NORTH AYRSHIRE COUNCIL 
21 January 2025   
Cabinet 
Title:    Our Council Plan Six Monthly Progress Report 1 April to 30
September 2024 
Purpose:  To consider and approve Our Council Plan Six Monthly
Progress Report 1 April to 30 September 2024 
Recommendation:  Cabinet agrees to: (i) Approve Our Council Plan Six
Monthly Progress Report 1 April to 30 September 2024
attached at Appendix 1; (ii) Note the report will be
presented to the Audit and Scrutiny Committee for
consideration on 23 January 2025. 
1 Executive Summary 
1.1 Our Council Plan 2023-28 is the overarching strategy of our council and details
our council’s strategic priorities.  We have a statutory duty to publish information
that enables effective scrutiny of our performance.
1.2 This report presents the progress made in delivering our Council Plan 2023 to
2028 as at 30 September 2024. The report has been expanded to include further
details of our Transformation workstreams and integrate LGBF more timeously. 
Workforce planning information is included regarding the results of the Best
Value Thematic Audit on Workforce Innovation and a more general update will
be included in future updates.
1.3 Following Cabinet approval, our corporate performance reports are published on
our website www.north-ayrshire.gov.uk/performance.
2 Background 
2.1 Under the Local Government (Scotland) Act 1992 and Local Government in
Scotland Act 2003 we have a duty to demonstrate Best Value.  To ensure we
support our residents, fulfil our statutory duties and invite scrutiny, we actively
manage performance and develop our reporting to make it accessible and
engaging.
2.2 How we demonstrate our performance is defined in the Statutory Performance
Information (SPI) Direction 2021 for up to year ending 31 March 2025.  In

Page 2

December the SPI Direction 2024 was published.  It will take effect from reporting
years beginning 1 April 2025 for approximately three years.  However, to ensure
continuous improvement, elements of the new SPI Direction have also been
considered when developing this six-monthly report.  
2.3 Performance targets were set for 2024 to 2025 and for some quarterly indicators
it is not appropriate to set quarterly targets (for example, Community Asset
Transfers and carbon emissions). However, to ensure effective scrutiny, we
include a review of progress within the narrative of the report and compare
performance to date to year end targets.
2.4 A Best Value Thematic Audit focusing on ‘Workforce Innovation’ was conducted
by Audit Scotland and details how our council is responding to workforce
challenges through building capacity, increasing productivity and innovation.
Audit Scotland outlined our council has a clear vision for workforce planning in
our Council Plan 2023 to 2028 and demonstrated how agile working has been
promoted and strengthened by our council. It included recommendations relating
to how workforce planning is reported, which have been reflected in our Audits,
Inspections and Accreditations section of the progress report. A more general
update on workforce planning will be included in future reports to meet the
recommendation.
2.5 We recognise the concerns around LGBF data needing to be reported earlier. 
As the Improvement Service now provide scheduled data releases throughout
the year via their dashboard, we are able to report on LGBF data as it becomes
available throughout the year in our six-monthly reporting rather than separately
annually.  This will enable some of the data to be scrutinised by the Executive
Leadership Team, Cabinet and the Audit and Scrutiny Committee up to six
months earlier than previously.  We will seek to improve reporting on the LGBF
further, rationalising information where possible and including detailed feedback
from relevant services on their performance.  In this initial inclusion within the
reporting, detailed performance compared to family groups is included for each
indicator with fresh data.
2.6 We have embedded key contextual indicators from the Wellbeing Economy
Dashboard (formerly called the Inclusive Growth Dashboard) - which outlines our
council’s Wellbeing Economy journey. We will continue to work with the
Economic Policy Team to further embed this approach as the new Wellbeing
Economy Dashboard becomes established.  
3 Assessment of Performance 
3.1 Our Council Plan is a progressive plan building on previous work undertaken. As
a result, many areas are continuing to progress well from the previous Council
Plan.
3.2 There are 47 actions within our Council Plan, with one reported directly through
the Health and Social Care Partnership (HSCP) and excluded from this report.
From the remaining 46 actions, 45 are on target (green) for mid-year, and one is
slightly adrift of target (amber) as detailed below:

Page 3

• CP07 Maximising access to and uptake of benefits, entitlements and
financial advice: This action is currently slightly adrift of target (amber) due
to a delay in the review and refresh of the Financial Inclusion Strategy for
2024 to 2030. However, the strategy is due to be updated by early 2025 for
2025 to 2030 and delivery of support is continuing. During the first six
months of 2024 to 2025 this has included:
o Integration of welfare rights services through our in-house team moving
to single case working and an improved performance management
system.
o Improved and streamlined referral pathways for services in line with our
“Accessing our Council” transformation activity.
o Meeting targets for referrals to commissioned debt advice service.
o Increased capacity to support welfare rights within schools across North
Ayrshire, expanding the established successful approach from
secondary schools into primary and early years settings.
3.3 There are 26 performance indicators within our framework. At mid-year, the
status of 12 PIs were either unknown or data only, 11 were on target (green),
one was slightly adrift of target (amber), and two were significantly off target
(red). Of the two significantly adrift of target, one (CP_46) has previously been
reported on at year end.  The details of the second indicator are below.  
• CP_10 % of procurement spent on local enterprises: This indicator is a
ratio of our local spend against total spend. Though this ratio has decreased,
the amount of actual local spend has increased from £57.5million to
£71.5million. There was an increase of approximately £71million in overall
external spend, mainly due to an increase in large capital projects including
flood protection schemes and enabling works. These can only be carried
out by tier one contractors and there were no local tier one contractors who
could bid for these contracts. However, the tier one contractors reported
subcontracting to local suppliers to the value of £10million, which, if
considered in the above figure, would have increased the local spend
percentage to 28%, above our target of 26% for 2023 to 2024.
3.4 Though data is not available at mid-year for several indicators, the status of the
indicators compared to annual targets alongside the impact of our activities
captured within the body of the report, gives confidence that performance is on
track. Where quarterly targets are available, performance is stronger than
expected.  For example, the actual for CP_27 Street Cleanliness Index is 91.7%
clean against a target of 87% and participatory budgeting is currently sitting at
1.85% against a target of 1%.
3.5 Key Highlights
• Our most recent Best Value Thematic Audit focusing on Workforce
Innovation was positive, showing how our council is responding to current
challenges by building capacity, increasing productivity and innovation.
• Our council was successful in becoming one of Scotland’s Fairer Future
Partnerships (FFP).  This £350,000 investment in a Fairer Futures Team

Page 4

will enhance a systematic approach to addressing child poverty in North
Ayrshire.  
• Our council’s two new solar photovoltaic (PV) farms have progressed to
construction stage. Solar panels have been installed on the majority of the
former Nethermains landfill site in Kilwinning and good progress is also
being made at the former Shewalton landfill site.  They are expected to
generate £400,000 of revenue per year over 25 years as well as reducing
our carbon footprint.
• We have implemented our Strategic Housing Investment Plan 2024 to
2029, including starting on-site at Ayrshire Central Hospital in Irvine and at
the former Garnock Academy site in Kilbirnie and completion of sheltered
housing refurbishment projects at Cheviot Court, Irvine and Barnett Court,
Saltcoats. 
• Montgomerie Park Primary School opened in August 2024, achieving and
exceeding certification for energy efficiency meaning reduced operational
costs.  Passivehaus-certified, this construction will significantly inform
future sustainable construction projects.
• Almost £2.1 million in external funding has been secured to advance the
Local Transport and Active Travel Strategy.
• To date, 36,531 trees have been planted across North Ayrshire through
the 2030 Woodland: A Tree Planting Strategy.
• We commissioned a study into opportunities for Community Transport,
specifically examining the existing public transport provision on Arran and
in the Garnock Valley.
• We published our new Participation Strategy which will focus on raising
awareness of participation processes including locality partnerships and
enhance our budget consultation.
• Locality Plans were approved at Locality Partnership meetings in
September.  To date, £177,574 of community grants have been awarded
by Locality Partnerships this year.
• We have commenced a comprehensive review of our locality planning
framework.
• We have expanded our capacity to support Community Asset Transfers
(CATs) through engaging with our Active Schools team. We are currently
working with 19 community groups to progress CATs.
• A number of activities were delivered for our care experienced young
people through our Corporate Parenting Summer Programme, as well as
Active Schools and Community Partnership Officers working closely with
our Health and Social Care Partnership.  638 of our young people took
part, with 71% supported into longer term extra-curricular activity.  Over
65% of attendees felt safer, that they were achieving more and/or felt more
respected.
• Our Financial Inclusion Partnership is developing a communications plan
to help promote services to island residents, our gypsy traveller
community, those who are digitally excluded and residents with disabilities.
• 35 Modern Apprentices were recruited into our council in August.

Page 5

• 15 households on Cumbrae and 25 in Kilwinning have been identified for
improvements via the Energy Efficient Scotland: Area Based Scheme. 
This will help address the impact of energy costs and address fuel poverty.
• Four community renewable projects have been awarded £130,000 in
funding through the Community Renewable Energy Generation Fund.
• Our recycling performance is the third strongest in Scotland, improving
from 55.3% to 56.1% in 2023 (data recently released from SEPA).
• Our Transformation Programme continues to progress, with key
milestones reached within the Digital Workstream, Irvine Property Review
as well as the Nethermains and Shewalton Solar PV Farm detailed above.  
• The Transformation Board is overseeing service reviews across the
Learning Resource; Housing Service; Financial Inclusion Services;
External Residential Placements; Economic Development, Growth and
Regeneration; and Waste Services.
3.6 Key Next Steps
• We will establish our Fairer Futures Partnership team to bring a more
systematic approach to addressing child poverty in North Ayrshire.
• We will progress work as one of three places in the Collaborating for Health
Equity in Scotland (CHES) programme, which is being jointly led by Public
Health Scotland and the University College London Institute for Health Equity.
The aim of this programme is to strengthen and accelerate the action
underway to improve Scotland's health, increase wellbeing and reduce health
inequities. This work will complement the Fairer Futures Partnership Activity
to address child poverty.  (Though outside of the timescales for this report, we
were appointed to the CHES programme in November and further information
will be included in our Year End reporting.)
• We will complete the annual review of our Strategic Housing Investment Plan.
• Our Tenant Inspection Panel will scrutinise our Aids and Adaptations
provision.
• We will complete our review of our Locality Partnerships and present
proposals to Cabinet in early 2025.
• We will commence a comprehensive review of our approach to application,
assessment, award and compliance in relation to community funds and
grants.
• We will explore Community Climate Action Plans for our six localities.
• We will continue to provide support for local enterprise through the Business
Recovery and Sustainability Fund.
• We will develop a battery storage pilot scheme in non-domestic buildings to
maximise the use of existing roof mounted solar PV, helping support local
energy networks.
• We will continue to progress recommendations arising from the Audit
Scotland Best Value Thematic Work.
• We will continue to progress property rationalisation.
• We will commence our budget consultation for 2025 to 2026.

Page 6

4 Proposals 
4.1 Cabinet agrees to: (i) Approve Our Council Plan Six Monthly Progress Report 1
April to 30 September 2024 attached at Appendix 1; (ii) Note the report will be
presented to the Audit and Scrutiny Committee for consideration on 23 January
2025.
5 Implications/Socio-economic Duty
Financial
5.1  There are no financial implications arising from this report.
Human Resources
5.2 There are no human resource implications arising from this report.
Legal
5.3 There are no legal implications arising from this report.
Equality/Socio-economic
5.4 There are no equality/socio-economic implications arising from this report.
Climate Change and Carbon
5.5 There are no climate change and carbon implications arising from this report.
Key Priorities
5.6 The Progress Report enables the effective scrutiny of the delivery of our Council
Plan strategic priorities.
Community Wealth Building
5.7 There are no Community Wealth Building implications arising from this report.
Consultation
5.8 The Executive Leadership Team (ELT) reviewed and scrutinised the report prior
to submission to Cabinet. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Isla Hardy, Senior Manager (Policy,
Performance and Democracy) on 01294 324035 or email IslaHardy@north-
ayrshire.gov.uk.

Page 7

Our Council Plan
Six Monthly
Progress Report
1 April to 
30 September 2024

Page 8

Contents
Our Performance at a Glance .................................................................................................................. 1
Welcome ................................................................................................................................................. 2
Our Priori�es ........................................................................................................................................... 3
Wellbeing ............................................................................................................................................ 4
Key Ac�vi�es ...................................................................................................................................... 4
Next Steps .......................................................................................................................................... 9
Case Study – Drama for Wellbeing................................................................................................... 10
Communi�es and Local Democracy .................................................................................................. 11
Next Steps ........................................................................................................................................ 14
Case Study – Garnock Valley Task Force .......................................................................................... 15
Climate Change ................................................................................................................................. 16
Key Ac�vi�es .................................................................................................................................... 16
Next Steps ........................................................................................................................................ 20
Climate Change Case Study – Solar PV Farm ................................................................................... 21
A Sustainable Council ........................................................................................................................ 22
Our Transforma�on Programme ...................................................................................................... 22
Case Study – Our First Passivhaus School – A Model for Sustainable Educa�on ............................. 24
Audits, Inspec�ons and Accredita�ons ............................................................................................ 25
Next Steps ........................................................................................................................................ 27
Performance Summary ..................................................................................................................... 28
Measures adri� of target ................................................................................................................. 28
Changes to indicators ....................................................................................................................... 29
Ac�ons Adri� of target .................................................................................................................... 29
Benchmarking ................................................................................................................................... 30
Peoples Services ............................................................................................................................... 31
Other Services .................................................................................................................................. 32
Performance Indicators ..................................................................................................................... 42
Ac�on Tracker ................................................................................................................................... 45

Page 9

Our Council Plan Progress Update – Mid Year 2024 to 2025  Page 1 of 49
Our Performance at a Glance
35 Modern
Apprentices
recruited in August
2024
Child Poverty Action
Plan Progress Report
approved by Cabinet
in August 2024
£165,377 of
Participatory
Budgeting funding
available for our
community groups
and organisations
12,647 items of
rubbish logged in
September through
the new ‘LitterLotto’
app
£17.4million funding
secured from UK
Government Levelling
Up Fund Round 3 for
Commercial and Low
Carbon Infrastructure
£130,000 of funding
awarded to four
community
renewable projects 
We opened our three
state of the art
educational facilities,
investing £41.265m in
our young peoples’
education
11.2 tonnes of
mattresses and 117
tonnes of household
furniture for reuse
collected, assisting
875 households 
72 climate change
and energy lessons
delivered to 26
primary schools
442 referrals to our
new Debt Advice
Service exceeding the
referral target
437 P4 to P7 pupils
participated in
programmes during
Scotland’s Climate
Week
Our new
Participation
Strategy for North
Ayrshire was
approved by Cabinet
in June 2024

Page 10

Our Council Plan Progress Update – Mid Year 2024 to 2025  Page 2 of 49
Welcome
Welcome to our Mid-Year Report on our Council Plan 2023 to 2028. This report covers the
period 1 April to 30 September 2024. Our Council Plan is our contract with our residents and
details how we are progressing our four priori�es of Wellbeing, Communities and Local
Democracy, Climate Change and A Sustainable Council.
Delivery of our Council Plan is progressing posi�vely as 86% of our indicators where the
status is known are either on target or only slightly adri� of target and 96% of our ac�ons
are on target. We ac�vely compare our performance to other similar local authori�es
through the Local Government Benchmarking Framework (LGBF). Of these LGBF indicators,
17 of the 33 indicators that link closely to our priori�es are in the top two quar�les.  This
means we are performing more strongly in priority areas compared to other councils.
We are priori�sing ways in which we can alleviate the impact of cost of living.  This includes:
Our Money Maters Team helping residents access financial advice; funds being allocated
from our Child Poverty and Early Interven�on Fund to review childcare provision; emergency
support payments allocated to households struggling with high u�lity bills through our
Energy Smart Programme; and parents being supported into employment by council services
to improve household income.
We received a posi�ve Best Value audit on the theme of Workforce Innova�on. Our council
has set out a clear vision for workforce planning in its Council Plan 2023 to 2028.  We have a
comprehensive approach to workforce planning, real �me workforce data is u�lised to
inform future plans and we have adopted a wide range of approaches to improve the skills
and capacity of our exis�ng and future workforce, including agile working.
We con�nue to focus on embedding Our ‘No Wrong Door’ approach within our council,
ensuring that residents are always directed to helpful advice efficiently and that Cost of
Living support is easy to access. To access this support, please call 01294 310000 or visit our
website www.north-ayrshire.gov.uk.
Our council’s two new solar photovoltaic (PV) farms have progressed to construc�on stage.
Solar panels have been installed on the majority of the former Nethermains landfill site in
Kilwinning and good progress is also being made at the former Shewalton landfill site. The
two solar farms are expected to generate £400,000 revenue per year over a 25-year period
resul�ng in a total gross income of approximately £10million. Both sta�ons have brought the
sterile land at these sites (former landfill sites) back into use.  This shows how we are
embracing sustainable transforma�onal change to meet our council’s challenges as well as
realising community benefits from the use of our land assets.
Key contextual indicators from the Wellbeing Economy Dashboard (formerly the Inclusive
Growth Dashboard) include: 
Together we will ensure a North Ayrshire that is fair for all. 
Population of North Ayrshire:
133,349 (2023)
29% of our children live in poverty after
housing costs
28% of our households live in
fuel poverty (2021-22)
65.2% of working age
population is in employment
(June 2024)
10.4% of people earn less than the living
wage (2023)
Area wide CO2 emissions are
682kt CO2 (July 2023)

Page 11

Our Council Plan Progress Update – Mid Year 2024 to 2025  Page 3 of 49
Our Priori�es
Our Vision – A North Ayrshire that is fair for all.
Our Mission – Working together to improve the
lives of our people in North Ayrshire

Page 12

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 4 of 49
Wellbeing
To transi�on to a wellbeing economy,
delivering prosperity, wellbeing and
resilience for local people.
Key Ac�vi�es
Cost of Living
Our council was successful in becoming
one of Scotland’s Fairer Future
Partnerships (FFP). This partnership will
fund three posts for 18 months at a value
of approximately £350,000 to help bring a
more systematic approach to addressing
child poverty. Through innovation, small-
scale tests and reform, we are aiming to
develop a larger scale and sustainable
approach for North Ayrshire.
We have con�nued to strengthen our links
with the Third and Voluntary Sectors. For
example, we have reconfigured our Child
Poverty and Cost of Living Board within
the Community Planning Partnership. This
followed recent self-evalua�on with
partners that emphasised the importance
of engaging more with the third sector to
address child poverty. A commitment has
been made by the Child Poverty
Governance Group to work more closely
with the Third Sector Interface (TSI) to
progress place-based approaches to
address child poverty across our locali�es
using the Child Poverty Early Interven�on
Fund.
Our Child Poverty Ac�on Plan Progress
Report 2023 to 2024 was approved by our
Cabinet in August. The report highlights
ac�on that has been taken. Key areas of
focus include:
• Ensuring residents can access available
cost of living support quickly and
effec�vely through the No Wrong Door
approach, which ensures council
employees can support our residents
to access the advice and services they
need.
• Improving out-of-school care
provision.
• Improving the data that is gathered on
the six priority groups (lone parent
families, minority ethnic families,
families with a disabled child or adult,
families with a younger mother (under
25), families with a child under one,
and larger families (three or more
children) so that resources can be
beter targeted to support them.
In September, we began trialling a
simplified Council Tax process, we are
currently monitoring how well the new
process works and intended benefits. Our
Lived Experience group will be tes�ng this
change in November to ensure it is
suitable for real world environments.
Our young people and their families in the
Garnock Valley have been receiving
support during the cost of living crisis
from the Garnock Valley Youth Forum.
Weekly atendees of the forum have been
given goods and snacks whist families
have been provided with uniforms, clothes
and toiletries at no cost through the “New
to You” ini�a�ve.
Our community growing ini�a�ves are
sharing excess food with local larders to
reduce food waste and promote
sustainable food systems. Larders are also
u�lising FareShare (the UK’s na�onal
network of charitable food redistributors)
to collect surplus food from
supermarkets, further
minimising waste and
providing food for
our residents in
need.

Page 13

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 5 of 49
Our Financial Inclusion Partnership is
developing a communica�ons plan for
2025 to promote North Ayrshire Financial
Inclusion services. This will promote
services available, the range of pla�orms
for engagement and contact details for
support services. It is hoped this will
improve awareness par�cularly for our
island residents, the gypsy/traveller
community, people who are digitally
excluded and those with physical or
learning disabili�es or ill health. 
Our Garnock Valley Locality Team, in
Partnership with North Ayrshire’s Health
and Social Care Partnership and Café
Solace Kilbirnie, has launched a Recovery
Hub in Bridgend Community Centre. The
hub provides a safe and suppor�ve
environment for individuals in recovery,
offering access to informa�on and
resources.
Care Experienced Young People
Our Corporate Paren�ng Summer
Programme offered our care experienced
young people a chance to build
rela�onships with others who may have
had similar experiences. The programme
provided opportuni�es to take part in
ac�vi�es that they otherwise may not
have such as bowling. The event also
provided parents and carers with some
respite, with one carer sta�ng:
“Being twins, the girls have quickly learnt
to rely on each other in their own small
bubble. Atending events that can take
them out of their comfort zone and help
them interact with other young people is
great for their own personal development.
Both girls really enjoyed so� play and as a
carer it gave us a couple of hours off
knowing the children were safe and being
looked a�er.”
Our Ac�ve Schools and Community
Partnership Officers have been working
with a range of Health and Social Care
partners such as Foster and Adop�on,
Kinship Families, Residen�al House,
Children and Families team and Young
Carers to remove barriers care
experienced young people experience
when accessing sport and physical ac�vity
opportuni�es. This is part of our ongoing
commitment to ensure that each young
person has an equal opportunity to thrive.
Achievements include:
• 51 opportuni�es provided for our
young people, such as visits to leisure
centres, team building days at
Newmilns Dry Ski Slope and
residen�als at Inverclyde Na�onal
Sports Centre.
• We have worked with 638 of our
young people who are care
experienced to provide sport and
physical ac�vity opportuni�es.
• 71% of our young people atending
these opportuni�es have been
supported into more frequent ac�vity
such as extra-curricular Ac�ve School
programmes, community provision in
partnership with KA Leisure, or a local
community club.
• We work with our young people to
monitor the impact of these
opportuni�es. As a result of these
ac�vi�es, 65% felt safer, 66% felt they
were achieving more, 65% felt more
respected, and 67% atended more
sports clubs.
Atainment
Our Educa�on Service
Improvement Plan has
an enhanced focus
on raising

Page 14

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 6 of 49
atainment. Following significant analysis
of our Achievement of Curriculum for
Excellence Data, we have adapted the
work of our Educa�on Scotland
Atainment Advisor to ensure greatest
impact during 2024 to 2025.
Our Auchenharvie cluster of primary
schools has engaged with the 'Keeping the
Promise in Educa�on Award' and will be
looking at specific Personal Social
Educa�on (PSE) resources developed by
Adop�on UK. We are also inves�ga�ng
how we can collaborate with the Adop�on
UK educa�on team to support our care
experienced learners. 
We are currently analysing ini�al data on
how well our care experienced young
people are progressing to be able to
support them at school. Although further
analysis within our schools has s�ll to take
place, ini�al informa�on from the na�onal
Insight system indicates that of the 2023
to 2024 S4 cohort, 69% of our care
experienced young people achieved Level
4 Literacy, and 79% achieved Level 4
Numeracy. 
A series of ac�vi�es promo�ng good
mental health for children in Primaries 4
to 7 took place via our Outdoors for
Wellbeing camp. Our 27 young people in
atendance took part in cra�s, nature
ac�vi�es and a park liter pick.
Lifelong Learning Ac�vi�es
A series of cyber sessions took place over
the summer in local libraries hosted by
our Youth Work Modern Appren�ces. The
sessions focussed on:
• Cyber resilience and online safety
• Young people’s rights online
• Digital technologies
• Inclusion and digital opportuni�es to
learn online or take the next step in
employment
Our Youth Work Modern Appren�ce, Max,
said:
“As a young person, I know how important
being digitally connected is to young
people. But there can be a dark side too.
We want to empower young people to
know the dangers of online, how to
protect themselves against cyber-atacks
but also how to u�lise the power of online
and apps to help overcome obstacles, look
a�er their mental health, build
connec�ons and help them to achieve
their aspira�ons and goals.”
We were delighted to receive funding
from UK Government for a first of its kind
Cyber Resilience programme. Cyber
Explorers is the first in the UK delivering
this programme in a community se�ng
whilst working alongside our Educa�on
Department. Primary 6 and 7 as well as S1
and S2 pupils are being targeted ini�ally,
along with delivery in community centres
and at the Mobile Youth Centre.
The Discovery Award Group in the
Garnock Valley is aimed at all people over
50 years of age to help combat isola�on
and promote an ac�ve and healthy
lifestyle. It offers challenges to both
s�mulate and mo�vate and has seen nine
members progressing towards their Silver
Award, with one member now working
towards their Gold Award. 
During the summer, we delivered our “Big
Class Experiment”, aimed at
bringing together English
for Speakers of Other
Languages (ESOL)
learners located
across North

Page 15

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 7 of 49
Ayrshire, each with a variety of diverse
needs. Recognising the challenge of
providing effec�ve language educa�on,
we learned from the Glasgow ESOL
Forum’s approaches to managing classes
with diverse needs. 
Our Ranger Service led 13 events and
ac�vi�es that were atended by 124 of our
young people and 100 adults. These
events included guided Science,
Technology, Engineering and Maths
(STEM) trail ac�vi�es, biodiversity
informa�on events and Ayrshire walking
fes�val walks. 
Our Ranger Service also supported four
corporate volunteering sessions, three
being through our Reconnected
Programme in partnership with Human
Resources and Occupa�onal Development
(HR & OD), and one provided externally.
Equali�es
Our Bri�sh Sign Language Plan (BSL) was
published in May. This is our second
Ayrshire Shared BSL Local Plan and was
developed in partnership with Ayrshire
College; East and South Ayrshire Councils;
North, East and South Ayrshire Health and
Social Care Partnerships; and NHS Ayrshire
and Arran. Our BSL Local Plan sets out the
priori�es iden�fied through consulta�on
with BSL users living, working and
studying in Ayrshire. The priori�es
included within this plan cover: 
• BSL accessibility.
• Children, young people and their
families.
• Access to employment.
• Health and wellbeing.
• Celebra�ng BSL culture.
• BSL data.
• Democra�c par�cipa�on.
Employment
As part of our council's workforce
planning commitment, 35 Modern
Appren�ces were recruited in August 2024
across various council services. In
addi�on, six employees have commenced
Graduate Appren�ceship courses in
September 2024 with the University of the
West of Scotland (UWS), taking the overall
total to 12 employees who are advancing
through a Graduate Appren�ceship
programme.
Community Wealth Building
We consider Community Wealth Building
(CWB) to be a key mechanism to achieving
a wellbeing economy in North Ayrshire.
Following cabinet approval of our 2024 to
2027 Community Wealth Building Strategy
in February 2024, services across our
council are working together to maximise
local economic opportuni�es, increase the
number of good quality local jobs, and
retain wealth within North Ayrshire. 
We are undertaking research to consider
how we can use CWB principles to build
on opportuni�es within our locali�es and
meet the needs and aspira�ons of our
communi�es. 
CWB is at the heart of the Ayrshire
Regional Economic Strategy and we are
progressing our Regional Economic
Strategy Delivery Plan. We are working
with partners across Ayrshire including
South and East Ayrshire councils, Ayrshire
Chamber of Commerce and Ayrshire
College to deliver ac�ons which will
support business growth under the
Support for Enterprise
theme. A review of the
Year One Delivery Plan
has highlighted good
progress, with some

Page 16

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 8 of 49
ac�ons being carried forward into Year
Two. Supported by the Regional Economic
Strategy, Ayrshire was successful in
securing £3.7million of funding from the
UK Department for Science, Innova�on
and Technology to facilitate emergent
telecommunica�on technologies and 5G
coverage across the region through the 5G
Innova�on Regions programme. Project
delivery is underway alongside partners,
with our council as the overall programme
lead.
Commercial Estate Developments
Our new business pavilion within
Annickbank Innova�on Campus in Irvine,
now has an iden�fied bidder for the
ground floor space and marke�ng will
con�nue for the upper floor. The building
is low carbon and energy efficient with an
Energy Performance Cer�ficate (EPC)
ra�ng of A+. It is hoped that the pavilion
will support the growth of local
businesses. Phase Four of our Annickbank
Innova�on Campus project is currently
awai�ng confirma�on of external funding.
Community Transport
A study to inves�gate poten�al
opportuni�es to develop Community
Transport across North Ayrshire was
commissioned in 2024. 
The study aims to assess the exis�ng
public transport coverage and established
community transport services currently
opera�ng on Arran and in the Garnock
Valley.  It will be informed by public and
stakeholder engagement to determine the
impacts of transport limita�ons on the
community and iden�fy how further
community transport services could beter
support travel needs. 
Consulta�on ac�vi�es to inform the study
were undertaken between February and
June 2024. The dra� study was received in
August and next steps are being
established.
A further study is being commissioned on
behalf of the Garnock Valley Locality
Partnership on the travel challenges and
barriers in the area and their impact on
the community. This will commence in
Quarter Three of 2024 to 2025 and
include extensive consulta�on.
Housing
Alongside our Registered Social Landlords
(RSLs) our Housing Service con�nues to
deliver our social house building
programme in the form of new build
proper�es and buybacks of ex-local
authority proper�es via the Strategic
Housing Investment Plan (SHIP). There are
a number of projects currently on site:
• Ayrshire Central Hospital site, Irvine.
• Garnock Academy site, Kilbirnie.
• Newhouse Drive, Kilbirnie.
• Laburnum Avenue, Beith.
• James McFarlane site, Ardrossan.
• Stanecastle site, Irvine.
• Former Kings Arms hotel, Irvine.
• St Mary's site, Largs.
The sheltered housing reprovisioning
programme con�nues to be implemented
with the comple�on of the refurbishment
of Barnet Court in Saltcoats and Cheviot
Court in Irvine. The next phase planned
for refurbishment includes Laigh Court in
Beith and Vineburgh Court in Irvine.
We con�nue to invest in and maintain our
current housing stock. We are proac�vely
installing sustainability
measures to ensure they
are as thermally
efficient as possible
to reduce fuel bills

Page 17

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 9 of 49
for tenants. Measures include installing
external wall insula�on and solar
photovoltaic (PV) technology to suitable
proper�es. We are also undertaking a
pathfinder project to explore a 'whole
house' retrofit approach to our exis�ng
homes. This will inform future asset
investment for different property types to
achieve our energy efficiency targets and
reduce fuel costs for our tenants.
Following submission of the Annual
Return on the Charter (ARC) on 31 May
2024, the Annual Assurance Statement
(AAS) will be presented to Audit and
Scru�ny on 31 October 2024 for
endorsement and duly submited to the
Sco�sh Housing Regulator. The AAS will
also be presented to the North Ayrshire
Network (NAN) on 10 October 2024 to
seek feedback and scru�ny prior to
endorsement.
Our Tenant Inspec�on Panel scru�nises
one area of service per year. For 2024 to
2025 the area of focus is Aids and
Adapta�ons. This was decided
independently through a review of our
performance informa�on and support
from officers.  The project will commence
during January 2025.
Next Steps
• We will establish our Fairer Futures
Partnership team to bring a more
systema�c approach to addressing
child poverty in North Ayrshire.
• We will progress work as one of three
places in the Collabora�ng for Health
Equity in Scotland (CHES) programme,
which is being jointly led by Public
Health Scotland and the University
College London Ins�tute for Health
Equity. The aim of this programme is
to strengthen and accelerate the
ac�on underway to improve Scotland's
health, increase wellbeing and reduce
health inequi�es. This work will
complement the Fairer Futures
Partnership ac�vity.
• Review the impact and further
develop our approach to the
Mo�va�on, Commitment and
Resilience (MCR) pathways for our
young people.
• We will review the Debt Advice
service.
• We will develop a communica�on plan
for our Financial Inclusion Partnership.
• We will hold Secondary Atainment
discussions to examine atainment
data to support improvement.
• We will produce our Bri�sh Sign
Language Opera�onal Plan. 
• We will further refine our approach to
our Wellbeing Alliance.
• We will review research commissioned
by our council into the poten�al to
deliver a more locality based approach
to Community Wealth Building across
North Ayrshire.
• We will work with island stakeholders
to influence the development of the
new Na�onal Islands Plan for Scotland.
• We will progress the valida�on process
for our Levelling Up Fund Round 3
Commercial and Low Carbon
Infrastructure project. 
• We will con�nue to provide support
for local enterprise through the
Business Recovery and Sustainability
Fund.
• We will complete the annual review of
our Strategic Housing Investment Plan
• Our Tenant Inspec�on
Panel will scru�nise
our Aids and
Adapta�ons
provision.

Page 18

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 10 of 49
Case Study – Drama for Wellbeing 
Youth Services returned to the Harbour Arts Centre in August for a week–long drama
workshop. This year, the North Ayrshire Drama for Wellbeing sessions were atended by over
35 young performers aged between six and 15 years old.
Following a series of workshops throughout the week with a mental health and wellbeing
focus, the hard work of the children and young people was celebrated with an on-stage
performance to the Provost, special guests and family members.
Some of the young performers have already been used to the stage, starring in amateur
drama and local dance school produc�ons. However, for others, this was their first �me.
One of our youth workers who led the workshops throughout the week supported by drama
facilitators working in the industry said:
“I am incredibly proud of our talented performers. The free
workshops were fully booked. We were really amazed how
well received the uptake was as the aspiring performers
were able to discover the power of youth work via
confidence building and wellbeing sessions. It has been great
to welcome performers who were with us last summer too,
they’ve grown so much.”
Parent feedback included:
“The singing was incredible, and the drama was really
moving. I was deeply moved by the produc�on and it’s great
to hear from my daughter and her friends that they’ve been
able to learn some valuable performance skills and develop
techniques to be more mentally resilient ahead of the new
school term.”
The programme is an example of how we con�nue to champion children and young people’s
rights – building their confidence and encouraging them to learn new skills beyond the
classroom.

Page 19

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 11 of 49
Communi�es and Local
Democracy
We will have ac�ve, inclusive and resilient
communi�es.
Key Ac�vi�es
Community Learning and
Development
We published our new Community
Learning and Development (CLD) Plan
2024 to 2027. Reflec�ng the
recommenda�ons within the recently
published Sco�sh Government “Learning: 
For All. For Life” report, key themes have
been iden�fied and commitments made
to the communi�es of North Ayrshire. 
Adult Learning, Youth Work and Capacity
Building are the founda�on of the CLD
Plan, with themes of health and
wellbeing, Community Wealth Building
and workforce development woven in. It
also covers inequali�es and the targe�ng
of resources, as well as describing unmet
need and governance. 
Par�cipa�on
In June 2024 our new Par�cipa�on
Strategy was approved. The delivery of the
first year of the strategy will focus on the
following ac�ons: 
• Promote and raise awareness of the
strategy and the ways in which people
can be involved.
• Gather examples of effec�ve
engagement, par�cipa�on and change
to share.
• Enhance our budget consulta�on
process.
• Work to further develop and promote
our locality planning approach.
Addi�onally, we con�nue to develop a
virtual community directory to support
residents in crisis, in alignment with the
work of the North Ayrshire Child Poverty
and Cost of Living Board.
We have recruited community reviewers
for both the locality and youth
par�cipatory budge�ng (PB) process. Our
reviewers will be involved in all aspects of
the PB process across all six locali�es.
There is a total of £165,377 available
through the PB process which our
community groups and organisa�ons may
apply for. The Consul online engagement
pla�orm will facilitate vo�ng for young
people aged eight to 25 years. Vo�ng
packs created by our Modern Appren�ces
will be distributed to schools promo�ng
democracy and ac�ve ci�zenship.
Vo�ng for the PB funding available
through the UK Shared Prosperity Fund
(SPF) Communi�es and Place Grant is also
in progress across our six locali�es.  There
is a budget of £31,000 available and vo�ng
will conclude in November.
Training has been delivered to the Ac�ve
Schools Team to expand the capacity for
suppor�ng the Community Asset Transfer
(CAT) process. The Ayrshire Community
Trust (TACT) hosted an informa�on session
for local groups either considering or at
the early stages of a CAT. We currently
have 12 expressions of interests pending,
are assessing 11 full applica�ons, and four
groups are considering making an
applica�on.
In the summer, our Members
of the Sco�sh Youth
Parliament (MSYP)
atended the na�onal
si�ng of the
Sco�sh Youth

Page 20

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 12 of 49
Parliament. Along with the Scotland-wide
membership, our MSYPs took part in the
vote to decide the three campaign areas
for the next two years. These have
received a good amount of support from
organisa�ons across Scotland including
the Third Sector. Campaigns include: 
• Increasing mental health training and
educa�on.
• Inves�ng in and protec�ng youth work
services.
• Ending gender-based violence.
Our MSYPs took part in consulta�on to
help shape na�onal policy such as:
• Transi�ons to Adulthood for Disabled
Young People.
• Sco�sh COVID-19 Inquiry Workshop 2
– Mental Health and Digital Inclusion.
• Ar�ficial Intelligence in the Children’s
Hearings System.
• Educa�on Reform – What Should
Happen Next?
• Together (Sco�sh Alliance for
Children’s Rights): State of Children’s
Rights Report.
• Learning for Sustainability Project –
Phase 2 Workshop.
Our MSYPs have also been mee�ng
regularly via the Execu�ve Youth Council,
atending summer events and
programmes, volunteering and working on
individual projects.
Locality Planning
One of the key routes for par�cipa�on in
North Ayrshire is through locality
planning, including the work of the locality
partnerships which bring our Community
Planning Partners, Elected Members and
community representa�ves together to
jointly address local priori�es. Using our
new North Ayrshire Par�cipa�on Strategy
as a catalyst, a programme of self-
assessment work in rela�on to locality
planning has been developed. This reflects
our ambi�on to con�nue to grow and
improve the local governance framework
using locality planning.  It augments the
ambi�ons of communi�es across Scotland
which have been iden�fied so far through
the Local Governance Review and
Democracy Maters 2 conversa�on.  The
self-assessment exercise will take place
over summer/autumn 2024 and will
include: 
• Surveys with key locality
representa�ves to gain a deeper
understanding and iden�fy what is
currently working well, the challenges
to locality working and opportuni�es
to develop the collec�ve contribu�on. 
• A wider review of the best of prac�ce
across na�onal networks to inform our
locality planning approach, tailored to
local circumstances as required.
The 2024 to 2025 Locality Plans were
approved at Locality Partnership mee�ngs
in September.
Community Planning Partnership
Our Community Planning X (formerly
called Twiter) account is experiencing
steady growth, nearing 900 followers. The
team has recently reassessed the social
media plan to enhance the use of the
pla�orm, aiming to further expand the
account and highlight the ini�a�ves of the
Community Planning Partnership and
Locality Partnerships. 
Following posi�ve feedback
from par�cipants a�er
the first session in
March, the second of
two Community and

Page 21

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 13 of 49
Locality Planning training sessions has
been planned for November. 
A development session took place in May
2024 led by the Sco�sh Fire and Rescue
Service and atended by CPP partners.
Ac�ons to be considered include a review
of CPP governance and looking at ways to
increase working on a pan Ayrshire basis.
Discussions have taken place with CPP
Teams at East and South Ayrshire councils
regarding increasing pan-Ayrshire working
in the coming year.
We are undertaking a review of Locality
Planning which will look at findings from
engagement ac�vity and local data
including locality surveys and profiles. It
aims to strengthen our locality planning
approach in North Ayrshire and aligns with
our council's ongoing commitment to
community empowerment.
Community Asset Transfer (CAT)
Community Asset training has been
delivered to employees who are
interested in being the Single Point of
Contact for community groups exploring
community asset ownership. This training
will build on exis�ng communica�ons
between departments to ensure groups
feel fully supported through the CAT
journey.
We have worked to understand where we
can support groups who are interested in
a CAT of a building.  This includes carrying
out some repairs to make buildings more
sustainable using our CAT Start Up Fund
and working alongside our Energy team to
understand what adapta�ons might
improve the energy use of various
buildings.
Modern Appren�ces from Building
Services helped to carry out work to the
Garnock Valley Men’s Shed building,
bringing it to a state where the group
were able to progress to full ownership.
We are working with 19 different groups
who are at various stages of the CAT
process to help them progress their
ambi�ons.
Community Grants and Funding
Par�cipatory Budge�ng 2024 to 2025
(locality and youth) was launched across
all six locali�es, with launch events held in
each locality, providing opportuni�es for
groups to find support to apply and a
chance to network with other local
organisa�ons.
PB training has been delivered across
locali�es to staff and a community
reviewer engagement session has taken
place for this round of PB.
Community grants totalling £177,574.98
have been awarded by Locality
Partnerships so far this year.
We are planning to review our processes
for making and monitoring grants to
ensure they are as easy as possible for
community and voluntary organisa�ons to
access.
Community and Voluntary Sector
We have been working with the North
Ayrshire Third Sector Chief Officers’ Group
(COG), who represent a range of local,
regional and na�onal organisa�ons in
North Ayrshire. This is a key group of
senior leaders who have the poten�al to
influence and shape CWB within the third
sector as well as becoming a
trusted partner for our
council.
This work includes
looking at how we

Page 22

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 14 of 49
can work together with third sector
organisa�ons to invest in them in a
collabora�ve rather than compe��ve
manner. Development sessions are
planned to explore this further and create
agreed ac�ons we can take forward
together.
We con�nue to support a range of other
community and voluntary sector
organisa�ons including Community
Associa�ons who operate key holding at a
number of community facili�es, and the
Fairer Food Network who operate 16 food
larders across North Ayrshire.
Islands
We have con�nued to support
communi�es on Arran and Cumbrae with
the implementa�on of our Ten-Year Island
Plans. This has included suppor�ng
communi�es on both islands to prepare
and submit applica�ons to the Sco�sh
Government's Islands Programme for
capital projects. In addi�on, we supported
Cumbrae Community Development
Company to prepare and submit a funding
applica�on to the Sco�sh Government's 
Carbon Neutral Islands Capital Fund.
Next Steps
• We will complete our review of our
Locality Partnerships and present
proposals to Cabinet in early 2025.
• We will begin delivery of our year one
outcomes of our new Community
Learning and Development Plan.
• We will make progress on the
priori�es iden�fied through the
Community Asset Transfer Start-up
Fund review.
• We will commence a comprehensive
review of our approach to applica�on,
assessment, award and compliance in
rela�on to community funds and
grants.
• We will implement the ac�on plan
iden�fied by our joint work with the
Third Sector Chief Officers Group.
• We will con�nue to develop our new
virtual Community Directory for
community members in crisis.
• We will prepare our CPP Project Plan
for 2025 to 2026.
• We will carry out Community and
Locality Planning training sessions in
November.
• We will undertake a consulta�on on
rent se�ng op�ons for 2025 to 2026
for our council homes. 
• We will issue our tri-annual tenant
sa�sfac�on survey. 
• We will test our streamlined Council
Tax process with our Lived Experience
Group in November. 
• We will undertake both a locality and
youth par�cipatory budge�ng process.

Page 23

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 15 of 49 
Case Study – Garnock Valley Task Force
In response to a growing trend in youth related disorder across the Garnock Valley, a
Wellbeing Task Force was established to drive a fresh and effec�ve approach to the
challenge. This ini�a�ve is part of the North Ayrshire Health and Wellbeing Alliance broader
delivery programme, aligning:
• Diversionary opportuni�es for young people.
• Educa�onal messaging on life choices and the dangers of substance misuse.
• Beter links with local partners to provide more opportuni�es for young people to
find their future pathway.
The primary goal was to create a cohesive and skilled delivery team capable of reducing
youth disorder.  Through careful analysis of local data, the task force iden�fied disengaged
students within the educa�on system as a key demographic requiring aten�on.  They o�en
face barriers to posi�ve engagement leading to an�social ac�vi�es within their
communi�es.
By addressing these challenges head on, the Wellbeing Task Force is working to empower
young people with the tools, opportuni�es and guidance needed to make beter decisions
and build brighter futures.
A pilot commenced in December 2023 using KA Leisure coaches and instructors who have
focused on building rela�onships and developing trust with the young people to build
confidence through sport and physical ac�vity and develop transferable skills such as:
• Goal se�ng
• Discipline
• Rou�ne
• Teamwork
• Resilience
Our young people have completed KA Leisure’s Elevate Academy and received a 3-month
fitness membership to con�nue their wellbeing journey out with school.
The second phase of this project focusses on empowering our young people to design and
lead ini�a�ves that benefit their local area and wider community.  This stage aims to ins�l a
sense of responsibility and belonging while equipping par�cipants with valuable skills and
experiences.  By involving our young people in meaningful, community-driven projects, the
ini�a�ve also seeks to shi� percep�ons, highligh�ng the posi�ve contribu�ons of youth and
fostering stronger connec�ons between the school and the wider community.
The next steps will involve collabora�ng with addi�onal partners to expand
engagement, broaden opportuni�es, and create more pathways for our
young people.  We will also explore new ways to promote access to
community ac�vi�es and lifelong learning opportuni�es.

Page 24

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 16 of 49
Climate Change
To achieve net-zero by 2030.
Key Ac�vi�es
Energy
Our council’s two new solar photovoltaic
(PV) farms have progressed to
construc�on stage. Solar panels have been
installed on the majority of the former
Nethermains landfill site in Kilwinning and
good progress is also being made at the
former Shewalton landfill site. The new
solar farms will make a major contribu�on
to renewable energy genera�on and
carbon reduc�on whilst also bringing
sterile land back into produc�ve use. 
The two solar farms are expected to
generate £400,000 of revenue per year
over a 25 period resul�ng in a gross
income of approximately £10million. The
projects are both in the construc�on
stages and are scheduled for energisa�on
in early 2025.
Following an engagement exercise via our
Energy Efficient Scotland: Area Based
Scheme (EES:ABS), 15 households on
Cumbrae have been iden�fied for
improvements. This aims to address the
impact of energy costs and fuel poverty in
private housing across Scotland. Further
engagement with eligible households will
con�nue to support affordable warmth
and reduced carbon emissions. In
addi�on, 25 proper�es in Kilwinning have
been iden�fied as eligible and are
awai�ng technical surveys. 
Our council con�nues to support wider
ac�on on climate change beyond our own
estate. Four community renewable
projects have been awarded funding
through the Community Renewable
Energy Genera�on Fund, totalling
approximately £130,000. Addi�onal
awareness raising ac�vity is underway to
increase the uptake of the available
funding, with support from Connected
Communi�es. A programme for
Community Climate Ac�on Plans is
underway to increase ac�on based on
community priori�es and this will
maximise access to funding and support. 
Procurement ac�vity has commenced to
undertake a review of the renewable
energy poten�al across our council’s land
and assets. The scope of this work will also
include assessing the poten�al for
community owned renewable energy
projects. This study will be completed by
December 2024 and is likely to involve
community engagement as part of its
development. 
Together with Development Trusts
Associa�on Scotland (DTAS) and the Three
Towns locality team, we are collabora�ng
with the Stevenston Community Company
to explore the poten�al for a solar farm
and the community asset transfer of the
Kerelaw School site. This ini�a�ve offers
opportuni�es for community ownership
and the development of renewable energy
sources.
Reuse and Recycling
Since the introduc�on of the ‘LiterLoto’
app in April 2024, there has been a steady
increase in residents helping to dispose of
liter appropriately and recording this via
the app. Throughout September 2024, a
total of 12,647 items of rubbish were
disposed of by app users,
which has shown a
significant increase
from 4,942 items in
July 2024. The

Page 25

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 17 of 49
‘LiterLoto’ partnership, facilitated by the
environmental charity, Keep Scotland
Beau�ful, gives users in North Ayrshire the
opportunity to enter a UK wide weekly
draw with a jackpot of £1,000 to be won,
and a monthly prize draw with a cash prize
of £100 to be won.
Our council's bulky waste reuse partner,
Cunninghame Furniture Recycling
Company (CFRC), collected 410 matresses
for reuse (11.2 tonnes) between April and
September 2024 as part of an ini�a�ve to
promote opportuni�es for their reuse.
During the same period, CFRC also
collected 117 tonnes of household
furniture for reuse and assisted 875
households to furnish their homes
suppor�ng the employment of 16 people.
The Sco�sh Environment Protec�on
Agency (SEPA) published the 2023
recycling data which showed our council
improved its recycling performance from
55.3% in 2022, to 56.1% in 2023. We are
ranked as the 3rd best performing of all 32
local authori�es in Scotland. 
Following the enactment of the Circular
Economy (Scotland) Act 2024 in August,
our officers have been working closely
with COSLA, SOLACE and the Sco�sh
Government through a co-design process
to develop the key policy and ac�ons to be
taken forward within a new Waste Route
Map for Scotland.  This is expected to be
published later in 2024 and will be used to
inform the development of our council's
new Zero Waste Strategy.
Net Zero Ambi�on
We are currently partnering with Zero
Waste Scotland (ZWS) to implement the
Islands Net Zero Accelerator (NZA)
through our Business Recovery and
Sustainability fund in addi�on to atrac�ng
£25,000 of match funding from ZWS. This
unique island specific programme will help
local businesses embrace new technology
and reduce their environmental impact.
Through their transi�on to Net-Zero by
2030, the programme closely aligns to the
Local Island Plans priori�es of:
• Climate ac�on and sustainability.
• Local supply chains.
• Business resilience.
• Skills development.
• Green innova�on.
• Energy provision.
• Energy costs.
15 small enterprises are being supported
through the 12-month programme.  It is
designed to help companies in their
transi�on to Net-Zero, providing advice
and support associated with reducing
their carbon footprint, making energy
efficiency improvements, adop�ng
renewable energy sources and using
carbon accoun�ng tools.
The Islands Net-Zero ambi�on posi�ons
our islands as pioneers and role models in
the broader context of climate ac�on and
sustainable development. By showcasing
successful outcomes and scalable models,
Arran and Cumbrae can inspire other
island communi�es and regions to embark
on similar journeys towards a greener and
more resilient future. 
In collabora�on with Ayrshire College, we
are working on the Carbon Assistant
Programme aimed at suppor�ng
unemployed parents and local businesses
by cul�va�ng a skilled
workforce in the
expanding field of
carbon accoun�ng.

Page 26

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 18 of 49
Through this programme, nine
unemployed parents have received
valuable skills training and secured work
placements with businesses across North
Ayrshire, gaining prac�cal experience in
carbon management prac�ces. Net Zero
Interna�onal will provide in-work
con�nued professional development
accredited training focused on carbon
repor�ng skills, equipping par�cipants to
make impac�ul contribu�ons to
sustainability within their placements.
Addi�onally, par�cipants will have the
opportunity to join the second year of the
North Ayrshire Net Zero Accelerator
Programme, offering con�nuous support
and development in sustainable prac�ces. 
Our council con�nues to work with Keep
Scotland Beau�ful to support free energy
resources for secondary schools and are
developing a community carbon literacy
training pack for small community groups,
in conjunc�on with the Associa�on for
Public Service Excellence (APSE) Energy.
A community focused carbon literacy
module has been dra�ed to be made
available to community groups
throughout North Ayrshire. Final
amendments are being addressed with
the support from the Carbon Literacy
Trust.
Transport
Following approval of the Regenera�on
Delivery Plan funding proposals at Cabinet
in August 2024, works have progressed on
the Levelling Up Fund Ac�ve Travel Route
ini�a�ves including Heatherhouse Road,
the River Irvine Path, Long Drive and
Riverside Way. Construc�on on the next
phase of Fairlie Coastal Path is also
ongoing and due for comple�on in
November 2024. 
Since April, our Local Transport and Ac�ve
Travel Strategy (LTATS) has made further
significant progress through partnership
working, community consulta�on, project
funding, and infrastructure improvements.
Key achievements include comple�ng
ac�ve travel paths in Kilwinning and
Fairlie, expanding electric vehicle
infrastructure on Arran, ini�a�ng
feasibility studies for new Ac�ve Travel
Routes, and con�nuing our workplace and
community behaviour change programme.
Nearly £2.1million in funding has been
secured to advance the LTATS, sourced
from the Sco�sh Government,
Strathclyde Partnership for Transport,
Sustrans and Cycling Scotland. This
includes: 
• General capital funding of £942,452
from the Sco�sh Government via
Transport Scotland’s Ac�ve Travel
Infrastructure Fund (ATIF) Tier 1 and
Local Authority Direct Award (LADA)
capital award.
• Specific project grants such as
£392,506 this year for the Fairlie
Coastal Path from Sustrans.
• £400,000 for the North Crescent
Coastal Path in Ardrossan and
£165,000 for McGavin Park in
Kilwinning from Sustrans and ATIF Tier
Two.
Addi�onally, revenue awards of £157,200
from Strathclyde Partnership for
Transport’s People and Place programme,
along with £70,905 from the LADA
Revenue, enable our council to
enhance sustainable
transport and ac�ve
travel op�ons across
North Ayrshire,
aligning with

Page 27

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 19 of 49
broader environmental goals and
community needs.
Biodiversity
As part of our Sustainable North Ayrshire
Strategy 2024-27, we are developing
Community Climate Ac�ons Plans for each
locality area, building on the Climate
Ac�on Town Stevenston project.
Development of this programme is
progressing with support from our
Connected Communi�es service and
APSE.
Our Environmental Health Team is
launching a ‘No Idling’ campaign for
schools in an effort to encourage drivers
to switch off their engines while they wait.
A wider authority ini�a�ve is also being
planned for inclusion in a bid for Clean Air
Day 2025 funding from Sco�sh
Government.
Our Sustainability Team has delivered 72
Climate Change and Energy lessons to 26
primary schools to date. 
The lessons support awareness of ac�on
on climate change and encourage
ac�vi�es within schools via their climate
ac�on plans.
Cumbrae Primary School will par�cipate in
the first round of ‘Climate 180’ training
with Learning through Landscapes. This is
an ini�a�ve to empower children and
young people with the knowledge and
skills necessary to ac�vely par�cipate in
posi�ve changes in rela�on to climate
change.
Con�nuing our collabora�on with Keep
Scotland Beau�ful and the Climate Ready
Classrooms Primary programme, 437
Primary 5 to 7 learners from 17 se�ngs
par�cipated in the programme throughout
September, culmina�ng in the crea�on of
Climate Ac�on Plans during Scotland’s
Climate Week. This is in addi�on to the 24
ac�ve Green Flags held by our schools and
four currently in progress. Green Flags are
an interna�onally recognised achievement
for schools and nurseries commited to
Learning for Sustainability.
A self-led sustainability trail is currently
being developed for the Community
Gardens at Eglinton Park which will be
trialled in the Autumn. Par�cipant
feedback will help inform the design and
installa�on of a permanent trail to be
opened for Spring 2025. 
Our 2030 Woodland: A Tree Plan�ng
Strategy con�nues to be a key area of
focus, with support from our
Arboricultural and Strategy teams
provided to local community groups and
the assessment of suitable plan�ng sites.
To date, 36,531 trees have been planted
across North Ayrshire through various
projects and by community partners
crea�ng new habitat opportuni�es for
birds and other wildlife. The total number
of trees planted within the first three
years of the strategy is on schedule to
achieve the overall target of 108,000 trees
to be planted by 2030, with six years of
the strategy s�ll remaining. A Tree
Plan�ng webapp has been created for
internal GIS system users within our
Streetscene Service which has been used
to iden�fy several poten�al tree plan�ng
sites within the Irvine area.  These areas
are currently being assessed for
developing new tree plan�ng proposals
for the 2024 to 2025 tree plan�ng season.
The Community Woodland Grant Fund
Scheme for 2024 to 2025 launched at the
end of September with a total of £25,000
available in the fund with a
maximum of £5,000 per
applicant. It will
support local tree
plan�ng ambi�ons,
including the

Page 28

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 20 of 49
crea�on of new community orchards. The
fund has been widely adver�sed through a
press release, social media posts and
communica�ng directly with local
community groups and allotment
associa�ons. Our council also planted
perennial plants to replace tradi�onal
summer bedding plants which have beter
biodiversity outcomes. 
Next Steps
• We will develop Community Climate
Ac�on Plans for our six locali�es. 
• We will revise our Renewable Energy
Strategy and build an asset
decarbonisa�on model.
• We will develop a batery storage pilot
scheme on non-domes�c buildings to
maximise the use of exis�ng roof
mounted solar PV helping support
local energy networks.
• We will con�nue to review the current
bulky upli� service to align with the
new SEPA guidance.
• We will con�nue to develop a
community focussed carbon literacy
module that will be made available to
community groups.
• We will host a series of Biodiversity
and Sustainability, and Climate
Chemistry seminars.
• We will create a North Ayrshire
Network Strategy, aligned with the
Sco�sh Government’s Biodiversity
Strategy.
• We will install a new permanent self-
led sustainability trail at Eglinton Park.
• We will con�nue to develop projects
for future Ac�ve Travel and
Infrastructure Tier 2 Funding
applica�ons.
• We will complete the construc�on of
our Fairlie Coastal Path.

Page 29

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 21 of 49
Climate Change Case Study – Solar PV Farm 
Our council iden�fied a growing need for sustainable energy solu�ons to meet local energy
demands and reduce carbon emissions. With increasing energy costs and the need for
greener ini�a�ves, the development of two new solar farms was proposed at the
Nethermains landfill site in Kilwinning and the former Shewalton landfill site in Irvine with an
aim to generate clean energy for our community while suppor�ng our commitment to
achieving net zero emissions by 2030.
Our primary objec�ve was to design, construct and execute the solar farm projects ensuring
environmental and economic feasibility whilst gaining community support and mi�ga�ng
poten�al environmental concerns for local residents in our communi�es. These projects are
believed to be the first solar farms to be owned and operated by a local authority in Scotland
and mark a major milestone in our council’s priority to cut carbon emissions.
These projects represent a £12.5million investment and are key elements of delivery of our
council's Sustainable North Ayrshire Strategy.  They will have the added benefit of genera�ng
income for the council to help sustain local services and will also generate 15% of any net
profit as community benefits for local communi�es, by selling the electricity generated via a
Power Purchase Agreement.
Both solar farms have progressed to construc�on stage and are scheduled for energisa�on in
early 2025. The Nethermains site alone is expected to create enough energy to power more
than 2,000 homes.  Once complete, it will feature more than 12,000 solar panels and is
expected to generate approximately 7,700MWh of electricity annually. The annual reduc�on
in CO2 emissions is es�mated at 2,700 tonnes of CO2 per year based on the combined
annual energy genera�on of over 13,000 MWh.
The two solar farms are expected to generate £400,000 of revenue per year over a 25 year
period resul�ng in a gross income of approximately £10million, whilst significantly reducing
our carbon footprint and contribu�ng towards our net zero goals. 
These sites will make a major contribu�on to renewable energy genera�on and carbon
reduc�on whilst also bringing sterile unused land back into produc�ve use.  They
demonstrate our council’s capability to deliver impac�ul, transforma�onal and sustainable
projects.

Page 30

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 22 of 49
A Sustainable Council
To transi�on to a wellbeing economy, delivering prosperity, wellbeing and resilience for local
people.
Our Transforma�on Programme
Our current Transforma�on Programme was approved in 2023 and developed alongside our
Council Plan 2023 to 2028. The Transforma�on programme is one of the key approaches in
addressing the financial challenges of our council, alongside exploring opportuni�es for
further revenue genera�on, wider reform (including sharing services), the planned use of
council reserves and, through extensive engagement with communi�es, considera�on of the
range and level of services provided by our council. 
A culture of con�nuous improvement ensures projects are delivered to improve the impact
of our services for our people of North Ayrshire. This sec�on provides a summary of
progress on workstreams where key milestones have been reached during the first six
months of 2024-2025.  Other projects will be reported as they reach relevant stages.
Digital Workstream
Linked Priori�es:   All four priori�es, with Wellbeing as the main focus.
Current Status:   On Target.
Expected Outcome:   Easier access to services for residents. Part of the Digital
Workstream which is expected to deliver £200k of savings by the
end of 2027.
The Accessing the Council project, part of the Digital Workstream, reviewed our frequently
used online processes to iden�fy and implement improvements with an aim of streamlining
how our residents access services. Last year we: Introduced a new Customer Services Digital
Team; launched the My NAC online account using the na�onal My Account pla�orm for
authen�ca�on; and launched our new website in September 2024. 
Consequently, we are now seeing a reduc�on in public facing telephone numbers and email
addresses on our website. With regards to the wider Digital programme the Transforma�on
Board con�nue to explore opportuni�es which align to the digital North Ayrshire strategy. A
range of work is currently being progressed na�onally through SOLACE, the Improvement
Service and the Digital Office. This includes a “Scotland first” approach to council processes
and ac�vi�es across a range of areas. 
Irvine Locality Property Review
Linked Priori�es:   Climate Change and A Sustainable Council.
Current Status:   On Target
Expected Outcome:  Part of wider ‘Our Future Working
Environment’ work, expected to deliver
£670k in savings by the end of 2026.

Page 31

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 23 of 49
The Irvine Locality Review is being undertaken as part of the Land and Property workstream
to ra�onalise our council’s property estate. Our approach was approved by Cabinet in
September 2024. Work completed to date includes:
• Move of Genealogy from Town House to Irvine Library.
• Floor plans and move schedule for services into Cunninghame House approved.  This
includes the agreement of designs for a new Training Suite and Customer Services Centre
in Cunninghame House.
• Designs agreed for Quarry Road, Irvine.
Nethermains and Shewalton Solar PV Farm
Linked Priori�es:   Climate Change and A Sustainable Council.
Current Status:   On Target
Expected Outcome:   Reduced emissions and a long term income to the council.
Work con�nues on the installa�ons of two new solar PV farms at the former Nethermains
landfill site in Kilwinning and the former Shewalton landfill site in Irvine. The programme of
works for the first six months of 2024 to 2025 included: 
• Approval of the detailed designs for both Nethermains and Shewalton solar PV farms.
• The start of the installa�on of the grid connec�on works by SPEN.
• Comple�on of site clearance works and fencing erected at both sites.
• Compound area and road installa�on complete at Nethermains site.
• Moun�ng structure work complete at Nethermains site.
• Compound area and road installa�on underway at Shewalton site.
• Power Purchase Agreement (PPA) inves�ga�on work and discussions with energy
provider underway. 
Service Reviews
The following service reviews are in progress, governed by the Transforma�on Board.
• Learning Resource review.
• Housing Services review.
• Financial Inclusion Services.
• External Residen�al Placements (Brighter Pathways programme).
• Economic Development, Growth and Regenera�on services review.
• Waste Services Review.
In terms of wider local government reform, discussions are ongoing with neighbouring
authori�es to explore opportuni�es for sharing services on a regional basis.  Further
informa�on will be provided in future repor�ng.

Page 32

Case Study – Our First Passivhaus School – A Model for Sustainable
Educa�on
In response to our commitment to achieve net-zero carbon emissions, our council decided
to build its first Passivhaus-cer�fied school. The goal was to create an energy-efficient
learning environment to accommodate 342 primary school students, an Early Years facility
for 32 children and ac�vity areas on a greenfield site in Montgomerie Park while maintaining
high standards of comfort for our young people and employees. 
Our Property Team was tasked with designing, project managing and delivering a school that
met the stringent Passivhaus energy performance standards with a site specific Passivhaus
induc�on taking place on site prior to works commencing. This required collabora�on with
architects, engineers and contractors to overcome the challenges of different construc�on
techniques, �ght �melines and budget constraints. A Passivhaus Champion was on site
throughout the construc�on process to monitor and record quality standards.
The project began with extensive stakeholder engagement to align sustainability goals with
educa�onal needs.
Key ac�ons included:
• Implemen�ng advanced insula�on and air�ght construc�on techniques to minimise
energy loss using precast concrete.
• Priori�sa�on of reducing embodied carbon, using green steel produced through electric
arc furnaces, aligning the project with its environmental goals.
• Regular performance checks and on-site adjustments ensured the construc�on met all
cer�fica�on requirements and ensured quality throughout the build process.
Montgomerie Park Primary School opened its doors in August 2024, achieving and exceeding
cer�fica�on for energy efficiency, using less energy than a conven�onal building and
reducing opera�onal costs significantly. The project also served as a learning experience for
future sustainable construc�on projects.
This project demonstrates how our
commitment to sustainability can
deliver tangible environmental,
economic and social benefits while
se�ng new standards for
educa�onal infrastructure.

Page 33

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 25 of 49
Audits, Inspec�ons and Accredita�ons
Best Value Thema�c Approach – Workforce Innova�on
Our most recent Best Value Thema�c Audit focussed on Workforce Innova�on.  The final
report was presented to the Audit and Scru�ny Commitee in August.  It shows how our
council is responding to current workforce challenges through building capacity, increasing
produc�vity and innova�on.
The report iden�fied: 
• Staff costs equate to around 49 per cent of our council’s overall revenue budget.
• Our council has set out a clear vision for workforce planning in its Council Plan 2023 to
2028.
• We have a comprehensive approach to Workforce planning at a service level with
detailed ac�on plans, with some strengthening required at corporate level.
• Real �me workforce data is u�lised to inform future planning.
• We have adopted a wide range of approaches to improve the skills and capacity of our
exis�ng and future workforce.  This includes agile working, which was strengthened in
2021.
The recommended ac�ons arising from the audit are detailed below.   Work towards these
ac�ons is progressing and a full update on progress will be provided in our Year End
repor�ng.   
Recommendation Agreed Management Action
The council should establish corporate
workforce planning priorities and develop a
SMART action plan to allow progress in
delivering these priorities to be measured.
The Workforce Strategy will be updated to
include corporate workforce planning priorities
and an action plan to allow progress to be
measured.
The council’s workforce strategy should be
updated to align with all four Council Plan
2023 to 2028 priorities and with other key
strategies and plans. It should include an
analysis of council-wide workforce data and
set out what the required skills, learning and
development needs of its staff are.
The Workforce Strategy will be updated to
ensure alignment to all Council Plan priorities,
other key strategies/plans and include an
extract of council-wide workforce data.

Page 34

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 26 of 49
Recommendation Agreed Management Action
The council should build on the work it has
done to date to demonstrate and quantify
what workforce benefits and productivity
gains have been made through its use of
digital technology.
Further work will be undertaken to capture and
quantify efficiencies from digital improvements
and for this work to be incorporated within our
council’s Medium Term Financial Planning
The council should consider conducting
another digital skills survey to inform the
support it provides for improving the digital
skills and knowledge of its workforce.
A digital skills survey will be conducted to
inform future development interventions.
The council should consider gathering further
feedback from staff on the impact of agile
working on wellbeing and productivity.
Further feedback will be gathered from those
employees who are deemed an agile workstyle
to gauge continued benefits on wellbeing and
productivity.
The council should explore further where it
can work together with partners to share
services and increase collaboration.
The Medium-Term Financial Planning process
for 2025 to 2026 and 2027 to 2028 will include
the exploration of further opportunities for
sharing services and collaboration across
partner organisations.
In addition to providing general workforce
planning updates, the council should regularly
report its progress against its workforce
planning priorities to elected members
through its Council Plan updates or other
means.
Workforce planning updates and progress
against priorities will be regularly reported
through Council Plan Progress Reports and
other means.
The council should develop a performance
dashboard to provide a user-friendly overview
of the impact of its workforce planning. This
could help to inform future workforce
planning.
A performance dashboard will be developed to
monitor and inform future workforce planning.
Sco�sh Construc�on Quality Improvement Charter (CQIC)
In August, Cabinet approval was granted for our council to become signatories to the
Sco�sh Construc�on Quality Improvement Charter (CQIC). The CQIC is a Sco�sh campaign
aimed at improving construc�on quality and promo�ng good prac�ce to deliver improved
performance, create safer buildings, deliver compliance to building standards, and help
towards achieving net zero ambi�ons.
We have already taken steps to align processes to the CQIC with officers
integra�ng the guidance into requirements for the new build projects for
Ardrossan Campus and Montgomerie Park Primary School.

Page 35

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 27 of 49
The ini�a�ve is supported by the Sco�sh Futures Trust and all Sco�sh local authori�es are
encouraged to commit to the charter. Various contractors, trade associa�ons, professional
bodies, design consultants and other public sector bodies have also made a commitment to
the CQIC.
The Associa�on for Public Service Excellence (APSE)
Our Waste Resources Team were awarded a Gold Award for Waste and Recycling as part of
the APSE Striving for Excellence Awards in May 2024.  These awards are an opportunity for
Sco�sh local authori�es to demonstrate best prac�ce in delivering fleet, waste and grounds
services for their communi�es.
In November 2024, our teams were named as finalists in the APSE Performance Network
Awards across various categories.  In the Best Performer Category, Building Maintenance,
Environmental Health, Refuse Collec�on, Roads, Highways and Winter Maintenance and
Transport, Opera�ons and Vehicle Maintenance were nominated.  Nomina�ons were also
given in the Most Improved Performer Category for Building Maintenance, Roads, Highways
and Winter Maintenance and Transport, Opera�ons and Vehicle Maintenance.  Results will
be announced in December.
Educa�on
Educa�on Scotland published inspec�on reports on seven educa�onal establishments in
North Ayrshire in academic year 2023 to 2024 and the overall performance of our schools
and centres con�nues to be very posi�ve. 
The Care Inspectorate published inspec�on reports on eight local authority early learning
and childcare establishments in North Ayrshire in session 2023 to 2024, and the
performance of all these establishments was posi�ve. 
Since the introduc�on of the current inspec�on framework “How Good is our School? (4th
edi�on)” in session 2016 to 2017, there have been a total of 32 inspec�ons by Educa�on
Scotland across North Ayrshire’s schools and early years classes. During this period, North
Ayrshire has outperformed regional and na�onal comparators across all quality indicators. 
In addi�on, our schools have experienced a record year for “Sportscotland” School Sport
Awards with 16 schools awarded gold and six awarded silver.  10 are awai�ng their award.
The award looks at all aspects of school sport from curriculum physical educa�on and
teacher training to extracurricular provision and access to na�onal events. 
Next Steps
• We will con�nue to progress recommenda�ons arising from the Audit Scotland Best
Value Thema�c Work.
• We will con�nue to progress property ra�onalisa�on.
• We will commence our budget consulta�on for 2025-26.
• We will present an update to the Audit and Scru�ny Commitee,
providing greater detail on our council’s carbon emission repor�ng
and work to reduce scope 3 emissions.

Page 36

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 28 of 49 
Performance Summary 
Measures adri� of target
This sec�on details the performance indicators adri� of target and the ac�on being taken to
address performance. Due to expected data lags, the most recent data may relate to
previous �me periods but may only now be available to report. To avoid duplica�on, only
data that has not previously been reported to our Cabinet is included in this sec�on.  Further
details can be found in the Performance Indicators sec�on at the end of this report.
CP_10a % of procurement spent on local enterprises – Significantly Adri� / Red
This indicator is a ra�o of our local spend against total spend. Though this ra�o has
decreased, the amount of actual local spend has increased from £57.5million to
£71.5million. There was an increase of approximately £71million in overall external spend,
mainly due to an increase in large capital projects including flood protec�on schemes and
enabling works. These can only be carried out by �er one contractors and there were no
local �er one contractors who could bid for these contracts. However, the �er one
contractors reported subcontrac�ng to local suppliers to the value of £10million, which, if
considered in the above figure, would have increased the local spend percentage to 28%,
above our target of 26% for 2023 to 2024.  
On Target,
11, 42%
Slightly Adrift of
Target, 1, 4%
Significantly Adrift
of Target, 2, 8%
Data Only,
12, 46%
Performance Indicators
On Target,
45, 98%
Slightly Adrift
of Target, 1,
2%
Actions

Page 37

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 29 of 49
Changes to indicators
CP_06 Average total tariff score: All Leavers
CP_37 Average total tariff score of pupils living in SIMD 20% most deprived areas
CP_38 Average total tariff for Care Experienced Young People
For the above three indicators, the source data from Insight, the na�onal benchmarking tool
for analysing atainment data in the senior phase, has changed due to its annual review.  As
such, there are changes to previously reported data.  However these changes do not
substan�ally affect previously reported performance.
CP_44 % of council dwellings that are energy efficient (LGBF)
No data is available from the Improvement Service LGBF for this indicator.  The Sco�sh
Government is consul�ng on the new Social Housing Net Zero Standard (SHNZS) which will
replace the currently measured Energy Efficiency Standard for Social Housing (EESSH). 
Ac�ons Adri� of target
This sec�on details ac�ons adri� of target and the measures being taken to address
performance. Further details can be found in the Ac�on Tracker sec�on at the end of this
report.
CP 07 Maximising access to and uptake of benefits, en�tlements and financial advice.
This ac�on is currently slightly adri� of target (amber) due to a delay in the review and
refresh of the Financial Inclusion Strategy for 2024 to 2030.   However, the strategy is due to
be updated by early 2025 for 2025 to 2030 and delivery of support is con�nuing.  During the
first six months of 2024 to 2025 this has included:
• Integra�on of welfare rights services through our in-house team moving to single
case working and improved performance management system.
• Improved and streamlined referral pathways for services in line with our “Accessing
our Council” transforma�on ac�vity.
• Mee�ng targets for referrals to commissioned debt advice service.
• Increased capacity to support welfare rights within schools across North Ayrshire,
expanding the established successful approach from secondary schools into primary
and early years se�ngs.

Page 38

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 30 of 49
Benchmarking
The Local Government Benchmarking Framework (LGBF) provides an opportunity to
benchmark our performance with other local authori�es in Scotland. It is administered by
the Improvement Service in partnership with the Society of Local Authority Chief Execu�ves
(SOLACE) and highlighted within the Accounts Commission’s Statutory Performance
Informa�on Direc�on 2021 which defines how local authori�es should demonstrate they are
achieving Best Value for the people they serve. 
We have iden�fied 33 indicators that closely link to the priori�es within our Council Plan.
Data for these indicators is released in phases during the year. Areas such as CO2 emissions,
Gross Value Added and claimant count are included as priority indicators as they are
monitored by our council to reflect our opera�ng environment, though we have limited
influence on these areas directly. This sec�on demonstrates our rela�ve performance for
these indicators as at the October 2024 data release. This informa�on alongside the LGBF
Dashboard enables us to learn from others to improve services for our residents.
As at October 2024, 17 of our 33 priority indicators are in the top two quar�les. Top quar�le
performance includes areas such as percentage of pupils entering posi�ve des�na�ons,
immediately available employment land as a percentage of total land allocated for
employment purposes in the local development plan and percentage of invoices sampled
that were paid within 30 days.
In the short term (most recent one year period available), 26 of our 33 priority indicators
have shown improvement in performance, whereas seven have demonstrated a reduc�on in
performance. Some of the indicators which have improved include percentage of children
mee�ng developmental milestones, number of business gateway start-ups per 10,000
popula�on and street cleanliness score. Those that have declined in performance include
percentage of unemployed people assisted into work from council operated/funded
employability programmes, percentage of children living in poverty (a�er housing costs) and
the percentage of Sco�sh Welfare fund community care grant decision in 15 days. 
The following is a breakdown of the priority indicators that have been updated since our
year end repor�ng within the context of family groups. Family groups enable local
authori�es to make as close to a like for like comparison as possible with other councils by
grouping those with similar traits depending on the indicator. Grouping is based on levels of
depriva�on (people services) or rurality (other services): 
People Services
• North Ayrshire Council
• Comhairle nan Eilean Siar
• Dundee City Council
• East Ayrshire Council 
• North Lanarkshire Council
• Inverclyde Council 
• West Dunbartonshire Council
• Glasgow City Council
Other Services 
• North Ayrshire Council
• Perth and Kinross 
• S�rling Council 
• Moray Council 
• South Ayrshire Council 
• East Ayrshire Council 
• East Lothian Council 
• Fife Council

Page 39

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 31 of 49
Peoples Services
Propor�on of Children Living in Poverty A�er Housing Costs 
The most recent data release shows 29.2% of our children in North Ayrshire are living in
poverty (a�er housing costs). This is above the family group average of 27.2%. Only Glasgow
City Council has a higher propor�on of children living in poverty (a�er housing costs) at
32.9%. From 2021 to 2023 we moved from 31st to 30th in the rankings and we remain in the
4th quar�le.
Gross Rent Arrears (All Tenants) as a Percentage of Rent Due for the Year 
The gross rent arrears (all tenants) as a percentage of rent due for the year was 5.9%. This is
lower than the family group average of 8.3%. We are the strongest performing local
authority in our family group. Between 2022 and 2024 we have risen in the rankings from 6th
to 4th.  We remain in the 1st quar�le.

Page 40

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 32 of 49
Propor�on of Council Dwellings Mee�ng Sco�sh Housing Quality Standards 
The most recent data release shows that 76.9% of council dwellings mee�ng Sco�sh
Housing Quality Standards. This is lower than the family group average of 78%. As at 2023 to
2024, we are currently 2nd lowest of our family group, with West Dunbartonshire ranking
lower. Our ranking has remained the same from 2022 to 2024 at 16 which means we are in
the 2nd quar�le. The con�nuity of this data has been impacted by the energy efficiency
elements of Sco�sh Housing Quality Standards being replaced by the Energy Efficiency
Standard for Social Housing (EESSH).                               
Other Services
CO2 Emissions Area Wide per Capita 
The most recent data release shows 4.64 tonnes of CO2 area wide emissions compared to
the family group average of 5.5 tonnes. From 2021 to 2023 we have risen in rank from 20 to
18 but remain in the 3rd quar�le. East Ayrshire Council is currently performing most strongly
with 3.70 tonnes of CO2 emissions area wide.

Page 41

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 33 of 49
CO2 Emissions Area Wide:  Emissions within Scope of Local Authority per
Capita 
The most recent data release shows 4.97 tonnes of CO2 emissions within scope of North
Ayrshire compared to the family group average of 5.17 tonnes. We have risen in rank from
22 to 21 but remain in the 3rd quar�le. Similarly to the previous indicator, East Ayrshire is
currently performing most strongly within our family group with 4.13 tonnes of CO2
emissions within scope of the local authority. 
CO2 emissions area wide and within scope were impacted by con�nuity issues as during the
produc�on of the 2022 es�mates, new data was introduced alongside improvements to the
underlying methodology. To ensure that the data for 2005 to 2021 is consistent with the
data now available for 2022, the es�mates for these years have been revised to incorporate
both the new data and the improvements in the methodology. For some local authori�es,
these revisions have resulted in no�ceable changes to the emissions es�mates in historic
years.
CO2 Emissions from Transport per Capita

Page 42

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 34 of 49
Most recent data shows that there were 30.75 tonnes of CO2 emissions from Transport. This
is compared to our family group average of 25.99 tonnes. Between 2021 and 2023, there has
been decline in our ranking from 23rd to 25th (from the 3rd quar�le to 4th). Only Moray
Council with 43.81 tonnes of emissions from transport is currently performing less well than
our council. We have allocated significant funding towards the decarbonisa�on of our fleet
over current and future years.
CO2 Emissions from Electricity per Capita 
Most recent data shows that there were 44.92 tonnes of CO2 emissions from electricity. This
is compared to the family group average of 39.43 tonnes. Between 2021 and 2023, there has
been a decline in our ranking from 22nd to 23rd and we remain in the 3rd quar�le. Our CO2
emissions from electricity is currently the second lowest performing within our family group
with only S�rling Council recording a higher figure of 45.64 tonnes. Moray Council is
currently performing strongest with 30.23 tonnes. 
CO2 Emissions from Natural Gas per Capita

Page 43

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 35 of 49
The most recent data release shows 71.36 tonnes of CO2 emissions from natural gas
compared to the family group average of 52.55 tonnes. There has been a decline in our rank
from 24th to 25th, meaning we move from quar�le 3 to quar�le 4. We are currently
performing least well in this area.  Perth and Kinross Council is performing the strongest with
42.35 tonnes of CO2 emissions from natural gas. 
All three of the transport, electricity and natural gas CO2 emissions indicators have
con�nuity issues within the data. Although mid-year es�mates for mid-2022 have been
published, the denominator for this indicator con�nues to use up to mid-2021 es�mates.  As
Na�onal Records of Scotland (NRS) have advised that the mid-2022 es�mates should not be
compared to es�mates for years prior to 2021. NRS is undertaking work to revise mid-2011
to mid-2021 es�mates to ensure comparability between mid-2022 Es�mates and previous
years.
Claimant Count as a Percentage of Working Age Popula�on* 
The most recent data release shows the claimant count as a percentage of working age
popula�on is 4.4% compared to the family group average of 3.8%. From 2022 to 2024 our
rank has improved slightly from 31 to 30 though we remain in quar�le 4.

Page 44

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 36 of 49
Claimant Count as a Percentage of Popula�on Aged Between 16 and 24
Years* 
The most recent data release shows the claimant count as a percentage of popula�on aged
between 16 and 24 years is 5.6% compared to the family group average of 4.5%. We have
declined from 31 to 32 in the rankings and remain in quar�le 4. 
Number of Business Gateway Start-Ups per 10,000 Popula�on* 
The most recent data release shows the number of business gateway start-ups per 10,000
popula�on is 12.3, compared to the family group average of 14.3. Subsequently we have
risen in the rankings from 25th to 21st. Moving from the 4th to 3rd quar�le.
*The data is available monthly for these indicators and the yearly values for 2024 to 2025
are an average of the monthly values to date. In addi�on, cau�on is required when
comparing to previous years as Na�onal Records Scotland are undertaking work to revise
mid-2011 to mid-2021 popula�on es�mates to ensure consistency.

Page 45

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 37 of 49
Street Cleanliness Score 
The most recent data release within LGBF shows our street cleanliness score for 2023 to
2024 is 89.1%, compared to the family group average of 90%. However, most recent figures
available from the Local Environmental Audit and Management System (LEAMS) at Q2 2024
to 2025 show our percentage has increased to 91.7%, above the target of 87%.
Based on LGBF data. between 2022 and 2024 we have risen to the 3rd quar�le as our rank
has improved from 29th to 24th.

Page 46

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 38 of 49
Percentage of A Class Roads That Should Be Considered
for Maintenance Treatment
Percentage of C Class Roads That Should Be Considered
for Maintenance Treatment 
Percentage of B Class Roads That Should Be Considered
for Maintenance Treatment
Percentage of Unclassified Roads That Should Be
Considered for Maintenance Treatment

Page 47

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 39 of 49
The most recent data release for our roads indicators, shows 28.9% of A class roads should
be considered for maintenance treatment. This is compared to the family group average of
27.4%. We have also moved into the 3rd quar�le by improving our rank from 27th to 21st. For
B class roads 27.4% should be considered for maintenance treatment, compared to the
30.3% family group average. We have also moved into the 2nd quar�le by improving our rank
from 19th to 13th. For C class roads the most recent percentage that should be considered for
maintenance treatment is 38.5%, compared to the 31.9% family group average. Again, we
have improved our rank, from 27th to 26th, however we remain in quar�le 3. The percentage
of unclassified roads that should be considered for maintenance treatment is 32.4%,
compared to the 35.8% family group average. We have also risen in the rankings from 16th to
11th and remain in quar�le 2. 
The requirement for maintenance remained rela�vely constant over the past four years.
Please note, these are two-year rolling averages. 
Percentage of Total Household Waste Arising that is Recycled 
The most recent percentage of total house waste arising that is recycled was 56.1% and our
family group average was 52.3%. We remain in the first quar�le by rising from 4th to 3rd in
the rankings. This is currently the highest in our family group.

Page 48

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 40 of 49
Percentage of the Highest Paid 5% of Employees who are Women 
Our most recent figure for the percentage of the highest paid 5% of employees who are
women was 64.7%, whereas our average family group percentage was 60.2%. This is a rise
from the 2nd to 1st quar�le and improvement in rank from 10th to 4th. We currently perform
strongest within our family group.
Percentage of Income Due from Council Tax Received by the End of the Year 
The most recent data release shows that 93.6% of income due from Council Tax was
received by the end of the year compared to the family group average of 94.2%. We remain
in the 4th quar�le as we have declined from 29th to 30th in the rankings. We are currently
performing least well within our family group with Perth and Kinross and S�rling councils
performing most strongly.

Page 49

Our Council Plan Progress Update – Mid Year 2024 to 2025 Page 41 of 49
Percentage of Invoices Sampled that were Paid within 30 Days 
The percentage of invoices sampled that were paid within 30 days was 95.8%, compared to
the 89.5% family group average. We have improved to reach the 1st quar�le moving from
11th to 7th in rank. Only Fife Council with 96.41% is ahead of our council in the family group
rankings.
Percentage of Opera�onal Buildings that are Suitable for their Current Use 
The percentage of opera�onal buildings that are suitable for their current use is 95.2%
compared to the family group average of 90.7%. We remain at 6th in the ranking and in
quar�le 1. Only Perth and Kinross and Moray councils are performing more strongly within
our family group.

Page 50

Our Council Plan Progress Update – Mid Year 2024 to 2025        Page 42 of 49
Performance Indicators
PI Code and Description 2021-22
Value
2021-22
Target
2021-22
Status
2022-23
Value
2022-23
Target
2022-23
Status
2023-24
Value
2023-24
Target
2023-24
Status
Q2
2024-25
Value
Q2
2024-25
Target
Q2
2024-25
Status
2024-25
Target
CP_36 Number of residents participating in
community learning and development activity
including youth work   
17,804   23,503 18,700  10,228   19,500
CP_04 Proportion of children meeting
developmental milestones (LGBF) 78.7%   79.5%  
Data
Available
April
2025
79%  Not measured for Quarters 79%
CP_37 Average total tariff score of pupils living
in SIMD 20% most deprived areas 704.8   670.2  
Data
Available
March
2025
714  Not measured for Quarters 720
CP_06 Average tariff score: All Leavers 905.6 880  847.2  
Data
Available
February
2025
908  Not measured for Quarters 910
CP_38 Average total tariff for care experienced
Young People 450.3   411.5  
Data
Available
March
2025
465  Not measured for Quarters 470
CP_07 % of school leavers entering positive
destinations (LGBF) 96% 93.5%  96.5%  
Data
Available
February
2025
96.4%  Not measured for Quarters 96.8%
CP_39b Number of unemployed people that
have progressed to employment as a result of
participation in council funded or operated
employability activities
555   427   475   Not measured for Quarters 475
CP_10a % of procurement spend on local
enterprises 22.93% 24%  26.04% 25%  24.48% 26%  Not measured for Quarters 27%
PI Status 
Significantly Adrift of Target 
Slightly Adrift of Target 
On Target 
Data Not Available 
Data Only

Page 51

Our Council Plan Progress Update – Mid Year 2024 to 2025        Page 43 of 49
PI Code and Description 2021-22
Value
2021-22
Target
2021-22
Status
2022-23
Value
2022-23
Target
2022-23
Status
2023-24
Value
2023-24
Target
2023-24
Status
Q2
2024-25
Value
Q2
2024-25
Target
Q2
2024-25
Status
2024-25
Target
CP_40 Number of new build housing units
reaching completion (all tenures) (actual not
cumulative)   
562   384 295  74   396
CP_41 Number of empty homes brought back
into use (actual) 335   120   378 200  84   300
CP_28 Hectares of vacant and derelict land in
North Ayrshire 1,198 1,144  1,130 1,094  951 1,094  Not measured for Quarters 925
CP_27 Street Cleanliness Index - % Clean (LGBF) 86.7 94  84.6 90  89.1 87  91.7* 87  87
CP_20 Overall percentage of road network that
should be considered for maintenance
treatment
33.9% 37.5%  34.8% 33.8%  32.5% 34.8%  Not measured for Quarters 32.5%
CP_42 Provided floor space of
commercial/industrial space within our council
portfolio (sq. ft)   
400,991   404,897 404,755  Not measured for Quarters 423,077
CP_02 % of council budget directed via
participatory methods 2.32% 1.1%  2.74% 1%  2.05% 1.5%  1.85% 1%  1.5%
CP_43 Number of council assets under
community management (cumulative)    49   53 54  54   56
CP_30 Total installed capacity of low carbon
heat and electricity generation across the
council's estate
11,680 11,000  12,104 11,800  15,992 12,000  Not measured for Quarters 28,499
CP_29 Overall carbon emissions (tonnes) (Non-
domestic council estate) 21,791 21,247  20,896 21,000  20,745 19,500  4,027   19,953

Page 52

Our Council Plan Progress Update – Mid Year 2024 to 2025        Page 44 of 49
PI Code and Description 2021-22
Value
2021-22
Target
2021-22
Status
2022-23
Value
2022-23
Target
2022-23
Status
2023-24
Value
2023-24
Target
2023-24
Status
Q2
2024-25
Value
Q2
2024-25
Target
Q2
2024-25
Status
2024-25
Target
CP_44 % of council dwellings that are energy
efficient (Formerly known as SHSN05a)
(LGBF)**
97.7       98.1  Not measured for Quarters 98.5
CP_45 Length of new or improved active travel
routes per annum (Metres)    1,090   3,900 2,000  Not measured for Quarters 2,000
CP_46 Number of trees planted under the
North Ayrshire 2030 Tree Planting Strategy       36,531 40,000  Not measured for Quarters 47,000
CP_19 Proportion of operational buildings that
are suitable for their current use (LGBF) 91.1% 93%  95.1% 93%  95.2% 92.1%  Not measured for Quarters 93%
CP_31 % of total household waste that is
recycled (calendar year as per SEPA) (LGBF) 56.3% 53.1%  55.3% 56.9%  56.1% 57% 
Data
Available
Nov 2024
51%  56%
CP_25 % of council dwellings that meet the
Scottish Housing Quality Standard (LGBF) 49.3% 99.5%  63.2%   76.9% 72.5%  Not measured for Quarters 97.4%
CP_47 Gross rent arrears (all tenants) as at 31
March each year as a percentage of rent due
for the reporting year (LGBF)
6.6%   7.1%   5.9% 6.5%  Not measured for Quarters TBC
CP_48 % of income due from council tax
received by the end of the year (LGBF) 93.34%   94.7%   93.6% 94%  Not measured for Quarters 98% 
*Sourced from the Local Environmental Audit and Management System (LEAMS) audit conducted by Keep Scotland Beau�ful.
** The 2025 and 2032 EESSH Milestones have been suspended as the Sco�sh Government are reviewing the EESSH2 standards to strengthen and realign the standard with
the target for net zero heat in houses from 2045.

Page 53

Our Council Plan Progress Update – Mid Year 2024 to 2025      Page 45 of 49  
Ac�on Tracker 
Action Status 
Significantly Adrift of Target 
Slightly Adrift of Target 
On Target
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP01 Ensuring that wellbeing is at the heart of local life and
opportunities, with a focus on tackling inequalities.                   
CP02 Developing a Community Wealth Building approach to a
wellbeing economy.                   
CP03 Improving educational attainment and achievement and
closing the attainment gap.                   
CP04 Improving outcomes for care experienced young people
including implementation of The Promise.                   
CP05 Developing the Young Workforce and ensuring positive
destinations for school leavers.                   
CP06 Providing lifelong learning opportunities for individuals and
organisations, including digital literacy.                   
CP07 Maximising access to and uptake of benefits, entitlements and
financial advice.                  
CP08
Ensuring that supports are available in communities to alleviate
cost-of-living pressures through community hubs and
networks.

Page 54

Our Council Plan Progress Update – Mid Year 2024 to 2025      Page 46 of 49  
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 
CP09
Through our housebuilding programme and wider Housing
Investment provide homes for life that meet the needs of our
residents.                   
CP10
Increase the number of homes in the area through a mix of
private and social developments and bringing empty buildings
back in to use.                   
CP11 Exploration of models and the development of pilot schemes
to increase access to and use of public/community transport.                   
CP12 Ensure our places and spaces where we live, work and visit are
well maintained and accessible.                   
CP13 Developing infrastructure to support business growth.                   
CP14 Support KA Leisure’s leadership of North Ayrshire’s Health and
Wellbeing Alliance.                   
CP15
Through the Health and Social Care Partnership Strategic Plan
we will protect and provide care and support for those in
need.***                   
CP16
Developing strong relationships with communities and partners
based on trust and shared aspirations using their experiences
to inform service provision.                   
CP17
Providing support for community organisations in achieving
their goals, including as Community Wealth Building anchor
organisations.                   
CP18 Creating a participation and engagement framework which
ensures opportunities and support for all residents to take part

Page 55

Our Council Plan Progress Update – Mid Year 2024 to 2025      Page 47 of 49  
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
in influencing local democracy and council and partner
strategies. 
CP19 Supporting participatory budgeting.                   
CP20 Supporting community asset transfer and community owned
and operated/managed assets.                   
CP21 Supporting the Community Planning Partnership and the
Community Plan (LOIP).                   
CP22 Developing partnerships with the third and voluntary sector.                   
CP23
Placemaking, including creation of locality action plans based
on the Community Plan (LOIP) priorities and support the
delivery of Islands Plans.                   
CP24 Ensuring an inclusive, fair, rights-based and asset-based
approach in our work.                   
CP25 Accessible public services, both digitally and locally, ensuring a
‘No Wrong Door’ approach.                   
CP26 Embedding our net-zero ambition in all democratic decision-
making.                   
CP27
Reducing the carbon footprint of our estate through
rationalisation utilising a locality-based approach and taking a
fabric first and low carbon energy generation approach to
homes and buildings.

Page 56

Our Council Plan Progress Update – Mid Year 2024 to 2025      Page 48 of 49  
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP28
Improving resilience and reducing carbon by developing and
supporting supply chains where materials and goods are
sourced locally.                   
CP29 Promoting new woodland creation and protecting our green
spaces to provide a natural resource for carbon sequestration.                   
CP30 Supporting local businesses as they meet their climate change
obligations.                   
CP31
Promoting a circular economy in North Ayrshire to reduce
consumption of raw materials and promote reuse, repair and
recycling, and generating energy from residual waste.                   
CP32 Developing local low carbon energy generation schemes and
networks.                   
CP33
Unlocking the potential of community owned energy
generation to bring new income streams into communities and
help them take direct action to combat climate change.                   
CP34
Learning for sustainability, and work with communities to
adopt low carbon behaviour change and encourage climate-
based volunteering activities.                   
CP35 Improving communities’ preparedness to deal with the impacts
of climate change already locked-in.                   
CP36 Working with communities to adopt low carbon behaviour
change and encourage climate-based volunteering activities.                   
CP37 Taking a nature-based approach to protect our habitats and
species.

Page 57

Our Council Plan Progress Update – Mid Year 2024 to 2025      Page 49 of 49  
***Delivery of this ac�on is managed through the Health and Social Care Partnership Strategic Plan.
Priority
Ref # Existing Overall Action
2023-24
2023-24
2023-24
2024-25
2024-25
2024-25
2024-25
2025-26
2025-26
2025-26
2025-26
2026-27
2026-27
2026-27
2026-27
2027-28
2027-28
2027-28
2027-28   
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
CP38 Developing and promoting active travel infrastructure.                   
CP39 Transitioning to low and zero carbon travel.                   
CP40
Ensuring robust governance arrangements are in place to fulfil
the council’s statutory duties, manage risk and support delivery
of key priorities.                   
CP41 Using dynamic data and lived experiences to inform decision-
making.                   
CP42 Working with partners nationally, regionally and locally to
secure investment and target resources towards our priorities.                   
CP43
Driving change and transformation, using technology where
appropriate, to deliver efficient and effective services and
support delivery of priorities.                   
CP44 Maximising financial flexibilities to help support delivery of
priorities.                   
CP45 Maximising value from the use of our assets.                   
CP46 Focusing our investment on priorities.                   
CP47 Effective workforce planning ensuring that we have the right
skills/resources to deliver priorities.

Page 58

Our Council Plan Progress Update – Mid Year 2024 to 2025     
Page 50 of 49   
We strive to make our repor�ng as accessible as possible. If you have
any ques�ons or require further informa�on on our council’s
performance please contact:
The Corporate Policy and Performance Team
Tel:  01294 310000  Email:  NorthAyrshirePerforms@north-ayrshire.gov.uk
Reports can be viewed at www.north-ayrshire.gov.uk.