NORTH AYRSHIRE COUNCIL 
23 January 2024 
Cabinet 
Title:    Levelling Up Fund – Round 3 Provisional Award 
Purpose:  To update Cabinet on the provisional UK Government Levelling
Up Fund Round 3 award for the Levelling Up For Ayrshire –
Commercial and Low Carbon Infrastructure project and to seek
approval to complete the validation and onboarding process. 
Recommendation:  That Cabinet:
a) Notes and approves acceptance of the provisional award
for the Levelling Up For Ayrshire – Commercial and Low
Carbon Infrastructure under the Levelling Up Fund
Round 3 subject to the successful completion of the
validation and onboarding process;
b) Approves the proposed amendments to the original
application proposal;
c) Provides delegated authority to the Executive Director
(Place) to conclude the validation and onboarding
process and subject to successful completion, progress
project development and delivery; and
d) Agrees to receive a further update on progress as part of
the annual Regeneration Delivery Plan update report. 
1. Executive Summary 
1.1 On 20 November 2023 the UK Government announced fifty-five projects had been
provisionally selected to receive funding from the Levelling Up Fund Round 3. This
includes £122 million for six projects in Scotland, including the £37.4m Levelling Up for
Ayrshire: Commercial and Low Carbon Infrastructure proposal submitted jointly by
North and South Ayrshire Councils. 
1.2 The third round moves away from the competitive approach of Rounds 1 and 2 and
has seen funding provisionally awarded through a reassessment of high-quality bids
submitted in Round 2. A validation and onboarding process is underway with UK
Government. This is in recognition that bids were submitted in Summer 2022 and as
such, changes to projects may affect deliverability. Until this process is completed, all
funding announced is provisional. 
1.3 This report provides an update on progress, the proposed amendments to the North
Ayrshire elements of the project and seeks approval for the next steps in the project’s
development.

Page 2

2. Background 
2.1 The UK Government’s £4.8 billion Levelling Up Fund (LUF) aims to invest at least
£800 million in Scotland, Wales and Northern Ireland. North Ayrshire was identified as
a ‘priority one’ category authority given our socio-economic and connectivity
challenges. The Fund focusses investment on projects across three themes: town
centre and high street regeneration; local transport projects; and maintaining or
explaining cultural and heritage assets. 
2.2 Applications could be submitted for up to £20 million per authority bid or up to £50
million for a strategic transport project. North Ayrshire successfully secured an award
under Round 1 for the B714 upgrade. In November 2021, Cabinet approved the
development of a Round Two joint bid with South Ayrshire Council alongside the
resubmission of the Lochshore Park proposal. The Levelling Up for Ayrshire:
Commercial and Low Carbon infrastructure bid centred around commercial estate
development and associated low carbon infrastructure in Irvine and around Prestwick
airport. The Lochshore Park bid aimed to accelerate the delivery of Phase 2 to create
an attractive area of parkland with a focus on outdoor play and active lifestyles. 
2.3 Both submissions were unfortunately unsuccessful in Round 2. This was due to
investment being informed by Ministerial consideration of which Local Authorities had
received funding in the first round to maximise the geographical spread of investment.
The Levelling Up for Ayrshire bid was however announced as having been
provisionally selected as receiving funding under Round 3 on 20 November 2023. It
was identified as one of six projects across Scotland receiving £37,456,821 as part of
a total of £122 million investment. 
2.4 The project sought to deliver new energy efficient commercial property and associated
access, active travel and electric vehicle charging infrastructure at key employment
locations. This was comprised of two office pavilions and two speculative flexible
industrial units at three sites in Irvine, North Ayrshire, and a Maintenance, Repair,
Operations (MRO) and aircraft decommissioning hangar at Prestwick Airport, South
Ayrshire. The three Irvine sites proposed were Annickbank, Kyle Road and i3. 
2.5 LUF Round 3 moved away from the competitive approach of Rounds 1 and 2 to an
allocative approach. Funding was provisionally awarded to high-quality bids that were
submitted in Round 2. These have been reassessed using the Round 3 methodology.
UK Government has advised that this change has been made recognising both the
ambition for a simple and streamlined funding landscape illustrated in the Funding
Simplification Plan, and in acknowledgement of the large volume of robustly assessed,
high-quality projects that were not able to be funded at Round 2. 
2.6 Officers within the Council’s Regeneration Services are currently working with
colleagues in South Ayrshire Council and the UK Government to undertake a
validation and onboarding process. This is in recognition that bids were submitted in
Summer 2022 and as such proposals and priorities may have changed. This therefore
may impact on the alignment with LUF priorities and deliverability within the Fund’s
timescales. 
2.7 Initial information was submitted from both Local Authorities on 1 December 2023 and
is currently being assessed by the Department for Levelling Up Housing and

Page 3

Communities (DLUHC). This considers the original proposal and any proposed
amendments we wish to be considered. Any changes need to be within an acceptable
threshold and demonstrate that they can meet the minimum standards on
deliverability. Until this process is completed, all funding remains provisional.
Confirmation is being sought of the timescales for and requirements of this process
from DLUHC. 
2.8 There are no significant changes to the North Ayrshire element of the bid since
submission to Round 2. Two elements of the original submission have however now
commenced through the construction of an office pavilion at Annickbank and Flexible
space at i3. As a result, the following amendments are proposed to the original
proposal: 
• Annickbank: Delivery of additional commercial space suitable for use classes 4
(business), 5 (general industry) and 6 (storage or distribution) is proposed. Rather
than a pavilion, this may be in an alternative format, subject to market feedback. 
• i3: Delivery of additional commercial space suitable for use classes 4 (business), 5
(general industry) and 6 (storage or distribution), aligned with the Ayrshire Growth
Deal (AGD) proposals. 
2.9 Market advice is currently being sought to inform the format of commercial space
proposed at Annickbank. This is being informed by input from the Council’s Business
Support and Development team and feedback from local businesses. Significant
progress has been made at Kyle Road with construction tender information currently
being finalised. Furthermore, the outcome of the funding submission to the Vacant and
Derelict Land Investment Programme (VDLIP) is anticipated in early 2024. 
2.10 The funding window for Round 3 ends in financial year 2025/26. This requires delivery
to commence quickly on the ground. The following risks and uncertainties identified in
the original submission are being reviewed through the validation process. This
includes an updated assessment of the revenue generation potential and implications
of the project: 
• Increased capital costs;
• Delayed timescales for development and build;
• Lower than anticipated demand and uptake from industry;
• The higher value target sectors do not occupy the property;
• External macro-economic shocks;
• Landowner agreements for elements of the active travel provision; and
• Staff resource to support delivery. 
2.11 North Ayrshire Council was identified as the lead applicant for the project. This was
due to the Central Ayrshire constituency crossing the two Authorities’ administrative
boundaries. The LUF requires that in such circumstances one authority takes
responsibility as the lead bidder. Initial governance arrangements were agreed
through the initial submission. These will be reviewed and updated as required
through the validation and on-boarding process with input from both Authorities’ Legal
Services. Full details of the requirements as lead organisation will also be sought from
DLUHC through this process.

Page 4

2.12 The process is ongoing, and subject to approval, Cabinet will be updated when
appropriate during 2024 within the annual update report on the Regeneration Delivery
Plan. 
3. Proposals 
3.1 The Cabinet: 
a) Notes and approves acceptance of the provisional award of £37.5m for the
Levelling Up For Ayrshire – Commercial and Low Carbon Infrastructure under the
Levelling Up Fund Round 3 subject to the successful completion of the validation
and onboarding process;
b) Approves the proposed amendments to the original application proposal;
c) Delegates authority to the Executive Director Place to conclude the validation and
onboarding process and subject to successful completion, progress project
development and delivery; and
d) Agrees to receive a further update on progress as part of the annual Regeneration
Delivery Plan update report. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Council requires to provide a minimum of 10% match funding to support all LUF
bids. It is intended that the North Ayrshire match funding for this proposal will be
incorporated in the Council’s capital planning. Further external funding sources will
also be explored where possible. This is currently estimated at £2,129,000 however
the final match funding value and sources will be established through the validation
process. South Ayrshire Council will also be required to meet their 10% match funding
contribution separately. 
The Levelling Up Fund provides Capital investment and small scale revenue support
to build capacity during project development. Whilst resource costs can be capitalised
to support delivery, future ongoing revenue implications will require to be fully
considered. 
Human Resources 
4.2 It is expected that there will be staffing requirements to develop and deliver the
project. The estimated cost of this was included within the original LUF application.
Subject to the successful outcome of the validation process, recruitment and
appointments would take place in accordance with the Council’s procedures. 
Legal 
4.3 North Ayrshire Council was identified as the lead applicant for the project. Initial
governance arrangements were prepared and agreed through the submission. These
will be reviewed and updated as required with input from Legal Services. Subject to a
successful validation process, landowner negotiations and agreements will be
required for elements of the active travel infrastructure within the project.

Page 5

Equality/Socio-economic 
4.4 The project will assist in meeting our socio-economic duty as set out in the Fairer
Scotland Duty. It seeks to reverse economic, social and physical decline and reduce
socio-economic disadvantage. It aims to build community wealth and tackle local
deprivation through the regeneration of our communities by maximising the potential
of our land and assets. It will tackle long term vacant and derelict land bringing it back
into positive use thereby reducing the level and impact on local communities and
supporting economic development. 
Climate Change and Carbon 
4.5 The project aligns with the Sustainable North Ayrshire Strategy through the delivery of
low carbon infrastructure. It will also transform vacant and derelict land into vibrant
places and quality commercial space which supports employment and the economy,
and that local people can be proud of. 
Key Priorities 
4.6 The project will contribute to achieving a wide range of the Council Plan outcomes. It
will contribute towards achieving our Council priorities of wellbeing, communities and
local democracy, and Climate Change. It will accelerate the delivery of a range of
actions identified in the Regeneration Delivery Plan and contribute to the delivery of
the Vacant and Derelict Land Strategy and Local Transport and Active Travel Strategy
priorities. 
Community Wealth Building 
4.7 The project will contribute to Community Wealth Building and will have a significant
positive impact on Council’s ambitions under the Land and Assets pillar. 
• Procurement: Local supply chain opportunities will be created through the project.
For future procurement exercises related to the project, the Business Development
team will review opportunities for the North Ayrshire business base and provide
supplier development support as required.
• Fair Employment: The project will create employment opportunities particularly
within the construction sector. Where North Ayrshire is the contractor for services,
through our enhanced Community Benefits approach we will ensure the creation of
local training and work experience opportunities.
• Land and Assets: The project will regenerate sites which are long term vacant and
derelict land and identified as priorities for investment. This will bring underutilised
land into positive use to support local social, economic and environmental
wellbeing.
• Financial Power: The project will invest in localities and leverage external national
investment into North Ayrshire.
• Plural Ownership: The project will create commercial space to support local
businesses to stay and grow in North Ayrshire.

Page 6

5. Consultation 
5.1 The project has been informed by the Regeneration Delivery Plan (RDP). The RDP
sets out the Council’s priorities for regeneration over the next five years. The RDP was
subject to extensive consultation including workshops with Council Officers;
workshops with Elected Members; reports to and feedback from North Ayrshire
Ventures Trust and the Community Wealth Building Expert Panel; and public
engagement via Consul. It was also informed by the Locality Partnerships’ priorities. 
5.2 Support was obtained from the local MP for the constituency covered by the
application for the original submission. Confirmation of continued support will be
sought when the proposals for both Authorities are confirmed. 
5.3 An update on the project will be provided to the January Irvine Locality Partnership
meeting. Further consultation and engagement will be undertaken with local
communities and stakeholders on the detailed design for the constituent elements of
the projects as appropriate, subject to the outcome of the validation process. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Claire Fitzsimmons, Interim Senior Manager -
Regeneration, on 01294 315305. 
Background Papers
Cabinet Report: Regeneration Delivery Plan, 23 March 2021
Cabinet Report: Levelling Up Fund, 15 June 2021
Cabinet Report: Levelling Up Fund – Round 2, 2 November 2021
Cabinet Report: Regeneration Delivery Plan Action Programme, 30 May 2023