Democracy Spraffa

Item 1 - Revenue and Capital Budget Monitoring report

Renfrewshire Council · 12 September 2024
Back to Finance, Resources and Customer Services Policy Board — 12 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 12 September 2024
___________________________________________________________________
Report by: Director of Finance and Resources
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring 2024/25 at 21 June 2024
___________________________________________________________________
1. Summary
1.1 At the close of reporting Period 3 on 21 June 2024, the projected revenue
outturn at 31 March 2025 for those services reporting to the Finance,
Resources and Customer Services Policy Board was an overspend position
of £0.375m (0.4%) against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2025 for projects reporting to the
Finance, Resources and Customer Services Policy Board is a break-even
position. 
1.3  This is summarised over the relevant services in the table below and further
analysis is provided in the report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Finance and Resources 43,750 43,693 57 0.1%
Environment, Housing and
Infrastructure  23,094 23,471 (377) (1.6%)
Chief Executive's Service (Estates) (168) (113) (55) (32.7%)
Miscellaneous 27,852 27,852 0 0.0%
Total 94,528 94,903 (375) (0.4%)
Capital    
Finance, Resources and Customer
Services Policy Board 14,294  14,294 0  0.0%

Page 2

2. Recommendations
2.1 Members are requested to: 
a) Note the projected Revenue outturn overspend position of £0.375m;
b) Note the projected Capital outturn break-even position; and
c) Agree to homologate the budget adjustments detailed at sections 5 and 6. 
3. Revenue Budget Projection – overspend of £0.375m by 31 March 2025
3.1 The tables in Appendix 1 present the projected year-end position for all
services reporting to this Board, by both subjective analysis (what the budget
is spent on) and objective analysis (which division is spending the budget).
Significant variances affecting the projected position are analysed further
below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle until the close of reporting Period 10. Budget holders are
obliged to seek mitigating action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances
4.1 Finance, Resources and Customer Services - £0.057m underspend
This forecast position mainly reflects the underspend in Internal Audit.  The
post of Chief Auditor remains vacant pending the result of informal
discussions between Chief Finance Officers of Renfrewshire Council,
Inverclyde Council and West Dunbartonshire Council with regards improving
resilience within their respective internal audit and counter fraud services. 
4.2 Environment, Housing and Infrastructure - £0.377m overspend
There is an anticipated overspend of £389k being forecast within Public
Building Repairs. This is due to the continued inflationary and cost pressures
that have been experienced by the service over the last few financial years.
The position has improved since last year and continues to be closely
monitored. Mitigating actions will be taken by management where
appropriate.  
Soft Facilities Management is forecasting an underspend of £12k. There are
under and overspends across the budget headings but the main overspend
is within premises related costs (cleaning £0.190m) and transport costs
(£0.114m).

Page 3

In addition, there is a projected over-recovery of income which largely relates
to recharge income that is recovered from HSCP (£0.560m) for staff costs.
This is offset by an under-recovery of HQ car parking income, along with a
lower than expected school meal income expected in the final quarter. This
reduced income relates to the provision of school meals to P6 and P7 pupils
who receive the Scottish Child Payment.  The position will be closely
monitored throughout the year and any updates provided to Board. 
4.3         Chief Executive’s Service (Estates) - £0.055m overspend
This forecast position mainly reflects an anticipated under-recovery in rental
income as a result of a property at Houston Square held vacant as part of
the delivery of the Johnstone Vision regeneration programme. 
4.4 Miscellaneous Services – break even
While the service is currently projected to break even by year-end, there is
an anticipated over-recovery of investment interest income owing to interest
rates increasing after the budget was established. This will be closely
monitored with a view to the additional income covering expected
overspends in loan charges (borrowing interest), as outlined to Council
during its revenue budget setting for 2024/25. Further information will be
reported to the Board as it emerges throughout the year. 
5. Subjective Analysis – Significant Variances
5.1 Employee Costs - £0.021m overspend 
Finance and Resources is projecting a £0.389m overspend mainly due to
lower than expected levels of staff turnover at this stage in the financial year. 
The position will be closely monitoring with the overspends expected to ease
in the coming periods as a result of some staff movements across the
service. This is partly offset by a projected underspend within Soft Facilities
Management (£0.462m) which reflects the high staff turnover and the
difficulty filling posts. 
5.2 Premises Related - £0.739m overspend 
This projected overspend predominantly sits within repairs and maintenance
in Public Building Repairs due the continued inflationary and cost pressures
that have been experienced by the service over the last few financial years.
It is partly offset by underspends and income elsewhere in the service at
present. The position has improved since last year and continues to be
closely monitored.

Page 4

5.3 Transport Related - £0.126m overspend 
This projected overspend predominantly sits within Environment, Housing &
Infrastructure and in the main relates to external vehicle hire required to
support the Universal Free School Meals project. 
5.4 Supplies and Services - £1.244m overspend 
This projected overspend predominantly sits within Environment, Housing &
Infrastructure (£1.318m) on work by contractors within Property Services, the
costs of which are recovered through the fees process. 
5.5 Income - £1.625m over-recovery 
This projected over-recovery of income predominantly sits within
Environment, Housing & Infrastructure (£1.480m), and mainly relates to the
recovery of Property Services costs and HSCP costs, currently showing as
overspends within expenditure lines. A budget realignment exercise will be
completed in Period 6. There is a further over-recovery within Finance and
Resources (£0.194m) the majority of which relates to income generated from
ICT support for a digital programme. 
6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and
Resources for submission to the relevant policy board for approval. 
Since the budget was approved in February 2024, the Director now seeks
homologation from the Board for the following affected virements: 
Revenue Budget Adjustments for homologation 
Objective Heading Subjective
Heading
Amount
(£m)
Reason
Finance and
Resources
Employee Costs (0.443) Transfer of Clark Street Depot
Staffing from Business Services
to Building Services in EH&I
Finance and
Resources
Employee Costs (0.137) Transfer of Customer Services
Homeless Team Staffing to
Housing in EH&I

Page 5

Objective Heading Subjective
Heading
Amount
(£m)
Reason
Finance and
Resources
Employee Costs 0.086 Transfer of 2 Licensing Officer
posts from EH&I to Corporate
Governance
Environment, Housing
& Infrastructure
Premises Costs 0.115 Transfer from various other
services to cover commissioned
repairs
Environment, Housing
& Infrastructure
Employee Costs 0.443 Transfer of Clark Street Depot
Staffing from Business Services
to Building Services in EH&I
Environment, Housing
& Infrastructure
Income (0.298) Transfer of lets income budget
from Community Learning and
Development
Environment, Housing
& Infrastructure
Employee Costs
Premises
Transport
Supplies & Services
Transfer Payments
Income
1.363
0.124
0.015
0.262
0.020
(1.784)
Realignment of budgets within
the service to reflect revised
establishment and forecast
workload for 2024/25. 
6.3. The following budget adjustments reflect allocations of agreed pay
settlements, approved savings, and changes to superannuation rates for
employers, and are therefore for noting only: 
Revenue Budget Adjustments for noting
Objective Heading Subjective Heading Amount
(£m)
Reason
Finance and
Resources
Employee Costs (0.307) Right for Renfrewshire savings
realised
Finance and
Resources
Employee Costs (3.619) Contribution to reserves re
reduction in employers’
superannuation
Finance and
Resources
Employee Costs 2.817 Pay award 2023/24
Environment,
Housing &
Infrastructure
Employee Costs (1.708) Contribution to reserves re
reduction in employers’
superannuation
Environment,
Housing &
Infrastructure
Employee Costs 1.613 Pay award 2023/24 
Miscellaneous Transfer Payments 3.771 Council wide Right for
Renfrewshire savings 
Miscellaneous Employee Costs (14.448) Allocation of pay award 2023/24
to services and contribution to
reserves re reduction in
employers’ superannuation

Page 6

6.4. Budget holders are obliged to seek mitigating action to minimise significant
budget variances. The Board is therefore asked to approve the following
virements, which are not currently applied to the budget: 
Revenue Budget Adjustments for approval
Objective Heading  Subjective
Heading 
Amount
(£m)
Reason
Soft FM Employee costs  0.560  Realignment of budget to reflect
recharge of staff costs to HSCP
Income (0.560)
Property Services Supplies and
Services
0.718  Realignment of budgets to reflect
increased work by contractor
costs being recharged to capital
and other services
Income (0.718) 
7. Capital Budget Projection – break-even position by 31 March 2025
7.1 The Capital Investment Programme 2024/25 to 2028/29 was approved by
the Council on 29 February 2024. Finance, Resources and Customer
Services approved capital spend for 2024/25 is £9.707m. 
7.2 The in-year Capital budget is forecast to break-even by 31 March 2025,
however, this will be monitored as the projects progress. Further details of
the programme can be found in the Capital Monitoring report at Appendix 2. 
7.3 Budget adjustments totalling £4.587m have been carried forward into
2024/25 to reflect updated timing on the programming of some capital
projects. The revised capital spend for 2024/25 is £14.294m, and details of
the adjustments are as follows: 
Capital Budget Adjustments
Project Amount
(£m)
ICT Infrastructure Maintenance & Renewal Programme 0.969
Lifecycle Capital Maintenance (LCM) Fund 2.360
Artificial Pitch Upgrades 0.524
Digital Infrastructure Provision 0.032
Community Empowerment Fund 0.552
Villages Improvement Fund 0.076
Retail Improvement Fund 0.074
Total 4.587

Page 7

Implications of the Report
1. Financial
The projected budget outturn position for Finance, Resources and Customer
Services’ Revenue budget is an overspend of £0.375m (0.4%) at 31 March
2025.  Income and expenditure will continue to be monitored closely for the rest
of the financial year and as far as possible, steps will be taken to mitigate any
overspend.   
The projected outturn position for Finance, Resources and Customer Services’
Capital budget is break-even, after the adjustments outlined at section 7.   
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report. 
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report.

Page 8

5. Property/Assets 
The capital expenditure noted in this report will result mainly in lifecycle
maintenance improvements to existing properties, replacement of ICT assets
and infrastructure and replacement of artificial pitches. 
6. Information Technology 
While ICT assets and revenue costs are included within these reported
budgets, there are no direct implications arising from the recommendations in
this report. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report. 
8. Health & Safety 
The capital expenditure noted in this report will result in lifecycle maintenance
improvements to existing properties and replacement of ICT assets, which may
in some cases rectify health and safety issues. 
9. Procurement 
While Procurement is an important consideration prior to the Council incurring
any revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report.

Page 9

13. Children’s Rights 
There are no direct implications arising from the recommendations in this report 
14. Cosla Policy Position 
N/a 
List of Background Papers 
 Revenue Budget and Council Tax 2024/25, Council 29 February 2024
 The Capital Investment Programme 2024/25 to 2028/29, Council 29
February 2024 
Author:     Valerie Howie and Lisa Dickie, Finance Business Partners; Alison Burns,
Corporate Finance Manager; and Linsey McGregor, Senior Accountant
(Capital)

Page 10

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Objective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Finance and Resources  44,383  (633)  43,750  43,693  57  0.1% 
Environment, Housing and Infrastructure  23,015  79  23,094  23,471  (377)  (1.6%) 
Chief Executive's Service (Estates)  (168)  0  (168)  (113)  (55)  (32.7%) 
Miscellaneous  38,494  (10,642)  27,852  27,852  0  0.0% 
NET EXPENDITURE  105,724  (11,196)  94,528  94,903  (375)  (0.4%) 
Subjective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Employees  99,621  (14,486)  85,135  85,156  (21)  0.0% 
Premises Related  13,700  (306)  13,394  14,133  (739)  (5.5%) 
Transport Related  2,173  16  2,189  2,315  (126)  (5.8%) 
Supplies and Services  26,763  2,202  28,965  30,209  (1,244)  (4.3%) 
Third Party Payments  1,925  0  1,925  1,901  24  1.2% 
Transfer Payments  40,488  4,847  45,335  45,245  90  0.2% 
Support Services  171  31  202  186  16  7.9% 
Depreciation and Impairment Losses  9,182  0  9,182  9,182  0  0.0% 
GROSS EXPENDITURE  194,023  (7,696)  186,327  188,327  (2,000)  (1.1%) 
Income  (88,299)  (3,500)  (91,799)  (93,424)  1,625  1.8% 
NET EXPENDITURE  105,724  (11,196)  94,528  94,903  (375)  (0.4%)

Page 11

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Objective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Finance and Resources Directorate  (4,060)  3,253  (807)  (898)  91  11.3% 
Audit Services  677  (65)  612  538  74  12.1% 
Corporate Governance  3,239  (327)  2,912  2,912  0  0.0% 
Digital, Transformation & Customer Services  24,625  (1,591)  23,034  23,050  (16)  (0.1%) 
Finance and Procurement  5,932  (401)  5,531  5,525  6  0.1% 
Business Services  9,154  (1,292)  7,862  7,849  13  0.2% 
Housing Benefits  1,669  9  1,678  1,694  (16)  (1.0%) 
People & Organisational Development  2,329  (219)  2,110  2,205  (95)  (4.5%) 
Social care (non‐delegated)  818  0  818  818  0  0.0% 
NET EXPENDITURE  44,383  (633)  43,750  43,693  57  0.1%

Page 12

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ FINANCE & RESOURCES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Subjective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Employees  35,166  (1,334)  33,832  34,221  (389)  (1.1%) 
Premises Related  2,552  186  2,738  2,660  78  2.8% 
Transport Related  259  0  259  237  22  8.5% 
Supplies and Services  8,865  1,025  9,890  9,816  74  0.7% 
Third Party Payments  1,883  0  1,883  1,859  24  1.3% 
Transfer Payments  45,300  1,049  46,349  46,300  49  0.1% 
Support Services  380  0  380  375  5  1.3% 
GROSS EXPENDITURE  94,405  926  95,331  95,468  (137)  13.6% 
Income  (50,022)  (1,559)  (51,581)  (51,775)  194  0.4% 
NET EXPENDITURE  44,383  (633)  43,750  43,693  57  0.1%

Page 13

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ ENVIRONMENT, HOUSING AND INFRASTRUCTURE 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Objective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Building Services  (265)  374  109  109  0  0.0% 
Public Building Repairs  3,591  331  3,922  4,311  (389)  (9.9%) 
Soft Facilities Management Services  19,542  (682)  18,860  18,848  12  0.1% 
Property Services  147  56  203  203  0  0.0% 
NET EXPENDITURE  23,015  79  23,094  23,471  (377)  (1.6%) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Subjective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Employees  30,027  1,296  31,323  30,955  368  1.2% 
Premises Related  3,114  460  3,574  4,385  (811)  (22.7%) 
Transport Related  1,514  16  1,530  1,678  (148)  (9.7%) 
Supplies and Services  11,086  190  11,276  12,594  (1,318)  (11.7%) 
Transfer Payments  124  27  151  110  41  27.2% 
Support Services  1,191  31  1,222  1,211  11  0.9% 
GROSS EXPENDITURE  47,056  2,020  49,076  50,933  (1,857)  (3.8%) 
Income  (24,041)  (1,941)  (25,982)  (27,462)  1,480  5.7% 
NET EXPENDITURE  23,015  79  23,094  23,471  (377)  (1.6%)

Page 14

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ CHIEF EXECUTIVE'S SERVICE (ESTATES) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Subjective Summary 
Approved 
Annual Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget Variance  
(Adverse) or Favourable 
 
 
£000  £000  £000  £000  £000  % 
Employees  0  0  0     0  0.0% 
Premises Related  1,128  0  1,128  1,134  (6)  (0.5%) 
Supplies and Services  4  0  4  4  0  0.0% 
Transfer Payments  66  0  66  66  0  0.0% 
GROSS EXPENDITURE  1,198  0  1,198  1,204  (6)  (0.5%) 
Income  (1,366)  0  (1,366)  (1,317)  (49)  (3.6%) 
NET EXPENDITURE  (168)  0  (168)  (113)  (55)  (32.7%)

Page 15

Appendix 1 
RENFREWSHIRE COUNCIL 
REVENUE BUDGET MONITORING STATEMENT 2024/25 
1 April 2024 to 21 June 2024 
 
 
 
 
 
 
 
 
 
 
 
 
POLICY BOARD:  FINANCE, RESOURCES & CUSTOMER SERVICES ‐ MISCELLANEOUS 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Subjective Summary 
Approved Annual 
Budget  
Budget 
Adjustments 
Revised Annual 
Budget at 
Period 3 
Projected 
Outturn 
Budget 
Variance  
(Adverse) or 
Favourable 
 
 
£000  £000  £000  £000  £000  % 
Employees  34,428  (14,448)  19,980  19,980  0  0.0% 
Premises Related  6,906  (952)  5,954  5,954  0  0.0% 
Transport Related  400  0  400  400  0  0.0% 
Supplies and Services  6,808  987  7,795  7,795  0  0.0% 
Third Party Payments  42  0  42  42  0  0.0% 
Transfer Payments  (5,002)  3,771  (1,231)  (1,231)  0  0.0% 
Support Services  (1,400)  0  (1,400)  (1,400)  0  0.0% 
Depreciation and Impairment Losses  9,182  0  9,182  9,182  0  0.0% 
GROSS EXPENDITURE  51,364  (10,642)  40,722  40,722  0  0.0% 
Income  (12,870)  0  (12,870)  (12,870)  0  0.0% 
NET EXPENDITURE  38,494  (10,642)  27,852  27,852  0  0.0%

Page 16

Appendix 2 
Approved   Budget  Revised  Projected 
Budget Adjustments Budget Outturn Total Approved Projected
2024‐25 in 2024‐25 2024‐25 2024‐25 Budget Outurn 
Project Title to 31‐Mar‐29 to 31‐Mar‐29
£000 £000 £000 £000 £000 £000
CORPORATE PROJECTS
ICT Infrastructure Maintenance & Renewal Programme 600 969 1,569 1,569 0 0% 3,369 3,369 0 0%
Strategic Asset Management Fund 0 0 0 0 0 0% 0 0 0 0%
Energy Efficiency Programme 0 0 0 0 0 0% 0 0 0 0%
Lifecycle Capital Maintenance (LCM) Fund 8,837 2,360 11,197 11,197 0 0% 23,827 23,827 0 0%
Artificial Pitch Upgrades 0 524 524 524 0 0% 1,801 1,801 0 0%
Digital Infrastructure Provision 0 32 32 32 0 0% 1,936 1,936 0 0%
Commnunity Empowerment Fund 0 552 552 552 0 0% 951 951 0 0%
Greenspaces and Parks 0 0 0 0 0 0% 1,273 1,273 0 0%
Villages Improvement Fund 200 76 276 276 0 0% 550 550 0 0%
Retail Improvement Fund 70 74 144 144 0 0% 220 220 0 0%
CO2 Monitors 0 0 0 0 0 0% 233 233 0 0%
TOTAL FINANCE, RESOURCES & CUSTOMER SERVICES 
BOARD 9,707 4,587 14,294 14,294 0 0% 34,160 34,160 0 0%
Budget Variance (Adverse) or 
Favourable
Budget Variance (Adverse) or 
Favourable
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY ‐ NON‐HOUSING SERVICES
1st April to 21st June 2024
POLICY BOARD: FINANCE, RESOURCES & CUSTOMER SERVICES
Current Year 2024‐25 Full Programme ‐ All years