Page 1

NORTH AYRSHIRE COUNCIL 
29 August 2023 
Cabinet 
Title:    Capital Programme and Treasury Management Performance
to 30 June 2023 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2023/24 and the associated Treasury
Management performance to 30 June 2023. 
Recommendation:  That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30
June 2023; and (ii) the forecast expenditure to 31 March
2024; 
(c) approve the virement proposals noted within the HRA
programme detailed in appendix 2; 
(d)  note the additional investment of £5.000m to support the
B714 upgrading project as detailed in paragraphs 2.12 and
2.13; and
(e)  note the estimated performance against the Prudential
Indicators set out in the Treasury Management and
Investment Strategy.
.
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2023/24 to 2030/31 was
approved by Council on 1 March 2023. The Housing Revenue Account (HRA) Capital
Investment Programme 2023/24 sits within the updated HRA Business Plan and was
approved by Council on 15 February 2023. 
1.2  This report identifies the current programme for 2023/24, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 31
June 2023 (Period 3) and forecast expenditure to 31 March 2024. 
1.3   At Period 3 the General Fund is forecasting a net underspend of (£0.236m) against a
revised budget of £107.252m. The HRA is forecasting a projected underspend of
(£0.638m) against a revised budget of £59.655m.

Page 2

1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £3.401m, including Scottish Government funding in
relation to the Place Based Investment, Nature Restoration and Road Safety
Improvement programmes. In addition, following the Local Government Finance
Settlement, the Scottish Government has withdrawn the previously announced capital
funding to support the expansion of Universal Free School Meals, pending a review of
the rollout of the expansion. This has resulted in a £1.954m increase in Prudential
Borrowing in order to maintain the agreed investment level. 
1.5 Reviews of individual project plans have identified a number of adjustments to the
current profiles. As a result, (£31.179m) has been reprofiled for delivery in 2024/25
and beyond. This has been partly offset by the previously reported re-profiling of
£14.941 from 2022/23 to 2023/24 and the acceleration of £4.158m to 2023/24 from
future years. 
1.6 Within the HRA, a review of delivery timescales has identified a requirement to re-
profile (£122.978m) of works for delivery in 2024/25 and beyond. This is partly offset
by £10.212m previously re-profiled from 2022/23 to 2023/24 and the acceleration of
£0.105m to 2023/24 from future years. 
1.7 The major risk to the forecast position is the uncertainty arising from the ongoing
inflationary pressures, supply chain issues, which are impacting on tender returns and
the cost of materials, and continued increases in the cost of borrowing. Some
mitigation has been built into the programme to offset cost pressures and supplement
the Loans Fund. However, any further significant increase in costs will result in
increased borrowing requirements and may have a negative impact on the
deliverability of both the General Fund and HRA capital programmes for 2023/24 and
beyond. Projects will continue to be monitored closely with cost increases met initially
from the additional flexibility built into the programme. However, any requirement for
further borrowing not met from a funding source will be a matter for Council to
consider. 
1.8 As noted by Council on 1 March 2023, the ongoing review of capital funding had
identified that no additional funding was being made available by the UK Government
to address the additional cost risks in relation to the upgrading of the B714. The
estimated additional costs have now been quantified at £5.000m over the period to
February 2026. Proposals in relation to the additional investment are detailed in a
separate report to Cabinet and will be drawn from a combination of reviewing existing
commitments from the Council Investment and Renewal and Recovery Funds,
allocating anticipated capital receipts not currently committed and utilisation of existing
resources from within the current programme. 
1.9 The Treasury Management and Investment Strategy (TMIS) for 2023/24 was
approved by Council on 1 March 2023 and detailed the key performance indicators
under the Prudential Code for Capital Finance in Local Authorities (2021 edition). The
current estimated performance indicates that North Ayrshire Council has operated
within the treasury limits and performance indicators set out in the TMIS and the
current capital investment plans remain affordable.

Page 3

2. Background 
General Fund 
2.1 The following table outlines the movements in the 2023/24 General Services budget: 
2.2 (a) Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
2023/24
£m
Budget as at 1 March 2023 115.931   
a) Changes to Funding 1.140        
b) Other Revisions to the Programme 2.261        
Revised Budget 119.332   
c) Alterations to phasing of projects:-
2022/23 to 2023/24 14.941     
2023/24 to 2024/25 (31.179)         
2024/25 to 2023/24 4.158        
Budget as at 30 June 2023 107.252   
Funding Body Amount Project
Scottish Government £0.761m Place Based Investment Programme
Scottish Government £0.355m Nature Restoration Fund
Scottish Government £0.216m Road Safety Improvement Fund
Scottish Government £0.030m Cycling, Walking and Safer Roads
Scottish Government (£1.954m) Withdrawal of UFSM expansion grant
UK Government £0.202m Shared Prosperity Fund
SPT £0.050m Ardrossan Harbour Interchange
SPT £0.350m Cumbrae Ferry & Bus Stop
SPT £0.100m Bus Corridor Improvements
SPT £0.050m Irvine Friendly Cycle Town
SPT £0.080m Brodick to Corrie Cycle Path
SPT £0.400m B714 Active Travel Links
Sustrans £0.500m Nature Restoration Fund
Total £1.140m

Page 4

2.3 (b) Other Revisions to the Programme 
The programme has also been updated to reflect the undernoted adjustments: 
2.4 (c) Alterations to the Phasing of Projects 
The reprofiling of £14.941m from 2022/23 to 2023/24 reflects projects not completed
within the year, or accelerated from future years, and incorporated within the 2023/24
capital programme. These were previously reported within the 2022/23 Capital
Programme performance reports: 
Funding Source Amount Project
Borrowing £1.954m Additional borrowing to offset grant withdrawn
CFCR £0.300m Funding for 47 West Road
Receipts £0.007m Insurance recoveries (Vehicles)
Total £2.261m
Service Amount Project
Communities £0.146m CO2 Monitors
£0.139m Lockhart Campus
(£0.636m) Moorpark PS
£0.148m Other minor adjustments
(£0.203m)
Chief Executives £0.243m ICT Projects
£0.243m
HSCP £0.363m Residential & Respite
£0.168m Carefirst Replacement
£0.157m Improvement Grants
£0.020m Other minor adjustments
£0.708m

Page 5

Service Amount Project
Place £1.572m Place Based Investment Programme
£0.788m Ardrossan Promenade
£0.768m Upper Garnock FPS
£0.724m Millport Coastal FPS
£0.712m Fleet Decarbonisation
£0.693m AGD Projects
£0.602m Vacant & Derelict Land Funding
£0.540m Islands Pit Stops
£0.435m Vehicles
£0.434m Millport Town Hall Phase 2
£0.431m Industrial Portfolio
£0.418m PLI Projects
£0.417m Lighting
£0.400m Annickbank - V&DL Investment Programme
£0.398m Solar PV - Nethermains
£0.356m Nature Restoration Fund
£0.350m CCTV Review
£0.323m B714 Improvements
£0.275m Solar PV - Shewalton
£0.246m Gallowgate Toilets
£0.241m A737 Dalry Trunk Road
£0.238m BUILD Project
£0.221m Millport Town Hall Regeneration
£0.214m Saltcoats Old Cal Railway Ph 1
£0.206m Town Centre Regeneration
£0.175m Access Paths
£0.170m Parking / DPE
£0.157m Emergency Control Centre
£0.154m LED Lighting
£0.154m Cycling / Walking /Safer Streets
£0.140m Island Infrastructure Fund
£0.126m Renewal of Play Parks
£0.116m Irvine high Street
£0.112m Lochshore Garnock Hub
£0.110m Repurposing Property Grant Fund
£0.107m Lochshore
£0.104m Montgomerie Park Masterplan
(£0.145m) Bridges Infrastructure
£0.607m Other minor adjustments
£14.089m
Other £0.104m Flexibility Fund
£0.104m
Total £14.941m

Page 6

A further review of individual project plans, taking cognisance of the current levels of
volatility within the construction sector, has identified a requirement to re-profile
(£31.179m) of works for delivery in 2024/25 and beyond. This includes a corporate
phasing adjustment reflecting the degree of uncertainty in the total expenditure
projections: 
These adjustments have been partly offset by the acceleration of £0.588m of
expenditure to 2023/24 from future years. 
2.5 These adjustments have resulted in a revised 2023/24 budget at 30 June 2023 of
£107.252m. 
Service Amount Project
Chief Executives (£0.150m) ICT Projects
(£0.150m)
Place (£1.918m) AGD Projects
(£0.300m) Ardrossan Cemetery Extension
(£0.068m) Other minor adjustments
(£2.286m)
Corporate (£27.513m) Sensitivity Adjustment
(£1.230m) Flexibility
(£28.743m)
Total (£31.179m)
Service Amount Project
Communities £1.230m Moorpark Primary
£2.305m Montgomerie Park School
£3.535m
Place £0.428m B714 Upgrade
£0.112m Cemetery Programme
£0.083m Other minor adjustments
£0.623m
Total £4.158m

Page 7

2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of £11.091m from the revised budget,
including: 
18.349 0.799 0.757 93.126 2.900 115.931
21.681 0.892 2.265 107.802 (25.388) 107.252
3.332 0.093 1.508 14.676 (28.288) (8.679)
Approved Programme
Movement
Programme @ P3
Category Amount Comments
Borrowing £16.649m Rephased aligned to projected expenditure
CFCR (£0.300m) Additional CFCR Contribution
Capital Grants (£5.199m) Rephased and additional government grants
Other Grants (£2.464m) Rephased and revised contributions
Capital Receipts (£0.007m) Realigned capital receipts
Total £8.679m

Page 8

2.8 Projected Capital Expenditure to 31 March 2024 
The projections are summarised by service in the following table:   
2.9 An underspend of (£0.236m) is projected within the General Fund capital programme
for 2023/24 arising from revisions to the BUILD project, which is subject to a separate
report to Cabinet. These funds will be transferred to the Flexibility budget to offset
anticipated budget pressures elsewhere in the programme. Information on the
progress of all projects can be found in Appendix 1. 
2.10 Although not formally reflected in the financial performance reports at this time due to
ongoing uncertainty, areas of cost risk have been identified as a result of cost volatility
arising from the ongoing inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials
across a number of projects. Specific projects where cost risks have been identified,
or are anticipated, include Moorpark Primary, Montgomerie Park Primary, Ardrossan
Campus, Upper Garnock Flood Prevention Scheme, Millport Coastal Flood Prevention
Scheme, Largs Sea Wall, Ardrossan North Shore and Ardrossan Harbour
Interchange. While some mitigation has been built into the Capital Programme in the
form of flexibility budgets, totalling £10m over the next few years, cost pressures may
exceed this provision. These risks will be quantified as individual projects are
completed and tendering exercises are finalised, with the impact on the costs of the
programme being monitored and reported to Cabinet as appropriate. It is recognised
however, with a significant budget gap being forecast for 2024/25 and to limit any
additional unfunded borrowing, any costs in excess of the current level of flexibility
provision will require to be funded from existing resources. 
Approved
Budget
2023/24
Budget
Revisions
Carry
Forwards
and
Adjustments
Revised
Budget
2023/24
Projected
Expenditure
/ Income to
31 March
2024
Projected
Variance
Over /
(Under)
£m £m £m £m £m £m
Expenditure
Communities 18.349 - 3.332 21.681 21.681 -
Chief Executive 0.799 - 0.093 0.892 0.892 -
Health and Social Care Partnership 1.257 0.300 0.708 2.265 2.265 -
Place 92.018 3.101 12.683 107.802 107.566 (0.236)
Other including Flexibility 3.508 - (28.896) (25.388) (25.388) -
Total Expenditure 115.931 3.401 (12.080) 107.252 107.016 (0.236)
Income
General Capital Grant (35.704) 1.368 - (34.336) (34.336) -
Specific Capital Grant (9.401) (1.055) (5.512) (15.968) (15.968) -
Capital Funded from Current Revenue - (0.300) - (0.300) (0.300) -
Capital Receipts (0.466) (0.007) - (0.473) (0.473) -
Other Grants & Contributions (2.068) (1.530) (0.934) (4.532) (4.532) -
Prudential Borrowing (68.292) (1.877) 18.526 (51.643) (51.407) 0.236
Total Income (115.931) (3.401) 12.080 (107.252) (107.016) 0.236

Page 9

2.11 In addition to the risks identified in relation to individual projects, significant financing
risks continue to be identified in relation to the overall affordability of the capital
investment programme due to the increased cost of borrowing. As reported to Council
on 1 March 2023, the programme is currently affordable based on the estimated
funding streams and the actions agreed by Council to supplement the Loans Fund.
The ongoing cost risk will continue to be monitored and a full assessment of
affordability will be included in the next major review of the capital programme due for
completion during 2023/24. 
2.12 As noted by Council on 1 March 2023, the UK Government previously confirmed that
North Ayrshire Council had been awarded £23.693m from the Levelling Up Fund to
support the upgrading of the B714 to improve connectivity between North Ayrshire
and the wider motorway network. The report highlighted that additional costs were
anticipated in relation to this project, although no additional funding was being made
available form the UK Government. Following a review of the costs involved in the
delivery of the project, together with appropriate value engineering, it has been
determined that an additional investment of £5.000m is required. 
2.13 In view of the current pressures and areas of risk and uncertainty being experienced
in relation to the capital investment programme, there is no capacity to support
increased borrowing costs to support additional investment. However, a review of
existing commitments from the Investment and Recovery & Renewal Funds,
additional allocations from anticipated capital receipts not currently committed and the
proposed utilisation of existing resources from within the current programme has
identified the following funds available for investment:  
Recovery & Renewal Fund:  
Stimulating Start Up and
Early Stage Business Growth
£1.000m Full original allocation of £1.000m
released. Future development to be
supported through specific grant
funding from the Place Based
Investment Programme and the Shared
Prosperity Fund.
Investment Fund:  
Community Wealth Being -
Community and Town
Centres
£0.857m Original allocation of £1.200m to be
reduced to £0.343m. Additional specific
grant funding from the Place Based
Investment Programme, VDLF and
identification of other potential funding
sources to be utilised to deliver original
policy intent. 
Commercial
Estate/Infrastructure/Town
Centre Investment
£0.988m Original allocation of £1.155m to be
reduced to £0.167m. Additional specific
grant funding from the Place Based
Investment Programme, VDLF and
identification of other potential funding
sources to be utilised to deliver original
policy intent.

Page 10

Existing Capital Resources:  
Industrial Portfolio £0.430m Reallocation of existing budget – no
current commitments
Flexibility £0.377m Allocation from current Flexibility
budget.
Capital Receipts:  
Uncommitted Capital
Receipts
£1.348m Anticipated capital receipts of £5.555m
have been identified. Following the
deduction of abnormal and other costs,
a balance of £1.348m is now available
for utilisation to support capital
investment.
Total Additional Investment £5.000m 
Housing Revenue Account 
2.14 The following table outlines the movements in the 2023/24 HRA Capital budget: 
2.15  (a) Alterations to the Phasing of Projects 
£10.212m of planned expenditure has been reprofiled from 2022/23 to 2023/24,
reflecting projects not completed within the year which have been incorporated within
the 2023/24 capital programme. These were previously reported within the 2022/23
Capital Programme performance reports: 
2023/24
£m
Budget as at 15 February 2023 172.316     
a) Alterations to phasing of projects:-
2022/23 to 2023/24 10.212       
2023/24 to 2024/25 (122.978)         
2024/25 to 2023/24 0.105         
Budget as at 30 June 2023 59.655

Page 11

Category Amount Project
New Builds £1.548m House Building General
£1.022m Contingency
£0.855m Harbourside
£0.543m Corsehillhead
£0.525m Afton Court
£0.335m Largs Police Station
£0.323m Caley Court
£0.302m Flatt Road
£0.233m Acquisitions
£0.231m Friars Lawn
(£0.114m) James Reid
£0.083m Other minor adjustments
£5.886m
Improvements £2.321m EWI
£2.273m Solar Panels
£0.223m Window
£0.180m Energy Efficiency
£0.094m Saltcoats MSF
(£0.120m) Kitchen
(£0.505m) Insulated Rendering
(£1.207m) Bathroom
(£1.303m) Fullarton Regeneration
£0.014m Other minor adjustments
£1.970m
Other Capital Works £2.369m Demolitions
£0.207m Health & Safety
£0.063m Sheltered Housing
(£0.298m) Regeneration Programme
£0.015m Other minor adjustments
£2.356m
Total £10.212m

Page 12

A review of the timescale for delivery of capital projects has identified a requirement to
re-profile (£122.978m) of works for delivery in 2024/25 and beyond, including: 
This has been partly offset by the acceleration of £0.105m of project expenditure for
delivery during 2023/24, including: 
2.16 These adjustments have resulted in a revised 2023/24 budget at 30 June 2023 of
£59.655m. 
Category Amount Project
New Builds (£34.671m) Ayrshire Central
(£26.166m) Montgomerie Park
(£9.033m) James Reid
(£7.593m) Garnock Academy
(£7.337m) Fullarton Street
(£6.093m) Stanecastle
(£4.780m) Regeneration Project 1d
(£3.908m) James MacFarlane
(£3.894m) Bourtreehill Village
(£2.874m) Laburnum Avenue / Newhouse Drive
(£1.660m) Glebe Place
(£1.465m) Corsehillhead
(£1.098m) Regeneration Project 1e
(£0.931m) Kings Arms
(£0.572m) Nelson Street Regeneration
(£112.075m)
Improvements (£0.945m) Kitchens
(£0.821m) Smoke Detector Programme
(£0.228m) Electrical Rewiring
(£1.994m)
Other Capital Works (£8.555m) Sheltered Housing
(£0.354m) Lift Replacement
(£8.909m)
Total (£122.978m)
Category Amount Project
New Builds £0.085m Harbourside
£0.020m Other minor adjustments
£0.105m
Total £0.105m

Page 13

2.17 The impact on budgeted funding is a reduction of £29.986m in the drawdown of
Capital Grants and reduced Prudential Borrowing aligned to the revised programme: 
2.18  Projected Capital Expenditure to 31 March 2024 
The projections are summarised in the following table:   
2.19 A variance of (£0.638m) is projected within the HRA capital programme for 2023/24
arising from revisions to a number of projects, including: 
Category Amount Comments
Capital Grants £29.986m Reduction aligned to projected expenditure
Borrowing £82.675m Reduction aligned to projected expenditure
Total £112.661m
Approved
Budget
2023/24
Carry
Forwards
and
Adjustments
Revised
Budget
2023/24
Projected
Expenditure /
Income to 31
March 2024
Projected
Variance
Over /
(Under)
Service £m £m £m £m £m
Expenditure
Housing Revenue Account 172.316 (112.661) 59.655 59.017 (0.638)
Total Expenditure 172.316 (112.661) 59.655 59.017 (0.638)
Income
CFCR (5.151) - (5.151) (5.151) -
Capital Grants (44.979) 29.986 (14.993) (14.993) -
Use of Reserves (4.065) - (4.065) (4.065) -
Affordable Housing Contribution (2.445) - (2.445) (2.445) -
Prudential Borrowing (115.676) 82.675 (33.001) (32.363) 0.638
Total Income (172.316) 112.661 (59.655) (59.017) 0.638
Project Variance Comments
Brathwic Terrace £0.125m Previous underspend overstated
Springvale £0.108m Previous underspend overstated
Dalrymple Place £0.017m Previous underspend overstated
Heating (£0.552m) Scope of works reduced
Health & Safety (£0.207m) Budget no longer required
St Michael's Wynd (£0.101m) Previous overspend overstated
Asbestos (£0.017m) Budget no longer required
Major Improvements (£0.006m) Budget no longer required
Newhouse Drive (£0.005m) Budget no longer required
Total (£0.638m)

Page 14

2.20 In addition to the adjustments noted above Appendix 2 highlights a number of
proposed virements which are required to transfers budgets between individual
projects and align the budgets with the projected expenditure. 
2.21 Further cost pressures resulting from inflationary and supply chain issues continue to
be monitored and a review of the potential impact on the Business Plan and Capital
Programme will be undertaken to address any identified issues. Further information
on the progress of all projects can be found in Appendix 2. 
Treasury Management and Investment 
2.22 The Prudential Code for capital finance in local authorities (2021 edition) requires the
Council to set and monitor performance against specified prudential indicators.  The
indicators for the current year were set out in the Treasury Management and
Investment Strategy 2023/24, approved by Council on the 1 March 2023.  A summary
of the key indicators and our current estimated performance against them is shown in
the following table. Further details of all the Prudential and Treasury indicators can be
found in appendix 3. 
2.23 (a) Loans Capital Financing Requirement 
The Loans Capital Financing Requirement (CFR) is the underlying borrowing
requirement of the Council. This is currently lower than the approved estimate as a
result of the change in profile of the capital programmes highlighted within this report. 
2.24 (b) Gross Borrowing 
Gross Borrowing is projected to be lower than anticipated due to the revised profile of
capital projects and the continued use of internal funds, the latter being a key element
of the Treasury Management Strategy to minimise costs. 
Prudential and Treasury Indicators
2023/24
Approved
Estimate
£m
2023/24
Revised
Estimate
£m
Movement
£m
(a) Loans Capital Financing Requirement
General Services 267.879 270.543 2.664
HRA 284.275 190.569 (93.706)
Total 552.154 461.112 (91.042)
(b) Gross Borrowing 490.154 372.112 (118.042)
(c) Operational Boundary for Borrowing 571.667 480.138 (91.529)
Authorised Limit for Borrowing 628.834 528.152 (100.682)
Total Operational Boundary (incl. PPP/NPD) 659.399 567.870 (91.529)
Total Authorised Limit (incl. PPP/NPD) 716.566 615.884 (100.682)
(d) Investments 20.000 20.000 -

Page 15

2.25 (c) Operational Boundary 
The Operational Boundary is the maximum which the Council anticipates borrowing to
fund the current year capital programme, building in flexibility for the timing of the
different funding streams and principal repayments.  The in-year variance is linked to
the continued use of internal funds and the re-profiling of the capital programme. 
2.26 (d) Investments 
It is estimated that the Council will maintain an average balance of £20.000m of
internally managed funds and utilise cash balances during the year in support of the
under-borrowed position.  The internally managed funds are primarily invested in call
accounts with banks, Money Market Funds and other UK local authorities. 
2.27 It is critical that the Council ensures that its capital investment plans are affordable. 
Affordability of borrowing is measured by the percentage of financing costs relative to
the net revenue stream of the General Fund and Housing Revenue Account (HRA). 
As at 30 June, the estimated percentages for 23/24 are 2.8% and 21.4% for the
General Fund and HRA respectively.  Capital expenditure impacts on the revenue
budget through financing charges so it is essential the Council ensures the financing
costs remain affordable and do not constitute an excessive proportion of the revenue
resources available. From a General Fund perspective, the Scottish Local Authority
average in 2021/22 was 5.5%, therefore demonstrating a prudent borrowing policy.
For the HRA, the Scottish average was 22.7%. The level of loan charges is deemed
prudent and affordable within the framework of the 30 year Housing business plan. 
3. Proposals 
3.1 That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30 June 2023; and (ii)
the forecast expenditure to 31 March 2024; 
(c) approve the virement proposals noted within the HRA programme detailed in
appendix 2; 
(d)  note the additional investment of £5.000m to support the B714 upgrading project
as detailed in paragraphs 2.12 and 2.13; and
(e)  note the estimated performance against the Prudential Indicators set out in the
Treasury Management and Investment Strategy. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None.

Page 16

Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our
investment on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Capital Investment Programme 2023/24 to 2030/31 - Council 1 March 2023
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget and
Rent Levels for 2023/24 – Council 15 February 2023 
Treasury Management and Investment Strategy 2023/24 – Council 1 March 2023

Page 17

APPENDIX 1
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Brought / Carry
Forward to 2024/25
Total Revised
Budget 2023/24
Year to Date Budget
2023/24
Actual Expenditure to
30 June 2023
Year to date
Variance 2023/24
Projected Expenditure
to 31st March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 16,368,237 15,896,227 16,368,237 0 568,862 0 568,862 0 96,852 96,852 568,862 0 0
Primary Schools 44,655,442 11,166,669 44,655,442 0 11,977,694 3,534,602 15,512,296 0 2,999,016 2,999,016 15,512,296 0 0
Secondary Schools 83,010,742 4,189,004 83,010,742 0 5,072,285 0 5,072,285 0 272,329 272,329 5,072,285 0 0
Special Education 25,343,637 25,239,710 25,343,637 0 138,595 0 138,595 0 34,668 34,668 138,595 0 0
Schools Other 880,194 393,639 880,194 0 728,737 0 728,737 0 242,182 242,182 728,737 0 0
Information & Culture 113,479 6,563 113,479 0 106,916 0 106,916 0 0 0 106,916 0 0
Completed Projects 43,419,379 43,394,998 43,419,379 0 3,679 0 3,679 0 (20,702) (20,702) 3,679 0 0
SUB TOTAL 213,791,110 100,286,809 213,791,110 0 18,596,768 3,534,602 22,131,370 0 3,624,345 3,624,345 22,131,370 0 0
Chief Executive
Council IT Strategy 8,797,380 2,652,103 8,797,380 0 1,041,645 (150,000) 891,645 0 168,369 168,369 891,645 0 0
SUB TOTAL 8,797,380 2,652,103 8,797,380 0 1,041,645 (150,000) 891,645 0 168,369 168,369 891,645 0 0
Health & Social Care
Management & Support 2,350,596 790,721 2,350,596 0 1,226,875 0 1,226,875 0 0 0 1,226,875 0 0
Housing Non HRA 656,571 159,758 656,571 0 656,571 0 656,571 0 159,758 159,758 656,571 0 0
Adults 4,608,078 4,590,097 4,608,078 0 18,047 0 18,047 0 66 66 18,047 0 0
Young People 5,579,718 5,223,534 5,579,718 0 363,177 0 363,177 0 6,993 6,993 363,177 0 0
SUB TOTAL 13,194,962 10,764,109 13,194,962 0 2,264,670 0 2,264,670 0 166,817 166,817 2,264,670 0 0
Place
Roads 107,944,875 30,624,516 107,944,875 468,054 40,423,938 468,054 40,891,992 0 4,722,759 4,722,759 40,891,992 0 0
Streetscene 7,891,828 4,423,461 7,891,828 0 2,147,915 (188,166) 1,959,749 0 743,321 743,321 1,959,749 0 0
Transport 4,757,454 1,973,635 4,757,454 0 4,494,466 0 4,494,466 0 1,710,646 1,710,646 4,494,466 0 0
Waste Services 14,539,343 14,539,343 14,539,343 0 0 0 0 0 0 0 0 0 0
Renewable Energy 15,307,181 1,948,354 15,307,181 0 7,727,424 0 7,727,424 0 79,745 79,745 7,727,424 0 0
Office Accommodation 1,600,920 348,738 1,600,920 0 1,600,920 (68,314) 1,532,606 0 348,738 348,738 1,532,606 0 0
Other Property 6,519,441 621,040 6,519,441 0 4,989,531 0 4,989,531 0 124,151 124,151 4,753,194 (236,337) (236,337)
Other Housing 470,000 0 470,000 0 381,025 0 381,025 0 (88,975) (88,975) 381,025 0 0
Economic Development & Regeneration 169,372,636 29,150,413 169,372,636 0 47,209,402 (1,874,104) 45,335,298 0 1,018,773 1,018,773 45,335,298 0 0
Completed Projects 6,355,261 6,275,623 6,355,261 0 40,595 0 40,595 0 (36,958) (36,958) 40,595 0 0
SUB TOTAL 334,758,940 89,905,123 334,758,940 468,054 109,015,216 (1,662,530) 107,352,686 0 8,622,201 8,622,201 107,116,349 (236,337) (236,337)
Other
Other 10,103,666 0 8,873,616 (1,230,050) 3,354,666 (1,230,050) 2,124,616 0 0 0 2,124,616 0 0
SUB TOTAL 10,103,666 0 8,873,616 (1,230,050) 3,354,666 (1,230,050) 2,124,616 0 0 0 2,124,616 0 0
Uncertainty / Sensitivity Adjustment* (27,512,826) (27,512,826) (27,512,826)
Total Project Expenditure 580,646,058 203,608,144 579,416,008 (761,996) 134,272,965 (27,020,804) 107,252,161 0 12,581,731 12,581,731 107,015,824 (236,337) (236,337)
Total Project Income (134,272,965) 27,020,804 (107,252,161) (16,762,960) (16,762,960) 0 (107,015,824) 236,337 236,337
Total Net Expenditure 0 0 0 (16,762,960) (4,181,229) 12,581,731 0 0 0
* Sensitivity adjustment of 10% or 25% based on source and reliability of expenditure projections
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2023/24
North Ayrshire Council Capital Statement 2023/24
Year Ended 31st March 2024
Period 3
The following classifications have been used to highlight delivery performance
against original timescales set

Page 18

Revised Budget
23/24 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 68,291,931 5,814,577 2,683,086 76,789,594 1,874,755 78,664,349 79,707,239 1,042,890
SUB TOTAL 68,291,931 5,814,577 2,683,086 76,789,594 1,874,755 0 78,664,349 0 79,707,239 1,042,890
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Early Learning & Childcare 0 26,594 59,206 85,800 0 85,800 85,801 85,800 0
Cycling / Walking /Safer Streets 1,159,954 (117,150) 271,000 1,313,804 30,000 1,343,804 0 1,343,804 0
Vacant & Derelict Land Funding 3,857,216 403,874 198,048 4,459,138 0 4,459,138 2,953,137 4,459,138 0
UK Government Grant - AGD 3,653,000 (98,741) 3,554,259 0 3,554,259 0 2,339,000 (1,215,259)
Town Centre Regeneration 0 65,691 140,000 205,691 0 205,691 205,690 205,691 0
Annickbank - Vacant & Derelict Land Investment Programme 400,000 400,000 0 400,000 400,000 400,000 0
Millport Town Hall Regeneration 0 (31,995) 252,529 220,534 0 220,534 220,534 220,534 0
Millport Town Hall Phase 2 94,022 339,498 433,520 0 433,520 433,520 433,520 0
Ardrossan Promenade 788,000 788,000 0 788,000 763,000 788,000 0
Islands Pit Stops 20,000 520,000 540,000 0 540,000 540,000 540,000 0
Islands Cost Crisis Emergency Fund 17,000 17,000 0 17,000 17,000 17,000 0
Place Based Investment Programme 0 622,801 948,836 1,571,637 761,000 2,332,637 1,571,637 2,332,637 0
UK Shared Prosperity Fund 98,414 98,414 202,330 300,744 98,414 300,744 0
Island Infrastructure Fund 0 140,373 140,373 0 140,373 140,374 140,373 0
B714 Improvements 500,000 322,741 822,741 0 822,741 322,741 1,250,795 428,054
Road Safety Improvement Fund 215,647 215,647 0 215,647 0
Renewal of Play Parks 231,000 231,000 (231,000) 0 0 0 0
2-4 Boyle Street Hostel 31,025 31,025 0 31,025 0 31,025 0
CO2 Monitors in Schools 0 0 76,651 76,651 76,651 76,651 0
Capital Grants
Flooding 20,525,000 20,525,000 0 20,525,000 0 20,525,000 0
General Capital Grant 15,179,000 15,179,000 (1,368,000) 13,811,000 8,495,250 13,811,000 0
SUB TOTAL 45,105,170 1,896,235 3,615,531 50,616,936 (313,372) 0 50,303,564 16,323,750 49,516,359 (787,205)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 0 0 0 0 0 0 0 0 0 0
Change & Service Redesign Fund 0 0 0 0 0 0 0 0 0 0
CFCR 0 0 0 0 300,000 0 300,000 300,000 300,000 0
Grants & Contributions 2,068,411 632,323 301,603 3,002,337 1,530,000 0 4,532,337 132,050 4,532,337 0
Capital Receipts 465,555 0 0 465,555 7,160 0 472,715 7,160 472,715 0
SUB TOTAL 2,533,966 632,323 301,603 3,467,892 1,837,160 0 5,305,052 439,210 5,305,052 0
TOTAL CAPITAL PROGRAMME FUNDING 115,931,067 8,343,135 6,600,220 130,874,422 3,398,543 0 134,272,965 16,762,960 134,528,650 255,685
23/24 Budget at
Capital Refresh
Mar 2023
Capital Programme Funding 2023/24
Projected Income
to 31st March
2024
Approved budget
at Period 1 used
as revised starting
point 2023/24
Actual Income to 30
June 2023Funding Description
Carry Forward
from 2022/23
Changes after
Capital Refresh Mar
2023
Total Changes in
Year
Changes at Capital
Refresh Mar 2024

Page 19

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date Budget
2023/24
Actual Expenditure to
30 June 2023
Year to date Variance
2023/24
Projected
Expenditure to 31
March 2024
Actual Over/ (Under)
Spend for 2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
EARLY LEARNING & CHILDCARE FUTURE PROJECTS 4,307 4,073 4,307 0 234 0 0 0 234 0 0 Future Projects Future Projects Future Projects Complete Complete
ST BRIDGETS EARLY YEARS 787,477 787,477 787,477 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
KILMORY EARLY YEARS 55,978 28,187 55,978 0 27,791 0 0 0 27,791 0 0 31-Aug-24 31-Aug-24 Pre Tender On Target On Target
ST PETERS EARLY YEARS 1,261,310 1,248,429 1,261,310 0 17,583 0 4,703 4,703 17,583 0 0 31-Aug-23 31-Aug-23 Construction On Target On Target
ST JOHN OGILVIE EARLY YEARS 177,415 177,415 177,415 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MAYFIELD PS EARLY YEARS 215,710 215,710 215,710 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
BEITH PS EARLY YEARS 339,763 341,180 339,763 0 0 0 1,417 1,417 0 0 0 Complete Complete Complete Complete Complete
SKELMORLIE PS EARLY YEARS 358,835 358,835 358,835 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
WEST KILBRIDE EARLY EARLY YEARS 232,807 221,228 232,807 0 7,752 0 (3,827) (3,827) 7,752 0 0 31-May-23 31-May-23 Construction On Target On Target
GATESIDE EARLY YEARS 407,764 407,764 407,764 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
GARNOCK CAMPUS EARLY YEARS 58,755 58,755 58,755 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
FAIRLIE EARLY YEARS 205,120 205,120 205,120 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ELDERBANK EARLY YEARS 22,983 22,983 22,983 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
DREGHORN EARLY YEARS 82,940 82,940 82,940 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CUMBRAE EARLY YEARS 40,184 40,195 40,184 0 0 0 12 12 0 0 0 Complete Complete Complete Complete Complete
LARGS CAMPUS EARLY YEARS 45,836 45,836 45,836 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MOORPARK EARLY YEARS 182 182 182 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
PIRNMILL EARLY YEARS 80,000 71,911 80,000 0 8,154 0 65 65 8,154 0 0 28-Feb-24 28-Feb-24 Construction On Target On Target
SHISKINE EARLY YEARS 127,013 127,013 127,013 0 0 0 0 0 0 0 0 28-Feb-24 28-Feb-24 Construction On Target On Target
CORRIE EARLY YEARS 38,605 28,442 38,605 0 10,163 0 0 0 10,163 0 0 01-Aug-23 01-Aug-23 Defects On Target On Target
LAMLASH EARLY YEARS 15,000 877 15,000 0 14,123 0 0 0 14,123 0 0 31-Aug-24 31-Aug-24 Tender On Target On Target
BRODICK EARLY YEARS 354,659 354,659 354,659 0 0 0 0 0 0 0 0 31-Aug-23 31-Aug-23 Construction On Target On Target
MARRESS HOUSE 4,010,310 3,654,793 4,010,310 0 450,000 0 94,483 94,483 450,000 0 0 22-Jul-22 Construction On Target Slightly off target  Delays anticipated
Completed Nursery Education
GLENCAIRN / LOUDON MONTGOMERY EARLY YEARS 170,429 170,429 170,429 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ARDEER EARLY YEARS 216,819 216,819 216,819 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ST JOHNS EARLY YEARS 283,930 283,930 283,930 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
STANLEY EARLY YEARS 27,514 27,514 27,514 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
KILWINNING (PENNYBURN SCHOOL) EARLY YEARS 648,135 648,135 648,135 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
DALRY EARLY YEARS CENTRE 56,920 56,920 56,920 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
SPRINGVALE EARLY YEARS 104,557 104,557 104,557 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ABBEY / ST LUKES PRIMARY SCHOOL EARLY YEARS 64,615 64,615 64,615 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ST LUKES EARLY YEARS 1,966 1,966 1,966 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CASTLEPARK EARLY YEARS 219,376 219,376 219,376 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
LAWTHORN EARLY YEARS 201,037 201,037 201,037 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
HAYOCKS EARLY YEARS 246,765 246,765 246,765 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
WOODLANDS EARLY YEARS 181,546 181,546 181,546 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CORSEHILL EARLY YEARS 536,144 536,144 536,144 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CALEDONIA EARLY YEARS 255,432 255,432 255,432 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
BLACKLANDS EARLY YEARS 204,144 204,144 204,144 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
WINTON EARLY YEARS 5,290 5,290 5,290 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
SPRINGSIDE EARLY YEARS 566,752 566,752 566,752 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ST MARKS EARLY YEARS 350,497 350,497 350,497 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
Other Nursery Education
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,103,416 3,070,354 3,103,416 0 33,062 0 0 0 33,062 0 0 01-Jun-23 01-Jun-23 Construction On Target On Target
Total Nursery Education 16,368,237 15,896,227 16,368,237 0 568,862 0 96,852 96,852 568,862 0 0 0
CAPITAL MONITORING 2023/24
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2023/24 BUDGETS

Page 20

COMMUNITIES
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date Budget
2023/24
Actual Expenditure to
30 June 2023
Year to date Variance
2023/24
Projected
Expenditure to 31
March 2024
Actual Over/ (Under)
Spend for 2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
CAPITAL MONITORING 2023/24
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2023/24 BUDGETS
Primary Schools
MOORPARK PRIMARY 10,849,441 7,643,802 10,849,441 0 4,312,892 0 1,107,253 1,107,253 5,542,942 1,230,050 1,230,050 30-Sep-24 30-Sep-24 Construction On Target On Target
MONTGOMERIE PARK SCHOOL 23,448,999 2,992,086 23,448,999 0 6,939,048 0 1,896,088 1,896,088 9,243,600 2,304,552 2,304,552 01-Aug-25 01-Aug-25 Tender On Target On Target
UNIVERSAL FREE SCHOOL MEALS EXPANSION 3,211,546 0 3,211,546 0 252,174 0 0 0 252,174 0 0 31-Mar-24 31-Mar-24 Tender On Target On Target
UFSM ARDEER PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BEITH PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BRODICK PRIMARY SCHOOL 144,178 121,450 144,178 0 22,844 0 117 117 22,844 0 0 31-Aug-23 31-Aug-23 Construction On Target On Target
UFSM CORRIE PRIMARY SCHOOL 52,795 52,795 52,795 0 0 0 0 0 0 0 0 31-Aug-23 31-Aug-23 Construction On Target On Target
UFSM CORSEHILL PRIMARY SCHOOL 60,000 0 60,000 0 60,000 0 0 0 60,000 0 0 31-Aug-25 31-Aug-25 Tender On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 90,000 0 90,000 0 90,000 0 0 0 90,000 0 0 31-Aug-25 31-Aug-25 Tender On Target On Target
UFSM GLEBE PRIMARY SCHOOL 2,043,869 0 2,043,869 0 0 0 0 0 0 0 0 31-Aug-29 31-Aug-29 Tender On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM HAYOCKS PRIMARY SCHOOL 82,500 0 82,500 0 82,500 0 0 0 82,500 0 0 31-Aug-25 31-Aug-25 Development On Target On Target
UFSM KILMORY PRIMARY SCHOOL 60,000 0 60,000 0 60,000 0 0 0 60,000 0 0 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM LARGS PRIMARY SCHOOL 148,533 148,533 148,533 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,081,077 0 2,081,077 0 0 0 0 0 0 0 0 31-Aug-28 31-Aug-28 Tender On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 22,500 0 22,500 0 22,500 0 0 0 22,500 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM SHISKINE PRIMARY SCHOOL 15,000 6,072 15,000 0 8,928 0 0 0 8,928 0 0 31-Aug-23 31-Aug-23 Construction On Target On Target
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,252,504 201,931 2,252,504 0 34,308 0 (4,441) (4,441) 34,308 0 0 31-Aug-27 31-Aug-27 On Site On Target On Target
UFSM WHITING BAY PRIMARY SCHOOL 25,000 0 25,000 0 25,000 0 0 0 25,000 0 0 31-Aug-24 31-Aug-24 Tender On Target On Target
Total Primary Education 44,655,442 11,166,669 44,655,442 0 11,977,694 0 2,999,016 2,999,016 15,512,296 3,534,602 0 3,534,602 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,428,004 2,805,435 0 378,401 0 970 970 378,401 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
AYRSHIRE COLLEGE PARTNERSHIP DEVELOPMENT 0 0 0 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ARDROSSAN NEW BUILD 80,205,307 1,761,000 80,205,307 0 4,693,884 0 271,359 271,359 4,693,884 0 0 31-Aug-26 31-Aug-26 In Development On Target On Target
Total Secondary Education 83,010,742 4,189,004 83,010,742 0 5,072,285 0 272,329 272,329 5,072,285 0 0 0
Special Education
LOCKHART CAMPUS 25,343,637 25,239,710 25,343,637 0 138,595 0 34,668 34,668 138,595 0 0 Complete Complete Snagging Complete Complete
Total Special Education 25,343,637 25,239,710 25,343,637 0 138,595 0 34,668 34,668 138,595 0 0 0
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 151,457 298,000 0 146,543 0 0 0 146,543 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 582,194 242,182 582,194 0 582,194 0 242,182 242,182 582,194 0 0 31-Mar-24 31-Mar-24 On-going On Target On Target
Total Schools Other 880,194 393,639 880,194 0 728,737 0 242,182 242,182 728,737 0 0 0
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 0 0 38,303 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 75,176 6,563 75,176 0 68,613 0 0 0 68,613 0 0 31-Mar-25 31-Mar-25 Planning On Hold On Hold
Total Information & Cultural 113,479 6,563 113,479 0 106,916 0 0 0 106,916 0 0 0
Completed Projects
GARNOCK CAMPUS 40,307,259 40,283,664 40,307,259 0 2,893 0 (20,702) (20,702) 2,893 0 0 Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,112,120 3,111,334 3,112,120 0 786 0 0 0 786 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 43,419,379 43,394,998 43,419,379 0 3,679 0 (20,702) (20,702) 3,679 0 0 0
Total Communities 213,791,110 100,286,809 213,791,110 0 18,596,768 0 3,624,345 3,624,345 22,131,370 3,534,602 0 3,534,602

Page 21

CHIEF EXECUTIVE
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 30
June 2023
Year to date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 4,075,490 957,838 4,075,490 0 543,757 0 48,105 48,105 543,757 0 0 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 902,197 402,197 902,197 0 0 0 0 0 0 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
LAN/WiFi 2,673,000 1,060,026 2,673,000 0 228,838 0 115,865 115,865 228,838 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
TELEPHONY 1,146,693 232,042 1,146,693 0 269,050 0 4,399 4,399 119,050 (150,000) (150,000) 31-Mar-28 31-Mar-28 Implementation On Target On Target
Total IT Strategy 8,797,380 2,652,103 8,797,380 0 1,041,645 0 168,369 168,369 891,645 (150,000) 0 (150,000)
Total Chief Executive 8,797,380 2,652,103 8,797,380 0 1,041,645 0 168,369 168,369 891,645 (150,000) 0 (150,000)   
CAPITAL MONITORING 2023/24
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2023/24 BUDGETS

Page 22

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date Budget
2023/24
Actual Expenditure to
30 June 2023
Year to date Variance
2023/24
Projected Expenditure
to 31 March 2024
Actual Over/
(Under) Spend for
2023/24  
True Over/(Under)
Spend            
Brought / Carry
Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Management & Support
HOME CARE SYSTEM 433,917 433,917 433,917 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 4,190 996,000 0 658,810 0 0 0 658,810 0 0 31-Dec-23 31-Dec-23 Future Years On Target On Target
CAREFIRST IT SYSTEM 84,620 84,620 84,620 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 268,065 0 0 0 268,065 0 0 31-Aug-24 31-Aug-24 In development On Target On Target
47 WEST ROAD 300,000 0 300,000 0 300,000 0 0 0 300,000 0 0 21-Jun-24 21-Jun-24 Refurbishment On Target On Target
Total Management & Support 2,350,596 790,721 2,350,596 0 1,226,875 0 0 0 1,226,875 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 656,571 159,758 656,571 0 656,571 0 159,758 159,758 656,571 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target 
Total Housing Non HRA 656,571 159,758 656,571 0 656,571 0 159,758 159,758 656,571 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,590,097 4,608,078 0 18,047 0 66 66 18,047 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,590,097 4,608,078 0 18,047 0 66 66 18,047 0 0 0
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,223,534 5,579,718 0 363,177 0 6,993 6,993 363,177 0 0 Complete Complete Snagging Complete Complete
Total Young People 5,579,718 5,223,534 5,579,718 0 363,177 0 6,993 6,993 363,177 0 0 0
Total Health & Social Care 13,194,962 10,764,109 13,194,962 0 2,264,670 0 166,817 166,817 2,264,670 0 0 0
CAPITAL MONITORING 2023/24
2023/24 BUDGETSTOTAL PROJECT COMPLETION DATES
CommentsProject Description
DELIVERY STATUS

Page 23

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 30
June 2023
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 4,447,261 4,447,261 4,447,261 0 4,447,261 0 266,574 266,574 4,447,261 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
ROAD SAFETY IMPROVEMENT FUND 215,647 215,647 215,647 0 215,647 0 0 0 215,647 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
A737 DALRY BYPASS 375,735 375,735 375,735 0 375,735 0 0 0 375,735 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target 
TRAFFIC CALMING 175,000 92,047 175,000 0 82,953 0 0 0 82,953 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
LIGHTING * 1,417,342 63,348 1,417,342 0 1,417,342 0 63,348 63,348 1,417,342 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 694,999 79,132 694,999 0 154,169 0 79,132 79,132 154,169 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target
A737 DALRY BYPASS LIGHTING 20,685 0 20,685 0 16,611 0 0 0 16,611 0 0 31-Mar-24 31-Mar-24 Preparing Works PackagesOn Target On Target
UPPER GARNOCK FPS 18,503,800 17,558,640 18,503,800 0 1,067,828 0 122,667 122,667 1,067,828 0 0 Complete Complete Complete Complete Complete
MILLPORT COASTAL FPS 48,599,797 5,401,766 48,599,797 0 26,724,382 0 3,561,351 3,561,351 26,724,382 0 0 31-Aug-24 31-Aug-24 Construction On Target On Target
MILLBURN FPS 1,757,000 253,471 1,757,000 0 393,547 0 0 0 393,547 0 0 31-Jul-24 31-Jul-24 Design On Target On Target
MILLPORT PIER 500,000 150,080 500,000 0 0 0 0 0 40,000 40,000 40,000 31-Mar-25 31-Mar-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 899,430 194,854 899,430 0 899,430 0 194,854 194,854 899,430 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 3,969,000 337,674 3,969,000 0 3,635,046 0 3,719 3,719 3,635,046 0 0 30-Apr-24 30-Apr-24 Construction On Target On Target
B714 UPGRADE 26,063,443 1,319,710 26,063,443 0 822,741 0 430,452 430,452 1,250,795 428,054 428,054 28-Feb-26 28-Feb-26 Outline Design On Target On Target
LARGS CAR PARK INFRASTRUCTURE 55,128 55,128 55,128 0 661 0 661 661 661 0 0 Complete Complete Complete Complete Complete
PARKING CHARGES & DPE 250,610 80,025 250,610 0 170,585 0 0 0 170,585 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target
Total Roads 107,944,875 30,624,516 107,944,875 0 40,423,938 0 4,722,759 4,722,759 40,891,992 468,054 0 468,054
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 526,939 0 526,939 0 (111,834) 0 0 0 0 111,834 111,834 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, LAMLASH - EXTENSION 715,065 715,065 715,065 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CMTY, ARDROSSAN - PLOTS/WALLS 217,922 152,479 217,922 0 61,864 0 (3,578) (3,578) 61,864 0 0 Complete Complete Complete Complete Complete
CMTY, KILBIRNIE - WORKS 25,383 25,383 25,383 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CMTY, KILWINNING - NEW 1,402,589 1,363,542 1,402,589 0 138,061 0 99,014 99,014 138,061 0 0 31-May-23 31-May-23 Construction On Target On Target
CMTY, KNADGERHILL - EXTENSION 416,471 414,810 416,471 0 1,661 0 0 0 1,661 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WORKS 398,033 361,141 398,033 0 36,892 0 0 0 36,892 0 0 28-Feb-24 28-Feb-24 Construction On Target On Target
CMTY, STEV HIGH ROAD - WORKS 506,878 491,694 506,878 0 137,408 0 122,223 122,223 137,408 0 0 30-Apr-23 30-Apr-23 Construction On Target On Target
ARDROSSAN CEMETERY NEW 603 603 603 0 0 0 0 0 0 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, BRODICK - NEW 12,000 8,317 12,000 0 4,979 0 1,296 1,296 4,979 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, KILBIRNIE - WALLS 188,370 15,626 188,370 0 172,744 0 0 0 172,744 0 0 31-Mar-25 31-Mar-25 Feasibility Works On Target On Target
CMTY, BEITH - WALLS 87,542 14,635 87,542 0 72,907 0 0 0 72,907 0 0 31-Mar-25 31-Mar-25 Feasibility Works On Target On Target
CMTY, ABBEY TOWER - WALLS 95,550 6,052 95,550 0 89,498 0 0 0 89,498 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, STEV HAWKHILL - WALLS 108,732 5,860 108,732 0 102,872 0 0 0 102,872 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, WEST KILBRIDE - WALLS 99,528 4,604 99,528 0 94,924 0 0 0 94,924 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, MILLPORT - WALLS 2,846 2,846 2,846 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, ARDROSSAN - WALLS 4,338 4,338 4,338 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, IRVINE OP CHURCH - WALLS 2,775 2,775 2,775 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, DREGHORN - WALLS 3,260 3,260 3,260 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE BARONY - WALLS 1,828 1,828 1,828 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, LAMLASH - WALLS 3,627 3,627 3,627 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, STEV HIGH KIRK - WORKS 22,754 22,754 22,754 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 600,514 11,287 600,514 0 389,227 0 0 0 389,227 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, DALRY - WALLS 2,450 2,450 2,450 0 0 0 0 0 0 0 0 On Target On Target
CMTY, ARDROSSAN - EXTENSION 900,000 0 900,000 0 600,000 0 0 0 300,000 (300,000) (300,000) 31-Mar-25 31-Mar-25 Planning On Target On Target
COASTAL PLAY PARKS 0 255,071 0 0 0 0 255,071 255,071 0 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
STREET FURNITURE IMPROVEMENT 69,469 87,123 69,469 0 0 0 17,654 17,654 0 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PARK ENABLING WORKS 85,363 111,102 85,363 0 0 0 25,740 25,740 0 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,391,000 335,189 1,391,000 0 356,712 0 225,901 225,901 356,712 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
Total Streetscene 7,891,828 4,423,461 7,891,828 0 2,147,915 0 743,321 743,321 1,959,749 (188,166) 0 (188,166)
Transport
VEHICLES * 2,130,744 1,709,616 2,130,744 0 2,130,744 0 1,709,616 1,709,616 2,130,744 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target 
WORKPLACE CHARGERS 318,261 226,433 318,261 0 92,858 0 1,030 1,030 92,858 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target
FLEET DECARBONISATION 2,308,449 37,585 2,308,449 0 2,270,864 0 0 0 2,270,864 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target
Total Transport 4,757,454 1,973,635 4,757,454 0 4,494,466 0 1,710,646 1,710,646 4,494,466 0 0 0
Waste Services
SHEWALTON LANDFILL 13,272,542 13,272,542 13,272,542 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
WASTE COLLECTION REVIEW 1,266,801 1,266,801 1,266,801 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
Total Waste Services 14,539,343 14,539,343 14,539,343 0 0 0 0 0 0 0 0 0
CAPITAL MONITORING 2023/24
Project Description
TOTAL PROJECT 2023/24 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments

Page 24

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 30
June 2023
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2023/24
Project Description
TOTAL PROJECT 2023/24 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 42,014 120,000 0 77,986 0 0 0 77,986 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 7,289,441 211,694 7,289,441 0 6,622,319 0 66,013 66,013 6,622,319 0 0 30-Apr-24 30-Apr-24 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 5,540,347 148,669 5,540,347 0 252,530 0 50,558 50,558 252,530 0 0 30-Oct-24 30-Oct-24 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 899,585 1,000,000 0 63,589 0 (36,827) (36,827) 63,589 0 0 31-Mar-24 31-Mar-24 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 711,000 0 711,000 0 711,000 0 0 0 711,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target 
ELECTRIC VEHICLES INFRASTRUCTURE 646,392 646,392 646,392 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-24 Various On Target On Target 
Total Renewable Energy 15,307,181 1,948,354 15,307,181 0 7,727,424 0 79,745 79,745 7,727,424 0 0 0
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * 133,604 419 133,604 0 133,604 0 419 419 133,604 0 0 0 31-Mar-24 31-Mar-24 Mulitple projects On Target On Target 
PLI BEITH CEMETERY 69 69 69 0 69 0 69 69 69 0 0 Complete Complete Complete Complete Complete
PLI TOWNEND CC 7,949 7,949 7,949 0 7,949 0 7,949 7,949 7,949 0 0 Complete Complete Complete Complete Complete
PLI PORTLAND PLACE 27,967 17,267 27,967 0 27,967 0 17,267 17,267 27,967 0 0 0 30-Nov-23 30-Nov-23 Planning On Target On Target
PLI WEST BYREHILL DEPOT 106,204 106,204 106,204 0 106,204 0 106,204 106,204 106,204 0 0 0 Complete Complete Complete Complete Complete
PLI GOLDCRAIGS DEPOT 114,767 4,878 114,767 0 114,767 0 4,878 4,878 114,767 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI BEITH PRIMARY SCHOOL 2,300 1,957 2,300 0 2,300 0 1,957 1,957 2,300 0 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI BLACKLANDS PRIMARY SCHOOL 0 (4,080) 0 0 0 0 (4,080) (4,080) 0 0 0 Complete Complete Complete Complete Complete
PLI CASTLEPARK PRIMARY SCHOOL 83,915 0 83,915 0 83,915 0 0 0 83,915 0 0 18-Aug-23 18-Aug-23 Planning On Target On Target
PLI CUMBRAE PRIMARY 3,867 3,867 3,867 0 3,867 0 3,867 3,867 3,867 0 0 Complete Complete Complete Complete Complete
PLI DALRY PRIMARY SCHOOL 68,314 0 68,314 0 68,314 0 0 0 0 (68,314) (68,314) 18-Aug-24 18-Aug-24 Planning On Target On Target
PLI DREGHORN PRIMARY SCHOOL 71,453 2,633 71,453 0 71,453 0 2,633 2,633 71,453 0 0 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI PENNYBURN PRIMARY 178,419 520 178,419 0 178,419 0 520 520 178,419 0 0 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI PIRNMILL PRIMARY 0 6,142 0 0 0 0 6,142 6,142 0 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI SKELMORLIE PRIMARY SCHOOL 73,980 2,178 73,980 0 73,980 0 2,178 2,178 73,980 0 0 30-Nov-23 30-Nov-23 Planning On Target On Target
PLI ST BRIDGETS PRIMARY 855 124 855 0 855 0 124 124 855 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI ST JOHN OGILVIE PRIMARY SCHOOL 6,744 6,744 6,744 0 6,744 0 6,744 6,744 6,744 0 0 Complete Complete Complete Complete Complete
PLI AUCHENHARVIE ACADEMY* 374,081 173,833 374,081 0 374,081 0 173,833 173,833 374,081 0 0 31-Dec-23 31-Dec-23 Construction On Target On Target
PLI IRVINE ROYAL ACADEMY* 12,000 12,000 12,000 0 12,000 0 12,000 12,000 12,000 0 0 Complete Complete Complete Complete Complete
PLI KILWINNING ACADEMY 188,421 1,014 188,421 0 188,421 0 1,014 1,014 188,421 0 0 31-Oct-23 31-Oct-23 Planning On Target On Target
PLI KYLE ROAD UNIT 34 4,067 0 4,067 0 4,067 0 0 0 4,067 0 0 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ACHNAMARA CHILDREN'S UNIT 9,000 0 9,000 0 9,000 0 0 0 9,000 0 0 31-Aug-23 31-Aug-23 Planning On Target On Target
PLI ANAM CARA 28,333 5,020 28,333 0 28,333 0 5,020 5,020 28,333 0 0 31-Oct-23 31-Oct-23 Planning On Target On Target
PLI EGLINTON CASTLE 48,000 0 48,000 0 48,000 0 0 0 48,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
PLI THE PORTAL 56,611 0 56,611 0 56,611 0 0 0 56,611 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 1,600,920 348,738 1,600,920 0 1,600,920 0 348,738 348,738 1,532,606 (68,314) 0 (68,314)
Other Property
INDUSTRIAL PORTFOLIO * 430,713 0 430,713 0 430,713 0 0 0 430,713 0 0 On Hold On Hold On Hold On Hold On Hold
HOME 4,470,198 289,898 4,470,198 0 3,148,529 0 1,250 1,250 3,148,529 0 0 0 On Hold On Hold On Hold On Hold On Hold
BUILD 284,086 47,749 284,086 0 237,837 0 1,500 1,500 1,500 (236,337) (236,337) 0 On Hold On Hold On Hold On Hold On Hold
EMERGENCY CONTROL CTR 158,000 66,220 158,000 0 156,780 0 65,000 65,000 156,780 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 766,000 25,000 766,000 0 741,000 0 0 0 741,000 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
GALLOWGATE TOILETS 275,803 87,983 275,803 0 246,153 0 58,333 58,333 246,153 0 0 31-Jul-23 31-Jul-23 Planning On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 104,190 134,641 0 28,519 0 (1,932) (1,932) 28,519 0 0 Complete Complete Complete Complete Complete
Total Property 6,519,441 621,040 6,519,441 0 4,989,531 0 124,151 124,151 4,753,194 (236,337) (236,337) 0   
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
2-4 BOYLE STREET HOSTEL 120,000 0 120,000 0 31,025 0 (88,975) (88,975) 31,025 0 0 12-May-23 12-May-23 Construction On Target On Target
Total Other Housing 470,000 0 470,000 0 381,025 0 (88,975) (88,975) 381,025 0 0 0
Regeneration
TOWN CENTRE REGENERATION 1,201,659 1,002,714 1,201,659 0 205,691 0 6,745 6,745 205,691 0 0 30-Sep-23 30-Sep-23 Construction On Target On Target
REPURPOSING PROPERTY GRANT FUND 348,665 23,845 348,665 0 347,985 0 23,165 23,165 347,985 0 0 30-May-25 30-May-25 In development On Target On Target
STEVENSTON BEACH HUB 95,475 95,475 95,475 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MILLPORT TOWN HALL REGENERATION 754,026 712,814 754,026 0 220,534 0 179,322 179,322 220,534 0 0 31-May-23 31-May-23 Construction On Target On Target
MILLPORT TOWN HALL PHASE 2 433,520 61,696 433,520 0 433,520 0 61,696 61,696 433,520 0 0 31-May-23 31-May-23 Construction On Target On Target
ISLANDS PIT STOPS 540,000 0 540,000 0 540,000 0 0 0 540,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 259,000 118,626 259,000 0 140,374 0 0 0 140,374 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
ISLANDS COST CRISIS FUND 17,000 0 17,000 0 17,000 0 0 0 17,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 1,041,035 279,275 1,041,035 0 1,010,258 0 248,498 248,498 1,010,258 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 300,744 0 300,744 0 300,744 0 0 0 300,744 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
PBIP 36 BANK STREET 169,999 89,528 169,999 0 86,827 0 6,356 6,356 86,827 0 0 31-Dec-25 31-Dec-25 In development On Target On Target
PBIP GALT HOUSE 50,000 0 50,000 0 50,000 0 0 0 50,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
IRVINE HIGH STREET 2,837,316 2,720,001 2,837,316 0 115,961 0 (1,353) (1,353) 115,961 0 0 Complete Complete Complete Complete Complete
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
MILLPORT CARS 11,943 0 11,943 0 11,943 0 0 0 11,943 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target
MONTGOMERIE PARK MASTERPLAN 4,218,597 1,775,944 4,218,597 0 353,665 0 1,012 1,012 353,665 0 0 31-Mar-30 31-Mar-30 In development On Target On Target

Page 25

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2023/24
Year to Date
Budget 2023/24
Actual
Expenditure to 30
June 2023
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Actual Over/
(Under) Spend for
2023/24
True Over/
(Under) Spend         
Brought / Carry
Forward to
2024/25
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
CAPITAL MONITORING 2023/24
Project Description
TOTAL PROJECT 2023/24 BUDGETS COMPLETION DATES DELIVERY STATUS
Comments
LOCHSHORE, KILBIRNIE 2,061,138 1,771,188 2,061,138 0 419,358 0 129,409 129,409 419,358 0 0 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,195,999 4,023,247 4,195,999 0 112,229 0 (60,524) (60,524) 112,229 0 0 Complete Complete Complete Complete Complete
VDLF - IRVINE KYLE ROAD SITE PREP* 1,421,110 1,421,110 1,421,110 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 1,798,066 143,495 1,798,066 0 1,657,226 0 2,655 2,655 1,657,226 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF - ANNICKBANK PH 3* 1,981,000 228,066 1,981,000 0 1,904,739 0 151,805 151,805 1,904,739 0 0 31-Mar-24 31-Mar-24 Tender On Target On Target
VDLF - DEVELOPMENT WORK* 422,479 114,955 422,479 0 329,012 0 21,488 21,488 329,012 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF - MAIN ST KILBIRNIE* 53,000 53,000 53,000 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
VDLF - DALRY RD SALTCOATS* 2,905 2,905 2,905 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
VDLF - STRATEGY 28,555 0 28,555 0 28,555 0 0 0 28,555 0 0 30-Sep-23 30-Sep-23 In development On Target On Target
VDLF - TREE PLANTING 50,000 2,400 50,000 0 47,600 0 0 0 47,600 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
VDLF - MINOR IMPROVEMENTS 10,000 10,000 10,000 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK NEIGHBOURHOOD CTR 175,000 0 175,000 0 175,000 0 0 0 175,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
VDLF STALLED SPACES FUND 125,000 0 125,000 0 125,000 0 0 0 125,000 0 0 31-Mar-24 31-Mar-24 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 4,778 0 0 0 4,778 0 0 Complete Complete Complete Complete Complete
VDLF - GAS WORKS (DALRY)* 173,896 173,896 173,896 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CYCLING/WALKING/SAFER STREETS * 1,311,610 819,545 1,311,610 0 1,311,610 0 26,449 26,449 1,311,610 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 669,667 669,667 669,667 0 669,667 0 1,262 1,262 669,667 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
FAIRLIE COASTAL PATH 500,000 500,000 500,000 0 500,000 0 0 0 500,000 0 0 31-Dec-23 31-Dec-23 In development On Target On Target
IRVINE CYCLE FRIENDLY TOWN 50,000 466,198 50,000 0 50,000 0 0 0 50,000 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
BRODICK TO CORRIE CYCLE PATH 80,000 60,199 80,000 0 80,000 0 0 0 80,000 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
ARDROSSAN PROMENADE 788,000 0 788,000 0 788,000 0 0 0 788,000 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
BUS CORRIDOR IMPROVEMENTS 289,041 189,041 289,041 0 100,000 0 0 0 100,000 0 0 31-Mar-24 31-Mar-24 Various On Target On Target
CUMBRAE FERRY & BUS STOP 489,547 140,253 489,547 0 350,000 0 706 706 350,000 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
B714 ACTIVE TRAVEL IMPROVEMENTS 500,000 100,000 500,000 0 400,000 0 0 0 400,000 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
B777 CORRIDOR IMPROVEMENTS 38,400 10,592 38,400 0 33,600 0 5,792 5,792 33,600 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
SALTCOATS OLD CAL RAILWAY PH1 268,588 55,075 268,588 0 213,513 0 0 0 213,513 0 0 26-Jun-23 26-Jun-23 Planning On Target On Target
SALTCOATS OLD CAL RAILWAY PH2 31,888 0 31,888 0 31,888 0 0 0 31,888 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target
Total Regeneration 35,103,365 23,039,468 35,103,365 0 13,266,277 0 804,481 804,481 13,266,277 0 0 0
Ayrshire Growth Deal
AGD - I3 DPMC PHASE 1 1,000,000 5,449 1,000,000 0 600,000 0 0 0 400,000 (200,000) (200,000) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 DPMC PHASE 2 4,999,999 248,651 4,999,999 0 210,554 0 9,235 9,235 200,000 (10,554) (10,554) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 15,617,569 610,750 15,617,569 0 3,671,828 0 65,327 65,327 2,339,000 (1,332,828) (1,332,828) 31-Oct-24 31-Oct-24 Multiple Projects On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 100,000 0 100,000 0 100,000 0 0 0 100,000 0 0 31-Mar-28 31-Mar-28 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,001 234,562 18,040,001 0 353,892 0 2,335 2,335 200,000 (153,892) (153,892) 31-Mar-30 31-Mar-30 Multiple Projects On Target On Target
AGD - GREAT HARBOUR 14,187,576 635,194 14,187,576 0 646,013 0 37,105 37,105 503,000 (143,013) (143,013) 31-Mar-28 31-Mar-28 Multiple Projects On Target On Target
AGD - IMSE 10,500,000 137,404 10,500,000 0 142,747 0 3,891 3,891 100,000 (42,747) (42,747) 31-Mar-30 31-Mar-30 Design On Target On Target
AGD - MARINE TOURISM ARDROSSAN 7,500,000 335,474 7,500,000 0 463,683 0 778 778 450,000 (13,683) (13,683) 31-Mar-26 31-Mar-26 Design On Target On Target
AGD - MARINE TOURISM ARRAN 2,025,577 66,203 2,025,577 0 40,482 0 5,719 5,719 30,000 (10,482) (10,482) 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - MARINE TOURISM CUMBRAE 2,025,577 75,870 2,025,577 0 60,648 0 7,691 7,691 50,000 (10,648) (10,648) 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 75,996,300 2,349,558 75,996,300 0 6,289,847 0 132,082 132,082 4,372,000 (1,917,847) 0 (1,917,847)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,127,112 472,478 4,127,112 0 84,257 0 17,026 17,026 128,000 43,743 43,743 1st Qtr 2026 1st Qtr 2026 Design On Target On Target
IRVINE ENTERPRISE AREA 10,746,072 0 10,746,072 0 0 0 0 0 0 0 0 Ongoing Ongoing Multiple Projects On Target On Target
LOW CARBON HUB 1,430,017 112,005 1,430,017 0 1,318,012 0 0 0 1,318,012 0 0 30-Sep-24 30-Sep-24 Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 41,532,859 2,898,951 41,532,859 0 26,092,051 0 65,185 65,185 26,092,051 0 0 27-May-24 27-May-24 Tender On Target On Target
VDLF - HARBOUR MASTERS OFFICE 157,500 20,933 157,500 0 136,567 0 0 0 136,567 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 279,411 257,020 279,411 0 22,391 0 0 0 22,391 0 0 31-Mar-24 31-Mar-24 Design On Target On Target
Other Growth & Investment 58,272,971 3,761,387 58,272,971 0 27,653,278 0 82,211 82,211 27,697,021 43,743 0 43,743
Total Economic Development & Regeneration 169,372,636 29,150,413 169,372,636 0 47,209,402 0 1,018,773 1,018,773 45,335,298 (1,874,104) 0 (1,874,104)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,163 3,378,163 0 0 0 (1,000) (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,898,460 2,977,098 0 40,595 0 (38,043) (38,043) 40,595 0 0 Complete Complete Defects Period Complete Complete
ARDROSSAN HOSTEL 0 0 2,086 2,086 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 6,355,261 6,275,623 6,355,261 0 40,595 0 (36,958) (36,958) 40,595 0 0 0
Total Place 334,758,940 89,905,123 334,758,940 0 109,015,216 0 8,622,201 8,622,201 107,116,349 (1,898,867) (236,337) (1,662,530)

Page 26

OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Year to Date Budget
2023/24
Actual Expenditure
to 30 June 2023
Year to Date
Variance 2023/24
Projected
Expenditure to 31
March 2024
Over/ (Under)
Spend for 23/24
£ £ £ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 10,103,666 0 8,873,616 (1,230,050) 3,003,666 0 0 0 1,773,616 (1,230,050)
CORE INFRASTRUCTURE INVESTMENT 351,000 0 351,000 0 351,000 0 0 0 351,000 0
Total Other Budgets 10,103,666 0 8,873,616 (1,230,050) 3,354,666 0 0 0 2,124,616 (1,230,050)
2023/24 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 27

APPENDIX 2
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Actual Expenditure to
31 June 2023
Projected Expenditure
to 31st March 2024 Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/
(Under) Spend
Delivery Status
Financial
Delivery Status
Physical Narrative
£ £ £ £ £ £ £ £ £
EXPENDITURE
Council House Building
Afton Court 1,335,654 1,088,468 1,335,654 0 681,987 434,801 681,987 0 0 On Target On Target Project on-site, due to complete July 2023.
Ayrshire Central Site 50,373,322 2,611,059 50,373,322 0 35,270,992 52,408 600,000 (34,670,992) On Target Significantly off
target
Project due to commence on site February 2024.  Project start date delayed to allow an
energy options appraisal to be carried out to inform the heating strategy for the site. 
Following confirmation of the strategy, further design work was required for the site and
internal layouts of the properties.  Due to the size of the development a second public
consultation event was also required.
Bourtreehill Village 9,924,743 65,865 9,924,743 0 3,944,138 0 50,000 (3,894,138) On Target Significantly off
target
First draft plans consultation event took place 28 June 2023.  Due to commence on-site
October 2024.
Brathwic Terrace 6,674,074 6,522,518 6,674,074 0 26,403 (91,173) 151,556 125,153 On Target Complete Complete - reported underspend in 22/23 offset by overspend in 23/24
Caley Court 3,131,066 2,808,436 3,131,066 0 322,630 1,863 322,630 0 On Target Complete Complete
Corsehillhead 2,027,810 212,599 2,027,810 0 1,815,211 0 350,000 (1,465,211) On Target Significantly off
target
Project due to commence on site November 2023.
Dalrymple Place 5,838,627 5,820,488 5,838,627 (0) 1,473 (82,125) 18,139 16,666 On Target Complete Complete - reported underspend in 22/23 offset by overspend in 23/24
Flatt Road 19,934,544 19,620,843 19,934,544 0 302,327 (11,374) 302,327 0 On Target Complete Complete
Friars Lawn 2,199,628 1,968,980 2,199,628 0 230,648 0 231,468 820 On Target Complete Complete
Fullarton Street (High Flats) 14,481,290 25,935 14,481,290 0 7,436,946 0 100,000 (7,336,946) On Target Significantly off
target
Demolition project completion deferred to November 2023.  New build project due to
commence on site July 2024.
Garnock Academy Site 12,092,889 602,453 12,092,889 0 11,093,276 7,468 3,500,000 (7,593,276) On Target Significantly off
target
Project due to commence on site October 2023. Project start date delayed by one year to
allow an energy options appraisal to be carried out to inform the heating strategy for the
site. Additional design work was required following this decision. Tender due to be
returned July 2023. 
Garrier Court 2,335,551 2,382,239 2,382,239 46,688 0 (0) 0 0 On Target Complete Complete
Glebe Place 1,894,952 0 1,894,952 0 1,659,897 0 0 (1,659,897) On Target On Target Project deferred to 2026/27 following refurbishment of the block for Ukraines funded by
the Scottish Government.
Harbourside 14,622,742 14,068,220 14,622,742 0 854,503 299,981 939,356 84,853 On Target Complete Complete
James McFarlane Site 4,784,118 376,551 4,784,118 0 4,407,567 0 500,000 (3,907,567) On Target Significantly off
target
Project due to commence on site November 2023.
James Reid Site 11,896,026 862,603 11,896,026 0 11,033,423 0 2,000,000 (9,033,423) On Target Significantly off
target
Project due to commence on site November 2023. Project start date delayed by one year to
allow an energy options appraisal to be carried out to inform the heating strategy for the
site.  Additional design work was required following this decision.
Kings Arms (113-115 High Street) 2,169,980 307,149 2,169,980 0 1,863,106 275 932,000 (931,106) On Target Significantly off
target
Project due to commence on site September 2023.
Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 95 3,274,506 0 3,274,411 0 400,000 (2,874,411) On Target Significantly off
target
Project due to commence on site January 2024.
Largs Police Station 2,769,301 2,111,027 2,769,301 0 1,038,675 380,401 1,038,673 (2) On Target On Target Project on-site due to complete August 2023
Montgomerie Park (Both Phases) 46,166,866 4,679,142 46,166,866 0 27,666,119 0 1,500,000 (26,166,119) On Target Significantly off
target
Project due to commence on site February 2024.  Project start date delayed to allow an
energy options appraisal to be carried out to inform the heating strategy for the site. 
Following confirmation of the strategy, further design work was required for the site and
internal layouts of the properties.  Due to the size of the development a second public
consultation event was also required.
Regeneration Project 1d 9,965,851 2,750 9,965,851 0 4,779,553 0 0 (4,779,553) On Target Significantly off
target
Pre Site
Regeneration Project 1e 1,658,083 0 1,658,083 0 1,097,853 0 0 (1,097,853) On Target Significantly off
target
Project due to commence on site June 2024.
Springvale  2,852,016 2,743,995 2,852,016 0 0 (2,000) 108,021 108,021 On Target Complete Complete - reported underspend in 22/23 offset by overspend in 23/24
Stanecastle Site 7,768,147 604,509 7,768,147 0 6,843,473 0 750,000 (6,093,473) On Target Significantly off
target
Project due to commence on site November 2023. Project start date delayed by one year to
allow an energy options appraisal to be carried out to inform the heating strategy for the
site. Additional design work was required following this decision.
St Beya Gardens 3,691,052 3,689,346 3,691,052 0 0 0 1,706 1,706 On Target Complete Complete 
St Colm's Largs 4,907,987 4,808,504 4,907,987 0 0 (65,376) 12,685 12,685 On Target Complete Complete 
St Michael's Wynd 13,996,769 14,097,801 13,996,769 (0) 0 (188,682) (101,032) 0 (101,032) On Target Complete Complete  - in year credit expected from Scottish Water.
Towerlands Primary School 8,579,943 8,461,992 8,579,943 0 3,673 (108,673) 9,279 5,606 On Target Complete Complete
Unallocated Regeneration Block 8,304,876 0 8,304,876 0 478,702 0 479,000 298 On Target On Target
Nelson Street Regeneration 622,116 0 622,116 0
622,116
0 50,000 (572,116) On Target Significantly off
target
Pre Site
Acquisition Of Land & Buildin 0 (292) 0 0 0 (292) 0 0 On Target On Target
House Building - General 1,547,765 0 1,547,765 0 1,547,765 0 1,547,765 0 On Target On Target
Acquisition Houses-Open Market 587,980 38,666 254,752 (333,228) 587,980 38,666 254,752 (333,228) 0 On Target On Target
Dickson Drive Phase 2 0 0 0 0 0 0 0 0 On Target On Target
Harbour Street 0 0 0 0 0 0 0 0 On Target On Target
Refurb - Connell Court 0 (30,395) 0 0 0 (30,395) 0 0 On Target On Target Complete
Kinnear Road 2,118 0 2,118 0 2,118 0 2,118 0 On Target Complete Complete
Contingency 11,000,624 0 11,000,624 0 11,000,624 0 11,000,624 0 On Target On Target
Internal Management Charges 1,757,259 235,101 1,757,259 0 1,757,259 235,101 1,757,259 0 On Target On Target
SUB TOTAL 293,413,016 100,551,545 293,126,475 (286,541) 141,644,848 870,875 29,490,313 (333,228) (111,970,115) 148,808
HRA Capital Statement 2324
Period 2
CURRENT YEAR 2023/24 DELIVERY STATUS

Page 28

APPENDIX 2
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2023/24
Actual Expenditure to
31 June 2023
Projected Expenditure
to 31st March 2024 Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/
(Under) Spend
Delivery Status
Financial
Delivery Status
Physical Narrative
£ £ £ £ £ £ £ £ £
HRA Capital Statement 2324
Period 2
CURRENT YEAR 2023/24 DELIVERY STATUS
Improvements to existing stock
Bathrooms 426,386 0 426,386 0 426,386 0 426,386 0 On Target On Target
Bathrooms - Void 770,876 46,561 770,876 0 770,876 46,561 770,876 0 On Target On Target
Wet Room - Planned 150,025 0 150,025 0 150,025 0 150,025 0 On Target On Target
Wet Room - Void 341,561 7,211 341,561 0 341,561 7,211 341,561 0 On Target On Target
Electrical Rewiring 969,075 43,665 969,075 0
969,075
43,665 741,075 (228,000) On Target On Target Anticipated slippage of 76 units due to no access.  Tender for new contract due in
September.
Heating 2,924,745 249,347 2,372,885 (551,860)
2,924,745
249,347 2,372,885 0 (551,860) On Target On Target Additional 32 units completed but scope of works reduced resulting in an anticipated
underspend.  Tender for new contract due in September.
Kitchens 2,646,010 40,005 2,526,347 (119,663) 2,646,010 40,005 1,581,530 (119,663) (944,817) On Target On Target Carry forward from 22/23 to be re-profiled to future years.
Kitchens - Void 1,085,091 101,528 1,204,754 119,663 1,085,091 101,528 1,204,754 119,663 0 On Target On Target
Roofing 878,404 25,661 1,105,661 227,257 878,404 25,661 1,105,661 227,257 0 On Target On Target
Wallfloor rendering 1,006,924 454,216 1,090,726 83,802
1,006,924
454,216 1,090,726 83,802 0 On Target On Target Projected overspend of £84k to be met from underspend in Smoke Detection programme
EWI 2,321,052 0 2,369,236 48,184
2,321,052
2,369,236 48,184 0 Projected overspend of £48k to be met from underspend in Smoke Detection programme
Window Replacement 541,903 54,368 541,903 0 541,903 54,368 541,903 0 On Target On Target
Saltcoats MSF Investment 947,986 204,795 1,281,214 333,228 947,986 204,795 1,281,214 333,228 0 On Target On Target Projected expenditure includes buy-back houses, budget virement requested.
Smoke Detector Programme 1,467,917 70,817 1,070,902 (397,015)
1,467,917
70,817 250,000 (397,015) (820,902) On Target On Target Carry forward of £821k to be reprofiled over future years. £397k of underspend vired to
meet in year pressures in other budget lines.
Energy Efficiency 1,846,610 0 1,552,610 (294,000)
1,846,610
0 1,552,610 (294,000) 0 On Target On Target Budget virement of £294k to support sustainability works within sheltered housing units.
Solar Panels 5,012,228 0 5,050,000 37,772
5,012,228
0 5,050,000 37,772 0 On Target On Target Current projected overspend of £38k to be met from underspend in Smoke Detection
programme.
SUB TOTAL 23,336,793 1,298,174 22,824,161 (512,632) 23,336,793 1,298,174 20,830,442 39,228 (1,993,719) (551,860)
Other Capital works
Estate Based Regeneration 2,093,064 (103,733) 2,093,064 0 2,093,064 (103,733) 2,093,064 0 On Target On Target
Lift Replacement 454,425 0 454,425 0 454,425 0 100,000 (354,425) On Target On Target Slippage on programme . Works now expected to commence Dec/Jan
Sheltered Housing Units 12,407,531 19,482 12,701,531 294,000
12,407,531
19,482 4,146,664 294,000 (8,554,867) On Target On Target Significant slippage on a multi year sheltered housing project.  A reprofiling exercise over
the medium term is to be carried out.
High Flats Demolition 2,368,970 247,100 2,368,970 0 2,368,970 247,100 2,368,970 0 On Target On Target Completion anticipated November 2023
Health and Safety Works 207,000 0 0 (207,000) 207,000 0 0 0 (207,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Parkhall & Kirkhall Asbestos 17,358 0 0 (17,358) 17,358 0 0 0 (17,358) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Major Improvements 6,000 0 0 (6,000) 6,000 0 0 0 (6,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Newhouse Drive (Regen 1b) 5,000 0 0 (5,000) 5,000 0 0 0 (5,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24.
Maress House Refurb (12,540) 0 (12,540) 0 (12,540) 0 (12,540) 0 On Target On Target
SUB TOTAL 17,546,808 162,849 17,605,450 58,642 17,546,808 162,849 8,696,158 294,000 (8,909,292) (235,358)
Total Expenditure 310,959,824 100,714,393 310,731,925 (227,899) 182,528,449 2,331,898 59,016,913 0 (122,873,126) (638,410)
Income
Affordable Housing Contributn (2,444,930) (2,444,930)
CFCR (5,151,045) (5,151,045)
Capital Grants (44,979,389) (14,993,130) 29,986,259
Prudential Borrowing (125,888,418) (32,363,141) 92,886,867 638,410
Council HB fund contribution (4,064,667) (4,064,667)
SUB TOTAL (182,528,449) 0 (59,016,913) 122,873,126 638,410
Total Project Expenditure 310,959,824 100,714,393 310,731,925 (227,899) 182,528,449 2,331,898 59,016,913 (122,873,126) (638,410)
Total Project Income (182,528,449) 0 (59,016,913) 122,873,126 638,410
Total Net Expenditure 0 2,331,898 0 0 0
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget

Page 29

Appendix 3
Treasury Management Performance to 30 June 2023    
Capital Expenditure for both the General Fund and HRA vary from original estimates due to changes
in the profile of projects. Full details of all movements in the capital expenditure budgets are
included in this report.  
The reduction to the Capital Financing Requirement reflects the change in profile of the capital
programme. 
Capital expenditure impacts on the revenue budget through financing charges so it is essential the
Council ensures the financing costs remain affordable and do not constitute an excessive proportion
of the revenue resources available.   From a General Fund perspective, the latest Scottish Local
Authority average was 5.5%, thereby demonstrating a prudent borrowing policy.   For the HRA, the
Scottish average was 22.7%. The level of loan charges is deemed prudent and affordable within the
framework of the 30 year Housing business plan.  
2023/24 2023/24 2023/24
Original Estimate P3 Projection Movement
£m £m £m
General Services Capital expenditure                   115.931                    107.016                       (8.915)
Funded by:
Borrowing                     68.292                      52.195                     (16.097)
Receipts / Grants                     47.639                      54.521                         6.882
Funded from Revenue                              -                            0.300                         0.300
Funded from Reserves                              -                                  -                                  -   
Total                   115.931                    107.016                       (8.915)
HRA Capital expenditure                   172.316                      59.017                  (113.299)
Funded by:
Borrowing                   115.676                      32.363                     (83.313)
Receipts / Grants                     44.979                      14.993                     (29.986)
Funded from Revenue                        5.151                         5.151                               -   
Funded from Reserves                        6.510                         6.510                               -   
Total                   172.316                      59.017                  (113.299)
Estimates of Capital Expenditure and Income
2023/24 2023/24 2023/24
Original Estimate P3 Projection Movement
£m £m £m
General Services                   355.611                    358.275                         2.664
HRA                   284.275                    190.569                     (93.706)
Sub-total                   639.886                    548.844                     (91.042)
Less PPP/NPD long-term liability                    (87.732)                    (87.732)                              -   
Loans Capital Financing Requirement (CFR)                   552.154                    461.112                     (91.042)
Capital Financing Requirement (CFR)
2023/24 2023/24
Original Estimate P3 Projection
% %
General Services 3.4% 2.8%
HRA 27.8% 21.4%
Proportion of financing costs to net revenue
stream

Page 30

The Council is currently under-borrowed by £89.000m due to the continuing strategy to delay long-
term external borrowing by utilising internal cash balances.
Liability Benchmark
The liability benchmark is an important tool to help establish whether the Council is likely to be a
long-term borrower or long-term investor in the future, and so shape its strategic focus and decision
making. 
The Liability benchmark graph above is used to inform the Council’s borrowing strategy.  The shaded
grey area shows the Councils current debt and the gap between this and the Liability benchmark line
is how much more borrowing the Council likely needs to undertake to support its current capital
plans once taking into account its balance sheet resources including the net debtor / creditor and
useable reserves.  The above graph indicates that long term borrowing for the period of around 20
years would be most appropriate to meet the Councils borrowing needs and mitigate against interest
rate risk.
2023/24 2023/24 2023/24
Original Estimate P3 Projection Movement
£m £m £m
Gross Debt at 31 March                   490.154                    372.112                  (118.042)
CFR                   552.154                    461.112                     (91.042)
(Under)/Over Borrowed Position                    (62.000)                    (89.000)                    (27.000)
Current Portfolio Position (excluding PPP/NPD)
0
200
400
600
800
1,000
2023 2027 2031 2035 2039 2043 2047 2051 2055 2059 2063 2067 2071
£m Liability Benchmark - North Ayrshire
Fixed rate loans LOBO loans
2023/24 2023/24 2023/24
Original
Estimate
£m
P3 Projection
£m
Movement
£m
Loans CFR                   552.154                    461.112                     (91.042)
Less Balance sheet resources                    (78.200)                 (155.300)                    (77.100)
Net loans requirement                   473.954                    305.812                  (168.142)
Liquidity allowance                     10.000                      10.000                               -   
Liability Benchmark                   483.954                    315.812                  (168.142)
Liability Benchmark

Page 31

The maturity structure of the debt portfolio at 30 June 2023 is shown below and shows the period
when the Council is required to repay and/or refinance debt. It is important to ensure a reasonable
spread of debt to mitigate against high exposure levels in respect of refinancing.  The current profile
ensures this: 
The overall reduction in debt is a result of maturing debt which has not currently required to be
replaced to slippage in the capital programme and the use of interna funds in line with the Council’s
strategy.
31-Mar-23 31-Jun-23
Maturity Profile of Borrowing (Indicator 10) Actual Actual Movement
£m £m £m
Under 12 months                      43.481                      41.949                       (1.532)
12 months and within 24 months                        2.950                         2.950                               -   
24 months and within 5 years                        6.207                         9.907                         3.700
5 years and within 10 years                     21.639                      24.439                         2.800
10 years and within 20 years                     33.177                      26.177                       (7.000)
20 years and within 30 years                        6.225                         6.225                               -   
30 years and within 40 years                   106.887                    106.887                               -   
40 years and within 50 years                     15.000                      15.000                               -   
50 years and above                     10.000                      10.000                               -   
Total Borrowing                   245.566                    243.534                       (2.032)