Page 1

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Cabinet 
A Meeting of the Cabinet of North Ayrshire Council will be held in the Council
Chambers, Ground Floor, Cunninghame House, Irvine, KA12 8EE on Tuesday,
20 February 2024 at 14:30 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  Where possible, the meeting will be live-streamed
and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.   
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the minutes of meeting of the Cabinet held on 23
January 2024 will be confirmed and the Minutes signed in accordance
with Paragraph 7(1)of Schedule 7 of the Local Government (Scotland)
Act 1973 (copy enclosed).  
EDUCATION ITEMS FOR DECISION  
Reports by the Executive Director (Communities and Education) 
3 Early Learning and Childcare – Redesign of Service
Submit a report by the Executive Director (Communities and Education)
to seek approval for the proposed refresh of North Ayrshire Council’s
Early Learning and Childcare provision (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
4 Review of Early Learning and Childcare (ELC) Hourly Rate for Funded
Providers
Submit a report by the Executive Director (Communities and Education)
to seek approval from Cabinet to increase the sustainable rate of
payment to funded providers of early learning and childcare (ELC) in
North Ayrshire who are contracted by the Council to deliver funded ELC
to eligible 2–5-year-olds (copy enclosed). 
5 Naming of the New Primary School at Montgomerie Park, Irvine
Submit a report by the Executive Director (Communities and Education)
to select a name for the new non-denominational primary school currently
being built at Montgomerie Park, Irvine (copy enclosed). 
6 Proposals for Community Investment Fund (CIF) Expenditure
Submit a report by the Executive Director (Communities and Education)
on applications by Locality Partnerships on the allocation of CIF funding
to proposed projects (copy enclosed).  
GENERAL BUSINESS FOR DECISION  
Reports by the Executive Director (Place) 
7 Scottish Maritime Museum Trust – Memorandum of Understanding
Submit a report by the Executive Director (Place) to seek approval to sign
a Memorandum of Understanding with the Scottish Maritime Museum
Trust, to develop the Maritime Heritage Hub project at Irvine harbourside
as part of the Ayrshire Growth Deal funded Great Harbour programme
(copy enclosed). 
8 International Marine Science & Environment (IMSE) Ayrshire Growth
Deal Project - Collaboration Agreement
Submit a report by the Executive Director (Place) outlining progress in
developing a business case pathway for Ayrshire Growth Deal
investment in IMSE with partners Field Studies Council and University of
Stirling (copy enclosed). 
9 Transport Scotland - Public consultation for the Clyde and Hebrides
Ferry Services (CHFS3) Contract
Submit a report by the Executive Director (Place) to seek approval for the
proposed North Ayrshire Council submission to Transport Scotland’s
public consultation for the Clyde and Hebrides Ferry Services (CHFS3)
contract (copy enclosed). 
10  Community Wealth Building Refresh Strategy
Submit a report by the Executive Director (Place) to update on progress
of the Council’s Community Wealth Strategy 2020-2025 and seek
approval of the refreshed Community Wealth Building Strategy 2024-
2027 (copy enclosed).
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
11  Social Housing Net Zero Standard (SHNZS) Consultation
Submit a report by the Executive Director (Place) provide Cabinet with
details of the proposed new Social Housing Net Zero Standard (SHNZS)
and to seek approval of the proposed response to the Scottish
Government consultation (copy enclosed). 
12  Scottish Government Consultation on the proposed Heat in Buildings
Bill
Submit a report by the Executive Director (Place) to provide Cabinet with
details of the proposed Heat in Buildings Bill and to seek approval of the
proposed response to the Scottish Government consultation (copy
enclosed). 
13  Urgent Items
Any other items which the Chair considers to be urgent.  
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public seating areas will not be filmed. However,
by entering the Council Chambers, using the press or public seating area
or (by invitation) participating remotely in this meeting, you are consenting
to being filmed and consenting to the use and storage of those images and
sound recordings and any information pertaining to you contained in them
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. If you
do not wish to participate in a recording, you should leave the
meeting.  This will constitute your revocation of consent.
If you have any queries regarding this and, in particular, if you believe that
use and/or storage of any particular information would cause, or be likely
to cause, substantial damage or distress to any individual, please contact
dataprotectionofficer@north-ayrshire.gov.uk. 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Cabinet Sederunt 
Elected Members 
Marie Burns (Chair)
Shaun Macaulay (Vice-Chair)
Tony Gurney
Alan Hill
Margaret Johnson
Christina Larsen 
Church Representatives 
Mr Andrew Bruce
Ms Elizabeth Turbet
Rev Mark Goodman
Teaching Representative 
Ms Jacqui MacKenzie 
Youth Council Representatives 
Chair: 
Apologies: 
Attending: 
4

Page 5

Cabinet
23 January 2024
IRVINE, 23 January 2024 - At a Meeting of the Cabinet of North Ayrshire Council at
2.30 p.m.
Present
Marie Burns, Tony Gurney, Christina Larsen and Shaun Macaulay.
Also Present
Cameron Inglis and Chloe Robertson.
In Attendance
C. Hatton, Chief Executive, M. Boyd, Head of Service and D. Forbes, Senior
Manager (Finance) (Chief Executive’s Service); A. Sutton, Executive Director, R.
Leith, Head of Service and C. Hope, Senior Manager (Communities) (Communities &
Education); R. McCutcheon, Executive Director, D. Hammond, Head of Service
(Sustainability, Transport and Corporate Property), L. Kirk, Interim Head of Service
(Economic Development & Regeneration) and N. McIlvanney, Interim Head of
Service (Growth, Investment & Employability) (Place); A. Craig, Head of Service, J.
Hutcheson, Senior Communications Officer (Communications) and S. Wilson,
Committee Services Officer (Democratic Services).
Apologies
Margaret Johnson and Alan Hill.
Chair
Marie Burns in the Chair. 
1. Declarations of Interest
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors.
2. Minutes
The Minutes of the Meeting of the Cabinet held on 5 December 2023 were confirmed
and the Minutes signed in accordance with Paragraph 7 (1) of Schedule 7 of the
Local Government (Scotland) Act 1973.
Agenda Item 2
5

Page 6

3. Council Plan Mid-Year Progress Report
Submitted a report by the Head of Service (Democratic Services) to consider and
approve the Council Plan Mid-Year Progress Report 2023-24 attached at Appendix 1
to the report. 
The Cabinet agreed (a) to approve the Council Plan Mid-Year Progress Report
2023-24 attached at Appendix 1; and (b) to refer the Council Plan Mid-Year Report
2023-24 to the Audit and Scrutiny Committee for consideration.
4. Capital Programme and Treasury Management Performance to 30
November 2023
Submitted a report by the Head of Service (Finance) on progress in delivering the
Capital Investment Programme 2023/24 and the associated Treasury Management
Performance to 30 November 2023. 
A Member asked a question and was provided with further information in relation to
the review of local authority capital accounting arrangements and the associated
risks.
The Cabinet agreed to (a) approve the virement proposals noted within the HRA
programme detailed in appendix 2 to the report; and (b) note (i) the revisions to
budgets outlined in the report; (ii) the General Services and HRA revised budgets at
30 November 2023; (ii) the forecast expenditure to 31 March 2024; and (iii) the
estimated performance against the Prudential Indicators set out in the Treasury
Management and Investment Strategy. 
5. Revenue Budget 2023/24: Financial Performance to 30 November
2023
Submitted a report by the Head of Service (Finance) advising Cabinet of the financial
performance for the Council at 30 November 2023. 
Members asked questions and were provided with further information in relation to:
• the overspend  for residential placements for children and demand pressures
affecting the Health and Social Care Partnership  (HSCP) and the action plan
being progressed  on a partnership basis to address issues;; and
• the results of the Reinforced Autoclaved Aerated Concrete (RAAC) surveys
carried out across the authority and the associated costs for remediation
works.
The Cabinet agreed to (a) approve the virements detailed in Appendix 7 to the
report; and (b) note (i) the information and financial projections outlined in the report;
and (ii) the latest financial projection for the Health and Social Care Partnership
highlighted at section 2.6 of the report.
6

Page 7

6. North Ayrshire Local Heat and Energy Efficiency Strategy
Submitted a report by the Executive Director (Place) seeking approval of the 
draft North Ayrshire Local Heat and Energy Efficiency Strategy (LHEES) 
and Delivery Plan attached at Appendices 1 and 2, respectively, to the report.
A Member asked a question and was provided with further information in relation to
district heating networks and the role these played in decarbonising domestic heat
demand in North Ayrshire.
The Cabinet agreed to approve the draft LHEES and Delivery Plan attached at
Appendices 1 and 2, respectively, to the report.
7. North Ayrshire Strategic Tourism Infrastructure Development Plans –
Mainland and Islands
Submitted a report by the Executive Director (Place) seeking approval for Strategic
Tourism Infrastructure Development Plans for the North Ayrshire Mainland and
Islands, to support funding applications for projects which helped manage
infrastructure relating to domestic tourism. The draft Strategic Tourism Infrastructure
Development Plan – Mainland and draft Strategic Tourism Infrastructure
Development Plan – Islands were attached at Appendices 1 and 2, respectively, to
the report. 
A Member asked a question and was provided with further information in relation to
the interventions identified within the report and how these could be translated into
delivery through a process of prioritisation and identification of funding sources.
The Cabinet agreed to approve (i) the draft Strategic Tourism Infrastructure
Development Plan – Mainland set out at Appendix 1 to the report; and (ii) the draft
Strategic Tourism Infrastructure Development Plan – Islands attached at Appendix 2
to the report. 
8. UK Shared Prosperity Fund – Communities and Place Fund Update
Submitted a report by the Executive Director (Place) updating on the first round of
the Communities and Place Fund under the UK Shared Prosperity Fund and seeking
approval for the proposed approach to the second round for 2024/25. 
A Member asked a question and was provided with further information in relation to
the likely availability of further funding beyond 2024/25. 
The Cabinet agreed to (a) note the update on the first round of the Communities and
Place Fund in 2023/24 and (b) approve the proposed approach to the second round
of the Fund in 2024/25.
7

Page 8

9. Levelling Up Fund – Round 3 Provisional Award
Submitted a report by the Executive Director (Place) on the provisional UK
Government Levelling Up Fund Round 3 award for the Levelling Up For Ayrshire –
Commercial and Low Carbon Infrastructure Project and seeking approval to
complete the validation and onboarding process. 
A Member asked a question and was provided with further information in relation to
the industrial units constructed at three sites in Irvine, North Ayrshire and the letting
arrangements.
The Cabinet agreed to (a) approve (i) acceptance of the provisional award for the
Levelling Up For Ayrshire – Commercial and Low Carbon Infrastructure under the
Levelling Up Fund Round 3 subject to the successful completion of the validation
and onboarding process; and (ii) the proposed amendments to the original
application proposal; and (b) provide delegated authority to the Executive Director
(Place) to conclude the validation and onboarding process and, subject to successful
completion, progress project development and delivery; and (c) receive a further
update on progress as part of the annual Regeneration Delivery Plan update report.
10. Amendment to the Approved Community Asset Transfer of Ardeer
Quarry Football Ground and Adjacent Land
Submitted a report by the Executive Director (Communities and Education) seeking
approval for an amendment to the Community Asset Transfer of Ardeer Quarry
Football Ground. A map of the site at Ardeer, Garnock Road, Stevenston was
attached at Appendix 1 to the report.
The Cabinet agreed to (a) amend the previously approved Asset Transfer of Ardeer
Quarry Football Ground and adjacent land from North Ayrshire Council to Scottish
Charitable Incorporated Organisation (SCIO), "TASS Community Sports” to include
an additional area of adjacent land; and (b) authorise officers to conclude the
associated legal and community asset transfer processes for Ardeer Quarry Football
Ground and adjacent land, inclusive of the additional piece of land. 
11. Proposals for Community Investment Fund (CIF) Expenditure
Submitted a report by the Executive Director (Communities and Education) on
applications by Locality Partnerships on the allocation of Community Investment
Fund (CIF) funding to proposed projects. Applications from Beith Community
Association SCIO, Garnock Valley Locality Partnership Working Group, Bourtreehill
and Broomlands Community Association, Fullarton Community Association, Turning
Point PEAR Project and Stevenston Community Council were attached at
Appendices 1 – 6, respectively, to the report. 
Having reviewed the applications in line with the CIF criteria, the Cabinet agreed to
approve CIF awards to (i) Beith Community Association SCIO (£22,098.04); (ii)
Garnock Valley Locality Partnership Working Group (£51,200); (iii) Bourtreehill and
Broomlands Community Association (£12,777); (iv) Fullarton Community Association
8

Page 9

(£100,000); (v) Turning Point PEAR Project (£96,112); and (vi) Stevenston
Community Council (£29,988).
12. Public Conveniences
Submitted a report by the Executive Director (Communities and Education) updating
on the current position and future operation in relation to public conveniences in
North Ayrshire.
The Chair, on behalf of the Cabinet, acknowledged that a community consultation
period was planned and requested that the paper be amended to remove “or close
thereafter” from the site recommendations pending the outcome of the consultation
process.
The Cabinet agreed to (a) approve the proposals for the future of the remaining
Council-operated public conveniences as set out in this report, subject to the above-
mentioned amended wording; and (b) receive a further report in April 2024 to
consider the results of the engagement in relation to community interest in five public
conveniences. 
13. Urgent Items
There were no urgent items.
The meeting ended at 3:35 p.m.
9

Page 10

10

Page 11

NORTH AYRSHIRE COUNCIL 
20 February 2024 
North Ayrshire Council Cabinet 
Title:    Early Learning and Childcare – Redesign of Service 
Purpose:  To seek Cabinet approval for the proposed refresh of North
Ayrshire Council’s Early Learning and Childcare provision. 
Recommendation:  That Cabinet approves the proposed redesign of North
Ayrshire’s Early Learning and Childcare provision as outlined in
this report. 
1. Executive Summary 
1.1 1.1   North Ayrshire Council (NAC) has implemented the Scottish Government’s
policy to provide 1140 hours of funded Early Learning and Childcare (ELC) to eligible
children since August 2021, utilising the additional grant funding received to support
this new policy. 
1.2 This report provides information on a proposed refresh of provision taking into
consideration local uptake data and engagement with parents, carers, and staff in North
Ayrshire on the redesign of the service, within a significantly reduced budget. This paper
also outlines for Cabinet’s consideration the potential workforce implications, service
impacts and opportunities, and proposed approach to organisational change in
delivering required service changes and cost reductions. 
1.3 Revised delivery models proposed in this paper take into consideration affordability,
local demand for places, and the views of North Ayrshire families who currently or will
soon access this service.     
2. Background 
2.1    Early Learning and Childcare Funding 
2.1.1 The Scottish Government introduced a policy to increase funded ELC for eligible
children from 600 hours per year to 1140 hours per year from August 2020, supported
through the provision of specific annual grant funding to local authorities. North
Ayrshire Council phased in this programme with full implementation of 1140 hours of
funded early learning and childcare for all eligible children from August 2021.  There
was a delay in full implementation due to the impact of the Covid-19 pandemic.
Agenda Item 3
11

Page 12

2.1.2 Data for the whole of Scotland shows that there are fewer children eligible for funded
ELC and that the uptake of 1140 hours is lower than originally anticipated when the
multi-year grant funding agreement was reached. 
2.1.3 In line with the national picture, the uptake of children’s ELC places in North Ayrshire
has been lower than originally estimated. In addition, declining birth rates will continue
to impact the overall level of uptake. Current North Ayrshire Council capacity is 2228
spaces with 1852 spaces allocated to children accessing their full 1140 hours through
a Local Authority provision (83% occupancy rate). 
2.1.4 Scottish Government has advised local authorities that they now intend to replace the
specific annual grant funding for 1140 funded hours and provide an annual core
funding quantum for the provision of early learning and childcare. The Scottish
Government has worked with COSLA to agree the annual core quantum for 2024/25
onwards. 
2.1.5 The share of the annual quantum received by local authorities is based on:
a) the number of eligible children in the local authority area; and
b) the percentage uptake of 1140 hours in the local authority area. 
2.1.6 A cumulative budget reduction of £1.527m was confirmed in 2023/24 due to the factors
outlined in 2.1.5. To date, the £1.527m budget reduction has been met through use of
temporary funding sources, including earmarked funds, to enable longer term planning
to take place and the current proposals to be developed. 
2.1.7 As a result of the factors outlined in 2.1.5, a local review of early learning and childcare
service delivery is underway, governed by an ELC Review Board. The key aim of this
review is to redesign the early years service to meet current and anticipated levels of
demand, which has been informed by local data, within the revised Scottish
Government 2024/25 funding envelope. This includes the implementation of refreshed
delivery models through the proposals outlined in section 3.1. 
2.1.8 It should also be noted that the Scottish Government has outlined an ambition to
increase the eligibility of 2-year-olds to access 1140hrs of funded ELC. North Ayrshire
Council currently makes provision for eligible 2-year-olds in several establishments,
and these children are typically referred by Health Visitors. Should the eligibility for 2-
year-olds be expanded at a future date or expanded to include all 2-year-olds, then
there would be a requirement to again increase ELC delivery. There is currently no
published timescale for this. 
2.2 Current ELC delivery models
2.2.1 Funded ELC is delivered by North Ayrshire Council alongside our funded providers,
which are predominantly private nurseries and childminders. As of the 2023 census
return, 2394 children in total are accessing 1140 hours of funded ELC in North
Ayrshire. A breakdown is provided below: 
12

Page 13

Type of provision No. of
children
Overall % of
children accessing
1140 
Full 1140 hours through Local Authority  1852 77% 
Full 1140 hours through Partner Nursery  427 18% 
Full 1140 hours through Partner Childminder 21 1% 
1140 hours through a blend of providers 94 4% 
2.2.2 Based on wide-ranging consultation at the original design stage, there are currently
three models of service delivery provided by North Ayrshire Council schools and ELC
centres:
Model Service Provided Number of 
Establishments
1
8am to 6pm over 48 weeks per year. Option of
either full year (48 weeks) or term time (38 weeks)
with a variety of children’s attendance patterns to
obtain 1140 hours of funded ELC.
24
2
8.45am to 4.30pm over term-time (38 weeks). 665
hours of funded ELC provided by NAC with 475
hours available to blend childcare with a private
nursery or childminder.
11
3
9am to 3pm over term-time (38 weeks).  Children
attend 6 hours each day to obtain 1140 hours of
funded ELC.
8
2.2.3 An overview of the current models delivered in each locality is provided below:
Locality Model 1 Model 2 Model 3
Kilwinning 3 2 0
Irvine 7 4 0
Three Towns 7 4 0
Garnock Valley 4 1 1
North Coast 2 0 2
Arran 1 0 5
Totals 24 11 8 
2.2.4 In delivering ELC, the Council is required to maintain a minimum statutory adult:child
ratio based on the age group of children. For children aged 3-5 years, this ratio is 1
adult to 8 children. For children under the age of 3, this ratio is 1 adult to 5 children. 
2.2.5 The employee budget required to support current service delivery models is £16.8m.
Existing model 1 and 2 sites require complex staffing schedules to ensure statutory
ratios are maintained across a maximum day from 8am to 6pm that enable lunch
breaks as well as annual leave for full year staff. 
13

Page 14

2.3 Engagement with parents and carers
2.3.1 Following Cabinet approval on the 5th of December 2023, an engagement exercise
took place between the 18th of December 2023 to 26th of January 2024 to gather views
of parents and carers to inform revised models. Views were gathered via an online
survey, which was promoted in several ways. These included cascading information
to parents and carers via early years establishments and funded provider networks;
emailing current families accessing North Ayrshire’s ELC service and/or primary
school education directly; and promoting this via social media channels. The survey
was completed by 835 respondents. 
2.3.2 835 parents and carers responded to the survey with 556 respondents indicating they
access their entitlement to 1140 hours through a North Ayrshire Council early years
provision (67%). The remaining 33% of respondents either accessed a ‘private/
voluntary early years’ (169 respondents), ‘childminder’ (40 respondent), or ‘a blend of
these services’ (70 respondents). The primary benefits of early years provision
delivered across North Ayrshire were recorded as ‘child wellbeing / development’ (737
respondents), ‘support to work/ study’ (372 respondents), and ‘reduced childcare
costs’ (336 respondents). 
2.3.3 The proposals within this paper focus on the redesign of ELC provision delivered by
North Ayrshire Council and consequently the analysis presented in sections 2.3.3 –
2.3.5. below and referenced in section 3.2, has been based on respondents who
access ELC through a North Ayrshire Council early years provision. A breakdown of
the model accessed by respondents accessing a North Ayrshire Council early years
provision is provided below: 
Model Number of
respondents
Percentage of
respondents
accessing ELC
through North
Ayrshire Council
ELC
Term time (full 1140 hours from a NAC
early years) 256 46%
Full year Full Year (full 1140 hours from
a NAC early years)  248 45%
Term time (blend of full 1140 hours from
a NAC and private provider /
childminder)  36 6%
Other pattern (private provision /
childminder)  16 3% 
2.3.4 Of the respondents who access ELC through North Ayrshire Council (556
respondents), 36% of families do not access their full entitlement to ELC (200
respondents). This data gathered suggests a significant number of families do not
have an available pattern that meets their needs (65 responses), have limited
providers available (48 responses), or encounter complications in accessing a
blended model (35 responses). These insights are a key driver in the proposed models
14

Page 15

outlined in section 3.1. A breakdown of the main reasons given for not accessing full
entitlement to ELC is provided below: 
Reason for not accessing full entitlement to ELC using North
Ayrshire Council early years provision
Number of
times selected
Personal choice 69
Available pattern doesn’t meet my needs 65
Limited providers available 48
Complications of accessing a blended model 35
Other 28
Unaware of full entitlement 15 
2.3.5 Parental views were also gathered on the factors that are important when deciding
which early years provision is best for their child. The two most important factors
identified by parents/carers in deciding on an early learning and childcare provision
were proximity to their home and the quality of resources and facilities of the provision.
A breakdown of all factors selected by parents / carers accessing a North Ayrshire
Council early years provision (556 respondents) is provided below: 
Factors used by parents and carers to decide which early
years provision is best for their child
No. of times
this factor
was selected
Close to home 396
Resources and facilities 299
Word of mouth / reputation 278
Availability of full year or term time place 178
My other child already attends 157
Flexibility in hours 138 
2.4 Engagement with ELC staff and establishment leadership teams 
2.4.1 It is recognised North Ayrshire Council’s ELC staff and establishment leadership
teams play an important role in ensuring the effective delivery of high quality ELC in
North Ayrshire. Consequently, an ELC staff engagement survey was conducted
between the 11th and 25th of January to gather views from across North Ayrshire
Council’s ELC workforce. 344 responses were gathered in total. A breakdown of
responses by current model is provided below: 
Employed in current ELC
model
Number of staff survey respondents
1 262
2 60
3 22 
2.4.2 The views gathered from ELC practitioners mirror the primary benefits expressed by
surveyed parents and carers referenced in section 2.3. ELC staff highlighted ‘child
wellbeing / development’ (282 responses), ‘parenting support’ (165 responses), and
‘reduced childcare costs’ (146 responses) as the primary benefits of the ELC
provision. ELC practitioners also spotlighted ‘access to high quality indoor and outdoor
learning environments’ (155 responses); ‘improved outcomes for children and families’
15

Page 16

(150 responses); and ‘availability of full year and term time options’ (140 responses)
as all working well in the delivery of ELC. 
2.4.3 Engagement data gathered through the ELC staff survey has also provided the
education service with a greater understanding of the areas for improvement within 
ELC delivery in North Ayrshire. Areas for further improvement highlighted by
respondents include: ‘additional time out to plan for children’s learning’ (283
responses); ‘enhanced collegiate time for staff development and training’ (271
responses); and ‘increased focus on supporting staff wellbeing’ (251 responses). 
2.4.4 The staff engagement survey also provided an opportunity for staff to express any
other views in relation to the remodelling of ELC provision. Qualitative data coding of
the 213 responses obtained indicated ‘improving staff wellbeing (63 responses),
‘ensuring time for planning, preparation and professional dialogue’ (63 responses),
and ‘providing greater availability of term time 9am – 3pm ELC provision’ (46
responses) are priorities in the remodelling of North Ayrshire Council’s ELC provision.
Areas of improvement highlighted by staff will be considered as part of plans to
operationalise proposed models referenced in section 3.1. Additional findings from the
staff engagement survey are provided in section 3.2 below as part of the rationale for
the revised models. 
2.4.5 Alongside the ELC staff engagement survey, a focus group was conducted with a
sample of 9 heads of ELC establishments from across current ELC delivery models.
Analysis of the key messages from this session strengthen feedback provided by staff
gathered in the engagement survey. Key messages included a need to streamline
North Ayrshire Council’s ELC offer for parents and carers; consider approaches to
ensure enhanced time for planning, preparation, professional dialogue and staff
cohesion; and continue to provide a flexible ELC offer across localities whilst
enhancing availability of ELC provision that mirrors 9am – 3pm school term-time
provision to meet local demand. Additional key messages gathered through this focus
group are provided in section 3.2 within the rationale for proposed models.   
3. Proposals 
3.1    New ELC Delivery Models 
3.1.1 It is proposed that the existing ELC delivery models are redesigned to take account of
reducing birth rates, available data on uptake of 1140 hours funded ELC (particularly
outside of the school term), current parental preferences and the projected budget
envelope. 
3.1.2 The proposed redesigned models, which would be implemented from the new
academic session in August 2024, are as follows:   
Revised
Model
Service Provided Number of 
Establishments
1 8am to 6pm over 48 weeks per year. Children
can attend 5 half day sessions (am or pm) each
week, or 2.5 days per week to obtain 1140 hours
of funded ELC (23.75 hours per week).
9
16

Page 17

2 8am – 6pm over term time (38 weeks). Children
can attend one full day and 4 half day sessions
(am or pm) per week to obtain 1140 hours of
funded ELC (30hours per week).
13
3 9am to 3pm over term-time (38 weeks). 
Children attend 6 hours each day to obtain 1140
hours of funded ELC (30hours per week).
22 
3.1.3 The redesign of models is based on a review of ELC requirements across localities
and ensures North Ayrshire Council will continue to meet the Scottish Government’s
principles of flexibility and accessibility for parents and carers. The proposed
changes to models across all North Ayrshire Council establishments are provided
below. It is important to note that proposals reconfigure current ELC models and
there are no proposed closures of any North Ayrshire Council ELC provisions: 
Model  Hours of delivery No. of weeks Current Proposed
1
8am – 6pm 48 weeks
(Full Year)
24 9
2 (existing
model) 
8.45am – 4.45pm 38 weeks 
(Term Time)
11 0 
2 (revised
model) 
8am – 6pm  38 weeks 
(Term Time)
0 13 
3
9am – 3pm  38 weeks 
(Term Time)
8 22 
3.1.4 There are no catchment areas prescribed within ELC guidance. Parents and carers in
North Ayrshire are asked to list their choice of five establishments on application. In
the event that the Council is unable to accommodate any of these choices, the service
will allocate an alternative place for a child which is the closest establishment to the
home postcode (unless a different request is submitted). The recent survey reinforced
that location is important to parents and carers. Therefore the range of proposed North
Ayrshire Council model options available to parents and carers is shown below on a
locality basis: 
Locality Model 1 Model 2
(revised)
Model 3
Kilwinning 2 2 1
Irvine 2 4 6
Three Towns 2 4 5
Garnock Valley 1 2 3
North Coast 1 1 2
Arran 1 0 5
Totals 9 13 22 
17

Page 18

3.1.5 An options appraisal within the redesign process explored the possibility of removing
existing model 2 options in favour of 12 model 1 sites and 32 model 3 sites. Whilst this
realised additional savings and reduced the complexity in the ELC offer for parents
and carers, this was ruled out as capacity within North Ayrshire Council ELC
establishments would be reduced below anticipated levels of demand. This would
likely result in North Ayrshire Council being unable to deliver 1140 hours of ELC to all
eligible children should greater numbers of North Ayrshire families wish to access a
Council provision. 
3.1.6 The redesigned models will ensure that there is capacity for all eligible children across
North Ayrshire Council to receive 1140 hours of funded ELC provision either through
a North Ayrshire Council establishment or a funded provider. 
3.2 Rationale for model changes 
3.2.1 The proposal to reduce the number of ELC establishments delivering full year
provision was informed by uptake data from the 2023 summer holiday period. 41% of
3-5 year olds and 44% of eligible 2s did not opt to access 1140 hours during this period
and consequently did not benefit from their full entitlement. Parental engagement
survey findings suggest the inverse of this with only 21% of respondents who access
a full year provision (52 respondents) indicating they do not use their full entitlement
within a full year provision. This sample of parents who responded to the engagement
survey and access a full year provision is therefore not representative of all parents
accessing full year provision due to the disparity in uptake data versus engagement
survey responses. Staff engagement survey respondents who chose to express a
view on future remodelling indicated further work is needed to improve uptake of full
1140 hours as part of the revised models (26 respondents), with many respondents
specifically referencing reduced uptake during holiday periods. This perspective was
also supported by some heads of early years establishments operating a current
model 1 site. 
3.2.2 Increasing the number of term time only facilities is supported by data demonstrating
that term time service is the most popular choice for parents / carers with almost all
current term time establishments being full. Enhancing availability of term-time 9am –
3pm ELC provision was also viewed as a priority by respondents to the ELC staff
engagement survey. 20% of staff survey respondents who chose to express their
views on the remodelling of ELC indicated a preference for increasing availability of
term time 9am – 3pm ELC provision (43 respondents). Reasons provided for this
preference were to better support families to avoid the need for multiple childcare
arrangements if a child accessing ELC has school-aged siblings; and providing greater
scope for parents / carers to access work, further education, or training opportunities.
It should also be noted engagement with heads of ELC establishment and some staff
survey respondents who chose to express a view on the remodelling of ELC indicated
North Ayrshire Council should continue to offer a range of flexible ELC options (43
respondents), including full-year provisions (13 respondents). Data gathered from the
parental engagement survey also supports the need to continue with a range of
options as 32% of respondents accessing a North Ayrshire early provision (178
respondents) indicated ‘availability of full year or term time place’ was a factor when
deciding which early years provision is best for their child. 
18

Page 19

3.2.3 Blending of ELC provision through current models is not widely utilised across North
Ayrshire. Current data shows that only 20% of those currently attending a model 2
ELC provision blend their 1140 entitlement across a local authority and funded
provider provision, with some only using a few hours per week from a funded provider.
Notably, this data also highlights that 80% of children in model 2 sites do not access
475 hours of their 1140 entitlement due to challenges of securing a blend that meets
their needs. Data gathered from the parent and carer engagement survey provides
further evidence of the challenges around a formalised blended model. 24% of the
respondents who access an early years provision provided by North Ayrshire Council
but do not utilise their full entitlement (200 respondents in total) referenced ‘limited
funded providers’ (48 respondents) as a factor. In addition, 18% of respondents who
do not access their full entitlement referenced ‘complications of accessing a blended
model’ (35 respondents) as a barrier to using their full 1140 hours entitlement with
North Ayrshire. 
3.2.4 North Ayrshire’s funded providers play a vital role in supporting families and North
Ayrshire Council will continue to work in partnership to promote blended ELC provision
as an option that can be utilised by parents to meet their early learning and childcare
needs. Blending with a funded provider continues to be proposed as a choice for
parents and carers, which can be pursued through engaging in discussions with a
North Ayrshire ELC establishment. 
3.3 Direct people and financial implications of the proposed review of delivery
models 
3.3.1 The early years projected employee budget required to support the proposed new
service delivery models is £15.3m. The overall remodelling proposals generate a
saving of £1.074m with an August 2024 implementation or an equivalent full year
saving of £1.611m. It is important to note that the financial implications of this change
now result in the alignment of resource requirements with available levels of funding. 
3.3.2 The proposed redesign of the early years’ service will impact on the current ELC
workforce of approximately 450 early years employees (DSM 317.9 FTE entitlement).
This will include shifts in requirements from full-year to term-time working and in the
weekly working hours required to support children’s attendance patterns.  
3.3.3 In recognition of the significant impact of these proposals an Organisational Change
Plan will be developed in consultation with trade unions to set out the organisational
change process, communication and engagement plan, and timeline. 
3.3.4 The proposed Organisational Change Plan would include the use of service redesign
principles including Voluntary Early Release (VER) and compensatory payment for
loss of earnings as means of mitigating the impact of these proposals on affected
employees. 
3.4 Consideration of adjustment to eligibility dates for funded early learning and
childcare 
19

Page 20

3.4.1 In North Ayrshire a child becomes eligible for funded early learning and childcare at
the beginning of the school term following their third (or in some cases second)
birthday. This is aligned to the Scottish Government standard outlined in the Children
and Young People (Scotland) Act 2014 and in the associated Scottish Statutory
Instruments and has been in place in North Ayrshire for a number of years. 
3.4.2 An opportunity was taken during the review of delivery models to reassess when
eligible children can start receiving funded early learning and childcare in North
Ayrshire. Specifically, consideration was given to changing the start of funded
provision from the term after the child’s birthday to the month after the child’s birthday. 
3.4.3 Detailed financial modelling was undertaken to assess the viability of this proposed
change. However, it was concluded that changing the start of funded provision to the
month after the child’s eligible birthday would increase costs significantly and is
therefore not an affordable option within the current financial envelope. This position
will be kept under review in future years. 
3.5  Proposal 
3.5.1 It is recommended that Cabinet approves the proposed redesign of North Ayrshire’s
Early Learning and Childcare provision as outlined in this report. 
4. Implications/Socio-economic Duty 
Financial 
4.1.1   The projected Early Years employee budget required to support the proposed service
delivery models is £15.3m. The proposed remodelling generates a saving of £1.074m
with an August 2024 implementation date or an equivalent full financial year budget
saving of £1.611m.   
4.1.2 The £1.527m cumulative reduction for 2023/24 referenced at section 2.1.6 has been
funded to date via earmarked reserves and unallocated funding which was available
due to the delay in implementation of 1140 hours. This has allowed appropriate
engagement with parents, carers and staff in order to ensure the proposed redesign
is fully informed by their views. It is important to note that the financial implications of
this change now result in the alignment of resource requirements with available levels
of funding. 
4.1.3 The remodelling of early years provision may require early release or mitigation
payments to impacted staff. The cost of release or compensation payments would be
met within current earmarked reserves. 
Human Resources 
4.2  The workforce implications of proposals outlined in this paper will be supported through
an Organisational Change Plan that will be developed through consultation with trade
unions. 
20

Page 21

Legal 
4.3 The National Care Standards Early Education and Childcare up to the age of 16 outlines
a statutory requirement for ratios of 1:5 for 2 to under 3s and 1:8 for children aged 3
and over in ELC provisions. The proposals outlined in this paper are cognisant of this
statutory requirement and will ensure that ratios are maintained. The Children and
Young People (Scotland) Act 2014 (Modification) Order 2021 places a statutory duty on
education authorities to make provision for 1,140 hours of funded ELC available to all
children aged 3-5, and eligible 2-year-olds. The proposals outlined in this paper enable
the local authority to more effectively deliver on this to provide full access to 1140 to a
greater number of parents and carers by realigning delivery models to better meet the
needs of North Ayrshire families. 
Equality/Socio-economic 
4.4   Proposals contained in this paper will impact the provision of ELC across North Ayrshire
with a potential impact on learners residing in North Ayrshire’s areas of highest
deprivation. Some of the proposed changes are anticipated to be positive due to the
proposed redesign of the service based on patterns of uptake. Regular reviews that
currently take place to ensure that ELC capacity and demand are as closely aligned as
possible will continue. A review of the current Equality and Children’s Rights Impact
Assessment (ECRIA) for ELC has been carried out to inform implementation. 
Climate Change and Carbon 
4.5  The revised ELC models provide a range of options to access ELC across each locality,
continuing to mitigate where possible the requirement of parents/carers to travel outwith
their locality area to access ELC. 
Key Priorities 
4.6  Proposals outlined in this report support the Council Plan 2023-28 strategic aim to
“transition to a wellbeing economy, delivering prosperity, wellbeing and resilience for
local people” and more specifically “improving educational attainment and achievement
and closing the attainment gap” activities. 
Community Wealth Building 
4.7  North Ayrshire’s Education Service works closely with a range of funded providers
(private nurseries and childminders) to deliver 1140 through procurement of local
services. Implementation of this proposal will also continue to support community
wealth building through support for parental employment. 
5. Consultation 
5.1  Engagement on these proposals has taken place via the ELC Review Board with
parents and carers, impacted staff groups, ELC management and senior leadership
teams. Further formal consultation and engagement with relevant stakeholders,
including trade unions, will take place as part of the proposed organisational change
plan. 
21

Page 22

Audrey Sutton
Executive Director Communities and Education 
For further information please contact Andrew McClelland, Head of Service (Education),
on 01294 32 324413. 
Background Papers
0
22

Page 23

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet 
Title:    Review of early learning and childcare (ELC) hourly rate
for funded providers 
Purpose:  To seek approval from Cabinet to increase the sustainable rate
of payment to funded providers of early learning and childcare
(ELC) in North Ayrshire who are contracted by the Council to
deliver funded ELC to eligible 2–5-year-olds. 
Recommendation:  It is recommended Cabinet:
a) Agrees an increase in the current hourly rate paid by the
Council to funded providers from 1st of April 2024; and
b) Agrees to receive a further report in advance of the next
annual review of the sustainable rate for funded providers. 
1. Executive Summary 
1.1 North Ayrshire Council currently contracts with 15 funded provider nurseries and 66
childminders to deliver ELC entitlement to families across the authority. Funded
providers - those in the private and not-for-profit sector and childminders - enter a
contract with NAC which requires them to meet the National Standard for Early Learning
and Childcare Providers. In return the Council pays an hourly (sustainable) rate for up
to a maximum of 1140 hours per annum for each child in their care. 
1.2 Cabinet approved an increase in the hourly rate paid to funded providers in the financial
year 2022-23. This rate increase was paid retrospectively from 1st of August 2022 and
will be in place until 31st of March 2024. 
1.3 Non-financial assistance is also provided by Council staff in the form of teacher support,
professional learning for staff and management, and quality improvement support to
ensure national ELC standards are upheld. 
1.4 Scottish Government published revised Funding Follows the Child and National
Standard for Early Learning and Childcare Providers: Operating Guidance in December
2023. This guidance sets out how settings meet the National Standard criteria and the
role of local authorities in delivering the approach. The principles in the guidance
highlight the importance of the rate setting process being underpinned by an evidence-
based approach; transparency; and partnership working between local authorities and
funded providers in the private, third and childminding sectors.
Agenda Item 4
23

Page 24

1.5 The Council’s grant funding for ELC has already reduced significantly and is anticipated
to reduce further in 2024/25 because of lower levels of eligible children than anticipated
when the original grant funding agreement was reached between Scottish Government
and Local Authorities at the outset of the programme. 
2. Background 
2.1   Since August 2021, all 3 and 4-year-old children and eligible 2-year-old children have
been entitled to 1140 hours of funded early learning and childcare per annum. To deliver
this across Scotland, Councils work with both Council-run services and local partner
providers in the private and not-for-profit sectors, including childminders, to ensure there
is sufficient capacity to deliver 1140 hours to all eligible families in their local areas. In
addition to the 43 Council establishments, North Ayrshire Council currently contracts
with 15 funded provider nurseries and 66 childminders to deliver ELC entitlement to
families across the authority. Funded providers enter a contract with North Ayrshire
Council   which requires them to meet the National Standard for Early Learning and
Childcare Providers and in return NAC pay an hourly (sustainable) rate for up to a
maximum of 1140 hours per annum for each child in their care. 
2.2 Cabinet approved an increase in the sustainable rate in May 2023 which increased the
rate from £5.31 per hour to £5.76 per hour for all eligible 2–5-year-olds. This increase
was also backdated to August 2022 with agreement this would be in place until 31st of
March 2024. It was also agreed this rate would be reviewed prior the 2024-25 financial
year. 
2.3 In addition to the hourly rate paid to providers, funded providers receive an additional
payment of £3 per meal (or the provision of a meal through the North Ayrshire Council
School Meals Service). Childminders receive £2.50 for each meal provided. All
registered childcare providers have access to funding through the Scottish Milk and
Healthy Snack Scheme to provide milk and a portion of fruit or vegetables for every
child each day at the national current rate of 58.2p per day. 
2.4 In December 2023, Scottish Government revised Funding Follows the Child and
National Standard for Early Learning and Childcare Providers: Operating Guidance in
December 2023. This guidance provides guidance on how local authorities should set
sustainable rates, based on the following principles: 
• The rate will support delivery of a high quality ELC experience for all children;
• It will be a rate that reflects the cost of delivery, including the delivery of national
policy objectives;
• The rate will allow for investment in the setting – staff, resources and physical
environment; and
• It will enable payment of the real Living Wage for those childcare workers
delivering the funded entitlement. 
2.5 In April 2019, Scotland Excel provided guidance for local authorities which set out the
following key principles for setting sustainable rates for the delivery of funded early
learning and childcare (ELC): 
24

Page 25

• Local authorities and providers should approach the sustainable rate setting process
with a focus on a high-quality ELC experience;
• The rate should be evidence-based;
• Local authorities and funded providers should work together to be as transparent
and open as commercially reasonable when discussing rates and costs;
• Local authorities should clearly set out what is included (and not included) in the
support package in addition to the hourly rate, at the point of application; and
• Inflationary and real Living Wage increases should be reviewed on a regular basis,
to understand any changes to these and their impact on costs. 
2.6 The guidance also highlights that, from a local authority perspective, the following points
should also be considered: 
• The rate should not have a detrimental effect on the local authority’s ability to continue
to pay for the service in the long-term;
• The wider package of ‘in-kind benefits,’ which are separate to the sustainable rate,
available to the funded provider as part of their contract with the local authority; and 
• The rate does not need to be cross subsidised by parents and carers through charges
for non-funded hours. 
2.7 The guidance sets out that inflationary and Real Living Wage increases should be
reviewed on a regular basis, to understand any changes to these and their impact on
costs. As the Real Living Wage changes each year, in November, and the sustainable
rate should reflect up-to-date information, an annual review of the sustainable rate is
required. As part of Scottish Government’s budget for 2024-25 it was announced that
additional funding of £200m will be provided to ensure all social care and early learning
and childcare workers in the private, third and independent sectors are paid at least £12
per hour from April 2024, which is the Real Living Wage. Further clarity is to be provided
by Scottish Government on how this will be distributed and whether this will involve local
authorities in supporting distribution. 
2.8  North Ayrshire Council provides a range of in-kind benefits to funded provider partners
which include the following measures: 
• Funded provider staff are included in all professional learning that is delivered by NAC
staff to early years practitioners;
• Funded provider managers and business owners are included in all ELC Head
Teacher meetings and in all relevant professional learning opportunities; and 
• Teacher access is provided by the Council and each funded provider nursery has an
allocated teacher who provides learning and development and quality improvement
support for staff and managers. 
2.9  Based on a declining population and a lower than anticipated national and local uptake
of 1140hrs of funded ELC, North Ayrshire Council has already received a reduction in
core allocation and specific grant allocation for the delivery of ELC.  The Scottish
Government, as part of a national review of funding, now plans to replace the additional
grant funding with an annual core quantum for the provision of ELC. North Ayrshire’s
budget will decrease by £1.6m per annum. 
2.10 North Ayrshire Council has had a significant reduction in funding since 2022/23. The
table below outlines reductions in NAC core and grant funding allocations for ELC: 
25

Page 26

Financial
Year 
ELC Specific
Grant  Funding  
ELC Specific
Grant  Funding
Reduction 
NAC Core
Allocation  
NAC Core
Allocation
Reduction  
Funding
Revision 
Total
Funding
Reduction  
  
£m  £m  £m  £m  £m  £m 
2021/22  14.013     11.654          
2022/23  13.093   -0.920   12.033   0.379   0.000   -0.541  
2023/24  12.579   -0.514   11.561   -0.684   0.212   -0.986  
Total
Funding
Movement
to 2023-
24     -1.434      -0.305   0.212   -1.527    
2.11 Engagement with the neighbouring South West Education Improvement Collaborative
(SWEIC) local authorities indicates they are facing similar financial challenges.   
2.12 In December 2023, Scottish Government and COSLA undertook a review of sustainable
rates. This review recommended updating the Sustainable Rates Guidance for 2024-
25, with a view to: 
i. Enhance guidance on the approach to rate-setting, to provide a more standardised
approach and minimise any unwarranted variation between the rates set by local
authorities (recognising that a certain level of variation is expected), including how
frequently they are set;
ii. Further develop guidance around the rates payable for eligible 2-year-olds to help
ensure these rates are sustainable and are reflective of the costs of delivery;
iii. Further develop the guidance in relation to meal rates, to help ensure these are set
sustainably and are reflective of costs;
iv. Set clearer expectations around engagement and communications for both local
authorities and funded providers in the private, third and childminding sectors
regarding the rate setting process – including ensuring that providers have greater
certainty and clarity on rates to support their financial planning; and
v. Ensure the guidance adequately supports local authorities when setting
sustainable rates for, and engaging with, childminders.   
2.13 North Ayrshire Council’s evidence-based approach has included:
• The current strategic context; 
• Prior cost analysis of ELC funded rates undertaken in 2022; 
• Benchmarking funded provider sustainable rates paid by neighbouring local
authorities; 
• Ongoing engagement with local providers; 
• The greater staff to pupil ratios required for 2-year-old pupils; and 
• Current local authority budget pressures. 
2.14 As a result it is proposed North Ayrshire Council’s funded provider sustainable rates
are increased to £6.05 per hour for 3–5-year-olds and a larger increase to £6.33 for
eligible 2-year-old children from 1st of April 2024, taking into account feedback from
partner providers in relation to greater costs for this age group. 
3. Proposals 
26

Page 27

3.1 It is recommended Cabinet: 
a) Agrees an increase in the current hourly rate paid by the Council to funded providers
from 1st of April 2024; and
b) Agrees to receive a further report in advance of the next annual review of the
sustainable rate for funded providers. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The additional cost of the increased payment will be approximately £215,000 based on
existing numbers of children. This has been included in budget planning for the 2024-
25 financial year. 
Human Resources 
4.2 None. 
Legal 
4.3 In April 2019, Scotland Excel provided guidance for local authorities which set out key
principles for setting sustainable rates for the delivery of funded early learning and
childcare (ELC). These are detailed at 2.3 above. Scottish Government Guidance
requires that rates are reviewed on an annual basis and processes will be put in place
to ensure this takes place. 
Equality/Socio-economic 
4.4 In supporting a sustainable ELC provision within the private, not for profit and
childminding sectors, we aim to reduce any inequalities of provision and quality of ELC
services. We aim to ensure all children experience the best start in life, and families are
supported into work, thus reducing poverty. 
Climate Change and Carbon 
4.5 Ensuring sustainable access to ELC provision within the private, voluntary and
independent sector ensures that parents / carers are able to access a range of ELC
services within their local community. Consequently, this encourages the use of active
travel to access provision and will encourage reduction in greenhouse gas emissions in
North Ayrshire. 
Key Priorities 
4.6 Proposals outlined in this report support the Council Plan 2023-28 strategic aim to
“transition to a wellbeing economy, delivering prosperity, wellbeing and resilience for
local people” and more specifically “improving educational attainment and achievement
and closing the attainment gap” activities. 
27

Page 28

Community Wealth Building 
4.7   The proposals support the following pillars of community wealth building: 
• Advancing community enterprises
• Supporting local business activities and increasing the variety of ownership models. 
5. Consultation 
5.1 At the previous review of sustainable rates paid to funding providers, three funded
provider nurseries took part in a confidential costs analysis exercise that was
undertaken by NAC’s Finance Business Partner team. This was used to inform the initial
rate increase in the 2023-24 financial year and informed the proposed uplift in 2024-25
financial year. North Ayrshire Council’s ELC leadership team meet regularly with funded
providers, including private and partner nurseries as well as childminders, and have
considered views expressed in relation to the need for enhanced rates for 2-year-olds
due to the requirement for lower staff to learner ratios. 
Audrey Sutton
Executive Director (Communities & Education) 
For further information please contact Andrew McClelland, Head of Service (Education),
on (01294) 324413. 
Background Papers
0
28

Page 29

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet 
Title:    Naming of the new primary school at Montgomerie Park,
Irvine 
Purpose:  To select a name for the new non-denominational primary school
currently being built at Montgomerie Park, Irvine. 
Recommendation:  That Cabinet:
• Considers the proposed names selected for consultation; and
• Decides the name of the new primary school 
1. Executive Summary 
1.1 On 27 April 2021, Cabinet approved the establishment of a new non-denominational
primary school at Montgomerie Park, Irvine. 
1.2 As a result, there is a requirement to formally name the new school.  Cabinet is asked
to consider the engagement that has taken place with stakeholders within the locality to
propose a shortlist of names and make a final decision. 
2. Background 
2.1 New housing developments at Montgomerie Park, Irvine resulted in an increase in the
local population and, subsequently, education accommodation pressures at Annick
Primary School. 
2.2 In October 2020, the Scottish Futures Trust (SFT) invited bids for funding to develop
innovative educational and community facilities as part of their Phase 2 Learning Estate
Investment Programme. North Ayrshire Council submitted a bid to obtain up to 50%
funding contribution for the proposed new primary school, inclusive of early learning and
childcare provision.  An announcement made by the Depute First Minister on 18
December 2020 included North Ayrshire Council as one of the successful bids. 
2.3 On 27 April 2021, Cabinet approved the establishment of a new non-denominational
primary school at Montgomerie Park, Irvine.  The new school was scheduled to open in
August 2023, however, due to the impact on the construction industry post-Covid, the
opening date was revised to August 2024.  Currently, the project is on track to be
completed on time and is being closely monitored for any potential delays. 
Agenda Item 5
29

Page 30

2.4 Outdoor opportunities for learning have been a key design focus, and the building will
be fully digitally capable.  The new school has been designed with sustainability as a
key priority and will be the first Passivhaus school in the Council’s portfolio.  The new
facilities include: 
• 12 classroom bases with direct access to breakout areas; 
• General purpose spaces for STEM and other non-class based school activities;
• Distinct PE and dining spaces located together with a stage area, for delivery of
music and drama;
• Nurture and Visiting Services spaces; and
• Staff resource areas. 
2.5 Agreeing a suitable name for the new school is vitally important for the project to allow
a number of key decisions to be taken timeously, e.g., school uniform/branding, signage
and décor within the building and creating a sense of identity for the new school
community. 
2.6 In August 2023, Education asked Cultural and Heritage colleagues to compile a list of
potential school names based on the history and landmarks of the local area. The Senior
Leadership Team in Education and Communities met to consider this list and following
their discussion, a shortlist of three names was selected to allow engagement to take
place with project stakeholders. 
2.7 All of the names included below appear on the 1911 Irvine Ordnance Survey map
(https://maps.nls.uk/view/75494366) and are the names of landmark features in the
area.  The three names shortlisted for consideration are as follows: 
• Belvidere Primary School – Belvidere is the name of a hill within the adjacent
Eglinton Park
• Eglinton Primary School – due to the close proximity of the Eglinton Estate to the
new school
• Montgomerie Park Primary School – the location of the school is within the
development of new homes known as Montgomerie Park 
2.8 Further to Cabinet approval to build the new school, a Stakeholder Reference Group
was established in order to facilitate the communication of information between North
Ayrshire Council and parent/carers of children who live in the new school catchment
area.  This group effectively acts as the new school community, until a new Parent
Council can be established. 
2.9 At the most recent Stakeholder Reference Group meeting, held on 26 October 2023,
the shortlist of names was presented, and feedback requested.  Further engagement
then took place across the local school communities to gather feedback on the
shortlisted names. 
2.10 In order to involve local children in the process, it was agreed that engagement would
take place with children from Annick and Lawthorn primary schools.  Officers visited
both school assemblies in December 2023 and following a short presentation outlining
the background and relevance of each name, a show of hands indicated the following
overall order of preference: 
30

Page 31

1. Montgomerie Park Primary School
2. Eglinton Primary School
3. Belvidere Primary School 
Each assembly indicated a strong preference for Montgomerie Park Primary School.  A
flavour of the comments heard: 
 ‘It is exactly the place that it’s in’ (Montgomerie Park Primary School), and
 ‘Eglinton is a nice name for a school’ 
2.8 Further to the school assemblies, the Parent Councils of both Annick and Lawthorn
primary schools were asked for their views.  Annick Primary School issued an MS Form,
to which 11 people responded as follows: 
1. Montgomerie Park Primary School - 6
2. Eglinton Primary School - 4
3. Belvidere Primary School - 1 
2.9 Lawthorn Primary School Parent Council responded via email to confirm that
Montgomerie Park Primary School was the most popular name from their engagement
with parents. 
2.10 Throughout the engagement, the following feedback and comments were gathered in
respect of each school name: 
Montgomerie Park Primary School 
Those stakeholders who expressed a preference for this name, provided the following
feedback: 
• Locally, people have already been associating this name with the new school during
construction.
• Reflects the location of the new school. 
Some stakeholders did not favour this name for the following reasons: 
• Potential confusion with Loudoun-Montgomery Primary School.
• Knadgerhill is included within the catchment area and this is not reflected in the
name ‘Montgomerie Park.’ 
Eglinton Primary School 
Some stakeholders preferred this name because it was viewed as neutral, in that it did
not exclude any part of the catchment area.  It was also noted that this name conveys
the proximity to Eglinton Park and the opportunities which this will offer for outdoor
learning. 
Some stakeholders felt that this name was more associated with Kilwinning, rather than
Irvine. 
31

Page 32

Belvidere Primary School 
During the engagement process, this was the least popular name across all groups. 
3. Proposals 
3.1 Following the consultation undertaken with the local community, it is proposed that
Cabinet: 
• Considers the proposed names selected; and
• Decides the name of the new primary school 
4. Implications/Socio-economic Duty 
Financial 
4.1 There are no financial implications within the current report.  Costs of branding, signage
and associated activities have been incorporated within the financial planning for the
new school project. 
Human Resources 
4.2 There are no HR implications within the current report. 
Legal 
4.3 There are no legal implications within the current report. 
Equality/Socio-economic 
4.4 There are no equality/socio-economic implications within the current report. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 The collaborative process which has led to the development of the options for the
naming of the new school has contributed to the creation of an identity for the new
school community.  This has contributed to the following key activities: 
• Developing strong relationships with communities and partners based on trust and
shared aspirations using their experiences to inform service provision
• Ensuring an inclusive, fair, rights-based and asset-based approach in our work
• Using dynamic data and lived experiences to inform decision-making 
Community Wealth Building 
4.7 None. 
32

Page 33

5. Consultation 
5.1 Engagement on this important matter has been undertaken with the following key
stakeholders: 
• Children and young people; 
• Parents/Carers;
• Parent Councils of Annick and Lawthorn primary schools; and
• Stakeholder Reference Group. 
The shortlist of names has also been discussed with colleagues in other relevant
Council services. 
Audrey Sutton
Executive Director, Education and Communities 
For further information please contact Lynn Taylor, Senior Manager, on 01294 324437. 
Background Papers
0
33

Page 34

34

Page 35

NORTH AYRSHIRE COUNCIL
20 January 2024
Cabinet
Title: Proposals for Community Investment Fund (CIF)
Expenditure
Purpose: To determine applications by Locality Partnerships to allocate
CIF funding to proposed projects.
Recommendation: That Cabinet:
a) Reviews the enclosed application from the Irvine Locality
Partnership in line with CIF criteria; and
b) Approves the CIF application in relation to The Micah
Project.
1. Executive Summary
1.1 Within its budget for 2017-18, North Ayrshire Council provided a funding allocation for
the creation of an innovative fund to enable communities to address the priorities they
have identified through Local Planning Partnerships and within the context of North
Ayrshire Community Planning Partnership’s Fair for All Strategy and the Council’s
Community Wealth Building Strategy. In June 2021, Cabinet approved a further £1m
top-up for the funding, with a further £2m added in November 2021.
1.2 Locality Partnerships have subsequently continued to work on their local action pans
and are refining proposals for expenditure in line with their locally identified needs. It is
a testament to the dedication of the Locality Partnerships and their community partners
that proposals are now emerging to provide create approaches to addressing local
challenges.
1.3 This report brings forward proposals which respond to the specific need of the local
community, and which have been developed based on local circumstances and
opportunities.
2. Background
2.1 Within its budget for 2017-18, North Ayrshire Council provided an allocation for the
creation of an innovative fund to enable communities to address the priorities they have
identified through Locality Planning Partnerships and within the context of North
Ayrshire Community Planning Partnership’s Fair for All Strategy and the Council’s
Agenda Item 6
35

Page 36

Community Wealth Building Strategy. A further £3m was added to the funding in 2021,
to be distributed among Localities as follows: 
2.2 It was agreed that the CIF awards would range between £5,000 and £100,000 for the
community organisations, as defined in the CIF guidance, in order to support
proposals and projects that connect with: 
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis;
• The Community Planning Partnership and Locality priorities;
• North Ayrshire Council’s values, priorities, and business objectives; and
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies; 
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of people
possible;
• Exhibit project and/or organisational innovation in their approaches to their work in
their way of addressing community challenges and in their request to Locality
Partnerships and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon requests) and efficiently and effectively managed. This can
include an organisation to be created to deliver the project;
• Include options or potential for NAC and CPP employee engagement and
volunteering where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular
basis.
Locality Value of
CIF from
first funding
allocation
(2017-18)
Expenditure
to date
Value of CIF
from second
funding
allocation
(June 2021)
Value of CIF
from third
funding
allocation
(Nov 2021)
Total balance
available
Irvine £754 000 £858 858 £290 000 £580 000 £765 142
Kilwinning £286 000 £322 190 £120 000 £240 000 £323 810
Three
Towns
£598 000 £937 561  £240 000 £480 000 £380 439
Garnock
Valley
£390 000 £415 103.04 £150 000 £300 000 £424 896.96
North Coast £468 000 £429 066 £170 000 £340 000 £548 934
Arran £104 000 £125 079 £30 000 £60 000 £68 921
TOTAL £2 600 000 £3 087 857.04 £1 000 000 £2 000 000 £2 512 142.96
36

Page 37

2.3 The proposal development and application process has been agreed as follows: 
• Locality Partnerships should continue to engage with their communities and
stimulate interest in the CIF. Each Locality Partnership will then strategically
access the applications, make links, and look at the funding ‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a full
application form, which they will decide upon before making a proposal to Cabinet
for final approval.
• The proposal will go to the next suitable Cabinet for final approval. 
2.4 The enclosed applications have been developed by community partners and North
Ayrshire Council officers and are now recommended for approval by Cabinet. The
proposals are as follows: 
2.5  The Irvine Locality Partnership 
The allocation and funds committed to date are outlined in the table below. 
The Irvine Locality Partnership CIF allocation to date:  £1,624,000
Irvine Digital Officer   £84,604*
Vineburgh & Fullarton Community Enablers  £100,000 
Irvine New Town Mens Shed   £10,000 
Irvine Harbourside Mens Shed   £10,000 
Irvine Youth Hub   £100,000 
Irvine Tennis Club  £100,000 
INPUT   £60,000 
Children's 1st   £97,580 
CHAP  £91,534
BABCA Community Garden  £12,777
Fullarton Outdoor Gym £100,000
Turning Point -  Pathways to Progress  £96,112
Balance 
£765,142 
2.6 Proposal: The Micah Project £50,000 (see Appendix 1) 
2.6.1 The Micah Project was developed in Troon initially as a response to the Covid
lockdown in 2020, becoming a SCIO (Scottish Charitable Incorporated Organisation) in
2022. Its work is aimed at supporting families and helping to restore dignity, reduce stigma
and decrease waste. The proverb “it takes a village to raise a child” inspired the idea that
by involving the community we can decrease unwanted and unnecessary items going to
landfill and support struggling families with simple solutions like clothes, food therefore
helping them to feel valued and seen. The project aims to address two crucial aspects of
child development—material need and mental wellbeing. The group understands that
children's early years are critical for their overall growth and development and that a
significant number of families face financial difficulties that impede their ability to provide
37

Page 38

basic necessities for their children, including adequate clothing and resources that support
the development of their mental health.
The group has broadened its work to initiatives across Ayrshire, such as distributing new and
pre-loved clothing at Christmas time. 
2.6.2 There are no restrictions on who can access the services they provide and they
encourage people to get involved by volunteering or by donating. This fosters
ownership, alleviates poverty and enhances wellbeing both for the individual and the
family. 
2.6.3 This project for the Irvine locality will provide a storage base, coordinator, and delivery
support within the town for a 2-year period. The project will provide a wellbeing package
for the ages of each vaccination stage - 3-6 months, 9-12 months, 2-3 years and 3-4
years. By providing a small pack of clothes and age-appropriate toys, books, and
resources that will promote early childhood development at each of their vaccinations
the group will also have the opportunity to signpost parents to more support, educate
on the value and sustainability of preloved clothing and destigmatise need by making
them available to all families. 
2.6.4 A successful small pilot has already been carried out with newborn packs in one GP
surgery, and the project will build on this, expanding the age range and the number of
surgeries participating.  The project also has already made links with local partners and
schools and will continue to build on those to expand contact points for families, as well
as working with North Ayrshire Council Community Facilities to create a network of
collection points for donations. 
2.6.5 The project supports the Irvine Locality Partnership’s priorities, in particular Alleviating
Poverty, as well as supporting a range of sustainability outcomes. 
3. Proposals 
3.1 That Cabinet: 
a) Reviews the enclosed application from the Irvine Locality Partnership in line with CIF
criteria; and
b) Approves the CIF application in relation to The Micah Project.  
38

Page 39

4. Implications/Socio-economic Duty 
Financial 
4.1 CIF funding is allocated within existing resources. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The purpose of Locality Planning is to reduce inequalities, increase community
cohesion and advance community empowerment. Each of the CIF proposals is tested
against that purpose before being presented to Cabinet. 
Climate Change and Carbon 
4.5 Environmental and sustainability along with Climate Change and Carbon issues are
considered in relation to each CIF application. This proposal supports recycle and re-
use principles. 
Key Priorities 
4.6 The proposals contained within the report support the North Ayrshire Council Plan
strategic aims: 
• To transition to a wellbeing economy, delivering prosperity, wellbeing and resilience
for local people.
• We will have active, inclusive, and resilient communities.
• A Community Wealth Building Council that is efficient and accessible, maximising
investment and focusing resources towards our priorities. 
Community Wealth Building 
4.7 The applications support the following pillars of community wealth building: 
• Advancing community enterprises;
• Advancing local ownership of underused land and buildings;
• Making financial power work for local places; and
• Supporting the local business activities and increasing the variety of ownership
models. 
5. Consultation 
5.1 The proposals contained within this report have been developed by the Locality
Partnerships, through consultation with local people, including young people. 
39

Page 40

Audrey Sutton
Executive Director (Communities and Education) 
For further information please contact Rhonda Leith, Head of Service (Connected
Communities), on 01294 324415. 
Background Papers
Appendix 1: CIF Application The Micah Project 
40

Page 41

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
The CIF will support proposals and projects that: 
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis;
• The Community Planning Partnership and Locality priorities; 
• North Ayrshire Council’s values, priorities and business objectives;
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies; 
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of people
possible;
• Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project;
• Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular basis. 
When to apply and how? 
• LPs should continue to engage with their communities, and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’. 
• If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval. 
• The finalised proposal will go to the next suitable Cabinet for final approval.
• Forms should be returned to your Locality Officer, by email if possible: 
Elaine Baxter
Locality Officer (Irvine Locality) 
North Ayrshire Council
Base:  Redburn Community Centre, Dickson Drive, Irvine, KA12 9EW
Email: ebaxter@north-ayrshire.gov.uk 
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf 
41

Page 42

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
1. Details of your organisation 
Name of Organisation 
The Micah Project 
Postal Address for Correspondence
The Micah Project c/o 30a Central Avenue, Troon, KA10 7AZ 
Name of Contact Person Helen Hogg 
Position in Organisation Trustee   
Telephone Number 07591332235 
Email Address Helen@micahproject.co.uk 
2. Brief description of your organisation 
Please include its legal status, aims and objectives, activities or services provided
and how long it has been in existence. 
The Micah Project started as a response to the 2020 pandemic supporting
families in need by matching up what people had and no longer needed with
what people needed and didn’t have. 
The proverb “it takes a village to raise a child” inspired the idea that by involving
the community we can decrease unwanted and unnecessary items going to
landfill and support struggling families with simple solutions like clothes, food
therefore helping them to feel valued and seen. 
The Micah Project became a SCIO in November 2022 and continues to lead
several wellbeing initiatives aimed at supporting families and helping to restore
dignity, reduce stigma and decrease waste. These include running the New 2U
community clothes closet, distributing food surplus and facilitating wellbeing
workshops such as sewing and cooking. Our Christmas project in 2022 saw us
distribute 568 bags of preloved and new clothing to families throughout
Ayrshire. 
42

Page 43

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP 
We have a 40+ strong team of volunteers that sort, store and organise the
physical donations that come into the project. 
We are based out of 2 local church halls in Troon who have generously provided
free accommodation for an initial 2 years but we are rapidly out growing both
premises, taking in around 1200 bin bag sized donations across the year and
require areas to sort and store all our items. 
There are no restrictions on who can access the services we provide and we
encourage people to get involved in the giving and the taking both physically by
volunteering or by donating clothes, toys etc. This fosters ownership, alleviates
poverty and enhances wellbeing both for the individual and the family. 
3. Title and summary of proposal 
Tell us about your idea. Please describe in as much detail as possible, what the
funding will be used for. 
Please include: 
• where it will be held / delivered
• who is your target audience
• who will benefit from it and how
• any partners that are involved. 
VAC PACK & N2U Irvine FUNDING 
Whilst our main base will remain in Troon, this project will be carried out in the
Irvine locality. We aim to provide a storage base, coordinator, and drivers to
ensure that we can be effective throughout this project.
Our project aims to address two crucial aspects of child development—material
need and mental wellbeing. We understand that children's early years are
critical for their overall growth and development. Unfortunately, a significant
number of families face financial difficulties that impede their ability to provide
43

Page 44

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
basic necessities for their children, including adequate clothing and resources
that support the development of their mental health.
In its simplest form we would provide a wellbeing package for the ages of each
vaccination stage - 3-6 months, 9-12months, 2-3years and 3-4years. 
Our target audience are families with under 5 year olds of which we estimate
there are about 22,000 in the Irvine area. By providing a small pack of clothes
and  age-appropriate toys, books, and resources that will promote early
childhood development at each of their vaccinations we will also have the
opportunity to signpost parents to more support, educate on the value and
sustainability of preloved clothing and destigmatise need by making them
available to all families.
We will be working closely with Community Development staff from North
Ayrshire Council and partnering with GP practices but most of our work will be
alongside the health visitors and vaccination team. We aim to begin with one
practice where we have already carried out a very successful pilot with
newborns only and build up steadily across the Irvine practices as well as
partnering and working alongside local organisations and groups, ensuring our
general ‘New 2U’ clothing closet is more accessible to the communities and
people they work with within the Irvine area by providing more drop off and
pick up points locally. This has been trialled using some of the Irvine Community
Centres and has been very successful with a number of people requesting
clothes through our discreet online ordering service 
4. What difference will this project make within the locality and to local
services and programmes? 
Please include: 
• The outcomes you aim to achieve
• How you will approach reducing inequality
• How this proposal fits with the Locality Partnership priorities of:
1. Supporting Skills & Work Opportunities
2. Enhancing our Mental Health & Wellbeing
44

Page 45

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
3. Alleviating Poverty
4. Championing Green Health & the Natural Environment 
Our outcomes: 
• Helping families alleviate poverty, reducing financial stress by receiving
and using preloved clothes 
• Supporting families to redirect income from buying clothes to other
essential bills, energy, nutritious food   
• Educating parents on the importance for our environmental footprint to
use preloved clothes and toys 
• Reduce stigma and need for families by using what is already available in
a way that show them love and dignity 
• Use sustainable fashion practices as a means to promote well-being, self-
esteem, and a positive sense of community
The Micah Project values equality by removing criteria barriers requiring
families to prove that they are in receipt of benefits. We encourage use of
preloved items by everyone, reducing stigma and encourages a dignified and
valued person-centred approach. 
We also aim to work with families who make known to us or partner agencies
that they are struggling by signposting and partnering with local organisations
that deal with mental health and wellbeing, energy provision, extra living
support or debt management. 
45

Page 46

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
5. What engagement has taken place in relation to the project? 
Please include the number of people who have been engaged with or consulted as
well as the range of people. 
As this is an entirely new project we don’t have a lot of evidence at this stage
but we are building on a very small pilot that we run through Frew Terrace GP
Surgery in Irvine. 
Dr Newton (GP with special interest in CAMHS) based at Arrol Park Resource
Centre and Darvel Medical Centre is also in support of our application and in
discussion with the child immunisation team in North Ayrshire to work out the
practicalities for delivery in the Irvine area. 
We do know from our work with Irvine Royal Academy, Crossing Together in
Bourtreehill, Friends of Redburn and the Dundonald Crescent Estate Resident
Association that the work we are involved in is very well received and verbal
feedback would evidence that it does reduce financial stress on families. This is
why we believe there is scope and we have the ability to expand the project and
enable more families to be aware of the help available. 
6. How will the project be managed? 
Please include: 
• How the finances will be managed 
• Does the proposed project contribute to volunteering or employment
opportunities in Three Towns? Please include the number of volunteering
opportunities and employment opportunities
• If there are any staff requirements, please outline your HR plans 
46

Page 47

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
Project Management:
We will establish a project management team which will include the new
coordinator, existing and new members from our volunteer team and the
charity trustees. The coordinator will be in regular communication with the
team and Board of Trustees to ensure effective collaboration throughout  the
team and oversee the Project.
This team will meet regularly and the Co-ordinator will provide regular
monitoring and progress reports to the them – this will highlight progress as
well as identify any unmet needs. 
Financial Management:
Using the budget detailed in this application the coordinator will ensure that all
expenditure is tracked and accounted for, ensuring that any spending aligns
with the approved budget by regularly reviewing and updating it as needed,
with approval from relevant stakeholders. 
Contributions to Volunteering and Employment Opportunities:
We will be highlighting available volunteering opportunities throughout the
project and having active conversations and engagement opportunities to
encourage local volunteers to participate. These will include people who travel
into Irvine for work as well as residents. 
Staffing and HR Plans:
We would be seeking to appoint a Vac Pack – New2U Coordinator who will
oversee volunteers. 
HR policies and procedures will be provided to govern staff and volunteer
conduct, performance evaluation, and conflict resolution.
There will also be a clear chain of command and reporting structure within the
project team. 
47

Page 48

COMMUNITY INVESTMENT FUND 
IRVINE  LOCALITY PARTNERSHIP
7. Amount of funding being requested 
Please supply details of funding being requested and any other funding you have
had over the past 5 years, both financially and “in kind”. 
Amount of funding requested (£) £50,000 
Please give a breakdown of cost and recent quotations where appropriate. 
Part time NEW2U / Vac Pack Coordinator – 
20 hours per week ,  total cost over 2 years - £32,400 
Purchase of Bags: 3000 = £2,200
Storage 150ft, 2 X £44 per week - £4,600 (total across 2 years) 
Delivery costs: £450 per month - £10800 
8. Monitoring and evaluation process 
Please include detail on the monitoring and evaluation processes planned or in
place. 
As detailed earlier, monitoring and evaluation of the project will be ongoing and
reports produced on a regular basis to show any progress or areas identified as
needing more work. 
We will collect feedback and comments from families and individuals receiving
the packs as well as partner agencies using the following methods including,
feedback forms, face to face interviews, impact statements, case studies and
evaluation questionnaires. 
48

Page 49

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet
Title: Scottish Maritime Museum Trust – Memorandum of
Understanding 
Purpose: This report seeks approval to sign a Memorandum of
Understanding with the Scottish Maritime Museum Trust, to
develop the Maritime Heritage Hub project at Irvine harbourside
as part of the Ayrshire Growth Deal funded Great Harbour
programme.
Recommendation: That Cabinet approves the signing of a Memorandum of
Understanding between North Ayrshire Council and the Scottish
Maritime Museum Trust to facilitate collaboration between
parties to develop the Maritime Heritage Hub project as part of
the Ayrshire Growth Deal funded Great Harbour programme. 
1. Executive Summary 
1.1 The Great Harbour programme is a key project for the Ayrshire Growth Deal in terms
of its Tourism Programme, with planned investment of £14m, subject to business case
approval. The programme aims to stimulate investment in the Irvine harbourside area
through the Ayrshire Growth Deal, including improving facilities around the
harbourside and promoting the area as a regionally significant destination that will
benefit local communities and businesses. 
1.2 The overall Masterplan for the Great Harbour area was approved at Cabinet on 5
December 2023, subject to approval of Planning Committee and sets out how the
investment will be targeted along the Maritime Mile from Irvine Railway Station to the
Beach Park. This focusses on three key areas and phases – the Coastal Hub (around
the Beach Park) as Phase 1, the Marine & Arts Hub and Public Realm (around the
Harbour Arts Centre) as Phase 2 and the Maritime Heritage Hub (around the Puffers
Café) as Phase 3. 
1.3 A Memorandum of Understanding (MoU) will help to establish a collaboration
between NAC and the Scottish Maritime Museum Trust, for the development and
delivery of the Maritime Heritage Hub as Phase 3.
2. Background 
2.1 The Scottish Maritime Museum (SMM) was founded in 1983 and operates from two
sites in Scotland at Irvine and Dumbarton, with the aim of promoting Scotland’s
Agenda Item 7
49

Page 50

maritime heritage. It is part of a network of 15 industrial museums in Scotland and is
a major heritage asset within the Great Harbour project area and an important
tourism attraction, holding a nationally recognised collection of historic vessels,
artefacts, art, and Scotland’s largest collection of shipbuilding tools and machinery. 
2.2 The SMM has an established presence within the local community as a key
institution and as custodian, interpreter, educator, provider of volunteering
opportunities and supporter of community engagement. The SMM also holds a
number of events within the local events calendar. With a growth aspiration
expressed in their Strategic Business Plan for 2022-27, the SMM is recognised as an
anchor partner for the Great Harbour project, to help achieve the ambitions of the
Masterplan and to deliver Community Wealth Building benefits as part of the project. 
2.3 Whilst the main SMM building is the “A” listed Linthouse located off Harbour Road
and Linthouse Vennel, the SMM also operates the Puffers Café and Gift Shop on
Harbour Street and adjacent to the River Irvine, where there is an opportunity to
create a focal point and to enhance and expand visitor and tourist facilities along the
main tourist route of the Maritime Mile, increasing dwell time and opportunities for
visitor spend. 
2.4 Subject to legal and funding requirements, proposals could potentially include an
extension to the Puffers Cafe building to host a new gallery for the Museum’s
maritime artwork, exhibition and education space, and additional outdoor event and
public space to the front of the building adjacent to Harbour Street. This would extend
the visitor attraction to wider and new audiences and provide more facilities for
education and community activity, alongside public amenities and tourist information
and increase employment opportunities. The project will also explore improvements
to the existing café including extending the provision into the evening, supporting the
local evening economy and activity in the area. The Maritime Heritage Hub will be
developed as the last phase of the Great Harbour programme, which is anticipated to
be on site in mid-2027. 
2.5 The project has been developed to a concept stage and, in order to realise the full
collective ambition of the partners, SMM are working to raise additional funding to
increase the scale of offer from the SMM at the Puffers Café area. The MoU
provides a basis for collaboration to allow SMM to identify fundraising opportunities
to match planned AGD investment and thereafter develop a joint business case,
setting out delivery arrangements, given that some aspects of the project will likely
be delivered by the SMM. Therefore, the MoU is required to provide the basis for
collaboration on the Maritime Heritage Hub project and to enable the parties to
work together in developing and realising the aims of the project, and establishing
its specific remit, content, total funding package, operational viability and
management and overall project governance. 
2.6 The MOU has a 12-month term, which can be extended by mutual agreement. The
aims of the MoU are to: 
• provide a basis for the Council and SMM to collaborate on the project;
• help deliver the AGD vision for the Maritime Mile, contributing to the
establishment of the wider Great Harbour destination; 
50

Page 51

• enable the Council and SMM to work together in developing and realising
the aims of the project and establishing its specific remit, content, funding
(particularly to enable SMM to identify external funding sources to support
the expansion of the SMM offer at Puffers Café), operational management
and governance. 
2.7 The Council and SMM have provisionally agreed to have regard to the following
areas of opportunity as part of the MoU: 
• Works to open up the waterfront as part of the Puffers Café compound;
• Creating a new visitor attraction to display the artworks owned by the SMM;
• Showcasing the vessels owned by the SMM in a waterfront setting; and 
• Providing new berthing facilities and upgrading existing slipways 
3. Proposals 
3.1 That Cabinet approves the signing of a Memorandum of Understanding with the
Scottish Maritime Museum Trust, to facilitate collaboration between the parties to
develop the Maritime Heritage Hub as part of the Ayrshire Growth Deal funded Great
Harbour programme. 
4. Implications/Socio-economic Duty
Financial
4.1 There are no direct financial implications arising from the proposed MoU. The Maritime
Heritage Hub project is currently estimated at around £9m with £5.6m for the proposed
building extension to create the gallery space and café upgrade, which includes
proposed Ayrshire Growth Deal funding as well as partner investment for the enabling
external, works including surrounding public realm and events space from the AGD.
The MoU will provide the SMM a window of opportunity to fund raise to develop and
deliver the gallery project to complement planned Ayrshire Growth Deal investment. 
Human Resources 
4.2 The progress of the MoU will be monitored and supported within the Growth and
Investment Team by the Great Harbour Project Lead. 
Legal 
4.3 The MoU has been developed and discussed with the SMM, in line with the terms set
out in this report and in conjunction with Legal Services. The parties will ensure that
any action ultimately agreed upon through their collaboration is compliant with all
applicable law, including (but not limited to) subsidy control and procurement rules,
and in which respect the parties shall respectively take their own legal advice as
required. The MOU is being considered by the SMM Board for approval on 23rd
February 2024.  
51

Page 52

Equality/Socio-economic 
4.4 There are no impacts arising from the MoU. Any emerging proposals developed from
the MoU will be subject to future approvals and further considerations would be given
at that time to equalities and / or social economic implications. 
Climate Change and Carbon 
4.5 None.
Key Priorities 
4.6 The wider Great Harbour programme which this MoU is part of, reflects the
Council priorities contained in the new Council Plan 2023 to 2028 of wellbeing,
communities and local democracy, climate change and a sustainable Council. 
Community Wealth Building 
4.7 Collaboration with the Scottish Maritime Museum, which is an anchor institution
located within the Great Harbour area, reflects the Council’s community wealth
building approach. The museum has already a strong presence in the area, including
its work and support of the local community groups and is well placed to work with
NAC to tackle challenges and inequalities within the local community. 
4.8 The informal engagement with the SMM is already supporting CWB, including
collaboration on organising local events and, most recently, the appointment of the
local area resident as a Community Engagement Officer to aid the fundraising
process and support community events.   
5. Consultation 
5.1 The Maritime Heritage Hub proposals were consulted publicly as part of the draft
Great Harbour Masterplan consultation during March and April 2023, with overall
wide support for the proposals. A final draft was endorsed by the Cabinet on the 5
December 2023, for submission to Planning Committee in February 2024. 
5.2 Crown Estate Scotland own land within the Maritime Heritage Hub project area and
have been consulted as part of the development of the MoU and are supportive of
the project progressing.  
5.3 Further development of the proposals will be subject to wide stakeholder
engagement and public consultation. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Neale Mcilvanney, Interim Head of Service, Growth,
Investment and Employability, on nealemcilvanney@north-ayrshire.gov.uk. 
52

Page 53

Background Papers 
None
53

Page 54

54

Page 55

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet 
Title:    International Marine Science & Environment (IMSE)
Ayrshire Growth Deal project - Collaboration Agreement 
Purpose:  This report outlines progress in developing a business case
pathway for Ayrshire Growth Deal investment in IMSE with
partners Field Studies Council and University of Stirling.   
Recommendation:  It is recommended that Cabinet approves:  
i) The strategic direction for the IMSE project
ii) The establishment of a Collaboration Agreement
between the Council, Field Studies Council and
University of Stirling to develop related project activity 
1. Executive Summary 
1.1 This report sets out progress in developing interventions for an International Marine
Science & Environment (IMSE) project as part of the Ayrshire Growth Deal (AGD) within
North Ayrshire.   
1.2 This report seeks approval of a Collaboration Agreement with partners Field Studies
Council (FSC) and University of Stirling (UoS) to co-develop an outline business case.   
2. Background 
2.1 The Ayrshire Growth Deal, which was signed in November 2020, committed £250m to 
the Ayrshire region co-funded by UK and Scottish Governments and the three 
Ayrshire Councils. North Ayrshire’s portfolio of growth deal projects includes a £10.5m
investment towards marine science at Ardrossan. 
2.2 Since 2020 North Ayrshire has been in discussions on the potential for collaborating
on innovation driven economic development with a specific focus on the blue economy
(as defined in the Ayrshire Growth Deal).  The UoS produced a pathway finder
analysis report for NAC during 2021, which highlighted a potentially nationally and
globally significant opportunity to create a blue economy innovation programme,
headquartered at IMSE and delivered through the Ayrshire Growth Deal.  To advance
the concept of the blue economy programme and to create a business case for the
IMSE project (the “Business Case”), NAC and UoS entered into a Memorandum of
Understanding in February 2022.   
Agenda Item 8
55

Page 56

2.3 Since 2022, NAC and UoS have engaged in discussions with FSC to develop the
opportunity further. Enhancing the offering at FSC and forging strong partnerships with
the blue economy could significantly contribute to marine science, and blue economy
research, development, and innovation in the region as well as being a cost effective
and lower risk option for delivery.   
2.4 It is proposed that a Collaboration Agreement will be entered with FSC and UoS to
develop and maintain a collaborative relationship to successfully create an outline
business case for the IMSE project.  The partnership looks to determine the nature of
interventions required for the Project, including research and analysis, concept design
work for infrastructure, and challenge awards.  Long and short-listing exercises will be
conducted for available options, aligning with the requirement outlined in HM
Treasury’s Green Book.   
2.5 The agreement will be timebound for 2 years to achieve an outline business case to be
submitted to UK and Scottish Government and create a plan of works required for the
creation of the full business case, or phased full business cases, and corresponding
procurement works.   
2.6 Each party has agreed to contribute up to a maximum of £50,000 to support the work
required by this agreement with each party role being defined as below.   
Party Role
North Ayrshire
Council
Senior Responsible Officer (SRO) 
Project Management & RPMO Liaison 
AGD reporting to Scottish & UK Government
Funder 
Growth Deals link (Ayrshire Growth Deal) 
Field Studies
Council
Site Operator expertise
Landowner
Island community engagement
University of
Stirling
Academic, Innovation & Enterprise expertise 
Business Case Development
Economic Modelling
Growth Deals link (Argyll & Bute, Stirling and Clackmannanshire) 
3. Proposals 
3.1 
It is recommended that Cabinet approves:  
iii) The strategic direction for the IMSE project
iv) The establishment of a Collaboration Agreement between the Council, Field
Studies Council and University of Stirling to develop related project activity 
4. Implications/Socio-economic Duty 
Financial 
4.1 There are no direct financial implications. Project development activity related to the
proposals may require advance funding through Ayrshire Growth Deal, as allocated
within approved capital budgets.  
56

Page 57

Human Resources 
4.2 No direct implication. 
Legal 
4.3 The recommendation for the establishment of a Collaboration Agreement partnership
with Field Studies Council and University of Stirling, has been developed with support
from Legal Services.   
Equality/Socio-economic 
4.4 All project and programme work will be subject to equality impact assessment. 
Climate Change and Carbon 
4.5 Any statutory requirement related to environmental impact will be undertaken; however,
in addition, the Ayrshire Growth Deal business case requirements include carbon
scoring and measures to mitigate and carbon increases. 
Key Priorities 
4.6 This Ayrshire Growth Deal project looks to contribute to the regions vision for Ayrshire
to be ‘a vibrant, outward looking, confident region, attractive to investors and visitors,
making a major contribution to Scotland’s growth and local well-being, and leading the
implementation of digital technologies and the next generation of manufacturing.’  It also
aims to promote activity to feed into North Ayrshires priorities of wellbeing, community,
climate change and sustainability.   
Community Wealth Building 
4.7 It is anticipated that the impact of the paper will support development of interventions
that will support the Community Wealth Building strategy by supporting job creation and
skills and employability opportunities, supporting investment in North Ayrshire,
supporting a just transition to net zero and securing anchor institutions within North
Ayrshire – all of which are likely to have positive equality impacts. 
5. Consultation 
5.1 The content of the report has been developed and informed by engagement with sector
leads from and academic, private, and public sector perspective. It is recommended
that subject to the approval of this report, an ongoing programme of action is developed,
which includes engagement with communities to shape and influence the wider
programme development. 
Russell McCutcheon
Director, Place 
57

Page 58

For further information please contact Neale McIlvanney, Interim Head of Service
(Growth, Investment and Employability), on nealemcilvanney@north-ayrshire.gov.uk. 
Background Papers
0
58

Page 59

NORTH AYRSHIRE COUNCIL  
20 February 2024 
Cabinet
Title: Transport Scotland - Public consultation for the Clyde and
Hebrides Ferry Services (CHFS3) contract 
Purpose:
To seek approval for the proposed North Ayrshire Council
submission to Transport Scotland’s public consultation for the
Clyde and Hebrides Ferry Services (CHFS3) contract. 
Recommendation:
That Cabinet approves the submission of the proposed response
to the consultation provided at Appendix One. 
1. Executive Summary 
1.1 Transport Scotland, on behalf of the Scottish Government, has launched a public
consultation on the next Clyde and Hebrides Ferry Services (CHFS3) contract. The
current contract ends at midnight on 30 September 2024. The consultation is seeking
views until 8 March 2024 on current ferry services and how the new contract can best
meet local needs to inform the specification. This report seeks approval for the
proposed submission to the consultation provided at Appendix One. 
2. Background 
2.1 Transport Scotland currently subsidises, on behalf of Scottish Ministers, the vital ferry
services serving the west coast of Scotland and the Clyde Estuary.  They work with
CalMac Ferries Ltd (CFL) and Caledonian Maritime Assets Ltd (CMAL) through a
tripartite arrangement to operate the services. CFL provide the ferry services under the
current tendered Clyde and Hebrides Ferry Services (CHFS) contract with Scottish
Ministers. 
2.2 These services play a crucial role in the transport system in North Ayrshire, providing
vital links for residents, businesses, and tourists to and from our islands. This includes
services between Largs and Cumbrae, Ardrossan and Brodick, and Lochranza and
Claonaig. The provision of a modern, sustainable ferry service is therefore critical to our
islands and the wider North Ayrshire economy. 
2.3 Transport Scotland are currently developing the new CHFS3 contract and are seeking
the views of communities and service users on their expectations for the service. This
is in recognition that there are areas where enhancements can be made in the contract.
The focus for the new contract has been to review and reflect on the existing feedback
from the ferry-dependent communities, key stakeholders and reports conducted
throughout the current CHFS2 contract, including the recent report by the Scottish
Parliament’s Net Zero, Energy and Transport Committee A Modern and Sustainable
Ferry Service for Scotland. 
2.4 The consultation notes that Scottish Ministers’ preferred route for procurement of the
Agenda Item 9
59

Page 60

next CHFS contract is a direct award via a Teckal arrangement. This is an exemption
which allows in certain circumstances for a contract to be directly awarded to an in-
house operator, without undertaking a competitive bidding process. This would be
subject to a satisfactory due diligence exercise, with a final decision expected summer
2024. The new contract is scheduled to commence on 1 October 2024. 
2.5 The consultation closes on 8 March 2024 and aims to provide an opportunity for those
who have asked for change to directly contribute to the contract development process.
Views are being sought on areas such as improved resilience; greater transparency;
better communications; responsiveness; flexibility in service; and certainty for
communities and service-users. 
2.6 To ensure that our island communities’ views are reflected, Officers have liaised with
both the Isle of Arran Ferry Committee and the Cumbrae Ferry Users Group to prepare
the proposed response. Both ferry committees will also be submitting their own
responses directly to the consultation. The proposed response is provided at Appendix
One. Key points from this include: 
• Welcoming the consultation recommendation to rebuild public confidence in ferry
services starting with measuring performance in a clear way that inspires trust. 
• Highlighting that the current performance measures are insufficient and the need to
measure performance in a clear way within the new contract, which inspires
confidence and trust within island communities and ferry users. The direct award of
the contract would not be supported without such provisions on this basis.
• Proposing that clear criteria for measuring reliability could include weather impacts,
maintenance, servicing and repairs, community and customer service and
satisfaction metrics and a needs assessment.
• Noting that a range of measures could support sustainable travel to/from the islands
and reduce vehicle demand. This could include greater co-ordination between all
transport modes, on island transport improvements for active travel and public
transport, improved integration of ferry ticketing and timetabling, consideration of
the impact of delays on passengers and the introduction of a discounted ticket for
combined public transport journeys.
• Identifying the need for improved communications regarding the operation of the
ferries. The next contract should include specific requirements for the operator to
work with and be accountable to local authorities and ferry-dependent communities
on service delivery and decision making. The contract needs to provide sufficient
time for the ferry user groups/committees to be consulted and provide feedback on
proposed timetable amendments.
• Highlighting that the construction of the Ardrossan Harbour works and Cumbrae
Slip improvements, and the delivery of the new vessels will assist with achieving the
net zero targets for the services.
• Proposing that the new contract should include clauses to ensure that any
accessibility issues are addressed within an appropriate timescale.
• Outlining that the provision of a dedicated service for freight would potentially assist
with demand, especially at peak times.
• Proposing that a clear and SMART strategy be included within the new contract,
setting out how feedback will be analysed and the approach to improvements
informed by the feedback. 
2.7 In addition to the CHFS3 consultation, Transport Scotland’s Islands Connectivity Plan
(ICP) will shortly consult on the draft ICP Strategic Paper. This will set out a proposed
vision and priorities for the delivery of ferry services in Scotland, and the Long-Term
Plan for Vessels and Ports setting out plans and proposals for a programme of
investments in the CHFS and Northern Isles Ferry Service (NIFS) networks until 2045. 60

Page 61

It will also propose how to prioritise decisions during a period of funding constraints,
when difficult choices between projects are expected to be needed. A further report will
be brought to cabinet when this consultation commences. 
3. Proposals 
3.1 That Cabinet approves the proposed consultation response provided at Appendix One. 
4. Implications/Socio-economic Duty 
Financial 
4.1 No direct impacts from this report. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The provision of a modern, sustainable ferry contract and service will support the
reversal of economic, social and physical decline and reduce socio-economic
disadvantage. Ensuring that any new contract considers the views of the public is
therefore vital for our local communities. It will also contribute to the delivery of the Isle
of Cumbrae and Isle of Arran Local Island Plans, their key themes and priorities. Both
plans recognise the multiple impacts of the unreliability and capacity of the existing
ferry services to island residents, businesses and the local economy. Reliable ferry
provision is identified as a key priority for the Isle of Cumbrae Plan and ferry provision
and infrastructure is identified as a key priority for the Isle of Arran Plan. The provision
of a modern, sustainable ferry service is critical to our islands and the wider North Ayrshire
economy. The Centre for Economics and Business Research Phase 2 report (September
2022) identified that in 2019/2020 the ferry operations contributed, in terms of GVA,
£1.48million to the Arran economy and £0.109million to the Cumbrae economy. Additionally,
the Fraser of Allander Institute report on the Impact of Covid-19 on the Arran economy
identified that on average, each day of ferry operation contributes just under £170,000 to the
island’s economy. It is therefore essential that the new contract provides ferry services that
fully meets the needs of island communities, residents, visitors and workplaces. 
Climate Change and Carbon 
4.5 The provision of a modern, sustainable ferry contract and service aligns with the
Council’s Sustainable North Ayrshire Strategy workstreams of Energy and Transport
by reducing emissions and encouraging low carbon behaviours in relation to energy
use and supporting more active and low carbon methods of travel. Furthermore, it
aligns with the Council’s commitment to reduce carbon emissions through our
declaration of a Climate Emergency and will contribute to the ambition to achieve net
zero by 2030. 
Key Priorities 
4.6 Transport Scotland is seeking views on the requirements for a modern, sustainable
ferry service contract. This will align with the Councils mission of working together to
improve the lives of our people in North Ayrshire. It will contribute to several of the
61

Page 62

Council Plan priorities to transition to a wellbeing economy, delivering prosperity,
wellbeing and resilience for local people; we will have active, inclusive and resilient
communities; and achieving net-zero by 2030. 
Community Wealth Building 
4.7 The Inclusive Growth Diagnostic identified transport as a barrier to inclusive growth at
a local level. The provision of a modern, sustainable ferry contract and service for our
islands is vital to local communities and delivering inclusive growth and Community
Wealth Building. 
5. Consultation 
5.1 Transport Scotland has committed to engaging with ferry users to understand the
impact of problems with the existing ferry services contract and examine how the new
contract can best meet local needs. The proposed Council response was prepared by
Officers from across the Place Directorate, including Regeneration, Economic Policy,
Growth and Investment, and Roads. It has also been informed by input from the Isle of
Arran Ferry Committee and the Cumbrae Ferry Users Group.   
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Claire Fitzsimmons, Interim Senior Manager –
Regeneration on 01294 315305. 
Background Papers 
Fraser of Allander Institute report: The Impact of Covid-19 on the Arran economy, September
2020.
Cabinet Report: Net Zero Energy and Transport Committee – Inquiry into a modern and
sustainable ferry service for Scotland, 22 August 2022.
Centre for Economics and Business Research: The socio-economic impact of CalMac ferry
services: Phase 2 report, September 2022. 
62

Page 63

63

Page 64

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
2 
Hebrides Ferry Services Contract (CHFS3) Transport Scotland 
Public Consulta�on for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Ministerial Foreword 
I am pleased to present this public consultation on the new Clyde and Hebrides Ferry
Services Contract (CHFS3). 
Scottish Ministers’ preferred route for procurement of the next CHFS contract is a
direct award via a Teckal arrangement, (which allows in certain circumstances for a
contract to be directly awarded to an in house operator, without having to go through
a competitive bidding process). This would be subject to a satisfactory due diligence
exercise, with a final decision expected next summer. 
In terms of value and importance to our island communities, this is one of the most
significant contracts this Government will enter into, and as such it is vital that
communities have the opportunity to contribute and help us shape the future of these
vital ferry services.  
This public consultation will provide an opportunity for those who have asked for
change, including improved resilience; greater transparency; better communications;
responsiveness; flexibility in service; and more certainty for communities and service-
users to directly contribute to the contract development process.  
Throughout this process we will continue to engage with our communities and
stakeholders to inform the development of the contract to help shape the future of
these services. 
The public consultation will be available for 12 weeks from 15 December 2023 to 08
March 2024.  
For more information, please visit Transport Scotland's website. 
64

Page 65

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
3   
Fiona Hyslop, MSP 
Minister for Transport 
Consulta�on Statement 
We are seeking your views on potential ferry service improvements through the
CHFS3 contract.  
Background 
The Clyde & Hebrides Ferry Services play a crucial role in our transport system,
providing vital links for residents, businesses, and tourists across the west coast of
Scotland. However, we recognise that there are areas where enhancements can be
made. We are therefore planning to introduce a new, enhanced contract for these
ferry services which is scheduled to commence on 01 October 2024. 
To date our focus for CHFS3 has been to review and reflect on the existing feedback
from our ferry-dependent communities, key stakeholders and reports conducted
throughout the CHFS2 contract period, including the recent report by the Scottish
Parliament’s Net Zero, Energy and Transport Committee A Modern and Sustainable
Ferry Service for Scotland | Scottish Parliament. The feedback provided by these
sources and further focused discussions with key stakeholders has aided the
development of the consultation themes and questions.  
Consulta�on Process 
This consultation will be open for a period of 12 weeks from 15 December 2023 to 08
March 2024 and we invite you to share your views during this time to actively shape
the forward thinking of the Clyde & Hebrides Ferry Services Contract. 
You can do this by completing the online consultation, providing a response by email
or submitting a written response to:  
CHFS3 Consultation  
Transport Scotland  
George House  
2nd Floor  
36 North Hanover Street  
Glasgow G1 2AD 
65

Page 66

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
4 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
Assessing impact 
We are committed to assessing the impact of CHFS3 on ferry-dependent
communities and other stakeholder groups across Scotland.  
This consultation will support development of the following impact assessments: 
Business and Regulatory Impact Assessment (BRIA); Child Rights and Wellbeing
Impact Assessment (CRWIA); Equality Impact Assessment (EQIA); and the Island
Communities Impact Assessment (ICIA). 
We will publish these impact assessments on the Transport Scotland website. We
would like your views on these. Views can be provided to us by emailing Transport
Scotland. 
For example, your views will inform us about the likely impact of our policy on
advancing equality, eliminating discrimination, and fostering good relations for people
who share certain protected characteristics such as:  
• Age
• Disability
• Sex
• Gender reassignment
• Sexual orientation
• Race and religion or belief
• Pregnancy and maternity
We will take a robust evidence-based approach to the development of our impact
assessments and will work in close consultation with key stakeholders and
representatives of groups that are likely to be impacted. 
Next Steps 
In addition to the CHFS3 consultation, Transport Scotland’s Islands Connectivity Plan
(ICP) will shortly consult on the draft ICP Strategic Paper which sets out a proposed
vision and priorities for the delivery of ferry services in Scotland, and the Long-Term
Plan for Vessels and Ports which sets out plans and proposals for a programme of
investments in the CHFS and NIFS networks until 2045, and proposes how to
prioritise decisions during a period of funding constraint when difficult choices
between projects are expected to be needed. A further update on this consultation will
be provided by Transport Scotland in the coming weeks.   
66

Page 67

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
5  
Once the CHFS3 consultation period has ended, responses will be reviewed by a
specialist independent analysis team and a recommendations report will be provided
to Transport Scotland to consider when finalising the terms of the CHFS3 contract. 
We value your input and look forward to hearing your views on how we can improve
our Clyde and Hebrides Ferry Services. 
Please note that this is a public consultation, and all responses will be made publicly
available, although personal details will be kept confidential. Should you wish for your
comments not to be made publicly available, please select the appropriate box at the
end of the consultation. 
Thank you for taking the time to participate in this important process. 
Reliability and Resilience 
Community feedback highlighted that the resilience & reliability of ferry services
needs to be addressed as a priority due to the impact on business & communities
when ferry services are disrupted. 
Q1. Do you think that the current performance measures of the ferry services
are the right ones: 
Yes 
No 
Please explain your answer 
North Ayrshire Council has previously expressed concern regarding the efficiency and
reliability of the ferry services being delivered by the Scottish Government and its
associated bodies to our island communities. The inadequacies of these services are
resulting in inconvenience to residents, substantial disruption to the holiday trade and
the loss of business to the island. 
The impact of this is illustrated by the Arran Recovery Group estimate that losses
exceeded £2.7m as a result of the removal of the Isle of Arran vessel (2021) to cover
routes elsewhere in Scotland. The Fraser of Allander report on the Impact of Covid-19
on the Arran economy (2020) identified that on average, each day of ferry operation
contributes approximately £170,000 to the island’s economy.  
Our islands need reliable, resilient, and well performing services that provide for
everyday journeys for rural communities, tourism, leisure and business needs. There
67

Page 68

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
6 
are no alternative transport modes for journeys to and from Arran or Cumbrae
therefore vessel and service resilience, performance and reliability is critical. Reliable
and resilient ferry services are critical to the supply chain between mainland and
island businesses and the sustainability of our island businesses going forward.
Unless the performance measures are improved and more focussed on the users’
experience then the proposal for a direct award, via the Teckal exemption, would not
be supported. The inclusion of such measures within any updated contract should be
carefully considered on this basis. 
The new contract should provide a service for passengers which fully adheres to the
Regulation (EU) No 1177/2019 of the European Parliament and of the Council and
the Guidance on Obligations of carriers and terminal operators in the event of
interrupted travel (guidance note 6) (updated January 2021). The current contract
provides an inadequate response to this requirement. The new contract should
include the provision of suitable accommodation in such circumstances. 
As part of its contract management arrangements, Transport Scotland has a 
series of performance measures to assess its ferry operators. It reports two of 
these to its senior management team, namely: 
• Reliability: The Performance Measure for Reliability is the completion of each
Sailing referred to in the Published Timetable. This is the percentage of scheduled
sailings that take place.
• Punctuality: The measure will be deemed to have been met if the Operator and
connecting public service agree to delay the connecting service beyond its
scheduled time so that passengers, including any with a disability, to board the
connecting vehicle or vessel. This is the percentage of sailings that are on time. 
There are further performance measures relating to Compliance, Customer Care and
Accessibility Process, Services - Vehicle Accommodation and Call Centre. However,
it is not clear as to how these are reported so greater transparency of the process
and sharing of performance would be welcomed. 
Each ferry contract sets out the financial penalties that will apply for failures against
the measures. Performance deductions are not made against reliability and
punctuality measures when a sailing is cancelled or delayed due to a ‘relief event.’
Relief events include adverse weather, tidal conditions, traffic problems and other
issues of safety. Other reasons for cancellations, or the late running of services,
include vessel breakdowns or crew shortages. 
CalMac's criteria for measuring reliability are opaque, poorly understood and
apparently not widely trusted within ferry-using communities. It is often unclear as to
when and how relief events are measured, with no clear details provided or
measured. It is often the case that timetables are altered to ensure that reliability and
performance measures are met. The current contract requires CalMac to sail at set
times using set vessel. The contract should be less prescriptive with flexibility built in,
for example, to operate a minimum number of sailings per day. Furthermore clarity is
68

Page 69

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
7 
required around the classification of issues in relation to sailings to ensure
transparency and that customers are appropriate compensated 
As noted in the Executive Summary of the “Modern and Sustainable Ferry Service for
Scotland, 11th Report, 2023” (Executive Summary) there is an urgent need for better
performance metrics and reporting to drive improvement and create more trust in the
service. The root causes of the current problems include an ageing fleet, lack of
resilience, increased usage and a “pass the parcel” of responsibility culture in
governance structures. 
We would also suggest that customer service metrics must be included within the
performance criteria for the new contract. This will help to ensure that the lived
experience of our ferry-dependent communities is given due consideration when
assessing the operator’s performance. These should promote a proactive approach
by the operator to service delivery and support early resolution of issues on the
network. 
Q2.  Are there any additional or alternative performance measures that you
think could be introduced to improve resilience and reliability of ferry services? 
Yes 
No 
Please give us your views 
North Ayrshire Council would agree with the findings of the Executive Summary that
closer working between the operator and local authorities and communities, simplified
contract variation processes, collection of more data on which to assess value for
money and key performance indicators require to be included in the new contract. 
Clear criteria for measuring reliability should be agreed with key stakeholders and
included within the contract. This should include but not be limited to: 
1. Weather impacts – has extreme weather increased? Are other routes operating
when the Arran and Cumbrae services are not?
2. Maintenance, servicing and repairs – is this taking longer than previously?
3. Community and customer satisfaction rates. Needs of the community to be clearly
identified and agreed. New contract needs to satisfy the needs of the community.
4. Carry out a needs assessment for each route and include the outcomes within the
new contract.
5. The lateness measurement on the short crossing to Cumbrae is considered
lenient for a short crossing. On crossings that are under 10 minutes they should
not be more than 2 minutes out of step for departures and arrivals. The existing
Level 1 and Level 2 lateness (5 or 10 minute thresholds) are far too lenient for
these short routes.
6. Consideration of the cumulative impact of ferry delays, including onward
connection issues. 
69

Page 70

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
8  
The reporting on performance indicators should also include detailed reporting on
which relief event was associated with reliability and punctuality measurements.
Statistics must accurately reflect the lived experience of travellers. At the very least,
the "actual performance" figure for cancellation or significant delay of services should
be published alongside the "contractual reliability" figures cancellations to better
reflect the customer experience. A route cause analysis may inform this process. 
The recommendation of rebuilding public confidence in ferry services starting with
measuring performance in a clear way that inspires trust is welcomed. However,
unless there are measures in place to enable and secure an immediate improvement
in performance this will have little impact in rebuilding confidence in the ferry services. 
Future performance indicators should consider and draw attention to best practice in
ferry provision and service including considering examples from private enterprise or
internationally. Lessons should be learned from private operators’ service models.
They should be adapted to the different needs, experiences and solutions of different
islands and communities. 
To improve performance and reliability the new contract should also consider the
following: 
1. Introducing accountability clauses and incentives to ensure the operator provides
an excellent service.
2. The reliability and performance measurements should not just include the
percentage of sailings but also detail all performance relief events to establish a
pattern of performance and identify issues to address.
3. The contract should provide the operator with more flexibility to respond to
circumstances. For example the contract should aim to provide a minimum
number of sailings per day regardless of the time of sailings.
4. Provision of a longer term contract with changed structure which would be more
attractive to operators.
5. The inclusion of customer service metrics within the performance criteria for the
new contract. This will help to ensure that the lived experience of our ferry-
dependent communities is given due consideration when assessing the operator’s
performance. 
Capacity and Demand 
Fares have significantly reduced and made Scottish Islands more accessible to
everyone through the Road Equivalent Tariff (RET) however, we understand there is
a balance to be struck between vessel capacity and passenger demand, therefore we
need to find a better way to manage the number of users and the available space. 
Community feedback has highlighted the high demand for ferry services during
summer. Therefore, there is a requirement to consider the balance between capacity
and demand to ensure car spaces are available to make essential or urgent travel. 
70

Page 71

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
9 
Q3. We know that vehicle space capacity is at a premium during peak time
sailings. Do you have any suggestions that could be introduced to reduce
vehicle space demand? 
Yes 
No 
If yes, what are your suggestions? 
It is clear from the evaluation of the impact of Road Equivalent Tariff (RET) that there
has been a significant impact on both the Isle of Arran and especially Cumbrae. RET
has led to substantial increases in the number of private vehicles accessing the
islands and the lack of integration between the ferry, rail and bus services further
exacerbates this. 
Ferry services should be suitably flexible to respond to local pressures associated
with RET. For example, campervan restrictions are currently applied on some routes
on the network but there is not currently flexibility to extend this to other routes where
required. Any measures to help reduce the impacts of RET would be welcomed. 
Consideration should be given to: 
1. The provision of funding for on-island transport improvements. Improving active
travel infrastructure will make it easier and more attractive for visitors to travel
around islands by alternative modes such as active travel and reduce the need
and attractiveness to take cars to our islands. 
2. Improved on island and ferry terminal cycling infrastructure is vital to reducing
non-essential car use, reducing carbon emissions, and maximising vehicle space
on vessels for essential business and personal travel.
3. Building provision and responsibility into the contract for onward travel for foot
passengers if there are delays would also support modal shift.
4. Developing a regional/national Mobility as a Service (MaaS) system that co-
ordinates all forms of transport.
5. Transport Scotland and the Scottish Government progressing the on-island
aspects of the Islands Connectivity Plan promptly including consideration of all
sustainable transport options. This should be informed by engagement with island
communities, ferry users and Local Authorities.
6. The introduction of a discounted ticket for a combined public transport and ferry
travel to incentivise sustainable travel journeys and seasonal or discounted tickets
for foot passengers.
7. Formalising the prioritisation of islanders travelling for medical purposes and
appointments. Port staff at Cumbrae and Largs operate a process to prioritise
islanders traveling for urgent medical appointments which generally works well but
would benefit from being formalised. 
Q4. To reduce the number of cars on deck at peak times, would you be willing
to travel to and from a port using public transport? 
71

Page 72

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
10 
N/A
Yes 
No 
If no, please explain your answer 
As per Q3 above the following needs to be considered to help travellers make this
decision. 
1. The provision of funding for on-island transport improvements. Improving active
travel infrastructure will make it easier and more attractive for visitors to travel
around islands by alternative modes such as active travel and reduce the need
and attractiveness to take cars to our islands. Improved on island and ferry
terminal cycling infrastructure is vital to reducing non-essential car use, reducing
carbon emissions, and maximising vehicle space on vessels for essential
business and personal travel.
2. Building provision and responsibility into the contract for onward travel for foot
passengers if there are delays would also support modal shift.
3. Developing a regional/national Mobility as a Service (MaaS) system that co-
ordinates all forms of transport.
4. Transport Scotland and the Scottish Government progressing the on-island
aspects of the Islands Connectivity Plan promptly including consideration of all
sustainable transport options. This should be informed by engagement with island
communities, ferry users and Local Authorities.
5. The introduction of a discounted ticket for a combined public transport and ferry
travel to incentivise sustainable travel journeys. 
Q5. To reduce the number of cars on deck at peak times, would you be willing
to travel to and from a port using active travel modes (walking, wheeling,
cycling)? 
N/A
Yes 
No 
If no, please explain your answer 
As per Question 3 above the following should be considered to support ferry
passengers to make sustainable travel choices: 
1. The provision of funding for on-island transport improvements. Improving active
travel infrastructure will make it easier and more attractive for visitors to travel
around islands by alternative modes such as active travel and reduce the need
and attractiveness to take cars to our islands. Improved on island and ferry
terminal cycling infrastructure is vital to reducing non-essential car use, reducing
72

Page 73

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
11 
carbon emissions, and maximising vehicle space on vessels for essential
business and personal travel.
2. Building provision and responsibility into the contract for onward travel for foot
passengers if there are delays would also support modal shift.
3. Developing a regional/national Mobility as a Service (MaaS) system that co-
ordinates all forms of transport.
4. Transport Scotland and the Scottish Government progressing the on-island
aspects of the Islands Connectivity Plan promptly including consideration of all
sustainable transport options. This should be informed by engagement with island
communities, ferry users and Local Authorities.
5. Improvements to mainland public transport connections to/from ferry terminals
and ensuring balanced pricing to incentivise public transport options. 
Q6. Should operators be required to hold dedicated vehicle deck spaces on
busy routes for the use of island residents and key worker personnel required
to travel at short notice? 
Yes 
No 
Unsure
If no, please explain your answer 
The introduction of a dedicated vehicle space would introduce a priority system that
would require significant consideration before implementation. Agreement on the
prioritisation criteria, management and priority queuing areas would be required. This
would require careful management and could potentially lead to misunderstanding or
abuse. It is noted that whilst there are arrangements in place currently for emergency
medical related journeys, the return journeys are not always suitably accommodated. 
Holding dedicated space on the Cumbrae ferry would also be challenging
operationally as it is a non-bookable service. If it is considered appropriate to hold
back a percentage of space for short notice trips, the criteria should be agreed with all
stakeholders noting that additional separate queuing facilities may be required at
ports/slips and clear management responsibilities would require to be included in the
contract. 
Community Voice, Transparency and Accountability 
Community feedback suggests there could be more dialogue and consultation carried
out across the network, giving local communities a better opportunity to provide
feedback, which will aid decisions related to ferry services. 
Community feedback highlighted that ferry services need to be appropriately
timetabled to balance the needs of different users. 
73

Page 74

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
12 
Q7. How could communities be provided with a stronger role in providing input
on ferries related decisions? 
Please give us your views  
North Ayrshire’s islands communities are represented by two well-established,
recognised ferry groups, the Isle of Arran Ferry Committee and the Cumbrae Ferry
Users Group. The island communities however need to be able to better understand
what they can influence and the process to do so. Sufficient time is however also
needed to ensure that consultation exercises are not meaningful and take account of
the community view. 
Early consultation needs to be undertaken to ensure that there is sufficient time to
influence the decision making process. The community voice should be more
inclusive and reflected in the contract. The contract should be focussed on providing
a service to the community, not just delivering the timetable. The new contract should
include specific requirements for the operator to work with and be accountable to
local authorities and ferry-dependent communities on service delivery and decision
making. 
Decisions on timetables need to be informed by an assessment of the wider
economic and social need, including the overall impact on the islands’ economies,
rather than the cost to the operator to provide the Service. 
Q8. Are there ways in which Operators’ engagement with local communities
can be improved? 
Please give us your views 
There is a clear need for improved communications regarding the operation of the
ferries. At present much of the information comes via media channels first rather than
directly from the Operator. Procedures to engage with the community and clear
mechanisms for an escalation of disagreements and to provide feedback on service
provision within the contract are essential. This should outline roles and
responsibilities for the organisations involved and detail how feedback will be collated
and used. 
At present the stakeholder process is fragmented with no one organisation having a
clear responsibility to respond to issues or address weaknesses in service provision.
As noted at Q7, the next CHFS contract should include specific requirements for the
operator to work with and be accountable to local authorities and ferry-dependent
communities on service delivery and decision making. This should include a clear
approach and communication on how feedback is used and agreed actions are
progressed within identified timescales.
Q9. Is the Ferries Community Board representative of island populations? 
Yes 
74

Page 75

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
13 
No 
If no, please explain your answer 
At present the Ferries Community Board has representatives from the Cumbrae Ferry
User Group and Arran Ferry Committee. 
Q10. Does the Ferries Community Board reflect your interests for the next
contract? 
Yes 
No 
If no, please explain your answer 
Largely yes however the Board only considers strategic issues that affect the whole
network, not island specific issues. The consideration of island specific issues and
escalation processes may be useful on this basis.  
Q11. Should communities have greater say in the development of timetables,
so they suit the needs of ferry users? 
Yes 
No 
Please explain your answer 
At present North Ayrshire Council and the ferry user groups and committees have the
opportunity comment on proposed timetables as part of the general consultation with
the public. Timetable decisions do not currently take account of the impact on
residents and businesses and focus on the cost of Services. A wider range of factors
should inform decision making and be agreed with Local Authorities and
communities. Clear feedback on the changes made or not made informed by
consultation would be beneficial.  This would allow consultees to understand how
their feedback was being considered and addressed.  The current lack of information
results in consultees being unclear if their feedback is being fully considered.   
More transparency including clear explanations as to why decisions are made
regarding operational matters is required. This includes decisions in relation to
timetables where early engagement and ability to influence would be beneficial. The
difficulties in considering multiple opinions are acknowledged, however it would be
beneficial if any proposed changes were discussed with the recognised ferry
groups/committees prior to any wider public consultation exercise. This would allow
these groups the opportunity to input to and inform the process.
75

Page 76

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
14 
The Clyde, Kintyre and Islands Ferry Stakeholder Group meets every six months and
are therefore not able to respond to timetable changes in a timely manner. Therefore,
the contract needs to build in sufficient time for comments and amendments. 
Carbon Reduc�on and Environmental Impact 
We are making good progress towards a net zero future; however, low carbon ferry
engine technology is still being developed so we need to think of alternative ways to
reduce our carbon footprint and our impact on the environment. 
Q12. In what ways can ferries reduce their carbon emissions in line with Net
Zero targets? 
Please give us your views 
Ferry decarbonisation would be a matter for the Scottish Government however North
Ayrshire Council would welcome this policy to help reduce carbon emissions. This
aligns with the Sustainable North Ayrshire strategy. 
We would however note that the provision of a reliable and resilient ferry service is
critical to our island communities and their economies. Future procurement should
therefore focus on proven technologies to ensure continuity of service. Whilst we
recognise the desire and ambition to look at new technology, this should not be at the
expense of the connectivity of our island communities. Tried and tested technology
and engineering should be used to help ensure that the delivery programme can be
achieved. 
Delays to the Ardrossan Harbour works and Cumbrae Slip improvements and
Claonaig slip improvements, and delays in the delivery of the new vessels are
contributing to the existing carbon emission levels. Progression and final delivery of
these will assist with achieving the net zero targets. 
Q13. Would you consider reducing your car use when travelling by ferry? 
N/A
Yes 
No 
If no, please explain your answer. 
As per our responses to Q3 and Q4 above, we would welcome measures which
encourage more sustainable travel to, from and on our islands.  This could include: 
1. The provision of funding for on-island transport improvements. Improving active
travel infrastructure and sustainable travel options will make it easier and more
76

Page 77

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
15 
attractive for visitors to travel around islands by alternative modes such as active
travel and reduce the need and attractiveness to take cars to our islands.
Improved on island and ferry terminal cycling infrastructure is vital to reducing
non-essential car use, reducing carbon emissions, and maximising vehicle space
on vessels for essential business and personal travel.
2. Building provision and responsibility into the contract for onward travel for foot
passengers if there are delays would also support modal shift.
3. Developing a regional/national Mobility as a Service (MaaS) system that co-
ordinates all forms of transport.
4. Transport Scotland and the Scottish Government progressing the on-island
aspects of the Islands Connectivity Plan promptly including consideration of all
sustainable transport options. This should be informed by engagement with island
communities, ferry users and Local Authorities.
5. Improvements to mainland public transport connections to/from ferry terminals
and ensuring balanced pricing to incentivise public transport options. 
Onward and Connec�ng Travel 
Looking at how onward and connecting travel can be promoted will enable us to
provide opportunities for better connectivity and ferry user-access via active travel,
public transport, and other more sustainable transport modes. 
Q14. What do you think could be introduced to improve public transport
connectivity between ferries, rail and bus operators? 
Please give us your views 
Ardrossan, Brodick, Cumbrae and Largs are the only ports in the area with adequate
public transport links to provide the connectivity between ferry, bus and rail. North
Ayrshire Council has limited powers to manage the bus and rail network, a function
carried out by the Scottish Government. We are however supportive of the
development of a regional rail network and ensure the multi-faceted role of rail in the
region is recognised by investment decision makers. This would help ensure the rail
system provides reliable and punctual services, offers good value for money and high
levels of passenger satisfaction, increasing integration of the rail system with ferry
services. 
There needs to be greater co-ordination between all transport modes including
connecting modes on islands and on the mainland. On both Arran and Cumbrae, bus
services are largely timed to meet the ferry on arrival. Reliability issues with the ferry
can therefore have a significant knock-on impact for the wider transport network. If
the buses wait for late-running ferries the timetable is not met which impacts the
buses serving the wider communities on the islands. 
On both Arran and Cumbrae these bus services are also critical to school transport.
The impact of unreliable ferry services therefore disrupts residents, school pupils and
tourists. Furthermore, residents and visitors disembarking at Ardrossan being
inconvenienced by relying on rail travel which is similarly synchronised with expected
77

Page 78

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
16 
ferry arrival times. Greater co-ordination between Scottish Government departments
responsible for rail and ferry services would raise the profile of the need to improve
connectivity. 
Better integration of ferry ticketing and timetabling with bus and rail services, and
improved cycling infrastructure is vital to reducing non-essential car use, reducing
carbon emissions, and maximising vehicle space on vessels for essential business
and personal travel. There also requires to be an acknowledgement of the wider
policy benefits from integration public transport with ferries for example reducing
carbon emissions and increasing the attractiveness of sustainable travel. 
Accessibility 
Community feedback showed that some equality groups face additional challenges
when accessing and using ferry services. 
Q15. Would you support a regular accessibility audit taking place with
accessibility groups such as Mobility Access Committee Scotland (MACS), with
the aim of improving accessibility at ports and onboard vessels.  
Yes 
No 
What else you think could be done to improve accessibility on our ferry services? 
Of the five ports/slips within North Ayrshire Council only the Brodick terminal could
largely be considered as accessible. The terminals at Largs, Cumbrae and Lochranza
have slopes with substantial gradients that require assistance to negotiate at certain
times. With regards the Ardrossan ferry terminal, it is not currently fully accessible
however future planned improvements will improve the accessibility. The Council is
also aware that improvements are proposed for Cumbrae Ferry slip. 
Any improvements should be designed to ensure that the ferry is fully accessible. An
accessibility review should be carried out at Largs and Lochranza slips with any
recommendations being addressed. A clearer accessibility policy and promotion of
accessibility information are essential to enable informed journeys. Repairs to
accessibility infrastructure should be addressed as a priority, noting that lifts are often
out of action for prolonged periods. 
It is envisaged that any new ferries procured by the Scottish Government will meet
the accessibility requirements. Regular accessibility audits of both ports and onboard
vessels would be of value however the new contract should include clauses to ensure
that any accessibility issues should be addressed within an appropriate timescale. 
78

Page 79

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
17 
Freight Services 
Feedback provided by the community has highlighted that freight bookings can
impact available vehicle spaces on vessels. 
Q16. Are there ways to improve the Operator’s collaboration with hauliers and
businesses to better plan commercial traffic volumes? 
Please give us your views 
North Ayrshire Council Services including our Roads Network and Waste teams
generally have a good line of communication with the current operator. However, the
experience for many years is that Council Services including the Roads Network and
Waste teams do not receive the same treatment as other hauliers when being
allocated space on the ferry.  For example, when undertaking resurfacing works a
minimum number of spaces per sailing (both ways) is required for tar lorries. This is
to make the works financially viable and ensure best value for the works. 
Despite being a frequent and high volume user of the services, the Council does not
receive early notification of service issues and cancellations. Council Services are
therefore reliant on the wider public communications to manage their operations. It
would therefore be beneficial to be given a higher level of priority when making such
bookings and to improve communications. 
The Council requires to make these journeys to maintain the road network and
manage waste for the island communities, but often finds itself disadvantaged when
trying to take materials on and off the islands. Furthermore, the lack of bookings
allocated and disruption to the service over the last few years has left the Council in a
position where many contractors are refusing to undertake works and projects on the
island which is to the detriment of our island communities. Clearer ticketing is also
required for agricultural users, particularly for vehicles towing trailers and
consideration should be given to maximising the use of facilities to the benefit of
users. 
Q17. Do you have any suggestions to better manage or reduce the demand on
routes which experience high freight volumes? 
Please give us your views 
Additional sailings, particularly during the summer season, would assist Council
Services’ operation through associated freight journeys. For example more allocated
space could be provided on these sailings to support road improvements and other
work being delivered by the Roads Network team. The provision of a dedicated
service for freight would potentially assist with demand, especially at peak times. This
should include provision for Council services including Roads Network bookings. The
definition of freight should be broader and take account of the needs of island freight
requirements.  
79

Page 80

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
18 
Monitoring and Review 
Feedback has highlighted that communities would like greater clarity and accuracy on
performance reporting to be embedded within the next contract. 
Community feedback indicates that the true passenger experience is not reflected in
the way the operator reports performance. 
Q18. Would you welcome the opportunity to provide feedback to improve
services? 
Yes 
No 
If yes, how often should this happen and how should this be conducted? 
Yes, the Council would welcome the opportunity to provide feedback to improve
services both as a user of the services and alongside the island communities. The
feedback should consider not only the value of the ferry to Arran and Cumbrae’s
economy, but also the negative impacts of ferry uncertainty, cancellations and delays,
and whether these factors would be considered in developing the contract. A clear
and SMART strategy should be included within any new contract that sets out how
feedback will be analysed and what/how improvements are being made because of
the feedback. 
Q19. Do you have any suggestions on how the Operator could provide a more
accurate reflection of the passenger experience? 
Please give us your views 
Any new approach to accurately reflect the views of passenger should be tested on
user groups that include representatives of ferry-dependent communities and other
regular ferry users. We would support the Net Zero, Energy and Transport Committee
recommendation that the Scottish Government provides an update on the status of
the revised communications and stakeholder strategy highlighted in their response to
the Rural Economy and Connectivity Committee. This should include a copy of the
strategy and information on how it is implemented and how performance is being
measured, including feedback from communities. 
We would also suggest that customer service metrics should be included within the
performance criteria for the new contract. This would help to ensure that the lived
experience of our ferry-dependent communities is given due consideration when
assessing the operator’s performance. Improved and transparent communication is
required with customers, providing clear information when service changes and
cancellations are required.   
80

Page 81

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
19 
Respondent informa�on form 
Please Note this form must be completed and returned with your
response. 
To find out how we handle your personal data, please see our Privacy
Policy 
Are you responding as an individual or an organisation?   
Individual 
Organisation 
Full name or organisation’s name 
North Ayrshire Council - Regeneration
Phone number  
Address  
Regeneration
Economic Development, Growth and Regeneration Services
Cunninghame House
Irvine 
Postcode      
Email 
07785 597877
KA12 8EE 
transportation@north-ayrshire.gov.uk
X
81

Page 82

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
20 
Are you responding as a: 
CHFS network resident (Islands including Peninsulas)  
CHFS network resident (Scottish Mainland)  
Are you a CHFS network visitor or tourist? 
CHFS network business (Island and Scottish mainland) 
If you are a CHFS network resident (Islands, Peninsulas, Scottish
Mainland) please advise which CHFS community in which you are
resident, and which local authority area you live in. If you are a visitor or
tourist, please advise in which location you are resident: 
Why do you mainly use CHFS network services?   
For Business 
For Work/Education 
For Personal/Leisure 
All of the above 
Other 
How frequently do you use CHFS services?   
5-7 times a week 
2-4 times a week 
Once a week 
Once every other week 
Once a month 
Occasionally 
Seasonal (Summer Period) 
Other 
X
X
82

Page 83

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
21 
Are you:   
Under 16 
16 to 18 
19 to 21 
22 to 34 
35 to 44 
45 to 54 
55 to 64 
65 or over 
Other 
Do you consider yourself to have a disability? 
Yes 
No 
The Scottish Government would like your permission to publish your
consultation response. Please indicate your publishing preference: 
Publish response with name 
Publish response only (without name)    
Do not publish response 
We will share your response internally with other Scottish Government
policy teams who may be addressing the issues you discuss. They may
wish to contact you again in the future, but we require your permission to
do so. Are you content for Scottish Government to contact you again in
relation to this consultation exercise? 
Yes 
No 
Information for organisations: 
X
X
83

Page 84

Public Consultation for the next Clyde & 
Hebrides Ferry Services Contract (CHFS3) 
Transport Scotland 
22 
The option 'Publish response only (without name)’ is available for
individual respondents only. If this option is selected, the organisation
name will still be published.    
84

Page 85

85

Page 86

Transport Scotland
Buchanan House, 58 Port Dundas Road, 
Glasgow, G4 0HF 0141 272
7100
info@transport.gov.scot
www.transport.gov.scot
978-1-911672-37-1
© Crown copyright 2023
You may re-use this informa�on (excluding logos and images) free of charge in any format or medium, under the terms
of the Open Government Licence. To view this licence, visit htp://www.na�onalarchives.gov.uk/doc/open-
government-licence/ or e-mail: psi@na�onalarchives.gsi.gov.uk
Where we have iden�fied any third party copyright informa�on you will need to obtain permission from the
copyright holders concerned.
Further copies of this document are available, on request, in audio and large print formats and in
community languages.
Any enquiries regarding this document should be sent to us at info@transport.gov.scot
This document is also available on the Transport Scotland website: www.transport.gov.scot
Produced for Transport Scotland by APS Group Scotland PPDAS1384774 (12/23) Published by Transport
Scotland, December 2023
Follow us:
transcotland@transcotland
transport.gov.scottransportscotland.gov.uk 
86

Page 87

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet 
Title:    Community Wealth Building Strategy Refresh 
Purpose:  To update on progress of the Council’s Community Wealth
Strategy 2020-2025 and seek approval of the refreshed
Community Wealth Building Strategy 2024-2027 
Recommendation:  That Cabinet: 
a) Notes the progress against actions of the Community Wealth
Building Strategy 2020-2025; and
b) Approves the refreshed Community Wealth Building
Strategy 2024-2027, provided at Appendix One.   
1. Executive Summary 
1.1 North Ayrshire Council launched Scotland’s first Community Wealth Building Strategy
in May 2020.  Since the launch of the strategy, the North Ayrshire economy has seen
a series of significant impacts including the immediate and longer-term effects of the
Covid-19 pandemic, increasing energy costs, workforce shortages across various
industries and the ongoing Cost of Living Crisis. 
1.2 A first year progress report on the Strategy was considered and approved by Cabinet
on 28 September 2021 and this outlined the significant progress achieved despite
challenging economic conditions.  Since then, it has become evident that the
significant challenges in the wider UK and global economy have created a different
context in which the CWB Strategy operates.  National interest in Community Wealth
Building has also grown considerably in this period resulting in an increased focus at a
local, regional and national level.  In response to this and the learning gained over the
past three years, there was a recognition that a refreshed CWB Strategy could better
respond to these new challenges. 
1.3 The refreshed strategy for 2024-2027 aims to provide a Community Wealth Building
focussed approach to economic development in North Ayrshire in the coming years,
allowing the Council to remain at the forefront of this innovative policy area.  This
report provides an update of progress against the actions of the original strategy and
seeks approval of a refreshed strategy, provided at Appendix One.  
Agenda Item 10
87

Page 88

2. Background 
2.1 The Community Wealth Building Strategy 2020-2025 was launched in May 2020. This
was in response to a commitment in the 2019-2024 Council Plan to develop and
implement a CWB Strategy for North Ayrshire under the Priority Outcome ‘North
Ayrshire has an inclusive, growing and enterprising economy’. 
2.2 CWB is a radical and bold approach to economic development which has seen the
Council, along with regional Anchor Institution partners, use our economic levers to
create a more resilient local economy.  The aim of the original CWB Strategy, carried
through to the refresh, is that this new economic model will support economic, social
and environmental sustainability for our communities, through an approach centred on
wellbeing and inclusion. 
2.3  Prior to the launch of the original strategy, the Council: 
• Established a CWB Commission chaired by the Council Leader and comprising of
senior Elected Members, North Ayrshire Community Planning Partnership (CPP)
Anchor Institutions and Council Officers;
• Commissioned the Centre for Local Economic Strategies (CLES) to undertake a
CWB diagnostic for the Council, providing recommendations to support the
development of an ambitious CWB strategy;
• Established an officer CWB Working Group, chaired by the Head of Service for
Economic Development and Regeneration, to drive CWB activities across the
Council; and
• Delivered a CWB NAC Staff Leadership Conference to around 100 senior leaders,
and a CWB training session and e-learning video for Elected Members. 
2.4 Since the launch of the CWB Strategy in May 2020, the Council has made significant
progress towards embedding CWB practices within the North Ayrshire economy and
this approach has taken on a regional dimension.  In parallel with our achievements
and progress on CWB, the Scottish Government is taking forward CWB Legislation in
the current Parliament which, if approved, may place a duty on public bodies to embed
CWB principles into their economic development approaches.  During this period, the
Council has: 
• Developed the North Ayrshire CWB Commission into a regional Ayrshire CWB
Commission, supported by a Lead Officer Working Group.
• Led on the development of the Ayrshire Regional Economic Strategy and Delivery
Plan, embedding CWB principles throughout as a cross-cutting theme- a first in
Scotland.
• Hosted and managed the £3m Ayrshire Growth Deal Community Wealth Building
programme.
• Created a Community Benefits Wish List to match organisations delivering Council
contracts with community organisations in need of support.
• Developed and delivered the Repurposing Property Grant Fund (RPGF) which
directly supports and provides benefits to our local communities to bring
underutilised land and property back into positive use.
• Achieved our target of 26% local procurement spend one year early. Since
launching the CWB Strategy in 2020 our local procurement spend has improved
from 19.75% in 2020-21 to 26.04% in 2022-23. 
88

Page 89

• Considered Community Wealth Building implications as part of all Committee
reports.
• Delivered several key CWB capital projects including Phase One of Lochshore
Park comprised of the Lochshore Park Hub, 5k circular loop, woodland planting
and active travel links.
• Established an Expert Panel, comprising experts in CWB from across the globe to
provide advice, from organisations including The Democracy Collaborative, CEIS
and Future Economy Scotland.
• Created additional capacity aligned to CWB across services in Economic
Development and Regeneration and Connected Communities, including seven
posts funded through the Ayrshire Growth Deal.
• Delivered Scotland’s first Community Wealth Building Conference to an audience
of over 100 delegates from across the country and further afield.
• Participated in the Scottish Government’s CWB Bill Steering Group.
• Submitted a comprehensive response to the CWB legislation consultation, in
favour of a CWB Duty being placed on public sector organisations.
• Developed the membership of the CWB Working Group to continue to drive CWB
activities across the Council. 
2.5 National interest in Community Wealth Building (CWB) has also grown considerably in
the three years since the strategy launch, with the Scottish Government supporting
five pilot authorities to follow in the footsteps of North Ayrshire Council.  Recognised
by our role as pioneers in CWB, there has been significant interest in our approach
from a range of Scottish local authorities, Anchor Institutions and the third sector and
we regularly share our expertise with other organisations.  This culminated in the
Council hosting Scotland’s first CWB conference in October 2022 which brought
together over 100 delegates from across Scotland and further afield. 
2.6  The original strategy had a series of 55 actions. These were aligned across six
objectives comprised of “Community Wealth Building Council” plus the five CWB
pillars as follows: 
• Community Wealth Building Council: We will work across all our services and
wider local and regional partners to implement Scotland’s first approach to
Community Wealth Building. Looking at how we do things differently and with CWB
ambitions in mind;
• Procurement: We will use our spend to actively encourage and support a
growing, diverse and resilient local business base, and to support our net zero
carbon ambitions;
• Fair Employment: We will encourage the creation of fair and meaningful jobs with
progression opportunities to unlock the potential of our residents;
• Land and Assets: We will support the wider regeneration of our communities by
maximising all of our land and assets including through alternative uses for
community and business benefit;
• Financial Power: We will invest locally and encourage regional and national
institutions to invest in our communities; and
• Plural Ownership of the Economy: We will support the creation and
sustainability of a range of business models including SMEs, social enterprise,
employee ownership, cooperatives, municipal activity and community enterprises. 
89

Page 90

2.7  Our proposed 2024-2027 CWB Strategy, provided at Appendix One, builds upon the
pioneering approach of Scotland’s first CWB Strategy, and outlines our approach to
creating a more inclusive and sustainable economy through CWB.  Having emerged
from the Covid-19 Pandemic into a Cost of Living Crisis and dealing with the effects of
our changing climate, compounded by the conflict in Ukraine, we continue to face a
range of social, economic and environmental challenges.  The refreshed strategy
aspires to a vision of a Wellbeing Economy- an economy which works for both people
and planet- providing an economically and environmentally sustainable future for our
communities and young people to flourish.  The Strategy outlines the steps in our
journey to creating a Wellbeing Economy and to support the Council Plan’s vision of a
North Ayrshire that is ‘Fair for All’.   
2.8 The refreshed CWB Strategy has a total of 53 actions aligned to the same six
objectives.  This reflects the fact that some actions from the original strategy have
been completed, some actions have been updated to reflect the changing economic
environment, and several new actions have been developed.  Our commitment to
environmental sustainability and climate action is regarded as a cross-cutting theme
which relates to all six objectives. 
2.9  The refreshed CWB Strategy has been developed using a cross-service approach,
with broad engagement to refine existing and create new actions.  This includes
Economic Development, Regeneration, Growth and Investment, Employability,
Connected Communities, Finance, HR, Procurement, Planning, and Sustainability. It
has also been reviewed by and informed by feedback from the Expert Panel and the
Council’s Policy Advisory Panel. 
2.10 The strategy recognises the significant progress achieved in 2020-2023 through the
inclusion of a wealth of case studies and aligns to the wider Ayrshire Regional
Economic Strategy.  It identifies 53 actions across the six objectives of Community
Wealth Building Council and the five CWB pillars. Several new actions and revised are
identified, building on the continuing actions from the first strategy. These include: 
• Refresh the CWB Anchor Charter and work with partners to establish a wider
Anchor Network to promote CWB across the region.
• Proactively engage with our communities and Third Sector organisations, for
example community and development trusts, to provide a voice within CWB
activities and support to develop, co-produce and maximise CWB opportunities.
• Informed by our commitment to place-making, we will explore options for
developing Community Wealth Building approaches at a locality level including
consideration of unique island contexts.
• Work with the Scottish Government to establish a Regional Intelligence Hub in
Ayrshire and explore options for further analysis and evaluation of Community
Wealth Building.
• Develop our approach to using our land and assets for community benefit through
the delivery of our Repurposing Property Grant Fund, Vacant and Derelict Land
Strategy and the Vacant and Derelict Land Investment Programme.
• Explore the feasibility of creating a CWB assessment framework for development
proposals.
• Support our business base to embed fair work practices, workplace innovation and
reducing their environmental impact.
• Embed CWB within the development of Ayrshire Growth Deal business cases to
ensure lasting benefits for our businesses and communities.
90

Page 91

2.11 Regular monitoring of progress on the 53 actions will be undertaken to ensure that
objectives are being delivered across all CWB pillars and that we are on track for
achieving our vision of a Wellbeing Economy for North Ayrshire. 
3. Proposals 
3.1 That Cabinet: 
a) Notes the progress against actions of the Community Wealth Building Strategy
2020-2025; and
b) Approves the refreshed Community Wealth Building Strategy 2024-2027,
attached as Appendix One. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The refreshed strategy aims to support and maximise the impact of the investment
being made through existing Council resources and external funding. It will also inform
our priorities for securing and delivering against local, regional and national external
funding sources. 
Human Resources 
4.2 The Economic Policy Manager- Community Wealth Building will lead on the
implementation of the CWB Strategy with cross service support.  The delivery and
ownership of the identified actions has been agreed with the relevant services,
recognising that the Council's CWB approach is embedded across all Services' remit.   
Legal 
4.3 Legal advice is sought where relevant and will be sought in future in relation to any
impending legislation that may result from the Scottish Government’s CWB Bill.   
Equality/Socio-economic 
4.4 The refreshed strategy continues to present a transformational approach to an
inclusive economy.  In particular, actions on Fair Employment support excluded
groups in North Ayrshire and contribute to our aim to reduce child poverty in North
Ayrshire.   
Climate Change and Carbon 
4.5 The refreshed strategy actions aim to contribute to our ambition as a Council to
become carbon neutral by 2030 and align with the Sustainable North Ayrshire
strategy.   
Key Priorities 
4.6 The refreshed strategy aims to develop a Community Wealth Building approach to a
wellbeing economy, which is a key activity of the Council Plan. The strategy contains
91

Page 92

several actions to meet Council Plan priorities, primarily under the Wellbeing and
Sustainable Council priorities.  It aims to support the strategic aim of a Community
Wealth Building Council that is efficient and accessible, maximising investment and
focusing resources on our priorities. 
Community Wealth Building 
4.7 The strategy is key to delivering a cross-cutting approach to Community Wealth
Building and will continue to promote North Ayrshire as a CWB Council. 
5. Consultation 
5.1 Engagement on the Council’s CWB Strategy has taken place widely since its inception
in 2020. This includes with the Community Wealth Building Commission, Locality
Planning Partnerships, wider communities, stakeholders, Elected Members and with
senior leaders via the staff Leadership Conference.  The 2022 CWB Conference
enhanced this engagement. A cross-service approach has been taken to the
development of the refreshed strategy with senior officers from several services
inputting directly into the appraisal and revision of existing actions and the formulation
of new actions. It has been reviewed by and informed by feedback from the CWB
Expert Advisory Panel and the Council’s Policy Advisory Panel. 
RUSSELL McCUTCHEON 
Executive Director (Place) 
For further information please contact Emma McMullen, Senior Manager, Economic
Policy on 07787 221271 or via emmamcmullen@north-ayrshire.gov.uk. 
Background Papers
Emergency Governance Decisions (Covid-19 Outbreak) Report – Community Wealth
Building, 24 April 2020
North Ayrshire Council Community Wealth Building Strategy 2020-2025
92

Page 93

1 
North Ayrshire Council
Community Wealth Building Strategy 
2024 - 2027 
Delivering a Wellbeing Economy 
93

Page 94

2 
Contents
Leader’s Foreword ............................................................................................................................................................................................... 4
Executive Summary .............................................................................................................................................................................................. 6
Our Vision for a Wellbeing Economy .................................................................................................................................................................... 7
What is a Wellbeing Economy? ........................................................................................................................................................................ 7
The role of Community Wealth Building in a Wellbeing Economy ................................................................................................................... 7
National Policy Context .................................................................................................................................................................................... 8
Local Policy Links .............................................................................................................................................................................................. 8
What is Community Wealth Building? ................................................................................................................................................................ 11
Why do we need Community Wealth Building? ................................................................................................................................................. 13
Our Community Wealth Building Journey Continues ......................................................................................................................................... 15
Scotland’s First Community Wealth Building Conference .............................................................................................................................. 17
Community Wealth Building Commission .......................................................................................................................................................... 19
Community Wealth Building Anchor Charter ................................................................................................................................................. 20
Ayrshire Regional Economic Strategy ................................................................................................................................................................. 21
Ayrshire Growth Deal Community Wealth Building Programme ........................................................................................................................ 24
Fair Work Ayrshire ......................................................................................................................................................................................... 26
Strategy Ambitions and Objectives .................................................................................................................................................................... 28
A Community Wealth Building Council ........................................................................................................................................................... 30
Progressive Procurement ............................................................................................................................................................................... 33
Fair Employment ............................................................................................................................................................................................ 35
94

Page 95

3 
Land and Assets .............................................................................................................................................................................................. 38
Diverse Ownership ......................................................................................................................................................................................... 40
Financial Power .............................................................................................................................................................................................. 42
How we will monitor our progress ..................................................................................................................................................................... 43
Appendix 1 – Our 2024-2027 Community Wealth Building Strategy Actions ..................................................................................................... 45 
95

Page 96

4 
Leader’s Foreword 
Community Wealth Building has been at the heart of everything we do at North Ayrshire Council since we launched Scotland’s first Strategy
back in 2020. The local and national economic context has changed considerably over the past few years and in response to the Covid-19
pandemic and Cost of Living Crisis. Now more than ever we need take an inclusive and people-centred approach to developing our local
economy and ensure fair distribution of wealth and opportunities for our communities. This is why we are committed to delivering a Wellbeing
Economy for North Ayrshire – an economy which works for people and planet – and we see Community Wealth Building as a key mechanism
for achieving that vision. 
Community Wealth Building is moving forward at quite a pace and shaping the economic landscape in this region and beyond.  We are
delighted with the progress we have made - the early stages saw us put the building blocks in place, spread the message and get buy-in from
partners, businesses and communities across the region. None of the successes of this bold economic strategy would have been possible
without the support and shared determination of all our partners.  I would personally like to offer my thanks to all those who have signed up
and joined us on this important and exciting journey.
It has been heartening to see national support for Community Wealth Building develop over recent years and it’s been great to share our story
with other Scottish local authorities, Anchor Institutions and the Third Sector. We were delighted to host Scotland’s first Community Wealth
Building Conference in October 2022, bringing together over 100 individuals and organisations from across Scotland. We are leading the way in
this bold new economic approach and we should be immensely proud of what we’ve achieved.
We’ve developed new processes and ways of working and have helped dozens of local businesses to take part in the often difficult and
complex procurement process.  This has seen the amount spent with North Ayrshire businesses from April 2022 to March 2023 increasing by
almost £6.4million on the previous year. This equates to 26.04% of our total procurement spend going to local businesses, meaning that we
reached our target of 26% local spend one year early.   
We have also developed new initiatives which deliver benefits directly to our communities. Our Community Benefits Wish List matches council
suppliers with requests from community organisations and has delivered huge benefits including materials, staff expertise and small cash
donations. Stage 1 of our Repurposing Property Grant Fund saw a total of £149, 271 awarded to help support community groups and
landowners bring vacant and derelict sites back into productive use. 
96

Page 97

5 
Building upon this strong foundation, this new strategy demonstrates our continued commitment to pioneering Community Wealth Building in
Scotland and across Ayrshire. In demonstration of this commitment we recently led the development of a new Regional Economic Strategy for
Ayrshire, ensuring Community Wealth Building principles are embedded throughout. 
We are determined to play our part in creating a diverse Ayrshire economy that is more resilient and capable of standing firm in the face of
national and global adversity. We have made a promising start and this Strategy lays out our vision and priorities for Community Wealth
Building up to 2027.  If you haven’t already, please join us on this exciting journey.
Councillor Marie Burns
Council Leader, North Ayrshire Council 
97

Page 98

6 
Executive Summary 
Our 2024-2027 Community Wealth Building Strategy builds upon the pioneering approach of Scotland’s first Community Wealth Building
Strategy which we launched in May 2020. A lot has changed in the three years since including the effects of the Covid-19 Pandemic, soaring
fuel and food costs resulting in a Cost of Living Crisis and escalating inflation. We remain as committed as ever to the need to create a more
inclusive and sustainable economy through Community Wealth Building. 
National interest in Community Wealth Building has increased significantly, with Community Wealth Building referenced within the National
Strategy for Economic Transformation and a consultation on Building Community Wealth in Scotland in 2023. This strategy builds upon the
valuable learning we have gained as pathfinders in Community Wealth Building and recognises the challenges posed by the new economic
context. It cements our position as leaders within local economic development and demonstrates our commitment to Community Wealth
Building as the key mechanism for achieving a Wellbeing Economy. 
A fundamental aspect of Community Wealth Building is working in collaboration with our Anchor partners, local businesses and communities.
We reflect on the value of key achievements which have facilitated this collaborative approach such as the creation of the Ayrshire Community
Wealth Building Commission and Anchor Charter, delivery of the Ayrshire Growth Deal Community Wealth Building Programme and new
initiatives such as the Community Benefits Wish List and Repurposing Property Grant Fund (RPGF) which directly support and provide benefits
to our local communities. 
Having emerged from the Covid-19 Pandemic into a Cost of Living Crisis and dealing with the effects of our changing climate, we continue to
face a range of social, economic and environmental challenges. We aspire to the vision of a Wellbeing Economy – an economy which works for
both people and planet – providing an economically and environmentally sustainable future for our communities and young people to flourish.
This strategy outlines our next steps in our journey to create a Wellbeing Economy and to support the Council Plan’s vision of a North Ayrshire
that is ‘Fair for All’. 
98

Page 99

7 
Our Vision for a Wellbeing Economy 
What is a Wellbeing Economy?
A Wellbeing Economy is an economy that works for people and the planet and delivers social, economic and environmental justice for all. It
prioritises fair distribution of wealth, opportunities and privileges within our society, all on a healthy, thriving planet. 
The Wellbeing Economy Alliance (WEAll) defines a Wellbeing Economy as: “an economy designed to serve people and the planet, not the other
way around. Rather than treating economic growth as an end in and of itself and pursuing it at all costs, a Wellbeing Economy puts our human
and planetary needs at the centre of its activities, ensuring that these needs are all equally met, by default.”
This is our aspiration for North Ayrshire’s economy; to be inclusive to all our residents, with wealth and opportunities fairly distributed and for
our young people to reach their full potential as part of a sustainable future. 
The role of Community Wealth Building in a Wellbeing Economy
We consider Community Wealth Building to be a key mechanism to achieving a wellbeing economy. Rather than relying on Gross Domestic
Product (GDP) as a measure for how well an economy performs, Community Wealth Building looks beyond this and aims to ensure our local
economies are more inclusive for our residents and enterprises. 
The Scottish Government consider Community Wealth Building and other progressive commitments such as the upcoming Land Reform Bill,
Just Transition Plans and the Refreshed Fair Work Action Plan as supporting economic reform and the transition to a wellbeing economy. 
The 2021-22 Programme for Government set out a commitment to bring forward Community Wealth Building Legislation in the current
Parliament. A consultation on “Building Community Wealth in Scotland” ran from January to May 2023 with the purpose of seeking views on a
proposal for a new duty to advance Community Wealth Building. It also sought to identify whether new legal measures or changes to existing
laws are required to accelerate the implementation of Community Wealth Building. 
99

Page 100

8 
National Policy Context
The Scottish Government is committed to transitioning to a Wellbeing Economy and is a founding member of the Wellbeing Economy
Governments (WEGo) – an initiative bringing together governments to learn and support each other in the transition to a wellbeing economy.
In March 2022 Scotland’s National Strategy for Economic Transformation (NSET) was launched by Scottish Government. The strategy outlines
a vision to create a wellbeing economy as part of a just transition to a more green and sustainable future. It recognises the need to learn from
the lessons of the Covid-19 pandemic and develop a more resilient economy, delivering fair work, better employment opportunities and
reducing poverty and inequality. Community Wealth Building is highlighted as an example of a practical approach to achieving a wellbeing
economy. 
National Planning Framework 4 (NPF4) was  adopted in February 2023, providing guidance to support the creation of sustainable, liveable and
productive places. It will also play a key role in delivering the National Strategy for Economic Transformation. Community Wealth Building is
one of the National Planning Policies outlined within NPF4. It is recommended that Local Development Plans align to Community Wealth
Building priorities and seek to tackle economic disadvantage and inequality and provide benefits for local communities.   
Local Policy Links 
The 2024-2027 Community Wealth Building Strategy has been designed to align and interact with various North Ayrshire Council strategies.
North Ayrshire Council Plan
The 2023-2028 Council plan outlines how we will deliver the priorities of our communities during the next five years. It was developed
alongside North Ayrshire communities and outlines our four key priorities:
• Wellbeing – to transition to a wellbeing economy, delivering prosperity, wellbeing and resilience for local people.
• Communities and Local Democracy – we will have active, inclusive and resilient communities.
• Climate Change – achieving net-zero by 2030.
• A Sustainable Council – a Community Wealth Building Council that is efficient and accessible, maximising investment and focusing
resources towards our priorities.
100

Page 101

9 
North Ayrshire Partnership Plan 2022-2030
The North Ayrshire Partnership Plan is our Local Outcomes Improvement Plan and sets how we will work together with our Community
Planning partner organisations in North Ayrshire. It will deliver on our vision of “North Ayrshire – Fair for All” and has three key themes:
• Wellbeing – We will address health inequalities. We will promote children and young people’s wellbeing. We will enable community
wellbeing. 
• Work – We will increase employment. We will develop volunteering. We will better support our young people. 
• World – We will work together to reduce carbon emissions and mitigate the impacts of climate change. We will increase active travel. We
will increase carbon literacy within our organisations and communities. 
Regional Economic Strategy for Ayrshire
Ayrshire’s first ever Regional Economic Strategy was launched in June 2023. It is a ten-year strategy which aims to build wealth for everyone in
Ayrshire. It is the first regional economic strategy in Scotland to embed Community Wealth Building principles throughout. More information
on the Regional Economic Strategy can be found on page 21. 
Regeneration Delivery Plan
The 2021-2026 North Ayrshire Regeneration Delivery Plan aims to address local priorities, support changes within communities and deliver a
wellbeing economy. It is closely aligned to the priorities of our Council Plan and Community Wealth Building strategy and outlines the delivery
of physical regeneration across North Ayrshire through an ambitious project based rolling action programme, working in partnership with our
communities. 
Island Recovery and Renewal Plans for Arran and Cumbrae
To support an inclusive and green economic recovery for our island communities of Arran and Cumbrae, the Council are involved in an Islands
Recovery and Renewal Pilot in partnership with the Scottish Government and Highlands and islands Enterprise. Working in partnership with
island communities, businesses and wider stakeholders, two separate ten-year Island plans have been developed for Arran and Cumbrae.
Aligning to the delivery of the National Islands Plan and Community Wealth Building principles, the island plans aim to maximise and develop
the economic potential of North Ayrshire’s islands. 
Sustainable North Ayrshire Strategy 2024-2027 
In June 2019 the Council declared a Climate Emergency and committed to the ambitious target of achieving net zero by 2030. The new
Sustainable North Ayrshire Strategy was approved by Cabinet in December 2023 and sets out a plan to achieve this target and tackle climate
101

Page 102

10 
change through the implementation of nine strategic priorities, action across five workstreams and a proposed Carbon Footprint and Project
Register. The new strategy has a vision of a sustainable, climate ready North Ayrshire that drives area-wide reductions in carbon emissions in a
way which tackles inequality, promotes fair work, supports Community Wealth Building and contributes to achieving a Wellbeing Economy. 
North Ayrshire Vacant and Derelict Land Strategy 2023-2028
North Ayrshire has one of the highest proportions of vacant and derelict land in Scotland. The strategy has been informed by consultation with
stakeholders and local communities who have highlighted the negative effect of vacant and derelict land on the local economy, environment
and communities. The Vacant and Derelict Land Strategy considers how vacant and derelict land fits within the wider context of National and
Local priorities and objectives, including Community Wealth Building, the challenge of net zero, the climate emergency and the Scottish
Biodiversity Strategy. 
The refreshed Community Wealth Building Strategy also takes cognisance of other strategies including the Financial Inclusion Strategy 2023-
2028 and the Digital North Ayrshire Strategy 2023-2028. 
102

Page 103

11 
What is Community Wealth Building?
Community Wealth Building is an approach to economic development which aims to retain wealth, jobs and opportunities within local areas
and improve economic prosperity. It uses the economic power and levers of Anchor Institutions – large organisations which are rooted in local
areas – to support and improve the local economy. These Anchor Institutions bring wealth to the local area in the form of jobs, buying power
and physical assets and can be local authorities, NHS health boards, further and higher education institutions and other public sector
organisations. 
Community Wealth Building uses five pillars to encourage Anchors to use their organisational power to retain wealth locally and create more
economic benefits for our local area. 
103

Page 104

12 
Community Wealth Building enables communities and businesses to have a greater stake in their local economy, ensuring that money is
retained locally and recirculates within communities and makes areas economically stronger, more resilient and sustainable. 
It does this by changing the flows of wealth and economic power to bring them closer to communities – such as by increasing community
ownership and control of assets; developing and growing more ‘generative’ enterprises such as small, locally-owned enterprises, co-operatives
and social enterprises which lock and share wealth within the local area. 
104

Page 105

13 
Why do we need Community Wealth Building? 
Like many parts of Scotland and the UK, North Ayrshire is facing a range of unprecedented economic challenges following the Covid-19
pandemic and the impacts of high inflation, energy and living costs. The current context has exposed the high levels of inequality that exist
within our economy and has further marginalised the most vulnerable within society. Community Wealth Building seeks to rebalance
economic inequality by retaining money, jobs and economic power within our local area and provide routes out of poverty for our families.
Now more than ever we need mechanisms which create resilient and sustainable local economies which can withstand future economic
shocks.
• 28.6% of children in North Ayrshire live in relative poverty (after housing costs). This is the second highest rate in Scotland1
• 27.4% of P6 and P7 pupils in North Ayrshire are eligible for free school meals2
• 39.8% of our residents live in the most deprived areas as defined by the Scottish Index of Multiple Deprivation3
• 38% of households are in fuel poverty or extreme fuel poverty4
• North Ayrshire has one of the lowest job densities in Scotland (ranked 4th lowest in Scotland)5
• 27.6% of residents are economically inactive. This is one of the highest rates in Scotland6
• North Ayrshire has 12% of all vacant and derelict land in Scotland, making it the local authority with the second highest proportion in
the country7
• Island specific challenges include access to affordable housing, higher costs of living and doing business and connectivity. 
1 DWP – Children in low income families – local area statistics 2023
2 Scottish Government – School Healthy Living Survey statistics 2022
3 Scottish Index of Multiple Deprivation 2020 v2
4 Scottish Government – Scottish House Condition Survey 2021 Key Findings
5 NOMIS (2023) based on data from Jul 2022 – Jun 2023 
6 NOMIS (2023) based on data from Jul 2022 – Jun 2023
7 Scottish Vacant and Derelict Land Survey 2021
105

Page 106

14 
Despite facing significant challenges, there are a range of strengths within North Ayrshire from which we can seek to maximise and develop:
• 3380 Businesses in North Ayrshire8
• 120 Social Enterprises9
• North Ayrshire unemployment rate has reduced by 2.4 % points since 202010
• Female Employment Rate has increased by 4% points since 202011
• Significant opportunity to grow the blue economy for example fishing, aquaculture, offshore renewables and leisure activities.
• £251.5 million regional investment across Ayrshire via the Ayrshire Growth Deal 
8 Scottish Government – Business in Scotland 2022
9 Social Enterprises in Scotland 2021 Census
10 NOMIS (2023) based on data between Jul 2020, Jun 2021 and Jul 2022, Jun 2023
11 NOMIS (2023) based on data between Jul 2020, Jun 2021 and Jul 2022, Jun 2023
106

Page 107

15 
Our Community Wealth Building Journey Continues
Since launching our Community Wealth Building Strategy in May 2020 we have seen significant impacts to the local economy including the
immediate and longer-term effects of the Covid-19 pandemic, increasing energy costs due to the conflict in Ukraine, workforce shortages
across various industries and the ongoing Cost of Living Crisis. 
In light of the changing economic context, we recognise the challenges associated with delivering our Community Wealth Building ambitions
and aspirations to create a stronger and more resilient local economy. The Cost of Living Crisis, pressures of rising inflation and ferry disruption
for Arran and Cumbrae have been particularly challenging for local businesses, particularly SME’s. Our Business Support and Development
team worked hard throughout the pandemic to help businesses in immediate distress and provide a package of support focussed on business
recovery, diversification and new opportunities aligned to Community Wealth Building and a green recovery. Providing further support, the
successful three-year Ayrshire Growth Deal Community Wealth Building Programme was launched in 2021 and works with businesses to
create more local, good quality employment and create a larger and more diverse business base.  
Locality community support hubs were established in each of the six North Ayrshire localities immediately after the start of the pandemic to
provide urgent support to our local communities. Coordinated by a team of Council, Health and Social Care staff and local volunteers, the hubs
provided a range of essential support to communities, children and vulnerable residents including food parcels and deliveries, prescription
deliveries, money advice services and health and wellbeing advice. 
The effects of climate change and biodiversity loss are being felt around the world and is a fundamental threat facing North Ayrshire residents
and businesses. We know the impacts of our changing climate are likely to hit the most vulnerable in society the hardest and the climate crisis
is a key concern for our young people. To mitigate these effects, and as demonstrated in our Sustainable North Ayrshire Strategy 2024-2027,
we are committed to using the principles of Community Wealth Building to ensure a fair and green transition to a sustainable society which
operates within planetary limits and where no one in North Ayrshire is left behind. 
National interest in Community Wealth Building has grown considerably in the past three years. Recognised by our role as pioneers in
Community Wealth Building, there has been significant interest in our approach from a range of organisations including other Scottish local
authorities, Anchor Institutions and the 3rd Sector. We were delighted to host Scotland’s first Community Wealth Building Conference in
October 2022, bringing together over 100 individuals and organisations from across Scotland. 
107

Page 108

16 
The 2021-2022 Programme for Government set out a commitment to bring forward Community Wealth Building Legislation in the current
Parliament. We were invited to join a Community Wealth Building Bill Steering Group to help inform the development of the legislation. In
May 2023 we engaged across Council Services and with our Anchor partners to provide a comprehensive response to the consultation
“Building Community Wealth in Scotland”. 
As we continue our Community Wealth Building journey and reflect on the new economic context and learning we have gained over the past
three years, we feel it is an appropriate time to revisit our Community Wealth Building Strategy. We remain committed to all five pillars of
Community Wealth Building and this new strategy will seek to improve and deepen the benefits of this approach by engaging across Council
Services and our Health and Social Care Partnership. We will ensure that Community Wealth Building strengthens and informs our approach to
place-making by recognising and responding to the distinct needs and opportunities of our North Ayrshire localities. Community Wealth
Building is embedded within our Island Plans for Arran and Cumbrae. In recognition of the unique opportunities and challenges for Community
Wealth Building on our islands we will explore options for piloting a locality based approach to Community Wealth Building on Arran.  
We are committed to developing our Community Wealth Building approach in partnership with our local and regional Anchor partners.
Building upon the strong relationships developed through the Community Wealth Building Commission we will support the delivery of the first
Regional Economic Strategy for Ayrshire and ensure Community Wealth Building remains at the heart of the economic vision for Ayrshire. By
nature of our two island communities, the Council also sits within the Highlands and Islands Regional Partnership. We will work with partners
to embed Community Wealth Building and maximise opportunities to increase economic wealth and benefits for rural and island communities. 
108

Page 109

17 
Scotland’s First Community Wealth Building Conference
We were delighted to host Scotland’s first ever conference focussed on Community Wealth Building at Saltcoats Town Hall in October 2022.
Economic practitioners and policymakers from across Scotland attended to learn more about Community Wealth Building and be inspired
hearing about the success stories, challenges and why different approaches to Community Wealth Building are important for urban and rural,
mainland and island communities.  
The event was well-attended with over 100 guests from 42 different organisations and groups. A total of 35 officers from 20 different Scottish
local authorities attended, not including North Ayrshire Council staff. This included representatives from Aberdeen City, Orkney, Argyll and
Bute, Perth and Kinross and Stirling Councils. We were delighted to welcome Mr Tom Arthur, Minister for Community Wealth and Public
Finance to the conference who spoke of the Scottish Government interest in Community Wealth Building and praised the work underway in
North Ayrshire and Ayrshire. 
109

Page 110

18 
Participants heard about the North Ayrshire approach to Community Wealth Building as well directly from some of our Anchor partners and
the development of the Regional Economic Strategy for Ayrshire. There were presentations from several highly respected guest speakers who
shared their knowledge and experience of Community Wealth Building and stimulated lively and engaging discussions:
• A video recording by Ted Howard, Co-Founder and President of the Democracy Collaborative
• Stewart Macgregor, Scottish Enterprise
• Sarah Deas, Wellbeing Economy Alliance
• Sarah McKinley, Democracy Collaborative
• Calum Iain MacIver, Comhairle Nan Eilean Siar
• Artemis Pana, Scottish Rural Action
• Neil McInroy, Democracy Collaborative 
In addition to presentations and Q & A sessions, there were several stalls showcasing key Community Wealth Building projects, allowing
attendees to engage directly with officers as well as providing opportunity for wider networking and sharing ideas. The conference also
included the premiere of a Community Wealth Building film showcasing how Community Wealth Building can have a positive impact on the
lives of young people in North Ayrshire. 
110

Page 111

19 
Community Wealth Building Commission 
A key focus of the 2020 Community Wealth Building Strategy was working in partnership with our wider regional Anchor Institutions. All Anchor
Institutions have the potential to use their economic power to have a positive influence on the local economy. By working together we can add
value to our shared goals around Community Wealth Building and ensure positive long-term transformational change. To facilitate collaboration
across a range of partners, we established the Community Wealth Building Commission. Led by North Ayrshire Council it is a partnership of nine
Anchor Institutions including all three Ayrshire Councils, NHS Ayrshire & Arran, Ayrshire College, The Ayrshire Community Trust (3rd Sector
Interface), Police Scotland, the Scottish Fire and Rescue Service and Scottish Enterprise. The CWB Commission drives a strategic approach to
Community Wealth Building in Ayrshire and brings partners together to work on shared challenges and opportunities and share best practice
and examples of Community Wealth Building.   
In December 2020, the CWB Commission agreed a workplan of activity and established a Lead Officer Working Group of senior officers from
across the Anchor partners to take the workplan forward. As part of the workplan, three workstreams were established: Fair Employment,
Procurement and Land and Assets. Examples of some activities underway within the workstreams include:
• The procurement workstream has developed an Ayrshire wide interactive map which plots 2021/22 and 2022/23 procurement spend
of seven Commission Anchor partners. This provides an opportunity to understand potential for redirecting spend locally as well as
collaborative procurement opportunities.
• The Fair Employment workstream is focussing on three areas of activity – Recruitment, Volunteering and Apprenticeships to maximise
and join-up approaches across the partner organisations. 
• The Land and Assets workstream has created a Geographic Information System (GIS) map and spreadsheet of under-utilised assets for
all the partners, with the intention of linking this data to opportunities for businesses, communities and the Third Sector. 
111

Page 112

20 
Community Wealth Building Anchor Charter
To aid collaboration and support Anchors to use their economic levers and embed Community Wealth Building practices within their
respective organisations, we launched a CWB Anchor Charter in October 2020. The Charter has sixteen pledges across the five CWB pillars and
a sixth pillar of Climate Action. There are currently eleven organisations signed up to the Charter: North, East and South Ayrshire Councils, NHS
Ayrshire and Arran, Ayrshire College, Scottish Enterprise, The Ayrshire Community Trust (TACT), Police Scotland and the three Ayrshire Joint
Integration Boards. 
Anchor Charter Mission Statement
To commit to long-term collaboration between Ayrshire Anchor Institutions,
supporting shared Community Wealth Building goals to improve collective wellbeing
and create a strong, resilient and inclusive local and regional economy. This includes a
commitment to the embedding of Community Wealth Building principles and
reporting on progress to the CWB Commission. 
112

Page 113

21 
Ayrshire Regional Economic Strategy 
A new ten-year Regional Economic Strategy for Ayrshire was approved by the Ayrshire Economic Joint Committee in February 2023 and
formally launched in June 2023.  A Year 1 Delivery Plan was subsequently approved in September 2023. The strategy has been supported by
North Ayrshire Council and developed by an industry-led working group with representation from the six regional recovery and renewal
workstreams and public sector partners.
The Regional Economic Strategy has six priority themes:
• Support for Enterprise
• Fair Work
• Innovation
• Good Health and Wellbeing
• Stronger Places and Communities
• Enhancing Natural Capital 
These priority themes are supported by a Culture of Delivery theme and cross-cutting themes of Community Wealth Building, Skills and Digital.
It is the first regional economic strategy in Scotland to embed Community Wealth Building principles throughout. It aims to build wealth for
everyone in Ayrshire and sets out the vision for 2033 of a region: 
• Where wealth is shared fairly;
• Where people of all ages can live full and healthy lives;
• That is attractive to investors and visitors;
• That makes a major contribution to Scotland’s economic development; and
• Where protection of natural wealth and culture is prioritised.
Although Community Wealth Building is embedded throughout the Regional Economic Strategy and the Delivery Plan, there are specific
Community Wealth Building actions as follows:
113

Page 114

22 
• Review Community Wealth Building work across Ayrshire including the CWB Commission and AGD CWB Programme to support regional
delivery of Community Wealth Building and the Regional Economic Strategy.
• Develop options for an Ayrshire Anchor Network to support regional delivery of Community Wealth Building.
• Respond to requirements of any forthcoming Scottish Government legislation on Community Wealth Building.
• Refresh the Community Wealth Building Anchor Charter and promote adoption of pledges within Ayrshire Anchor Institutions.
These actions have been reflected in the refresh of the North Ayrshire Community Wealth Building Strategy.  They offer the opportunity for us
to link more widely with partners and to push forward Community Wealth Building at a regional level.  
114

Page 115

23 
115

Page 116

24 
Ayrshire Growth Deal Community Wealth Building Programme
Funded by the Ayrshire Growth Deal (AGD) and launched in 2021, the AGD Community Wealth Building Programme is a three-year pan-
Ayrshire programme which aims to develop resilient, inclusive local economies, with more local employment and a large and more diverse
business base. Specifically the project advances activities within the procurement, employment, ownership and asset pillars of CWB. This video
explains more about the Community Wealth Building Programme. 
The project has three key elements:
• CWB Business Locality Officers – working with local organisations to facilitate CWB activities across the region;
• CWB Fund – a £1m fund to support place-based CWB activity, and the work of CWB locality officers; and
• Fair Work Ayrshire - a dedicated service that works with employers to implement Fair Work in workplaces across the Ayrshire. 
The Programme aligns with existing local authority resource, including business development teams, employability programmes, regeneration
activities, community development and locality/area partnerships. A total of 13 officers were recruited to support delivery of the Programme
which is managed by North Ayrshire Council as the lead authority:
• A Programme Manager to support overall delivery of the programme;
• Nine CWB Business Locality Officers divided across the three Ayrshire Local Authorities (three officers in each council); and
• A Fair Work Ayrshire (FWA) Programme Manager and two Fair Work Ayrshire Project Officers.
The CWB officers and Fair Work Ayrshire team engage with businesses across Ayrshire through an array of support mechanisms. This included
1-2-1 support, Fair Work Action plans, networking opportunities through CWB pillar focussed workshops, and providing financial assistance
through the CWB Business Support Fund. The programme is performing well against targets and in many instances exceeding its key output
targets. As of September 2023, the Programme has engaged with over 800 businesses across Ayrshire on CWB activities and it is likely that the
overall programme target of supporting 900 enterprises will be exceeded. 
In March 2023, the Programme hosted an in-person event at Ayrshire College in Kilmarnock. There were 130 attendees including local
businesses, Third Sector enterprises and senior officers from across the public sector and further education institutions. There were a wide
range of presentations including from Ayrshire businesses owners who shared their experiences of engaging with the Programme and why
Community Wealth Building is important to them. 
116

Page 117

25 
117

Page 118

26 
Fair Work Ayrshire 
The Fair Work Ayrshire Team are fully operational and have from April 2022 – September 2023:
• Engaged with 327 businesses across Ayrshire.
• Conducted 245 initial meetings to develop fair work action plans.
• Completed 124 Fair Work Ayrshire action plans. 
• 52 Ayrshire businesses have been referred to secure real living wage for accreditation.
• 54 Ayrshire businesses have been referred to secure disability confident accreditation.
• 50 referrals to Working for a Healthy Economy (AGD) SALUS
• 26 referrals for Carer Positive scheme Scotland (following engagement with MSPs in Jan 23).
• 16 Ayrshire businesses have been signposted to create Modern Apprenticeship opportunities.
• 36 Ayrshire business have been signposted to learning & development opportunities. 
118

Page 119

27 
Cunninghame Housing Association/Citrus Energy/Cunninghame Furniture Recycling – recently Real Living Wage
accredited and investing in local the community. 
Cunninghame Housing Association (CHA) through their Head of Social and Economic Development, Scott Mould, have
been working hard over the last six months to reach Real Living Wage accreditation.  This involved looking at all
aspects of the business and associated contractors to ensure that the Real Living Wage is paid and promoted
throughout the business and the social enterprise arm involved in furniture recycling.  Due to the size of the
organisation this had to be reviewed and staff understood the benefits to all staff in every aspect of the business. 
Cunninghame Housing Association is Disability Confident registered and are signing up to become a Carer positive and
Scottish Credit and Qualifications Framework (SCQF) inclusive recruiter.  Scott is keen to continue attracting talent to
the organisation and will be looking at increasing staff development opportunities over the coming months. 
Cunninghame Housing Association has worked closely with North Ayrshire Council Employability team and have
employed several Kickstart recruits and parents returning to work, providing training development and mentoring. 
119

Page 120

28 
Strategy Ambitions and Objectives 
To ensure consistency in our approach, we remain committed to the five pillars of Community Wealth Building and our aspirations of being a
Community Wealth Building Council. These commitments form our strategic objectives for how we will deliver Community Wealth Building in
North Ayrshire. 
As part of our vision for a wellbeing economy in North Ayrshire we recognise the crucial role of ensuring our local economy operates within
safe and sustainable environmental limits and delivers on our Net Zero targets. Our commitment to environmental sustainability and climate
action is therefore regarded as a cross-cutting theme which relates to all six of our Community Wealth Building Strategy objectives. 
Community Wealth Building Council – We will work across all our services and wider local and regional partners to
implement our pioneering approach to Community Wealth Building 
Progressive Procurement – We will use our spend to actively encourage and support a growing, diverse and resilient local
business base and to support our net zero carbon ambitions 
Fair Employment – We will encourage the creation of fair and meaningful jobs with progression opportunities to unlock the
potential of our residents 
Land and Assets – We will support the wider regeneration of our communities by maximising all our land and assets including
through alternative uses for community and business benefit 
Diverse Ownership – We will support the creation and sustainability of a range of business models including SMEs, social
enterprises, employee ownership, cooperatives, municipal activity and community enterprises 
120

Page 121

29 
Financial Power – We will invest locally and encourage regional and national institutions to invest in our communities 
121

Page 122

30 
A Community Wealth Building Council 
We will work across all our services and wider local and regional partners to implement our pioneering approach to Community Wealth
Building
We will continue to develop our pioneering approach to Community Wealth Building and achieve our long-term objective of being a
Community Wealth Building Council. 
Community Wealth Building is firmly woven throughout our Council Plan (2023-28) and will help us deliver a wellbeing economy and
contribute to our vision of ‘A North Ayrshire that is fair for all’. 
This refreshed strategy recognises our intentions to engage a broader range of council services in Community Wealth Building to ensure that
we are maximising all opportunities to leverage economic improvements for our communities. It also informs how we will work with our wider
Anchor partners, local business base, communities and the Third Sector to develop, co-produce and maximise Community Wealth Building
opportunities. We will ensure that Community Wealth Building strengthens and informs our approach to place-making by recognising and
responding to the distinct needs and opportunities of our North Ayrshire localities.
In recognition of the fundamental threats posed by the climate crisis, we will take a Community Wealth Building approach to addressing the
climate challenges and ensure a Just Transition for North Ayrshire. 
122

Page 123

31 
What we will do:
• Work with local and regional anchor institutions through the Community Wealth Building Commission and Regional Economic Strategy Delivery Group to
deliver Community Wealth Building across North Ayrshire and the wider Ayrshire economy.
• Refresh the CWB Anchor Charter and work with partners to establish a wider Anchor Network to promote CWB across the region.
• Proactively engage with our communities and Third Sector organisations, for example development and community trusts, to provide a voice within CWB
activities and support to develop, co-produce and maximise CWB opportunities.
• Analyse outcomes of the Ayrshire Growth Deal Community Wealth Building Programme to inform our ongoing support for businesses and enterprises.
• Ensure all North Ayrshire Council employees have an awareness of Community Wealth Building and undertake their role through a Community Wealth
Building lens through provision of regular training and engagement sessions.
• Use our municipalisation strategy as a tool to secure and enhance local public services, fill gaps in provision where necessary and develop local skills to
meet changing service needs.
• Use Community Wealth Building to deliver on our ambitions to become a carbon neutral Council and ensure a green and Just Transition for North Ayrshire.
• Encourage our staff and communities to shop and spend locally and highlight the benefit of this to support local jobs in the North Ayrshire and Ayrshire
economy.
• Participate in national, regional and international Community Wealth Building and inclusive economy networks to identify and showcase best practice.
• Continue our conversations with young people about what Community Wealth Building and a Wellbeing Economy means to them.
• Deliver digital economic transformation for North Ayrshire by addressing digital constraints to an inclusive economy such as improving digital skills,
infrastructure and connectivity, and digital innovation.
• In our role as partner, support both the Highlands and Islands and Ayrshire Regional Economic Partnerships to embed CWB approaches and maximise
opportunities to increase local economic wealth and benefits.
• Continue to participate in the Scottish Government CWB Bill Steering Group and respond to requirements of any forthcoming Scottish Government
legislation on CWB.
• Deliver CWB workshops for Island Plan Steering Groups to identify opportunities, scale and embed an island-wide CWB approach as the Island Plans are
delivered, with the intention of creating greater local economic, community and environmental benefits.
• Develop and implement a CWB Action Plan for North Ayrshire Health and Social Care Partnership.
• Informed by our commitment to place-making, we will explore options for developing Community Wealth Building approaches at a locality level including
consideration of unique island contexts.
• Work with the Scottish Government to establish a Regional Intelligence Hub in Ayrshire and explore options for further analysis and evaluation of
Community Wealth Building. 
123

Page 124

32 
Island Recovery and Renewal Pilot
The National Islands Plan (NIP) was published in December 2019 and provided a framework for action to meaningfully improve outcomes for
island communities. Aligned to the National Islands Plan, the Council is participating in an ambitious three-year Islands Recovery and Renewal
Pilot. Jointly funded by the Council, Scottish Government and Highlands and Islands Enterprise, the Pilot aims to support an inclusive and green
economic recovery and renewal of North Ayrshire’s island communities in line with their unique needs. A key part of the recovery and renewal
is the development of ten-year socio-economic Island Plans for both Arran and Cumbrae.
The Local Island Plans were developed in partnership with island communities, stakeholders and partners and were subsequently launched in
early 2022. A key area of focus for the Island Recovery and Renewal Pilot is on closer and more coordinated working between the island
communities, community planning partners, national and local government and agencies. This aims to ensure a stronger place-based
partnership working and a whole systems approach to improve island wellbeing, including in areas such as housing and the economy.
Annual Action Plans for Arran and Cumbrae were developed alongside the Local Island Plans and set out the steps and actions to be progressed
to deliver the vision for the future of each island. The Action Plans outline a framework to align with each island’s key themes and priorities as
well as draw on opportunities to contribute to Community Wealth Building principles and net zero objectives.  Island geographies provide
unique opportunities and challenges for Community Wealth Building and in recognition of this we will explore options for piloting a locality
based approach to Community Wealth Building on Arran. 
In support of the Island Plan Steering Groups, we will deliver workshops to communicate the benefits of Community Wealth Building and how
it can be used to strengthen local economies, making them more resilient and sustainable. The workshops will provide an opportunity to
identify opportunities to embed Community Wealth Building approaches within the island economies as well as share practical examples of
good practice and consider how to overcome challenges. 
124

Page 125

33 
Progressive Procurement 
We will use our spend to actively encourage and support a
growing, diverse and resilient local business base and to
support our net zero carbon ambitions 
Our 2020 Strategy set an ambitious target of increasing Council
procurement spend with local businesses from 19.75% in 2020 to
26% by 2024. Following the launch of the strategy, new staff
were appointed within the Business Support and Development
team and new processes implemented across the Procurement
and Business Support teams including:
• Engaging and supporting local suppliers to enable them to bid
for contracts.
• Alerting local suppliers of future procurement opportunities
and considering procurement options to promote local spend.
• Publishing a contracts register and two-year forward plan
within an Annual Procurement Plan to provide visibility of
opportunities.
As a result of this coordinated approach, we were able to achieve
our local spend target one year early. In the year from April 2022
to March 2023 the amount spent with North Ayrshire businesses
had increased by almost £6.4million on the previous year,
equating to 26.04% of our total procurement spend going to local
businesses. To build upon this success, a new target of 27% local spend has been set for achievement by 2027/28. 
What we will do:
• Maintain the corporate culture and status of procurement as a key
feature of Community Wealth Building.
• Continue to work with anchor institutions through the Community
Wealth Building Commission Procurement Workstream to explore
opportunities for more local spend and identify and progress joint
opportunities locally and regionally.
• Support our business base – including a wide range of business models
– to enhance their capacity to bid for public sector contracts.
• Continue our proactive approach to procurement wave-planning which
enables deeper market and locality engagement before commissioning.
• Proactively promote upcoming Council procurement opportunities
including through Meet the Buyer events, early supplier engagement
events and Prior Information Notices (PINs).
• Increase knowledge of local suppliers and identify gaps in the market to
create locally-driven economic opportunities.
• Continue to maximise our approach to Community Benefits to ensure
they meet our CWB ambitions and the needs of our communities. This
will include exploring the creation of further apprenticeships through
Community Benefit Clauses, building on the review of our Community
Benefits policy and creation of the Community Benefits Wish List. 
125

Page 126

34 
Community Benefits Wish List – Barrmill and District Community Association 
Our Community Benefits Wish List was launched in October 2021. This is an online “noticeboard” where community groups can submit “wishes” to
the Council’s network of public sector contractors who can respond to the requests as part of Community Benefits within the procurement process.
A total of 61 wishes have been delivered between October 2021 and August 2023. Wishes can involve requests for supplier time, expertise or
materials that will help a community organisation – for example volunteering staff time to clear an overgrown community garden, support with
developing architectural plans or supplying fresh baked rolls to community larders. 
Barrmill and District Community Association run a successful community centre from a prefabricated former army barracks building in the centre of
the village. The age of the building is beginning to show through general wear and tear, exacerbated by the centre having to pause lets and other
activities due to COVID restrictions. Water is running into the centre in a few places from the roof, and the windows are reaching the end of their
life. The association requested support through the Community Benefits Wish List in September 2021, with the first offer of support received a
month later from City Building LLP, a Glasgow-based construction firm who delivering a contract to supply new kitchen units for North Ayrshire
Council. Based on the association’s wish submissions, City Building undertook a roof survey for the group in December 2021. This provided an up to
date picture of the hall’s structure along with recommended next steps regarding further work and the type of advice required to inform the future
of the building. One of these recommendations was to undertake a more in depth structural survey to investigate some of the areas the roof
surveyor highlighted.
A surveyor was identified 7 months later, in July 2022. Faskin Group, a roofing contractor for the Council, covered the cost of a fabric condition
survey report. These two surveys updated the information the association held about their building, which was previously a barrier to identifying
appropriate solutions. Using the surveys as match funding evidence, the Council’s Funding Officer, with support from the Regeneration Team, has
been supporting the group through an application to the Repurposing Property Grant Fund (RPGF). The group’s RPGF application has been
successful and they have been awarded £10,000 to allow them to carry out a feasibility study to provide options in respect of
refurbishing/rebuilding the community centre to ensure that it is not lost to the community.   
126

Page 127

35 
Fair Employment 
We will encourage the creation of fair and meaningful jobs with
progression opportunities to unlock the potential of our
residents
We are ambitious for our North Ayrshire residents and are
committed to providing good quality jobs, with training and
progression opportunities. In collaboration with a range of
partners we have successfully delivered a range of employability
services including:
• EQUAL Supported Employment Programme supports people
with disabilities or long-term health conditions into sustainable
employment. It also supports employers to create an
environment where a person with disabilities can work
effectively.
• Skills for Life offers 6 month placements for parents within a
vocational mentored programme. Between 2017 and 2022, the
programme supported 132 placements in council services and
45 placements within Anchor and Third Sector organisations.
• Streetscene Training Academy provides high quality vocational
26 week real living wage placements for long term
unemployed participants. These provide training and
accredited qualifications to support progress into sustainable
employment within the Council and externally whilst delivering
environmental improvements across North Ayrshire. 
As demonstrated by the Ayrshire Community Wealth Building
Anchor Charter, we are driving engagement on Fair Employment
What we will do:
• Continue to work with anchor institutions to review workforce policy and planning and
ensure Ayrshire is recognised as a Fair Work region, building on success of the CWB
Commission Fair Employment workstream.
• Support our businesses to implement Fair Work principles and flexible working
opportunities including promotion of case studies and good practice.
• Deliver employability programmes which support residents to improve their income from
employment, reducing child poverty and the impacts of the cost of living crisis.
• Recognising health as an ongoing barrier to an inclusive and wellbeing economy in North
Ayrshire, deliver our 'EQUAL' supported employment programme and work with Ayrshire
partners to deliver Working for a Healthy Economy as part of the AGD.
• Aspire to align employability support with locality partnerships to ensure enhanced access
to provision across North Ayrshire.
• Support other employers to achieve Disability Confident status, following our attainment of
this status.
• Develop a video to promote the Council as an ‘Employer of Choice’ highlighting our good
Terms and Conditions and opportunities for flexible working.
• Work with key partners and anchor institutions to deliver a new apprenticeship
programme which supports future workforce needs and provides high quality
opportunities for young people across a range of apprenticeship offers including Modern,
Graduate and Foundation.
• Engage with services and anchor partners to better understand the barriers to recruitment
and particularly for entry level roles, take steps to make the recruitment application
process more accessible.
• Support the creation of an Island Skills Coordinator post, as identified in the Arran CVS
Skills Audit Report 2023 that links the local curriculum officer and skills development
initiatives to the needs of the Arran economy, providing choice, chance and collaborative
approaches to addressing labour and skills shortages, upskilling and re-skilling and to
address depopulation and improve opportunities for the working age population.
127

Page 128

36 
with our local and regional Anchor partners. Delivered through the Fair Employment workstream as part of the CWB Commission workplan,
our Anchor partners are looking at ways to encourage more local recruitment, including from priority groups, as well as growing local skills and
ensuring Ayrshire has a broad offering of accessible apprenticeship and volunteering opportunities. 
128

Page 129

37 
Step Into Business
North Ayrshire has over 1100 lone parents claiming universal credit. Family poverty
remains high in North Ayrshire and is currently the second highest rate in Scotland. To help
move more families into good quality, local employment, the Council developed Step Into
Business – a pilot programme which works with our local and regional Anchor Institutions
and private sector to encourage fair and flexible recruitment pathways for parents entering
or returning to the labour market. 
The programme has been shaped by discussions with parents who identified the key
challenges associated with entering the labour market. Informed by these conversations,
the programme provides pre-employment advice, childcare support, money management
advice, wellbeing advice, in-work support and ‘moving on’ sessions. Delivered in
partnership with Ayrshire College, We Work for Families and supported by the wider
employability partnership, it is a truly collaborative approach between the Council and
Anchor partners to improve employment opportunities for local residents. 
Nine parents are being supported via the programme with employers hosting six month
fully funded placement opportunities within administration or customer service roles. 
Parents are paid the Real Living Wage and given the option of flexible working patterns to
support family life. Employers are encouraged to provide meaningful, positive, and
supportive mentored placements that allows parents to gain the knowledge required to
complete their SVQ qualification.
To date the programme has been very successful. One parent within the cohort recently
secured a new post within the NHS.  To allow parents to gain more experience, posts
hosted by Anchors have also been extended for a further six months at a reduced cost to
the employer. It is hoped that two further cohorts of parents will be supported by the
programme in the coming months. 
129

Page 130

38 
Land and Assets
We will support the wider regeneration of our communities by maximising all our land and assets including through alternative uses for
community and business benefit
We are committed to supporting our communities and businesses to
use and take ownership of local assets, in a way which is appropriate
for them and which helps address unique local issues or aspirations.
In 2022 Lochshore Park Hub opened to the public, regenerating a
major long-term strategic site and bringing 64.73ha of vacant and
derelict land back into productive use. A site of a former steelworks,
it was purchased by the Council from Scottish Enterprise in 2021 and
now is an excellent example of a productive asset for the community
with a café, accessible public toilets and meeting space.
Millport Town Hall was purchased by the community in 2019 and is
currently undergoing a significant renovation programme to create a
sustainable, accessible and multifunctional space for the people of
Cumbrae. The renovation has been supported by a range of sources
including Community Investment Funding (CIF) from the Council and
the Scottish Government’s Islands Programme and Regeneration
Capital Grant Fund.
Repurposing of council owned land also provides an opportunity to
tackle the climate emergency and reinvest financial returns from
renewable energy generation back into North Ayrshire. The
construction of solar photovoltaic farms at two former landfill sites in
Irvine, Nethermains and Shewalton is now imminent. Together they
are expected to provide two-thirds of the council’s energy needs.
What we will do:
• Develop our approach to using our land and assets for community benefit
through the delivery of our Repurposing Property Grant Fund, Vacant and
Derelict Land Strategy (2023-2028) and the Place Based Investment
Programme.
• Ensure our commercial property portfolio and business development offer
supports the growth of local businesses, social enterprise and
entrepreneurial activity.
• Roll out Place Frameworks for towns across North Ayrshire and consider
opportunities to add value through CWB such as alternative use of land and
property assets, partnership working and supporting diverse ownership
models.
• Continue to support Community Asset Transfer and support community
capacity building to grow community ownership.
• Review potential sites for increased town centre living, in line with actions
from the Regional Economic Strategy.  
• Explore the feasibility of creating a CWB assessment framework for
development proposals.
• Guided by NPF4, we will embed CWB and related policies such as 20
Minute Neighbourhoods within LDP3, ensuring future developments take
account of local economic priorities and provide benefits for communities.
• Utilise our land and property assets to support a green transition including
active travel routes and developing low carbon and renewable energy
schemes and networks, such as Nethermains and Shewalton Solar PV. 
130

Page 131

39 
Progress continues to develop a renewable energy framework for i3 aligned to the wider Ayrshire Growth Deal investment. 
Repurposing Property Grant Fund
The Repurposing Property Grant Fund (RPGF) was created to help support landowners and community groups to bring smaller vacant land
and property sites back into use. It provides financial support to investigate these sites and allow business and the community to explore
alternative uses. It aims to:
• Enable or support the repair or redevelopment of vacant land and buildings.
• Act as a catalyst to promote future investment from the private sector and external funding.
• Safeguard the future of prominent buildings by indicating how high-quality conversion may be achieved.
• Enable the Council to map development potential and barriers to development.
Stage 1 of the programme supports property owners or community groups to carry out feasibility studies to identify potential options for
the sites and their viability. A total of £149, 271 has been awarded to date across thirteen projects. This has allowed one previously vacant
site to achieve planning permission for three industrial units in Saltcoats. Three community groups are using the funds to explore the re-use
of key assets within their community and are being supported to understand the steps required to acquire the sites and access funding
streams to improve the area for their communities. 
Stage 2 of the fund commenced in summer 2023 and will build upon the feasibility works undertaken at Stage 1. Grants of up to £50,000 are
available to support landowners to prepare detailed designs, obtain necessary consents, confirm costs and to identify sources of funding.
The assessment process prioritises applications relating to North Ayrshire Locality priorities, long-term vacant sites, and historic or
prominent buildings or sites in proximity to Town Centres. 
131

Page 132

40 
Diverse Ownership 
We will support the creation and sustainability of a range of business models including SMEs, social enterprises, employee ownership,
cooperatives, municipal activity and community enterprises
By supporting the creation and transition to more diverse business ownership models within North Ayrshire we are putting more economic
control into the hands of local people and communities. Local enterprises are more likely to care about what happens in their communities
and often have strong social and environmental values that respect the needs and views of local people. We recognise the strong links
between Diverse Ownership and other pillars of Community Wealth Building. For example we will ensure our approach to maximising use of
our Land and Assets includes consideration of new organisations and enterprises and actively supports diverse ownership models.  
Diverse ownership models include social and community
enterprises, employee owned companies, co-operatives, small and
medium sized enterprises (SMEs) (including family businesses) and
municipal ownership.
Together with Cooperative Development Scotland (CDS), our
Business Support and Development team are committed to
supporting local enterprises to explore alternative business models.
In 2022 they supported Kilwinning based Shuttle Buses to transition
to employee ownership, giving all 70 members of staff a meaningful
stake in the business and a genuine voice in how it is run.
Employee-owned businesses are more resilient during times of
economic crisis, as well as more profitable, more productive and
have greater staff engagement. 
What we will do:
• Support the development of wider forms of progressive business
ownership including employee ownership, cooperatives, community
businesses, and social enterprises.
• Support our business base to embed fair work practices, workplace
innovation and reducing their environmental impact.
• Support work via the RES to undertake research to map and analyse
the 3rd sector in North Ayrshire and provide support for the sector to
grow and develop.
• Encourage and support the conversion of existing businesses to
employee ownership.
• Continue to offer specialist support to family owned businesses
through Scotland’s first Family Business Advisor.
• Consider alternative delivery models and feasibility studies for large
scale regeneration opportunities.
132

Page 133

41 
Jack’s Alt Stays – Cumbrae
Jack’s Alt Stays is a unique accommodation offering on the Isle of Cumbrae. Established
by cousins Daniel and Adam, they provide five alternative eco-cabins only a short walk
from Millport. 
Since the early stages of design and construction Daniel and Adam have demonstrated
a strong commitment to using local suppliers and tradespeople. The cabins were
brought to life by Largs based architects Stewart Associates and Stevenston based local
builders System 5. Being based locally, Daniel and Adam were able to work closely with
the architects and builders, ensuring they were involved in every step of the process
and could make decisions along the way. It also enabled the production of a series of
You Tube videos tracking the construction journey which raised awareness to the
public and became a powerful marketing tool for attracting visitors. 
Jack’s Alt Stays is also committed to supporting other local businesses on Cumbrae,
demonstrating the value that locally owned SMEs bring to the economy. They use local
produce and suppliers where they can and signpost guests to other local businesses
and attractions, helping to keep tourist spend local and within other SMEs. For
example their optional breakfast add-ons includes produce from the Cumbrae butchers
and milk and orange juice from a dairy on Largs. Offering these high quality items
supports other local businesses and encourages visitors to purchase food on the island
rather than doing their shopping at large mainland supermarkets before they arrive. 
Jack’s Alt Stays recognise the importance of employing locally and supporting their
staff. It provides much needed secure and year-round employment for five members of
staff, all of whom live on Cumbrae, including three Ukrainians who have recently
settled on the island. 
As plans for the future develop, Daniel and Adam remain committed to the principles
of Community Wealth Building and keeping it local, having seen the benefits and
opportunities it creates for their business and the local economy on Cumbrae.
133

Page 134

42 
Financial Power 
We will invest locally and encourage regional and national institutions to invest in our communities 
We know that investing locally empowers our communities and
enterprises and acts as a catalyst for delivering a wide range of social,
economic and environmental outcomes. We are committed to
ensuring that our communities have a voice and are fully engaged in
how money is invested locally. Our innovative Community Investment
Fund (CIF), Communities and Place Fund, and excellent track record in
delivering Participatory Budgeting are examples of how we use our
financial power as a local authority to invest in projects and causes
which are important to our communities. 
As part of an action within the 2020 Community Wealth Building
Strategy we investigated the feasibility of establishing a mutually-
owned Community Bank within North Ayrshire. Although the research
concluded a bank within North Ayrshire was not currently feasible, we
know that other banking options such as locally based credit unions
are important services which provide safe, inclusive and accessible
finance options for our residents. 
What we will do:
• Continue to promote work with 1st Alliance Community Bank to
increase financial literacy and encourage progressive finance.
• Continue to empower our communities through our Community
Investment Fund (CIF).
• Showcase North Ayrshire as part of the wider Ayrshire region to
promote our investment opportunities to regional and national
institutions to gain investment in our communities, in partnership
with actions under the RES.
• Develop our progressive and leading approach to Participatory
Budgeting by moving towards mainstreaming participatory
budgets, including through our approach to allocating external
funding and further empowering our local communities.
• Embed CWB within the development of Ayrshire Growth Deal
business cases to ensure lasting benefits for our businesses and
communities. 
134

Page 135

43 
How we will monitor our progress 
We will regularly monitor progress on each of the 53 actions detailed within this 2024-2027 Community Wealth Building Strategy. This will
ensure we deliver our objectives across all Community Wealth Building pillars and are on track to achieving our vision of a Wellbeing Economy
for North Ayrshire. 
We will also use our Inclusive Economy Dashboard to track our progress on delivering a Wellbeing Economy. Our Economic Recovery and
Renewal Approach published in September 2020 outlined an action to ‘develop an Inclusive Economy Dashboard to track inclusive and green
economic recovery.’ Based on the Doughnut Economics model, the Inclusive Economy Dashboard recognises that an inclusive and wellbeing
economy must be based upon an acceptable social foundation and operate within safe and sustainable environmental limits. The revised
Dashboard will act as a framework to ensure our Community Wealth Building approach is being used to develop our local economy in a way
which is socially inclusive but also within safe environmental limits.
The Inclusive Economy Dashboard also provides insight to the broader national context within which we operate as a Council and forms part of
our Council Plan Performance Management Framework. These contextual indicators give a sense of national trends and complex social,
economic and environmental challenges facing a variety of councils. It will act as a guiding framework for collaborating with our Anchor
partners and wider national organisations on shared goals and challenges. 
135

Page 136

44 
The Stevenston Community Hub
The idea behind Stevenston Hub was developed by Raise Your Voice with Ardeer (RYVwA) and initially focussed on re-establishing public toilets
at Stevenston Beach. Following a community consultation, it was determined that in addition to public toilets, the community also wanted
somewhere to meet and socialise, inspiring the idea of establishing a ‘community hub’. 
Through various funding streams, RYVwA raised nearly £500,000 which included Scottish Government’s Regeneration Capital Grant Fund and
£250,000 from North Ayrshire Council’s Community Investment Fund (CIF). Initially RYVwA received £100,000 in CIF funding however post
lockdown it became apparent that material and other costs had risen substantially. The group returned to the Three Towns Locality Planning
Partnership (TTLPP) requesting a further £150,000 to complete the build. CIF money was used to undertake another community consultation,
fund concept and design, architectural and planning activities as well as the supply of utilities and project build management.
In February 2023, RYVwA held a ‘soft’ opening of the community facility and ‘Doon the Beach’ café. The hub and café very quickly became a go-
to meeting place and refreshment stop for locals, dog walkers, cyclists and walking groups. A formal public opening and fun day was held on the
8th of July with over 2000 people in attendance and taking part in a range of activities. 
The support received via the CIF allowed the project to become a reality and is not only meeting the needs and expectations of the local
community, but also contributing to the delivery of the Three Towns Locality Priorities. 
136

Page 137

45 
Appendix 1 – Our 2024-2027 Community Wealth Building Strategy Actions 
Number Pillar Action
1 CWB Council 
Work with local and regional anchor institutions through the Community Wealth Building Commission and
Regional Economic Strategy Delivery Group to deliver Community Wealth Building across North Ayrshire and
the wider Ayrshire economy
2 CWB Council 
Refresh the CWB Anchor Charter and work with partners to establish a wider Anchor Network to promote
CWB across the region
3 CWB Council 
Proactively engage with our communities and Third Sector organisations, for example community and
development trusts, to provide a voice within CWB activities and support to develop, co-produce and
maximise CWB opportunities
4 CWB Council 
Analyse outcomes of the Ayrshire Growth Deal Community Wealth Building Programme to inform our ongoing
support for businesses and enterprises
5 CWB Council 
Ensure all North Ayrshire Council employees have an awareness of Community Wealth Building and undertake
their role through a Community Wealth Building lens through provision of regular training and engagement
sessions
6 CWB Council 
Use our municipalisation strategy as a tool to secure and enhance local public services, fill gaps in provision
where necessary and develop local skills to meet changing service needs
7 CWB Council 
Use Community Wealth Building to deliver on our ambitions to become a carbon neutral Council and ensure a
green and Just Transition for North Ayrshire
8 CWB Council 
Encourage our staff and communities to shop and spend locally and highlight the benefit of this to support
local jobs in the North Ayrshire and Ayrshire economy
9 CWB Council 
Participate in national, regional and international Community Wealth Building and inclusive economy
networks to identify and showcase best practice
10 CWB Council 
Continue our conversations with young people about what Community Wealth Building and a Wellbeing
Economy means to them
11 CWB Council 
Deliver digital economic transformation for North Ayrshire by addressing digital constraints to an inclusive
economy such as improving digital skills, infrastructure and connectivity, and digital innovation
137

Page 138

46 
12 CWB Council 
In our role as partner, support both the Highlands and Islands and Ayrshire Regional Economic Partnerships to
embed CWB approaches and maximise opportunities to increase local economic wealth and benefits
13 CWB Council 
Continue to participate in the Scottish Government CWB Bill Steering Group and respond to requirements of
any forthcoming Scottish Government legislation on CWB
14 CWB Council 
Deliver CWB workshops for Island Plan Steering Groups to identify opportunities, scale and embed an island
wide CWB approach as the Island Plans are delivered, with the intention of creating greater local economic,
community and environmental benefits
15 CWB Council  Develop and implement a CWB Action Plan for North Ayrshire Health and Social Care Partnership
16 CWB Council
Informed by our commitment to place-making, we will explore options for developing Community Wealth
Building approaches at a locality level including consideration of unique island contexts
17 CWB Council
We will work with the Scottish Government to establish a Regional Intelligence Hub in Ayrshire and explore
options for further analysis and evaluation of Community Wealth Building
18 Progressive Procurement Maintain the corporate culture and status of procurement as a key feature of Community Wealth Building
19 Progressive Procurement
Continue to work with anchor institutions through the Community Wealth Building Commission Procurement
Workstream to explore opportunities for more local spend and identify and progress joint opportunities locally
and regionally
20 Progressive Procurement
Support our business base – including a wide range of business models – to enhance their capacity to bid for
public sector contracts
21 Progressive Procurement
Continue our proactive approach to procurement wave-planning which enables deeper market and locality
engagement before commissioning
22 Progressive Procurement
Proactively promote upcoming Council procurement opportunities including through Meet the Buyer events,
early supplier engagement events and Prior Information Notices (PINs)  
23 Progressive Procurement
Increase knowledge of local suppliers and identify gaps in the market to create locally-driven economic
opportunities
138

Page 139

47 
24 Progressive Procurement
Continue to maximise our approach to Community Benefits to ensure they meet our CWB ambitions and the
needs of our communities, including exploring the creation of further apprenticeships through Community
Benefit Clauses, building on the review of our Community Benefits policy and creation of the Community
Benefits Wish List
25 Fair Employment
Continue to work with anchor institutions to review workforce policy and planning and ensure Ayrshire is
recognised as a Fair Work region, building on success of the CWB Commission Fair Employment workstream.
26 Fair Employment
Support our businesses to implement Fair Work principles and flexible working opportunities including
promotion of case studies and good practice
27 Fair Employment
Deliver employability programmes which support residents to improve their income from employment,
reducing child poverty and the impacts of the cost of living crisis
28 Fair Employment
Recognising health as an ongoing barrier to an inclusive and wellbeing economy in North Ayrshire, deliver our
'EQUAL' supported employment programme and work with Ayrshire partners to deliver Working for a Healthy
Economy as part of the AGD.
29 Fair Employment
Aspire to align employability support with locality partnerships to ensure enhanced access to provision across
North Ayrshire
30 Fair Employment
Support other employers to achieve Disability Confident status, following attainment of our Disability
Confident Leader status.
31 Fair Employment
Develop a video to promote the Council as an ‘Employer of Choice’ highlighting our good Terms and
Conditions and opportunities for flexible working.
32 Fair Employment
Work with key partners and anchor institutions to deliver a new apprenticeship programme which supports
future workforce needs and provides high quality opportunities for young people across a range of
apprenticeship offers including Modern, Graduate and Foundation.
33 Fair Employment
Engage with services and anchor partners to better understand the barriers to recruitment and particularly for
entry level roles, take steps to make the recruitment application process more accessible.
139

Page 140

48 
34 Fair Employment
Support the creation of an Island Skills Coordinator post, as identified in the Arran CVS Skills Audit Report 2023
that links the local curriculum officer and skills development initiatives to the needs of the Arran economy,
providing choice, chance and collaborative approaches to addressing labour and skills shortages, upskilling and
re-skilling and to address depopulation and improve opportunities for the working age population
35 Land and Assets
Develop our approach to using our land and assets for community benefit through the delivery of our
Repurposing Property Grant Fund, Vacant and Derelict Land Strategy (2023-2028) and the Place Based
Investment Programme.
36 Land and Assets
Ensure our commercial property portfolio and business development offer supports the growth of local
businesses, social enterprise and entrepreneurial activity.
37 Land and Assets
Roll out Place Frameworks for towns across North Ayrshire and consider opportunities to add value through
CWB such as alternative use of land and property assets, partnership working and supporting diverse
ownership models.
38 Land and Assets
Continue to support Community Asset Transfer and support community capacity building to grow community
ownership.
39 Land and Assets
Review potential sites for increased town centre living, in line with actions from the Regional Economic
Strategy.  
40 Land and Assets Explore the feasibility of creating a CWB assessment framework for development proposals.
41 Land and Assets
Guided by NPF4, we will embed CWB and related policies such as 20 Minute Neighbourhoods within LDP3,
ensuring future developments take account of local economic priorities and provide benefits for communities.
42 Land and Assets
Utilise our land and property assets to support a green transition including active travel routes and developing
low carbon and renewable energy schemes and networks, such as Nethermains and Shewalton Solar PV farms.
43 Diverse Ownership
Support the development of wider forms of progressive business ownership including employee ownership,
cooperatives, community businesses, and social enterprises
44 Diverse Ownership
Support our business base to embed fair work practices, workplace innovation and reducing their
environmental impact
140

Page 141

49 
45 Diverse Ownership
Support work via the RES to undertake research to map and analyse the 3rd sector in North Ayrshire and
provide support for the sector to grow and develop.
46 Diverse Ownership Encourage and support the conversion of existing businesses to employee ownership.
47 Diverse Ownership
Continue to offer specialist support to family owned businesses through Scotland’s first Family Business
Advisor.
48 Diverse Ownership Consider alternative delivery models and feasibility studies for large scale regeneration opportunities.
49 Financial Power
Continue to promote work with 1st Alliance Community Bank to increase financial literacy and encourage
progressive finance.
50 Financial Power Continue to empower our communities through our Community Investment Fund (CIF).
51 Financial Power
Showcase North Ayrshire as part of the wider Ayrshire region to promote our investment opportunities to
regional and national institutions to gain investment in our communities, in partnership with actions under the
RES.
52 Financial Power
Develop our progressive and leading approach to Participatory Budgeting by moving towards mainstreaming
participatory budgets, including through our approach to allocating external funding and further empowering
our local communities
53 Financial Power
Embed CWB within the development of Ayrshire Growth Deal business cases to ensure lasting benefits for our
businesses and communities 
141

Page 142

142

Page 143

NORTH AYRSHIRE COUNCIL 
20 February 2024 
Cabinet 
Title: 
Social Housing Net Zero Standard (SHNZS)
Consultation  
Purpose:
To provide Cabinet with details of the proposed new Social
Housing Net Zero Standard (SHNZS) and to seek approval
of the proposed response to the Scottish Government
consultation. 
Recommendation:
That Cabinet: (i) notes the potential implications arising
from the introduction of the Social Housing Net Zero
Standard; and (ii) approves the proposed response at
Appendix 1 to the consultation document. 
1. Executive Summary 
1.1 North Ayrshire Council has been improving the energy efficiency of its housing stock
in accordance with the Energy Efficiency Standard for Social Housing (EESSH)
since its introduction in 2014. We have performed well against the original standard;
in 2023 we achieved 98.7% compliance. 
1.2 A second edition of the standard (EESSH2) was confirmed in 2019, setting a target
date of 2032 for compliance. In October 2022, the Scottish Government announced
a review of the planned EESSH2 standard in the wider context of the target for net
zero heat homes, as set out in the Scottish Government’s Climate Change Update,
the Heat in Buildings Strategy, and the Housing to 2040 Route Map.
1.3 In response to this review, the Scottish Government has launched its consultation
on a new ‘Scottish Housing Net Zero Standard’ (SHNZS) which will replace
EESSH2.
1.4 The proposed SHNZS builds upon the Scottish Government’s commitment to a
fabric first approach and proposes: a new fabric efficiency rating measured in
kilowatt hours per metre squared (kWh/m2) per year (level to be confirmed); and a
requirement to replace polluting heating systems with a clean heating alternative by
a backstop date of 2045.
1.5 There are a number of implications arising from the proposed introduction of the new
SHNZS, and these are set out within the report below and within the proposed
consultation response attached at Appendix 1. Cabinet approval is sought for
submission of the consultation response to the Scottish Government. 
Agenda Item 11
143

Page 144

2. Background
2.1 The new SHNZS builds on the previous Energy Efficiency Standard in Social
Housing (EESSH).  EESSH was introduced in March 2014 and set a first
milestone for social landlords to meet by 31 December 2020. A second milestone
(EESSH2) was confirmed in June 2019, for social rented houses to meet by
December 2032. The EESSH2 milestone was that: 
‘All social housing meets, or can be treated as meeting, EPC Band B (Energy
Efficiency rating), or is as energy efficient as practically possible, by the end of
December 2032 and within the limits of cost, technology and necessary consent.’
2.2  North Ayrshire Council’s housing stock has performed very well when measured  
against the original EESSH standard, reaching 98.7% compliance in 2023. The
relatively small percentage of failures are of a construction type or layout that
means further adaptations are not practical to install. Despite our high
performance when measured against the EESSH standard, less than 8% of North
Ayrshire Council properties met the requirements of the proposed EESSH2. This
was typical across other local authorities and Registered Social Landlords (RSLs). 
2.3 In March 2021, the Zero Emissions Social Housing Taskforce (ZEST) was
convened by the then Minister for Local Government, Housing and Planning.  The
Taskforce reviewed the opportunities, barriers, and solutions for social housing in
order to maximise its contribution to the Scottish Government’s climate change
targets, including in response to feedback in terms of the challenges of meeting
EESSH2 across the social rented housing sector.  
2.4 Interim guidance on the implementation of the EESSH2 standard was then issued
by the Scottish Government on 31 October 2022. This guidance suspended the
EESSH2 milestones and the reporting of stock performance against the revised
standard (reverting back to EESSH1) until the ZEST review was completed.
2.5 The ZEST report was published in August 2021 and recommended that a review
of the current EESSH guidance be brought forward and to agree new milestones
which were more closely aligned with the national 2045 net zero target.
2.6  The Scottish Government has now published its consultation on the replacement
for EESSH2, which will be called the Social Housing Net Zero Standard (SHNZS).
2.7 The consultation period closes in March 2024, following which the Scottish
Government will commission an independent analysis of the feedback received.
The new Standard is expected to be introduced by 2025 at the earliest. 
The Proposed Standard 
2.8 The SHNZS proposes a new fabric efficiency rating (which focuses on the amount
of energy for heat consumed by a property) measured in kWh/m2/year.  The level
and implementation date will be confirmed after consultation. This reflects a
change from EESSH2, which relied on an Energy Performance Certificate (EPC)
rating. 
144

Page 145

2.9 Alongside other provisions, the SHNZS also includes a requirement to replace
polluting heating systems with a clean alternative by a backstop date of 2045.
Interim target dates will be confirmed after consultation. 
SHNZS Implications   
2.10 If introduced, the proposed SHNZS would have a variety of implications for the
Council, with the main challenge being financial. The steps required to achieve
EESSH and EESSH2 were not funded by the Scottish Government and this is set
to continue under the SHNZS. While funding is provided indirectly through the
Strategic Housing Investment Plan for new-build properties, improvement of our
current stock has been funded though rental income. The consultation paper has
estimated that the costs for the provision of the clean heating element of the new
standard national are £4.6 billion. 
2.11 Currently, £132m has been allocated in the Council’s 30 Year HRA Business Plan
to make energy efficiency improvements within the existing stock. Existing capital
plans also include £111m for heating replacement, however, this is based on
provision of gas systems. Initial estimates for replacing gas systems with air-
source heat pumps indicate costs in the region of £370m alone. This underlines
the scale of the funding gap, and does not include additional fabric improvement
investment required to meet the proposed new fabric efficiency rating. 
2.12 At present, however, the full costs of meeting the proposed new SHNZS cannot be
fully quantified as the technical requirements of the Standard are not yet
confirmed. Also, there is likely to be a need for data relating to our existing stock to
be updated to align with the new Standard’s requirements.
2.13 There a variety of other implications which are reflected in the proposed
consultation response at Appendix 1. Some of the key concerns include: 
• Clean Heating –alongside the financial implications noted above, there are
technical challenges associated with retrofitting air source heat pumps (space
requirements internally, implications of new, larger radiators required), and
additional disturbance to tenants and additional maintenance costs.  The
running costs of clean heating will need to be carefully considered to ensure
tenants are not put at greater risk of fuel poverty.
• Fabric improvements – to meet the proposed standard and ensure the
viability of clean heating systems, the majority of properties will require
additional fabric measures.  Full costs for fabric improvements are unknown
at this time, however officers are progressing a pathfinder project on a
sample of our housing stock to gather detailed information in this area, and
consideration will also need to be given to cyclical replacement of these
measures.
• Air Tightness – additional costs arising from the design, installation and
maintenance of mechanical ventilation systems will be required following
enhanced fabric measures to ensure adequate ventilation arrangements and
address additional risks of increased condensation, dampness and mould
issues.
145

Page 146

• Business Planning – major revision of the 30 Year HRA business plan will be
required to ensure delivery aligns with the SHNZS proposals, with significant
financial pressure as a result.
• Multi- tenure – the proposed SHNZS is likely to only be achievable if
additional funding sources are made available to support private owners’
involvement with retrofit works in multi-tenure blocks.
• Infrastructure concerns – it is unlikely that the current national electricity
infrastructure has sufficient capacity to cope with increased electrification of
heating.  
• Skills and supply chain- new training and skills development will be required
for Building Services and our external contractors in relation to installation,
maintenance and repair of new systems, alongside development of the
supply chain to ensure adequate availability of systems and replacement
parts.
• Tenant engagement – the move towards clean heating systems will require
extensive tenant engagement to ensure buy-in of changes and effective
operation of alternative heating systems. 
2.14 The proposed consultation response at Appendix 1 welcomes the principles of the
new Standard, which align with the Council’s net zero aspirations, but clearly
articulates of the need for detailed further discussions in relation to the financial,
technical and other challenges that the new Standard would bring. 
2.15 Although we cannot currently quantify the full impact of the proposed new SHNZS,
without significant support from external sources, the full cost will require to be borne
by tenants’ rents. This raises significant concerns in relation to affordability and
therefore deliverability. There is an opportunity for the Scottish Government to
further consider grant funding arrangements to ‘pump-prime’ early adoption and
delivery of the fabric measures and new clean heating systems required to stimulate
the supply chain and establish more sustainable costs for future delivery of the
SHNZS. 
3.0 Proposals 
3.1  It is proposed that Cabinet: 
(i) notes the potential implications arising from the introduction of the Social
Housing Net Zero Standard; and (ii) approves the proposed response at Appendix
1 to the consultation document. 
4.0 Implications/Socio-economic Duty 
Financial 
4.1 The current HRA 30 Year Business Plan does not include provision for the full,
proposed SHNZS requirements. The costs and associated impact on the HRA
Business Plan will need to be carefully considered taking account of inflation, cyclical
replacement and maintenance once further clarity on the final SHNZS is provided.   
146

Page 147

Human Resources 
4.2 The implementation of the new SHNZS may have additional human resource
implications. This will be confirmed when the detailed nature of proposals are
clarified. 
Legal 
4.3 There are no legal implications arising from the report. 
Equality/Socio-economic 
4.4 There are additional costs associated with implementation of the fabric
improvements and clean heating solutions associated with the new SHNZS. This
is likely to have implications for future rent levels. The consultation response also
notes the risk of higher running costs associated with electrified heating systems,
which could put tenants at greater risk of fuel poverty. 
Climate Change and Carbon 
49.5 The proposals aim to: 
• make a positive contribution to national carbon reduction targets;
• contribute to the North Ayrshire Council Climate Emergency declaration and
commitment to be a net zero authority by 2030; and
• contribute to the delivery of the Sustainable North Ayrshire Strategy 
Key Priorities 
4.6 The proposals contained within the report support the North Ayrshire Council Plan
priority of addressing climate change and ensuring the provision of high quality
housing. 
Community Wealth Building 
4.7 There are no immediate Community Wealth Building implications arising from this
report. 
147

Page 148

5.0 Consultation 
5.1 A number of services were involved in the preparation of the consultation response,
including: 
• Property Management and Investment 
• Housing Services
• Energy and Sustainability
• Building Services
• Building Standards 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact David W. Hammond, Head of
Sustainability, Corporate Property & Transport, on 01294 324514. 
148

Page 149

Consultation on the Social Housing Net Zero
Standard 
Respondent Information Form 
Please Note this form must be completed and returned with your response.
To find out how we handle your personal data, please see our privacy policy:
https://www.gov.scot/privacy/ 
Are you responding as an individual or an organisation?   
Individual 
Organisation
Full name or organisation’s name 
Phone number 
Address 
Postcode 
Email Address 
The Scottish Government would like your 
permission to publish your consultation 
response. Please indicate your publishing 
preference: 
Publish response with name 
Publish response only (without name) 
Do not publish response
We will share your response internally with other Scottish Government policy teams who
may be addressing the issues you discuss. They may wish to contact you again in the
future, but we require your permission to do so. Are you content for Scottish
Government to contact you again in relation to this consultation exercise? 
Yes 
No 
North Ayrshire Council
Cunninghame House
Irvine
KA12 8EE
01294 310000
KA12 8EE
pmienquiries@north-ayrshire.gov.uk
Information for organisations:
The option 'Publish response only (without
name)’ is available for individual
respondents only. If this option is selected,
the organisation name will still be
published. 
If you choose the option 'Do not publish
response', your organisation name may still
be listed as having responded to the
consultation in, for example, the analysis
report. 
149

Page 150

Questionnaire 
Question 1
To what extent do you support the use of a fabric efficiency rating, based on heat
demand, in the SHNZS? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t Know
Please include any additional comments below. 
The introduction of the proposed rating would support national and local net zero
targets.  The rating would support the proposed energy efficiency standard (fabric
measures) for the Heat in Buildings Bill, which is currently out for consultation. The
rating would complement national fuel poverty targets and support reduced energy
costs for tenants. North Ayrshire Council's Local Heat and Energy Efficiency Strategy
has identified specific fabric measures which would improve energy efficiency and
reduce fuel poverty, supporting the new rating proposal. 
This approach should also incentivise improvements to fabric efficiency as it gives a
clearer measure of fabric performance and will align with changes to the EPC. 
We suggest further information will need to be provided to identify the most suitable
fabric upgrades, for example data relating to the fabric performance of the property
to ensure modelling is accurate and aligns to the new calculation method. 
The Council is currently progressing a pathfinder project to help determine the
different levels of fabric improvements possible for our stock types, achievable
performance gains, and the associated costs to both the Council and the tenants in
terms of capital, operating and lifecycle costs to inform our preparedness for the new
standards. 
We would support the new rating being linked to or replacing existing assessments
e.g. EPCs and alignment with Building Standards where these are applicable to the
work being undertaken. 
Our principal concern is in relation to affordability and the burden the new standard
will place on tenants due to the anticipated costs involved. We consider it essential
that Scottish Government makes addition funding available in the first instance to
support early delivery through pathfinder projects, which would develop further
understanding on new technologies and stimulate the supply-chain to drive costs
down to a more sustainable level. This ‘pump-priming’ is a similar approach to that
taken in encouraging installation of solar panels, electric vehicle charging
infrastructure etc. 
150

Page 151

Question 2
Of the options presented for the fabric efficiency rating, which one do you support for the
new SHNZS? 
Question 3
Are there additional options for the fabric efficiency rating that you think should be
included? If yes, please describe these here: 
Question 4
What, if any, are your views on how performance against the fabric efficiency rating
should be measured? 
Option 2 - kWh/m2 - Space Heating only
We would be supportive of the incremental approach (for example with an EPC ‘C
rating’ by 2033 and EPC B by 2040).   
This will provide a clear initial target with a back-stop date for full compliance. 
Within the options, we support the space heating demand only measure to ensure
that the fabric efficiency rating provides a baseline to measure against, should non-
fabric measures be introduced (i.e. changes to heating/hot water/solar PV etc.) 
The fabric of the building should be viewed as a long-term feature, whilst hot water
systems a have a shorter life span.  Including domestic hot water demand within the
calculation may complicate the metric and lessen the focus on the fabric measures. 
We also believe that mixed tenure and mixed use properties and different legislative
timescales could pose challenges for fabric retrofits in terms of achieving economies
of scale and securing support from other owners to proceed with improvements. 
No; we have not identified additional options for fabric efficiency rating. 
We would urge that there is consistency with any ratings/standards across housing
tenures to avoid confusion. 
We support the proposal to measure performance using SAP methodology.  This
aligns with our current approach. 
151

Page 152

Question 5
What are your views, if any, on the proposal for a minimum fabric efficiency standard? 
Question 6
What, if any, are your views on whether homes should not be relet if they cannot meet a
minimum fabric efficiency standard? 
Question 7
What, if any, are your views on whether ventilation and monitoring strategies should be
required where MVHR is not installed? 
Question 8
To what extent do you support the requirement to install a clean heating system by
2045)? 
Strongly support 
Somewhat support
We support the proposal for a minimum fabric efficiency standard as this provides
clear guidance for landlords.  However, we suggest that there must be suitable and
clear exemptions where such measures are not technically feasible or cost effective. 
The development of the LHEES indicated that a fabric first approach could have an
immediate impact on reducing carbon emissions. However, hard to treat, rural,
islands, mixed tenure mixed use and historic properties would need to be considered
on a case-by-case basis. 
We agree that homes should be of a suitable standard prior to letting. However, we
have significant concerns regarding the impact of this proposal on void turn-over
times, with a resultant impact on the timescales for allocation of homes, overall
availability of housing stock to meet housing need, and the impact on rental income
within the Housing Revenue Account 30 Year Business Plan. These impacts need to
be carefully considered and understood to avoid likely unintended consequences and
further pressure on housing need and Business Plan affordability. 
At this time, we would not support a national strategy regarding ventilation and
monitoring as part of the SHNZS. 
Where fabric improvements may require additional ventilation/monitoring, this should
be considered as part of the design. We therefore suggest that the requirements for
MVHR should be assessed on a case-by-case basis, including air quality, rather than
as a blanket requirement. 
152

Page 153

Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t Know
Please include any additional comments below. 
We are supportive of the move towards clean heating if it is supported by a sustainable
funding model. The cost of this work would significantly impact upon rent levels and the
affordability of the HRA 30 Year Business Plans going forward. 
We currently have in the region of 12,800 gas heating systems installed across our
housing stock.  The costs associated with replacing these with clean heating systems,
together with the associated fabric improvements to make the systems viable, is
considerable. 
Initial estimates for replacing our gas systems with air-source heat pumps suggest
costs in the region of £370m across the life of our latest 30 Year Business Plan. This
would have a considerable impact on affordability of rent levels in the future, and is
exclusive of fabric improvement investments which would be required to comply with
the SHNZS. 
The transition to clean heating systems (presumed likely to be principally air-sourced
heat pumps as the most practical option) will have several implications: 
- Increased capital costs (circa £5k more per home than a gas system).
- Increased maintenance and lifecycle costs
- Risk of increased running costs for tenants, alongside increased risk of fuel
poverty
- Adding potentially complex ventilation systems, alongside associated running
and lifecycle costs
- Internal space implications through buffer tanks and increased radiator sizes 
- External space implications for siting ASHP units
- As a result of space implications, not all existing properties will be suitable for
conversion. 
- Additional communication with tenants about how the systems work and “buy-in”
to changes in energy usage.  
- Skills and capacity within our direct labour and wider supply chain in relation to
maintenance and reactive and cyclical maintenance
- Disruption to tenants and residents during the delivery phase of adaptation
programmes
Mixed tenure properties will also pose challenges, and the interface between the
SHNZS proposals for those other tenures within the current Heat in Buildings Bill which
has been published for consultation also needs to be considered. 
The move to electric heating will place significant strain on current grid capacity. We
consider that an assessment of the grid implications nationally is required, with clarity
on the nature, cost and timescales for any grid improvements then being linked to the
targets and timescales for clean heating within the new SHNZS. 
153

Page 154

Question 9
Of the options presented for the interim targets, which one do you support for the
SHNZS? 
Question 10
What are your views on whether neighbouring landlords could work together to reach
such a target on a regional basis? 
Question 11
Are there any additional options for interim targets that you think should be included? If
yes, please describe these here: 
Question 12
To what extent do you support the requirement for mandatory connections to heat
networks under certain circumstances? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose
We support the phasing-in of milestone measures and interim targets. As we have
relatively few properties ‘off-gas’, option one is therefore a more relevant model. 
We need to consider carefully the cost of phased implementation on rent levels and
the HRA business plan. This cannot be done until the analysis of the implications on
our housing stock is completed. We consider that a lead-in time will therefore be
required for local authorities and Registered Social Landlords, following confirmation of
the new SHNZS, to model different fabric and clean heating system scenarios,
understand and plan for the investment required, re-design current capital investment
and lifecycle maintenance programmes, and engage with tenants in relation to
proposed changes and ensure readiness for the new heating systems. 
The Council has previously worked with Social Registered Landlords through funds
such as Heat & Energy Efficiency Scotland, Area Based Scheme and the Capital
Acceleration Programme and continues to support collaborative ventures where
possible. 
The Council support the ambition to connect to heat networks where practical,
affordable and suitable arrangements for installation, usage and on-going
maintenance costs are in-place and provide best value. 
No; we have not identified any additional options for interim targets beyond those
outlined. 
154

Page 155

Strongly oppose 
Don’t Know
Please include any additional comments below. 
We support the principle of heat networks and recognise these will support national
and local net zero targets and allows local authorities to fulfil their duties under the
Heat Network (Scotland) Act 2021. However, we do not believe the introduction of
mandatory connection to heat networks is applicable in an individual retrofit situation. 
Heat network connection may be most suitable where new build properties are under
consideration or for larger scale refurbishment or regeneration projects. 
Business cases for heat networks, in our experience, are highly sensitive to a number
of factors, including type of fuel, number of buildings and associated heat load, nature
of project (new build or refurbishment) and utility costs. This means that the projects
must be considered on a case-by-case basis to ensure they are viable, that running
costs for those connecting will be affordable, and that connection costs to the network
are reasonable.   
We believe that heat networks have a future role to play in the decarbonisation of
heat in Scotland, but mandatory connections are unlikely to be an effective means of
facilitation. 
155

Page 156

Question 13
To what extent do you support the need for landlords to have an element of discretion to
ensure measures are cost effective and in the best interest of tenants? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t Know
Please include any additional comments below.
Question 14
What, if any, are your views on whether targets should be varied by guidance from the
Scottish Government in specific circumstances?
Question 15
To what extent do you agree that the new SHNZS should apply to mixed tenure
properties? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t Know
We strongly support the need for discretion within the SHNZS.  We suggest any
discretionary list must be clearly defined, with a set process for application. 
The list of measures needs to be practical and clear with appropriate guidance. 
Measures must be practical, cost effective, reduce fuel poverty and support national
and local net zero targets. Consultation with relevant stakeholders will be important
before any measures or timescales are introduced. 
We note that varied targets could increase the risk of confusion and non-compliance.
We would be able to comment further on this question if specific examples where
targets would be varied are provided. 
156

Page 157

Please include any additional comments below. 
Question 16
Do you agree that for some blocks where the local authority or RSL is not a sole or
majority owner, then a phased approach to retrofit work should be undertaken? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t Know
Please include any additional comments below. 
Question 17
To what extent do you agree that the new SHNZS should apply to Gypsy/traveller sites? 
Strongly support 
Somewhat support 
Neither support nor oppose
We suggest that, without concomitant funding, it would be unachievable to impose
the SHNZS on private owners. If a single standard is to be adopted, lack of funding
to private owners will be a risk. 
The Council’s LHEES confirmed, through consultation with stakeholders, that
landlords and private owners in mixed tenure buildings have experienced difficulty
in upgrading their properties due to a failure to come to an agreement with other
owners. 
The LHEES also identified that implementing insulation measures in mixed tenure
properties is likely to be more challenging and would require further engagement,
with the following feedback from stakeholders:
• installing any energy efficiency measures can be expensive and it can take a
long time to recover the outlay, if at all
• concerns regarding hard-to treat properties, the availability of skilled
contractors to undertake the work as well as having clarity on which
measures contribute to an improvement on EPC rating
• reporting on mixed tenure blocks and a requirement to evidence that
connected owner or landlord properties have been engaged (i.e. support
offered through Home Energy Scotland grants and loans or Area Based
Schemes to owners/landlords 
This will only be achievable if additional funding sources are made available to
support private owners’ involvement within retrofit works, for the reasons noted in our
responses above. 
157

Page 158

Somewhat oppose 
Strongly oppose 
Don’t Know
Please include any additional comments below.
Question 18
What are your views on the timetable for introducing the new SHNZS? 
These units are not within the scope of the current legislation and as such are not
reported as a dwelling.  We therefore do not agree that the SHNZS should be applied
as these are not categorised as dwellings.
Significant risks to the timescales include:  
• Resolving affordability issues and establishing a sustainable funding model for
local authorities and RSLs to meet the SHNZS
• We need to consider carefully the cost of phased implementation on rent levels
and the HRA business plan. This cannot be done until the analysis of the
implications on our housing stock is completed. We consider that a lead-in
time will therefore be required for local authorities and Registered Social
Landlords, following confirmation of the new SHNZS, to model different fabric
and clean heating system scenarios, understand and plan for the investment
required, re-design current capital investment and lifecycle maintenance
programmes, and engage with tenants in relation to proposed changes and
ensure readiness for the new heating systems. 
• Any further delay beyond 2025 should be reflected in the target dates provided
to ensure timescales are not shortened and become unachievable.
• The ability of the national electricity grid to cope with the increased load arising
from the projected switch from gas to electrically based heating systems
158

Page 159

NORTH AYRSHIRE COUNCIL  
20 February 2024 
Cabinet
Title: Scottish Government Consultation on the proposed Heat in
Buildings Bill 
Purpose: To provide Cabinet with details of the proposed Heat in Buildings
Bill and to seek approval of the proposed response to the
Scottish Government consultation. 
Recommendation: That Cabinet: (i) notes the potential implications arising from
the proposed Heat in Buildings Bill; and (ii) approves the
proposed response at Appendix 1 to the consultation
document. 
1. Executive Summary 
1.1 The Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 requires that
net zero emissions are achieved by 2045, with associated interim targets. Emissions
from buildings are the third largest source of greenhouse gas emissions in Scotland.
1.2 In response to this challenge, a consultation has been published by the Scottish
Government setting out proposals for a Heat in Buildings Bill to:
• prohibit the use of polluting heating systems after 2045 in all buildings (2038 for
public sector non-domestic buildings) and, before then, within a fixed period (not
yet specified) after a point of property purchase or when a heat network
connection is available; and,
• require a minimum energy efficiency standard by 2028 for the private rental
sector, and 2033 for owner occupiers.
1.3 Cabinet approval is sought for submission of the proposed response to the consultation
at Appendix 1 to the Scottish Government. 
2. Background 
2.1 The Climate Change (Emissions Reduction Targets) (Scotland) Act 2019 requires us to
reach net zero emissions by 2045, with interim targets of 75% reduction in emissions
by 2030 and a 90% reduction in emissions by 2040.  The Council declared a climate
emergency and aims to achieve net zero carbon emissions by 2030.  
2.2 The Council’s latest Sustainable North Ayrshire strategy sets out the pathway to
achieving this ambition, and includes a strategic priority to act on emissions from heat,
including through project pathfinder approaches for decarbonisation of domestic and
non-domestic buildings to bring scale and pace to emissions reduction.
2.3 The way in which homes, businesses and public buildings are heated is the third-
largest cause of greenhouse gas emissions in Scotland.  Most heating systems burn
fossil fuels such as gas, oil and liquid petroleum gas (LPG).  These are known as ‘direct
Agenda Item 12
159

Page 160

emissions heating systems’ because they produce emissions when we use them.  In
order to decarbonise heating systems, we need to adopt clean heating systems which
do not produce any greenhouse gas emissions at the point of use.  Some examples of
clean heating systems include heat pumps, high efficiency electric storage heaters and
heat networks.
2.4 It is recognised that whilst some households, business and public sector buildings are
working towards heat decarbonisation and improved energy efficiency, the pace of
change falls short of what is required to reach our climate change targets.
2.5 It is estimated that approximately 89% of homes and 49% of non-domestic premises
are using fossil fuel heating at present, while around 55% of homes do not meet what is
considered a good level of energy efficiency, i.e. an Energy Performance Certificate
(EPC) rating of C or above. 
2.6 In response, the Scottish Government is proposing to introduce a Heat in Buildings Bill
containing the powers to create a new ‘Heat in Buildings Standard’. The draft Bill and
Standard would include the following regulations: 
Prohibition of fossil fuels
2.7 A prohibition on fossil fuels as the main heating fuel would ban the use of heating
systems such as gas boilers, oil boilers or LPG to provide heat or hot water in homes
and non-domestic buildings. In practice, this would mean that homes and non-
domestic buildings will instead need to use clean heating systems such as heat pumps,
electric storage heaters or heat networks. The clean heating system that a building
should move to will be a choice for the owner, with the systems suitable for their
buildings varying depending on a range of factors such as size, construction type and
nature of the building use. 
Non-Domestic Buildings
2.8 The Council has 630 non-domestic properties of which 131 use gas, 20 use biomass,
four use oil, and one uses LPG, with the remainder using electricity as the main heating
fuel. The requirement to move to clean energy solutions is necessary to achieve net
zero emissions; it is the type of technology, energy efficiency solutions to support the
new heating system, and of course the capital cost which requires further
consideration.  Furthermore, the planned and reactive maintenance schedules and their
associated costs for new clean heating systems also need to be factored in. Local
authorities are not currently resourced to provide the level of investment required to
fully decarbonise building stock. 
Owner Occupied Housing Stock 
2.9 A good level of energy efficiency is defined in the Heat in Buildings Strategy as
equivalent to EPC band C. EPCs are a legal requirement whenever a home or non-
domestic building is advertised for sale or let.  It is proposed in the Bill that, by
In all buildings (including
non-domestic)
•Prohibit use of fossil
fuel as main heating
source from 2045.
•All buildings owned by
a Scottish public
authority to be using
clean heating systems
by the end of 2038.
In owner occupied
homes
•Require homes to meet
minimum energy
efficiency standard by
the end of 2033.
In private rented homes
•Require landlords to
meet a minimum
energy efficiency
standard by the end of
2028.
160

Page 161

stipulating a straightforward list of energy efficiency measures, this minimum standard
could be met in an affordable manner.  The proposed list of measures is as follows:
• 270mm loft insulation
• Cavity wall insulation
• Draught-proofing
• Heating controls
• 80mm hot water cylinder insulation
• Suspended floor insulation
2.10 It is further proposed that if an owner occupier installs a clean heating system, they will
not be required to meet the energy efficiency standard, although will be encouraged to
do so. This is because by switching to a clean heating system, an owner would remove
carbon emissions associated with heating. 
2.11 There are no proposals to set a minimum energy efficiency standard for non-domestic
buildings.  The variety of size, construction type, and nature of use of non-domestic
building would render a prescriptive list of measures ineffective. 
2.12 It is proposed within the consultation that those purchasing a property (either domestic
or non-domestic) will be required to comply with the prohibition of a fossil fuel heating
source within a specified amount of time following completion of the sale.  Further
proposals and regulations are being developed around this proposed requirement
including the use of a post-sale grace period for compliance.
2.13 Traditional properties, which make up a significant proportion of Scotland’s homes and
buildings, may have different requirements based on their construction type, location or
status, and work is ongoing with Historic Environment Scotland to find the best
solutions for these buildings while being sympathetic to their character and features. 
Private Rented Housing Stock
2.14 An earlier date for meeting the minimum energy efficiency standards is set for the
private rental sector in order to help address the Scottish Government’s obligation to
tackle fuel poverty. The standard aims to support tenants to have warmer homes that
are easier and less expensive to heat, whilst enhancing the quality of the asset for the
landlord.
2.15 It is proposed within the consultation that even if a private rented property installs a
clean heating system, it will also be required to meet the energy efficiency standard.
Properties in the private rented sector which do not meet the energy efficiency standard
by the end of 2028 would not be allowed to be leased to a new tenant, should the
existing tenant vacate.
2.16 The Heat in Buildings Standard will not be applied to the social rented sector, as
recommendations for social rented stock are currently being consulted on through the
Social Housing Net Zero Standard (which is subject to a separate report to Cabinet).
However, the Council will be required to consider what the Heat in Building Standard
means our non-domestic estate, and how to support implementation in private sector
housing.  
2.17 The Council currently supports private sector households in relation to energy efficiency
and decarbonisation through various services and programmes, for example energy
advice and support through Energy Smart, alongside provision of measures through
ECO Flex and annual Area Based Schemes.
2.18 The role of local authorities in the implementation of the Heat in Buildings proposals is
not sufficiently clear, and this is reflected in our consultation response.
2.19 A recurring consideration in the proposed consultation response is the resources
required to deliver on the proposed aspirations. The new clean heating systems
161

Page 162

required for Council owned non-domestic properties are not deliverable within current
local authority funding envelopes. The Council is undertaking a review of the non-
domestic estate to identify the decarbonisation measures required, and indicative costs,
to achieve net zero.  This information will help to determine the most suitable
technology and support future any opportunities for external grant funding applications.
2.20 There also remains questions as to how the implementation of clean heat and energy
efficiency standards will be monitored and enforced across the area. The current EPC
enforcement regimes are inadequately resourced and applied to varying degrees, thus
demonstrating that a significant level of resource would be required if the Council were
to be the enforcing body, either through EPC monitoring or sampling methods.  
2.21 The purpose of this consultation is to raise awareness of Scottish Government’s
proposal to make new laws around the heating systems that can be used in homes and
places of work, and it seeks views on those proposals.  A cross-service response has
been prepared, which reflects the comments above and other observations, and is
provided at Appendix 1.  The Heat in Buildings Bill aligns with the aspiration of the
North Ayrshire Council Plan priority of addressing climate change, and the new
Sustainable North Ayrshire strategy, to achieve net zero emissions. Further clarity is
required on the specific role of local authorities and the resources required to achieved
the ambitions articulated.   
3. Proposals 
3.1 It is proposed that Cabinet approves the consultation response at Appendix 1 for
submission to the Scottish Government. 
4. Implications/Socio-economic Duty
Financial
4.1 The financial implications of the proposals being consulted on will be significant for
local authorities, and this has been raised repeatedly in the proposed consultation
response. 
Human Resources 
4.2 If implemented, the proposals being consulted on would require additional human
resources for delivery, monitoring and enforcement.  The nature and extent of such
resources is not yet clear. This is reflected in the proposed consultation response. 
Legal 
4.3 Under the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019, all
public bodies in Scotland have a duty to contribute to the delivery of the net zero
emissions target. 
Equality/Socio-economic 
4.4 The ambition to decarbonise heating systems and improve energy efficiency in all
buildings contributes to our socio-economic duty by ensuring our homes and buildings
are well insulated and energy efficient, making them cheaper to heat and reducing
their emissions. 
162

Page 163

Climate Change and Carbon 
4.5 The consultation responses support the Council’s net zero ambitions and aspiration to
reduce fuel poverty across North Ayrshire. 
Key Priorities 
4.6 The consultation responses are in keeping with the aim ‘To achieve net-zero by 2030’
within the Council Plan 2023-28. 
Community Wealth Building 
4.7 There are no community wealth building implications arising from the report. 
5. Consultation 
5.1 The consultation documents have reviewed by various Council services including
Protective Services, Property Management and Investment, Housing Strategy &
Development and Sustainability to provide a cross-service response. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact David W. Hammond, Head of Sustainability,
Corporate Property & Transport, on (01294) 324514. 
Background Papers
0
163

Page 164

Changing the way we heat our homes and
buildings – A consultation on proposals for a Heat
in Buildings Bill 
Respondent Information Form 
Please Note this form must be completed and returned with your response.
To find out how we handle your personal data, please see our privacy policy:
https://www.gov.scot/privacy/ 
Are you responding as an individual or an organisation?   
Individual 
X Organisation
Full name or organisation’s name 
Phone number 
Address 
Postcode 
Email Address 
The Scottish Government would like your 
permission to publish your consultation 
response. Please indicate your publishing 
preference: 
x Publish response with name 
Publish response only (without name) 
Do not publish response
We will share your response internally with other Scottish Government policy teams who
may be addressing the issues you discuss. They may wish to contact you again in the
future, but we require your permission to do so. Are you content for Scottish
Government to contact you again in relation to this consultation exercise?
x Yes 
No 
North Ayrshire Council
Cunninghame House, Irvine, Ayrshire
KA12 8EE 
Information for organisations:
The option 'Publish response only (without
name)’ is available for individual
respondents only. If this option is selected,
the organisation name will still be
published. 
If you choose the option 'Do not publish
response', your organisation name may still
be listed as having responded to the
consultation in, for example, the analysis
report. 
164

Page 165

Questionnaire 
Question 1
To what extent do you support our proposal to prohibit the use of polluting heating
systems in all buildings after 2045? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below.
Question 2
To what extent do you agree that we should introduce a minimum energy efficiency
standard to be met by private sector landlords by the end of 2028 (even if they are
already using clean heating)? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know
Please include any additional comments below.
North Ayrshire Council supports, in principle, the proposal to prohibit the use of
polluting heating systems in buildings after 2045, as this is aligned to both national
and local net zero targets.   
Whilst the proposals for the Bill are ambitious and necessary to support carbon
emission and fuel poverty reduction, success will be reliant on addressing the
financial and technical challenges associated with improved fabric efficiency of
buildings and replacement of polluting heating systems.  A clear routemap for
delivery is required which address funding constraints for building owners, risks of
higher operation and maintenance costs than traditional heating solutions, alongside
the skills and supply chain investment that is required for roll-out of energy efficiency
measures and replacement heating systems at scale. 
165

Page 166

Question 3
To what extent do you agree that we should introduce a minimum energy efficiency
standard to be met in owner occupied homes (which still have a polluting heating
system) by the end of 2033? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
This proposal would support both the Council’s and national net zero targets. In relation to fuel
poverty, installing energy efficiency measures would make homes more energy efficient, easier to
heat and, by further installing clean heat, this would reduce the financial burden on tenants.
The Council’s Local Heat and Energy Efficiency Strategy (LHEES) clearly identified specific
strategic energy efficiency measures (such as loft and wall insulation, cylinder insulation and
glazing) which would improve energy efficiency of properties and further reduce fuel poverty within
North Ayrshire domestic properties. 
It is, however, anticipated that there would be difficulties for private sector landlords to install
measures by 2028 to meet the minimum energy efficiency standard without additional resource
and support. Feedback from our LHEES consultation with private landlords suggests that costs to
install any energy efficiency measures are often cost-prohibitive, with no direct means for the
landlord to recover the expenditure. 
If the building is of mixed tenure, private sector landlords generally cannot influence other owners
in the building to carry out installation of the same measures at the same time. The different
proposed target timescales for different tenures should also be addressed within final proposals to
ensure implementation is feasible. Concerns regarding skills and supply chain to undertake the
work, as well as having clarity on which measures contribute to an improvement on EPC rating,
are also noted.   
Further clarity is required on how the clean heat and energy efficiency standards will be monitored
and whether this would become part of the Repairing/Tolerable Standard. 
166

Page 167

Question 4
Do you agree with our proposal to set a minimum energy efficiency standard that can be
met by either installing a straightforward list of measures, or showing a good level of
energy efficiency based on a reformed EPC fabric efficiency metric?   
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
We welcome the ambition to reduce carbon emissions and reduce fuel poverty
through the introduction of minimum energy efficiency standards.  Making homes
more energy efficient and easier to heat by installing energy efficiency measures first
and then addressing the need for clean heat would reduce the financial burden for
owner occupiers and reduce carbon emissions for North Ayrshire and Scotland.
However, the costs for owner occupiers to install any required energy efficiency
measures and clean heating systems are likely to be cost prohibitive to meet the 2033
timescale due to the scale and volume of interventions required. There is also a lack
of clarity on what the most effective measures are for a given property. This was
reinforced through our recent LHEES consultation feedback. 
Mixed tenancy, mixed use properties will be more challenging where all residents may
not be able to afford or want to make improvements at the same time, due to the
different proposed legislative compliance timescales.
Historic properties and off-gas properties (particularly in rural and islands) cannot
always incorporate the energy efficiency measures or clean heat options. These
would need to be reviewed on a case by case basis.  There are also difficulties in
securing contractors at reasonable cost to undertake works and repairs in more
remote locations, alongside general challenges in terms of supply chain and skills
capacity.
The proposal to set a minimum energy efficiency standard by installing the
straightforward fabric measures listed is welcomed in principle, in order to provide a
level of clarity for building owners in terms of the most effective measures to pursue.   
The wider financial and supply chain challenges in implementing the measures are
noted in our responses above. 
Any standard list needs to take cognisance of the fact that a ‘one size fits all’
approach to measures is challenging in practice due to the variety of building types
and potential gaps in knowledge of building maintenance, including previous
improvements. 
167

Page 168

Question 5
What is your view on the initial proposed list of measures to meet the minimum energy
efficiency standard? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Question 6 
Do you think that properties for which most or all of the measures on the initial proposed
list are not relevant should be required to meet an equivalent minimum energy efficiency
standard? 
No – these properties should be considered compliant once they have installed all
the measures that are appropriate for their building type, even if this is few or no
measures. 
Yes – they should be required to meet the standard and additional measures should
be included on the list (such as solid wall insulation, solid floor insulation and flat roof
insulation), and they should be required to install all of these where feasible 
Yes – they should be required to meet the standard and additional measures should
be included on the list (such as solid wall insulation, solid floor insulation and flat roof
insulation), but they should only be required to install some of these where feasible and
cost effective 
Yes – they should be required to meet the standard and additional measures should
be included on the list (such as solid wall insulation, solid floor insulation and flat roof
insulation), but they should only be required to install some of these where feasible, and
they should be allowed additional time to do so 
We agree with the proposed list of fabric measures to support the minimum energy
efficiency standard. However, we would recommend that the list needs to be
developed further to prioritise the measures that would have the most impact for
properties, including with reference to cost and level of disruption, and how this
would align with our LHEES. 
Financial support and information resources will be key to enabling successful
uptake of the measures. 
168

Page 169

Please include any additional comments below. 
Question 7 
Do you think that an alternative approach to setting the minimum energy efficiency
standard is required? 
Yes 
No 
Don’t know 
Please include any additional comments below. 
Question 8 
Do you agree that the use of bioenergy should continue to be permitted in certain
circumstances? 
No, it should be prohibited in all cases 
Yes, it should be permitted for those buildings already using it  
Yes, it should be permitted for those buildings who have no other clean heating
system available. 
Question 9
Our LHEES identified, based on Home Analytics data, that in North Ayrshire around
40% of domestic properties will require an energy efficiency measure(s) and/or
installation of clean heat to improve their Energy Performance Certificate (EPC)
rating to C or better. All domestic properties, where practical and cost effective,
should be required to meet or exceed the standard, which could include installing
additional/different measures based on the result of an EPC assessment of the
property. However, consideration on a case-by-case basis needs to be taken into
account for historic, rural and hard to treat properties, alongside the other financial
and supply chain issues noted in our other responses.   
The proposals in the consultation paper detail the requirements for the introduction
of setting a minimum energy efficiency standard. In principle, this approach appears
appropriate and practical, and will support emission reductions and help reduce fuel
poverty, alongside supporting national and local net zero targets. 
Affordability for the cost to install energy efficiency measures and clean heat are, as
noted elsewhere in our responses, a significant concern. 
169

Page 170

To what extent do you support the requirement to end the use of polluting heating
following a property purchase? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Question 10 
We are proposing to give those purchasing a property a ‘grace period’ to end their use of
polluting heating.  Do you agree with this proposal? 
Yes -  the grace period should be two years 
Yes – the grace period should be three years 
Yes – the grace period should be four years 
Yes – the grace period should be five years 
No, please provide reasons for your view. 
Question 11 
The ability for homeowners to fund a new clean heating system, within the grace
period, could simply be out with their financial capability. There are also questions
regarding how compliance would be monitored and enforced. 
While we welcome the scenarios laid out in the consultation document, there
remains a significant concern over the affordability for building owners to fund the
measures required. 
Compliance within the grace period will depend on each individual property owners’
financial circumstances. The proposal to provide information to the buyer from a
variety of sources, in advance of the sale, to raise awareness of timescales and
requirements is a pragmatic approach. 
170

Page 171

To what extent do you support our proposal to apply a cost-cap where people are
required to end their use of polluting heating following a property purchase? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please provide reasons for your view. 
Question 12 
Which of the following methods of applying a cost-cap do you support? 
A flat cost-cap 
A size-based cost-cap 
A purchase price-based cost-cap 
None 
Another, please suggest below 
Please provide alternative 
Question 13 
To what extent do you support the proposal that the Scottish Ministers should be given
powers to extend the circumstances in future (beyond a property purchase) in which
people could be required to end their use of polluting heating? 
This could be, for example, preventing the installation of new fossil fuel boilers when
replacing the heating in your home or business premises. 
Strongly support
The proposal to apply a cost-cap is practical and will provide reliable upfront
information for potential buyers and sellers. However, it is noted that there may be
some unintended consequences and we would welcome further clarity and
suggested resolution to those.
Also, we would recommend a level of quality assurance from contractors, so that
purchasers are not left with issues arising from poor quality installations. 
Furthermore, upskilling in the marketplace and further education will be required to       
There are disadvantages to each of the proposed cap solutions, and we would
require further details on each in order to provide meaningful feedback. 
171

Page 172

Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
This proposal requires further details before we can respond. 
Question 14 
To what extent do you support our proposal to provide local authorities (and Scottish
Ministers) with powers to require buildings within a Heat Network Zone to end their use
of polluting heating systems by a given date? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Heat networks should support national and local net zero targets and allows local authorities
to fulfil their duties under the Heat Network (Scotland) Act 2021. 
The Council’s LHEES highlighted that North Ayrshire has a relatively low density of heat
demand (around 3.5% of domestic properties) which limits the opportunities for heat
networks.  
There is a distinction between having powers and exercising them. We are aware that
business cases for heat networks, in our experience, are highly sensitive to a number of
factors, including type of fuel, number of buildings and associated heat load, nature of project
(new build or refurbishment) and utility costs. This means that projects must be considered
on a case by case basis to ensure they are viable, that running costs for those connecting
will be affordable, and that connection costs to the network are reasonable. These will be key
considerations in the exercise of any powers to mandate the termination of polluting heating
systems.   
The nature of monitoring and compliance of any requirement also needs to be considered. 
172

Page 173

Question 15 
To what extent do you support our proposal to provide powers to local authorities (or
Scottish Ministers) that require developers to connect new buildings within Heat Network
Zones to a heat network? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Question 16 
To what extent do you support our proposal to require occupiers of non-domestic
properties to provide information about unused heat on their premises? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below.
Heat networks should support national and local net zero targets and allow local authorities
to fulfil their duties under the Heat Network (Scotland) Act 2021. 
The Council’s LHEES highlighted that North Ayrshire has a relatively low density of heat
demand (around 3.5% of domestic properties) which limits the opportunities for heat
networks.  
There is a distinction between having powers and exercising them. We are aware that
business cases for heat networks, in our experience, are highly sensitive to a number of
factors, including type of fuel, number of buildings and associated heat load, nature of project
(new build or refurbishment) and utility costs. This means that projects must be considered
on a case by case basis to ensure they are viable, that running costs for those connecting
will be affordable, and that connection costs to the network are reasonable. These will be key
considerations in the exercise of any powers to mandate the termination of polluting heating
systems.   
The nature of monitoring and compliance of any requirement also needs to be considered. 
173

Page 174

Question 17 
To what extent do you support our proposal to potentially require buildings with unused
heat to provide this to a local heat network? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Question 18 
We will need to have a way to monitor if people are meeting the Heat in Buildings
Standard, and discussed two options for this.  Which do you support?
The Council’s LHEES includes analysis of the Non-Domestic Analytics datasets and
the outputs of the first national assessment of heat networks for North Ayrshire’s
non-domestic stock. The Non-Domestic Analytics dataset had data gaps, which
limited the analysis of non-domestic buildings and further data collection and
investigation will be required.   
The proposal to require occupiers of non-domestic properties to provide information
about unused heat on their premises would improve available datasets and allow
the Scottish Government and local authorities to undertake more detailed analysis
to identify and develop potential heat network opportunities.
Our LHEES recognises that there are some potential heat network opportunities in
the North Ayrshire area. In addition, there may be opportunities to connect to other
significant heat loads with adjoining local authorities. The proposal to potentially
require buildings with unused heat to provide this to a local heat network would
support local opportunities to decarbonise heat, reduce emissions and reduce fuel
poverty. 
However, any requirement for discharge of waste heat from buildings into a heat
network will require detailed consideration. We would suggest that the requirement is
to investigate the viability of connection as opposed to mandating a connection for
discharge of waste heat. 
174

Page 175

Submitting EPCs alone 
Sampling a percentage of buildings 
A combination of the two 
None, there should be no monitoring 
Another method, please suggest below or explain your selected answer 
Question 19 
We will need to have a way to enforce the Heat in Buildings Standard.  We discussed
possible options to help achieve compliance.  What are your views on these ideas? 
I support relying on market and financial product mechanisms such as mortgages or
home/ building insurance 
I support extra Council Tax and Non-domestic Rates charges, in future, for those
who don’t comply 
I support the introduction of civil penalties, in future, if compliance is not achieved 
I support a mixture of the above options 
I do not support any form of enforcement 
Please explain your answer: 
Question 20 
Collection of both sets of information would enhance accuracy of non-domestic
data. Using the already familiar EPC methodology will ensure consistency in
capturing and reporting data. A desktop sampling audit would ensure compliance
and accuracy of EPC for buildings. 
However there are resource implications for each local authority should this be
undertaken, which cannot be met within current resources. 
If enforcement lies with local authorities, we would need to understand what
resources would be provided to discharge these responsibilities before being able
to respond. 
Other enforcement and sanctions consultations which are currently underway in
relation to the Building (Scotland) Act may offer additional insight into the legal
complexities, resources and barriers to effective enforcement of built environment
issues. In addition, the current EPC enforcement regimes are inadequately
resourced and applied to varying degrees, demonstrating that a significant level of
resource would be required if local authorities were to be the enforcing body and be
responsible for sampling.
175

Page 176

To what extent do you support our proposals to modify the Standard or exempt certain
people from the need to meet the Heat in Buildings Standard? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below. 
Question 21 
Which people, businesses, or types of buildings, if any, should be eligible for a modified
standard or exemptions? 
Question 22 
To what extent do you support our proposals to give certain people extra time to meet
the Heat in Buildings Standard? 
X Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know
Hard to treat, rural and historic properties would need to be reviewed on a case by
case basis as energy efficiency measures and clean heat options may not be
suitable for these buildings, which in effect would result in non-compliance with the
standard. 
• Listed buildings
• Mixed use mixed tenancy (due to different timescales for compliance)
• People in fuel poverty / extreme fuel poverty
• First time buyers
• Rural properties (due to difficulties to access suppliers / repairs and additional costs
i.e. “island premium”)
176

Page 177

Please include any additional comments below. 
Question 23 
Which people, businesses or types of buildings, if any, should be eligible for extra time? 
Question 24 
To what extent do you support our proposal to require all buildings owned by a Scottish
public authority to be using clean heating systems by 2038? 
Strongly support 
Somewhat support 
Neither support nor oppose 
Somewhat oppose 
Strongly oppose 
Don’t know 
Please include any additional comments below.
We are supportive for additional time to be provided to hard to treat, rural and
historic properties. These buildings need to be reviewed on a case by case basis as
energy efficiency measures and clean heat options may not be suitable for these
buildings, which in effect would result in non-compliance with the standard. 
See response above. 
177

Page 178

Question 25 
We are considering the following further duties on public sector organisations to support
planning for the transition by 2038: 
Placing a new duty on public sector organisations which would, from 2025, prevent
them from replacing a polluting heating system with another (unless impractical) 
Creating a new duty for each public body to develop and implement a plan to
decarbonise their buildings 
Placing a new statutory reporting duty on public sector organisations to demonstrate
progress towards their 2038 objective (with the potential for the 2038 then to be non-
statutory); and/or 
Placing no further statutory requirements on public sector organisations (instead
relying on their ability to plan alongside our delivery and funding programmes to meet
the 2038 objective) 
[Multiple choice boxes] 
Please include any additional comments below. 
Question 26 
Do you agree with our proposals to include powers in the proposed Heat in Buildings Bill
to change the current requirement in legislation for a narrowly-defined renewable heat
target? 
It is recognised that local authorities should lead by example. This proposal would help
provide a degree of certainty for a pipeline for work for skills and supply chains to be
developed to ready the market for commercial properties. Our LHEES and Ayrshire Energy
Masterplan will help identify decarbonisation opportunities within our non-domestic estate but
may require further analysis and investigation. 
However, the resourcing of this proposed requirement is key. Local authorities are currently
unable to meet decarbonisation requirements for building stock within existing financial
envelopes. In addition, further personnel resource (either internal or external to local
authorities) will be required to identify, design, implement and monitor the projects
associated with the proposal. 
We welcome the proposal to halt fossil fuel use and develop a plan to decarbonise
the heating systems in our existing stock.  Additional resource will be required to
undertake these tasks.  The current Public Bodies Climate Change Duty requires
robust reporting, therefore we would suggest this is the format used for compliance,
rather than a further reporting requirement, which would lay more administrative
burden on local authorities.  
The LHEES and energy masterplans could be used to support this work.
178

Page 179

Yes 
No 
Don’t know 
Please include any additional comments below 
Question 27 
Do you agree that the Heat Networks (Scotland) Act 2021 should be amended in light of
the passage of the Energy Act 2023? 
Yes 
No 
Don’t know 
Please include any additional comments below 
Question 28 
Are there any further amendments to the Heat Networks (Scotland) Act 2021 that the
Scottish Government should consider? 
The current target does not capture the ways in which we are performing on heat
decarbonisation and emissions.
We would welcome the UK Energy Act being reflected in the Heat Networks
(Scotland) Act as it includes new consumer protections for heat network consumers.
N/A.
179

Page 180

180