Integration Joint Board
13th  March 2026
Subject : Transformation Plan Update
Purpose : The purpose of this report is to provide an update on the HSCP’s
Transformation Plan:-
• Awareness 
• Approval
• Discussion
Recommendation : The Integration Joint Board are asked to note the contents of the
report and progress to date.   
Direction Required to
Council, Health Board or
Both 
Direction to :- 
1. No Direction Required 
2. North Ayrshire Council 
3. NHS Ayrshire & Arran 
4. North Ayrshire Council and NHS Ayrshire & Arran 
Glossary of Terms 
NHS AA NHS Ayrshire and Arran
HSCP Health and Social Care Partnership
IJB Integrated Joint Board
PMI Property Management and Investment
TEC Technology Enabled Care
DPIA Data Protection Impact Assessment 
1. EXECUTIVE SUMMARY 
1.1 This report provides an update to the Integrated Joint Board (IJB) on progress with
the HSCP Transformation Plan 2024–27. Following external scrutiny and an internal
review, the Plan has been refreshed to improve focus, deliverability and alignment
with financial plans, with a reduced number of clearly defined projects now overseen
by the Transformation Board. 
A formal benefits realisation approach has been introduced, strengthening
governance, transparency and reporting of cashable and non-cashable benefits. The
Programme has delivered £1.824m in savings to date, with total savings of over £4.8m
anticipated by 2026/27, subject to successful delivery of projects in progress. 
The report proposes that the IJB note the progress made and the strengthened
arrangements now in place.

Page 2

2. BACKGROUND 
2.1 In March 2024, the Integration Joint Board (IJB) approved the Transformation Plan for
2024-27.  The Plan was established to deliver transformation projects and
programmes across the Partnership.  It was agreed that updates on the
Transformation Plan would be provided to the IJB every six months.  The previous
update was in August 2025.   
In September 2025, Audit Scotland produced its annual audit report of the North
Ayrshire Integration Joint Board.  The audit highlighted the importance of
the Transformation Plan in managing within budget, while also recognising that future
recurring savings will be delivered in other areas, such as workforce changes and
service reviews.   
2.2 Internal Audit carried out an audit of the IJB Transformation arrangements with the
final report in August 2025 reporting Substantial Assurance.  The objectives of the
audit being that there are adequate governance arrangements in place for
transformation workstreams, adequate financial monitoring arrangements are in place
for the transformation workstreams and that there are adequate programme
management arrangements in place for transformation workstreams. 
Substantial Assurance is an assessment that indicates there is - “A sound system of
governance, risk management and control exist, with internal controls operating
effectively and being consistently applied to support the achievement of objectives in
the area audited.” 
The audit opinion summarised that: 
• Overall, substantial assurance was obtained with regard to the governance of
the HSCP’s Transformation Plan. The current governance arrangements
include clear reporting lines and involve senior managers at an appropriate
level. The Transformation Board meets regularly and has a good overview of
the projects, including access to a tracker which is summarised in a 1-page
dashboard. A low priority action has been recommended to correct a
discrepancy in the Terms of Reference for the Board. 
• Projects have governance arrangements which are appropriate to their size.
The documentation required for the projects is clearly laid out and includes the
requisite elements to give managers and sponsors the information they require
for decision-making. Risk registers are maintained for the projects and regularly
reviewed. Exceptions are escalated and appropriate actions put in place.
Financial monitoring arrangements are in place that would highlight any
significant divergences from budget.

Page 3

2.3 In light of the scale of challenge faced across the HSCP and critical importance of the
transformation plans a further internal review was undertaken of the projects on the
Transformation Plan in November.  The objective of the review was to: 
• Rationalise the number of projects on the Transformation Plan to a more
manageable set of projects.
• Ensure that projects on the Plan were appropriately scoped and detailed, and
could be delivered within the lifetime of the Transformation Plan.
• Improve reporting mechanisms so that all involved in delivering projects and
overseeing governance of the Plan had improved oversight of project
objectives.  
• Improve alignment with HSCP savings plan and financial challenges. 
A number of outputs have resulted from the review.  
i. An updated Transformation Plan has been produced
ii. A new approach to monitoring the impact of projects has been introduced as
part of a new Benefits Realisation approach
iii. Improved reporting and governance arrangements 
(i) Updated Transformation Plan 
2.4 The review of Transformation Projects made clear that projects varied in their scope
and size.  Over time, the number of projects on the Plan had grown to 77.  Where
some projects were clearly defined with set objectives and savings, others were found
to be part of wider workstreams or strategic policy reviews. Some of this activity was
also considered business as usual. 
The following steps were taken as part of the review: 
• Condensing any workstreams into one singular project with defined benefits. 
• Closing or accelerating to completion any projects that are nearing their end
and/or unlikely to deliver benefits. 
• Removing items from the Plan which are not projects, e.g. research, reviews,
strategy updates. 
• Ensuring any remaining projects have clearly defined objectives and benefits
and support the HSCP’s financial plans. 
Appendix 1 shows the current new Transformation Plan.  The visual diagram provides
the following information: 
• The current status of each project, from proposal status, through to business
case and onto benefit delivery
• The RAG status of each project that is in delivery, allowing an ‘at a glance’
view of projects 
• Which projects are anticipated to deliver financial benefits

Page 4

The Transformation Plan is reviewed by the Transformation Board every 2 months. 
(ii) Benefit Realisation 
2.5 Introducing a framework to monitor and measure the impacts of projects
can help address the recommendations outlined by Audit Scotland.  On 4 December
2025, the Transformation Board approved Benefit Realisation and Management
Approach.  This defines what a benefit is, how it should be measured and also the
roles and responsibilities for ensuring benefits are achieved.   
All projects that have an approved business case will now also have a benefit tracker,
which outlines what is the expected benefit of each project.  Benefits are defined as:
• Cashable
• Quantitative
• Qualitative. 
In introducing this framework, the Transformation Board ensures that: 
• Projects can be appraised on what they are forecast to achieve. 
• Monitoring of project impact is clear and transparent. 
• Steps can be taken at an early stage to take corrective action should progress
slip. 
• Evidence can be readily provided to externally bodies examining the impact
and progress of transformation and other initiatives.   
As noted above, all projects on the Transformation Plan will have benefits trackers, to
monitor the delivery of all project benefits, including cashable benefits. 
Appendix 2 provides an example of what a benefit tracker looks like for projects.  Three
benefits for the Brighter Pathways project have been included to demonstrate the way
in which benefits are baselined, tracked and monitored. 
(iii) Enhanced Governance  
2.6 The introduction of benefit trackers has enabled a clearer picture of the financial
benefits aligned to projects on the Programme and the progress in achieving these
benefits.  This is also underpinned by close working with HSCP finance colleagues. 
While this good working relationship is not new, sharing the position on project
progress with cashable benefits contributes to improved planning and coordination. 
In addition, a new process has been introduced for projects being appraised and
approved by Transformation Board, with a move to a streamlined project
documentation approach.  This is outlined below:

Page 5

Planning Managers complete Status Update reports every two months for discussion
at Transformation Board.  These are attached as an appendix and discussed in more
detail in section 2.8-2.10.   
Transformation Update 
2.7 In addition to the updates and changes to the Transformation approach outlined
above, the following key activities have taken place this period: 
• The Terms of Reference for the Transformation Board has been updated and
approved.  This was an action from a recent internal audit.
• During March, Planning Managers will receive training on Service Design. 
Delivered by the Service Design Academy, the training will equip Planning
Managers with a new skillset aimed at supporting teams and services through
service changes in a collaborative and dynamic way
• A new Digital Working group has been established which aims to better
coordinate the Partnership’s digital approach.  This group will report to the
Transformation Board and be a space to share knowledge, issues, updates
and best practice with colleagues from IT in the Council and Health Board
being core members.
• Senior Officers are participating in a corporate trial of Microsoft CoPilot.  This
is designed to explore the benefits of CoPilot in speeding up routine and every
day tasks, thereby improving productivity.   
Appendix 1 displays all of the projects on the Transformation Plan.  Appendices 3-5
provide greater detail on progress within each of the three Services: Children, Families
and Justice, Health and Community Care and Mental Health and Learning Disabilities.
This section will provide a spotlight on a selected project within each area, to provide
members with more detail and information on some of the initiatives currently taking
place.   
2.8 Children, Families and Justice
Project spotlight: Brighter Pathways 
Brighter Pathways has a number of workstreams established to deliver the
programme.  The residential placement workstream targets the creation of a new
residence for young people supporting them to make the transition to sustain tenancy,
Boyle Street.  The building will have capacity for 6 young people.  Significant activity

Page 6

is therefore currently taking place to have the new service operational for April.  This
is happening on a number of fronts including working with colleagues to identify
individuals to move into Boyle St, working with Property Management and Investment
(PMI) to ensure building works are complete and mobilising the contract and service
with the new provider Blue Triangle. 
Overall, works are progressing well and currently on course for opening in April.  It is
anticipated this step down model will have a positive impact on use of internal and
external residential placements. 
2.9 Health and Community Care
Project spotlight: Technology Enabled Care Hub 
The Technology Enabled Care (TEC) Hub is a key element of the refreshed
Transformation Plan and supports a shift towards a TEC First approach across North
Ayrshire HSCP. The project brings together technology, equipment and professional
expertise in a single, community-facing hub, with the aim of supporting earlier
intervention, greater independence and reduced reliance on traditional care
packages. It aligns with national digital health and care priorities and local ambitions
around prevention and sustainability.  Our North Ayrshire Hub will be based at
Castleview Hub in Ardrossan, co-located with our moving and handling hub for staff
and carers. 
Good progress has been made, with the business case developed and preparatory
work underway to establish the hub space, including layout planning, clearance works
and early procurement of technology and equipment. The next phase will focus on
completing refurbishment, installing and testing technology and moving towards
operational delivery, with a clear focus on benefits realisation, including supporting
discharge, reducing pressure on care at home services and increasing confidence in
the use of technology enabled care. 
2.10 Mental Health and Learning Disabilities 
Project Highlight: Magic Notes  
Magic Notes is an AI-powered meeting summarisation tool developed specifically for
social work.  It records, transcribes and summarises meetings into templates built
bespoke to suit the requirements of the case management system.  With funding from
the North Ayrshire Council Change Fund, the HSCP has procured a trial of Magic
Notes to test and evaluate the benefits it may bring to Services.   
The Mental Health and Learning Disabilities teams will trial its use for 6-8 weeks
beginning on 2 March 2026.  Evaluations from other areas have shown positive time
savings, increased quality of interactions and practitioner sentiment.  A thorough Data
Protection Impact Assessment (DPIA) was completed as part of the procurement to
ensure data is processed safely and any risks are mitigated.  As a part of this process,
a robust consent procedure has been developed and will be followed by staff prior to
the use of the product.  Assuming positive benefits are achieved from the trial, a

Page 7

business case outlining expected benefits from a roll out across all social work
services will be developed. 
3. PROPOSALS 
3.1 It is proposed that IJB note the contents of the report and the progress made to date.
3.2 Anticipated Outcomes 
Informing IJB and the people of North Ayrshire on the progress of the Transformation
Plan and also providing assurance of the governance arrangements and that the
Transformation Board has appropriate oversight. 
3.3 Measuring Impact 
Stakeholders are assured of progress. 
4. IMPLICATIONS 
4.1 Financial 
Some projects on the Transformation Plan will deliver financial benefits and progress
towards this has been outlined in section 2.6. 
4.2 Human Resources
None
4.3 Legal
None
4.4 Equality/Socio-Economic
None
4.5 Risk
None
4.6 Community Wealth Building
None
4.7 Key Priorities
None 
5. CONSULTATION 
Consultation has taken place with members of Transformation Board, which includes
Heads of Service and Planning Managers. 
Caroline Cameron, Director 
Stuart MacMillan, Principal Manager
stuartmacmillan@north-ayrshire.gov.uk 
Appendices

Page 8

• 1.  Refreshed Transformation Plan
• 2. Brighter Pathways Benefit Tracker
• 3. Children, Families and Justice Update
• 4. Health and Community Care update
• 5. Mental Health and Learning Disabilities Update

Page 9

Appendix 1 – Transformation Plan

Page 10

Appendix 2: Brighter Pathways Benefit Tracker 
Benefit
Type
Benefit
Category Benefit Name Baseline
Measurement
Baseline
Date
Baseline
Source
Benefit 
Target
Value
Benefit 
Target
Date
Frequency of
Measurement
Benefits
Owner
Non-Cashable Quantitative
Reduction in the
number of external
residential
placements
34 2025/26
Brighter Pathways
Report presented
to IJB Nov 2025
(Page 46)
25 31-Mar-27 Quarterly Elizabeth
Stewart
Cashable Rationalisation
Reduction in the cost
of external
residential
placements
£8,442,349 2025/26
Brighter Pathways
Report presented
to IJB Nov 2025
(Page 46)
£6,706,621 31-Mar-27 Quarterly Elizabeth
Stewart
Non-Cashable Quantitative
Increase in the
number of foster care
placements
135 2025/26
Brighter Pathways
Report presented
to IJB Nov 2025
(Page 46)
138 31-Mar-27 Quarterly Elizabeth
Stewart

Page 11

Appendix 3: Children, Families and Justice update

Page 12

Appendix 4: Health and Community Care update

Page 13

Appendix 5: Mental Health and Learning Disabilities Update