NORTH AYRSHIRE COUNCIL 
21 March 2023 
Cabinet 
Title:    Capital Programme Performance to 31 March 2023 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme for 2022/23. 
Recommendation:  That Cabinet agrees to (a) note the revisions to budgets
outlined in the report; (b) note (i) the General Services and HRA
revised budgets at 31 January 2023; and (ii) the forecast
expenditure to 31 March 2023; and (c) approve the proposed
revision to the General Services Capital Programme in respect
of the additional borrowing requirement to support the
Shewalton and Nethermains Solar PV projects. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2022/23 to 2030/31 was
approved by Council on 2 March 2022. The Housing Revenue Account (HRA) Capital
Investment Programme 2022/23 sits within the updated HRA Business Plan and was
approved by Council on 16 February 2022. 
1.2  This report identifies the current programme for 2022/23, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 31
January 2023 (Period 10) and forecast expenditure to 31 March 2023. 
1.3   At Period 10 the General Fund is forecasting a projected underspend of (£0.104m)
against a revised budget of £42.813m. The HRA is forecasting a projected
underspend of (£9.102m) against a revised budget of £43.451m. 
1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £1.145m, including Scottish Government funding in
relation to the Place Based Investment Programme. Further reviews of individual
project plans have identified a number of adjustments to the current profiles. As a
result, (£7.379m) has been reprofiled for delivery in 2023/24. This has been partly
offset by the acceleration of £0.420m to 2022/23 from future years. 
1.5 Within the HRA, a review of delivery timescales has identified a requirement to re-
profile (£15.302m) of works for delivery in 2023/24 and beyond. This is offset by the
acceleration of £0.985m to 2022/23 from future years.

Page 2

1.6 The major risk to the forecast position is the uncertainty arising from the ongoing
inflationary pressures and supply chain issues which are impacting on tender returns
and the cost of materials, as reported across a number of General Fund and HRA
projects. While some mitigation has been built into the programme to offset cost
pressures, any further significant increase in costs will result in increased borrowing
requirements and may have a negative impact on the deliverability of both the
General Fund and HRA capital programmes for 2022/23 and beyond. Projects will
continue to be monitored closely with cost increases met initially from the additional
flexibility built into the programme. However, any requirement for further borrowing not
met from a funding source will be a matter for Council to consider. 
1.7  Following completion of the tender exercise in relation to the Shewalton and
Nethermains Solar PV projects, it has been identified that an additional investment of
£0.781m is required. Cabinet is requested to approve the additional borrowing
requirement to support this investment with the associated costs to be met from the
anticipated income associated with the projects. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2022/23 General Services budget: 
2.2 (a) Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
2022/23
£m
Budget as at 30 November 2022 48.627     
a) Changes to Funding 1.082        
b) Other Revisions to the Programme 0.063        
Revised Budget 49.772     
c) Alterations to phasing of projects:-
2022/23 to 2023/24 (7.379)           
2023/24 to 2022/23 0.420        
Budget as at 31 January 2023 42.813

Page 3

2.3 (b) Other Revisions to the Programme 
An adjustment of £0.063m has been reported due to an additional CFCR contributions
in relation to the Brodick Library and the vehicle fleet. 
2.4 (c) Alterations to the Phasing of Projects 
The ongoing review of individual project plans, taking cognisance of the current levels
of volatility within the construction sector, has identified a requirement to re-profile a
further (£7.379m) of works for delivery in 2023/24 and beyond. This includes a
corporate phasing adjustment reflecting the degree of uncertainty in the total
expenditure projections: 
Funding Body Amount Project
Specific Capital Grant £1.093m Place Based Investment Programme
Specific Capital Grant £0.098m UK Shared Prosperity Fund
Specific Capital Grant £0.017m Island Crisis Emergency Fund
Energy Savings Trust £0.102m Workplace Chargers
Scottish Forestry £0.090m Lochshore
Sustrans (£0.133m) Lochshore
SPT (£0.185m) Cumbrae Ferry & Bus Stop
Total £1.082m
Service Amount Project
Communities (£0.160m) UFSM Expansion
(£0.148m) Montgomerie Park Primary
(£0.147m) CO2 Monitors
(£0.032m) Annick Primary Early Years
(£0.070m) Other minor adjustments
(£0.557m)
Chief Executives (£0.130m) LAN/WIFI
(£0.100m) ICT Investment Fund
(£0.012m) Other minor adjustments
(£0.242m)
HSCP (£0.156m) Improvement Grants
(£0.020m) Other minor adjustments
(£0.176m)

Page 4

Service Amount Project
Place (£1.700m) Millport Coastal FPS
(£0.641m) PBIP Bank Street
(£0.520m) Island Pit Stops
(£0.356m) Nature Restoration Fund
(£0.343m) Lighting
(£0.330m) AGD i3 DPMC
(£0.300m) Upper Garnock FPS
(£0.252m) Millport Town Hall Regeneration
(£0.239m) Repurposing Property Grant Fund
(£0.237m) Place Based Investment
(£0.168m) Parking Charges & DPE
(£0.163m) LED Lighting Replacement
(£0.159m) Millport Town Hall Phase 2
(£0.148m) Access Path Network
(£0.140m) Town Centre Reneration
(£0.132m) PLI Kilwinning Academy
(£0.113m) Fleet Decarbonisation
(£0.111m) Irvine High Street
(£0.102m) Stevenston Cemetery
(£0.100m) Montgomerie Park Masterplan
(£0.098m) UK Shared Prosperity Fund
(£0.095m) PLI Cunninghame House
(£0.088m) Kilbirnie Cemetery Wall
(£0.077m) VDLF Development Work
(£0.074m) A737 Dalry Bypass
(£0.071m) VDLF Kyle Road
(£0.216m) Other minor adjustments
(£6.973m)
Other (£2.521m) Flexibility Fund
(£2.521m)
Corporate £3.090m Uncertainty / Sensitivity Adjustment
£3.090m
Total (£7.379m)

Page 5

These adjustments have been partly offset by the acceleration of £0.420m of
expenditure to 2022/23 from future years. 
2.5 These adjustments have resulted in a revised 2022/23 budget at 31 January 2023 of
£42.709m. 
2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
Service Amount Project
Chief Executives £0.053m Schools ICT Investment
Place £0.078m PLI Auchenharvie Academy
£0.198m Kilwinning Cemetery
£0.075m Other minor adjustments
£0.351m
Communities £0.016m Other minor adjustments
£0.016m
Total £0.420m
38.672 32.249 0.492 50.239 2.500 124.152
25.201 8.948 2.002 43.502 (10.019) 69.634
25.196 6.764 1.672 38.451 (8.321) 63.762
9.045 2.555 1.578 40.231 (4.782) 48.627
8.573 2.366 1.262 34.676 (4.064) 42.813
(30.099) (29.883) 0.770 (15.563) (6.564) (81.339)
Approved Programme
Movement
Programme @ P6
Programme @ P4
Programme @ P10
Programme @ P8

Page 6

2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of £5.814m from the revised budget,
including: 
2.8 Projected Capital Expenditure to 31 March 2023 
The projections are summarised by service in the following table:   
2.9 Minor underspends totalling £0.104m have been reported in relation to completed
projects, including Annick Primary ELC Extension, £0.098m; Our Future Working
Environment, £0.001m; and Largs Car Park Infrastructure, £0.005m. These funds will
be transferred to the Flexibility budget to offset anticipated budget pressures
elsewhere in the programme. Information on the progress of all projects can be found
in Appendix 1. 
Category Amount Comments
Borrowing £2.268m Rephased aligned to projected expenditure
CFCR (£0.063m) Additional CFCR Contribution
Capital Grants £2.995m Rephased and additional government grants
Other Grants £0.360m Rephased and revised contributions
Capital Receipts £0.254m Realigned capital receipts
Total £5.814m
Revised
Budget
2022/23
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Projected
Expenditure
/ Income to
31 March
2023
Projected
Variance
Over /
(Under)
£m £m £m £m £m £m
Expenditure
Communities 9.045 0.069 (0.541) 8.573 8.475 (0.098)
Chief Executive 2.555 - (0.189) 2.366 2.365 (0.001)
Health and Social Care Partnership 1.578 (0.140) (0.176) 1.262 1.262 -
Place 40.231 1.067 (6.622) 34.676 34.671 (0.005)
Other including Flexibility (4.782) 0.149 0.569 (4.064) (4.064) -
Total Expenditure 48.627 1.145 (6.959) 42.813 42.709 (0.104)
Income
General Capital Grant (26.341) - - (26.341) (26.341) -
Specific Capital Grant (12.189) (1.208) 4.203 (9.194) (9.194) -
Capital Funded from Current Revenue (0.018) (0.063) - (0.081) (0.081) -
Capital Receipts (0.466) - 0.254 (0.212) (0.212) -
Other Grants & Contributions (3.039) 0.126 0.234 (2.679) (2.679) -
Prudential Borrowing (6.574) - 2.268 (4.306) (4.202) 0.104
Total Income (48.627) (1.145) 6.959 (42.813) (42.709) 0.104

Page 7

2.10 Although not formally reflected in the financial performance reports at this time due to
ongoing uncertainty, areas of cost risk have been identified as a result of cost volatility
arising from the ongoing inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials
across a number of projects, as highlighted in appendix 1. Some mitigation has been
built into the Capital Investment Programme in the form of enhanced flexibility
budgets. However, cost pressures may exceed this provision, requiring additional
revenue investment to offset any additional borrowing requirements. These risks will
be quantified as individual projects are completed and tendering exercises are
finalised, with the impact on the costs of the programme being monitored and reported
to Cabinet as appropriate. Any funding in excess of the current level of financial
flexibility, which is required to deliver the current capital programme, will be a matter
for Council to consider within the context of overall affordability. This affordability
assessment was included in the Capital Budget approved at Council on 1 March 2023
and incorporated all known cost pressures, funding and borrowing requirements
based on current and projected interest rates, the anticipated re-direction of revenue
resources and use of financial flexibilities to support delivery of the programme and a
further flexible allowance to help manage the ongoing cost risks associated with the
programme.   
2.11 Following the completion of the P10 projections detailed in this report, the tender
exercise in relation to the Solar PV developments at Shewalton and Nethermains has
been completed as noted below: 
It is currently estimated that the additional borrowing costs associated with the
£0.781m additional investment would result in additional revenue costs of £0.060m
per annum. It is anticipated that these additional borrowing costs can be met from the
net annual income projected from the generation of electricity and it is requested that
Cabinet approve the updating of the Capital Investment Programme on this basis. 
Nethermains Shewalton Total
£m £m £m
Approved Funding
Prudential Borrowing £2.268m - £2.268m
Investment Fund £4.500m £1.400m £5.900m
Recovery & Renewal Fund - £3.880m £3.880m
Total £6.768m £5.280m £12.048m
Tender Values £7.289m £5.540m £12.829m
Additional Costs £0.521m £0.260m £0.781m

Page 8

Housing Revenue Account 
2.12 The following table outlines the movements in the 2022/23 HRA Capital budget: 
2.13  (a) Alterations to the Phasing of Projects 
A further review of the timescale for delivery of capital projects has identified a
requirement to re-profile (£15.302m) of works for delivery in 2023/24 and beyond,
including: 
2022/23
£m
Budget as at 30 November 2022 57.768       
a) Alterations to phasing of projects:-
2022/23 to 2023/24 (15.302)           
2023/24 to 2022/23 0.985         
Budget as at 31 January 2023 43.451       
Category Amount Project
New Builds (£2.150m) James McFarlane ASN
(£1.750m) Stanecastle ASN
(£1.700m) Garnock Academy
(£1.542m) Council House Building General
(£1.450m) New Build Montgomerie Park
(£1.400m) Ayrshire Central
(£1.005m) James Reid ASN
(£0.005m) Other Minor Adjustments
(£11.002m)
Improvements (£0.152m) Kitchen Programme Voids
(£0.068m) Other minor adjustments
(£0.220m)
Refurbishments (£0.731m) Demolition High Flats Irvine
(£0.215m) Window Replacement
(£0.159m) Kitchen Programme
(£0.001m) Other minor adjustments
(£1.106m)
Other (£1.820m) Solar Panels
(£0.711m) Other Capital Works
(£0.207m) Health & Safety Works
(£0.180m) Energy Efficiency Standard
(£0.056m) Other minor adjustments
(£2.974m)
Total (£15.302m)

Page 9

This has been partly offset by the acceleration of £0.985m of project expenditure for
delivery during 2022/23, including: 
2.14 These adjustments have resulted in a revised 2022/23 budget at 31 January 2023 of
£43.451m. 
2.15 The impact on budgeted funding is a reduction of £14.317m in Prudential Borrowing
aligned to the revised projected expenditure. 
2.16  Projected Capital Expenditure to 31 March 2023 
The projections are summarised in the following table:   
Category Amount Project
New Builds £0.357m New Build Flatt Road Phase 1
£0.193m New Build St Michaels Wynd
£0.115m New Build Afton Court
£0.109m New Build Brathwic Terrace
£0.159m Other minor adjustments
£0.933m
Improvements £0.018m Bathroom Programme
Refurbishments £0.034m Friars Lawn
Total £0.985m
Revised
Budget
2022/23
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Projected
Expenditure /
Income to 31
March 2023
Projected
Variance
Over /
(Under)
Service £m £m £m £m £m
Expenditure
Housing Revenue Account 57.768 (14.317) 43.451 34.349 (9.102)
Total Expenditure 57.768 (14.317) 43.451 34.349 (9.102)
Income
CFCR (12.209) (12.209) (12.209) -
Capital Grants (1.767) (1.767) (1.767) -
Use of Reserves (1.151) (1.151) (1.151) -
Affordable Housing Contribution (1.596) (1.596) (1.596) -
Prudential Borrowing (41.045) 14.317 (26.728) (17.626) 9.102
Total Income (57.768) 14.317 (43.451) (34.349) 9.102

Page 10

2.17 A variance of (£9.102m) is projected within the HRA capital programme for 2022/23
arising from revisions to a number of projects, including: 
2.18 Increased costs arising from tender inflation and supply chain issues have been
identified in relation to some projects, including the Door Replacement Programme
and Sheltered Housing Unit Improvements. Further cost pressures resulting from
inflationary and supply chain issues continue to be monitored and a review of the
potential impact on the Business Plan and Capital Programme will be undertaken to
address any identified issues. Further information on the progress of all projects can
be found in Appendix 2. 
3. Proposals 
3.1 That Cabinet agrees to (a) note the revisions to budgets outlined in the report; (b) note
(i) the General Services and HRA revised budgets at 31 January 2023; and (ii) the
forecast expenditure to 31 March 2023; and (c) approve the proposed revision to the
General Services Capital Programme in respect of the additional borrowing
requirement to support the Shewalton and Nethermains Solar PV projects. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Project Variance Comments
Kitchen Programme (£2.997m) Aligned to revised Business Plan and labour
shortages
Roofing & Rendering (£2.145m) Aligned to revised Business Plan
Electrical Rewiring (£1.532m) Aligned to revised Business Plan and labour
shortages
Insulated Re-rendering (£1.480m) Aligned to revised Business Plan and labour
shortages
Central Heating (£0.948m) Aligned to revised Business Plan
Total (£9.102m)

Page 11

Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2019 to 2024 by maximising resources
and providing value for money to support financially sustainable delivery models. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Programme Performance to 31 March 2023 – Cabinet, 24 January 2023

Page 12

Appendix 1
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Brought / Carry
Forward to 2023/24
Total Revised
Budget 2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 January 2023
Year to date
Variance 2022/23
Projected Expenditure
to 31st March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 15,860,427 15,422,071 15,762,427 (98,000) 2,350,765 (91,599) 2,259,166 0 1,912,409 1,912,409 2,161,166 (98,000) (98,000)
Primary Schools 35,676,441 5,831,314 35,676,441 0 4,692,399 (302,871) 4,389,528 0 2,866,347 2,866,347 4,389,528 0 0
Secondary Schools 74,575,465 3,839,126 74,575,465 0 919,053 0 919,053 0 541,087 541,087 919,053 0 0
Special Education 25,443,178 25,295,310 25,443,178 0 903,203 0 903,203 0 755,336 755,336 903,203 0 0
Schools Other 298,000 151,457 298,000 0 191,892 (146,543) 45,349 0 45,349 45,349 45,349 0 0
Information & Culture 125,916 16,470 125,916 0 53,289 0 53,289 0 9,907 9,907 53,289 0 0
Completed Projects 43,419,379 43,395,373 43,419,379 0 3,679 0 3,679 0 (20,327) (20,327) 3,679 0 0
SUB TOTAL 195,398,806 93,951,121 195,300,806 (98,000) 9,114,280 (541,013) 8,573,267 0 6,110,106 6,110,106 8,475,267 (98,000) (98,000)
Chief Executive
Council IT Strategy 9,840,210 3,809,256 9,839,597 (613) 2,555,286 (189,552) 2,365,734 0 2,297,528 2,297,528 2,365,121 (613) (613)
SUB TOTAL 9,840,210 3,809,256 9,839,597 (613) 2,555,286 (189,552) 2,365,734 0 2,297,528 2,297,528 2,365,121 (613) (613)
Health & Social Care
Management & Support 2,050,595 790,721 2,050,595 0 217,029 0 217,029 0 46,964 46,964 217,029 0 0
Housing Non HRA 686,065 441,464 686,065 0 686,065 (156,065) 530,000 0 441,464 441,464 530,000 0 0
Adults 4,608,078 4,588,276 4,608,078 0 46,804 (19,936) 26,868 0 27,002 27,002 26,868 0 0
Young People 5,579,718 5,216,166 5,579,718 0 487,982 0 487,982 0 124,430 124,430 487,982 0 0
SUB TOTAL 12,924,457 11,036,627 12,924,457 0 1,437,880 (176,001) 1,261,879 0 639,861 639,861 1,261,879 0 0
Place
Roads 107,634,049 26,604,339 107,628,516 (2,736,214) 16,643,800 (2,730,681) 13,913,119 0 9,280,655 9,280,655 13,907,586 (5,533) (5,533)
Streetscene 6,580,996 2,900,769 6,580,996 0 2,268,848 (37,924) 2,230,924 0 1,481,239 1,481,239 2,230,924 0 0
Transport 4,668,111 1,036,281 4,668,111 0 2,802,511 (113,000) 2,689,511 0 920,681 920,681 2,689,511 0 0
Waste Services 14,844,503 14,844,503 14,844,503 0 305,160 0 305,160 0 305,160 305,160 305,160 0 0
Renewable Energy 8,890,393 1,726,700 8,890,393 0 1,067,368 (356,000) 711,368 0 128,236 128,236 711,368 0 0
Office Accommodation 3,331,321 745,943 3,331,321 0 1,918,188 (221,020) 1,697,168 0 745,943 745,943 1,697,168 0 0
Other Property 5,986,638 440,307 5,986,638 0 987,925 (25,682) 962,243 0 57,677 57,677 962,243 0 0
Other Housing 350,000 0 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0
Economic Development & Regeneration 152,281,929 28,312,101 152,281,929 0 14,913,347 (3,096,834) 11,816,513 0 6,389,025 6,389,025 11,816,513 0 0
Completed Projects 6,390,674 6,311,034 6,390,674 0 40,595 (40,595) 0 0 (28,842) (28,842) 0 0 0
SUB TOTAL 310,958,614 82,921,978 310,953,081 (2,736,214) 41,297,742 (6,621,736) 34,676,006 0 19,279,774 19,279,774 34,670,473 (5,533) (5,533)
Other
Other 9,474,863 0 7,562,125 (1,912,738) 2,520,738 (2,520,738) 0 0 0 0 0 0 0
SUB TOTAL 9,474,863 0 7,562,125 (1,912,738) 2,520,738 (2,520,738) 0 0 0 0 0 0 0
Uncertainty / Sensitivity Adjustment* (4,064,230) (4,064,230) (4,064,230)
Total Project Expenditure 538,596,951 191,718,982 536,580,067 (4,747,565) 56,925,926 (14,113,270) 42,812,656 0 28,327,269 28,327,269 42,708,510 (104,146) (104,146)
Total Project Income (56,925,926) 14,113,270 (42,812,656) (37,269,953) (37,269,953) 0 (42,708,510) 104,146 104,146
Total Net Expenditure 0 0 0 (37,269,953) (8,942,684) 28,327,269 0 0 0
* Sensitivity adjustment of 10% or 25% based on source and reliability of expenditure projections
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2022/23
North Ayrshire Council Capital Statement 2022/23
Year Ended 31st March 2023
Period 10
The following classifications have been used to highlight delivery performance
against original timescales set

Page 13

Revised Budget
22/23 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 94,515,334 9,882,875 1,655,477 106,053,686 (90,238,701) 15,814,985 8,265,765 (7,549,220)
SUB TOTAL 94,515,334 9,882,875 1,655,477 106,053,686 (90,238,701) 0 15,814,985 0 8,265,765 (7,549,220)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Early Learning & Childcare 464,253 517,775 982,028 0 982,028 978,659 922,822 (59,206)
Cycling / Walking /Safer Streets 1,111,122 38,831 (300,566) 849,387 (252,322) 597,065 261,387 597,065 0
Vacant & Derelict Land Funding 3,710,375 123,927 848,022 4,682,324 (2,476,215) 2,206,109 4,252,324 2,013,629 (192,480)
UK Government Grant - AGD 2,040,120 2,040,120 (1,832,120) 208,000 0 208,000 0
Lochshore - Garnock Community Visitor Hub 0 50,000 50,000 0 50,000 50,000 50,000 0
Town Centre Regeneration 0 166,774 250,000 416,774 0 416,774 416,773 276,774 (140,000)
Stevenston Beach Hub 0 34,525 50,000 84,525 0 84,525 84,525 84,525 0
Annickbank - Vacant & Derelict Land Investment Programme 400,000 400,000 0 400,000 0
Millport Town Hall Regeneration 0 382,028 1,187,810 1,569,838 0 1,569,838 1,569,838 1,317,309 (252,529)
Millport Town Hall Phase 2 509,450 509,450 0 349,952 (159,498)
Islands Pit Stops 540,000 540,000 0 20,000 (520,000)
Islands Cost Crisis Emergency Fund 17,000 17,000 0 17,000 0
Place Based Investment Programme 706,000 147,903 346,040 1,199,943 1,093,000 2,292,943 2,292,944 1,344,107 (948,836)
UK Shared Prosperity Fund 98,414 98,414 98,414 0 (98,414)
Island Infrastructure Fund 0 259,000 259,000 0 259,000 259,000 259,000 0
Bridges Infrastructure 567,000 (567,000) 0 0 0 0 0 0
B714 Improvements 857,907 197,160 1,055,067 156,933 1,212,000 1,212,000 1,212,000 0
Renewal of Play Parks 0 117,000 117,000 (117,000) 0 0 0 0
Nature Restoration Fund 0 0 0 0 0 0 0
CO2 Monitors in Schools 0 122,000 122,000 0 122,000 122,000 122,000 0
Capital Grants
Flooding 2,778,000 2,778,000 8,676,000 11,454,000 0 11,454,000 0
General Capital Grant 9,805,000 845,000 10,650,000 4,237,000 14,887,000 24,103,000 14,887,000
SUB TOTAL 22,039,777 1,780,923 3,035,306 26,856,006 11,050,140 0 37,906,146 35,700,863 35,535,183 (2,370,963)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 4,718,975 140,833 88,942 4,948,750 (4,948,750) 0 0 0 0 0
Change & Service Redesign Fund 0 42,682 0 42,682 (42,682) 0 0 0 0 0
CFCR 600,000 0 0 600,000 (518,835) 0 81,165 0 81,165 0
Grants & Contributions 1,925,682 866,594 1,539,395 4,331,671 (1,418,689) 0 2,912,982 1,360,092 2,678,629 (234,353)
Capital Receipts 352,500 0 0 352,500 (141,852) 0 210,648 208,998 211,998 1,350
TOTAL CAPITAL PROGRAMME FUNDING 124,152,268 12,713,907 6,319,120 143,185,295 (86,259,369) 0 56,925,926 37,269,953 46,772,740 (10,153,186)
22/23 Budget at
Capital Refresh
Mar 2022
Capital Programme Funding 2022/23
Projected Income
to 31st March
2023
Approved budget
at Period 1 used
as revised starting
point 2022/23
Actual Income to 31
January 2023Funding Description
Carry Forward
from 2021/22
Changes after
Capital Refresh Mar
2022
Total Changes in
Year
Changes at Capital
Refresh Mar 2023

Page 14

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 January 2023
Year to date Variance
2022/23
Projected
Expenditure to 31
March 2023
Actual Over/ (Under)
Spend for 2022/23   
True Over/(Under)
Spend            
Brought / Carry
Forward to 2023/24 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
ST BRIDGETS EARLY YEARS 785,068 770,580 785,068 0 7,969 0 (6,519) (6,519) 7,969 0 0 Complete Complete Complete On Target On Target
KILMORY EARLY YEARS 55,978 28,117 55,978 0 27,986 0 125 125 195 (27,791) (27,791) 15-Aug-22 31-Aug-23 Pre Tender On Target On Target
ST PETERS EARLY YEARS 1,261,310 1,226,705 1,261,310 0 42,333 0 7,728 7,728 25,646 (16,687) (16,687) Complete Complete Complete On Target On Target
ST JOHN OGILVIE EARLY YEARS 177,415 177,415 177,415 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
MAYFIELD PS EARLY YEARS 215,850 215,542 215,850 0 5,820 0 5,512 5,512 5,820 0 0 Complete Complete Complete On Target On Target
BEITH PS EARLY YEARS 341,321 339,763 341,321 0 6,540 0 4,983 4,983 6,540 0 0 Complete Complete Complete On Target On Target
SKELMORLIE PS EARLY YEARS 366,440 346,635 366,440 0 11,492 0 (8,313) (8,313) 11,492 0 0 Complete Complete Complete On Target On Target
WEST KILBRIDE EARLY EARLY YEARS 232,807 220,254 232,807 0 11,531 0 (1,022) (1,022) 11,531 0 0 Complete Complete Complete On Target On Target
GATESIDE EARLY YEARS 407,478 407,478 407,478 0 2,613 0 2,612 2,612 2,613 0 0 Complete Complete Complete On Target On Target
GARNOCK CAMPUS EARLY YEARS 58,755 58,755 58,755 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
FAIRLIE EARLY YEARS 204,528 204,528 204,528 0 878 0 878 878 878 0 0 Complete Complete Complete On Target On Target
ELDERBANK EARLY YEARS 22,983 22,983 22,983 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
DREGHORN EARLY YEARS 84,784 82,843 84,784 0 2,341 0 400 400 2,341 0 0 Complete Complete Complete On Target On Target
CUMBRAE EARLY YEARS 40,184 40,184 40,184 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
LARGS CAMPUS EARLY YEARS 45,836 45,836 45,836 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
MOORPARK EARLY YEARS 1,000 182 1,000 0 818 0 0 0 818 0 0 14-Aug-20 15-Aug-22 Development On Target On Target
PIRNMILL EARLY YEARS 80,000 51,433 80,000 0 77,510 0 48,944 48,944 77,510 0 0 31-Oct-21 30-Apr-23 Construction On Target On Target
SHISKINE EARLY YEARS 74,808 120,031 74,808 0 18,650 0 63,872 63,872 18,650 0 0 31-Oct-21 30-Apr-23 Construction On Target On Target
CORRIE EARLY YEARS 38,606 24,708 38,606 0 37,046 0 23,149 23,149 36,441 (605) (605) 31-Oct-21 01-Aug-23 Defects On Target On Target
LAMLASH EARLY YEARS 15,000 807 15,000 0 14,318 0 125 125 195 (14,123) (14,123) 31-Oct-21 31-Aug-23 Tender On Target On Target
BRODICK EARLY YEARS 342,590 322,508 342,590 0 334,151 0 314,070 314,070 334,151 0 0 Complete Complete Complete Complete Complete
MARRESS HOUSE 3,460,332 3,338,890 3,460,332 0 1,532,990 0 1,411,548 1,411,548 1,532,990 0 0 22-Jul-22 31-May-23 Construction On Target Significantly off target result of poor performance by the contractor and continuing issues
with the condition of the existing building
Completed Nursery Education
LAWTHORN EARLY YEARS 201,037 201,037 201,037 0 77 0 77 77 77 0 0 Complete Complete Complete Complete Complete
Other Nursery Education
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,201,415 3,029,954 3,103,415 (98,000) 215,702 0 44,241 44,241 85,309 (130,393) (98,000) (32,393) Complete Complete Complete On Target On Target
Total Nursery Education 15,860,427 15,422,071 15,762,427 (98,000) 2,350,765 0 1,912,409 1,912,409 2,161,166 (189,599) (98,000) (91,599)
Primary Schools
MOORPARK PRIMARY 10,849,442 4,831,726 10,849,442 0 3,086,371 0 2,017,289 2,017,289 3,086,371 0 0 30-Sep-22 30-Sep-23 Construction Slightly off target  Significantly off target Delays are being experienced by the contractor and wider supply
chain.
MONTGOMERIE PARK SCHOOL 14,470,000 649,380 14,470,000 0 884,778 0 499,111 499,111 736,478 (148,300) (148,300) 30-Apr-24 12-Aug-24 Tender Significantly off target On Target Revised project costs £2.550m above initial budget as reported to
Cabinet on 27/4/22
UNIVERSAL FREE SCHOOL MEALS EXPANSION 2,626,572 0 2,626,572 0 159,572 0 0 0 0 (159,572) (159,572) 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM BRODICK PRIMARY SCHOOL 177,928 106,159 177,928 0 144,178 0 106,159 106,159 144,178 0 0 Complete Complete Complete Complete Complete
UFSM CORRIE PRIMARY SCHOOL 52,500 44,306 52,500 0 52,500 0 44,306 44,306 52,500 0 0 Complete Complete Complete Complete Complete
UFSM LARGS PRIMARY SCHOOL 195,000 19,271 195,000 0 150,000 0 19,271 19,271 150,000 0 0 Complete Complete Complete Complete Complete
UFSM SHISKINE PRIMARY SCHOOL 15,000 24,678 15,000 0 15,000 0 24,678 24,678 3,553 (11,447) (11,447) Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,500,000 155,794 2,500,000 0 200,000 0 155,532 155,532 216,448 16,448 16,448 31-Aug-24 31-Jan-23 Tender On Target On Target
Total Primary Education 35,676,441 5,831,314 35,676,441 0 4,692,399 0 2,866,347 2,866,347 4,389,528 (302,871) 0 (302,871) 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,426,731 2,805,435 0 127,953 0 72,329 72,329 127,953 0 0 31-Aug-21 31-Mar-24 Construction On Target On Target
AYRSHIRE COLLEGE PARTNERSHIP DEVELOPMENT 200,000 0 200,000 0 200,000 0 0 0 200,000 0 0 31-Mar-22 31-Jan-23 Future Years On Target On Target
ARDROSSAN NEW BUILD 71,570,030 1,412,395 71,570,030 0 591,100 0 468,758 468,758 591,100 0 0 31-Aug-26 31-Aug-26 In Development Slightly off target  Slightly off target  Delayed expenditure linked to anticipated delays and inflationary
pressures linked to the advance works tender process.
Total Secondary Education 74,575,465 3,839,126 74,575,465 0 919,053 0 541,087 541,087 919,053 0 0 0
Special Education
LOCKHART CAMPUS 25,443,178 25,295,310 25,443,178 0 903,203 0 755,336 755,336 903,203 0 0 Complete Complete Snagging On Target On Target
Total Special Education 25,443,178 25,295,310 25,443,178 0 903,203 0 755,336 755,336 903,203 0 0 0
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 151,457 298,000 0 191,892 0 45,349 45,349 45,349 (146,543) (146,543) 31-Mar-23 31-Mar-24 Planning On Target On Target
Total Schools Other 298,000 151,457 298,000 0 191,892 0 45,349 45,349 45,349 (146,543) 0 (146,543)
Information & Culture
CASTLES & HISTORIC MONUMENTS 50,740 9,907 50,740 0 50,740 0 9,907 9,907 50,740 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 75,176 6,563 75,176 0 2,549 0 0 0 2,549 0 0 Autumn 2023 Autumn 2023 Planning On Hold On Hold
Total Information & Cultural 125,916 16,470 125,916 0 53,289 0 9,907 9,907 53,289 0 0 0
Completed Projects
GARNOCK CAMPUS 40,307,259 40,284,039 40,307,259 0 2,893 0 (20,327) (20,327) 2,893 0 0 Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,112,120 3,111,334 3,112,120 0 786 0 0 0 786 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 43,419,379 43,395,373 43,419,379 0 3,679 0 (20,327) (20,327) 3,679 0 0 0
Total Communities 195,398,806 93,951,121 195,300,806 (98,000) 9,114,280 0 6,110,106 6,110,106 8,475,267 (639,013) (98,000) (541,013)
CAPITAL MONITORING 2022/23
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS

Page 15

CHIEF EXECUTIVE
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
January 2023
Year to Date
Variance 2022/23
Projected Expenditure
to 31 March 2023 
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to
2023/24
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Council IT Strategy
SCHOOLS ICT INVESTMENT * 1,297,915 1,350,363 1,297,915 0 1,297,915 0 1,350,363 1,350,363 1,350,363 52,448 52,448 31-Mar-23 31-Mar-23 On-going On Target On Target
ICT INVESTMENT FUND 3,822,986 936,131 3,822,986 0 430,000 0 306,341 306,341 330,000 (100,000) (100,000) 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 857,100 352,453 857,100 0 94,297 0 89,649 89,649 94,297 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
LAN/WiFi 2,673,000 930,505 2,673,000 0 691,816 0 559,321 559,321 561,816 (130,000) (130,000) 31-Mar-28 31-Mar-28 Implementation On Target On Target
TELEPHONY 1,146,693 197,902 1,146,693 0 36,988 0 (11,803) (11,803) 24,988 (12,000) (12,000) 31-Mar-28 31-Mar-28 Implementation On Target On Target
OUR FUTURE WORKING ENVIRONMENT 42,516 41,903 41,903 (613) 4,270 0 3,657 3,657 3,657 (613) (613) 0 Complete Complete Complete Complete Complete
Total IT Strategy 9,840,210 3,809,256 9,839,597 (613) 2,555,286 0 2,297,528 2,297,528 2,365,121 (190,165) (613) (189,552)
Total Chief Executive 9,840,210 3,809,256 9,839,597 (613) 2,555,286 0 2,297,528 2,297,528 2,365,121 (190,165) (613) (189,552)   
CAPITAL MONITORING 2022/23
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2022/23 BUDGETS

Page 16

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 January 2023
Year to Date Variance
2022/23
Projected Expenditure
to 31 March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to 2023/24   Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Management & Support
HOME CARE SYSTEM 433,917 433,917 433,917 0 42,682 0 42,682 42,682 42,682 0 0 Complete Complete Complete Complete Complete
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 4,190 996,000 0 6,190 0 4,190 4,190 6,190 0 0 31-Dec-23 31-Dec-23 Future Years On Target On Target
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 168,157 0 92 92 168,157 0 0 31-Aug-24 31-Aug-24 In development On Target On Target
Total Management & Support 2,050,595 790,721 2,050,595 0 217,029 0 46,964 46,964 217,029 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 686,065 441,464 686,065 0 686,065 0 441,464 441,464 530,000 (156,065) (156,065) 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
Total Housing Non HRA 686,065 441,464 686,065 0 686,065 0 441,464 441,464 530,000 (156,065) 0 (156,065)
Adults
TRINDLEMOSS 4,608,078 4,588,276 4,608,078 0 46,804 0 27,002 27,002 26,868 (19,936) (19,936) Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,588,276 4,608,078 0 46,804 0 27,002 27,002 26,868 (19,936) 0 (19,936)
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,216,166 5,579,718 0 487,982 0 124,430 124,430 487,982 0 0 Complete Complete Snagging On Target On Target
Total Young People 5,579,718 5,216,166 5,579,718 0 487,982 0 124,430 124,430 487,982 0 0 0
Total Health & Social Care 12,924,457 11,036,627 12,924,457 0 1,437,880 0 639,861 639,861 1,261,879 (176,001) 0 (176,001)
CAPITAL MONITORING 2022/23
2022/23 BUDGETSTOTAL PROJECT COMPLETION DATES
CommentsProject Description
DELIVERY STATUS

Page 17

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
January 2023
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
PHYSICAL ENVIRONMENT
Roads
ROADS IMPROVE/RECONSTRUCTION * 4,814,795 4,814,795 4,814,795 0 4,814,795 0 4,439,975 4,439,975 4,814,795 0 0 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
A737 DALRY BYPASS 210,000 136,000 210,000 0 210,000 0 85,699 85,699 136,000 (74,000) (74,000) 31-Mar-24 31-Mar-24 In Development On Target On Target 
TRAFFIC CALMING 175,000 9,980 175,000 0 100,000 0 9,980 9,980 100,000 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
VEHICLE RESTRAINT SYSTEM UPGRADE 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-23 31-Mar-23 In Development On Target On Target
LIGHTING * 1,587,827 908,556 1,587,827 0 1,587,827 0 908,556 908,556 1,244,770 (343,057) (343,057) 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 695,000 200,700 695,000 0 492,190 0 200,700 200,700 329,690 (162,500) (162,500) 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target
A737 DALRY BYPASS LIGHTING 20,685 0 20,685 0 20,685 0 0 0 6,485 (14,200) (14,200) 31-Mar-23 31-Mar-23 Preparing Works PackagesOn Target On Target
UPPER GARNOCK FPS 18,503,800 17,351,773 18,503,800 0 3,454,934 0 2,302,907 2,302,907 3,154,934 (300,000) (300,000) Complete Complete Complete Slightly off target  Slightly off target  The contractor did not achieve the programme before winter. The
drainage and topsoiling/ seeding cannot be completed until next
spring
MILLPORT COASTAL FPS 48,599,796 1,306,302 48,599,796 0 3,000,000 0 41,506 41,506 1,300,000 (1,700,000) (1,700,000) 31-Aug-24 31-Aug-24 Construction On Target On Target
MILLBURN FPS 1,757,000 194,541 1,757,000 0 60,000 0 7,523 7,523 60,000 0 0 31-Mar-23 31-Jul-24 Design On Target Significantly off
target
Delays in the design process
BRIDGES INFRASTRUCTURE PROG * 1,000,000 621,165 1,000,000 0 1,000,000 0 621,165 621,165 1,000,000 0 0 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 3,039,000 302,224 3,039,000 0 160,840 0 191,596 191,596 191,596 30,756 30,756 31-Oct-23 31-Oct-23 Tender Slightly off target  On Target Increased tender cost risks identified
B714 UPGRADE 26,063,443 462,662 26,063,443 0 1,212,000 0 462,662 462,662 1,212,000 0 0 31-Mar-25 31-Mar-25 Outline Design Significantly off target On Target Increased tender cost risks identified
LARGS CAR PARK INFRASTRUCTURE 60,000 54,467 54,467 (5,533) 5,533 0 0 0 0 (5,533) (5,533) 0 Complete Complete Complete Complete Complete
GALLOWGATE TOILETS 250,000 3,977 250,000 0 247,316 0 1,294 1,294 247,316 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PARKING CHARGES & DPE 257,705 87,119 257,705 0 177,680 0 7,095 7,095 10,000 (167,680) (167,680) 31-Mar-24 31-Mar-24 In Development On Target On Target
Total Roads 107,634,049 26,604,339 107,628,516 (5,533) 16,643,800 0 9,280,655 9,280,655 13,907,586 (2,736,214) (5,533) (2,730,681)
Streetscene
LAMLASH CEMETERY EXTENSION 715,065 715,065 715,065 0 30,540 0 30,540 30,540 30,540 0 0 Complete Complete Complete Complete Complete
HIGH KIRK CEMETERY 0 767 0 0 0 0 767 767 0 0 0 On Target On Target
DREGHORN CEMETERY 0 1,110 0 0 0 0 1,110 1,110 0 0 0 On Target On Target
ARDROSSAN CEMETERY PLOTS AND WALLS 217,922 151,142 217,922 0 67,219 0 439 439 55,921 (11,298) (11,298) Complete Complete Complete Complete Complete
KILBIRNIE CEMETERY 623,833 34,605 623,833 0 9,223 0 9,223 9,223 9,223 0 0 31-Mar-25 31-Mar-25 Feasibility Works On Hold On Hold
KILWINNING CEMETERY NEW 1,240,642 926,124 1,240,642 0 953,868 0 837,678 837,678 1,152,196 198,328 198,328 01-Sep-22 31-May-23 Construction On Target Significantly off
target
Contractor appointed and work commenced
KNADGERHILL CEMETERY EXTENSION 443,581 390,453 443,581 0 49,340 0 (3,787) (3,787) 49,340 0 0 01-Oct-22 31-Mar-23 Construction On Target On Target
WEST KILBRIDE CEMETERY 349,622 218,694 349,622 0 310,902 0 187,481 187,481 310,902 0 0 25-Nov-22 28-Feb-24 Construction On Target On Target
STEVENSTON CEMETERY 545,429 206,281 545,429 0 467,991 0 162,453 162,453 365,961 (102,030) (102,030) 23-Dec-22 30-Apr-23 Construction On Target On Target
ARDROSSAN CEMETERY NEW 900,603 603 900,603 0 0 0 0 0 0 0 0 Future years Future years Future years On Hold On Hold
BRODICK CEMETERY 12,000 7,021 12,000 0 7,021 0 7,021 7,021 9,521 2,500 2,500 Future years Future years Planning On Hold On Hold
KILBIRNIE CEMETERY WALL 188,370 2,043 188,370 0 90,000 0 2,043 2,043 2,043 (87,957) (87,957) 31-Mar-23 30-Apr-23 Feasibility Works On Target On Target
BEITH CEMETERY-WALL REPAIRS 87,542 3,122 87,542 0 40,000 0 2,533 2,533 2,533 (37,467) (37,467) 31-Mar-23 30-Apr-23 Feasibility Works On Target On Target
ABBEY TOWER CEMETERY WALL 95,550 2,314 95,550 0 3,520 0 2,314 2,314 3,520 0 0 31-Mar-24 31-Mar-24 Feasibility Works On Target On Target
HAWKHILL CEMETERY-WALL REPAIRS 108,732 1,811 108,732 0 1,811 0 1,811 1,811 1,811 0 0 31-Mar-24 31-Mar-24 Feasibility Works On Target On Target
WEST KILBRIDE CEMETERY WALL 99,528 771 99,528 0 2,413 0 771 771 2,413 0 0 31-Mar-24 31-Mar-24 Feasibility Works On Hold On Hold
STREET FURNITURE IMPROVEMENT 0 48,941 0 0 0 0 48,941 48,941 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PARK ENABLING WORKS 0 71,394 0 0 0 0 71,394 71,394 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
RENEWAL OF PLAY PARKS 235,000 109,288 235,000 0 235,000 0 109,288 109,288 235,000 0 0 31-Mar-23 31-Mar-23 Construction On Target On Target
Total Streetscene 6,580,996 2,900,769 6,580,996 0 2,268,848 0 1,481,239 1,481,239 2,230,924 (37,924) 0 (37,924)
Transport
VEHICLES * 1,851,898 787,138 1,851,898 0 1,851,898 0 787,138 787,138 1,851,898 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
WORKPLACE CHARGERS 316,213 225,283 316,213 0 200,613 0 109,683 109,683 200,613 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target
FLEET DECARBONISATION 2,500,000 23,860 2,500,000 0 750,000 0 23,860 23,860 637,000 (113,000) (113,000) 31-Mar-23 31-Mar-23 Ongoing On Target On Target
Total Transport 4,668,111 1,036,281 4,668,111 0 2,802,511 0 920,681 920,681 2,689,511 (113,000) 0 (113,000)
Waste Services
SHEWALTON LANDFILL 13,577,702 13,577,702 13,577,702 0 305,160 0 305,160 305,160 305,160 0 0 Complete Complete Complete Complete Complete
Total Waste Services 14,844,503 14,844,503 14,844,503 0 305,160 0 305,160 305,160 305,160 0 0 0
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 41,795 120,000 0 78,205 0 0 0 78,205 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 6,768,000 139,534 6,768,000 0 500,000 0 96,094 96,094 500,000 0 0 30-Apr-24 30-Apr-24 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 0 640 0 0 0 0 640 640 0 0 0 30-Oct-24 30-Oct-24 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 890,890 1,000,000 0 63,589 0 (45,521) (45,521) 63,589 0 0 31-Mar-23 31-Mar-23 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 356,000 0 356,000 0 356,000 0 0 0 0 (356,000) (356,000) 31-Mar-23 31-Mar-23 Planning On Target On Target 
ELECTRIC VEHICLES INFRASTRUCTURE 646,392 653,841 646,392 0 69,574 0 77,023 77,023 69,574 0 0 31-Mar-23 31-Mar-23 Various On Target On Target 
Total Renewable Energy 8,890,393 1,726,700 8,890,393 0 1,067,368 0 128,236 128,236 711,368 (356,000) 0 (356,000)
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments

Page 18

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
January 2023
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * 33,105 0 33,105 0 33,105 0 0 0 33,105 0 0 0 31-Mar-23 31-Mar-23 Mulitple projects On Target On Target 
PLI CALEY COURT RESOURCE CTR 3,000 0 3,000 0 3,000 0 0 0 3,000 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI CENTRAL AVE STREETSCENE DEPOT* 64,344 64,344 64,344 0 64,344 0 64,344 64,344 64,344 0 0 0 Complete Complete Complete Complete Complete
PLI BEITH CEMETERY 429 429 429 0 429 0 429 429 429 0 0 Complete Complete Complete Complete Complete
PLI WHITLEES COMMUNITY CTR 3,600 0 3,600 0 3,600 0 0 0 3,600 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI WEST KILBRIDE COMMUNITY CENTRE 135,499 98,575 135,499 0 135,499 0 98,575 98,575 135,499 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI WOODWYND HALL 2,000 0 2,000 0 2,000 0 0 0 0 (2,000) 0 (2,000) 21-Oct-22 31-May-23 Planning On Target On Target
PLI PORTLAND PLACE 27,967 0 27,967 0 27,967 0 0 0 18,000 (9,967) 0 (9,967) 31-Dec-22 30-Jun-23 Planning On Target On Target
PLI PADDOCKHOLM DEPOT 10,000 0 10,000 0 10,000 0 0 0 10,000 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI WEST BYREHILL DEPOT 160,513 28,385 160,513 0 160,513 0 28,385 28,385 160,513 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI GOLDCRAIGS DEPOT 134,000 15,405 134,000 0 14,024 0 15,405 15,405 15,405 1,381 1,381 31-Mar-23 31-Mar-24 Planning On Target On Target
PLI ANNICK PRIMARY SCHOOL 5,825 5,825 5,825 0 5,825 0 5,825 5,825 5,825 0 0 Complete Complete Complete Complete Complete
PLI ARDEER PRIMARY SCHOOL 2,952 2,952 2,952 0 2,952 0 2,952 2,952 2,952 0 0 0 Complete Complete Complete Complete Complete
PLI BLACKLANDS PRIMARY SCHOOL 210,000 191,777 210,000 0 210,000 0 191,777 191,777 210,000 0 0 Complete Complete Complete Complete Complete
PLI CALEDONIA PRIMARY SCHOOL 11,968 6,646 11,968 0 11,968 0 6,646 6,646 11,968 0 0 Complete Complete Complete Complete Complete
PLI DALRY PRIMARY SCHOOL 89,000 6,704 89,000 0 19,907 0 6,704 6,704 19,907 0 0 18-Aug-23 18-Aug-23 Planning On Target On Target
PLI FAIRLIE PRIMARY SCHOOL 7,374 0 7,374 0 7,374 0 0 0 7,374 0 0 Complete Complete Complete Complete Complete
PLI GLENCAIRN PRIMARY SCHOOL 175,759 155,088 175,759 0 175,759 0 155,088 155,088 175,759 0 0 Complete Complete Complete Complete Complete
PLI PENNYBURN PRIMARY 415,450 0 415,450 0 35,000 0 0 0 3,500 (31,500) (31,500) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ST BRIDGETS PRIMARY 5,500 0 5,500 0 5,500 0 0 0 5,500 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI SHISKINE PRIMARY 3,927 28 3,927 0 3,927 0 28 28 3,927 0 0 Complete Complete Complete Complete Complete
PLI ST JOHN OGILVIE PRIMARY SCHOOL 13,323 13,323 13,323 0 13,323 0 13,323 13,323 13,323 0 0 Complete Complete Complete Complete Complete
PLI ST PETER'S PRIMARY 1,971 1,971 1,971 0 1,971 0 1,971 1,971 1,971 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE PRIMARY* 325 325 325 0 325 0 325 325 325 0 0 0 Complete Complete Complete Complete Complete
PLI WOODLANDS PRIMARY 5,553 5,553 5,553 0 5,553 0 5,553 5,553 5,553 0 0 Complete Complete Complete Complete Complete
PLI AUCHENHARVIE ACADEMY* 821,820 100,109 821,820 0 471,820 0 100,109 100,109 550,000 78,180 78,180 31-Mar-23 30-Jun-23 Construction On Target On Target
PLI IRVINE ROYAL ACADEMY* 378,785 10,171 378,785 0 10,171 0 10,171 10,171 10,171 0 0 31-Aug-23 31-Aug-23 Pupil Toilets: Complete AW Pitches: TenderOn Target Significantly off
target
Resource pressures within PMI resulting in this project being
delayedPLI KILWINNING ACADEMY 270,000 17,677 270,000 0 220,000 0 17,677 17,677 87,677 (132,323) (132,323) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI 6A KILWINNING ROAD 7,619 7,619 7,619 0 7,619 0 7,619 7,619 7,619 0 0 Complete Complete Complete Complete Complete
PLI LARGS LIBRARY 5,000 0 5,000 0 5,000 0 0 0 5,000 0 0 Complete Complete Complete Complete Complete
PLI CUNNINGHAME HOUSE 98,273 3,482 98,273 0 98,273 0 3,482 3,482 3,482 (94,791) (94,791) 31-Mar-23 31-Aug-23 On Hold On Target Slightly off target  Works on hold depending on Land and Property review
PLI H&SCP 47 WEST ROAD 10,000 9,555 10,000 0 10,000 0 9,555 9,555 10,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI GALT HOUSE 12,486 0 12,486 0 12,486 0 0 0 12,486 0 0 Complete Complete Complete Complete Complete
PLI ACHNAMARA CHILDREN'S UNIT 25,000 0 25,000 0 25,000 0 0 0 25,000 0 0 Complete Complete Complete Complete Complete
PLI THE MEADOWS 5,900 0 5,900 0 5,900 0 0 0 5,900 0 0 Complete Complete Complete Complete Complete
PLI ANAM CARA 80,000 0 80,000 0 80,000 0 0 0 50,000 (30,000) (30,000) 30-Apr-23 31-May-23 Planning On Target On Target
PLI GARNOCK CAMPUS 11,443 0 11,443 0 11,443 0 0 0 11,443 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI THE PORTAL 6,611 0 6,611 0 6,611 0 0 0 6,611 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Office Accommodation 3,331,321 745,943 3,331,321 0 1,918,188 0 745,943 745,943 1,697,168 (221,020) 0 (221,020)
Other Property
INDUSTRIAL PORTFOLIO * 430,713 0 430,713 0 430,713 0 0 0 430,713 0 0 On Hold On Hold Multiple projects On Target On Target 
HOME 4,470,199 288,648 4,470,199 0 100,000 0 50,533 50,533 100,000 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
BUILD 284,086 46,249 284,086 0 247,284 0 9,448 9,448 247,284 0 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
EMERGENCY CONTROL CTR 158,000 1,220 158,000 0 158,000 0 1,220 1,220 158,000 0 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 509,000 0 509,000 0 25,000 0 0 0 25,000 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,640 104,190 134,640 0 26,928 0 (3,523) (3,523) 1,246 (25,682) (25,682) Complete Complete Complete On Target On Target
Total Property 5,986,638 440,307 5,986,638 0 987,925 0 57,677 57,677 962,243 (25,682) 0 (25,682)   
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Other Housing 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 0

Page 19

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
January 2023
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2022/23
Project Description
TOTAL PROJECT 2022/23 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
Regeneration
TOWN CENTRE REGENERATION 1,290,257 1,055,769 1,290,257 0 416,774 0 182,287 182,287 276,774 (140,000) (140,000) 30-Sep-22 30-Sep-23 Construction On Target On Target
REPURPOSING PROPERTY GRANT FUND 330,000 30,177 330,000 0 329,320 0 29,497 29,497 90,000 (239,320) (239,320) 30-May-25 30-May-25 In development On Target On Target
STEVENSTON BEACH HUB 180,000 180,000 180,000 0 84,525 0 84,525 84,525 84,525 0 0 Complete Complete Complete Complete Complete
MILLPORT TOWN HALL REGENERATION 2,103,330 1,757,966 2,103,330 0 1,569,838 0 1,224,474 1,224,474 1,317,309 (252,529) (252,529) 31-Dec-22 31-May-23 Construction On Target Slightly off target  Contractor is delayed, revised completion May 2023
MILLPORT TOWN HALL PHASE 2 509,450 77,634 509,450 0 509,450 0 77,634 77,634 349,952 (159,498) (159,498) 31-Mar-23 31-May-23 Construction On Target Slightly off target  Contractor is delayed, revised completion May 2023
ISLANDS PIT STOPS 540,000 0 540,000 0 540,000 0 0 0 20,000 (520,000) (520,000) 31-Mar-24 31-Mar-24 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 259,000 137,112 259,000 0 259,000 0 137,112 137,112 259,000 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
ISLANDS COST CRISIS FUND 17,000 0 17,000 0 17,000 0 0 0 17,000 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 1,343,000 421,478 1,343,000 0 1,312,223 0 390,701 390,701 1,075,000 (237,223) (237,223) 31-Mar-26 31-Mar-26 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 98,414 0 98,414 0 98,414 0 0 0 0 (98,414) (98,414) 31-Mar-25 31-Mar-25 In development On Target On Target
PBIP 36 BANK STREET 770,000 72,103 770,000 0 741,400 0 43,504 43,504 100,000 (641,400) (641,400) 31-Dec-24 31-Dec-25 In development On Target On Target
IRVINE HIGH STREET 2,837,316 2,706,355 2,837,316 0 165,818 0 34,857 34,857 54,327 (111,491) (111,491) Complete Complete Complete Complete Complete
MILLPORT CARS 255,611 231,239 255,611 0 255,611 0 231,239 231,239 255,611 0 0 31-Mar-23 31-Mar-23 Construction On Target On Target
MONTGOMERIE PARK MASTERPLAN 3,718,598 1,761,020 3,718,598 0 136,264 0 18,686 18,686 36,264 (100,000) (100,000) 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 2,010,638 1,323,779 2,010,638 0 1,441,786 0 754,927 754,927 1,441,786 0 0 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,195,999 3,984,927 4,195,999 0 1,377,575 0 1,166,503 1,166,503 1,377,575 0 0 Complete Complete Complete On Target On Target
VDLF - IRVINE KYLE ROAD SITE PREP* 1,421,110 1,421,110 1,421,110 0 180 0 180 180 180 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 267,066 165,790 267,066 0 245,893 0 144,617 144,617 175,000 (70,893) (70,893) 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF - ANNICKBANK PH 3* 1,481,000 116,261 1,481,000 0 475,000 0 59,220 59,220 475,000 0 0 31-Mar-24 31-Mar-24 Tender On Target On Target
VDLF - DEVELOPMENT WORK* 347,479 86,437 347,479 0 152,479 0 37,175 37,175 75,000 (77,479) (77,479) 30-Sep-23 31-Mar-24 In development On Target On Target
VDLF - STRATEGY 50,000 21,445 50,000 0 50,000 0 21,445 21,445 40,000 (10,000) (10,000) 31-Mar-23 30-Sep-23 In development On Target On Target
VDLF - TREE PLANTING 50,000 2,400 50,000 0 7,600 0 0 0 7,600 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 25,301 0 20,523 20,523 25,301 0 0 Complete Complete Complete Complete Complete
VDLF - GAS WORKS (DALRY)* 173,896 166,061 173,896 0 0 0 (7,835) (7,835) 0 0 0 Complete Complete Complete Complete Complete
CYCLING/WALKING/SAFER STREETS * 559,956 583,433 559,956 0 559,956 0 499,637 499,637 559,956 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 199,257 51,000 199,257 0 199,257 0 (8,878) (8,878) 51,000 (148,257) (148,257) 31-Mar-24 31-Mar-24 Various On Target On Target
FAIRLIE COASTAL PATH 50,000 50,000 50,000 0 50,000 0 12,089 12,089 50,000 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
PENNYBURN ROUNDABOUT BUS LANE 15,420 123,668 15,420 0 15,420 0 0 0 15,420 0 0 31-Mar-23 31-Mar-23 Feasibility On Target On Target
IRVINE CYCLE FRIENDLY TOWN 250,000 251,050 250,000 0 250,000 0 1,050 1,050 250,000 0 0 31-Mar-23 31-Mar-23 Various On Target On Target
BRODICK TO CORRIE CYCLE PATH 50,000 35,212 50,000 0 50,000 0 0 0 50,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
BUS CORRIDOR IMPROVEMENTS 204,955 74,955 204,955 0 130,000 0 0 0 130,000 0 0 31-Mar-23 31-Mar-23 Various On Target On Target
BUS ROUTE CONGESTION MEASURES 757,821 606,570 757,821 0 152,571 0 1,320 1,320 152,571 0 0 31-Mar-23 31-Mar-23 Construction On Target On Target
CUMBRAE FERRY & BUS STOP 223,690 53,405 223,690 0 200,000 0 29,715 29,715 200,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
B714 ACTIVE TRAVEL IMPROVEMENTS 100,000 29,435 100,000 0 100,000 0 29,435 29,435 100,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
B777 CORRIDOR IMPROVEMENTS 38,400 0 38,400 0 4,800 0 0 0 4,800 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
STTS U88 NORTH SANNOX 181,580 115,555 181,580 0 181,580 0 115,555 115,555 181,580 0 31-Mar-23 31-Mar-23 Planning On Target On Target
STTS ROSS ROAD ARRAN 221,340 281,245 221,340 0 221,340 0 221,340 221,340 221,340 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Regeneration 32,476,983 23,245,215 32,476,983 0 12,326,375 0 5,552,534 5,552,534 9,519,871 (2,806,504) 0 (2,806,504)
Ayrshire Growth Deal
AYRSHIRE GROWTH DEAL 0 286,806 0 0 0 0 286,806 286,806 0 0 0 31-Mar-26 31-Mar-26 On Target On Target
AGD - I3 DPMC PHASE 1 1,000,000 5,449 1,000,000 0 500,000 0 0 0 200,000 (300,000) (300,000) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 DPMC PHASE 2 5,000,000 179,970 5,000,000 0 100,000 0 0 0 70,000 (30,000) (30,000) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE 15,000,000 247,568 15,000,000 0 208,000 0 8,886 8,886 208,000 0 0 31-Mar-26 31-Mar-27 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,001 198,695 18,040,001 0 200,000 0 12,575 12,575 200,000 0 0 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target
AGD - GREAT HARBOUR 14,017,799 411,016 14,017,799 0 400,000 0 114,698 114,698 400,000 0 0 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target
AGD - IMSE 10,500,000 102,260 10,500,000 0 174,000 0 0 0 174,000 0 0 31-Mar-27 31-Mar-27 Design On Target On Target
AGD - MARINE TOURISM ARDROSSAN 11,428,354 292,225 11,428,354 0 137,638 0 81,484 81,484 137,638 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - MARINE TOURISM ARRAN 58,887 30,122 58,887 0 30,176 0 1,411 1,411 30,176 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - MARINE TOURISM CUMBRAE 66,747 35,972 66,747 0 32,186 0 1,411 1,411 32,186 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 75,111,787 1,790,082 75,111,787 0 1,782,000 0 507,270 507,270 1,452,000 (330,000) 0 (330,000)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,077,112 389,956 4,077,112 0 50,000 0 247 247 50,000 0 0 31-Dec-24 31-Dec-24 Design Slightly off target  On Target Increased tender cost risks identified
LOW CARBON HUB 1,430,017 112,005 1,430,017 0 123,698 0 25,204 25,204 123,698 0 0 30-Apr-24 30-Apr-24 Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 27,285,478 2,592,962 27,285,478 0 501,647 0 295,438 295,438 541,317 39,670 39,670 30-Apr-24 30-Apr-24 In development Slightly off target  Slightly off target  Projected spend increased to include additional site investigations
and service design costs.VDLF - HARBOUR MASTERS OFFICE 157,500 20,722 157,500 0 0 0 0 0 0 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 996,981 161,160 996,981 0 129,627 0 8,332 8,332 129,627 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
Other Growth & Investment 44,693,159 3,276,804 44,693,159 0 804,972 0 329,221 329,221 844,642 39,670 0 39,670
Total Economic Development & Regeneration 152,281,929 28,312,101 152,281,929 0 14,913,347 0 6,389,025 6,389,025 11,816,513 (3,096,834) 0 (3,096,834)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,162 3,378,163 0 0 0 (1,002) (1,002) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,898,460 2,977,098 0 40,595 0 (38,043) (38,043) 0 (40,595) (40,595) Complete Complete Defects Period Complete Complete
ARDROSSAN HOSTEL 0 0 10,203 10,203 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 6,390,674 6,311,034 6,390,674 0 40,595 0 (28,842) (28,842) 0 (40,595) 0 (40,595)
Total Place 310,958,614 82,921,978 310,953,081 (5,533) 41,297,742 0 19,279,774 19,279,774 34,670,473 (6,627,269) (5,533) (6,621,736)

Page 20

OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Year to Date Budget
2022/23
Actual Expenditure
to 31 January 2023
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023
Over/ (Under)
Spend for 22/23
£ £ £ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 9,474,863 0 7,562,125 (1,912,738) 1,912,738 0 0 0 0 (1,912,738)
CORE INFRASTRUCTURE INVESTMENT 608,000 0 0 (608,000) 608,000 0 0 0 0 (608,000)
Total Other Budgets 9,474,863 0 7,562,125 (1,912,738) 2,520,738 0 0 0 0 (2,520,738)
2022/23 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 21

Appendix 2
HRA Capital Statement APPENDIX 2
For the Ten months to 31 January
2023
Description
Approved
budget 16
February
2022
Current
budget
including
carry forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised Budget
2022/23
Actual Spend to
31/12/2022 P10 Projection True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Council House Build Programme
Council House Building General 1,542 1,542 - (1,542) - (6) - - On Target On Target
Acquisition Of Houses On Open Market 720 526 210 - 736 367 736 - On Target On Target
New Build Corsehillhead 1,450 600 - - 600 34 600 - On Target Slightly off target  Expected completion Autumn/Winter 2023.
New Build Brathwic Terrace 18 168 - 109 277 54 277 - On Target Complete Completed - final properties were handed over in June 2022
New Build Flatt Road Phase 1 1,712 1,072 (648) 357 781 102 781 - Slightly off target  Complete Completed - final properties were handed over in December 2021.  Remaining budget to be transferred to projects in Lots
E and F for 2023/24.
New Build Towerlands 25 160 20 - 180 18 180 - On Target Complete Completed - final properties were handed over in March 2022.
New Build Kinnier Road 3 2 (2) - - - - - Complete Complete Completed - properties were handed over in October 2021.
New Build St Colms 1,896 782 302 65 1,149 1,088 1,149 - Complete Complete
New Build St Michaels Wynd - 592 210 193 995 903 995 - On Target Complete Completed - final properties handed over in August 2002.
New Build Harbourside Irvine 6,460 6,000 (237) - 5,763 3,474 5,763 - On Target Slightly off target  Expected completion March 2023.
New Build Afton Court 910 1,080 24 115 1,219 24 1,219 - On Target Slightly off target  Expected completion Summer 2023.
New Build Caley Court 1,769 1,843 (35) 35 1,843 1,496 1,843 - On Target Slightly off target  Completed January 2023.
New Build Springvale Saltcoats - 133 7 1 141 8 141 - On Target Complete Completed - properties were handed over in November 2021.
New Build Dalrymple Place - 101 - - 101 3 101 - On Target Complete Completed - properties were handed over in October 2021.
New Build St Beya Millport 6 53 - - 53 51 53 - On Target Complete Completed - properties were handed over in July 2021.
Garnock Academy Site 7,950 1,800 - (1,700) 100 - 100 - Slightly off target  Slightly off target  Tender stage. Expected completion Spring 2025. 
Largs police Station 1,908 1,600 105 - 1,705 360 1,705 - On Target Slightly off target  Demolition complete. Expected completion Summer 2023.
Ayrshire Central Site 9,497 1,500 - (1,400) 100 13 100 - On Target Slightly off target  Pre-planning stage. Expected completion Spring 2026.
Bourtreehill Village 2,000 25 - - 25 17 25 - On Target Slightly off target  Pre-planning stage. New completion date to be established. 
James McFarlane ASN Site 3,050 2,250 - (2,150) 100 48 100 - On Target Slightly off target  Consultation stage. Expected completion Summer 2024.
James Reid ASN school 6,050 1,125 - (1,005) 120 103 120 - On Target Slightly off target  Consultation stage. Expected completion Winter 2024.
Stanecastle ASN School 3,300 1,850 - (1,750) 100 76 100 - On Target Slightly off target  Consultation stage. Expected completion Summer 2024.
Fullarton Street 4,090 25 - - 25 10 25 - On Target Slightly off target  Delays to delivery due to rehousing of tenants, which has now been completed. Demolition contractor appointed and
onsite, demolition expected to complete in Summer 2023. Expected completion 2025.
New Build Montgomerie Park 10,900 1,500 - (1,450) 50 6 50 - On Target Slightly off target  Pre-planning stage. Expected completion Winter 2026.
Glebe Place 10 50 (50) 25 25 - 25 - On Target On Target New build project deferred until 2025/26
Regeneration Project 1e 15 5 - - 5 - 5 - On Target On Target Pre-planning stage.
Unallocated Regeneration Block 1 55 - - - - - - - On Target On Target Pre-planning stage.
Laburnum Avenue (Regen 1a) 160 5 5 - 10 - 10 - On Target On Target Pre-planning stage.

Page 22

Appendix 2
Description
Approved
budget 16
February
2022
Current
budget
including
carry forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised Budget
2022/23
Actual Spend to
31/12/2022 P10 Projection True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Newhouse Drive (Regen 1b) 175 5 - (5) - - - - On Target On Target Pre-planning stage.
Regeneration Project 1d 360 5 - - 5 3 5 - On Target On Target Pre-planning stage.
Contingency 1,163 8,820 (8,820) - - - - -
CONNEL COURT (49) 49 1 1 (30) 1 - Complete Complete
GARRIER COURT (56) 25 32 1 (33) 1 - Complete Complete
Total For Council House Build Programme 67,194 35,114 (8,835) (10,069) 16,210 8,189 16,210 -
Improvement to Existing Homes - Building
Services
Window Replacement 325 364 11 (215) 160 8 160 - On Target On Target
Bathroom Programme 75 75 183 18 276 571 276 - On Target On Target
Kitchen Programme 2,610 4,450 - (159) 4,291 496 1,294 (2,997) On Target Slightly off target  324 units will now not be programmed due to labour shortage. Additional underspend showing due to previous years
underspend not required.  Previous years uncompleted units were included in the revised business plan last year,
therefore already accounted for.
Bathroom Programme Voids - - 1,024 (33) 991 - 991 - On Target On Target
Kitchen Programme Voids - - 1,297 (152) 1,145 - 1,145 - On Target On Target
Door replacement programme 2,191 2,191 (2,191) - - - - - Significantly off
target
Significantly off
target
Door replacement programme - tender has been re-issued following specification review due to unviable costs.  Balance
of budget requires to be earmarked for 2023/24.
Sheltered Housing Units 8,531 8,495 (8,245) - 250 114 250 - Significantly off
target
Significantly off
target
Projection reduced due to Procurement Issues and external contractor issues - remaining budget to be carried forward to
23/24.  Spend this financial year will only be consultants and staff costs. Construction estimated to commence late 22/23.
Tender for Barnett returned and checking quality.
Saltcoats MSF Investment 4,767 1,881 (663) (35) 1,183 611 1,183 - On Target Slightly off target  Additional works required.  Expected completion Winter 2022.
Total For Improvements to Existing Homes -
Building Services
18,499 17,456 (8,584) (576) 8,296 1,800 5,299 (2,997)
Improvement to Existing Homes - External
Contractors
Central Heating 2,524 4,442 (1,756) - 2,686 1,026 1,738 (948) On Target On Target Underspend showing due to previous years underspend not required.  Previous years uncompleted units were included in
the revised business plan last year, therefore already accounted for.
Insulated Re-Rendering 421 865 1,756 - 2,621 - 1,811 (1,480) On Target On Target Budget vired from roofing & rerendering offset additional spend in insulated rerendering. Following contractor surverys
some wall/floor render has been reprofiled as EWI and virement approved.
Electrical Rewiring 698 1,742 - - 1,742 101 210 (1,532) On Target On Target Underspend showing due to previous years underspend not required.  Previous years uncompleted units were included in
the revised business plan last year, therefore already accounted for. Also issues with contractor labour shortages and no
access.
0
Total For Improvements to Existing Homes -
External Contractors
3,643 7,049 - - 7,049 1,127 3,759 (3,960)
Refurbishment Schemes
Roofing & Rendering 4,450 5,507 - - 5,507 2,102 2,689 (2,145) Slightly off target  On Target Uncompleted units from previous years accounted for in future years. Previous years carry forward not required.
Following contractor surverys some wall/floor render has been reprofiled as EWI and virement approved.
Demolition High Flats Irvine 6,780 3,000 (1,302) (731) 967 145 967 - Slightly off target  Slightly off target  Tender received lower than budget estimate. Demolition contractor appointed and onsite, demolition expected to
complete in Summer/Autumn 2023.  Balance of budget requires to be earmarked for 2023/24.
Kings Arms Project 265 600 (440) (1) 159 110 159 - On Target Slightly off target  Consultation stage, construction is due to commence Winter 2022
Refurb Maress House - (12) 13 - 1 - 1 - On Target On Target HRA contribution to the project complete.
Refurb Friars Lawn - 254 (34) 34 254 23 254 - On Target Complete Final completion expected August 2022.
Total For Refurbishment Schemes 11,495 9,349 (1,763) (698) 6,888 2,380 4,073 (2,145)
-

Page 23

Appendix 2
Description
Approved
budget 16
February
2022
Current
budget
including
carry forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised Budget
2022/23
Actual Spend to
31/12/2022 P10 Projection True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Other Capital Works
Energy Efficiency Standard 5,362 5,488 (5,309) (180) (1) 180 (1) - On Target On Target
Other Capital Works 726 712 - (711) 1 - 1 - On Target On Target
Major Improvements 6 6 - (6) - - - - On Target On Target
Parkhall & Kirkhall Asbestos - 17 - - 17 - 17 - On Target On Target
Detection Equipment 458 1,463 (1,263) (50) 150 103 150 - Slightly off target  Slightly off target  Contractor continuing to work through addresses, forced entries process in place / limited capacity due to staff issues
(contractors) will span 2 years.  Balance of budget to be earmarked for 2023/24.
Solar Panels 3,862 3,888 7 (1,820) 2,075 512 2,075 - On Target On Target
Professional Management Charges 1,326 1,738 - - 1,738 523 1,738 - On Target On Target
Estate Based Regeneration 1,287 2,190 (1,187) - 1,003 282 1,003 - Slightly off target  Slightly off target  Programme currently being revised. Proposals to Cabinet in Autumn/Winter 2022. Balance of budget to be earmarked for
2023/24.
Nelson Street Regeneration 442 451 (426) - 25 - 25 - Significantly off
target
Significantly off
target
Final property obtained through CPO. Feasibility exercise being undertaken.  Balance of budget to be earmarked for
2023/24.
Health and Safety Works 207 207 - (207) - - - - On Target On Target
Total For Other Capital Works 13,676 16,160 (8,178) (2,974) 5,008 1,600 5,008 -
TOTAL EXPENDITURE 114,507 85,128 (27,360) (14,317) 43,451 15,096 34,349 (9,102)
CFCR (12,209) (12,209) - - (12,209) (1) (12,209)
Capital Grants (14,175) (7,138) 5,371 - (1,767) (87) (1,767) - Slippage in house building resulting in reduction in grant claims.
Affordable Housing Contribution (1,596) (1,596) - (1,596) - (1,596)
Prudential Borrowing (85,376) (63,034) 21,989 14,317 (26,728) - (18,000) 9,102
Council House Build Fund (1,151) (1,151) - (1,151) - (777)
TOTAL INCOME (114,507) (85,128) 27,360 14,317 (43,451) (88) (34,349) 9,102
NET EXPENDITURE - - - - - 15,008 - -
The following classifications have been used to highlight financial performance against budget
On Target On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)