NORTH AYRSHIRE COUNCIL 
24 January 2023 
Cabinet 
Title:    Community Asset Transfer – Toilet Block and adjacent
land at Ardrossan South Beach 
Purpose:  To seek approval, in principle, for a 25-year lease of the toilet
block and adjacent land at Ardrossan South Beach to Ardrossan
Community Development Trust. 
Recommendation:  That Cabinet: 
a) Agrees, in principle, to the 25-year lease of the Toilet Block and
adjacent land at Ardrossan South Beach between North
Ayrshire Council and Ardrossan Community Development
Trust, subject to the satisfactory conclusion of the Council’s
Community Asset Transfer process, including the requirements
detailed in paragraph1.3; 
b) Approves the recommended terms of transfer on this occasion
as a £6,000 in annual rental fee (a total of £150,000 over the
25-year period of the lease); and 
c) Authorises officers to conclude the associated legal and
community asset transfer processes with regard to the lease. 
1. Executive Summary 
1.1 The report proposes agreement that a lease should be developed, under the community
asset transfer process, of the existing toilet block and adjacent land at Ardrossan South
Beach, South Crescent Road, Ardrossan between Ardrossan Community Development
Trust and North Ayrshire Council. 
1.2 The lease to Ardrossan Community Development Trust (ACDT) will allow the area to
be developed with funding secured from The National Lottery Communities Fund,
Scottish Government’s Regeneration Capital Grant Fund, North Ayrshire Council and
other funders. This will enable ACDT to progress works, for which planning permission
has been granted, in order to enhance local facilities including the creation of a new
children’s play facility and beach visitor facilities.   
1.3 This report is being brought to Cabinet at an early stage in the Community Asset
Transfer (CAT) process because of the time-critical nature of the funding. It
recommends that Cabinet agrees, in principle, to the lease subject to the satisfactory
completion of the CAT process including:

Page 2

• Locality Officers’ assessment of the full application;
• Assessment by Legal Service of the full application, including assessing ACDT
governance documents in line with the CAT requirements of the Community
Empowerment (Scotland) Act 2015;
• Assessment by Financial Services and Property Maintenance and Investment teams to
ensure that the public interest is protected and that the organisation can maintain the
assets;
• Assessment of the ACDT Business Plan by Council’s Business Team to ensure that the
organisation is a ‘going concern’ and can meet the financial implications of the CAT;  
• Agreement with Planning, Regeneration, Roads, PMI, Streetscene and CPP partners,
as appropriate, to ensure that the public safety and access is protected; and
• Delivery of the full statutory public consultation and any subsequent objections
satisfactorily concluded. 
1.4 It is recommended that a £6,000 annual rental fee (a total of £150,000 over the 25-
year period of the lease) be applied to this CAT, reflecting the investment to date and
the potential social return on investment. 
1.5 Once the assessment is completed and is satisfactory, it is requested that Council
Officers are authorised to progress through the full stages of the CAT process, with
any outstanding issues brought back to Cabinet for decision. 
2. Background 
2.1 Under the terms of the Community Empowerment (Scotland) Act 2015, community
asset transfer provides an opportunity for people to be involved in developing and
providing opportunities or services for their local communities. It may also allow
groups to develop commercial ventures, which will support community benefit. Asset
transfer may also mean that public assets get used more frequently and more
effectively. Furthermore, community-led ownership may allow additional opportunities
for groups to secure extra funding or resources.  
Ardrossan Community Development Trust 
2.2 Following the Three Towns’ Charrette in summer 2017, Ardrossan Community
Development Trust was established in 2019 to take forward the local ideas and to
engage in activities that benefit and support the community of Ardrossan. ACDT works
to attract funding to resource local projects and activities and administer those funds in
accordance with their constitution. ACDT works towards increasing local opportunities,
endeavours to improve the physical environment, attract more visitors and revive the
sense of pride in the town. Their key aims (benefiting principally the community of
Ardrossan) are:   
• The advancement of community development including the advancement of urban/rural
redevelopment;
• The maintenance, regeneration and improvement of the community’s physical
economic, social and cultural infrastructure; and
• The advancement of education, training, arts, culture, heritage, sports, recreation,
environmental improvement, social and economic wellbeing.

Page 3

2.3 The Trust was established to succeed the National Lottery’s Our Place programme and
continue with community development within Ardrossan, including the completion of
the proposed playpark for the town.  This secured the £250,000 investment from
National Lottery’s Our Place programme and the preferred site is on land owned by
North Ayrshire Council at Ardrossan South Beach. ACDT has a full Board and recently
secured Community Investment Funding from The Three Town’s Locality Partnership
for a Community Development Officer. The Trust has held consultations and public
engagement and is now one of the largest Community Development Trusts in Scotland
with over 400 members. ACDT is supported by both the Development Trusts
Association Scotland (DTAS), CEIS and the Connected Communities team to
strengthen and develop the skills and expertise of Directors. A new engaging and
informative website was launched in 2020 and provides detailed information on projects
being developed within Ardrossan and can be found at www.ardrossantrust.org. 
Ardrossan South Beach Proposals 
2.4 While the planning for the playpark has been developing, two further projects were
launched: 
• Deckchair loans, which is part of the objective to develop ideas and actions to help
coasts and waters, including being more resilient to climate change: and 
• Beach-accessible wheelchair loans. A container was installed beside a disused toilet
block to house the free deckchair and wheelchair services. 
2.5  A proposal was also put to the Council to re-purpose the toilet block to provide modern 
beach visitor facilities, including a café, and planning permission was granted. A
Scottish Government Regeneration Capital Grant Fund award of £748,000 was
secured for this project. In August 2022, planning permission was granted to demolish
the toilet block and re-build with a more environmentally sustainable building within the
same footprint as the existing building. 
2.6   The lease of the toilet block and adjacent land at Ardrossan South Beach (Plan of
Ardrossan South Beach Toilet Block and adjacent land – Appendix I) will provide a
sustainable base for local community activity that meets the aims of ACDT.   
2.7 The proposed improvements will be completed in a phased approach: 
2.7.1 Phase 1 – July 2023 
• A hub area will be created on the grounds of the existing toilet block creating a focal
point for visitors to the promenade. The hub will include public toilet facilities and will be
fully accessible with an additional changing place facility. 
• The hub will also include a new café area giving the wider community a new space
where they can meet and interact. 
• At the rear of the hub there will be a storage space to service the crazy golf and hire of
the free to use Hippocamp wheelers and deckchairs. 
• The new area will include Swing Play, adding accessible basket swings and a
wheelchair accessible swing.
• Rotating play equipment will include roundabouts accessible to people in wheelchairs.
• The former 18-hole crazy golf course will be fully reinstated with 2.4metre flagpoles in
bright colours.

Page 4

• Beach Huts will be constructed of steel cladded in painted timber to be used by
community groups and for social enterprise
• A Hedge Maze will add play value and provide some shelter.   
2.7.2 Phase 2 – dependent on future funding 
• The creation of an Events Area is a future phase which is not yet funded. ACDT have
secured Planning Permission for this development and any changes will be made in
partnership with Council officers and subject to public consultation as part of securing
new Planning Permission. 
2.8 The advice of Streetscene has been provided with regard to on-going grounds 
maintenance, sustainability and the suitability of planting in salt winds. ACDT has
adjusted its proposals as a result of this. Streetscene has agreed to work with ACDT to
ensure that within the terms of the lease the ongoing maintenance is in line with the
existing Streetscene standard and will be subject to annual review.   
2.9 The project will deliver transformational change for Ardrossan, improving the
appearance and attractiveness of the promenade. The creation of a new play facility
will bring accessible facilities for disabled users, especially those who are wheelchair
ambulant. It will include wheelchair swings and roundabouts and additional accessible
features. This additional swing park area will complement the existing playpark. The
existing playpark will remain within Streetscene’s remit. ACDT is working with
Streetscene regarding the regulatory weekly inspection of the play equipment. 
2.10 The addition of new beach huts will create new community assets, promoting social 
enterprises and providing a place on the promenade where local businesses can
provide services to the community and its residents. 
2.11 Full Planning Permission has been granted, however ACDT does not intend   
progressing the following elements on the advice of the Council’s Streetscene team
due to the intensive and costly maintenance: 
• The Wavefield
• Climbing Boulders (to complement the Wavefield)
• Ship Wind Vanes
• Mini Castles on the Mound 
• What’s Washed up on the Beach. 
The revised phased approach is detailed in Appendix 2. 
Community Asset Transfer Process
2.12 The community asset transfer process will not transfer from the Council. Leasing 
under the community asset transfer process permits the Council to exercise its rights
under the Community Empowerment (Scotland) Act 2015 to evaluate its Best Value
duty in terms of social value, rather than monetary best value. Granting a lease in this
way means that the community organisation is not charged commercial rates, as the
Council recognises that the greater opportunity is for the community to benefit from local
community operational management. This CAT will facilitate the development of range
of events and activities within the enhanced area, encouraging a wider range of people

Page 5

to get involved, giving opportunities for local volunteering and stimulating involvement
in shaping and regenerating community life, building self-esteem and confidence. In
addition, the creation of the beach huts will support local business enterprise, with
profits being used to sustain ACDT’s projects.   
2.13 Although Ardrossan South Beach attracts a significant number of visits, especially in 
the height of summer, there are currently limited facilities on the promenade to support
visitors. The planned projects will regenerate the area and will not only give the local
community a sense of pride in their promenade but provide a place where they can
meet and be active. The facilities will encourage tourism to the local area and in turn
improve the local economy, increase social enterprise and employment opportunities. 
2.14 Securing ownership through a 25-year lease, enhancing the assets and increasing the 
range of events and activities within an improved facility will encourage a wider range
of people to get involved. Participants will benefit from being more physically active and
engaged in sport. This will support several strategic and policy areas relating to the
delivery of North Ayrshire’s Active Communities Strategy, the Local Outcome
Improvement Plan’s Wellbeing priority, the National Performance Framework’s
priorities of physical activity and positive mental health and wellbeing, and Public Health
Priority 6, Diet and Healthy Weight.  Opportunities for local volunteering will increase,
stimulating involvement in shaping and regenerating community life, building self-
esteem and confidence. 
Alignment with Strategic Plans 
2.15 The Regeneration Delivery Plan sets out the Council’s Plans for delivering on the 
ambitions of the Council Plan and Community Wealth Building Strategy.  This seeks to
redevelop strategic regeneration sites, working in partnership with communities.  The
CAT will therefore contribute to the delivery of the Regeneration Delivery Plan themes
of: 
• Strengthening Communities; 
• Inclusive and Green Economy; 
• Placemaking; and 
• Enabling Infrastructure.   
2.15.1 It will contribute to the objectives of the Scottish Government’s Regeneration 
Strategy by supporting the creation of a sustainable place, created through and
supported by a holistic and collaborative approach. 
2.15.3 The development will contribute to the priorities of Scotland’s Economic Strategy by 
prioritising investment to ensure that Scotland protects and nurtures its natural
resources and captures the opportunities offered by the transition to a more resource
efficient, lower carbon economy. It will contribute to achieving the outcomes outlined in
the Scottish Government’s Programme for Government 2021-22 of: “We value, enjoy,
protect and enhance our environment; We live in communities that are inclusive,
empowered, resilient and safe; We are healthy and active; and We tackle poverty by
sharing opportunities, wealth and power more equally.” 
2.15.4 It will deliver against the key priorities of Town Centre Action Plan of town centre

Page 6

first, town centre living, vibrant local economies, enterprising communities and
accessible public services. In doing so it accords with the Town Centre First Principle
by putting town centre health at the heart of decision making and seeking to deliver the
best local outcomes to support vibrancy, equality and diversity. The project aligns with
the North Ayrshire Local Development Plan aspirations to support delivery of
community priorities, sustainable tourism opportunities and enhancement of local
landscape. 
2.15.5The proposal demonstrates the delivery on the ground of the Place Principle as it will 
promote a shared understanding of place for the Promenade. It will be delivered through
a collaborative approach to achieve better outcomes for users and local communities.
This will result in the facilities becoming more flexible and able to respond to and be
used for local needs and aspirations. This will contribute to achieving the full potential
of the seafront including the identified buildings in line with the CWB Strategy. 
2.15.6 The rebuilding of the toilet block accords with the Climate Change Plan and North 
Ayrshire Environmental Sustainability and Climate Change Strategy.  It will contribute
to achieving the target of net-zero carbon emissions by: 
• Utilising sustainable construction methods and materials to minimise the impact of the
works 
• Making the former toilet block more energy efficient thereby reducing energy
consumption and waste
• Bringing a current unused / underutilised resource back into positive use and
management 
• Promoting and supporting active travel for journeys to and from South Beach and across
Ardrossan
• Improving the awareness and understanding of local communities and visitors on
sustainability, climate change and the transition to net-zero. The regenerated facilities
will be utilised to showcase and raise awareness of this agenda. 
This aligns with the recently adopted North Ayrshire Environmental Sustainability and
Climate Change Strategy and will contribute to the delivery of its workstreams. 
2.16 The project and proposed approach to delivery accords with the Community 
Empowerment Act and aligns with Part 5 of the Act to buy, lease, manage or use land 
and buildings belonging to Local Authorities. The project contributes to the delivery of 
the Capacity Building Priority in the North Ayrshire Community Learning and 
Development Strategic Plan 2021-24.  This aims to support community organisations 
and groups seeking to secure local management/control of community assets, 
through lease, ownership, or management. 
Partnership approach 
2.17 A strong working relationship has existed between ACDT and the Council since the
Trust’s inception. The Three Towns Locality Partnership and Community Planning
Partnership, local Elected Members and the Council have been supportive of the
developments at Ardrossan South Beach. This has led to the support in principle for
Community Investment Funding to support the project and the Trust.  The Three Towns
Locality Officer and Community Development officers provide day to day support to the
group and are fully supportive of the project. This has been further augmented with

Page 7

officer resource from the Regeneration Team to assist in the preparation of funding
applications and the delivery of the project. The commitment to this support will be
sustained by the Council throughout the delivery of the project. 
2.18 The Trust also works in partnership with a range of local regional and national
organisations including Sustrans, Cunninghame Housing Association, Whitlees Centre,
Ardrossan Community Association, Ardrossan Castle Heritage Society, and the local
branch of the British Legion.  The Trust also incorporates the Ardrossan Christmas
Lights Committee who have helped improve infrastructure and better seasonal lighting.
Public Consultation 
2.19 In February 2020 an external consultancy, Wave Particle, carried out a two day,
community workshop to discuss how the community could use green spaces for a
playpark and crazy golf course. In addition, in August and September 2021, ACDT and
its project partners organised a Community Engagement Day event. The event
encouraged residents of Ardrossan and South Beach to see the plans for the
regenerations of the area, ask questions, raise any concerns and meet with key project
partners to get a clear idea of the regeneration proposals. A total of 194 people attended
the event. ACDT also commissioned IBP research to carry out a survey within the
community to ascertain what the community wanted for the promenade. The feedback
from these events and activities have helped shape the planned developments. 
2.20 Based on a survey of 438 local people carried out in September 2021: 
• 89% believed that Ardrossan would become a more attractive place to live and work
when the South Beach Regeneration is completed, whilst 92% believed it would deliver
better facilities and amenities for the people of Ardrossan.
• 77% thought that the focus on providing people with opportunities to be more active
would lead to increased physical health and fitness. With links between outdoor activity
and mental health well established, 82% of people said the project will lead to improved
mental health and wellbeing.
• Most people (89%) said the physical regeneration of the South Beach promenade and
the investment made in the town, would increase people’s pride of living in Ardrossan. 
• 95% said that the development will increase the use of the beach and its facilities by
disabled people, making Ardrossan a better place to live for people with disabilities and
sensory impairments - with the opportunity to access the beach and use the promenade
for leisure increase the potential to improve physical and mental health of disabled
people.
• Most respondents (87%) thought that the redevelopment of South Beach will have a
positive impact on the safety of the local area whilst 89% acknowledged South Beach
was a great place for the community to meet and socialise, and the project would
therefore help increase community cohesion.  
• Although the current playpark is well-used by children, it is perceived to be not very
attractive and lacking excitement. 82% of interviewees believe new and improved play
facilities will challenge children and young people to become more active and learn by
doing so.

Page 8

• Economically the benefits envisaged from the project will also be significant. 91%
believed that the project will attract more visitors to Ardrossan for leisure purposes who
will spend money on their visit – with residents of Ardrossan similarly more encouraged
to stay locally for leisure purposes rather than go elsewhere.
• 92% of people believed that the development would act as a catalyst for further
investment and funding from elsewhere. 
2.21 To better understand the transformational nature of the project and the potential value
created for its stakeholders of the impacts set out above, a Social Return On Investment
(SROI) forecast was commissioned for from Social Value Lab. SROI provides a
framework for measuring and accounting for the full social, economic and environmental
impact of activities, including finding ways to put a monetary value on these impacts
and calculating a ratio of return for those organisations that are contributing to create
the changes which the project is enabling locally. 
2.22 This SROI forecast covers the capital investment of the first phase of the South Beach
Promenade Regeneration project.  The study examined the research and stakeholder
consultation and mapped the anticipated range of outcomes against the Scottish
Government’s regeneration outcomes defined in the “Achieving A Sustainable Future”
Regeneration Strategy. SROI uses financial proxies to establish a monetary value of
intangible outcomes and then expresses the Social Return value as a ratio, with the
value of the impact divided by the value of the investment. The study concluded that for
every £1 of investment in the project £5.68 of Social Value would be created. 
The Community Empowerment Act 
2.23 The Community Empowerment Act provides that while relevant authorities have a duty
to secure Best Value in their operations, including when disposing of or letting property,
it has long been recognised that best value does not always mean the highest possible
price. All authorities have the ability to dispose of property at less than market value
where there are wider public benefits to be gained. This is set out in the Disposal of
Land by Local Authorities (Scotland) Regulations 2010, and in the Scottish Public
Finance Manual for other relevant authorities. The financial and non-financial impacts,
both positive and negative, of the different options must be balanced. The price
proposed reflects the investment the Trust plans to make, and full community ownership
will facilitate the implementation of comprehensive business plan proposals for
envisaged development. 
2.24 All Community Asset Transfer agreements are safeguarded with ‘claw-back’ provisions.
Other safeguards will be set out in the lease and any additions to plans will require new
Planning Permission, including public consultation. 
2.25 This report is being brought to Cabinet at an early stage in the Community Asset
Transfer (CAT) process because of the time-critical nature of the Scottish Government’s
Regeneration Capital Grant funding, which needs to be committed before the end of
March 2023. That requires the tender process to be complete, and the lease must be

Page 9

secured in order to start tender processes. The increase in building costs adds a second
time imperative with the need to act swiftly on quotations to avoid cost escalation. 
Concluding the Community Asset Transfer Process 
2.26 It is recommended that a £6,000 annual rental fee (a total of £150,000 over the 25-year
period of the lease) be applied to this CAT, reflecting the investment to date and the
potential social return on investment. 
2.27 Once the officer assessment has been satisfactorily completed, it is requested that
Council Officers be authorised to progress through the full stages of the CAT process. 
2.28 Any outstanding issues will be brought back to Cabinet for decision. 
3. Proposals 
3.1 It is proposed that Cabinet: 
a) Agrees, in principle, to the 25-year lease of the Toilet Block and adjacent land at
Ardrossan South Beach between North Ayrshire Council and Ardrossan Community
Development Trust, subject to the satisfactory conclusion of the Council’s Community
Asset Transfer process, including the requirements detailed in paragraph 1.3; 
b) Approves the recommended terms of transfer on this occasion as a £6,000 in annual
rental fee (a total of £150,000 over the 25-year period of the lease); and
c) Authorises officers to conclude the associated legal and community asset transfer
processes with regard to the lease. 
4. Implications/Socio-economic Duty 
Financial 
4.1 Through the transfer of the assets, the Council will achieve an income of £6,000 per
annum for the 25-year period of the lease. This totals £150,000 over the 25-year period.
There is loss of income to NAC in relation to the transfer of these assets due to the loss
of the direct income to the Council from the fair ground operator and other ad hoc
events. In addition, in partnership with NAC, ACDT have already attracted RCGF
funding totalling £748,000 to fund the hub. Legacy Big Lottery (now The National Lottery
Communities Fund) funding totalling £249,584 towards the play area has been secured
and North Ayrshire Council has allocated funds of £10,416 towards Active Travel
infrastructure. 
Human Resources 
4.2 None. 
Legal 
4.3 The approval is subject to satisfactory assessment by Legal Services and the support
of the Legal Services team in relation to the development of a lease. The Local
Government (Scotland) Act 1973 places a statutory obligation on the Council to obtain
the best price or the best rent when it disposes of any asset by sale or lease.  These

Page 10

regulations permit a disposal at less than the best price achievable where either (a) the
property is valued at less than £10,000, or (b) the Council has compared the financial
cost of transfer against the community benefits and determined that the transfer is
reasonable and promotes either economic development or regeneration, health, social
well-being or environmental well-being. 
Equality/Socio-economic 
4.4 There will be considerable socio-economic benefits from the community asset transfer
of the toilet block and adjacent land and these are outlined in the feedback from local
people. The sum proposed reflects the community benefits. These include a variety of
positive impacts, for the community of Ardrossan and the surrounding area. 
Climate Change and Carbon 
4.5 The transfer seeks to provide sustainable community facilities outlined at paragraph
2.15.4. The initiatives, which the CAT will support, encourages the Active Travel
network and includes the building of a more environmentally sustainable building with
integrated roof-mounted solar panels. 
Key Priorities 
4.6 The proposals contained within the report support the following North Ayrshire Council
Plan priorities: 
•  Active and strong communities; 
•  Inclusive, growing and enterprising local economy; 
•  People enjoy good life-long health and wellbeing; and  
• Vibrant, welcoming and attractive places. 
Community Wealth Building 
4.7 This proposal supports the following pillars of community wealth building: 
• Advancing community enterprises; 
• Advancing local ownership of underused land and buildings; and  
• Supporting local business activities and increasing the variety of ownership models. 
5. Consultation 
5.1 Officers have sufficient confidence that there is public and Council services support to
bring this CAT request at an early stage because of the amount of consultation already
carried out. This will facilitate the delivery of the project. The initiation of ACDT and the
projects in this report stemmed from The Towns Charrette with local people in 2017.
Further specific consultation and engagement has been carried out and is detailed in
the report. The statutory public consultation required in terms of the Community
Empowerment (Scotland) Act 2015 for a community asset transfer application is
currently ongoing. 
5.2 Elected Members have been briefed and are supportive.

Page 11

5.3 Consultation is currently taking place with Economic Development, Streetscene,
Finance, Estates, Property Maintenance and Investment, and Legal Services regarding
operational implications and the development of the lease. All parties are supportive of
the proposal for the listed assets. Streetscene’s advice has been welcomed by ACDT
and has informed changes to proposals to ensure that grounds maintenance stays
within current Streetscene affordability and is annually reviewed. 
Audrey Sutton 
Executive Director (Communities & Education) 
For further information please contact Rhonda Leith, Head of Service (Connected
Communities), on (01294) 324415. 
Background Papers
Appendix 1: Plan of Ardrossan South Beach Plan 
Appendix 2: Ardrossan South Beach Phased Approach