NORTH AYRSHIRE COUNCIL 
30 May 2023 
Cabinet 
Title:    Regeneration Delivery Plan Action Programme and
Funding Proposals 
Purpose:  To seek approval for the proposed Regeneration Delivery
Plan action programme and funding proposals 
Recommendation:  That Cabinet: 
(a) Notes the progress made on the implementation of the
Regeneration Delivery Plan; 
(b) Approves the draft Action Programme as detailed at
Appendix One; 
(c) Approves the Regeneration Delivery Plan funding
proposals as detailed at Appendix Two; and
(d) Provides delegated authority to the Executive Director
(Place) to agree changes to the funding allocations in
consultation with the Portfolio Lead as required. 
1. Executive Summary 
1.1 The Regeneration Delivery Plan was agreed by Cabinet in March 2021.  This
sets out our priorities for delivering on the regeneration ambitions of the Council
Plan and Community Wealth Building strategy, working in partnership with
communities.   
1.2 The Plan focusses on the delivery of physical regeneration across North
Ayrshire through an ambitious project based rolling action programme.  It
informs our priorities for securing and delivering against external funding
sources including Scottish and UK Government funds.  This report provides an
update on progress to date and seeks approval for the action programme for
2023/24 and 2024/25. 
2. Background 
2.1 The Council has placed the regeneration of communities at the heart of its
agenda.  This focus is reflected within the priorities of the Council Plan and
Community Wealth Building Strategy.  The Regeneration Delivery Plan sets out

Page 2

our priorities for delivering on these ambitions and was approved by Cabinet on
23 March 2021.   
2.2 The Plan focuses on the delivery of physical regeneration in the period 2021 to
2026.  Informed by stakeholder consultation, reviewing existing community
priorities and the output of previous consultations, it aims to address local
priorities, support changes within communities and deliver a well-being
economy. 
2.3 Action in 2021/22 and 2022/23 substantially focussed on maximising the impact
and leverage of investment including securing sources of external funding to
support and accelerate delivery.  The following table outlines the progress and
key successes achieved to date.  This includes the completion and launch of
Lochshore Park Hub, securing an award from the Levelling Up Fund for the
B714 Upgrade and the completion and occupation of a new industrial unit at
Kyle Road, Irvine. 
Strengthening Communities
‒ Approval of the local delivery plans for the £1.32m annual allocation for
21/22 and 22/23 from the Scottish Government’s Vacant and Derelict
Land Fund (VDLF). This includes the review of the Vacant and Derelict
Land Strategy and further delivery on key regeneration sites.
‒ Completion of the new car park, path works and environmental
improvements at the former Gas Works, Dalry funded by the VDLF.
‒ Launch of new Repurposing Property Grant Fund to support landowners
and communities to bring vacant and derelict land and properties into
positive management including two rounds of awards. This is funded by
the Place Based Investment Programme (PBIP), VDLF and North
Ayrshire Ventures Trust.
‒ Securing £0.4m from the Scottish Government’s Vacant and Derelict Land
Investment Programme (VDLIP) 2022/23 to support the construction of an
additional Office pavilion at Annickbank, Irvine
‒ Securing £0.6m from the Scottish Government’s Vacant and Derelict Land
Investment Programme (VDLIP) 2023/24 to support the regeneration of
the King’s Arms, Irvine
‒ Continued development of a town centre living pilot project at 36 Bank
Street, Irvine and Howgate, Kilwinning under the PBIP. 
‒ Conclusion of the sale of Sites A and B at Montgomerie Park, Irvine to
enable the delivery of the Simplified Planning Zone and commencement
of construction.  Commencement of next phases including proposals for
neighbourhood retail site development.
Placemaking
‒ Approval of the delivery plan for the 2021/22 £1.26m allocation from the
PBIP. This included the development of a Communities Project Fund,
development of a Place Framework for Kilwinning and delivery of Phase 2
of the West Kilbride Shopfronts Scheme.

Page 3

‒ Approval of the delivery plan for the 2022/23 £1.096 allocation from the
PBIP including implementation of the Place Framework pilots in
Kilwinning, Largs and Saltcoats and Lochshore Park play. 
‒ Approval of the Communities and Place investment priority proposals
under the UK Government’s Shared Prosperity Fund 
‒ Securing £0.199m from the UK Government’s Community Renewal Fund
(CRF) for the development of a Place Framework Pilot in Largs and
Saltcoats informed by extensive community and stakeholder consultation.
‒ Working in partnership with Millport Town Hall Trust on Phases One and
Two of the regeneration of Millport Town Hall including securing funding
from the Scottish Government’s Regeneration Capital Grant Fund (RCGF)
and Islands Programme.
‒ Working in partnership with Ardrossan Community Development Trust to
successfully secure £0.749m from the RCGF for Ardrossan Promenade. 
‒ Completion of the Scottish Government’s Town Centre Fund (TCF) public
realm works at: Garnock Street; Kilbirnie; Main Street, Beith; and Mill Dam
and New Street, Stevenston.
‒ Completion of Phase 1 of the West Kilbride Shopfronts Scheme funded
through the TCF.
‒ Commencement of Phase 2 of the West Kilbride Shopfronts Scheme
funded through the Place Based Investment Programme.
‒ Refurbishment of the Dalry Public Park Pavilion funded through the TCF.
‒ Working in partnership with Raise Your Voice With Ardeer to deliver the
Stevenston Beach Hub project.
‒ Completion of key Phase 1 projects for the Lochshore Park Masterplan
including the Hub building and active travel route. 
‒ Launch of the Lochshore Park Hub including a Family Fun Day
‒ Commenced construction on remaining Phase 1 projects of the 5km loop
and play at the Hub.
‒ Secured £0.1m funding from Forestry and Land Scotland for the delivery
of new woodland at Lochshore Park.
‒ Commenced developing a Supplementary Street Development Guide for
North Ayrshire as a supplement to the National Roads Development
Guide created by SCOTS.
Inclusive and Green Economy
‒ Completion and occupation by a local business of a new industrial unit at
Kyle Road, Irvine funded by the VDLF.
‒ Design development and tender of Phase 3 of Pavilion development at
Annickbank Irvine including securing £0.25m from North Ayrshire
Ventures Trust towards the construction.
‒ Design development for the next phase of industrial unit development at
Kyle Road, Irvine.
‒ Contributed to the development of 10-year Island Plans for Arran and
Cumbrae.

Page 4

‒ Securing £0.456m from the UK Government’s Community Renewal Fund
for the Green Islands Programme incorporating the Islands Connectivity
Study.
‒ Securing £0.509m from the Scottish Government Islands Programme for
Phase Two of Millport Town Hall and £0.540m for the Islands Pit Stop
project.
‒ Supporting the development of Stevenston Climate Action Town
programme with Architecture and Design Scotland.
Enabling Infrastructure
‒ Submission of a successful application to the LUF securing £23.7m
towards the B714 Upgrade project between Saltcoats and Dalry.
Progression of the project including: the formation of a Project Board,
development of the Business Case and works to secure the necessary
consents and approvals and undertaking public and stakeholder
consultation to inform the development of the business case and design.
‒ Securing £1.31m in 2021/22 and £1.385m in 2022/23 from Strathclyde
Partnership for Transport’s (SPT) Capital Programme for the delivery of a
range of active travel and transport projects across North Ayrshire.
‒ Securing £0.18m from Transport Scotland’s Bus Partnership Fund for the
extension of the Bus Routes Congestion Measures project to the Three
Towns and to investigate the potential to extend the Stevenston Bus Lane
at Pennyburn Roundabout.
‒ Construction of active travel routes including the Bay Street to Ferry Row
section of the Fairlie Coastal Path, i3 Active Travel link in Irvine,
Kilwinning Short Links and Circuit active travel links in Irvine.
‒ Securing £0.427m from the Scottish Timber Transport Fund for upgrades
to the Ross Road on the Isle of Arran across 21/22 and 22/23 and
£0.199m for the U88 at North Sannox.
‒ Securing £0.248m across 2021/22 and 2022/23 from the Smarter Choices
Smarter Places for the continued delivery of the Trinity Active Travel Hub
and Travel Smart programme.
‒ Development of a delivery programme for the £0.259m allocation under
the Scottish Government’s Islands Infrastructure Fund to upgrade the car
parking and Electric Vehicle infrastructure on Arran and Cumbrae.
‒ Development and delivery of a £1.45m programme of active travel design
and works under the Scottish Government’s Cycling, Walking and Safer
Routes programme across 2021/22 and 2022/23.
‒ Continued delivery of the £1.96m Ardrossan Low Carbon Hub under the
European Regional Development Fund Low Carbon Travel and Transport
Challenge Fund.
‒ Commencement of the review of the Local Transport Strategy
incorporating the Active Travel Strategy informed by extensive community
and stakeholder consultation.
‒ Hosting the Pedal Irvine event as part of Pedal for Scotland in partnership
with Cycling Scotland.

Page 5

‒ Processed 12 Road Construction Consents in 2021 and 10 in 2022 to
enable developments to progress. Adopted roads, footways and footpaths
within 8 developments in 2021 to 2022. 
2.4 The Regeneration Delivery Plan is delivered through an ambitious rolling action
focused programme.  This approach seeks to ensure that the list of projects
never exceeds a realistic assessment of capacity, with projects being prioritised
annually. It informs our priorities for securing and delivering against a range of
external funding sources.   
2.5 The draft action programme for 2023/24 and 2024/2025 provided at Appendix
One has been prepared to align priorities with resource.  This has been
informed by an assessment of progress to date, local priorities, project
deliverability and funding.  The implementation of action programme projects
aligned to competitive funding sources will however be dependent on the
success of the funding applications. 
2.6 Significant levels of funding have been secured to support delivery in 2023/24. 
The details of the funds and the proposed approach to their expenditure are
provided at Appendix Two.  These include the: 
‒ Scottish Government’s Place Based Investment Programme
‒ Scottish Government’s Vacant and Derelict Land Fund
‒ Scottish Government’s Cycling Walking and Safer Routes
‒ Strathclyde Partnership for Transport’s Capital Programme
‒ UK Government’s Shared Prosperity Fund 
2.7 Funding applications are also proposed to a range of competitive funding
sources to support the delivery of the Plan.  The details of the funds,
applications submitted to date and proposed submissions are provided at
Appendix Two.  These include: 
‒ Scottish Government’s Regeneration Capital Grant Fund
‒ Scottish Government’s Islands Programme
‒ Scottish Government’s Vacant and Derelict Land Investment Programme
‒ UK Government’s Levelling Up Fund Round Three (if appropriate) 
2.8 Further consultation and engagement will be undertaken with local
communities, stakeholders and Elected Members through the detailed
development of any successful projects. 
3. Proposals 
3.1 That Cabinet: 
(a) Notes the progress made on the implementation of the Regeneration
Delivery Plan;
(b) Approves the draft Action Programme as detailed at Appendix One;
(c) Approves the Regeneration Delivery Plan funding proposals as detailed at
Appendix Two; and

Page 6

(d) Provides delegated authority to the Executive Director (Place) to agree
changes to the funding allocations in consultation with the Portfolio Lead as
required. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Regeneration Delivery Plan aims to build on and maximise the impact of
the investment being made through a variety of sources including the Ayrshire
Growth Deal, Council’s Capital Programme and the Strategic Housing
Investment Programme (SHIP). It also seeks to lever private funding and
investment into North Ayrshire. 
It informs our priorities for securing and delivering against external funding
sources.  The implementation of action programme projects aligned to
competitive funding sources will be dependent on the success of the funding
applications. 
Human Resources 
4.2 The Regeneration Delivery Plan projects will be delivered through the existing
Regeneration Team resource. Opportunities to secure funding for additional
staff resource to support delivery will be investigated on a project by project
basis as required. 
Legal 
4.3 The legal implications of all Regeneration Delivery Plan projects will be
considered through their development. Legal agreements will be developed on
a project by project basis as required with support from Legal Services.
Negotiation will be required in relation to land and building acquisitions with
support from the Council’s Legal Services and Property Management and
Investment Service. Mechanisms such as Compulsory Purchase Orders will be
considered on a case by case basis, where considered appropriate. 
Equality/Socio-economic 
4.4 The Regeneration Delivery Plan assists in meeting our socio-economic duty as
set out in the Fairer Scotland Duty. It seeks to reverse economic, social and
physical decline and reduce socio-economic disadvantage. It will tackle long-
term vacant and derelict land and buildings thereby reducing their levels and
impact on communities. It aims to build community wealth and tackle local
deprivation through the regeneration of our communities by maximising the
potential of our land and assets and those of anchor institutions. 
The Plan also contributes to the delivery of the Isle of Cumbrae and Isle of
Arran Local Island Plans, their key themes and priorities. The funding proposals
will directly contribute to several of the actions identified within the annual
action plans. The proposals for the Scottish Government’s Islands Programme

Page 7

have been informed by the Islands Plans and identified from the Action
Programmes. 
An initial screening will be undertaken to establish if an Equality and Children’s
Rights Impact Assessment is required for projects on a case by case basis. 
Climate Change and Carbon 
4.5 The Regeneration Delivery Plan aligns with the Environmental Sustainability
and Climate Change Strategy workstreams of: Green Economy; Transport and
Travel; Natural Environment; Sustainable Operations; and Carbon Absorption.
Furthermore, it aligns with the commitment to reduce carbon emissions through
declaration of a Climate Emergency and will contribute to the ambition to
achieve net zero by 2030. 
Key Priorities 
4.6 The Regeneration Delivery Plan has been informed by the priorities identified
within the Local Outcomes Improvements Plan and Locality Partnership
priorities. The implementation of the Plan will contribute to achieving the
Council Plan priority outcomes and will contribute to the ambitions for: an
inclusive, growing and enterprising economy; North Ayrshire to be well-
connected with effective infrastructure; and for a sustainable, vibrant,
welcoming and attractive environment. 
Community Wealth Building 
4.7 The Regeneration Delivery Plan sets out our priorities for delivering on the
ambitions on the Community Wealth Building Strategy. Its delivery will have a
significant positive impact on the Council’s ambitions across the pillars of: 
- Land and Assets: by supporting equitable land development and the
development of underutilised assets for community use.
- Procurement: by contributing to the development of the procurement wave
plan; through the inclusion of appropriate community benefit of local
supplier clauses within projects; and by considering phasing and
programming of projects to create local supply chain opportunities and
support delivery by smaller scale and local contractors where appropriate.
- Fair Employment: by supporting the creation of employment opportunities
particularly within the construction sector. Where North Ayrshire is
procuring services, through our enhanced Community Benefits approach
we will seek to ensure the creation of local training and work experience
opportunities.  Consideration will also be given to delivery through
employability programmes where appropriate.
- Financial Power: by investing in localities and leveraging external national
investment into North Ayrshire.

Page 8

5. Consultation 
5.1 The Regeneration Delivery Plan was the subject of extensive consultation
including workshops with Council Officers; workshops with Elected Members;
reports to and feedback from North Ayrshire Ventures Trust and the Community
Wealth Building Expert Panel; and public engagement via Consul. It was also
informed by the Locality Partnerships’ priorities and previous public consultation
exercises including Charettes. 
5.2 The action programme outlined at Appendix One and the funding proposals
outlined at Appendix Two have been informed by this consultation.  Further
consultation and engagement will be undertaken with local communities,
stakeholders and Elected Members through the detailed development of the
identified projects. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Claire Fitzsimmons, Interim Senior
Manager Regeneration, on 01294 324766. 
Background Papers
Cabinet Report – Regeneration Delivery Plan, 23 March 2021
Cabinet Report – Levelling Up Fund, 15 June 2021
Cabinet Report – Levelling Up Fund – Round 2, 2 November 2021
Cabinet Report – Regeneration Delivery Plan Update, 22 February 2022
Cabinet Report – Regeneration Delivery Plan Funding Proposals. 07 June 2022

Page 9

Appendix One: Draft Action Programme
The following summarises the draft action programme for 2023/24 and 2024/25 under each Regeneration Delivery Plan theme: 
Strengthening Communities    
Maximising Land and Assets      
2023-25 Action Updated 2026 Outcome  Lead Service
Review of land and
assets
Public consultation, finalisation and
adoption of Vacant and Derelict Land
Strategy for 2023-28
Confirmation of vacant and derelict land
priorities and actions and implementation of
Years 1 and 2 
Economic
Development, Growth
& Regeneration
(EDG&R) 
Review of land and
assets
Prepare annual local delivery plans for SG
approval under the Vacant and Derelict
Land Fund (VDLF), and projects for
submission to the Vacant and Derelict Land
Investment Programme (VDLIP)
Implementation of vacant and derelict land
priorities on an annual basis under the
Vacant and Derelict Land Fund and Vacant
and Derelict Land Investment Programme
(VDLIP)
EDG&R 
Development
potential of land
and assets
Review the development potential of
Council landholdings to inform the Local
Development Plan 3 (LDP3)
Clarity on the priority sites for intervention
and/or investment
Housing and Public
Protection (H&PP) /
EDG&R 
Investment in land
and assets
Implement the Repurposing Property Grant
Fund (RPGF) including development of
further phases, subject to external funding
Landowners and communities are
supported to bring vacant and derelict land
and properties back into positive use
EDG&R
Investment in land
and assets
Identify opportunities and priorities for
future investment 
A social housing and commercial portfolio
that supports the needs of communities and
the growth of local businesses and
entrepreneurial activity
EDG&R / H&PP
Levelling Up Fund Identify priorities for consideration of
potential submission to Round 3 of the UK
Government's Levelling Up Fund 
Levelling Up funding is secured to support
capital investment in identified priorities
EDG&R

Page 10

Housing and Town Centre Living     
Strategic Housing
Investment
Programme (SHIP)
Construct new social housing sites
including Corsehillhead, Kilwinning;
Bourtreehill, Irvine; Ayrshire Central, Irvine;
Fullarton Street, Irvine; and West Byrehill,
Kilwinning
Delivery of 1,900 unit SHIP programme to
2026
H&PP
SHIP Review of SHIP contribution to community
regeneration
Identification of priority sites and process
for selection of opportunities
H&PP / EDG&R
Housing Delivery Preparation of Supplementary Guidance for
Development Frameworks
Approval by Planning Committee;
Implementation of Guidance
H&PP
Housing Delivery Preparation and approval of development
frameworks for strategic sites
Approval by Planning Committee;
Implementation of development
frameworks; Completion of developments
EDG&R
Housing Delivery Analysis of the most suitable delivery
mechanism for housing on strategic sites
Delivery of appropriate development on
NAC owned strategic sites in line with CWB
strategy and LHS
EDG&R / H&PP
Housing Delivery Next phase of Montgomerie Park delivery
including marketing of further phase(s) and
site start(s)
Completion of Sites A-B housing
development; retail site sale and
development; and marketing land, sale and
site start for remaining phases
EDG&R
Town Centre
Living
Review of potential sites for increased town
centre living given decline in retail activity
and complete town centre living pilot project
New residential development in town
centres 
EDG&R / H&PP
Town Centre
Living
Redevelopment of Kings Arms, Irvine to
deliver amenity flats
Completion of development H&PP
Community Investment and Enterprise 
Community Project
Development
Support new community project
development, physical regeneration
projects, funding applications and asset
transfer processes and delivery including
Ardrossan Promenade
Identification and delivery of community
development and community led
regeneration projects
Connected
Communities (CC) /
EDG&R

Page 11

Community Project
Development
Develop a grant funding CRM to manage
Council grant processes including the
creation of an expression of interest
process to identify a pipeline of projects for
submission to external funding sources
Identification and delivery of community
development and community led
regeneration projects
EDG&R / CC
Shared Prosperity
Fund
Implement the approved Shared Prosperity
Fund Investment Plan including facilitating
governance arrangements
Implement and administer the North
Ayrshire award under the Shared Prosperity
Fund 
EDG&R / CC
Shared Prosperity
Fund
Implement Council priority projects under
the Communities and Place Investment
Priority informed by Place Frameworks
Delivery of Council led projects under the
Shared Prosperity Fund Communities and
Place Investment Priority
EDG&R / CC
Shared Prosperity
Fund
Develop and implement a Shared
Prosperity Fund Communities and Place
Fund
Identification and delivery of community
development projects under the Shared
Prosperity Fund Communities and Place
Investment Priority
EDG&R / 
CC
Locality
Partnerships
Coordinate the identification and delivery of
community development projects through
the operation of Locality Partnerships
Identification and delivery of community
development projects
CC
Participatory
approaches
Extend and mainstream a participatory
approach to offer communities, including
young people, more opportunities to lead in
local decision-making
Increased community involvement decision-
making
CC
Community Asset
Transfer
Support Community Asset Transfer and
Participation Requests  
Increased community ownership of land
and property and redevelopment of
underutilised assets
CC
Community
Investment Fund
Co-design, co-production and co-delivery of
projects
Identification and delivery of community
development projects
Locality Partnerships
/ CC

Page 12

Delivery Models  
Third Party Assets
Review
Review the identified sites including the
case for the purchase of third-party land to
address a recognised problem or facilitate
positive development – including sites
identified through the RDP
A property portfolio that supports
communities, improved public amenity and
the growth of local businesses and
entrepreneurial activity
EDG&R
Land Development
Model
Develop a model for the development and
sale of vacant land/property and
reinvestment in further programme
Confirmation and implementation of model EDG&R
Commercial Estate Develop proposals for Commercial Estates,
Infrastructure and Town Centre allocation
under the Recovery and Renewal
Investment Fund and external funding
sources
Identification and implementation of priority
projects
EDG&R
Placemaking      
Town and Local Centres 
Updated 2023-25 Action Updated 2026 Outcome  Lead Service
Place Framework
Development
Roll out of programme of Place
Frameworks to direct future investment
through the Investment Fund, Place Based
Investment Programme and external
funding
Use of Place Framework to facilitate
community consultation and to direct and
implement projects contributing to a
wellbeing economy
EDG&R / CC
Place Framework
Development
Implementation phase of pilot place
frameworks for Kilwinning, Saltcoats and
Largs. 
Use of Place Framework to facilitate
community consultation and to direct and
implement projects contributing to a
wellbeing economy
EDG&R / CC
Place Plan
Development
Support local communities to develop Local
Place Plans under the Planning Act
Community development of Local Place
Plans
H&PP / CC / EDG&R
Town Centre
Improvements 
Completion of SG funded Town Centre
Fund projects 
Implementation of projects EDG&R

Page 13

Town Centre
Improvements 
Investigate potential to upgrade grass pitch
provision and implementation of any
recommendations
Completion of Quarry Road project EDG&R/ CC / KA
Leisure
Town Centre
Improvements 
Identify and adopt a new approach to town
centre footfall monitoring
Effective monitoring of town centre activity EDG&R
Town Centre
Improvements 
Prepare an investment plan for Years 3 to 5
of the Place Based Investment Programme
allocation working collaboratively with local
communities, business, third and public
sectors
Implementation of projects identified in
Investment Plan
EDG&R
Town Centre
Improvements 
Develop and implement proposals for CWB
- Town Centres and Communities allocation
under the Recovery and Renewal
Investment Fund
Identification and implementation of town
centre priority projects
EDG&R
Conservation
Projects
Completion of Millport Conservation Area
Regeneration Scheme
Completion of project EDG&R
Conservation
Projects
Identification of potential conservation
projects through the development of Place
Frameworks and Local Place Plans
Development and implementation of
conservation projects
EDG&R
Strategic Sites      
Ardrossan North
Shore & Marina
Deliver the next phases of civil
infrastructure to support the Ardrossan
Campus including delivery of a programme
to facilitate the delivery of the Campus
Supporting the completion of the Ardrossan
Campus
EDG&R
Ardrossan North
Shore & Marina
Develop a major Branding exercise to
reflect the national scale regeneration
opportunity including North Shore, Harbour
and town centre
Secure appropriate press coverage and
community understanding of investment in
town, changing perceptions at key points in
the programme’s delivery
Communications

Page 14

i3 Enterprise Area Operation of Phase 1 of the Digital
Processing Manufacturing Centre (DPMC)
digital hub. Delivery and occupation of
Phase 1 of the flexible space programme
and development of Phase 2 project
Delivery of AGD investment and leverage of
private investment
EDG&R
Irvine Harbourside,
‘Great Harbour’
Development and implementation of the
Great Harbour Masterplan informed by
community and stakeholder consultation
Delivery of AGD investment and leverage of
private investment
EDG&R
Lochshore Completion of £8m Phase One of the
Lochshore Park Masterplan including: 5km
circular loop; Play at the Hub; woodland
creation and community play links
Completion of Phase One of the Lochshore
Park Masterplan
EDG&R
Lochshore Identify funding opportunities, submit
applications and secure funding for Phase
Two delivery
Completion of Phase Two of the Lochshore
Park Masterplan (subject to funding)
EDG&R
Lochshore Identify opportunities to fund and deliver
Lochshore Masterplan Phase 2 including:
appointing project team, formalising
governance arrangements, and
commencing delivery (subject to funding)
Completion of Phase Two of the Lochshore
Park Masterplan (subject to funding)
EDG&R
Lochshore Delivery of Play at the Hub Completion of Phase One of the Lochshore
Park Masterplan
EDG&R
Hunterston Development of options for site with
partners Peel Ports Group and SE 
Hunterston is recognised as a strategically
significant national asset contributing to
local, regional and national blue and green
economy aspirations. 
EDG&R 
Growth Deal Plans

Page 15

Growth Deal
Delivery
Delivery of North Ayrshire’s share of the
£251m Growth Deal programme including:
manufacturing space and a digital hub at i3
in Irvine, International Marine Science &
Environmental Centre at Ardrossan; Centre
for Research into Low Carbon Energy &
Circular Economy at Hunterston; the
development of island marina projects and
the Great Harbour project in Irvine 
Delivery of Growth Deal investment and
leverage of partnership and private sector
funding
EDG&R
Leverage of AGD
funding
Securing additional leverage including
private sector investment and external
funding 
Additional funding and profile to enhance
the outcomes achieved through the AGD
EDG&R
Destinations / Visitor Hubs 
Commercial/leisure
investment in
Ardrossan 
Review of market potential for commercial
opportunities within Ardrossan
Delivery of new commercial uses alongside
public investment
EDG&R
Inclusive and Green Economy
Inward Investment 
Updated 2023-25 Action Updated 2026 Outcomes Lead Service
Supporting inward
investment
Engage with existing and new businesses
to support inward investment including the
co-ordination and review of enquiries and
assessment of contribution to net zero,
CWB and socio-economic impact 
Inward investment is secured across North
Ayrshire
EDG&R
Supporting inward
investment
Review NAC land and assets’ potential to
deliver on inward investment enquiries  
Inward investment is secured across North
Ayrshire
EDG&R
Development of Commercial Estate

Page 16

Commercial estate
improvements
Review of commercial estate to identify
opportunities to improve or redevelop
council assets to encourage local business
growth utilising Investment Fund
Improvement of commercial estate to allow
business growth
EDG&R
Commercial estate
development
Completion of technical design, funding
secured and contractor appointed for
additional office pavilion at Annickbank for
construction in 23/24
Completion and long-term lease of space,
securing local employment
EDG&R
Commercial estate
development
Identify opportunities and apply for funding
to support the delivery of new commercial
estate development
New commercial estate development to
support business growth (subject to
funding)
EDG&R
Commercial estate
development
Implement next phase of commercial estate
development at Kyle Road, Irvine including:
securing funding package and necessary
permissions and consents
Completion and long-term lease of space,
securing local employment
EDG&R
Commercial estate
development
Review of third-party assets for acquisition
to support commercial estate delivery
Improvement of commercial estate to
support business growth
EDG&R
Harbourmasters
House, Irvine
Improvement of derelict Council property
and development of proposals for market
opportunity
Delivery of new commercial uses alongside
public investment at Great Harbour
EDG&R
Partnership Activity 
Islands Recovery
and Renewal Pilot
Implement ten year Island Plans for Arran
and Cumbrae working in partnership with
local island communities and stakeholders,
Highlands and Islands Enterprise and the
Scottish Government
Development of strategic Island Plan
projects and leverage of external funding
EDG&R
Islands Recovery
and Renewal Pilot
Develop and facilitate Island Plan Delivery
Groups
Long term strategic direction and
community and stakeholder engagement in
the implementation of Island Plans
EDG&R

Page 17

Partnership
Opportunities
Identify partnership opportunities for
regeneration delivery with private sector
and third sector
Partnership opportunities for delivery and
maximisation of funding and resources
EDG&R 
Ardeer Continue to engage with NPL to identify any
opportunities at Ardeer that complement the
AGD Great Harbour masterplan investment
at Irvine Harbour and Beach Park.
Delivery of AGD investment and leverage of
private investment
EDG&R 
Enabling Infrastructure
Transport Infrastructure  
Updated 2023-25 Action Updated 2026 Outcome Lead Service
Ardrossan Harbour Finalise funding package and partner
agreements; and Publication of tender
package and award of contract for marine
and landside works to enable construction
Completion of harbour regeneration
programme with partners
EDG&R
Transport Policy Public consultation, finalisation and
adoption of Local Transport Strategy for
2023-28
Confirmation of local transport priorities and
actions for implementation
EDG&R
Transport Policy Promotion of North Ayrshire transport
priorities for inclusion within national and
regional transport policy including the
Regional Transport Strategy (RTS) and
Islands Connectivity Plan (ICP)
Funding and delivery of local and regional
transport priorities
EDG&R
Transport Policy Support the completion of the B714
Upgrade Full Business Case and design
processes including submission to UK
Government to facilitate construction
Completion of B714 Upgrade EDG&R and
Neighbourhood
Services (NS)
Active Travel Identify priorities for and implement new
and improved active travel route
infrastructure across North Ayrshire
informed by the revised LTATS
Securing external funding and
implementation of projects
EDG&R

Page 18

Active Travel Implement the recommendations of the
Community Renewal Fund Islands
Connectivity Study with partner
organisations
Delivery of a network of infrastructure to
support active and sustainable travel and a
Mobility as a Service pilot project on Arran
and Cumbrae.
EDG&R
Active Travel Complete the Ardrossan Connections
Street Design Project focused on Glasgow
Street, Princes Street and Montgomerie
Street with Sustrans
Implementation of improvements to
encourage active travel, improve residential
environment and link major development
projects
EDG&R 
Public Transport Investment in public transport infrastructure
improvements informed by the revised
LTATS
Improvement of the public transport
network for everyday journeys
EDG&R
External Grant Support
External Funding Work with partners to identify funding
opportunities and submit funding
applications to maximise the potential of
regeneration resources and funding
Submission of successful funding
applications on an annual basis to enable
project implementation
EDG&R
Community
Funding
Support communities to identify funding
opportunities and submit funding
applications to implement community
regeneration priorities
Submission of successful funding
applications on an annual basis to enable
project implementation
CC / EDG&R
Digital Infrastructure
Broadband Support the roll out of R100 Broadband
programme and raise awareness of the
Scottish Broadband Voucher Scheme
(SBVS) and the UK Gigabit Broadband
Voucher Scheme
Improved broadband coverage across area
and increased vouchers uptake
EDG&R
Connectivity Develop the Digital Renewal route map and
approach to support Digital Economic
Transformation, focusing on four pillars:
Connectivity (including infrastructure),
Digital Skills, Innovation, and Digital
Inclusion
Improved digital connectivity growing a
strong and resilient digital economy
delivering digital economic transformation 
EDG&R

Page 19

Strategic
Connectivity
Review the digital investment through AGD
to maximise the benefits to gain a
competitive business advantage and
support the development of a Digital
Masterplan for Ayrshire
Delivery of digital investment to secure
competitive advantage for North Ayrshire
and support business growth and
encouraging private sector investment
EDG&R
Low Carbon Economy
Review of land and
assets for low
carbon delivery
Review of potential for land assets to
support low carbon project delivery and
contribute to net zero targets including: new
tree planting; renewable energy; food
growing; and electric vehicle projects
Maximisation of land and assets to deliver
low carbon projects and Contribution to net
zero ambitions
EDG&R / NS /
Sustainability,
Corporate Property &
Transport (SCP&T)
Delivery of low
carbon projects
Identify opportunities for innovative delivery
of low carbon projects including tree
planting; renewable energy; food growing;
and electric vehicle projects
Delivery of low carbon projects and
contribution to net zero ambitions
Physical Environment
/ NS / EDG&R /
Flood Protection
Schemes
Implementation of the Millport Coastal
Flood Protection Scheme and development
of the River Irvine Scheme
Implementation of flood protection schemes NS
Active Travel Hub Deliver the Trinity Active Travel Hub and
Travel Smart programme to support active
and sustainable travel
Modal shift to active and sustainable travel /
contribution to net zero ambitions
EDG&R
Low Carbon Hub Complete the £1.96m ERDF Low Carbon
Travel and Transport funded Ardrossan
Low Carbon Hub including path works, e-
bike and EV infrastructure implementation.
Delivery and implementation of the project EDG&R 
Solar Photovoltaic
Farm development
Detailed development of Solar PV Farm at
Nethermains and Shewalton, Irvine
including: procurement, planning, grid
connections and design.  Investigation of
renewables opportunities at i3
Completion of Solar PV farms by end of
2024; regeneration of the former
Nethermains and Shewalton Landfill Sites;
and contribution towards net zero ambitions
SCP&T

Page 20

Appendix Two – Regeneration Delivery Plan Funding Proposals 
The following provides a summary of each of the funds and the proposed approach for
2023/24. Funding awards are generally received on an annual basis therefore a further
report will be provided for 2024/25 awards.  The proposals have been identified from the
Regeneration Delivery Plan action programme and an assessment of the: 
- Projects’ stage of development;
- Fit with the fund objectives and priorities;
- Potential benefits;
- Budget available;
- Ability to secure match funding; and
- Deliverability of the project(s) within funders’ timescales. 
This approach aims to implement a range of projects that deliver impactful improvements in
line with the Regeneration Delivery Plan and the various funding streams’ ambitions. 
Where there is an underspend within one of the allocations in 2023/24, it is proposed that
the Executive Director (Place) will reallocate any underspend across the other identified
actions following engagement with the Portfolio Lead. 
Place Based Investment Programme 
The Scottish Government established the five year £325m Place Based Investment
Programme (PBIP) in 2021/22. Underpinned by the Place Principle, this aims to support
community-led regeneration, town centres and the 20-minute neighbourhood ambitions.
The main objectives of the Programme are to: 
- Link and align place based initiatives and establish a coherent local framework to
implement the Place Principle;
- Support place policy ambitions such as town centre revitalisation, community led
regeneration, 20 minute neighbourhoods and Community Wealth Building;
- Ensure that all place based investments are shaped by the needs and aspirations 
- of local communities; and
- Accelerate the ambitions for tackling inequality and disadvantage, wellbeing and
inclusive economic development, net zero, community involvement and ownership 
Local Government is a key partner in delivering the Programme and will receive a share of 
the funding over the five years to support and advance local priorities. A £0.761m allocation
has been received for the current financial year. This requires to be fully expended or at a
minimum financially committed by 31 March 2024. Any unused grant will require to be
repaid to the Scottish Government unless otherwise agreed by Scottish Ministers. 
The table below outlines the proposal for the expenditure of the allocation.  The proposals
aim to support the delivery of the Place Frameworks prepared through the previous
allocations and the UK Government’s Community Renewal Fund. Furthermore, they aim to
continue the development of Place Frameworks across North Ayrshire.

Page 21

Project Allocation
Lochshore Park Hub Play
To construct play facilities at the Hub.
£50,000
Kilwinning Abbey Tower Repair
To support repairs to Kilwinning Abbey informed by the Kilwinning Place
Framework.
£100,000
Stevenston Climate Action Town: Projects Fund
To support the delivery of the recommendations of the Climate Action
Town Report.
£35,000
Town Centre Living Pilot: 36 Bank Street, Irvine
To support the completion of the design and tender process.
£25,000
Future Year Project Development
To support the preparation of proposals for implementation in future years
and support funding applications.
£40,000
Repurposing Property Grant Fund
To support the continued provision of the Fund.
£60,000
Kyle Rd Phase 2 
To support the delivery of 1200m² new Class 4/5/6 business space
capable of sub-division.
£400,000
PBIP Regeneration Officer
This will meet the costs associated with the dedicated Regeneration
Officer to support the delivery of the Programme.
£51,000
Total £761,000 
Vacant and Derelict Land Fund 
The Scottish Government's Vacant and Derelict Land Fund (VDLF) aims to tackle the
presence of long-term vacant, for 15 years or longer, and derelict land in Scotland. In doing
so, it aims so stimulate economic growth, job creation, an improved environment and
quality of life. From its inception in 2007, access to the Fund was restricted to 5 local
authorities to focus the available financial resource and prioritise authorities most impacted
by both the extent of vacant and derelict land and levels of deprivation. 
A review in 2015, resulted in North Ayrshire Council benefitting from access to the Fund 
from the financial year 2016/17. The other four authorities which currently benefit are South
Lanarkshire, North Lanarkshire, Fife and Glasgow City Councils. Funding is limited to sites
that have been vacant for at least 15 years and are between 0.1ha and 99ha in size, with a
preference of Council ownership or a landowner agreement in place. It cannot be used on
housing or infrastructure projects such as transport or flooding. 
A Local Delivery Plan requires to be submitted to the Scottish Government to allow
Ministerial approval of the expenditure of the funding in 2023/24. In developing the
proposals for this, several factors have been considered, including the: 
- Scottish Government funding criteria;
- Economic development focus of the funding;
- The priority sites identified of Irvine Enterprise Area, Ardrossan Campus Site, Lochshore
and Irvine Harbourside and their stage of development;

Page 22

- Alignment with the North Ayrshire Regeneration Delivery Plan (2021) and Vacant and
Derelict Land Strategy (2014) and the current draft Vacant and Derelict Land Strategy;
- Deliverability of projects within the funding timescales;
- Need to balance feasibility and site preparation work, with interventions that see
physical space and employment created;
- Need to secure a spread of interventions in terms of type and geography; and
- Scottish Government’s aspiration for circa 25% to be spent on greening projects. 
An allocation of £1.507m has been confirmed for 2023/24.  The following projects are
proposed for inclusion in the local delivery plan.  This has been submitted to the Scottish
Government, subject to Cabinet approval: 
Project Allocation
Kyle Rd Phase 2 
To support the delivery of 1200m² new Class 4/5/6 business space capable
of sub-division. 
£1,132,000 
Montgomerie Park Neighbourhood Centre 
To support environmental improvements and ground works adjacent to the
new Montgomerie Park Primary 
£175,000 
Stalled Spaces Fund 
To support the visual improvement or naturalisation of sites, including grant
funding to community groups for temporary repurposing of sites. 
£125,000 
Development Work 
To support surveys and investigations to inform proposals for
implementation in future years. This will include grant funding to support
landowners and community groups to bring back vacant land and
properties to positive use by funding feasibility studies, investigation work
and statutory approvals 
£75,000 
Total  £1,507,000 
Cycling, Walking and Safer Routes 
The Scottish Government’s Cycling Walking and Safer Routes programme provides direct
allocations to Local Authorities.  This can only be used for cycling, walking, safer routes and
active travel related projects.   
It is proposed that the £857,000 award received for 2023/24 be allocated as follows.  This
approach aims to support a range of eligible projects across North Ayrshire and secure
additional funding to maximise and accelerate delivery. 
Project Allocation
Local Transport and Active Travel Strategy
To support Year 1 delivery and implementation of the active travel strategy
action plan, which will be considered by Cabinet after the Recess.
£250,000
Active Travel Route Construction
To provide match funding to support applications to Sustrans Places for
Everyone and other active travel funding programmes.
£200,000
Future Years Feasibility Studies and Design Development
To support the preparation of feasibility and studies for active travel
projects.
£100,000

Page 23

Ardrossan Low Carbon Hub
To provide an additional match funding contribution towards the path
creation element of the ERDF Low Carbon Travel and Transport Challenge
Fund Project.
£150,000
Route Monitoring 
To support the network of pedestrian and cycle counters across North
Ayrshire including the installation of new infrastructure.
£35,000
Staff costs and resourcing
To support the existing externally funded posts within the Active Travel and
Transport Team and provide match funding toward the Travel Smart
project funded by Smarter Choices Smarter Places.
£122,000
Total £857,000 
Strathclyde Partnership for Transport Capital Programme 
Strathclyde Partnership for Transport’s (SPT) Capital Plan sets out the funding programme
for projects to be delivered by SPT and partners on an annual basis.  Applications are
invited from Local Authorities in the Autumn of the preceding year.  Priorities for funding are
informed by the National, Regional and Local Transport Strategies.   
The following projects have been allocated funding through the overall £1.03m award from
2023/24 Capital Programme: 
Project  Award 
Ardrossan Harbour Interchange
To support the tender process for the public transport interchange at the
Harbour.
£50,000
B714 Active Travel Links
To tender and construct the first phase of active travel links in Dalry and
Saltcoats designed in 2022/23 to improve local path networks.
£400,000
Brodick to Corrie Cycle Path
To deliver the next phase of the off-road National Cycle Network (NCN)
Route 73 at Brodick Castle and Country Park.
£80,000
Bus Corridor Improvements
To deliver a programme of bus stop infrastructure improvements across
North Ayrshire.
£100,000
Cumbrae Ferry Bus Stop and Queuing Facilities
To deliver the next phase of recommendations of the feasibility study
developed in 2021/22 including detailed designs and construction
£350,000
Irvine Cycle Friendly Town
To deliver the next phase of the Irvine Cycle Friendly Town Study
recommendations including new path construction and signage.
£50,000
Total £1,030,000

Page 24

Shared Prosperity Fund 
The Communities and Place investment priority of the Shared Prosperity Fund aims to
enable places to invest to restore their community spaces and relationships and create the
foundations for economic development at the neighbourhood-level.  Its objectives are to
strengthen the social fabric and foster a sense of local pride and belonging and build
resilient, healthy and safe neighbourhoods. 
The investment priority requires Councils to be mindful of how interventions under this
priority align with the existing funding streams received from the Scottish Government
including the Place Based Investment Programme.  The alignment with Scotland’s National
Strategy for Economic Transformation (NSET) also requires to be considered to ensure that
they contribute to a fairer and more equal society, new market opportunities and productive
businesses and regions. 
Thirteen interventions are identified under the investment priority.  The approved North
Ayrshire Investment Plan supports delivery of projects across the range of interventions. 
The approved Investment Plan outlined that the Communities and Place investment priority
would be comprised of a: Participatory Budgeting programme; Competitive grant scheme
for communities; and Funding allocation for Council projects.  £349,208 capital and
£107,106 revenue funding has been allocated to support smaller scale Council led projects
that meet the aims and objectives of SPF and allow the Council to meet strategic goals.
These projects will be aligned to the Regeneration Delivery Plan. Wherever possible match
funding will be sought to support the delivery of these projects. 
Scottish Government’s Regeneration Capital Grant Fund 
The Scottish Government’s Regeneration Capital Grant Fund (RCGF) is delivered annually
in partnership with COSLA and local government. It supports locally developed place-based
regeneration projects that involve local communities, help to tackle inequalities and deliver
inclusive growth in deprived, disadvantaged and fragile remote communities across
Scotland. 
The Fund is subject to a two-stage assessment process. Applicants are required submit a
summary of their project on the form provided at Stage 1 by 21 June 2023. Successful
projects at this stage will be invited by the panel to then complete a full Stage 2 application
in October 2023. An independent investment panel will agree the recommendations to
Scottish Ministers and COSLA on projects to be offered grant support. 
The Fund is primarily aimed at providing new and/or improved infrastructure to improve the
economic, social, and physical environment of communities. Projects are expected to detail
how they are considering and contributing towards the target of net zero carbon emissions
by 2045. Projects should also: 
- Primarily focus on areas that suffer from high levels of deprivation and disadvantage; 
- Demonstrate clear community involvement;
- Deliver large scale transformational change with strong regeneration outcomes; and 
- Encourage additional investment and address market failure. 
Officers from Connected Communities and Economic Development and Regeneration 
have supported with local groups and organisations to identify potential projects for 
submission to the Fund. This process has been informed by the funding criteria, key

Page 25

considerations and the level of community involvement based on the experience from 
previous successful applications. On this basis is it recommended that applications be 
submitted for the following 4 projects, listed in order of priority: 
i) Geilsland Courtyard Hall, Beith 
ii) Harbour Arts Centre, Irvine  
iii) Great Harbour Phase 1, Irvine 
iv) Eglinton Park Visitor Centre, Kilwinning 
v) Kilwinning Abbey Tower, Kilwinning 
Scottish Government’s Islands Programme 
The Islands Programme represents a £30million capital investment over five years to
support the delivery of the National Islands Plan. It aims to support projects which
encourage population growth and stem population decline and deliver on net zero
ambitions in a way that no-one is left behind. This will support a green economic recovery
from the ongoing impacts of the COVID-19 pandemic.   
The Programme is being delivered on a competitive bid basis across all six local authorities
with islands with a budget of £4m in 2023/24. It is open to applications from the six island
Local Authorities including North Ayrshire Council. The Councils are required to act as the
lead applicant. Project proposals are however expected to have been developed with the
involvement and support of relevant communities, as well as third sector and private sector
partners as appropriate. 
For 2023/24 there will only be a one stage application process.  Project proposals require to
use clear Place based, Community Wealth Building principles to support inclusive island
growth while working to achieve Scottish Government’s net zero ambitions and to support
recovery from the impacts of the pandemic.  They should: 
- Meet the overall objectives of the Islands Programme.
- Link directly to at least one of the National Islands Plan Strategic Objectives.
- Ensure transformational impact against place-based priorities to accelerate local growth
and resilience.
- Align with local critical infrastructure priorities and have the potential to collaborate with
other place-based investment opportunities to maximise benefits.
- Demonstrate project readiness, collaborative and partnership models, project viability
and long-term sustainability.
- Demonstrate clear Community Wealth Building principles and community involvement
and engagement.
- Support Scottish Government Net Zero Ambitions and a Just Transition. 
Officers from Connected Communities and Economic Development and Regeneration 
supported local groups and organisations to identify potential projects for submission to the
Fund. This process was informed by the funding criteria, key considerations and the level of
community involvement. Informed by this assessment two applications were submitted for
the following two projects and have subsequently received awards from the Programme: 
i. Garrison House Regeneration Scheme (Project Value £950,934): £730,998 grant
sought to restore, re-purpose and enhance the Garrison House complex in Millport,
Isle of Cumbrae. This will secure the building fabric for future generations, improve

Page 26

accessibility, improve the availability of and access to services, and increase its
energy efficiency and resilience to climate change.
ii. Dyemill Park (Project Value £570,000): £220,625 grant sought to build, manage and
maintain an accessible, inclusive and safe, all-weather environment to grow and
develop the island’s cycling community, inspiring Arran to cycle.   
Priorities for the 2024/25 round of the programme will be identified through engagement
with the Island Plan Delivery Groups.  It is intended that project progress reports will be
provided to the Island Delivery Groups’ meetings to provide an opportunity to engage in
and contribute to the projects’ delivery, where appropriate. 
Scottish Government’s Vacant and Derelict Land Investment Programme 
The Scottish Government announced a 5 year £50M competitive Vacant and Derelict Land
Investment Programme (VDLIP) in 2021/22. This aims to tackle persistent vacant and
derelict land and support place based approaches to delivering regeneration and
sustainable inclusive growth, as part of a ‘just transition’ to net-zero by 2045. The fund
complements the Place Based Investment Programme and is open for all local authorities
in Scotland to apply. 
Potential projects were identified for the 2023/24 round based on the funding criteria, level
of project development and delivery timescales with Council Services.  The following
applications are proposed for submission in order of priority: 
i) Kyle Road Phase 2
ii) 36 Bank Street Town Centre Living Pilot 
UK Government’s Levelling Up Fund 
The Levelling Up Fund (LUF) is a £4.8 billion capital investment fund that will support town
centre and high street regeneration, local transport projects, and cultural and heritage
assets. North Ayrshire has been allocated as a ‘priority one’ category authority given our
socio-economic and connectivity challenges. 
This is a competitive bidding process against other local areas and the Council requires to
put forward high-quality, detailed and compelling business cases which meet the LUF
criteria. There are 4 assessment criteria for the fund: place (priority area categories),
strategic fit, value for money and deliverability. 
Two applications were submitted to Round 2 of the Fund: 
• Lochshore Park – This aimed to accelerate the delivery of Phase 2 of the Lochshore
Park project through the transformation of the former steelworks site, including 64.73ha
of Vacant and Derelict land, into an attractive area of parkland with a focus on outdoor
play and active lifestyles.
• Levelling Up for Ayrshire: Commercial and Low Carbon Infrastructure – This partnership
project with South Ayrshire Council aimed to deliver new commercial estate
development to increase capacity in Irvine and Prestwick.  This focused on three long
term vacant and derelict land sites at Annickbank, Kyle Road and i3 Enterprise area.  It
also included low carbon infrastructure to improve active and sustainable travel links.

Page 27

Both applications were confirmed as being unsuccessful in January 2023.  An explanatory
note was issued on 19 January 2023 regarding the decision making process.  This advised
that Ministers took account of which local authorities had received funding in the first round,
noting that this would help maximise the geographical spread of investment across rounds
one and two.  This information was not previously available to Officers.   
Detailed feedback has now been received on both applications from UK Government.  This
included highly positive feedback on the quality of the Lochshore Park project submission. 
Several of the constituent elements of the partnership bid with South Ayrshire Council have
now been progressed through alternative funding sources.  Informed by this, it is proposed
that further consideration be given to the resubmission of the Lochshore Park project
Round 3.  This would be subject to confirmation that Authorities with previously successful
projects will be considered for funding and a detailed assessment of the Fund’s criteria. 
Priorities for a partnership bid with South Ayrshire Council will be considered when further
information is available on Round 3.