NORTH AYRSHIRE COUNCIL 
21 March 2023 
Cabinet 
Title:    Strategic Risk Register 2023/24 
Purpose:  To seek Cabinet approval of the Strategic Risk Register for
2023/24. 
Recommendation:  That Cabinet approves the Council’s Strategic Risk Register for
2023/24. 
1. Executive Summary 
1.1 The Strategic Risk Register has been reviewed and updated for 2023/24. 
1.2 It is recommended that 7 of the 8 previous risks remain on the Strategic Risk Register
at their existing risk scores and titles – Financial Environment, Inequalities, Cyber
Security, Transformation, Climate Change, Financial Sustainability of the Health and
Social Care Partnership, and Community Capacity Building & Empowerment. 
1.3 A previous risk relating to the Operating Environment of the Council post-COVID has
been removed from the register. This risk had previously been included to take
account of the challenges of recovery and the uncertain operating environment. These
risks are captured fully within other specific risks within the register which will lead to
improved management of those risk mitigation actions. 
1.4 A new strategic risk has been added relating to the implementation of the National
Care Service, and the potential impact on the Council’s resources. 
2. Background 
2.1 North Ayrshire Council is committed to ensuring that it is proactive in identifying and
managing the risks impacting on the authority. The Council recognises that a certain
amount of risk is inevitable if the organisation is to achieve its objectives. 
2.2 The aim of risk management is to reduce the likelihood and/or impact of risk by
identifying and controlling risks to the Council.  If risk is to be managed appropriately,
and Services are aware of these risks, risk management can contribute positively
towards the organisation's decision-making processes, making the Council more
innovative and effective in its approach to service delivery.

Page 2

2.3 The most significant risks are identified through the Council's Strategic Risk Register,
recognising the challenges facing the Council and demonstrating the arrangements in
place to manage these risks. 
2.4 The Strategic Risk Register has been reviewed and updated for 2023/24 and is
attached at Appendix 1 to this report.  For each of the risks detailed within the register
a number of components are identified: 
• Risk proximity factors.
• Risk score.
• Potential effect on the Council's priorities.
• Internal controls currently in place.
• Assessment of controls, and
• Additional actions identified. 
2.5 To assist in the assessment of each risk, the Council’s agreed risk matrix was used to
ensure consistency. This is used to assess the likelihood of occurrence (on a scale
from 1 to 5) and the significance of the impact of the risk should it occur (on a scale
from 1 to 5). The risk score is the product of likelihood multiplied by impact. Only those
risks rated as high or very high (10 or above) will feature on the SRR to ensure a
focus on managing the most significant risks. 
2.6 Seven risks remain on the Strategic Risk Register at their existing risk scores –
Financial Environment, Inequalities, Cyber Security, Financial Sustainability of the
Health and Social Care Partnership, Transformation, Climate Change and Community
Capacity Building and Empowerment. 
2.7 An additional risk has been captured within the Strategic Risk Register around the
implementation of the National Care Service.  The risk reflects that this is one of the
most significant reorganisations for local government since 1996, and there is
uncertainty over the scope of the National Care Service which could result in tight
timescales and significant resource pressures for implementation. 
2.8 The risk included in the 2022/23 strategic risk register around the Operating
Environment as the Council recovered from COVID-19 has now been removed.  This
reflected a number of challenging emerging risks at the time including recovery, living
with COVID, inflationary impacts, cost of living, and supply chain/construction inflation. 
Risks which remain relevant for 2023/24 are still included within the register but
captured within the specific risks relevant to these challenges, primarily Financial
Environment. 
2.9 Very High Risks  
• Financial Environment – this risk reflects the ongoing financial challenge faced
by the Council (risk score 20).
• Inequalities – this highlights the socio-economic inequalities faced in North
Ayrshire (risk score 20).
• National Care Service – this risk reflects the challenges and uncertainty the
Council faces with a major reorganisation of one of its most significant and
important functions (risk score 20).

Page 3

High Risks 
• Cyber Security – this reflects the ongoing risk from external cyber-attack which
is being faced by all organisations (risk score 16).
• Transformation – this reflects the wider risks associated with delivering the
current Transformation Programme and developing a pipeline of future initiatives
(risk score 16).
• Climate Change – this risk has been on the Strategic Risk Register following the
declaration by the Council of a Climate Change Emergency during 2019 (risk
score 16).
• Financial Sustainability of the Health and Social Care Partnership – this
reflects the ongoing financial challenges faced by the Partnership and the risk
these present to the Council (risk score 12).
• Community Capacity Building and Empowerment – this highlights the
challenges associated with community empowerment (risk score 12). 
2.10 Council services have identified high level strategic actions within their planning for
2023/24 to help the Council mitigate against its strategic risks. These actions are
detailed in summary format in the Risk Management Action Plans following each Risk
within Appendix 1.  These actions will assist with performance monitoring and
reporting on the strategic risks. 
2.11 The Council’s Internal Audit Plan 2023/24 is scheduled to be approved at the Audit
and Scrutiny Committee on 28 March 2023 and is risk-based with clear links in place
between the audit plan and key risks the Council faces. 
3. Proposals 
3.1 Cabinet is requested to approve the Strategic Risk Register 2023/24. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Council continues to have a robust long- and medium-term financial planning
framework. Key strands include development of key transformation themes and the
establishment of an Investment Fund that will generate future savings alongside
delivery of a number of key Council priorities. 
Human Resources 
4.2 None. 
Legal 
4.3 None.

Page 4

Equality/Socio-economic 
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current control
measures fall into two categories - measures to address the root causes of socio-
economic inequalities - income through employment or benefits – and mitigation
measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to help
mitigate the risk of flooding is included within the Capital Plan. The Council is
undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the
Council’s strategic priorities in the Council Plan 2019-2024. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 The Strategic Risk Register has been reviewed in consultation with the Executive
Leadership Team and the Corporate Risk Management Group. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Laura Miller, Senior Manager (Audit, Fraud, Safety
and Insurance), on 01294-324524. 
Background Papers
None.

Page 5

Appendix 1 - Strategic Risk Report 2023/24
Risk Code SRR2324_R01 Risk Title Financial Environment Latest Note Date 25-Jan-2023
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from Scottish
Government to local government will require the Council
to take increasingly difficult and challenging decisions,
potentially operating with increased levels of risk to
ensure service delivery and investment in assets align
with available resources. The 2023/24 local government
settlement represents an increase of 0.33% in core
grant funding, this has to continue to be looked at within
the context of financial pressures facing the council
including pay, significant inflationary, contractual and
demographic pressures over the short, medium and
long term.
Additional challenges are being faced where Scottish
Government is ringfencing increasing areas of the
budget settlement, and this is further exacerbated by the
inclusion of some elements of the 2023/24 budget being
conditional on certain criteria being met.
The Budget gap for 2023/24 sits at £10.3m. The gap for
24/25 is estimated at £17m. The continuation of single
year settlements makes effective medium and long term
financial planning challenging. It is recommended that
following the settlement and within the wider financial
pressure context, the risk score remains unchanged at
this time. Any consideration to change this will only
occur following a sustained period of annual growth in
core revenue funding, however, this will also have to be
considered within the context of inflation and the
resultant cost pressures.
The Council is exposed to financial risk as a result of
underlying cost pressures within the IJB; more detail on
this is set out at risk SRR03.  
Funding not keeping pace with
demand and inflationary cost
pressures means that there will
be a reduction in some service
areas potentially resulting in
higher risks for service users.
The future delivery of balanced
budgets will become
increasingly challenging.   
Robust monitoring of the Council’s revenue and capital budgets is in
place as well as regular reporting of financial performance of the IJB
to Cabinet and Audit and Scrutiny. 
To assist financial planning The Long Term Financial Outlook (LTFO)
to 2030/31 was approved at Council on 16 December 2020 - this is
the cornerstone of the Council's financial planning in the medium to
long term. 
The Council approved a balanced budget for 2022/23 on 2 March
2022. A range of additional finance pressures have been identified
including additional national insurance contributions, energy cost
inflation, contractual commitments as well as significant construction
inflation coming through the capital programme. To help mitigate the
impact of cost pressures in 2022/23 the Cabinet report dated 7 June
2022 included the earmarking of funds:-
• Contribution to the Loans Fund to support the 10 year Capital
Investment Programme and address rising cost pressures, £2.569m; 
• Provision for contractual electricity and gas price increases for
2022/23 to reflect current market inflationary levels, £1.066m; 
• Provision for additional non-contractual inflationary pressures (e.g.
food costs, fuel, etc.), £0.822m
Further, due to the creation of IJB unearmarked reserves, an
acceleration of early repayment of IJB debt owed to the Council will
be actioned during 2022/23, therefore releasing resources to help
address the £10.3m Budget gap for 2023/24. Finally, the Budget for
2023/24 was approved at Council on 1st March 2023. The budget
included savings of £5m, a 5% increase in council tax and use of
reserves totalling £3.5m. The indicative gap for 24/25 is over £17m
with use of reserves planned at £5m. This will continue to present
significant challenges to the Council.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 20

Page 6

Strategic Risk Action Plan Date Updated 25-Jan-2023
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Regular financial monitoring of Revenue and
Capital Budgets  
25 January 2023: 
Bi-monthly monitoring  
31-Mar-2024 Mark Boyd 
Deliver balanced Budget for 2023/24 and
outline Medium Term Financial Plan
1 March 2023:
23/24 Budget approved 1 March 2023
01-Mar-2023 Mark Boyd 
Maintain Financial Governance
Arrangements for IJB  
25 January 2023:
Bi-monthly monitoring.  
31-Mar-2024 Mark Boyd 
Progress dialogue via COSLA with Scottish
Government on a range of areas including
fair funding, multi-year settlements,
reduction in levels of ring-fenced resources,
true costs of SG policy areas, financial
flexibilities and a New Deal partnership with
SG and local Govt
25 January 2023:
Regular engagement through Directors of finance group
31-Mar-2024 Mark Boyd

Page 7

Risk Code SRR2324_R02 Risk Title Inequalities Latest Note Date 25-Jan-2023
Risk Owner Audrey Sutton/Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and in
particular certain excluded groups, will
experience increasing levels of poverty
and its effects, as a result both of the
economic situation and Covid-19. 
Health inequality is closely linked to
poverty, employment and people's
earliest experiences as children, and will
increase. 
The population of North Ayrshire is
projected to fall over the next 10 years
but there will also be a larger proportion
of the population considered dependent
(not economically active).  
The impact on specific risk groups is
greatest for our children, young people
and families, unemployed people and
those in in-work poverty and people
exposed to the risks of drug and alcohol
addiction. 
Demand for HSCP and Council Services
will increase. 
As reductions in resources increase,
early intervention and prevention
activities are at risk, thus increasing the
potential for an increase in costly crisis
interventions. 
The local economy will be impacted by
reduced spending power by
economically inactive residents.  
The HSCP re-affirmed its commitment to Tackling Inequalities by
continuing to consider it a key priority with the Partnership’s Strategic
Plan.
Through the HSCP strategic plan, the Partnership sets out actions to
tackle inequality through its Partnership Pledge and across its strategic
priorities. Tackling inequalities is addressed across HSCP service
areas. An example of actions to help address local inequalities include:
Establishing the Money Matters service in 9 GP practices and 7 local
schools in the more deprived areas of North Ayrshire. This will improve
accessibility of the service to those who would benefit most.
Increase the number of employability mentors in Justice Services, to
support those with experience of the justice service into meaningful
employment or training opportunities and to help divert away from
criminal behaviours.
Working closely with Housing colleagues to ensure formerly looked
after young people can access a positive and stable housing
destination.
In our Drug and Alcohol Services, we are implementing actions to
reduce the number of local drug and alcohol related harms and deaths.
This includes implementing the national MAT (Medicated Assisted
Treatment) standards and increasing the number of ABIs (Alcohol Brief
Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased
approach to improve local primary care premises (GP Practices and
Health Centres). This will improve overall professional capacity within
GP practices for Multi-Disciplinary Teams, ensuring the right support is
available for local people with health concerns.
5 4
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Stable 20

Page 8

Strategic Risk Action Plan Date Updated 25-Jan-2023 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
The Communities and Education Directorate considers reducing inequalities to be at the heart of its work. 
The Directorate leads the Community Planning Partnership for the Council and the CPP has recently developed a
new Local Outcomes Improvement Plan, the purpose of which is reducing inequalities. The themes are Wellbeing,
Work and World. Locality Planning priorities and CIF funded initiatives are also focused on a range of inequalities,
including poverty, age-related inequalities and digital inequalities.
The Directorate also leads the work of the Child Poverty and Cost of Living Board, chaired by the Council Leader.
The four strategic themes of the Board to date have been:
• No Wrong Door – access to services
• Employability
• Food
• Islands 
Progress has been made with partners through a series on mini-enquiries, ensuring that lived experience
influences developments and actions. 
The commitment to reducing inequalities is also reflected in the Communities and Education Directorate plans: 
• the Educational Service Improvement Plan
• Connected Communities strategic plans and
• Facilities Management plans.
Examples of actions to reduce inequalities:
• Deployment of Scottish Attainment Challenge funding to reduce the poverty related attainment gap in
schools
• Use of the Pupil Equity Fund to ensure equity of pupil experience in schools, at the discretion of head
teachers
• Cost of the School Day actions to reduce, for example, the cost of school uniforms and clothing, food and
outings
• Support for care experienced young people, both in schools and through youth services
• The Fairer Food Network, with 14 community larders which support the needs of individual communities
• A network of warm spaces and events to mitigate energy use and social isolation
• Work to support “New Scots,” in schools, with families and in community settings through language support
and capacity building, including women’s groups
• LGBT support groups for young people and those over 18
• Mentoring support for young people in secondary schools through a partnership with MCR Pathways
• Participation strategies for children young people and adults to ensure our strategies and investment are
informed by as wide a range of view as possible.
25 January 2023:
Each of these strategies, taken
together, and further developed
and implemented, should make
a significant contribution to
inequalities. 
Actions are being progressed
and remain within the Target
date for completion.
31-Mar-2024 Audrey Sutton;
Caroline Cameron

Page 9

Risk Code SRR2324_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 23-Jan-2023 
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Uncertainty of future funding against growing
demand and demographic pressures.
Resources have not kept pace with the demand for
and cost of social care services. The budget
settlement for 23-24 is extremely challenging with a
gap of around £7.5m across the IJB.
There remains uncertainty around Covid-related
costs with no additional funding for these beyond
the end of 22-23.
In earlier years, the HSCP did not manage to
contain spend within the delegated budget, but
surpluses were achieved in 20-21 and 21-22.
Current projections are that the Partnership will also
achieve a small surplus in 22-23.
Outstanding debt to the Council is currently
£2.321m but it is planned to clear the debt by the
end of the 22-23 financial year.
Current Scottish Government proposals to introduce
a National Care Service (NCS) by 2026 will
significantly impact on the IJB.
Significant inflationary pressures across employee
pay and contractual costs will increase the financial
challenges for the Partnership.
Low-volume high-cost care packages continue to
present a financial challenge to the Partnership.
Funding levels could result in savings being
made that are not in alignment with the
strategic plan. This could impact on the future
demand levels e.g. reduction in early
intervention and prevention means that future
demand is increased. 
Funding levels increase the requirement to
transform services at scale and pace.
The impact of the National Care Service will
become clearer as legislation is progressed.
The IJB actively monitors the financial position with
regular detailed reporting. Directors of Finance of the
Council and Health Board have oversight and regular
updates are provided to the Council's Cabinet.
There is an integrated approach to managing the
totality of NHS and Council resources delegated to
the IJB. The Medium Term Financial Outlook will be
refreshed for 2023-26 and presented to the IJB in
March 2023. Previous financial settlements have
seen both partners meet the Scottish Government
settlement conditions with any additional resources
passed to the IJB.
The IJB had uncommitted financial reserves of
£7.248m at the beginning of April 2022, which
equated to around 2.6% of the budget. This is
towards the lower end of the good practice target of
2%-4%.
Significant funding has been provided to IJBs for the
Covid-19 response, supported by regular financial
returns to the Scottish Government. Costs were fully
funded in 20/21, 21/22 and 22/23. 
The Partnership has a Transformation Board
overseeing the programme of service re-design.
3 4
Status Risk Score
Heat Map 
Change in Score Approach
Remain at 12 Tolerate
Stable 12

Page 10

Strategic Risk Action Plan Date Updated 23-Jan-2023 
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Budget Monitoring - Regular budget
monitoring reports to IJB are effective.  
23 January 2023:
No additional actions planned at this time but will keep under review
31-Mar-2024
Caroline Cameron;
Paul Doak 
Corrective Action – Transformation Board is
effective  
23 January 2023:
No additional actions planned at this time but will keep under review.
31-Mar-2024
Caroline Cameron;
Paul Doak

Page 11

Risk Code SRR2324_R04 Risk Title Cyber Security Latest Note Date 19-Jan-2023 
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business
operations or a data breach orchestrated via
either digital channels or the IT
infrastructure. This can include targeting of
the user base. Risk derives from both
Council operations and those of its supply
chain. 
The increasing importance of delivering
services through digital channels and
maximising efficiency through effective and
secure use of technology. This includes a
growing adoption of cloud-based computing
resources which extend processing
capabilities, and associated risks, beyond
the Council’s network. 
The response to the Covid-19 pandemic
resulted in the remote and mobile working
by staff as effectively being the normal
working practice. This is likely to continue as
a hybrid approach becomes the new normal. 
Such a distributed work force increases the
complexity of protecting against cyber and
data protection risks.  
Failure by Services to adopt and comply
with strategies, policies and procedures
may result in a failure to adequately ensure
the desired levels of cyber-security required
to maintain and protect council systems and
data. 
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a
loss of public confidence and significant
financial loss incurred through fines and
service disruption. 
A successful cyber-attack (malicious
external or internal action) on the Council’s
IT environments could also result in
significant service disruption, loss of income
streams and possible data loss/exposure. 
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).  
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system. 
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council maintains a comprehensive set of
policies, standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 12

Strategic Risk Action Plan Date Updated 19-Jan-2023
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Incident Detection and Response – Recent
cyber-attacks on public sector organisations
highlight the need for robust incident
detection and response procedures and
technologies. The current response
procedures been shown to be effective
based on incidents experienced so far,
however detection capabilities will need to
be reviewed and improved.  
19 January 2023:
In progress – A joint procurement of a Managed Security Operation
Centre (SOC) service with other local authorities is being taken
forward by the Digital Office.  The procurement was expected to be
completed December 2022 however the Digital Office recruitment of a
new chief information security officer (CISO) has delayed this.
31-Mar-2024 Fiona Walker 
19 January 2023:
In progress – Work is ongoing to implement a security information
and event management (SIEM) solution to allow log collection and
detection by a SOC. A proof of concept (POC) is planned with a
potential SOC provider to advance the SIEM implementation.
Procurement of a SOC will also help to complete this action.
31-Mar-2024 Fiona Walker 
19 January 2023:
In progress – The investigation of potential options and quotes is still
underway with Aon.  The risk assessment is complete and will now be
used in discussions to establish whether it is possible to broker for
quotes.  
31-Mar-2024 Fiona Walker 
Training and Awareness – The pandemic
has impacted on the cyber training
programme with the long-term cancellation
of all classroom-based training. However, a
new online course was launched to
compensate for this.  
19 January 2023:
In progress – Face to face training has resumed with sessions being
organised to tackle the backlog caused by the pandemic. Phishing
simulations have also been restarted and will continue to be ran to
test the effectiveness of training and raise awareness.
Ongoing Fiona Walker

Page 13

Risk Code SRR2324_R05 Risk Title Transformation Latest Note Date 25-Jan-2023
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
There is an overarching risk that
transformation and change management
activities, which are core to the future
delivery models and long-term financial
sustainability of both the Council and Health
and Social Care Partnership, fail to deliver.  
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2019-24 and the
Local Outcome Improvement Plan (LOIP). 
Failure to deliver the HSCP Transformation
programmes across the Partnership,
involving North Ayrshire Council (NAC) and
NHS Ayrshire & Arran (NHSAA) services
may lead to the identified outcomes not
being delivered; resulting in financial
instability, reduced performance,
deteriorating patient outcomes, and
reputational damage within North Ayrshire
Health and Social Care Partnership
(NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in building
future workforce capacity and in ensuring
we have an engaged, skilled and
knowledgeable workforce to meet service
demand.  
The transformation programme aligns to the Council Plan and is
monitored via the Transformation Board.
Workstreams have been developed across Transport and Travel,
Accessing our Council, Land and Property and Sustainability. 
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. IJB approved budget and Strategic
Plan for 2022-23 which align with financial plans with transformational
strategic change ambitions.
Cultural transformation activities continue to evolve to support the
Council’s transformation and improve effectiveness and capability.
This includes sharing learning and skills, engagement, design
experiments and a whole systems approach to transformation and
change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills and
capabilities, are planned. Each Head of Service has a workforce plan,
and these are monitored six-monthly with continued HR support and
guidance to ensure service review and redesign of the workforce is on
track. 
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 14

Strategic Risk Action Plan Date Updated 25-Jan-2023
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Existing project level governance and
controls remain effective and are constantly
reviewed. 
25 January 2023:
Progress on Transformation projects continues to be governed and
monitored via the Transformation Board which is chaired by the
Chief Executive. Meeting at the end of March will consider the next
phase of projects required for delivery to address the significant
financial challenges in 2024/25
Quarterly Mark Boyd / Chief Executive
and Executive Directors

Page 15

Risk Code SRR2324_R06 Risk Title Climate Change Latest Note Date 24-Jan-2023
Risk Owner David Hammond
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rises and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms. 
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding. 
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences. 
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.  
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands on
services, often with little notice. 
Risk to life, transport disruption and
pollution to the local environment, as well as
impact adversely on the local economy if
businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and identify
actions to increase resilience to climate
change.  
North Ayrshire Council declared a Climate Emergency in June 2019,
committing to act on climate change and reduce carbon emissions.
In January 2020 the Council approved the target to become net-zero
carbon by 2030, for both Council estate emissions and area-wide
emissions.
The third iteration of the Environmental Sustainability & Climate
Change Strategy was approved by Cabinet in May 2021, providing a
road map to achieve the net zero carbon emissions by 2030 target. 
Climate Change Adaptation has been included as a workstream
within the new strategy, utilising Adaptation Scotland’s Capability
Framework to ensure North Ayrshire takes a strong, proactive
approach to adapting to climate change.  Officers are participating in
the Sustainable Scotland Network’s ‘Adaptation Scotland
Benchmarking Group’ to learn and share best practice with other
local authorities.
The Flood Risk Management Strategy has been developed into a 6-
year plan which began in 2016. A second plan, which will follow on,
is in development. 
In addition, actions to mitigate Climate Change risk are held within
strategies such as the Core Paths Plan, Outdoor Access Strategy,
Local Biodiversity Action Plan, and Weather and Winter
Emergencies Plan. Asset management plans are in place which are
regularly reviewed for our Roads, Fleet, Housing, Property and Open
Spaces. 
Furthermore, through the Ayrshire Civil Contingencies Team there
are emergency planning arrangements in place in the event of
severe weather and flooding conditions causing major disruption and
damage to the area or to individual communities within it. 
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 16

Strategic Risk Action Plan Date Updated 24-Jan-2023
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate Emergency in June 2019, committing to
act on climate change and reduce carbon emissions. In January 2020 the Council
approved the target to become net-zero carbon by 2030, for both Council estate
emissions and area-wide emissions.
The Council has taken action against climate change since our first Carbon
Management Plan in 2006/07, by working to reduce emissions associated with
Council services, and using the baseline year of 2005/06 from which to measure
progress.
Since the baseline year of 2005/06, Council estate emissions have reduced by
67.8%, from 67,719 tonnes of carbon dioxide equivalent (tCO2e) to 21,794 tCO2e (a
reduction of 1,052 tCO2e from the previous year). Area-wide emissions are published
by BEIS two years in arrears. Total emissions have reduced across North Ayrshire by
49%, from 1,437 kilotonnes of carbon dioxide (ktCO2) in 2005 to 730 ktCO2 in 2020.
To ensure North Ayrshire Council can develop a leading, cross-sector and community
led approach we established a Climate Change Steering Group (CCSG) in 2021. The
CCSG is chaired by the Cabinet Member for Economy and Climate Change and
brings together young people, local businesses and community organisations from
across North Ayrshire.
Existing controls remain effective and are under review as our response to climate
change develops and we progress towards achieving net zero by the 2030 target.
24 January 2023:
Continuing the Implementation of the 3rd Environmental Sustainability
& Climate Change Strategy, which Includes a Roadmap with actions
towards achieving the target. The ESCCS 3 contains workstreams: 
• Affordable Warmth 
• Green Economy 
• Transport and Travel 
• Natural Environment 
• Sustainable Operations 
• Carbon Absorption 
• Climate Change Adaptation, which follows Adaptation Scotland’s
Capability Framework, to build a climate resilient North Ayrshire. 
Across seven thematic workstreams (Affordable Warmth, A Green
Economy, Transport & Travel, Natural Environment, Sustainable
Operations, Carbon Absorption and Climate Change Adaptation), 65
actions have been identified and progressed over the course of the
ESCCS 3 period. Updates on progress are provided through the
Council’s performance reporting system, Pentana, on a quarterly
basis. These actions are designed to be directly and indirectly
responsible for carbon reduction and deliver other socio-economic
benefits.
Officers started preparation of 4th Environmental Sustainability &
Climate Change Strategy.
31-Mar-2023 David
Hammond 
Flood Risk Management Plan:
Cycle 2 of the Ayrshire Local Flood Risk Management Plan has been developed and
published on 31st December 2022.
Studies and modelling will be undertaken to identify and prioritise vulnerable areas
where financial damage and risk to life are most likely.
There is an ongoing programme of monthly inspections of debris screens which have
been installed to prevent vulnerable culverts from blocking and causing flooding.
CCTV inspections of culverts are also undertaken to identify blockages and
deterioration of assets that might cause flooding. This has been effective in reducing
flooding, although there are capacity issues which this process cannot address.
The Upper Garnock Valley FPS has been substantially completed and is currently
providing flood protection.
24 January 2023:
We will undertake the actions outlined in cycle 2 of the Ayrshire Local
Flood Risk Management Plan. We will continue to look for
opportunities to implement Natural Flood Management and we will
develop a range of further flood protection measures which can be
put forward as schemes for inclusion in cycle 3 of the ALFRMP.
We will complete the Millport Coastal FPS and the Mill Burn FPS.
Inspections and CCTV surveys of culverts and screens will continue,
including prioritised maintenance. Efforts will be made to continue to
identify unknown culverts and add them to the ongoing inspection and
maintenance process.
30-06-2028 Thomas
Reaney

Page 17

Risk Code SRR2324_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date 20-Jan-2023
Risk Owner Rhonda Leith
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for implementation of
aspects of legislation of the Community
Empowerment Act (Scotland) 2015, such as
Community Asset Transfer. 
Pressure to support community capacity
building and the variation of needs within a
reducing workforce. 
Duplication of effort across HSCP and
Locality Partnerships to foster community
participation and deliver engagement
activities.
Complying with the complex consultation
legislation in service redesign.  
Rising energy and utility costs relating to
property management.
Budget savings and pressure on property
maintenance budgets.
Where the risk is not managed effectively
the potential benefits of community capacity
building and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda
are high and those with less social capital
where interest remains low, which
constrains the ability to influence the
planning and delivery service. 
Any disconnect between the Council’s
aspirations, community appetite for
increasing ownership of assets and what
communities themselves feel able and
prepared to commit to can result in
community assets reverting back to Council. 
Accelerating asset transfer risks losing
services and facilities. 
Over-engagement carries disengagement
and engagement fatigue.  
Increased property costs can be a deterrent
for organisations engaging and completing
the CAT process.
Lack of budget to undertake proactive
maintenance may result in NAC buildings
falling into disrepair detracting organisations
from progressing to lease and or ownership
of NAC assets.
Ongoing commitment to community empowerment
and locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements. 
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and
support with third sector interface to build capacity and
identify opportunities for growth and sustainability. 
Reviewed guidance and processes relating to asset
transfer, allotment and Community Councils. 
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice
in mainstreaming participatory approaches 
External funding bid help for groups through regular
meetings with third sector, funders and funding
officers. 
Membership of The Consultation Institute.  
Additional investment of £1m for a Community Asset
Transfer Start Up Fund, prioritising additional staffing
capacity to support CAT in Connected Communities
and TACT.  
A collaboration and shared resource approach across
Connected Communities Teams will be taken to
ensure the Service deliver on this priority.
3 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Tolerate
Stable 12

Page 18

Strategic Risk Action Plan Date Updated 23-Jan-2023
Analysis of Effectiveness of Controls Further Action Required Target Date for Completion Officers Responsible Current Status: RAG
Implementation of CEA: 
Existing controls remain effective and are
kept under review.
23 January 2023:
Strategic CLD Plan 2021-2024 identifies priorities for capacity
building and the programme of community support is addressing
needs. Community larders and Community Cafes are being
supported by the NA Food System and Connected Communities staff
to ensure the network can be sustained and develop further. All other
actions are being progressed and remain within the target date for
completions.
31-Mar-2024 Rhonda Leith 
Implementation of CEA:
Existing controls remain effective and are
kept under review to monitor impact and
performance.  
23 January 2023:
A New Local Outcomes Improvement Plan for 22-30 was approved
by the CPP Board in March 2022. Work is now being undertaken to
develop and implement the LOIP action plan to continue to work to
improve outcomes for our communities across North Ayrshire.
31-Mar-2024 Rhonda Leith 
Staff capacity: 
Existing controls remain effective and are
kept under review, Recruitment remains a
challenge. 
23 January 2023:
Ongoing review and monitoring on progress of CAT applications. 
31-Mar-2024 Rhonda Leith 
Alignment of engagement:
Existing controls remain effective.
23 January 2023:
Actions are being progressed and remain within the target date for
completion. Ongoing focus to ensure the right balance of time and
resource to community / stakeholder engagement aligning to the
Consultation Institute frameworks.
31-Mar-2024 Rhonda Leith 
Consultation: 
Existing controls remain effective and hybrid
engagement models have been
implemented post covid to encourage and
provide greater access to participation.
23 January 2023:
Actions are being progressed and remain within the target date for
completion. Ongoing focus to consultation and engagement.
31-Mar-2024 Rhonda Leith

Page 19

Risk Code SRR2324_R08 Risk Title National Care Service Latest Note Date 25-Jan-2023
Risk Owner Craig Hatton
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The proposals for a National Care Service
represent one of the largest reorganisations in
local government since the creation of local
authorities in 1995/96.
Uncertainty around future delivery models and the
scope of the National Care Service, leading to
uncertainty around the level of local authority
resources which will be transferred to the National
Care Service and also the level of funding to cover
the remaining local authority services, with the
Social Care Budget accounting for almost one third
of local government expenditure.
Complexity in the transferring of one of local
government’s most significant and important
services, therefore resulting in considerable staff
resourcing to undertake this task, as well as
considerable financial cost.
The arrangements for Children’s Services are still
to be determined, but if these are removed from
the local authority there are risks arising from the
arm’s length proximity to Education.
Tight timescales for implementation by the end of
the current Parliamentary term in 2026, when
boundaries and service scope are uncertain.
Impact on local government revenue and capital
funding.
Potential impact on all corporate support
services.
Delays in the implementation of existing
priorities and commitments as a result of
diverted resource.
Potential loss of ‘whole service’ approach within
local government that benefitted from shared
leadership and links across essential services.
Uncertainty created for the council’s workforce
which may result in a loss of existing talent and
experience as well as difficulties with
recruitment.
Risk to the ongoing work and service delivery by
the Council into Children’s Services if these are
removed from the local authority.
Challenges around agreeing the funding of all
historic borrowing attached to Social Care
assets. 
Reducing the capacity of local authorities
exposes civil emergency arrangements to new
risks.
Engagement within the Health & Social Care Partnership
with lead professionals, input by Senior Managers within
the HSCP and consideration by the Partnership Senior
Management Team on the Scottish Government’s
proposals for the National Care Service.
The North Ayrshire Integration Joint Board approved
their response to the consultation at their meeting of 21
October 2021.
Cabinet approved their response to the consultation at
their meeting of 2 November 2021.
Participation in the annual National Care Service Forum,
with the first meeting held on 3 October 2022.
5 4
Status Risk Score
Heat Map 
Change in Score Approach
New risk Treat
Increasing 20

Page 20

Strategic Risk Action Plan Date Updated 27-Jan-2023 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Further actions will be identified and undertaken once details are known around the scope of the National Care Service
and timescales for implementation.
A detailed response plan will be prepared which will detail the preparations required in order to mitigate any risk.
27 January 2023:
Actions will be identified and
progressed in due course.
31-Mar-2026
Caroline
Cameron/Mark
Boyd/Craig Hatton