NORTH AYRSHIRE COUNCIL 
21 March 2023 
Cabinet 
Title:    Roads, Structures and Street Lighting Maintenance
Programme 2023/24 
Purpose:  To seek Cabinet approval of the proposed Roads, Structures
and Street Lighting Maintenance Programme for 2023/24. 
Recommendation:  That the Cabinet (a) notes the approach taken to determining
the asset maintenance programme for roads, structures and
street lighting; (b) approves the maintenance programme for
2023/24, as shown at Appendix 1a and 1b; (c) approves the
additional works up to the value of £1m, identified for 2023/24 at
Appendix 1c should the Council realise an underspend of £1m
or more for 2022/23 and (d) notes that the programme will be
issued to the Locality Planning Partnerships for information. 
1. Executive Summary 
1.1 North Ayrshire Council has a statutory obligation under the Roads (Scotland) Act 1984
to manage and maintain its public road network. The adopted road network within
North Ayrshire has a total length of 1044km.  The core roads assets are currently
estimated at a value of approximately £1.7billion. 
1.2 The Council’s Roads Service has adopted an asset management approach to road
maintenance to allocate available road maintenance funds to locations that will offer
the most beneficial return on the investment. 
1.3 The Roads Asset Management Plan (RAMP) and the roads assets maintenance
strategy follows the recommendations contained within the ‘Well Maintained
Highway’s Code of Practice, ensuring that the Council’s statutory obligations as
delegated Roads Authority are met. 
1.4 In complying with the Code of Practice, an effective regime of inspection, assessment
and condition recording is well established which assists in not only providing a road
network for the future but one that promotes social inclusion and contributes to
economic growth within the area. This approach also ensures the Council is providing
value for money on any investment attributed to road maintenance. 
1.5 The proposed Roads, Structures and Street Lighting Maintenance Programme
2023/24 is attached in Appendix 1a and 1b. The Programme is based on approved
Revenue and Capital budgets, including an additional £0.5m which will be funded from
approved capital infrastructure investment. At the Council’s budget setting me on 1

Page 2

March 2023 an extra (up to) £1m was agreed for roads infrastructure subject to the
Council realising an underspend for Financial Year 2022/23. Details of proposed
additional works are attached at Appendix 1c. 
2. Background 
2.1 North Ayrshire Council is responsible for the maintenance of the adopted local road
network including lighting and structures assets as well as its other non-adopted road
assets. However, the Council has no responsibility for the maintenance of the Trunk
Road Network which falls to Transport Scotland and their management contractor,
Amey. The Trunk Road network includes the A78, the A737 from Kilwinning to the
Renfrewshire Boundary and A738 from the Pennyburn Roundabout to the A737 Dalry
Road Kilwinning. 
2.2  North Ayrshire Council’s roads are the Council’s largest community asset and play a
vital role in supporting the local and wider economy by facilitating the movement of
people, goods and services and connecting people with economic and social
opportunities. 
2.3  The proposed Roads, Structures and Street Lighting Maintenance Programme for
2023/24 has been developed in accordance with the strategy contained within the
Roads Asset Management Plan (RAMP) to deliver the maximum return on investment
and ensures the provision of an effective road network throughout North Ayrshire. 
2.4  Road Condition is measured nationally through the Scottish Road Maintenance
Condition Survey (SRMCS). The measure in place, the Road Condition Index (RCI),
records the percentage of the Council’s roads which should be considered for
maintenance. North Ayrshire’s RCI has been improving in recent years and is
currently 33.9%. 
2.5 The estimated carriageway maintenance backlog figure for North Ayrshire is currently
£34.8m. The ‘steady state’ figure for maintaining our roads at present condition is
£4.3m per year. The capital budget supported by revenue funding is £4.45m for
2023/24. This includes £100,000 carried forward from 2022/23 for planned works. An
additional £0.5m has been identified from the ‘core infrastructure, property and
vehicles renewal investment’ capital budget allocation, taking the total investment in
the road network to £4.95m for 2023/24. Additionally, at the Council’s budget setting
meeting on 1 March 2023 an extra (up to) £1m was allocated to roads revenue
investment for 2023/24 should the year end outturn for 2022/23 deliver an underspend
of £1m or more.  This level of investment outpaces the ‘steady state’ figure and should
therefore contribute to an improvement in the road network condition over time.  
2.6 Road lighting condition is measured through programmes of structural and electrical
assessment and testing and is complemented through the ongoing review of age
profile and material type life expectancy. The results are categorised and recorded in
the lighting asset management database to inform a prioritised list of replacement
schemes. Lighting is allocated an annual Capital budget of £1m to address a ‘steady
state’ position of maintaining our lighting at present annualised depreciation rate. 
2.7 Bridge and retaining wall condition is also evaluated through a robust inspection
programme. General inspections are undertaken every 2 years, while an in-depth

Page 3

‘principal inspection’ is carried out every 6 years and the results of the inspections are
used to inform work programmes. The results of the inspections are input into a
Structures database which is then used to calculate an average Bridge Structure
Condition Index (BSCIav) based on the total number of assets. The BSCIav is
currently 85.79 (2021/22 figure) which is within the ‘good’ classification of 85 to 94.
This figure is a slight fall on the previous year. The allocated capital budget of
£935,000 is supported by a small amount of revenue funding giving a total of £1.07m. 
2.8  Details of how condition assessments are carried out and how roads, structures and
lighting locations are prioritised for inclusion in our maintenance programme are
provided in Appendix 2. The assessment matrix used for scoring and ranking
structures for inclusion in the Structures Maintenance Programme is attached in
Appendix 3. 
2.9 The road maintenance programme in 2022/23 mitigated high inflationary cost
increases through two factors - by forecasting higher projected costs and building this
into the programme early in the financial year and, secondly, the Ayrshire Minor Works
Framework contract price being held for the 6 months to September 2022.  Works
completed by the operational team and any works tendered since then were subject to
inflationary rises in material and plant costs as well as contractor price increases.  The
2023/24 road maintenance programme has been prepared based on a 20%
contingency increase in 2022/23 costs to allow for further inflationary rises in
operational costs and to ensure that programmed works can be completed. 
3. Proposals 
3.1 That Cabinet notes the approach taken to determining the asset maintenance
programme for roads, structures and street lighting. 
3.2  That Cabinet approves the maintenance programme for 2023/24, as shown at
Appendix 1a and 1b. 
3.3 That Cabinet approves Appendix 1c which will deliver an additional up to £1m of road
infrastructure works for 2023/24 should the year end outturn for 2022/23 realise an
underspend of £1m. 
3.4  That Cabinet notes that the programme will be issued to Locality Planning
Partnerships for information. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Roads, Structures and Street Lighting Maintenance Programme will be delivered
from allocated Capital and Revenue budgets. Estimated costs are detailed within the
appendices. 
Human Resources 
4.2 Delivery of the programme will be met from existing staff resources.

Page 4

Legal 
4.3 North Ayrshire Council has a statutory obligation to manage and maintain its public
road network under the terms of the Roads (Scotland) Act 1984. 
Equality/Socio-economic 
4.4 There are no equality implications. The maintenance programme contributes to the
Council’s socio-economic duty, as well-maintained roads are essential for the social
and economic prosperity of North Ayrshire. 
Environmental and Sustainability 
4.5 Effective programming and management of these assets will assist in reduced carbon
associated with mobilisation of unplanned reactive maintenance resources and
extends the use of assets in a cost effective and sustainable manner. 
Key Priorities 
4.6 Effective management of these assets contributes to a number of Council plan
objectives ensuring that North Ayrshire is well-connected with effective infrastructure
and that we maximise resources and provide value for money. 
Community Wealth Building 
4.7 The maintenance programme contributes to Community Wealth Building through
community benefits clauses associated with maintenance contracts. It is also the case
that a proportion of the maintenance programme is also delivered in-house by the
Roads Operations Team and Building Services. 
5. Consultation 
5.1 The maintenance programme will be shared with each Locality Partnership. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Thomas Reaney, Head of Neighbourhood
Services, on Tel: 01294 324570. 
Background Papers
0

Page 5

Mainland Roads Programme 2023/24
Appendix 1a
Carriageway Resurfacing
Street Town Location Estimate
Cost
Stanley Road /
Galloway Place
Saltcoats Carried forward from 22/23 £100,000
B706 Dunlop Road Barrmill Roundabout and exit towards A736 include
circle at McHardy Crescent
£120,000
The Strand /
Townhead
Beith Eglinton Street to Kirk Road  £65,000
B780 Kilbirnie Loadingbank towards Roundabout £140,000
Stuart Street Millport Cardiff Street to Clifton Street £180,000
Parkhouse Road Ardrossan McDowall Avenue to Garage £110,000
Sorbie Road Saltcoats Approach to Traffic Lights £55,000
Shore Road Stevenston near the level crossing £55,000
Ardeer Road Stevenston From Railway Bridge to Roundabout £140,000
Old High Road Stevenston Mayville Street to A738 £105,000
Mayville Street /
Glebe Street
Stevenston High Road to Boglemart Street £80,000
Middleton Road Irvine Part Length £150,000
East Road / High
Street
Irvine mini roundabout to Kirk Vennel  £60,000
Braehead   Dalry Braehead to speed limit signs £160,000
Netherlee Crescent Dalry Including Ryeside and Templand Road £80,000
Caledonia Road /
Argyle Road
Saltcoats Sorbie Road to Jacks Road £210,000
Main Street West Kilbride West Kilbride Parish church to Headrigg
Gardens
£75,000
Merlewood Road West Kilbride Full Length £15,000
Castlepark Gardens Fairlie Full Length £60,000
Alexander Avenue Largs Holehouse Road to Burnside Road £95,000
Brisbane Road Largs Boyd Street to Seamore Street £25,000
Waterside Street Largs Including junctions at Silverdale £80,000
Stakehill Largs Part Length £65,000
Anderson Terrace Ardrossan Part Length £60,000
Chapelhill Mount Ardrossan Part Length £100,000
Carson Drive Irvine Ayr Road to just passed Gray Crescent £60,000
Castlepark circle Irvine Leven Place to existing joint £130,000
Harbour Road Irvine Victoria Roundabout to Portland
Roundabout
£140,000
Station Road Springside Part Length £95,000
Barra Crescent /
Place / Lane
Irvine 3 cul de sacs and part of main entrance
road
£70,000
Gigha Crescent Irvine From Roundabout to end £50,000
Greenside/Mid-
rig/Chapelgill
Irvine Part Length £40,000
B778 Kilwinning South of Mossculloch to Goldcraigs Depot  £150,000
Beechwood Kilwinning Part Length £50,000
Corsehill Road Kilwinning Part Length £110,000

Page 6

Mainland Roads Programme 2023/24
Appendix 1a
Kennedy Road Saltcoats Full Length, Including West Doura Junction £114,000
Station Road Skelmorlie Part Length £30,000
Seton Terrace Skelmorlie Skelmorlie Castle Road for approx 50m £20,000
Hillview Skelmorlie Part Length £25,000
Martin Square Saltcoats Part Length £60,000
Sannox Drive Saltcoats Even side £60,000
Greenhead Avenue Stevenston Full Length £75,000
Ardchoille Drive Stevenston Full Length £20,000   
£3,684,000 
Carriageway Surface Dressing
Street Town Location Estimate Cost
B781 West Kilbride Blackshaw Farm to Gill Farm £16,000   
£16,000

Page 7

Mainland Roads Programme 2023/24
Appendix 1a
Carriageway Screeding
Street Town Location Estimate Cost
Glebe Street Saltcoats Springvale Street to Glebe Place £14,000
Lawson Drive /
Ashgrove Street
Ardrossan Lawson Drive past shops to Ashgrove £24,000
Whitlees court Ardrossan Part Length £18,000
Pollock Crescent Kilwinning Part Length £22,000
C68 Beith Junction with U42 to A736 £45,000
U42 Lugtonridge
Road
Beith South Nettlehirst and Lugtonridge £28,000
Dipple Road Kilbirnie Part Length £67,000
C99 Dalry Stoopshill to the joint before the B707 £106,000
C20 Kilwinning South Lodge cottage to Torranyard £71,000
U8 Boag Road Beith Part Length £46,000
Brownmuir farm to
boundary
Beith Full Length £17,000
Woodside Beith Woodside to boundary £22,000
Bogside Beith Part Length £50,000
Kilruskin Road West Kilbride Part Length £20,000   
£550,000

Page 8

Mainland Roads Programme 2023/24
Appendix 1a  
Footway Resurfacing
Street Town Location Estimate Cost
Thorntree Avenue  Beith Part Length  (Full Length Odd Nos, 38-56
Even Nos)
£26,000
St Margarets Avenue Dalry Kittyshaw to Houston Crescent (incl 2 cul-
de-sacs)
£50,000
North Street /
Braehead
Dalry Regal Court to Braehead Place £43,000
St Andrews Road Ardrossan Number 1 to Number 35 £28,000
Kilruskin Drive  West Kilbride Full Length £29,000
Provosts Loan Cumbrae Full Length £17,000
Braeside Ave and
Meadowbank Rd
Largs Part Lengths £36,000
Main Street Dreghorn One side only from No.108 to change in
surface
£10,000
Stronsay court Irvine Full Length £5,000
Clements Place Stevenston Full Length £9,000
Oakland Drive Stevenston Full Length £5,500
West Doura Way /
Court
Kilwinning Whitehirst Park PS to shop, including car
park and shop footpaths and the slabbed
area outside shop
£17,500
Murray Avenue Saltcoats Mid Dykes Road to road end (Both Sides) £15,000
Longfield Avenue Saltcoats Part Length £14,000
Wellpark Road Saltcoats Number 23 to Number 31 (One side only) £4,000
Kenilworth Drive Saltcoats Footpath from Kenilworth Drive to Munro
Place
£6,000
Miller Road Saltcoats Full Length £15,000   
£330,000

Page 9

Mainland Roads Programme 2023/24
Appendix 1a
Lighting Deteriorated Infrastructure Replacements
Area Town Estimate Cost
Longhill
Seton Terrace
Sandy Brae Road
Skelmorlie £90,000
Corsehill Drive West Kilbride £55,000
Lindsay Crescent
Auchenmaid Drive
Linn Avenue
The Roundel
Castlehill Drive
Largs £80,000
Tarryholme Drive
Warrix Avenue
Kirk Vennel
Parterre
Benbain Place
Golf Place
Ravenscroft
Braeside
Whyte Avenue
Irvine £205,000
Schoolwell Street
Grange Road
Kerelaw Road
Sinclair Street
Loccard Road
Limekiln Road
Stevenston £127,000
St Inans Drive 
Rowan Avenue
Bigholm Road
Backburn
Beith £70,000
Milton Road
Ladyland Drive Kilbirnie £87,000
Findlay Avenue
West End
Sharon Street
Dalry £59,000  
£773,000 
Lighting Deteriorated Column Replacements
Area Town Location Estimate Cost
Various Unplanned Locations   £169,000 
Lighting Deteriorated Column Inspections
Area Town Location Estimate Cost
Various Locations   £58,000

Page 10

Mainland Roads Programme 2023/24
Appendix 1a 
Carriageway Resurfacing:   £3,684,000
Carriageway Surface Dressing:   £16,000
Carriageway Screeding:    £550,000
Footway Resurfacing:    £330,000 
Lighting Infrastructure Replacements:  £773,000
Deteriorated Column Replacements:  £169,000
Deteriorated Column Inspections:  £58,000 
Structures Projects:    £755,000 
Overall Mainland Total:    £6,335,000 
Structures Projects
Structure Road Project Estimate Cost
Kersland Culvert B714 UV liner culvert repairs £80,000
Seven Acres Mill
Bridge 
U54 Bridge Replacement £450,000
Roughwood Bridge U12 General Repairs £30,000
Threadmill Bridge  C99 Replacement / Strengthening  £160,000
Carsehead Bridge  B714 General Repairs   £35,000   
£755,000

Page 11

Arran Roads Programme 2023/24
Appendix 1b 
Carriageway Resurfacing
Street Town Location Estimate Cost
Benlister Road Lamlash 8 Park Terrace to road end £40,000
Golf Course Road Blackwaterfoot Queenscliff to Car Park £30,000
B880 String Road Brodick Patching Various Locations £200,000
A841  3 sections between Brodick & Sannox £160,000
A841 Lochranza Patching Works - Ballarie Bridge
towards Sannox
£70,000   
£500,000 
Carriageway Surface Dressing
Street Town Location Estimate Cost
A841 Brodick
Junction B880 to slipway past Shore
Lodge £60,000
A841 Lamlash
Strathwillan Road Junction Brodick to
Glenisle Hotel £140,000   
£200,000 
Carriageway Resurfacing: £500,000
Carriageway Surface Dressing: £200,000
Structures Projects:  £180,000
Overall Arran Total:  £880,000
Structures Projects
Structure Road Project Estimate Cost
Culvert West of
Ballymeanoch  
C147 Retaining wall strengthening                  £70,000
Dougarie
Bridge             
C147 Temporary Strengthening/ Scour
repairs    
£50,000
Catacol
Bridge                
C147 Temporary Strengthening/ Scour
repairs    
£60,000   
£180,000

Page 12

Mainland Roads Programme 2023/24
Appendix 1c 
Additional Budget £1m
CARRIAGEWAYS
Street Town Location Estimate Cost
Dickson Drive  Irvine From Redburn CC to jct Dick Terrace £50,000
B7081 Annick Road Irvine Riverside Lodge to Newmoor  £57,000
Stobbs Crescent Kilwinning Part Length £40,000
Pennyburn Road Kilwinning A738 jct to Cranberry Road jct £66,000
B7049 Eglinton Road Beith From ped crossing at Main St to speed
table
£97,000
A760 Kilbirnie From Connelston to Auchencloigh Farm
Rd
£225,000
C18 Ardrossan High
Road
West Kilbride Part Lengths £36,000
Mackerston Place Largs Full Length incl Stanlane jct £67,000
Brisbane Glen Road Largs From Douglas Street to cemetery £114,000
B896 Cumbrae Patching and Screeding £80,000
Various  PATCHING CONTRACT £80,000
FOOTWAYS   
Street Town Location Estimate Cost
Sillars Meadow Irvine Full Length £64,000
Townhead Street Stevenston No.103 to Post Office £20,000
Lochlie Place Stevenston Full Length £4,000   
£1,000,000

Page 13

Appendix 2 
Condition Assessment and Prioritisation Process 
1.1 The Audit Scotland Follow-up report, Maintaining Scotlands Roads published in
August 2016 stated that Councils should use their RAMPs to establish long term
investment plans for maintaining the road network taking into acount whole-life
costing and treatment options. 
1.2 As part of the Roads Asset Management process, annual condition assessments
are carried out on the public road network as part of the inspection regime. All
locations are assessed using a risk based approach. 
1.3 Condition assessments are carried out simultaneously with the Safety 
Inspections in accordance with the pre-determined timescales contained within
our Safety Inspection Manual. All faults noted during these inspections are
logged within our electronic Routine Maintenance System (RMS). 
1.4 For carriageways, to take account of whole-life and different treatment options
the carriageway maintenance programme is developed using road asset
management principles. Lifecycle planning is at the core of this approach and
takes into account, hierarchies, condition and local community priorities.
Preventative treatments are used to prolong the life of carriageway surfaces
before their condition deteriorates and requires extensive resurfacing.   
1.5 The main factors considered are:- 
• Road Condition – based on detailed visual inspection and the Scottish Road
Maintenance Conditions Survey (SRMCS). 
• Road Hierarchy – this takes account of the strategic importance of the road
and is determined from our Local Transport Plan. 
• Assistance to Council and Community Priorities – this takes account of other
priorities such as economic development,  access to shops, amenity housing
or schools. 
1.6 Carriageways and footways are both condition assessed and scored in
accordance with the assessment table below. These condition scores, RCI data,
road hierarchy information and priorities information as above are utilised
through our electronic WDM Scheme Manager to target locations for
improvement works in order to optimise investment.

Page 14

Appendix 2 
Assessment Table   
CONDITION
Extent 1
(Acceptable)
2
(Safe but poor
appreance)
3
(Minor
deterioration)
4
(Major
deterioration)
1 - Up to 25%  5 9 13
2 – 25% to
50% 
6 10 14
3 – 50% to
75% 
7 11 15
4 – 75% to
100% 
4 8 12 16 
Each location is also reviewed at least once a year depending on its location
within the Roads Hierarchy as part of the routine inspection process. 
1.7 There are various types of surfacing materials and processes available
depending on the particular road type, location and level of existing deterioration.
Options available for treatment include preventative measures such as surface
dressing and resurfacing options such as screeding, resurfacing (inlay and
overlay), depending on the severity of deterioration full reconstruction may be
the most effective option. 
1.8 The level of investment associated with the varying treatment types identified in
the table below was established using the Society of Chief Officers of
Transportation in Scotland’s cost projection model,  developed as part of the
Roads Asset Management Planning project. The model assists with identifying
the effect of various treatments on the  on-going condition of the carriageway.
This enables a more accurate design life for the treatments currently available to
be developed and ensuring value for money on their use.   Costs for works can
vary from the figures below depending on restricted working arrangements, traffic
management required and the extent of preparatory works necessary to enable
resurfacing.  There is also an additional uplift for island working of up to 50% for
works on Arran and Cumbrae.

Page 15

Appendix 2 
Treatment Option Table 
Treatment Option Cost per Sqm
2021/22
Cost per Sqm
2022/23
%
Change
Extension to life
Surface Dressing £3.30 £3.60 +9% Up to 10 years
Screeding £9.00 £11.50 +28% 5 – 10 years
Inlay HRA £18.00 £22.00 +22% Up to 20 years
Overlay <100mm £20.70 £26.50 +28% Up to 20 years
Inlay 100mm £27.26 £32.30 +18% Up to 20 years
Reconstruction 
300mm
£112.40 £140.00 +25% Up to 20 years 
1.9 Street Lighting column replacement is prioritised through non-destructive
strength testing to determine the level of deterioration associated with the
columns. Following testing, columns are categorised within the Asset
Management database for road lighting. 
1.10 Testing is carried out in accordance with the Institute of Lighting Engineer's
Technical Report No.22 Managing a Vital Asset: Lighting Supports as well as UK
Lighting Board Code of Practice: Well-lit Highways. 
1.11 Once results are input, the database then compares these results against the
more general age profile to determine a final list of priority repairs. This produces
recommendations in order of priority for both individual units and whole streets
or areas. 
1.12 Recommendations are generally categorised as Category A through K as
follows: 
A:  Immediate replacement 
B:  Replace urgently or reinspect within 6 months 
C1: Column Material failure, replace as soon as possible or reinspect within
1 year 
C2: Bracket failure, sleeve where possible or replace unit within 1 year 
D:  Foundation failure, realign, reinstate and reinspect within 6 months 
E: Material approaching failure, replace as part of planned maintenance
programme or reinspect within 2 years 
F:  Material approaching failure, replace as part of planned maintenance
programme or reinspect within 5 years

Page 16

Appendix 2 
G:  Condition reasonable, but age expired and certified insured  for 2 year
periods until replaced 
H:  Condition reasonable, but age expired and certified insured  for 5 year
periods until replaced 
I:  Acceptable condition but age expired and insured for 5 years  periods
until replaced. 
J:  Sound condition but age expired & visually poor (evidence of concrete
cracking etc.) 
K:  Sound condition and not age expired – no current requirement for strength
structural inspection, visual only at planned maintenance cycle. 
1.13 Where non-urgent replacement recommendations (Category F through to J) are
on an individual column basis, the data is further analysed to determine a
percentage value for recommended replacement numbers against the balance
of units in a street. If this figure exceeds 30% then the entire street will be
considered for higher prioritisation which will address the design class standard
of the street beyond individual replacement for safety reasons only. 
1.14 The structures programme is identified based on the structures prioritisation
matrix which ranks assets based on a number of factors including its condition,
safety, and usage.

Page 17

Structure Name: Enter score based on the description in the following coloured cells
Date when the scoring is carried out:
Priority Ranking for structure capital programme Structure Net score % of
Maximum Score total Score
No. Factors Score Input
1
Type of Bridge 1 Score 1 if road bridge and 0
if foot bridge
Culverts, Subways which carry road shall be
considered as road bridge as per this scoring system.
Structures which carry only pedestrians, cyclists and
equestrians shall be considered as footbridge.
NA
2 Route Factor 40 Score based on NAC route hierachy Route hierachy 0 0%
Cat 2 - SPT/ NAC strategic routes - 40
Cat 3a - Main distributor routes - 30
Cat 3b - secondary distributor routes - 20
Any other category - 10
Routes serving fewer than 5 properties - 5
3 HGV Restriction 60 Score based on weight capacity Weight restriction 0 0%
factor 3 tonnes - 60
7.5 to 13 tonnes tonnes - 50
18 tonnes - 40                 
26 tonnes - 30
No weight restriction - 0
4 Condition factor 10 Score based on the condition of the
bridge
Sliding score based on 0 for very good condition to
10 for poor condition. (10 - (BCI crit/ 10)) 0 0%
5
Deterioration
factor
10 Score based on the rate of
deterioration of the structure
Sliding score based on 0 for very slow deterioration
to 10 for rapid deterioration 0 0%
6
Pedestrian
factor
20 Score based on pedestrian usage.
Bridges with footways of heavy
pedestrian usage shall score a
maximum of 30.
Structures with footways in heavily used urban areas
score 20. Score 20 if route is access to a school or
railway station. Apply a sliding scale going down to 0
for rural structures without footways.
0 0%
7
Flooding factor 40 Score based on the potential for the
existing structure to contrubute to
flooding
A structure that makes no contribution to flooding
risk will score 0. Structures that are know to increase
the risk of flooding due to restrictions in width or
soffit height will score 30.
0 0%
8
Scour factor 60 Score based on risk of collapse due
to expose to scour in heavy flow
conditions
Risk of collapse of structure due to scouring.
Structures which have been deterioted severely
because of inadequate scour protection and on verge
of collapse score maximum. Scour risk based on a
sliding scale.
0 0%
9
Parapet Condition
Factor
15 Score based on the condition of the
parapets
Structures with substandard Parapets with poor
conditon will score 15 . Structures with substandard
parapets with a 'monitor only' recommendation will
score 10. Structures which have parapets to current
standards will score 0.
0 0%
10
Parapet Risk
Factor
10 Score based on risk  in the event of a
parapet collapse leading to high risk
injuries and human casualties.
What is the likelihood of severe injury or even death
while the parapet is open to use considering the
condition of the structure. Risk based on a sliding
scale.
-5 100%
Structure Name:
Additional commentry

Page 18

11
Delay factor 10 Score based on whether existing
restrictions such as limited width
cause delays at the structure
Structures where delays are caused by width, weight,
height or other restrictions such as traffic lights will
be given a score higher than zero. Delays less then 2
minutes at peak times will score 5 and longer than 2
minutes will score 10. Score maximum if fire station,
railway station or hospital affected by delay.
0 0%
12
Structure Risk
factor
10 Score based on risk  in the event of a
Structure collapse leading to high
risk injuries and human casualties.
What is the likelihood of someone getting a high risk
injury or even death while the structure is open to
use considering the condition of the structure. Risk
based on a sliding scale.
0 0%
13
Maintenance
factor
20 Score based on maintenance
required to keep the existing
structure open.
Score based on known maintenance history and
requirement. No maintenance requirement will score
0. Listed structures score 15.
0 0%
14
Diversion factor 10 Score based on the length of the
diversion route if the structure is
closed in an unplanned manner with
no finite time limit.
Score based on diversion length. Any diversion equal
to or more than 20 miles scores 20. Score 1 for each
2 miles of diversion up to 20. Score 10 if a road
closure adversly affects a fire or railway station or
hospital. Score 10 if there is no alternative diversion.
0 0%
-5
Note maximum score that can be achieved for road bridge= 500
Priority level Chart Structure Name:
Date of Scoring: 00-Jan-00
Priority Level Indicator Overall works (500) Structure works (100) Parapet works (70) Scour Protection (60)
Level Score Level Score Level Score Level Score
No Action Rquired       
Low Priority       
Medium Priority       
High Priority       
Immediate action required       
Note : Works are divided above into three sub categories as each work can be independent and
each has its own significance in terms of attention required.