Revenue and Capital Budget Monitoring Overview Report

Renfrewshire Council · 13 February 2025
Back to Finance, Resources and Customer Services Policy Board — 13 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 13 February 2025
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring – Council Overview as at
8 November 2024
___________________________________________________________________
1. Summary of Financial Position
1.1 At the close of reporting Period 8 on 8 November 2024, the projected
revenue outturn position at 31 March 2025 for Council services is a small
underspend position of £0.119m (0.0%) against the revised budget for the
year. Adult Services (HSCP) is projecting an overspend of £4.643m (4.4%),
resulting in a combined projected overspend of £4.524m (0.9%).
1.2 The projected capital outturn at 31 March 2025 all services is a break-even
position. 
1.3 This is split between General Fund Services and the Housing Revenue
Account (HRA) in the table below, with further analysis provided in the
Appendices.
Table 1
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
General Fund Services (Council) 423,476 423,357 119 (0.0%)
Adult Services (HSCP) 106,460 111,103 (4,643) (4.4%)
Housing Revenue Account (HRA) 0 0 0 0.0%
Total 529,936 534,460 (4,524) (0.9%)
Capital    
General Fund Services 103,575 103,575 0 0.0%
Housing Revenue Account (HRA) 30,862 30,862 0 0.0%

Page 2

2. Recommendations
2.1 Members are requested to: 
a) Note the projected Revenue outturn overspend position of £4.524m;
b) Note the projected Capital outturn break-even position; and
c) Note the prudential indicators detailed in section 7 of the report.
_________________________________________________________
3. Revenue Budget Projection – overspend of £4.524m by 31 March 2025
3.1 The projected overspend of £4.524m across all services includes £4.643m
for Adult Services (HSCP), leaving a forecast underspend of £0.119m for
Council services. 
3.2 The tables in Appendix 1 present the projected year-end position for all
services, by both subjective analysis (what the budget is spent on) and
objective analysis (which division is spending the budget). Significant
variances affecting the projected position are analysed further below. 
3.3 The projected outturn is based on information currently available, and
assumptions made by service budget holders.  Any changes to these
projections will be detailed in future reports to this board. 
4. Significant Variances
4.1 Education & Children’s Services £0.901m overspend 
This projected forecast includes overspends in Supplies & Services
(£0.762m) mainly due to payments to care leavers and increased demand
for Care at Home services for children with additional support needs. 
Overspends in Transfer Payments (£0.803m) relates mainly to Children &
Families, in particular Direct Payments and Section 22 payments. The
projected overspend in Third Party payments (£0.606m) relates to Fostering
and Adoption fees, following the implementation of the national rate for
fostering allowances, and services related to Children with Disability, related
to projected placement costs. 
These overspends are partly offset by Employee Costs currently projecting a
£1.197m underspend.   
4.2 Infrastructure, Land & Environment £1.160m overspend
The projected overspend predominantly sits within Waste Services, where
trade waste income is significantly under-recovered owing to a reduction in
demand.

Page 3

There are further cost pressures related to increased software and work by
contractor costs within Infrastructure and Assets, and Fleet Services are
projecting an overspend which is mainly reflective of the inflationary impact
on replacement parts for vehicles and specialist contractors. 
4.3 Finance, Resources & Customer Services £2.053m underspend 
The anticipated underspend is mainly driven by an expected £3.000m
increase in investment interest income, owing to the level of interest rates
prevailing. This is offset by a forecast overspend in Public Building Repairs
of £0.739m due to the continued inflationary and cost pressures that have
been experienced by the service over the last few financial years. The
position continues to be closely monitored, and mitigating actions will be
taken by management where appropriate. There is also an expected
£0.128m overspend within Soft FM, principally due to inflation on food and
provisions. 
4.4 Adult Services £4.643m overspend 
The overspend is mainly due to external care at home packages for both
Older People and those with Physical or Sensory Difficulties. This results
from increased acuity of patients with more complex needs discharged from
hospital, meaning more intensive Care at Home packages are required to
support people to remain in their own homes. Note that these projections do
not take into account the cost associated with the back pay in relation to care
at home staff regrade, which is still to be fully agreed.  This overspend is
further impacted by inflationary increases as a result of the adult supported
living framework renewal in November 2024. 
5. Capital Budget Projection – Housing Services Programme
5.1 The HRA Capital Investment Programme 2024/25 to 2028/29 was approved
by the Council on 29 February 2024. For 2024/25, the revised programme
totals £30.862m, an increase of £0.093m since Period 6, as a result of a net
acceleration from 2025/26 into 2024/25. Decelerations for Regeneration
have been offset by accelerations within Improvements to Existing Assets
and Other Assets. 
5.2 Capital expenditure to 8 November 2024 amounted to £14.298m,
representing 46% of available resources, compared to 53% for the same
period in 2023/24.

Page 4

5.3 22% of expected capital income has been received to date, compared to 74%
for the equivalent period in 2023/24. This difference relates to grant received
in 2023/24 for energy efficiency improvements which came in at the start of
the year; this has not been awarded for 2024/25. The remainder of expected
capital income is expected to come in towards the end of the financial year. 
5.4 The projected outturn position, after budget changes, is for the Housing
Services Programme to break even (see Appendix 2). However, inflationary
impacts of delays to work and related cost estimates are still ongoing and
therefore this forecast will be kept under review. 
6. Capital Monitoring: Non-Housing Services Programme
6.1 The General Services Capital Investment Programme 2024/25 to 2028/29
was approved by Council on 29 February 2024. For 2024/25, the current
revised programme totals £103.575m, a decrease of £3.135m since Period 6,
resulting mainly from the net effect of: 
 projects reprofiled from 2024/25 into 2025/26 of £4.859m, mainly as a
result of updated cashflow profiles for Thorn New Build, Dargavel Primary
School 2, Community Halls Refurbishment & Lagoon Internal Play Centre;
and
 budget increases in 2024/25 of £1.724m largely reflecting grant awards for
Recycle Improvement Fund and Shared Prosperity Fund. 
6.2 Capital expenditure to 8 November 2024 totals £44.395m, representing 43%
of the available resources, compared to 45% for the equivalent period in
2023/24. 
6.3 Capital income totalling £12.963m has been received to 8 November 2024.
This represents 41% of the total anticipated income, compared to 44% for the
equivalent period in 2023/24. 
6.4 The projected outturn position after these budget changes is to break even
(see Appendix 2). However, the full impact of inflation on capital costs on each
project is not yet determined, with increased costs through inflation and
compliance expected to increase the risk of overspends across the capital
programme. 
7. Capital Overview: Prudential Indicators 
7.1  The Council is required to set prudential indicators to ensure that its capital
investment plans are affordable, proportionate, prudent and sustainable. The
current prudential indicators were approved by Council on 12 December 2024.

Page 5

7.2 The CIPFA Prudential Code 2021 recommends that from 2024/25 a regular
update is provided to members noting the current forecasts for prudential
indicators compared to those approved at the start of the financial year. These
are outlined in 7.4 to 7.8 below. 
7.3 The Council will be asked to approve new Prudential Indicators in late
February 2025 as part of the non-housing capital investment programme
report. 
7.4     Capital Expenditure: The limit on capital expenditure that the Council has set
for 2024/25 is shown in the table below. The limit is based on the resources
available to fund the capital programmes, split between Housing and Non-
Housing Services, but excludes the Public Sector Housing Grant, as this is not
considered to be capital spend for the Council. The forecast expenditure is
lower owing to the changes outlined at 6.1 above. 
Approved Plan
£m
Forecast Expenditure
£m
Non-Housing 107 104
Housing 31 31
Total 138 135 
7.5       Capital Finance Requirement (CFR): The CFR originally planned by the
Council for 2024/25 is shown in the table below and is split between Housing
and Non-Housing Services. The projected outturn at 31 March 2025 is also
shown. Any significant increase in the capital expenditure without planned
funding at the point of spend will result in an increase to the CFR. 
Planned CFR to 
31 March 2025
£m
Projected CFR to 
31 March 2025
£m
Non-Housing 462 458
Housing 130 129
Total 592 587 
7.6   Operational Boundary: This is the focus of day-to-day treasury management
activity within the Council and is an estimate of the most likely, but not worst
case, scenario in terms of cashflow. Risk analysis and risk management
strategies are taken into account, as are plans for capital expenditure,
estimates of the CFR and estimates of cashflow requirements for all
purposes.

Page 6

It is possible that this boundary could be breached occasionally, and this
should not be regarded as significant. However, a sustained or regular trend
of such would be significant and require investigation and action. 
Planned Operational
Boundary to 
31 March 2025 
£m
Projected Operational
Boundary to 
31 March 2025
£m
Borrowing 498 493
Other Long-Term Liabilities 94 94
Total 592 587 
7.7   Authorised Limit: This is based on the same assumptions as the Operational
Boundary, with additional headroom to ensure sufficient capacity to allow for
both planned and exceptional cashflow requirements, without breaching the
limit. 
Planned Authorised
Limit to 
31 March 2025
£m
Projected Authorised
Limit to 
31 March 2025
£m
Borrowing 523 518
Other Long-Term Liabilities 94 94
Total 617 612 
7.8   Ratio of Financing Costs to Net Revenue: A key measure of affordability is
the incremental impact of investment decisions on Council Tax or housing
rents. Estimates of the ratio of financing costs to net revenue stream provide
an indication of how much of the Council’s revenue budget is committed to the
repayment of debt. 
Approved Ratio of
Financing Costs to Net
Revenue 2024/25 
%
Projected Ratio of
Financing Costs to Net
Revenue 2024/25 
%
Non-Housing 3.47 3.22
Housing 28.59 28.49 
Financing costs include the interest payable with respect to forecast borrowing
levels, interest payable on finance leases, interest and investment income,
loans fund and finance lease principal repayments and gains/losses on the
repurchase or early settlement of borrowing.

Page 7

There is a decrease in the projected ratios due to the updated capital spend
profile and interest rate outlook. 
Revenue streams relate either to the amounts received in terms of
government grant and local taxpayers for Non-Housing, or to the amounts
received from tenants in respect of housing rents for Housing.
8. Private Sector Housing Grant Programme
8.1. The overall budget provision for this programme is included within the revenue
budget. However, in order to monitor the performance of the individual
programmes, it is included within capital budget monitoring procedures.
8.2. The Council approved expenditure up to £0.526m for 2024/25. The current
revised budget totals £1.186m, an increase of £0.660m, reflecting a
contribution from revenue for Disabled Adaptations and Care & Support.
8.3. The programme is expected to fully spend by 31 March 2025 and will be
contained within the overall resources. 
Implications of the Report
1. Financial
The projected budget outturn position for General Fund Services Revenue
budget is an overspend of £4.524m (0.9%) and break-even for the HRA
Revenue budget.  Income and expenditure will continue to be monitored closely
for the rest of the financial year and, where necessary, steps will be taken to
mitigate overspends.    
The projected outturn position for General Fund Services and HRA Capital
budgets is a break-even position. The Capital programme will continue to be
monitored closely for the rest of the financial year.   
Any changes to current projections in either Revenue or Capital budgets will be
detailed in future reports to this board. 
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report.

Page 8

3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT, infrastructure, and
plant and equipment. 
6. Information Technology 
There are no direct implications arising from the recommendations in this
report. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report. 
8. Health & Safety 
There are no direct implications arising from the recommendations in this
report.

Page 9

9. Procurement 
While Procurement is an important consideration prior to the Council incurring
any revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Children’s Rights  
There are no direct implications arising from the recommendations in this
report. 
13. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report. 
14. Cosla Policy Position - N/a
___________________________________________________________________
List of Background Papers 
 Revenue Budget and Council Tax 2024/25, Council 29 February 2024
 The Capital Investment Programme 2024/25 to 2028/29, Council 29
February 2024
___________________________________________________________________ 
Author: Alison Burns, Corporate Finance Manager 
Geoff Borland, Finance Manager

Page 10

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 8 November 2024 
        
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ OVERVIEW 
        
Policy Board ‐ Objective Summary 
Annual 
Budget at 
Period 6 
Budget 
Adjustments 
Revised 
Annual 
Budget at 
Period 8 
Projected 
Outturn 
Budget Variance  
(Adverse) or 
Favourable 
Previous 
Projected 
Outturn 
Variance 
Movement 
 
 
£000  £000  £000  £000  £000  %  £000  £000 
Communities and Housing Services  14,629  249  14,878  14,878  (0)  0.0%  0  0 
Education and Children's Services  256,996  589  257,585  258,486  (901)  (0.3%)  (659)  (242) 
Infrastructure, Land and Environment  31,072  1,049  32,121  33,281  (1,160)  (3.6%)  (1,210)  50 
Finance, Resources and Customer Services  92,334  3,541  95,875  93,822  2,053  2.1%  1,651  402 
Adult Services  106,460  0  106,460  111,103  (4,643)  (4.4%)  (6,700)  2,057 
Planning   584  0  584  584  0  0.0%  (5)  5 
Economy and Regeneration  2,306  0  2,306  2,214  92  4.0%  76  16 
Chief Executive's Service  20,119  8  20,127  20,092  35  0.2%  28  7 
GENERAL SERVICES NET EXPENDITURE  524,500  5,436  529,936  534,460  (4,524)  (0.9%)  (6,819)  2,295 
Housing Revenue Account (HRA)  0  0  0  0  0  0.0%  0  0 
NET EXPENDITURE  524,500  5,436  529,936  534,460  (4,524)  (0.9%)  (6,819)  2,295

Page 11

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 8 November 2024 
        
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ OVERVIEW 
        
Subjective Summary 
Annual 
Budget at 
Period 6 
Budget 
Adjustments 
Revised 
Annual 
Budget at 
Period 8 
Total 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
Previous 
Projected 
Outturn 
Variance 
Movement 
 
 
£000  £000  £000  £000  £000  %  £000  £000 
Employees  359,278  4,406  363,684  359,293  4,391  1.2%  2,977  1,414 
Premises Related  52,354  486  52,840  54,539  (1,699)  (3.2%)  (1,301)  (398) 
Transport Related  15,376  2,126  17,502  18,462  (960)  (5.5%)  (2,699)  1,739 
Supplies and Services  97,099  (85)  97,014  99,935  (2,921)  (3.0%)  (1,746)  (1,175) 
Third Party Payments  92,630  873  93,503  100,270  (6,767)  (7.2%)  (7,975)  1,207 
Transfer Payments  99,988  39  100,027  101,082  (1,055)  (1.1%)  (1,051)  (4) 
Support Services  6,248  (1)  6,247  6,307  (60)  (1.0%)  (5)  (55) 
Depreciation and Impairment Losses  27,068  518  27,586  27,598  (12)  0.0%  (12)  0 
GROSS EXPENDITURE  750,041  8,362  758,403  767,486  (9,084)  (1.2%)  (11,811)  2,727 
Income  (225,541)  (2,926)  (228,467)  (233,026)  4,560  2.0%  4,992  (433) 
NET EXPENDITURE  524,500  5,436  529,936  534,460  (4,524)  (0.9%)  (6,819)  2,295

Page 12

Appendix 2 
Prior Years Approved   Budget  Revised  Projected 
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2024* 2024‐25 since previous 2024‐25 2024‐25 Budget Outurn 
Board report to 31‐Mar‐29 to 31‐Mar‐29
£000 £000 £000 £000 £000 £000 £000
EDUCATION & CHILDREN'S SERVICES
Education & Children's Services 20,894 31,623 (1,337) 30,286 30,286 0 0% 198,480 198,480 0 0%
TOTAL 20,894 31,623 (1,337) 30,286 30,286 0 0% 198,480 198,480 0 0%
COMMUNITIES, HOUSING & PLANNING
Housing (HRA) 53,408 30,769 93 30,862 30,862 0 0% 219,144 219,144 0 0%
Housing (PSHG) 0 526 660 1,186 1,186 0 0% 2,926 2,926 0 0%
TOTAL 53,408 31,295 753 32,048 32,048 0 0% 222,070 222,070 0 0%
INFRASTRUCTURE, LAND & ENVIRONMENT
Environment & Infrastructure 4,137 18,517 167 18,684 18,684 0 0% 54,578 54,578 0 0%
TOTAL 4,137 18,517 167 18,684 18,684 0 0% 54,578 54,578 0 0%
ECONOMY & REGENERATION
Economy and Development 81,445 16,612 690 17,302 17,302 0 0% 109,893 109,893 0 0%
TOTAL 81,445 16,612 690 17,302 17,302 0 0% 109,893 109,893 0 0%
FINANCE, RESOURCES & CUSTOMER SERVICES
Corporate Projects 3,993 9,259 10 9,269 9,269 0 0% 32,997 32,997 0 0%
TOTAL 3,993 9,259 10 9,269 9,269 0 0% 32,997 32,997 0 0%
LEADERSHIP
Leisure Services 24,924 2,982 (1,570) 1,412 1,412 0 0% 28,005 28,005 0 0%
Chief Executives 158,319 27,717 (1,095) 26,622 26,622 0 0% 360,395 360,395 0 0%
TOTAL 183,243 30,699 (2,665) 28,034 28,034 0 0% 388,400 388,400 0 0%
TOTAL ALL BOARDS 347,120 138,005 (2,382) 135,623 135,623 0 0.0% 1,006,418 1,006,418 0 0%
MADE UP OF:
Non-Housing Programme 293,712 106,710 (3,135) 103,575 103,575 0 0% 784,348 784,348 0 0%
Housing Programme (HRA) 53,408 30,769 93 30,862 30,862 0 0% 219,144 219,144 0 0%
Housing Programme (PSHG) 0 526 660 1,186 1,186 0 0% 2,926 2,926 0 0%
PROGRAMME TOTAL 347,120 138,005 (2,382) 135,623 135,623 0 0.0% 1,006,418 1,006,418 0 0%
Budget Variance (Adverse) 
or Favourable
Budget Variance (Adverse) 
or Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY ‐ NON‐HOUSING SERVICES
1st April to 8th November 2024
POLICY BOARD: FINANCE, RESOURCES & CUSTOMER SERVICES
Current Year 2024‐25 Full Programme ‐ All years

Page 13

Appendix 2 
2024/25
Housing Non Housing PSHG Total
Services Services Programme
A. RESOURCES AVAILABLE TO FUND CAPITAL PROGRAMME £'000 £'000 £'000 £'000
1. Prudential Borrowing 22,147 66,996 89,143
2a General Capital Grant 13,627 600 14,227
2b. Specific Capital Grant 2,578 1,469 4,047
3. Usable Capital Receipts 1,350 16,154 17,504
4. Contribution From Current Revenue (CFCR) 4,787 5,329 586 10,702
5 Total Resource Availability 30,862 103,575 1,186 135,623
B. CAPITAL PROGRAMME
6. Resources Available 30,862 103,575 1,186 135,623
7. Current Programme 30,862 100% 103,575 100% 1,186 100% 135,623 100%
C. ACTUAL EXPENDITURE VS PROJECTED
8. Resource Availability 30,862 103,575 1,186 135,623
9. Cash Spent at 8 November 2024 14,298 46% 44,395 43% 586 49% 59,279 44%
10. Cash to be Spent by 31 March 2025 16,564 59,180 601 76,344
D. ACTUAL RECEIPTS VS PROJECTED
11. Current Programme (total receipts expected) 3,928 31,250 600 35,778
12. Actual Cash Received at 8 November 2024 857 22% 12,963 41% 340 57% 14,160 40%
13. Receipts to be received by 31 March 2025 3,071 18,287 260 21,618
RENFREWSHIRE COUNCIL
2024/25 CAPITAL BUDGETS MONITORING SUMMARY REPORT TO 8TH NOVEMBER 2024