NORTH AYRSHIRE COUNCIL 
19 March 2024 
Cabinet 
Title:    Roads, Structures and Street Lighting Maintenance
Programme 2024/25 
Purpose:  To seek Cabinet approval of the proposed Roads, Structures
and Street Lighting Maintenance Programme for 2024/25 
Recommendation:  That the Cabinet (a) notes the approach taken to determining
the asset maintenance programme for roads, structures and
street lighting; (b) approves the maintenance programme for
2024/25, as shown at Appendix 1a and 1b; (c) approves the
additional works to the value of £0.75m as agreed at the
Council’s budget setting meeting, as shown at Appendix 1c and
(d) notes that the programme will be issued to the Locality
Planning Partnerships for information. 
1. Executive Summary 
1.1 North Ayrshire Council has a statutory obligation under the Roads (Scotland) Act 1984
to manage and maintain its public road network. The adopted road network within
North Ayrshire has a total length of 1045m.  The core roads assets are currently
estimated at a value of approximately £1.7billion. 
1.2 The Council’s Roads Service has adopted an asset management approach to road
maintenance to allocate available road maintenance funds to locations that will offer
the most beneficial return on investment. 
1.3 The Roads Asset Management Plan (RAMP) and the roads assets maintenance
strategy follows the recommendations contained within the ‘Well Maintained
Highway’s’ Code of Practice, ensuring that the Council’s statutory obligations as
delegated Roads Authority are met. 
1.4 In complying with the Code of Practice, an effective regime of inspection, assessment
and condition recording is well established which assists in not only providing a road
network for the future but one that promotes social inclusion and contributes to
economic growth within the area. This approach also ensures the Council is providing
value for money on any investment attributed to road maintenance. 
1.5 The proposed Roads, Structures and Street Lighting Maintenance Programme
2024/25 is attached in Appendix 1a and 1b. The Programme is based on approved
Revenue and Capital budgets. At the Council’s budget setting meeting on 28 February
2024 an additional £0.75m was approved for roads infrastructure. Details of the
proposed works are attached at Appendix 1c.

Page 2

2. Background 
2.1 North Ayrshire Council is responsible for the maintenance of the adopted local road
network including lighting and structures assets as well as its other non-adopted road
assets. However, the Council has no responsibility for the maintenance of the Trunk
Road Network which falls to Transport Scotland and their management contractor,
Amey. The Trunk Road network includes the A78, the A737 from Kilwinning to the
Renfrewshire Boundary and A738 from the Pennyburn Roundabout to the A737 Dalry
Road Kilwinning. 
2.2  North Ayrshire Council’s roads are the Council’s largest community asset and play a
vital role in supporting the local and wider economy by facilitating the movement of
people, goods and services and connecting people with economic and social
opportunities. 
2.3  The proposed Roads, Structures and Street Lighting Maintenance Programme for
2024/25 has been developed in accordance with the strategy contained within the
Roads Asset Management Plan (RAMP) to deliver the maximum return on investment
and ensures the provision of an effective road network throughout North Ayrshire. 
2.4  Road Condition is measured nationally through the Scottish Road Maintenance
Condition Survey (SRMCS). The measure in place, the Road Condition Index (RCI),
records the percentage of the Council’s roads which should be considered for
maintenance. North Ayrshire’s RCI had been improving in recent years but there was
a 0.9% reduction last year with an RCI of 34.8% published in 2023. Our position in the
RCI tables also changed from 20th out of 32 authorities to 21st.  It should be noted that
due to the method employed to calculate road condition, overall RCI is based on the
previous 2 to 4 years survey information, as such, improvement from additional
investment may not be immediately apparent. 
2.5 The estimated carriageway maintenance backlog figure for North Ayrshire is currently
£38.5m. The ‘steady state’ figure for maintaining our roads at present condition has
increased to £5.5m per year from £4.3m per year. 
2.6 The previous steady state figure of £4.3m was calculated in May 2019, the revised
steady state figure of £5.5m was calculated in September 2023.The revised figure has
been calculated using road condition data from 2021 and 2022 for A, B and C
classified roads and 4 years of condition data for unclassified roads 2019 to
2022.  The treatment rates used in this calculation are Scotland wide treatment costs
released by the Scottish Roads Research Board unit cost benchmarking group in
August 2023 and are based on actual costs. 
2.7 Despite road condition improving nationally over the last 4 years, the overall backlog
figure for Scotland has increased by 16.3% primarily as a result of an increase in
treatment costs. Treatment costs have increased significantly as a result of difficulties
in sourcing materials post pandemic, inflationary rises and increasing energy prices,
this also impacting significantly on contractor costs.  In North Ayrshire, our treatment
costs have increased by approximately 18% since 2022/23. 
2.8 The capital budget supported by revenue funding is £4.3m for 2024/25. This level of
investment is outpaced by the ‘steady state’ figure and may therefore contribute to a
deterioration of the road network condition over time. However, it should be noted that

Page 3

at the Council’s budget setting meeting on 28 February 2024 an additional £0.75m
was approved for roads infrastructure for 2024/25 which will help reduce the gap
between investment and the ‘steady state’ figure. 
2.9 Road lighting condition is measured through programmes of structural and electrical
assessment and testing and is complemented through the ongoing review of age
profile and material type life expectancy. The results are categorised and recorded in
the lighting asset management database to inform a prioritised list of replacement
schemes. Lighting is allocated an annual Capital budget of £1m to address a ‘steady
state’ position of maintaining our lighting at present annualised depreciation rate. 
2.10 Bridge and retaining wall condition is also evaluated through a robust inspection
programme. General inspections are undertaken every 2 years, while an in-depth
‘principal inspection’ is carried out every 6 years and the results of the inspections are
used to inform work programmes. The results of the inspections are input into a
Structures database which is then used to calculate an average Bridge Structure
Condition Index (BSCIav) based on the total number of assets. The BSCIav is
currently 86.36 (2022/23 figure) which is within the ‘good’ classification of 85 to 94.
This figure is a slight improvement on the previous year. The allocated capital budget
of £560,000 is supported by carryover from 2023/24 giving a total of £695,000. 
2.11 Details of how condition assessments are carried out and how roads, structures and
lighting locations are prioritised for inclusion in our maintenance programme are
provided in Appendix 2. The assessment matrix used for scoring and ranking
structures for inclusion in the Structures Maintenance Programme is attached in
Appendix 3. 
2.12 The road maintenance programme in 2023/24 mitigated high inflationary cost
increases through two factors - by forecasting higher projected costs and building this
into the programme early in the financial year and, secondly, the Ayrshire Minor Works
Framework contract price being held for the 6 months to September 2023.  Works
completed by the operational team and any works tendered since then were subject to
inflationary rises in material and plant costs as well as contractor price increases.  The
2024/25 road maintenance programme has been prepared using increased rates from
2023/24 costs to allow for further inflationary rises in operational costs and to ensure
that programmed works can be completed. 
2.13 The following footway locations are being carried over from the 2023/24 maintenance
programme due to an unforeseen contractor availability issue: 
• Thorntree Avenue, Beith
• St Margarets Avenue, Dalry
• North Street / Braehead Dalry 
2.14 The following structure contracts are being carried over from the 2023/24 maintenance
programme, feasibility and design works are ongoing: 
• Seven Acres Mill Bridge (U54)
• Threadmill Bridge (C99)
• Carsehead Bridge (B714)
• Dougarie Bridge (C147)
• Catacol Bridge (C147)

Page 4

3. Proposals 
3.1 That Cabinet notes the approach taken to determining the asset maintenance
programme for roads, structures and street lighting. 
3.2  That Cabinet approves the maintenance programme for 2024/25, as shown at
Appendix 1a and 1b. 
3.3    That Cabinet approves the additional works at a value of £0.75m as agreed at the
Council’s budget setting meeting, as shown at Appendix 1c. 
3.3  That Cabinet notes that the programme will be issued to Locality Planning
Partnerships for information. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Roads, Structures and Street Lighting Maintenance Programme will be delivered
from allocated Capital and Revenue budgets. Estimated costs are detailed within the
appendices. 
Human Resources 
4.2 Delivery of the programme will be met from existing staff resources. 
Legal 
4.3 North Ayrshire Council has a statutory obligation to manage and maintain its public
road network under the terms of the Roads (Scotland) Act 1984. 
Equality/Socio-economic 
4.4 There are no equality implications. The maintenance programme contributes to the
Council’s socio-economic duty, as well-maintained roads are essential for the social
and economic prosperity of North Ayrshire. 
Environmental and Sustainability 
4.5 Effective programming and management of these assets will assist in reduced carbon
associated with mobilisation of unplanned reactive maintenance resources and
extends the use of assets in a cost effective and sustainable manner. 
Key Priorities 
4.6 Effective management of these assets contributes to Council plan priorities ensuring
that our places and spaces where we live, work and visit are well maintained and
accessible.

Page 5

Community Wealth Building 
4.7 The maintenance programme contributes to Community Wealth Building through
community benefits clauses associated with maintenance contracts. It is also the case
that a proportion of the maintenance programme is also delivered in-house by the
Roads Operations Team and Building Services. 
5. Consultation 
5.1 The maintenance programme will be shared with each Locality Partnership. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Susan Macfadyen, Interim Senior Manager,
Commercial Services (Roads), on Tel: 01294 324844. 
Background Papers
0

Page 6

Mainland Roads Programme 2024/25
Appendix 1a
Carriageway Resurfacing
Street Town Location Estimate
Cost
A71  Irvine
Warrix Interchange to Greenwood
Interchange £250,000
A737 Marress Road Irvine Southbound Carriageway £200,000
A738 Glencairn
St/High Road Stevenston Tesco to Mayfield Road  £145,000
B780 Manse Street Saltcoats Memorial Roundabout to existing joints £60,000
B7048 Portencross West Kilbride
Car park to cottage, from Ardneil cottage
for approx 800m, plus patching £165,000
B781 Yerton Brae West Kilbride Full length £82,000
B777 Beith
From Surface Dressing joint at anti skid on
a section starting from Blaelochside to
Lochend
£115,000
B777 near school Glengarnock
From Kersland across front of school to
bend sign £100,000
B780 Sharon St/West
Kilbride Road Dalry
Full Length Sharon St to just past
Wingfaulds Avenue £135,000
B780 Roche Way Dalry
South of James Street towards Townend
Street  £63,000
Glebe Road Beith Full Length £122,000
Paddockholm Road Kilbirnie Holmhead to Mill Road £82,000
South road Glengarnock Full Length £56,000
Sycamore Court Beith Full length £37,000
Morrishill Drive Beith Dalry Road to Cuff Crescent £17,000
St Inans Beith Full length £57,000
Garnock Street Dalry To No entry signs £94,000
Lynn Avenue Dalry Full Length     £63,000
Finlay Avenue Dalry Full Length £28,000
Newhouse Drive Kilbirnie no.73 to Place View £45,000
New Street Irvine
Friars Croft to Fullarton Roundabout -
include Roundabouts at Greggs and McDs £186,000
Shewalton Rd Irvine
Roundabout to Murdoch Place +
contribution to Murdoch Place £126,000
Smithstone
Way/Smithstone
Court Irvine Auchenharvie Place to Kersland Foot
£30,000
Paterson Avenue Irvine no. 46 to Stewart Drive £42,000
Castlepark Road Irvine Castlepark Crescent to Castlepark Circle £74,000
West Doura Way Kilwinning A738 to shops £39,000
Glenbervie Drive Kilwinning Part Length £83,000
Longford Avenue Kilwinning From junction of Dubbs Road £29,000
Love Street Kilwinning no. 15 to Moncur Road £15,000
Cambusdoon Place Kilwinning Main access road only  £62,000
B785 Fergushill Road Kilwinning A737 to Parkhead Avenue £78,000
The Roundel Largs Full Length £49,000

Page 7

Mainland Roads Programme 2024/25
Appendix 1a
Auchenmaid
Crescent Largs Full Length to Joint on Scotlaw Drive £37,000
Seamore Street Largs Full Length £95,000
Montgomerie
Crescent Saltcoats
Melbourne Park towards South Beach to
include Traffic Calming £99,000
Dockhead Street Saltcoats Contribution to improvements £109,000
West Doura Avenue Saltcoats Full Length £55,000
St Andrews Road Ardrossan Full Length £47,000
Moorpark Rd East
and West Stevenston
Include Island crossing point at Moorpark
West £115,000
Golf Road Millport Part Length £94,000
Ritchie Street Millport Full Length £15,000   
£3,395,000 
Carriageway Screeding
Street Town Location Estimate Cost
Oakwood Drive Beith Full Length     £23,000
Windyedge Rd Dalry 272m section prior to Brodoclea (approx
83m north of Millour Burn)
£30,000
C5 From railway
bridge to B706
Dalry From Jct C68 to railway bridge at Giffen
cottage (Multi hog patching required
from there to B706)
£49,000
Castlepark Drive Fairlie Glen Road to Fairlie castle jct £15,000
Knoxville Road south Kilbirnie Resurface Cway, kerb & surface gravel
path including associated lighting works.
£70,000
Kenilworth Saltcoats Half width £10,000
Long Hill Skelmorlie Full Length £73,000
Annetyard Road Skelmorlie from Fosterland jct to Eglinton Terrace,
include Fosterland jct
£20,000
Misk Knowes Stevenston Small section from Ardoch Crescent £13,000
U35 West Kilbride  £92,000
Lindsay Crescent Largs Full Length - high kerb upstand, patch and
screed
£55,000   
£450,000

Page 8

Mainland Roads Programme 2024/25
Appendix 1a 
Footway Resurfacing
Street Town Location Estimate Cost
Thorntree Avenue  Beith Full Length - Odd Nos, 38-56 Even Nos £26,000
St Margarets Avenue Dalry Kittyshaw to Houston Crescent £50,000
North St/Braehead Dalry Regal Court to Braehead Place £43,000
Raise Street Saltcoats Footway one side only (Argyle road to
Station) £31,000
Canal Street Saltcoats Robertson Cresent to old railway bridge £4,000
Manse Street Saltcoats Sainsbury car park exit to bus stop at
memorial roundabout £8,000
Braeside Irvine Braefoot to Parking Bays £16,500
Castlepark
Footpaths Irvine Various Sections £60,000
Remote Footpath Millport Howard Street to Bute Terrace £18,000
Pennyburn
Footpaths Kilwinning Various Sections £40,000
Manse Crescent Largs Full Length £33,500   
£330,000

Page 9

Mainland Roads Programme 2024/25
Appendix 1a
Lighting Deteriorated Infrastructure Replacements
Area Town Estimate Cost
Anderson Drive
Merryvale Road
Lamont Drive
Rubie Crescent
Broomlands Drive
Whitehope Green
Braehead
Lammermuir Court
Moorfoot Way
Earncraig Green
Pentland Place
Windlestraw Court
Irvine £554,150
West Kilbride Road
Lynn Avenue Dalry £82,850
Lindsay Avenue
Plan View
School Wynd
Kilbirnie £55,010
Montgomery Terrace Skelmorlie £74,590  
£766,600 
Lighting Deteriorated Column Replacements
Area Town Location Estimate Cost
Various Unplanned Locations   £179,000 
Lighting Deteriorated Column Inspections
Area Town Location Estimate Cost
Various Locations   £54,400 
Structures Projects
Structure Road Project Estimate Cost
Seven Acres Mill
Bridge  U54 Bridge Replacement £350,000
Bungle Burn Bridge A736 General Repairs £40,000
Threadmill Bridge  C99 Replacement / Strengthening  £160,000
Carsehead Bridge  B714 General Repairs   £35,000   
£585,000

Page 10

Mainland Roads Programme 2024/25
Appendix 1a 
Carriageway Resurfacing:   £3,395,000
Carriageway Screeding:    £450,000
Footway Resurfacing:    £330,000 
Lighting Infrastructure Replacements:  £766,600
Deteriorated Column Replacements:  £179,000
Deteriorated Column Inspections:  £54,400 
Structures Projects:    £585,000 
Overall Mainland Total:    £5,760,000

Page 11

Arran Roads Programme 2024/25
Appendix 1b 
Carriageway Resurfacing
Street Town Location Estimate Cost
C3 Ross Road Sliddery Approx 600m from C147 Junction. £30,000
C147 Sliddery Sliddery Just north of Sliddery heading to
Corriecravie £70,000
C147 Kilpatrick Kilpatrick South of previous resurfacing heading
to Corriecravie £150,000
Auchrannie Road Brodick Willowdale to Peddar £25,000
U87 & B880 Machrie Timber Transport Match Funding  £75,000
C147 Tormore Machrie Tormore to Machrie Bridge £75,000
U86 Levencorroch Kilmory Full Length £30,000   
£455,000 
Carriageway Resurfacing: £455,000
Structures Projects:  £110,000
Overall Arran Total:  £565,000
Structures Projects
Structure Road Project Estimate Cost
Dougarie
Bridge             
C147 Temporary Strengthening/ Scour
repairs 
£50,000
Catacol
Bridge                
C147 Temporary Strengthening/ Scour
repairs    
£60,000   
£110,000

Page 12

Mainland Roads Programme 2023/24
Appendix 1c 
Additional Budget £750,000
CARRIAGEWAYS
Street Town Location Estimate Cost
Smith Street Dalry New Street to Car Park £40,000
West Kirklands Place Dalry Full Length £38,000
A737 Merryvale
Roundabout
Irvine  Including A737 North & South
Approach
£93,000
A737 Marress Roundabout Irvine  Various Sections £60,000
Stockbridge Crescent Kilbirnie  Various Sections £52,000
Milton Road Kilbirnie  Milton Quad to Herriot Avenue £92,000
A760 Cochrane Street Kilbirnie Patching £15,000
B779 Almswall Road Kilwinning Car Park to Nethermains
Roundabout, including roundabout
£150,000
A737 Lauchlan Way Kilwinning Woodwynd to Church Street £15,000
Holehouse Court Largs Full Length £45,000
B780 Stevenston Cross Stevenston  Glebe Street to Post Office £100,000
C147 Machrie Machrie Machrie Tea Room to Machrie
Moor Road
£50,000   
£750,000

Page 13

Appendix 2 
Condition Assessment and Prioritisation Process 
1.1 The Audit Scotland Follow-up report, Maintaining Scotlands Roads published in
August 2016 stated that Councils should use their RAMPs to establish long
term investment plans for maintaining the road network taking into acount
whole-life costing and treatment options. 
1.2 As part of the Roads Asset Management process, annual condition
assessments are carried out on the public road network as part of the
inspection regime. All locations are assessed using a risk based approach. 
1.3 Condition assessments are carried out simultaneously with the Safety 
Inspections in accordance with the pre-determined timescales contained within
our Safety Inspection Manual. All faults noted during these inspections are
logged within our electronic Routine Maintenance System (RMS). 
1.4 For carriageways, to take account of whole-life and different treatment options
the carriageway maintenance programme is developed using road asset
management principles. Lifecycle planning is at the core of this approach and
takes into account, hierarchies, condition and local community priorities.
Preventative treatments are used to prolong the life of carriageway surfaces
before their condition deteriorates and requires extensive resurfacing.   
1.5 The main factors considered are:- 
• Road Condition – based on detailed visual inspection and the Scottish Road
Maintenance Conditions Survey (SRMCS). 
• Road Hierarchy – this takes account of the strategic importance of the road
and is determined from our Local Transport Plan. 
• Assistance to Council and Community Priorities – this takes account of
other priorities such as economic development,  access to shops, amenity
housing or schools. 
1.6 Carriageways and footways are both condition assessed and scored in
accordance with the assessment table below. These condition scores, RCI
data, road hierarchy information and priorities information as above are utilised
through our electronic WDM Scheme Manager to target locations for
improvement works in order to optimise investment.

Page 14

Appendix 2 
Assessment Table   
CONDITION
Extent 1
(Acceptable)
2
(Safe but poor
appreance)
3
(Minor
deterioration)
4
(Major
deterioration)
1 - Up to 25%  5 9 13
2 – 25% to
50% 
6 10 14
3 – 50% to
75% 
7 11 15
4 – 75% to
100% 
4 8 12 16 
Each location is also reviewed at least once a year depending on its location
within the Roads Hierarchy as part of the routine inspection process. 
1.7 There are various types of surfacing materials and processes available
depending on the particular road type, location and level of existing
deterioration. Options available for treatment include preventative measures
such as surface dressing and resurfacing options such as screeding,
resurfacing (inlay and overlay), depending on the severity of deterioration full
reconstruction may be the most effective option. 
1.8 The level of investment associated with the varying treatment types identified in
the table below was established using the Society of Chief Officers of
Transportation in Scotland’s cost projection model,  developed as part of the
Roads Asset Management Planning project. The model assists with identifying
the effect of various treatments on the  on-going condition of the carriageway.
This enables a more accurate design life for the treatments currently available
to be developed and ensuring value for money on their use.   Costs for works at
any location further vary from the figures below depending on restricted working
arrangements, traffic management required and the extent of preparatory works
necessary to enable resurfacing.  There is also an additional uplift for island
working of up to 50% for works on Arran and Cumbrae.

Page 15

Appendix 2 
Treatment Option Table 
Treatment Option Cost per Sqm
2022/23
Cost per Sqm
2023/24
%
Change
Extension to life
Surface Dressing £3.60 £4.00 +11% Up to 10 years
Screeding £11.50 £14.40 +25% 5 – 10 years
Inlay HRA £22.00 £26.00 +18% Up to 20 years
Overlay <100mm £26.50 £33.00 +25% Up to 20 years
Inlay  100mm £32.30 £38.00 +18% Up to 20 years
Reconstruction 
300mm
£140.00 £165.00 +18% Up to 20 years 
1.9 Street Lighting column replacement is prioritised through non-destructive
strength testing to determine the level of deterioration associated with the
columns. Following testing, columns are categorised within the Asset
Management database for road lighting. 
1.10 Testing is carried out in accordance with the Institute of Lighting Engineer's
Technical Report No.22 Managing a Vital Asset: Lighting Supports as well as
UK Lighting Board Code of Practice: Well-lit Highways. 
1.11 Once results are input, the database then compares these results against the
more general age profile to determine a final list of priority repairs. This
produces recommendations in order of priority for both individual units and
whole streets or areas. 
1.12 Recommendations are generally categorised as Category A through K as
follows: 
A:  Immediate replacement 
B:  Replace urgently or reinspect within 6 months 
C1: Column Material failure, replace as soon as possible or reinspect within
1 year 
C2: Bracket failure, sleeve where possible or replace unit within 1 year 
D:  Foundation failure, realign, reinstate and reinspect within 6 months 
E: Material approaching failure, replace as part of planned maintenance
programme or reinspect within 2 years 
F:  Material approaching failure, replace as part of planned maintenance
programme or reinspect within 5 years

Page 16

Appendix 2 
G:  Condition reasonable, but age expired and certified insured  for 2 year
periods until replaced 
H:  Condition reasonable, but age expired and certified insured  for 5 year
periods until replaced 
I:  Acceptable condition but age expired and insured for 5 years  periods
until replaced. 
J:  Sound condition but age expired & visually poor (evidence of concrete
cracking etc.) 
K:  Sound condition and not age expired – no current requirement for
strength structural inspection, visual only at planned maintenance cycle. 
1.13 Where non-urgent replacement recommendations (Category F through to J) are
on an individual column basis, the data is further analysed to determine a
percentage value for recommended replacement numbers against the balance
of units in a street. If this figure exceeds 30% then the entire street will be
considered for higher prioritisation which will address the design class standard
of the street beyond individual replacement for safety reasons only. 
1.14 The structures programme is identified based on the structures prioritisation
matrix which ranks assets based on a number of factors including its condition,
safety, and usage.

Page 17

Structure Name: Enter score based on the description in the following coloured cells
Date when the scoring is carried out:
Priority Ranking for structure capital programme Structure Net score % of
Maximum Score total Score
No. Factors Score Input
1
Type of Bridge 1 Score 1 if road bridge and 0
if foot bridge
Culverts, Subways which carry road shall be
considered as road bridge as per this scoring system.
Structures which carry only pedestrians, cyclists and
equestrians shall be considered as footbridge.
NA
2 Route Factor 40 Score based on NAC route hierachy Route hierachy 0 0%
Cat 2 - SPT/ NAC strategic routes - 40
Cat 3a - Main distributor routes - 30
Cat 3b - secondary distributor routes - 20
Any other category - 10
Routes serving fewer than 5 properties - 5
3 HGV Restriction 60 Score based on weight capacity Weight restriction 0 0%
factor 3 tonnes - 60
7.5 to 13 tonnes tonnes - 50
18 tonnes - 40                 
26 tonnes - 30
No weight restriction - 0
4 Condition factor 10 Score based on the condition of the
bridge
Sliding score based on 0 for very good condition to 10
for poor condition. (10 - (BCI crit/ 10)) 0 0%
5
Deterioration
factor
10 Score based on the rate of
deterioration of the structure
Sliding score based on 0 for very slow deterioration to
10 for rapid deterioration 0 0%
6
Pedestrian
factor
20 Score based on pedestrian usage.
Bridges with footways of heavy
pedestrian usage shall score a
maximum of 30.
Structures with footways in heavily used urban areas
score 20. Score 20 if route is access to a school or
railway station. Apply a sliding scale going down to 0
for rural structures without footways.
0 0%
7
Flooding factor 40 Score based on the potential for the
existing structure to contrubute to
flooding
A structure that makes no contribution to flooding
risk will score 0. Structures that are know to increase
the risk of flooding due to restrictions in width or
soffit height will score 30.
0 0%
8
Scour factor 60 Score based on risk of collapse due to
expose to scour in heavy flow
conditions
Risk of collapse of structure due to scouring.
Structures which have been deterioted severely
because of inadequate scour protection and on verge
of collapse score maximum. Scour risk based on a
sliding scale.
0 0%
9
Parapet Condition
Factor
15 Score based on the condition of the
parapets
Structures with substandard Parapets with poor
conditon will score 15 . Structures with substandard
parapets with a 'monitor only' recommendation will
score 10. Structures which have parapets to current
standards will score 0.
0 0%
10
Parapet Risk
Factor
10 Score based on risk  in the event of a
parapet collapse leading to high risk
injuries and human casualties.
What is the likelihood of severe injury or even death
while the parapet is open to use considering the
condition of the structure. Risk based on a sliding
scale.
-5 100%
Structure Name:
Additional commentry

Page 18

11
Delay factor 10 Score based on whether existing
restrictions such as limited width
cause delays at the structure
Structures where delays are caused by width, weight,
height or other restrictions such as traffic lights will
be given a score higher than zero. Delays less then 2
minutes at peak times will score 5 and longer than 2
minutes will score 10. Score maximum if fire station,
railway station or hospital affected by delay.
0 0%
12
Structure Risk
factor
10 Score based on risk  in the event of a
Structure collapse leading to high risk
injuries and human casualties.
What is the likelihood of someone getting a high risk
injury or even death while the structure is open to
use considering the condition of the structure. Risk
based on a sliding scale.
0 0%
13
Maintenance
factor
20 Score based on maintenance
required to keep the existing
structure open.
Score based on known maintenance history and
requirement. No maintenance requirement will score
0. Listed structures score 15.
0 0%
14
Diversion factor 10 Score based on the length of the
diversion route if the structure is
closed in an unplanned manner with
no finite time limit.
Score based on diversion length. Any diversion equal
to or more than 20 miles scores 20. Score 1 for each 2
miles of diversion up to 20. Score 10 if a road closure
adversly affects a fire or railway station or hospital.
Score 10 if there is no alternative diversion.
0 0%
-5
Note maximum score that can be achieved for road bridge= 500
Priority level Chart Structure Name:
Date of Scoring: 00-Jan-00
Priority Level Indicator Overall works (500) Structure works (100) Parapet works (70) Scour Protection (60)
Level Score Level Score Level Score Level Score
No Action Rquired       
Low Priority       
Medium Priority       
High Priority       
Immediate action required       
Note : Works are divided above into three sub categories as each work can be independent and
each has its own significance in terms of attention required.