Democracy Spraffa

Capital Programme and Treasury Management Performancce to 31 January 2024

North Ayrshire Council · 19 March 2024
Back to Cabinet — 19 March 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

NORTH AYRSHIRE COUNCIL 
19 March 2024 
Cabinet 
Title:    Capital Programme and Treasury Management Performance
to 31 January 2024 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2023/24 and the associated Treasury
Management performance to 31 January 2024. 
Recommendation:  That Cabinet agrees to: 
(a)  note the revisions to budgets outlined in the report; and
(b)  note (i) the General Services and HRA revised budgets at 31
January 2024; and (ii) the forecast expenditure to 31 March
2024. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2023/24 to 2030/31 was
approved by Council on 1 March 2023. The Housing Revenue Account (HRA) Capital
Investment Programme 2023/24 sits within the updated HRA Business Plan and was
approved by Council on 15 February 2023. 
1.2  This report identifies the current programme for 2023/24, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 31
January 2024 (Period 10) and forecast expenditure to 31 March 2024. 
1.3   At Period 10 the General Fund is forecasting a net breakeven position against a
revised budget of £86.766m. The HRA is forecasting a projected underspend of
(£1.899m) against a revised budget of £37.371m. 
1.4  Within the General Fund, adjustments to funding have resulted in a net reduction to
the overall capital programme of (£0.104m). These are primarily related to additional
Scottish Government funding of £3.791m to support the Ayrshire 5GIR project, offset
by the transfer of (£4.000m) of previously notified funding to Revenue to support the
2023/24 SJC pay settlement. 
1.5 Reviews of individual project plans have identified a number of adjustments to the
current profiles. As a result, (£10.753m) has been reprofiled for delivery in 2024/25
and beyond. This has been partly offset by the acceleration of £0.544m to 2023/24
from future years.

Page 2

1.6 Within the HRA, a further review of delivery timescales has identified a requirement to
re-profile £4.853m of works for delivery in 2024/25 and beyond. This has been partly
offset by the acceleration £1.560m to 2023/24 from future years.   
1.7 Major risks to the forecast position continue to arise from ongoing cost volatility and
the uncertainty around potential future changes to local authority capital accounting
arrangements. In terms of cost volatility, individual project costs will continue to be
monitored closely with cost increases met initially from the additional flexibility built
into the programme. Any costs in excess of the current level of flexibility provision will
require to be funded from within existing resources. In addition, COSLA and the
Directors of Finance Group continue to engage with the Scottish Government to
ensure that the potential impact of any proposed regulatory changes on local
government capital investment programmes are given due consideration. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2023/24 General Services budget: 
2.2 (a) Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
2023/24
£m
Budget as at 30 November 2023 97.079     
a) Changes to Funding 3.361        
b) Other Revisions to the Programme (3.465)      
Revised Budget 96.975     
b) Alterations to phasing of projects:-
2023/24 to 2024/25 (10.753)         
2024/25 to 2023/24 0.544        
Budget as at 31 January 2024 86.766     
Funding Body Amount Project
Scottish Government £3.791m Ayrshire 5GIR
SPT Grant Downturn (£0.140m) B714 Active Travel Links
SPT Grant Downturn (£0.087m) Bus Corr idor Improvements
SPT Grant Downturn (£0.020m) Cumbrae Ferry & Bus Stop
SUSTRANS downturn (£0.100m) Saltcoats Old Cal Railway Ph1 & 2
SUSTRANS downturn (£0.083m) Links to Eglinton Park
Total £3.361m

Page 3

2.3 (b) Other Revisions to the Programme 
The programme has also been updated to reflect the undernoted adjustments: 
2.4 (c) Alterations to the Phasing of Projects 
A further review of individual project plans, taking cognisance of the current levels of
volatility within the construction sector, has identified a requirement to re-profile
(£10.753m) of works for delivery in 2024/25 and beyond: 
Funding Source Amount Project
CFCR £0.410m Coastal Play Parks
CFCR £0.065m Park Improvements
CFCR £0.058m Street Furniture
Capital Receipts £0.002m Sale of Vehicles
Prudential Borrowing (£4.000m) Transfer to Revenue for 23/24 Pay Settlement
Total (£3.465m)
Service Amount Project
Chief Executives (£0.190m) ICT Investment Fund
(£0.016m) Telephony
(£0.206m)
Communities (£0.240m) Kilwinning Learning Environment
(£0.223m) Marress House
(£0.137m) CO2 Monitors
(£0.100m) Lockhart Campus
(£0.027m) Universal Free School Meals
(£0.727m)
HSCP (£0.355m) Residential & Respite Unit
(£0.254m) 47 West Road
(£0.017m) Trindlemoss
(£0.626m)
Place (£6.042m) Solar PV Nethermains
(£3.791m) Ayrshire 5GIR
(£1.356m) Solar PV Shewalton
(£0.530m) Fleet Decarbonisation
(£0.511m) Nature Restoration Fund
(£0.395m) Lochshore Hub Play Area
(£0.380m) Lighting
(£0.350m) CCTV Review
(£0.235m) PBIP Kilwinning Abbey
(£0.180m) Access Path Network Prog

Page 4

These adjustments have been partly offset by the acceleration of £0.544m of
expenditure to 2023/24 from future years. 
2.5 These adjustments have resulted in a revised 2023/24 budget at 31 January 2024 of
£86.766m. 
Service Amount Project
Place (continued) (£0.140m) Montgomerie Park Neighbourhood Centre
(£0.132m) VDLF - Harbour Master Office
(£0.130m) VDLF Kyle Road Phase 2
(£0.115m) Digital SIPP Great Harbour
(£0.100m) Dockhead St Saltcoats
(£0.090m) Lochshore Kilbrinie
(£0.080m) Island Infrastructure Fund
(£0.077m) Irvine High Street
(£0.071m) AGD - Great Harbour
(£0.065m) VDLF Development Work
(£0.060m) Lochshore Garnock Hub
(£0.059m) Montgomerie Park Masterplan
(£0.258m) Other Minor Adjustments
(£15.147m)
Corporate £5.953m Sensitivity Adjustment
£5.953m
Total (£10.753m)
Service Amount Project
Communities £0.426m Ardrossan New Build
£0.040m Other Minor Adjustments
£0.466m
Place £0.059m Property Lifecycle Investment
£0.019m Other Minor Adjustments
£0.078m
Total £0.544m

Page 5

2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of (£10.313m) from the revised budget,
including: 
Category Amount Comments
Borrowing £9.385m Reduced and rephased aligned to projected
expenditure
CFCR (£1.025m) Additional CFCR Contribution
Capital Grants £1.389m Rephased and additional government grants
Other Grants £0.574m Rephased and revised contributions
Capital Receipts (£0.010m) Realigned capital receipts
Total £10.313m
18.349 0.799 0.757 93.126 2.900 115.931
21.681 0.892 2.265 107.802 (25.388) 107.252
22.099 0.771 2.265 102.971 (22.274) 105.832
18.466 4.711 2.460 84.085 (12.643) 97.079
18.205 0.505 1.834 72.912 (6.690) 86.766
(0.144) (0.294) 1.077 (20.214) (9.590) (29.165)
Approved Programme
Movement
Programme @ P5
Programme @ P3
Programme @ P10
Programme @ P8

Page 6

2.8 Projected Capital Expenditure to 31 March 2024 
The projections are summarised by service in the following table:   
2.9 A net breakeven position is projected. Information on the progress of all projects can
be found in Appendix 1. 
2.10 Although not formally reflected in the financial performance reports at this time due to
ongoing uncertainty, areas of cost risk have been identified across a number of
projects. These risks are linked to a number of factors, including cost volatility linked
to inflationary pressures; limited availability of contractors, supply chain issues and
material shortages which are impacting on tender returns and the cost of materials;
delays resulting from interaction with external agencies and regulators; and other
contract management issues across a number of projects. Specific projects where
cost risks have been identified, or are anticipated, include Moorpark Primary,
Montgomerie Park Primary, Ardrossan Campus, Upper Garnock Flood Prevention
Scheme, Millport Coastal Flood Prevention Scheme, Largs Sea Wall, Ardrossan North
Shore and Ardrossan Harbour Interchange. While some mitigation has been built into
the Capital Programme in the form of flexibility budgets, totalling £10m over the next
few years, cost pressures may exceed this provision. These risks will be quantified as
individual projects are completed and tendering exercises are finalised, with the
impact on the costs of the programme being monitored and reported to Cabinet as
appropriate. It is recognised, however, that any costs in excess of the current level of
flexibility provision will require to be funded from within existing resources. 
Revised
Budget
2023/24
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2023/24
Projected
Expenditure
/ Income to
31 March
2024
Projected
Variance
Over /
(Under)
£m £m £m £m £m £m
Expenditure
Communities 18.466 - (0.261) 18.205 18.205 -
Chief Executive 0.711 - (0.206) 0.505 0.505 -
Health and Social Care Partnership 2.460 - (0.626) 1.834 1.834 -
Place 88.085 (0.104) (15.069) 72.912 72.912 -
Other including Flexibility (12.643) - 5.953 (6.690) (6.690) -
Total Expenditure 97.079 (0.104) (10.209) 86.766 86.766 -
Income
General Capital Grant (38.482) - - (38.482) (38.482) -
Specific Capital Grant (12.918) (3.791) 5.180 (11.529) (11.529) -
Capital Funded from Current Revenue (0.380) (1.025) - (1.405) (1.405) -
Capital Receipts (0.527) (0.010) - (0.537) (0.537) -
Other Grants & Contributions (3.890) 0.430 0.144 (3.316) (3.316) -
Prudential Borrowing (40.882) 4.500 4.885 (31.497) (31.497) -
Total Income (97.079) 0.104 10.209 (86.766) (86.766) -

Page 7

2.11 In addition to the risks identified in relation to individual projects, significant financing
risks continue to be identified in relation to the overall affordability of the capital
investment programme due to the increased cost of borrowing and proposed changes
to capital and loans fund accounting regulations currently being considered by the
Scottish Government. Proposals currently under consideration include limitations to
the methodology used to calculate the annual Loans Fund repayments for the
financing of capital investments. If the current annuity method is withdrawn and
replaced with straight line charges over the life of the advance this could have a
significant impact on the affordability of the current capital investment programme. 
2.12 The Scottish Government have also indicated a desire to undertake a wider review of
local authority capital accounting arrangements which could have unforeseen
implications for local authority investment programmes. COSLA and the Directors of
Finance group continue to engage with the Scottish Government, challenging the
proposed changes to the regulations and the need for a wider review of capital
accounting arrangements. 
Housing Revenue Account 
2.13 The following table outlines the movements in the 2023/24 HRA Capital budget: 
2.14 (a) Alterations to the Phasing of Projects 
A review of the timescale for delivery of capital projects has identified a requirement to
re-profile (£4.853m) of works for delivery in 2024/25 and beyond, including: 
2023/24
£m
Budget as at 30 November 2023 40.664       
a) Alterations to phasing of projects:-
2023/24 to 2024/25 (4.853)             
2024/25 to 2023/24 1.560         
Budget as at 31 January 2024 37.371       
Category Amount Project
New Builds (£1.200m) James Reid Site
(£0.972m) Garnock Academy Site
(£0.479m) Unallocated Regeneration Block
(£0.428m) Montgomerie Park
(£0.350m) Corsehillhead
(£0.300m) Kings Arms - High Street
(£0.015m) Acquisitions - Open Market
(£3.744m)

Page 8

This has been partly offset by the acceleration of £1.560m of project expenditure for
delivery during 2023/24, including: 
2.15 These adjustments have resulted in a revised 2023/24 budget at 31 January 2024 of
£37.371m. 
2.16 The impact on budgeted funding is reduced Prudential Borrowing aligned to the
revised programme: 
Category Amount Project
Improvements (£0.447m) Solar Panels
(£0.240m) Pathfinder Project
(£0.203m) Heating
(£0.083m) Roofing
(£0.973m)
Other Capital Works (£0.086m) Estates Based Regeneration
(£0.050m) Lift Replacement
(£0.136m)
Total (£4.853m)
Category Amount Project
New Builds £0.676m St Marys Primary Largs
£0.200m Laburnum Av/Newhouse Dr
£0.035m Bourtreehill Village
£0.911m
Improvements £0.046m Electrical Wiring
£0.041m Wallfloor Rendering
£0.028m Window Replacement
£0.115m
Other Capital Works £0.534m Sheltered Housing Units
£0.534m
Total £1.560m
Category Amount Comments
Borrowing £3.293m Reduction aligned to projected expenditure
Total £3.293m

Page 9

2.17  Projected Capital Expenditure to 31 March 2024 
The projections are summarised in the following table:   
2.18 A variance of (£1.899m) is projected within the HRA capital programme for 2023/24
arising from revisions to a number of projects, including: 
The most significant movements since the previous reporting period are in relation to: 
•  a (£0.334m) reduction in the projected overspend on EWI, reflecting a reduction in
the number of units now projected for completion this year; and 
• a (£0.539m) increase in the reported underspend on the demolition of the High
Flats following the completion of the project.
Approved
Budget
2023/24
Carry
Forwards
and
Adjustments
Revised
Budget
2023/24
Projected
Expenditure /
Income to 31
March 2024
Projected
Variance
Over /
(Under)
Service £m £m £m £m £m
Expenditure
Housing Revenue Account 40.664 (3.293) 37.371 35.472 (1.899)
Total Expenditure 40.664 (3.293) 37.371 35.472 (1.899)
Income
CFCR (5.151) - (5.151) (5.151) -
Capital Grants (6.785) - (6.785) (6.785) -
Use of Reserves (4.065) - (4.065) (4.065) -
Affordable Housing Contribution (2.445) - (2.445) (2.445) -
Prudential Borrowing (22.218) 3.293 (18.925) (17.026) 1.899
Total Income (40.664) 3.293 (37.371) (35.472) 1.899
Project Variance Comments
High Flats Demolition (£0.643m) Project Complete
Heating (£0.552m) Scope of works reduced
Wet Rooms & Bathrooms (£0.386m) Scope of works reduced
Health and Safety Works (£0.207m) Budget no longer required
Kitchen Voids (£0.166m) Scope of works reduced
Friars Lawn (£0.114m) Project Complete
St Michael's Wynd (£0.101m) Project Complete
Parkhall & Kirkhall Asbestos (£0.017m) Budget no longer required
Major Improvements (£0.006m) Budget no longer required
Newhouse Drive (Regen 1b) (£0.005m) Budget no longer required
EWI £0.012m Increased Unit Costs
Marress House Refurb £0.012m Project Complete
Dalrymple Place £0.017m Project Complete
St Colms Largs £0.021m Project Complete
Springvale £0.107m Project Complete
Brathwic Terrace £0.129m Project Complete
Total (£1.899m)

Page 10

2.19 Further cost pressures resulting from inflationary and supply chain issues continue to
be monitored and a review of the potential impact on the Business Plan and Capital
Programme will be undertaken to address any identified issues. Further information
on the progress of all projects can be found in Appendix 2. 
3. Proposals 
3.1 That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; and
(b)  note (i) the General Services and HRA revised budgets at 30 November 2023;
and (ii) the forecast expenditure to 31 March 2024. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our
investment on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None.

Page 11

5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Programme Performance to 31 August 2023 – Cabinet 7 November 2023
Treasury Management and Investment Mid-Year report 2023/24 – Cabinet 7 November
2023

Page 12

North Ayrshire Council Capital Statement 2023/24 Appendix 1
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Brought / Carry
Forward to 2024/25
Total Revised
Budget 2023/24
Year to Date Budget
2023/24
Actual Expenditure to
31 January 2024
Year to date
Variance 2023/24
Projected Expenditure to
31st March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 16,349,969 16,142,929 16,349,969 0 550,594 (223,090) 327,504 0 343,554 343,554 327,504 0 0
Primary Schools 45,955,442 23,365,634 45,955,442 0 15,377,417 (18,200) 15,359,217 0 15,197,981 15,197,981 15,359,217 0 0
Secondary Schools 82,214,567 4,569,039 82,214,567 0 1,594,172 185,742 1,779,914 0 652,364 652,364 1,779,914 0 0
Special Education 25,343,637 25,243,710 25,343,637 0 138,595 (99,927) 38,668 0 38,668 38,668 38,668 0 0
Schools Other 880,194 772,697 880,194 0 728,737 (105,285) 623,452 0 621,240 621,240 623,452 0 0
Information & Culture 113,479 6,563 113,479 0 106,916 0 106,916 0 0 0 106,916 0 0
Completed Projects 43,419,379 43,394,998 43,419,379 0 3,679 0 3,679 0 (20,702) (20,702) 3,679 0 0
SUB TOTAL 214,276,667 113,495,569 214,276,667 0 18,500,110 (260,760) 18,239,350 0 16,833,105 16,833,105 18,239,350 0 0
Chief Executive
Council IT Strategy 8,797,380 2,786,384 8,797,380 0 711,645 (205,550) 506,095 0 302,649 302,649 506,095 0 0
SUB TOTAL 8,797,380 2,786,384 8,797,380 0 711,645 (205,550) 506,095 0 302,649 302,649 506,095 0 0
Health & Social Care
Management & Support 1,832,058 1,124,677 1,832,058 0 1,421,922 (254,187) 1,167,735 0 852,494 852,494 1,167,735 0 0
Housing Non HRA 656,571 542,561 656,571 0 656,571 0 656,571 0 542,561 542,561 656,571 0 0
Adults 4,608,078 4,590,773 4,608,078 0 18,047 (16,755) 1,292 0 742 742 1,292 0 0
Young People 5,579,718 5,224,534 5,579,718 0 363,177 (355,184) 7,993 0 7,993 7,993 7,993 0 0
SUB TOTAL 12,676,425 11,482,544 12,676,425 0 2,459,717 (626,126) 1,833,591 0 1,403,789 1,403,789 1,833,591 0 0
Place
Roads 113,754,874 47,382,784 113,754,874 0 40,177,663 (527,467) 39,650,196 0 25,704,290 25,704,290 39,650,196 0 0
Streetscene 8,424,557 4,809,566 8,424,557 0 1,400,510 102 1,400,612 0 1,129,426 1,129,426 1,400,612 0 0
Transport 4,760,064 2,998,118 4,760,064 0 3,997,076 (530,165) 3,466,911 0 2,735,130 2,735,130 3,466,911 0 0
Waste Services 13,321,491 13,272,542 13,321,491 0 48,949 (48,949) 0 0 0 0 0 0 0
Renewable Energy 14,660,789 2,153,075 14,660,789 0 9,266,377 (7,909,499) 1,356,878 0 930,858 930,858 1,356,878 0 0
Office Accommodation 2,398,377 1,276,971 2,398,377 0 1,571,557 58,596 1,630,153 0 1,276,971 1,276,971 1,630,153 0 0
Other Property 1,672,164 812,657 1,672,164 0 434,275 (13,926) 420,349 0 315,768 315,768 420,349 0 0
Other Housing 470,000 0 470,000 0 381,025 (350,000) 31,025 0 (88,975) (88,975) 31,025 0 0
Economic Development & Regeneration172,073,059 33,931,791 172,073,059 0 31,056,486 (5,708,623) 25,347,863 0 8,191,855 8,191,855 25,347,863 0 0
Completed Projects 6,355,261 6,276,590 6,355,261 0 40,595 (39,628) 967 0 (35,991) (35,991) 967 0 0
SUB TOTAL 337,890,637 112,914,093 337,890,637 0 88,374,513 (15,069,559) 73,304,954 0 40,159,331 40,159,331 73,304,954 0 0
Other
Other 8,633,036 0 8,633,036 0 1,884,036 0 1,884,036 0 0 0 1,884,036 0 0
SUB TOTAL 8,633,036 0 8,633,036 0 1,884,036 0 1,884,036 0 0 0 1,884,036 0 0
Uncertainty / Sensitivity Adjustment* (9,001,848) (9,001,848) (9,001,848)
Total Project Expenditure 582,274,144 240,678,590 582,274,144 0 111,930,021 (25,163,843) 86,766,178 0 58,698,874 58,698,874 86,766,178 0 0
Total Project Income (111,930,021) 25,163,843 (86,766,178) (48,789,701) (48,789,701) 0 (86,766,178) 0 0
Total Net Expenditure 0 0 0 (48,789,701) 9,909,173 58,698,874 0 0 0
* Sensitivity adjustment of 10% or 25% based on source and reliability of expenditure projections
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2023/24
Year Ended 31st March 2024
Period 10
The following classifications have been used to highlight delivery performance
against original timescales set

Page 13

Revised Budget
23/24 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 68,291,931 5,814,577 2,683,086 76,789,594 (25,452,169) 51,337,425 40,499,362 (10,838,063)
SUB TOTAL 68,291,931 5,814,577 2,683,086 76,789,594 (25,452,169) 0 51,337,425 0 40,499,362 (10,838,063)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Early Learning & Childcare 0 26,594 59,206 85,800 1 85,801 85,801 85,801 0
Cycling / Walking /Safer Streets 1,159,954 (117,150) 271,000 1,313,804 30,000 1,343,804 301,464 1,343,804 0
Vacant & Derelict Land Funding 3,857,216 403,874 198,048 4,459,138 (1,413,630) 3,045,508 4,459,137 2,533,187 (512,321)
UK Government Grant - AGD 3,653,000 (98,741) 3,554,259 (2,125,602) 1,428,657 74,116 1,435,431 6,774
Town Centre Regeneration 0 65,691 140,000 205,691 (1) 205,690 205,690 205,690 0
Annickbank - Vacant & Derelict Land Investment Programme 400,000 400,000 0 400,000 400,000 400,000 0
Millport Town Hall Regeneration 0 (31,995) 252,529 220,534 0 220,534 220,534 220,534 0
Millport Town Hall Phase 2 94,022 339,498 433,520 0 433,520 433,520 433,520 0
Garrison House Project 730,998 730,998 0 730,998 0
Ardrossan Promenade 788,000 788,000 0 788,000 763,000 788,000 0
Islands Pit Stops 20,000 520,000 540,000 (500,000) 40,000 540,000 40,000 0
Islands Cost Crisis Emergency Fund 17,000 17,000 0 17,000 17,000 17,000 0
Place Based Investment Programme 0 622,801 948,836 1,571,637 256,000 1,827,637 2,332,637 1,207,171 (620,466)
UK Shared Prosperity Fund 98,414 98,414 202,330 300,744 300,744 300,744 0
Island Infrastructure Fund 0 140,373 140,373 1 140,374 140,374 60,000 (80,374)
Dyemill Bike Park Project 220,625 220,625 0 220,625 0
B714 Improvements 500,000 322,741 822,741 428,054 1,250,795 1,250,795 1,250,795 0
Road Safety Improvement Fund 215,647 215,647 0 215,647 0
Digital-SIPP Great Harbour 114,883 114,883 114,883 0 (114,883)
Ayrshire 5GIR 3,791,000 3,791,000 1,356,835 0 (3,791,000)
2-4 Boyle Street Hostel 31,025 31,025 0 31,025 31,025 31,025 0
CO2 Monitors in Schools 0 0 76,651 76,651 76,651 9,358 (67,293)
Capital Grants
Flooding 20,525,000 20,525,000 0 20,525,000 0 20,525,000 0
General Capital Grant 15,179,000 15,179,000 2,778,000 17,957,000 32,894,500 17,957,000 0
SUB TOTAL 45,105,170 1,896,235 3,615,531 50,616,936 4,573,957 0 55,190,893 45,998,706 50,011,330 (5,179,563)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 0 0 0 0 0 0 0 300,000 0 0
CFCR 0 0 0 0 1,404,729 0 1,404,729 1,404,729 1,404,729 0
Grants & Contributions 2,068,411 632,323 301,603 3,002,337 457,699 0 3,460,036 1,002,464 3,315,667 (144,369)
Capital Receipts 465,555 0 0 465,555 71,383 0 536,938 83,802 536,938 0
SUB TOTAL 2,533,966 632,323 301,603 3,467,892 1,933,811 0 5,401,703 2,790,994 5,257,334 (144,369)
TOTAL CAPITAL PROGRAMME FUNDING 115,931,067 8,343,135 6,600,220 130,874,422 (18,944,401) 0 111,930,021 48,789,701 95,768,026 (16,161,995)
23/24 Budget at
Capital Refresh
Mar 2023
Capital Programme Funding 2023/24
Projected Income
to 31st March
2024
Approved budget
at Period 1 used
as revised starting
point 2023/24
Actual Income to 31
January 2024Funding Description
Carry Forward
from 2022/23
Changes after
Capital Refresh Mar
2023
Total Changes in
Year
Changes at
Capital Refresh
Mar 2024

Page 14

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date Budget
2023/24
Actual Expenditure
to 31 January 2024
Year to date Variance
2023/24
Projected
Expenditure to 31
March 2024
Actual Over/ (Under)
Spend for 2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
KILMORY EARLY YEARS 57,108 65,190 57,108 0 28,921 0 37,003 37,003 28,921 0 0 Complete Complete Complete Complete Complete
ST PETERS EARLY YEARS 1,261,310 1,273,594 1,261,310 0 17,583 0 29,867 29,867 17,583 0 0 Complete Complete Complete Complete Complete
BEITH PS EARLY YEARS 341,180 341,180 341,180 0 1,417 0 1,417 1,417 1,417 0 0 Complete Complete Complete Complete Complete
WEST KILBRIDE EARLY EARLY YEARS 226,562 226,562 226,562 0 1,507 0 1,507 1,507 1,507 0 0 Complete Complete Complete Complete Complete
FAIRLIE EARLY YEARS 208,220 208,220 208,220 0 3,100 0 3,100 3,100 3,100 0 0 Complete Complete Complete Complete Complete
CUMBRAE EARLY YEARS 41,339 41,339 41,339 0 1,155 0 1,155 1,155 1,155 0 0 Complete Complete Complete Complete Complete
PIRNMILL EARLY YEARS 78,680 78,680 78,680 0 6,834 0 6,834 6,834 6,834 0 0 Complete Complete Complete Complete Complete
SHISKINE EARLY YEARS 127,013 142,324 127,013 0 0 0 15,311 15,311 0 0 0 Complete Complete Complete Complete Complete
CORRIE EARLY YEARS 29,405 29,337 29,405 0 963 0 895 895 963 0 0 Complete Complete Complete Complete Complete
LAMLASH EARLY YEARS 15,000 4,001 15,000 0 14,123 0 3,124 3,124 14,123 0 0 Complete Complete Complete Complete Complete
BRODICK EARLY YEARS 364,857 364,358 364,857 0 10,198 0 9,698 9,698 10,198 0 0 Complete Complete Complete Complete Complete
MARRESS HOUSE 4,010,310 3,781,160 4,010,310 0 450,000 0 220,850 220,850 226,910 (223,090) (223,090) 22-Jul-22 30-May-24 Construction On Target Significantly off target Contractor Delays
Other Nursery Education
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,085,147 3,083,147 3,085,147 0 14,793 0 12,793 12,793 14,793 0 0 Complete Complete Complete Complete Complete
Total Nursery Education 16,349,969 16,142,929 16,349,969 0 550,594 0 343,554 343,554 327,504 (223,090) 0 (223,090)
Primary Schools
MOORPARK PRIMARY 12,149,441 10,592,368 12,149,441 0 5,612,892 0 4,055,819 4,055,819 5,612,892 0 0 31-Jan-24 31-Jan-24 Construction On Target Slightly off target  Further information on the delivery status is awaited from
the contractor
MONTGOMERIE PARK SCHOOL 23,448,999 12,158,004 23,448,999 0 9,303,600 0 11,062,005 11,062,005 9,312,399 8,799 8,799 01-Aug-24 01-Aug-24 Construction On Target On Target
UNIVERSAL FREE SCHOOL MEALS EXPANSION 3,214,757 0 3,214,757 0 255,385 0 0 0 255,385 0 0 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM ARDEER PRIMARY SCHOOL 22,500 1,155 22,500 0 22,500 0 1,155 1,155 21,817 (683) (683) 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BEITH PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 0 (22,500) (22,500) 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BRODICK PRIMARY SCHOOL 144,178 124,065 144,178 0 22,844 0 2,732 2,732 2,732 (20,112) (20,112) Complete Complete Complete Complete Complete
UFSM CORRIE PRIMARY SCHOOL 53,977 53,977 53,977 0 1,182 0 1,182 1,182 1,182 0 0 Complete Complete Complete Complete Complete
UFSM CORSEHILL PRIMARY SCHOOL 60,000 219 60,000 0 0 0 219 219 9,375 9,375 9,375 31-Aug-25 31-Aug-25 Tender On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 90,000 0 90,000 0 0 0 0 0 5,000 5,000 5,000 31-Aug-25 31-Aug-25 Tender On Target On Target
UFSM GLEBE PRIMARY SCHOOL 2,046,397 2,528 2,046,397 0 2,528 0 2,528 2,528 2,528 0 0 31-Jul-28 31-Jul-28 Tender On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 22,500 1,091 22,500 0 22,500 0 1,091 1,091 22,500 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM HAYOCKS PRIMARY SCHOOL 82,500 234 82,500 0 0 0 234 234 10,091 10,091 10,091 31-Aug-25 31-Aug-25 Development On Target On Target
UFSM KILMORY PRIMARY SCHOOL 60,000 47,487 60,000 0 60,000 0 47,487 47,487 54,987 (5,013) (5,013) 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,540 1,463 2,082,540 0 1,463 0 1,463 1,463 1,463 0 0 31-Aug-28 31-Aug-28 Tender On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 22,500 998 22,500 0 22,500 0 998 998 17,660 (4,840) (4,840) 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM SHISKINE PRIMARY SCHOOL 6,616 10,135 6,616 0 544 0 4,063 4,063 544 0 0 Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,252,504 204,013 2,252,504 0 1,979 0 (2,359) (2,359) 3,662 1,683 1,683 31-Jul-27 31-Jul-27 On Site On Target On Target
UFSM WHITING BAY PRIMARY SCHOOL 25,000 19,363 25,000 0 25,000 0 19,363 19,363 25,000 0 0 30-Sep-23 30-Sep-23 Construction On Target On Target
Total Primary Education 45,955,442 23,365,634 45,955,442 0 15,377,417 0 15,197,981 15,197,981 15,359,217 (18,200) 0 (18,200) 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,491,322 2,805,435 0 378,401 0 64,288 64,288 138,338 (240,063) (240,063) 31-Mar-24 30-May-24 Construction On Target On Target
ARDROSSAN NEW BUILD 79,409,132 2,077,718 79,409,132 0 1,215,771 0 588,076 588,076 1,641,576 425,805 425,805 31-Aug-26 31-Aug-26 In Development On Target On Target
Total Secondary Education 82,214,567 4,569,039 82,214,567 0 1,594,172 0 652,364 652,364 1,779,914 185,742 0 185,742
Special Education
LOCKHART CAMPUS 25,343,637 25,243,710 25,343,637 0 138,595 0 38,668 38,668 38,668 (99,927) (99,927) Complete Complete Snagging Complete Complete
Total Special Education 25,343,637 25,243,710 25,343,637 0 138,595 0 38,668 38,668 38,668 (99,927) 0 (99,927)
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 159,315 298,000 0 146,543 0 7,858 7,858 9,358 (137,185) (137,185) 31-Mar-25 31-Mar-25 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 582,194 613,382 582,194 0 582,194 0 613,382 613,382 614,094 31,900 31,900 31-Mar-24 31-Mar-24 On-going On Target On Target
Total Schools Other 880,194 772,697 880,194 0 728,737 0 621,240 621,240 623,452 (105,285) 0 (105,285)
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 0 0 38,303 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 75,176 6,563 75,176 0 68,613 0 0 0 68,613 0 0 31-Mar-25 31-Mar-25 Planning On Hold On Hold
Total Information & Cultural 113,479 6,563 113,479 0 106,916 0 0 0 106,916 0 0 0
Completed Projects
GARNOCK CAMPUS 40,307,259 40,283,664 40,307,259 0 2,893 0 (20,702) (20,702) 2,893 0 0 Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,112,120 3,111,334 3,112,120 0 786 0 0 0 786 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 43,419,379 43,394,998 43,419,379 0 3,679 0 (20,702) (20,702) 3,679 0 0 0
Total Communities 214,276,667 113,495,569 214,276,667 0 18,500,110 0 16,833,105 16,833,105 18,239,350 (260,760) 0 (260,760)
CAPITAL MONITORING 2023/24
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2023/24 BUDGETS

Page 15

CHIEF EXECUTIVE
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 31
January 2024
Year to date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 4,055,131 965,196 4,055,131 0 423,398 0 55,463 55,463 233,398 (190,000) (190,000) 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 922,556 402,197 922,556 0 20,359 0 0 0 20,359 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
LAN/WiFi 2,673,000 1,167,848 2,673,000 0 228,838 0 223,686 223,686 228,838 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
TELEPHONY 1,146,693 251,143 1,146,693 0 39,050 0 23,500 23,500 23,500 (15,550) (15,550) 31-Mar-28 31-Mar-28 Implementation On Target On Target
Total IT Strategy 8,797,380 2,786,384 8,797,380 0 711,645 0 302,649 302,649 506,095 (205,550) 0 (205,550)
Total Chief Executive 8,797,380 2,786,384 8,797,380 0 711,645 0 302,649 302,649 506,095 (205,550) 0 (205,550)   
CAPITAL MONITORING 2023/24
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2023/24 BUDGETS

Page 16

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual Expenditure
to 31 January 2024
Year to date
Variance 2023/24
Projected Expenditure
to 31 March 2024
Actual Over/
(Under) Spend for
2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Management & Support
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 844,521 996,000 0 853,857 0 840,331 840,331 853,857 0 0 31-Dec-24 31-Dec-24 In progress On Target On Target
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 268,065 0 0 0 268,065 0 0 31-Aug-24 31-Aug-24 In development On Target On Target
47 WEST ROAD 300,000 12,163 300,000 0 300,000 0 12,163 12,163 45,813 (254,187) (254,187) 21-Jun-24 21-Jun-24 Refurbishment On Target On Target
Total Management & Support 1,832,058 1,124,677 1,832,058 0 1,421,922 0 852,494 852,494 1,167,735 (254,187) 0 (254,187)
Housing Non HRA
IMPROVEMENT GRANTS * 656,571 542,561 656,571 0 656,571 0 542,561 542,561 656,571 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target 
Total Housing Non HRA 656,571 542,561 656,571 0 656,571 0 542,561 542,561 656,571 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,590,773 4,608,078 0 18,047 0 742 742 1,292 (16,755) (16,755) Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,590,773 4,608,078 0 18,047 0 742 742 1,292 (16,755) 0 (16,755)
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,224,534 5,579,718 0 363,177 0 7,993 7,993 7,993 (355,184) (355,184) Complete Complete Snagging Complete Complete
Total Young People 5,579,718 5,224,534 5,579,718 0 363,177 0 7,993 7,993 7,993 (355,184) 0 (355,184)
Total Health & Social Care 12,676,425 11,482,544 12,676,425 0 2,459,717 0 1,403,789 1,403,789 1,833,591 (626,126) 0 (626,126)
CommentsProject Description
DELIVERY STATUS
CAPITAL MONITORING 2023/24
2023/24 BUDGETSTOTAL PROJECT COMPLETION DATES

Page 17

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 31
January 2024
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 4,447,261 4,399,766 4,447,261 0 4,447,261 0 4,114,503 4,114,503 4,399,766 (47,495) (47,495) 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
ROAD SAFETY IMPROVEMENT FUND 215,647 215,647 215,647 0 215,647 0 46,813 46,813 215,647 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
A737 DALRY BYPASS 375,735 375,735 375,735 0 375,735 0 281,026 281,026 375,735 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target 
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 0 0 0 (100,000) (100,000) 31-Mar-25 31-Mar-25 In development On Target On Target
LIGHTING * 1,417,342 532,028 1,417,342 0 1,417,342 0 532,028 532,028 1,037,370 (379,972) (379,972) 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 694,999 122,210 694,999 0 154,169 0 122,210 122,210 154,169 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target
A737 DALRY BYPASS LIGHTING 20,684 15,973 20,684 0 16,610 0 15,973 15,973 16,610 0 0 31-Mar-24 31-Mar-24 Preparing Works Packages On Target On Target
UPPER GARNOCK FPS 18,503,800 17,947,156 18,503,800 0 600,000 0 511,184 511,184 600,000 0 0 Complete Complete Complete Complete Complete
MILLPORT COASTAL FPS 48,599,797 17,801,636 48,599,797 0 26,724,382 0 15,961,221 15,961,221 26,724,382 0 0 31-Aug-24 30-Sep-24 Construction On Target On Target
MILLBURN FPS 1,757,000 255,851 1,757,000 0 50,000 0 2,380 2,380 50,000 0 0 31-Jul-24 31-Jul-25 In Development On Target Slightly off target  Delays due to Scottish Water permissions
MILLPORT PIER 500,000 150,080 500,000 0 40,000 0 0 0 40,000 0 0 31-Dec-25 31-Dec-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 799,430 528,314 799,430 0 799,430 0 528,314 528,314 799,430 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 4,149,000 2,639,722 4,149,000 0 3,815,046 0 2,305,767 2,305,767 3,815,046 0 0 30-Apr-24 31-Jul-24 Construction On Target On Target
B714 UPGRADE 31,693,443 2,153,621 31,693,443 0 1,250,795 0 1,264,363 1,264,363 1,250,795 0 0 31-Jul-26 31-Jul-26 In Development On Target On Target
LARGS CAR PARK INFRASTRUCTURE 55,128 55,128 55,128 0 661 0 661 661 661 0 0 Complete Complete Complete Complete Complete
PARKING CHARGES & DPE 250,610 97,871 250,610 0 170,585 0 17,846 17,846 170,585 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
Total Roads 113,754,874 47,382,784 113,754,874 0 40,177,663 0 25,704,290 25,704,290 39,650,196 (527,467) 0 (527,467)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 479,055 0 479,055 0 (1,149) 0 0 0 (1,149) 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, ARDROSSAN - PLOTS/WALLS 217,922 162,154 217,922 0 61,864 0 6,096 6,096 61,864 0 0 Complete Complete Complete Complete Complete
HAYLIE BRAE CEMETERY 455 455 455 0 455 0 455 455 455 0 0 Complete Complete Complete Complete Complete
DALRY CEMETERY 250 250 250 0 250 0 250 250 250 0 0 Complete Complete Complete Complete Complete
CMTY, KILWINNING - NEW 1,402,589 1,365,070 1,402,589 0 138,061 0 100,542 100,542 138,061 0 0 Complete Complete Complete Complete Complete
CMTY, KNADGERHILL - EXTENSION 416,471 415,470 416,471 0 1,661 0 660 660 1,661 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WORKS 398,033 371,493 398,033 0 36,892 0 10,352 10,352 18,743 (18,149) (18,149) Complete Complete Complete Complete Complete
CMTY, STEV HIGH ROAD - WORKS 506,878 496,535 506,878 0 137,408 0 127,065 127,065 137,408 0 0 Complete Complete Complete Complete Complete
CMTY, BRODICK - NEW 12,000 8,317 12,000 0 4,979 0 1,296 1,296 4,979 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, KILBIRNIE - WALLS 134,370 16,106 134,370 0 46,601 0 480 480 46,601 0 0 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, BEITH - WALLS 182,592 15,135 182,592 0 65,124 0 500 500 70,624 5,500 5,500 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, ABBEY TOWER - WALLS 95,550 6,612 95,550 0 560 0 560 560 560 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, STEV HAWKHILL - WALLS 108,732 6,340 108,732 0 480 0 480 480 480 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, WEST KILBRIDE - WALLS 99,528 4,964 99,528 0 360 0 360 360 360 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, DREGHORN - WALLS 8,240 8,240 8,240 0 4,980 0 4,980 4,980 4,980 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 601,663 26,580 601,663 0 12,543 0 15,293 15,293 25,294 12,751 12,751 Future years Future years Feasibility Works On Target On Target
COASTAL PLAY PARKS 409,925 410,685 409,925 0 409,925 0 410,685 410,685 409,925 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
STREET FURNITURE IMPROVEMENT 127,741 138,549 127,741 0 58,272 0 69,080 69,080 58,272 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PARK ENABLING WORKS 149,895 158,775 149,895 0 64,532 0 73,412 73,412 64,532 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,391,000 416,167 1,391,000 0 356,712 0 306,879 306,879 356,712 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
Total Streetscene 8,424,557 4,809,566 8,424,557 0 1,400,510 0 1,129,426 1,129,426 1,400,612 102 0 102
Transport
VEHICLES * 3,296,237 2,660,819 3,296,237 0 3,296,237 0 2,660,819 2,660,819 3,296,237 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target 
WORKPLACE CHARGERS 318,261 292,285 318,261 0 92,858 0 66,882 66,882 92,858 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target
FLEET DECARBONISATION 1,145,566 45,014 1,145,566 0 607,981 0 7,429 7,429 77,816 (530,165) (530,165) 31-Mar-24 31-Mar-24 Ongoing On Target On Target
Total Transport 4,760,064 2,998,118 4,760,064 0 3,997,076 0 2,735,130 2,735,130 3,466,911 (530,165) 0 (530,165)
Waste Services
SHEWALTON LANDFILL 13,321,491 13,272,542 13,321,491 0 48,949 0 0 0 0 (48,949) (48,949) Complete Complete Complete Complete Complete
Total Waste Services 13,321,491 13,272,542 13,321,491 0 48,949 0 0 0 0 (48,949) 0 (48,949)
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 50,936 120,000 0 77,986 0 8,922 8,922 77,986 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 7,289,441 681,622 7,289,441 0 6,622,319 0 535,941 535,941 580,077 (6,042,242) (6,042,242) 30-Apr-24 30-Apr-24 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 5,540,347 501,368 5,540,347 0 1,791,483 0 403,258 403,258 435,226 (1,356,257) (1,356,257) 30-Oct-24 30-Oct-24 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 919,149 1,000,000 0 63,589 0 (17,263) (17,263) 63,589 0 0 31-Mar-24 31-Mar-24 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 711,000 0 711,000 0 711,000 0 0 0 200,000 (511,000) (511,000) 31-Mar-24 31-Mar-24 Planning On Target On Target 
Total Renewable Energy 14,660,789 2,153,075 14,660,789 0 9,266,377 0 930,858 930,858 1,356,878 (7,909,499) 0 (7,909,499)
Project Description
TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS
Comments
CAPITAL MONITORING 2023/24
COMPLETION DATES

Page 18

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 31
January 2024
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Project Description
TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS
Comments
CAPITAL MONITORING 2023/24
COMPLETION DATES
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * (106,596) 0 (106,596) 0 (106,596) 0 0 0 0 106,596 106,596 31-Mar-24 31-Mar-24 Mulitple projects On Target On Target 
PLI CASTLEVIEW DAY SERVICES 140,000 5,604 140,000 0 140,000 0 5,604 5,604 140,000 0 0 31-May-24 31-May-24 Planning On Target On Target
PLI CENTRAL AVE STREETSCENE DEPOT* 6,654 6,325 6,654 0 6,654 0 6,325 6,325 6,654 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE CEMETERY 30,000 26,399 30,000 0 30,000 0 26,399 26,399 30,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI BEITH CEMETERY 69 69 69 0 69 0 69 69 69 0 0 Complete Complete Complete Complete Complete
PLI TOWNEND CC 7,949 7,949 7,949 0 7,949 0 7,949 7,949 7,949 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE COMMUNITY CENTRE 650 650 650 0 650 0 650 650 650 0 0 Complete Complete Complete Complete Complete
PLI PORTLAND PLACE 17,267 17,267 17,267 0 17,267 0 17,267 17,267 17,267 0 0 Complete Complete Complete Complete Complete
PLI WEST BYREHILL DEPOT 107,524 107,524 107,524 0 107,524 0 107,524 107,524 107,524 0 0 Complete Complete Complete Complete Complete
PLI GOLDCRAIGS DEPOT 114,767 4,878 114,767 0 4,878 0 4,878 4,878 4,878 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PLI ANNICK PRIMARY SCHOOL 186 186 186 0 186 0 186 186 186 0 0 Complete Complete Complete Complete Complete
PLI BEITH PRIMARY SCHOOL 1,957 1,957 1,957 0 1,957 0 1,957 1,957 1,957 0 0 Complete Complete Complete Complete Complete
PLI BLACKLANDS PRIMARY SCHOOL 809 809 809 0 809 0 809 809 809 0 0 Complete Complete Complete Complete Complete
PLI CASTLEPARK PRIMARY SCHOOL 84,253 84,253 84,253 0 84,253 0 84,253 84,253 84,253 0 0 Complete Complete Complete Complete Complete
PLI CUMBRAE PRIMARY 3,867 3,867 3,867 0 3,867 0 3,867 3,867 3,867 0 0 Complete Complete Complete Complete Complete
PLI DREGHORN PRIMARY SCHOOL 64,503 64,503 64,503 0 64,503 0 64,503 64,503 64,503 0 0 Complete Complete Complete Complete Complete
PLI GLENCAIRN PRIMARY SCHOOL 4,469 4,469 4,469 0 4,469 0 4,469 4,469 4,469 0 0 Complete Complete Complete Complete Complete
PLI LOUDOUN MONTGOMERY PS 2,700 0 2,700 0 2,700 0 0 0 2,700 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI MAYFIELD PRIMARY 4,850 0 4,850 0 4,850 0 0 0 4,850 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI PENNYBURN PRIMARY 179,316 172,899 179,316 0 179,316 0 172,899 172,899 179,316 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL 618,480 16,996 618,480 0 123,980 0 16,996 16,996 123,980 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI ST BRIDGETS PRIMARY 20,184 20,184 20,184 0 20,184 0 20,184 20,184 20,184 0 0 Complete Complete Complete Complete Complete
PLI ST JOHN OGILVIE PRIMARY SCHOOL 6,744 6,744 6,744 0 6,744 0 6,744 6,744 6,744 0 0 Complete Complete Complete Complete Complete
PLI AUCHENHARVIE ACADEMY* 374,081 372,749 374,081 0 374,081 0 372,749 372,749 374,081 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI IRVINE ROYAL ACADEMY* 12,974 18,369 12,974 0 12,974 0 18,369 18,369 12,974 0 0 Complete Complete Complete Complete Complete
PLI KILWINNING ACADEMY 207,433 200,395 207,433 0 207,433 0 200,395 200,395 207,433 0 0 Complete Complete Complete Complete Complete Underlying structural issues identified during constuction
work which now requires remedial action. Cost and PLI KYLE ROAD UNIT 34 4,069 4,069 4,069 0 4,069 0 4,069 4,069 4,069 0 0 Complete Complete Complete Complete Complete
PLI BRIDGEGATE HOUSE 166,423 2,912 166,423 0 12,306 0 2,912 2,912 12,306 0 0 30-Sep-24 30-Sep-24 Planning On Target On Target
PLI ACHNAMARA CHILDREN'S UNIT 11,954 11,954 11,954 0 11,954 0 11,954 11,954 11,954 0 0 Complete Complete Complete Complete Complete
PLI THE MEADOWS 39,500 0 39,500 0 39,500 0 0 0 39,500 0 0 Complete Complete Complete Complete Complete
PLI ANAM CARA 95,473 56,343 95,473 0 95,473 0 56,343 56,343 95,473 0 0 31-Oct-23 19-Jan-24 Construction On Target On Target
PLI TAIGH MOR 3,500 0 3,500 0 3,500 0 0 0 3,500 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
PLI VIKINGAR 2,500 3,096 2,500 0 2,500 0 3,096 3,096 2,500 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI EGLINTON CASTLE 48,000 0 48,000 0 48,000 0 0 0 0 (48,000) (48,000) 31-Mar-24 31-Oct-24 Planning On Target On Target
PLI GARNOCK CAMPUS 5,800 5,800 5,800 0 5,800 0 5,800 5,800 5,800 0 0 Complete Complete Complete Complete Complete
PLI THE PORTAL 47,754 47,754 47,754 0 47,754 0 47,754 47,754 47,754 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 2,398,377 1,276,971 2,398,377 0 1,571,557 0 1,276,971 1,276,971 1,630,153 58,596 0 58,596
Other Property
HOME 289,971 289,971 289,971 0 1,323 0 1,323 1,323 1,323 0 0 On Hold On Hold On Hold On Hold On Hold
BUILD 47,749 47,749 47,749 0 1,500 0 1,500 1,500 1,500 0 0 On Hold On Hold On Hold On Hold On Hold
EMERGENCY CONTROL CTR 158,000 67,191 158,000 0 156,780 0 65,971 65,971 156,780 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 766,000 25,000 766,000 0 0 0 0 0 11,650 11,650 11,650 31-Mar-26 31-Mar-26 In development On Target On Target
GALLOWGATE TOILETS 275,803 273,681 275,803 0 246,153 0 244,031 244,031 246,153 0 0 31-Aug-23 17-Nov-23 Construction On Target Slightly off target  Contractor delays
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 109,065 134,641 0 28,519 0 2,943 2,943 2,943 (25,576) (25,576) Complete Complete Complete Complete Complete
Total Property 1,672,164 812,657 1,672,164 0 434,275 0 315,768 315,768 420,349 (13,926) 0 (13,926)   
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 0 0 0 (350,000) (350,000) 31-Mar-25 31-Mar-25 Planning On Target On Target
2-4 BOYLE STREET HOSTEL 120,000 0 120,000 0 31,025 0 (88,975) (88,975) 31,025 0 0 12-May-23 12-May-23 Construction On Target On Target
Total Other Housing 470,000 0 470,000 0 381,025 0 (88,975) (88,975) 31,025 (350,000) 0 (350,000)

Page 19

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 31
January 2024
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Project Description
TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS
Comments
CAPITAL MONITORING 2023/24
COMPLETION DATES
Regeneration
TOWN CENTRE REGENERATION 1,201,658 1,104,030 1,201,658 0 205,690 0 108,062 108,062 205,690 0 0 30-Sep-23 31-Mar-24 Construction On Target On Target
REPURPOSING PROPERTY GRANT FUND 348,665 94,466 348,665 0 97,985 0 93,786 93,786 97,985 0 0 30-May-25 30-May-25 In development On Target On Target
MILLPORT TOWN HALL REGENERATION 754,026 754,026 754,026 0 220,534 0 220,534 220,534 220,534 0 0 Complete Complete Complete Complete Complete
MILLPORT TOWN HALL PHASE 2 433,520 135,327 433,520 0 433,520 0 135,327 135,327 433,520 0 0 31-May-23 31-Mar-24 Construction On Target Significantly off
target
GARRISON HOUSE PROJECT 730,998 15,980 730,998 0 730,998 0 15,980 15,980 730,998 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
ISLANDS PIT STOPS 540,000 0 540,000 0 40,000 0 0 0 40,000 0 0 31-Jul-24 31-Jul-24 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 259,000 144,183 259,000 0 140,374 0 25,557 25,557 60,000 (80,374) (80,374) 31-Mar-24 31-Dec-24 In development On Target On Target
DYEMILL BIKE PARK PROJECT 220,625 171,938 220,625 0 220,625 0 171,938 171,938 220,625 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
ISLANDS COST CRISIS FUND 17,000 17,000 17,000 0 17,000 0 17,000 17,000 17,000 0 0 Complete Complete Complete Complete Complete
PLACE BASED INVESTMENT PROGRAMME (PBIP) 910,681 512,154 910,681 0 529,904 0 481,377 481,377 490,000 (39,904) (39,904) 31-Mar-26 31-Mar-26 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 300,744 102,330 300,744 0 300,744 0 102,330 102,330 300,744 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
DIGITAL - SIPP GREAT HARBOUR 242,765 0 242,765 0 114,883 0 0 0 0 (114,883) (114,883) 31-Mar-25 30-Jul-25 Planning On Target On Target
AYRSHIRE 5GIR 3,791,000 0 3,791,000 0 3,791,000 0 0 0 0 (3,791,000) (3,791,000) 31-Mar-25 31-Mar-25 Planning On Target On Target
PBIP – KILWINNING ABBEY IMPROVEMENTS 235,354 0 235,354 0 235,354 0 0 0 0 (235,354) (235,354) 31-Mar-25 31-Mar-25 In development On Target On Target
LOCHSHORE HUB PLAY AREA 445,000 0 445,000 0 445,000 0 0 0 50,000 (395,000) (395,000) 30-Jun-24 30-Jun-24 Construction On Target On Target
PBIP 36 BANK STREET 169,999 107,238 169,999 0 36,827 0 24,066 24,066 36,827 0 0 31-Dec-25 31-Dec-25 In development On Target On Target
PBIP GALT HOUSE 50,000 4,125 50,000 0 25,000 0 4,125 4,125 5,000 (20,000) (20,000) 31-Mar-24 31-Mar-25 In development On Target On Target
IRVINE HIGH STREET 2,837,316 2,720,001 2,837,316 0 115,961 0 (1,353) (1,353) 38,647 (77,314) (77,314) Complete Complete Complete Complete Complete
MILLPORT CARS 11,943 0 11,943 0 11,943 0 0 0 11,943 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
MONTGOMERIE PARK MASTERPLAN 4,218,597 1,787,539 4,218,597 0 78,665 0 12,606 12,606 20,000 (58,665) (58,665) 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 1,961,138 1,840,274 1,961,138 0 319,358 0 198,495 198,495 230,000 (89,358) (89,358) 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,145,999 4,086,620 4,145,999 0 62,229 0 2,850 2,850 2,850 (59,379) (59,379) Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 1,398,066 143,495 1,398,066 0 170,208 0 2,655 2,655 40,000 (130,208) (130,208) 31-Mar-24 31-Dec-26 In development On Target On Target
VDLF - ANNICKBANK PH 3* 1,988,996 1,698,678 1,988,996 0 1,912,735 0 1,622,417 1,622,417 1,912,735 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
VDLF - DEVELOPMENT WORK* 417,479 212,861 417,479 0 205,000 0 119,394 119,394 140,000 (65,000) (65,000) 31-Mar-25 31-Mar-25 In development On Target On Target
VDLF - STRATEGY 25,559 25,559 25,559 0 25,559 0 25,559 25,559 25,559 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK NEIGHBOURHOOD CTR 175,000 0 175,000 0 175,000 0 0 0 35,000 (140,000) (140,000) 31-Mar-24 31-Dec-24 In development On Target On Target
VDLF STALLED SPACES FUND 125,000 0 125,000 0 25,000 0 0 0 0 (25,000) (25,000) 31-Mar-24 31-Mar-25 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 4,778 0 0 0 4,778 0 0 Complete Complete Complete Complete Complete
CYCLING/WALKING/SAFER STREETS * 1,343,799 1,478,835 1,343,799 0 1,343,799 0 685,739 685,739 1,343,799 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 239,616 60,000 239,616 0 239,616 0 26,912 26,912 60,000 (179,616) (179,616) 31-Mar-24 31-Mar-25 Various On Target On Target
FAIRLIE COASTAL PATH 500,000 500,000 500,000 0 500,000 0 0 0 500,000 0 0 31-Dec-23 01-Jun-24 Construction On Target On Target
IRVINE CYCLE FRIENDLY TOWN 50,000 466,198 50,000 0 50,000 0 0 0 50,000 0 0 31-Mar-24 31-Mar-24 Pre Construction On Target On Target
BRODICK TO CORRIE CYCLE PATH 80,000 60,199 80,000 0 80,000 0 0 0 80,000 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
ARDROSSAN PROMENADE 788,000 45,613 788,000 0 788,000 0 45,613 45,613 788,000 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
BUS CORRIDOR IMPROVEMENTS 201,513 201,514 201,513 0 12,472 0 12,472 12,472 12,472 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
CUMBRAE FERRY & BUS STOP 219,547 208,041 219,547 0 80,000 0 68,494 68,494 80,000 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
KILBIRNIE TO KILWINNING 20,000 0 20,000 0 20,000 0 0 0 20,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
B714 ACTIVE TRAVEL IMPROVEMENTS 360,000 112,532 360,000 0 260,000 0 12,532 12,532 260,000 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
B777 CORRIDOR IMPROVEMENTS 38,400 27,710 38,400 0 33,600 0 22,910 22,910 33,600 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
CYCLE SHELTER 11,409 11,409 11,409 0 11,409 0 11,409 11,409 11,409 0 0 Complete Complete Complete Complete Complete
NCN73 ACCESSABILITY IMPROVEMENTS 34,516 4,900 34,516 0 34,516 0 4,900 4,900 34,516 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
NCN753 LARGS PROMENADE 88,230 8,055 88,230 0 88,230 0 8,055 8,055 88,230 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
LINKS TO EGLINTON PARK 243,407 0 243,407 0 243,407 0 0 0 243,407 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
COMMUNITY BUS FUND 146,000 0 146,000 0 146,000 0 0 0 146,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
SALTCOATS OLD CAL RAILWAY PH1 195,075 187,011 195,075 0 140,000 0 131,936 131,936 140,000 0 0 Complete Complete Complete Complete Complete
SALTCOATS OLD CAL RAILWAY PH2 48,666 17,623 48,666 0 48,666 0 17,623 17,623 48,666 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
Total Regeneration 37,823,803 24,274,584 37,823,803 0 14,811,589 0 4,431,300 4,431,300 9,310,534 (5,501,055) 0 (5,501,055)
Ayrshire Growth Deal
AGD - I3 DPMC PHASE 1 1,000,000 0 1,000,000 0 294,551 0 (5,449) (5,449) 294,551 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 DPMC PHASE 2 4,999,999 275,147 4,999,999 0 45,449 0 35,732 35,732 45,449 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 15,617,569 1,727,781 15,617,569 0 2,146,226 0 1,182,358 1,182,358 2,153,000 6,774 6,774 31-Oct-24 31-Oct-24 Multiple Projects On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-28 31-Mar-28 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,001 242,760 18,040,001 0 20,000 0 10,532 10,532 20,000 0 0 31-Mar-30 31-Mar-30 Multiple Projects On Target On Target
AGD - GREAT HARBOUR 14,187,576 849,349 14,187,576 0 423,021 0 251,260 251,260 352,000 (71,021) (71,021) 31-Mar-28 31-Mar-28 Multiple Projects On Target On Target
AGD - IMSE 10,500,000 145,602 10,500,000 0 50,000 0 12,089 12,089 50,000 0 0 31-Mar-30 31-Mar-30 Design On Target On Target
AGD - MARINE TOURISM ARDROSSAN 7,483,693 337,528 7,483,693 0 1,693 0 2,832 2,832 1,693 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - MARINE TOURISM ARRAN 2,033,077 79,550 2,033,077 0 37,500 0 19,066 19,066 37,500 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - MARINE TOURISM CUMBRAE 2,034,384 104,822 2,034,384 0 80,807 0 36,643 36,643 80,807 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 75,996,300 3,762,540 75,996,300 0 3,199,247 0 1,545,064 1,545,064 3,135,000 (64,247) 0 (64,247)
Community led regeneration project by Millport Town Hall
Charity. Project has been delayed due to challenges with
contractor and work needing redone as did not met a
satisfactory standard.  Regeneration team continues to
support MTHC in the delivery of the project.

Page 20

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 31
January 2024
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Project Description
TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS
Comments
CAPITAL MONITORING 2023/24
COMPLETION DATES
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,127,112 526,460 4,127,112 0 119,000 0 71,008 71,008 108,000 (11,000) (11,000) 1st Qtr 2026 1st Qtr 2026 Design On Target On Target
LOW CARBON HUB 613,828 656,984 613,828 0 501,823 0 544,979 544,979 501,823 0 0 30-Sep-24 30-Sep-24 Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 42,329,034 4,433,271 42,329,034 0 12,265,869 0 1,599,504 1,599,504 12,265,869 0 0 27-May-24 31-Dec-24 Tender On Target On Target
VDLF - HARBOUR MASTERS OFFICE 157,500 20,933 157,500 0 136,567 0 0 0 4,246 (132,321) (132,321) 31-Mar-24 31-Mar-24 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 279,411 257,020 279,411 0 22,391 0 0 0 22,391 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
Other Growth & Investment 58,252,957 5,894,667 58,252,957 0 13,045,650 0 2,215,492 2,215,492 12,902,329 (143,321) 0 (143,321)
Total Economic Development & Regeneration 172,073,059 33,931,791 172,073,059 0 31,056,486 0 8,191,855 8,191,855 25,347,863 (5,708,623) 0 (5,708,623)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,163 3,378,163 0 0 0 (1,000) (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,899,427 2,977,098 0 40,595 0 (37,076) (37,076) 967 (39,628) (39,628) Complete Complete Defects Period Complete Complete
ARDROSSAN HOSTEL 0 0 2,086 2,086 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 6,355,261 6,276,590 6,355,261 0 40,595 0 (35,991) (35,991) 967 (39,628) 0 (39,628)
Total Place 337,890,637 112,914,093 337,890,637 0 88,374,513 0 40,159,331 40,159,331 73,304,954 (15,069,559) 0 (15,069,559)

Page 21

OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Year to Date Budget
2023/24
Actual Expenditure
to 31 January 2024
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Over/ (Under)
Spend for 23/24
£ £ £ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 8,633,036 0 8,633,036 0 1,533,036 0 0 0 1,533,036 0
CORE INFRASTRUCTURE INVESTMENT 351,000 0 351,000 0 351,000 0 0 0 351,000 0
Total Other Budgets 8,633,036 0 8,633,036 0 1,884,036 0 0 0 1,884,036 0
2023/24 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 22

HRA Capital Statement 2324 Appendix 2
TOTAL PROJECT CURRENT YEAR 2023/24 - Period 10
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Actual Expenditure to
31 January 2024
Projected
Expenditure to 31st
March 2024
Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
EXPENDITURE
Council House Building
Afton Court 1,335,654 1,214,308 1,335,654 0 681,987 560,641 681,987 On Target Complete Complete
Ayrshire Central Site 50,373,322 2,923,473 50,373,322 0 600,000 440,559 600,000 On Target Significantly off target Project due to commence on site February 2024. 
Bourtreehill Village 9,924,743 87,799 9,924,743 0 50,000 67,457 85,000 35,000 On Target Significantly off target Project due to commence on site October 2024.
Brathwic Terrace 6,674,074 6,678,395 6,678,395 4,321 26,403 148,855 155,877 129,474 On Target Complete Complete
Caley Court 3,131,066 2,865,079 3,131,066 0 322,630 56,644 322,630 On Target Complete Complete
Corsehillhead 2,027,810 212,599 2,027,810 0 350,000 0 0 (350,000) On Target Significantly off target Value engineering exercise being undertaken due to significant increase in construction
costs.
Dalrymple Place 5,838,627 5,822,700 5,838,627 0 1,473 2,212 18,139 16,666 On Target Complete Complete
Flatt Road 19,934,544 19,698,658 19,934,544 0 302,327 72,033 302,327 On Target Complete Complete
Friars Lawn 2,199,628 2,055,110 2,086,112 (113,516) 231,468 86,130 117,952 (113,516) On Target Complete Complete
Fullarton Street (High Flats) 14,481,290 30,435 14,481,290 0 50,000 4,500 50,000 On Target Significantly off target New build project due to commence on site July 2024.
Garnock Academy Site 12,092,889 661,581 12,092,889 0 1,110,750 88,400 138,400 (972,350) On Target Significantly off target Project site start delayed due to outstanding consent required from Scottish Water.
Garrier Court 2,369,763 2,380,699 2,369,763 0 34,212 (1,540) 34,212 On Target Complete Complete
Glebe Place 1,894,952 0 1,894,952 0 0 0
0
On Target On Target Project deferred to 2026/27 following refurbishment of the block for Ukrainian funded by
the Scottish Government.
Harbourside 14,622,742 14,119,065 14,622,742 0 939,356 350,827 939,356 On Target Complete Complete
James McFarlane Site 4,784,118 376,551 4,784,118 0 450,000 11,786 450,000 On Target Significantly off target Project due to commence on site November 2023.
James Reid Site 11,896,026 862,603 11,896,026 0 1,200,000 0 0 (1,200,000) On Target Significantly off target Project site start delayed due to non resolution of culvert maintenance issue
Kings Arms (113-115 High Street) 2,169,980 311,550 2,169,980 0 482,000 25,627 182,000 (300,000) On Target Significantly off target Project site start delayed due to value engineering being undertaken and additional budget
approval at Full Council 14 February 2024.
Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 95 3,274,506 0 250,000 133,654 450,000 200,000 On Target Significantly off target Project due to commence on site January 2024.
Largs Police Station 2,769,301 2,759,320 2,769,301 0 1,038,673 884,700 1,038,673 On Target On Target Project on-site due to complete August 2023
Montgomerie Park (Both Phases) 46,166,866 4,727,689 46,166,866 0 780,000 80,456 352,208 (427,792) On Target Significantly off target Tender for grouting works to be awarded following clarification of costs.
Regeneration Project 1d 9,965,851 2,750 9,965,851 0 0 0 On Target Significantly off target Pre Site
Regeneration Project 1e 1,658,083 0 1,658,083 0 0 0 On Target Significantly off target Project due to commence on site June 2024.
Springvale  2,852,016 2,747,677 2,852,016 0 0 1,682 106,021 106,021 On Target Complete Complete
Stanecastle Site 7,768,147 604,509 7,768,147 0 450,000 405 450,000 On Target Significantly off target Project due to commence on site November 2023.
St Beya Gardens 3,691,052 3,689,346 3,691,052 0 1,706 0 1,706 On Target Complete Complete 
St Colm's Largs 4,907,987 4,808,504 4,907,987 0 12,685 (65,376) 34,107 21,422 On Target Complete Complete 
St Michael's Wynd 13,996,769 13,908,729 13,996,769 0 0 (189,072) (101,032) (101,032) On Target Complete Complete  - in year credit expected from Scottish Water.
Towerlands Primary School 8,579,943 8,545,982 8,579,943 0 9,279 (24,683) 9,279 On Target Complete Complete
Unallocated Regeneration Block 8,304,876 0 8,304,876 0 479,000 0 0 (479,000) On Target On Target Budget to be transferred to future years as not required for 2023/24.
Nelson Street Regeneration 622,116 0 622,116 0 50,000 0 50,000 On Target Significantly off target Pre Site
Acquisition Of Land & Buildin 0 (109) 0 0 0 (84) On Target On Target
House Building - General 1,547,765 0 1,547,765 0 0 0 On Target On Target
Acquisition Houses-Open Market 254,752 340,938 254,752 0 254,752 498,618 239,505 (15,247) On Target On Target
Dickson Drive Phase 2 0 0 0 0 0 0 On Target On Target
Harbour Street 0 0 0 0 0 0 On Target On Target
Refurb - Connell Court 0 (30,395) 0 0 0 (30,395) On Target On Target Complete
Kinnear Road 2,118 0 2,118 0 2,118 0 2,118 On Target Complete Complete
Sy Mary's Primary, Largs 676,260 676,260 On Target On Target
Contingency 11,000,624 0 11,000,624 0 0 0 On Target On Target
Internal Management Charges 1,757,259 693,039 1,757,259 0 1,757,259 916,616 1,757,259 On Target On Target
SUB TOTAL 293,114,000 102,405,640 293,004,805 (109,194) 11,918,078 4,120,653 9,143,984 0 (2,833,129) 59,035
DELIVERY STATUS

Page 23

TOTAL PROJECT CURRENT YEAR 2023/24 - Period 10
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Actual Expenditure to
31 January 2024
Projected
Expenditure to 31st
March 2024
Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
DELIVERY STATUS
Improvements to existing stock
Wet Room - Void 426,386 157,616 286,936 (139,450) 426,386 189,714 286,936 (139,450) On Target On Target Reduction in estimated number of completions based on jobs received to date
Bathrooms - Void 770,876 349,339 524,333 (246,543) 770,876 382,752 524,333 (246,543) On Target On Target Reduction in estimated number of completions based on jobs received to date
Wet Room - Planned 150,025 0 150,025 0 150,025 0 150,025 On Target On Target
Bathrooms - Planned 341,561 160,277 334,699 0 334,699 227,663 334,699 On Target On Target
Electrical Rewiring 585,710 304,458 580,895 0 535,280 295,113 580,895 45,615 On Target On Target Anticipated slippage due to no access. 
Heating 2,924,745 1,200,209 2,169,965 (754,780) 2,924,745 1,494,987 2,169,965 (202,920) (551,860) On Target On Target Scope of works less than budgeted for some properties and reduced numbers resulting in
an anticipated underspend.
Kitchens 1,581,530 617,773 1,458,554 0 1,458,554 743,252 1,458,554 On Target On Target Reduction in estimated number of completions due to no accesses.
Kitchens - Void 1,313,771 697,316 1,146,886 (166,885) 1,313,771 859,679 1,146,886 (166,885) On Target On Target Reduction in estimated number of completions due to no accesses.
Roofing 1,105,661 680,898 1,434,218 0 1,516,630 961,760 1,434,218 (82,412) On Target On Target
Wallfloor rendering 62,000 1,887,956 134,783 0 93,594 2,238,328 134,783 41,189 On Target On Target Budget pulled forward to reflect additional addresses
EWI 4,473,962 0 4,486,246 12,284 4,473,962 0 4,486,246 12,284 On Target On Target Overspend element due to an increase in anticipated unit rate
Window Replacement 541,903 366,936 376,925 0 349,037 382,767 376,925 27,888 On Target On Target Work being undertaken in relation to access arrangements. Housing will be reviewing this in
order to improve access.
Saltcoats MSF Investment 1,314,188 659,257 1,314,188 0 1,314,188 728,809 1,314,188 0 On Target On Target Projected expenditure includes buy-back houses, budget virement requested.
Smoke Detector Programme 250,000 136,950 250,000 0 250,000 194,210 250,000 On Target On Target
Energy Efficiency 122,610 5,050 10,000 0 10,000 5,050 10,000 0 On Target On Target
Path Finder Project 250,000 0 10,000 0 250,000 0 10,000 (240,000) On Target On Target
Solar Panels 5,050,000 1,654,903 4,560,026 0 5,007,000 1,384,765 4,560,026 (446,974) On Target On Target Recently surveyed houses not suitable. Sent out another batch but unlikely to complete by
year end
SUB TOTAL 21,264,928 8,878,938 19,228,679 (1,295,374) 21,178,747 10,088,849 19,228,679 (857,614) (1,092,454)
Other Capital works
Estate Based Regeneration 2,093,064 364,605 2,093,064 0 825,629 391,371 740,089 (85,540) On Target On Target Skelmorlie parking costs lower than expected.
Lift Replacement 454,425 0 454,425 0 50,000 0 (50,000) On Target On Target Slippage on programme . Works now expected to commence Dec/Jan
Sheltered Housing Units 12,965,531 56,572 12,965,531 0 4,100,000 4,109,592 4,633,521 533,521 On Target On Target Budget pulled forward due to an accleration of works
High Flats Demolition 2,368,970 1,296,243 1,725,818 (643,152) 2,368,970 1,424,132 1,725,818 (643,152) On Target On Target Final Account has now been agreed
Health and Safety Works 207,000 0 0 (207,000) 207,000 0 0 (207,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Parkhall & Kirkhall Asbestos 17,358 0 0 (17,358) 17,358 0 0 (17,358) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Major Improvements 6,000 0 0 (6,000) 6,000 0 0 (6,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Newhouse Drive (Regen 1b) 5,000 0 0 (5,000) 5,000 0 0 (5,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Maress House Refurb (12,540) 0 (12,540) 0 (12,540) 0 0 12,540 On Target On Target
Other Capital works 1,975 0
SUB TOTAL 18,104,808 1,717,421 17,226,298 (878,510) 7,567,417 5,927,070 7,099,428 397,981 (865,970)
Total Expenditure 311,218,808 104,123,061 310,231,103 (987,704) 40,664,242 20,136,572 35,472,091 0 (3,292,762) (1,899,389)
Income
Affordable Housing Contributn (2,444,930) (2,444,930)
CFCR (5,151,045) (13,158) (5,151,045)
Capital Grants (6,785,747) (142,334) (6,785,747)
Prudential Borrowing (22,217,853) 155,492 (17,025,702) 3,292,762 1,899,389
Council HB fund contribution (4,064,667) (4,064,667)
Sale of Assets
Other Capital Income
SUB TOTAL (40,664,242) 0 (35,472,091) 3,292,762 1,899,389
Total Project Expenditure 311,218,808 104,123,061 310,231,103 (987,704) 40,664,242 20,136,572 35,472,091 0 (3,292,762) (1,899,389)
Total Project Income (40,664,242) 0 (35,472,091) 0 3,292,762 1,899,389
Total Net Expenditure 0 20,136,572 0 0 0 0
Check Total
On Target (+0.5% of budget)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less)
The following classifications have been used to highlight financial performance against
budget