NORTH AYRSHIRE COUNCIL 
19 March 2024 
Cabinet
Title: Irvine Locality Property Review
Purpose: To provide Cabinet with details of the Irvine Locality Property
Review and recommended next steps. 
Recommendation: That Cabinet approves the Irvine Locality Property Review
recommendations for implementation. 
1. Executive Summary 
1.1 As part of the approach to address the current financial challenges facing local
authorities, the Council has adopted an ambitious sustainable change programme
aligned to its Medium-Term Financial Plan, Council Plan and other relevant
strategies. One of the key workstreams within this programme is focused on land
and property. The purpose of the land and property workstream is to rationalise the
Council’s property estate, in a managed way, aligned to clear strategic objectives. 
1.2 The Council’s most significant concentration of property assets is in Irvine, which has
therefore been the focus of the first phase of the property review work, taking a whole
locality approach. Officers have been working together to review the Council’s property
assets in Irvine to understand opportunities for remodelling of the estate to accord with
the strategic objectives outlined at paragraph 2.1. 
1.3 This report sets out a series of recommendations for implementation on a phased
basis, which together reflect a structured approach to: 
• Vacate and subsequently market property assets including: Quarry Road, Trinity
Church, Galt House and Greenwood Conference Centre
• Consolidate operations from the above buildings primarily within Cunninghame
House to optimise utilisation of that building 
• As a future phase, vacate Bridgegate House and consider future uses as part of the
Irvine town centre regeneration work and establishment of the Irvine Town Board,
aligned to the Long Term Plan for Towns Levelling Up Funding allocation 
1.4 Key benefits of this property rationalisation proposal include: 
• Optimisation of under-utilised property assets
• Reduction of carbon emissions by an estimated 286tCO2e/year
• Reduction of property running costs and property maintenance costs, with
combined estimated potential revenue savings of up to £0.357m per annum
• Generation of potential capital receipts or revenue income through leasing
arrangements following marketing of the surplus buildings

Page 2

1.5 Cabinet approval is sought for implementation of the property rationalisation
recommendations, on a phased basis, with proposed next steps and estimated
timescales provided for each phase within the body of the report below. 
2. Background 
2.1  As part of the approach to address the financial challenges currently facing local
authorities, the Council has adopted an ambitious sustainable change programme
aligned to its Medium-Term Financial Plan, Council Plan and other relevant
strategies. One of the key workstreams within the programme is focused on land
and property. The purpose of the land and property workstream is to rationalise the
Council’s property estate, in a managed way, in order to: 
• Reduce the Council’s carbon emissions arising from the property estate and
future exposure to investment requirements for public sector buildings to reach
ZDE (‘zero direct emissions’) by 2038
• Reduce property running costs, i.e. from rates, utilities etc.
• Reduce property maintenance and future investment costs, to enable limited
resources to be focused on property assets that will be retained in the longer-
term
• Address under-utilisation of key office accommodation and provide a
proportionate property estate that ensures members of the public can access the
services they need
• Provide potential opportunities for community ownership of surplus property
assets 
• Consider wider opportunities linked to existing and forthcoming regeneration
proposals, for example the recent £20 million allocation for Irvine town centre as
part of the Levelling Up Fund 
2.2  The Council’s most significant concentration of property assets is in Irvine, which
has therefore been the focus of the first phase of the property review work, taking a
whole locality approach. Officers have been working together to review the Council’s
property assets in Irvine to understand opportunities for remodelling of the estate to
accord with the above objectives. 
2.3  Extensive feasibility work, alongside a number of service engagement sessions with
key stakeholders, has been completed to develop the property rationalisation
concept, generate options, and assess costs, benefits and risks. The information
gathered from this work has led to identification of a set of recommendations for the
Council’s property estate within Irvine, for implementation on a phased basis. A
summary of each of the proposed phases is set out below. 
Phase 1A: Quarry Road Office & Trinity Church 
2.4 The first phase proposal is to vacate both the Quarry Road office block and the
Trinity Church building. The Council owns the office block located at Quarry Road
which is currently leased to KA Leisure, with a sub-lease to the Council’s Business
Support & Development Service. The office block was completed in 2019 and
provides an attractive, modern working environment, and there is expected to be
interest if it was marketed for lease or sale. 
2.5 The first step would be to relocate the Council’s Genealogy Team from the

Page 3

Townhouse to Irvine Library. This provides clear synergies between library services
and genealogy but will also free-up accommodation for KA Leisure staff from Quarry
Road to relocate to the Townhouse, meaning that they will be co-located with the
wider KA Leisure management team based at the Portal. 
2.6 The Council’s Business Support & Development Service currently located within
Quarry Road would be relocated to Cunninghame House. This would then allow
Quarry Road to be marketed. 
2.7 Quarry Road is currently leased from the Council by KA Leisure at a rental of £0.100m
per annum, with a sub-lease from KA Leisure to the Council for the Business Support &
Development Service accommodation at £0.030m per annum. It is anticipated that KA
Leisure would enter into a new lease for the required space at Irvine Townhouse. 
2.8 Works will be needed to separate the Quarry Road offices from the Circuit sports
centre and form a new reception space for KA Leisure to continue operating the Circuit
facility. These alteration works would not affect any immediate marketing exercise or
any new owner or lessee occupying the building before the works were fully completed. 
2.9 A final consideration is the original capital funding package for the construction of
Quarry Road. This included an element of Regeneration Capital Grant Fund monies,
which  has clawback arrangements if the building is sold. The nature of these
arrangements is being considered further with colleagues in Democratic Services. This
may restrict any sale of the building in the short to medium term but does not preclude
marketing of the building for lease. 
2.10 In relation to Trinity Church, North Ayrshire Council and Irvine Bay Regeneration
Company developed a conservation plan for Bridgegate in 2010 with Trinity Church
playing a key role. Funding was secured from Historic Environment Scotland’s
Conservation Area Regeneration Scheme in 2011 to support comprehensive repair
works to the main church and hall, along with conservation work on the tower and
spire.  The Ayrshire Community Trust (TACT) also secured funding from the Town
Centre Communities Capital Fund to transform the Annexe into a community hub. 
TACT initially occupied the Annexe, however the main building remained empty
despite several marketing attempts. In 2017, an award was secured an award from
the European Regional Development Fund (ERDF) through Transport Scotland’s
Low Carbon Travel and Transport Challenge Fund to develop an Active Travel Hub
in the former church. The Trinity Active Travel Hub opened during 2019 and
continues to operate.  The Equal supported employment service later moved into
the Annexe and delivers a range of services to support people with disabilities to
find long term employment. 
2.11 The proposal is for the Active Travel and Employability teams to vacate Trinity
Church and relocate to Cunninghame House. The building would then be marketed.
Earlier funding conditions for the refurbishment of the building, similarly to Quarry
Road, mean that the building may need to be leased.  It is understood that market
interest in the building may be limited at the current time. If no buyer/lessee can be
found, the property would be secured and regularly inspected in the meantime, with
a view to consideration via the Irvine Town Board through forthcoming Irvine Town
Centre regeneration plans aligned to the Long Term Plan for Towns Levelling Up
Fund allocation.

Page 4

2.12 The Galt House building was originally proposed to be included in this phase. A
partial vacation of Galt House has been completed, with some staff now relocated to
Bridgegate House. The next step in this process was to undertake internal
alterations within Bridgegate House in order to accommodate the services provided
by the Housing Advice Team (HAT). This work is proposed to be paused, resulting
in a saving of c.£0.166m. The works and associated investment would then be
incorporated into the remodelling of Cunninghame House (see phase two below),
allowing the Housing Advice Team to relocate and vacate the building as part of a
subsequent phase. Negotiations with two existing private tenants within Galt House
will also have to agree exit terms and timelines.  
2.13 The key steps and estimated timescales associated with Phase 1A proposals are
summarised in the following table: 
Key Milestones Forecasted Dates
1 Relocation of Genealogy services from the Townhouse to
Irvine Branch Library, including internal alterations to the
library
July 2024 – March 2025
2 Relocation of Business Support & Development services
from Quarry Road offices to Cunninghame House
September 2024
3 Relocation of Active Travel and Employability services from
Trinity Church to Cunninghame House
September 2024
4 Marketing of Trinity Church September 2024 –
March 2025
5 Marketing of Quarry Road offices September 2024 –
March 2025
6 Relocation of KA Leisure from Quarry Road offices to the
Townhouse
April 2025
7 Alterations to Quarry Road offices (works would not
preclude marketing or occupation of buyer/lessee)
April 2025 – March
2026 
Phase 1A costs and savings overview: 
Details Value (£)
Capital 
Alterations to Irvine Branch Library (50k)
Alterations to Quarry Road office/ Circuit (206k)
Potential Capital Receipt for Quarry Road office* 478k
Potential Capital Receipt for Trinity Church* 195k
TOTAL ESTIMATED CAPITAL RECEIPT 417k
Revenue 
Loss of rental income from Quarry Road (NALL lease) (100k)
Savings from BS&D office sub-lease 30k
Potential rental income for the Townhouse 50k
Savings from Quarry Road property running costs N/A
Savings from Trinity Church property running costs 37k
Savings from property maintenance £8.8k
TOTAL ESTIMATED REVENUE SAVINGS 25.8k
*Subject to review of grant funding arrangements- if the buildings cannot be disposed for
sale, they would be marketed for lease to provide a revenue income instead with a view to
disposal at a later date.

Page 5

Phase 1B: Relocate staff from Bridgegate House to Cunninghame House
2.14 The majority of staff based at Cunninghame House and Bridgegate House are
operating on an agile working pattern. This provides an opportunity to optimise
utilisation of available office accommodation in line with the objectives at paragraph
2.1. The office accommodation across Cunninghame House and Bridgegate House
has been mapped against future working requirements to understand the scale of
potential, while ensuring that sufficient office accommodation, civic space, meeting
space, storage facilities etc. are provided both for now and the future. 
2.15 This assessment has identified the opportunity for a phased closure of Bridgegate
House, starting with relocation of most staff on the upper floors of Bridgegate House
to Cunninghame House. In the meantime, essential staff would remain at
Bridgegate House in order to service the Customer Service Centre (CSC)
requirements on the ground floor of the building. The continued operation of the
CSC and retail units on the ground floor of Bridgegate House will ensure the
continuation of an active office and retail frontage in the town centre for the
timebeing. 
2.16 The future of the Bridgegate House building will be further considered, with the
Irvine Town Board, as part of the Irvine town centre regeneration proposals aligned
to the £20m Long Term Plan for Towns Levelling Up Fund allocation (see phase two
below). 
2.17 This phase will involve establishing a cross-service working group of staff to prepare
a detailed accommodation plan for Cunninghame House, which takes cognisance of
service needs and the works proposed under phase two below. There will be some
costs for relocation of staff and materials under this phase, anticipated to be
c.£0.050m. 
2.18 The key steps and predicted timescales associated with Phase 1B proposals are
summarised in the following table: 
Key Milestones Forecasted Dates
1 Form cross-service staff steering group and undertake a
series of engagement workshops
April 2024 – July 2024
2 Prepare detailed staff accommodation plan for
Cunninghame House (taking into account works proposed
under phase two below)
August 2024 – October
2024
3 Complete the relocation of office staff from Bridgegate and
within Cunninghame House 
November- December
2024
4 Isolate redundant services and unoccupied floors in
Bridgegate House
January 2025 
Phase 1C: Greenwood Conference Centre
2.19 The Council’s Greenwood Conference Facility was closed during the pandemic and
leased to the NHS. The NHS has since renounced the lease and vacated the site in
February 2024. It is proposed that the site remains closed and is marketed for sale. 
2.20 In order to ensure that the Council has suitable training and development facilities, it
is proposed that, as part of this phase, design work is commenced for re-
configuration of the 4th Floor East within Cunninghame House to provide a new

Page 6

training suite. Location of the facility on this floor would align with the existing cafe
provision.   
2.21 Currently, there is a 29.9kW Solar PV array at GCC generating a Feed-In Tariff
income of c.£2,500 per annum. Discussions would take place with Ofgem and the
Council’s energy supplier to relocate the panels and continue receiving income. 
2.22 This phase would also include design work for other reconfiguration works required
as part of phase two below. 
2.23 The key steps and estimated timescales associated with Phase 1C proposals are
summarised in the following table: 
Key Milestones Forecasted Dates
1 Marketing of Greenwood Conference Centre for disposal April 2024 – December
2024
2 Develop scheme designs for Cunninghame House Training
Suite, ICT alterations and CSC alterations (see phase two
below)
April 2024 – July 2024 
Phase 1C costs and savings overview: 
Details Value (£)
Capital 
Potential Capital Receipt for Greenwood Conference Centre 700k
TOTAL ESTIMATED CAPITAL INCOME 700k
Revenue 
Savings from Greenwood Conference Centre property running
costs
101k  
Savings from property maintenance costs 23.3k
TOTAL ESTIMATED REVENUE SAVINGS 124.3k   
Phase 2: Closure of Bridgegate House and Re-configuration of Cunninghame House
2.24 This would be the final phase of the Irvine Locality Property Review, and would
incorporate reconfiguration of Cunninghame House and associated works as
follows: 
• Creation of new Customer Service Centre, mirroring similar provision as
currently provided (and planned) at Bridgegate, including required interview
rooms
• Creation of new Training Suite on the 4th Floor East
• Provision of new ICT work room and storage area
• Addressing any immediate, existing property maintenance requirements in the
building, e.g. heating and ventilation that are required regardless of the Irvine
Locality Property Review work. Only the heating and ventilation costs are
included in the costs below. 
2.25 In light of forthcoming requirements for all public sector buildings to have ZDE (zero
direct emissions) by 2038, it is proposed that a detailed study is commissioned to
understand the measures and investment requirements for Cunninghame House to

Page 7

reach this standard. This work can then be considered, if viable, as part of the
specification of the phase two works above. 
2.26 Following completion of the above works, all remaining staff in Bridgegate House
(i.e. those not relocated as part of phase 1B) and Galt House will be relocated. 
2.27 The ICT Disaster Recovery servers will relocate to an alternative Council building.
Retail units at Bridgegate House would also be vacated. 
2.28 The future use of Bridgegate House will be considered as part of the Irvine town
centre regeneration work noted above. Market research shows a low likelihood of
achieving any interest or capital receipt for Bridgegate House, therefore an
allowance for demolition has been made at this stage. 
2.29 The key steps and estimated timescales associated with Phase 2 proposals are
summarised in the following table: 
Key Milestones Forecasted Dates
1 Alterations to form new Disaster Recovery facility (out-with
Bridgegate House) and relocate ICT equipment, test &
commission
August 2024 – October
2024
2 Repairs and remedial works to existing high-priority
property maintenance issues at Cunninghame House
September 2024 –
December 2024
3 Alterations to 4th Floor West to form new Training Suite January 2025 –
September 2025
4 Alterations to Ground West to form ICT secure storage and
build area, and enhance staff welfare facilities
September 2025 –
February 2026
5 Alterations to Ground East to form new Customer Service
Centre and alter reception space
February 2026 –
December 2026
6 Marketing of Galt House for disposal September 2026
7 Review of Bridgegate House options as part of Irvine town
centre regeneration masterplan
Ongoing
8 Relocate remaining staff from Bridgegate House and Galt
House
January 2027 
Phase 2 costs and savings overview: - 
Details Value (£)
Capital 
Alterations to Cunninghame House Ground East (Customer
Service Centre)
(311k)
Alterations to Cunninghame House Ground West (ICT) (121k)
Heating repairs to Cunninghame House (Ground West & 4 West) (313k)
Year 1 high-priority backlog maintenance (198k)
Alterations to Fourth Floor East (Training Suite) (436k)
Relocation of workforce costs (30k)
Relocation of Disaster Recovery facility (187k)
Potential Capital Receipt for Galt House 280k
Potential Capital Receipt for Bridgegate House  TBC
Estimated demolition costs  (800k)
TOTAL ESTIMATED CAPITAL INVESTMENT REQUIREMENT (2.116M)

Page 8

Revenue 
Loss of rental income from Bridgegate House (retail and masts) (140k)
Loss of rental income from Galt House (retail) (15k)
Savings from Bridgegate House property running costs 265k
Savings from Galt House property running costs* 35k
Savings from property maintenance 61.7k
TOTAL ESTIMATED REVENUE SAVINGS 206.7k
*These costs have already been removed from the budget through a previously agreed
saving. 
2.30 A summary of all capital costs, capital receipts, revenue savings and carbon
emissions savings are provided in the table below. It should be noted that these
figures are all high-level estimates at this stage and will be subject to change
following detailed design and implementation work. 
Rationalisation
Work Stream
Revenue Capital Annual
Carbon
Emissions
(tCO2e/year)
Net Property
Running Cost
Savings
(£)
Property
Maintenance
Costs Savings
(£)
Investment
Requirements
(£)
Potential
Capital
Receipts
(£)
10yr PLI
Savings
(£)
Phase 1A 17k 8.8k 0.256m 673k 400k* 12
Phase 1B - - - - - -
Phase 1C 101k 23.3k - 700k 212k 37
Phase 2 145k 61.7k 2.396m 280k 1.347m 237
TOTAL 0.357m 2.652m 1.653m 1.959m 286
* PLI information not held for Trinity Church and the Townhouse therefore assumed lifecycle investment data used. 
2.31 The table above shows that the Irvine Locality Property Review potential property
cost savings may be in the order of £0.357m per annum, with total capital receipts
estimated at £1.653m, and avoided capital expenditure of £1.959m. This is set
against capital investment costs estimated at £2.652m to deliver the proposals. 
Governance
2.32 Subject to Cabinet approval, the development and implementation of the Irvine
Locality Property Review recommendations set out within this report would be led by
a cross-service working group, remitted to oversee: 
• Stakeholder communication & engagement 
• Preparation and implementation of detailed project plans
• Budget management
• Programme management
• Risk management
• Development of reviews for other North Ayrshire localities 
3. Proposals 
3.1 That Cabinet approves the Irvine Locality Property Review recommendations for
implementation.

Page 9

4. Implications/Socio-economic Duty 
Financial 
4.1 An allocation of £2.500m was made within the Council’s Capital Investment
Programme aligned to the forthcoming locality based review, as part of the annual
budget setting process on 28th February 2024. A range of estimates have been
provided in relation to capital costs, capital receipts, and revenue savings within this
report. These will be further refined as detailed work develops. 
Human Resources 
4.2 The resources for programme management of the proposed recommendations will
require additional resources, which will be met from the Council’s Change and
Service Redesign Fund, and/or from capitalisation of employee costs from the
£2.500m allocation noted at paragraph 4.1 above. 
Legal 
4.3 There are a number of legal implications arising from the report, including in relation to
lease arrangements for the retail units and telecommunications masts at Bridgegate
House, and also for lease arrangements with KA Leisure at Quarry Road and Irvine
Townhouse.   
Equality/Socio-economic 
4.4 There are no equality/socio-economic implications arising from the report. 
Climate Change and Carbon 
4.5 The proposals set out within this report are designed to have a direct impact on
reduction of carbon emissions from the Council’s property estate and support the
Council’s ambitions to be net zero by 2030. 
Key Priorities 
4.6 The proposals would support delivery of the Council Plan priority in relation to tackling
climate change and becoming a sustainable Council. 
Community Wealth Building 
4.7 Any tender documents for physical works would include provision for Community
Wealth Building benefits.

Page 10

5. Consultation 
5.1 A range of services were consulted in the preparation of this report. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact David W. Hammond, Head of Sustainability,
Corporate Property & Transport, on (01294) 324514. 
Background Papers - None