To: Finance, Resources and Customer Services Policy Board
On: 13 June 2024 
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure 
___________________________________________________________________
Heading: Contract Award: Demolition and site clearance of Council properties at 
Tannahill area, Paisley (RC-CPU-23-218)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract for Demolition and site clearance of Council properties at
Tannahill area, Paisley (RC-CPU-23-218) to Caskie Limited.  
 
1.2 The recommendation to award the Contract follows a procurement
exercise conducted in accordance with both the Council’s Standing
Orders Relating to Contracts and the requirements under the Scotland
Excel Framework Agreement for Demolition and Deconstruction Works
(Reference 1119) . 
1.3 A Mini-Competition was conducted under Lot 2 (Demolition and
Deconstruction Works on or over £50,000). 
1.4 A Contract Strategy was approved by the Corporate Procurement
Manager on 28 March 2024 and the Head of Housing Services on 4
April 2024.

Page 2

__________________________________________________________________________________
2. Recommendations 
2.1 It is recommended that the Finance, Resources and Customer Services
Policy Board: 
(a) Authorises the Head of Corporate Governance to award a
Works Contract, a Call-Off Contract under Lot 2 of the Scotland
Excel Framework Agreement for Demolition and Deconstruction
Works in the form of SBCC Minor Works Building Contract for
use in Scotland, 2016 Edition as supplemented and amended by
the Employer’s Amendments for Demolition and site clearance
of Council properties at Tannahill area, Paisley, reference RC-
CPU-23-218 to Caskie Limited; 
(b) Authorises the Contract Sum of £630,817.00 excluding VAT for
this Contract (the approved contract value); 
(c) Notes the Date for Commencement of the Works is 15 July 2024
and the Date for Completion is 52 weeks from the Date for
Commencement of the Works. The actual dates will be
confirmed in the Council’s Letter of Acceptance to Caskie
Limited.
_________________________________________________________
3. Background
3.1 This procurement is for the appointment of a Contractor to carry out the
Demolition and site clearance of 51 Housing blocks of empty Council-
owned domestic dwellings at Ferguslie Park Avenue, Drums Avenue,
Tannahill Road and Tannahill Terrace, Paisley. 
3.2 The proposed demolition of these buildings was approved at the
Communities, Housing and Planning Policy Board on 30 October 2018.
The properties have recently been subject to fire-raising and instances
of anti-social behaviour.  The site will be landscaped on completion of
the demolition works while longer term proposals for the site are
considered within the context of the Community Led Development
Framework that was approved by the Leadership Board on 01
December 2021.

Page 3

Opportunities for the redevelopment of the site will be considered
within the context of the community and stakeholder consultation on
the emerging development framework for the wider Ferguslie Park
area. 
3.3  The Scotland Excel Framework Agreement for Demolition and
Deconstruction Works (Reference 1119) (“Framework”) has been in
place since 1 August 2020.  The Framework has a Lot specific to
Demolition and Deconstruction Works on or over £50,000 (Lot 2). This
procurement exercise was conducted as a mini competition under Lot 2
of this Framework.  
3.4 In accordance with the Framework, the Council invited all 17
Contractors appointed to the Renfrewshire Council area for Lot 2 to
participate in the Mini Competition for the required Demolition and site
clearance of Council properties at Tannahill area, Paisley via Public
Contracts Scotland – Tender Portal (PCS-T) on 4 April 2024.  
3.5 By the closing date set for the return of electronic tender submissions,
12 noon on 25 April 2024, five Contractors submitted a tender response
to the mini competition, one Contractor declined, and eleven
Contractors failed to respond. 
3.6 During the evaluation period one Contractor withdrew from the tender
process due to an error in their price submission.
3.7 The four remaining Contractor tender submissions were each
evaluated against the Award Criteria of 60% Price and 40% Quality.
The scores relative to the Award Criteria for each of the four tender
submissions are noted below:
Tenderer Price
(60%)
Quality
(40%) Total
Caskie Limited 54.67% 38.00% 92.67%
George Beattie & Sons Limited 45.45% 40.00% 85.45%
Central Demolition Limited 60.00% 22.75% 82.75%
Dem-Master Demolition Limited 47.56% 33.75% 81.31% 
3.8 The evaluation of tender submissions received identified that the tender
submission by Caskie Limited was the most economically
advantageous tender.

Page 4

3.9 The form of Contract is the SBCC Minor Works Building Contract for
use in Scotland, 2016 Edition as supplemented and amended by the
Employer’s Amendments. 
3.10  The costs for this Contract will be met from the Housing Revenue
Account (HRA) Capital Programme budget.
3.11 Community Benefits were requested as part of this procurement
exercise and Caskie Limited confirmed that the following Community
Benefits would be made available to the Council for this Contract: 
Community Benefit Description No of People
/ Activity
Job for a young person (16-24) 1
Work Experience for individual 16+ 2
Industry Awareness Event 1  
___________________________________________________________________
Implications of the Report
1. Financial –The cost of £630,817 will be met through the Housing
Revenue Account (HRA) Capital Programme budget. The anticipated
Contract start date is 15 July 2024 for duration of 52 weeks.   
2. HR & Organisational Development – None directly arising from this
report. 
3. Community/Council Planning –  
 Our Renfrewshire is safe – removing wholly vacant properties
within regeneration areas that are causing security and safety
concerns to tenants and residents. 
 Place: 
- Working with partners to ensure our neighbourhoods are safe,
vibrant, and attractive places to live.

Page 5

- Economy: 
- Creating sustainable opportunities for people who live in
Renfrewshire, attracting good employers to the area and
encouraging growth of businesses already operating here,
ensuring that all people can benefit from the inclusive growth in
Renfrewshire.
- Supporting our citizens, particularly those furthest from the jobs
market, into fair work – well paid, fulfilling employment.
- Matching the skills developed in Renfrewshire with the
opportunities available in Renfrewshire and equipping all
children and young people to achieve success in life.
- Green: 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
- Ensuring our journey to net zero is a just transition with climate
justice and fairness at the heart, finding opportunities to
challenge inequalities in new green ways as we tackle the
climate crisis.
- Empowering colleagues, organisations, businesses, and
communities to access the information they need to make
informed and positive green choices.
- Living our Values: 
- Ensuring Renfrewshire Council delivers best value for our
citizens and customers, that we are well governed, effective
organisation. 
4. Legal – The Procurement of this Contract was conducted in
accordance with the requirements for a Mini Competition under Lot 2
(Demolition and Deconstruction Works on or over £50,000) of the
Scotland Excel Framework Agreement for Demolition and
Deconstruction Works (Reference 1119) and the Council’s Standing
Orders Relating to Contracts (1 January 2024). 
5. Property/Assets – Demolition of 51 Housing blocks of empty Council-
owned domestic dwellings at Ferguslie Park Avenue, Drums Avenue,
Tannahill Road and Tannahill Terrace, Paisley. 
6. Information Technology – None directly arising from this report.

Page 6

7. Equality & Human Rights - The recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report. If required
following implementation, the actual impact of the recommendations
and the mitigating actions will be reviewed and monitored, and the
results of the assessment will be published on the Council’s website.
8. Health & Safety – Caskie Limited health and safety credentials were
evaluated by Corporate Health and Safety and met the Council’s
minimum requirements regarding health and safety.  
9. Procurement – The procurement procedures outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency, and modern Government.  
10. Risk – Caskie Limited insurances have been assessed and evaluated
to confirm that they meet the requirements regarding insurance risk.    
11. Cosla Policy Position – None directly arising from this report.  
12. Climate Risk – The level of impact associated with provision of these
works have been assessed using the Scottish Government
Sustainability Test and is considered High Risk. 
To mitigate against the High Risk, impact the Contractor:
- Has an Environmental Policy and Emissions Policy that is
reviewed annually.
- Use only deforestation free paper that is 100% recycled.
- Company policy is not to leave office equipment on standby.
- Offices have been transferred to a 100% renewable electricity
supplier and all lighting within building replaced with low energy
LED fitments.
- Waste will be collected and segregated using a licensed Waste
Management Contractor
- The Waste Management Contractor will provide detailed
monthly waste reports to inform of recycled waste and waste to
landfill. Copies of waste reports will be made available to the 
Council’s Contract Administrator. 
- Anticipate that around 95% of all materials arising from
demolition works will be recycled in line with normal company
outcomes.

Page 7

- Clean timber will be recycled for use as Biomass or Timber chip
for board manufacturers.  Metal and electrical cables will be
recycled through specialist scrap metal dealers and concrete,
brick and masonry crushed to form aggregates for supply to
local construction projects. Only contaminated materials will be
disposed of to landfill.
- Aim to work with organisations such as Circular Communities
Scotland to support reuse and recycling charities in their efforts
to prevent materials from entering landfill. Where possible
suitable materials and broken but repairable items would be
segregated for refurbishment through this network enabling
existing material and products to remain in use for as long as
possible.
- Site management will monitor dust emissions daily ensuring
appropriate methods to damp down debris using pressure
washers to minimise dust generated and water canon to
suppress any airborne particles that do arise. Drivers will
undertake wheel cleaning protocol prior to leaving site, where
necessary we will deploy a road brush to maintain the
surrounding highways.
- On site Plant Equipment in intermittent use shall be shut down
during the periods between work or, where this is impractical,
shall be throttled to a minimum. 
- Where practical, the use of HVO (Hydrotreated Vegetable Oil)
will be utilised as a renewable diesel alternative and means of
reducing emissions. Battery powered hand tools will be used in
preference to petrol driven alternatives.
The Contractor is also required as per the Scope to:
- Provide a site-specific waste management plan to reflect the key
elements of the waste hierarchy i.e. Prevention, Re-use,
Recycling, Recovery & Disposal.
- Comply with all requirements stipulated by ISO14001 standards
across the project in terms of environmental best practice
- All on site waste management will be in line with the
requirements of the Waste (Scotland) Regulations 2012, with
Zero Waste to be applied where possible.
- Fully comply with the Duty of Care requirements set out in the
Environmental Protection Act 1990 (including the use of sub-
contractors).
_________________________________________________________

Page 8

List of Background Papers 
(a) Report to Communities, Housing and Planning Policy Board on 30
October 2018 titled “Housing Investment Strategy for the Tannahill
Area, Ferguslie Park”. 
(b) Report to Leadership Board on 01 December 2021 titled “The
Making of Ferguslie – Framework Report and Place Plan”. 
___________________________________________________________________ 
Author:          Claire Earnshaw, Senior Procurement Specialist, Corporate
Procurement Unit, claire.earnshaw@renfrewshire.gov.uk