NORTH AYRSHIRE COUNCIL 
02 May 2023 
Cabinet
Title: Lease Disposal – Lower Ground Floor, Lochshore Hub,
Glengarnock 
Purpose: To seek Cabinet approval to provide a lease of the Lower Ground
Floor of the new Lochshore Hub to Garnock Rugby Club. 
Recommendation: That Cabinet approve the lease disposal of the Lower Ground
Floor at Lochshore Hub to Garnock Rugby Club for a period of 25
years at an initial rent of £5,500 per annum, exclusive of VAT. 
1. Executive Summary 
1.1 The Lochshore Hub forms part of the first phase of development at Lochshore Park.
This was delivered using a package of funding including the Scottish Government’s
Regeneration Capital Grant Fund as noted in the previous Cabinet report of 10
November 2020 when it was agreed to transfer the site from Scottish Enterprise to
North Ayrshire Council. 
1.2 Following practical completion of the development, this report is seeking Cabinet
approval to grant a commercial lease to Garnock Rugby Club. The proposed lease will
enable the club access to the Lower Ground Floor as identified within Appendix 1. 
1.3 Having undertaken initial negotiations with Garnock Rugby Club, it is recommended that
the Council grants a commercial lease, the terms of which have been agreed in principle,
for a period of 25 years at an initial discounted rent of £5,500 per annum, exclusive of
VAT. Due to the length of proposed lease being in excess of 5 years, Cabinet approval
is required in terms of the Council’s Standing Orders. 
2. Background 
2.1 Lochshore Park is a key regeneration and Community Wealth Building project for the
Council.  It aims to bring the site of the former Glengarnock Steelworks into positive use
as an outdoor visitor destination.  Cabinet approved the transfer of the site from Scottish
Enterprise in November 2020 and received an update on the funding package for and
approach to the delivery of the first phase of the project. 
2.2 The first phase has seen the construction of the Lochshore Hub, acting as a bridge
between the outdoors and indoors to facilitate visits and longer stays.  This was delivered
through a package of funding including from the Council’s Capital Programme, Nuclear
Decommissioning Authority, Garnock Rugby Club and the Scottish Government’s
Regeneration Capital Grant Fund.   
2.3 The Ground Floor Level of the Lochshore Hub provides a café operated by the Council’s
Facilities Management Team, community rooms for hire and office space.  The Lower

Page 2

Ground Floor was designed in collaboration with Garnock Rugby Club and provides
sports changing facilities. 
2.4 Garnock Rugby Club agreed to contribute £350,000 towards the construction of
Lochshore Hub which comprised of £200,000 of Club resources, £100,000 award from
Sport Scotland and £50,000 from Scottish Rugby. Of this, £330,000 has been spent on
their required bespoke fit out of the lower ground changing room area. The remaining
£20,000 has been deemed as rent in advance over the first five years of occupation. 
2.5 The commercial rent of the subjects is valued at £9,500 per annum. Considering the
£20,000 rent in advance, a discounted rent of £5,500 per annum has been agreed for the
first 5 years. On the fifth anniversary there will be a rent review. 
2.6 The lease will be on Internal Repairing and Insuring basis with the club being liable for
all repairs, maintenance, and statutory compliances within their leased area only. 
2.7 The lease will make the club liable for 50% of costs in relation to reactive repairs, and
cleaning of the common area of the ground floor only. 
2.8 Formal subletting is not permitted; however, the lease will permit the club to undertake
hourly lets, similar to the current arrangements for community or sports groups. 
2.9 All other areas of the building will remain within Council operation with the Council liable
for any items of maintenance, repair, and statutory compliance.   
2.10 The lease will grant the tenant a right of use over the pitches. For the avoidance of doubt,
this land will still be considered open space and remain available to members of the
public. 
2.11 As stated, Garnock Rugby Club have agreed to contribute £350,000 to the construction
of this building. These funds are yet to be released. Consequently, the lease will be
subject to the funds being transferred to the Council. 
3. Proposals 
3.1 It is recommended that the Council grants a commercial lease of the Lower Ground Floor,
Lochshore Hub to Garnock Rugby Club for a period of 25 years at an initial rent of £5,500
per annum exclusive of VAT with a rent review period after 5 years. 
4. Implications/Socio-economic Duty
Financial
4.1 The proposed lease will result in the Council obtaining a rental income of £5,500 per
annum exclusive of VAT, for the initial 5-year period. 
Human Resources 
4.2 None. 
Legal 
4.3 Due to the length of lease being in excess of 5 years, Cabinet approval is required in
terms of the Council’s Standing Orders. The Legal documentation required for the
lease will be progressed via Legal Services.

Page 3

Equality/Socio-economic 
4.4 The Lochshore Hub and partnership approach to its future operation with Garnock
Rugby Club seeks to contribute to reversing economic, social and physical decline
and reducing socio-economic disadvantage within the Garnock Valley. It contributes to
tackling long-term vacant and derelict land at Lochshore thereby reducing its level and
impact on communities. It aims to build community wealth and tackle local deprivation
through the regeneration of our communities by maximising the potential of our land
and assets in partnership with the Club. 
Climate Change and Carbon 
4.5 Sustainable and energy efficient measures have been incorporated into the Hub’s
development wherever practical.   
Key Priorities 
4.6 The Lochshore Park Hub and partnership approach to its future operation with
Garnock Rugby Club aims to contribute to achieving the Council Plan priority
outcomes and will contribute to the ambitions for: active and strong communities,
good life-long health and well-being; an inclusive, growing and enterprising economy;
and for a sustainable, vibrant, welcoming and attractive environment. 
Community Wealth Building 
4.7 The Lochshore Park Hub and partnership approach to its future operation with Garnock
Rugby Club aims to contribute to Community Wealth Building by supporting equitable
land development and the development of underutilised assets for community use. 
5. Consultation 
5.1 Consultations have taken place with Economic Development and Regeneration in
arriving at the recommendation contained in this report. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact David Hammond, Head of Sustainability, Corporate
Property & Transport on 01294 324514.
Background Papers 
Cabinet Report – Lochshore Regeneration Project, 10 November 2020 
1 – Lease Plan

Page 4

Store
14.7sqm
Plant Room
37.5sqm
Car Park
ESS
Switch Room/SPEN and ICT
15sqm Rev Description Drawn Chkd. Date
Changing Room 6
37.9 m2
Main circulation Reproduced from the Ordnance Survey map with the
permission of The Controller of Her Majesty's Stationery
Office © Crown copyright and database rights 2019
Ordnance Survey 100023393
WARNING: Paper copies distort. Always check scalebar
before measuring.
Changing Room 5
37.4 m2
North Ayrshire Council
Comhairle Siorrachd Air a Tuath
Yvonne Baulk - Head of Physical Environment
Changing Room 4
37.5 m2 (t) : (01294) 324888 (e) landandproperty@north-ayrshire.gov.uk
CUNNINGHAME HOUSE , IRVINE , KA12 8EE
Property Management & Investment - Estates
Title: Property at
Lochshore
Project:
Survey:
Scale:
Temporary Occupation Licence
Glengarnock
KA14 3AW
Drawing No:
Checked:
Drawn:
1:125
AC
AC
Filename:
Type: Temporary Occupation Licence
06/10/2022Date:
OS Grid Reference:
Rev.
2022-10-06 - Garnock Rugby Club.dwg
NS326536
Sheet Size
A3
Path
(um
)
Drain
DW
DW
Drain
Changing Room 134.6 m2
CR1 Lobby
Changing Places10.6 m2PlatformLiftencased
Officials Room 5 m2
Officials Room
4.5m2
cleanersstore 2 m2
Physiotherapy/first aid 12.8 m2
Changing Room 234.3 m2
Changing Room 339.4 m2
15.2 m2
39.2 m2
W.C.W.C.
W.C.
W.C.
W.C.
W.C.