NORTH AYRSHIRE COUNCIL
01 November 2022
Cabinet
Title: Estate Based Regeneration Programme (EBRP)
Update
Purpose: To provide a progress update to Cabinet on the delivery
of the HRA Estate Based Regeneration Programme
(EBRP) and to seek approval for a refreshed Programme
for 2022-2029.
Recommendation(s): That Cabinet (i) notes progress on, and revisions to, the
EBRP to March 2022 as noted in Appendix 1; (ii) notes
the revised programme for 2022/23 to recognise slippage
in previous years; (iii) approves the detailed programme
for 2023/24; and (iv) notes that the remainder of the
projects in the Estate Based Regeneration Programme
scheduled for delivery in 2024/25 and beyond, as shown
in Appendix 2, may be subject to revision.
1. Executive Summary
1.1. In January 2019, Cabinet approved a 10-year, £10million Estate Based
Regeneration Programme (EBRP) which aimed to improve Council-owned
housing estates across North Ayrshire.  Implementation of the specific projects
in years one to three of the Programme was agreed, with an annual review to
be presented to Cabinet.
1.2. This report provides an update on projects which were scheduled for 2020/21
and 2021/22, some of which continued to be impacted by the COVID-19
pandemic and other global economic issues affecting the construction industry
and have still to be delivered.  A revised Programme for 2022-2029 is also
included, following a scoping exercise of projects scheduled for 2022/23 and
2023/24.
1.3. Cabinet is asked to note progress on projects undertaken in 2021/22 and
previous years provided at Appendix 1; note the updated Estate Based
Regeneration Programme 2022-2029 as noted in Appendix 2; and approve the
specific projects scheduled for 2023-24.
2. Background
2.1. In January 2019, Cabinet approved a 10-year Estate Based Regeneration
Programme, representing indicative minimum investment in our stock and
estates of some £10m, which is included in the Housing Revenue Account 30-
year Business Plan.

Page 2

2.2. The concept of an Estate Based Regeneration Programme was borne through
an aspiration to further invest in our estates to address pockets of low demand
stock; antisocial behaviour; external appearance; parking provision; road and
footpath condition; fencing; landscaping; and general grounds maintenance
issues.
2.3. This approach complements the Council’s ambitious housing development
programme via the Strategic Housing Investment Plan 2022-2027 (SHIP).  The
SHIP sees a commitment to build 1,625 new Council homes by March 2027. 
Several EBRP projects will involve selective demolition of existing stock, which
will attract further investment associated with the replacement new build
provision.  A total allocation of 250 units has been identified in the SHIP for that
purpose.
2.4. The Programme was initially developed though a comprehensive map-based
review of our estates, incorporating condition information, local intelligence,
environmental and visual audits, enquiries and complaints, and ownership
details.  
2.5. The mapping work identified a variety of potential improvements within our
estates, including the need for demolition and redevelopment of low demand
stock, external improvements to existing stock, additional parking provision,
new fencing, new lighting, and bin stores.
2.6. Potential improvements were subsequently assessed using the Scottish
Government’s ‘Place Standard’ tool.  Projects were prioritised based on their
evaluation score, complexity, and programming requirements as well as
anticipated budget availability, and a programme was developed. 
Progress to Date 
2.7. The large-scale improvement project in 2021/22 – Glass Fronted Closes, Irvine
- significantly exceeded the indicative costs provided at programme inception. 
The indicative costs were prepared prior to the full scope of each project being
agreed.  However, due to costs for other projects for the 2020/21 EBRP being
less than estimated, the overall programme remained within budget. 
2.8. Global economic issues which have impacted the construction industry and the
COVID-19 pandemic had - and continue to have - a significant impact on
delivery of the projects scheduled for 2021/22 and 2022/23 in the EBRP. 
Shortages of materials and increasing costs have impacted each project. As a
result, most projects planned for completion during 2021/22 have been re-
programmed or are only partially completed.   
2.9. From 2020/21 onwards the Programme has been funded through a dedicated
capital budget. The total spend for 2021/22 was £0.440m against provision
within the HRA capital budget of £1.530m (this figure includes a carry forward
of £0.530m from previous financial years).  The underspend will be carried
forward to support the reprogrammed projects.

Page 3

2.10. A new Housing team was established during 2021 to support the delivery of the
Estate Based Regeneration Programme. One of the objectives of the team is to
assist in co-ordinating information following scoping works for projects in future
years and engaging with tenants on individual proposals. 
Programme Revisions 
2.11. Following development of the initial EBRP in early 2019, a Project Board was
established.  The group remit of the group includes oversight of the scope,
design, and implementation of projects, in addition to continuous review of the
Programme to address emerging issues and ensure alignment with strategic
objectives. 
2.12. The following revisions have been made to the original schedule in the 2021-
2029 Programme: 
o The proposed regeneration projects at Bourtreehill Village and Fullarton,
Irvine have been removed from this programme as both projects are being
progressed and reported through the Strategic Housing Investment Plan
2023-2028 (SHIP). 
o Identification of redevelopment options for derelict land at Fergushill Road,
Kilwinning and Regeneration Project 13, Stevenston have been removed
from the Programme.  Both are subject to discussions with developing
partners through the SHIP. 
o The budgets for parking and render improvements in the original programme
have been combined to create a budget for ad-hoc minor projects. This will
allow flexibility for minor estate issues to be resolved expeditiously. 
o Allocated budgets in the original programme have been revised based on
the scoping information gathered to date.  Larger projects have also been
split over financial years where required to reflect the estimated time for
acquisitions (where appropriate), procurement and consultation.   
o The noted interventions detailed in appendix 2 regarding the confidential
regeneration projects have been revised to ‘develop regeneration plan’ to
allow a full scope of works and project plan to be developed to better inform
the programme. 
Estate Based Regeneration Programme 2022-2029 
2.13. The updated programme comprises a range of projects across localities and
covers a period of seven years. It is predicated on provision within the Housing
Revenue Account (HRA) capital budget of £1m per annum for each of the
seven years plus funds carried forward from previous financial years; the total
remaining budget is £8.822m. 
2.14. A review of all proposed projects for the current and forthcoming year has been
undertaken, and their indicative costs updated. The budgeted costs for the

Page 4

projects within the wider programme are indicative at this stage. Cabinet
approval is sought for the projects scheduled for 2023/24.  For the projects
planned for 2024/25 to 2028/29 timescales shown are indicative and are
subject to further detailed project design and costings.  Areas where there is
mixed ownership will require review to ensure planned investment aligns with
Guidance on the Operation of Local Authority Housing Revenue Accounts
(HRAs) in Scotland. 
2.15. To maximise the impact of regeneration and ensure a holistic approach is taken
to improving our estates, consideration will be given to upcoming capital
investment due in an area such as roofing, rendering, windows, external doors,
kitchens, and bathrooms.  Future reports to Cabinet on the programme will
outline the total investment in an area from the EBRP budget, and report on
spend through other budgets to complement the improvement programme. 
2.16. The Scottish Government published their new Housing to 2040 strategy in
March 2021, which will see a focus on energy efficiency upgrades and installing
low carbon heating systems to decarbonise our housing stock in the coming
years.  The external advisor supporting the Council in developing a Local Heat
and Energy Efficiency Strategy (LHEES) was commissioned to undertake
research and provide a report on the solutions available and financial impact of
achieving the Energy Efficiency Standard for Social Housing (EESSH2) across
our housing stock.   
2.17. The output from this review, alongside property lifecycle data, is informing
future capital investment needs and will identify the properties where the
investment required is not economically viable and other solutions may be
preferable, such as demolition.  It will also inform future reviews of the Estate
Based Regeneration Programme. 
2.18. The investment programme will continue to be updated annually to ensure it
remains up to date and the most effective use of funding is achieved. With each
annual review, Cabinet will be asked to approve the next phase of projects in
the programme. 
2.19. The latest projected cost of the EBRP programme from 2022/23 to 2028/29 is
£9.118m against the remaining budget available of £8.822m, i.e., an overspend
of £0.296m is currently forecast. Furthermore, as noted above all projects from
2024/25 onwards still require a full scoping exercise to be undertaken and
detailed project costs determined, therefore the individual project budgets
currently noted within the programme may be subject to change. 
2.20. Given the current global financial situation and increased construction industry
inflation rates, it is likely that the original £10m budget earmarked in the HRA
Business Plan for the EBRP would be significantly exceeded if all the projects
currently identified went ahead. 
2.21. In addition to the issues noted above, it should be noted that a fundamental
review of the HRA Business Plan is currently underway to inform options for

Page 5

rent levels for 2023/24. This review may require a number of capital and
revenue spending plans, including the EBRP, to be revisited and reviewed. 
2.22. Recognising the lead time for fully developing projects and appointing
contractors etc, it is therefore proposed that Cabinet approves the projects
within the EBRP for 2023-24 only at this stage. The EBRP for 2024-25 and
beyond will require to be revisited as part of the fundamental review of the HRA
Business Plan, with the outcome and recommendations presented to the
Council meeting on 15 February 2023. 
Current Phase of the Programme (2022/23 to 2023/24) 
2.23. There are 13 projects included in the current phase of the EBRP, some of
which will conclude in future years.  A fencing programme and other capital
programme work will run alongside these projects and contribute to the overall
regeneration of our housing estates. 
2.24. Three previously anonymised projects in the Garnock Valley locality were
subsequently combined as a single project during 2020/21.  These were
regeneration projects 4, 5 and 6 - Laburnum Avenue in Beith, Newhouse Drive
in Kilbirnie and Baidland Avenue in Dalry.  Works commenced on site in August
2022, with works expecting to complete early 2023. 
2.25. Two projects planned to commence during the current phase, ‘Regeneration
Project 7’ and ‘Regeneration Project 9’ are confidential at this stage.  This is
because they involve major regeneration and will require consultation with
tenants, and potentially owner occupiers, prior to full plans being developed. 
Members will be consulted prior to the project being progressed. 
3. Proposals 
3.1. That Cabinet (i) notes progress on, and revisions to, the EBRP to March 2022
as noted in Appendix 1; (ii) notes the revised programme for 2022/23 to
recognise slippage in previous years; (iii) approves the detailed programme for
2023/24; and (iv) notes that the remainder of the projects in the Estate Based
Regeneration Programme scheduled for delivery in 2024/25 and beyond, as
shown in appendix 2, may be subject to revision. 
4. Implications/Socio-economic Duty 
Financial 
4.1 Budget of £8.822m has been allocated within the Housing Revenue Account
30 Year Business Plan to fund the Estate Based Regeneration Programme
from 2022/23 to 2028/29. Budget for replacement new build provision totalling

Page 6

250 units through the Strategic Housing Investment Plan is also included in
the Business Plan. 
Human Resources
4.2 None 
Legal
4.3 All projects in the Estate Based Regeneration Programme will be undertaken
in line with Guidance on the Operation of Local Authority Housing Revenue
Accounts (HRAs) in Scotland.   
Equality/Socio-economic
4.4 Regenerating the estates throughout North Ayrshire will have a positive
impact for our tenants as we address areas of low demand and enhance the
external environment.  The benefits of attractive, good quality green space
and surroundings in relation to health, wellbeing, and educational attainment,
are well documented. 
Climate Change and Carbon
4.5 Investment in neighbourhoods through the Estate Based Regeneration
Programme will be carried out alongside measures developed to improve
energy efficiency and reduce carbon emissions in our housing stock, to
achieve national net zero targets.  This reflects the approach set out in the
Council’s recently approved Environmental Sustainability & Climate Change
Strategy 2021-23, which supports the Council’s sustainability aspirations to
become net-zero carbon by 2030, become a climate resilient local authority
and support enhanced biodiversity across North Ayrshire. 
Key Priorities 
4.6 The Estate Based Regeneration Programme 2022 2029 aligns with the
Council Plan strategic priorities: ‘Active and strong communities’; ‘Affordable,
modern, and well-designed homes that meets residents’ needs’: and ‘Vibrant,
welcoming and attractive places’. 
Community Wealth Building
4.7 North Ayrshire Council has integrated local economic development into all
policy decisions as part of the Community Wealth Building ethos.  As part of the
procurement process to identify contractors for works, there will be a
requirement for them to deliver agreed community benefits.  Building Services
are responsible for carrying out all fencing works identified in the programme,
adopting the Council’s Community Wealth Building ethos as practice.

Page 7

5. Consultation
5.1 Consultees at inception of the Estate Based Regeneration Programme included
housing professionals, corporate colleagues from across the Council, Health
and Social Care Partnership and Police Scotland.  Consultation will continue to
be undertaken with the relevant partners, as well as tenants and residents, as
projects develop. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Fiona Ellis, Senior Manager (Housing
Strategy & Development), on 01294 324031. 
Background Papers 
None

Page 8

Appendix 1
Estate Based Regeneration Programme 
Progress on previous years projects and those with spend during 2021/22
Project
Indicative
cost reported
to Cabinet Jan
2019
Revised
Project
Budget
following
scoping
Total Spend
Pre 2021/22
2021/22
Spend
Total Spend
to 31 March
2022
Scheme Carried
Forward to
2022/23 Onwards
Programme
(Appendix 2)
Proposed Interventions Progress
Bimson Place,
Irvine £15,000 £50,000 £0 £0 £0 Yes
Rationalise tenant garden layouts
where possible and install sub-
divisional fencing.
Consultation took place during 2021/22 with a positive response.  Budget has been increased in
the revised programme following the project being fully scoped.  Works commenced in July
2022.
Broomlands
area, Irvine £188,000 £273,624 £273,624 £0 £273,624 No
Increase parking and grounds
maintenance to replace poor
condition shrubbery which attracts
litter with turf to give the area a
more open and tidy appearance.  
380 additional parking spaces were created and landscaped around parking areas. 
Burns Street,
Irvine £195,500 £300,000 £0 £0 £0 Yes External painter work and new roofs
Project to be deferred to 2023/24.  Work is ongoing to ascertain internal reconfiguration works
required to adapt these properties to a more lettable standard. A new roof and external wall
insulation has been installed to one of the blocks as part of planned capital investment.
Castlepark
area, Irvine £100,000 £200,000 £245,590 £0 £245,590 No
Increase parking provision (minimum
150 new spaces).  Works planned for
year 2 have been brought forward to
year 1.
Works planned for both 2019/20 and 2020/21 were complete by March 2020 (total budget was
£200,000 over the two years).  125 additional parking spaces were created, and landscaping
undertaken around parking areas.
Glass Fronted
Closes, Irvine £380,000 £640,953 £0 £875 £875 Yes Upgrade close screens at nine Irvine
locations
Locations increased from nine to ten following scoping exercise. Budget has been increased in
the revised programme to reflect additional work identified.  Works were scheduled to
commence during 2021/22, however the supply of steel has caused a significant delay to this
project.  Works are scheduled to commence on site on 20 September 2022 and are expected to
complete during spring 2023.
Corsehill
Parking,
Kilwinning
£27,500 £17,229 £17,229 £0 £17,229 No Redevelop derelict ground for
parking provision Complete.  7 parking spaces were created, and perimeter fencing installed.
Dirrans,
Kilwinning £295,000 £130,000 £0 £0 £0 Yes
Upgrade fencing, provide in-curtilage
parking for tenants where feasible,
streetscape improvements
Due to the shortage of tarmac, works commenced on site in June 2022.  Budget has been
decreased in the revised programme following initial scoping.
Highfield
Street.
Kilwinning
£81,000 £5,779 £5,779 £0 £5,779 No
Remedial works to retaining wall
along the street frontage.
Scope of works was reviewed due to roads and footpaths being out with scope of HRA spend.  
Garnock Valley
Demolitions
(Regeneration
Projects 4,5,6)
£495,000 £495,000 £0 £95,975 £95,975 Yes Demolition of low demand flatted
blocks
Regeneration projects 5 and 6 were accelerated to 2021/22 to combine all three proposals as
one demolition project.  Budget information has been collated in the revised programme to
reflect this. Works commenced on site 1 August 2022.
Woodburn
Road, Beith £4,000 £0 £0 £0 £0 No Fencing improvements Fencing improvements for tenants who wished it were previously completed through the HRA
fencing programme.
Pier Crescent,
Fairlie £30,000 £12,220 £0 £12,220 £12,220 No
Increase car parking provision by
utilising grassed areas in front of
properties
Works completed during 2021/22.

Page 9

Appendix 1
Project
Indicative
cost reported
to Cabinet Jan
2019
Revised
Project
Budget
following
scoping
Total Spend
Pre 2021/22
2021/22
Spend
Total Spend
to 31 March
2022
Scheme Carried
Forward to
2022/23 Onwards
Programme
(Appendix 2)
Proposed Interventions Progress
Keppenburn,
Fairlie £55,000 £45,000 £0 £13,686 £13,686 Yes
Review garage occupation and
consider rationalisation of
replacement with parking provision
Works commenced 2021/22.
Moorburn
Road, Largs £77,000 £15,260 £15,260 £0 £15,260 No
Hard landscaping at rear of amenity
properties and fencing
improvements
Complete.  Cost was significantly less than the identified budget.  
Kilmahew
Street,
Ardrossan
£0 £5,977 £5,977 £0 £5,977 No
Landscaping of rear gardens, fencing,
painting closes and tidying of front
entrances
Residual works for the Kilmahew Street Project paid in 2020/21.  
Stanley Road,
Ardrossan £125,500 £27,504 £0 £27,504 £27,504 No Increase parking and upgrade fencing Following a scoping exercise and site visit parking was found to be adequate at this site. 
Fencing works complete during 2021/22.
Burns Terrace
and Chapelhill
Mount,
Ardrossan
£354,000 £124,434 £109,651 £14,783 £124,434 No
Increase parking provision including
use of under-utilised amenity areas,
and upgrade fencing
Two projects were merged from previous programme (Burns Terrace from 2020/21 and
Chapelhill Mount from 2023/24) given the proximity and to provide economies of scale.  Works
are complete, with 63 additional parking spaces provided and c.300m2 resurfacing undertaken. 
Works completed during 2021/22.
Regeneration
Project 9  £165,000 £250,000 £0 £62,400 £62,400 Yes
Buy back owner-occupied units, re-
house tenants, demolish flats and
redevelop through the SHIP
One remaining owner-occupier is unwilling to sell their property.  An options appraisal is being
prepared to consider the next steps to progress this scheme.
McNay
Crescent,
Saltcoats
£40,000 £10,810 £0 £10,810 £10,810 No Extend rear gardens to encompass
surplus land
Following scoping, the project was amended to involve landscaping the surplus land and budget
reduced to reflect this.  Works completed during 2021/22.
Regeneration
Project 13,
Stevenston
£77,000 £0 £0 £0 £0 No
Buy back owner-occupied unit and
redevelop derelict development site
through SHIP
This project focused on two derelict sites in the area, one of which has since been sold and the
other will be discussed with developing partners through the SHIP.  The project has, therefore,
been removed from the programme.
Regeneration
Project 14 £440,000 £440,000 £0 £84,277 £84,277 Yes
Buy back owner-occupied units, re-
house tenants, demolish flats and
redevelop through the SHIP
Three remaining owner-occupiers unwilling to sell their properties.  An options appraisal is
being prepared to consider the next steps to progress this scheme.
Ad hoc
Improvements £35,000* £35,000* £16,226 £6,116 £22,342 Yes Small ad-hoc parking and render
issues Minor ad hoc requests only.
Ad hoc Sub-
divisional
Fencing
£150,000* £150,000* £29,925 £68,605 £98,530 Yes Programme of fencing Minor ad hoc fencing requests only.
Management
charges N/A N/A £12,300 £42,449 £42,449 Yes N/A N/A
Total Cost £2,694,500 £2,549,127 £731,561 £439,700 £1,171,261 
*budget set as an allowance per annum for the lifetime of the EBRP to allow ad-hoc schemes to be addressed as and when required, for example, the Kilmahew Street, Ardrossan project.

Page 10

Estate Based Regeneration Programme 2022-2029
Project Name 
Locality 
Town
Letting Area
Street
SIMD Decile
Issue Interventions
No of Properties
No of Tenants
%
of Tenants
Town/Village Centre
2022/23(£000)
2023/24 (£000)
2024/25 (£000)
2025/26 (£000)
2026/27 (£000)
2027/28 (£000)
2028/29 ONWARDS
(£000)
Irvine Locality                                   
Bimson Place IR
Irvine
HARB
Bimson Place 1 Rear garden sub-division
issues
Rationalise tenant garden
layouts where possible and
install sub-divisional fencing.
12 6 50%   £50,000             
Burns Street IR
Irvine
IRVC Burns St 1 Low demand flatted
blocks 
Consider options for
improving appearance and
addressing low demand stock
14 10 71%  £5,000 £195,000 £100,000        
Glass Fronted Closes, Irvine IR
Irvine
IRVN Glass fronted closes
throughout area 2
Unattractive and rotting
glass fronted close
screens
Upgrade close screens at ten
Irvine locations 36 36 100%   £640,078            
Regeneration Project 1 IR
Irvine - Confidential 1 Low demand stock Develop regeneration plan TBC TBC TBC             TBC  
Regeneration Project 2 IR
Irvine - Confidential 1 Low demand stock Develop regeneration plan TBC TBC TBC              TBC
Kilwinning Locality                                   
Dirrans area KW
Kilwinning
DIRN Dirrans, Bartonholm &
Ninians Terrace, Seymour
Avenue, Smith Crescent
2 Streetscape issues,
quality of fencing
Upgrade fencing, provide in
curtilage parking for tenants
where feasible, streetscape
improvements 
192 91 47%   £130,000            
Fergushill Road Flats KW
Kilwinning
CHIL Fergushill Rd (flats) 1
Low demand flatted
blocks, streetscape
issues, anti-social
behaviour issues
Identify programme of
improvements, including
render, lighting, bin stores and
increased parking, where
possible given ownership
ratio.
28 20 71%   £50,000 £245,000 £200,000        
Hazelgrove KW
Kilwinning
CHIL Hazelgrove 3
Insufficient parking,
roads and footpath
condition issues
Improve parking provision and
road and footpath condition,
where possible given
ownership ratio.
106 26 25%     £50,000          
Town Centre Flats (East),
Kilwinning KW
Kilwinning
KWTC
Church Street  2
Difficult to let flatted
blocks, streetscape
issues, anti-social
behaviour issues
Identify programme of
improvements, including
render, lighting, bin stores and
increased parking where
possible given ownership
ratio.
22 16 73%        £400,000 £464,500    
Town Centre Flats (West),
Kilwinning KW
Kilwinning
KWTC Byres Road and
Claremont Crescent 1
Difficult to let flatted
blocks, streetscape
issues, anti-social
behaviour issues
Identify programme of
improvements, including
render, lighting, bin stores and
increased parking where
possible given ownership
ratio.  
51 34 67%      £400,000 £295,000      
Garnock Valley Locality                                 
Appendix 2

Page 11

Barrmill                                   
Regeneration Project 3 GV
Barmill
BML Confidential 6 Low demand stock  Develop regeneration plan 38 24 63%               TBC
Beith                                   
Garnock Valley
Regeneration (Formerly
Regeneration Projects 4,5 &
6)
GV GV GV Acacia Drive, Baidland
Avenue, Laburnum
Avenue, Newhouse Drive
2
Four streets with low
demand flatted
properties
Re-house tenants, demolish
flats, redevelop through SHIP
where appropriate, provide
additional parking and
landscape where appropriate
48 48 100%  £211,124 £187,901          
North Coast Locality                                   
Fairlie                                   
Keppenburn Avenue NC
Fairlie
FRLI
Keppenburn (garage site) 4 Under-occupied garage
sites, insufficient parking
Maximise parking and
upgrade fencing where
possible given ownership
ratio.
84 24 29%  £31,314            
Largs                                   
Royal Avenue / Holehouse
Court NC
Largs
LARG Royal Avenue/Holehouse
Road 4
Insufficient parking,
fencing issues, mixed
ownership blocks with
poor physical appearance
Identify programme of
improvements, including
render, lighting, bin stores and
increased parking where
possible given ownership
ratio.
78 39 50%    £300,000          
Skelmorlie                                   
Skelmorlie Parking NC
Skelmorlie
SKML
Innes Park Rd 5 Insufficient parking Maximise parking and
upgrade fencing 127 30 24%      £70,000        
West Kilbride                                   
Simson Avenue NC
West Kilbride
WKIL
Simson Ave 2
Under-occupied garage
sites, insufficient parking,
access to refuse area
Maximise parking, upgrade
fencing and consider options
for bin storage
76 52 68%   £65,000            
Three Towns Locality                                 
Ardrossan                                   
Burns Terrace & Chapelhill
Mount 3T
Ardrossan
ADSS
Burns Terrace 2 Insufficient parking and
fencing
Complete outstanding works
from 2020/21 project,
including maximise parking
and upgrade fencing
223 107 48%                
Regeneration Project 7 3T
Ardrossan
- Confidential 2
Low demand flats above
retail units, parking,
fencing
Develop regeneration plan TBC TBC TBC   £5,000 £42,500 £200,000      
Regeneration Project 8 3T
Ardrossan
- Confidential 1
Low demand flats above
retail units, parking,
fencing
Develop regeneration plan TBC TBC TBC      £185,000 £300,000    
Regeneration Project 9 3T
Ardrossan
- Confidential 1 Low demand flats  Develop regeneration plan TBC TBC TBC    £187,600

Page 12

Saltcoats                                   
Regeneration Project 10 3T
Saltcoats
- Confidential 1
Blocks of low demand
flats with anti-social
behaviour issues
Develop regeneration plan TBC TBC TBC           £500,000 £693,500  
Regeneration Project 11 3T
Saltcoats
- Confidential 1
Block of low demand
flats with anti-social
behaviour issues
Develop regeneration plan TBC TBC TBC       £187,000        
Regeneration Project 12 3T
Saltcoats
- Confidential 2
Blocks of low demand
flats, flats with retail
units on ground floor
Develop regeneration plan TBC TBC TBC       £342,500 £400,000      
Stevenston                                   
Regeneration Project 14 3T
Stevenston
- Confidential 1 Low demand flats,
streetscape issues Develop regeneration plan TBC TBC TBC    £200,000 £155,723        
Regeneration Project 15 3T
Stevenston
- Confidential 2
Low demand stock, flats
with retail units on the
ground floor, anti-social
behaviour issues, lack of
amenity space
Develop regeneration plan TBC TBC TBC               TBC
All Areas                                   
Ad hoc projects All All All Various N/A Various small scale
estate based issues
Smaller scale improvement
projects identified outwith the
wider programme.
- - TBC  £35,000 £35,000 £35,000 £35,000 £35,000 £35,000 £35,000
Fencing All All All Various N/A
Estate management
issues and poor visual
appearance through lack
of fencing.
Programme of fencing
improvements to complement
the EBRP.
- - TBC  £150,000 £150,000 £150,000 £150,000 £150,000 £150,000 £150,000
Management charges N/A
N/A
N/A N/A N/A     N/A  £43,722 £45,034 £46,385 £47,777 £49,210 £50,686 £52,206          
Total pa  £1,411,238 £1,600,535 £1,729,108 £1,712,777 £1,498,710 £929,186 £237,206          
Projects
total      
Projects
total £9,118,759                 
Budget
total £8,822,155