NORTH AYRSHIRE COUNCIL 
1 November 2022 
Cabinet
Title: Strategic Housing Investment Plan 2023 – 2028
Purpose: To seek Cabinet approval of the Strategic Housing Investment   
Plan 2023 – 2028 
Recommendation: That Cabinet (i) approves the Strategic Housing Investment Plan
2023-2028 at Appendix 1 for submission to Scottish Government
and (ii) gives delegated authority to the Executive Director
(Place) and the Cabinet Member for Place to liaise directly with
the Scottish Government in agreeing the North Ayrshire
development programme and the rescheduling of projects as
required. 
1. Executive Summary 
1.1 The Strategic Housing Investment Plan (SHIP) 2023 – 2028 sets out the priorities and
locations for affordable housing investment by the Council and Registered Social
Landlords in North Ayrshire over the next five years. The SHIP is based on projected
Scottish Government grant funding provision for the Council and our partner Registered
Social Landlords of £120.855m during the period 2023 – 2028 and represents Council
investment of £84.773m. 
1.2 It is proposed that delegated authority is assigned to the Executive Director (Place), in
consultation with the Cabinet Member for Place, to liaise with the Scottish Government
and agree the rescheduling of projects detailed in the SHIP, as required. Any additional
projects that are not contained within the approved SHIP will require further Cabinet
approval. 
1.3 From a Council perspective, the SHIP reflects the previous commitment to construct
1,625 new build homes, including provision for 275 new homes to replace the Fullarton
tower blocks, which are scheduled for demolition following re-housing of all tenants and
250 new units to support the Council’s Estate Based Regeneration Programme. 
1.4 The Council and its RSL partners have been monitoring the impact of both COVID-19
and ongoing global economic factors impacting supply chains, labour availability and
materials costs affecting the construction industry, on the SHIP. It is clear that both
issues have contributed to time and financial impacts, due to labour and material
shortages and an increase in material costs. The SHIP includes the latest available
estimates of the time and financial impacts of COVID-19 on the development
programme.   
1.5 The SHIP 2023 - 2028 will secure investment in a total of 1,652 properties across the six
North Ayrshire social landlords currently active in housebuilding and will provide

Page 2

sustainable, affordable, accessible, and high-quality homes which will contribute to the
wider regeneration aims for the area. This will in turn secure employment and training
opportunities for North Ayrshire businesses and residents and support the Council’s
Community Wealth Building Strategy. Members are invited to approve the SHIP at
Appendix 1 for submission to the Scottish Government, as the Council’s investment plan
for new affordable housing in the area over the next five years. 
2. Background 
2.1 The Strategic Housing Investment Plan (SHIP) 2023 – 2028 sets out the priorities for
affordable housing investment in North Ayrshire over the next five years to support the
outcomes in the Local Housing Strategy. The Plan is prepared in accordance with
Scottish Government guidance and includes details of individual development projects to
be taken forward over its five-year lifespan (see Appendix 1). 
2.2 The plan supports the Council’s historic commitment to develop 1,100 new build Council
homes.  In June 2018, the demolition of the Fullarton tower blocks in Irvine was
approved. The SHIP makes provision for the replacement of all 275 of these homes
within the Irvine locality. 
2.3 In January 2019, the Estate Based Regeneration Programme was approved. To assist
the delivery of this programme, the SHIP includes provision for 200 units as an indicative
replacement for any selective demolition of particularly low demand stock.   
2.4 Programme revisions to date include the addition of a further 50 new units towards the
Estate Based Regeneration Programme, bringing the total to 250. These projects take
the total investment in Council developments to £165.361m during the period 2023 -
2028 and represents Council investment of £84.773m. 
2.5 The Scottish Government has committed to providing North Ayrshire Council with grant
funding for the Council and our RSL partners of £63.005m from April 2022 to March
2026.  The funding levels beyond March 2026 are not currently known and have
therefore been estimated for planning purposes, based on trend assumptions.  The
Scottish Government benchmark grant rates are subject to annual inflation in line with
the Scottish Social Housing Tender Price Index. For new build Council developments
funding levels have been estimated for projects not yet at tender stage at benchmark
rates plus annual inflation which was 8.3% for 2021/22 and has been assumed at 8.6%
for 2022/23 and 3.7% for 2023/24.  The Council will seek grant funding above these
levels in accordance with Scottish Government guidance on a site-by-site basis, as
required. The RSL funding rates have been included as requested by each developing
organisation and will be subject to Scottish Government authorisation.   
2.6 The SHIP is based on total projected Scottish Government grant funding provision of
£120.855m for the Council and our RSL partners during the period 2023 - 2028. In
accordance with Scottish Government guidance, the Council has over committed the
funding within the SHIP by approximately 25% to ensure that the allocation is spent, and
to provide the opportunity for North Ayrshire to absorb slippage from other local authority
areas.  For this reason, a significant portion of the funding is allocated during the second
and third years of the SHIP. 
2.7 The Council and its RSL partners have been monitoring the impact of both COVID-19
and ongoing global economic factors impacting the SHIP. It is clear both have
contributed to time and financial impacts, due to labour and material shortages and an
increase in material costs. The SHIP includes the latest available estimates of the time

Page 3

and financial impacts on the development programme. 
2.8 An additional £32.762m is required to support the Council’s developments set out within
the SHIP to offset rising rates of inflation and ensure that the costs associated with the
introduction of new legislation which requires the installation of Zero Direct Emissions
heating systems and Electrical Vehicle Charging Points can be met. The Council is also
enhancing the building fabric for all new homes to reduce the need for heating. This
additional expenditure alongside estimated additional grant of £13.933m, will be
considered within the review of the HRA Business Plan to be presented to Council in
February 2023 as part of the 2023-24 HRA Budget and rent setting. 
2.9  For any projects noted within the SHIP, Cabinet is asked to delegate authority to the
Executive Director (Place), in consultation with the Cabinet Member for Place, to liaise
with the Scottish Government and agree the rescheduling of projects as required.  This is
of particular importance where deliverability is delayed or acceleration is possible due to
emerging challenges or opportunities that require to be addressed. Any additional
projects that are not contained within the SHIP will require Cabinet approval. 
Strategic Priorities 
2.10 The SHIP is based on a series of guiding principles for housing provision, taken from the
Local Housing Strategy. 
2.11  In order to prepare the SHIP, the Council invited site nominations from its partners. No
new sites were nominated for the SHIP 2023 however three RSL partners introduced
buy back programmes. If any project becomes delayed or non-viable, the Council will
work with RSL partners and the Scottish Government to ensure that new homes are
delivered, and the available grant funding spent, by accelerating other projects. 
2.12  In terms of ongoing governance, senior officers monitor the progress of the new build
programme monthly through the SHIP Project Board. 
Demand 
2.13 Demand figures have been obtained from the North Ayrshire Housing Register (NAHR).
House size and type priorities have also been informed by the NAHR. The Housing
Need and Demand Assessment (HNDA) sets the housing estimate for the period 2022-
2027 as 2,330 new units, either in the social rented sector, or, in the case of strong
economic recovery, split across all tenures. Housing supply targets will be set out in the
emerging Local Housing Strategy. 
2.14 Figure 1 plots SHIP completions against net gain from 2022 to 2028. The 'net gain'
columns indicate the additional homes available per locality following completion of the
developments, minus the strategic demolitions set out in the SHIP. 
Figure 1: SHIP Actual & Projected Completions 2022-2028 & Net Gain 2022-2028

Page 4

2.15 The Council allocates funding to each developing organisation from the Scottish
Government Resource Planning Assumption (RPA). Figures 2 and 3 show the proportion
of stock held by each developing organisation, and the share of funding per developing
organisation. 
Figure 2: Proportion of stock held in North Ayrshire per developing organisation (%) 
Figure 3: Proportion of funding per developing organisation (%) 
2.16 An indicative size mix (Table 1) for new developments across North Ayrshire has been
prepared based on North Ayrshire Housing Register (NAHR) intelligence to meet existing
and future housing need. 
NAC, 72%CHA, 13%
Riverside
(IHA), 9%
Cairn (ANCHO), 4% Trust, 2%
Link, 0%Developer
North 
Ayrshire
Stock
NAC 13,135
CHA 2,329
Riverside (IHA) 1,710
Cairn (ANCHO) 657
Trust 287
Link 0
Total 18,118
Developer
Completions 
in SHIP 
2023 - 2028
NAC 988
CHA 485
Riverside (IHA) 122
Cairn (ANCHO) 13
Trust 32
Link 12
Total 1652 NAC, 60%CHA, 29%
Riverside
(IHA), 7%
Cairn
(ANCHO), …
Trust, 2%
Link, 1%

Page 5

Table 1: Indicative mix by bedroom size 
No of
Beds
Three
Towns Arran Garnock
Valley
Irvine /
Kilwinning
North
Coast
North
Ayrshire
1 14% 14% 10% 15% 14% 14%
2 60% 54% 56% 56% 63% 57%
3 15% 20% 20% 15% 15% 16%
4+ 11% 12% 14% 14% 8% 13% 
Specialist Accommodation 
2.17 Analysis of the NAHR, and projected future demographic trends signifying an ageing
population, indicate that at least 25% of all new build homes should be designed for
older people (i.e., amenity housing or sheltered housing). 
2.18 Following a review of North Ayrshire’s Housing Allocation Policy in 2019, the age
restriction for the allocation of amenity housing was removed. This allowed allocation of
amenity homes to younger people with an accessible housing requirement, promoting
independent living.  Currently, 79% of applicants for amenity housing are aged over 51. 
The Council will continue to monitor the availability of housing for older people to ensure
that their needs can be addressed through the affordable housing supply programme. 
2.19 In order to promote independent living, the Flatt Road development site in Largs was
used as an exemplar for assistive technology. Features can be included within the
sheltered housing complex and supported accommodation where required to support
tenants’ individual needs. 
2.20 The Council’s Housing Service and Health and Social Care Partnership (HSCP) worked
together over the last five years to consider a model for Extra Care Sheltered Housing. 
The vision was to create safe, affordable homes for tenants who require additional
support with extra services to promote independent living, such as assistance with meals
or welfare checks, to be available for tenants for an additional fee.  Following
development of the outline model, demand analysis was undertaken by the HSCP in
2021 alongside engagement with other areas in Scotland where similar housing models
operate.  At that time, it was determined that there was not sufficient demand to
integrate the model into a new sheltered housing complex and there are challenges in
sustainable funding to operationalise the model.  The Council has, however,
incorporated flexibility into some new build sheltered housing complexes to allow this
model to be reconsidered in future, with minimal investment should the HSCP choose to
develop this further. 
2.21 To ensure need is met now and in the future, the Local Housing Strategy 2018 – 2022
set a target for all tenures, with at least 7% of all new build stock being fully wheelchair
accessible.  This will be reviewed in the next LHS (due for renewal in early 2023) and the
future Local Development Plan following Scottish Government guidance for local
authorities on the setting of targets to support the delivery of more wheelchair accessible
housing. 
2.22 The SHIP will support the Health and Social Care Partnership to meet specialist housing
need through dedicated projects using the jointly developed supported accommodation
model, and as part of a wider site mix on other developments, a further emerging area
being explored is how the SHIP can support those with more complex care needs. The
latest SHIP includes provision for 25 supported accommodation housing units at two

Page 6

different locations. 
Child Poverty and Improving Health and Wellbeing 
2.23 North Ayrshire’s Local Child Poverty Action Plan and Report 2020/21 recognises that the
instance of child poverty within North Ayrshire is one of the highest in Scotland and
acknowledges the role that access to good quality and affordable housing has in
combating inequality.  All new build Council family homes have study space and private
gardens. 
2.24 The Council is also considering ways in which young people can access construction
related learning and training opportunities. The North Ayrshire Local Employability
Partnership Delivery Plan 2022 – 2026 sets out the intentions to help people of all ages
to gain skills for employment. It will prepare people for employment, training, education
and/or volunteering, with the aim of increasing qualification levels and job prospects as
well as reducing unemployment. Officers from Housing and PMI will work alongside
Education colleagues to determine how our housebuilding programme can support the
Council’s ambitions to encourage more young people into training and employment. 
Island Development 
2.25 On Arran, the Council’s development of 34 units at Brathwic Terrace, Brodick completed
during June 2022.  In addition, Trust Housing Association is currently in discussions with
a local landowner to develop 26 new homes in Brodick. These developments, alongside
work with communities on the island, are anticipated to support investment to encourage
economic growth. Similarly, 18 new homes have recently been completed on Cumbrae
through the SHIP as part of a second phase of the successful St Beya Gardens site.  It is
hoped that these developments will help to address local housing need, support key
employment and enable people to remain on the islands. Work is ongoing to determine
housing need on Arran at a town / village level, through analysis of the North Ayrshire
Housing Register and further contact with applicants. Consideration is also being given
to commissioning independent research with a particular focus on housing’s role in
supporting the local economy. The outcome of this work will be reported to Cabinet in
due course, alongside any proposed action. 
Buy Backs 
2.26 Bringing empty homes back into use supports regeneration; it is a strategic priority within
the current LHS and will continue to be a priority in the future.  It also supports the
Council’s Regeneration Delivery Plan.  In recognition of this, a target has been set to
purchase at least five second hand or empty properties during each financial year of the
new SHIP, subject to the availability of Scottish Government Grant. 
Sustainability & Safety 
2.27 Council officers are seeking to maximise the incorporation of energy efficiency measures
and renewable technologies within the new build programme. The developments within
the SHIP will benefit from a range of sustainable measures, for example solar
photovoltaic panels, small scale district heating schemes, and passive design measures
to minimise space heating demand. The exact package of measures will be determined
through assessment of opportunities on a site-by-site basis. 
2.28 Following a revision to national Building Standards, all new build social housing
properties with planning applications submitted on or after 1 March 2021 require to be

Page 7

fitted with fire suppression systems. In advance of this legislation, and in recognition of
the safety benefits of fire suppression systems, the Council has installed fire suppression
systems in all new build housing proposals which reached technical design stage after
October 2019. 
Regeneration 
2.29 The provision of affordable, modern and well-designed homes that meets residents’
needs is one of nine strategic priorities within the Council Plan 2019 - 2024. 
2.30 The Council, along with its strategic partners, continues to explore the site and area
specific opportunities to secure maximum regeneration benefits, supporting the
ambitions of the Council’s Regeneration Delivery Plan to drive forward development on
strategic regeneration sites, including town centres.  Our town centres continue to be of
strategic importance as the economic and social focus points of North Ayrshire.  The
Council has acquired the former King’s Arms public house in Irvine Town Centre and will
redevelop the site into six amenity flats to address local housing need and encourage
town centre living.  Other town centre projects include: the redevelopment of the former
Largs Police Station and adjacent former St Colm’s Place Sheltered Housing Complex;
the development of the former Springvale depot in Saltcoats; the redevelopment of
former sheltered housing complexes at Afton Court and Caley Court in Stevenston; and
the redevelopment of the Irvine High Flats.  Regeneration Project 1d in Ardrossan and
the unallocated regeneration blocks will also be utilised to further support North Ayrshire
regeneration.   
2.31 The SHIP also includes the provision of funding for 250 units to assist the delivery and
funding of Housing’s Estate Based Regeneration Programme.  Most of this investment
is anticipated to be replacement for any selective demolition of stock.  The regeneration
units included within the SHIP will allow Housing Services to continue the
implementation of the Estate Based Regeneration Programme, as well as support a
review of our assets in relation to our EESSH2 and zero emissions targets to consider
further redevelopment opportunities.   
Community Wealth Building 
2.32 Effective use of community benefit clauses in development contracts, and partnership
work with colleagues in Economic Development to support local construction and supply
chain companies to bid for this work, can secure many of these jobs for our local people
and support the Council’s Community Wealth Building Strategy.  The Council has
undertaken a review of our Dickson Drive, Irvine house building pilot and will utilise this
to inform a second project with Building Services to construct a number of new homes at
Ayrshire Central, Irvine.   
2.33 The Council is also currently developing a pilot model for employability by offering
training and employment opportunities obtained through community benefits from
Housing Services maintenance and investment contracts to our Housing First tenants,
supporting some of our most complex support cases to sustain housing and
employment.  The delivery of the SHIP, alongside investment in land and asset
maintenance, plays a key role in community wealth building. 
Affordability 
2.34 The Council is committed to ensuring rent levels are affordable. Many tenants in social
housing are partly or fully dependent on benefits and are under increasing pressure from

Page 8

the impacts of Welfare Reform and rising living costs. The Scottish Housing Regulator
has intimated that social landlords will be expected to keep rent increases to a minimum.
To ensure homes are affordable, the Council and all RSL partners will be expected to set
rent levels on new build homes at or below the Local Housing Allowance.  North Ayrshire
Council has an approved rent structure based on house size and type, with no additional
charge for new build properties. Current rent levels are set below the Local Housing
Allowance. 
Key Achievements from 2021/22 
2.35 During 2021/22, the Council’s largest development to date at Flatt Road, Largs reached
completion providing 123 units including a new sheltered housing complex, supported
accommodation, amenity bungalows, general needs properties and homes suitable for
wheelchair users. The site is serviced by a district heating scheme which provides
heating and hot water to all residents. The redevelopment of Dalrymple Place, Irvine also
completed providing 33 new sheltered and amenity homes. A further 18 units were
completed at the St Beya Gardens, Millport development; 14 new homes were delivered
at Springvale, Saltcoats; 50 units were created at Towerlands, Irvine; and the 34 new
homes at Brathwic Terrace, Arran were all allocated by June 2022. 
2.36 During September 2022 works concluded at the 79-unit St. Michael’s Wynd, Kilwinning
site which delivered supported accommodation, sheltered housing, general needs
properties and accessible housing.  The 29 new homes at the St. Colm’s Place sheltered
housing complex also reached completion during September 2022. The 16 units of
supported accommodation at Caley Court, Steveston are expected to complete during
autumn / winter 2022.  Work continues to develop 71 new homes at Irvine Harbourside
which are expected to complete during early 2023. 
2.37 The contractor has commenced work on site to deliver 12 new amenity flats at the former
Largs Police Station. The completion date for this site has slipped by eight months due
to analysis being undertaken to determine the most cost-effective heating option for
future tenants. At Afton Court, Stevenston works are anticipated to commence on site
during late 2022 to deliver six new amenity bungalows. Now that a contractor has been
appointed, the timeline has been confirmed and this scheme will complete around six
months later than previously anticipated. 
2.38 Cunninghame Housing Association completed 76 units at Sharphill Phase 4 in Saltcoats
and allocated their two new wheelchair accessible homes at Glebe Place.  Work
continues to develop 72 units at West Byrehill, Kilwinning and 24 units at Green Street,
Saltcoats.  Riverside Scotland continue works on site for 77 units at Tarryholme Phase 2,
Irvine which is expected to complete in early 2023. 
2.39 North Ayrshire’s Resource Planning Assumption for the Council and our RSL partners
during 2021/22 was £18.205m.  During the year, a total of £20.641m was claimed,
through obtaining slippage funding of £2.436m from other local authority areas.  North
Ayrshire Council and our RSL partners have been able to claim an additional £19.165m
towards affordable housing in the area from slippage in other local authority areas in the
six years from April 2016 to March 2022.   
2.40 As a result of past success in accelerating projects and claiming additional funding year
upon year to date, and also due to the slippage in some of the projects noted below, it is
unlikely that North Ayrshire will be able to claim our full Resource Planning Assumption
for the 2022/23 financial year. Discussions are ongoing with the Scottish Government to
ensure that grant funding is maximised wherever possible.

Page 9

Removal of Projects from the SHIP 2023 - 2028 
2.41 Cunninghame Housing Association’s Confidential sites 9 and 11 have been removed
from the SHIP as they have been assessed as unviable.  A block of 92 units named
‘Unallocated CHA Block’ has been added into the SHIP to provide CHA with capacity for
future development while the association identifies suitable sites. 
2.42 The Council’s ‘Unallocated Regeneration Block 2’ is no longer required as the units have
now been allocated to specific projects within the SHIP where additional capacity was
identified.  
Amendments to the SHIP 
2.43 The following amendments have been made in this update of the SHIP: 
• Following value engineering design work, the James Reid, Saltcoats site can
accommodate 47 units (increased from 44 units), the Stanecastle, Irvine site can
accommodate 31 units (increased from 28 units) and the James McFarlane,
Ardrossan site can accommodate 19 units (increased from 18 units).
• The Ayrshire Central, Irvine site has been increased to 202 units from 171 units. 
• Redevelopment Projects 10, 11b and 14 located in Irvine have now been named as
Montgomerie Park, Irvine and can accommodate 189 units, increased from 168
units.
• The Laburnum Avenue, Beith site can accommodate seven units, increased from
six.
• The Fullarton Street, Irvine site can accommodate 62 units, increased from the 54
units previously anticipated. The estimated project start and completion dates for
this site have been adjusted by a year now that the timeline for the demolition of the
high flats has been established.
• Glebe Place, Saltcoats has been reprofiled from 2024/25 to 2026/27 to enable the
Council in assisting the Scottish Government to meet accommodation needs for
Ukrainian Displaced People.
• Unallocated Regeneration Block 1 has been reduced from 49 units to 30 units; the
other 19 units have been allocated to projects in the SHIP.
• Cairn Housing Association’s Confidential Site 1 has reduced from 20 units to 9
units following site viability assessments.
• Cunninghame Housing Association’s (CHA) Confidential Site 8 has been named as
Garven Road, Stevenston and can accommodate 20 units, increased from 19. 
• CHA’s site at Harbour Road, Irvine has been reduced to 27 units from 29 units.
• Cunninghame Housing Association’s phase 5 site at Sharphill, Saltcoats has been
increased to 100 units from 82 units.  
• Riverside are unable to deliver their development at 111 Bank Street, Irvine.
Cunninghame Housing Association are currently reviewing site viability and this site
has therefore remained within the SHIP.
• Trust Housing Associations Confidential Site 4 can now accommodate 26 units,
increased from 20 units. 
2.44 A number of North Ayrshire Council project timelines have experienced slippage due to
the requirement for redesign and value engineering to offset increasing costs and whilst
studies were undertaken to ensure that the introduction of Zero Direct Emissions heating
and hot water systems provided value for money for tenants.

Page 10

2.45 Some SHIP sites have been anonymised for reasons of commercial sensitivity, or as
they require further work to ensure that they comply with the Council’s Planning or
Roads policies. 
New Council Projects 2023 - 2028 
2.46 The Council has included a three unit refurbishment of a property on Nelson Street in
Largs and a further two unit refurbishment project in Irvine, a viability assessment is
currently underway for this scheme and it has therefore been marked as confidential until
this is complete. 
New RSL Projects 2023 - 2028 
2.47 Cunninghame Housing Association, Riverside Scotland and Trust Housing Association
have included buy back programmes within the new SHIP. 
SHIP Impact on North Ayrshire School Capacity 
2.48 Officers from Housing, Planning and Education will continue to monitor emerging
development to ensure any impact upon school capacity can be addressed or mitigated. 
3. Proposals 
3.1  It is proposed that Cabinet (i) approve the North Ayrshire Strategic Housing Investment
Plan 2023-2028 for submission to the Scottish Government; and (ii) gives delegated
authority to the Executive Director (Place) and the Cabinet Member for Place to liaise
directly with the Scottish Government in agreeing the North Ayrshire development
programme and the rescheduling of projects as required.

Page 11

4. Implications/Socio-economic Duty
Financial
4.1 The financial implications arising from the projects included within the SHIP 2023 - 2028
have been assessed by each of the developing organisations, ensuring that the
programme is fully deliverable within the timescales set out.  The current HRA Business
Plan includes a budget of £165.361m to deliver the North Ayrshire Council development
projects set out within the SHIP, inclusive of Scottish Government funding. It is
estimated that an additional £32.762m is required to support the Council’s developments
set out within the SHIP 2023-2028 to offset rising rates of inflation and ensure that the
costs associated with the introduction of new legislation which requires the installation of
Zero Direct Emissions heating systems and Electrical Vehicle Charging Points can be
met. The Council is also enhancing the building fabric for all new homes to reduce the
need for heating. This additional expenditure alongside estimated additional grant of
£13.944m, will be considered within the current review of the HRA Business Plan prior to
it being presented to Council in February 2023 as part of the 2023-24 HRA Budget and
rent setting. 
Human Resources 
4.2 Council projects within the Strategic Housing Investment Plan will be delivered by
North Ayrshire Council staffing and complemented by external expertise, where
required. 
Legal 
4.3 The Town & Country Planning (General Permitted Development) (Scotland) Order
1992, Schedule 1, Part 12, Class 33, as amended, enables local authorities to carry
out works, within their district, for the erection of dwellings so long as the development
conforms with the Local Development Plan. The Council’s House Building Protocol
governs the design and consultation processes for such development to ensure that
appropriate levels of design scrutiny and consultation are maintained.  In 2019, it was
agreed that all future Council housing developments progressed as permitted
development will be required to obtain a ‘Certificate of Lawfulness’ from the Council’s
Planning Service. This will certify that each site within the SHIP has been considered
against the full terms of the adopted Local Development Plan. Housing development
proposals by the Council which do not fall within the scope of permitted development,
including schemes which require an Environmental Impact Assessment (EIA) will
require planning permission. Proposals over 0.5 hectares in area will require to be
screened for the purposes of EIA. 
Equality/Socio-economic 
4.4 The provision of new social housing will have a positive impact on those who require
specialist accommodation, older people, those who are homeless, or at risk of
homelessness, and those for whom purchasing a home is not an affordable option.
The benefits of new build housing in relation to health, wellbeing and educational
attainment, are well documented.  New housing will also support our island
communities and their economies. 
Climate Change and Carbon 
4.5 New homes should have a low environmental impact, with the aim of reducing fuel
use and associated fuel costs. All projects within the SHIP will be delivered in
accordance with Building Standards regulations for energy efficiency. In addition, the

Page 12

majority of the new projects incorporated into the plan will meet the Scottish
Government’s ‘Greener Standard’. Innovative approaches to fuel efficient
development will be considered on a site-by-site basis (e.g., Passivhaus design
measures, biomass boilers, solar photovoltaic panels, smart technologies etc). New
Council homes contribute significantly to the Council’s Sustainability agenda.  New
housing is more energy efficient, better ventilated, and has higher levels of thermal
comfort, which supports improved health and well-being. 
Key Priorities 
4.6 The provision of new affordable housing supports the Council Plan priority to provide
affordable, modern and well-designed homes that meet residents’ needs.  It supports
the ambitions of the Council’s Regeneration Delivery Plan to drive forward
development on strategic regeneration sites, including town centres.  There is also
evidence that children and young people can benefit from improved cognitive
development and a reduction in behavioural issues through living in a more attractive,
warmer, and better ventilated environment and the provision of new affordable
housing also supports the Council Plan priority that children and young people
experience the best start in life.  New housing will also support our island communities
and their economies. 
Community Wealth Building 
4.7 The Council’s contractors are required to participate in the Council’s Community
Benefits Programme.  The projects within the SHIP aim to deliver new employment
opportunities for the area, including the provision of dedicated apprentice starts,
graduate positions and the creation of local jobs. The project contractors also engage
with local schools to provide health and safety presentations, undertake STEM
activities, provide mock interviews, and host design competitions. 
5. Consultation 
5.1 The Council has taken a collaborative approach to the preparation of the SHIP, and
the following stakeholders have been involved in the process: 
• ANCHO in partnership with Cairn
• Cunninghame Housing Association
• Riverside (formerly Irvine Housing Association)
• Link Group Ltd
• Trust Housing Association
• The Scottish Government
• North Ayrshire Council Officers (Economic Growth, Education, Finance, Housing,
Planning, Property Management and Investment, Active Travel & Transport, Roads,
and the Health and Social Care Partnership). 
5.2 Regular meetings are held with developing organisations, the Council and the Scottish
Government as part of the SHIP governance process. The meetings will continue to
be convened on a quarterly basis each year, to ensure that partners’ requirements are
identified, and the development programme delivered.

Page 13

RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Fiona Ellis, Senior Manager, Housing Strategy and
Development, on 01294 324031. 
Background Papers
0

Page 14

North Ayrshire Council
Strategic Housing
Investment Plan
2023 - 2028

Page 15

Introduction 
Purpose
Environment 
A Strategic Environmental Assessment
(SEA) pre-screening questionnaire
undertaken for the LHS confirmed that
the development proposals within the
SHIP have been scoped within the SEA
for the North Ayrshire Local
Development Plan.
Strategic Policy Context 
Housing to 2040, Scotland’s first 20-year
housing strategy, was announced in
March 2021. The strategy commits to
providing around £16bn of investment to
support the delivery of 100,000 new
homes by 2032, with at least 70% of
these being for social rent.  The Scottish
Government’s Affordable Housing Supply
Programme (AHSP) comprises a range
of funding mechanisms to enable
affordable housing providers to deliver
homes in communities across Scotland
to support local authorities’ Local
Housing Strategies.  The Scottish
Government has allocated Resource
Planning Assumptions (RPAs) for the full
five-year period of the current parliament
to deliver the ambitious affordable homes
target set out in Housing to 2040. 
The SHIP is an extension of, and aligns
to, the Local Housing Strategy 2018-22
(LHS). In preparing the SHIP, the
Council has referred to the outcomes
identified in the LHS, which support
objectives of the Council Plan. 
The SHIP also aligns with the Council’s
Economic Recovery and Renewal
Approach, which sets out how the
Council, in conjunction with our
residents, will recover and renew
services by: building upon the outcomes
of the Council Plan; committing to
Community Wealth Building; and
committing to a Green New Deal. 
Equalities 
In line with our Council Plan, fairness and
equity is core to the Strategic Housing
Investment Plan. We strive for a North
Ayrshire where everyone has the same
life chances to grow, prosper and have
fulfilling and healthy lives.  An Equality
Impact Assessment has been
undertaken for the SHIP.  It found that
there are no negative or discriminatory
effect on any equality groups. 
The provision of new social housing will
have a positive impact on those who
require specialist accommodation, older
people, those who are homeless, or at
risk of homelessness, and those for
whom purchasing a home is not an
affordable option. The benefits of new
build housing in relation to health,
wellbeing and educational attainment,
are well documented.  
The Strategic Housing Investment
Plan (SHIP) 2023-2028 sets out the
priorities for affordable housing
investment in North Ayrshire over
the next five years and outlines
how the Council and its partners
will deliver these priorities. The
focus of the SHIP is to support the
Scottish Government’s Affordable
Housing Supply Programme
(AHSP) which delivers affordable
housing for rent in North Ayrshire.

Page 16

Consultation and Collaboration     Key SHIP Stakeholders 
As the strategic housing authority, the Council is
committed to supporting our partners to deliver
affordable housing development within North Ayrshire. 
The Council adopts a collaborative approach in the
preparation of the SHIP. The key stakeholders opposite
have influenced the final programme. 
In preparing the SHIP 2023-2028 the Council invited site
nominations from its Registered Social Landlord (RSL)
partners.  All developments proposed were considered
on their individual merits, with reference to the
development priorities set out within the LHS and any
known constraints. 
Thereafter, the Council issued the draft SHIP to its
partners to review the priorities of each individual site
and assist in agreeing the wider plan. The Council will
continue to monitor the development programme and
any arising opportunities at quarterly meetings held with
developing RSLs and the Scottish Government. 
Council Officers monitor the impact of the new build
programme on education facilities and other services
through the SHIP Project Board. 
If any project becomes delayed or non-viable, the
Council will work with RSL partners and the Scottish
Government to ensure that new homes are delivered by
Local registered social landlord partners,
including ANCHO, Cairn, Cunninghame Housing
Association (CHA), Link Group Ltd, Riverside
Scotland and Trust Housing Association
North Ayrshire Council internal departments,
including Economic Growth, Education, Finance,
Housing, Planning, Property Management and
Investment, Active Travel and Transport, Roads,
and the Health and Social Care Partnership
The Scottish Government

Page 17

accelerating other projects within the SHIP.
Investment Priorities 
Consider their role in providing health benefits to tenants and supporting young people to maximise their educational attainment.   
North Ayrshire’s Local Child Poverty Action Plan and Report
2020/21 recognises that the instance of child poverty within
North Ayrshire is one of the highest in Scotland. 
Research undertaken by Shelter suggests children can
benefit from improved cognitive development and a
reduction in behavioural issues through living in a more
attractive, warmer, and better ventilated environment.  All
new build Council family homes have study space and
private gardens. 
Developing the Young Workforce have launched an online
Skills Academy to support school leavers and job seekers.   
The North Ayrshire Local Employability Partnership Delivery Plan 2022 – 2026 sets out the intentions to help people of all ages to gain skills
for employment. It will prepare people for employment, training, education and/or volunteering, with the aim of increasing qualification levels
and job prospects as well as reducing unemployment. 
We are committed to working alongside Education colleagues to determine how our housebuilding programme can support the Council’s
ambitions to encourage more young people into training and employment. 
The LHS indicates the importance of establishing clear investment priorities to meet the housing needs of local people,
allow partners to identify projects, and ensure that the Scottish Government’s goals for new affordable social homes
are supported. To ensure maximum benefit is achieved from social housing investment, all projects must:

Page 18

Be attractive and have aesthetic value, to contribute
to the regeneration of North Ayrshire, including its
town centres.   
The provision of affordable, modern and well-designed
homes that meets residents’ needs is one of nine
strategic priorities within the Council Plan.  Public sector
investment can have a transformational impact within
communities, and there are cumulative benefits through
considering how this can be coordinated with developing
partners and the private sector. 
The Council explores site and area specific opportunities
with partners to secure maximum regeneration benefits. 
This supports the ambitions of the Council’s
Regeneration Delivery Plan to drive forward development
on strategic regeneration sites, including town centres. 
Town centre regeneration is a primary focus of the SHIP,
with several projects completed to date within, or near,
town centres.   
The SHIP supports major housing led regeneration in
North Ayrshire, an example being provision for the
replacement of the 275 homes in the Fullarton tower
blocks in Irvine which are scheduled for demolition. The
SHIP also includes the provision of funding for 250 units
to assist the delivery and funding of Housing’s Estate
Based Regeneration Programme (EBRP).  This
investment aims to provide new homes to replace any
stock which requires to be demolished or reconfigured as
part of the EBRP. 
The Kings Arms located in Irvine Town Centre will be
redeveloped to provide 6 new amenity flats
The Fullarton tower blocks in Irvine is a major regeneration project

Page 19

Be sustainable. Project design,
building materials and component
parts will maximise energy efficiency
and reduce running costs. Design will
also contribute to community stability
and promote feelings of safety and
inclusion. 
The Council’s Environmental
Sustainability & Climate Change Strategy
includes actions to achieve net-zero
carbon emissions by 2030.  The delivery
of new housing has a key role to play in
carbon reduction, climate change
mitigation, and alleviation of fuel poverty. 
The Council and its partners will continue
to consider innovative and sustainable
approaches to heat and power, such as
low carbon heat, solar photovoltaic panels
and smart technologies.  The Council
recognises that a ‘fabric first’ approach to
sustainability can provide benefits to
tenants, in terms of reducing heating
costs, and also benefit the environment,
all of our homes are designed to minimise
heat loss. 
The Council completed two ‘sustainable
demonstrator homes’ within Dickson
Drive, Irvine in 2020 to highlight best
practice in design and innovation,
ensuring benefits from sustainable
technologies are maximised. The benefits
are currently being assessed, and the
findings will be shared with partners to
inform future developments. To build
upon this, we are developing a
‘sustainability shopping basket’ to
establish a standard suite of sustainability
measures for each development and
have committed to engaging a
sustainability expert to ensure technology
delivers low fuel costs for tenants whilst
maximising energy efficiency and
reducing carbon emissions.   
All Council developments are planned
using ‘secure by design’ principles.  Also,
in recognition of the safety benefits of
sprinkler systems, the Council installed
sprinklers in all new build housing
proposals which reached technical design
stage after October 2019, prior to the
introduction of Building Standards
legislation in March 2021.
Biomass District Heating Network at Flatt
Road, Largs
Dickson Drive, Irvine

Page 20

Recognise local needs and aspirations and become an integral
part of existing estates. Homes should be designed in such a
way that they can be ‘homes for life’ and easily adapted to the
changing needs of their occupants.   
It has become clear from numerous development project consultation
events carried out by the Council and its partners to date, that most
local people express a preference for houses rather than flats. In
some areas it may be appropriate to include flatted development,
which will be assessed on a case-by-case basis. 
In 2019, the updated North Ayrshire Housing Allocation Policy
removed the age restriction for the allocation of amenity housing. 
The allocation of amenity homes to younger people with mobility
requirements promotes independent living and ‘homes for life’. 
The Council and its partners recognise that bringing former social
housing stock into ownership can assist with housing management
and maintenance issues and increase housing available through the
North Ayrshire Housing Register.  Empty homes are detrimental to
the local environment, often the target of antisocial behaviour and are
more likely to fall into disrepair. Bringing empty homes back into use
is a strategic priority within the current LHS and will continue to be a
priority in the future.  The second hand and empty homes buy back
scheme can also assist the Council to deliver our Estate Based
Regeneration Programme by acquiring homes in communal blocks or
in areas identified for improvement through the scheme.
Before and after photographs of an empty home brought back
into use

Page 21

Maximise return on investment and value for money by considering build and lifetime maintenance costs.  
As part of the tendering process we prepare a minimum
specification for materials utilised in our new build
developments to ensure that they align to our current
lifecycle replacement and maintenance programmes.  We
have also developed a suite of standard house types to
further assist with maintenance programmes and reduce
project design costs. 
The Council is committed to making efficiency savings
through strategic procurement arrangements in the
delivery of our new build affordable housing programme,
to ensure value for money for our tenants.  We have
procured contractors for several SHIP projects through
the HubSW, as part of a procurement strategy to achieve
cost and time savings through economies of scale.  The
Council has also, with ten local authority partners, worked
with Scotland Excel to develop a New Build Residential
Construction Framework Agreement available for use by
all Scottish local authorities and registered social
landlords.   
The LHS recognises that many tenants in social housing
are on lower incomes and/or dependant on benefits. The
Scottish Housing Regulator expects social landlords to be
able to demonstrate affordability and engage meaningfully
with tenants on rent increases. Therefore, to ensure
homes are affordable, partners are expected to set rent
levels on new build homes at or below the Local Housing
Allowance.
Standard House Type: 3-bedroom ground floor living for wheelchair users

Page 22

Involve the local community through
consultation and wider action initiatives.  
The Council and our partners engage with
local communities when developing all new
build development sites through the SHIP. 
For Council projects local residents are
invited to review and comment upon the draft
plan for the site.  Thereafter the final plans
are presented to the community and local
residents are also invited to ‘Meet the
Builder’ when a contractor has been
appointed. 
The Council’s Community Wealth Building
Strategy introduced a new model to develop
resilient, inclusive local economies, with
more local employment and a larger and
more diverse business base, ensuring that
wealth is locally owned and benefits local
people.  Through the SHIP, contractors are
expected to participate in the Council (or
partners’) Community Benefits scheme,
providing apprenticeships to young people,
skilling up the local workforce and supporting
economic growth. Homes for Scotland
suggests there are 4.1 jobs created for every
new home constructed. Effective use of
community benefit clauses in development
contracts, and partnership work with
colleagues in Economic Development to
support our local construction and supply
chain companies to bid for this work, can
secure many of these jobs for our local
people. 
The Council is currently developing a pilot
model for employability by offering training
and employment opportunities obtained
through community benefits from Housing
Services maintenance and investment
contracts to our Housing First tenants,
supporting some of our most complex
support cases to sustain housing and
employment. 
The Council also plans to undertake a review
of our Dickson Drive, Irvine house building
pilot and will utilise this to inform a second
project with Building Services to construct a
number of new homes at Ayrshire Central,
Irvine.   
Seek to continually improve, with lessons
learnt and good practice shared across all
partners.  The Council regularly meets with
the Scottish Government and our partner
RSLs to review the progress of the SHIP and
share good practice and lessons learned. 
The Council also holds ‘lessons learned’
meetings and undertakes tenant satisfaction
surveys for each site.
All projects which meet the criteria
outlined within the SHIP will be
considered to be ‘high priority’. In
the case of developments by
Registered Social Landlords
(RSLs), the housing mix and type
for each individual development
site and the proposed rent levels
for the new homes should be
formally agreed with the Council
prior to the submission of a
planning application. 
Projects from the SHIP 2022-2027
which have not yet completed have
been included in the new 2023-
2028 plan.  Thereafter, the Council
will prioritise all projects which are
considered deliverable and meet
the strategic goals outlined above.

Page 23

Demand 
Demand figures have been obtained from the North Ayrshire Housing Register (NAHR). House size
and type priorities have also been informed by the NAHR. 
The HNDA sets the housing estimate for the period 2022-2027 as 2,330 new units, either in the
social rented sector, or, in the case of strong economic recovery, split across all tenures. 
Housing supply targets will be set out in the new Local Housing Stategy which is currently being
prepared. 
Location 
A Sub Housing Market Areas (SHMA) is the widest area that a person would be willing to move to for new living accommodation for the
purposes of strategic housing planning. North Ayrshire contains five SHMAs, these are: 
The North Ayrshire Community Planning Partnership approach sets out six localities. The localities align to the SHMAs with the exception
of the Irvine and Kilwinning localities which combine to form one single Sub Housing Market Area. 
The total number of homes which will be developed over the lifetime of the SHIP have been plotted by SHMA in figure 1 below. These new
supply figures illustrate the aspiration to plan for a growing population, and to seek continued investment in our housing stock to improve
overall stock condition.   
Arran Garnock Valley Irvine/Kilwinning North Coast
(incl. Cumbrae) Three Towns
Whilst there are 6,994
applicants on the
NAHR, only 49% of
these applicants
(3,460) have a
recognised housing
need (NAHR, August
2022).

Page 24

Figure 1: SHIP Actual & Projected Completions 2022-2028 & Net Gain 2022-2028 
The 'net gain' columns indicate the additional homes available per locality following completion of the developments, minus the strategic
demolitions set out in the SHIP. 
To further inform demand for housing on the Isle of Arran, the Council has undertaken research to determine locality preferences for housing
on the island. 
Development is not the only policy intervention being explored by the Council. It would be very difficult for the Council
and its partners to meet housing need only through investment in new homes.   
Work to maintain and improve the condition of our existing social housing stock, provide aids and adaptations and
improve the private rented sector are all intended to address the housing needs of the local population

Page 25

Size 
Analysis of the North Ayrshire Housing Register identifies demand trends for properties. House size has been identified by considering the
minimum accommodation size suitable for the household; this is referred to as the 'strategic bedroom requirement’.   
Table 1: % Applicants by Strategic Bedroom Requirement and SHMA 
No of Beds Three Towns Arran Garnock Valley Irvine / Kilwinning North Coast North Ayrshire
1 60% 54% 56% 56% 63% 57%
2 14% 14% 10% 15% 14% 14%
3 15% 20% 20% 15% 15% 16%
4 7% 9% 6% 10% 5% 8%
5+ 4% 3% 8% 4% 3% 5%
(Source: North Ayrshire Housing Register, August 2022) 
The strategic bedroom need is used for planning purposes only. Generally, one-bedroom homes are found to be of lower demand.  Two-
bedroom homes are a more popular option for smaller households and are more flexible in meeting households’ future needs. An additional
bedroom can also provide study space, or space for home working. 
An indicative size mix (Table 2) for developments across North Ayrshire has been prepared by uplifting the two-bedroom provision and
reducing the one-bedroom, thus meeting tenant aspirations and providing flexibility in terms of property sizes as households change
composition over time. 
Table 2: Altered Demand by Bedroom Size (Reflecting Aspiration) and SHMA 
This mix is intended as a guide only; each project will be considered on a site-by-site basis by the developing organisation, before being
approved by the Council. 
No of Beds Three Towns Arran Garnock Valley Irvine / Kilwinning North Coast North Ayrshire
1 14% 14% 10% 15% 14% 14%
2 60% 54% 56% 56% 63% 57%
3 15% 20% 20% 15% 15% 16%
4 7% 9% 6% 10% 5% 8%
5+ 4% 3% 8% 4% 3% 5%

Page 26

Dementia Friendly Design
Wet Floor Shower Rooms with
Contrasting Fittings as Standard Visiting Service Rooms
Specialist Housing Needs 
Housing for Older People 
Analysis of the HNDA and the NAHR indicates a rising need
for accommodation for older people. For this reason, the
LHS sets a target of approximately 25% of all new homes to
be suitable for older people (i.e., amenity housing and
sheltered accommodation). It is anticipated that these homes
will primarily comprise one and two bedrooms.  In the 12
months from 1 September 2021, 70% of applicants allocated
amenity housing were aged over 51. The Council will
continue to monitor the availability of housing for older
people to ensure that their needs can be addressed through
the affordable housing supply programme.   
Alongside the new build programme, the Council will
continue to deliver our Sheltered Housing Re-provisioning
Programme, which includes £25m investment in the
refurbishment of sheltered housing units out with the SHIP. 
Glencairn House Sheltered Complex

Page 27

Extra Care Housing 
Housing Services and the Health and Social Care Partnership worked together over the last few years to consider a model for Extra Care
Sheltered Housing. The vision was to create safe, affordable homes for tenants who require additional support, with extra services to
promote independent living, such as assistance with meals or welfare checks, to be available to tenants for an additional fee. 
Following development of the outline model, demand analysis was undertaken by the Health and Social Care Partnership in 2021 alongside
engagement with other areas in Scotland where similar housing models operate.  At that time, it was determined that there was not sufficient
demand to integrate the model into a new sheltered housing complex and there are challenges in sustainable funding to operationalise the
model.  The Council has, however, incorporated flexibility into some new build sheltered complexes to allow this model to be reconsidered
in the future should the HSCP chose to develop this further. 
Assistive Technology 
In order to promote independent living, the Flatt Road development in Largs is being used as an exemplar for assistive technology.  Features
that can be installed within the sheltered housing complex and supported accommodation, where required, to support tenants’ individual
needs include: 
An integrated home communications hub with:
video door entry video calls electronic welfare
checks
enhanced assistive
technology
safety monitors
and sensors
electronic
noteboard &
calendar
android apps
Automatic lights and blinds
Smart heating controls
Super-fast broadband

Page 28

2 Bedroom Wheelchair User Bungalow
Wheelchair Accessible Accommodation 
‘Housing for Varying Needs’, a national design guide, provides the following definitions which have been adopted by the LHS when
describing the applicable specialist housing: 
All amenity and sheltered housing in North Ayrshire should be built to an ambulant housing standard as a minimum.  To ensure need is met
now and in the future, the LHS sets a target for all partners to ensure at least 7% of all new build stock is fully wheelchair accessible.  To
date, 16% of new build homes delivered by North Ayrshire Council are suitable for wheelchair users.  It should be noted that most demand
for wheelchair user housing comes from those under 60 years old.  In addition, we have a set of standard house types for our developments,
which are of an accessible design to accommodate changing mobility needs.   
In 2019, the Scottish Government issued guidance for local authorities on the setting of LHS targets to support the delivery of more
wheelchair accessible housing, including the requirement for a private sector target.  The Council will consider this during renewal of the
LHS in late 2022, and the next Local Development Plan due to be published in 2023. 
Occasionally it may be necessary to build larger specialist housing to meet the specific needs of individual households. Where this is being
provided by an RSL, the Council will approve the proposals before a planning application is submitted. 
Ambulant Housing
Meets a wide range of specialist housing needs. The majority of demand is
likely to be from the older age group, who have mobility problems, but who
can walk with (or without) an aid. Some people in this group may occasionally
use a wheelchair. Demand is not exclusive to the older age group; mobility
issues can affect people throughout their lives, for various reasons.
Wheelchair User Housing
For people who use a wheelchair all or most of the time. The home will be level
access throughout, have space for a wheelchair to circulate and access all
rooms, a kitchen and bathroom that suits the occupant's particular needs and
fittings and services that are within reach and easy to use. A wheelchair user
may live alone, or with a carer or partner or be part of a family unit.

Page 29

Supported Accommodation 
Officers within the Place Directorate and the
Health and Social Care Partnership have
developed a new supported accommodation
housing model for implementation at various
sites across North Ayrshire. 
The focus is on maximising independence for
adults within a homely setting, who require a
higher level of support, and who are living with
learning disabilities, or mental ill-health issues
(all ages), or who are under 65 years and have
physical disabilities.  The new supported
accommodation model can: 
The SHIP will support the Health and Social Care Partnership to meet specialist housing need through dedicated supported accommodation
projects, and as part of a wider site mix on other developments. The SHIP makes provision for delivery of 25 supported accommodation
housing units at two different locations in addition to the 37 homes already delivered.  
prevent
demand for
additional
services
support a
more
independent
lifestlye for
service users
integrate
residents into
community
life
use
technological
advances to
support care
provision
provide care
and support
in a homely
setting
provide a
base for
effective care
provision
realise
financial
savings for
the HSCP
Supported accommodation at Bessie Dunlop Court, Dalry

Page 30

Gypsy / Travellers   
The Council has not identified any
additional demand issues in relation to
accommodation for gypsy / travellers.  We
will, however, review the condition of our
permanent site at Redburn, Irvine in
consultation with residents to identify any
future maintenance and investment
works. 
When this review is complete, the Council
will apply to the Scottish Governments
Gypsy / Traveller Accommodation Fund to
seek funding for any necessary
renovation or improvements to our
Redburn site. 
Island Communities   
The Council is committed to supporting
our island communities. 18 new homes
were completed on the Isle of Cumbrae
during summer 2021.  The site provided a
mixture of general needs houses, amenity
bungalows and homes for wheelchair
users.   
The Council also completed 34 new
homes at Brathwic Terrace on the Isle of
Arran during June 2022.   
A ‘Local Lettings Initiative’ was introduced
for Arran prior to the allocation of the new
Council homes. The Local Lettings 
Initiative gives additional priority to island
residents and key workers.   
Trust Housing Association is currently in
discussions with a local landowner to
develop 26 new units on Arran. 
These developments, alongside work with
communities on the island, are anticipated
to stimulate investment in other
infrastructure (transport, marine, digital) to
encourage economic growth. 
The Council will closely monitor demand
for future affordable housing on the island.   
St Beya Gardens, Cumbrae   St Beya Gardens, Cumbrae    Brathwic Terrace, Arran

Page 31

Homelessness 
North Ayrshire Council’s Rapid Rehousing Transition Plan 2019 –
2024 was approved in 2019. Our vision is to reduce the time spent
in temporary accommodation by enabling homeless households to
access settled accommodation quickly and with the right support
to sustain their housing outcome.  The North Ayrshire RRTP
outcomes are: 
The provision of new affordable housing through the Strategic
Housing Investment Plan will continue to support the delivery of
the Rapid Rehousing Transition Plan. 
Alternative Models of Affordable Housing Delivery 
Recognising that a suite of affordable housing solutions is required
to meet the needs and aspirations of local people, the Council has
embarked on two pilot projects aimed at the private housing
sector.   
The ‘HOME (Home Ownership Made Easy)’ project is based on a
model devised by Scottish Futures Trust. This shared ownership
housing option will provide households the opportunity to
purchase a stake in a home.  Two options are available, which
have been named for the level of investment required to secure
the HOME: 
• The £5k HOME, aimed at first time buyers.
• The £40k HOME, aimed at owner-occupiers over 60 years who
wish to downsize or secure more accessible housing.   
The Council’s ‘BUILD’ project will offer six fully serviced self-build
plots for sale to individuals interested in this type of project.   
Private Sector Property Condition 
The Council’s revised Scheme of Assistance 2019 introduced a
range of new measures to improve private sector housing
condition, including:
A ‘pre-tenancy support service’ for landlords to aid the
prevention of future property condition issues.
A ‘missing shares scheme’ to remove barriers where a
property owner refuses to meet their common repair
obligations.
Use of the Council’s powers for Compulsory Purchase Orders
(CPOs) where appropriate to acquire empty properties in poor
condition, bringing them back into mainstream housing stock.

Page 32

SHIP Funding Streams 
Affordable Housing Supply Programme
The Scottish Government has committed to providing North Ayrshire with
£63.005m funding for the Council and our RSL partners from April 2022 to
March 2026 (see table 3 below).  The SHIP is based on projected grant
funding of £120.855m.  Funding for Council projects not yet at tender stage
has been assumed at benchmark plus annual Scottish Social Housing
Tender Price Index inflation which was 8.3% for 2021/22 and has been
assumed at 8.6% for 2022/23 and 3.7% for 2023/24.  The Council will seek
grant funding above these levels on a site-by-site basis, as required. The
RSL funding rates have been included as requested by each developing
organisation and will be subject to Scottish Government authorisation.     
Reserves & Balances
All developing organisations
will utilise available reserves
and balances to support the
development programme.
Borrowing
The majority of development funding
is secured from borrowing. Private
finance supports RSLs’ development
programme, and prudential borrowing
supports local authority new build
projects.
Affordable Housing Policy Developer Contributions
The Council’s previous Affordable Housing Policy (RES4), which required
contributions to affordable housing provision from specified private
developments within North Ayrshire, was removed within the new Local
Development Plan (LDP2) which was adopted on 28 November 2019. 
Developer contributions, in the form of commuted sums, received through
the application of the Affordable Housing Policy to date under the previous
Local Development Plan, will be utilised to fund projects being delivered
through the SHIP, when required.
Other Funding
Sources
The Council will consider
utilising the Vacant and
Derelict Land Fund to
support the regeneration of
SHIP sites, where
strategically aligned to the
Council’s Regeneration
Delivery Plan.
Council Tax on Empty &
Second Homes
Income received from the reduction in
discount for empty and second homes
in North Ayrshire is held in the
Council’s Affordable Housing Account.
The Council provides grant funding to
support the development of projects
within the SHIP from the Affordable
Housing Account, when required. 
To meet the requirement for ‘slippage’, in accordance with Scottish Government guidance, the Council has over committed the funding
within the SHIP.  The slippage requirement is to ensure that the allocation is fully spent even if delays or constraints emerge on other
development sites, and to provide the opportunity for North Ayrshire to absorb slippage from other local authority areas.
Table 3: North Ayrshire Resource Planning Assumption per Annum 2022/23 to 2025/26  
2022/23 2023/24 2024/25 2025/26 Total
RPA £15.692m £15.648m £15.702m £15.963m £63.005m

Page 33

Planning and other
Regulatory Matters 
In 2014, the Council’s Cabinet approved the House Building
Protocol, to be used in all Council housing development projects
that meet the criteria for permitted development. Class 33 of the
Town and Country Planning (General Permitted Development)
(Scotland) Order 1992, as amended, enables local authorities to
carry out works, within their district, for the erection of dwellings
so long as the development conforms with the Local
Development Plan. 
In 2019, it was agreed that all future Council housing
developments progressed as permitted development will be
required to obtain a ‘Certificate of Lawfulness’ from the Council’s
Planning Service. This will certify that each site within the SHIP
has been considered against the full terms of the adopted Local
Development Plan. Housing development proposals by the
Council which do not fall within the scope of permitted
development, including schemes which require an Environmental
Impact Assessment (EIA) will require planning permission.
Proposals over 0.5 hectares in area will require to be screened
for the purposes of EIA. 
Risks to delivering the
SHIP 
Whilst delivery of the SHIP programme has recovered following
the temporary suspension of all projects on site in March 2020,
this has had longer term implications.  COVID-19 continues to
have an impact on the construction industry. 
Through our own experience and engagement with RSLs and
other developers, development constraints or risks to delivery of
the programme have been identified as: 
 Building costs inflation and rising tender prices
 Shortages of materials
 Capacity within the building and development industry
across the country
 Costs of infrastructure and ground remediation
 Delays to getting statutory utility consents in place
 Workforce interruptions related to COVID-19 
The Council and our partners will continue to work closely
to monitor and actively manage these risks through the period of
the SHIP.

Page 34

Amendments or Additions to the SHIP 
The delegated authority to accelerate any project detailed within the North Ayrshire approved SHIP is held by the Executive Director (Place)
and the Cabinet Member for Place. 
SHIP Development Projects 
An overview of projects detailed in the SHIP tables is provided below by locality.   
Irvine & Kilwinning 
Project Timeline Site Information
St. Michael’s Wynd,
Kilwinning (NAC)
79 units
Site Start: September 2020
Completion: 
7 September 2022
The new homes link to the first phase St Michael’s Wynd development.   The site
includes general needs, amenity, wheelchair user housing, sheltered housing and
supported accommodation and benefits from good transport links.
Harbourside, Irvine
(NAC)
71 units
Site Start: October 2020
Expected Completion: 
Early 2023
The site is in a high-demand area and is a short walk from Irvine Beach Park, the town
centre, shopping mall and train station. The site will deliver an intergenerational
development with a particular focus on older people’s housing provision. 
Bourtreehill Village,
Irvine (NAC)
32 units
Site Start: Autumn/winter 2023 
Expected Completion: 
Autumn/winter 2025 
The site will see the regeneration of the Bourtreehill Village area of Irvine. Consultations
are underway with residents of the local area and interested parties to develop the
vision for the site.  
Corsehillhead,
Kilwinning (NAC)
7 units
Site Start: Spring 2023 
Expected Completion: 
Spring 2024
The site will deliver a mix of general needs and amenity accommodation in the Corsehill
area of Kilwinning.
Montgomerie Park,
Irvine (NAC)
189 units
Site Start: Summer 2023
Expected Completion: 
Winter 2026  
This site will provide a mix of general needs, amenity and wheelchair user
accommodation.

Page 35

Ayrshire Central, Irvine
(NAC)
202 units
Site Start: Spring 2023
Expected Completion: 
Spring 2026
Located in a high demand area, this site will deliver a mix of general needs, amenity and
wheelchair properties at the Ayrshire Central, Irvine site.  
Stanecastle, Irvine
(NAC) 
31 units
Site Start: Spring 2023
Expected Completion: 
Autumn 2024
This site will deliver a mix of general needs, amenity and wheelchair user
accommodation on the site of the former Stanecastle School.
Fullarton Street, Irvine
(NAC) 
62 units
Site Start: Early 2024
Expected Completion: 
Summer 2025
This project will deliver a mix of general needs, amenity and wheelchair accommodation
on the site of the Irvine High Flats which are scheduled for demolition.
King’s Arms, Irvine
(NAC)
6 units
Site Start: Spring 2023
Expected Completion: 
Autumn 2024
This project involves the regeneration of a prominent town centre building to deliver six
amenity flats.
Confidential Site 1
(Cairn) 
9 units
Site Start: Winter 2023
Expected Completion: 
Winter 2024
This development will provide general needs, amenity and wheelchair accommodation.
This site is currently confidential due to a requirement for planning consent and for
acquisition of land.
Confidential Site 3
(Cairn) 
4 units
Site Start: Spring 2025
Expected Completion: 
Spring 2026
This site has the capacity for 4 affordable, general needs homes.  This site is currently
confidential due to a requirement for planning consent and for acquisition of land. 
West Byrehill,
Kilwinning (CHA) 
72 units
Site Start: April 2021
Expected Completion: 
February 2023
Located on the edge of Kilwinning, this site will provide a mix of general needs, amenity
and wheelchair user homes. 
Harbour Road, Irvine
(CHA)
27 units
Site Start: Spring 2023
Expected Completion: 
Spring 2024
Located in Irvine Harbourside this site will provide 27 new homes in close proximity to
the town centre and Irvine train station. 
Bank Street, Irvine
(CHA)
16 units
Site Start: Spring 2025
Expected Completion: 
Spring 2026
This town centre regeneration project in Irvine was previously allocated for Riverside.
Riverside are no longer able to progress the scheme and CHA are currently determining
the viability of delivering 16 new homes for affordable rent.
Tarryholme, Irvine,
Phase 2 (Riverside)
77 units
Site Start: June 2021
Expected Completion: 
February 2023
This project is a second phase of the Tarryholme development which will deliver an
additional 77 units.

Page 36

Three Towns 
Project Timeline Site Information
Caley Court,
Stevenston (NAC)
16 units
Site Start: August 2021
Expected Completion: 
Autumn/winter 2022
This development is located on the site of a former sheltered housing complex.  The new
homes will provide supported accommodation with an on-site staff base in close
proximity to Stevenston town centre and train station.
Afton Court,
Stevenston (NAC)
6 units
Site Start: Winter 2022
Expected Completion: 
Summer 2023
This town centre regeneration project will deliver 6 amenity bungalows, recognising the
highly accessible nature of this location. Modular construction will be utilised to reduce
the time on site and the impact of the works on local residents.  
James McFarlane,
Saltcoats (NAC)
19 units
Site Start: Spring 2023
Expected Completion: 
Spring/summer 2024
The site of the former James McFarlane school will provide general needs, amenity and
homes suitable for wheelchair accommodation. 
James Reid, Saltcoats
(NAC)
47 units
Site Start: Spring 2023
Expected Completion: 
Winter 2024
The site of the former James Reid school and the former Focus Centre will provide general
needs, amenity and wheelchair accommodation. 
Glebe Place, Saltcoats
(NAC)
8 units
Site Start: Spring 2026
Expected Completion: 
Spring/summer 2027
This regeneration project which includes the demolition of low demand flats can
accommodate approximately 8 new affordable homes near Saltcoats town centre.  
Regeneration Project
1d, Ardrossan (NAC)
36 units
Site Start: Autumn 2024
Expected Completion: 
Spring 2026
This project provides a regeneration opportunity for 36 affordable homes, comprising
general needs, amenity and wheelchair accommodation. 
Regeneration Project
1e, Ardrossan (NAC)
7 units
Site Start: Spring 2024
Expected Completion: 
Spring/summer 2025
This regeneration opportunity can accommodate approximately 7 new affordable homes. 
Glebe Street, Saltcoats
(CHA)
2 units
Site Start: June 2026
Expected Completion: 
March 2022
This formerly vacant site provided 2 homes suitable for wheelchair users. This site was
also supported by funding from the Council’s Affordable Housing Account. 
Green Street, Saltcoats
(CHA)
24 units
Site Start: April 2022
Expected Completion: 
Spring/summer 2023
Demolition of the former building on the site is now complete and works to construct the
24 new amenity homes commenced in April 2022. 
Sharphill Phase 5,
Saltcoats (CHA)
100 units
Site Start: Spring 2023
Expected Completion: 
Winter 2024
The next phase of the Sharphill site will deliver an additional 100 new homes, providing a
mix of general needs, amenity and wheelchair user homes.

Page 37

Garven Road,
Stevenston (CHA)
20 units
Site Start: Spring 2023
Expected Completion: 
Spring/summer 2024
This site was formerly known as Confidential Site 8 and has capacity to deliver 20 new
homes.
Confidential Site 9,
Stevenston (CHA)
70 units
Site Start: 
Expected Completion: 
This site has been removed from the SHIP as it is not viable.  The 70 units have been
moved to the ‘Unallocated CHA Block’ to provide CHA with capacity for future
development within the SHIP as sites are identified.
Confidential Site 10,
Ardrossan (CHA) 
50 units
Site Start: Spring 2025
Expected Completion: 
Winter 2026
This project has capacity for up to 50 homes and is confidential until site feasibility can
be confirmed. 
Confidential Site 11,
Saltcoats (CHA)
22 units
Site Start: 
Expected Completion:
This site has been removed from the SHIP as it is not viable.  The 22 units have been
moved to the ‘Unallocated CHA Block’ to provide CHA with capacity for future
development within the SHIP as sites are identified.
Parkend Gardens,
Saltcoats (Link)
12 units
Site Start: Early 2023
Expected Completion: 
Early 2024
This development is located in close proximity to Saltcoats town centre and adjacent to
North Ayrshire Council’s new development at Kyleshill Court, Saltcoats. It will deliver a
mix of general needs, amenity and wheelchair accommodation. 
North Coast
Project Timeline Site Information
Former St. Colm’s Place,
Largs (NAC)
29 units
Site Start: June 2021
Expected Completion: 
September 2022
The former sheltered housing complex at St. Colm’s Place was demolished and rebuilt as
part of the sheltered housing re-provisioning programme.  Located in a high demand
central area it has good transport links and access to the town centre. 
Former Largs Police
Station (NAC)
12 units
Site Start: Autumn 2022
Expected Completion: 
Autumn 2023
Located adjacent to the former St. Colm’s Place the former Largs Police Station will deliver
12 amenity flats in the high demand, town centre, location. 
Garnock Valley
Project Timeline Site Information
Former Garnock
Academy, Kilbirnie (NAC)
50 units
Site Start: Spring 2023
Expected Completion: 
Autumn/winter 2024
The site of the former Garnock Academy will see the development of a mixture of general
needs homes, amenity bungalows and homes suitable for wheelchair users.

Page 38

Laburnum Avenue, Beith
(NAC)
7 units
Site Start: Autumn 2023
Expected Completion: 
Autumn 2024
This development will regenerate low demand flatted accommodation to deliver 7 new
affordable homes in Beith.  
Newhouse Drive,
Kilbirnie (NAC)
7 units
Site Start: Autumn 2023
Expected Completion: 
Autumn 2024
This development will regenerate low demand flatted accommodation to deliver 7 new
affordable homes in Kilbirnie.   
Arran
Project Timeline Site Information
Confidential Site 4 
(Trust HA)
26 units
Site Start: Winter 2024
Expected Completion: 
Winter 2026
This site is confidential to allow the acquisition of land and whilst site viability is
confirmed. 
Locality to be Confirmed
Project Timeline Site Information
Unallocated
Regeneration Block (NAC)
30 units
Site Start: Autumn 2024
Expected Completion: 
Autumn 2026
This involves the regeneration of 30 properties to deliver a mix of general needs, amenity
and wheelchair user properties. The locations for these projects have still to be finalised. 
Regeneration Project 3
(Riverside)
30 units
Site Start: Spring 2025
Expected Completion: 
Spring 2027
This project involves the regeneration of 30 properties to deliver a mix of general needs,
amenity and wheelchair user properties. The location has still to be finalised. 
Unallocated CHA Block
(CHA)
92 units
Site Start: Spring 2024
Expected Completion:
Winter 2025 
The 92 units have been allocated within the SHIP to replace Confidential Sites 9 and 11
which were not viable. This will provide CHA with capacity for future development as the
association identifies suitable sites.

Page 39

Official‐Protect#
Appendix 1 SHIP 2023‐2028
Pre 2023/24
2023/24
2024/25
2025/26
2026/27
2027/28
2022/23
2023/24
2024/25
2025/26
2026/27
2027/28
General
Needs
Am
enity
Supported
W
heelchair
GFL
Sheltered
St. Michael's Wynd Kilw X: 229250 Y: 643100 NAC 79 New Build 14 Sep 20 07 Sep 22 2020/21 79 79 - 34 2 10 2 7 24 £4,661,000 £0 £0 £0 £0 £0 £0
Harbourside Irv X: 230880 Y: 638145 NAC 71 New Build 26 Oct 20 31 Jan 23 2020/21 71 71 - 24 11 4 4 28 £4,970,000 £0 £0 £0 £0 £0 £0
St. Colm's Place (Redev 5) Lrgs X: 220370 Y: 659565 NAC 29 New Build 09 Jun 21 15 Sep 22 2019/20 29 29 - 29 £1,711,000 £0 £0 £0 £0 £0 £0
Caley Court Stev X: 226725 Y: 641478 NAC 16 New Build 16 Aug 21 31 Oct 22 2021/22 16 16 £1,123,123 1 15 £1,036,348 £86,775 £0 £0 £0 £0 £0
2nd Hand & Empty Home Buy Backs ! ! NAC 30 Buy Back 01 Mar 22 31 Mar 27 2022/23 5 5 5 5 5 5 5 5 5 5 5 5 £1,200,000 30 £0 £200,000 £200,000 £200,000 £200,000 £200,000 £200,000
Largs Police Station (Redev 13) Lrgs X: 220315 Y: 659560 NAC 12 New Build 29 Aug 22 30 Sep 23 2022/23 12 12 £1,192,712 12 £177,031 £1,015,681 £0 £0 £0 £0 £0
Afton Court (Redev 6a) Stev X: 226665 Y: 641885 NAC 6 New Build 30 Nov 22 01 Jun 23 2022/23 6 6 £664,163 6 £0 £664,163 £0 £0 £0 £0 £0
Nelson Street Lrgs X: 220655 Y: 659595 NAC 3 Refurb 01 Feb 23 01 Feb 25 2022/23 3 3 £171,000 3 £0 £71,000 £100,000 £0 £0 £0 £0
Corsehillhead Kilw X: 231315 Y: 643095 NAC 7 New Build 01 Apr 23 30 Apr 24 2022/23 7 7 £711,516 5 2 £130,500 £0 £581,016 £0 £0 £0 £0
James McFarlane (Redev 8a) Ardr X: 223300 Y: 643345 NAC 19 New Build 01 Apr 23 31 May 24 2022/23 19 19 £1,993,029 10 4 1 4 £233,022 £0 £1,500,000 £260,006 £0 £0 £0
Stanecastle (Redev 11a) Irv X: 234070 Y: 640150 NAC 31 New Build 01 Apr 23 01 Sep 24 2022/23 31 31 £3,204,355 17 7 3 4 £493,411 £0 £1,500,000 £1,210,944 £0 £0 £0
James Reid & FC (Redev 8b) Salt X: 225511 Y: 642690 NAC 47 New Build 01 Apr 23 30 Nov 24 2022/23 47 47 £4,858,216 26 11 4 6 £602,999 £0 £2,161,579 £2,093,637 £0 £0 £0
Garnock Academy (Redev 9) Kilb X: 231290 Y:654800 NAC 50 New Build 01 Apr 23 30 Nov 24 2022/23 50 50 £5,306,966 28 13 2 7 £473,370 £0 £2,500,000 £2,333,596 £0 £0 £0
Ayrshire Central (Redev 12) Irv X: 232105 Y: 640785 NAC 202 New Build 01 Apr 23 31 Mar 26 2022/23 202 202 £20,010,798 65 87 24 26 £2,252,936 £0 £4,000,000 £7,000,000 £6,757,862 £0 £0
King's Arms (Regen 1c) Irv X: 232090 Y: 638935 NAC 6 New Build 01 Apr 23 31 Oct 24 2022/23 6 6 £543,319 6 £0 £0 £543,319 £0 £0 £0 £0
Montgomerie Park, Irvine Irv TBA NAC 189 New Build 01 Aug 23 30 Nov 26 2023/24 189 189 £19,698,882 111 39 19 20 £4,579,235 £0 £3,500,000 £5,000,000 £5,000,000 £1,619,647 £0
Bourtreehill Village (Redev 7) Irv X: 234475 Y: 639220 NAC 32 New Build 01 Sep 23 30 Sep 25 2023/24 32 32 £3,307,722 24 6 1 1 £0 £0 £1,000,000 £2,307,722 £0 £0 £0
Laburnum Avenue (Regen Project 1a) Beith X: 234170 Y: 653640 NAC 7 New Build 01 Oct 23 31 Oct 24 2022/23 7 7 £699,468 4 3 £0 £0 £200,000 £499,468 £0 £0 £0
Newhouse Drive (Regen Project 1b) Kilb X: 230940 Y: 653815 NAC 7 New Build 01 Oct 23 31 Oct 24 2022/23 7 7 £699,468 4 3 £0 £0 £200,000 £499,468 £0 £0 £0
Fullarton Street (HF) Irv X: 232050 Y: 638550 NAC 62 New Build 01 Feb 24 30 Jun 25 2023/24 62 62 £6,355,354 40 15 2 5 £0 £0 £0 £3,200,000 £3,155,354 £0 £0
Refurbishment Project 8 Irv TBA NAC 2 Refurb 01 Nov 23 01 Nov 25 2023/24 2 2 £114,000 2 £0 £0 £14,000 £100,000 £0 £0 £0
Regeneration Project 1e Ardr TBA NAC 7 New Build 01 Apr 24 30 Apr 25 2023/24 7 7 £725,348 4 3 £0 £0 £0 £400,000 £325,348 £0 £0
Regeneration Project 1d Ardr TBA NAC 36 New Build 01 Sep 24 30 Apr 26 2024/25 36 36 £3,983,812 20 5 11 £0 £0 £0 £1,000,000 £2,000,000 £983,812 £0
Unallocated Regeneration Block 1 TBA TBA NAC 30 New Build 01 Sep 24 30 Sep 26 2024/25 30 30 £3,188,953 16 9 2 3 £0 £0 £0 £1,000,000 £1,241,084 £947,870 £0
Glebe Place Salt X: 224700 Y: 641700 NAC 8 New Build 01 Apr 26 30 Apr 27 2024/25 8 8 £836,109 5 3 £0 £0 £0 £0 £0 £422,365 £413,744
Unallocated Regeneration Block 2 TBA TBA NAC 0 New Build - - - - £0 £0 £0 £0 £0 £0 £0
Confidential Site 1 ₴ Irv TBA Cairn 9 New Build 31 Oct 23 31 Oct 24 2023/24 9 9 £910,000 6 3 £0 £0 £600,000 £310,000 £0 £0 £0
Confidential Site 3 Kilw TBA Cairn 4 New Build 01 Apr 25 31 Mar 26 2024/25 4 4 £320,000 4 £0 £0 £0 £0 £320,000 £0 £0
Sharphill (Ph 4) Salt X: 225343 Y: 643182 CHA 76 New Build 20 Jan 20 31 Mar 22 2019/20 76 76 - 65 5 5 1 £6,915,235 £0 £0 £0 £0 £0 £0
Glebe Street (Confidential Site 5) Salt X: 224625 Y: 641747 CHA 2 New Build 07 Jun 21 02 Mar 22 2021/22 2 2 - 2 £144,000 £0 £0 £0 £0 £0 £0
West Byrehill (Phase 1 & 2) Kilw X: 228760 Y: 642710 CHA 72 New Build 12 Apr 21 28 Feb 23 2020/21 72 72 £6,351,729 59 8 3 2 £6,351,729 £0 £0 £0 £0 £0 £0
Green Street (Confidential Site 7) Salt X: 224755 Y: 641300 CHA 24 New Build 18 Apr 22 31 May 23 2021/22 24 24 £2,065,435 22 2 £418,365 £1,647,070 £0 £0 £0 £0 £0
CHA Buy Back Programme ! ! CHA 6 Buy Back 01 Nov 22 31 Mar 28 2022/23 6 1 1 1 1 1 1 £240,000 6 £0 £40,000 £40,000 £40,000 £40,000 £40,000 £40,000
Garven Road (Confidential Site 8) Stev TBA CHA 20 New Build 01 Feb 23 30 Apr 24 2022/23 20 20 £2,050,000 20 £0 £400,000 £1,650,000 £0 £0 £0 £0
Harbour Road Irv X: 231397 Y: 638254 CHA 27 New Build 28 Feb 23 30 Apr 24 2022/23 27 27 £3,224,983 27 £0 £400,000 £1,500,000 £1,324,983 £0 £0 £0
Sharphill (Ph 5) Salt X: 225351 Y: 643409 CHA 100 New Build 01 Mar 23 30 Dec 24 2022/23 100 100 £11,400,000 100 £0 £500,000 £5,246,122 £5,653,878 £0 £0 £0
Confidential Site 11 Salt TBA CHA - New Build - - 2023/24 - £0 £0 £0 £0 £0 £0 £0
Confidential Site 9 ₴ Stev TBA CHA - New Build - - 2023/24 - £0 £0 £0 £0 £0 £0 £0
Unallocated CHA Block TBA TBA CHA 92 New Build 01 Apr 24 01 Dec 25 2023/24 92 92 £10,524,800 64 23 5 £0 £0 £0 £2,500,000 £4,656,800 £3,368,000 £0
Confidential Site 10 Ardr TBA CHA 50 New Build 01 Apr 25 31 Oct 26 2025/26 50 50 £6,951,200 45 3 2 £0 £0 £0 £0 £4,430,000 £2,521,200 £0
Bank Street (111) Irv X: 232720 Y: 639260 CHA 16 New Build 01 Apr 25 30 Apr 26 2024/25 16 16 £2,224,384 16 £0 £0 £0 £0 £1,000,000 £1,224,384 £0
Parkend Gardens Salt X: 225165 Y: 641130 Link 12 New Build 31 Jan 23 31 Jan 24 2022/23 12 12 £1,932,331 8 3 1 £83,625 £0 £297,759 £600,000 £950,947 £0 £0
Tarryholme (Ph 2) Irv X: 233023 Y: 637910 Riverside 77 New Build 07 Jun 21 28 Feb 23 2020/21 77 77 - 30 36 5 6 £6,000,000 £0 £0 £0 £0 £0 £0
Riverside Buy Back Programme ! ! Riverside 15 Buy Back 01 Apr 23 31 Mar 26 2022/23 15 15 £1,170,000 15 £0 £0 £250,000 £600,000 £320,000 £0 £0
Regeneration Project 3 TBA TBA Riverside 30 New Build 01 Apr 25 31 Mar 27 2024/25 30 30 £2,634,000 18 6 2 4 £0 £0 £0 £0 £1,600,000 £1,034,000 £0
Trust Buy Back Programme Arran ! Trust 6 Buy Back 01 Nov 22 31 Mar 28 2022/23 1 1 1 1 1 1 1 1 1 1 1 1 £600,000 6 £0 £100,000 £100,000 £100,000 £100,000 £100,000 £100,000
Confidential Site 4 ₳  Arran TBA Trust 26 New Build 01 Oct 24 30 Sep 26 2024/25 26 26 £4,500,000 26 £0 £0 £0 £1,000,000 £2,000,000 £1,500,000 £0
1652 638 691 197 106 14 6 429 49 352 423 392 7 £137,687,174 988 356 25 91 111 81 £41,233,807 £5,124,689 £27,683,795 £39,233,701 £34,097,395 £13,961,278 £753,744
SHIP 2021 - 2026 £0 £12,700,000 £12,700,000 £12,700,000 £12,700,000
New addition to SHIP £10,160,000 £10,160,000 £10,160,000 £10,160,000
Confidential Sites
Removed from SHIP 2023 - 2028
₳ The access point for this development should be agreed with NAC Roads as the existing road network may not cope with the additional units
₴ This site is located on Open Ground and can only progress subject to a Planning Application for change of use
Dev Units Type Pre 2022/23
Spend
Estimated
Site Start
Estimated
Practical
Completion
SHIP
Approval
Year
Site Starts Site Completions
Scottish
Government
Grant
House Types
Site Town Site Coordinates SHIP Spend
2026/27
SHIP Spend
2027/28
Estimated
SHIP Spend
2022/23 (as at
18/08/2022)
SHIP Spend
2023/24
SHIP Spend
2024/25
SHIP Spend
2025/26
#Official‐Protect