NORTH AYRSHIRE COUNCIL 
19 March 2024 
Cabinet 
Title:    Strategic Risk Register 2024/25 
Purpose:  To seek Cabinet approval of the Strategic Risk Register for
2024/25. 
Recommendation:  That Cabinet approves the Council’s Strategic Risk Register for
2024/25. 
1. Executive Summary 
1.1 The Strategic Risk Register has been reviewed and updated for 2024/25. 
1.2 It is recommended that three of the eight previous risks remain on the Strategic Risk
Register at their existing risk scores and titles – Inequalities, Cyber Security and
Climate Change. 
1.3 The risk previously titled Financial Environment is recommended to change to
Financial Sustainability to more closely reflect the fundamental funding issues the
Council is facing in this year and future years budgets. The risk scoring remains the
same. 
1.4 The Financial Sustainability of the Health and Social Care Partnership risk and the
Community Capacity Building & Empowerment risk have increased in risk scoring
whereas the Transformation risk has reduced in scoring. 
1.5 A new risk reflecting the impact of a deteriorating property asset portfolio with
insufficient funding is proposed. 
1.6 It is proposed by the Health and Social Care Partnership’s Head of Finance and
Transformation that the previously identified National Care Service Risk be removed
from the Strategic Risk register. 
2. Background 
2.1 North Ayrshire Council is committed to ensuring that it is proactive in identifying and
managing the risks impacting on the authority. The Council recognises that a certain
amount of risk is inevitable if the organisation is to achieve its objectives.

Page 2

2.2 The aim of risk management is to reduce the likelihood and/or impact of risk by
identifying and controlling risks to the Council.  If risk is to be managed appropriately,
and Services are aware of these risks, risk management can contribute positively
towards the organisation's decision-making processes, making the Council more
innovative and effective in its approach to service delivery. 
2.3 The most significant risks are identified through the Council's Strategic Risk Register,
recognising the challenges facing the Council and demonstrating the arrangements in
place to manage these risks. 
2.4 The Strategic Risk Register has been reviewed and updated for 2024/25 and is
attached at Appendix 1 to this report.  For each of the risks detailed within the register
a number of components are identified: 
• Risk proximity factors;
• Risk score;
• Potential effect on the Council's priorities;
• Internal controls currently in place;
• Assessment of controls; and
• Additional actions identified. 
2.5 To assist in the assessment of each risk, the Council’s agreed risk matrix was used to
ensure consistency. This is used to assess the likelihood of occurrence (on a scale
from 1 to 5) and the significance of the impact of the risk should it occur (on a scale
from 1 to 5). The risk score is the product of likelihood multiplied by impact. Only those
risks rated as high or very high (10 or above) will feature on the SRR to ensure a
focus on managing the most significant risks. 
2.6 Four risks remain on the Strategic Risk Register at their existing risk scores –
Financial Sustainability (previously Financial Environment), Inequalities, Cyber
Security and Climate Change. 
2.7 The Financial Sustainability of the Health and Social Care Partnership risk has
increased in risk from score 12 to 16 due to increasing budget pressures. 
2.8 Community Capacity Building and Empowerment risk has increased from score 12 to
16 due to increasing financial and resource demands. 
2.9 Transformation risk has reduced from score 16 to 12 as a result of positive
workstream developments and programme delivery against the requirements of The
Council Plan. 
2.10 An additional risk is proposed around the condition of property and the lack of
sufficient funding for ongoing maintenance. 
2.11 It is recommended, by the Health and Social Care Partnership Head of Finance and
Transformation, that the previously identified risk regarding the implementation of the
National Care Service is removed from the Strategic Risk Register as there have been
a number of changes to the proposals. These are as follows: 
• A tripartite agreement between national and local government and the NHS in
Summer 2023 included agreement that statutory delivery functions would remain

Page 3

with local authorities and health boards, along with assets, employment of staff and
relevant funding.
• Scottish Ministers will exercise strategic framework accountability for NCS services
which will include a role in setting policy, having oversight and providing direction;
this will be done through the establishment of a National Care Service Board, but
otherwise local integration authorities will remain in place but may be subject to
some reform.
• Timescales have also slipped by 3 years, with the new arrangements not now
expected to be in place until 2029. 
2.12 Very High Risks  
• Financial Sustainability – this risk reflects the ongoing financial challenge
faced by the Council year on year (risk score 20).
• Inequalities – this highlights the socio-economic inequalities faced in North
Ayrshire (risk score 20).
• Property Asset Risk – This reflects the impact of long-term restricted budgets
on the Councils ability to maintain these to a good standard (risk score 20).   
High Risks 
• Cyber Security – this reflects the ongoing risk from external cyber-attack which
is being faced by all organisations (risk score 16).
• Transformation – this reflects the wider risks associated with delivering the
current Transformation Programme and developing a pipeline of future initiatives
(risk score 12).
• Climate Change – this risk has been on the Strategic Risk Register following the
declaration by the Council of a Climate Change Emergency during 2019 (risk
score 16).
• Financial Sustainability of the Health and Social Care Partnership – this
reflects the ongoing financial challenges faced by the Partnership and the risk
these present to the Council (risk score 16).
• Community Capacity Building and Empowerment – this highlights the
challenges associated with the community empowerment act (risk score 16). 
2.13 Council services have identified high level strategic actions within their planning for
2024/25 to help the Council mitigate against its strategic risks. These actions are
detailed in summary format in the Risk Management Action Plans following each Risk
within Appendix 1.  These actions will assist with performance monitoring and
reporting on the strategic risks. 
2.14 The Council’s Internal Audit Plan 2024/25 is scheduled to be approved at the Audit
and Scrutiny Committee on 21 March 2024 and is risk-based with clear links in place
between the audit plan and key risks the Council faces. 
Longer-term risks & Horizon Scanning 
2.15 The Strategic Risk Register identifies the most significant risks which the Council
faces at the present time. 
2.16 The Corporate Risk Management Group identifies any new relevant risks though
internal reviews and external horizon scanning utilising a number of sources.

Page 4

3. Proposals 
3.1 Cabinet is requested to approve the Strategic Risk Register 2024/25. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Council continues to have a robust long- and medium-term financial planning
framework. Key strands include development of key transformation themes and the
establishment of an Investment Fund that will generate future savings alongside
delivery of a number of key Council priorities. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The risk to the Council is that North Ayrshire residents, and in particular certain
groups, will experience increasing levels of poverty and its effects. Current control
measures fall into two categories - measures to address the root causes of socio-
economic inequalities - income through employment or benefits – and mitigation
measures to minimise the impacts of poverty. 
Climate Change and Carbon 
4.5 The Council has declared a climate change emergency and has in place an
Environmental Sustainability and Climate Change Strategy. Significant work to help
mitigate the risk of flooding is included within the Capital Plan. The Council is
undertaking an ambitious renewable energy programme. 
Key Priorities 
4.6 A successful risk management framework helps to underpin the delivery of the
Council’s strategic priorities in Our Council Plan 2023-2028. 
Community Wealth Building 
4.7 None.

Page 5

5. Consultation 
5.1 The Strategic Risk Register has been reviewed in consultation the Corporate Risk
Management Group. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Alex Fitzharris, Team Manager (Risk and
Insurance), on 01294-324515. 
Background Papers
None.

Page 6

Appendix 1 - Strategic Risk Report 2024/25 
Risk Code SRR2425_R01 Risk Title Financial Sustainability Latest Note Date 09-Feb-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The risk is that the level of funding from Scottish Government
to local government falls significantly below the level required
to operate services effectively. This will require the Council to
take increasingly difficult and challenging decisions. The
2024/25 local government settlement represents a reduction in
core funding of £2.191m (0.64%). This is against a backdrop of
significant cost increases, resulting in a Budget gap of
£16.000m for 2024/25. The North Ayrshire position is further
affected by a reducing overall population demographic and a
growing elderly population. This will further impact the
Council’s share of funding across the short, medium and long
term.
Although there is a commitment through the Verity House
agreement for Councils and Scottish Government to work
together there continues to be challenges around the level of
flexibility the Council has on key areas of Budget, most notable
in areas like HSCP funding and funding for teachers and
support staff, where conditions remain. The Scottish
Government has passed legislation to give Councils powers to
charge additional council tax for second homes. This is an area
the Council will consider within the context of local
circumstances and island communities.
Scottish Government funding to support the Council’s capital
programme has also been reduced by almost 10% in the
Budget settlement for 2024/25. Set against high inflationary
driven construction costs there is a risk that the 10-year capital
programme will be unaffordable. This could require projects to
be reduced in scale or even ceased.
Funding not keeping pace with demand
and inflationary cost pressures means that
there will be a reduction in some service
areas potentially resulting in higher risks
for service users. The future delivery of
balanced budgets will become increasingly
challenging. The capital programme could
also be significantly impacted leading to
reduced levels of capital investment.
Robust monitoring of the Council’s revenue and
capital budgets is in place as well as regular
reporting of financial performance of the IJB to
Cabinet and Audit and Scrutiny. 
To assist financial planning The Medium and Long-
Term Financial Outlook (LTFO) to 2033/34 was
approved at Council on 13 December 2023 – this is
the cornerstone of the Council's financial planning in
the medium to long term. 
The annual budget process for the General Fund
revenue and Capital Programmes and financial
performance monitoring process will continue to
provide the framework from which control measures
will continue in addressing the financial position.
Delivery of the Council’s Change Programme is also
vital in addressing the Budget challenges and this is
being progressed by the Council’s Transformation
Board, which is chaired by the Chief Executive.
Utilising the Council’s available statutory powers is
another important area in addressing the financial
challenges.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 20

Page 7

Strategic Risk Action Plan Date Updated 09-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Regular financial monitoring of Revenue and Capital Budgets.
09 February 2024:
Ongoing monitoring. 
31-Mar-2025 Mark Boyd 
Maintain Financial Governance Arrangements for IJB.
09 February 2024:
Under ongoing review.
31-Mar-2025 Mark Boyd 
Progress dialogue via COSLA with Scottish Government on a range of
areas including fair funding, multi-year settlements, reduction in levels of
ring-fenced resources, true costs of SG policy areas, financial flexibilities
and a New Deal partnership with SG and local government.
09 February 2024:
Ongoing discussions via COSLA around the Verity House Agreement and the
need for maximum financial flexibility for Councils.
31-Mar-2025 Mark Boyd 
Develop the 2024/25 to 2026/27 revenue budget (medium-term financial
strategy) and capital programme taking account of all pressures and
savings via Directorates and Transformation programme.
09 February 2024:
Options to address the £16m Budget gap for 2024/25 have been developed
for elected member consideration at Council Meeting on 28 February 2024.
Following this, require to develop a more detailed programme of options to
address the structural funding challenges over the medium and long-term.
31-Mar-2025 Mark Boyd

Page 8

Risk Code SRR2425_R02 Risk Title Inequalities Latest Note Date 25-Jan-2024
Risk Owner Audrey Sutton/Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
North Ayrshire residents, and in
particular certain excluded
groups, will experience
increasing levels of poverty and
its effects, as a result both of the
economic situation and Covid-
19.
Health inequality is closely
linked to poverty, employment
and people's earliest
experiences as children, and will
increase.
The population of North Ayrshire
is projected to fall over the next
10 years but there will also be a
larger proportion of the
population considered
dependent (not economically
active).
The impact on specific risk
groups is greatest for our
children, young people and
families, unemployed people
and those in in-work poverty
and people exposed to the
risks of drug and alcohol
addiction.
Demand for HSCP and
Council Services will
increase.
As reductions in resources
increase, early intervention
and prevention activities are
at risk, thus increasing the
potential for an increase in
costly crisis interventions.
The local economy will be
impacted by reduced
spending power by
economically inactive
residents.
The HSCP re-affirmed its commitment to Tackling Inequalities by continuing to consider it a key priority with the
Partnership’s Strategic Plan.
Through the HSCP strategic plan, the Partnership sets out actions to tackle inequality through its Partnership Pledge and
across its strategic priorities. Tackling inequalities is addressed across HSCP service areas. An example of actions to
help address local inequalities include:
Establishing the Money Matters service in 9 GP practices and 7 local schools in the more deprived areas of North
Ayrshire. This will improve accessibility of the service to those who would benefit most. Building on this approach through
the launch of the Financial Inclusion Partnership bringing a range of key partners and stakeholders together to improve
access and support for the most vulnerable NA residents.
Increase the number of employability mentors in Justice Services, to support those with experience of the justice service
into meaningful employment or training opportunities and to help divert away from criminal behaviours.
Working closely with Housing colleagues to support transitions from care and ensuring care experienced young people
can access a positive and stable housing destination.
In our Drug and Alcohol Services, we are implementing actions to reduce the number of local drug and alcohol related
harms and deaths. This includes implementing the national MAT (Medicated Assisted Treatment) standards and
increasing the number of ABIs (Alcohol Brief Interventions) delivered across North Ayrshire.
Through the Caring for Ayrshire programme, we have set out a phased approach to improve local primary care premises
(GP Practices and Health Centres). This will improve overall professional capacity within GP practices for Multi-
Disciplinary Teams, ensuring the right support is available for local people with health concerns.
Investment in early intervention teams and approaches in Children’s Services to support vulnerable families, including in
Child Protection and Whole Family Support.
The Council considers reducing inequalities to be at the heart of its work.
The Communities and Education Directorate leads the Community Planning Partnership for the Council and the CPP has
recently developed a new Local Outcomes Improvement Plan, the purpose of which is reducing inequalities. The themes
are Wellbeing, Work and World, the latter addressing climate change and fuel poverty. Locality Planning priorities and
Community Investment Fund funded initiatives are also focused on a range of inequalities, including poverty, age-related
inequalities and digital inequalities. Recent CIF-funded projects have focused on employability, addictions and community
food.
The Directorate also leads the work of the Child Poverty and Cost of Living Board, chaired by the Council Leader. The
five strategic themes of the Board to date have been:
• No Wrong Door – access to services
• Employability
• Food
• Islands
• Childcare
5 4

Page 9

Work to address child poverty and the Cost-of-Living crisis includes a range of employability initiatives to support parents
and people with disabilities, each of whom are Scottish Government priority groups.
Progress has been made with partners through a series on mini-enquiries, ensuring that lived experience influences
developments and actions. This is supported by the data and Single Shared Assessment projects being developed by the
Transformation team, to provide holistic support for residents who need it most.
The Child Poverty Early Intervention Fund is being used to address gaps in current planning and provision. Recent
funding decisions have been made, as a consequence of the mini-enquiries - to support employability and travel,
childcare developments and support for care experienced young people and families.
The Scottish Government has provided a second year of funding to address inequalities on the islands.8 This has been
used to fund energy support, welfare advice and support, third sector interventions and school activities.
The commitment to reducing inequalities is also reflected in the Communities and Education Directorate plans:
• The Educational Service Improvement Plan
• Connected Communities strategic plans and
• Facilities Management plans.
Examples of actions to reduce inequalities:
• Deployment of Scottish Attainment Challenge funding to reduce the poverty related attainment gap in schools
• Use of the Pupil Equity Fund to ensure equity of pupil experience in schools, at the discretion of head teachers
• Cost of the School Day actions to reduce, for example, the cost of school uniforms and clothing, food and outings
• Support for care experienced young people, both in schools and through youth services
• Additional national and local investment in Active Schools to focus on inequalities and equity
• The Fairer Food Network, with 14 community larders which support the needs of individual communities
• A network of warm spaces and events to mitigate energy use and social isolation
• Work to support “New Scots,” in schools, with families and in community settings through language support and
capacity building, including women’s groups
• LGBT support groups for young people and those over 18
• Mentoring support for young people in secondary schools through a partnership with MCR Pathways
Participation strategies for children and young people and adults to ensure our strategies and investment are informed by
as wide a range of views as possible.
Status Risk Score
Heat Map 
Change in Score Approach
No Change Treat
Stable 20

Page 10

Strategic Risk Action Plan Date Updated 25-Jan-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Global and national conditions which affect the cost-of-living and poverty continue
to undermine the effectiveness of local control measures. Substantial work
continues to mitigate inequalities but child poverty data, for example, continues to
show an increase. National data collection methodologies have changed which
explains the change in part, but North Ayrshire continues to have c. 29% of
children living in poverty.
Although unemployment has reduced, it continues to be a driver of poverty, with
in-work poverty a key factor.
Access to benefits is a key driver of poverty and the range of strategies described
above continues to ensure we are maximising access to entitlements. The Single
Shared Assessment work will improve this.
25 January 2024:
The wide range of strategies and initiatives described above, and
further developed and implemented, will continue to make a
significant contribution to a range of inequalities. 
Actions are being progressed and remain within the target dates
for completion.
31-Mar-2025 Audrey Sutton;
Caroline Cameron

Page 11

Risk Code SRR2425_R03 Risk Title Financial Sustainability of the Health and Social Care Partnership Latest Note Date 06-Feb-2024 
Risk Owner Caroline Cameron
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Resources have not kept pace with the demand for and
cost of social care services. The budget settlement for
2024-25 is extremely challenging with a gap of over
£10m across the IJB. Financial modelling suggests
significant ongoing challenges across the medium-term.
There is no certainty around future funding against
growing demand, increasing costs and demographic
pressures, with one-year budget settlements remaining
in place.
The ongoing work to review the Integration Scheme and
to develop new risk-sharing arrangements between the
Council and Health Board in relation to the acute set
aside and primary care prescribing present a financial
risk to the Partnership.
An overspend in the region of £3.7m is projected for
2023-24 which will reduce the reserves held by the
Partnership to less than the recommended minimum
level of 2%. Low-volume high-cost care packages and
care placements and an increasing reliance on agency
staff continue to present a particular financial challenge
to the Partnership.
Funding levels could result in
savings being made that are not
in alignment with the strategic
plan. This could impact on the
future demand levels e.g.
reduction in early intervention
and prevention means that
future demand is increased. 
An in-year overspend position
impacts on financial reserves
and ultimately poses a financial
risk to the Council and NHS
Board as funding bodies. 
Funding levels increase the
requirement to transform
services at scale and pace.
The IJB actively monitors the financial position with regular detailed
reporting. Directors of Finance of the Council and Health Board have
oversight and regular updates are provided to the Council's Cabinet.
There is an integrated approach to managing the totality of NHS and
Council resources delegated to the IJB. A three-year Medium-term
Financial Outlook is updated on a rolling basis each year.
Previous financial settlements have seen both partners meet the
Scottish Government settlement conditions with any additional
resources passed to the IJB.
The IJB had uncommitted financial reserves of £5.821m at the
beginning of April 2023, which remains towards the lower end of the
good practice target of 2%-4%. In addition, £2m of additional reserves
were set aside at the start of 23-24 to offset the likelihood of an
overspend in-year, this reduces the impact on unearmarked reserves
of the current projected overspend to £1.7m.
The Partnership has developed a new 3-year Transformation Plan
2024-2027 which will be approved by the IJB in March 2024. There is
£2.2m of earmarked reserves set aside to support service change
and re-design.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 12 to 16 Tolerate
Increasing risk 16

Page 12

Strategic Risk Action Plan Date Updated Feb-2024 
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current Status:
RAG
Budget Monitoring - Regular budget monitoring reports to IJB are effective. 
06 February 2024:
Budgets are closely monitoring by the finance team in conjunction
with budget holders to enable corrective action to be taken and
regular in-year budget monitoring reports are presented to the
IJB.
31-Mar-2025
Caroline
Cameron;
Paul Doak 
Corrective Action – Transformation Board is effective  
06 February 2024:
A three-year Transformation Plan covering the period 2024-2027
will be approved by the IJB in March 2024. This focusses on
addressing the future financial challenge in a sustainable way, as
well as reviewing service delivery models and implementing local
and national priorities. 
31-Mar-2025
Caroline
Cameron;
Paul Doak

Page 13

Risk Code SRR2425_R04 Risk Title Cyber Security Latest Note Date 17-Jan-2024 
Risk Owner Fiona Walker
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The potential compromise of business operations or a
data breach orchestrated via either digital channels or
the IT infrastructure. This can include targeting of the
user base. Risk derives from both Council operations
and those of its supply chain. 
The increasing importance of delivering services
through digital channels and maximising efficiency
through effective and secure use of technology. This
includes a growing adoption of cloud-based computing
resources which extend processing capabilities, and
associated risks, beyond the Council’s network. 
Hybrid remote and mobile working is now the normal
working practice for over 3,000 staff. Such a distributed
work force increases the complexity of protecting
against cyber and data protection risks. 
Failure by Services to adopt and comply with
strategies, policies and procedures may
result in a failure to adequately ensure the
desired levels of cyber-security required to
maintain and protect council systems and
data. 
There may be a significant impact on the
authority through the release of personal
and/or sensitive information resulting in a loss
of public confidence and significant financial
loss incurred through fines and service
disruption. 
A successful cyber-attack (malicious external
or internal action) on the Council’s IT
environments could also result in significant
service disruption, loss of income streams
and possible data loss/exposure. 
Impacts of a cyber-attack could include
economic (i.e. inability to collect online
payments), societal disruption (i.e. loss of
diaries and client appointments), and
reputational damage (i.e. loss of public
confidence in digital services).
It is recognised that it is not possible for any
organisation to expect to be completely protected
against continually evolving cyber threats. A threat
actor with sufficient motivation, resource and capability
will be able to compromise the most secure system. 
The Council takes a sociotechnical approach to
reducing risk by continually developing protective
measures through technical, organisational and
people-focused controls. 
Technical controls are implemented in areas such as
network defences, secure configuration of systems,
user authentication, malware protection, and
vulnerability management. These are based on best
practice and independently tested on an annual basis
to confirm their effectiveness in accordance with
compliance schemes. 
The Council maintains a comprehensive set of policies,
standards, guidelines, metrics and reporting
mechanisms as part of its information security
governance structure. A comprehensive training and
awareness programme is delivered to nurture a cyber-
aware workforce and culture.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 14

Strategic Risk Action Plan Date Updated 17-Jan-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Incident Detection and Response – Recent cyber-attacks on public
sector organisations highlight the need for robust incident detection
and response procedures and technologies. The current response
procedures been shown to be effective based on incidents
experienced so far, however detection capabilities will need to be
reviewed and improved.
17 January 2024:
A joint procurement of a Managed Security Operation Centre (SOC) service with
other local authorities is being taken forward by the Digital Office.  This has
however been delayed due to resource challenges and to date no procurement
timescales have been set.
Given the delays to the national SOC procurement project, the Council will
consider other SOC alternatives and Manage Detect & Response (MDR) services.
31-Mar-2025 Fiona Walker 
Training and Awareness
17 January 2024:
Cyber Security in person training has resumed with multiple sessions being
organised to tackle the backlog incurred due to the pandemic.
The Cyber Security Essentials E-Learning course is a mandatory training
requirement for all staff with access to Council digital resources. Staff are also
encouraged to complete this annually. In addition, the course has been converted
into a briefing to provide as a toolbox talk to reach all of our workforce.
Phishing simulations continued to be hosted to test the effectiveness of training
and raise awareness.
Ongoing Fiona Walker

Page 15

Risk Code SRR2425_R05 Risk Title Transformation Latest Note Date 09-Feb-2024
Risk Owner Mark Boyd
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
There is a risk that transformation and change
activities, which are core to the future delivery
models and long-term financial sustainability of
both the Council and Health and Social Care
Partnership, fail to deliver at the level of scale
and pace required.
Failure to deliver transformational change
will impact on the Council’s financial
sustainability, effectiveness of service
delivery and delivery of the outcomes set
out in the Council Plan 2023-28 and the
Local Outcome Improvement Plan
(LOIP). 
Failure to deliver the HSCP
Transformation programmes across the
Partnership, involving North Ayrshire
Council (NAC) and NHS Ayrshire & Arran
(NHSAA) services may lead to the
identified outcomes not being delivered;
resulting in financial instability, reduced
performance, deteriorating patient
outcomes, and reputational damage
within North Ayrshire Health and Social
Care Partnership (NAHSCP). 
Failure to embed cultural transformation
activities may lead to difficulties in
building future workforce capacity and in
ensuring we have an engaged, skilled
and knowledgeable workforce to meet
service demand.
The transformation programme aligns to the Council Plan and is
monitored via the Transformation Board. The Board is chaired by
the Chief Executive.
Workstreams have been developed across Transport and Travel,
Accessing our Council, Land and Property assets, Sustainability,
Financial Inclusion as well as ongoing reviews across Waste
Services, ELC, Learning Resources and Housing. 
HSCP have an established Transformation Board to closely monitor
progress with plans, regular updates on programme to the IJB and
regular meetings with the Chief Executive and S95 Officer to review
progress and mitigation plans. Cultural transformation activities
continue to evolve to support the Council’s transformation and
improve effectiveness and capability. This includes sharing learning
and skills, engagement, design experiments and a whole systems
approach to transformation and change. 
Our workforce planning approach utilises a variety of tools and
techniques, such as career development, succession planning,
vacancy management, redeployment and early release schemes to
ensure our workforce requirements for the future, in terms of skills
and capabilities, are planned. Each Head of Service has a workforce
plan, and these are monitored six-monthly with continued HR
support and guidance to ensure service review and redesign of the
workforce is on track.
3 4
Status Risk Score
Heat Map  
Change in Score Approach
Reduce from 16 to 12 Treat
Stable 12

Page 16

Strategic Risk Action Plan Date Updated 25-Jan-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Existing project level governance and controls remain effective and are
constantly reviewed.
25 January 2024: 
Progress on Transformation projects continues to be governed and
monitored via the Transformation Board which is chaired by the
Chief Executive. Meetings held quarterly Workstreams have been
fully developed and progress and all actions tracked. Financial
efficiencies across commercial property, waste review, learning
resource review, ELC review and the sustainability programme have
been fed into the Council’s Budget programme for 2024/25 to
2026/27.
Quarterly
Mark Boyd / Chief
Executive and
Executive Directors 
Review current governance arrangements and project delivery in view of
land and property workstream to seek optimal delivery aligned to the
council’s net zero ambitions.
25 January 2024:
Key progress made around Irvine Based locality property Review.
Next stages to present Cabinet Paper in March 2024 to consider
plans.
March 2024
Mark Boyd / Chief
Executive and
Executive Directors

Page 17

Risk Code SRR2425_R06 Risk Title Climate Change Latest Note Date 08-Feb-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Climate change is expected to continue and
worsen in the future if no action is taken,
with increases to mean global temperatures,
sea level rises and the increasing frequency
and severity of weather events such as
floods, heatwaves, droughts and storms. 
More frequent and intense heavy rainfall
events increase the risk of soil erosion and
flooding. 
Rises in mean sea level increases risks of
coastal erosion, flooding, saltwater intrusion
and soil salinisation (risk to agricultural land
and freshwater habitats). 
Severe weather is already affecting public
services across Scotland, with operational,
reputational, financial and legal
consequences. 
There is also an ongoing impact of severe
winter weather including snowfall and
freezing temperatures which impact service
delivery and the integrity of our roads open
space and buildings infrastructure. This shift
in weather patterns caused by climate
change is also affecting biodiversity across
Scotland.
Increased frequency of severe weather
conditions and flooding events may lead to
more instances of damage to Council
infrastructure and property, interruptions to
service delivery and increased demands
on services, often with little notice. 
Risk to life, transport disruption and
pollution to the local environment, as well
as impact adversely on the local economy
if businesses are unable to operate. 
Council requirement to provide immediate
response and manage the adverse effects
of more frequent and severe weather
emergency situations, including support to
local communities and businesses. 
The Council is required to comply with the
‘Public Bodies Climate Change Duties’
under the Climate Change (Scotland) Act
2009. These duties require the Council to
assess the risks, threats and opportunities
associated with climate change and
identify actions to increase resilience to
climate change.
North Ayrshire Council declared a Climate Emergency in June 2019, committing
to act on climate change and reduce carbon emissions. In January 2020 the
Council approved the target to become net-zero carbon by 2030, for both Council
estate emissions and area-wide emissions.
Following implementation of the Council’s third Environmental Sustainability and
Climate Change Strategy (2021-23), Cabinet approved the new Sustainable North
Ayrshire Strategy (2024-27) in December 2023. This strategy provides a road
map to achieve the net zero carbon emissions by 2030 target. 
There are 5 workstreams within the Sustainable North Ayrshire strategy, namely
Energy, Nature, Transport, Waste and Adaptation. We continue to utilise
Adaptation Scotland’s Capability Framework to ensure North Ayrshire takes a
strong, proactive approach to adapting to climate change.  Officers are
participating in the Sustainable Scotland Network’s ‘Adaptation Scotland
Benchmarking Group’ to learn and share best practice with other local authorities.
Adaptation actions are identified within the Ayrshire Flood Risk Management Plan
(2021), the Ayrshire Local Flood Risk Management Plan (2022), the Ayrshire
Shoreline Management Plan and in the Adaptation Capability Framework.
Flood studies are undertaken to help the Council identify areas that are at risk of
flooding and to appraise options to reduce flood risk to communities and
infrastructure.
In addition, actions to mitigate Climate Change risk are held within strategies such
as the Core Paths Plan, Outdoor Access Strategy, Local Biodiversity Action Plan,
and Weather and Winter Emergencies Plan. Asset management plans are in
place which are regularly reviewed for our Roads, Fleet, Housing, Property and
Open Spaces. 
Furthermore, through the Ayrshire Civil Contingencies Team there are emergency
planning arrangements in place in the event of severe weather and flooding
conditions causing major disruption and damage to the area or to individual
communities within it.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
No change Treat
Stable 16

Page 18

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Reducing Carbon Emissions:
North Ayrshire Council declared a Climate Emergency in June
2019, committing to act on climate change and reduce carbon
emissions. In January 2020 the Council approved the target to
become net-zero carbon by 2030, for both Council estate
emissions and area-wide emissions.
The Council has taken action against climate change since our
first Carbon Management Plan in 2006/07, by working to reduce
emissions associated with Council services, and using the
baseline year of 2005/06 from which to measure progress.
Since the baseline year of 2005/06, Council estate emissions
have reduced by 68.9%, from 67,719 tonnes of carbon dioxide
equivalent (tCO2e) to 20,940 tCO2e (a reduction of 854 tCO2e
from the previous year). Area-wide emissions are published by
BEIS. Current records show total emissions have reduced across
North Ayrshire by 42.6%, from 1,437 kilo-tonnes of carbon
dioxide (ktCO2) in 2005 to 835 ktCO2 in 2019.
To ensure North Ayrshire Council can develop a leading, cross-
sector and community led approach we established a Climate
Change Steering Group (CCSG) in 2021. The CCSG is chaired
by the Cabinet Member for Green Environment and Economy,
and brings together young people, local businesses and
community organisations from across North Ayrshire.
Existing controls remain effective and are under review as our
response to climate change develops and we progress towards
achieving net zero by the 2030 target.
8th February 2024:
Implementation of the Sustainable North Ayrshire strategy, which includes 9 strategic
principles and 46 actions under the 5 workstreams of Energy, Nature, Transport, Waste
and Adaptation. The 9 strategic principles which are being implemented are:
1.We will take a whole system approach (including behaviour change) to tackling climate
change as far as possible, including identification of optimal approaches to achieve
social and economic benefits alongside environmental ones.
2.We will continue to clarify and report transparently on our emissions so that the North
Ayrshire emissions baseline is clearly understood.
3.We will complete a Local Heat and Energy Efficiency Strategy to help understand
where efforts to reducing emissions and reducing fuel poverty are best focused.
4.We will prioritise actions in relation to two of the biggest emissions sources where
have the most influence, commonly referred to as ‘heat and fleet’, including through
project pathfinder approaches for decarbonisation of domestic and non-domestic
buildings and vehicles to bring scale and pace to emissions reduction.
5.We will work with stakeholders, including the Scottish Government, to articulate the
potential costs and skills requirements to meet our net-zero aspirations.
6.We will expand on the need for adaptation measures, recognising mitigation alone will
not combat the impacts of climate changes on communities.
7.We will identify opportunities for expansion of carbon sinks and other carbon capture
technologies, which are expected to be an essential element of our net-zero strategy to
mitigate residual emissions by 2030.
8.We will seek to expand the remit and membership of the CCSG to enable us to work
more closely with communities, taking account of outcomes from recent projects such as
Climate Action Towns and Carbon Neutral Islands.
9.We will explore the potential for carbon accounting, including carbon budgets for
Council services, to support our journey to net-zero.
Updates on progress are provided through the Council’s performance reporting system,
Pentana, on a quarterly basis, and governed through the Sustainability Board. Actions
are designed to be directly and indirectly responsible for carbon reduction and deliver
other socio-economic benefits.
31-Mar-2027 Russell
McCutcheon

Page 19

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Flood Risk Management Plan:
Cycle 2 of the Ayrshire Local Flood Risk Management Plan has
been developed and was published on 31st December 2022.
Studies and modelling will be undertaken to identify and prioritise
vulnerable areas where financial damage and risk to life are most
likely.
There is an ongoing programme of monthly inspections of debris
screens which have been installed to prevent vulnerable culverts
from blocking and causing flooding. CCTV inspections of culverts
are also undertaken to identify blockages and deterioration of
assets that might cause flooding. This has been effective in
reducing flooding, although there are capacity issues h that this
process cannot address.
The Upper Garnock Valley FPS has been completed and is
currently providing flood protection.
Ayrshire Shoreline Management Plan:
The Ayrshire Shoreline Management Plan will be replaced with a
Coastal Change Adaptation Plan. The adaptation plan will enable
the Council and other stakeholders to effectively plan our future
actions whilst allowing for flexibility in response to future changes.
It will incorporate recent international and UK advances in
adaptation and shoreline management planning to allow for local
interpretation and involvement.
22 February 2024:
1. We will undertake the actions outlined in cycle 2 of the Ayrshire Local Flood Risk
Management Plan. 
2. We will continue to look for opportunities to implement Natural Flood Management
and we will develop a range of further flood protection measures, which can be put
forward as schemes for inclusion in cycle 3 of the Ayrshire Flood Risk Management Plan
and the Ayrshire Local Flood Risk Management Plan.
3. We will complete the Millport Coastal FPS and the Mill Burn FPS.
4. We will continue to Inspect culverts, screens and watercourses for clearance and
repair work in accordance with the published schedule and prioritise maintenance works
that would substantially reduce flood risk. Efforts will be made to continue to identify
unknown culverts and add these assets to the ongoing inspection and maintenance
process.
5. We will develop the Ayrshire Coastal Change Adaptation Plan in partnership with
South Ayrshire Council and other stakeholders.
30-06-2028 Thomas Reaney

Page 20

Risk Code SRR2425_R07 Risk Title Community Capacity Building and Empowerment Latest Note Date  05 February 2024
Risk Owner Rhonda Leith
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
Unrealistic timescales for implementation of
aspects of legislation of the Community
Empowerment Act (Scotland) 2015, such as
Community Asset Transfer. 
Pressure to support community capacity building
and the variation of needs within a reducing
workforce. 
Duplication of effort across HSCP and Locality
Partnerships to foster community participation and
deliver engagement activities.
Complying with the complex and resource
intensive consultation legislation in service
redesign.
Rising energy and utility costs relating to property
management.
Budget savings and pressure on property
maintenance budgets.
Where the risk is not managed effectively the
potential benefits of community capacity building
and empowerment may be lost. 
Widening inequality gap between those
communities where levels of capacity and
engagement with the empowerment agenda are
high and those with less social capital where
interest remains low, which constrains the ability
to influence the planning and delivery service. 
Any disconnect between the Council’s
aspirations, community appetite for increasing
ownership of assets and what communities
themselves feel able and prepared to commit to
can result in community assets reverting back to
Council. 
Accelerating asset transfer risks losing services
and facilities and risks the ability to plan, connect
and deliver strategic services. 
Over-engagement carries disengagement and
engagement fatigue.
Increased property costs can be a deterrent for
organisations engaging and completing the CAT
process.
Lack of budget to undertake proactive
maintenance may result in NAC buildings falling
into disrepair detracting organisations from
progressing to lease and or ownership of NAC
assets.
Ongoing commitment to community empowerment and
locality partnerships from CPP. 
Six locality partnerships and alignment with HSCP
locality arrangements. 
Leadership of the CPP Senior Officers’ Group. 
Enabling approach with community partners and support
with third sector interface to build capacity and identify
opportunities for growth and sustainability. 
Reviewed guidance and processes relating to
community empowerment functions. 
Participatory budgeting approach local grants,
commitment to PB with partners and leading practice in
mainstreaming participatory approaches 
External funding bid help for groups through regular
meetings with third sector, funders and funding officers. 
Membership of The Consultation Institute.
Investment from Community Asset Transfer Start Up
Fund, prioritising additional staffing capacity to support
CAT in Connected Communities and TACT.
A collaboration and shared resource approach across
Connected Communities Teams will be taken to ensure
the Service deliver on this priority.
4 4
Status Risk Score
Heat Map 
Change in Score Approach
Increase from 12 to 16 Tolerate
Stable 16

Page 21

Strategic Risk Action Plan Date Updated 05 Feb 2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
Implementation of Community Empowerment Act: 
Existing controls remain effective and are kept under review.  
05 February 2024: 
Strategic CLD Plan 2021-2024 identifies priorities for capacity building and the programme
of community support is addressing needs. No further update at this time.  31-Mar-2025 Rhonda Leith 
05 February 2024: 
Post implementation the plan will be monitored and reported as per statutory timescales.
31-Jul-2024 Rhonda Leith 
Staff capacity: 
Existing controls remain effective however forthcoming VER
structure changes will result in a reduction of CLD professional
staff and risks further pressures on staff to deliver effectively to
key outcomes.
05 February 2024: 
CLD service redesign will be implemented from 1st of April with a 6-month review date. The
redesign in light of VER impacts has resulted in the loss of the Capacity and Empowerment
Team, all key priorities of the team will be embedded in the newly formed localities Contact
agreement established with key 3rd Sector organisations This will mitigate the impact on
developments of the key outcomes as detailed in the CLD plan. The CLD plan review will
commence in April, following guidance due to be issued by the Scottish Government which
will be informed by the National Review Of CLD.
31-Jul-2024 Rhonda Leith 
Duplication of effort:
Clearly defined roles and lean processes are reviewed and
maintained to avoid duplication of effort and minimise time and
resource wastage. The team foster open communication
channels with both staff and key stakeholders.
05 February 2024:
Existing controls are effective but remain under proactive review.
31-Jul-2024 Rhonda Leith 
Consultation:
Existing controls remain effective. Existing controls remain
effective and hybrid engagement models have been
implemented post covid to encourage and provide greater
access to participation.
05  February 2024:  Proactive review 6 months post VER restructure to assess the
effectiveness of CLD support for community engagement and consultation.
No further update at this time.
31-Jul-2024 Rhonda Leith 
Increased property costs and lack of investment in community
assets.
05 February 2024
A collaborative approach involving PMI and CC is being used to survey and evaluate
community buildings that require investment. CAT funds have been identified for corrective
actions, which will involve incorporating green investments to support future CAT and
Service development initiatives.
31-Jul-2024 Rhonda Leith

Page 22

Risk Code SRR2425_R08 Risk Title Property Asset Risk Latest Note Date  08-Feb-2024
Risk Owner Russell McCutcheon
Risk Proximity Factors Consequences / Impact Existing Risk Control Measures Likelihood Impact
The long-term impact of restricted budget
availability for investment in the Council’s property
assets means these assets means they are in
declining condition and have greater long term
investment needs. 
Systemic building safety issues have been
evidenced by issues such as national high profile
safety issues, and the presence of RAAC through
the public sector property portfolio. These have
highlighted the substantial increasing burden of
property asset management.
There have been a number of near misses or
critical failures of aging heating plant and
equipment which the council cannot afford to
replace on a programmed basis.
Inflationary pressures, and on-going volatility in the
construction & related activities sphere, place
further difficulties in the ability of restricted budgets
to address all priorities. 
Maintenance issues and failure of building
components are increasingly likely to result in
disruption to service delivery. There is also an
increasing risk of health and safety and statutory
compliance obligations not being achieved. 
Property events requiring significant interventions
leading to service disruption, closure of facilities,
decant etc. are in increasing in frequency and
often over-lapping (often coinciding with weather
events).
Property condition information is gathered and recorded
within the Council’s electronic asset management
system, providing a baseline to measure building
element lifecycle replacement requirements across the
corporate estate.
Limited investment is therefore targeted on priorities. 
Reactive maintenance, and statutory compliance are
also undertaken corporately by PMI by appropriately
trained / experienced staff. 
There is an on-going Transformation programme
workstream focusing on property rationalisation as a
means of reducing the financial burden of the estate
through reducing overall area occupied (aligned to
carbon reductions). 
Post Incident reviews and lessons learned exercises
with actions undertaken where feasible to do so.
Risk based property reviews are underway to examine,
on a property by property basis, where property risks
have the potential to impact service delivery. The
information gathered influences both investment plans
and business continuity plans. This work is on-going in
respect of the school estate and is being rolled-out to
other services’ assets.
4 5
Status Risk Score
Heat Map 
Change in Score Approach
New Risk Tolerate
Increasing 20

Page 23

Strategic Risk Action Plan Date Updated 08-Feb-2024
Analysis of Effectiveness of Controls Further Action Required Target Date for
Completion
Officers
Responsible
Current
Status: RAG
CC&M team within PMI managing reactive maintenance and
statutory compliance.
Team resources stretched; however, restricted budgets are principal risk. Ongoing Russell
McCutcheon 
Asset management team within PMI collecting asset condition
information and leading prioritisation of lifecycle investment.
Improved asset management system is being investigated; however, restricted budgets
are principal risk. Ongoing Russell
McCutcheon 
Property rationalisation programme Locality based property review work currently underway to increase scale and pace of
implementation. Ongoing Russell
McCutcheon 
Risk based property review process Requires up to date property information, including client information and cross service
buy-in to be effective. Ongoing Russell
McCutcheon