Integration Joint Board
30th April 2026
Subject: Strategic Risk Register 
Purpose: To present the updated IJB Strategic Risk Register for
consideration and approval. 
Recommendation: To approve the updated IJB Strategic Risk Register   
Direction Required to
Council, Health Board or
Both 
Direction to:- 
1. No Direction Required X
2. North Ayrshire Council 
3. NHS Ayrshire & Arran 
4. North Ayrshire Council and NHS Ayrshire & Arran 
Glossary of Terms 
IJB Integrated Joint Board    
NHS National Health Service         
PAC  Performance Audit Committee 
PSMT  Partnership Senior Management Team 
1. EXECUTIVE SUMMARY 
1.1 This report provides an update on the strategic risk register, to help ensure the IJB
are proactive in identifying and managing the risks to the successful delivery of our
Strategic Plan. 
2. BACKGROUND 
2.1 A Strategic Risk Register is a requirement of the Clinical and Care Governance
Framework and as part of our Risk Management Strategy, which was last approved
by the IJB in June 2025. 
The review focussed on updating previous risks and identifying if there were any new
risks. 
2.2 New Risks:
There are no new proposed Strategic Risks.

Page 2

2.3 Risks with an increased score: 
Ref Title Description
SRR01 Financial
Sustainability 
Resources have not kept pace with the demand for
and cost of social care services.  Financial modelling
suggests significant ongoing challenges across the
medium-term with 2026/27 being particularly
challenging. This results in a greater risk to the
financial sustainability of the IJB. The gross risk
remained at 25 (Very High) but the residual risk
increased from 16 (High) to 20 (Very High).
SRR05 Transformation
Programme
Failure to deliver the transformational change
required to meet current and future demands and
ensure our long-term financial sustainability. The
gross risk remained at 12 (High) but the residual risk
increased from 6 (Moderate) to 9 (Moderate).
SRR09 Local Impact of
Scottish
Government
Policies
Risk of further legislative, policy developments or
change which impacts on the IJBs ability to deliver on
strategic objectives. The gross risk remained at 16
(High) but the residual risk increased from 12 (High)
to 16 (High) mainly in relation to the ongoing
uncertainty around the Reduced Working Week
(RWW) and any future policy intent following the
Scottish Parliamentary Elections.
SRR13 Provider
Failure
(commissioned
services)
There is an ongoing risk of social care supplier failure
due to staffing and recruitment challenges and the
financial viability of care providers.  Supplier failure
leads to risk to service users, potential for withdrawal
of care and disruption to care plans. The gross risk
remained at 16 (High) but the residual risk increased
from 12 (High) to 16 (High).
SRR15 Risk of Harm A lack of resources combined with an increase in both
demand and complexity is leading to increasing
numbers of residents waiting for services, whether
that be for referral, assessment or the provision of
care and support.  Resources will be directed at those
with the greatest need, reducing capacity for early
intervention and prevention supports.  This results in
a greater likelihood of residents experiencing harm as
a result.  The gross risk increased from 16 to 20 which
reflects the current financial position and the move to
critical eligibility criteria for access to social care
services. 
2.4 The actions required to manage and control the risks have been identified and they
will be subject to ongoing monitoring and review by the PSMT with an update to be
reported to the Performance and Audit Committee. 
2.5  There are 12 risks noted on the Strategic Risk Register, with a number of these graded
as very high or high risk.  While there are a number of controls and mitigations in place
there may be further actions required to reduce the risks further in line with the level
of risk tolerance.  The current Strategic Risk Register is included as Appendix A.   
The risks are summarised below:

Page 3

Ref Title Gross
Risk
(score
pending
further
controls) 
2025
Residual
Risk          
(score
after
further
controls)     
2025
Gross
Risk
(score
pending
further
controls) 
2026
Residual
Risk          
(score
after
further
controls)     
2026
SRR01 Financial
Sustainability 
25             
Very 
High
16
High
25             
Very 
High
20             
Very 
High 
SRR02 Infrastructure                        
(ICT Integration)
12
High 
9                   
Moderate
12
High 
9                   
Moderate
SRR05 Transformational
Change Programme
12
High 
6
Moderate
12
High 
9
Moderate
SRR06 Governance 9
Moderate
3                    
Low
9
Moderate
3                    
Low
SRR07 Demography and
Inequality Pressures
16
High 
12
High
16
High 
12
High
SRR08 Workforce 12                       
High
9
Moderate
12                       
High
9
Moderate
SRR09 Local Impact of
Scottish
Government
Policies
16                       
High
12                 
High
16                       
High
16                 
High
SRR12  Clinical and Care
Governance
9
Moderate
9 
Moderate
9
Moderate
9 
Moderate
SRR13 Provider Failure
(commissioned
services)
16
High
12          
High
16
High
16          
High
SRR14  Asylum Arrivals 12
High
12          
High
12
High
12          
High
SRR15 Risk of Harm  16                       
High
16                 
High
20             
Very 
High 
16                 
High
SRR16 Growth and
expansion of
specialist complex
care developments 
25 Very
High 
15               
High
25 Very
High 
15               
High 
2.7 The scoring of the risks is based the severity of the risk multiplied by the likelihood of
it happening.  The background to this is given in the extract of the approved risk
management strategy in Appendix B.
2.8 The operational risks of the partnership are regularly reviewed and considered at
service management meetings.  The Clincial and Care Governance Group is
responsible for the oversight of operational risks within the partnership. The Group
consider any High or Very High risks (as defined by the approved risk management
strategy) and if required esalate these to the Partnership Senior Management Team
(PSMT) for consideration for inclusion on the Strategic Risk Register. 
3. PROPOSALS

Page 4

3.1 It is proposed to approve the risk register detailed in Appendix A including the action
required to manage, mitigate and control the risks. 
3.2 Anticipated Outcomes 
Risk management is an integral part of governance, and it is essential that the IJB has
assurance that risks are identified and managed appropriately to ensure the safe and
sustainable delivery of services. 
3.3 Measuring Impact 
The risk register will be monitored with the individual risk owners being responsible
for keeping the register up to date under the overview of the Principal Manager –
Finance.  It is recommended that risk assessments be reviewed on an annual basis
as a minimum. PAC will monitor the register to ensure the actions required to manage
and control the risk are being progressed, with updates provided to the IJB and PAC
at least annually. 
4. IMPLICATIONS 
4.1 Financial
None 
4.2 Human Resources
None 
4.3 Legal
None 
4.4 Equality/Socio-Economic
None
4.5 Risk
The report falls in line with the agreed risk appetite statement which is low-risk
appetite in respect to adherence to compliance duties. 
4.6 Community Wealth Building
None. 
4.7 Key Priorities
Appropriate and effective risk management practice will deliver better outcomes for
the people of North Ayrshire, protecting the health, safety and wellbeing of everyone
who engages with the IJB or for maximising opportunity, delivering innovation and
best value, and increasing performance.

Page 5

5. CONSULTATION 
5.1 The strategic risks have been reviewed by the relevant risk owners.   
For more information please contact:
Eleanor Currie, Chief Finance Officer – Finance at eleanorcurrie@north-
ayrshire.gov.uk

Page 6

Appendix A 
Strategic Risk Register 
Glossary of Terms 
Term Definition Term Definition 
NAHSCP North Ayrshire Health and Social Care Partnership ARG Allocation of Resources Group
SAHSCP South Ayrshire Health and Social Care Partnership ICT Information and Computer Technology
EAHSCP East Ayrshire Health and Social Care Partnership MDTs Multi-Disciplinary Teams
NHS/ NHS AAA NHS Ayrshire & Arran  EKSF Electronic Knowledge and Skills Framework
MTFP Medium Term Financial Plan TURAS Training Management System
CRES Cash Releasing Efficiency Savings SPOG Strategic Planning Officers Group
LD Learning Disability ICF Integrated Care Fund
IJB Integrated Joint Board RMP Records Management Plan
PSMT Partnership Senior Management Team CPAG Child Poverty Action Group
NAC  North Ayrshire Council

Page 7

North Ayrshire Integration Joint Board
Strategic Risk Register
Is the description of the risk still relevant and accurate?
Have any of the proposed control measures from Sept 2024(column J) been implemented?  If so, then move them to this
column and rescore the risk (col F and G) based on the additional mitigation and control.
Add any new proposed measures
Risk Ref
Description of Risk Risk Owner Updated for April 2026 Mitigations/Control Measures
Previous
Score Severity Probability Score Rating Proposed New Control Measures
Previous
Score Severity Probability Score Rating
Risk
Tolerance /
Appetite
SRR01 Financial Sustainability of the Health and Social Care Partnership - Resources have not kept pace with the
demand for and cost of social care services.  Financial modelling suggests significant ongoing challenges across the
medium-term with 2026/27 being particularly challenging as the superannuation increase will cost £7.2m approx and
this is prior to considering other pressures which takes the total pressures to £25m approx. There is no certainty
around future funding against growing demand, increasing costs and demographic pressures, with one-year budget
settlements remaining in place. The most recent Medium Term Financial Outlook identified that, based on the
current assumptions made, there could be a budget gap across the period 2026-2029 ranging from £27.746m in the
best case to £47.968m in the worst case if no new funding is provided.
The 2026/27 Scottish Government budget settlement did not include any direct investment in social care.  The level
of 2026/27 funding will be subject to the agreement of the North Ayrshire Council budget.
The ongoing work to review the Integration Scheme and to develop new risk-sharing arrangements between the
Council and Health Board in relation to the acute set aside and primary care prescribing present a financial risk to
the Partnership and Council.
Unearmarked reserves are depleted, there is no scope to absorb in-year variances, with any overspends requiring
additional funding from partners.
The wider system financial challenges and impact across the whole system, for example the financial position of
NHS AA and the decisions taken to reduce the Board’s deficit may have impacts on other parts of the health and
care system.
The Partnership is projecting an overspend of £2.7m (month 10) in 2025/26, reduced to £2.251m if the additional
Reduced Working Week funding is approved.                       
Chief Finance Officer Updated The IJB actively monitors the financial position with regular detailed reporting. Directors of Finance of the Council and Health
Board have oversight, and regular updates are provided to the Council's Cabinet. There is an integrated approach to
managing the totality of NHS and Council resources delegated to the IJB. A three-year Medium-term Financial Outlook is
updated on a rolling basis each year.
Previous financial settlements have seen both partners meet the Scottish Government settlement conditions with any
additional resources passed to the IJB.
The Partnership has developed a new 3-year Transformation Plan 2024-2027 which was approved by the IJB in March 2024.
Services will continue to work towards implementing the recovery plan to deliver cost reduction targets while carefully
managing the level of risk. The management actions and governance framework agreed in 2024/25 will continue throughout
2025/26. 
Additional actions approved for 2025/26:
•	Recruitment delay – there will be a recruitment drag with vacancy scrutiny approved vacancies being held for four weeks
•	High-cost care package group – the remit of this group will be expanded to include care packages for children with a disability
and all UNPACs placement requests.
·	Oversight group for looked after and accommodated children in residential care
·	Care home placements – move to one admission for every two discharges as per PSMT approval on 20th November 2025.
The care placements at CARG to be approved on the basis of risk and need rather than current care setting. This may impact
on delayed discharges within our acute and community hospitals.
·	Care at home – recruitment freeze to gradually reduce the overspend position. Again, this will impact on wait times and
service performance.
·	All care packages (outwith in house care at home and older people placements agreed via CARG) will be considered for
approval by the high-cost care package group.
In preparation for the 2026/27 a six week budget engagement was undertaken with the public, staff, providers and community
groups.
Budget updates have also been provided regularly to the IJB Finance working group.
25 5 5 25 Very High The December 2025 Transformation Board apprroved an updated Terms of Reference and a refreshed
Transformation Plan.  This will see a reduction in the number of projects as a result of the following
actions:
·	Condensing any workstreams into one singular project with defined benefits.
·	Closing or accelerating to completion any projects that are nearing their end and/or unlikely to deliver
benefits.
·	Removing items from the Plan which are not projects, e.g. research, reviews, strategy updates.
·	Ensuring any remaining projects have clearly defined objectives and benefits and support the HSCP’s
financial plans                                                                                                                              All recovery
plan actions will be maintained into 2026/27 as will the operation of the high cost care package group and
vacancy controls.                                                                                                                                                                
The finance working group will continue to meet throughout 2026/27 and assist in the planning of the
2027/28 budget setting.                                                                                                                                                                  
The Chief Officer and Chief Finance officer will continue to lobby the Scottish Government and make the
case for investment in community based Health and Social Care and to recognise the demographic
impact of demand and resources in North Ayrshire.                                                                                                                                                                              
Continued representation at the Chief Officer and CFO networks,  Participation in SG sessions to outline
the local and national financial position of IJBs.
16 5 5 25 Very High Treat
SRR01
(cont)
2026/27 Budget - the 2026/27 budget was approved on 13th March 2026.  This included £2.9m of savings classified as:
•	Previously agreed savings
•	Adjustments (payroll turnover and recharges)
•	Operational savings
•	Policy – Models of care or efficiency
•	Policy – Service reduction or cessation                                                                                                                                                                 
There was also a separate paper on the £5.828m balnace of savings which will be met from revised eligibility critieria.             
The Partnership has undertaken extensive community engagement which commenced early December 2025 on the
challenges of delivering social care services within budget.  The £5.828m will be met through the review of eligibility criteria
and the 3 interlinked proposals which have been developed to implement the reductions to care packages, namely:
Proposal 1 - Changing Eligibility – Support Only for People at Critical Risk
Proposal 2 - Best Value Care Funding Framework
Proposal 3 - Prioritising Personal Care
SRR02 Infrastructure - ICT System Integration and Property - lack of an integrated IT system to meet the needs of
NAHSCP leading to non-robust and inefficient information recording and sharing resulting in inefficient business
models, duplication of effort, inaccurate or lack of data on service demand and delivery and risk to service users,
patients and staff. 
Principal Manager 
Transformation 
(usually updated by
Neil McLaughlin)
Updated                                                                                                                                                                      
* Access to systems can be requested to allow NHS-Partnership staff access to NAC systems, and NAC-Partnership staff
access of NHS systems.
* Work has progressed to reduce the number of MH ancillary recording systems and consolidate data on centralised systems.                                                                            
* HSCP systems and performance team supporting work across the partnership and progressing developments and issues
with systems                                                                                                                                                                                                   
* NHSAAA are undertaking a review of all MS Access databases in use for removal to centralised systems. - local review
linked to MH reporting completed to plan removal                                                                                          
* Implementation of Trakcare functionality within Adult Community Mental Health Services to manage patient clinics across all
three Partnerships.                                                                                                                                                                                                                                                                                           
* MH Digital Transformation board established                                                                                                                                                        
* MH digital business case being developed to address future planning needs.                                                                                                                                                                 
* Digital pilot for CYP neurodevelopment transformation with Strata Health.                                                                                                                                
12 4 3 12 High * Two groups have recently been established to better coordinate ICT issues/concerns/developments: (i)
HSCP Digital Leads with NAC, SAC, EAC and NHS IT and HSCP digital leads which is chaired by NHS
(ii) NAHSCP Digital Working Group which includes representatives from each Service.  A ToR was
recently approved at Transformation Board in February.  This group will have oversight of digital projects
on the Transformation Board.    
* Network access issues at NHS/NAC sites being explored and supported by NAC IT   
12 3 3 9 Moderate Tolerate
SRR05 Transformational Change Programme  - failure to deliver the transformational change required to meet current
and future demands and ensure our long term financial sustainability.
Principal Manager 
Transformation 
(Stuart MacMillan)
Updated * Senior Manager leading on the delivery of the Transformation Plan.
* NAHSCP Transformation Board for oversight of programme development and delivery.                                                                                                
* Reporting regularly to NAHSCP Integration Joint Board.  
* Development of Workforce Plan, and Digital and Data Plan, to ensure alignment with transformed products and services.                                                                                                                                                                                                                                                                                                                                                                                                
* Programme risk register in place, with high rated risks escalated to the Board.
* Alignment of service change/transformation plans to Strategic Plan priorities                                                                                                                                                                                                                                     
* Raise awareness of Programme within the three parent organisations (including elected members and board members) via
established reporting arrangements.                             
12 4 3 12 High * Transformation Plan has been refreshed, updating project scopes and anticipated benefits
* A benefits management approach has been introduced and all projects will have benefit trackers
assigned
* Transformation Board terms of reference has been approved
* Regular meetings in place with planning managers and Finance colleagues to ensure coordinated
approach to change and  transformation                                                                                                                                                                                                                                                                                                                                                              
12 3 3 9 Moderate Treat
SRR06 Governance -    IJB governance arrangements are not conducive to effective working and decision making, Leading
to a lack of confidence in the IJB and reputational damage.  Failure to comply with governance requirements such
as Freedom of Information, Complaints and other regulations laid down within the Public Bodies (Scotland) Act.  
This could lead to a breach of specific regulations resulting in enforcement action from governing bodies, adverse
public reaction and/or prosecution.  
Statutory Instrument to revise voting membership of IJBs to include lived experience, unpaid carer and third sector
representatives will come into effect in September 2026.    Revisions will be required to Integration Schemes,
Standing Orders.
Governance Officer 
(Karen Andrews)
Updated * Statutory governance arrangements defined by Integration Scheme are in place for representation at the IJB and sub-
committees and reviewed within prescribed requirements.
* Integration Scheme, Strategic Plan, Standing Orders and Code of Conduct in place. 
* Policies and procedures developed and in place for each function including Complaints, FOIs/Adverse Events for both
HSCP and IJB.                                                                                                                                                                                                       
* Operational Governance / Delivery groups in place to ensure appropriate action planning and monitoring including
Performance and Audit Committee, Clinical and Care Governance Group, Adverse Events Review Group, Health and Safety
Groups and the Staff Partnership Forum.        
* IJB receives 6 monthly updates on Clinical and Care Governance activity including details of adverse events; significant case
review; complaints.    This update includes details of outcomes and lessons learned. The Adverse Event Review Group now
includes a fortnightly update for all AERs across the North HSCP.                                                                                                                                                
*Approved a Risk Management Strategy, Strategic Risk Register and risk appetite statement.                                                                                                                           
*Health and Care Governance Framework in place                                                                                            
9 3 3 9 Moderate *Strengthened induction programme and governance training including code of conduct to be delivered
throughout 2026 folloiwng the changes to IJB voting rights.
* IJB Carer Representative was appointed following a successful recruitment campaign.  Additional
stakeholder appointments still to be confirmed. 
*Staturoty Instrument to extend IJB Voting Rights to include lived experience, unpaid carer and third sector
representatives
* HSCP reviewing resourcing and capacity for demand to undertake SAERs.  Proposal to enhance
process with training and reviewing capacity across the three HSCPs.
*Ongoing Integration Scheme and Standingn Orders review is underway to ensure fitness for purpose.
*Refresh of induction programme for new IJB members and refresher of code of conduct and standing
orders planned during 2026.
*Regular PAC/Internal Audit review of governance processes.
3 3 1 3 Low Treat
Review this score after
updating the mitigation and
control measures in column D
Review this score after
updating the mitigation and
control measures in column J
Gross Risk Residual Risk

Page 8

North Ayrshire Integration Joint Board
Strategic Risk Register
Is the description of the risk still relevant and accurate?
Have any of the proposed control measures from Sept 2024(column J) been implemented?  If so, then move them to this
column and rescore the risk (col F and G) based on the additional mitigation and control.
Add any new proposed measures
Risk Ref
Description of Risk Risk Owner Updated for April 2026 Mitigations/Control Measures
Previous
Score Severity Probability Score Rating Proposed New Control Measures
Previous
Score Severity Probability Score Rating
Risk
Tolerance /
Appetite
Review this score after
updating the mitigation and
control measures in column D
Review this score after
updating the mitigation and
control measures in column J
Gross Risk Residual Risk
SRR07 Demography and Inequality Pressures - failure to adequately plan for and respond to changes in our population
profile and in the levels of poverty in North Ayrshire will result in more people experiencing higher levels of physical
and mental ill health, resulting in increasing demand on services, an inability of services to provide adequate care
and negative impact on health and wellbeing. 
Chief Officer  (usually
updated by Seony
Ross)
Updated • A full review of demographics was carried out throughout 2025. The Strategic Needs Assessment was published in August
2025 and reviews information regarding general health and wellbeing, mental health, hospital and community care, children
and young people, economy and inequality. This has supported the review of the Strategic Plan as well as other internal
service reviews and other pieces of work, and has been shared with partners to support their workstreams.
•The HSCP reviewed and refreshed its Strategic Plan ‘Caring Together’ for the remainder of the plan period, which will be in
place from 1st April 2026 to the 31st of March 2030. In addition to identifying Service Delivery Priorities which support the
health and wellbeing of our communities, the Plan identified 3 Strategic Priorities which are and intended to reduce the
pressures on the HSCP by anticipating future demand and aiming to improve outcomes at a population level.
• Demography increases are factored into budget planning to ensure the resource requirements are understood and funding is
identified to meet needs. The budget has also been considered in the development of the new Strategic Plan priorities.
• The transformation programme is focused on reviewing services and ensuring transformation of services is focussed on
meeting the needs of service users, including ensuring appropriate support is in place for complex and intensive support
needs.
• A new set of Equality Outcomes was published in April 2025 which considered inequality and demographic data, and the
lived experience of equality groups within North Ayrshire. The new Equality Outcomes were published alongside a set of
actions to be achieved between 2025 and 2029 to support mainstreaming equality activity and equality of opportunity for
marginalised groups.
• Equality and Children’s Rights Impact Assessments are carried out for new policies, proposed projects and service change
proposals which are considered by IJB to inform decision making. These integrated assessments consider impacts for
protected characteristics, socio-economic disadvantage, island consideration and impacts on consumers of services.
• The HSCP has recently analysed all previous engagement carried out across the HSCP over the previous 3 years and
developed a new Participation and Engagement Strategy for 2026-2030. This strategy outlines how communities, carers, and
families will be able to share their views, and ensures the HSCP has the opportunity to hear people’s lived experience when
developing services. This will allow people’s own experiences of inequalities to be considered in our review and design of
services
16 4 4 16 High • The Strategic Plan outlines 3 Strategic Outcomes which aim to address future service requirements
based on demographic changes and local inequalities and aim to better understand and assess how we
may influence improved health and wellbeing. The Strategic Priorities are: Supporting the improvement of
population health, Addressing the Changing needs of an ageing population, and tackling the root causes
of health inequality. During 2026, the HSCP will begin a programme of work with Public Health Scotland
Analysts to research anticipated future demographic changes, how services are currently responding to
these issues and where improvements can be made. The 3 workstreams will inform the HSCPs
transformation programme and complement participation in the CHES programme.
• The CHES Programme will continue with extensive engagement activity to ensure lived experience
influences the recommendations made through the programme.
• The HSCP will develop locality plans which will consider the individual needs and circumstances of
people living in smaller communities, and will outline how our services will meet the needs of those specific
communities
• the Strategic Planning group will continue to monitor the HSCPs Strategic plan and related strategies
and respond to any demographic changes that may impact strategy delivery.
12 3 4 12 High Treat
SRR07
(cont)
Updated
• A new Learning Disability learning plan was published in 2025, which comprises of service information and engagement
insights, and explores where there may be further need for development for this specific client group.
• A new Strategy for unpaid carers: Together we care 2026-2029 was agreed by IJB in December 2025. It advises carers of
their rights, sets out plans to identify carers, routes for assessment and support, and information about local and national
services. The aim is that all North Ayrshire carers are identified, supported and valued and are afforded an opportunity to live,
work, thrive and stay connected to their communities enjoying a life alongside caring, where they choose to continue to care.
Care needs are becoming increasingly complex in North Ayrshire due to demographic changes, and the strategy will support
the unpaid carers that provide care in the community.
• North Ayrshire is participating in the Collaboration for Health Equity in Scotland Programme which will consist of intensive
research and engagement in order to make recommendations for reducing health inequalities for North Ayrshire Residents. In
North Ayrshire the programme will focus on 3 principles in 3 specific areas:
•	In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and
alcohol related harms and deaths. This includes implementing the national MAT (Medicated Assisted
Treatment) standards and increasing the number of ABIs (Alcohol Brief Interventions) delivered across
North Ayrshire.
* North Ayrshire is one of 3 areas in Scotland as part of the CHES programme (Collaboration for Health
Equity Scotland) which launched in February 2025 - this programme is a partnership between NAC and
the IJB and will involve all public sector partners to determine:
- What are the most impactful areas for intervention for Scotland to make meaningful progress in closing
the inequalities gap in healthy life expectancy?
- What action can be taken to enable national and local organisations to work more effectively together to
close the recognised implementation gap between policy intent and impact?
SRR08 Workforce - failure to recruit and retain and plan workforce requirements effectively leading to an insufficient
workforce (number of staff, key roles and competency levels), resulting in a reduction in capacity to safely and
effectively care for local people and a negative impact on service user and patient's needs being met                                                                                                 
Chief Officer  (usually
updated by Seony
Ross)
Updated •	In March 2025 the HSCP submitted a workforce template to the Scottish Government which outlined workforce challenges
for the HSCP including the agenda for change pay reform, demographic changes and increasingly complex needs, financial
pressures, and recruitment challenges. No further guidance has yet been issued by the Government
•	To develop the refreshed strategic plan for 2026, service engagement was carried out which asked services for their
challenges and opportunities which included staffing and resource challenges for specific teams
•	The learning and Development strategy for social work and social care 2023-2028 continues into its third year, continuing to
offer training and succession planning.
•	HR and service leads will continue to meet quarterly to review, update and align workforce plans in line with evolving service
demands and strategic planning requirements. Workforce Planning meetings incorporate a structured review of external
factors using PESTLE to ensure workforce strategies remain responsive and proactive.
•	The Care at Home service has an ongoing recruitment review in place as part of budget savings plan, with regular
establishment meetings taking place to review all vacancies and high-cost areas of spend to ensure all critical vacancies are
being filled where applicable.  This is done via regular recruitment events and advertising. The service has a robust
recruitment strategy which includes a retention plan which is monitored via stay/exit questionnaire completion by senior
members of the management team. 
•	The iMatter staff experience survey continues, to ensure senior managers are able to get feedback from employees about
what is important to them in the workplace. 
•	In Arran, there are ongoing high costs of agency to support Montrose House Care Home to meet staffing legislation
requirements for residents. A contract with the agency is in place to help reduce these costs and there is a rolling recruitment
programme for vacant posts and a variety of recruitment opportunities have been explored including a recruitment campaign
with assistance of an external agency.
•	Roles have been diversified to support challenges, e.g. Psychiatry has expanded MDT responsibilities to enable psychiatrists
to focus on the most complex cases, and Health Care assistant roles have been developed in wards for long-term conditions.
•	Collaborative recruitment in A&A for areas including ICT, Primary Care Implementation plan, Mental Health and Clinical
Leadership
•	Exit interviews with staff to understand reasons for leaving, using this intelligence to inform plans to improve working
conditions and role satisfaction    
12 4 3 12 High •	A new workforce plan for the HSCP which considers the above information, as well as projected
demographic challenges, will be developed in 2027.
•	With the addition of a Workforce Data Analyst, a review of workforce information was undertaken and a
phased release of new efficiently produced information developed.  This information is being phased into
use starting with the extension of core absence information to include - absence reason, absence cost,
recruitment, vacancies - now as a core element included in the Partnership's quarterly performance report
to the IJB Performance and Audit Committee.
•	A revised approach to jointly managing waiting lists has been implemented.  Adult Providers have access
to current waiting lists at all times and face to face meetings are also taking place to minimise waiting
times for services users as much as possible and maximise providers staffing resources.
•	A review of provider forums is almost complete - the focus has been on consulting with providers to
ensure a clear understanding of what the key issues are that the HSCP could support providers with at this
time.
•	The HSCP continues to review the structure on an iterative basis with opportunities progressed as they
arise to look at senior roles and to undertake gap analysis on roles and levels within the HSCP to better
deliver on team and partnership outcomes. Examples of this being the recent review of the leadership
structure in relation to finance and transformation and the review of disability services which introduced
Senior Practitioner roles to the team.  The review will continue on that basis, led by opportunity and
service need
•	Increased focus on vacancy management and recruitment alongside service impact and for service areas
with workforce shortage proactively looking to skill mix and different roles to address recruitment
challenges - examples being SLT and OT.     
9 3 3 9 Moderate Treat
SRR09 Local Impact of Scottish Government Policies:  risk of further legislative, policy developments or change which
impacts on the IJBs ability to deliver on strategic objectives, examples include theNHS Agenda for Change in the
Reduced Working Week, the Promise, the Living Wage, Free Personal Care and other future policy developments
including the now amended National Care Service. The impact being the inability to deliver on these alongside
strategic plan commitments and objectives and the impact of funding for new policy and legislative commitments.
Chief Officer Updated * Horizon scanning for policy developments through partners, professional networks including links with Scottish Government
policy teams
* Regular liaison with Scottish Government and COSLA senior officers                                                                      *
Attendance and participation at the national Chief Officer network.
* Responses to consultations on potential implementation of new policy areas
* Early impact assessments locally for national policies, including operational and financial service impact
* Financial modelling to respond to requests for information to support full funding
* Fully brief IJB members and wider partners on policy implications for the IJB to gather support and awareness of any
implementation issues or concerns
16 4 4 16 High * Promote and develop pan-Ayrshire approaches to impact assessment of policy implementation
* Reinforce the role of Elected Members and IJB members to influence Scottish Government decision
making through political routes.
12 4 3 12 High Treat
SRR12 Clinical and Care Governance: Failure to have an appropriate framework in place leading to an adverse impact on
the culture resulting in a reduction in the quality of the delivery of the highest quality of care and support is
understood.  
Chief Social Work
Officer and Associate
Nursing Director 
Updated *continuous review of arrangements for Clinical and Care Governance are essential for the delivery of statutory, policy and
professional requirements and the achievement of our quality ambitions.
*ongoing review of established structures and processes to assure Integration Joint Boards, Health Boards and Local
Authorities
*empowering clinical and care staff to contribute to the improvement of quality 
*making sure that there is a strong voice of the people and communities who use our services.
* ensure that professional leadership develops good governance for each of the following components: culture, systems,
practices, performance, vision and leadership.                                                                                   * delivery of the highest
quality of care and support is understood to be the
responsibility of everyone working in the organisation - built upon partnership and
collaboration within teams, and between health and social care professionals and
managers.
* Health and community Care have developed a governance Board to ensure feedback to the overarching Clinical and Care
Governance arrangements.
9 3 3 9 Moderate * Continue to develop and monitor key performance indicators and report effectively through governance
framework.
* Ensuring we further develop clear and consistent reporting frameworks acknowledging the growing risks
posed to service delivery due to financial and resource contraints.
9 3 3 9 Moderate Tolerate

Page 9

Appendix B
Extract from the Risk Strategy on Risk Scoring

Page 10

SEVERITY CONSEQUENCE MATRIX - Description and definition of the CONSEQUENCE / IMPACT of the risk should it occur (these are a
guide)
Severity
“Domains”
1
Insignificant
2
Minor
3
Moderate
4
Major
5
Extreme
Objectives
and projects
 Barely noticeable
reduction in scope /
quality / schedule
 Minor reduction in
scope / quality /
schedule
 Reduction in scope or
quality, project
objectives or schedule.
 Significant reduction in
ability to meet project
objectives or schedule.
 Inability to meet project
objectives, reputation of
the organisation
seriously damaged and
failure to appropriately
manage finances.
Injury
(physical and
psychological)
to
patients/staff.
 Adverse event leading
to minor injury not
requiring first aid.
 Minor injury or illness,
first-aid treatment
needed. No staff
absence required.
 Significant injury
requiring medical
treatment and/or
counselling.
 Major injuries or long-
term incapacity/ disability
(loss of limb), requiring
medical treatment and/or
counselling.
 Incident leading to death
or major permanent
incapacity.
Patient
experience /
outcome 
 Reduced quality of
patient experience /
clinical outcome not
directly related to
delivery of clinical
care. 
 Unsatisfactory patient
experience / clinical
outcome directly
related to care
provision – readily
resolvable
 Unsatisfactory patient
experience / clinical
outcome, short term
effects – expect recovery
< 1Wk
 Unsatisfactory patient
experience / clinical
outcome, long term
effects -  expect
recovery > 1Wk
 Unsatisfactory patient
experience / clinical
outcome continued
ongoing long-term
effects.

Page 11

Complaints /
claims
 Locally resolved
complaint
 Justified complaint
peripheral to clinical
care
 Below excess claim.
 Justified complaint
involving lack of
appropriate care.
 Claim above excess
level.
 Multiple justified
complaints.
 Multiple claims or single
major claims.
Staffing and
competence
 Short term low staffing
level (< 1 day), where
there is no disruption
to patient care.
 Ongoing low staffing
level results in minor
reduction in quality of
patient care
 Minor error due to
ineffective training /
implementation of
training.
 Late delivery of key
objective / service due to
lack of staff.
 Moderate error due to
ineffective training /
implementation of
training.
 Ongoing problems with
staffing levels
 Uncertain delivery of key
objective / service due to
lack of staff.
 Major error due to
ineffective training /
implementation of
training.
 Non delivery of key
objective / service due to
lack of staff.
 Loss of key staff.
 Critical error due to
insufficient training /
implementation of
training.
Service /
business
interruption
 Interruption in a
service which does
not impact on the
delivery of patient
care or the ability to
continue to provide
service
 Short term disruption
to service with minor
impact on patient
care.
 Some disruption in
service with
unacceptable impact on
patient care.
 Temporary loss of ability
to provide service.
 Sustained loss of service
which has serious
impact on delivery of
patient care resulting in
major contingency plans
being invoked.
 Permanent loss of core
service or facility.
 Disruption to facility
leading to significant
“knock on” effect.
Financial  Negligible
organisational
financial loss (£< 1k).
 Minor organisational
financial loss (£1-
10k).
 Significant organisational
financial loss (£10-100k).
 Major organisational
financial loss (£100k-
1m).
 Severe organisational
financial loss (£>1m).
Inspection /
assessment /
audit
 Small number of
recommendations
which focus on minor
quality improvement
issues.
 Minor
recommendations
made which can be
addressed by low
level of management
action.
 Challenging
recommendations but
can be addressed with
appropriate action plan.
 Enforcement Action.
 Low rating.
 Critical report.
 Prosecution.
 Zero Rating.
 Severely critical report.

Page 12

Adverse
publicity /
reputation
 No media coverage,
little effect on staff
morale.
 Local Media – short
term.
 Minor effect on staff
morale / public
attitudes.
 Local Media – long term.
 Impact on staff morale
and public perception of
the organisation.
 National Media (< 3
days).
 Public confidence in the
organisation
undermined.
 Usage of services
affected.
 National Media (> 3
days).
 MP / MSP Concern
(Questions in
Parliament).
Organisational
/ Personal
Security, and
Equipment
 Damage, loss, theft
(£< 1k).
 Damage, loss, theft       
 (£1-10k).
 Damage, loss, theft     
 (£10-100k).
 Damage, loss, theft 
 (£100k-1m).
 Damage, loss, theft
(£>1m). 
1
Remote
2
Unlikely
3
Possible
4
Likely
5
Almost Certain
Probability  Will only occur in
exceptional
circumstances.
 Unlikely to occur
but definite
potential exists.
 Reasonable chance of
occurring – has
happened before on
occasions.
 Likely to occur –
strong possibility.
 The event will
occur in most
circumstances.

Page 13

Risk Rating 
LIKELIHOOD
SEVERITY
1
Insignificant
2
Minor
3
Moderate
4
Major
5
Extreme
5
Almost Certain
5 10 15 20 25
4
Likely
4 8 12 16 20
3
Possible
3 6 9 12 15
2
Unlikely
2 4 6 8 10
1
Remote
1 2 3 4 5