Customer Services Policy Board to enter into an Enabling
Works Contract with HWS. 
3.10. RC will enter into a DBDA with HWS and thereafter HWS will enter into a
construction contract with BAM Construction Limited to deliver all works
required under this Contract.

Page 5

3.11. Following conclusion of RIBA 1 & 2 Design Stages, a HWS Stage 1
Report was received by the RC on 12 December 2024 and presented to
the Learning Estate Strategy and Delivery Board on 18 December 2024
confirming that at time of submission of the report, the Project was on
time, on budget and on programme. 
3.12. The Enabling Works Contract contains Limitation on HWS’s Liability for
uninsured losses up to the value of the Contract Sum for the Enabling
Works Contract. This is the market standard position. 
3.13. The key RC critical success factor is that the project be complete by May
2027 in order that the school will be operational for pupils by the new term
in August 2027. Enabling Works are programmed to commence in March
2025 and to be complete by October 2025. Entering into this Enabling
Works Contract is critical to maintaining the Project programme. 
3.14. It is anticipated that a further contract, an Advance Works Contract, will be
required following Enabling Works before the Main Works Contract can be
entered into.  The Advance Works contract will be to carry out targeted
civil engineering and services preparatory works that will assist timely
delivery of the Main Works Contract. The extent of the Advance Works
package is currently being developed in conjunction with BAM/ HWS and
RC. The Advance Works contract is currently anticipated to start in late
October 2025 and expected to last approximately 10 weeks. 
3.15. The Main Works Contract is anticipated to start in January 2026, with
handover of the facility to RC anticipated in May 2027. Further approval
will be sought from future Finance, Resources and Customer Services
Policy Boards with regard to entering into an Advance Works and a Main
Works Contract during quarter 4 of 2025. 
3.16. Pre-Construction Professional Services Fees
A design team of professional consultants has been assembled by HWS
to deliver the Project who have the credentials and relevant experience for
a project of this nature, coupled with the skill set to deliver within a
challenging delivery programme.  As part of the HWS Model, RC enters
into a contract with HWS to provide the professional and design services
and HWS sub-contracts these services to the various professional
consultants on their supply chain. HWS will incur substantial design and
other professional fees in advance of entering into the Main Works
Contract DBDA.  These services can last a considerable number of
months, and it is necessary to ensure payment of these fees to ensure
cashflow for HWS and their consultant team.

Page 6

The design team members were appointed by HWS following a detailed
tender exercise, which included an interview process involving member of
Property Services and the Corporate Procurement Unit. The team is
detailed below: 
3.17. Pre-Construction Professional Services Fees will amount to £2,228,624. 
This is broken down as follows:

Page 7

No embedded text on this page.

Page 8

3.18. The limitation of liability of HWS’s Sub-Consultants shall be limited to the
sums referred to in the table below on an each and every claim basis
except for claims relating to pollution and contamination and asbestos
where those limits will be in the annual aggregate. These figures reflect
market limitations.  
Consultant Appointment cl
19.1 (PI) and (40)
Limitation of
Liability
Sub-limitations Comments
JMA £10,000,000 (ten
million pounds) any
one occurrence
Except for claims relating
to pollution and
contamination and
asbestos where the
cover will be in the
annual aggregate.
Architect and Lead
consultant
ERZ  Landscape Architect
Sub-Consultancy:
£5,000,000 (five million
pounds) on an any one
claim or series of claims
arising from the same
originating cause basis.
Defence costs in addition
or series of claims
arising from the same
originating cause but in
the Aggregate in respect
of Pollution and
Contamination claims.
Sub consultant to
JMA
Digital
Guerrilla 
BIM Manager Sub-
Consultancy: £2,000,000
(two million pounds) any
one claim.
Sub consultant to
JMA
Carbon
Futures 
Sustainability & Carbon
Advisor Sub-
Consultancy: £5,000,000
(five million pounds)
each and every claim or
loss excluding defence
costs. 
Sub consultant to
JMA
Spacezero  Furniture, Fixtures &
Equipment specialist
Sub-Consultancy:
£10,000,000 (ten million
pounds) any one claim. 
Sub consultant to
JMA
AECOM £10,000,000 (ten
million) any one
claim
except for claims relating
to pollution and
contamination and
Civil and Structural

Page 9

Consultant Appointment cl
19.1 (PI) and (40)
Limitation of
Liability
Sub-limitations Comments 
asbestos where the limit
will be in the annual
aggregate.
Rybka £10,000,000 (ten
million pounds) any
one claim
except for claims relating
to:
Fire Safety: £10,000,000
(ten million pounds) in the
aggregate
Pollution: £1,000,000
(one million pounds) in
the aggregate
Asbestos: £250,000 (two
hundred and fifty
thousand pounds) in the
aggregate 
Mechanical,
Electrical and
Plumbing
Jensen
Hughes
£11,732,250
(eleven million
seven hundred and
thirty two thousand
two hundred and
fifty pounds) 
per occurrence and
aggregate but excludes
fire/combustibility.
Fire sub
consultant to
Rybka
Sandy
Brown
£5,000,000 (five
million pounds) any
one claim
except for claims relating
to:
Pollution:  £5,000,000 in
the aggregate
Asbestos: £2,000,000 in
the aggregate 
Acoustic sub
consultant to
Rybka
Currie and
Brown
£10,000,000 (ten
million pounds) any
one claim 
Cost Consultant
and Principal
Designer 
3.19. RC will enter into a Strategic Support Partnering Services letter with HWS
in order to pay the various professional fees as noted above.  In advance
of paying these professional fees, HWS must demonstrate to RC that they
have entered into a formal appointment with the relevant Professional
Consultant and must provide RC with a collateral warranty signed by both
HWS and the relevant Professional Consultant. 
Community Benefits 
3.20. RC provided HWS with a Community Benefit Outcome Menu that targets
150 points for a Project of this overall value.

Page 10

The outcome menu was also replicated onto the SFT themes, outcomes
and measures (TOMs) system as part of the HWS tender process. BAM
Construction Limited committed to achieving 680 points on the
Community Benefit Outcome Menu and £10.4m worth of Social, Local
Economic Value through the SFT TOMs menu. The Community Benefits
will be delivered as part of the Enabling Works Package and continue
through until overall Project completion. 
3.21. This approach and model (both an Enabling Works Contract, and
Payment of the Design Team fees in this manner) was followed
successfully in the project for the award-winning Paisley Learning and
Cultural Hub. 
___________________________________________________________________
Implications of the Report
1. Financial – The cost for these 2 named contracts of
£5,270,044.05exclusive of VAT will be met through the Capital –
General Services budget. The limits of liability are as detailed within
paragraph 3.20. 
2. HR & Organisational Development – None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable.
• Our Renfrewshire is well - supporting the wellness and resilience
of our citizens and communities. 
Place - Demonstrating that Renfrewshire is a great place to grow up,
it's a place of opportunity for those that live and work here.   
Economy:
- Improving lives and securing wellbeing through a stronger, inclusive
and sustainable economy, being creative, imaginative and linking
opportunities to enhance the benefits for Renfrewshire. 
- Matching the skills developed in Renfrewshire with the opportunities
available in Renfrewshire and equipping all children and young
people to achieve success in life.

Page 11

Green: 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
- Ensuring our journey to net zero is a just transition with climate
justice and fairness at the heart, finding opportunities to challenge
inequalities in new green ways as we tackle the climate crisis.
- Integrating climate considerations into our long term strategic and
financial planning as an organisation 
- Boosting our green economy, creating good green jobs that are
sustainable for the future. 
Living Our Values:
- Leading positively through transition and change. 
- Delivering best value for our citizens and customers. 
4. Legal - The procurement exercise to establish the ability of the Council
to enter into a contract with Hub West Scotland has been conducted in
accordance with the EU Procurement Regulations. 
5. Property/Assets - The Council’s investment in its learning estate offers
the opportunity for a place-based approach to local outcomes and
integrating local services to support communities. The new school will
have capacity for a minimum of 800 pupils as well as facilities for
Community Use including a full-size Flood-lit 3G playing field. 
6. Information Technology – None directly arising from this report 
7. Equality & Human Rights – None directly arising from this report 
8. Health & Safety – None directly arising from this report 
9. Procurement – Hub West Scotland is a joint-venture organisation
which is owned by both the public and private sectors. 
10. Risk – A Risk Register has been produced for the Project and will be
managed and maintained throughout the Project lifetime. 
11. Privacy Impact – None directly arising from this report 
12. Climate Risk – None directly arising from this report

Page 12

13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights. 
14. Cosla Policy Position – None directly arising from this report.
_______________________________________________________
List of Background Papers 
(a) Learning Estate Update – on 14th March 2023 to Education and
Children’s Services Policy Board
(b) Learning Estate Update – on 23 May 2023 to Education and
Children’s Services Policy Board
___________________________________________________________________
Author:           Joanna Tannock, Interim Strategic Category Manager 
David Donnelly, Project Manager