NORTH AYRSHIRE COUNCIL 
3 June 2025 
Cabinet 
Title:    Regeneration Delivery Plan Action Programme and
Funding Proposals Update 2025/26 
Purpose:  To provide an update on progress on the action programme
and seek approval for proposed funding allocations for the
Regeneration Delivery Plan. 
Recommendation:  That Cabinet: 
(a) Notes the progress made on the implementation of the
Regeneration Delivery Plan Action Programme at Appendix
One;
(b) Approves the Regeneration Delivery Plan funding proposals
as detailed at Appendix Two;
(c) Notes the update on previously secured or applied for funds
provided at Appendix Three; 
(d) Provides delegated authority to the Executive Director (Place)
to agree submissions to both the RCGF and Islands
Programme 2025/26; and
(e) Provides delegated authority to the Executive Director (Place)
to agree changes to the funding allocations in Appendices
Two and Three in consultation with the Portfolio Lead as
required. 
1. Executive Summary 
1.1 The Regeneration Delivery Plan was approved by Cabinet in March 2021. This sets
out our priorities for delivering on the regeneration ambitions of the Council Plan and
Community Wealth Building strategy, working in partnership with communities. 
1.2 The Plan focusses on the delivery of physical regeneration across North Ayrshire
through an ambitious project based rolling action programme. It informs our priorities
for securing and delivering against external funding sources including Scottish and UK
Government funds. This report provides an update on progress to date and seeks
approval for the funding proposals for 2025/26. 
1.3 The actions of the Regeneration Delivery Plan have been reformatted to illustrate their
alignment with the priorities and outcomes of the North Ayrshire Council Plan 2023 –
2028.

Page 2

2. Background 
2.1 The Council has placed the regeneration of communities at the heart of its agenda.
This focus is reflected within the priorities of the Council Plan and Community Wealth
Building Strategy. The Regeneration Delivery Plan sets out our priorities for delivering
on these ambitions and was approved by Cabinet on 23 March 2021. 
2.2 The Plan focuses on the delivery of physical regeneration in the period 2021 to 2026.
Informed by stakeholder consultation, reviewing existing community priorities and the
output of previous consultations, it aims to address local priorities, support changes
within communities and deliver a well-being economy. 
2.3 Actions in 2024/25 substantially focussed on maximising the impact and leverage of
investment including securing sources of external funding to support and accelerate
delivery. Appendix One outlines the progress and key successes achieved to date
against the Regeneration Delivery Plan Action Programme. This includes: 
• Approval of the local delivery plans for the £0.961m annual allocation for 2024/25
Scottish Government’s Vacant and Derelict Land Fund (VDLF).
• Provision of 12 further grants to sites through Stage 1 and 2 of the Repurposing
Property Grant Fund (RPGF) with a total value of £171,415.
• Identification of a preferred bidder for sites E-G at Montgomerie Park and
conclusion of missives for the neighbourhood retail site, subject to conditions.
• Approval of the delivery plan for the 2024/25 allocation from the PBIP to support
the detailed design and delivery of access, green space, infrastructure and facility
improvements and to support environmental improvements and activity by the
Friends of Lochshore community group and Community Engagement Officer.
• Working in partnership with Ardrossan Community Development Trust to complete
the Ardrossan South Beach Hub.
• Completion of the Phase 2 extension of the West Kilbride Shopfronts Scheme.
• Design development for the next phase of industrial unit development at Kyle
Road, Irvine and Annickbank Innovation Campus, Irvine.
• Preparation and submission of the annual Vacant and Derelict Land Survey
• Approval of the Communities and Place investment priority proposals under the UK
Government’s Shared Prosperity Fund
• Working in partnership with Millport Town Hall Trust on Phases One and Two of
the regeneration of Millport Town Hall including securing funding from the Scottish
Government’s Islands Programme.
• Working in partnership with the Irvine Neighbourhood Board to develop the £20m,
UK Government funded, Plan for Neighbourhoods programme.
• Delivery of a £1.069m programme of active travel design and construction works
under the Scottish Government’s Active Travel and Infrastructure programmes.
• Completion of the Fairlie Coastal Path through a £0.393m grant from Sustrans.
• Delivery of the Travel Smart Behaviour Change programme in our communities
and workplaces through a £0.228m grant from SPT People and Place Programme
and the Scottish Government’s Local Authority Direct Award.
• Promoting and supporting the delivery of the Ayrshire Walking Festival.
• Upgrade of Largs Seawall and Promenade
• Partnership working with Sustrans to deliver a £0.227m programme of active travel
design and construction works.

Page 3

2.4 The Regeneration Delivery Plan is delivered through an ambitious rolling action
focused programme. This approach seeks to ensure that the project list never
exceeds a realistic assessment of capacity, with projects prioritised annually. It
informs our priorities for securing and delivering against funding sources. 
2.5 The action programme, approved at Cabinet in May 2023 for 2023/24 and 2024/2025
was prepared to align priorities with resource. This was informed by an assessment of
progress to date, local priorities, project deliverability and funding. The implementation
of action programme projects aligned to competitive funding sources will however be
dependent on the success of the funding applications. 
2.6 Significant levels of funding have been secured or are anticipated to support delivery
in 2025/26. The details of these funds and the proposed approach to their expenditure
are provided at Appendix Two. These include the: 
• Scottish Government’s Place Based Investment Programme (provisional)
• Scottish Government’s Vacant and Derelict Land Fund
• Scottish Government’s Active Travel Infrastructure Fund Tier 1
• Scottish Government’s People and Place Local Authority Direct Award
• Strathclyde Partnership for Transport’s (SPT) Capital Programme (provisional)
• SPT’s People and Place Programme 
Updates on previously secured or applied for funds are provided at Appendix Three
including the: 
• UK Government’s Smart Infrastructure Pilot Programme
• UK Government’s 5G Innovations Regions
• UK Government’s Shared Prosperity Fund (SPF)
• Scottish Government’s Island Programme
• Scottish Government’s Regeneration Capital Grant Fund (RCGF)
• Scottish Government’s Vacant and Derelict Land Investment Programme (VDLIP)
• UK Government’s Levelling Up Round 3 (LUF3)
• UK Government’s Plan for Neighbourhoods
• Scottish Government’s Active Travel Infrastructure Fund Tier 2
• Strategic Timber Transport Fund (STTF) 
2.7 The economic climate has resulted in uncertainty regarding external funds available to
support the Regeneration Delivery Plan. Most funding received is single year funding.
Combined with increased project costs, this will potentially result in smaller numbers of
projects successfully securing funding in future. Appendix Two also includes
provisional approach to allocations where the funding position is currently
unconfirmed. 
2.8 Further consultation and engagement will be undertaken with local communities,
stakeholders and Elected Members through the development of individual projects. 
2.9  The Regeneration Delivery Plan covers the period 2021-2026. An updated Plan will be
developed by the Regeneration team during 2025/26 informed by Elected Member
and stakeholder engagement. A further report will be brought to Cabinet in due course
for consideration.

Page 4

3. Proposals 
3.1 That Cabinet: 
(a) Notes the progress made on the implementation of the Regeneration Delivery Plan
Action Programme at Appendix One;
(b) Approves the Regeneration Delivery Plan funding proposals as detailed at
Appendix Two;
(c) Notes the updates on previously secured or applied for funds provided at Appendix
Three; 
(d) Provides delegated authority to the Executive Director (Place) to agree
submissions to both the RCGF and Islands Programme 2025/26; and.
(e) Provides delegated authority to the Executive Director (Place) to agree changes to
the funding allocations in Appendices Two and Three in consultation with the
Portfolio Lead as required. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Regeneration Delivery Plan aims to build on and maximise the impact of the
investment being made through a variety of sources including the Ayrshire Growth
Deal, the Council’s Capital Programme, and the Strategic Housing Investment
Programme (SHIP). It also seeks to lever private funding and investment into North
Ayrshire. It informs priorities for securing and delivering against external funding
sources. The implementation of action programme projects aligned to competitive
funding sources will be dependent on the success of the funding applications. Whilst
resource costs can be capitalised to support delivery, future ongoing revenue
implications need be fully considered on a project-by-project basis. 
Human Resources 
4.2 The Regeneration Delivery Plan projects will be delivered through the existing
Regeneration Team resource. Opportunities to secure funding for additional staff
resource to support delivery will be investigated on a project-by-project basis. 
Legal 
4.3 The legal implications of all Regeneration Delivery Plan projects will be considered
through their development. Legal agreements will be developed on a project-by-
project basis as required with support from Legal Services. Negotiation will be
required in relation to land and building acquisitions with support from the Council’s
Legal Services and Property Management and Investment Service. Mechanisms such
as Compulsory Purchase Orders will be considered on a case-by-case basis, where
considered appropriate. 
Equality/Socio-economic 
4.4 The Regeneration Delivery Plan assists in meeting our socio-economic duty as set out
in the Fairer Scotland Duty. It seeks to reverse economic, social and physical decline
and reduce socio-economic disadvantage. It will tackle long-term vacant and derelict
land and buildings thereby reducing their levels and impact on communities. It aims to

Page 5

build community wealth and tackle local deprivation through the regeneration of our
communities by maximising the potential of our land and assets and those of anchor
institutions. 
The Plan also contributes to the delivery of the Isle of Cumbrae and Isle of Arran
Local Island Plans, their key themes and priorities. The funding proposals will directly
contribute to several of the actions identified within the annual action programme. Any
proposals for the Scottish Government’s Islands Programme will be informed by the
Islands Plans and identified from the Action Programmes. 
An initial screening will be undertaken to establish if an Equality and Children’s Rights
Impact Assessment is required for projects on a case-by-case basis. 
Climate Change and Carbon 
4.5 The Regeneration Delivery Plan aligns with the Sustainable North Ayrshire Strategy
for 2024-2027. Furthermore, it aligns with the commitment to reduce carbon
emissions through declaration of a Climate Emergency. 
Key Priorities 
4.6 The Regeneration Delivery Plan has been informed by the priorities identified within
the Local Outcomes Improvement Plan and Locality Partnership priorities. The
implementation of the Plan will contribute to achieving the Council Plan priorities that
focus on Wellbeing, Communities and Local Democracy, Climate Change, and A
Sustainable Council. 
Community Wealth Building 
4.7 The Regeneration Delivery Plan sets out our priorities for delivering on the ambitions
within the 2024-2027 Community Wealth Building Strategy. Its delivery will have a
significant positive impact on the Council’s ambitions across the pillars of: 
• Land and Assets: by supporting equitable land development and the development
of underutilised assets for community and business use.
• Procurement: by contributing to the development of the procurement wave plan;
through the inclusion of appropriate community benefit of local supplier clauses
within projects; and by considering phasing and programming of projects to create
local supply chain opportunities and support delivery by smaller scale and local
contractors where appropriate.
• Fair Employment: by supporting the creation of employment opportunities
particularly within the construction sector. Where North Ayrshire is procuring
services, through our enhanced Community Benefits approach we will seek to
ensure the creation of local training and work experience opportunities.
Consideration will also be given to delivery through employability programmes
where appropriate.
• Financial Power: by investing in localities and leveraging external national
investment into North Ayrshire.

Page 6

5. Consultation
5.1 The Regeneration Delivery Plan was the subject of extensive consultation including
workshops with Council Officers; workshops with Elected Members; reports to and
feedback from North Ayrshire Ventures Trust and the Community Wealth Building
Expert Panel; and public engagement via Consul. It was also informed by the Locality
Partnerships’ priorities and previous public consultation exercises including Charettes.
5.2 The funding proposals outlined at Appendix Two have been informed by this
consultation, and subsequent Place Plans that were developed by communities in
2024/25. Further consultation and engagement will be undertaken with local
communities, stakeholders and Elected Members through the detailed development of
the identified projects.
Russell McCUTCHEON
Executive Director (Place)
For further information please contact Claire Fitzsimmons, Senior Manager,
Regeneration, on 01294 324766. 
Background Papers
Cabinet Report – Regeneration Delivery Plan, 23 March 2021 
Cabinet Report – Levelling Up Fund, 15 June 2021
Cabinet Report – Levelling Up Fund – Round 2, 2 November 2021 
Cabinet Report – Regeneration Delivery Plan Update, 22 February 2022
Cabinet Report – Regeneration Delivery Plan Funding Proposals, 07 June 2022
Cabinet Report – Regeneration Delivery Plan Action Programme and Funding Proposals,
30 May 2023
Cabinet Report – Local Transport and Active Travel Strategy 2023-2028, 3 October 2023
Cabinet Report – Vacant and Derelict Land Strategy 2023-2028, 3 October 2023
Cabinet Report – Long-Term Plan for Towns, 5 December 2023
Cabinet Report – Levelling Up Round 3, 23 January 2024
Cabinet Report – Regeneration Delivery Plan Action Programme and Funding Proposals,
27 August 2024
Cabinet Report – UK Government Shared Prosperity Fund, 18 February 2025
Cabinet Report - Crown Estates Fund 2024/25, 18 March 2025
Council Report - Irvine: Plan for Neighbourhoods, 14 May 2025

Page 7

Appendix 1 
Strengthening Communities  
Maximising Land and Assets   
2023-2025 Action 2026 Outcome 2025 Update Lead Service
Review of land
and assets
Public consultation, finalisation and
adoption of Vacant and Derelict Land
Strategy for 2023-28
Confirmation of vacant and derelict
land priorities and actions and
implementation of Years 1 and 2
Implementation is ongoing, subject to
funding.
Economic
Development,
Growth &
Regeneration
(EDG&R)
Review of land
and assets
Prepare annual local delivery plans
for Scottish Government (SG)
approval under the Vacant and
Derelict Land Fund (VDLF), and
projects for submission to the
Regeneration Capital Grant Fund
(RCGF)
Implementation of vacant and derelict
land priorities on an annual basis
under the Vacant and Derelict Land
Fund and Vacant and Regeneration
Capital Grant Fund (RCGF)
VDLF Delivery Plans are prepared
and submitted to SG on annual basis,
following consideration of proposals
by Cabinet. 
SG advised in April 2025 that Kyle
Road Phase 2 was awarded
£892,990 under the VDLIP. The 36
Bank Street proposal was
unfortunately unsuccessful. 
EDG&R
Development
potential of land
and assets
Review the development potential of
Council landholdings to inform the
Local Development Plan 3 (LDP3)
Clarity on the priority sites for
intervention and/or investment
Work is ongoing to review the
potential of land opportunities.
Housing and
Public
Protection
(H&PP) /
EDG&R 
Investment in
land and assets
Implement the Repurposing Property
Grant Fund (RPGF) including
development of further phases,
subject to external funding
Landowners and communities are
supported to bring vacant and derelict
land and properties back into positive
use
Stages 1 & 2 of RPGF are open for
applications, with over £0.300m of
funding committed across twenty-four
sites to date. Stage 3 is being
finalised for publication in Summer
2025 to support project delivery. 
EDG&R
Investment in
land and assets
Identify opportunities and priorities for
future investment
A social housing and commercial
portfolio that supports the needs of
communities and the growth of local
businesses and entrepreneurial
activity
Work is ongoing to review the
potential opportunities.
EDG&R /
H&PP

Page 8

Appendix 1 
Levelling Up
Fund
Identify priorities for consideration of
potential submission to Round 3 of
the UK Government's Levelling Up
Fund 
Levelling Up funding is secured to
support capital investment in identified
priorities
The validation process has concluded
and the Council has received a
Memorandum of Understanding
(MoU) to support the Levelling Up for
Ayrshire – Commercial and Low
Carbon Infrastructure project. 
EDG&R
Housing and Town Centre Living   
Strategic
Housing
Investment
Programme
(SHIP)
Construct new social housing sites
including Corsehillhead, Kilwinning;
Bourtreehill, Irvine; Ayrshire Central,
Irvine; Fullarton Street, Irvine; and
West Byrehill, Kilwinning
Delivery of 1,900 unit SHIP
programme to 2026
1,900 units relates to RSL & Council
projects in the SHIP 2022-2027. As of
31 March 2025, 956 new Council
homes delivered towards 1,643
target. From April 2013, RSL partners
delivered 913 units. 
H&PP
SHIP Review of SHIP contribution to
community regeneration
Identification of priority sites and
process for selection of opportunities
Site selection and priorities are
reviewed annually as part of SHIP
review. 
H&PP /
EDG&R
Housing
Delivery
Preparation of Supplementary
Guidance for Development
Frameworks
Approval by Planning Committee;
Implementation of Guidance
National Guidance is set out in
National Planning Framework 4 and
PAN 83: Masterplanning.
Supplementary Guidance has not
been progressed following change in
personnel and priorities within the
Strategic Planning team. 
H&PP
Housing
Delivery
Preparation and approval of
development frameworks for strategic
sites
Approval by Planning Committee;
Implementation of development
frameworks; Completion of
developments
Masterplans continue to be prepared
for key strategic sites including the
Great Harbour, Irvine. 
EDG&R
Housing
Delivery
Analysis of the most suitable delivery
mechanism for housing on strategic
sites 
Delivery of appropriate development
on NAC owned strategic sites in line
with CWB strategy and LHS
Work is ongoing to review the
potential of land opportunities. 
EDG&R /
H&PP
Housing
Delivery
Next phase of Montgomerie Park
delivery including marketing of further
phase(s) and site start(s)
Completion of Sites A-B housing
development; retail site sale and
development; and marketing land,
The sale of Sites A & B has been
concluded, Sites C & D have been
transferred to Housing Services for
development. Missives have been
EDG&R

Page 9

Appendix 1 
sale and site start for remaining
phases
concluded on the Phase 1 Retail site,
subject to conditions, and a preferred
bidder identified for Sites E, F, & G.
The remaining land is under
consideration for Tree Planting. 
Town Centre
Living
Review of potential sites for increased
town centre living given decline in
retail activity and complete town
centre living pilot project. 
New residential development in town
centres
Work is ongoing to review the
potential opportunities. Site selection
and priorities are reviewed annually
as part of SHIP review.
EDG&R /
H&PP
Town Centre
Living
Redevelopment of Kings Arms, Irvine
to deliver amenity flats
Completion of development Works commenced on site on 13 May
2024 and are anticipated to conclude
by Autumn / Winter 2025. 
H&PP
Community Investment and Enterprise
Community
Project
Development
Support new community project
development, physical regeneration
projects, funding applications and
asset transfer processes and delivery
including Ardrossan Promenade
Identification and delivery of
community development and
community led regeneration projects
External funding opportunities to
support delivery in 2024/25 were
limited due to the pause of several
key funds. 
Support has been provided in the
Garnock Valley to support the
development of a local place plan. 
The Repurposing Property Grant
Fund has been promoted to support
the development of community led
regeneration projects. 
Ardrossan South Beach Hub has
achieved practical completion and is
operational with a café tenant. 
Connected
Communities
(CC) /
EDG&R
Community
Project
Development
Develop a grant funding CRM to
manage Council grant processes
including the creation of an
expression of interest process to
identify a pipeline of projects for
Identification and delivery of
community development and
community led regeneration projects
The CRM is being prepared to deliver
the next round of the Communities
and Place Fund. 
EDG&R / CC

Page 10

Appendix 1 
submission to external funding
sources
Shared
Prosperity Fund
Implement the approved Shared
Prosperity Fund (SPF) Investment
Plan including facilitating governance
arrangements
Implement and administer the North
Ayrshire award under the Shared
Prosperity Fund
The programme is entering its third
year with delivery on-track across the
investment priorities. The latest UK
Gov report was successfully
submitted. North Ayrshire has been
awarded £2.67m for 2025/26 to
deliver the programme for a single
year, across three investment
priorities: Communities & Place,
People and Skills and Supporting
Local Business. The single year of
funding will continue to follow the
previously approved investment plan. 
EDG&R / CC
Shared
Prosperity Fund
Implement Council priority projects
under the Communities and Place
Investment Priority informed by Place
Frameworks
Delivery of Council led projects under
the Shared Prosperity Fund
Communities and Place Investment
Priority
Twenty-one projects have benefitted
from the Council-led SPF support
across the fund to date. 
EDG&R / CC
Shared
Prosperity Fund
Develop and implement a Shared
Prosperity Fund Communities and
Place Fund
Identification and delivery of
community development projects
under the Shared Prosperity Fund
Communities and Place Investment
Priority
Round 1 of the funding administered
£160,330 of funding to nine projects
across North Ayrshire. Round 2 of the
funding received 52 applications with
a value of £2.2m requested. The
second round of funding supported 19
projects across North Ayrshire with a
total investment of £0.6m. 
EDG&R / CC
Locality
Partnerships
Coordinate the identification and
delivery of community development
projects through the operation of
Locality Partnerships
Identification and delivery of
community development projects
The use of the Community Investment
Fund continues to be a lever to
support community led projects within
localities. Work to establish stronger
relationships with third sector
organisations, including co-production
work with the Chief Officers Group, is
CC

Page 11

Appendix 1 
helping to develop capacity across
the sector. The recent review of
Locality Planning and its
implementation will create further
opportunities for collaboration and the
identification and development of
projects to meet locality priorities and
needs. 
Participatory
approaches
Extend and mainstream a
participatory approach to offer
communities, including young people,
more opportunities to lead in local
decision-making 
Increased community involvement
decision- making 
The 2024/25 round of Participatory
Budgeting (PB) concluded in
December 2024, with 15,882 votes
cast across Locality and Youth PB
funding rounds. Our hybrid approach
to participation saw voting taking
place online and in schools, libraries
and community group settings across
North Ayrshire, with local people aged
8 and over allocating £171,377 to 190
community-led projects. For the first
time, Youth PB was hosted in full on
the Shaping North Ayrshire site, giving
young people parity of experience
with adults and enabling them to also
engage with locality projects in their
area. 
CC
Community
Asset Transfer
Support Community Asset Transfer
and Participation Requests
Increased community ownership of
land and property and redevelopment
of underutilised assets
The use of Community Asset
Transfers continues to allow
community groups to increase their
capacity and improve local use and
ownership of assets. Between May
2024 and May 2025 16 Expressions
of Interest were submitted, 10 groups
were working on a Full Application
and 2 Full Applications were received.
2 CATs were concluded and one was
amended from a lease to full
ownership to better meet local needs.
CC

Page 12

Appendix 1 
Requests can be complex, with land
and assets at times being held by the
Housing Revenue Account, Common
Good or Charitable Trusts. Support is
provided to groups through a Single
Point of Contact to make the process
as accessible and straightforward as
possible 
Community
Investment
Fund 
Co-design, co-production and co-
delivery of projects
Identification and delivery of
community development projects
In the reporting period May 2024 -
May 2025 12 Full Applications to the
Community Investment Fund has
been passed by the Locality
Partnerships and 11 Full Applications
have been approved by the Council’s
Cabinet, total amount awarded during
this period is £678,348. 
Locality
Partnerships
/ CC

Page 13

Appendix 1 
Delivery Models   
Third Party
Assets Review
Review the identified sites including
the case for the purchase of third-
party land to address a recognised
problem or facilitate positive
development – including sites
identified through the RDP 
A property portfolio that supports
communities, improved public amenity
and the growth of local businesses
and entrepreneurial activity
The review remains ongoing.
However, funding opportunities are
limited to support acquisition and
delivery currently. 
The Repurposing Property Grant
Fund is being promoted to property
owners and community groups to
facilitate positive development. This is
also in line with the Land & Assets
pillar of the 2024-2027 CWB Strategy. 
EDG&R
Land
Development
Model
Develop a model for the development
and sale of vacant land/property and
reinvestment in further programme 
Confirmation and implementation of
model
A model was explored for Town
Centre living however, development
costs vs. market value are too far
apart to make the approach viable. 
Furthermore, the conditions of
external funding often include a
clawback provision, unless agreed
otherwise with ministers. 
EDG&R
Commercial
Estate
Develop proposals for Commercial
Estates, Infrastructure and Town
Centre allocation under the Recovery
and Renewal Investment Fund and
external funding sources 
Identification and implementation of
priority projects
UK Government LUF3 funding has
been secured to enable the delivery
of the Levelling Up for Ayrshire –
Commercial and Low Carbon
Infrastructure projects. Informed by
market feedback, the North Ayrshire
proposal includes the delivery of new
energy efficient commercial property
and associated low carbon
infrastructure at key employment
including Kyle Road, Annickbank and
i3.
EDG&R

Page 14

Appendix 1 
Placemaking  
Town and Local Centres 
2023-25 Action 2026 Outcome 2025 Update Lead Service
Place Framework
Development
Roll out of programme of Place
Frameworks to direct future
investment through the Investment
Fund, Place Based Investment
Programme and external funding
Use of Place Framework to facilitate
community consultation and to
direct and implement projects
contributing to a wellbeing economy
New planning legislation has
introduced a right for communities
to produce their own plans, known
as Local Place Plans. These
provide the opportunity for
communities to feed into the
planning system with their own
ideas and proposals for the
development and use of land. 
Informed by this, rather than the
Council leading on further Place
Frameworks, it is proposed that
local priorities for physical change
are identified and captured as part
of the RDP refresh process. 
EDG&R / CC
Place Framework
Development
Implementation phase of pilot place
frameworks for Kilwinning, Saltcoats
and Largs.
Use of Place Framework to facilitate
community consultation and to
direct and implement projects
contributing to a wellbeing economy. 
Pilot Place Frameworks were
presented to their respective
Locality Planning Partnerships. 
Support is on-going towards the
development of the Garnock Valley
Place Framework. 
EDG&R / CC
Place Plan
Development
Support local communities to
develop Local Place Plans under the
Planning Act
Community development of Local
Place Plans
A ‘Handbook’ is being prepared to
support community bodies
preparing or thinking about
preparing a Local Place Plan 
Where required, groups will be
supported to identify funding to
provide or procure on behalf of the
community body other technical
support required to prepare the
Local Place Plan.
H&PP / CC /
EDG&R

Page 15

Appendix 1 
Town Centre
Improvements
Completion of SG funded Town
Centre Fund projects
Implementation of projects Projects were completed March
2024. Funding supported over 40
projects ranging from shopfront
improvement schemes, temporary
events, new community projects
and active travel improvements. 
EDG&R
Town Centre
Improvements
Investigate potential to upgrade
grass pitch provision and
implementation of any
recommendations 
Completion of Quarry Road project Additional funding was secured
from SFA, the contractor appointed
and works are ongoing. The pitch is
anticipated to be ready for play in
September 2025. 
EDG&R/ CC /
KA
Leisure
Town Centre
Improvements
Identify and adopt a new approach
to town centre footfall monitoring
Effective monitoring of town centre
activity
A CCTV pilot proposal has been
developed in collaboration with the
Public Safety Team using AI
software and analytics on camera
data. However, this has been put on
hold pending the agreement of the
Council’s AI policy. 
EDG&R
Town Centre
Improvements
Prepare an investment plan for
Years 3 to 5 of the Place Based
Investment Programme allocation
working collaboratively with local
communities, business, third and
public sectors 
Implementation of projects identified
in Investment Plan
Proposals are prepared annually
and presented to Cabinet for
approval. Funding was substantially
paused in 2024/25 by SG and
limited to £75,000 investment at
Lochshore. 
2025/26 proposals have been
directed by cross-service
collaboration, changes in policy,
and support to expand existing
initiatives. 
EDG&R
Town Centre
Improvements
Develop and implement proposals
for CWB
- Town Centres and Communities
Identification and implementation of
town centre priority projects
Proposals captured under the pilot
frameworks, and going forward will
be included with Place Plans
prepared by communities. 
EDG&R

Page 16

Appendix 1 
allocation under the Recovery and
Renewal Investment Fund
Conservation
Projects
Completion of Millport Conservation
Area Regeneration Scheme
Completion of project Final project achieved practical
completion in January 2024. 
EDG&R
Conservation
Projects
Identification of potential
conservation projects through the
development of Place Frameworks
and Local Place Plans
Development and implementation of
conservation projects
Works to Kilwinning Abbey were
identified through the Kilwinning
Place Framework. Additional
funding has been secured to enable
conservation repairs to be
undertaken. 
Additional heritage projects have
been identified, with funding being
sought. 
EDG&R
Strategic Sites
Ardrossan Coastal
Quarter
Deliver the next phases of civil
infrastructure to support the
Ardrossan Campus including
delivery of a programme to facilitate
the delivery of the Campus
Supporting the completion of the
Ardrossan Campus
The Remediation and Enabling
Works Contractors remain on site
with works substantially progressed
including construction of the coastal
defences and path. The phased
completion of the works is now
taking pace to facilitate the delivery
of the Campus. 
EDG&R
Ardrossan Coastal
Quarter
Develop a major Branding exercise
to reflect the national scale
regeneration opportunity including
North Shore, Harbour and town
centre
Secure appropriate press coverage
and community understanding of
investment in town, changing
perceptions at key points in the
programme’s delivery
Significant ongoing engagement
with stakeholders including a
regular newsletter outlining site
progress and future works. Site
signs detailing the work being
carried out have been erected.
Further branding will take place
closer to completion.     
Communications
i3 Enterprise Area Operation of Phase 1 of the Digital
Processing Manufacturing Centre
(DPMC) digital hub. Delivery and
occupation of Phase 1 of the flexible
Delivery of AGD investment and
leverage of private investment
Phase 1 of the DPMC project is
operational with the official launch
taking place in February 2025 and
several digital demonstrators in
EDG&R

Page 17

Appendix 1 
space programme and development
of Phase 2 project
place. Phase 1 of the Flexible
Space Programme is substantially
complete and the building is being
marketed. Phase 2 is currently at
planning application stage.   
Irvine Harbourside,
‘Great Harbour’
Development and implementation of
the Great Harbour Masterplan
informed by community and
stakeholder consultation.
Development and construction of
phase 1 – Coastal Hub.
FBC for the Coastal Hub. 
Tender for the Lead Designer for
phase 2 – Maritime Mile. 
Delivery of the Coastal Hub as first
phase of the Great Harbour
programme utilising £5m of AGD
investment of £14m.
Tender of works for phase 2 –
Maritime Mile. 
FBC for Maritime Mile. 
The Phase 1 - Coastal Hub project
received Full Business Case
approval. This enabled the award of
the works contract, which is
currently on site, with completion of
the play facilities expected in
Autumn 2025. The remaining works
are expected to complete in April
2026. A tender for appoint the
design team for Phase 2 is
complete and the contract award
planned is for May 2025. 
EDG&R
Lochshore Completion of £8m Phase One of
the Lochshore Park Masterplan
including: 5km circular loop; Play at
the Hub; woodland creation and
community play links
Completion of Phase One of the
Lochshore Park Masterplan
The Phase One works comprised of
a 5km circular loop, woodland
creation, hub and active travel
connections, play at the hub and
community play links have been
completed. 
EDG&R
Lochshore Identify funding opportunities,
submit applications and secure
funding for Phase Two delivery 
Completion of Phase Two of the
Lochshore Park Masterplan (subject
to funding)
Funding review remains underway.
Additional funding applied for to
support delivery of the community
garden and activity hub, to be
managed by Employability
Services. 
EDG&R
Lochshore Delivery of Play at the Hub Completion of Phase One of the
Lochshore Park Masterplan
Construction was completed in July
2024 
EDG&R
Hunterston Development of options for site with
partners Peel Ports Group and SE
Hunterston is recognised as a
strategically significant national
asset contributing to local, regional
Hunterston is recognised as a
strategically significant national
asset contributing to local, regional
EDG&R

Page 18

Appendix 1 
and national blue and green
economy aspirations.
and national blue and green
economy aspirations. Partners
completed site analysis with JLL
and are now progressing with
delivery options.   
Growth Deal Plans
Growth Deal
Delivery
Delivery of North Ayrshire’s share of
the £251m Growth Deal programme
including: manufacturing space and
a digital hub at i3 in Irvine,
International Marine Science &
Environmental Centre at Ardrossan;
Centre for Research into Low
Carbon Energy & Circular Economy
at Hunterston; the development of
island marina projects and the Great
Harbour project in Irvine 
Growth Deal investment and
leverage of partnership and private
sector funding
Delivery of the Growth Deal
investment and leverage of
partnership and private sector
funding is ongoing.  Project
Business Cases are progressing
through the HM Treasury Green
Book Business Case processes in
line with the requirements of the
Deal.  
EDG&R
Leverage of AGD
funding
Securing additional leverage
including private sector investment
and external funding
Additional funding and profile to
enhance the outcomes achieved
through the AGD
Additional funding and profile to
enhance the outcomes achieved
through the AGD is continually
reviewed.  Leverage is reported
over all AGD projects and project
leads continue to apply and
negotiate funding applications and
partnership agreements.   
EDG&R
Destinations / Visitor Hubs
Commercial/leisure
investment in
Ardrossan
Review of market potential for
commercial opportunities within
Ardrossan
Delivery of new commercial uses
alongside public investment
The potential for commercial
investment continues to be
reviewed as the Coastal Quarter
project is being delivered. 
EDG&R

Page 19

Appendix 1 
Inclusive and Green Economy 
Inward Investment 
2023-25 Action 2026 Outcome 2025 Update Lead Service
Supporting inward
investment
Engage with existing and new
businesses to support inward
investment including the co-
ordination and review of enquiries
and assessment of contribution to
net zero, CWB and socio-economic
impact
Inward investment is secured across
North Ayrshire
There have been 20 new secured
investments with c.300 new jobs
predicted. These only relate to
businesses that we have secured
and are operational at this time.
This will increase given larger
developments including XLCC at
Hunterston. 
Current open inward investment
enquiries are significantly related to
the green sector and supply chain
and continue to be progressed. 
EDG&R
Supporting inward
investment
Review NAC land and assets’
potential to deliver on inward
investment enquiries
Inward investment is secured across
North Ayrshire
Review is ongoing to identify
priority land assets linked to
potential opportunities.
Development of This Is North
Ayrshire (TINA) website to enable
Land and Assets to be captured
and promoted through this portal as
part of offer. 
EDG&R
Development of Commercial Estate
Commercial estate
improvements
Review of commercial estate to
identify opportunities to improve or
redevelop council assets to
encourage local business growth
utilising Investment Fund
Improvement of commercial estate
to allow business growth
Review remains underway. The UK
Government LUF3 funding has
been secured to enable the delivery
of the Ayrshire Commercial and
Low Carbon Infrastructure projects.
Informed by market feedback. The
North Ayrshire proposal includes
the delivery of new energy efficient
commercial property and
associated low carbon
infrastructure at key employment
EDG&R

Page 20

Appendix 1 
including Kyle Road, Annickbank
and i3.  
Commercial estate
development
Completion of technical design,
funding secured and contractor
appointed for additional office
pavilion at Annickbank for
construction in 23/24
Completion and long-term lease of
space, securing local employment
350m2 of new modern, energy-
efficient business space achieved
practical completion March 2024.
EDG&R
Commercial estate
development
Identify opportunities and apply for
funding to support the delivery of
new commercial estate development
New commercial estate
development to support business
growth (subject to funding)
Employment land appraisal
completed Feb 2024. The appraisal
will support the Evidence Report for
the next Local Development Plan
(LDP3) and the Regeneration
Delivery Plan by informing
proposals to encourage local
business growth through
improvements or redevelopment of
the Council’s commercial estate. 
EDG&R
Commercial estate
development
Implement next phase of
commercial estate development at
Kyle Road, Irvine including: securing
funding package and necessary
permissions and consents
Completion and long-term lease of
space, securing local employment
The UK Government LUF3 funding
has been secured to enable the
delivery of the next phase of
development.
EDG&R
Commercial estate
development
Review of third-party assets for
acquisition to support commercial
estate delivery
Improvement of commercial estate
to support business growth
Review remains ongoing however
funding opportunities are currently
limited to support acquisition and
delivery. 
EDG&R
Harbour Master’s
House, Irvine
Improvement of derelict Council
property and development of
proposals for market opportunity 
Delivery of new commercial uses
alongside public investment at Great
Harbour
Conservation works completed in
the second half of 2024, utilising
VDLF funds. Works included the
roof replacement, structural repairs,
external and internal demolitions to
create open-plan space for future
use, external clock restoration. 
EDG&R
Partnership Activity

Page 21

Appendix 1 
North Ayrshire
ISLANDS
Programme
Implement ten year Island Plans for
Arran and Cumbrae working in
partnership with local island
communities and stakeholders,
Highlands and Islands Enterprise
and the Scottish Government
Development of strategic Island
Plan projects and leverage of
external funding
In early 2024 the pilot was
mainstreamed and takes forward
the next steps and ambitions of
Arran and Cumbrae as the ‘North
Ayrshire ISLANDS Programme’. 
Support and promote the islands as
wellbeing economies through the
delivery of the strategic Local Island
Plans, to thrive economically,
socially and environmentally.  
Striving to create opportunities for a
prosperous, fair, growing and
greener Arran and Cumbrae, in line
with their unique challenges and
opportunities and aligned with the
National Islands Plan, National
Strategy for Economic
Transformation (NSET), Community
Wealth Building and the Ayrshire
Regional Strategy (RES). 
EDG&R
North Ayrshire
ISLANDS
Programme
Develop and facilitate Island Plan
Steering Groups
Long term strategic direction and
community and stakeholder
engagement in the implementation
of Island Plans
The programme continues to
develop and strengthen effective
and valuable partnership working
and opportunities for peer-to-peer
exchange to improve our islands
wellbeing, exchange ideas on
issues affecting islands and ensure
the voices and needs of our island
communities are effectively
communicated at all levels. 
EDG&R
Partnership
Opportunities
Identify partnership opportunities for
regeneration delivery with private
sector and third sector
Partnership opportunities for
delivery and maximisation of funding
and resources
Work is ongoing to identify
additional partnership opportunities. 
Multiple partnerships have been
developed through the AGD. 
EDG&R

Page 22

Appendix 1 
Ardeer Continue to engage with NPL to
identify any opportunities at Ardeer
that complement the AGD Great
Harbour masterplan investment at
Irvine Harbour and Beach Park.
Delivery of AGD investment and
leverage of private investment
The Council continues to scope out
opportunities with NPL as
landowner of Ardeer. 
EDG&R 
Enabling Infrastructure
Transport Infrastructure 
2023-25 Action 2026 Outcome 2025 Update Lead Service
Ardrossan Harbour Finalise funding package and
partner agreements; and Publication
of tender package and award of
contract for marine and landside
works to enable construction
Completion of harbour regeneration
programme with partners
NAC carried out significant work
with Transport Scotland and Peel
Ports Group to move forward with a
revised business case. In February
2025, the Scottish Government
announced its intention to enter
negotiations directly with Peel Pots
Group (PPG) through CMAL to
purchase the port. NAC remains a
key stakeholder and the outcome is
awaited following the April 2025
Ardrossan Harbour Task Force
meeting with the Cabinet Secretary
for Transport.   
EDG&R
Transport Policy Public consultation, finalisation and
adoption of Local Transport Strategy
for 2023-28
Confirmation of local transport
priorities and actions for
implementation
Complete  EDG&R

Page 23

Appendix 1 
Transport Policy Promotion of North Ayrshire
transport priorities for inclusion
within national and regional
transport policy including the
Regional Transport Strategy (RTS)
and Islands Connectivity Plan (ICP)
Funding and delivery of local and
regional transport priorities
The Active Travel and Transport
team have contributed to
consultations on Strathclyde
Partnership for Transport’s (SPT)
Regional Bus Strategy, SPT’s
Active Travel Strategy, SPT’s Clyde
Metro, Transport Scotland’s Islands
Connectivity Plan – Strategic
Approach and the Long-Term Plan
for Vessels and Ports consultation.   
EDG&R
Transport Policy Support the completion of the B714
Upgrade Full Business Case and
design processes including
submission to UK Government to
facilitate construction 
Completion of B714 Upgrade The design has been completed,
and the contractor works are out to
tender. The Compulsory Purchase
Order was approved and is being
progressed. The draft FBC is under
review by the Department for
Transport (DfT). This will be
finalised upon receipt of the tender
costs. Works are anticipated to
begin in September 2025. 
EDG&R and
Neighbourhood
Services (NS)
Active Travel Identify priorities for and implement
new and improved active travel
route infrastructure across North
Ayrshire informed by the revised
LTATS
Securing external funding and
implementation of projects
Priorities have been identified, and
funding has been sought from the
Active Travel Infrastructure Fund
(ATIF) and other funding sources. A
proportion of the ATIF Tier 1
funding for 2025/26 has been
allocated to projects contained
within the LTATS.  
EDG&R
Active Travel Implement the recommendations of
the Community Renewal Fund
Islands Connectivity Study with
partner organisations
Delivery of a network of
infrastructure to support active and
sustainable travel and a Mobility as
a Service pilot project on Arran and
Cumbrae.
Following discussions with the local
communities and key stakeholders
nine cycle racks were purchased
and installed in Cumbrae 2024/25.
A location for a solar electric bike
charging station could not be
EDG&R

Page 24

Appendix 1 
progressed however a new location
will be identified in 2025/26. 
Active Travel Complete the Ardrossan
Connections Street Design Project
focused on Glasgow Street, Princes
Street and Montgomerie Street with
Sustrans
Implementation of improvements to
encourage active travel, improve
residential environment and link
major development projects
Sustrans advised that they are no
longer able to resource the
Ardrossan Connections project.
This is due to the current national
budget position and a need to focus
on projects which can be
progressed more quickly within
available resources. 
EDG&R
Public Transport Investment in public transport
infrastructure improvements
informed by the revised LTATS
Improvement of the public transport
network for everyday journeys
No funding was available to
improve public transport
infrastructure in 2024/25. However,
a small amount of residual funding
from the Community Bus Fund was
used to replace nine shelters at bus
stops. Additionally, SPT replaced
three damaged bus shelters
through their own budgets. 
EDG&R
External Grant Support
External Funding Work with partners to identify
funding opportunities and submit
funding applications to maximise the
potential of regeneration resources
and funding
Submission of successful funding
applications on an annual basis to
enable project implementation
Funding was received in 2024/25
from the Scottish Government’s
Active Travel Infrastructure Fund
Tier 1 and Tier 2; Cycling Scotland;
SPTs People and Place
Programme; Scottish Government’s
People and Place Local Authority
Direct Award; and Sustrans to
enable capital projects totalling
£1.885m and revenue projects
totalling £0.228m to be completed. 
Funding applications/requests were
also submitted to SPT, Strategic
Timber Transport Scheme (STTS),
Active Travel Infrastructure Fund
EDG&R

Page 25

Appendix 1 
Tier 2 (ATIF2) for 2025/26. We are
currently awaiting the outcomes of
these bids. 
A successful bid was submitted to
the SPT People and Places
Programme 2025/26, which
secured £157,000 revenue funding
for our Travel Smart Programme
and £200,000 capital for Real Time
Passenger Information signs in
Garnock Valley and North Coast. 
Funding has been secured from the
Scottish Government’s People and
Place Local Authority Direct Award
for 2025/26, which secured
£82,673.10 revenue funding and
£41,336.66 capital funding. 
Community
Funding
Support communities to identify
funding opportunities and submit
funding applications to implement
community regeneration priorities
Submission of successful funding
applications on an annual basis to
enable project implementation
Support has been provided to
workplaces and communities to
obtain funding for cycle shelters.
This included Abbey Croft Care
Home in Kilwinning, which received
funding from Cycling Scotland to
install a cycle shelter. 
CC / EDG&R
Digital Infrastructure 
Broadband Support the roll out of R100
Broadband programme and raise
awareness of the Scottish
Broadband Voucher Scheme
(SBVS) and the UK Gigabit
Broadband Voucher Scheme
Improved broadband coverage
across area and increased vouchers
uptake
North Ayrshire continues to act as
the lead liaison for the Scottish
Government on the R100
programme, supporting its ongoing
rollout and maintaining engagement
with Project Gigabit. At present no
active procurement lots currently
cover North Ayrshire.
EDG&R

Page 26

Appendix 1 
The Digital Connectivity webpage
remains a key resource for
residents and businesses, offering
guidance on available schemes and
helping inform regional telecoms
discussions. A Digital Connectivity
Layer that will map infrastructure
coverage and overlay it with
strategic investment zones is being
developed with the GIS team. 
Connectivity Develop the Digital Renewal route
map and approach to support Digital
Economic Transformation, focusing
on four pillars: Connectivity
(including infrastructure), Digital
Skills, Innovation, and Digital
Inclusion
Improved digital connectivity
growing a strong and resilient digital
economy delivering digital economic
transformation
Focus has moved from planning to
delivery through strategic pilot
initiatives. The Smart Infrastructure
Pilot Programme (SIPP), currently
being delivered at Great Harbour, is
trialling a public-sector-led model
for digital infrastructure supporting
CCTV, IoT sensor for weather,
footfall and public and event Wi-Fi.
The Transformation Team’s newly
established SMART Project Group
is using the SIPP as a pathfinder
for wider smart place development.
This includes connecting with other
Local Authorities to share learning
and explore opportunities in areas
such as housing, care, and health
integration. 
A Digital Infrastructure &
Connectivity Plan (DICP) is being
progressed in parallel to improve
how we plan. This will also support
pipeline development and maximise
EDG&R

Page 27

Appendix 1 
the impact of internal and external
investment. 
Strategic
Connectivity
Review the digital investment
through AGD to maximise the
benefits to gain a competitive
business advantage and support the
development of a Digital Masterplan
for Ayrshire 
Delivery of digital investment to
secure competitive advantage for
North Ayrshire and support business
growth and encouraging private
sector investment
At the regional level, the Ayrshire
5G Innovation Region (5GIR)
continues to strengthen
collaboration across the three
Ayrshire councils and partners
including UWS, NMIS, Ayrshire
College, and the Scotland 5G
Centre (S5GC). Through the new
Ayrshire Digital Economy
Ecosystem (ADEE) approach, the
programme is aligning delivery
across innovation, skills,
infrastructure, and business
adoption. 
To date, the 5GIR programme has
delivered 19 active use cases,
including the deployment of 5G
Mobile Private Networks at three
key sites creating wireless
innovation hubs tailored to
advanced manufacturing and
immersive learning, and 12
advanced wireless business
adoption projects, improving
productivity, operational efficiency,
and upskilling employees across
sectors. 
The region is preparing for the next
phase through the Digital
Innovation Accelerator (DIA) which
will develop stronger links to
Scottish Enterprise’s Capital
Investment Fund under the national
Productivity Mission. This will
EDG&R

Page 28

Appendix 1 
support scale-up activity, innovation
diffusion, and regional investment
readiness. 
This collaborative effort has also
unlocked an additional £1.5 million
in commercial investment from
Vodafone. This investment will
significantly upgrade mobile 5G
infrastructure across strategic North
Ayrshire sites, including the i3
Enterprise Area, enhancing mobile
coverage for residents, businesses,
and future digital services. 
Low Carbon Economy
Review of land and
assets for low
carbon delivery
Review of potential for land assets
to support low carbon project
delivery and contribute to net zero
targets including: new tree planting;
renewable energy; food growing;
and electric vehicle projects
Maximisation of land and assets to
deliver low carbon projects and
Contribution to net zero ambitions
The Council’s Renewable Energy
Strategy is being developed, with a
draft report expected in late May.  A
series of stakeholder engagement
sessions have been undertaken to
support the strategy, which
considers large scale renewable
energy projects and the potential
for community participation and
ownership. 
£2.8m of funding has been secured
from Transport Scotland to support
the Electric Vehicle Infrastructure
Fund (EVIF) project with Ayrshire
Roads Alliance, supported by
Scottish Futures Trust. A
procurement activity is underway,
led by East Ayrshire Council, to
secure a private sector partner to
install a further 307 EV charge
EDG&R / NS /
Sustainability,
Corporate
Property &
Transport
(SCP&T)

Page 29

Appendix 1 
points across Ayrshire, through a
concession contract.  The private
sector partner would operate and
maintain the existing and new
public charge points. A series of
land ownership checks are being
undertaken and will be provided in
the second phase of the
procurement activity. It is intended
that the partner will be appointed by
November 2025. 
Delivery of low
carbon projects
Identify opportunities for innovative
delivery of low carbon projects
including tree planting; renewable
energy; food growing; and electric
vehicle projects
Delivery of low carbon projects and
contribution to net zero ambitions
The Council’s Sustainable North
Ayrshire strategy was approved by
Cabinet on 5 December 2023 and
is the Council's route map to
achieving net zero carbon
emissions by 2030.  The strategy
contains nine strategic priorities
and a range of actions under 5
workstreams, namely: 
• Energy
• Nature
• Transport
• Waste
• Adaptation
A series of energy audits are being
undertaken internally to identify
decarbonisation measures with
consultancy support sought for
larger, more complex buildings. 
The Investment Fund is being
utilised to support a pipeline of
decarbonisation projects, and
external funding is also being
sought to support this work.  
Physical
Environment
/ NS / EDG&R /

Page 30

Appendix 1 
Behaviour change also plays a vital
role in our route to decarbonisation,
with a cross-service
decarbonisation working group
being established to utilise league
table data, project registers and
promote positive energy efficient
action across the Council.  Carbon
Literacy training is also being
investigated for dissemination in
Autumn 2025. 
Flood Protection
Schemes
Implementation of the Millport
Coastal Flood Protection Scheme
and development of the River Irvine
Scheme
Implementation of flood protection
schemes
Millport Coastal FPS was
completed in October 2024.  NAC
have requested funding from the
Scottish Government / COSLA joint
funding distribution group to
develop a flood protection scheme
for the Lower Irvine area, Fairlie
and Brodick & Lamlash in Arran.
This is still under review and no
funding has been awarded.
Development funding has also
been requested for two smaller
flood protection schemes in Largs
and Saltcoats/Stevenson. 
NS
Active Travel Hub Deliver the Trinity Active Travel Hub
and Travel Smart programme to
support active and sustainable travel
Modal shift to active and sustainable
travel / contribution to net zero
ambitions
The Travel Smart programme has
been successfully delivered during
2024/25 utilising SPT’s People and
Place Programme and the Scottish
Government’s People and Place
Local Authority Direct Award. The
Trinity Active Travel Hub has moved
to a more mobile operation with
Trinity on the Move, located within
libraries throughout localities within
North Ayrshire. The programme will
continue to be delivered in 2025/26.
EDG&R

Page 31

Appendix 1 
Low Carbon Hub Complete the £1.96m ERDF Low
Carbon Travel and Transport funded
Ardrossan Low Carbon Hub
including path works, e- bike and EV
infrastructure implementation.
Delivery and implementation of the
project
The North Crescent Coastal Path
Phase 2 was delivered utilising
funding from Sustrans and the
Scottish Government’s Active
Travel Infrastructure Tier 2 fund.
The project is now complete. 
EDG&R
Solar Photovoltaic
Farm development
Detailed development of Solar PV
Farm at Nethermains and
Shewalton, Irvine including:
procurement, planning, grid
connections and design. 
Investigation of renewables
opportunities at i3
Completion of Solar PV farms by
end of 2024; regeneration of the
former Nethermains and Shewalton
Landfill Sites; and contribution
towards net zero ambitions
Ameresco are the appointed
design, build, operate and
maintenance contractor for both
Nethermains (7.48MW) and
Shewalton (5MW) solar PV farms. 
Construction of both sites has been
completed, with Scottish Power
Energy Network's communication
and commissioning works
estimated to be completed by the
end of June 2025. 
A Solar PV Farm Board continues
to meet every 2months, with
representation from Economic
Policy, Finance, Legal,
Procurement, PMI, Sustainability,
Transformation, and Waste
services.
SCP&T

Page 32

Appendix Two – Regeneration Delivery Plan Funding Proposals 
The following provides a summary of each of the funds and the proposed approach for
2025/26. The proposals have been identified from the Regeneration Delivery Plan action
programme and an assessment of the: 
- Projects’ stage of development;
- Fit with the fund objectives and priorities;
- Potential benefits;
- Budget available;
- Ability to secure match funding;
- Deliverability of the project(s) within funders’ timescales; and
- Cross-Service collaboration. 
This approach aims to implement a range of projects that deliver impactful improvements in
line with the Regeneration Delivery Plan and the various funding streams’ ambitions. Where
there is an underspend within one of the allocations in 2025/26, it is proposed that the
Executive Director (Place) will reallocate any underspend across the other identified actions
following engagement with the Portfolio Lead. 
Place Based Investment Programme 
The Scottish Government established the five year £325m Place Based Investment
Programme (PBIP) in 2021/22. Underpinned by the Place Principle, this aims to support
community-led regeneration, town centres and the 20-minute neighbourhood ambitions.
The main objectives of the Programme are to: 
• Link and align place based initiatives and establish a coherent local framework to
implement the Place Principle;
• Support place policy ambitions such as town centre revitalisation, community led
regeneration, 20-minute neighbourhoods and Community Wealth Building;
• Ensure that all place based investments are shaped by the needs and aspirations of
local communities; and
• Accelerate the ambitions for tackling inequality and disadvantage, wellbeing and
inclusive economic development, net zero, community involvement and ownership 
Local Government is a key partner in delivering the Programme and will receive a share of
the funding over the five years to support and advance local priorities. A £0.761m allocation
is anticipated for the current financial year however this has still to been formally confirmed.
No funding commitments can therefore formally be made at this stage. The allocation will
require to be fully expended, or at a minimum financially committed, by 31 March 2026. Any
unused grant will require to be repaid to the Scottish Government unless otherwise agreed
by Scottish Ministers. 
The table below outlines the proposal for the expenditure of the allocation, subject to formal
confirmation of an award. The proposals aim to support the delivery of actions identified in
the Regeneration Delivery Plan that align with the Place Based Investment Programme
Outcomes.

Page 33

Project Allocation
Dockhead Street, Saltcoats
Public realm improvements including full replacement of the block paving,
replacement drainage full length, upgraded lighting installation, new street
furniture. This includes providing new lighting provision to enable simple
installation of Christmas Lights.
£0.250m
Community Project Fund
Grant scheme to support community led place based project development
and implementation across North Ayrshire. This provides 50% match
funding to UK SPF allocation, recognising over subscription to previous
schemes.
£0.250m
Repurposing Property Grant Fund
To continue the implementation of the Repurposing Property Grant Fund
which supports landowners and community groups to bring back vacant land
and properties to positive use by funding feasibility studies, investigation
work, detailed designs, statutory approvals and delivery.
£0.170m
Public Space Camera
Re-deployable camera to support public safety and project delivery.
£0.050m
Beith Kirk
Supporting sustainable repairs to the historic grade C listed building to
preserve the asset and ensure it is available for future generations.
£0.041m
Total £0.761m 
Vacant and Derelict Land Fund 
The Scottish Government's Vacant and Derelict Land Fund (VDLF) aims to tackle the
presence of long-term vacant, for 15 years or longer, and derelict land in Scotland. In doing
so, it aims so stimulate economic growth, job creation, an improved environment and
quality of life. From its inception in 2007, access to the Fund was restricted to five local
authorities to focus the available financial resource and prioritise authorities most impacted
by both the extent of vacant and derelict land and levels of deprivation. 
A review in 2015, resulted in North Ayrshire Council benefitting from access to the Fund
from the financial year 2016/17. The other four authorities which currently benefit are South
Lanarkshire, North Lanarkshire, Fife and Glasgow City Councils. Funding is limited to sites
that have been vacant for at least 15 years and are between 0.1ha and 99ha in size, with a
preference of Council ownership or a landowner agreement in place. 
In addition to the original funding objectives, the 2025/26 fund will consider a range of
project types which meet the key place-based objectives and contribute to the wider social
and economic regeneration outcomes of the fund. This could now include projects which
involve affordable housing and public realm improvements, which can demonstrate that
they contribute to a wider place plan which: 
• supports place policy ambitions such as town centre revitalisation, community led
regeneration, 20-minute neighbourhoods and Community Wealth Building and the
project forms part of a wider place based development e.g. an affordable housing
development alongside community provision;
• demonstrates that all place-based investments are shaped by the needs and aspirations
of local communities;

Page 34

• accelerates our shared ambitions for net zero, wellbeing and inclusive economic
development, tackling inequality and disadvantage including child poverty, community
involvement and ownership.  
The fund is not intended be a primary source of funding for: 
• Projects focussed on housing or non social/affordable housing which do not contribute
to a wider place plan.
• Major infrastructure projects relating to transport.
• Purchase of moveable infrastructure, furniture and fittings.
• Projects relating solely to hotel or retail developments are unlikely to be supported if
there are no clear regeneration outcomes.
• Projects that focus solely on public realm improvements, new roads / paths or upgrades
are unlikely to be funded where these are not part of a wider regeneration project and
will not contribute to regeneration outcomes.
• Flood protection/work/upgrades are not eligible.
• Staffing Costs 
A Local Delivery Plan requires to be submitted to the Scottish Government to allow
Ministerial approval of the expenditure of the funding in 2025/26. In developing the
proposals for this, several factors have been considered, including the: 
• Scottish Government funding criteria;
• Economic development focus of the funding;
• The priority sites identified of Irvine Enterprise Area, Ardrossan Campus Site, Lochshore
and Irvine Harbourside and their stage of development;
• Alignment with the North Ayrshire Regeneration Delivery Plan (2021) and Vacant and
Derelict Land Strategy (2023);
• Deliverability of projects within the funding timescales;
• Need to balance feasibility and site preparation work, with interventions that see
physical space and employment created;
• Need to secure a spread of interventions in terms of type and geography; and
• Scottish Government’s aspiration for circa 25% to be spent on greening projects. 
An allocation of £1.561m has been confirmed for 2025/26. Aligned with the actions
identified in the Regeneration Delivery Plan and Vacant and Derelict Land Strategy, the
following projects are proposed for submission as local delivery plans. These will be
formatted as delivery plans and submitted to the Scottish Government, subject to Cabinet
approval: 
Project Allocation
Levelling Up For Ayrshire: Commercial and Low Carbon Infrastructure
Funding to contribute to the North Ayrshire Commercial and Low Carbon
Infrastructure LUF project. This project aims to address market failure in the
delivery of new energy efficient commercial property alongside the provision
of associated low carbon and active travel infrastructure at Kyle Road,
Annickbank and i3 sites.
£0.432m
Lochshore Garden, Activity Hub and Associated Works
To support works to conclude Phase 1 of the Lochshore Masterplan,
including detailed design and delivery of access, green space,
infrastructure, facilities and environmental improvements. 
£0.350m

Page 35

99 Nelson Street, Largs – Town Centre Living*
Funding to contribute to the refurbishment of 99 Nelson Street which aims to
regenerate a block of flats which have fallen into significant disrepair. The
homes were acquired due to their poor condition and the Council proposes
to convert the block into three homes for affordable Council rent. The costs
include enhanced building fabric and the provision of Air Source Heat
Pumps to provide net zero direct emissions heating systems.
£0.300m
Repurposing Property Grant Fund
To continue the implementation of the Repurposing Property Grant Fund
which support landowners and community groups to bring back vacant land
and properties to positive use by funding feasibility studies, investigation
work, detailed designs, statutory approvals and delivery.
£0.250m
Ardrossan Coastal Quarter Residential Masterplan
Masterplan to re-establish the residential development capacity, market
interest and associated value of land adjacent to the Ardrossan Campus.
£0.150m
Maintenance Works to VDL Sites
Maintenance works associated with sites that are unlikely to be developed in
the short/medium term.
£0.079m
Total £1.561m 
*The Nelson Street proposal is subject to further engagement with Scottish Government. If
Scottish Government do not support the delivery plan proposal, the funding allocation will
be reallocated to the Lochshore Garden, Activity Hub and Associated Works to support
additional works. 
Active Travel Infrastructure Fund (ATIF) Tier 1 
The Scottish Government’s Active Travel Infrastructure Fund, managed by Transport
Scotland (TS) on behalf of the Scottish Government, supports the design, development,
and delivery of active travel infrastructure measures across all 32 LAs in Scotland. 
Funding of £962,000 has been secured through ATIF Tier 1. The table below sets out the
2025/26 proposals. This approach aims to support a range of eligible projects across North
Ayrshire and secure additional funding to maximise and accelerate delivery. 
ATIF Tier 2 funding has been applied for several of the projects listed below as noted in
Appendix 3. Should the funding be successful then Tier 1 funding will be allocated to
alternative projects under the same theme. 
Project Allocation
Active Travel Route Construction:
To support delivery of the Local Transport and Active Travel
Strategy Actions for improving Active Travel Routes on strategic
corridors and local links. 
£442,000
Active Travel Facilities:
To support delivery of the Local Transport and Active Travel
Strategy Actions to expand and improve facilities for Active Travel
such as eBike charging infrastructure and cycle stands.
£32,000
Future Years Feasibility Studies and Design Development: 
To support the preparation of feasibility studies and preliminary
designs for active travel projects; and finalise projects to
construction ready status to enable bids to ATIF Tier 2. 
£250,000

Page 36

LUF Match Funding: 
To support the delivery of the LUF Active Travel Projects.
£125,000
Route Monitoring: 
To support the network of pedestrian and cycle counters across
North Ayrshire including the installation of new infrastructure. 
£12,000 
Staff costs and resourcing:
To support the existing externally funded posts within the Active
Travel and Transport Team. 
£101,000 
Total £962,000 
Strathclyde Partnership for Transport Capital Programme
Strathclyde Partnership for Transport’s (SPT) Capital Plan sets out the funding programme
for projects to be delivered by SPT and partners on an annual basis. Priorities for funding
are informed by the National, Regional and Local Transport Strategies. The following
projects for 25/26 were approved by SPT’s Partnership Board meeting on the 14 March
2025. 
An award for Cumbrae Ferry Bus Stop and Queuing facilities was also approved through
this process. The works are now being delivered by CMAL as part of the overall Cumbrae
Slip Improvements and the SPT approved funds are therefore not required. 
Project Allocation
Ardrossan Harbour Interchange* £250,000
Total £250,000
*A grant offer letter has not currently been received therefore funding is not formally
confirmed at this stage. Cabinet approval is therefore subject to its receipt and
implementation of the project is subject to the outcome of the Scottish Government’s
investigations regarding the purchase of Ardrossan Harbour. 
Strathclyde Partnership for Transport People and Place Programme
The long-term success of Active Travel depends on a close relationship between
infrastructure delivery and behaviour change activities. Behaviour change programmes
remain central to the delivery of the visions set out in the Local Transport and Active Travel
Strategy, the national Active Travel Framework, and the Cycling Framework for Active
Travel. 
The SPT People and Place Programme covers active travel behaviour change and access
to bike initiatives. In 2024/25 this programme assisted in funding the Council’s Travel Smart
Behaviour Change Programme including undertaking workplace engagement across a
range of businesses to support active travel, delivering active travel training, e-bike
sessions, walking programmes and step count challenges, providing personalised travel
planning and delivering the Beat the Street programme. The following projects for 2025/26
were approved by SPT’s Partnership Board meeting on 14 March 2025. 
Project Revenue
Allocation
Capital
Allocation
Real Time Passenger Information signs (RTPI) - Garnock
Valley and North Coast
N/A £200,000
Travel Smart Programme – Communities and Workplaces £157,000 N/A
Total £157,000 £200,000

Page 37

People and Place Local Authority Direct Award 
The Scottish Government’s People and Place Local Authority Direct Award, managed by
Transport Scotland (TS), supports sustainable and active travel behaviour change
initiatives. The funding is provided directly to local authorities on a pro-rata basis. In
2024/25 this programme assisted in funding the Council’s Travel Smart Behaviour Change
Programme. For 2025/26, the Council has been awarded the following to continue the
delivery of the Travel Smart programme: 
Local Authority TOTAL Revenue Capital
North Ayrshire £124,009.66 £82,673.10 £41,336.55

Page 38

Appendix 3 – Project Updates 
5G Innovation Regions (5GIR)
North Ayrshire is the lead authority for the Ayrshire 5GIR initiative on behalf of the regional
Digital Economy workstream, the three Ayrshire councils and associated partners, including
the University of the West of Scotland (UWS), Ayrshire College, the Scotland 5G Centre
(S5GC) and the National Manufacturing Institute Scotland (NMIS). The project was
successfully awarded £3,791,000 by the UK Government’s Department of Science,
Innovation and Technology (DSIT) in 2023. Ayrshire has been granted a 6-month extension
to September 2025 with additional funding of £175,000. This additional funding will support
a Digital Innovation Accelerator (DIA) working closely with Scottish Enterprise to ensure
alignment with their Capital Investment funding for productivity mission. 
The Ayrshire 5GIR vision is to become the “UK’s premier manufacturing-focused 5G hub”.
This will be driven by five transformative principles: technological excellence, a thriving
innovation ecosystem, sustainable economic growth, skills and talent development, and
influential investment strategies. Investment will be centred around three strategic
locations: the Digital Processing Manufacturing Centre (DPMC) in Irvine, the Aerospace
Innovation Hub (AIH) in Prestwick, and the Ayrshire Innovation Park (AIP) in Moorfield,
Kilmarnock. The overall project comprises the following six workstreams, three of which are
led by NAC: 
Workstream Title Lead
Organisation
Value
1 Digital Process Manufacturing Centre (DPMC) NAC £1m
2 Aerospace Innovation Hub SAC £0.9m
3 Small to Medium Enterprises Internet of
Things Adoption
EAC £0.45m
4 Tourism Events NAC £0.5m
5 Digital Ambassador / Immersive Learning SAC £0.3m
6 Ecosystem Development NAC - 
Smart Infrastructure Pilot Programme
£242,000 was secured from the UK Government’s Department of Science, Innovation and
Technology (DSIT), to enhance the £14m Ayrshire Growth Deal Great Harbour project. The
Great Harbour SIPP project is a transformative Digital Infrastructure initiative designed to
integrate innovative technology with our rich maritime history, creating a sustainable,
connected, and thriving waterfront destination. 
Key components include the provision of Internet of Things (IoT) sensors, CCTV
enhancements, and intelligent lighting systems. Future considerations also encompass
integrating advanced wireless connectivity solutions 5G, advanced Wi-Fi, EV charging
points and augmented reality experiences, further elevating the region's digital capabilities. 
The project aims to catalyse economic growth, enhance connectivity, attract investment
and interest from Mobile Network Operators (MNOs). It will adopt a learning-by-doing
approach which will inform a future SMART place strategy. 
Shared Prosperity Fund
The Communities and Place investment priority of the Shared Prosperity Fund aims to
enable places to invest to restore their community spaces and relationships and create the
foundations for economic development at the neighbourhood-level. Its objectives are to

Page 39

strengthen the social fabric and foster a sense of local pride and belonging and build
resilient, healthy and safe neighbourhoods. 
The investment priority requires Councils to be mindful of how interventions under this
priority align with the existing funding streams received from the Scottish Government
including the Place Based Investment Programme. The alignment with Scotland’s National
Strategy for Economic Transformation (NSET) also requires to be considered to ensure that
they contribute to a fairer and more equal society, new market opportunities and productive
businesses and regions. 
Thirteen interventions are identified under the investment priority. The approved North
Ayrshire Investment Plan supports delivery of projects across the range of interventions.
The approved Investment Plan outlined that the Communities and Place investment priority
would be comprised of a: Participatory Budgeting programme; competitive grant scheme for
communities; and funding allocation for Council projects. 
In 2024/25 the Communities and Place theme supported 19 community projects through
the competitive grant fund, with a total award of £600,000. 16 Council-led projects were
also supported across 2024/25. 
UK Government announced an additional year of the UK Shared Prosperity Fund for
2025/26 with the Communities and Place theme awarded a total budget of £674,348. The
additional year will continue the work identified in the Investment Plan approved by Cabinet
in 2022. Participatory Budgeting will be supported and delivered through Connected
Communities, with a value of £26,974, representing 1% of the UKSPF Budget. 
The competitive grant funding programme will be supported with £250,000, in recognition of
the shorter timescales for delivery and the reduction in overall funding for 2025/26. The
grant fund will be matched with an additional £250,000 from the Place Based Investment
Programme. The overall budgetary position reflects the interest from communities over the
previous two years of funding, both of which were significantly oversubscribed.
The additional match funding will seek to streamline the grant programmes within
regeneration and improve the user experience. 
As with previous years, small scale council-led regeneration projects will also be supported
within the SPF. The total budget for council projects is £397,374 (of which £376,535 is
capital) and this will support the projects below which align with the priorities of the funding,
the Regeneration Delivery Plan and support projects across all localities. Portfolio Holder
approval will be sought for any variations to the initial suite of projects below, with a
requirement to ensure delivery within the 2025/26 financial year. 
Project Allocation
Dockhead Street, Saltcoats
Public realm improvements including full replacement of the block paving,
replacement drainage full length, upgraded lighting installation, new street
furniture. 
£0.080m
Seagate Castle
Additional funding to carry out essential stabilisation and conservation works
at Seagate Castle and support common good contribution. 
£0.070m
Lochshore Garden, Activity Hub and Associated Works £0.125m

Page 40

To support works to conclude Phase 1 of the Lochshore Masterplan,
including detailed design and delivery of access, green space,
infrastructure, facilities and environmental improvements. 
Public Space Camera
Re-deployable camera to support public safety and project delivery.
£0.030m
Kilwinning – Development Funding
To support Kilwinning Abbey Tower, which was previously identified within
the Regeneration Delivery Plan, and the Kilwinning Main St public realm
enhancements.
£0.072m 
£0.377m 
Scottish Government’s Regeneration Capital Grant Fund
The Scottish Government’s Regeneration Capital Grant Fund (RCGF) has been delivered
annually in partnership with COSLA and local government. It supports locally developed
place-based regeneration projects that involve local communities, help to tackle inequalities
and deliver inclusive growth in deprived, disadvantaged and fragile remote communities
across Scotland. 
The 2025/26 programme was announced on 15 May 2025. This round of RCGF will
streamline the funding previously delivered through the Vacant and Derelict Investment
Programme (VDLIP) and RCGF through a single fund to support place based community-
led regeneration in disadvantaged communities. 
Expressions of interest are due by 27 June 2025. The Regeneration team will work cross-
service to identify suitable priorities in liaison with the Portfolio Holder and Executive
Director (Place). 
Scottish Government’s Islands Programme
The Islands Programme represents a £30million capital investment over five years to
support the delivery of the National Islands Plan. It aims to support projects which
encourage population growth and stem population decline and deliver on net zero
ambitions in a way that no-one is left behind. 
The 2024/25 Programme opened for applications in late summer 2024. North Ayrshire
Council submitted four applications. NAC were successful in receiving £414,425 for the
delivery of the Millport Town Hall Regeneration project. 
The 2025/26 programme was announced on 13 May 2025 with applications to be submitted
by 22 July. 
Project proposals require to use clear place based, Community Wealth Building principles
to support inclusive island growth while working to achieve Scottish Government’s Net Zero
ambitions and to support recovery from the impacts of the pandemic. They should: 
• meet the overall objectives of the Islands Programme;
• link directly to at least one of the National Islands Plan Strategic Objectives;
• ensure transformational impact against place-based priorities to accelerate local growth
and resilience;
• align with local critical infrastructure priorities and have the potential to collaborate with
other place-based investment opportunities to maximise benefits;
• demonstrate project readiness, collaborative and partnership models, project viability
and long-term sustainability;

Page 41

• demonstrate clear Community Wealth Building principles and community involvement
and engagement; and
• support Scottish Government Net Zero Ambitions and a Just Transition. 
Priorities for the 2025/26 round of the programme will be identified through engagement
with the Island Plan Steering Groups and island communities in liaison with the Portfolio
Holder and Executive Director (Place). 
Scottish Government’s Vacant and Derelict Land Investment Programme
The Scottish Government announced a 5-year £50M competitive Vacant and Derelict Land
Investment Programme (VDLIP) in 2021/22. This aims to tackle persistent vacant and
derelict land and support place-based approaches to delivering regeneration and
sustainable inclusive growth, as part of a ‘just transition’ to net-zero by 2045. The fund
complements the Place Based Investment Programme and is open for all local authorities
in Scotland to apply. 
Potential projects were previously identified for the 2024/25 round based on the funding
criteria, level of project development and delivery timescales with Council Services. The
following applications were submitted in order of priority and invited to Stage 2 assessment: 
i. Kyle Road Phase 2 (£892,990)
ii. 36 Bank Street Town Centre Living Pilot (£1.45M) 
In 2024/25 Scottish Government revisited previously shortlisted submissions, for North
Ayrshire, this included both project proposals. In April 2025, Scottish Government
confirmed the Kyle Road Phase 2 proposal was successful and an award letter is
anticipated in due course. This is the final round of VDLIP with the fund being streamlined
through the 2025/26 RCGF process. 
. 
Scottish Forestry’s Strategic Timber Transport Fund 
Since 2005, the Strategic Timber Transport Fund (STTF) has financed projects that
facilitate the sustainable transport of timber in rural areas of Scotland and deliver benefits
for local communities and the environment through innovative projects and partnerships.
North Ayrshire Council has previously been successful in securing funding from this
scheme for works in Arran. 
An unsuccessful bid of £327,031, including NAC match funding of £102,656, to improve
Machrie Moor Road and the String Road was submitted for 2025/26. 
UK Government’s Levelling Up Fund
On 20 November 2023, the UK Government announced fifty-five projects had been
provisionally selected to receive funding from the Levelling Up Fund Round 3. This included
£122 million for projects in Scotland, including the £17.5m Levelling Up for Ayrshire:
Commercial and Low Carbon Infrastructure proposal submitted by North Ayrshire Council. 
Informed by market feedback, the North Ayrshire proposal aims to address market failure in
the delivery of new energy efficient commercial property alongside the provision of
associated low carbon infrastructure at key employment areas in Irvine. The Irvine
investment concentrates on Kyle Road, Annickbank and i3 sites including

Page 42

The validation and onboarding process is now completed, with a signed Memorandum of
Understanding received in April 2025. This enables project delivery to commence in
2025/26 and conclude in 2026/2027. The proposed breakdown of the funding award and
match funding is detailed below: 
LUF3 Project Allocation
LUF Allocation 
Commercial Estate: Annickbank Phase 4 £5,606,808
Commercial Estate: i3 Flex Space Phase 2 £4,706,259
Commercial Estate: Kyle Road Phase 2 £1,509,450
Active travel paths: Strategic Investment Route (River Irvine paths) £2,386,826
Active travel paths: Riverside Way, Irvine & Long Drive £1,698,799
Active travel paths: Heatherhouse Road, Irvine (including potential
junction improvement costs)
£1,548,678
Total LUF Allocation £17,456,821  
Confirmed Additional Funding  
Vacant and Derelict Land Fund £2,038,065
North Ayrshire Council Capital Programme £2,000,000
Vacant and Derelict Land Investment Programme £892,990
Place Based Investment Programme  £150,000
North Ayrshire Regeneration Services £118,843
Active Travel Infrastructure Fund Tier 1 £125,000
Total Confirmed Additional Funding  £5,324,898  
Provisional Additional Funding  
Ayrshire Growth Deal £1,450,000
Vacant and Derelict Land Fund £432,000
Active Travel Infrastructure Fund Tier 1 £125,000
Total Provisional Additional Funding  £2,007,000  
Total £24,788,729 
UK Government’s Plan for Neighbourhoods 
On 30 September 2023, the UK Government announced that fifty-five towns across the UK
would benefit from up to £20 million of investment through endowment style funding over a
10-year period. Irvine was identified as one of the initial seven, now ten, towns in Scotland
to benefit from this funding. The award was confirmed at £19.509m. 
Following the 2024 General Election, the programme was reconfirmed within the UK
Government’s 2024 Autumn Statement. An updated prospectus and guidance
documentation were published in March 2025. The new ‘Plan for Neighbourhoods’
programme seeks to drive growth over the long-term and includes updated strategic
objectives and list of pre-approved interventions 
The updated programme requires a partnership approach between the local authority, the
Neighbourhood Board and the community. It is the responsibility of the Board, in
partnership with their Local Authority, to develop and deliver a ten-year vision for the town.
There is also a requirement for a more detailed four-year investment plan which will inform
the delivery of the programme from 2026 onwards. The Plans must be approved by the UK

Page 43

Government prior to implementation, these can be submitted any time from Spring to
Winter 2025. Additional guidance is awaited regarding the Regeneration Plans. 
The Irvine Neighbourhood Board was established in August 2024 and has met on five
occasions. NAC Officers work in partnership with the Board to facilitate and deliver on the
4-year investment plan and ten-year Regeneration Plan for Irvine. A report was submitted
to Council on 14 May 2025 which provided an update on the refreshed ‘Plan for
Neighbourhoods’ programme and approved the submission an update to UK Government
on the Irvine Neighbourhood Board. This included confirming the appointment of the Chair,
Vice Chair and Elected Member representatives. Progress will be reported separately to
Cabinet on the development of the Plans. 
Active Travel Infrastructure Fund (ATIF) Tier 2
The Scottish Government’s Active Travel Infrastructure Tier 2 Fund supports design/pre-
construction and construction ready Active Travel Infrastructure projects. With Sustrans
winding down the Places for Everyone programme by December 2025 the majority of
Active Travel infrastructure funding will be managed via ATIF Tier 2. 
The following projects were submitted for ATIF Tier 2 funding. It is expected that the
outcome of the bid assessments will be announced in May/June 2025. It is anticipated that
not all the projects below will be successfully funded. Submitting these applications
however sets out the Council’s ambitions to Transport Scotland and provides an overview
of the long-term active travel pipeline projects for future delivery. 
Project Allocation
Girdle Toll to Irvine AT Route; Feasibility Study £50,000
Dalry to Saltcoats (B714) AT Route; Feasibility Study £100,000
George Street/NCN Bridge, Stevenston; Detailed Design £83,600
Castlepark Circle to Eglinton Park (Phase 3); Detailed Design £65,326
Cumbrae Slip to Ferry Road junction AT Route; Detailed Design £60,000
B714 Active Travel Links; Construction £730,904
Brodick to Glen Rosa AT Route; Construction £326,790
Links to Eglinton Phase 2; Construction £429,000
Total £1,845,620 
The following projects are being put forward for funding by Active Travel Infrastructure Fund
Tier 2, as a continuation of projects previously funded by Sustrans. The outcome of the
applications is not known at this stage. Cabinet approval is therefore subject to the
confirmation of awards. 
Project Allocation
Old Caledonian Railway, Saltcoats AT Route Phase 2; Detailed Design £86,628
B777 Wider Corridor, Beith; Detailed design £188,908
B714 Sharphill to NCN, Saltcoats AT Route; Feasibility/Detailed design £161,240
Total £436,776