Page 1

NORTH AYRSHIRE COUNCIL 
27 September 2022 
Cabinet 
Title:    Capital Programme Performance to 31 March 2023 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme for 2022/23. 
Recommendation:  That Cabinet agrees to (a) note the revisions to budgets
outlined in the report; and (b) note (i) the General Services and
HRA revised budgets at 31 July 2022; and (ii) the forecast
expenditure to 31 March 2023. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2022/23 to 2030/31 was
approved by Council on 2 March 2022. The Housing Revenue Account (HRA) Capital
Investment Programme 2022/23 sits within the updated HRA Business Plan and was
approved by Council on 16 February 2022. 
1.2  This report identifies the current programme for 2022/23, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 31
July 2022 and forecast expenditure to 31 March 2023. 
1.3   At Period 4 the General Fund is forecasting a projected breakeven position against a
revised budget of £69.634m. The HRA is forecasting a projected underspend of
£7.036m against a revised budget of £75.145m. 
1.4  Within the General Fund, adjustments to funding have resulted in additions to the
overall capital programme of £3.216m. Further reviews of individual project plans
have identified a number of adjustments to the current profiles. As a result,
(£75.255m) has been reprofiled for delivery in 2023/24. This has been partly offset by
the previously reported re-profiling of £17.521m from 2021/22 and future years to
2022/23. 
1.5  Within the HRA, a review of delivery timescales has identified a requirement to re-
profile (£60.066m) of works for delivery in 2023/24 and beyond. This is offset by
£18.317m previously re-profiled from 2021/22 to 2022/23 and the acceleration of
£2.387m to 2022/23 from future years.

Page 2

1.6 The major risk to the forecast position is the uncertainty arising from the ongoing
inflationary pressures and supply chain issues which are impacting on tender returns
and the cost of materials, as reported across a number of General Fund and HRA
projects. While some mitigation has been built into the programme to offset cost
pressures, any further significant increase in costs will result in increased borrowing
requirements and may have a negative impact on the deliverability of both the
General Fund and HRA capital programmes for 2022/23 and beyond. Projects will
continue to be monitored closely with cost increases met initially from the additional
flexibility built into the programme. However, any requirement for further borrowing will
be a matter for Council to consider. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2022/23 General Services budget: 
2.2 (a) Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
2022/23
£m
Budget as at 2 March 2022 124.152   
a) Changes to Funding 2.937        
b) Other Revisions to the Programme 0.279        
Revised Budget 127.368   
c) Alterations to phasing of projects:-
2021/22 to 2022/23 17.521     
2022/23 to 2023/24 (75.255)    
Budget as at 31 July 2022 69.634     
Funding Body Amount Project
Scottish Government £0.400m VDLF Annickbank
Scottish Government £0.322m Cycling/Walking/Safer Streets
Scottish Government £0.190m Nature Restoration
Scottish Government £0.117m Renewal of Playparks
Scottish Government £0.070m Millport Town Hall

Page 3

2.3 (b) Other Revisions to the Programme 
Adjustments to the utilisation of reserves and application of funding from Revenue have
resulted in adjustments of £0.279m.   
2.4 (c) Alterations to the Phasing of Projects 
The reprofiling of £17.521m from 2021/22 to 2022/23 reflects projects not completed
within the year, or accelerated from future years, and incorporated within the 2022/23
capital programme. These were previously reported within the 2021/22 Capital
Programme performance reports. 
SPT £0.385m Cumbrae Ferry Bus Stop
SPT £0.300m Brodick to Corrie Cycle Path
SPT £0.250m Irvine Cycle Friendly Town
SPT £0.200m Bus Corridor Improvements
SPT £0.100m Bus Route Congestion
SPT £0.100m B714 Active Travel Link
SPT £0.050m Ardrossan Harbour Interchange
Scottish Forestry £0.204m Ross Road Arran
Scottish Forestry £0.199m North Sannox
Sustrans £0.050m Fairlie Coastal Path
Total £2.937m
Funding Body Amount Project
Use of Reserves £0.230m LED lighting Replacement
CFCR £0.043m Homecare System
Capital Receipts £0.006m Vehicle Insurance Recoveries
Total £0.279m
Service Amount Project
Communities £2.177m Moorpark Primary
£0.903m Lockhart Campus
£0.505m Marress House
£0.314m Early Years
£0.251m Kilwinning Learning Environment
£0.221m Montgomerie Park Primary
£0.192m CO2 Monitors in Schools
£0.066m Other Minor Adjustments
£4.629m

Page 4

Chief Executive £0.795m VDLF i3 Irvine
£0.464m Schools ICT Investment
£0.362m AGD
£0.275m VDLF Ardrossan North Shore
£0.193m ICT Investment Fund
£0.123m WAN/LAN/Telephony
£0.116m Low Carbon Hub
£0.044m Other Minor Adjustments
£2.372m
HSCP £0.628m Residential & Respite Unit
£0.186m Improvement Grants
£0.107m Carefirst Replacement
£0.046m Other Minor Adjustments
£0.967m
Place £1.500m Millport Town Hall
£1.057m Lochshore
£0.541m Upper Garnock FPS
£0.465m Place Based Investment
£0.417m Town Centre Regeneration
£0.347m Access Paths Network
£0.316m HOME
£0.635m Cemeteries
£0.269m Repurposing Property Grant
£0.259m Island Infrastructure
£0.241m Bridges
£0.228m Millport CARS
£0.197m B714 Improvements
£0.168m Property Lifecycle Investment
£0.166m Nature Restoration Fund
£0.166m Irvine High Street
£0.118m Renewal of Playparks
£0.115m Roads Improvements
(£0.738m) VDLF realignment to Chief Executives
(£0.302m) CWSS
£0.687m Other Minor Adjustments
£6.852m
Other £2.701m Flexibility/Core Infrastructure
£2.701m
Total £17.521m

Page 5

In addition, a major review of individual project plans, taking cognisance of the current
levels of volatility within the construction sector, has identified a requirement to re-
profile a further (£75.255m) of works for delivery in 2023/24 and beyond. This includes
a corporate phasing adjustment reflecting the degree of uncertainty in the total
expenditure projections: 
2.5 These adjustments have resulted in a revised 2022/23 budget at 31 July 2022 of
£69.634m. 
Service Amount Project
Communities (£10.958m) Ardrossan Campus
(£6.002m) UFSM
(£0.323m) Kilwinning Learning Environment
(£0.066m) Abbey Tower
(£17.349m)
Chief Executives (£24.076m) Ardrossan North Shore
(£1.237m) Low Carbon Hub
(£1.111m) AGD
(£0.050m) Ardrossan Harbour Interchange
(£26.474m)
Place (£6.225m) Solar PV
(£3.232m) HOME
(£1.276m) Millburn FPS
(£1.244m) Cemeteries
(£0.949m) VDLF Annickbank
(£0.663m) Property Lifecycle
(£0.574m) CWSS
(£0.534m) Bridges Infrastructure
(£0.484m) Goldcraigs Refurbishment
(£0.445m) Access Paths
(£0.250m) Brodick to Corrie Cycle Path
(£0.146m) VDLF Development
(£0.100m) Dockhead Street Saltcoats
(£0.090m) Other Minor Adjustments
(£16.212m)
Corporate (£15.220m) Uncertainty / Sensitivity Adjustment
(£15.220m)
Total (£75.255m)

Page 6

2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of (£54.518m) from the revised budget,
including: 
38.672 32.249 0.492 50.239 2.500 124.152
25.201 8.948 2.002 43.502 (10.019) 69.634
(13.471) (23.301) 1.510 (6.737) (12.519) (54.518)
Approved Programme
Movement
Programme @ P4
Category Amount Comments
Borrowing (£54.929m) Rephased aligned to projected expenditure
Use of Reserves (£3.728m) Rephased draw on reserves
CFCR (£1.710m) Rephased contribution from Revenue
Capital Grants £2.984m Rephased and additional specific grants
Other Grants £2.859m Rephased and additional contributions
Capital Receipts £0.006m Rephased capital receipts
Total (£54.518m)

Page 7

2.8 Projected Capital Expenditure to 31 March 2023 
The projections are summarised by service in the following table:   
2.9 Information on the progress of all projects can be found in Appendix 1. 
2.10 Although not formally reflected in the financial performance reports at this time due to
ongoing uncertainty, areas of cost risk have been identified as a result of cost volatility
arising from the ongoing inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials.
Specific projects where cost risks have been identified, or are anticipated, include
Upper Garnock Flood Prevention Scheme, Millport Coastal Flood Prevention Scheme,
Moorpark Primary, Montgomerie Park Primary, Largs Sea Wall, Ardrossan North
Shore and Ardrossan Campus. While some mitigation has been built into the Capital
Investment Programme in the form of enhanced flexibility budgets, totalling £12.1m
over the next few years, cost pressures may exceed this provision, requiring
additional revenue investment to offset any additional borrowing requirements. These
risks will be quantified as individual projects are completed and tendering exercises
are finalised, with the impact on the costs of the programme being monitored and
reported to Cabinet as appropriate. Any funding in excess of the current level of
financial flexibility, which is required to deliver the current capital programme, will be a
matter for Council to consider within the context of overall affordability.  
Approved
Budget
2022/23
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Projected
Expenditure
/ Income to
31 March
2023
Projected
Variance
Over /
(Under)
£m £m £m £m £m £m
Expenditure
Communities 38.672 3.878 (17.349) 25.201 25.201 -
Chief Executive 32.249 3.174 (26.475) 8.948 8.948 -
Health and Social Care Partnership 0.492 1.510 - 2.002 2.002 -
Place 50.239 9.474 (16.211) 43.502 43.502 -
Other including Flexibility 2.500 2.701 (15.220) (10.019) (10.019) -
Total Expenditure 124.152 20.737 (75.255) 69.634 69.634 -
Income
General Capital Grant (13.150) (0.585) - (13.735) (13.735) -
Specific Capital Grant (8.890) (5.143) 2.744 (11.289) (11.289) -
Use of Reserve Funds (4.719) (0.230) 3.958 (0.991) (0.991) -
Capital Funded from Current Revenue (0.600) 0.465 1.245 1.110 1.110 -
Capital Receipts (0.352) (0.006) - (0.358) (0.358) -
Other Grants & Contributions (1.926) (2.859) - (4.785) (4.785) -
Prudential Borrowing (94.515) (12.379) 67.308 (39.586) (39.586) -
Total Income (124.152) (20.737) 75.255 (69.634) (69.634) -

Page 8

Housing Revenue Account 
2.11 The following table outlines the movements in the 2022/23 HRA Capital budget: 
2.12  (a) Alterations to the Phasing of Projects 
£18.317m of planned expenditure has been reprofiled from 2021/22 to 2022/23, 
reflecting projects not completed within the year which have been incorporated within
the 2022/23 capital programme. These were previously reported within the 2021/22
Capital Programme performance reports. 
2022/23
£m
Budget as at 16 February 2022 114.507     
a) Alterations to phasing of projects:-
2021/22 to 2022/23 18.317       
2022/23 to 2023/24 (60.053)           
2023/24 to 2022/23 2.374         
Budget as at 31July 2022 75.145       
Category Amount Project
New Builds £7.657m New Build Contingency
£0.592m St Michael's Wynd
£0.170m Afton Court
£0.150m Brathwic Terrace
£0.135m Towerlands
£0.133m Springvale Saltcoats
£0.101m Dalrymple Place
£8.938m
Improvements £1.918m Central Heating
£1.840m Kitchen Programme
£1.044m Electrical Rewiring
£0.444m Insulated Re-rendering
£0.003m Other Minor Adjustments
£5.249m

Page 9

A review of the timescale for delivery of capital projects has identified a requirement to
re-profile (£60.053m) of works for delivery in 2023/24 and beyond, including: 
Refurbishments £1.057m Roofing & Rendering
£0.335m Kings Arms Project
£0.254m Friars Lawn
£1.646m
Other £1.005m Detection Equipment
£0.903m Estate Based Regeneration
£0.412m Professional Mgmt Charge
£0.126m Energy Efficiency Standard
£0.038m Other Minor Adjustments
£2.484m
Total £18.317m
Category Amount Project
New Builds (£9.400m) New Montgomerie Park
(£7.997m) Ayrshire Central
(£6.150m) Garnock Academy Site
(£4.925m) James Reid Site
(£4.065m) Fullarton Street
(£1.975m) Bourtreehill Village
(£1.450m) Stanecastle Site
(£1.114m) St Colms
(£0.850m) Corsehillhead
(£0.800m) James McFarlane Site
(£0.748m) Flatt Road
(£0.720m) Garnock Academy Site
(£0.640m) Flatt Road
(£0.460m) Harbourside
(£0.355m) Regeneration Project
(£0.308m) Largs Police Station
(£0.194m) Acquisitions
(£0.170m) Newhouse Drive
(£0.155m) Laburnam Avenue
(£0.009m) Other minor adjustments
(£42.485m)
Improvements (£5.745m) Sheltered Housing Units
(£2.886m) Saltcoats MSF
(£2.191m) Door Replacement Programme
(£10.822m)

Page 10

This has been partly offset by the acceleration of £2.374m of projects for delivery during
2022/23, including: 
2.13 These adjustments have resulted in a revised 2022/23 budget at 31 July 2022 of
£75.145m. 
2.14 The impact on budgeted funding is a reduction of £39.362m in the drawdown of
Capital Grants and reduced Prudential Borrowing aligned to the revised programme. 
Refurbishments (£3.780m) High Flat Demolitions
(£1.117m) Demolition of High Flats
(£4.897m)
Other (£0.740m) Estate Based Regeneration
(£0.657m) Detection Equipment
(£0.426m) Nelson Street Regeneration
(£0.026m) Solar Panels
(£1.849m)
Total (£60.053m)
Category Amount Project
New Builds £0.104m Minor Projects
£0.104m
Improvements £1.149m Bathroom Programme
£1.110m Kitchen Programme
£0.011m Window Replacement
£2.270m
Total £2.374m
Category Amount Comments
Capital Grants £28.362m Reduction aligned to projected expenditure
Borrowing £11.000m Reduction aligned to projected expenditure
Total £39.362m

Page 11

2.15  Projected Capital Expenditure to 31 March 2023 
The projections are summarised in the following table:   
2.16 A variance of (£7.036m) is projected within the HRA capital programme for 2022/23
arising from revisions to a number of projects, including: 
These have been partly offset by a projected overspend of £0.028m in relation to: 
2.17 Increased costs arising from tender inflation and supply chain issues have been
identified in relation to some projects, including the Door Replacement Programme
and Sheltered Housing Unit Improvements. Further cost pressures resulting from
inflationary and supply chain issues continue to be monitored and a review of the
potential impact on the Business Plan and Capital Programme will be undertaken to
address any identified issues. Further information on the progress of all projects can
be found in Appendix 2. 
Approved
Budget
2022/23
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2022/23
Projected
Expenditure /
Income to 31
March 2023
Projected
Variance
Over /
(Under)
Service £m £m £m £m £m £m
Expenditure
Housing Revenue Account 114.507 (29.379) (9.983) 75.145 68.109 (7.036)
Total Expenditure 114.507 (29.379) (9.983) 75.145 68.109 (7.036)
Income
CFCR (12.209) - - (12.209) (12.209) -
Capital Grants (15.326) 7.037 3.963 (4.326) (4.326) -
Affordable Housing Contribution (1.596) - - (1.596) (1.596) -
Prudential Borrowing (85.376) 22.342 6.020 (57.014) (49.978) 7.036
Total Income (114.507) 29.379 9.983 (75.145) (68.109) 7.036
Project Variance Comments
Kitchen Programme (£2.900m) Aligned to revised Business Plan
Central Heating (£1.880m) Aligned to revised Business Plan
Electrical Rewiring (£1.044m) Aligned to revised Business Plan
Roofing & Rendering (£0.794m) Aligned to revised Business Plan
Insulated Rerendering (£0.444m) Aligned to revised Business Plan
Kinnier Road (£0.002m) Completed October 2021
Total (£7.064m)
Project Variance Comments
Towerlands £0.020m Completed March 2022
Springvale New Build £0.008m Completed November 2021
Total £0.028m

Page 12

3. Proposals 
3.1 That Cabinet agrees to (a) note the revisions to budgets outlined in the report; and (b)
note (i) the General Services and HRA revised budgets at 31 July 2022; and (ii) the
forecast expenditure to 31 March 2023. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2019 to 2024 by maximising resources
and providing value for money to support financially sustainable delivery models. 
Community Wealth Building 
4.7 None.

Page 13

5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Investment Programme 2022/23 to 2030/31 - Council 2 March 2022
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget and
Rent Levels for 2022/23 – Council 16 February 2022

Page 14

TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Brought / Carry Forward
to 2023/24
Total Revised
Budget 2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 July 2022
Year to date
Variance 2022/23
Projected Expenditure
to 31st March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 15,735,489 13,969,479 15,735,489 0 2,225,827 0 2,225,827 0 459,817 459,817 2,225,827 0 0
Primary Schools 35,676,441 3,761,644 35,676,441 0 26,525,016 (6,002,238) 20,522,778 0 796,677 796,677 20,522,778 0 0
Secondary Schools 74,575,465 3,472,710 74,575,465 0 12,580,717 (11,280,664) 1,300,053 0 174,670 174,670 1,300,053 0 0
Special Education 25,443,178 24,680,029 25,443,178 0 903,203 0 903,203 0 140,054 140,054 903,203 0 0
Schools Other 298,000 106,108 298,000 0 191,892 0 191,892 0 0 0 191,892 0 0
Information & Culture 125,916 14,848 125,916 0 119,353 (66,064) 53,289 0 8,285 8,285 53,289 0 0
Completed Projects 87,824,335 87,799,954 87,824,335 0 3,679 0 3,679 0 (20,702) (20,702) 3,679 0 0
SUB TOTAL 239,678,825 133,804,772 239,678,825 0 42,549,687 (17,348,966) 25,200,721 0 1,558,801 1,558,801 25,200,721 0 0
Chief Executive
Council IT Strategy 9,757,832 2,177,080 9,757,832 0 3,204,704 0 3,204,704 0 665,352 665,352 3,204,704 0 0
Ayrshire Growth Deal 75,093,987 1,375,174 75,093,987 0 4,635,437 (1,111,437) 3,524,000 0 92,362 92,362 3,524,000 0 0
Other Growth & Investment 44,718,115 3,107,857 44,718,115 0 27,582,883 (25,363,443) 2,219,440 0 160,273 160,273 2,219,440 0 0
SUB TOTAL 129,569,934 6,660,110 129,569,934 0 35,423,024 (26,474,880) 8,948,144 0 917,987 917,987 8,948,144 0 0
Health & Social Care
Management & Support 2,050,595 786,438 2,050,595 0 640,839 0 640,839 0 42,682 42,682 640,839 0 0
Housing Non HRA 686,065 130,411 686,065 0 686,065 0 686,065 0 130,411 130,411 686,065 0 0
Adults 4,608,078 4,561,314 4,608,078 0 46,804 0 46,804 0 40 40 46,804 0 0
Young People 5,720,000 5,091,798 5,720,000 0 628,264 0 628,264 0 61 61 628,264 0 0
SUB TOTAL 13,064,739 10,569,961 13,064,739 0 2,001,972 0 2,001,972 0 173,194 173,194 2,001,972 0 0
Place
Roads 86,520,829 24,311,414 86,520,829 0 24,549,861 (1,809,982) 22,739,879 0 2,939,580 2,939,580 22,739,879 0 0
Streetscene 6,580,996 1,624,611 6,580,996 0 3,267,516 (1,243,822) 2,023,694 0 205,080 205,080 2,023,694 0 0
Transport 3,293,811 179,045 3,293,811 0 3,178,211 0 3,178,211 0 63,445 63,445 3,178,211 0 0
Waste Services 14,689,343 14,539,343 14,689,343 0 0 0 0 0 0 0 0 0 0
Renewable Energy 8,890,393 1,572,432 8,890,393 0 7,291,928 (6,224,560) 1,067,368 0 (26,032) (26,032) 1,067,368 0 0
Office Accommodation 2,580,809 339,096 2,580,809 0 2,580,809 (662,707) 1,918,102 0 339,096 339,096 1,918,102 0 0
Other Property 5,986,638 381,987 5,986,638 0 5,604,008 (3,716,083) 1,887,925 0 (643) (643) 1,887,925 0 0
Other Housing 350,000 0 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0
Regeneration 31,732,432 20,312,516 31,732,432 0 12,850,121 (2,553,254) 10,296,867 0 2,294,471 2,294,471 10,296,867 0 0
Completed Projects 8,994,855 8,878,539 8,994,855 0 40,595 0 40,595 0 (65,608) (65,608) 40,595 0 0
SUB TOTAL 169,620,106 72,138,983 169,620,106 0 59,713,049 (16,210,408) 43,502,641 0 5,749,389 5,749,389 43,502,641 0 0
Other
Other 12,155,305 0 12,155,305 0 5,201,180 5,201,180 0 0 0 5,201,180 0 0
SUB TOTAL 12,155,305 0 12,155,305 0 5,201,180 0 5,201,180 0 0 0 5,201,180 0 0
Uncertainty / Sensitivity Adjustment* (15,220,421) (15,220,421) (15,220,421)
Total Project Expenditure 564,088,909 223,173,826 564,088,909 0 144,888,912 (75,254,675) 69,634,237 0 8,399,371 8,399,371 69,634,237 0 0
Total Project Income (144,888,912) 75,254,675 (69,634,237) (13,372,424) (13,372,424) 0 (69,634,237) 0 0
Total Net Expenditure 0 0 0 (13,372,424) (4,973,053) 8,399,371 0 0 0
* Sensitivity adjustment of 10% or 25% based on source and reliability of expenditure projections
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2022/23
North Ayrshire Council Capital Statement 2022/23
Year Ended 31st March 2023
Period 4
The following classifications have been used to highlight delivery
performance against original timescales set

Page 15

Revised Budget
22/23 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 94,515,334 9,882,875 1,655,477 106,053,686 840,348 106,894,034 54,805,725 (52,088,309)
SUB TOTAL 94,515,334 9,882,875 1,655,477 106,053,686 840,348 0 106,894,034 0 54,805,725 (52,088,309)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Early Learning & Childcare 464,253 517,775 982,028 0 982,028 978,659 982,028 0
Cycling / Walking /Safer Streets 1,111,122 38,831 (300,566) 849,387 321,632 1,171,019 (328,613) 597,065 (573,954)
Vacant & Derelict Land Funding 3,710,375 123,927 848,022 4,682,324 0 4,682,324 3,262,324 2,512,125 (2,170,199)
UK Government Grant - AGD 2,040,120 2,040,120 0 2,040,120 0 2,040,120 0
Lochshore - Garnock Community Visitor Hub 0 50,000 50,000 0 50,000 50,000 50,000 0
Town Centre Regeneration 0 166,774 250,000 416,774 0 416,774 416,773 416,774 0
Stevenston Beach Hub 0 34,525 50,000 84,525 0 84,525 84,525 84,525 0
Annickbank - Vacant & Derelict Land Investment Programme 400,000 400,000 0 400,000 0
Millport Town Hall Regeneration 0 382,028 1,187,810 1,569,838 0 1,569,838 1,569,838 1,569,838 0
Place Based Investment Programme 706,000 147,903 346,040 1,199,943 0 1,199,943 1,199,944 1,199,943 0
Island Infrastructure Fund 0 259,000 259,000 0 259,000 259,000 259,000 0
Bridges Infrastructure 567,000 (567,000) 0 0 0 0 0 0
B714 Improvements 857,907 197,160 1,055,067 0 1,055,067 1,212,000 1,055,067 0
CO2 Monitors in Schools 0 122,000 122,000 0 122,000 122,000 122,000 0
Capital Grants
Flooding 2,778,000 2,778,000 0 2,778,000 0 2,778,000 0
Renewal of Play Parks 0 117,000 117,000 0 117,000 0 117,000 0
General Capital Grant 9,805,000 845,000 10,650,000 190,000 10,840,000 4,666,000 10,840,000
SUB TOTAL 22,039,777 1,780,923 3,035,306 26,856,006 911,632 0 27,767,638 13,492,449 25,023,485 (2,744,153)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 4,718,975 140,833 88,942 4,948,750 0 0 4,948,750 0 992,190 (3,956,560)
Change & Service Redesign Fund 0 42,682 0 42,682 (42,682) 0 0 0 0 0
CFCR 600,000 0 0 600,000 (464,570) 0 135,430 42,682 135,430 0
Grants & Contributions 1,925,682 866,594 1,539,395 4,331,671 452,920 0 4,784,591 (204,726) 3,539,359 (1,245,232)
Capital Receipts 352,500 0 0 352,500 5,969 0 358,469 42,019 358,469 0
SUB TOTAL 7,597,157 1,050,109 1,628,337 10,275,603 (48,363) 0 10,227,240 (120,025) 5,025,448 (5,201,792)
TOTAL CAPITAL PROGRAMME FUNDING 124,152,268 12,713,907 6,319,120 143,185,295 1,703,617 0 144,888,912 13,372,424 84,854,658 (60,034,254)
22/23 Budget at
Capital Refresh
Mar 2022
Capital Programme Funding 2022/23
Projected Income
to 31st March
2023
Approved budget
at Period 1 used
as revised starting
point 2022/23
Actual Income to 31
July 2022Funding Description
Carry Forward
from 2021/22
Changes after
Capital Refresh Mar
2022
Total Changes in
Year
Changes at
Capital Refresh
Mar 2023

Page 16

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 July 2022
Year to date Variance
2022/23
Projected
Expenditure to 31
March 2023
Actual Over/ (Under)
Spend for 2022/23   
True Over/(Under)
Spend            
Brought / Carry
Forward to 2023/24 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
ST BRIDGETS EARLY YEARS 779,400 763,298 779,400 0 2,301 0 (13,801) (13,801) 2,301 0 0 Complete Complete Complete On Target On Target
KILMORY EARLY YEARS 55,978 27,992 55,978 0 27,986 0 0 0 27,986 0 0 15-Aug-22 15-Aug-22 Pre Tender On Target On Target
ST PETERS EARLY YEARS 1,218,977 1,203,224 1,218,977 0 0 0 (15,753) (15,753) 0 0 0 Complete Complete Complete On Target On Target
MAYFIELD PS EARLY YEARS 222,479 210,030 222,479 0 12,449 0 0 0 12,449 0 0 Complete Complete Complete On Target On Target
BEITH PS EARLY YEARS 338,885 327,554 338,885 0 4,104 0 (7,227) (7,227) 4,104 0 0 Complete Complete Complete On Target On Target
SKELMORLIE PS EARLY YEARS 374,372 346,604 374,372 0 19,424 0 (8,344) (8,344) 19,424 0 0 Complete Complete Complete On Target On Target
WEST KILBRIDE EARLY EARLY YEARS 227,676 220,254 227,676 0 6,400 0 (1,022) (1,022) 6,400 0 0 Complete Complete Complete On Target On Target
GATESIDE EARLY YEARS 405,105 405,105 405,105 0 240 0 240 240 240 0 0 Complete Complete Complete On Target On Target
FAIRLIE EARLY YEARS 204,118 203,996 204,118 0 468 0 346 346 468 0 0 Complete Complete Complete On Target On Target
DREGHORN EARLY YEARS 93,267 82,843 93,267 0 10,824 0 400 400 10,824 0 0 Complete Complete Complete On Target On Target
MOORPARK EARLY YEARS 1,000 182 1,000 0 818 0 0 0 818 0 0 14-Aug-20 15-Aug-22 Development On Target On Target
PIRNMILL EARLY YEARS 80,000 3,440 80,000 0 77,510 0 950 950 77,510 0 0 31-Oct-21 15-Aug-22 Pre Tender On Target On Target
SHISKINE EARLY YEARS 110,000 57,108 110,000 0 53,842 0 950 950 53,842 0 0 31-Oct-21 15-Aug-22 Pre Tender On Target On Target
CORRIE EARLY YEARS 38,721 2,510 38,721 0 37,161 0 950 950 37,161 0 0 31-Oct-21 15-Aug-22 Pre Tender On Target On Target
LAMLASH EARLY YEARS 15,000 682 15,000 0 14,318 0 0 0 14,318 0 0 31-Oct-21 15-Aug-22 Development On Target On Target
BRODICK EARLY YEARS 302,590 16,584 302,590 0 294,151 0 8,145 8,145 294,151 0 0 31-Oct-21 15-Aug-22 Development On Target On Target
MARRESS HOUSE 3,375,394 2,498,955 3,375,394 0 1,448,052 0 571,613 571,613 1,448,052 0 0 22-Jul-22 30-Nov-22 Construction On Target Significantly off target Poor performance by the contractor and continuing
issues with the condition of the existing building
Completed Nursery Education
LAWTHORN EARLY YEARS 201,037 201,037 201,037 0 77 0 77 77 77 0 0 Complete Complete Complete Complete Complete
Other Nursery Education
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,201,415 2,908,007 3,201,415 0 215,702 0 (77,706) (77,706) 215,702 0 0 Complete Complete Complete On Target On Target
Total Nursery Education 15,735,489 13,969,479 15,735,489 0 2,225,827 0 459,817 459,817 2,225,827 0 0 0
Primary Schools
MOORPARK PRIMARY 10,849,442 3,301,207 10,849,442 0 8,035,005 0 486,770 486,770 8,035,005 0 0 30-Sep-22 30-Sep-23 Construction On Target Significantly off target Delays are being experienced by the contractor and
wider supply chain.
MONTGOMERIE PARK SCHOOL 14,470,000 451,368 14,470,000 0 9,261,273 0 301,100 301,100 9,261,273 0 0 30-Apr-24 24-May-24 Tender Significantly off target On Target Revised project costs £2.550m above initial budget
as reported to Cabinet on 27/4/22
UNIVERSAL FREE SCHOOL MEALS EXPANSION 2,467,000 0 2,467,000 0 2,392,750 0 0 0 2,392,750 0 0 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM ARDEER PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 0 (22,500) (22,500) 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM BEITH PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 0 (22,500) (22,500) 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM BRODICK PRIMARY SCHOOL 225,000 2,072 225,000 0 191,250 0 2,072 2,072 191,250 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
UFSM CALEDONIA PRIMARY SCHOOL 60,000 0 60,000 0 60,000 0 0 0 60,000 0 0 31-Aug-23 31-Aug-23 Tender On Target On Target
UFSM CASTLEPARK PRIMARY SCHOOL 105,000 0 105,000 0 105,000 0 0 0 0 (105,000) (105,000) 31-Aug-23 31-Aug-23 Tender On Target On Target
UFSM CORRIE PRIMARY SCHOOL 52,500 0 52,500 0 52,500 0 0 0 52,500 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
UFSM CORSEHILL PRIMARY SCHOOL 60,000 0 60,000 0 60,000 0 0 0 0 (60,000) (60,000) 31-Aug-23 31-Aug-23 Tender On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 90,000 0 90,000 0 90,000 0 0 0 0 (90,000) (90,000) 31-Aug-23 31-Aug-23 Tender On Target On Target
UFSM GLEBE PRIMARY SCHOOL 2,125,000 0 2,125,000 0 1,806,250 0 0 0 0 (1,806,250) (1,806,250) 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 0 (22,500) (22,500) 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM HAYOCKS PRIMARY SCHOOL 82,500 0 82,500 0 82,500 0 0 0 0 (82,500) (82,500) 31-Aug-23 31-Aug-23 Development On Target On Target
UFSM KILMORY PRIMARY SCHOOL 30,000 0 30,000 0 30,000 0 0 0 30,000 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
UFSM LARGS PRIMARY SCHOOL 300,000 0 300,000 0 255,000 0 0 0 255,000 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,125,000 0 2,125,000 0 1,806,250 0 0 0 0 (1,806,250) (1,806,250) 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 0 (22,500) (22,500) 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM SHISKINE PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,500,000 6,997 2,500,000 0 2,162,238 0 6,735 6,735 200,000 (1,962,238) (1,962,238) 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM WHITING BAY PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Aug-22 31-Aug-22 Tender On Target On Target
Total Primary Education 35,676,441 3,761,644 35,676,441 0 26,525,016 0 796,677 796,677 20,522,778 (6,002,238) 0 (6,002,238) 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,372,863 2,805,435 0 451,033 0 18,461 18,461 127,953 (323,080) (323,080) 31-Aug-21 31-Mar-24 Construction On Target On Target
AYRSHIRE COLLEGE PARTNERSHIP DEVELOPMENT 200,000 0 200,000 0 200,000 0 0 0 200,000 0 0 31-Mar-22 31-Jan-23 Future Years On Target On Target
ARDROSSAN NEW BUILD 71,570,030 1,099,847 71,570,030 0 11,929,684 0 156,210 156,210 972,100 (10,957,584) (10,957,584) 31-Jan-25 31-Jan-25 In Development Slightly off target  Slightly off target  Delayed expenditure linked to anticipated delays and
inflationary pressures linked to the advance works
tender process.
Total Secondary Education 74,575,465 3,472,710 74,575,465 0 12,580,717 0 174,670 174,670 1,300,053 (11,280,664) 0 (11,280,664)
Special Education
LOCKHART CAMPUS 25,443,178 24,680,029 25,443,178 0 903,203 0 140,054 140,054 903,203 0 0 Complete Complete Snagging On Target On Target
Total Special Education 25,443,178 24,680,029 25,443,178 0 903,203 0 140,054 140,054 903,203 0 0 0
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 106,108 298,000 0 191,892 0 0 0 191,892 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Schools Other 298,000 106,108 298,000 0 191,892 0 0 0 191,892 0 0 0
CAPITAL MONITORING 2022/23
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS

Page 17

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 July 2022
Year to date Variance
2022/23
Projected
Expenditure to 31
March 2023
Actual Over/ (Under)
Spend for 2022/23   
True Over/(Under)
Spend            
Brought / Carry
Forward to 2023/24 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
CAPITAL MONITORING 2022/23
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS
Information & Culture
CASTLES & HISTORIC MONUMENTS 50,740 8,285 50,740 0 50,740 0 8,285 8,285 50,740 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 75,176 6,563 75,176 0 68,613 0 0 0 2,549 (66,064) (66,064) On Hold On Hold Planning On Hold On Hold
Total Information & Cultural 125,916 14,848 125,916 0 119,353 0 8,285 8,285 53,289 (66,064) 0 (66,064)
Completed Projects
GARNOCK CAMPUS 40,307,259 40,283,664 40,307,259 0 2,893 0 (20,702) (20,702) 2,893 0 0 Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,112,120 3,111,334 3,112,120 0 786 0 0 0 786 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 87,824,335 87,799,954 87,824,335 0 3,679 0 (20,702) (20,702) 3,679 0 0 0
Total Communities 239,678,825 133,804,772 239,678,825 0 42,549,687 0 1,558,801 1,558,801 25,200,721 (17,348,966) 0 (17,348,966)

Page 18

CHIEF EXECUTIVE
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
July 2022
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023 
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to
2023/24
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Council IT Strategy
SCHOOLS ICT INVESTMENT * 1,215,537 434,701 1,215,537 0 1,215,537 0 434,701 434,701 1,215,537 0 0 31-Mar-23 31-Mar-23 On-going On Target On Target
ICT INVESTMENT FUND 3,822,986 778,898 3,822,986 0 801,796 0 149,108 149,108 801,796 0 0 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 857,100 345,833 857,100 0 94,297 0 83,030 83,030 94,297 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
LAN/WiFi 2,673,000 383,604 2,673,000 0 801,816 0 12,420 12,420 801,816 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
TELEPHONY 1,146,693 192,140 1,146,693 0 286,988 0 (17,564) (17,564) 286,988 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
OUR FUTURE WORKING ENVIRONMENT 42,516 41,903 42,516 0 4,270 0 3,657 3,657 4,270 0 0 31-Mar-23 31-Mar-23 Procurement On Target On Target
Total IT Strategy 9,757,832 2,177,080 9,757,832 0 3,204,704 0 665,352 665,352 3,204,704 0 0 0
Ayrshire Growth Deal
AGD - I3 DIGILAB PHASE 1 1,000,000 5,449 1,000,000 0 494,551 0 0 0 500,000 5,449 5,449 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 DIGILAB PHASE 2 5,000,000 179,970 5,000,000 0 423,580 0 0 0 200,000 (223,580) (223,580) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE 15,000,000 244,356 15,000,000 0 1,720,276 0 5,674 5,674 1,050,000 (670,276) (670,276) 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY
& CIRCULAR ECONOMY
18,040,001 198,695 18,040,001 0 331,377 0 12,575 12,575 200,000 (131,377) (131,377) 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target
AGD - IRVINE HARBOURSIDE ARDEER (THE GREAT
HARBOUR)
13,999,999 344,875 13,999,999 0 904,897 0 48,557 48,557 900,000 (4,897) (4,897) 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target
AGD - ARDROSSAN (IMSE) 10,500,000 102,260 10,500,000 0 194,981 0 0 0 174,000 (20,981) (20,981) 31-Mar-27 31-Mar-27 Design On Target On Target
AGD - MARINE TOURISM 11,440,716 236,298 11,440,716 0 515,775 0 25,557 25,557 450,000 (65,775) (65,775) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - MARINE TOURISM ARRAN 46,226 28,711 46,226 0 17,515 0 0 0 17,515 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - MARINE TOURISM CUMBRAE 67,046 34,561 67,046 0 32,485 0 0 0 32,485 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 75,093,987 1,375,174 75,093,987 0 4,635,437 0 92,362 92,362 3,524,000 (1,111,437) 0 (1,111,437)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,077,112 389,956 4,077,112 0 142,748 0 247 247 92,748 (50,000) (50,000) 31-Dec-24 31-Dec-24 Design On Target On Target
IRVINE ENTERPRISE AREA * 10,746,072 0 10,746,072 0 103,079 0 0 0 103,079 0 0 Ongoing Ongoing Multiple Projects On Target On Target
LOW CARBON HUB 1,974,973 86,801 1,974,973 0 1,888,172 0 0 0 650,683 (1,237,489) (1,237,489) 30-Apr-24 30-Apr-24 Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 26,765,478 2,452,524 26,765,478 0 24,467,954 0 155,001 155,001 392,000 (24,075,954) (24,075,954) 30-Apr-24 30-Apr-24 In development Slightly off target  Slightly off target  Working group reviewing options for procurement and
delivery of this project, following the recent
unsuccessful tender process.
VDLF - HARBOUR MASTERS OFFICE 157,500 20,722 157,500 0 136,778 0 0 0 136,778 0 0 22-Aug-22 22-Aug-22 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 996,981 157,854 996,981 0 844,152 0 5,025 5,025 844,152 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
Other Growth & Investment 44,718,115 3,107,857 44,718,115 0 27,582,883 0 160,273 160,273 2,219,440 (25,363,443) 0 (25,363,443)
Total Chief Executive 129,569,934 6,660,110 129,569,934 0 35,423,024 0 917,987 917,987 8,948,144 (26,474,880) 0 (26,474,880)   
CAPITAL MONITORING 2022/23
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2022/23 BUDGETS

Page 19

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date Budget
2022/23
Actual Expenditure to
31 July 2022
Year to Date Variance
2022/23
Projected Expenditure
to 31 March 2023
Actual Over/
(Under) Spend for
2022/23
True Over/(Under)
Spend          
Brought / Carry
Forward to 2023/24   Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Management & Support
HOME CARE SYSTEM 433,917 433,917 433,917 0 42,682 0 42,682 42,682 42,682 0 0 31-Mar-23 31-Mar-23 Implementation On Target On Target
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 0 996,000 0 330,000 0 0 0 330,000 0 0 Future Years
CAREFIRST REPLACEMENT 536,058 267,901 536,058 0 268,157 0 0 0 268,157 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Management & Support 2,050,595 786,438 2,050,595 0 640,839 0 42,682 42,682 640,839 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 686,065 130,411 686,065 0 686,065 0 130,411 130,411 686,065 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
Total Housing Non HRA 686,065 130,411 686,065 0 686,065 0 130,411 130,411 686,065 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,561,314 4,608,078 0 46,804 0 40 40 46,804 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,561,314 4,608,078 0 46,804 0 40 40 46,804 0 0 0
Young People
RESIDENTIAL & RESPITE UNIT 5,720,000 5,091,798 5,720,000 0 628,264 0 61 61 628,264 0 0 Complete Complete Snagging On Target On Target
Total Young People 5,720,000 5,091,798 5,720,000 0 628,264 0 61 61 628,264 0 0 0
Total Health & Social Care 13,064,739 10,569,961 13,064,739 0 2,001,972 0 173,194 173,194 2,001,972 0 0 0
CAPITAL MONITORING 2022/23
2022/23 BUDGETSTOTAL PROJECT COMPLETION DATES
CommentsProject Description
DELIVERY STATUS

Page 20

Place
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
July 2022
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
PHYSICAL ENVIRONMENT
Roads
ROADS IMPROVE/RECONSTRUCTION * 4,914,795 4,914,795 4,914,795 0 4,914,795 0 441,524 441,524 4,914,795 0 0 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
TRAFFIC CALMING 175,000 0 175,000 0 175,000 0 0 0 175,000 0 0 31-Mar-23 31-Mar-23 In Development On Target On Target
VEHICLE RESTRAINT SYSTEM UPGRADE 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-23 31-Mar-23 In Development On Target On Target
LIGHTING * 1,587,827 408,656 1,587,827 0 1,587,827 0 408,656 408,656 1,587,827 0 0 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 695,000 158,230 695,000 0 492,190 0 158,230 158,230 492,190 0 0 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target
UPPER GARNOCK FPS 18,503,800 16,717,569 18,503,800 0 3,454,934 0 1,668,703 1,668,703 3,454,934 0 0 30-Jun-22 30-Sep-22 Construction Slightly off target  On Target increased tender cost risks identified
MILLPORT COASTAL FPS 27,053,000 1,280,326 27,053,000 0 9,278,436 0 15,529 15,529 9,278,436 0 0 31-Aug-24 31-Aug-24 Tender Slightly off target  On Target increased tender cost risks identified
MILLBURN FPS 1,757,000 187,018 1,757,000 0 1,335,982 0 0 0 60,000 (1,275,982) (1,275,982) 31-Mar-23 30-Nov-23 Design On Target Significantly off target due to delays in the design process
MILLPORT PIER 500,000 150,080 500,000 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 1,544,261 62,082 1,544,261 0 1,544,261 0 62,082 62,082 1,010,261 (534,000) (534,000) 31-Mar-23 31-Mar-23 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 3,039,000 239,417 3,039,000 0 160,840 0 128,789 128,789 160,840 0 0 31-Oct-23 31-Oct-23 Design Slightly off target  On Target increased tender cost risks identified
B714 UPGRADE 26,063,443 52,632 26,063,443 0 1,055,067 0 52,632 52,632 1,055,067 0 0 31-Mar-25 31-Mar-25 Outline Design On Target On Target
LARGS CAR PARK INFRASTRUCTURE 80,000 54,467 80,000 0 25,533 0 0 0 25,533 0 0 30-Jun-22 30-Jun-22 Planning On Target On Target
GALLOWGATE TOILETS 250,000 4,130 250,000 0 247,316 0 1,446 1,446 247,316 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PARKING CHARGES & DPE 257,705 82,015 257,705 0 177,680 0 1,990 1,990 177,680 0 0 31-Mar-23 31-Mar-23 In Development On Target On Target
Total Roads 86,520,829 24,311,414 86,520,829 0 24,549,861 0 2,939,580 2,939,580 22,739,879 (1,809,982) 0 (1,809,982)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 726,479 0 726,479 0 (16,879) 0 0 0 0 16,879 16,879 Holding Code Holding Code Holding Code Holding Code Holding Code
LAMLASH CEMETERY EXTENSION 706,165 684,525 706,165 0 21,640 0 0 0 21,640 0 0 Complete Complete Complete Complete Complete
ARDROSSAN CEMETERY PLOTS AND WALLS 217,922 150,703 217,922 0 67,219 0 0 0 67,219 0 0 Complete Complete Complete Complete Complete
KILBIRNIE CEMETERY 623,833 34,602 623,833 0 198,450 0 9,220 9,220 9,220 (189,230) (189,230) 31-Mar-25 31-Mar-25 Feasibility Works On Hold On Hold
KILWINNING CEMETERY NEW 1,240,642 277,809 1,240,642 0 1,152,196 0 189,364 189,364 718,868 (433,328) (433,328) 01-Sep-22 31-May-23 Construction On Target Significantly off target Contractor appointed, commencing on site 27/6/22
KNADGERHILL CEMETERY EXTENSION 443,581 390,453 443,581 0 49,340 0 (3,787) (3,787) 49,340 0 0 01-Oct-22 01-Oct-22 Construction On Target On Target
WEST KILBRIDE CEMETERY 349,622 31,791 349,622 0 318,408 0 578 578 310,902 (7,506) (7,506) 25-Nov-22 25-Nov-22 Construction On Target On Target
STEVENSTON CEMETERY 545,429 44,084 545,429 0 501,601 0 256 256 467,991 (33,610) (33,610) 23-Dec-22 23-Dec-22 Construction On Target On Target
ARDROSSAN CEMETERY NEW 900,603 603 900,603 0 161,727 0 0 0 0 (161,727) (161,727) Future years Future years Future years On Hold On Hold
BRODICK CEMETERY 12,000 7,021 12,000 0 12,000 0 7,021 7,021 7,021 (4,979) (4,979) Future years Future years Planning On Hold On Hold
KILBIRNIE CEMETERY WALL 188,370 562 188,370 0 184,367 0 562 562 90,000 (94,367) (94,367) 31-Mar-23 30-Apr-23 Technical Design On Target On Target
BEITH CEMETERY-WALL REPAIRS 87,542 589 87,542 0 85,093 0 0 0 40,000 (45,093) (45,093) 31-Mar-23 30-Apr-23 Technical Design On Target On Target
ABBEY TOWER CEMETERY WALL 95,550 568 95,550 0 93,520 0 568 568 3,520 (90,000) (90,000) 31-Mar-24 31-Mar-24 Technical Design On Target On Target
HAWKHILL CEMETERY-WALL REPAIRS 108,732 560 108,732 0 106,421 0 560 560 560 (105,861) (105,861) 31-Mar-24 31-Mar-24 Technical Design On Target On Target
WEST KILBRIDE CEMETERY WALL 99,528 0 99,528 0 97,413 0 0 0 2,413 (95,000) (95,000) 31-Mar-24 31-Mar-24 Feasibility Works On Hold On Hold
PARK ENABLING WORKS 0 740 0 0 0 0 740 740 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
RENEWAL OF PLAY PARKS 235,000 0 235,000 0 235,000 0 0 0 235,000 0 0 31-Mar-23 31-Mar-23 Construction On Target On Target
Total Streetscene 6,580,996 1,624,611 6,580,996 0 3,267,516 0 205,080 205,080 2,023,694 (1,243,822) 0 (1,243,822)
Transport
VEHICLES * 1,828,533 10,431 1,828,533 0 1,828,533 0 10,431 10,431 1,828,533 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target 
WORKPLACE CHARGERS 215,278 157,614 215,278 0 99,678 0 42,014 42,014 99,678 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target
FLEET DECARBONISATION 1,250,000 11,000 1,250,000 0 1,250,000 0 11,000 11,000 1,250,000 0 0 31-Mar-23 31-Mar-23 Ongoing On Target On Target
Total Transport 3,293,811 179,045 3,293,811 0 3,178,211 0 63,445 63,445 3,178,211 0 0 0
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 41,795 120,000 0 78,205 0 0 0 78,205 0 0 31-Jul-22 31-Jul-22 Future years On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 6,768,000 43,440 6,768,000 0 6,724,560 0 0 0 500,000 (6,224,560) (6,224,560) 31-Dec-23 31-Dec-23 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 0 140 0 0 0 0 140 140 0 0 0 31-Dec-23 31-Dec-23 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 890,890 1,000,000 0 63,589 0 (45,521) (45,521) 63,589 0 0 31-Mar-23 31-Mar-23 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 356,000 0 356,000 0 356,000 0 0 0 356,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target 
ELECTRIC VEHICLES INFRASTRUCTURE 646,392 596,167 646,392 0 69,574 0 19,349 19,349 69,574 0 0 31-Mar-23 31-Mar-23 Various On Target On Target 
Total Renewable Energy 8,890,393 1,572,432 8,890,393 0 7,291,928 0 (26,032) (26,032) 1,067,368 (6,224,560) 0 (6,224,560)
Project Description
TOTAL PROJECT
CAPITAL MONITORING 2022/23
Comments
COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS

Page 21

Place
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
July 2022
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
Project Description
TOTAL PROJECT
CAPITAL MONITORING 2022/23
Comments
COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * 387,449 0 387,449 0 387,449 0 0 0 387,449 0 0 0 31-Mar-23 31-Mar-23 Mulitple projects On Target On Target 
PLI CENTRAL AVE STREETSCENE DEPOT* 93,203 59,914 93,203 0 93,203 0 59,914 59,914 93,203 0 0 0 31-Dec-22 31-Dec-22 Construction On Target On Target
PLI BEITH CEMETERY 429 429 429 0 429 0 429 429 429 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE COMMUNITY CENTRE 100,000 73,895 100,000 0 100,000 0 73,895 73,895 100,000 0 0 0 24-Jun-22 24-Jun-22 Planning On Target On Target
PLI WEST BYREHILL DEPOT 167,500 0 167,500 0 167,500 0 0 0 167,500 0 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI GOLDCRAIGS DEPOT 134,000 575 134,000 0 134,000 0 575 575 134,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI ANNICK PRIMARY SCHOOL 0 (6,253) 0 0 0 0 (6,253) (6,253) 0 0 0 Complete Complete Complete Complete Complete
PLI ARDEER PRIMARY SCHOOL 2,952 2,364 2,952 0 2,952 0 2,364 2,364 2,952 0 0 0 Complete Complete Complete Complete Complete
PLI BLACKLANDS PRIMARY SCHOOL 210,000 0 210,000 0 210,000 0 0 0 210,000 0 0 31-Aug-22 31-Aug-22 Construction On Target On Target
PLI CALEDONIA PRIMARY SCHOOL 15,000 0 15,000 0 15,000 0 0 0 15,000 0 0 30-Nov-22 30-Nov-22 Planning On Target On Target
PLI DALRY PRIMARY SCHOOL 75,000 5,907 75,000 0 75,000 0 5,907 5,907 5,907 (69,093) (69,093) 18-Aug-23 18-Aug-23 Planning On Target On Target
PLI FAIRLIE PRIMARY SCHOOL 3,691 0 3,691 0 3,691 0 0 0 3,691 0 0 31-Aug-22 31-Aug-22 Planning On Target On Target
PLI GLENCAIRN PRIMARY SCHOOL 175,759 153,652 175,759 0 175,759 0 153,652 153,652 175,759 0 0 Complete Complete Complete Complete Complete
PLI SHISKINE PRIMARY 4,000 0 4,000 0 4,000 0 0 0 4,000 0 0 31-Aug-22 31-Aug-22 Planning On Target On Target
PLI SKELMORLIE PRIMARY SCHOOL 83,500 0 83,500 0 83,500 0 0 0 8,500 (75,000) (75,000) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ST JOHN OGILVIE PRIMARY SCHOOL 50,247 11,478 50,247 0 50,247 0 11,478 11,478 50,247 0 0 31-Aug-22 31-Aug-22 Wall ties: Complete
Roofing: Tender
On Target On Target
PLI WEST KILBRIDE PRIMARY* 325 325 325 0 325 0 325 325 325 0 0 0 Complete Complete Complete Complete Complete
PLI WOODLANDS PRIMARY 5,500 0 5,500 0 5,500 0 0 0 5,500 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI AUCHENHARVIE ACADEMY* 350,000 16,685 350,000 0 350,000 0 16,685 16,685 350,000 0 0 18-Aug-22 18-Aug-22 Planning On Target On Target
PLI IRVINE ROYAL ACADEMY* 368,981 367 368,981 0 368,981 0 367 367 367 (368,614) (368,614) 31-Aug-23 31-Aug-23 Pupil Toilets: Complete AW Pitches: TenderOn Target Significantly off target Resource pressures within PMI resulting in this project
being delayed a further year.
PLI KILWINNING ACADEMY 220,000 0 220,000 0 220,000 0 0 0 70,000 (150,000) (150,000) 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI CUNNINGHAME HOUSE 98,273 0 98,273 0 98,273 0 0 0 98,273 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI H&SCP 47 WEST ROAD 10,000 0 10,000 0 10,000 0 0 0 10,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI ACHNAMARA CHILDREN'S UNIT 25,000 0 25,000 0 25,000 0 0 0 25,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
PLI REDBURN CC* 0 19,760 0 0 0 0 19,760 19,760 0 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 2,580,809 339,096 2,580,809 0 2,580,809 0 339,096 339,096 1,918,102 (662,707) 0 (662,707)
Other Property
INDUSTRIAL PORTFOLIO * 430,713 0 430,713 0 430,713 0 0 0 430,713 0 0 On Hold On Hold Multiple projects On Target On Target 
HOME 4,470,199 238,116 4,470,199 0 4,232,083 0 0 0 1,000,000 (3,232,083) 0 (3,232,083) 31-Mar-24 31-Mar-24 In development On Target On Target
BUILD 284,086 38,962 284,086 0 247,284 0 2,160 2,160 247,284 0 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
EMERGENCY CONTROL CTR 158,000 720 158,000 0 158,000 0 720 720 158,000 0 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 509,000 0 509,000 0 509,000 0 0 0 25,000 (484,000) 0 (484,000) 31-Mar-23 31-Mar-23 In development On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,640 104,190 134,640 0 26,928 0 (3,523) (3,523) 26,928 0 0 Complete Complete Complete On Target On Target
Total Property 5,986,638 381,987 5,986,638 0 5,604,008 0 (643) (643) 1,887,925 (3,716,083) 0 (3,716,083)   
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Other Housing 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 0

Page 22

Place
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2022/23
Year to Date
Budget 2022/23
Actual
Expenditure to 31
July 2022
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023    
Actual Over/
(Under) Spend for
2022/23
True Over/
(Under) Spend         
Brought / Carry
Forward to
2023/4
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
Project Description
TOTAL PROJECT
CAPITAL MONITORING 2022/23
Comments
COMPLETION DATES DELIVERY STATUS2022/23 BUDGETS
Regeneration
TOWN CENTRE REGENERATION 1,290,257 1,046,095 1,290,257 0 416,774 0 172,612 172,612 416,774 0 0 30-Sep-22 31-Mar-23 Construction On Target On Target
REPURPOSING PROPERTY GRANT FUND 330,000 14,906 330,000 0 329,320 0 14,226 14,226 329,320 0 0 30-Sep-22 30-Sep-22 In development On Target On Target
STEVENSTON BEACH HUB 180,000 180,000 180,000 0 84,525 0 84,525 84,525 84,525 0 0 31-Aug-22 31-Aug-22 Construction On Target On Target
MILLPORT TOWN HALL REGENERATION 2,103,330 1,157,619 2,103,330 0 1,569,838 0 624,127 624,127 1,569,838 0 0 31-Dec-22 31-Dec-22 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 259,000 17,337 259,000 0 259,000 0 17,337 17,337 259,000 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 240,000 141,938 240,000 0 209,223 0 111,161 111,161 209,223 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
PBIP 36 BANK STREET 780,000 44,194 780,000 0 751,400 0 15,594 15,594 751,400 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
IRVINE HIGH STREET 2,837,316 2,706,186 2,837,316 0 165,818 0 34,688 34,688 165,818 0 0 Complete Complete Complete Complete Complete
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 0 0 0 (100,000) (100,000) 31-Mar-24 31-Mar-24 In development On Target On Target
MILLPORT CARS 255,611 133,717 255,611 0 255,611 0 133,717 133,717 255,611 0 0 30-Oct-22 30-Oct-22 Construction On Target On Target
MONTGOMERIE PARK MASTERPLAN 3,718,598 1,744,321 3,718,598 0 136,264 0 1,987 1,987 136,264 0 0 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 1,909,993 751,947 1,909,993 0 1,341,141 0 183,096 183,096 1,341,141 0 0 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,195,999 3,557,856 4,195,999 0 1,377,575 0 739,432 739,432 1,377,575 0 0 31-Oct-22 31-Oct-22 Construction On Target On Target
VDLF - IRVINE KYLE ROAD SITE PREP* 1,421,368 1,421,110 1,421,368 0 438 0 180 180 438 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 267,066 60,357 267,066 0 245,893 0 39,184 39,184 245,893 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF - ANNICKBANK PH 3* 1,481,000 122,686 1,481,000 0 1,423,959 0 65,645 65,645 475,000 (948,959) (948,959) 31-Dec-23 31-Dec-23 Tender On Target On Target
VDLF - DEVELOPMENT WORK* 345,000 52,801 345,000 0 295,738 0 3,539 3,539 150,000 (145,738) (145,738) 30-Sep-23 30-Sep-23 In development On Target On Target
VDLF - DALRY RD SALTCOATS* 5,125 4,153 5,125 0 2,220 0 1,248 1,248 2,220 0 0 30-Sep-22 30-Sep-22 Delivery On Target On Target
VDLF - STRATEGY 50,000 0 50,000 0 50,000 0 0 0 50,000 0 0 31-Mar-23 31-Mar-23 In development On Target On Target
VDLF - TREE PLANTING 50,000 2,400 50,000 0 47,600 0 0 0 7,600 (40,000) (40,000) 31-Dec-23 31-Dec-23 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,205,219 5,209,497 0 25,301 0 21,023 21,023 25,301 0 0 Complete Complete Complete Complete Complete
VDLF - GAS WORKS (DALRY)* 173,897 166,061 173,897 0 1 0 (7,835) (7,835) 1 0 0 Complete Complete Complete Complete Complete
CYCLING/WALKING/SAFER STREETS * 1,108,954 142,921 1,108,954 0 1,108,954 0 59,125 59,125 535,000 (573,954) (573,954) 31-Mar-24 31-Mar-24 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 797,617 353,014 797,617 0 797,617 0 (20,139) (20,139) 353,014 (444,603) (444,603) 31-Mar-24 31-Mar-24 Various On Target On Target
FAIRLIE COASTAL PATH 50,000 50,000 50,000 0 50,000 0 0 0 50,000 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
PENNYBURN ROUNDABOUT BUS LANE 15,420 123,668 15,420 0 15,420 0 0 0 15,420 0 0 31-Mar-23 31-Mar-23 Feasibility On Target On Target
IRVINE CYCLE FRIENDLY TOWN 250,000 250,000 250,000 0 250,000 0 0 0 250,000 0 0 31-Mar-23 31-Mar-23 Various On Target On Target
BRODICK TO CORRIE CYCLE PATH 300,000 35,212 300,000 0 300,000 0 0 0 50,000 (250,000) (250,000) 31-Mar-23 31-Mar-23 Design On Target On Target
BUS CORRIDOR IMPROVEMENTS 274,955 74,955 274,955 0 200,000 0 0 0 150,000 (50,000) (50,000) 31-Mar-23 31-Mar-23 Various On Target On Target
BUS ROUTE CONGESTION MEASURES 757,821 605,250 757,821 0 152,571 0 0 0 152,571 0 0 31-Mar-23 31-Mar-23 Construction On Target On Target
CUMBRAE FERRY & BUS STOP 408,690 23,690 408,690 0 385,000 0 0 0 385,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
B714 ACTIVE TRAVEL IMPROVEMENTS 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-23 31-Mar-23 Design On Target On Target
STTS U88 NORTH SANNOX 199,080 0 199,080 0 199,080 0 0 0 199,080 0 31-Mar-23 31-Mar-23 Planning On Target On Target
STTS ROSS ROAD ARRAN 203,840 59,905 203,840 0 203,840 0 0 0 203,840 0 0 31-Mar-23 31-Mar-23 Planning On Target On Target
Total Regeneration 31,732,432 20,312,516 31,732,432 0 12,850,121 0 2,294,471 2,294,471 10,296,867 (2,553,254) 0 (2,553,254)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,340,486 3,378,163 0 0 0 (37,678) (37,678) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,898,460 2,977,098 0 40,595 0 (38,043) (38,043) 40,595 0 0 Complete Complete Complete Complete Complete
ARDROSSAN HOSTEL 0 0 10,113 10,113 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 8,994,855 8,878,539 8,994,855 0 40,595 0 (65,608) (65,608) 40,595 0 0 0
Total Place 169,620,106 72,138,983 169,620,106 0 59,713,049 0 5,749,389 5,749,389 43,502,641 (16,210,408) 0 (16,210,408)

Page 23

OTHER BUDGETS
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2022/23
Year to Date Budget
2022/23
Actual Expenditure
to 31 July 2022
Year to Date
Variance 2022/23
Projected
Expenditure to 31
March 2023
Over/ (Under)
Spend for 22/23
£ £ £ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 12,155,305 0 12,155,305 0 4,593,180 0 0 0 4,593,180 0
CORE INFRASTRUCTURE INVESTMENT 608,000 0 608,000 0 608,000 0 0 0 608,000 0
Total Other Budgets 12,155,305 0 12,155,305 0 5,201,180 0 0 0 5,201,180 0
2022/23 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 24

HRA Capital Statement APPENDIX 2
For the Four months to 31 July 2022
Description
Approved
budget 16
February
2022
Current
budget
including
carry forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised Budget
2022/23
Actual Spend to
31/07/2022 P4 Projection True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Council House Build Programme
Council House Building General 1,542 1,542 - 1,542 (3) 1,542 - 
Acquisition Of Houses On Open Market 720 526 - 526 245 526 On Target On Target
New Build Corsehillhead 1,450 600 - 600 34 600 On Target On Target Expected completion Autumn/Winter 2023.
New Build Brathwic Terrace 18 168 - 168 53 168 - On Target Complete Completed - final properties were handed over in June 2022
New Build Flatt Road Phase 1 1,712 1,072 (748) 324 101 324 Slightly off target  Complete Completed - final properties were handed over in December 2021.  Remaining budget to be transferred to projects in Lots
E and F for 2023/24.
New Build Towerlands 25 160 - 160 14 180 20 On Target Complete Completed - final properties were handed over in March 2022.
New Build Kinnier Road 3 2 - 2 - - (2) Complete Complete Completed - properties were handed over in October 2021.
New Build St Colms 1,896 782 - 782 724 782 On Target On Target Expected completion Autumn 2022.
New Build St Michaels Wynd - 592 - 592 592 592 On Target Complete Completed - final properties handed over in August 2002.
New Build Harbourside Irvine 6,460 6,000 - 6,000 2,064 6,000 On Target Slightly off target  Expected completion Winter 2022.
New Build Afton Court 910 1,080 - 1,080 1 1,080 On Target Slightly off target  Expected completion Spring 2023.
New Build Caley Court 1,769 1,843 - 1,843 718 1,843 On Target Slightly off target  Expected completion Autumn 2022.
New Build Springvale Saltcoats - 133 - 132 8 140 8 On Target Complete Completed - properties were handed over in November 2021.
New Build Dalrymple Place - 101 - 101 3 101 - On Target Complete Completed - properties were handed over in October 2021.
New Build St Beya Millport 6 53 - 53 - 53 - On Target Complete Completed - properties were handed over in July 2021.
Garnock Academy Site 7,950 1,800 (720) 1,080 - 1,080 Slightly off target  On Target Consultation stage. Expected completion Winter 2023.  Budget to be carried forward to 2023/24.
Largs police Station 1,908 1,600 - 1,600 1 1,600 On Target Slightly off target  Demolition complete. New completion date to be established. 
Ayrshire Central Site 9,497 1,500 - 1,500 4 1,500 - On Target On Target Pre-planning stage. Expected completion 2024. 
Bourtreehill Village 2,000 25 - 25 17 25 - On Target Slightly off target  Pre-planning stage. New completion date to be established. 
James McFarlane ASN Site 3,050 2,250 - 2,250 44 2,250 - On Target Slightly off target  Consultation stage. New completion date to be established. 
James Reid ASN school 6,050 1,125 - 1,125 103 1,125 - On Target Slightly off target  Consultation stage. New completion date to be established. 
Stanecastle ASN School 3,300 1,850 - 1,850 70 1,850 - On Target Slightly off target  Consultation stage. New completion date to be established. 
Fullarton Street 4,090 25 - 25 - 25 - On Target Slightly off target  Delays to delivery due to rehousing of tenants, which has now been completed. Demolition contractor appointed and
onsite, demolition expected to complete in Spring 2023. Expected completion 2025.
New Build Montgomerie Park 10,900 1,500 - 1,500 3 1,500 - On Target On Target Pre-planning stage. Expected completion Winter 2025.
Glebe Place 10 50 - 50 - 50 On Target On Target Pre-planning stage.
Regeneration Project 1e 15 5 - 5 - 5 On Target On Target Pre-planning stage.
Unallocated Regeneration Block 1 55 - - - - - On Target On Target Pre-planning stage.
Laburnum Avenue (Regen 1a) 160 5 - 5 - 5 On Target On Target Pre-planning stage.
Newhouse Drive (Regen 1b) 175 5 - 5 - 5 On Target On Target Pre-planning stage.
Regeneration Project 1d 360 5 - 5 - 5 On Target On Target Pre-planning stage.
Contingency 1,163 8,820 - 8,820 - 8,820
CONNEL COURT (49) 49 - - Complete Complete
GARRIER COURT (55) 55 - - Complete Complete
Total For Council House Build Programme 67,194 35,115 - (1,364) 33,750 4,796 33,776 26
Improvement to Existing Homes - Building Services
Window Replacement 325 364 11 375 8 375 - On Target On Target
Bathroom Programme 75 75 177 252 224 252 - On Target On Target
Kitchen Programme 2,610 4,450 - 4,449 164 1,549 (2,900) On Target Slightly off target  200 units will not be completed as programmed due to labour shortage. Underspend showing due to previous years
underspend not required.  Previous years uncompleted units were included in the revised business plan last year,
therefore already accounted for.
Bathroom Programme Voids - - 972 972 - 972 - On Target On Target
Kitchen Programme Voids - - 1,110 1,110 - 1,110 - On Target On Target
Door replacement programme 2,191 2,191 (2,191) - - - - Significantly off
target
Significantly off
target
Door replacement programme - tender has been re-issued following specification review due to unviable costs.  Balance
of budget requires to be earmarked for 2023/24.
Sheltered Housing Units 8,531 8,495 (5,745) 2,750 39 2,750 - Significantly off
target
Slightly off target  Barnett Court out for tender.  Cheviot Court at consultation stage.  Balance of budget requires to be earmarked for
2023/24.
Saltcoats MSF Investment 4,767 1,881 - 1,882 - 1,882 On Target Slightly off target  Additional works required.  Expected completion Winter 2022.
Total For Improvements to Existing Homes - Building
Services
18,499 17,456 - (5,666) 11,790 435 8,890 (2,900)

Page 25

HRA Capital Statement APPENDIX 2
For the Four months to 31 July 2022
Description
Approved
budget 16
February
2022
Current
budget
including
carry forwards
Approved
Revisions to
programme
Carry forward
(to)/from
future years
Revised Budget
2022/23
Actual Spend to
31/07/2022 P4 Projection True Over /
(Under)spend
Delivery Status
Financial
Delivery Status
Physical Comments
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Improvement to Existing Homes - External Contractors
Central Heating 2,524 4,442 - 4,442 639 2,562 (1,880) On Target On Target Underspend showing due to previous years underspend not required.  Previous years uncompleted units were included in
the revised business plan last year, therefore already accounted for.
Insulated Re-Rendering 421 865 - 865 - 421 (444) On Target On Target Underspend showing due to previous years underspend not required.  Previous years uncompleted units were included in
the revised business plan last year, therefore already accounted for.
Electrical Rewiring 698 1,742 - 1,743 47 699 (1,044) On Target On Target Underspend showing due to previous years underspend not required.  Previous years uncompleted units were included in
the revised business plan last year, therefore already accounted for.
Total For Improvements to Existing Homes - External
Contractors
3,643 7,049 - - 7,050 686 3,682 (3,368)
Refurbishment Schemes
Roofing & Rendering 4,450 5,507 - 5,507 945 4,713 (794) Slightly off target  On Target Uncompleted units from previous years accounted for in future years. Previous years carryforward not required.
Demolition High Flats Irvine 6,780 3,000 (1,117) 1,883 20 1,883 - Slightly off target  Slightly off target  Tender received lower than budget estimate. Demolition contractor appointed and onsite, demolition expected to
complete in Summer/Autumn 2023.  Balance of budget requires to be earmarked for 2023/24.
Kings Arms Project 265 600 - 600 83 600 - On Target Slightly off target  Consultation stage, construction is due to commence Winter 2022
Refurb Maress House - (13) 13 - - - - On Target On Target HRA contribution to the project complete.
Refurb Friars Lawn - 254 - 254 22 254 - On Target Complete Final completion expected August 2022.
Total For Refurbishment Schemes 11,495 9,348 - (1,104) 8,244 1,070 7,450 (794)
-Other Capital Works
Energy Efficiency Standard 5,362 5,488 - 5,488 180 5,488 - On Target On Target
Other Capital Works 726 712 - 712 - 712 - On Target On Target
Major Improvements 6 6 - 6 - 6 - On Target On Target
Parkhall & Kirkhall Asbestos - 17 - 17 - 17 - On Target On Target
Detection Equipment 458 1,463 (657) 806 82 806 - Slightly off target  Slightly off target  Contractor continuing to work through addresses, forced entries process in place / limited capacity due to staff issues
(contractors) will span 2 years.  Balance of budget to be earmarked for 2023/24.
Solar Panels 3,862 3,888 (26) 3,862 200 3,862 - On Target On Target
Professional Management Charges 1,326 1,738 - 1,738 316 1,738 - On Target On Target
Estate Based Regeneration 1,287 2,190 (740) 1,450 90 1,450 - Slightly off target  Slightly off target  Programme currently being revised. Proposals to Cabinet in Autumn/Winter 2022. Balance of budget to be earmarked for
2023/24.
Nelson Street Regeneration 442 451 (426) 25 - 25 - Significantly off
target
Significantly off
target
Final property obtained through CPO. Feasibility exercise being undertaken.  Balance of budget to be earmarked for
2023/24.
Health and Safety Works 207 207 - 207 305 207 On Target On Target
Total For Other Capital Works 13,676 16,160 - (1,849) 14,311 1,173 14,311 -
TOTAL EXPENDITURE 114,507 85,128 - (9,983) 75,145 8,160 68,109 (7,036)
Sale Of Council Houses - - - - - -
Sale Of Assets - - - - (1) -
CFCR (12,209) (12,209) - - (12,209) - (12,209)
Other Income - House Building - - - - - -
Capital Grants (14,175) (7,138) 3,963 (3,175) (87) (3,176) Slippage in house building resulting in reduction in grant claims.
Other Capital Income - - -
Capital Grants - Energy Funding - - - -
Affordable Housing Contribution (1,596) (1,596) (1,596) - (1,596)
Funding from Reserves - - -
Capital Fund Contribution - - - -
Prudential Borrowing (85,376) (63,034) 6,020 (57,014) - (49,977) 7,036
Welfare Reform Reserve - - 0 - -
Council House Build Fund (1,151) (1,151) - - 1,151 - (1,151)
TOTAL INCOME (114,507) (85,128) - 9,983 (75,145) (88) (68,109) 7,036
NET EXPENDITURE - - - 0 0 8,072 0 -
The following classifications have been used to highlight financial performance against budget
On Target On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)