NORTH AYRSHIRE COUNCIL 
23 August 2022 
Cabinet 
Title:    Valaris DS-4 Investigation Report 
Purpose:  To inform Cabinet that the investigation by the Republic of the
Marshal Islands Maritime Administrator has been concluded
and a report issued. 
Recommendation:  That the Cabinet notes that (i) the investigation by the Republic
of the Marshall Islands Maritime Administrator has been
concluded and (ii) recommendations have been issued to the
parties concerned. 
1. Executive Summary 
1.1 An investigation carried out by the Republic of the Marshall Islands Maritime
Administrator into the incident at Hunterston on 2nd February 2021 incident when the
Valaris DS-4 broke free from its moorings has been concluded and a report and
recommendations issued. The Council has no legal responsibility or remit in relation to
investigation of the incident and this report is for information. 
2. Background 
2.1 Drill Ships Valaris DS-4 and Ensco DS-8 were moored at Hunterston jetty on 2nd
February 2021.  The Valaris DS-4 broke free from its moorings in strong winds and
emergency action required to be taken to have it re-secured to the jetty. The Ensco
DS-8 remained at the jetty relying on the assistance of tugs. The investigation into the
marine incident was the responsibility of the Republic of the Marshall Islands Maritime
Administrator as the ships were registered to the Marshall Islands and managed by
Joulon Asset Management and Noah Ship Management Companies.  The
investigation report notes in detail the causal factors which contributed to the incident,
the preventative actions taken following the incident and recommendations have been
issued to the parties concerned. The report is attached at Appendix 1 and is also
available on the Scottish Government website at :
Mooring failure of the drill ship Valaris DS-4 - GOV.UK (www.gov.uk)   
2.2 The report notes that the causal factors which contributed to the incident include:
(a) the inability of VALARIS DS-4’s crewmembers to bring the thrusters online in
time to prevent the mooring lines from being overloaded by the storm force
winds from the northeast; and

Page 2

(b) the Master of VALARIS DS-4 did not request tug assistance when the
weather forecast for storm force north easterly winds was received on the
afternoon of 2 February 2021.
Additional causal factors which may have contributed to the incident are detailed in the
investigation report are as follows: 
(a) inadequate coordination between Joulon Asset Management Company
(Joulon) and Clydeport Operations Ltd throughout the planning process for
the lay-up of VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty;
(b) inadequate identification and consideration of local conditions, including the
higher than forecast north-easterly and easterly winds, winter temperatures,
and the time required for tugs to arrive after being requested, as part of
Joulon’s risk assessment for berthing the drill ships alongside at Hunterston
Jetty;
(c) inadequate identification of the drill ships’ power requirements during the
Asset Management Companies’ planning for the lay-up of VALARIS DS-4 and
ENSCO DS-8 to ensure that a sufficient number of diesel generators and
thrusters would be available if needed during a period of high winds or an
emergency situation;
(d) the apparent deviation from the drill ships’ mooring plans when VALARIS DS-
4 and ENSCO DS-8 were moored after being shifted along the jetty in late
January 2021;
(e) the lack of third-party verification that VALARIS DS-4 and ENSCO DS-8 were
moored in accordance with the drill ships’ mooring plans;
(f) with the exception of the drill ships’ mooring plans, the lack of third-party
assurance of the Asset Management Companies’ planning and execution of
the lay-up of VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty;
(g) the lack of comprehensive flag State regulations intended to ensure the safety
and security of laid-up vessels;
(h) the lack of flag State requirements for Republic of the Marshall Islands-
registered vessels that are in lay-up to undergo inspections or other forms of
oversight to verify they do not pose a safety or security hazard; and
(i) the absence of port State regulations intended to ensure the safety and
security of ships laid-up in ports and harbours in the United Kingdom.
2.2 The report notes that preventative actions were taken by the ships’ asset management
companies, Clydeport Operations Ltd (COL) and the Republic of the Marshall Islands’
Maritime Administrator. The preventative actions taken by Clydeport are detailed in the
report and summarised as follows:
1. The COL risk assessment for the lay-up of drill ships was reviewed and additional
mitigation measures were added.
2. A risk assessment addressing emergency response for a fire on board a vessel and
lines parting in severe weather was conducted.
3. The existing COL procedures for the lay-up of vessels were reviewed and revised to
include more detailed guidance and establish clear expectations for vessel owners
wanting to lay a vessel up at one of its facilities on the Clyde Estuary. The revised
procedures require that vessel owners provide information regarding the vessel’s
planned lay-up status, the mooring plan, the status of machinery and safety systems

Page 3

while in lay-up, the maintenance and inspection of mooring lines, and emergency
procedures. They also require that the vessel’s proposed manning while in lay-up be
approved by the flag State before it will be reviewed by the statutory harbour authority.
The revised procedures are being adopted by each of the statutory harbour authorities
within Peel Ports.
4. COL, in coordination with Joulon, conducted a review of VALARIS DS-4’s and ENSCO
DS-8’s equipment status (e.g., diesel generators, thrusters, and related systems) and
criteria for activating the drill ships’ weather contingency plan. 
5. COL reviewed and agreed to Joulon’s revised manning for both VALARIS DS-4 and
ENSCO DS-8. 
6. COL conducted a review of the jetty infrastructure taking into consideration winter
conditions. 
7. COL contracted to have an independent third-party review of the drill ship’s new
mooring plans completed. 
8. Contingency response plans for responding to emergencies involving a laid-up vessel
were developed for each statutory harbour area within Peel Ports. 
9. A weather monitoring station was installed at the Hunterston Jetty. 
2.3 The report contains recommendations which are as follows: 
1. It is recommended that Joulon and Noah:
(a) review and revise their procedures for planning for vessel lay-ups
taking the lessons learned from this marine incident into account. 
2. It is recommended that Peel Ports:
(a) propose guidance on planning and conducting of vessel lay-up in ports
in the United Kingdom to the Marine Coastguard Agency’s Port Marine
Safety Code (PMSC) Steering Group, for inclusion in the PMSC’s
Guide to Good Practice. 
3. It is recommended that the Republic of the Marshall Islands Maritime
Administrator:
(a) develop additional regulatory requirements that take different lay-up
conditions into account to ensure the safety of Republic of the Marshall
Islands-registered vessels that are placed in lay-up and crews on
board such vessels; and 
(b) review, and revise where required, internal procedures related to
oversight of compliance with established requirements for vessels in
lay-up.
4. It is recommended that the Marine Coastguard Agency in coordination with the
PMSC Steering Group:
(a) consider publishing guidance on the planning and conducting of vessel
lay-ups in ports in the United Kingdom, for inclusion in the PMSC’s Guide
to Good Practice. 
3. Proposals

Page 4

3.1 That Cabinet notes that (i) the investigation by the Republic of the Marshall Islands
Maritime Administrator has been concluded (ii) that preventative actions have been
taken in response to the incident and (iii) recommendations have been issued. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None arising from this report. 
Human Resources 
4.2 None arising from this report. 
Legal 
4.3 None arising from this report. 
Equality/Socio-economic 
4.4 Not applicable. 
Climate Change and Carbon 
4.5 Not applicable. 
Key Priorities 
4.6 Not applicable. 
Community Wealth Building 
4.7 Not applicable. 
5. Consultation 
5.1 Not applicable. 
Aileen Craig
Head of Democratic Services 
For further information please contact Aileen Craig , Head of Democratic Services , on
email: acraig@north-ayrshire.gov.uk 
Background Papers
None 
Appendix 1

Page 5

Official Number: 3636 IMO Number: 9459943
VALARIS DS-4 CASUALTY INVESTIGATION REPORT
Loss of Moorings
Hunterston, Scotland  |  2 February 2021
REPUBLIC OF THE MARSHALL ISLANDS
Maritime Administrator
Appendix 1

Page 6

Published by: Republic of the Marshall Islands Maritime Administrator on 26 July 2022

Page 7

Maritime Administrator
Please submit questions to: 11495 Commerce Park Drive, Reston, Virginia 20191-1506 USA | tel: +1 703 620 4880 | investigations@register-iri.com
DISCLAIMER
In accordance with national and international requirements, the Republic of the Marshall Islands
Maritime Administrator (the “Administrator”) conducts marine safety investigations of marine
casualties and incidents to promote the safety of life and property at sea and to promote the prevention 
of pollution. Marine safety investigations conducted by the Administrator do not seek to apportion
blame or determine liability. While every effort has been made to ensure the accuracy of the information
contained in this Report, the Administrator and its representatives, agents, employees, or affiliates 
accept no liability for any findings or determinations contained herein, or for any error or omission, 
alleged to be contained herein.
Extracts may be published without specific permission providing that the source is duly acknowledged;
otherwise, please obtain permission from the Administrator prior to reproduction of the Report.
AUTHORITY
An investigation, under the authority of the Republic of the Marshall Islands laws and regulations,
including all international instruments to which the Republic of the Marshall Islands is a Party, was
conducted to determine the cause of the casualty.

Page 8

No embedded text on this page.

Page 9

LIST OF ABBREVIATIONS AND ACRONYMS
PART 1: EXECUTIVE SUMMARY
PART 2: FINDINGS OF FACT
PART 3: ANALYSIS
PART 4: CONCLUSIONS
PART 5: PREVENTIVE ACTIONS
PART 6: RECOMMENDATIONS
6
8
10
33
40
41
43
TABLE OF CONTENTS

Page 10

Republic of  the Marshall Islands Maritime Administrator
6
List of Abbreviations and Acronyms
1 A/E  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . First Assistant Engineer
3 A/E  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Third Assistant Engineer
3/O  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Third Officer
AIS  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Automatic Identification System
ANSI  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . American National Standards Institute
ANSI/API RP 2MET  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ANSI/API Recommended Practice Derivation
of Metocean Design and Operating Conditions
API  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . American Petroleum Institute
API RP 2SK  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .API Recommended Practice Design and Analysis
of Stationkeeping Systems for Floating Structures
ASD  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Able Seafarer Deck
ASE  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Able Seafarer Engineer
C/E  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Chief Engineer
C/O  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Chief Officer
COVID-19  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Coronavirus Disease 2019
DNV GL  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Det Norske Veritas Germanischer Lloyd
DNV GL-RP-C205  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DNV GL Recommended Practice Environmental
Conditions and Environmental Loads
DNV GL-ST-NOO1  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .DNV GL Standard Marine Operations and Marine Warranty
DOC  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Document of Compliance
DP  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Dynamic Positioning
DPA  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Designated Person Ashore
ERA5  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .European Centre for Medium-Range Weather Forecasts
ETO  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Electro-Technical Officer
HMPE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .High Modulus Polyethylene
ICLL  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . International Convention on Load Lines, 1966
ILO  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . International Labour Organization
IMO  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .International Maritime Organization
ISM  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .International Safety Management
ISM Code  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .International Management Code for the Safe
Operation of Ships and for Pollution Prevention
kg/m3  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Kilograms per Cubic Meter
LIST OF ABBREVIATIONS AND ACRONYMS

Page 11

7
List of Abbreviations and Acronyms
kn  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Knots
kW  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Kilowatt
m  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Meters
m/s  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Meters Per Second
m2  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Square Meters
MARPOL  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .International Convention for the Prevention of Pollution from Ships
MBL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Minimum Breaking Load
MLC, 2006  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Maritime Labour Convention, 2006
MODU  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Mobile Offshore Drilling Unit
MSMC  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Minimum Safe Manning Certificate
MSMS  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Marine Safety Management System
N  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Newtons
NM  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Nautical Miles
OICEW  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Officer in Charge of an Engineering Watch
OICNW  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Officer in Charge of a Navigational Watch
OS  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Ordinary Seafarer
P&I Club  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Protection and Indemnity Club
PA system  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Public Address System
PMSC  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Port Marine Safety Code
SMS  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Safety Management System
SOLAS  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . International Convention for the Safety of Life at Sea, 1974
SOP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Standard Operating Procedure
STCW Code  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Seafarers’ Training, Certification and Watchkeeping Code
STCW  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . International Convention on Standards of Training,
Certification and Watchkeeping for Seafarers
SWL  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Safe Working Load
T  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .True
t  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ton
UHMWPE  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Ultra High Molecular Weight Polyethylene
URL  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Uniform Resource Locator
V  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .Volt
VHF  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Very High Frequency

Page 12

Republic of  the Marshall Islands Maritime Administrator
8
PART 1: EXECUTIVE SUMMARY
On 2 February 2021, the Republic of the Marshall Islands-registered drill ships VALARIS DS-4 and ENSCO DS-8,
managed by Noah Ship Management DMCCO (Noah), were moored at the Hunterston Jetty, which is located at the
southern end of the Clyde Estuary, on the Largs Channel, between Great Cumbrae Island and the Scottish mainland. 
Both drill ships held a Provisional Certificate of Registry with the endorsement “This Certificate is Only Valid while 
the Vessel Remains in Laid-up Status and is Not Valid for Navigation.”1
Offshore winds from the northeast had increased throughout the day and by 18002 were between 50-55 kn. At about
1915, VALARIS DS-4’s moorings failed during storm force winds. The drill ship was blown off the jetty and drifted 
to the southwest until about 1923, when the anchor, which had previously been deployed as part of the VALARIS 
DS-4’s mooring arrangements, held. This likely prevented the drill ship from going aground on Great Cumbrae Island, 
which was about 400 m to the west.
VALARIS DS-4’s crew were able to start all but one of the drill ship’s diesel generators but did have difficulties bringing
the bow and stern thrusters online. VALARIS DS-4 was re-moored at Hunterston Jetty on 8 February 2021 after the
crewmembers were able to start all but one of the azimuth thrusters.
ENSCO DS-8 remained moored alongside the jetty with tug assistance and the use of its thrusters.
1 A vessel holding a Provisional Certificate of Registry with the endorsement “This Certificate is Only Valid while the Vessel Remains in Laid-up Status and is Not Valid 
for Navigation” is out of service and is not required to comply with the international and national requirements that would otherwise be applicable to the vessel when it 
is in service.
2 Unless otherwise stated, all times are the drill ships’ local time (UTC +0).
Part 1: Executive Summary

Page 13

9
The marine safety investigation conducted by the Republic of the Marshall Islands Maritime Administrator (the
“Administrator”)3 identified the following:
1. Causal factors that contributed to this marine incident include:
(a) the inability of VALARIS DS-4’s crewmembers to bring the thrusters online in time to prevent the
mooring lines from being overloaded by the storm force winds from the northeast; and
(b) the Master of VALARIS DS-4 did not request tug assistance when the weather forecast for storm force
north easterly winds was received on the afternoon of 2 February 2021.
2. Additional causal factors that may have contributed to this marine incident include:
(a) inadequate coordination between Joulon Asset Management (Joulon) and Clydeport Operations
Limited (COL) throughout the planning process for the lay-up of VALARIS DS-4 and ENSCO DS-8
at Hunterston Jetty;
(b) inadequate identification and consideration of local conditions, including the higher than forecast
northeasterly and easterly winds, winter temperatures, and the time required for tugs to arrive after being
requested, as part of Joulon’s risk assessment for berthing the drill ships alongside at Hunterston Jetty;
(c) inadequate identification of the drill ships’ power requirements during Joulon’s and Noah’s planning for
the lay-up of VALARIS DS-4 and ENSCO DS-8 to ensure that a sufficient number of diesel generators and
thrusters would be available if needed during a period of high winds or an emergency situation;
(d) the apparent deviation from the drill ships’ mooring plans when VALARIS DS-4 and ENSCO DS-8
were moored after being shifted along the jetty in late January 2021;
(e) the lack of third-party verification that VALARIS DS-4 and ENSCO DS-8 were moored in accordance 
with the drill ships’ mooring plans;
(f) with the exception of the drill ships’ mooring plans, the lack of third-party assurance of Joulon’s and
Noah’s planning and execution of the lay-up of VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty;
(g) the lack of comprehensive flag State regulations intended to ensure the safety and security of laid-up vessels;
(h) the lack of flag State requirements for Republic of the Marshall Islands-registered vessels that are in lay-up to
undergo inspections or other forms of oversight to verify they do not pose a safety or security hazard; and
(i) the absence of port State regulations intended to ensure the safety and security of ships laid-up in ports and
harbors in the United Kingdom.
3. Actions or events that reduced the adverse consequences of this marine incident include:
(a) that VALARIS DS-4’s and ENSCO DS-8’s anchors had been pre-deployed when the drill ships were berthed
at Hunterston Jetty and that VALARIS DS-4’s anchor was reset and held the drill ship in mid-channel after
being blown off the jetty following the loss of moorings; and
(b) the arrival of tugs to hold ENSCO DS-8 alongside the berth.
3 The United Kingdom of Great Britain and Northern Ireland (hereinafter “United Kingdom”) was a substantially interested State for this marine safety investigation. The 
United Kingdom Marine Accident Investigations Branch (MAIB) supported the Administrator throughout the investigation.
Part 1: Executive Summary

Page 14

Republic of  the Marshall Islands Maritime Administrator
10
PART 2: FINDINGS OF FACT
The following Findings of Fact are based on the information obtained
during the Administrator’s marine safety investigation.
1. Ship particulars: see charts to right.
2. VALARIS DS-4 and ENSCO DS-8 are both dynamically
positioned deep water drill ships (see Figure 1).
Figure 1: General Arrangement Drawing of VALARIS DS-4 (top) and ENSCO
DS-8 (bottom).
3. Both drill ships are equipped with three forward and three
aft electrically driven azimuth thrusters that are used for 
propulsion and steering. Electrical power is provided by six
diesel generators. Relevant details of the drill ships’ propulsion
systems are in the following table:
COMPONET VALARIS DS-4 ENSCO DS-8
Diesel
Generators
(six each)
Azimuth
Thrusters
(six each)
MAN B&W
8,000 kW
Wartsila
7,290 kW
Rolls Royce
5,500 kW
Rolls Royce
5,500 kW
Ship Name
VALARIS DS-4
Registered Owner
Ensco Ocean 1 Company
ISM Ship Management
Noah Ship Management DMCCO
Flag State
Republic of the Marshall Islands
Deadweight Tonnage
96,273
Length x Breadth x Depth
211.3 x 42 x 19 m
Year of Build
2010
Gross Tonnage
60,162
IMO No.
9459943
Official No.
3636
Call Sign
V7SE8
Net Tonnage
18,048
Ship Type
Drill Ship
Document of Compliance 
Recognized Organization
Bureau Veritas
Safety Management Certificate 
Recognized Organization
Bureau Veritas
Classification Society
American Bureau of Shipping
Persons on Board
Crewmembers: 7
Technical Support: 2
SHIP 
PARTICULARS
Part 2: Findings of Fact

Page 15

11
Lay-up at Las Palmas de Gran Canaria
4. Following their arrival at Las Palmas de Gran Canaria 
(hereinafter “Las Palmas”), Kingdom of Spain (hereinafter
“Spain”) in May 2020, VALARIS DS-4 and ENSCO DS-8 
were Laid-up Warm Stacked in accordance with American
Bureau of Shipping’s (ABS’s) Guide for Lay-up and 
Reactivation of Mobile Offshore Drilling Units.4 At the 
time, both drill ships were managed by Ensco International 
Inc. (Ensco).5
5. The Administrator issued a Provisional Certificate of Registry
with the endorsement “This Certificate is Only Valid while
the Vessel Remains in Laid-up Status and is Not Valid for
Navigation”6 to ENSCO DS-8 on 16 June 2020 and to 
VALARIS DS-4 on 1 July 2020.
6. ABS changed the lay-up status of VALARIS DS-4 in August 
2020 and ENSCO DS-8 in October 2020 to laid-up without
additional notation when annual lay-up surveys were 
not completed.
7. The drill ships’ owners decided to move VALARIS DS-4 and
ENSCO DS-8 to another lay-up location while they were at 
Las Palmas.
Change of Lay-up Location
8. By late September 2020, the drill ships’ owners had 
contracted Joulon to plan for the their continued lay-up at
either another Spanish port or in Hunterston, Scotland. This
included conducting risk assessments and the development of 
contingency plans, coordination with port authorities, and
establishing preventive maintenance requirements.
9. Joulon did not hold a DOC. Joulon subcontracted Noah,
who holds a DOC, as marine managers for both drill ships.
This included assisting with conducting risk assessments
and developing contingency plans. It also included daily 
4 The ABS guidelines are addressed in greater detail later in this report.
5 Ensco held a DOC issued in accordance with the ISM Code and was named on the SMCs held 
by VALARIS DS-4 and ENSCO DS-8 as the company responsible for the operation of both 
drill ships per SOLAS chapter IX.
6 A vessel holding a Provisional Certificate of Registry with the endorsement “This 
Certificate is Only Valid while the Vessel Remains in Laid-Up Status and is Not Valid for 
Navigation” is out of service and is not required to comply with the international and 
national requirements that would otherwise be applicable to the vessel when it is in service.
Part 2: Findings of Fact
Ship Name
ENSCO DS-8
Registered Owner
Ensco Intercontinental GMBH
ISM Ship Management
Noah Ship Management DMCCO
Flag State
Republic of the Marshall Islands
Deadweight Tonnage
77,000
Length x Breadth x Depth
213.6 x 38 x 18.5 m
Year of Build
2015
Gross Tonnage
57,335
IMO No.
9659531
Official No.
5307
Call Sign
V7CQ5
Net Tonnage
17,200
Ship Type
Drill Ship
Document of Compliance 
Recognized Organization
Bureau Veritas
Safety Management Certificate 
Recognized Organization
Bureau Veritas
Classification Society
American Bureau of Shipping
Persons on Board
Crewmembers: 6
Technical Support: 4
SHIP 
PARTICULARS

Page 16

Republic of  the Marshall Islands Maritime Administrator
12
management of both drill ships, hiring of marine crews, ensuring required preventive maintenance tasks were
conducted, and coordination with the drill ships’ flag State.
10. It was planned that Joulon and Noah would assume responsibility for managing the drill ships after their arrival 
at another lay-up location.
11. On 24 November 2020, ABS surveyors attended VALARIS DS-4 and ENSCO DS-8 to complete reactivation 
surveys. Both drill ships were issued short term international statutory certificates7 that were valid through 23 
December 2020 and class certificates for VALARIS DS-4 to complete a single voyage to Almería, Spain and for
ENSCO DS-8 to complete a single voyage to Motril, Spain.
12. Sometime after the reactivation surveys were completed, the drill ships’ owners, in coordination with Joulon and 
Noah, decided to move both drill ships from Las Palmas to Hunterston rather than Almería and Motril for 
continued lay-up.
Hunterston Jetty
13. Hunterston Jetty is located at the southern end of the River Clyde between Great Cumbrae Island and the Scottish
mainland (see Figure 2). The jetty was built in 1979 to accommodate ships up to 380 m in length on its outer 
face8 delivering iron ore to the Ravenscraig steelworks. The jetty has been largely vacant since the steelworks 
closed in 2016.9
Figure 2: Hunterston Jetty.
7 The following short term international certificates were issued to both drill ships: International Load Line Certificate, International Oil Pollution Prevention 
Certificate, International Air Pollution Prevention Certificate, Mobile Offshore Drilling Unit Safety Certificate (1989), and an International Sewage Pollution 
Prevention Certificate. The Safety Management Certificates held by both drill ships had remained valid since no intermediate audits had been required while the drill 
ships were in lay-up at Las Palmas.
8 Vessels up to 280 m in length could be moored on the inside face of the jetty.
9 The cranes and cargo handling equipment were removed from the jetty when the steelworks were closed.
Part 2: Findings of Fact

Page 17

13
14. The jetty is 443 m long and is oriented along the 033° T/213° T axis (see Figure 2). It is fitted with 100 t 
bollards approximately every 20 m. There is also a 150 t bollard on a dolphin at its north end (see Figure 2). The 
jetty is equipped with seven Yokohama fenders. The maximum tidal range alongside is 3.9 m.
15. The jetty was owned and operated by COL, which was the statutory harbor authority for the Clyde Estuary.
16. COL oversaw the safe operation of the port and jetty based on Peel Ports Group’s (Peel Port’s) MSMS and the
supporting SOPs.10
17. In 2014, COL created a generic risk assessment11 for the lay-up of ships within the area for which it was the 
statutory harbor authority. The following mitigation measures were identified that:
(a) the ship’s mooring plan met Classification Society requirements;
(b) the ship’s operating procedures and COL emergency procedures were aligned;
(c) the ship’s crewmembers were aware of local sensitivities and the Harbour Master’s requirements;
(d) a joint planning meeting be conducted to discuss the availability of tug assistance and to ensure that
the moorings were in good condition;
(e) the local police force and fire and rescue service were aware of the laid-up ship; and
(f) the proposed lay-up plan met the port’s emergency preparedness procedures as described in the 
port’s MSMS.
Planning for Lay-up at Hunterston Jetty
Drill Ship Risk Assessment
18. On 24 November 2020, Joulon completed a risk assessment for berthing drill ships alongside at Hunterston,
Scotland. Identified hazards, potential consequences, and current and additional controls include:12
POTENTIAL
CONSEQUENCES BARRIERS / CONTROLSHAZARD
Vessel mooring
component failure
Losing vessel
position at quay
Current Controls
• Mooring analysis and line
arrangement
• Regular inspections of lines
by crew
• Third-party verification
• Port competence – tug
availability
• Equipment maintenance and
certification
• Following procedures as per
contingency plan
• Power thruster availability
Additional Controls
• Equipment verification
• Additional mooring ropes
available
• Line adjustment for tidal
variations
• Deploying ship’s anchors
10 The MSMS was based on the United Kingdom’s PMSC and Guide to Good Practice on Port Marine Operations. Both documents are discussed later in the report.
11 Risk assessment 156 – lay-up vessels: covering vessels laid-up at Loch Striven, Great Harbour or elsewhere within COL’s jurisdiction.
12 The other identified hazards were tidal variations and collisions with another vessel.
Part 2: Findings of Fact

Page 18

Republic of  the Marshall Islands Maritime Administrator
14
POTENTIAL
CONSEQUENCES BARRIERS / CONTROLSHAZARD
Quayside mooring
component failure
Mooring rope failure
Adverse weather
Losing vessel
position at quay
Strain on the
mooring rope
Losing vessel
position at quay
Strain on the
mooring rope
Vessel structure
colliding with
quayside
Current Controls
• Mooring analysis and line
arrangement
• Third-party verification
• Port competence – tug
availability
• Quayside bollards
maintenance and load test
• Following procedures as per
contingency plan
• Power thruster availability
Additional Controls
• Cross lining to adjacent
bollard
• Additional mooring ropes
available
• Equipment verification
• Line adjustment for tidal
variations
• Deploying ship’s anchors
• Additional resources
available on quayside
Current Controls
• Constant monitoring of the
mooring ropes
• Monitoring environmental
conditions on daily basis
• Crew are trained in the event
of a mooring failure and
other associated emergencies
by way of regular drills (per
contingency plan)
• Daily operations
preparedness meeting
Additional Controls
• Additional mooring ropes
available
• Sufficient manning levels 
for adjusting lines
• Additional resources to be
made available at quayside
during adverse weather
conditions
• Deploying anchors as
required
Current Controls
• Mooring analysis and line
arrangement
• Monitoring environmental
conditions on daily basis
• Weather forecast data from
two independent parties
• Daily operations
preparedness meeting
• Coordination with Port
Authorities on regular basis
• Contingency plan and
emergency response in place
Additional Controls
• Power thrusters available
• Tug availability
• Additional resources
available on quayside
• Deploying ship’s anchors
• Deploying anchors as
required
19. It was determined that the level of residual risk for each of the identified hazards was broadly acceptable with the
identified current and additional controls in place.
Mooring Plan
20. On 25 November 2020, Joulon contracted InterMoor13 to develop a plan for mooring ENSCO DS-8 at Hunterston
Jetty. The plan was based on the drill ship’s anchor being deployed.14 Joulon also provided InterMoor with the
results of an extreme wind study with a 10-year return period that had been prepared for the drill ship’s owners
13 InterMoor is an engineering firm that specializes in design, installation, inspection, and maintenance of offshore mooring arrangements.
14 ENSCO DS-8’s ground tackle consists of one 14 t high holding power anchor and 14 shackles of anchor chain.
Part 2: Findings of Fact

Page 19

15
based on the ERA5 dataset for 1979-2019.15 The 10-year average maximum 1-minute wind speeds16 at an elevation
of 10 m identified by this study were:
WIND DIRECTION (T)
1-MINUTE
MEAN WIND SPEED
m/s
kn
337.5 ̊
- 022.5 ̊
157.5 ̊
- 202.5 ̊
067.5 ̊
- 112.5 ̊
247.5 ̊
- 292.5 ̊
022.5 ̊
- 067.5 ̊
202.5 ̊
- 247.5 ̊
112.5 ̊
- 157.5 ̊
292.5 ̊
- 337.5 ̊
18.5 30.621.4 34.720.5 34.226.3 28.3
36.1 59.541.5 67.439.8 66.551.1 55.0
21. On 30 November 2020, InterMoor provided an initial mooring plan (Rev. 00) for ENSCO DS-8 to Joulon for
their review.
22. On 1 December 2020, Joulon contracted InterMoor to produce a plan for mooring VALARIS DS-4 at Hunterston
Jetty. This plan was supposed to be based on the weather data that had been used for ENSCO DS-8’s mooring
plan. The initial plan (Rev. 00) was provided to Joulon on 4 December 2020. This plan was based on the use 
of two anchors rather than one.17
23. On 18 December 2020, in response to comments received from Joulon following their review of the initial mooring
plans for VALARIS DS-4 and ENSCO DS-8, InterMoor recommended that the revisions to these plans be based
on weather data for a 100-year return per DNV GL-ST-N001.18 The 100-year mean wind speeds at an elevation
of 10 m were calculated based on the ERA5 dataset of 1-hour mean wind speeds for 1979-2019. The wind
speeds were:19
WIND DIRECTION (T)
REPORTING
PERIOD
1-hour mean (m/s)
1-hour mean (kn)
10-minute mean (m/s)
10-minute mean (kn)
1-minute mean (m/s)
1-minute mean (kn)
3-second gust (m/s)
3-second gust (kn)
000° 120° 240°060° 180° 300°030° 150° 270°090° 210° 330°
17
18
20
22
33.0
35.0
38.9
42.8
19
21
23
25
36.9
40.8
44.7
48.6
27
30
33
38
52.5
58.3
64.1
73.9
20
22
24
26
38.9
42.8
46.7
50.5
25
27
30
33
48.6
52.5
58.3
64.1
25
27
30
34
48.6
52.5
58.3
66.1
18
20
22
24
35.0
38.9
42.8
46.7
23
25
27
31
44.7
48.6
52.5
60.3
27
30
33
38
52.5
58.3
64.1
73.9
20
22
24
27
38.9
42.8
46.7
52.5
25
28
31
35
48.6
54.4
60.3
68.0
22
24
26
29
42.8
46.7
50.5
56.4
15 This data is distributed by the Copernicus Climate Change Service (https://climate.copernicus.eu/).
16 The ERA5 dataset does not report 1-minute maximum winds speeds. These were determined by converting maximum 3-second wind gusts using a wind-averaging 
formula in ANSI/API RP 2MET.
17 VALARIS DS-4’s ground tackle consists of one 15 t high holding power anchor and 14 shackles of anchor chain.
18 Based on DNV GL-ST-N001, quayside/inshore moorings that are intended to be in place for more than one year should be based on a 100-year return, those that are 
intended to be in place for one month to a year should be based on a 50-year return, and those that will be in place for seven days to one month should be based on a 
10-year return. A lower return period could be used if the vessel could leave its berth on receipt of a forecast for poor weather.
19 The calculations to determine the 10-minute mean, 1-minute mean, and 3-second guest wind speeds were based on DNV GL-RP-C205.
Part 2: Findings of Fact

Page 20

Republic of  the Marshall Islands Maritime Administrator
16
24. On 23 December 2020, InterMoor provided the results of the mooring analysis completed using the data for the 
100-year return to Joulon and the drill ships’ owners. In response, Joulon directed InterMoor to base the mooring
plans on the data for the 10-year return as provided for by API RP 2SK.20 Joulon also informed InterMoor 
that VALARIS DS-4 had one anchor.
25. InterMoor provided the revised mooring plan for VALARIS DS-4 to Joulon on 24 December 2020. Based on 
this plan, the drill ship was to be moored with 15 UHMWPE lines and the anchor. The lines consisted of 30, 36, 
and 40 mm diameter lines. Except for a 36 mm line leading forward from a connection point on the starboard 
side forward of amidships, a 36 mm line leading aft from the starboard quarter, and two 40 mm stern lines, the
remainder of the lines were all 30 mm.
26. The revised mooring plan for ENSCO DS-8 was provided on 28 December 2020. The drill ship was to be moored
using 14 40 mm diameter UHMWPE lines and the anchor.
27. In addition to specifying the number of lines that were to be used and the points on the ships and on the jetty 
where each line was to be connected, they also specified the type, diameter, length of line that should be paid out 
from the fairlead, and pre-tension force for each line. Both plans also specified how much anchor chain should be 
paid out when the anchors were set.
28. Neither of the two mooring plans included a requirement for the drill ships’ thrusters to be started or that they should
leave the jetty when the forecast or actual wind speed exceeded a given speed.
29. InterMoor reported that the length of each line was established to maximize how much load it could absorb21 and to
account for tidal changes. This was done so the drill ships’ crewmembers would not need to adjust the lines when
the tide changed.
30. The mooring plan was developed using the OrcaFlex model, which assumes that wind speed is constant or steady.
31. The mooring plans were not reviewed by the Administrator nor were they required to be reviewed by 
the Administrator.22
Drill Ships’ Emergency Response Plans
32. On 24 December 2020, Joulon finalized the emergency response plans for both VALARIS DS-4 and ENSCO 
DS-8. Both plans included emergency contact numbers for Joulon, Noah, Hunterston Terminal, tugs, and 
emergency services. They also both included emergency response procedures for adverse weather.23
33. The procedures for adverse weather consisted of a decision-making flow chart that included a list of actions that
should be taken following the receipt of a forecast for adverse weather. Adverse weather was not defined by these
procedures. The flow chart included decision points for each Master to decide if tugs or a berthing team would 
be required.
20 API RP 2SK recommends that weather data for a 100-year return period be used for permanent moorings. It also indicates that a shorter return period, determined by a 
risk analysis that takes the consequences of a mooring failure into account, may be justified if the design life of the mooring is less than 20 years. Further, API RP 2SK 
does not differentiate between quayside/inshore moorings and offshore moorings.
21 This is based on the MBL and axial stiffness of the line, which are functions of the line type and diameter. In general, short lines are able to absorb less load than longer 
lines of the same type and diameter.
22 The Administrator’s requirements for vessels in lay-up are discussed later in the report.
23 They also included response procedures for vessel collision, fire, man overboard, loss of containment, and medical emergency.
Part 2: Findings of Fact

Page 21

17
34. The procedures did not include guidance addressing when to request the support of tugs or a berthing team or 
starting the drill ships’ thrusters nor did they reference the weather contingency plans that had been developed for
both drill ships.
Drill Ships’ Weather Contingency Plans
35. The weather contingency plans were developed taking into account the risk assessment that Joulon completed 
for berthing VALARIS DS-4 and ENSCO DS-8 alongside at Hunterston Jetty.24 The plans included the actions 
that should be taken in different scenarios, including winds that exceeded the upper limits of the drill ships’ 
mooring plan.25
36. The actions required by the weather contingency plans, if the forecast or actual wind speeds exceeded those that 
the mooring plans were based on, or if there was an indication that the drill ships’ moorings might fail, were 
divided into three phases based on forecast and actual wind speeds. The actions that were supposed to be taken 
during each of these phases were:
INITIAL PHASE
Wind Speed Forecast to Exceed
Mooring Plan Limits (> 50 kn)
SECOND PHASE
Wind Speed Increasedto 60 kn
THIRD PHASE
Wind Speed is MoreThan 70 kn
• Inform crew to prepare for
second phase
• Escalate port authority to standby
• Ensure the quayside is clear or
free from any obstruction
• Keep extra mooring lines and
equipment ready
• Put engines and thrusters on
standby
• Inform crew of escalation
• Mobilize port authority
contingency response team
• Follow emergency thruster control
procedure
• Start engines and keep thrusters
ready per the emergency thruster
control procedure
• Monitor mooring lines
• Call Peel Ports and request help
from contingency response team,
including tugs and mooring line
handling team
• Initiate onshore contingency
response organization
• Monitor engines and thrusters
• Monitor mooring lines
37. The weather contingency plan indicated that up to four thrusters were available for use when required. It also
stated that the thrusters should be limited to 30-50% of their rated capacity in extreme weather conditions. The plan 
also indicated that tugs at Greenock could arrive on scene within 2–3 hours and that tugs engaged in ship assist 
work might be available sooner.
Port Planning
38. In September 2020, a structural assessment conducted on behalf of Peel Ports determined the jetty could 
accommodate five drill ships, two of which were VALARIS DS-4 and ENSCO DS-8.
39. This assessment was based on three of the drill ships being moored side-by-side on the outside face of the jetty 
and the other two being moored side-by-side on the inside face. It was assumed that each drill ship had a 
transverse windage area of 8,000 m2. It was also assumed that the second and third drill ships would receive 30% 
and 15% of the force of the wind and current acting on the outermost drill ship.
24 This risk assessment is addressed earlier in this report.
25 The other scenarios were collision, an emergency departure from the quay, and extreme tidal variations.
Part 2: Findings of Fact

Page 22

Republic of  the Marshall Islands Maritime Administrator
18
40. It was reported that the mooring loads were calculated using different wind and current directions. Neither the 
source nor the details of the weather data that was used for this assessment were reported.
41. Also in September 2020, COL commissioned a third-party analysis of wind speeds and directions at the Hunterston
Jetty. The analysis was based on wind speeds recorded at 5-minute intervals from 2009-202026 that were averaged
to hourly mean values and adjusted to represent the speed at 10 m above the ground. This analysis indicated 
that the 10-year hourly extreme winds at the jetty were:
000°
16.9 11.115.7 19.719 24.122.7 22.1 14.610.4 26.2 18.6
32.8 21.630.5 38.336.9 46.844.1 43 36.2 28.420.2 50.9
120° 270°060° 180°030° 150° 300° 330°090° 240°210°
WIND DIRECTION (T)
REPORTING
PERIOD
1-hour mean (kn)
1-hour mean (kn)
The third-party’s report did state that it was not possible for a hindcast model to “resolve highly modified 
local features.”
42. In December 2020, Joulon provided copies of the initial mooring plans (Rev. 00) for both VALARIS DS-4 and
ENSCO DS-8 to COL for their review. It was reported that COL initially had some reservations about the mooring
plans and considered engaging a third-party to review them and to propose any changes deemed necessary. 
COL subsequently determined that the drill ships’ mooring plans were adequate given their understanding that 
they had been developed by InterMoor based on the conditions at the Hunterston Jetty and that they had 
been approved by the drill ships’ flag State and insurers.
43. After reviewing the mooring plans, COL advised Joulon there was a 3-hour lead time for tug support at the jetty.
It was not reported when COL provided this information to Joulon or if this information was also provided to the
Masters of VALARIS DS-4 and ENSCO DS-8.
44. Neither the risk assessment, the emergency response plans, nor the weather contingency plans were revised based 
on the information provided by COL regarding the lead times for tugs.
45. On 8 December 2020, COL had the mooring bollards on the jetty re-tested and certified by an independent 
consultant to confirm their SWL.
46. On 24 December 2020, a contractual agreement between COL and Thanh Ngoc DMCC (Thanh Ngoc)27 
for VALARIS DS-4 and ENSCO DS-8 to be laid-up at Hunterston Jetty was signed. The agreement was for 
24 months.
47. The agreement included the following clauses addressing the drill ships’ manning:
(a) that details regarding the drill ships’ lay-up crew were to be provided to COL “before the commencement of
the Vessel lay-up;”
(b) that Thanh Ngoc would always keep marine operations crew available at the jetty; and
26 The source of this data was not reported.
27 Thanh Ngoc is a subsidiary company of Joulon. See http://thanh-ngoc.com.
Part 2: Findings of Fact

Page 23

19
(c) that COL and Thanh Ngoc agreed the drill ship manning would be “to levels approved by [the] Harbour
Master and in accordance with Applicable Laws.”28
48. The agreement also included a schedule containing copies of the original revisions of the mooring plans for both
VALARIS DS-4 and ENSCO DS-8, a schedule stipulating conditions for mooring, and an annex with a list of
documents that were to be provided for each of the laid-up drill ships.
49. The stated conditions for mooring VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty included, among other
things, that:29
(a) two anchors be used by each of the two drill ships;
(b) the drill ships be provided with adequate moorings; and
(c) that “a sufficient number of persons” are available to maintain an effective mooring watch and fire patrol.
50. The documents that were required to be provided included:
(a) mooring plans that had been approved by the drill ships’ P&I Club(s);
(b) risk assessments for the moorings;
(c) layout plans for the ships’ anchors;
(d) action plans for emergency situations, including fire, oil spill, and loss of onboard systems (e.g., power 
or communications);
(e) ships’ particulars;
(f) minimum manning in accordance with flag State policy and proof that the ships’ flag State is content with
reduced manning during laid-up period; and
(g) arrangements for immobilization of propulsion systems.
51. Based on the information available to the Administrator, it is not possible to establish if Joulon or Noah
provided COL with drawings of the drill ships and details of their mooring arrangements, which showed
that both VALARIS DS-4 and ENSCO DS-8 were equipped with only one anchor each, prior to providing
COL copies of the drill ships’ mooring plans. It is also not possible to establish when COL may have received 
copies of the drill ships’ contingency plans.
Lay-up at Hunterston Jetty
52. On 14 December 2020, ABS surveyors attended VALARIS DS-4 and ENSCO DS-8 to conduct reactivation 
surveys. Both drill ships were issued short term international statutory certificates30 that were valid through 
13 January 2021 and class certificates for a single voyage from Las Palmas to Hunterston.
28 The agreement defined Applicable Laws as “the laws of England and Wales and any other laws, bye laws or regulations (including health and safety regulations), 
internationally binding conventions, regulatory policies, directives, guidelines or industry codes (including the Vessel Regulations) which apply to the operation of the 
Vessels and Terminal and personnel there.”
29 The stated conditions also addressed issues related to compliance with orders that might be issued by the Harbour Master, compliance with pollution prevention 
requirements, ballasting, maintenance of safe access to the drill ships, and communications.
30 The following short term international certificates were issued to both drill ships: International Load Line Certificate, International Oil Pollution Prevention Certificate, 
International Air Pollution Prevention Certificate, Mobile Offshore Drilling Unit Safety Certificate (1989), and an International Sewage Pollution Prevention 
Certificate. As previously noted, the Safety Management Certificates held by both drill ships had remained valid since no intermediate audits had been required while 
the drill ships were in lay-up at Las Palmas.
Part 2: Findings of Fact

Page 24

Republic of  the Marshall Islands Maritime Administrator
20
53. The Administrator issued a Provisional Certificate of Registry with an endorsement for a single voyage in 
ballast from Las Palmas to Hunterston to ENSCO DS-8 on 15 December 2020 and to VALARIS DS-4 on 
17 December 2020.
54. On 23 December 2020, a pre-arrival meeting involving COL, Joulon, and the Masters of VALARIS DS-4 and 
ENSCO DS-8 was conducted. It was reported that during the meeting the drill ships’ Masters asked for some
additional survey information for the locations where each drill ships’ anchor was planned to be dropped when 
they arrived at Hunterston Jetty. COL provided the requested information after the meeting was completed.
55. VALARIS DS-4 arrived at Hunterston Jetty on 27 December 2020. Prior to berthing, the drill ship’s anchor 
was dropped to the northeast of the jetty so that it would be about 35° off its starboard bow once the drill ship was
moored alongside. The drill ship then laid out 10 shackles of anchor chain while maneuvering alongside the jetty.
56. ENSCO DS-8 arrived at Hunterston Jetty on 28 December 2020. The drill ship’s anchor was dropped to the 
southeast of the jetty so it would be 45° off the port bow and then 12 shackles of anchor chain were laid out as it
maneuvered alongside the jetty.
57. It was reported that both VALARIS DS-4 and ENSCO DS-8 were then moored using additional lines and that 
some lines were made up to different connection points than those specified by the mooring plans developed by
InterMoor. Compliance with the mooring plan was not verified by the drill ships’ Masters, InterMoor, COL, or 
any other third-party. There is no available documentation recording the length of each of the mooring lines.
58. VALARIS DS-4 was moored starboard side to at the northeast end of the jetty with the bow extending past the
dolphin. ENSCO DS-8 was moored port side to at the southwest end of the jetty.
59. It was reported that the Masters of VALARIS DS-4 and ENSCO DS-8, during the transit from Las Palmas to
Hunterston, had expressed some concerns regarding the drill ships’ mooring plans to the pilot who was on board
when they were moored at the Hunterston Jetty. The concerns that the pilot reported to COL were related to the high
windage of the drill ships and included that the Masters would:
(a) normally plan on using the thrusters to supplement the moorings when the winds were from some relative
directions31 more than 18 kn; and
(b) typically depart the berth when the winds were above 25-30 kn and shift to safe water until the wind speeds
were lower.
It is not known if the Masters of the laid-up drill ships, who had also been on board during the transit from Las
Palmas, had similar concerns, or if they discussed this with Joulon or Noah.
60. It was also reported that the pilot advised the Masters of the laid-up drill ships regarding the need to ensure their
moorings were well maintained, particularly when easterly winds were forecast. The pilot was reported to have 
told the Masters that the actual velocity of winds from the east is typically higher than what was forecast.
Lastly, the pilot advised that there were no tugs in the immediate vicinity and a 6-hour notice was required 
for normal assistance. It is not known if Joulon or Noah were made aware of this information.
31 It was not reported what these relative directions were.
Part 2: Findings of Fact

Page 25

21
61. On 28 December 2020, United Kingdom Maritime and Coastguard Agency (MCA) inspectors attended 
VALARIS DS-4 and ENSCO DS-8 to conduct a port State control inspection on both drill ships. It was reported 
that both drill ships had a full marine crew32 on board when the inspections were conducted. The available
documentation for these inspections provides no indication that VALARIS DS-4 and ENSCO DS-8 were going 
to be placed in lay-up at Hunterston Jetty. Both inspection reports included an observation noting that they had 
been in lay-up at Las Palmas to explain why they held short term certificates.33 A deficiency was issued to ENSCO
DS-8 requiring that surveys for full-term certificates be conducted prior to departure.34 A similar deficiency was not
issued to VALARIS DS-4.35
62. On 28 December 2020, management of VALARIS DS-4 was transferred from Ensco to Joulon and Noah and the 
drill ship was placed into lay-up.
63. Concurrent with the change of management, there was a handover from the crewmembers who had been on board
for the transit from Las Palmas to the lay-up crew hired by Noah. The VALARIS DS-4 lay-up crew consisted of 
a Master, C/E, ETO, two ASDs, and two Oilers/Motormen. A Project Manager and Project Technician hired 
by Joulon were also on board.
64. On 29 December 2020, ENSCO DS-8 was also placed in lay-up after management was transferred from Ensco
to Joulon and Noah along with a handover from the transit crew to the lay-up crew. The lay-up crew consisted of 
a Master, C/E, ETO, two ASDs, and Motorman hired by Noah Ship Management, as well as an Operations 
Engineer, two Project Engineers, and a Technical Assistant hired by Joulon.
65. Based on the drill ships’ logs, the daily routine on board both VALARIS DS-4 and ENSCO DS-8, from the time 
that they entered lay-up, included checking and adjusting the mooring lines at least once a day. It could not be 
verified if the lines were adjusted to maintain the lengths specified in the InterMoor mooring plans or if this was to
prevent them from going slack per customary practice.
66. Following the VALARIS DS-4’s and ENSCO DS-8’s arrival at Hunterston Jetty, one main diesel generator and 
two thrusters on each drill ship were to be kept ready for use. Their other five main diesel generators and four
thrusters were placed into cold iron.
67. Both drill ships were fitted with a 220 V deck generator that provided power to the Accommodations and essential
services, such as the mooring winches and fire pumps. If the thrusters needed to be placed in standby or online, it
was necessary to switch over to one of the drill ships’ permanently installed 440 V diesel generators. The changeover 
was not automatic and required the drill ship be blacked out until a 440 V generator assumed the load.
32 Based on the MSMC issued by the Administrator, the minimum marine crew for both drill ships included a Master, C/O, two 3/Os, three ASDs, two OSs, C/E, 1 A/E, 
two 3 A/Es, and three Oilers/Motormen or ASE.
33 The following short term international certificates had been issued to both drill ships before they departed Las Palmas: International Load Line Certificate, International 
Oil Pollution Prevention Certificate, International Air Pollution Prevention Certificate, Mobile Offshore Drilling Unit Safety Certificate (1989), and an 
International Sewage Pollution Prevention Certificate. The certificates issued to both drill ships were valid through 13 January 2021. ENSCO DS-8 had also been issued 
interim Safety Management Certificate by Bureau Veritas since the drill ship’s full-term certificate expired on 14 December 2020 and a renewal audit had not been 
conducted while it was in lay-up. The Safety Management Certificate held by VALARIS DS-4 had been issued on 23 March 2020 and was valid through 17 July 2023.
34 ENSCO DS-8 was also issued a deficiency for an inoperable rescue boat that was required to be rectified prior to departure.
35 VALARIS DS-4 was issued three deficiencies for the emergency lighting for the Engine Room escape not working, the line throwing apparatus being expired, and the 
rescue boat not being operational. All three were required to be rectified prior to departure.
Part 2: Findings of Fact

Page 26

Republic of  the Marshall Islands Maritime Administrator
22
68. On 4 January 2021, Joulon updated the weather contingency plans for both drill ships based on comments from the
Master of VALARIS DS-4 regarding the potential impact of winds from the northeast. The plans were revised to
require that:
(a) when winds of 40 kn or more from the northeast to east were forecast, the crew should be on standby, the drill
ship’s diesel generator started, and the thrusters placed on standby; and
(b) when the winds were 50 kn or more from the northeast to east that two thrusters be engaged.
69. On 4 January 2021, based on the owner’s notification that VALARIS DS-4 and ENSCO DS-8 were safely moored 
at Hunterston Jetty, ABS changed the status of both drill ships to laid-up, without additional qualification.36 The 
effective date of the change of status was 28 December 2020 for VALARIS DS-4 and 29 December 2020 for 
ENSCO DS-8.
70. On 14 January 2021, the drill ships’ owners informed the Administrator that VALARIS DS-4 and ENSCO DS-8 
were in lay-up at Hunterston Jetty and requested that a Provisional Certificate of Registry in Laid-up Status be 
issued to each of the drill ships. These certificates were issued that same day.37
Weather Information
71. The Masters of VALARIS DS-4 and ENSCO DS-8 had access to the Meteorological (Met) Office’s inshore and
shipping forecasts38 and its local weather forecasts for Hunterston and the surrounding area. The inshore forecast
included the Firth of Clyde.39
72. Both drill ships also had functioning anemometers mounted on the port and starboard sides of the mainmast, which
is above the Bridge.
VALARIS DS-4 Partial Loss of Moorings on 13 January 2021
73. On the evening of 13 January 2021, the winds were from the northeast at 20-25 kn with gusts of 30 kn.40
74. Between about 2115–2230, VALARIS DS-4 was reported to be yawing on the jetty with the forward third of the
drill ship moving as far as 12-15 m away from the jetty. This caused the gangway to pull off the jetty and hang over 
the drill ship’s side.
75. It was reported that line No. 841 had parted. Although the remaining mooring lines remained intact, they were all
reported to have slipped as much as 4-5 m on the bollards.
76. The initial efforts to start the drill ship’s diesel generators so the thrusters could be brought online were not successful
and at 0028 on 14 January 2021, the Master contacted the port and requested tug assistance. He was informed that
tugs would not be on scene until 0600.
36 The notification was provided in an email to ABS that was sent on 30 December 2021.
37 The certificate for ENSCO DS-8 was dated 13 January 2021. This was because the Provisional Certificate of Registry that had been issued for the voyage from Las 
Palmas to Hunterston expired on that date.
38 The inshore forecast was for coastal waters extending up to 12 NM from shore whereas the shipping forecast included offshore waters.
39 The Firth of Clyde is the mouth of the River Clyde. Hunterston is located in this area.
40 Based on the drill ships’ deck logs, there had previously been winds of 20 knots from the northeast on 4 January 2020.
41 Line No. 8 was a 30 mm UHMWPE forward spring line.
Part 2: Findings of Fact

Page 27

23
77. Sometime after VALARIS DS-4 had stopped yawing, the engineers were able to start a diesel generator and bring 
the thrusters online. The Master then brought VALARIS DS-4 back alongside the jetty. Once alongside, the drill
ship’s crewmembers adjusted the mooring lines.
78. At 0139, the port was informed that the drill ship’s thrusters had been started and that tug assistance was no 
longer required.
79. Later in the day, COL conducted an inspection of VALARIS DS-4’s moorings. During this inspection they observed
that some of the lines appeared to have been damaged because of drill ship’s movement during the recent easterly
winds, that some of the lines appeared to not have been properly made fast on the drill ship’s bits, and that several 
of the mooring lines were slack.
80. On 15 January 2021, COL held a remote meeting with Joulon and Noah. It was reported that this included
a discussion of the observations made during COL’s inspection of the moorings. COL also questioned whether 
the drill ship’s mooring lines were the proper size. Following the meeting, COL produced a written inspection 
report with recommendations that was shared with Joulon and the Master of VALARIS DS-4.
Shift of VALARIS DS-4 and ENSCO DS-8
81. After meeting with COL, Joulon, and Noah decided to shift VALARIS DS-4 and ENSCO DS-8 to the southwest 
along the berth. Joulon also contracted InterMoor to conduct an analysis to determine the likely cause for 
VALARIS DS-4’s mooring line No. 8 parting and to develop a revised mooring plan. They also decided to replace 
all of VALARIS DS-4’s mooring lines with 42 mm and 48 mm diameter UHMWPE lines.
82. InterMoor determined that the likely cause of VALARIS DS-4’s Line No. 8 parting was that less line had been paid
out from the fairlead than was specified by the mooring plan.
83. Ahead of the planned move, a planning meeting involving the drill ships’ Masters, pilots, Joulon, and COL was 
held to discuss the sequence for how the move would be conducted and related safety issues.
84. Between 24-25 January 2021, VALARIS DS-4 was shifted 27 m and ENSCO DS-8 was shifted 10 m to the southwest
along the jetty and re-moored. After being re-moored, VALARIS DS-4’s bow did not extend past the dolphin at the
northeast end of the jetty.
85. The revised mooring plan InterMoor developed for VALARIS DS-4 specified that the drill ship be moored with 12 
42 mm and four 48 mm UHMWPE lines plus the anchor. Two of the 48 mm lines led aft from bits located 
amidships and starboard quarter. The other two 48 mm lines were used as stern lines.
86. It was reported that when VALARIS DS-4 was re-moored, some of the lines included in the revised mooring 
plan were made up to different connection points than specified by the plan. It was also reported that one 
additional line was installed at the drill ship’s bow and that two additional lines were installed at the stern. There is
no available documentation recording the actual length of the mooring lines when VALARIS DS-4 was re-moored.
87. The revised mooring plan InterMoor developed for ENSCO DS-8 specified that the drill ship be re-moored with 13 
40 mm and four 42 mm diameter UHMWPE lines plus the anchor.
Part 2: Findings of Fact

Page 28

Republic of  the Marshall Islands Maritime Administrator
24
88. It was reported that when ENSCO DS-8 was re-moored, some of the lines were made up to different connection
points than identified in the mooring plan developed by InterMoor. It was also reported that an additional 42 mm
diameter line was installed as a forward breast line. There is no available documentation recording the actual 
length of the mooring lines when ENSCO DS-8 was re-moored.
89. Compliance of the mooring arrangements with the mooring plans was not verified by any third-party on behalf of 
the drill ships’ managers or the port.
90. Based on the drill ships’ logs, the crewmembers continued to monitor and adjust the mooring lines each day. It 
could not be verified if the lines were adjusted to maintain the lengths specified in the mooring plans developed 
by InterMoor or if this was to prevent them from going slack.
91. Neither the owner, Joulon, nor Noah informed the Administrator of VALARIS DS-4’s partial loss of moorings 
as required by the Republic of the Marshall Islands Maritime Regulations (MI-108) (the “Maritime Regulations”), 
section 6.36.42
Availability of Diesel Generators and Thrusters
92. By mid-January 2021, the engineers on VALARIS DS-4 and ENSCO DS-8 were reported to have difficulty 
starting the diesel generators and thrusters on both drill ships due to inadequate preheating of the lube oil and 
jacket water for both the diesel generators and thrusters. There was also inadequate heating for the fuel oil 
purifiers. It was additionally reported that there were water leaks on the thrusters.
93. It was determined that these problems were related to the temperatures during this period, which generally 
were between -1 and 2°C, and that the 220 V deck generators on both drill ships could not provide sufficient 
power for the preheaters. In addition, it was also not possible to provide power to the feeder panel for thrusters 
Nos. 1-3 on both drill ships without switching over to the diesel generators.
94. Throughout January 2021, the engineers and Joulon technicians on VALARIS DS-4 and ENSCO DS-8 worked 
to identify a solution so that the diesel generators and thrusters could be placed online if needed.
95. On 30 January 2021, the Master of ENSCO DS-8 sent an email to Noah reporting that in an emergency they would
need to request tug assistance since the drill ship’s thrusters were not available for use. He also reported that they 
required weather forecasts that were more accurate. Noah responded by stating that the issue with the diesel
generators and thrusters needed to be resolved as soon as possible. Based on the records and information available 
to the Administrator, the Master of VALARIS DS-4 did not make any similar reports to Noah.
96. On 1 February 2021, the C/E on board ENSCO DS-8 sent an email to Joulon reporting that the cold weather 
(0°C) was making it difficult to preheat the jacket water and lube oil for diesel generator No. 4 using only 
one heating element.43 The C/E stated that they planned to turn off the preheater for the deck crane so that a 
second heating element could be turned on to better preheat the jacket water and lube oil for diesel generator No. 4.44
42 The Administrator was first made aware of this marine incident by the United Kingdom MCA on 12 February 2021.
43 It was planned to start this diesel generator to operate a deck crane.
44 The preheating system was designed to use five heating elements.
Part 2: Findings of Fact

Page 29

25
97. By the morning of 2 February 2021, the jacket water temperature had reached 60°C, which was the minimum
temperature for starting the diesel generator. By contrast, the lube oil temperature was between 21-33°C. It was
supposed to be not less than 40°C. The C/E advised Joulon that preheating the lube oil more efficiently would require
running the pre-lube oil pump continuously, but that they did not have sufficient electrical power to do this.
Weather 29 January 2021 to 1 February 2021
98. Between 29 January 2021 to 1 February 2021, both drill ships were reporting winds from the northeast between 
20-30 kn with some higher gusts. In the email that ENSCO DS-8’s Master sent Noah on 30 January 2021, it was
reported that gusts up to 55 kn had been observed. It also stated that based on the Met Office forecast that had 
been provided by Peel Ports, the winds had been expected to be from the northeast at 15 kn with gusts of 
20-25 kn. Based on the URL the Master included in the email, the reference was to the Met Office local forecast 
for Hunterston and the surrounding area.
99. The Met Office inshore forecasts for the period predicted that the winds would generally be from the northeast to
southeast between Beaufort Force 4-5 (11-21 kn) with occasional periods of Beaufort Force 6-8 (22-40 kn).
100. Local pilots and tug operators subsequently reported that easterly winds at the Hunterston Jetty can exceed the
forecast by up to 10 kn and that gusts can be as much as 15 kn higher than was forecast.
Loss of Moorings on 2 February 2021
101. Based on the Met Office inshore weather forecast issued at 0001 UTC on 2 February 2021, the forecast for the 
next 24 hours was for winds from the east to southeast between Beaufort Force 5-7 (17-33 kn) with periods of
Beaufort Force 8 (34-40 kn). Forecasts issued later in the day were for easterly winds of similar force.
102. Based on VALARIS DS-4’s Noon Report for 2 February 2021, the observed winds were from the northeast at 
25 kn with gusts between 45-53 kn. It was reported that the mooring lines and gangway were being checked due 
to the high gusts and that the drill ship was being prepared for the upcoming days of forecast high winds coming 
off the shore.45
103. ENSCO DS-8’s Noon Report indicated that winds from the east at 30-35 kn with gusts of 40-50 kn had been
recorded. It was also reported that the mooring lines were being adjusted as necessary and that diesel generators 
Nos. 3 and 4 were being preheated.
104. Based on the drill ships’ logs, the wind speed increased throughout the day. At 1600, VALARIS DS-4 reported
northeast winds of 50 kn. The storm force winds continued, and at 1830, it was reported that the winds were 55 kn.46
105. By 1720, ENSCO DS-8’s diesel generator No. 3 had been started and the drill ship’s power had been swapped from 
the portable deck generator.
106. At 1845, VALARIS DS-4’s Master, C/E, and ASD on duty reported hearing a noise that they thought sounded like 
the anchor chain. It was reported that the wind speed was about 70 kn.47 When the Master and ASD went on 
45 It was not reported if these actions included trying to make any of the diesel generators and thrusters ready to start.
46 Winds of 48-55 knots are Beaufort Force 10.
47 It was not reported if this was a gust or sustained speed.
Part 2: Findings of Fact

Page 30

Republic of  the Marshall Islands Maritime Administrator
26
deck to investigate, they observed that several of the forward mooring lines had parted, and that the drill ship was 
moving away from the jetty.
107. VALARIS DS-4’s C/E went to the Engine Room to start a diesel generator and to prepare thruster No. 5.
108. Based on AIS information, by about 1915, all of the drill ship’s forward mooring lines had parted. Within the next
2-3 minutes, the remaining mooring lines had parted. The drill ship was blown off the jetty and started drifting to 
the southwest at about 2 kn.
109. About when VALARIS DS-4 started drifting away from the jetty, the Master made an announcement on the 
drill ship’s PA system directing all crewmembers to muster on the Bridge. The C/E left the Engine Room and went 
to the Bridge.
110. It was reported that the diesel generator the C/E had started stopped running a short time after he left the 
Engine Room.
111. At 1915, the Master of VALARIS DS-4 broadcast a MAYDAY by VHF.
112. Based on AIS information, at about 1923, the anchor held. By this time, VALARIS DS-4 had drifted approximately
halfway across the channel between the jetty and Great Cumbrae Island, which was about 400 m to the west.
113. At about 1920, the Master of ENSCO DS-8 called the Harbor Master to request tug assistance. He also notified 
Noah, Joulon, Peel Ports, and the MCA.
114. Following VALARIS DS-4’s loss of moorings and reported inability to start the diesel generators and thrusters, the
MCA mobilized equipment for a Tier 3 oil spill response in case the drill ship went aground.
115. At 2040, the first tug arrived with a pilot on board. After determining that VALARIS DS-4 was not dragging 
anchor, the pilot directed the tug to go alongside ENSCO DS-8 and help hold the drill ship alongside the jetty. A 
second tug arrived on scene at 2040 and also started pushing ENSCO DS-8.
116. At 2204, ENSCO DS-8’s gangway was pulled off the jetty when the drill ship was struck by a gust of 60-70 kn.
117. A third tug arrived at 2310 and started pushing on ENSCO DS-8.
118. At 0530 on 3 February 2021, a fourth tug arrived and also was used to help hold ENSCO DS-8 alongside the jetty.
119. Throughout the day, both drill ships were reporting the winds to be from the east northeast. VALARIS DS-4, which
remained at anchor halfway across the channel between the jetty and Great Cumbrae Island, reported winds of 
30 kn with gusts of 45-50 kn. ENSCO DS-8 reported winds of 40-45 kn with gusts of 50-60 kn. The forecast 
was for winds from the east 30-35 kn with gusts of 45-55 kn.
120. By noon on 3 February 2021, VALARIS DS-4’s diesel generator No. 3 and thruster No. 2 had been started and 
were online. Efforts to start thruster No. 5 were not successful.48 ENSCO DS-8’s diesel generators Nos. 3
and 4 were online and thrusters Nos. 3, 5, and 6 were being preheated. These thrusters were started by noon on 
4 February 2021 and were being used to help hold the drill ship alongside the jetty.
48 Thrusters Nos. 2 and 5 were the two thrusters that had been designated to be started. It was reported that both had been successfully tested before the temperatures 
dropped to between -1 and 2°C in mid-January 2021.
Part 2: Findings of Fact

Page 31

27
121. From 4-5 February 2021, the crewmembers on board VALARIS DS-4, with remote assistance from service 
technicians from the manufacturers of the thrusters and the thruster control system, continued their efforts to 
determine why thruster No. 5 could not be started. During this period, tugs were pushing on the drill ship’s stern
to relieve pressure on the anchor chain. The number of tugs that were pushing at any one time varied between 
one and two.
122. The weather began to improve over the course of the next several days. The winds continued to be from the 
northeast but at 15-30 kn with gusts of 45-50 kn. By 6 February 2021, the winds had shifted to the east at 20 kn.
123. On 6 February 2021, service technicians from the manufacturers of the thrusters and the thruster control system
embarked VALARIS DS-4 to assist the crewmembers as they continued their efforts to troubleshoot the thrusters. 
It was reported that the issues that prevented the thrusters from being started included electrical faults and low
cooling water pressure due to leaking hoses.
124. During the day on 7 February 2021, most of the issues with the VALARIS DS-4’s thrusters were resolved and
thrusters Nos. 1-4 and No. 6 were operational. Thruster No. 5 remained non-operational due to the failure of some
diodes in the thruster’s control system.
125. At 1500, the Master of ENSCO DS-8 released the tugs on 30-minute notice after receiving permission from the
MCA. By this time, the winds were from the north at 10 kn with gusts up to 15 kn.
126. On the morning of 8 February 2021, the MCA granted permission for VALARIS DS-4 to return to the jetty. By 1700,
the drill ship was moored alongside the jetty.
Crew on Board VALARIS DS-4 and ENSCO DS-8
127. On 17 November 2020, while planning for the continued lay-up of VALARIS DS-4 and ENSCO DS-8 at
another Spanish port or at Hunterston, Noah informed the Administrator that they intended to maintain the
drill ships’ current manning, which consisted of a navigating officer, an engineering officer, an ETO, and
three ratings. The Administrator replied by stating that per Marine Guideline No. 1-11-1, Lay-Up of Vessels 
(MG 1-11-1),49 the manning level while the drill ships were in lay-up should be developed in coordination with the 
port or coastal State authorities and the drill ships’ P&I Club.50
128. On 20 November 2020, Ensco, who was then the drill ships’ manager, requested that the Administrator issue a
letter accepting their proposed manning for VALARIS DS-4, ENSCO DS-8, and five other drill ships while they
were in lay-up. It was proposed that each drill ship would have a five-person marine crew who held the required
STCW endorsements for their position on board and a two-person maintenance crew. The marine crew would 
consist of a Master, one OICNW, two ASDs/OSs, and one C/E or 2/E. The request did not state where the drill ships 
would be laid-up.51
129. The Administrator issued letters on 23 November 2020 stating there was no objection to the manning proposed
by Ensco for VALARIS DS-4, ENSCO DS-8, and the five other drill ships while they were in lay-up at Las
49 MG 1-11-1 is discussed later in the report.
50 The MSMCs that had previously been issued by the Administrator to VALARIS DS-4 and ENSCO DS-8 in accordance with SOLAS regulation V/14 were not 
applicable since the drill ships were out of service. Per SOLAS regulations V/14.2 and I/1(a), the MSMCs would be applicable when the drill ships departed Hunterston 
after coming out of lay-up.
51 Ensco had not submitted a similar request to the Administrator before VALARIS DS-4 and ENSCO DS-8 entered lay-up in May 2020.
Part 2: Findings of Fact

Page 32

Republic of  the Marshall Islands Maritime Administrator
28
Palmas. Each of the letters also stated that “the manning level, however, must be in compliance with all local
regulations and Administrator guidelines, and must be adequate to ensure the safety and security of the vessel 
and crew, and the protection of the marine environment.”
130. COL reported they had not been made aware of the specific number of crewmembers on board VALARIS DS-4
and ENSCO DS-8 while they were in lay-up before the drill ships arrived at Hunterston Jetty. COL also stated 
they first became aware of the Administrator’s requirement that the drill ships’ manning be approved by the port
authorities at the lay-up location sometime after 9 February 2021.
131. When the loss of moorings occurred on 2 February 2021, VALARIS DS-4 had a marine crew of six, along with a
project manager and technician on board. Each member of the marine crew held either a certificate of competence
or proficiency issued by their national administration. The Master held valid seafarer documentation issued by 
the Republic of the Marshall Islands for his position on board.52
132. The experience of the marine crew on board VALARIS DS-4 prior to 2 February 2021:
Rank Time On Board
VALARIS DS-4 Time in Rank Time with Company
Master 2 months 11 years 2 years
C/E 2 months 20 years 1 month
ETO 2 months 7 years, 1 month 2 months
ASD1 4 days 2 years, 15 days 4 days
ASD2 4 days 2 years, 15 days 4 days
Oiler 21 days 1 year, 2 months 21 days
133. On 2 February 2021, there was a marine crew of six, an operations engineer, two project engineers, and a technical
assistant on board ENSCO DS-8. Each member of the marine crew held either a certificate of competence or 
proficiency issued by their national administration. The Oiler held valid seafarer documentation issued by the
Republic of the Marshall Islands appropriate for his position on board.53
134. The experience of the marine crew on board ENSCO DS-8 prior to 2 February 2021:
Rank Time on Board
ENSCO DS-8 Time in Rank Time with Company
Master 2 months 1 year, 10 months 2 months
C/E 2 months 9 years 2 months
ETO 2 months 3 years, 4 months 2 months
ASD1 23 days 12 years, 6 months 23 days
ASD2 8 days 11 months 8 days
Oiler 4 days 1 year, 8 months 4 days
52 Because VALARIS DS-4 was out of service while holding a Provisional Certificate of Registry with the endorsement “This Certificate is Only Valid while the Vessel 
Remains in Laid-up Status and is Not Valid for Navigation,” the vessel was not in service as defined in STCW and therefore the crew were not required to hold Republic 
of the Marshall Islands’ seafarer documentation.
53 As noted previously, because ENSCO DS-8 held a Provisional Certificate of Registry with the endorsement “This Certificate is Only Valid while the Vessel Remains in 
Laid-Up Status and is Not Valid for Navigation,” the drill ship was not in service as defined in STCW and therefore the crew were not required to hold Republic of the 
Marshall Islands’ seafarer documentation.
Part 2: Findings of Fact

Page 33

29
135. VALARIS DS-4’s and ENSCO DS-8’s Master, C/E, and ETO had all signed on board the drill ships at Las Palmas 
in early December 2020. They remained on board for familiarization during the drill ships’ voyages to Hunterston.
136. The tonnage endorsements on the national certificates of competency held by the Masters were appropriate to work 
as Master on board VALARIS DS-4 and ENSCO DS-8. Both held the qualifications required to serve as a DP
operator on all three classes of DP vessels. 54
137. The C/E on board VALARIS DS-4 held a certificate of competency authorizing him to work as a C/E on vessels 
with up to 3,000 kW propulsion power.55 The certificate of competency held by the C/E on board ENSCO DS-8
authorized him to work as a C/E on board vessels with 3,000 kW or more propulsive power.56
138. The ETOs had extensive documented service on board DP equipped vessels before they signed on VALARIS DS-4
and ENSCO DS-8.
MCA Inspections
139. On 9 February 2021, MCA inspectors attended ENSCO DS-8 and issued improvement notices addressing:
(a) the drill ship’s moorings;
(b) that routine maintenance and inspection of fire fighting equipment and lifesaving appliances were not 
being conducted;
(c) that instructions and procedures related to the drill ship’s laid-up status were not available to the 
crewmembers; and
(d) the quality of the food on board.
A requirement to provide confirmation that the installation of the portable deck generator met the applicable
requirements was also issued.
They also issued a deficiency addressing the drill ship’s manning, based on the equipment that was being operated 
at the time of the inspection57 and a prohibition notice to prevent the drill ship from proceeding to sea until it held
valid applicable international certificates.58
140. On 10 February 2021, MCA inspectors conducted an inspection on board VALARIS DS-4. The deficiencies
documented by the attending inspectors were similar to those that were issued to ENSCO DS-8. The improvement
notices that were issued also addressed the same issues that were addressed in the notices that were issued to 
ENSCO DS-8. An additional improvement notice was issued that addressed that the deck crane used for taking 
on stores and equipment while the drill ship was moored to the jetty did not have valid certification. A prohibition 
notice to prevent VALARIS DS-4 from proceeding to sea without valid applicable certificates was also issued.59
54 See IMO Circular MSC.1/Circ.1580, Guidelines for Vessels and Units with Dynamic Positioning (DP) Systems.
55 Based on the MSMC issued by the Administrator, VALARIS DS-4 had a total propulsive power of 48,000 kW. As previously noted, the requirements of this certificate 
were not applicable since the drill ship held a Provisional Certificate of Registry with the endorsement “The Certificate is Only Valid while the Vessels Remains in 
Laid-Up Status and is Not Valid for Navigation.”
56 Based on the International Air Pollution Prevention Supplement issued by ABS, ENSCO DS-8 had a total propulsive power of 43,740 kW.
57 No action was taken by the MCA since there was not any legislation addressing manning of drill ships in lay-up.
58 As previously discussed, ENSCO DS-8’s international certificates expired on 13 January 2021, after the drill ship entered lay-up. Additional deficiencies related to the 
marine crew’s seafarer employment agreements and catering were also issued.
59 The international certificates held by VALARIS DS-4 had also expired on 13 January 2021.
Part 2: Findings of Fact

Page 34

Republic of  the Marshall Islands Maritime Administrator
30
ABS Guidance for Lay-up of MODUs60
141. The ABS Guide for Lay-up and Reactivation of Mobile Offshore Drilling Units (2017) (the “ABS Lay-up Guide”) 
provides guidelines for owners that address issues related to the preservation and protection of a laid-up vessel. 
It includes three basic conditions:61
(a) Laid-up: The vessel is out of service for an undetermined length of time and ABS has not reviewed lay-
up procedures that may have been prepared by the vessel’s owner or operator. All class surveys are held in
abeyance and statutory surveys are completed only if required by the vessel’s flag State. An initial lay-up
survey and annual surveys are not required. A reactivation survey, including all due and overdue class and
statutory surveys, is required before the vessel returns to operation.
(b) Laid-up Warm Stacked: The vessel is not in operation and is positioned in a sheltered location with a crew
on board to carry out maintenance and preservation activities per the lay-up procedures reviewed by ABS.62 
If requested, ABS will also conduct an engineering review of the mooring plan and will also conduct a
mooring survey. All class surveys are held in abeyance and statutory surveys are completed only if required
by the vessel’s flag State. An initial lay-up survey and annual surveys are required to be completed. A
reactivation survey, including all due and overdue class and statutory surveys, is required before the 
vessel returns to operation.
(c) Laid-up Cold Stacked: The only difference between this condition and Laid-up Warm Stacked is that the
vessel is not manned. The requirements for ABS to review the lay-up plan and the survey requirements 
are the same as Laid-up Warm Stacked.
142. In addition to the three basic conditions, the ABS guidance includes two enhanced conditions that are intended to
assist with managing the asset by minimizing risk exposure while also reducing the time and cost of reactivation.
These two conditions are:
(a) Enhanced Laid-up Warm Stacked; and
(b) Enhanced Laid-up Cold Stacked.
The difference between these two conditions is that a cold stacked vessel is not manned. In addition to the 
requirements for a vessel that is Laid-up Warm Stacked or Cold Stacked, ABS will review the proposed lay-up 
location, the planned mooring arrangements, the location specific risk assessment, and emergency response
capabilities in the area when a vessel is placed in either of these conditions.63 ABS will also conduct a mooring
survey once the vessel is on location.
143. A vessel owner or operator is required to inform ABS when placing a vessel into lay-up to keep it in class. It is for
the owner or operator to decide the lay-up condition for the vessel.
60 A MODU is a vessel capable of engaging in drilling operations for the exploration for or exploitation of resources beneath the seabed such as liquid or gaseous 
hydrocarbons, sulphur, or salt. See the 1989 MODU Code, paragraph 1.3.1. These include drill ships such as VALARIS DS-4 and ENSCO DS-8.
61 See ABS Lay-up Guide, Section 1. It is noted that other Classification Societies also have guidelines for placing vessels in lay-up.
62 Guidance regarding the scope and content of the lay-up procedures is provided in the ABS Lay-up Guide, Section 2.
63 Guidance addressing these issues is provided in the ABS Lay-up Guide, Section 3.
Part 2: Findings of Fact

Page 35

31
Flag State Requirements
144. The Republic of the Marshall Islands Maritime Act 1990 (MI-107) (the “Maritime Act”), section 214 establishes
requirements for issuing a Provisional Certificate of Registry to a vessel. These include requirements for the owner
to provide evidence that the vessel is in a seaworthy condition and the owner holds third-party liability insurance
providing, at a minimum, coverage for pollution liability and shipwreck removal.
145. The Republic of the Marshall Islands Vessel Registration and Mortgage Recording Procedures (MI-100), 
chapter III, section 4,64 issued by the Administrator addresses the registration of vessels that have been taken out
of service and are moored for a prolonged period. Provisional Certificates of Registry issued to laid-up vessels can
be issued for up to one year and are required to have the following endorsement: “This Certificate is Only Valid 
while the Vessel Remains in Laid-up Status and is Not Valid for Navigation.”
146. A vessel holding a Provisional Certificate of Registry with the endorsement “This Certificate is Only Valid while
the Vessels Remains in Laid-up Status and is Not Valid for Navigation” is not “in service” as defined in STCW and
is therefore not required to comply with the international and national seafarer’s documentation requirements that
would otherwise be applicable to the vessel when in service.
147. An owner wanting to register a vessel in a laid-up status must provide a statement from the vessel’s Classification
Society indicating that if it were surveyed when entering lay-up, it would meet the requirements for a classification
and tonnage measurement certificates. The owner is also required to, among other things, provide proof of liability
insurance and a notarized statement that the vessel will not be moved or navigated while out of class.65
148. The Maritime Regulations, section 5.34.2, require that vessels undergo an initial safety inspection before returning
to service “at the end of an official lay-up period.” Section 5.34.3 of these regulations exempt vessels that are in 
an official lay-up period from annual safety inspections while laid up.
149. The Administrator’s guidance in MG-1-11-1 identifies issues a vessel owner or operator should consider along with
recommended procedures for vessels entering, in, and coming out of lay-up.66
150. This guideline recommends that when planning to place a vessel in lay-up that the vessel owner develop lay-up
procedures that at a minimum address:
(a) vessel manning;
(b) firefighting, lifesaving, stability and watertight integrity;
(c) pre-lay-up preservation measures;
(d) maintenance while in lay-up;
(e) whether Classification Society and statutory certificates will be maintained; and
(f) contingency measures in case of emergencies while the vessel is laid-up.
64 The reference is to the June 2018 revision of the Vessel Registration and Mortgage Recording Procedures, which was the revision in effect on 2 February 2021. The 
Administrator revised and reissued this document under the title Vessel Registration and Instrument Recording in April of 2022.
65 The other required documents pertain to the vessel’s ownership and registration (if not currently registered in the Republic of the Marshall Islands).
66 It is noted that this document does not have the force of regulation.
Part 2: Findings of Fact

Page 36

Republic of  the Marshall Islands Maritime Administrator
32
Vessel owners are advised to seek assistance from the vessel’s Classification Society when preparing the lay-up
procedures.
151. Vessel owners are also advised to contact the local port and coastal State authorities to determine if there are any
specific requirements or regulations that may be applicable while the vessel is moored or anchored at the planned
lay-up location and that should be addressed in the lay-up procedures.
152. The Administrator’s guidelines include additional recommendations addressing vessel manning, maintenance, safety
and security, and pollution.
(a) Manning – Vessel owners are assigned responsibility for ensuring that the vessel’s manning is sufficient to
ensure:
(i) the safety and security of the vessel;
(ii) that the vessel is maintained; and
(iii) that it does not become a pollution risk.
It is recommended that the manning be developed in coordination with the port or coastal State authorities
and the vessel’s P&I Club. It is also recommended that if the vessel will not be manned, that all parties are
informed and that the lay-up procedures reflect this.
(b) Maintenance – Vessel owners are responsible for ensuring that the vessel’s basic structural and watertight
integrity, stability, and essential machinery and systems are properly maintained while in lay-up so that it does
not pose a safety or pollution risk.
(c) Safety and security – Vessel owners are advised to keep in place portions of the vessel’s Ship Security Plan
along with any local requirements to ensure the safety of the vessel.67 They are also advised that systems
required for crew comfort and safety are adequate for the number of persons who will be on board and are
both operational and ready for use in normal and emergency situations.
(d) Pollution – Vessel owners are assigned the responsibility of ensuring that the vessel does not present
any pollution hazards while in lay-up. They are also advised that the vessel is subject to any MARPOL
requirements that would apply if it were in active service, along with any port or coastal State requirements.
153. The Administrator’s guidance also addresses the owner’s responsibilities when a vessel leaves lay-up. These
responsibilities include ensuring that all Classification Society and statutory certificates are reactivated, that the SMS
is fully functional, and that the vessel is manned per the MSMC issued by the Administrator.
154. As required by the Maritime Act, sections 805 and 825 and the Maritime Regulations, section 7.47, the officers and 
crew are required to hold Republic of the Marshall Islands’ seafarer documentation when the vessel proceeds to sea
after leaving lay-up.
Port State Requirements
155. The PMSC sets out guidance for a national standard for all aspects of safety in port facilities and is intended to 
enhance safety for those who use or work in ports, vessels within the port area, passengers, and the marine 
67 Examples that are provided are accommodation systems, firefighting equipment, and lifesaving appliances.
Part 2: Findings of Fact

Page 37

33
environment. This PMSC provides general guidance addressing several areas related to the safe management 
of the port, including the use of risk assessments and principles of an effective MSMS.68
156. Guidance for implementing the PMSC is provided in the associated Guide to Good Practice. This Guide to 
Good Practice does not include guidance addressing issues that should be considered for the lay-up of vessels 
within a port or harbor.
157. The MCA does not have any requirements or guidance applicable to the lay-up of non-United Kingdom-
registered vessels.69
PART 3: ANALYSIS
The following Analysis is based on the above Findings of Fact.     
Loss of Moorings
VALARIS DS-4 lost its moorings and was blown off the jetty when the logged wind was from the northeast at 55 kn. 
There are some indications that the speed may have actually been higher when the mooring lines started to part. All 
the drill ship’s mooring lines had parted within 30 minutes after the Master and other crewmembers reported hearing 
what they thought was the anchor chain at 1845 on 2 February 2021. The vessel drifted halfway across the channel 
between the jetty and Great Cumbrae Island before the anchor reset. The fact the anchor held likely prevented the drill 
ship from going aground on Great Cumbrae Island.
The C/E on board VALARIS DS-4 had started a diesel generator sometime after the noise, thought to be the anchor 
chain, was heard. He had not been able to shift power from the portable generator to the diesel generator and then 
place one or more of the drill ship’s thrusters online before the drill ship was blown off the jetty or while it was drifting 
across the channel.
ENSCO DS-8’s moorings held the drill ship to the jetty without any lines parting or assistance from the time that 
VALARIS DS-4 mooring line started parting until a tug arrived and started pushing the drill ship against the jetty at 
2040 on 2 February 2021. One of the drill ship’s diesel generators had been started and the drill ship’s power shifted 
from the portable deck generator by 1720 on 3 February 2021, and by noon on 4 February 2021, three of the drill ship’s
thrusters were running.
It cannot be determined whether VALARIS DS-4 would have remained alongside the jetty if the crewmembers could 
have placed two thrusters online or if tugs had been pushing the drill ship alongside before 1845 on 2 February 2021.
It also cannot be determined whether ENSCO DS-8’s mooring lines would have kept the drill ship alongside the jetty 
without the use of thrusters or the assistance of the tugs pushing on the drill ship until the period of high winds from 
the northeast to east had abated by 6 February 2021.
68 Other areas that are addressed include the duties of key personnel, the duties and powers of harbor authorities, and compliance with directions from the General 
Lighthouse Authority.
69 The MCA does have guidance for their surveyors for conducting audits of SMSs on board ships holding Safety Management Certificates issued by the MCA. See 
MCA, Instructions for the Guidance of Surveyors on International Safety Management Code for the Safe Operation of Ships and for Pollution Prevention (MSIS02, 
Rev 06-2020), chapter 8, section 8.1.
Part 2: Findings of Fact / Part 3: Analysis

Page 38

Republic of  the Marshall Islands Maritime Administrator
34
On 7 February 2021, ENSCO DS-8 released the tugs that had been helping hold the drill ship alongside the jetty. On 
8 February 2021, VALARIS DS-4 weighed anchor and, under its own power, was re-moored alongside the jetty.
Availability of Diesel Generators and Thrusters
After the drill ships arrived at Hunterston Jetty, it was planned to keep one diesel generator and two thrusters available 
for use.
By mid-January 2021, Joulon and Noah were aware that the engineers on board VALARIS DS-4 and ENSCO
DS-8 were having difficulty starting the diesel generators and thrusters due to inadequate preheating of the
lube oil and jacket water and inadequate heating of the fuel oil purifiers. This was due to a combination of 
the temperatures in mid- to late-January 2021 and the 220 V deck generators on both drill ships having sufficient 
power to only energize a limited number of heating elements. In addition, preheating of thrusters Nos. 1-3 on both drill
ships required that the 440 V feeder panel for these thrusters be energized.
The engineers and Joulon technicians on board VALARIS DS-4 and ENSCO DS-8 worked throughout the latter half 
of January to identify a solution so that the thrusters could be made available if needed. They had not identified a 
solution to these problems by 2 February 2021.
The problems encountered on board both VALARIS DS-4 and ENSCO DS-8 with keeping a diesel generator and
thrusters ready for use after the drill ships arrived at Hunterston Jetty, is an indication that Joulon and Noah did not 
give adequate attention to the winter temperatures in the area while planning for the drill ships’ lay-up. It is noted that
the average temperature during January in North Ayrshire is 3.5°C, which is only slightly warmer than the -1.5 to 2°C
temperatures that were observed during January 2021.
Based on the information available to the Administrator, the inability to start thruster No. 5 on board VALARIS DS-4, 
after the loss of moorings, was due to a failure of a component and was not reasonably foreseeable.
Planning for Lay-up at Hunterston Jetty
Planning for the lay-up of VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty had been started in September 2020 
while the two drill ships were laid-up at Las Palmas. Based on the records available to the Administrator, Joulon 
appeared to have primary responsibility for conducting and coordinating vessel-focused planning activities.
It appears most of the detailed planning did not start until sometime after mid-November 2020 following the decision 
to not move the drill ships to the ports of Almería and Motril. By this time, Joulon had subcontracted Noah as the
marine manager for both drill ships. It was also during this time that it was decided that each drill ship would have a 
crew of five or six seafarers, which was similar to the size of the crews that were on board the drill ships while they were 
in Las Palmas.
The detailed planning included:
(a) conducting a risk assessment for berthing at Hunterston Jetty;
(b) contracting to have mooring plans developed;
(c) developing multi-hazard emergency response plans; and
(d) developing weather contingency plans.
Part 3: Analysis

Page 39

35
Risk Assessment
The risk assessment for berthing VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty identified multiple hazards 
related to a loss of moorings. These included a failure of a mooring fitting either on the drill ship or on the jetty, failure of 
a mooring line, and adverse weather. Several controls were identified for addressing these hazards.
The controls that were identified included the availability of the drill ships’ thrusters.70 Neither the risk assessment 
nor other information that is available to the Administrator provides any indication whether Joulon or Noah assessed 
how many thrusters might reasonably be required nor what was required to ensure that thrusters would be available 
considering the average winter temperatures in North Ayrshire. There is also no indication that the technical 
requirements for ensuring the availability of the thrusters were considered when they identified the number and 
qualifications of the drill ships’ engineers during lay-up.
Coordination with the port authority was one of the identified controls for managing a loss of moorings when the risk
assessment was conducted. The information available to the Administrator does not provide any indication that Joulon
sought input from COL to ensure that local conditions were considered when the risk assessment was completed 
in November 2020.
The risk assessment was not updated after COL informed Joulon that there was a 3-hour lead time for tug support at
the jetty in December 2020. The risk assessment was also not updated to take into account the information that the 
pilot provided the Masters of the laid-up drill ships when VALARIS DS-4 and ENSCO DS-8 arrived at Hunterston 
Jetty that the actual velocity of winds from the east is typically higher than forecast, that there were no tugs in the 
immediate vicinity, and that a 6-hour notice was required for normal assistance.
Mooring Plan
Joulon contracted InterMoor to conduct a mooring analysis and develop a site-specific mooring plan for both VALARIS
DS-4 and ENSCO DS-8 as part of their detailed planning for laying the drill ships up at Hunterston Jetty.
In response to instructions provided by Joulon, InterMoor based the mooring plans on the average maximum 1-minute
wind speeds at an elevation of 10 m for a 10-year return period. It is noted that InterMoor had proposed basing the plans
on the average maximum 1-minute wind speeds at an elevation of 10 m for a 100-year return period.
Whereas the 10-year average maximum 1-minute winds from the northeast to east were between 39.8-41.5 kn, the 
100-year 1-minute winds were between 42.8-46.7 kn. Because wind speed is squared when calculating the force of 
the wind acting on a surface,71 using the 100-year winds would have increased the force of the wind on both drill ships 
by about 1.8-2.9%.
As discussed, the magnitude of the speed of winds from the northeast and east were higher at Hunterston Jetty than the 
forecast speeds. It is not known if the weather data, which was based on the ERA5 dataset for 1979-2019, used for 
the mooring plan reflected this.
The mooring plans for both drill ships specified the number, type, sizes of the lines to be used, and where each line was
supposed to be connected on the drill ships and the jetty. They also specified the length of line that should be paid out 
70 It is noted that the risk assessment did not include any indication of how many thrusters would be available.
71 The force of wind acting on a surface is calculated using the formula Fw =1/2 ρ v2A, where Fw is wind force (N), ρ is the density of air (kg/m3), and A is the surface 
area (m2).
Part 3: Analysis

Page 40

Republic of  the Marshall Islands Maritime Administrator
36
from the fairlead and the pretension force for each line. Neither of the mooring plans included a requirement for 
thrusters to be used to relieve the tension on the lines when the wind speed exceeded any given speed.
The length of line that should be paid out from the fairlead was intended to maximize how much load an individual line
could absorb and to ensure the drill ships’ crewmembers would not need to adjust the lines each time the tide changed.
When VALARIS DS-4 and ENSCO DS-8 arrived at Hunterston Jetty and when they were shifted to the southwest in late
January 2021, both drill ships were reportedly moored using more lines and that some lines were made up to different
connection points than that specified by the mooring plans developed by InterMoor (see Figures 3 and 4). Based on 
the information available to the Administrator, it is not clear why the lines were not arranged as specified in the mooring
plans. It is possible that it was not clear that the drill ships’ Masters and Joulon program managers who were on board 
the drill ships were aware that compliance with the arrangements specified in the mooring plans was necessary to ensure 
that the drill ships’ moorings functioned as intended.
It could not be verified whether the line lengths when the drill ships were first moored at Hunterston Jetty or when they
were shifted along the jetty were as specified in the mooring plans.
Based on the drill ships’ logs, the daily routine on both VALARIS DS-4 and ENSCO DS-8 included checking and 
adjusting the mooring lines at least once a day. It was not possible to establish whether the lines were adjusted to maintain 
the lengths specified in the mooring plans, or if this was to prevent them from going slack per customary practice. 
If the lines were being adjusted based on customary practice, this could provide an explanation as to why the mooring 
plan was not followed.
Lastly, third-party verification was identified as a control during the risk assessment conducted by Joulon. However, it
is noted that there was no third-party verification that the drill ships were moored in accordance with the mooring plans 
either when they first arrived at Hunterston Jetty or after they were shifted along the jetty in late January 2021.
Joulon provided a copy of the original mooring plans for VALARIS DS-4 and ENSCO DS-8 to COL. There is no 
indication that copies of the revised mooring plans, that were completed shortly before the drill ships’ arrival at Hunterston
Jetty, were provided to COL. There is also no indication that COL verified if the drill ships’ mooring arrangements were 
per the mooring plans following their arrival at Hunterston Jetty or after they were shifted along the jetty in late 
January 2021.
Drill Ships’ Emergency Response Plans
The emergency response plans prepared by Joulon for VALARIS DS-4 and ENSCO DS-8 included procedures for 
adverse weather. These procedures consisted of a decision-making flow chart with a list of actions that should be taken
following the receipt of a forecast of adverse weather. It also included decision points for the Master to decide if tugs 
or a berthing team were required.
These procedures consisted of what is considered good practice. The potential effectiveness of the procedures was 
reduced by the fact that they did not provide objective guidance regarding either Joulon’s or Noah’s expectations 
regarding what might be considered adverse weather or how much lead time was required for tugs to arrive at
Hunterston Jetty. It is also noted that the drill ships’ emergency response plans did not reference their weather 
contingency plans.
Part 3: Analysis

Page 41

37
Based on the information that is available, it is not possible to establish to what extent the adverse weather procedures 
in the drill ships’ emergency response plans may have been implemented. What is known is that neither the Master
of VALARIS DS-4 or the Master of ENSCO DS-8 called for tug assistance until after VALARIS DS-4 experienced 
the full loss of moorings. It is also known that ENSCO DS-8 remained alongside the jetty with tug assistance 
until the period of heavy winds from the northeast to east abated. This is an indication that timely implementation of 
the adverse weather procedures could have potentially prevented a loss of moorings.
Drill Ships’ Weather Contingency Plans
The drill ships’ weather contingency plans included actions that were supposed to be taken based on the forecast 
greater than 50 kn and actual wind speeds greater than 60 and 70 kn regardless of direction. After the drill ships 
arrived at Hunterston Jetty, the plans were amended based on comments provided by the Master of VALARIS DS-4 
when winds of 40 kn or more from the northeast to east were forecast or when the actual wind speeds were 50 kn or more 
from the northeast to east.
Based on these plans, a diesel generator should have been started and the thrusters placed on standby when winds from 
the northeast to east of 40 kn or more were forecast and two thrusters should have been engaged when winds from the
northeast to east of 50 kn or more were being experienced. As previously discussed, thrusters on board both VALARIS
DS-4 and ENSCO DS-8 could not be made available for use on 2 February 2021.
On 30 January 2021, the Master of ENSCO DS-8 informed Noah that tug assistance would be needed in an emergency
since the thrusters were not available for use. However, he did not make such a request until after VALARIS DS-4 
was blown off the jetty on the evening of 2 February 2021. It was not reported why the Masters did not request tug
assistance when northerly winds greater than 40-50 kn were observed during the day.
The drill ships’ weather contingency plans both indicated that there were four thrusters available for use on both 
VALARIS DS-4 and ENSCO DS-8. In contrast, following the drill ships’ arrival at Hunterston Jetty it was planned to 
keep two thrusters available for use and to put the other thrusters in cold iron.
Port Planning
COL undertook a structural assessment of the jetty that determined as many as five drill ships similar to VALARIS DS-4
and ENSCO DS-8 could be accommodated. They also had the mooring bollards tested to confirm their SWL as part of 
their preparations for VALARIS DS-4 and ENSCO DS-8 being placed in lay-up at Hunterston Jetty.
COL additionally conducted an assessment of the initial mooring plans for VALARIS DS-4 and ENSCO DS-8. They
reportedly had some initial concerns with the plans and had engaged a third-party to review the plans and propose 
changes. However, COL did not have the third-party review completed and determined the mooring plans were adequate
based on their impression that they were based on weather conditions at Hunterston Jetty. It was also based on their
understanding that the mooring plans had been approved by the drill ships’ flag State and insurers. The basis for 
COL’s understanding is that the plans had been approved by the flag State and insurers could not be confirmed. As
previously stated, the Administrator had not reviewed these plans.
As part of their agreement for VALARIS DS-4 and ENSCO DS-8 to be laid-up at Hunterston Jetty, COL established
requirements regarding the drill ships’ crew. These included requirements that the drill ships would be manned with 
Part 3: Analysis

Page 42

Republic of  the Marshall Islands Maritime Administrator
38
enough persons to maintain an effective mooring watch and fire patrol, that evidence the manning was acceptable to 
the flag State, and that the manning would be approved by the Harbour Master. COL also reported that they had not 
discussed the size of the drill ships’ crews with Joulon or Noah before either VALARIS DS-4 or ENSCO DS-8 arrived 
at Hunterston Jetty. They also stated that they first became aware of the Administrator’s requirement that the drill 
ships’ manning be approved by the port authorities sometime after 9 February 2021.
COL also required, as part of the agreement for the drill ships to be laid-up at Hunterston Jetty, that they be provided 
a copy of the drill ships’ contingency plans. It is not clear when copies of the plans were provided.
Coordination Between Drill Ship Managers and Port
Although there were ongoing discussions, including a pre-arrival meeting on 23 December 2020, between COL and 
Joulon during the planning for the lay-up of VALARIS DS-4 and ENSCO DS-8, COL also reported that they were 
unaware of details regarding the drill ships’ crews until after VALARIS DS-4 and ENSCO DS-8 arrived at Hunterston 
Jetty. It is also not clear if COL had been provided copies of the revised mooring plans following the drill ships’ arrival.72 
Lastly, it is not clear whether Joulon had advised COL of their intention to have one diesel generator and two thrusters 
available for use on both drill ships. These are indications of possible ineffective coordination and communication 
between Joulon, Noah, and COL.
Classification Society Guidance
ABS’ lay-up guidance for MODUs provides guidelines for owners addressing issues related to the preservation and
protection of a laid-up vessel. This guidance identifies three basic lay-up conditions: Laid-up, Laid-up Warm Stacked, 
and Laid-up Cold Stacked. It also includes two enhanced conditions.73 It is for the owner of a vessel being placed in lay-up
to decide which of these conditions the vessel will be placed in.
One of the basic conditions is laid-up, which indicates the vessel is out of service for an undetermined length of time
and that ABS has not reviewed any lay-up procedures that the vessel’s owner or operator might have prepared. When a 
vessel is placed in this lay-up condition, Classification Society surveys are held in abeyance and statutory surveys are
completed only if required by the vessel’s flag State. Based on ABS records, both VALARIS DS-4 and ENSCO DS-8 
were placed in this status when they entered lay-up after arriving at Hunterston Jetty.74
Placing VALARIS DS-4 and ENSCO DS-8 in one of the other two basic lay-up conditions would have provided for
third-party review of Joulon’s lay-up plan. The support services that would have been provided by ABS would also 
have included the completion of an initial and annual lay-up surveys to verify compliance with the lay-up plan. On
request, ABS would also have conducted an engineering review of the mooring plan and survey of the installed 
mooring arrangements.
Placing VALARIS DS-4 and ENSCO DS-8 in either of the two enhanced lay-up conditions would have further increased 
the level of support provided by ABS to include a review of the proposed lay-up location, the planned mooring 
arrangements, the location specific risk assessment, and the emergency response capabilities in the area when a vessel 
72 These were the revisions that InterMoor completed on 24 and 28 December 2020.
73 As previously discussed, these are “Enhanced Laid-up Warm Stacked” and “Enhanced Laid-up Cold Stacked.”
74 It is noted that VALARIS DS-4 and ENSCO DS-8 had been in Laid-up Warm Stacked when they first went into lay-up in Las Palmas in June 2020. The status of both 
drill ships was later changed to laid-up after the drill ships’ managers at the time did not arrange to have annual lay-up surveys conducted.
Part 3: Analysis

Page 43

39
is placed in the either of these conditions. It would also have included the completion of a mooring survey after the 
drill ships arrived at Hunterston Jetty.
The Administrator is not aware whether the owners of VALARIS DS-4 and ENSCO DS-8, Joulon or Noah Ship 
Management gave consideration to placing the drill ships into Laid-up Warm Stacked, Laid-up Cold Stacked, or either 
of the two enhanced lay-up conditions following their arrival at Hunterston Jetty.
Some level of support from ABS may have contributed to ensuring the effectiveness of the controls identified during 
the risk assessment for berthing drill ships alongside at Hunterston Jetty that Joulon had conducted in November 2020.
Flag State Requirements
The Administrator requires the owner of a Republic of the Marshall Islands-registered vessel being placed in lay-up to
provide a statement from the relevant Classification Society indicating it would meet the requirements for classification 
if it was surveyed when it entered lay-up as a condition for issuing a Provisional Certificate of Registry with the 
endorsement “This Certificate is Only Valid while the Vessel Remains in Laid-up Status and is Not Valid for Navigation.”
Vessels are exempt from annual safety inspections while in an official lay-up period but are required to undergo an 
initial safety inspection before returning to service. These requirements provide a means for the Administrator to verify that
the vessel is seaworthy when it enters lay-up and when it returns to service.
The Administrator’s MG-1-11-1 places the responsibility for ensuring the safety and security of a Republic of the 
Marshall Islands-registered vessel while in lay-up on the vessel’s owner. This guidance includes provisions addressing 
the manning, vessel maintenance and preservation, vessel safety, and contingency measures in place for emergencies
during lay-up. This guidance does not have the force of regulation and cannot be enforced by the Administrator.
The Administrator’s guidance advises owners to seek assistance from the vessel’s Classification Society when preparing
lay-up procedures. Such assistance is consistent with the support ABS would have provided if VALARIS DS-4 and
ENSCO DS-8 had been placed in either Laid-up Warm Stacked, Laid-up Cold Stacked, or in one of the two enhanced 
lay-up conditions discussed previously.
The Administrator’s guidance also advises owners to contact the local port and coastal State authorities where the vessel
is going to be laid-up to determine if there are specific requirements or regulations that might be applicable to the laid-
up vessel. It also is recommended that the vessel owner develop the vessel manning in coordination with the port or 
coastal State authorities.75
In November 2020, the Administrator informed Noah that the drill ships’ manning while in lay-up should be
developed in coordination with the port or coastal State authorities and that it should comply with local regulations.
Based on the information available, it appears that COL was not aware of the number of crewmembers who would be
on board VALARIS DS-4 and ENSCO DS-8 until after their arrival at Hunterston Jetty. It also appears that neither 
Noah or Joulon had discussed the drill ships planned manning with the MCA before VALARIS DS-4’s loss of 
moorings on 2 February 2021.
75 As discussed previously, the Administrator informed Noah in November 2020 that the drill ships’ manning while in lay-up should be developed in coordination with 
the port or coastal State authorities and that it should be in compliance with local regulations.
Part 3: Analysis

Page 44

Republic of  the Marshall Islands Maritime Administrator
40
Port State Requirements
The MCA had not issued guidance for port authorities regarding issues that should be addressed when a vessel will be 
laid-up within a port or harbor. Similarly, the MCA has not issued regulations or guidance addressing the lay-up of 
non-United Kingdom-registered vessels.
PART 4: CONCLUSIONS
The following Conclusions are based on the above Findings of Fact and Analysis and shall in no way create a presumption
of blame or apportion liability.
1. Causal factors that contributed to this marine incident include:
(a) the inability of VALARIS DS-4’s crewmembers to bring the thrusters online in time to prevent the
mooring lines from being overloaded by the storm force winds from the northeast; and
(b) the Master of VALARIS DS-4 did not request tug assistance when the weather forecast for storm force
north easterly winds was received on the afternoon of 2 February 2021.
2. Additional causal factors that may have contributed to this marine incident include:
(a) inadequate coordination between Joulon and COL throughout the planning process for the lay-up of
VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty;
(b) inadequate identification and consideration of local conditions, including the higher than forecast
northeasterly and easterly winds, winter temperatures, and the time required for tugs to arrive after being
requested, as part of Joulon’s risk assessment for berthing the drill ships alongside at Hunterston Jetty;
(c) inadequate identification of the drill ships’ power requirements during Joulon’s and Noah’s planning for
the lay-up of VALARIS DS-4 and ENSCO DS-8 to ensure that a sufficient number of diesel generators and
thrusters would be available if needed during a period of high winds or an emergency situation;
(d) the apparent deviation from the drill ships’ mooring plans when VALARIS DS-4 and ENSCO DS-8
were moored after being shifted along the jetty in late January 2021;
(e) the lack of third-party verification that VALARIS DS-4 and ENSCO DS-8 were moored in accordance 
with the drill ships’ mooring plans;
(f) with the exception of the drill ships’ mooring plans, the lack of third-party assurance of Joulon’s and
Noah’s planning and execution of the lay-up of VALARIS DS-4 and ENSCO DS-8 at Hunterston Jetty;
(g) the lack of comprehensive flag State regulations intended to ensure the safety and security of laid-up vessels;
(h) the lack of flag State requirements for Republic of the Marshall Islands-registered vessels that are in lay-up to
undergo inspections or other forms of oversight to verify they do not pose a safety or security hazard; and
(i) the absence of port State regulations intended to ensure the safety and security of ships laid-up in ports and
harbors in the United Kingdom.
Part 3: Analysis / Part 4: Conclusions

Page 45

41
3. Actions or events that reduced the adverse consequences of this marine incident include:
(a) that VALARIS DS-4’s and ENSCO DS-8’s anchors had been pre-deployed when the drill ships were berthed
at Hunterston Jetty and that VALARIS DS-4’s anchor was reset and held the drill ship in mid-channel after
being blown off the jetty following the loss of moorings; and
(b) the arrival of tugs to hold ENSCO DS-8 alongside the berth.
PART 5: PREVENTIVE ACTIONS
In response to this marine incident, Joulon and Noah have taken the following the Preventive Actions:
1. Changes were made to the preheating systems so that all six thrusters could potentially be started simultaneously 
if necessary.
2. The number of diesel generators and thrusters that were supposed to be ready for use on board each drill ship was
changed from one generator and two thrusters to all six diesel generators and thrusters.
3. Established a requirement that a power swap from the deck generators to the drill ships’ diesel generators be 
conducted once a week and at each change of a senior officer.
4. Joulon contracted InterMoor to develop new mooring plans for both drill ships. After determining that the 1-minute
maximum average wind speeds for a 10-year return and 100-year return were comparable, it was decided to 
use the weather data for the 10-year return. The mooring plan for VALARIS DS-4 is a based on 25 mooring 
lines76 plus the anchor. The mooring plan for ENSCO DS-8 is based on 18 mooring lines77 plus the anchor. 
Both drill ships’ new mooring plans also included requirements for when thrusters should be engaged based on 
minimum wind speeds from different directions.
5. The drill ships’ weather contingency plans were revised to base the criteria for when each of three phases should
be implemented on forecast and actual wind speeds from different quadrants. These changes, which are based on 
the new mooring plans, reduce the threshold for implementing the initial phase when the winds were from the
northeast to east to 30 kn, for implementing the second phase to 35 kn, and for implementing the third phase to 
45 kn. The revised plans now require that at least one engine and two thrusters be online during the second 
phase and that a minimum of four thrusters be engaged during the third phase.
6. The drill ships’ emergency response plans were amended to refer to the weather contingency plans for determining
when preparations should be made to start one or more diesel generators, conduct a power swap, and bring thrusters
online. The revised plans also include additional guidance for requesting tug assistance.
7. Procedures were established for the planned departure of the drill ships from alongside the jetty if warranted 
based on the weather forecast or in an emergency situation. The plans included provisions for using tugs to move 
the drill ships off the jetty if it was not possible to swap power from the deck generator, the thrusters could not 
be started, or there was a loss of electrical power on board.
76 This consists of three 36 mm, 16 42 mm, two 44 mm, and four 48 mm UHMWPE lines.
77 This consists of 13 40 mm and five 42 mm UHMWPE lines.
Part 4: Conclusions / Part 5: Preventive Actions

Page 46

Republic of  the Marshall Islands Maritime Administrator
42
8.      The manning for both drill ships was revised so that the marine crew would consist of a Master, a navigation officer,
two engineering officers, an ETO, and four ratings between October and April. The number of ratings would be
reduced to three from May to September. The revised manning was agreed to by COL.
Peel Ports has taken the following Preventive Actions:
1. The COL risk assessment for the lay-up of drill ships was reviewed and additional mitigation measures were added.
2. A risk assessment addressing emergency response for a fire on board a vessel and lines parting in severe weather 
was conducted.
3. The existing COL procedures for the lay-up of vessels were reviewed and revised to include more detailed 
guidance and establish clear expectations for vessel owners wanting to lay a vessel up at one of its facilities on
the Clyde Estuary. The revised procedures require that vessel owners provide information regarding the vessel’s
planned lay-up status, the mooring plan, the status of machinery and safety systems while in lay-up, the maintenance
and inspection of mooring lines, and emergency procedures. They also require that the vessel’s proposed manning 
while in lay-up be approved by the flag State before it will be reviewed by the statutory harbor authority. The 
revised procedures are being adopted by each of the statutory harbor authorities within Peel Ports.
4. COL, in coordination with Joulon, conducted a review of VALARIS DS-4’s and ENSCO DS-8’s equipment 
status (e.g., diesel generators, thrusters, and related systems) and criteria for activating the drill ships’ weather
contingency plan.
5. COL reviewed and agreed to Joulon’s revised manning for both VALARIS DS-4 and ENSCO DS-8.
6. COL conducted a review of the jetty infrastructure taking into consideration winter conditions.
7. COL contracted to have an independent third-party review of the drill ship’s new mooring plans completed.
8. Contingency response plans for responding to emergencies involving a laid-up vessel were developed for each
statutory harbor area within Peel Ports.
9. A weather monitoring station was installed at the Hunterston Jetty. The information from this station is available 
to both VALARIS DS-4 and ENSCO DS-8 and relevant parties. It is also being compared to the wind speeds 
observed on the drill ships’ anemometers.
The Administrator has taken the following Preventive Actions:
1. In coordination with MAIB, issued Marine Safety Advisory No. 14-21, Loss of Moorings During Lay-Up on 
5 October 2021.
2. Revised its requirements for issuing a Provisional Certificate of Registry in Laid-up status to include a reference to
the MG 1-11-1.78
78 See the April 2022 revision of the Republic of the Marshall Islands Vessel Registration and Instrument Recording (MI-100), section 10.3.
Part 5: Preventive Actions

Page 47

43
PART 6: RECOMMENDATIONS
The following Recommendations are based on the above Conclusions and in consideration of the Preventive Actions taken.
1.      It is recommended that Joulon and Noah:
(a) review and revise their procedures for planning for vessel lay-ups taking the lessons learned from this marine
incident into account.
2.      It is recommended that Peel Ports:
(a) propose guidance on planning and conducting of vessel lay-up in ports in the United Kingdom to the MCA’s
PMSC Steering Group, for inclusion in the PMSC’s Guide to Good Practice.
3.      It is recommended that the Administrator:
(a) develop additional regulatory requirements that take different lay-up conditions into account to ensure the
safety of Republic of the Marshall Islands-registered vessels that are placed in lay-up and crews on board
such vessels; and
(b) review, and revise where required, internal procedures related to oversight of compliance with established
requirements for vessels in lay-up.
4.      It is recommended that the MCA, in coordination with the PMSC Steering Group:
(a) consider publishing guidance on the planning and conducting of vessel lay-ups in ports in the United
Kingdom, for inclusion in the PMSC’s Guide to Good Practice.
The Administrator’s marine safety investigation is closed. It will be reopened if additional information is received that
would warrant further review.
Part 5: Preventive Actions / Part 6: Recommendations