NORTH AYRSHIRE COUNCIL  
29th August 2023 
Cabinet
Title:
Proposals for Community Investment Fund (CIF)
Expenditure
Purpose: To determine applications by Locality Partnerships to allocate
CIF funding to proposed projects. 
Recommendation: That Cabinet: 
a) Reviews the enclosed applications from the Arran, Three
Towns and Kilwinning Locality Partnerships in line with CIF
criteria;
b) Approves the CIF application in relation to Arran Geopark;
c) Approves the CIF application in relation to Saltcoats Active
Lifestyle Team (SALT) ; and
d) Approves the CIF application in relation to the Corra
Foundation. 
1. Executive Summary 
1.1 Within its budget for 2017-18, North Ayrshire Council provided a funding allocation for
the creation of an innovative fund to enable communities to address the priorities they
have identified though Locality Planning Partnerships and within the context of North
Ayrshire Community Planning Partnership’s Fair for All Strategy and the Council’s
Community Wealth Building Strategy. In June 2021, Cabinet approved a further £1m
top-up for the funding, with a further £2m added in November 2021. 
1.2 Locality Partnerships have subsequently continued to work on their local action plans
and are refining proposals for expenditure in line with their locally identified needs. This
is a difficult process, and it is a testament to the dedication of the Locality Partnerships
and their community partners that proposals are now emerging to provide creative
approaches to addressing local challenges. 
1.3 This report brings forward proposals which respond to the specific need of the local
community, and which have been developed based on local circumstances and
opportunities. 
1.4 These proposals have been approved to be submitted to Cabinet through a process of
collaboration and consensus by the Locality Partnerships.

Page 2

2. Background 
2.1  Within its budget for 2017-18, North Ayrshire Council provided an allocation for the
creation of an innovative fund to enable communities to address the priorities they have
identified though Locality Planning Partnerships and within the context of North Ayrshire
Community Planning Partnership’s Fair for All Strategy and the Council’s Community
Wealth Building Strategy. A further £3m was added to the funding in 2021, to be
distributed among Localities as follows: 
2.2 It was agreed that the CIF awards range between £5,000 and £100,000 for the
community organisations, as defined in the CIF guidance, in order to support proposals
and projects that connect with: 
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis;
• The Community Planning Partnership and Locality priorities; 
• North Ayrshire Council’s values, priorities, and business objectives;
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies; 
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of
people possible;
• Exhibit project and/or organisational innovation in their approaches to their work
in their way of addressing community challenges and in their request to Locality
Partnerships and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can
include an organisation to be created to deliver the project; 
Locality Value of CIF
from first
funding
allocation
(2017-18)
Expenditure
to date
Value of CIF
from
second
funding
allocation
(June
2021)
Value of CIF
from third
funding
allocation
(Nov
2021)
Total balance
available
Irvine £754 000 £558 435 £290 000 £580 000 £1 065 565
Kilwinning £286 000 £286 190 £120 000 £240 000 £359 810
Three
Towns
£598 000 £861 973  £240 000 £480 000 £456, 027
Garnock
Valley
£390 000 £341 805 £150 000 £300 000 £498 195
North
Coast
£468 000 £429 066 £170 000 £340 000 £548 934
Arran £104 000 £45 226 £30 000 £60 000 £148 774
TOTAL £2 600 000 £2 522 695 £1 000 000 £2 000 000 £3 077 305

Page 3

• Include options or potential for NAC and CPP employee engagement and
volunteering where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular
basis. 
2.3   The proposal development and application process has been agreed as follows: 
• Locality Partnerships should continue to engage with their communities and
stimulate interest in the CIF. Each Locality Partnership will then strategically
assess the applications, make links, and look at the funding ‘in the round.’
• If the partnership supports a bid then the group will be encouraged to submit a
full application form, which they will decide upon before making a proposal to
Cabinet for final approval. 
• The proposal will go to the next suitable Cabinet for final approval. 
2.4  The enclosed applications have been developed by community partners and North
Ayrshire Council officers and are now recommended for approval by Cabinet. The
proposals are as follows: 
2.5 The Arran Locality Partnership 
The allocations and funds committed to date are outlined in the table below. 
The Arran Locality Partnership CIF
allocation to date: 
£194,000
Arran Youth Foundation and Arran High
Joint Bid - Young People's Mental Health
£45,226 
Balance  £148,774 
2.6 Proposal: Arran Geopark (£79,853) (See Appendix 1) 
2.6.1 Arran Geopark are seeking funding to appoint a Project Director who will develop
and implement the Geopark’s management plan, which is aligned with the Local
Island plan. The aim within the two-year project period is to gain UNESCO Global
Geopark status for the whole of the Isle of Arran. 
There are two proposed stages with funding only being released when the milestone
is passed: 
• Stage 1 – submission and management of the UNESCO application process,
including desktop and field assessment. A milestone for the project will occur when
notification is received (late 2024) from UNESCO that the application is successful or
if a decision is deferred, requiring further information; 
• Stage 2 – responding to UNESCO’s recommendations, which will be given if the
application is successful or deferred. An “improvement report” will be submitted to
UNESCO if the application is deferred. 
2.6.2 If the application is unsuccessful at stage 1, the stage 2 funding will not be released.
Stage 1 funding amounts to £40,291 and stage 2 would be a further £39,562. 
2.6.3 UNESCO Global Geopark status would act as a catalyst to drive diverse benefits to

Page 4

the island’s community, environment, and economy with a particular focus on the
following groups: 
• Local people and visitors will benefit from an increased understanding and
appreciation of the island's heritage.
• Visitors from new geographical areas and backgrounds will be enticed to visit by the
increased visibility provided by the UNESCO designation.
• Local businesses will benefit as a result of the global platform afforded by the
UNESCO designation. This will be true for local service providers as well as
producers/exporters.
• Young people (e.g. from local and visiting schools) will benefit through the Geopark’s
outreach programme and educational resources. 
2.6.4 The project would particularly support the locality priority of reducing social isolation
by providing residents with a deeper sense of belonging and pride in their island
and its heritage, and offering volunteering opportunities, as well as providing young 
people in particular with enhanced knowledge of their local environment. It would 
also support community wealth building aspirations by encouraging visitors to the 
island and increasing the potential for local businesses to generate income. 
2.7 The Three Towns Locality Partnership 
The allocation and funds committed to date are outlined in the table below. 
The Three Towns Locality Partnership CIF
allocation to date: 
£1,318,000
Ardrossan Community Development Trust   £25,000 
Three Towns Growers £100,000 
The Training Station £50,000 
Ardrossan Castle Heritage Society £17,912 
Raise Your Voice For Ardeer   £100,000 
Ardrossan Community Sports Hub   £43,320 
Winton Circus Playpark   £48,288 
Ardrossan Community Development Trust -
Development Officer   £53,100 
Raise Your Voice For Ardeer – increased cost
for multipurpose hub) £130,000 
Ardrossan Community Association (Whitlees)  £48,586 
Ardrossan Community Sport - Winton Park 3G £100,000 
CHAP – Advice Outreach 
£45,767 
Ardrossan Scouts  £100,000 
Balance £456, 027 
2.8 Proposal: Saltcoats Active Lifestyle Group (SALT) (£45,600) (see Appendix 2) 
2.8.1 SALT is a constituted voluntary community organisation which was
established in August 2021.Their aims and objectives are to advance
the emotional and physical wellbeing of the inhabitants of Saltcoats

Page 5

through the provision and regeneration of such facilities which enable
this. 
2.8.2 They have recently successfully completed the upgrade and
regeneration of the local playpark and secured the total funding
package of over £100,000. This has led to a safe space for the
provision and development of play for the children and young people
of the town. 
2.8.3 SALT are looking to install CCTV adjacent to the playpark to safeguard
the facilities and create a safe space where children, young people
and adults come together to enjoy the playpark. Recent survey
analysis has concluded that the installation of CCTV would create a
greater sense of community safety and lead to increased use of the
park. The project will be delivered in partnership with NAC and the
SALT group. Once the camera is in place NAC will add this to their
existing network and monitor the area.  The SALT CCTV has been
able to be included in the Council’s system on this occasion only due
to the availability of a licence which was freed up from another site. 
2.8.4 The project supports the delivery of the 3 Towns locality partnership
priorities, promoting the local economy and tourism and regenerating
community facilities by providing a safe and attractive play area,
increasing civic pride and community engagement by reducing anti-
social behavior and improving community wellbeing by helping
residents feel safer and encouraging children and families to be active
outdoors. 
2.9 Kilwinning Locality Partnership 
The allocation and funds committed to date are outlined in the table below. 
The Kilwinning Locality Partnership CIF
allocation to date: 
£646 000
Kilwinning McGavin Park  £35 000
Multi-Purpose Youth and Community Hub  £41 190
Multi-Purpose Youth and Community Hub –
Phase 2 £15,000 
Kilwinning McGavin Park – Phase 3  £45,000
Almswell Park Pitch replacement  £45,000
Corsehill Playpark  £50,000
Kilwinning Tennis Club £55,000
Balance  £359,810 
2.10 Proposal: The Corra Foundation (£36,000) (see Appendix 3) 
2.10.1. Corra Foundation exists to make a difference to the lives of people and communities.
It works with others to encourage positive change, opportunity, fairness, and growth
of aspirations which improve quality of life. Corra wants to see a society in which
people create positive change and enjoy fulfilling lives.

Page 6

2.10.2. Since 2016 Corra and North Ayrshire Council have been working in partnership
alongside the community of Blacklands.  This long-term work has supported strong
connections to be built and established a firm foundation of increased confidence,
capacity, and community-led action. This partnership has been underpinned by a
simple pledge designed to support, what was then, a new way of working alongside
communities.   
2.10.3 Corra plan to build their ongoing work in Blacklands around three key elements: 
• Priorities – we know that communities’ priorities are changing and can offer a
supportive space to explore, define and articulate them.
• Plans – supporting communities to set out their priorities and actions to achieve them
in a ‘community-owned’ plan.
• Partnerships – connecting with partners who can help to produce the plan and/or
help deliver on community priorities. 
2.10.4 Corra see their role within North Ayrshire as integral to supporting community
members in Blacklands to be aware of the Locality Plan, engage in the structures and
processes and help shape the evolution of the plan and priorities to recognise community
need. This will involve supporting community members to develop confidence and
capacity to deliver and lead on activity that directly contributes to the priorities identified. 
2.10.5 The requested funding would contribute to the overall running costs of the People in
Place project over the next three years and see a strengthening of the relationship that
already exists between Corra, North Ayrshire Council and the Kilwinning Locality
Partnership. 
2.10.6 Getting Alongside Communities will directly contribute to the Kilwinning Locality
Priorities of supporting skills and work, alleviating poverty and promoting equality of
access to opportunities, improving community wellbeing, and building strong
communities. As community confidence and capacity to grow in terms of participating in
locality planning structures and providing their ideas, there is also potential to make a
more significant contribution to the priority of ‘Improving our local environment’ which has
been a feature of some smaller scale local action to date. 
3. Proposals 
That Cabinet: 
a) Reviews the enclosed applications from the Three Towns and Kilwinning Locality
Partnerships in line with CIF criteria;
b) Approves the CIF application in relation to Saltcoats Active Lifestyle Team (SALT) ;
and
c) Approves the CIF application in relation to the Corra Foundation.

Page 7

4. Implications/Socio-economic Duty
Financial
4.1 CIF funding is allocated within existing resources. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 The purpose of Locality Planning is to reduce inequalities, increase community
cohesion and advance community empowerment. Each of the CIF proposals is tested
against that purpose before being presented to Cabinet. 
Climate Change and Carbon 
4.5 Environmental and sustainability along with Climate Change and Carbon issues are
considered in relation to each CIF application. 
Key Priorities 
4.6 The proposals contained within the report support the North Ayrshire Council Plan
priorities:
• Active and strong communities
• Inclusive, growing, and enterprising local economy
• People enjoy good life-long health and wellbeing.   
Community Wealth Building 
4.7 The applications support the following pillars of community wealth building:
• Advancing community enterprises;
• Advancing local ownership of underused land and buildings;
• Making financial power work for local places; and 
• Supporting local business activities and increasing the variety of ownership
models. 
5 Consultation 
5.1  The proposals contained within this report have been developed by the Locality  
Partnerships, through consultation with local people, including young people.

Page 8

Audrey Sutton
Executive Director (Communities & Education)
For further information please contact Rhonda Leith,  Head of Service (Connected
Communities), on (01294) 324415. 
Background Papers
Appendix 1: CIF Application: Arran Geopark
Appendix 2: CIF Application: Saltcoats Active Lifestyle Group (SALT)
Appendix 3: CIF Application: The Corra Foundation

Page 9

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
The CIF will support proposals and projects that:
• Connect with:
o The North Ayrshire Fair for All Inequalities Strategy;
o the Community Planning Partnership (CPP) and Locality priorities; and
o North Ayrshire Council’s (NAC) values, priorities and business objectives.
• Fulfil a compelling need and do not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of people
possible;
• Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project;
• Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular basis.
When to apply and how?
• LPs should continue to engage with their communities, and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval.
• The finalised proposal will go to the next suitable Cabinet for final approval.
• Forms should be returned to your Locality Officer, by email if possible:
Anne-Marie Hunter
Engagement and Participation Officer
North Ayrshire Council
Connected Communities
2nd Floor (West)
Cunninghame House
Irvine
KA12 8EE
Email: Anne-MarieHunter@north-ayrshire.gov.uk
Tel: 01294 324706
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf
Appendix 1

Page 10

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP 
1. Details of your organisation 
Name of Organisation 
Arran Geopark 
Postal Address for Correspondence
Click or tap here to enter text. 
Name of Contact Person Malcolm Wilkinson 
Position in Organisation Coordinator 
Telephone Number Click or tap here to enter text. 
Email Address Click or tap here to enter text. 
2. Brief description of your organisation 
Please include its legal status, aims and objectives, activities or services provided
and how long it has been in existence. 
Arran Geopark is managed by the Arran Access Trust (charity no. SC029027) and
the project has been in existence since 2017. We are in the process of forming a
separate SCIO. 
Arran Geopark’s vision is that “our environment and heritage are conserved,
enhanced, and valued for their contribution to people’s well-being and Arran’s
sustainability”. We aim to achieve this by: 
• Increasing understanding and appreciation of our remarkable environment and
heritage to local people and to visitors.
• Supporting sustainable local economic development through education,
interpretation, practical conservation work, and nature-based tourism.
• Collaborating with communities, businesses, and other local stakeholders who
share our vision.
• Provide opportunities for all to contribute to enhancing Arran’s environment
through a programme of volunteering, thereby increasing participants mental and
physical wellbeing. 
We see the UNESCO status as a catalyst to drive diverse benefits to our island’s
community, environment, and economy.

Page 11

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
3. Title and summary of proposal 
Tell us about your idea. Please describe in as much detail as possible, what the
funding will be used for. 
Please include: 
• where it will be held / delivered
• who is your target audience
• who will benefit from it and how
• any partners that are involved. 
We are seeking funding to appoint a Project Director who will develop and implement
the Geopark’s management plan, which is aligned with the Local Island plan. The
aim within the two-year project period is to gain UNESCO Global Geopark status for
the whole of the Isle of Arran. There are two proposed stages with funding only being
released when the milestone is passed: 
• Stage 1 – submission and management of the UNESCO application process,
including desktop and field assessment; 
o Milestone - notification is received (late 2024) from UNESCO that are
application is successful or if a decision is deferred, requiring further
information; 
o If application is rejected, Stage 2 funding will not be released. 
• Stage 2 – responding to UNESCO’s recommendations, which will be given if
the application is successful or deferred. An “improvement report” will be
submitted to UNESCO if the application is deferred. 
Where it will be held / delivered? 
The project, and the boundary of the proposed UNESCO Global Geopark, will cover
the entire area of the Isle of Arran (inclusive of Holy Isle and Pladda). This is an area
of almost 800 square kilometres and it includes the entirety of the South Arran
Marine Protected Area and No Take Zone. 
Who is your target audience? 
Our target audience is both local people and visitors to the island. 
Who will benefit from it and how?

Page 12

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP 
Gaining UNESCO Global Geopark status will act as a catalyst to drive diverse
benefits to our island’s community, environment, and economy – with a particular
focus on the following groups: 
• Local people and visitors will benefit from an increased understanding and
appreciation of the island's heritage.
• Visitors from new geographical areas and backgrounds will be enticed to visit
by the increased visibility provided by the UNESCO designation.
• Local businesses will benefit as a result of the global platform afforded by the
UNESCO designation. This will be true for local service providers as well as
producers/exporters.
• Young people (e.g. from local and visiting schools) will benefit through the
Geopark’s outreach programme and educational resources. 
Project partners 
Arran Geopark’s growing board is comprised of representatives of the following
organisations: 
• Arran Access Trust;
• Arran Community Council;
• Community of Arran Seabed Trust (COAST);
• Lochranza Centre CIC;
• National Trust for Scotland;
• VisitArran; and
• Community representatives. 
We have received or continue to receive funding from the following organisations,
who we work closely with: 
• Arran Trust;
• NatureScot; and
• North Ayrshire Council.

Page 13

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
4. What difference will this project make within the locality and to local
services and programmes? 
Please include: 
• The outcomes you aim to achieve
• How you will approach reducing inequality
• How this proposal fits with Communities, Economy and Environment. 
We are seeking funding to appoint a Project Director who will implement the
Geopark’s management plan, which is aligned with the Local Island plan, and aims
to gain UNESCO Global Geopark status for the island. 
The Geopark’s work, over this crucial two-year period, will tackle the following Island
Plan themes: 
● Community:
o Opportunities for practical conservation work;
o Increased mental and physical health through volunteering and outdoor
activities;
o Increased understanding & appreciation of natural heritage, amongst
residents young and old;
o Inclusion: reach out to more vulnerable groups to engage them in their
local environment; and
o Provide a forum for local representatives from land managers, tourism,
community groups and economic groups to discuss issues relating to the
environment and develop island-wide solutions to visitor management and
mitigate impacts. 
● Environment:
o Education and awareness of our natural environment and the human
impacts on it;
o Engage with the island community to develop local solutions for climate
change mitigation and adaptation;
o Support and monitor local efforts towards the Sustainable Development
Goals;
o Enhance the local environment through conservation programmes aimed
at increasing biodiversity and reducing the impact of visitors on our
landscape; and
o Develop partnerships with Universities and Colleges to encourage the use
of our island resource for research and furthering our understanding of the
island and its environment.

Page 14

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
● Economy:
o Gain international exposure, benefiting local businesses both through
tourism and increased exports; and
o Work with partners to develop a sustainable tourism strategy and to
provide opportunities to increase visitor stay duration and spend. 
Longer term sustainability is at the core of the proposal. We will seek new and
innovative funding streams to ensure the Geopark can continue to operate
indefinitely; such as commercial sponsorship, memberships and supporter fees. We
will also lobby with partners across Scotland to secure Scottish Government core
funding for the nation’s UNESCO sites. 
The success of the project will be measured and reported using a range of specific
and measurable goals – these are outlined in Question 8, below. 
How does proposal seek to reduce island inequalities? 
● Inclusion of a wide spectrum of groups through education and practical activities;
● Outreach to all ages enabling them to participate in volunteering and/or
educational experiences; and
● Development of a Geopark Community Liaison Group where all aspects of the
island’s society is represented and where solutions to issues can be developed.

Page 15

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
5. What engagement has taken place in relation to the project? 
Please include the number of people who have been engaged with or consulted as
well as the range of people. 
Due to the partnership structure of the Geopark, where representatives of various
local community groups sit on the board, community consultation has been an
intrinsic part of the organisation since it was formed in 2017. 
In addition to the membership of the board, project staff and board members have
engaged with the following groups and representative of these groups: 
● Archaeology Scotland
● Arran Community Council
● Arran Distillers
● Arran Eco Savvy
● Arran Estates
● Arran Farmers’ Show
● Arran Heritage Museum
● Arran Natural History Society
● Arran Trust
● Community of Arran Seabed Trust (COAST)
● Dougarie Estate
● Drumadoon Estate
● European Geoparks Network
● Forestry and Land Scotland
● Foundation Scotland
● Local outdoor activity providers
● NAC Islands Plan Working Group
● National Trust for Scotland
● NatureScot
● North Ayrshire Council
● Scottish Geology Trust
● Taste of Arran
● UK Geoparks Network
● UNESCO
● VisitArran
● VisitScotland

Page 16

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
6. How will the project be managed? 
Please include: 
• How the finances will be managed 
• Does the proposed project contribute to volunteering or employment
opportunities on Arran? Please include the number of volunteering
opportunities and employment opportunities
• If there are any staff requirements, please outline your HR plans 
The following chart shows the proposed management structure of Arran Geopark
and where the Project Director role fits in (circled in red): 
How the finances will be managed? 
Finances will be managed by the Geopark’s treasurer in close cooperation with other
board members and project staff. Two signatories will be required to make
withdrawals from the account. We have included fees for a bookkeeper to reduce
staff admin time and to ensure that the charity is meeting its regulatory requirements.

Page 17

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP 
Does the proposed project contribute to volunteering or employment opportunities on
Arran? 
Volunteering opportunities are integral to the Geopark’s management structure and
operations and are split between three distinct areas: 
• Community Liaison Group,
• Working Groups, and
• Practical outdoor work meets. 
A Community Liaison Group is to be formed to inform the Geoparks overall strategy
and delivery. This is an open invitation for local people to get involved and ensure
that they have a strong voice in the overall vision of Arran Geopark. This is
particularly important as all Geoparks are “grass roots” community-led organisations. 
Working Groups are to be formed in order to serve particular functions of the
Geopark (see organisation chart, above). There groups are to be formed largely of
volunteers and to be managed by Geopark staff. 
Practical outdoor work meets have been in action for several years now. These
popular activities have involved path maintenance, beach cleans, non-native species
work and installing/maintaining footpath and information boards. 
Providing employment opportunities is also a key part of the Geopark’s work. The
key aim of Geoparks is to encourage sustainable economic growth while protecting
and conserving natural heritage. Indeed, the motto of UNESCO Global Geoparks is
"Celebrating Earth Heritage, Sustaining Local Communities". 
Encouraging new high growth markets (identified by VisitScotland) of “localism”,
“authentic experiences”, and “voluntourism” are key to the Geopark’s vision of a
diverse island economy. 
Since its inception in 2017, Arran Geopark has employed a variety of staff including
rangers, educators, a path maintenance team, and apprenticeship scheme. Our
NatureScot funded Ranger Service is now in its third year of operation. We look
forward to continuing this work. 
Outline of HR plans 
To ensure the best candidate is recruited for the post, it will be advertised locally and
nationally (e.g. Arran Banner, Countryside Jobs Service, EnvironmentJob.co.uk, etc).

Page 18

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
Arran Geopark has equality and equal opportunities policies, available on request. 
7. Amount of funding being requested 
Please supply details of funding being requested and any other funding you have
had over the past 5 years, both financially and “in kind”. 
Amount of funding requested (£) 79,853 
Please give a breakdown of cost and recent quotations where appropriate. 
Costs Stage 1 Stage 2 TOTAL
Salary @ 0.8 FTE  £        24,000   £        24,960  
Pension & NICs  £          2,816   £          2,928  
Office & utilities  £          5,000   £          5,200  
Conference fees, travel &
accommodation  £          1,750   £          1,820  
UNESCO assessment (assessors'
travel, accommodation & expenses)  £          3,500   £                -    
European Geoparks Network
membership annual fee (€1,500)  £                -     £          1,300  
Other travel & expenses  £             450   £             468  
Bookkeeping & charity administration  £          1,250   £          1,300  
Insurance  £             875   £             910  
Training & development  £             350   £             364  
Website  £             300   £             312  
TOTALS  £        40,291   £        39,562   £        79,853 
The following table lists the total funds (both restricted and unrestricted) received by
the Arran Access Trust over the last 5 years: 
Year Total funds Funding source (only funders >£1k listed)
2017  £   78,335.00  Coastal Communities Fund
2018  £ 117,688.00  Coastal Communities Fund, NatureScot
2019  £ 143,824.00  Coastal Communities Fund, NatureScot, Arran Trust, Betty and Roy Ure Trust
2020  £   36,809.00  Coastal Communities Fund, Betty and Roy Ure Trust
2021  £   25,173.00  NatureScot, Betty and Roy Ure Trust, Betty and Roy Ure Trust
2022  £   19,565.00  NatureScot, North Ayrshire Council, Arran Trust, Betty and Roy Ure Trust
2023  TBC  NatureScot, North Ayrshire Council, Betty and Roy Ure Trust

Page 19

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP 
We have recently received project funding from NatureScot for two seasonal Island
Rangers (£25,428) and Heritage and Culture funding from NAC (£40,000). We have
no outstanding grant applications with other funding bodies.

Page 20

COMMUNITY INVESTMENT FUND
ARRAN LOCALITY PARTNERSHIP
8. Monitoring and evaluation process 
Please include detail on the monitoring and evaluation processes planned or in
place. 
The project will be managed by the Project Director who reports to the Arran
Geopark board. This will be done at project meetings, board meetings and by weekly
email updates. Project spend and projected spending will be included in the weekly
reports. A summary of the above will be provided to the Locality Partnership, in time
for its scheduled meetings. 
The success of the project will be measured and reported using the following
outcomes: 
● Gaining UNESCO Global Geopark status (staged approach to funding);
● Securing long-term funding;
● Number of business partners sign-ups;
● Number of volunteer hours logged;
● Number of inclusion groups engaged with;
● Number of participants in education/outreach activties;
● Number of school groups visiting Arran;
● Number of university groups visiting Arran;
● Social media reach; 
Longer term indicators in the success of UNESCO Global Geopark status are likely
to be:
● Increase in the average stay time of visitors; and
● Increase in the average spend of visitors.

Page 21

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
The CIF will support proposals and projects that:
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis.
• The Community Planning Partnership and Locality priorities.
• North Ayrshire Council’s values, priorities, and business objectives.
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies.
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities.
• Provide long-term, sustainable, positive results for the greatest number of people
possible.
• Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council.
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project.
• Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular basis.
When to apply and how?
• LPs should continue to engage with their communities and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval.
• The finalised proposal will go to the next suitable Cabinet for final approval.
• Forms should be returned to your Locality Officer, by email if possible:
Name Colin Ferris
Locality Officer (Three Towns Locality)
North Ayrshire Council
St John’s Primary School
Morrison Avenue
Stevenston
KA20 4HH
Email: colinferris@north-ayrshire.gov.uk
Tel: 475912/212
Mob: 0758461250
Appendix 2

Page 22

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP 
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf 
1. Details of your organisation 
Name of Organisation 
Saltcoats Active Lifestyles Team (SALT 
Postal Address for Correspondence 
Position in Organisation 
Donna McGregor Chairperson 
Telephone Number Click or tap here to enter text. 
Email Address 
2. Brief description of your organisation 
SALT is a constituted voluntary community organisation which was established in
August 2021. 
Our aims and objectives are to advance the emotional and physical wellbeing of the
inhabitants of Saltcoats through the provision and regeneration of such facilities
which enable this. 
We have recently successfully completed the upgrade and regeneration of the local
playpark and secured the total funding package of over £100,000. This has led to a
safe space for the provision and development of play for the children and young
people of the town.

Page 23

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
3. Title and summary of proposal 
We are looking to install CCTV adjacent to the playpark to safeguard the facilities
and create a safe space where children, young people and adults come together to
enjoy the playpark.   
Our recent survey analysis has concluded that the installation of CCTV would create
a greater sense of community safety and lead to increased use of the park. 
The project will be delivered in partnership with NAC and the SALT group. Once the
camera is in place NAC will add this to their existing network and monitor the area. 
.
4. What difference will this project make within the locality and to local
services and programmes? 
The installation of a CCTV camera adjacent to the park will have the following
benefits: 
• Reduction in crime i.e vandalism and anti-social behaviour
• Protect and safeguard community assets which would otherwise be expensive
to repair/replace.
• Greater use of the playpark as sense of community safety increases
• NAC are a key partner in the delivery of this project. 
The 3 Towns locality partnership priorities which will be met are as follows: 
• Promoting the local economy and tourism
• Regenerating Community Facilities
• Increasing civic pride and community engagement
• Improving community wellbeing 
The successful development of the playpark has had a positive impact on all of the
above and this will be further enhanced with the addition of CCTV.

Page 24

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
5. What engagement has taken place in relation to the project? 
We have success delivered a community consultation event at Winton Circus
playpark with 600 residents. There was overwhelming support for our CCTV initiative
with almost no negative responses. 
In addition, online surveys with local residents have also been carried out which
further support the need for CCTV. 
6. How will the project be managed 
The finances for the project will be managed by our voluntary management
committee. Our financial procedures ensure the efficient and safe management of
funds. 
Whilst this project does not directly create any specific paid employment
opportunities there is the opportunity to volunteer and join the voluntary management
committee and get involved in future projects. 
There is also the opportunity for local young people and children’s organisation who
are more likely to use the facilities as their concerns around safety will be somewhat
be alleviated with the installation of CCTV. 
7. Amount of funding being requested 
Please supply details of funding being requested and any other funding you have
had over the past 5 years, both financially and “in kind”. 
To date in excess of £100,000 has been secured for the successful development of
the playpark. 
Amount of funding requested (£)  - £45,600 
These are the costs to purchase and install a CCTV camera adjacent to the playpark
provided by Graham Emans (Co-ordinator Homeless and Community Safety)

Page 25

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
8. Monitoring and evaluation process 
Monitoring will be carried out by NAC as the new CCTV camera will be added to
their existing network and be monitored directly by trained staff who understand the
legislative and legal requirements around the use of CCTV 
The data from crime stats will provide evidence on the impact of the camera and its
success. 
The SALT group will carry out further community consultation after the installation of
the camera to look at the impact of the camera on user numbers of the parky and the
sense of security and safety which has resulted.

Page 26

COMMUNITY INVESTMENT FUND
KILWINNING LOCALITY PARTNERSHIP
The CIF will support proposals and projects that:
• Connect with:
o The North Ayrshire Fair for All Inequalities Strategy;
o the Community Planning Partnership (CPP) and Locality priorities; and
o North Ayrshire Council’s (NAC) values, priorities and business objectives.
• Fulfil a compelling need and do not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of people
possible;
• Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project;
• Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular basis.
When to apply and how?
• LPs should continue to engage with their communities, and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval.
• The finalised proposal will go to the next suitable Cabinet for final approval.
• Forms should be returned to your Locality Officer, by email if possible:
Louise Riddex
Locality Officer (Kilwinning & North Coast)
Economy and Communities
Community Development Team
St John's Primary School
Morrison Avenue
Stevenston
KA20 4HH
Email: lriddex@north-ayrshire.gov.uk
Tel: 01294475913
Mob: 07980964858
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf
Appendix 3

Page 27

COMMUNITY INVESTMENT FUND
KILWINNING LOCALITY PARTNERSHIP
1. Details of your organisation
Name of Organisation
Corra Foundation
Postal Address for Correspondence 
Name of Contact Person: Gordon McLean
Position in Organisation: National Programme Manager
Telephone Number:  
Email Address:
2. Brief description of your organisation
Please include its legal status, aims and objectives, activities or services provided
and how long it has been in existence.
Corra Foundation is a charity registered in Scotland (No SC009481) and is also a
company limited by guarantee (No SC096068). The organisation was previously
known as Lloyd’s TSB Foundation for Scotland from 1985 until it rebranded as Corra
in 2018.
Corra Foundation exists to make a difference to the lives of people and communities.
It works with others to encourage positive change, opportunity, fairness and growth
of aspirations which improve quality of life. Corra wants to see a society in which
people create positive change and enjoy fulfilling lives.
Corra achieves this through grantmaking and its place-based programme of which
Getting Alongside Communities is a key part.
In 2020 Corra launched a ten-year strategy. It is long term because making a
different on the big challenges will take time. At its heart is the strong belief that
when people find their voice, they unlock the power to make change happen.
www.corra.scot

Page 28

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
About Getting Alongside Communities 
Established in 2015, as part of Corra’s People in Place programme, Getting
Alongside Communities is currently working alongside eight communities across
seven Scottish local authority areas, supporting local people to connect, collaborate
on ideas, and take action to create positive change. 
The community is at the heart of everything we do.  Each community we work
alongside has a dedicated Community Co-ordinator whose long-term relational
approach - based on listening, bringing people together for conversations, and
helping to identify shared priorities – has established deep knowledge, trust and
connections with local people and partners. 
The approach is designed to help facilitate and enable capacity building within the
community; widening community participation, seeking out voices that are seldom
heard; and ultimately resulting in locally-led actions being taken. 
The ambition for each community is set by the people in that place. Corra’s
commitment is to help create the conditions and connections needed for bold change
to happen. 
3. Title and summary of proposal 
Tell us about your idea. Please describe in as much detail as possible, what the
funding will be used for. 
Please include: 
• where it will be held / delivered
• who is your target audience
• who will benefit from it and how
• any partners that are involved. 
Getting Alongside Communities: Blacklands 
The proposal is for a partnership funding contribution towards the continued delivery
of the Getting Alongside Communities programme in Blacklands for a three-year
period between 2023 and 2026.   
The work builds upon the community capacity that has been developed since Corra’s
partnership with North Ayrshire Council began in 2016, and will focus on increasing

Page 29

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
the sustainability of community initiatives through the development of local capacity,
infrastructure and connections with wider structures, including Locality Planning. 
Since 2016 People in Place has invested £235k directly into the work alongside
Blacklands. In addition, Corra’s local knowledge and trusting relationships have
connected local groups with other funding sources, including £46k to support
pandemic response work. 
During that time the programme has:
• Supported 13 community ideas into action 
• Engaged over 538 people 
• Benefitted from 587 hours of volunteering 
• Partnered with Council colleagues to support community and strategic
development
• Created opportunities for communites and colleagues to share learning, ideas
and amplify community voices at a national level. 
Some notable areas of activity include:
Increased Participation & Decision Making:  connecting with existing groups,
supporting new community activity and strategic developments - including
participatory budgeting through - Blacklands Community Kitty.
System Changers:  co-designed programme to explore systems and design thinking
– and how this knowlegde can be applied to support positive change in Kilwinning.
Community spaces: supporting community use of and investment in local facilities.
Tackling poverty and stigma:  including dignified food provision and clothing initiative. 
Partners that the Community Co-ordinator regularly works with include: 
North Ayrshire Council and HSCP, NHS Ayrshire, KA Leisure, Blacklands
Community Association, Kilwinning Community Football Academy, Blacklands
Primary School. 
The Community Co-ordinator has developed strong relationships with community
members and local partners and has been supporting and facilitating conversations
and responses to alleviating poverty, ensuring equality of access and improving
wellbeing. 
Integral to this approach is enabling individuals, groups and organisations to identify
and develop ideas – building confidence and capacity, which in turn results in
empowerment and a stronger and more sustainable community.

Page 30

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
In addition to directly working alongside Blacklands, Corra has supported the
development and delivery of a System Changers project for Kilwinning and will
continue to facilitate this work over the next two years. 
The ‘system changers’ are a mix of public and third sector staff and community
members. They have developed a deep understanding of systems change and are
exploring ways to put this theory into practice in Kilwinning. 
The group has identified metal health and wellbeing as a particular focus and are
developing experiments to test how best to meet need and improve outcomes. An
example of this is the coffee, cake and chat sessions, which libraries across North
Ayrshire are currently looking to establish following the positive impact – including
improved wellbeing and reduced in isolation - of pilot sessions in Kilwinning Library. 
The overall budget will include an annual ‘Ideas into Action’ allocation of £7,500 to
support community members and groups to test ideas and develop them. This
provides experience of managing funds and evidencing impact, which builds
confidence and the capacity to access larger sums of funding available through third
sector funding programmes in the future. 
4. What difference will this project make within the locality and to local
services and programmes? 
Please include: 
• The outcomes you aim to achieve
• How you will approach reducing inequality
• How this proposal fits with the Locality Partnership priorities of 1. Supporting
skills and work 2. Improving our local environment 3. Alleviating Poverty and
promoting equality of access to opportunities 4. Improving Community
Wellbeing. 
Since 2016 Corra and North Ayrshire Council have been working in partnership
alongside the community of Blacklands.  This long-term work has supported strong
connections to be built and established a firm foundation of increased confidence,
capacity and community-led action. This partnership has been underpinned by a
simple pledge designed to support, what was then, a new way of working alongside
communities.  Six years into the work, it feels timely and important to review and
deepen that collaboration. 
Collective investment from partners, with a shared interest in learning from and
resourcing communities to tackle deep-rooted social challenges, has always been at

Page 31

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
the heart of the People in Place programme.  This approach is now vital, if we are to
move beyond immediate financial pressures and achieve lasting change. 
Communities are facing a critical moment of transition as they emerge from the
pandemic and begin to grapple with the rising cost of living.  We are seeing and
hearing, in addition to difficult issues, new priorities emerging and an urgency to act. 
This proposal sets out how partner funding from North Ayrshire Council can support
a deeper collaboration with Corra and communities that can deliver new ways of
working. 
Through recent discussions we know that there are a shared ambitions - between
communities, Corra and North Ayrshire Council - including in relation to the wellbeing
economy, increasing community participation and how long-term funding models can
support strategic partnerships and key community organisations.   
To help achieve these ambitions, Corra will build our work around three key
elements: 
• Priorities – we know that communities’ priorities are changing and can offer a
supportive space to explore, define and articulate them.
• Plans – supporting communities to set out their priorities and actions to
achieve them in a ‘community-owned’ plan.
• Partnerships – connecting with partners who can help to produce the plan
and/or help deliver on community priorities. 
These ‘three P’s’, and the evolution of approach they support, build on the strong
foundations – of trust, relationships, skills and knowledge - that have been
established to date and will continue to be instrumental in the work. 
This approach will help North Ayrshire Council and communities deliver key
outcomes including: 
• An enhanced understanding of new and emerging community priorities.
• Communities taking action to achieve these priorities contributing to lasting
change.
• Improved connections between local action and strategic priorities.
• Leading examples - including in relation to the wellbeing economy and public
service transformation - for other Local Authorities to follow.
• Enabling structures that support increased community capacity, local
leadership, genuine sharing of decision-making and power.
• Financial and social returns on investment.

Page 32

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
Corra has a strong understanding of the Locality Plan and governance structures for
Kilwinning.  We see our role within North Ayrshire as integral to supporting
community members in Blacklands to be aware of the Locality Plan, engage in the
structures and processes and help shape the evolution of the plan and priorities to
recognise community need. This will involve supporting community members to
develop confidence and capacity to deliver and lead on activity that directly
contributes to the priorities identified. 
Getting Alongside Communities will directly contribute to the following Localotu
Partnership priorities: 
• Supporting skills and work 
• Alleviating Poverty and promoting equality of access to opportunities 
• Improving Community Wellbeing
• Building strong communities 
As community confidence and capacity to grow in terms of participating in locality
planning structures and providing their ideas, there is also potential to make a more
significant contribution to the priority of ‘Improving our local environment’ which has
been a feature of some smaller scale local action to date. 
5. What engagement has taken place in relation to the project? 
Please include the number of people who have been engaged with or consulted as
well as the range of people. 
Corra has worked alongside 538 different community members and partners within
Blacklands over the past 6 years and has established trust and effective
relationships. This has included children at Blacklands Primary and older people
engaging in chair-based exercise and the highly valued tea and chat afterwards,
which is often group members main chance for company each week. Corra also
supports parents to be involved and lead the local parent and toddler’s group. The
community-led grant making work (Community Kitty) involved a range of community
members including children and young people, who designed the process and
identified criteria and worked very effectively together. 
6. How will the project be managed? 
Please include: 
• How the finances will be managed

Page 33

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP
• Does the proposed project contribute to volunteering or employment opportunities in
Kilwinning? Please include the number of volunteering opportunities and employment
opportunities
• If there are any staff requirements, please outline your HR plans 
The investment will contribute to the overall budget for Blacklands and be managed
by Corra’s National Programme Manager. 
Volunteering and potential employability will be increased through development of
skills and confidence. As community members are supported to develop ideas,
community participation and volunteering increases. 
The intention is that some ideas and activity will result in the creation of governance
structures and local organisations that will develop over time and result in paid
employment. There has been 587 hours of volunteering provided so far and we
expect that to increase at a faster rate as momentum builds. 
The Community Co-ordinator is line managed by the National Programme Manager.
Corra has a central HR department that supports all staff in the organisation. 
7. Amount of funding being requested 
Please supply details of funding being requested and any other funding you have
had over the past 5 years, both financially and “in kind”. 
Amount of funding requested (£) £36000 over 3 years
Please give a breakdown of cost and recent quotations where appropriate. 
Getting Alongside
Communities: Blacklands
23/24 24/25 25/26 Total
Staff & Delivery Costs 43,579 43,579 43,579 130,737
Ideas into Action budget 7,500 7,500 7,500 22,500    
153,237 
From 2023–26 projected investment in Blacklands is £153k.  A contribution of £36k
(£12k p.a.) from North Ayrshire Council would be integral to the success of this
approach – and leverage further investment of £117k that would not otherwise
reach the area. 
Corra’s Board has confirmed investment in the People in Place programme for the
next 3 years.  Corra is also actively exploring investment from other partners.  A
funding commitment from North Ayrshire Council would be instrumental in securing
additional new investment, a significant endorsement of the work to date, and
underpin its continued success.

Page 34

COMMUNITY INVESTMENT FUND 
KILWINNING LOCALITY PARTNERSHIP 
8. Monitoring and evaluation process 
Please include detail on the monitoring and evaluation processes planned or in
place. 
Monitoring and evaluation is underpinned by reflective logs, produced by Corra’s
Community Co-ordinator, which include a mix of qualitative and quantitative data and
input from community members. This informs the analysis of our approach in
Blacklands and across the programme. We use the qualitative data analysis to
identify emerging themes, challenges and opportunities within and across
communities. 
The data collected through the reflective logs also informs the Annual Update that is
produced alongside community members to describe the activity that has taken
place, its impact and what has been learned.  There are also several case studies
within each Annual Update, the most recent of which is included as an example:
Blacklands Annual Update 2022.  
Annual Updates from 2017 onwards can be accessed here. 
The Getting Alongside Communities team regularly meets with Corra’s learning team
to discuss the learning gathered and identify opportunities to evolve the approach. 
Corra also supports community members to share their experiences and impact
through community stories. An example of a Blackland’s story is:
School Costs: A community pulls together - Corra 
An annual event brings communities and partners - including council staff - together
from across the People in Place programme to share learning, exchange ideas and
plan ahead.   
In addition, Corra facilitates a Community of Practice that brings colleagues from
across different partner local authorities together to explore shared challenges,
opportunities and exchange learning.  An example of this includes collaboration
between Fife and North Ayrshire Council colleagues that was instrumental in
supporting dignified food provision in communities across North Ayrshire.