Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 13 February 2025
___________________________________________________________________
Report by: Report by the Director of Environment, Housing & Infrastructure
and the Director of Finance and Resources
___________________________________________________________________
Heading: Contract Authorisation Report for: Park Mains High School
Extension – Design and Build (RC-CPU-24-053)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance, Resources
and Customer Services Policy Board to award a Pre-Construction Services
Agreement for Park Mains High School Extension – Design and Build (RC-
CPU-24-053) (the “PCSA”) to Galliford Try Construction Limited, T/A Morrison
Construction Scotland, which forms part of the procurement exercise for the
complete Design and Build (D&B) Works Contract for Park Mains High School
Extension – Design and Build (RC-CPU-24-053). 
1.2 The recommendation to award the PCSA (and subsequently the D&B
Contract) follows a procurement exercise which was conducted in accordance
with the Restricted Procedure under the Public Contracts (Scotland)
Regulations 2015 and the Council’s Standing Orders Relating to Contracts. 
1.3 A Contract Strategy was approved by the Corporate Procurement Manager,
the Head of Facilities and Property Services on 4 July 2024.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services Policy
Board:

Page 2

2.1 Authorises the Head of Corporate Governance to award a Pre-Construction
Services Agreement (PCSA) for the Park Mains High School Extension –
Design and Build (RC-CPU-24-053) to Galliford Try Construction Limited, T/A
Morrison Construction Scotland. 
2.2 Authorises the award of the PCSA Contract for the Pre-Construction Services
Fee of £1,191,440.74 excluding VAT. 
2.3 Authorises a contingency spend of £119,144.07 which equates to 10% of the
Pre-Construction Services Fee. 
2.4 Authorises a total Approved Contract Value of £1,310,584.81 (which is the
total of the Pre-Construction Services Fee plus the contingency spend). 
2.5 Note that the pre-construction services are scheduled for commencement on
Monday 17 March 2025. The actual date will be confirmed in the Council’s
Letter of Acceptance to Galliford Try Construction Limited, T/A Morrison
Construction Scotland. 
2.6 Note that, as part of the Pre-Construction Services Agreement it may be
identified that an Enabling Works Package is required and if that is the case, a
further report will be brought to a future Finance, Resources and Customer
Services Policy Board seeking formal approval to enter into the Enabling
Works Contract with Galliford Try Construction Limited, T/A Morrison
Construction Scotland. 
2.7 Note that a further report will be brought to a future Finance, Resources and
Customer Services Policy Board seeking formal approval to enter into the
Design and Build Contract with Galliford Try Construction Limited, T/A
Morrison Construction Scotland. 
2.8 Authorises that the Contractor’s total liability for matters which would be
covered by Professional Indemnity is limited to £10m in the aggregate with an
annual automatic reinstatement.
_________________________________________________________
3. Background
3.1 Park Mains High School (PMHS) is located in Erskine within the Renfrewshire
Council area. School estate management planning is central to the Council’s
asset management strategy. Planned housing developments within the
Bishopton and Erskine areas of Renfrewshire have resulted in significant
primary school growth in the catchment area.

Page 3

As a result of these planned housing developments there is a need to
increase the current pupil capacity within PMHS by extending the current
building infrastructure to accommodate the increasing pupil roll.
The Council requires to appoint a suitably experienced and qualified
Contractor capable of undertaking the pre-construction related services,
Enabling Works Packages (where required), and Design and Build Package
for the extension of Park Mains High School. 
3.2 The procurement exercise for the Park Mains High School Extension – Design
and Build (RC-CPU-24-053) was conducted as an above Threshold Works
procurement in accordance with the Public Contracts (Scotland) Regulations
2015 Regulation 29 – Restricted Procedure. The estimated value of the
procurement exercise was based on the total for all Contracts including the
PCSA, Enabling Works Contract(s) and Design and Build Contract that may
be required for Park Mains High School Extension. 
3.3 The Restricted Procedure is conducted in two stages, Selection (Stage 1) and
Invitation to Tender (Stage 2). Stage 1 of this process was open to all
interested organisations. The contract notice was published on the Public
Contacts Scotland advertising portal on 5 July 2024. The Invitation to
Participate documents were also available to download on 5 July 2024 from
the Public Contracts Scotland – Tender portal. 
3.4 During Stage 1, 25 organisations expressed an interest in these Contracts,
including this PCSA. By the closing date set for Stage 1 submissions, 12 noon
on 8 August 2024, 5 companies had submitted a request to participate (RTP). 
3.5 The 5 RTPs were each evaluated against a pre-determined set of criteria in
the form of the Single Procurement Document (SPD) Scotland by
representatives from the Council’s Corporate Procurement Unit and Property
Services. 4 of the 5 Candidates satisfied the Council’s minimum requirements
within the SPD selection criteria.
3.6 As part of the selection process, and to reduce the number of otherwise
qualified Candidates, in accordance with the Invitation to Participate,
Candidates had to respond to questions relating to previous experience,
technical capacity and capability with projects similar in nature, scope and
scale to the Contracts required under this procurement exercise. 1 Candidate
failed to meet the minimum requirements with regards to the examples
submitted to evidence their past experience in delivering projects of a similar
scale and value, and was excluded from the procurement exercise.

Page 4

3.7 A panel of representatives from the Council’s Property Services team assessed
each of the 4 remaining Candidate responses to the questions and the 4
remaining Candidates were selected to proceed to Stage 2 (Invitation to
Tender). 
The selection score for each Candidate within Stage 1 –
RTP is noted below: Candidate Weighting
Heron Bros. Ltd 98.50%
Galliford Try Construction Limited, T/A Morrison
Construction Scotland 98.00%
BAM Construction Limited 91.00%
Keir Construction Limited 76.00% 
3.8 All 4 Candidates from Stage 1 were invited, by invitation issued 24 October
2024 via the Public Contracts Scotland -Tender portal, to submit a tender
submission for Stage 2. By the Tender Deadline, 12 noon on 4 December 2024
3 Candidates had submitted a response and 1 had declined to respond. 
3.9 The 3 tender submissions received were assessed against the published
Award Criteria based on weightings of 30.00% price and 70.00% quality. The
tender submissions were assessed by an evaluation panel consisting of the
Council’s Property Services team, Corporate Procurement and an external
consultant. The Tenderer scores relative to the Award Criteria are set out in the
table below: 
Tenderer Price Quality Total
Galliford Try Construction Limited, T/A
Morrison Construction Scotland 20.12% 67.25% 87.37%
Heron Bros. Ltd. 30.00% 51.20% 81.20%
BAM Construction Limited 17.86% 52.05% 69.91% 
3.10 Following evaluation the Tender Submission from Galliford Try Construction
Limited T/A Morrison Construction Scotland is deemed the most economically
advantageous tender submission. 
3.11 The Pre-Construction Services sought will be contracted in the form of a
bespoke Pre-Construction Services Agreement (PCSA) and the Pre-
Construction Services will be carried out for RIBA stages 3&4 (inclusive).
Subject to further approval from a future Finance, Resources and Customer
Services Policy Board, the Council’s intention would be to enter into a Design
and Build Contract with Galliford Try Construction Limited, T/A Morrison
Construction Scotland at the end of RIBA stage 4. As tendered, the form of the
Design and Build Contract required will be SBCC Design and Build Contact for

Page 5

use in Scotland 2016 edition accompanied with bespoke Employer’s
Amendments and Preliminaries.
3.12 The site is occupied and once the PCSA is in place it may be identified that an
Enabling Works package is required prior to the Design and Build Contract. The
requirement for Enabling Works Contracts is included within the scope of this
procurement exercise. If that is the case, a further report will be brought to a
future Finance, Resources and Customer Services Policy Board seeking formal
approval to enter into the Enabling Works Contract with Galliford Try
Construction Limited, T/A Morrison Construction Scotland. 
3.13 Mandatory Community Benefits were included as a condition of contract award
for all parts of this Park Mains High School Extension– Design and Build (RC-
CPU-24-053. Galliford Try Construction Limited T/A Morrison Construction
Scotland confirmed they would provide community benefits as disclosed with
their Tender Submission. The commitment as tendered was to deliver 10
employment opportunities. 
In addition to the mandatory Community Benefits Galliford Try Construction
Limited T/A Morrison Construction Scotland committed to delivering 180
community benefit points. The Community Benefits to be delivered across both
Pre-Construction Services and the Design and Build Contract will be agreed at
the prestart meeting, and will include discussion with the Council’s Community
Benefit Forum. The table below sets out what Galliford Try Construction Limited
T/A Morrison Construction Scotland have committed to deliver: 
Community Benefit Description
No of
People /
Activity
Work Experience Placement for an individual 16+ years of age 20
Work Experience Placement for an individual aged 14 to 16
years of age 3
Business advice/support to a local SME /Social Enterprise/
Voluntary organisation 1
Event to promote supply chain opportunities 2
S/NVQ (or equivalent) for  
• New Employee
• Existing Employee  
• Supply Chain Employee
20
Industry Awareness Events 
• Schools
• Invest in Renfrewshire – Employability
• Further Education
24

Page 6

Community Benefit Description
No of
People /
Activity
Industry Skill Transfer to Schools 6
Financial Support for a Community Project 5
Non-Financial Support for a Community Project 5 
3.14 The costs for all Contracts forming the Park Mains High School Extension –
Design and Build (RC-CPU-24-053) will be met through the Capital – General
Services budget. 
___________________________________________________________________
Implications of the Report
1. Financial - Financial and Economic Standing have been assessed as
part of the tender selection criteria – which Galliford Try Construction
Limited, T/A Morrison Construction Scotland met. The cost of up to
£1,310,584.81 excluding VAT will be met through the Capital – General
Services budget. To note, the cost of all subsequent contracts noted in
this report will be met through the Capital – General Services budget.   
2. HR & Organisational Development - None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable.
• Our Renfrewshire is well - supporting the wellness and resilience
of our citizens and communities. 
Place - Demonstrating that Renfrewshire is a great place to grow up,
it's a place of opportunity for those that live and work here.   
Economy:
- Improving lives and securing wellbeing through a stronger, inclusive
and sustainable economy, being creative, imaginative and linking
opportunities to enhance the benefits for Renfrewshire. 
- Matching the skills developed in Renfrewshire with the opportunities
available in Renfrewshire and equipping all children and young
people to achieve success in life.

Page 7

Green: 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
- Ensuring our journey to net zero is a just transition with climate
justice and fairness at the heart, finding opportunities to challenge
inequalities in new green ways as we tackle the climate crisis.
- Integrating climate considerations into our long term strategic and
financial planning as an organisation 
- Boosting our green economy, creating good green jobs that are
sustainable for the future. 
Living Our Values:
- Leading positively through transition and change. 
- Delivering best value for our citizens and customers. 
4. Legal - The procurement of this Contract and related contracts for Park
Mains High School Extension– Design and Build (RC-CPU-24-053) has
been conducted in accordance with the Restrictive Procedure under the
Public Contracts (Scotland) Regulations 2015 and the Council’s
Standing Orders Relating to Contracts. 
5. Property/Assets - The Council’s investment in its learning estate offers
the opportunity for a place-based approach to local outcomes.
integrating local services to support communities. Extending the current
building infrastructure at Park Mains High School will accommodate the
increasing pupil roll. 
6. Information Technology – None directly arising from this report, the
Council’s Architecture & Technology team confirmed that no Cyber
Security input was required. 
7. Equality & Human Rights – None directly arising from this report.
8. Health & Safety - Galliford Try Construction Limited, T/A Morrison
Construction Scotland health and safety credentials were evaluated by
Corporate Health and Safety and met the Council’s requirements
regarding health and safety for this procurement exercise. 
9. Procurement – The procurement procedures outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency, and modern Government.

Page 8

If other related contracts are identified as part of the PCSA process,
such as enabling works, the scope within this procurement exercise
has included such requirements. 
10. Risk - Galliford Try Construction Limited, T/A Morrison Construction
Scotland insurances have been assessed and evaluated to confirm that
they meet the requirements regarding insurance risk for this
procurement exercise. 
The Contractor’s total liability for matters which would be covered by
Professional Indemnity is limited to £10m in the aggregate with an
annual automatic reinstatement.   
11. Privacy Impact – None directly arising from this report.   
12. Climate Risk – The level of impact associated with the provision of
these works have been assessed using the Scottish Government
Sustainability Test and is considered to be high risk. 
Mitigations the Council has taken in regard to sustainability within this
Contract is to include contractual elements within the Scope such as:
- The Contractor should aim to ensure that any deliveries to site are
consolidated to reduce emissions.  
- The Contractor is required to provide a Site Specific Waste
Management Plan detailing where all the waste produced will be
recycled or if it cannot be recycled where the waste will go.   
13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights. 
14. Cosla Policy Position – None directly arising from this report.
_______________________________________________________
List of Background Papers
(a)  None 
___________________________________________________________________ 
Author:           Joanna Tannock, Interim Strategic Category Manager, Corporate
Procurement Unit, Joanna.tannock@renfrewshire.gov.uk