NORTH AYRSHIRE COUNCIL 
30 May 2023 
Cabinet 
Title:    Capital Programme Performance to 31 March 2023 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme for 2022/23. 
Recommendation:  That Cabinet agrees to (a) note the revisions to budgets
outlined in the report; and (b) note the General Services and
HRA expenditure to 31 March 2023. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2022/23 to 2030/31 was
approved by Council on 2 March 2022. The Housing Revenue Account (HRA) Capital
Investment Programme 2022/23 sits within the updated HRA Business Plan and was
approved by Council on 16 February 2022. 
1.2  This is the final monitoring report for the year which identifies the current programme
for 2022/23, taking account of adjustments made to the initial budgets and advises of
the actual expenditure to 31 March 2023. 
1.3   The final outturn report for the General Fund reports a net breakeven position against
a revised budget of £36.194m. The final outturn position for the HRA is an
underspend of (£6.399m) against a revised budget of £36.910m. 
1.4  Within the General Fund, adjustments to funding have resulted in net reductions to the
overall capital programme of (£2.385m). Further reviews of individual project plans
have identified a number of adjustments to the current profiles. As a result, (£5.625m)
has been reprofiled for delivery in 2023/24. This has been partly offset by the
acceleration of £1.391m to 2022/23 from future years. 
1.5 Within the HRA, additional government grants of £0.496m have been received in
relation to the Ukrainian Resettlement programme while a review of delivery
timescales has identified a requirement to re-profile (£9.185m) of works for delivery in
2023/24 and beyond. This is offset by the acceleration of £2.158m to 2022/23 from
future years.

Page 2

1.6 Major cost risks have been identified across the Capital Investment Programme as a
result of the uncertainty arising from the ongoing inflationary pressures and supply
chain issues which are impacting on tender returns and the cost of materials, as
reported across a number of General Fund and HRA projects. In addition, upward
movements on the interest rates applicable to public sector borrowing present further
risks to the deliverability of both the General Fund and HRA capital programmes over
the medium term. While some mitigation has been built into the programme to offset
cost pressures, all projects will continue to be monitored to identify and assess any
cost pressures which cannot be met from within the existing flexibility. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2022/23 General Services budget: 
2.2 (a) Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
2022/23
£m
Budget as at 31 January 2023 42.813     
a) Changes to Funding 0.209        
b) Other Revisions to the Programme (2.594)      
Revised Budget 40.428     
c) Alterations to phasing of projects:-
2022/23 to 2023/24 (5.625)           
2023/24 to 2022/23 1.391        
Budget as at 31 March 2023 36.194     
Funding Body Amount Project
Scottish Government £0.120m Scottish Office New Grant - Boyle St Hostel
Sustrans £0.269m Saltcoats Old Cal Railway Ph1
£0.034m Access Paths
£0.032m Saltcoats Old Cal Railway Ph2
£0.029m AGD Great Harbour
Energy Saving Trust £0.002m Workplace Chargers
SPT (£0.222m) Bus Corridor etc. Grants Downturned
Scottish Forestry (£0.055m) STTS U88 North Sannox Grant Downturned
Total £0.209m

Page 3

2.3 (b) Other Revisions to the Programme 
Further additions to the programme of £1.204m have been identified in relation to
drawdowns from reserves and other revenue funding to support a range of projects.
This has been offset by the identification of a number of projects totalling (£3.798m)
which, although managed as part of the Capital Programme, have been transferred
for inclusion in the year end Revenue Monitoring report in line with accounting
requirements. 
2.4 (c) Alterations to the Phasing of Projects 
A review of individual project plans has identified a requirement to re-profile a further
(£5.625m) of works for delivery in 2023/24 and beyond. This includes the reversal of
the in-year corporate phasing adjustment which reflected the level of optimism bias
included in the expenditure forecasts:
Funding Source Amount Project
Transfers to Revenue (£1.605m) Millport Town Hall
(£0.886m) Various CFCR transferred to Revenue
(£0.587m) Place Based Investment Programme
(£0.529m) Improvement Grants
(£0.085m) Stevenston Beach Hub
(£0.069m) Town Centre Regeneration
(£0.037m) VDLF
CFCR £0.703m Glenartney Arran Staff Accommodation
£0.069m Marress House
£0.024m AGD - Irvine Harbourside (The Great Harbour)
£0.012m Brodick Library
£0.012m AGD Marine Tourism - Arran
£0.012m AGD Marine Tourism - Cumbrae
Capital Receipt £0.049m Insurance Recoveries
Use of Reserves £0.085m Park Improvements
£0.076m Shewalton PV
£0.069m Street Furniture
£0.052m Shiskine Early Years
£0.026m Gallowgate Toilets
£0.015m Ardrossan Hostel
Total (£2.594m)

Page 4

Service Amount Project
Communities (£0.139m) Lockhart Campus
(£0.055m) Kilwinning Learning Enviroment
(£0.151m) Other Minor Adjustments
(£0.345m)
Chief Executives (£0.050m) ICT Investment Fund
(£0.007m) Telephony
(£0.057m)
HSCP (£0.363m) Residential & Respite Unit
(£0.168m) Carefirst Replacement
(£0.001m) Other Minor Adjustments
(£0.532m)
Place (£0.768m) Upper Garnock FPS
(£0.724m) Millport FPS
(£0.599m) Fleet Decarbonisation
(£0.495m) Place Based Investment
(£0.475m) VDLF Development Work
(£0.435m) Vehicles
(£0.431m) Industrial Portfolio
(£0.398m) Solar PV Nethermains
(£0.369m) Lochshore Garnock HUB
(£0.350m) CCTV Review
(£0.323m) B714 Upgrade
(£0.246m) Gallowgate Toilets
(£0.238m) BUILD
(£0.214m) Saltcoats Old Railway
(£0.200m) AGD - I3 DPMC Phase 1
(£0.157m) Emergency Control Centre
(£0.154m) AGD - Hunterston -  Low Carbon Energy
(£0.151m) AGD - Great Harbour
(£0.143m) AGD - IMSE
(£0.140m) Island Infrastructure Fund
(£0.126m) Renew Playparks
(£0.112m) Lochshore Kilbirnie
(£1.403m) Other Minor Adjustments
(£8.651m)
Other (£0.104m) Flexibility Fund
(£0.104m)
Corporate £4.064m Uncertainty / Sensitivity Adjustment
£4.064m
Total (£5.625m)

Page 5

These adjustments have been partly offset by the acceleration of £1.391m of
expenditure to 2022/23 from future years. 
2.5 These adjustments have resulted in a revised 2022/23 budget at 31 March 2023 of
£36.194m. 
2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
Service Amount Project
Chief Executives £0.045m ICT Investment Fund
£0.011m LAN/WiFi
£0.056m
Place £0.149m Cycling/Safer Walking Streets
£0.099m AGD - I3 Flexible Business Space
£0.052m Cemetery Extensions & Walls
£0.153m Other Minor Adjustments
£0.453m
Communities £0.636m Moorpark Primary
£0.209m Montgomerie Park Primary
£0.035m Schools ICT Investment
£0.002m Other Minor Adjustments
£0.882m
Total £1.391m
38.672 32.249 0.492 50.239 2.500 124.152
25.201 8.948 2.002 43.502 (10.019) 69.634
25.196 6.764 1.672 38.451 (8.321) 63.762
9.045 2.555 1.578 40.231 (4.782) 48.627
8.573 2.366 1.262 34.676 (4.064) 42.813
10.207 1.014 0.903 24.070 - 36.194
(30.099) (29.883) 0.770 (15.563) (6.564) (81.339)
Approved Programme
Movement
Programme @ P6
Programme @ P4
Programme @ P10
Programme @ P8
Programme @ P12

Page 6

2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of (£6.619m) from the revised budget,
including: 
2.8 Capital Expenditure to 31 March 2023 
The actual expenditure by service is summarised in the following table:   
2.9 Significant cost risks have been identified across the Capital Investment Programme.
Although these have not all been formally reflected in the financial performance
reports at this time, areas of cost risk have been identified as a result of cost volatility
arising from the ongoing inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials
across a number of projects, as highlighted in appendix 1. Some mitigation has been
built into the Capital Investment Programme in the form of enhanced flexibility
budgets. However, cost pressures may exceed this provision, requiring additional
revenue investment to offset any additional borrowing requirements. These risks will
be quantified as individual projects are completed and tendering exercises are
finalised, with the impact on the costs of the programme being monitored and reported
to Cabinet as appropriate. 
Category Amount Comments
Borrowing £1.814m Rephased aligned to projected expenditure
CFCR (£0.428m) Additional CFCR Contributions
Capital Grants £4.768m Rephased and additional government grants
Other Grants £0.544m Rephased and revised contributions
Capital Receipts (£0.079m) Realigned capital receipts
Total £6.619m
Revised
Budget
2022/23
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Actual
Expenditure
/ Income to
31 March
2023
Variance
Over /
(Under)
£m £m £m £m £m £m
Expenditure
Communities 8.573 1.097 0.537 10.207 10.207 -
Chief Executive 2.366 (1.351) (0.001) 1.014 1.014 -
Health and Social Care Partnership 1.262 0.173 (0.532) 0.903 0.903 -
Place 34.676 (2.408) (8.198) 24.070 24.070 -
Other including Flexibility (4.064) 0.104 3.960 - - -
Total Expenditure 42.813 (2.385) (4.234) 36.194 36.194 -
Income
General Capital Grant (26.341) 0.530 - (25.811) (25.811) -
Specific Capital Grant (9.194) 2.263 1.975 (4.956) (4.956) -
Capital Funded from Current Revenue (0.081) (0.167) (0.261) (0.509) (0.509) -
Capital Receipts (0.212) (0.049) (0.030) (0.291) (0.291) -
Other Grants & Contributions (2.679) (0.089) 0.633 (2.135) (2.135) -
Prudential Borrowing (4.306) (0.103) 1.917 (2.492) (2.492) -
Total Income (42.813) 2.385 4.234 (36.194) (36.194) -

Page 7

2.10 Any funding in excess of the current level of financial flexibility, which is required to
deliver the current capital programme, will be a matter for Council to consider within
the context of overall affordability. This affordability assessment was included in the
Capital Budget approved at Council on 1 March 2023 and incorporated all known cost
pressures, funding and borrowing requirements based on current and projected
interest rates, the anticipated re-direction of revenue resources and use of financial
flexibilities to support delivery of the programme and a further flexible allowance to
help manage the ongoing cost risks associated with the programme.   
Housing Revenue Account 
2.11 The following table outlines the movements in the 2022/23 HRA Capital budget: 
2.12  (a) Changes to Funding 
The HRA capital programme has been updated to include additional Scottish
Government grant funding of £0.486m in relation to the Ukrainian Resettlement
programme supporting the redevelopment works at Glebe Place, Saltcoats. 
2.13 (b) Alterations to the Phasing of Projects 
A further review of the timescale for delivery of capital projects has identified a
requirement to re-profile (£9.185m) of works for delivery in 2023/24 and beyond,
including: 
2022/23
£m
Budget as at 31 January 2023 43.451       
a) Changes to Funding 0.486         
b) Alterations to phasing of projects:-
2022/23 to 2023/24 (9.185)             
2023/24 to 2022/23 2.158         
Budget as at 31 March 2023 36.910

Page 8

This has been partly offset by the acceleration of £2.158m of project expenditure for
delivery during 2022/23, including: 
Category Amount Project
New Builds (£0.728m) Harbourside Irvine
(£0.626m) Afton Court
(£0.543m) Corsehillhead
(£0.299m) Largs Police Station
(£0.282m) Caley Court
(£0.241m) Flatt Road Phase 1
(£0.219m) Acquisiton on Open Market
(£0.107m) Other Minor Adjustments
(£3.045m)
Improvements (£1.048m) Insulated Rerendering
(£1.018m) Kitchen Programme Voids
(£0.855m) Bathroom Programme Voids
(£0.063m) Sheltered Housing Units
(£2.984m)
Category Amount Project
Refurbishments (£0.478m) Roofing & Rendering
(£0.295m) Demolition High Flats Irvine
(£0.230m) Friars Lawn
(£0.024m) Other minor adjustments
(£1.027m)
Other (£1.738m) Professional Management Charges
(£0.348m) Solar Panels
(£0.043m) Other minor adjustments
(£2.129m)
Total (£9.185m)
Category Amount Project
New Builds £0.120m James Reid ASN
£0.113m Other minor adjustments
£0.233m
Improvements £0.997m Bathroom Programme
£0.297m Kitchen Programme
£0.132m Central Heating
£0.031m Other minor adjustments
£1.457m
Refurbishments £0.035m Friars Lawn
Other £0.384m Estate Based Regeneration
£0.049m Other minor adjustments
£0.433m
Total £2.158m

Page 9

2.14 These adjustments have resulted in a revised 2022/23 budget at 31 March 2023 of
£36.910m. 
2.15 The impact on budgeted funding is a reduction of (£6.297m) in Prudential Borrowing
and (£1.626m) in Use of Reserves aligned to the revised projected expenditure. This
has been partly offset by an increase drawdown of Capital grants of £1.382m. 
2.16  Capital Expenditure to 31 March 2023 
The actual expenditure is summarised in the following table:   
2.17 A variance of (£6.399m) is reported within the HRA capital programme for 2022/23
arising from revisions to a number of projects. This is primarily related to the
overprovision against a number of improvement programmes, which will be reprofiled
to align to the revised Business Plan and net underspends on the final costs across a
number of new build programmes which are now complete. In addition, the reports
highlights additional unbudgeted expenditure in relation to Ukrainian Resettlement
work and discussions with the Scottish Government are ongoing in relation to
potential funding: 
Category Amount Comments
Borrowing £6.297m Rephased aligned to actual expenditure
Use of Reserves £1.626m Rephased aligned to actual expenditure
Capital Grants (£1.382m) New grants and re-aligned to actual expenditure
Total £6.541m
Revised
Budget
2022/23
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Actual
Expenditure /
Income to 31
March 2023
Variance
Over /
(Under)
Service £m £m £m £m £m
Expenditure
Housing Revenue Account 43.451 (6.541) 36.910 30.511 (6.399)
Total Expenditure 43.451 (6.541) 36.910 30.511 (6.399)
Income
Sale of Assets - - - (0.005) (0.005)
CFCR (12.209) (12.209) (12.209) -
Capital Grants (1.767) (1.382) (3.149) (3.149) -
Use of Reserves (1.151) 0.580 (0.571) (0.571) -
Affordable Housing Contribution (1.596) 1.046 (0.550) (0.550) -
Prudential Borrowing (26.728) 6.297 (20.431) (14.027) 6.404
Total Income (43.451) 6.541 (36.910) (30.511) 6.399

Page 10

2.18 Increased costs arising from tender inflation and supply chain issues have been
identified in relation to some projects, including the Door Replacement Programme
and Sheltered Housing Unit Improvements. Further cost pressures resulting from
inflationary and supply chain issues continue to be monitored and a review of the
potential impact on the Business Plan and Capital Programme will be undertaken to
address any identified issues. Further information on the progress of all projects can
be found in Appendix 2. 
3. Proposals 
3.1 That Cabinet agrees to (a) note the revisions to budgets outlined in the report; (b) note
the General Services and HRA expenditure to 31 March 2023. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Project Variance Comments
Glebe Place Refurb £0.052m Unbudgeted Expenditure
New Build St Michaels Wynd £0.097m Complete
New Build St Beya Millport (£0.002m) Complete
New Build Towerlands (£0.009m) Complete
New Build Dalrymple Place (£0.017m) Complete
New Build St Colms (£0.034m) Complete
New Build Springvale Saltcoats (£0.091m) Complete
New Build Brathwic Terrace (£0.125m) Complete
Central Heating (£0.642m) Aligned to revised Business Plan
Electrical Rewiring (£1.494m) Aligned to revised Business Plan
Roofing & Rendering (£1.834m) Aligned to revised Business Plan
Kitchen Programme (£2.300m) Aligned to revised Business Plan
Total (£6.399m)

Page 11

Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2019 to 2024 by maximising resources
and providing value for money to support financially sustainable delivery models. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Programme Performance to 31 March 2023 – Cabinet, 21 March 2023

Page 12

TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Brought / Carry
Forward to 2023/24
Total Revised
Budget 2022/23
Actual Expenditure to
31 March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 15,918,237 15,799,375 15,918,237 0 2,316,976 (27,263) 2,289,713 2,289,713 0 0
Primary Schools 41,255,113 8,167,653 41,255,113 0 4,389,528 813,158 5,202,686 5,202,686 0 0
Secondary Schools 83,010,742 3,916,675 83,010,742 0 719,721 (101,085) 618,636 618,636 0 0
Special Education 25,343,637 25,205,042 25,343,637 0 803,662 (138,595) 665,067 665,067 0 0
Schools Other 1,648,363 1,536,800 1,648,363 0 1,395,712 34,980 1,430,692 1,430,692 0 0
Information & Culture 113,479 6,563 113,479 0 40,852 (40,852) 0 0 0 0
Completed Projects 43,419,379 43,415,700 43,419,379 0 3,679 (3,679) 0 0 0 0
SUB TOTAL 210,708,950 98,047,807 210,708,950 0 9,670,130 536,663 10,206,793 10,206,793 0 0
Chief Executive
Council IT Strategy 8,496,682 2,525,457 8,496,682 0 1,014,758 (1,030) 1,013,728 1,013,728 0 0
SUB TOTAL 8,496,682 2,525,457 8,496,682 0 1,014,758 (1,030) 1,013,728 1,013,728 0 0
Health & Social Care
Management & Support 2,753,095 1,493,221 2,753,095 0 919,529 (170,065) 749,464 749,464 0 0
Housing Non HRA 506 0 506 0 506 (506) 0 0 0 0
Adults 4,608,078 4,590,031 4,608,078 0 26,868 1,889 28,757 28,757 0 0
Young People 5,579,718 5,216,541 5,579,718 0 487,982 (363,177) 124,805 124,805 0 0
SUB TOTAL 12,941,398 11,299,792 12,941,398 0 1,434,885 (531,859) 903,026 903,026 0 0
Place
Roads 108,160,167 28,669,977 108,160,167 (2,154,880) 13,926,294 (2,154,880) 11,771,414 11,771,414 0 0
Streetscene 7,891,828 3,680,140 7,891,828 0 2,385,756 (125,146) 2,260,610 2,260,610 0 0
Transport 4,719,306 1,729,406 4,719,306 0 2,740,706 (1,126,900) 1,613,806 1,613,806 0 0
Waste Services 14,539,343 14,539,343 14,539,343 0 0 0 0 0 0 0
Renewable Energy 14,952,181 1,868,609 14,952,181 0 787,008 (516,864) 270,144 270,144 0 0
Office Accommodation 3,356,286 1,476,916 3,356,286 0 1,674,133 (197,217) 1,476,916 1,476,916 0 0
Other Property 5,986,638 467,239 5,986,638 0 962,243 (877,634) 84,609 84,609 0 0
Other Housing 470,000 88,975 470,000 0 470,000 (381,025) 88,975 88,975 0 0
Economic Development & Regeneration 165,624,490 28,313,889 165,624,490 0 9,306,699 (2,818,098) 6,488,601 6,488,601 0 0
Completed Projects 6,355,261 6,314,666 6,355,261 0 15,304 0 15,304 15,304 0 0
SUB TOTAL 332,055,501 87,149,160 332,055,501 (2,154,880) 32,268,143 (8,197,764) 24,070,379 24,070,380 0 0
Other
Other 7,704,146 0 7,600,000 (104,146) 104,146 (104,146) 0 0 0 0
SUB TOTAL 7,704,146 0 7,600,000 (104,146) 104,146 (104,146) 0 0 0 0
Uncertainty / Sensitivity Adjustment* (4,064,230) 4,064,230 0
Total Project Expenditure 571,906,677 199,022,217 571,802,531 (2,259,026) 40,427,832 (4,233,906) 36,193,927 36,193,927 0 0
Total Project Income (40,427,832) 4,233,906 (36,193,927) (36,193,927) (0) 0
Total Net Expenditure 0 0 0 (0) 0 0
* Sensitivity adjustment of 10% or 25% based on source and reliability of expenditure projections
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2022/23
North Ayrshire Council Capital Statement 2022/23
Year Ended 31st March 2023
Period 12
The following classifications have been used to highlight delivery performance
against original timescales set

Page 13

Revised Budget
22/23 Variance
£ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 94,515,334 9,882,875 1,655,477 106,053,686 (103,561,460) 2,492,226 2,492,226 0
SUB TOTAL 94,515,334 9,882,875 1,655,477 106,053,686 (103,561,460) 0 2,492,226 2,492,226 0
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Early Learning & Childcare 464,253 517,775 982,028 (89,170) 892,858 892,858 0
Cycling / Walking /Safer Streets 1,111,122 38,831 (300,566) 849,387 (135,172) 714,215 714,215 0
Vacant & Derelict Land Funding 3,710,375 123,927 848,022 4,682,324 (3,109,316) 1,573,008 1,573,008 0
UK Government Grant - AGD 2,040,120 2,040,120 (1,733,379) 306,741 306,741 0
Lochshore - Garnock Community Visitor Hub 0 50,000 50,000 0 50,000 50,000 0
Town Centre Regeneration 0 166,774 250,000 416,774 (274,288) 142,486 142,486 0
Stevenston Beach Hub 0 34,525 50,000 84,525 (84,525) 0 0 0
Annickbank - Vacant & Derelict Land Investment Programme 0 0 0 0
Millport Town Hall Regeneration 0 382,028 1,187,810 1,569,838 (1,569,838) 0 0 0
Millport Town Hall Phase 2 0 0 0 0 0
Ardrossan Promenade 0 0 0 0 0
Islands Pit Stops 0 0 0 0 0
Islands Cost Crisis Emergency Fund 0 0 0 0 0
Place Based Investment Programme 706,000 147,903 346,040 1,199,943 (1,065,579) 134,364 134,364 0
UK Shared Prosperity Fund 0 0 0 0
Island Infrastructure Fund 0 259,000 259,000 (140,373) 118,627 118,626 0
Bridges Infrastructure 567,000 (567,000) 0 0 0 0 0
B714 Improvements 857,907 197,160 1,055,067 (165,808) 889,259 889,259 0
Renewal of Play Parks 0 117,000 117,000 (117,000) 0 0 0
Nature Restoration Fund 0 0 0 0 0 0
2-4 Boyle Street Hostel 0 88,975 88,975 88,975 0
CO2 Monitors in Schools 0 122,000 122,000 (76,651) 45,349 45,349 0
Capital Grants
General Capital Grant 9,805,000 845,000 10,650,000 15,161,506 25,811,506 25,811,506 0
SUB TOTAL 22,039,777 1,780,923 3,035,306 26,856,006 3,911,382 0 30,767,388 30,767,388 0
CFCR 600,000 0 0 600,000 (91,325) 0 508,675 508,675 0
Grants & Contributions 1,925,682 866,594 1,539,395 4,331,671 (2,196,996) 0 2,134,675 2,134,675 0
Capital Receipts 352,500 0 0 352,500 (61,534) 0 290,966 290,966 0
SUB TOTAL 7,597,157 1,050,109 1,628,337 10,275,603 (7,341,287) 0 2,934,313 2,934,313 0
TOTAL CAPITAL PROGRAMME FUNDING 124,152,268 12,713,907 6,319,120 143,185,295 (106,991,365) 0 36,193,927 36,193,927 0
22/23 Budget at
Capital Refresh
Mar 2022
Capital Programme Funding 2022/23
Approved budget
at Period 1 used
as revised starting
point 2022/23
Actual Income to 31
March 2023Funding Description
Carry Forward
from 2021/22
Changes after
Capital Refresh Mar
2022
Total Changes in
Year
Changes at
Capital Refresh
Mar 2023

Page 14

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual Expenditure to
31 March 2023
Actual Over/ (Under)
Spend for 2022/23   
True Over/(Under)
Spend            
Brought / Carry
Forward to 2023/24 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
ST BRIDGETS EARLY YEARS 787,477 787,477 787,477 0 10,378 10,378 0 0 Complete Complete Complete On Target On Target
KILMORY EARLY YEARS 55,978 28,187 55,978 0 195 195 0 0 15-Aug-22 31-Aug-23 Pre Tender On Target On Target
ST PETERS EARLY YEARS 1,261,310 1,243,727 1,261,310 0 25,646 24,750 (896) (896) Complete Complete Complete On Target On Target
MAYFIELD PS EARLY YEARS 215,710 215,710 215,710 0 5,680 5,680 (0) (0) Complete Complete Complete On Target On Target
BEITH PS EARLY YEARS 339,764 339,763 339,764 0 4,983 4,983 (0) (0) Complete Complete Complete On Target On Target
SKELMORLIE PS EARLY YEARS 359,069 358,835 359,069 0 4,121 3,887 (234) (234) 30-Apr-23 30-Apr-23 Defects On Target On Target
WEST KILBRIDE EARLY EARLY YEARS 232,807 225,055 232,807 0 11,531 3,779 (7,752) (7,752) Complete Complete Complete On Target On Target
GATESIDE EARLY YEARS 407,764 407,764 407,764 0 2,899 2,899 0 0 Complete Complete Complete On Target On Target
FAIRLIE EARLY YEARS 205,120 205,120 205,120 0 1,470 1,470 0 0 Complete Complete Complete On Target On Target
DREGHORN EARLY YEARS 82,940 82,940 82,940 0 497 497 0 0 Complete Complete Complete On Target On Target
PIRNMILL EARLY YEARS 80,000 71,846 80,000 0 77,510 69,357 (8,154) (8,154) 31-Oct-21 30-Apr-23 Construction On Target On Target
SHISKINE EARLY YEARS 127,013 127,013 127,013 0 70,855 70,855 0 0 31-Oct-21 30-Apr-23 Construction On Target On Target
CORRIE EARLY YEARS 38,606 28,442 38,606 0 36,441 26,883 (9,558) (9,558) 31-Oct-21 01-Aug-23 Defects On Target On Target
LAMLASH EARLY YEARS 15,000 877 15,000 0 195 195 0 0 31-Oct-21 31-Aug-23 Tender On Target On Target
BRODICK EARLY YEARS 354,660 354,659 354,660 0 346,221 346,221 (0) (0) Complete Complete Complete Complete Complete
MARRESS HOUSE 3,560,310 3,560,310 3,560,310 0 1,632,968 1,632,968 (0) (0) 22-Jul-22 31-May-23 Construction On Target Significantly off target result of poor performance by the contractor and continuing issues with the
condition of the existing building
Completed Nursery Education
LAWTHORN EARLY YEARS 201,037 201,037 201,037 0 77 77 (0) (0) Complete Complete Complete Complete Complete
Other Nursery Education
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,103,415 3,070,354 3,103,415 0 85,309 84,640 (669) (669) Complete Complete Complete On Target On Target
Total Nursery Education 15,918,237 15,799,375 15,918,237 0 2,316,976 2,289,713 (27,263) 0 (27,263)
Primary Schools
MOORPARK PRIMARY 10,849,442 6,536,549 10,849,442 0 3,086,371 3,722,113 635,742 635,742 30-Sep-22 30-Sep-23 Construction Slightly off target  Significantly off target Delays are being experienced by the contractor and wider supply chain.
MONTGOMERIE PARK SCHOOL 23,449,000 1,095,998 23,449,000 0 736,478 945,730 209,252 209,252 30-Apr-24 12-Aug-24 Tender Significantly off target On Target Revised project costs £2.550m above initial budget as reported to Cabinet on
27/4/22
UFSM BRODICK PRIMARY SCHOOL 144,178 121,334 144,178 0 144,178 121,334 (22,844) (22,844) 31-Aug-23 31-Aug-23 Construction On Target On Target
UFSM CORRIE PRIMARY SCHOOL 52,795 52,795 52,795 0 52,795 52,795 0 0 Complete Complete Complete Complete Complete
UFSM LARGS PRIMARY SCHOOL 150,000 148,533 150,000 0 150,000 148,533 (1,467) (1,467) Complete Complete Complete Complete Complete
UFSM SHISKINE PRIMARY SCHOOL 15,000 6,072 15,000 0 3,553 6,072 2,519 2,519 Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,252,504 206,372 2,252,504 0 216,448 206,110 (10,338) (10,338) 31-Mar-24 31-Mar-24 On Site On Target On Target
Total Primary Education 41,255,113 8,167,653 41,255,113 0 4,389,528 5,202,686 813,158 0 813,158 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,427,034 2,805,435 0 127,953 72,632 (55,321) (55,321) 31-Aug-21 31-Mar-24 Construction On Target On Target
ARDROSSAN NEW BUILD 80,205,307 1,489,641 80,205,307 0 591,768 546,004 (45,764) (45,764) 31-Aug-26 31-Aug-26 In Development Slightly off target  Slightly off target  Delayed expenditure linked to anticipated delays and inflationary pressures
linked to the advance works tender process.
Total Secondary Education 83,010,742 3,916,675 83,010,742 0 719,721 618,636 (101,085) 0 (101,085)
Special Education
LOCKHART CAMPUS 25,343,637 25,205,042 25,343,637 0 803,662 665,067 (138,595) (138,595) Complete Complete Snagging On Target On Target
Total Special Education 25,343,637 25,205,042 25,343,637 0 803,662 665,067 (138,595) 0 (138,595)
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 151,457 298,000 0 45,349 45,349 0 0 31-Mar-23 31-Mar-24 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 1,350,363 1,385,343 1,350,363 0 1,350,363 1,385,343 34,980 34,980 31-Mar-23 31-Mar-23 On-going On Target On Target
Total Schools Other 1,648,363 1,536,800 1,648,363 0 1,395,712 1,430,692 34,980 0 34,980
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 (38,303) (38,303) Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 75,176 6,563 75,176 0 2,549 0 (2,549) (2,549) Autumn 2023 Autumn 2023 Planning On Hold On Hold
Total Information & Cultural 113,479 6,563 113,479 0 40,852 0 (40,852) 0 (40,852)
Completed Projects
GARNOCK CAMPUS 40,307,259 40,304,366 40,307,259 0 2,893 0 (2,893) (2,893) Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,112,120 3,111,334 3,112,120 0 786 0 (786) (786) Complete Complete Complete Complete Complete
Total Completed Projects 43,419,379 43,415,700 43,419,379 0 3,679 0 (3,679) 0 (3,679)
Total Communities 210,708,950 98,047,807 210,708,950 0 9,670,130 10,206,793 536,663 0 536,663
CAPITAL MONITORING 2022/23
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS

Page 15

CHIEF EXECUTIVE
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual
Expenditure to 31
March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to
2023/24
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 3,732,986 909,733 3,732,986 0 285,000 279,944 (5,057) (5,057) 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 902,100 402,197 902,100 0 139,297 139,394 97 97 31-Mar-28 31-Mar-28 Implementation On Target On Target
LAN/WiFi 2,673,000 944,162 2,673,000 0 561,816 572,978 11,162 11,162 31-Mar-28 31-Mar-28 Implementation On Target On Target
TELEPHONY 1,146,693 227,643 1,146,693 0 24,988 17,938 (7,050) (7,050) 31-Mar-28 31-Mar-28 Implementation On Target On Target
OUR FUTURE WORKING ENVIRONMENT 41,903 41,722 41,903 0 3,657 3,476 (181) (181) Complete Complete Complete Complete Complete
Total IT Strategy 8,496,682 2,525,457 8,496,682 0 1,014,758 1,013,728 (1,030) 0 (1,030)
Total Chief Executive 8,496,682 2,525,457 8,496,682 0 1,014,758 1,013,728 (1,030) 0 (1,030)   
CAPITAL MONITORING 2022/23
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2022/23 BUDGETS

Page 16

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual Expenditure to
31 March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to 2023/24   Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £
Management & Support
HOME CARE SYSTEM 433,917 433,917 433,917 0 42,682 42,682 0 0 Complete Complete Complete Complete Complete
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 4,190 996,000 0 6,190 4,190 (2,000) (2,000) 31-Dec-23 31-Dec-23 Future Years On Target On Target
CAREFIRST IT SYSTEM 84,620 84,620 84,620 0 0 0 0 0 Complete Complete Complete Complete Complete
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 168,157 92 (168,065) (168,065) 31-Aug-24 31-Aug-24 In development On Target On Target
ARRAN STAFF ACCOM – GLENARTNEY 702,500 702,500 702,500 0 702,500 702,500 0 0 31-Mar-23 31-Mar-23 Acquisition On Target On Target
Total Management & Support 2,753,095 1,493,221 2,753,095 0 919,529 749,464 (170,065) 0 (170,065)
Housing Non HRA
IMPROVEMENT GRANTS * 506 0 506 0 506 0 (506) (506) 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
Total Housing Non HRA 506 0 506 0 506 0 (506) 0 (506)
Adults
TRINDLEMOSS 4,608,078 4,590,031 4,608,078 0 26,868 28,757 1,889 1,889 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,590,031 4,608,078 0 26,868 28,757 1,889 0 1,889
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,216,541 5,579,718 0 487,982 124,805 (363,177) (363,177) Complete Complete Snagging On Target On Target
Total Young People 5,579,718 5,216,541 5,579,718 0 487,982 124,805 (363,177) 0 (363,177)
Total Health & Social Care 12,941,398 11,299,792 12,941,398 0 1,434,885 903,026 (531,859) 0 (531,859)
CAPITAL MONITORING 2022/23
2022/23 BUDGETSTOTAL PROJECT COMPLETION DATES
CommentsProject Description
DELIVERY STATUS

Page 17

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual
Expenditure to 31
March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £
PHYSICAL ENVIRONMENT
Roads
ROADS IMPROVE/RECONSTRUCTION * 4,814,795 4,767,534 4,814,795 0 4,814,795 4,767,534 (47,261) (47,261) 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
A737 DALRY BYPASS 136,000 129,955 136,000 0 136,000 129,955 (6,045) (6,045) 31-Mar-24 31-Mar-24 In Development On Target On Target 
TRAFFIC CALMING 175,000 92,047 175,000 0 100,000 92,047 (7,953) (7,953) 31-Mar-24 31-Mar-24 In Development On Target On Target
VEHICLE RESTRAINT SYSTEM UPGRADE 100,000 100,000 100,000 0 100,000 100,000 0 0 31-Mar-23 31-Mar-23 In Development On Target On Target
LIGHTING * 1,244,770 1,170,485 1,244,770 0 1,244,770 1,170,485 (74,285) (74,285) 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 695,000 338,021 695,000 0 329,690 338,021 8,331 8,331 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target
A737 DALRY BYPASS LIGHTING 20,685 4,074 20,685 0 6,485 4,074 (2,411) (2,411) 31-Mar-23 31-Mar-23 Preparing Works PackagesOn Target On Target
UPPER GARNOCK FPS 18,503,800 17,435,972 18,503,800 0 3,154,934 2,387,106 (767,828) (767,828) Complete Complete Complete Slightly off target  Slightly off target  The contractor did not achieve the programme before winter. The drainage and
topsoiling/ seeding cannot be completed until next spring
MILLPORT COASTAL FPS 48,599,796 1,840,415 48,599,796 0 1,300,000 575,618 (724,382) (724,382) 31-Aug-24 31-Aug-24 Construction Slightly off target  On Target
MILLBURN FPS 1,757,000 253,471 1,757,000 0 60,000 66,453 6,453 6,453 31-Mar-23 31-Jul-24 Design On Target Significantly off
target
Delays in the design process
MILLPORT PIER 500,000 150,080 500,000 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 1,000,000 1,000,570 1,000,000 0 1,000,000 1,000,570 570 570 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 3,969,000 333,954 3,969,000 0 191,596 223,326 31,730 31,730 31-Oct-23 31-Oct-23 Tender Slightly off target  On Target Increased tender cost risks identified
B714 UPGRADE 26,063,443 889,259 26,063,443 0 1,212,000 889,259 (322,741) (322,741) 31-Mar-25 31-Mar-25 Outline Design Significantly off target On Target Increased tender cost risks identified
LARGS CAR PARK INFRASTRUCTURE 54,467 54,467 54,467 0 0 0 0 0 Complete Complete Complete Complete Complete
GALLOWGATE TOILETS 275,803 29,650 275,803 0 273,119 26,967 (246,153) (246,153) 31-Mar-23 31-Mar-23 Planning On Target On Target
PARKING CHARGES & DPE 250,610 80,025 250,610 0 2,905 0 (2,905) (2,905) 31-Mar-24 31-Mar-24 In Development On Target On Target
Total Roads 108,160,167 28,669,977 108,160,167 0 13,926,294 11,771,414 (2,154,880) 0 (2,154,880)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 665,405 0 665,405 0 (52,174) 0 52,174 52,174 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, LAMLASH - EXTENSION 715,065 715,065 715,065 0 30,540 30,540 0 0 Complete Complete Complete Complete Complete
CMTY, ARDROSSAN - PLOTS/WALLS 217,922 156,058 217,922 0 55,921 5,355 (50,566) (50,566) Complete Complete Complete Complete Complete
CMTY, KILBIRNIE - WORKS 25,383 25,383 25,383 0 0 0 0 0 Complete Complete Complete Complete Complete
CMTY, KILWINNING - NEW 1,264,528 1,264,528 1,264,528 0 1,176,082 1,176,082 0 0 01-Sep-22 31-May-23 Construction On Target Significantly off
target
Contractor appointed and work commenced
CMTY, KNADGERHILL - EXTENSION 416,471 414,810 416,471 0 22,230 20,569 (1,661) (1,661) Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WORKS 361,142 361,141 361,142 0 322,422 329,928 7,506 7,506 25-Nov-22 28-Feb-24 Construction On Target On Target
CMTY, STEV HIGH ROAD - WORKS 545,429 369,470 545,429 0 365,961 325,642 (40,319) (40,319) 23-Dec-22 30-Apr-23 Construction On Target On Target
ARDROSSAN CEMETERY NEW 900,603 603 900,603 0 0 0 0 0 Future years Future years Future years On Hold On Hold
CMTY, BRODICK - NEW 12,000 7,021 12,000 0 9,521 7,021 (2,500) (2,500) Future years Future years Planning On Hold On Hold
CMTY, KILBIRNIE - WALLS 188,370 15,626 188,370 0 2,043 15,626 13,583 13,583 31-Mar-23 30-Apr-23 Feasibility Works On Target On Target
CMTY, BEITH - WALLS 87,542 14,635 87,542 0 2,533 14,046 11,513 11,513 31-Mar-23 30-Apr-23 Feasibility Works On Target On Target
CMTY, ABBEY TOWER - WALLS 95,550 6,052 95,550 0 3,520 6,052 2,532 2,532 31-Mar-24 31-Mar-24 Feasibility Works On Target On Target
CMTY, STEV HAWKHILL - WALLS 108,732 5,860 108,732 0 1,811 5,860 4,049 4,049 31-Mar-24 31-Mar-24 Feasibility Works On Target On Target
CMTY, WEST KILBRIDE - WALLS 99,528 4,604 99,528 0 2,413 4,604 2,191 2,191 31-Mar-24 31-Mar-24 Feasibility Works On Hold On Hold
CMTY, MILLPORT - WALLS 2,846 2,846 2,846 0 2,846 2,846 0 0 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, ARDROSSAN - WALLS 4,338 4,338 4,338 0 4,338 4,338 0 0 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, IRVINE OP CHURCH - WALLS 2,775 2,775 2,775 0 2,775 2,775 0 0 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, DREGHORN - WALLS 3,260 3,260 3,260 0 3,260 3,260 (1) (1) 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, KILBIRNIE BARONY - WALLS 1,828 1,828 1,828 0 1,828 1,828 (0) (0) 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, LAMLASH - WALLS 3,627 3,627 3,627 0 3,627 3,627 (0) (0) 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, STEV HIGH KIRK - WORKS 22,754 22,754 22,754 0 22,754 22,754 0 0 31-Mar-23 31-Mar-23 Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 598,450 11,287 598,450 0 9,223 11,287 2,064 2,064 31-Mar-25 31-Mar-25 Feasibility Works On Target On Target
CMTY, DALRY - WALLS 2,450 2,450 2,450 0 2,450 2,450 0 0 On Target On Target
COASTAL PLAY PARKS 0 0 0 0 0 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
STREET FURNITURE IMPROVEMENT 69,469 69,469 69,469 0 69,469 69,469 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PARK ENABLING WORKS 85,363 85,363 85,363 0 85,363 85,363 (0) (0) 31-Mar-23 31-Mar-23 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,391,000 109,288 1,391,000 0 235,000 109,288 (125,712) (125,712) 31-Mar-23 31-Mar-23 Construction On Target On Target
Total Streetscene 7,891,828 3,680,140 7,891,828 0 2,385,756 2,260,610 (125,146) 0 (125,146)
Transport
VEHICLES * 1,901,045 1,466,418 1,901,045 0 1,901,045 1,466,418 (434,627) (434,627) 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
WORKPLACE CHARGERS 318,261 225,403 318,261 0 202,661 109,803 (92,858) (92,858) 31-Mar-23 31-Mar-23 Ongoing On Target On Target
FLEET DECARBONISATION 2,500,000 37,585 2,500,000 0 637,000 37,585 (599,415) (599,415) 31-Mar-23 31-Mar-23 Ongoing On Target On Target
Total Transport 4,719,306 1,729,406 4,719,306 0 2,740,706 1,613,806 (1,126,900) 0 (1,126,900)
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 42,014 120,000 0 78,205 219 (77,986) (77,986) 31-Mar-23 31-Mar-23 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 7,289,441 145,681 7,289,441 0 500,000 102,241 (397,759) (397,759) 30-Apr-24 30-Apr-24 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 5,540,347 98,110 5,540,347 0 75,640 98,110 22,470 22,470 30-Oct-24 30-Oct-24 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 936,411 1,000,000 0 63,589 0 (63,589) (63,589) 31-Mar-23 31-Mar-23 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 356,000 0 356,000 0 0 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target 
ELECTRIC VEHICLES INFRASTRUCTURE 646,392 646,392 646,392 0 69,574 69,574 0 0 31-Mar-23 31-Mar-23 Various On Target On Target 
Total Renewable Energy 14,952,181 1,868,609 14,952,181 0 787,008 270,144 (516,864) 0 (516,864)
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments

Page 18

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual
Expenditure to 31
March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * (6,204) 0 (6,204) 0 (6,204) 0 6,204 0 6,204 31-Mar-23 31-Mar-23 Mulitple projects On Target On Target 
PLI CALEY COURT RESOURCE CTR 3,450 3,450 3,450 0 3,450 3,450 (0) 0 (0) Complete Complete Complete Complete Complete
PLI CENTRAL AVE STREETSCENE DEPOT* 64,494 64,494 64,494 0 64,494 64,494 (0) 0 (0) Complete Complete Complete Complete Complete
PLI BEITH CEMETERY 669 669 669 0 669 669 (0) (0) Complete Complete Complete Complete Complete
PLI WHITLEES COMMUNITY CTR 3,916 3,916 3,916 0 3,916 3,916 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE COMMUNITY CENTRE 135,699 135,499 135,699 0 135,699 135,499 (200) 0 (200) Complete Complete Complete Complete Complete
PLI WOODWYND HALL 2,000 1,809 2,000 0 0 1,809 1,809 0 1,809 Complete Complete Complete Complete Complete
PLI PORTLAND PLACE 27,967 0 27,967 0 18,000 0 (18,000) 0 (18,000) 31-Dec-22 30-Jun-23 Planning On Target On Target Planned for w/c 20/03
PLI PADDOCKHOLM DEPOT 10,000 7,754 10,000 0 10,000 7,754 (2,246) 0 (2,246) Complete Complete Complete Complete Complete
PLI WEST BYREHILL DEPOT 160,513 86,979 160,513 0 160,513 86,979 (73,534) 0 (73,534) 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI GOLDCRAIGS DEPOT 136,563 17,968 136,563 0 17,968 17,968 (0) (0) 31-Mar-23 31-Mar-24 Planning On Target On Target
PLI ANNICK PRIMARY SCHOOL 5,959 5,959 5,959 0 5,959 5,959 (0) (0) Complete Complete Complete Complete Complete
PLI ARDEER PRIMARY SCHOOL 2,952 2,952 2,952 0 2,952 2,952 0 0 0 Complete Complete Complete Complete Complete
PLI BEITH PRIMARY SCHOOL 2,300 0 2,300 0 2,300 0 (2,300) 0 (2,300) 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI BLACKLANDS PRIMARY SCHOOL 210,000 178,405 210,000 0 210,000 178,405 (31,595) (31,595) Complete Complete Complete Complete Complete
PLI CALEDONIA PRIMARY SCHOOL 6,646 6,646 6,646 0 6,646 6,646 (0) (0) Complete Complete Complete Complete Complete
PLI DALRY PRIMARY SCHOOL 89,000 20,686 89,000 0 19,907 20,686 779 779 18-Aug-23 18-Aug-23 Planning On Target On Target
PLI DREGHORN PRIMARY SCHOOL 1,500 0 1,500 0 1,500 0 (1,500) (1,500) 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI FAIRLIE PRIMARY SCHOOL 7,374 6,355 7,374 0 7,374 6,355 (1,019) (1,019) Complete Complete Complete Complete Complete
PLI GLENCAIRN PRIMARY SCHOOL 175,759 160,003 175,759 0 175,759 160,003 (15,756) (15,756) Complete Complete Complete Complete Complete
PLI PENNYBURN PRIMARY 415,450 0 415,450 0 3,500 0 (3,500) (3,500) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ST BRIDGETS PRIMARY 5,500 4,645 5,500 0 5,500 4,645 (855) (855) 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI SHISKINE PRIMARY 4,266 4,266 4,266 0 4,266 4,266 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL 75,000 1,020 75,000 0 0 1,020 1,020 1,020 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ST JOHN OGILVIE PRIMARY SCHOOL 16,708 16,708 16,708 0 16,708 16,708 0 0 Complete Complete Complete Complete Complete
PLI ST PETER'S PRIMARY 1,971 1,971 1,971 0 1,971 1,971 (0) (0) Complete Complete Complete Complete Complete
PLI WEST KILBRIDE PRIMARY* 325 325 325 0 325 325 0 0 0 Complete Complete Complete Complete Complete
PLI WOODLANDS PRIMARY 5,603 5,603 5,603 0 5,603 5,603 0 0 Complete Complete Complete Complete Complete
PLI AUCHENHARVIE ACADEMY* 821,820 498,739 821,820 0 550,000 498,739 (51,261) (51,261) 31-Mar-23 30-Jun-23 Construction On Target On Target
PLI IRVINE ROYAL ACADEMY* 378,785 11,354 378,785 0 10,171 11,354 1,183 1,183 31-Aug-23 31-Aug-23 Pupil Toilets: Complete AW Pitches: TenderOn Target Significantly off
target
Resource pressures within PMI resulting in this project being delayed
PLI KILWINNING ACADEMY 270,000 81,580 270,000 0 87,677 81,580 (6,098) (6,098) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI 6A KILWINNING ROAD 7,619 7,619 7,619 0 7,619 7,619 0 0 Complete Complete Complete Complete Complete
PLI LARGS LIBRARY 7,239 7,239 7,239 0 7,239 7,239 (0) (0) Complete Complete Complete Complete Complete
PLI STEVENSTON LIBRARY 5,915 5,915 5,915 0 5,915 5,915 0 0 Complete Complete Complete Complete Complete Works on hold depending on Land and Property review
PLI CUNNINGHAME HOUSE 98,273 3,482 98,273 0 3,482 3,482 0 0 31-Mar-23 31-Aug-23 On Hold On Hold On Hold
PLI H&SCP 47 WEST ROAD 9,555 9,555 9,555 0 9,555 9,555 0 0 Complete Complete Complete Complete Complete
PLI GALT HOUSE 8,593 8,593 8,593 0 8,593 8,593 (0) (0) Complete Complete Complete Complete Complete
PLI ACHNAMARA CHILDREN'S UNIT 29,671 29,671 29,671 0 29,671 29,671 0 0 Complete Complete Complete Complete Complete
PLI THE MEADOWS 5,900 5,482 5,900 0 5,900 5,482 (418) (418) Complete Complete Complete Complete Complete
PLI ANAM CARA 80,000 51,667 80,000 0 50,000 51,667 1,667 1,667 30-Apr-23 31-May-23 Planning On Target On Target
PLI GARNOCK CAMPUS 10,925 10,925 10,925 0 10,925 10,925 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI EGLINTON CASTLE 48,000 0 48,000 0 0 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI THE PORTAL 8,611 7,016 8,611 0 8,611 7,016 (1,595) (1,595) Complete Complete Complete Complete Complete
Total Office Accommodation 3,356,286 1,476,916 3,356,286 0 1,674,133 1,476,916 (197,217) 0 (197,217)
Other Property
INDUSTRIAL PORTFOLIO * 430,713 0 430,713 0 430,713 0 (430,713) (430,713) On Hold On Hold Multiple projects On Target On Target 
HOME 4,470,199 288,648 4,470,199 0 100,000 50,533 (49,467) 0 (49,467) On Hold On Hold On Hold On Hold On Hold
BUILD 284,086 46,249 284,086 0 247,284 9,448 (237,837) 0 (237,837) On Hold On Hold On Hold On Hold On Hold
EMERGENCY CONTROL CTR 158,000 1,220 158,000 0 158,000 1,220 (156,780) 0 (156,780) 31-Mar-23 31-Mar-23 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 509,000 25,000 509,000 0 25,000 25,000 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,640 106,122 134,640 0 1,246 (1,591) (2,837) (2,837) Complete Complete Complete On Target On Target
Total Property 5,986,638 467,239 5,986,638 0 962,243 84,609 (877,634) 0 (877,634)   
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 (350,000) (350,000) 31-Mar-23 31-Mar-23 Planning On Target On Target
2-4 BOYLE STREET HOSTEL 120,000 88,975 120,000 0 120,000 88,975 (31,025) (31,025) 12-May-23 12-May-23 Construction On Target On Target
Total Other Housing 470,000 88,975 470,000 0 470,000 88,975 (381,025) 0 (381,025)

Page 19

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Actual
Expenditure to 31
March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
Regeneration
TOWN CENTRE REGENERATION 1,201,660 995,968 1,201,660 0 188,177 122,486 (65,691) (65,691) 30-Sep-22 30-Sep-23 Construction On Target On Target
ISLAND INFRASTRUCTURE FUND 259,000 118,626 259,000 0 259,000 118,626 (140,374) (140,374) 31-Mar-23 31-Mar-23 In development On Target On Target
PBIP 36 BANK STREET 145,000 83,172 145,000 0 100,000 54,573 (45,427) (45,427) 31-Dec-24 31-Dec-25 In development On Target On Target
IRVINE HIGH STREET 2,837,316 2,721,355 2,837,316 0 54,327 49,857 (4,470) (4,470) Complete Complete Complete Complete Complete
MONTGOMERIE PARK MASTERPLAN 3,718,598 1,774,932 3,718,598 0 36,264 32,599 (3,665) (3,665) 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 2,011,138 1,641,780 2,011,138 0 1,442,286 1,072,928 (369,358) (369,358) 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,195,999 4,083,770 4,195,999 0 1,377,575 1,265,346 (112,229) (112,229) Complete Complete Complete On Target On Target
VDLF - IRVINE KYLE ROAD SITE PREP* 1,421,110 1,421,110 1,421,110 0 180 180 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 267,066 140,840 267,066 0 175,000 119,667 (55,333) (55,333) 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF - ANNICKBANK PH 3* 2,000,220 76,261 2,000,220 0 494,220 19,220 (475,000) (475,000) 31-Mar-24 31-Mar-24 Tender On Target On Target
VDLF - DEVELOPMENT WORK* 347,479 93,467 347,479 0 75,000 44,205 (30,795) (30,795) 30-Sep-23 31-Mar-24 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 25,301 20,523 (4,778) (4,778) Complete Complete Complete Complete Complete
CYCLING/WALKING/SAFER STREETS * 559,956 793,097 559,956 0 559,956 709,301 149,345 149,345 31-Mar-24 31-Mar-24 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 84,833 58,026 84,833 0 84,833 58,026 (26,807) (26,807) 31-Mar-24 31-Mar-24 Various On Target On Target
FAIRLIE COASTAL PATH 49,887 49,887 49,887 0 49,887 49,887 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
PENNYBURN ROUNDABOUT BUS LANE 533 124,201 533 0 533 533 0 0 31-Mar-23 31-Mar-23 Feasibility On Target On Target
IRVINE CYCLE FRIENDLY TOWN 216,198 466,198 216,198 0 216,198 216,198 0 0 31-Mar-23 31-Mar-23 Various On Target On Target
BRODICK TO CORRIE CYCLE PATH 24,987 60,199 24,987 0 24,987 24,987 (0) (0) 31-Mar-23 31-Mar-23 Design On Target On Target
BUS CORRIDOR IMPROVEMENTS 189,042 189,041 189,042 0 114,087 114,087 (0) (0) 31-Mar-23 31-Mar-23 Various On Target On Target
BUS ROUTE CONGESTION MEASURES 710,722 710,722 710,722 0 105,472 105,472 (0) (0) 31-Mar-23 31-Mar-23 Construction On Target On Target
CUMBRAE FERRY & BUS STOP 139,547 139,547 139,547 0 115,857 115,857 (0) (0) 31-Mar-23 31-Mar-23 Design On Target On Target
B714 ACTIVE TRAVEL IMPROVEMENTS 100,000 100,000 100,000 0 100,000 100,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
B777 CORRIDOR IMPROVEMENTS 38,400 4,800 38,400 0 4,800 4,800 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
SALTCOATS OLD CAL RAILWAY PH1 268,588 55,075 268,588 0 268,588 55,075 (213,513) (213,513) 26-Jun-23 26-Jun-23 Planning On Target On Target
STTS U88 NORTH SANNOX 126,572 126,572 126,572 0 126,572 126,572 0 31-Mar-23 31-Mar-23 Planning On Target On Target
STTS ROSS ROAD ARRAN 221,340 281,245 221,340 0 221,340 221,340 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Regeneration 31,427,633 22,417,236 31,427,633 0 6,932,778 4,822,344 (2,110,434) 0 (2,110,434)
Ayrshire Growth Deal
AYRSHIRE GROWTH DEAL 0 0 0 0 0 0 0 0 31-Mar-26 31-Mar-26 On Target On Target
AGD - I3 DPMC PHASE 1 1,000,000 5,449 1,000,000 0 200,000 0 (200,000) (200,000) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 DPMC PHASE 2 5,000,000 239,415 5,000,000 0 70,000 59,446 (10,554) (10,554) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE 15,000,000 545,423 15,000,000 0 208,000 306,741 98,741 98,741 31-Mar-26 31-Mar-27 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,001 232,228 18,040,001 0 200,000 46,108 (153,892) (153,892) 31-Mar-26 31-Mar-30 Multiple Projects On Target On Target Project has been reprofiled as part of the overall review of the AGD
programme. Slippage in current year due to work which is underway to clarify
partnership arrangements.
AGD - GREAT HARBOUR 14,164,951 598,089 14,164,951 0 452,909 301,771 (151,138) (151,138) 31-Mar-26 31-Mar-28 Multiple Projects On Target On Target  Masterplan currently under consultation and design works delayed until that
has been concluded.  Programme has been revised across the AGD timeframe
to reflect timing of the three Hubs
AGD - IMSE 10,500,000 133,513 10,500,000 0 174,000 31,253 (142,747) (142,747) 31-Mar-27 31-Mar-30 Design On Target On Target Project has been reprofiled as part of the overall review of the AGD
programme. Work is ongoing with partners to develop the delivery proposal for
this project.
AGD - MARINE TOURISM ARDROSSAN 7,500,000 334,696 7,500,000 0 137,638 123,955 (13,683) (13,683) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - MARINE TOURISM ARRAN 2,025,577 60,484 2,025,577 0 42,255 31,773 (10,482) (10,482) 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - MARINE TOURISM CUMBRAE 2,025,577 68,179 2,025,577 0 44,266 33,618 (10,648) (10,648) 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 75,256,105 2,217,477 75,256,105 0 1,529,068 934,665 (594,403) 0 (594,403)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,077,112 455,452 4,077,112 0 50,000 65,743 15,743 15,743 31-Dec-24 31-Dec-25 Design Slightly off target  On Target Increased tender cost risks identified
LOW CARBON HUB 1,430,017 112,005 1,430,017 0 123,698 25,204 (98,494) (98,494) 30-Apr-24 30-Sep-24 Multiple Projects On Target On Target Delays in securing landowner permissions for EV works and planning
applications awaited for Path works - both will now carry into 2324 FY
ARDROSSAN NORTH SHORE 41,532,860 2,833,766 41,532,860 0 541,317 536,243 (5,074) (5,074) 30-Apr-24 27-May-24 Tender Slightly off target  Slightly off target  Projected spend increased to include additional site investigations and service
design costs.
VDLF - HARBOUR MASTERS OFFICE 157,711 20,933 157,711 0 211 211 (0) (0) 31-Mar-23 31-Mar-23 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 996,981 257,020 996,981 0 129,627 104,192 (25,435) (25,435) 31-Mar-23 31-Mar-24 Design On Target On Target Slippage as Site Investigations for SIC will now take place during 23/24 Financial
Year.Other Growth & Investment 58,940,752 3,679,176 58,940,752 0 844,853 731,592 (113,261) 0 (113,261)
Total Economic Development & Regeneration 165,624,490 28,313,889 165,624,490 0 9,306,699 6,488,601 (2,818,098) 0 (2,818,098)
Completed Projects
ARDROSSAN HOSTEL 15,304 15,304 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 6,355,261 6,314,666 6,355,261 0 15,304 15,304 0 0 0
Total Place 332,055,501 87,149,160 332,055,501 0 32,268,143 24,070,380 (8,197,763) 0 (8,197,764)

Page 20

OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Actual Expenditure
to 31 March 2023
Over/ (Under)
Spend for 22/23
£ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 7,704,146 0 7,600,000 (104,146) 104,146 0 (104,146)
CORE INFRASTRUCTURE INVESTMENT 0 0 0 0 0 0 0
Total Other Budgets 7,704,146 0 7,600,000 (104,146) 104,146 0 (104,146)
2022/23 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 21

HRA Capital Statement APPENDIX 2
For the Twelve months to 31 March 2023
Description
Approved
budget 16
February
2022
Current
budget
including
carry
forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised
Budget
2022/23
Actual Spend
to
31/03/2023
True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'001 £'000 £'000
Council House Build Programme
Council House Building General 1,542 1,542 (1,542) (6) (6) (6) - On Target On Target
Acquisition Of Houses On Open Market 720 526 210 (219) 517 517 - On Target On Target
New Build Corsehillhead 1,450 600 - (543) 57 57 - On Target Slightly off target  Expected completion Winter 2024
New Build Brathwic Terrace 18 168 109 3 280 155 (125) On Target Complete Completed - final properties were handed over in June 2022
New Build Flatt Road Phase 1 1,712 1,072 (291) (241) 540 540 - On Target Complete Completed - final properties were handed over in December 2021.
New Build Towerlands 25 160 20 3 183 174 (9) On Target Complete Completed - final properties were handed over in March 2022.
New Build Kinnier Road 3 2 (2) - - - - Complete Complete Completed - properties were handed over in October 2021.
New Build St Colms 1,896 782 367 30 1,179 1,145 (34) Complete Complete Completed - properties were handed over in September 2022
New Build St Michaels Wynd - 592 403 26 1,021 1,118 97 On Target Complete Completed - final properties handed over in August 2022.
New Build Harbourside Irvine 6,460 6,000 (237) (728) 5,035 5,035 - On Target Slightly off target  Completed - final properties were handed over during April 2023.
New Build Afton Court 910 1,080 139 (626) 593 593 - On Target Slightly off target  Expected completion Summer 2023.
New Build Caley Court 1,769 1,843 - (282) 1,561 1,561 - On Target Slightly off target  Completed - properties were handed over January 2023.
New Build Springvale Saltcoats - 133 8 (1) 140 49 (91) On Target Complete Completed - properties were handed over in November 2021.
New Build Dalrymple Place - 101 - 4 105 88 (17) On Target Complete Completed - properties were handed over in October 2021.
New Build St Beya Millport 6 53 - - 53 51 (2) On Target Complete Completed - properties were handed over in July 2021.
Garnock Academy Site 7,950 1,800 (1,700) (25) 75 75 - Slightly off target  Slightly off target  Tender stage. Expected completion Spring 2025. 
Largs police Station 1,908 1,600 105 (299) 1,406 1,406 - On Target Slightly off target  Demolition complete. Expected completion Summer 2023.
Ayrshire Central Site 9,497 1,500 (1,400) 17 117 117 - On Target Slightly off target  Pre-planning stage. Expected completion Spring 2026.
Bourtreehill Village 2,000 25 - (8) 17 17 - On Target Slightly off target  Pre-planning stage. New completion date to be established. 
James McFarlane ASN Site 3,050 2,250 (2,150) 25 125 125 - On Target Slightly off target  Consultation stage. Expected completion Summer 2024.
James Reid ASN school 6,050 1,125 (1,005) 120 240 240 - On Target Slightly off target  Consultation stage. Expected completion Winter 2024.
Stanecastle ASN School 3,300 1,850 (1,750) (7) 93 93 - On Target Slightly off target  Consultation stage. Expected completion Summer 2024.
Fullarton Street 4,090 25 - (2) 23 23 - On Target Slightly off target  Demolition of existing flats expected to complete in Summer 2023. Expected completion 2025.
New Build Montgomerie Park 10,900 1,500 (1,450) (14) 36 36 - On Target Slightly off target  Pre-planning stage. Expected completion Winter 2026.
Glebe Place 10 50 (25) (25) - - - On Target On Target New build project deferred until 2025/26
Regeneration Project 1e 15 5 - (5) - - - On Target On Target Pre-planning stage.
Unallocated Regeneration Block 1 55 - - - - - - On Target On Target Pre-planning stage.
Laburnum Avenue (Regen 1a) 160 5 5 (10) - - - On Target On Target Pre-planning stage.
Newhouse Drive (Regen 1b) 175 5 (5) - - - - On Target On Target Pre-planning stage.
Regeneration Project 1d 360 5 - (2) 3 3 - On Target On Target Pre-planning stage.
Contingency 1,163 8,820 (8,820) - - - -
CONNEL COURT (49) 50 (1) - - - Complete Complete
GARRIER COURT (56) 57 (1) - - - Complete Complete
Harbour Street 5 5 5
Total For Council House Build Programme 67,194 35,114 (18,904) (2,812) 13,398 13,217 (181)

Page 22

Description
Approved
budget 16
February
2022
Current
budget
including
carry
forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised
Budget
2022/23
Actual Spend
to
31/03/2023
True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'001 £'000 £'000
Improvement to Existing Homes - Building Services
Window Replacement 325 364 (204) 2 162 162 - On Target On Target
Bathroom Programme 75 75 201 997 1,273 1,273 - On Target On Target
Kitchen Programme 2,610 4,450 (159) 297 4,588 2,288 (2,300) On Target Slightly off target  Additional underspend showing due to previous years underspend not required.  Previous years uncompleted units
were included in the revised business plan last year, therefore already accounted for.
Bathroom Programme Voids - - 991 (855) 136 136 - On Target On Target
Kitchen Programme Voids - - 1,145 (1,018) 127 127 - On Target On Target
Door replacement programme 2,191 2,191 (2,191) - - - - Significantly off
target
Significantly off
target
Door replacement programme - tender has been re-issued following specification review due to unviable costs. 
Balance of budget requires to be earmarked for 2023/24.
Sheltered Housing Units 8,531 8,495 (8,245) (63) 187 187 - Significantly off
target
Significantly off
target
Projection reduced due to Procurement Issues and external contractor issues - remaining budget to be carried
forward to 23/24.  Spend this financial year will only be consultants and staff costs. Construction estimated to
commence late 22/23. Tender for Barnett returned and checking quality.
Saltcoats MSF Investment 4,767 1,881 (698) 13 1,196 1,196 - On Target Significantly off
target
Additional works required.  Expected completion Summer 2023.
Total For Improvements to Existing Homes - Building Services
18,499 17,456 (9,160) (627) 7,669 5,369 (2,300)
Improvement to Existing Homes - External Contractors
Central Heating 2,524 4,442 (1,756) 132 2,818 2,176 (642) Significantly off
target
Significantly off
target
Underspend showing due to previous years underspend not required.  Previous years uncompleted units were
included in the revised business plan last year, therefore already accounted for.
Insulated Re-Rendering 421 865 1,756 (1,048) 1,573 1,573 - Significantly off
target
Significantly off
target
Budget vired from roofing & rerendering to offset additional spend in insulated render. Following contractor surverys
some wall/floor render has been reprofiled as EWI and virement approved.  The discorvery of asbestos delayed works
in to 2023/24.
Electrical Rewiring 698 1,742 - 16 1,758 264 (1,494) Significantly off
target
Significantly off
target
Underspend showing due to previous years underspend not required.  Previous years uncompleted units were
included in the revised business plan last year, therefore already accounted for. Also issues with contractor labour
shortages and no access.
Total For Improvements to Existing Homes - External
Contractors
3,643 7,049 - (900) 6,149 4,013 (2,136)
Refurbishment Schemes
Refurbishment Schemes - - - - - - -
Roofing & Rendering 4,450 5,507 - (478) 5,029 3,195 (1,834) Significantly off
target
Significantly off
target
Uncompleted units from previous years accounted for in future years. Previous years carry forward not required.
Following contractor surverys some wall/floor render has been reprofiled as EWI and virement approved.
Demolition High Flats Irvine 6,780 3,000 (2,033) (295) 672 672 - Slightly off target  Slightly off target  Tender received lower than budget estimate. Demolition contractor appointed and onsite, demolition expected to
complete in Summer/Autumn 2023.  Balance of budget requires to be earmarked for 2023/24.
Kings Arms Project 265 600 (441) (23) 136 136 - On Target Slightly off target  Tender stage.  Works are expected to commence summer/ autumn 2023.
Refurb Maress House - (12) 13 (1) - - - On Target On Target HRA contribution to the project complete.
Refurb Friars Lawn - 254 - (230) 24 24 - On Target Complete Complete - practical completion achieved during April 2023
Glebe Place Refurb (Ukraine) - 521 521 573 52
Total For Refurbishment Schemes 11,495 9,349 (2,461) (506) 6,382 4,600 (1,782)
-
Other Capital Works
Energy Efficiency Standard 5,362 5,488 (5,489) 1 - - - On Target On Target
Other Capital Works 726 712 (711) (1) - - - On Target On Target
Major Improvements 6 6 (6) - - - - On Target On Target
Parkhall & Kirkhall Asbestos - 17 - (17) - - - On Target On Target
Detection Equipment 458 1,463 (1,313) 48 198 198 - Slightly off target  Slightly off target  Contractor continuing to work through addresses, forced entries process in place / limited capacity due to staff issues
(contractors) will span 2 years.  Balance of budget to be earmarked for 2023/24.
Solar Panels 3,862 3,888 (1,813) (348) 1,727 1,727 - On Target On Target
Professional Management Charges 1,326 1,738 - (1,738) - - - On Target On Target
Estate Based Regeneration 1,287 2,190 (1,187) 384 1,387 1,387 - Slightly off target  Slightly off target  Programme currently being revised.  Balance of budget to be earmarked for 2023/24.
Nelson Street Regeneration 442 451 (426) (25) - - - Significantly off
target
Significantly off
target
Final property obtained through CPO. Feasibility exercise being undertaken.  Balance of budget to be earmarked for
2023/24.
Health and Safety Works 207 207 (207) - - - - On Target On Target
Total For Other Capital Works 13,676 16,160 (11,152) (1,696) 3,312 3,312 -
TOTAL EXPENDITURE 114,507 85,128 (41,677) (6,541) 36,910 30,511 (6,399)

Page 23

Description
Approved
budget 16
February
2022
Current
budget
including
carry
forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised
Budget
2022/23
Actual Spend
to
31/03/2023
True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'001 £'000 £'000
Sale Of Assets - - - - (5) (5)
CFCR (12,209) (12,209) - - (12,209) (12,209) -
Capital Grants (14,175) (7,138) 5,371 (1,382) (3,149) (3,149) -
Affordable Housing Contribution (1,596) (1,596) 1,046 (550) (550) -
Prudential Borrowing (85,376) (63,034) 36,306 6,297 (20,431) (14,027) 6,404
Council House Build Fund (1,151) (1,151) 580 (571) (571) -
TOTAL INCOME (114,507) (85,128) 41,677 6,541 (36,910) (30,511) 6,399
NET EXPENDITURE - - - - - - -
The following classifications have been used to highlight financial performance against budget
On Target On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)