NORTH AYRSHIRE COUNCIL 
03 December 2024 
Cabinet
Title: Strategic Housing Investment Plan 2025 – 2030
Purpose: To seek Cabinet approval of the Strategic Housing Investment   
Plan 2025 – 2030 
Recommendation: That Cabinet: (i) approves the Strategic Housing Investment Plan
2025-2030 at Appendix 1 for submission to Scottish Government;
(ii) approves the projects set out within the SHIP shadow
programme at Appendix 1; (iii) gives delegated authority to the
Executive Director (Communities and Housing) and the Cabinet
Member for Communities and Islands to liaise directly with the
Scottish Government in agreeing the acceleration of projects in
the main SHIP programme, as required; and (iv) notes that
acceleration of any projects from the SHIP shadow programme
will require Cabinet approval. 
1. Executive Summary 
1.1 The Strategic Housing Investment Plan (SHIP) is reviewed annually and sets out the
priorities and locations for affordable housing investment by the Council and registered
social landlords in North Ayrshire for a five-year period. 
1.2 Cabinet approved the Strategic Housing Investment Plan 2024 – 2029, delivery of 26 new
homes at St Mary’s, Largs, and a Buy Back programme to support Ukrainian Displaced
People in November 2023. The reports made a combined commitment for the Council and
its partners to deliver 1,368 new affordable homes by March 2029, supported by
anticipated £130m Scottish Government grant funding from April 2023 to March 2029. A
total of 78 new build homes and 42 buybacks were completed during 2023/24 from the
1,368 target. 
1.3 In May 2024, the Council was advised of a reduction to the 2024/25 funding Resource
Planning Assumption (RPA), and of an expectation that the funding would reduce in future
financial years. For strategic planning purposes, the Council was advised that the level of
funding that the government can legally commit to, for the current and three future financial
years (April 2024 to March 2028), is £33.264m. In September 2024, the 2024/25 RPA was
increased by £0.293m to be utilised to acquire housing (new build or off the shelf) and / or
to bring long term voids back into use to address temporary accommodation pressures,
revising the legal commitment value to £33.557m. 
1.4 Officers have been advised to assume funding for the Strategic Housing Investment Plan
2025-2030 at £11.880m per annum from April 2025 to March 2030. The draft SHIP is

Page 2

therefore based on projected Scottish Government grant funding of £71.573m for the
Council and its partner landlords for the six years from April 2024 to March 2030. 
1.5 The Council and its partners have legally agreed funding commitments totalling £32.876m
to date. When deducted from the current £33.557m maximum legal commitment available
this results in a balance of £0.681m uncommitted funding. 
1.6 The amount of funding that the government can legally commit to will increase if: 
• the Council is successful in obtaining additional funding from the £40m unallocated
grant allowance for local authorities during 2025/26.
• the Council is able to claim funding from slippage in other local authority areas.
• the RPA award for 2025/26 is above the current £9.504m legal commitment. 
1.7 Due to the funding reductions, existing projects have had to be prioritised based upon
housing need, deliverability, strategic alignment, value for money, and their impact upon
community regeneration in order to align with the grant funding envelope currently
available. Projects which cannot be supported in the main programme, due to the current
lack of funding, have been moved to a shadow programme which will be accelerated,
subject to Cabinet approval, should slippage occur in the main programme, or if additional
funding becomes available. 
1.8 To increase capacity, and as one of the sites is currently in use, the following projects
have been removed from the programme: 
• Refurbishment project 8 (2 units), North Ayrshire Council 
• Glebe Place, Saltcoats (8 units), North Ayrshire Council (currently in use)
• Unallocated block (67 units), Cunninghame Housing Association 
1.9 The Council and its partners continue to experience significant affordability challenges
due to changes in the rate of inflation, higher than budgeted interest rates for borrowing
and increasing housing standards and specifications, compared to the level of grant
funding available to offset these pressures. 
1.10 The Council projects detailed within the main programme represent Council investment of
£173.644m, supported by £80.550m Scottish Government Grant. Following the review of
the SHIP, an estimated additional £9.171m is required beyond the funding allocated in the
latest HRA 30-year Business Plan, which is expected to be addressed by an estimated
additional £12.524m in grant funding for the Council projects within the main programme.
The Council projects in the prioritised SHIP have grant funding assumed at benchmark
rates inflated to the site start date at an assumed 3.1% per annum. The funding variances
are considered within the current review of the HRA Business Plan, prior to it being
presented to Council in February 2025 as part of the 2025/26 HRA budget and rent setting. 
1.11 The Council projects within the shadow programme represent Council investment of
£41.289m, supported by £23.802m Scottish Government Grant. The Council projects in
the shadow programme have grant funding set at levels which will allow the schemes to
be wholly funded with borrowing costs offset by rental income, this approach has been
taken to remove the impact of these sites from the HRA Business Plan as part of the
2025/26 HRA budget and rent setting.

Page 3

1.12 The Council has delivered 897 new build homes (as at 11 November 2024) against its
1,641 unit target, with 744 homes still to be completed. The amendments to the SHIP
revise the Council’s cumulative new build development target to 1,643 units. 
1.13 It is proposed that delegated authority is assigned to the Executive Director (Communities
and Housing), in consultation with the Cabinet Member for Communities and Islands, to
liaise with the Scottish Government and agree the acceleration of projects detailed in the
main Strategic Housing Investment Plan, as required. This is of particular importance
where deliverability is delayed due to emerging constraints and challenges that require to
be addressed. Cabinet approval will be required for the acceleration of any projects in the
shadow programme or for the addition of any new projects to the approved Strategic
Housing Investment Plan. 
1.14 The draft Strategic Housing Investment Plan 2025 - 2030 aims to secure investment in a
total of 1,143 properties, providing sustainable, affordable, accessible, and high-quality
homes which will contribute to the wider regeneration aims for the area. This will in turn
secure employment and training opportunities for North Ayrshire businesses and residents
and support the Council’s Community Wealth Building Strategy. Members are invited to
approve the SHIP and the shadow programme at Appendix 1 for submission to the
Scottish Government, as the Council’s investment plan for new affordable housing in the
area over the next five years. 
2. Background 
2.1 The Strategic Housing Investment Plan (SHIP) sets out the priorities and locations for
affordable housing investment by the Council and registered social landlords in North
Ayrshire over a five year period to support the outcomes in the Local Housing Strategy. It
is prepared in accordance with Scottish Government guidance and includes details of
individual development projects to be taken forward over its lifespan (see Appendix 1). 
2.2 Cabinet approved the Strategic Housing Investment Plan 2024 – 2029 on 7 November
2023 which made a commitment for the Council and its partners to deliver 1,302 new
homes, on the assumption that this would be supported by £124m Scottish Government
grant funding. Cabinet also approved the development of 26 new homes on the former St
Mary’s school site, supported by £4m Scottish Government grant funding, and the
acquisition of up to 40 properties supported by £2m grant to accommodate Ukrainian
Displaced People for three years. 
2.3 The reports made a combined commitment for the Council and its partners to deliver 1,368
new affordable homes by March 2029, supported by £130m Scottish Government grant
funding for the six years from April 2023 to March 2029. 
2.4 In accordance with Scottish Government guidance, the Council has historically over-
committed the funding within the Strategic Housing Investment Plan by approximately 25%
to ensure that the full grant allocation is spent, and to provide the opportunity for North
Ayrshire to absorb slippage from other local authority areas.   
2.5 A total of 78 new build homes were completed during 2023/24 towards the 1,368 target.
This comprises Cunninghame Housing Association’s 24 homes at Green Street, Saltcoats,
and for the Council, the remaining 36 homes at Irvine Harbourside, six bungalows at Afton
Court, Stevenston, and 12 amenity flats at the former Largs Police Station.

Page 4

2.6 The Council and its partners acquired 42 buybacks during 2023/24. The Council
purchased 33 homes for Ukrainian households and five homes for the Council’s buyback
programme. Riverside Scotland bought back two homes in Kilwinning and Trust Housing
Association acquired two homes on Arran. 
Resource Planning Assumption 
2.7 The Council was advised of a reduction to the 2024/25 funding Resource Planning
Assumption (RPA) in May 2024. The Council was also advised of an expectation that the
funding would reduce in future financial years. The Scottish Government committed to
providing North Ayrshire Council and its registered social landlord partners with grant
funding of £11.880m from April 2024 to March 2025 and advised the amount of funding
which could be legally committed for April 2025 to March 2028 is: 
• 80% of £11.880m for 2025/26 (£9.504m).
• 60% of £11.880m for 2026/27 (£7.128m).
• 40% of £11.880m for 2027/28 (£4.752m). 
2.8 In September 2024, the Council was advised of a £0.293m increase to the 2024/25
Resource Planning Assumption, revising it to £12.173m. This funding is allocated from a
£40m fund for local authorities during 2024/25 to address temporary accommodation
pressures. The £0.293m should be directed towards acquisitions to help address
temporary accommodation pressures or, where appropriate, to bring long term voids back
into use. Acquisitions can either be existing properties or new build properties ‘off the
shelf’. There is a further £40m fund to be distributed to local authorities during 2025/26,
the allocation of which is still awaited. 
2.9 For strategic planning purposes, the level of funding that the government can currently
legally commit to from April 2024 to March 2028 is therefore £33.557m as illustrated in
Table 1 below.   
Table 1: Government grant funding which can be legally committed by financial year
Financial
year
Maximum legal
commitment
2024/25 £12.173m
2025/26 £9.504m
2026/27 £7.128m
2027/28 £4.752m
Total £33.557m 
2.10 The Council and its registered social landlord partners have offers of grant funding totalling
£44.245m (as at 1 October 2024) to deliver 369 units for the four year period as detailed
within Table 2 below. A total of £11.369m of this funding had been claimed as at 31 March
2024, leaving a £32.876m balance still to be claimed. 
Table 2: SHIP projects with committed Scottish Government grant funding.
Site Units
Scottish
Government
Grant (£m)
Pre 2024/25
Spend (£m)
Future
Spend (£m)
Laburnum Avenue, Beith (NAC) 7 £0.700 £0.621 £0.079
Newhouse Drive, Kilbirnie (NAC) 7 £0.699 £0.620 £0.079

Page 5

St Mary's, Largs (NAC) 26 £3.977 £2.458 £1.519
James McFarlane, Ardrossan (NAC) 19 £1.993 £0.801 £1.192
Stanecastle, Irvine (NAC) 31 £3.204 £1.082 £2.122
King's Arms, Irvine (NAC) 6 £0.769 £0.313 £0.456
Garnock Academy, Kilbirnie (NAC) 50 £5.307 £0.530 £4.777
Ayrshire Central, Irvine (NAC) 202 £24.356 £2.253 £22.103
Garven Road, Stevenston (CHA) 20 £3.200 £2.691 £0.509
Riverside Buy Back Programme 1 £0.040 £0.000 £0.040
Total 369 £44.245 £11.369 £32.876 
2.11 Deducting the £32.876m required from the £33.557m maximum legal commitment
available leaves a balance of £0.681m uncommitted funding. As set out at 2.8 above,
£0.293m should be committed to address temporary accommodation pressures, resulting
in £0.388m uncommitted funding for the remaining projects within the Strategic Housing
Investment Plan. 
2.12 Officers have been advised to assume funding for the Strategic Housing Investment Plan
2025-2030 at £11.880m per annum for the five years from April 2025 to March 2030. The
draft Strategic Housing Investment Plan is therefore based on projected Scottish
Government grant funding of £71.573m for the Council and its partner landlords for the
six years from April 2024 to March 2030 as illustrated in Table 3 below. 
Table 3: Resource Planning Assumption and maximum legal commitment per annum (£m) 
2024/25 2056/26 2026/27 2027/28 2028/29 2029/30 Total
(£m)
Resource
Planning
Assumption
£12.173 £11.880 £11.880 £11.880 £11.880 £11.880 £71.573
Maximum
legal
commitment 
£12.173 £9.504 £7.128 £4.752 £0.000 £0.000 £33.557 
2.13 In summary, whilst the Council’s assumed financial envelope for the period is £71.573m,
the amount of funding that the government can currently commit to legally is £33.557m.
This means that applications for funding beyond the £0.681m uncommitted funding
balance cannot be approved until further funding becomes available, which, in time, could
delay development.   
Preparing the Strategic Housing Investment Plan 2025 - 2030 
2.14 Due to the funding reductions, the existing SHIP projects have been prioritised based upon
housing need, deliverability, strategic alignment, value for money, and their impact upon
community regeneration to align to the grant funding envelope anticipated to be available.
Projects which cannot be supported in the main programme, due to the current lack of
funding, have been moved to a shadow programme which will be accelerated, subject to
Cabinet approval, should slippage occur in the main programme, and/or if additional
funding becomes available or as part of future annual SHIP reviews. 
2.15 Bringing primarily former social housing stock back into ownership can assist with housing
management and maintenance issues, increases housing supply, supports the Council’s
Regeneration Delivery Plan, and contributes to bringing long-term empty homes back into
use. All developing registered social landlord partners buyback programmes have

Page 6

therefore been prioritised within the Strategic Housing Investment Plan. 
2.16 The projects which have been prioritised in the main programme, which do not already
have an offer of grant as set out within Table 2 above, are detailed in Table 4 below
alongside the rationalisation for their prioritisation. The Council projects in the prioritised
SHIP have grant funding assumed at benchmark rates inflated to the site start date at an
assumed 3.1% per annum. 
Table 4: Projects prioritised in the main SHIP programme
Site Units Estimated
Site Start
Grant
funding
(£m)
Pre
2024/25
Grant
Spend
(£m)
Future
Grant
Spend
(£m)
Council
funding
(£m)
Rationale for
prioritisation
Nelson Street,
Largs (NAC) 3 Apr 2025 £0.171 £0 £0.171 £0.461
These homes are currently
empty and require
investment to be brought
back into effective use
Montgomerie
Park, Irvine
(NAC)
188 Mar 2026 £24.822 £4.579 £20.243 £29.285
Significant level of grant
claimed to date in relation
to site acquisition and
ground consolidation costs.
Site forms part of
compensatory provision for
the demolition of high flats.
Site contributes to wider
Masterplan area and school
roll.
Nursery Place,
Ardrossan
(NAC)
6 Apr 2026 £0.796 £0 £0.796 £0.962
The existing flatted
accommodation is being
vacated and the blocks are
scheduled for demolition.
The schemes require a low
level of investment making
them a good fit to absorb
slippage. 
Grange Court,
Stevenston
(NAC)
6 Apr 2026 £0.824 £0 £0.824 £0.683
Fullarton Street,
Irvine (NAC) 43 Jul 2026 £5.902 £0 £5.902 £7.051
The high flats have been
demolished and the
development will contribute
to stock replacement and
regenerate the vacant site
which is in a prominent
location.
Bourtreehill
Village, Irvine
(NAC)
32 Aug 2028 £4.630 £0 £4.630 £5.294
Crofthead Court has been
vacated and is scheduled
for demolition. The site is
part of a wider area
regeneration.
Springbank,
Arran (Trust) 26 Dec 2025 £5.000 £0 £5.000 
Arran development has
been long standing in the
SHIP and the site
contributes to addressing
housing need on the island.
Council Buy
Backs 60 Apr 2024 £2.400 £0 £2.400 £3.403 The acquisition of market
housing & empty homes
can assist with housing
management &
maintenance issues &
increase housing available
for social rent.
Cairn Buy Backs 2 Apr 2024 £0.085 £0 £0.085 
CHA Buy Backs 6 Nov 2023 £0.240 £0 £0.240 
Riverside Buy
Backs 14 Apr 2023 £1.328 £0.080 £1.248 
Trust Buy Backs 6 Nov 2023 £0.600 £0.196 £0.404

Page 7

Total 392  £46.798 £4.855 £41.943 £47.139 
2.17 Deducting the £32.876m legally committed sites and £41.943m sites prioritised within the
SHIP from the £71.573m projected grant funding leaves a balance of (£3.246m) for the
sites within the SHIP shadow programme.   
2.18 The Council projects in the shadow programme have indicative grant funding set at levels
which will allow the schemes to be wholly funded with borrowing costs offset by rental
income, this approach has been taken to remove the impact of these sites from the HRA
Business Plan as part of the 2025-26 HRA budget and rent setting review. It should be
noted that whilst this approach reduces the impact upon the HRA Business Plan, it
increases the demand upon the Resource Planning Assumption funding available within
the SHIP. The registered social landlord funding rates are also indicative and will be
subject to review at the point of the funding application when a construction tender has
been received. The projects in the shadow programme are listed in Table 5 below. Some
sites have been anonymised for reasons of commercial sensitivity, or as they require
further work to ensure that they comply with the Council’s Planning or Roads policies. 
Table 5: Projects in the SHIP shadow programme
Site Units Estimated
Site Start
Grant
Funding
(£m)
Pre
2024/25
Spend
(£m)
Future
Spend
(£m)
Comments /
constraints / current
challenges
Corsehillhead,
Kilwinning (NAC) 7 Jul 2027 £1.908 £0.203 £1.705
Options appraisal
required for financial
viability.
James Reid,
Saltcoats (NAC) 46 Jul 2027 £7.215 £0.830 £6.385
Culvert issues are
preventing Scottish
Water approval.
St Michael’s P3,
Kilwinning (NAC) 46 Oct 2027 £7.433 £0 £7.433
Site replaces the
unallocated
regeneration block.
Regeneration 1d,
Ardrossan (NAC) 36 Jan 2028 £7.246 £0 £7.246 Awaiting confirmation
of site availability.
Redburn Place
(Confidential site
1), Irvine (Cairn)
10 Oct 2025 £1.800 £0 £1.800 Planning consent
required.
Confidential site 3,
Kilwinning (Cairn)  4 Apr 2027 £0.407 £0 £0.407
Planning consent and
land acquisition
required.
Confidential site 12,
Kilwinning (CHA) 25 Apr 2026 £4.000 £0 £4.000
Site replaces part of
CHA unallocated
block.
Bank Street (111),
Irvine (CHA) 16 Apr 2027 £2.560 £0 £2.560 Proposals to be
agreed with CHA.
Sharphill (Ph 5),
Saltcoats (CHA) 100 Oct 2028 £14.800 £1.277 £13.523 Financial viability
assessment required.
Confidential site 10,
Ardrossan (CHA) 50 Apr 2029 £8.000 £0 £8.000
Land acquisition and
site feasibility
assessment required.
Parkend Gardens,
Saltcoats (Link) 12 Jan 2029 £1.910 £0.083 £1.827 Financial feasibility
review is ongoing.
Regeneration 3,
Kilwinning
(Riverside)
30 Apr 2028 £2.834 £0 £2.834 Location to be
finalised.
Total 382  £60.113 £2.393 £57.720 
2.19 It should be noted that the amount of funding that the government can legally commit to

Page 8

will increase if: 
• the Council is able to claim funding from slippage in other local authority areas.
• the Resource Planning Assumption award for 2025/26 is above the current £9.504m
legal commitment.
• the Council is successful in obtaining additional funding from the £40m unallocated
grant allowance for local authorities during 2025/26. 
2.20 The financial and / or technical feasibility is still being reviewed for a number of the sites
within the SHIP. 
Alternative funding and delivery models 
2.21 The Strategic Housing Investment Plan is not the only funding mechanism being explored
to deliver new build or acquired affordable housing. The Council and its partners are
exploring alternative delivery and funding models to maximise the funding available, and
units delivered, and reduce demand for the Council’s Resource Planning Assumptions.
For example, Trust Housing Association are accessing the governments Affordable
Housing for Key Workers initiative to acquire second hand homes on Arran. It is hoped
that alternative delivery mechanisms can free up funding within the main SHIP
programme, or assist to fund projects within the shadow programme, if funding does not
become available through slippage or additional grant funding allocations. As part of the
annual rent consultation an option has been included to consider an additional 1%
increase to support an increased provision of Council housing. 
Amendments to the SHIP 
2.22 In order to increase capacity within the SHIP, and as one of the sites is currently in use,
the projects listed below have been removed from the programme:
• The Council’s 2 unit refurbishment project 8 (£0.114m) 
• The Council’s 8 unit Glebe Place, Saltcoats project (£0.836m)
• 67 units from Cunninghame Housing Association’s unallocated block (£10.720m) 
2.23 An options appraisal determined that refurbishment project 8 would not represent value
for money and therefore the site was not acquired. The Glebe Place, Saltcoats homes,
which were previously scheduled for demolition, are currently occupied following
refurbishment, the options for the site will be considered when the properties become void.
Cunninghame Housing Association has retained 25 units from its unallocated block for a
scheme in Kilwinning. There are no other schemes associated with the remaining 67 units
which have been removed to aid overall affordability of the programme based on current
funding assumptions. 
2.24 The following amendments have also been made to the Strategic Housing Investment
Plan:
• The Council’s Montgomerie Park, Irvine site has been reduced from 189 to 188
units due to site constraints. The one excess unit has been moved to the
unallocated regeneration block.
• The Council’s Fullarton site has been reduced from 62 units to 43 units due to site
restrictions associated with flood risk. The 19 excess units have been moved to the
unallocated regeneration block.

Page 9

• The Council’s James Reid site has been reduced from 47 units to 46 units due to
site constraints. The one excess unit has been moved to the unallocated
regeneration block.
• The eight units associated with the Council’s Glebe Place, Saltcoats project have
been moved to the unallocated regeneration block as the site has been removed
from the plan.
• The Council’s unallocated regeneration block has been increased from 15 units to
44 units, utilising the 29 units reallocated from the four sites above. 
• A site has been identified for the Council’s unallocated units which will complete
the final phase of the former St Michael’s Academy in Kilwinning. The site can
provide 46 units, and as grant has been assumed at a rate which will deliver the
site with no impact to the HRA 30 year business plan, the additional two units have
also been included within the SHIP shadow programme. 
2.25  The Scottish Government benchmark grant rates are subject to annual inflation in line with
the Scottish Social Housing Tender Price Index. The Council and its partners continue to
experience significant affordability challenges due to changes in the rate of inflation, higher
than budgeted interest rates for borrowing and increasing housing standards and
specifications, compared to the level of grant funding available to offset these pressures.
The government has advised the Council and its partners that there is flexibility within the
grant award assessments and to seek funding at the minimum levels required to deliver
schemes, as the benchmark levels are set to determine the funding appraisal route. It
should be noted that each project is assessed on a case by case basis and funding may
be capped in accordance with the government’s value for money assessment. If the grant
funding obtained for sites increases, the capacity of the total Resource Planning
Assumption (which has been treated as fixed) will be reduced, as less units can be
delivered within the overall funding available. 
Progress to date 
2.26 The Council and its partners have delivered 1,778 new build homes since April 2013.
.
2.27 The approval of the Strategic Housing Investment Plan 2024 – 2029 revised the Council’s
new build completion target to 1,615 units. The addition of the 26 units at the former St
Mary’s site in Largs further revised the target to 1,641 units. The Council had delivered
885 new build homes to 31 March 2024, with 756 homes still to be completed. A further
12 homes have been completed at Newhouse Drive, Kilbirnie (three homes) and St Mary’s,
Largs (nine homes) as at 11 November 2024 leaving 744 homes still to be completed. 
2.28 The Council’s new build development target has been increased to 1,643 units from 1,641
units following the addition of the third phase St Michael’s Wynd site, which replaced the
unallocated regeneration block. 
2.29 Cunninghame Housing Association completed their 20 unit Garven Road, Stevenston
development in October 2024. The site provided 17 two bedroom general needs homes,
one three bedroom general needs house, a two bedroom amenity property and a two
bedroom bungalow suitable for wheelchair users. 
2.30 As reported to Cabinet on 7 November 2023, due to past successes in accelerating
projects and claiming additional funding year upon year, alongside slippage in some
projects, North Ayrshire was unable to claim the Resource Planning Assumption for the
2023/24 financial year. The Council claimed an estimated total of £10.234m against the

Page 10

Resource Planning Assumption of £15.648m for the year (this value will be confirmed
when the Scottish Government out-turn report is published later this year). This value is
£0.441m higher than the spend estimate reported to Cabinet in November 2023. 
2.31 As previously reported, the Council and its partners claimed an additional £19.165m
towards affordable housing in the area from slippage in other local authority areas in the
six years from April 2016 to March 2022. The slippage during 2022/23 and 2023/24
therefore results in a cumulative over-claim of £2.361m against the Resource Planning
Assumption for the period. Slippage was experienced at a number of Council
developments due to redesign works required as a result of regulatory changes and
assessment of zero direct emissions heating systems options. 
Housing demand 
2.32 Housing demand figures were obtained from the North Ayrshire Housing Register during
June 2024, there were 3,575 applicants with an assessed housing need. Proportionate
demand for social housing by locality is illustrated in Chart 1 below. The house size and
type priorities within the SHIP have also been informed by housing register demand. 
2.33 The Arran Housing Task Force was established to quantify the demand for affordable
housing on Arran and identify issues that may be limiting economic growth. A quantitative
study has been undertaken by North Star Consulting and Research to determine
affordable housing demand on the island. The Task Force has developed an action plan
to address any identified housing issues on the island. 
2.34 No demand issues have been identified in relation to accommodation for gypsy /
travellers.  Following consultation with current tenants at Redburn Grove, Irvine in April
2023, future improvement proposals for the site are being developed and costed, reflecting
feedback gathered in relation to their preferences for future housing. A business case is
being developed which will include all available funding streams and a full options
appraisal for the site, including the potential to transfer the site from the General Fund to
the Housing Revenue Account. 
Proposed housing delivery 
Arran, 163, 5%
Cumbrae (part of North
Coast), 33, 1%
Garnock Valley,
328, 9%
Irvine, 1366, 38%
Kilwinning, 494, 14%
North Coast, 339,
9%
Three Towns, 852,
24%
Chart 1: Proportionate demand for social housing by locality

Page 11

2.35 The Council and its registered social landlord partners aim to provide a total of 1,143 new
affordable homes across the six localities in the draft plan. The anticipated house types to
be delivered by locality are noted in Table 6 below. The 83 units noted as ‘TBA’ are the
buybacks being progressed by four developing organisations. 
Table 6: New supply housing (including buy backs & refurbs) by locality & type
Locality Arran Garnock
Valley Irvine Kilwinning North
Coast
Three
Towns TBA Sub
Total 
Total
All
Family
NAC 0 36 263 31 17 66 60 473
747 Family
RSL 32 0 22 48 0 149 23 274
Amenity
NAC 0 19 140 12 12 22 0 205
236 Amenity
RSL 0 0 2 5 0 24 0 31
Sheltered
NAC 0 0 0 0 0 0 0 0
0 Sheltered
RSL 0 0 0 0 0 0 0 0
W/chair
NAC 0 9 99 10 0 25 0 143
160 W/chair
RSL 0 0 2 6 0 9 0 17
Total All 32 64 528 112 29 295 83 1,143
Total
NAC 0 64 502 53 29 113 60 821
Total RSL 32 0 26 59 0 182 23 322 
2.36 The Council and its registered social landlord partners completed and planned
developments are noted by locality alongside housing demand in Table 7 below. 
Table 7: Housing demand and completed and planned development 
Arran Garnock
Valley Irvine Kilwinning North
coast
Three
Towns TBA Total
Demand
at June
2024
163 328 1366 494 372 852 0 3,575
Complete
at March
2024
90 73 592 283 351 389 0 1,778
Planned 32 64 528 112 29 295 83 1,143
Total
(complete
plus
planned)
122 137 1,120 395 380 684 83 2,921
*It should be noted that, in addition to the above RSL and NAC plans, Arran Development
Trust will deliver 18 new affordable homes in Lamlash, Arran. 
2.37 Chart 2 plots Strategic Housing Investment Plan completions against the net stock gain.
The 'net gain' column indicates the additional homes available per locality following
completion of the developments, minus the strategic demolitions set out in the plan. It also
illustrates proportionate demand from the housing register as at June 2024 and historic
new build completions from April 2013 to March 2024. Please note that proportionate

Page 12

demand is indicative to illustrate trends; the actual demand figures will be less as transfer
applicants who are included in these figures will leave an existing tenancy behind when
they are allocated a new home. 
Chart 2: Completions, net gain, proportionate demand and historic completions 
2.38 If any project becomes delayed or non-viable, the Council will work with registered social
landlord partners and the Scottish Government to review alternative opportunities to
ensure that new homes are delivered, and the available grant funding spent. 
2.39 In order to ensure that the Council can quickly absorb funding available from other local
authorities (which is generally available at short notice at the financial year end) and spend
its annual Resource Planning Assumption, Cabinet is asked to delegate authority to the
Executive Director (Communities and Housing), in consultation with the Cabinet Member
for Communities and Islands, to liaise with the Scottish Government and agree the
rescheduling of the projects noted within the main Strategic Housing Investment Plan, as
required. This is of particular importance where deliverability is delayed due to emerging
constraints and challenges that require to be addressed. Spending on projects within the
shadow programme or the additional of any new projects will require Cabinet approval. 
2.40 The Council will continue to progress sites within the SHIP shadow programme to a ‘shovel
ready’ state to support the absorption of any additional funding made available. 
2.41 In terms of ongoing governance, senior officers monitor the progress of the new build
programme monthly through the Strategic Housing Investment Plan project board. 
0
200
400
600
800
1000
1200
1400
Irvine Kilwinning 3 Towns North
Coast
Garnock
Valley
Arran TBA
SHIP Completions 2013 - March  2024
SHIP Completions April 2024 - March 2030
Net Gain 2013-2030
Proportionate Demand from NAHR

Page 13

Strategic Priorities 
2.42 The Strategic Housing Investment Plan is based on a series of guiding principles for
housing provision, taken from the Local Housing Strategy 2023 - 2028. The plan also
contributes to a wider range of Council and national priorities, including: 
• Children’s rights and wellbeing
• 20-minute neighbourhoods to allow people to meet their needs locally, where
feasible
• Regeneration, including town centre and estate based regeneration
• Green space provision for tenants
• Investment in island communities 
• Refugee resettlement programme
• Sustainability, affordable warmth and zero emissions
• Specialist accommodation delivery to support residents to live independently
• Bringing empty homes back into use 
SHIP impact on North Ayrshire school capacity 
2.43 Experience at other sites demonstrates that new affordable housing developments
generally comprise of families who already reside within the school catchment area.
Officers from Housing, Planning and Education continue to monitor developments to
ensure any impact upon school capacity can be addressed or mitigated. 
SHIP Investment 
2.44 The draft Strategic Housing Investment Plan (SHIP) 2025 - 2030 is based on future
projected Scottish Government grant funding provision of £132.538m for the Council and
its partner landlords from April 2024 to March 2030. 
2.45 The Council projects detailed within the main programme represent Council investment of
£173.644m, supported by £80.550m Scottish Government Grant. Following the review of
the SHIP, an estimated additional £9.171m is required beyond the funding allocated in the
latest HRA 30-year Business Plan, which is expected to be addressed by an estimated
additional £12.524m in grant funding for the Council projects within the main programme.
The £9.171m funding requirement comprises increased budget estimates due to delays
associated with grant funding reductions, and budget adjustments required to align with
revised project timelines. The funding variances are considered within the current review
of the HRA Business Plan, prior to it being presented to Council in February 2025 as part
of the 2025/26 HRA budget and rent setting. 
2.46 The Council projects within the SHIP shadow programme represent Council investment
of £41.289m, supported by £23.802m Scottish Government Grant. The grant funding rates
for the Council projects in the SHIP shadow programme are £4.708m higher than the
estimated benchmark rates inflated to their anticipated site start date, at an assumed 3.1%
per annum. 
2.47 As noted at 2.25 above, in accordance with Scottish Government guidance, the Council
will seek grant funding above benchmark levels to offset any funding shortfall, on a site-

Page 14

by-site basis, as required. 
3. Proposals 
3.1  It is proposed that Cabinet (i) approves the Strategic Housing Investment Plan 2025-
2030 at Appendix 1 for submission to Scottish Government; (ii) approves the projects
set out within the SHIP shadow programme at Appendix 1; (iii) gives delegated authority
to the Executive Director (Communities and Housing) and the Cabinet Member for
Communities and Islands to liaise directly with the Scottish Government in agreeing the
acceleration of projects in the main SHIP programme, as required; and (iv) notes that
acceleration of any projects from the SHIP shadow programme will require Cabinet
approval. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications arising from the projects included within the Strategic Housing
Investment Plan 2025-2030 have been assessed by each of the developing
organisations, ensuring that the programme is fully deliverable within the timescales set
out. The current HRA Business Plan includes a budget of £164.473m to deliver the
North Ayrshire Council development projects set out within the main SHIP programme,
inclusive of Scottish Government funding. It is estimated that an additional £9.171m is
required to support the Council’s developments set out within the main SHIP 2025-
2030, which is expected to be addressed by an estimated additional grant income of
£12.524m. The funding variances and the removal of the Council projects in the SHIP
shadow programme are considered within the current review of the HRA Business Plan
prior to it being presented to Council in February 2025 as part of the 2025-26 HRA
Budget and rent setting. The projects within the SHIP shadow programme are
anticipated to require estimated funding of £41.289m, inclusive of £23.802m
government grant. 
Human Resources 
4.2 Council projects within the Strategic Housing Investment Plan will be delivered by North
Ayrshire Council staffing and complemented by external expertise, where required. 
Legal 
4.3 The Town & Country Planning (General Permitted Development) (Scotland) Order
1992, Schedule 1, Part 12, Class 33, as amended, enables local authorities to
undertake works, within their district, for the erection of dwellings so long as the
development conforms with the Local Development Plan. The Council’s House Building
Protocol governs the design and consultation processes for such development to
ensure that appropriate levels of design scrutiny and consultation are maintained.  In
2019, it was agreed that all future Council housing developments progressed as
permitted development will be required to obtain a ‘Certificate of Lawfulness’ from the
Council’s Planning Service. This will certify that each site within the SHIP has been
considered against the full terms of the adopted Local Development Plan. Housing
development proposals by the Council which do not fall within the scope of permitted
development, including schemes which require an Environmental Impact Assessment
(EIA) will require planning permission. Proposals over 0.5 hectares in area will require

Page 15

to be screened for the purposes of EIA. 
Equality/Socio-economic 
4.4 The provision of new social housing will have a positive impact on those who require
specialist accommodation, older people, those who are homeless, or at risk of
homelessness, and those for whom purchasing a home is not an affordable option. The
benefits of new build housing in relation to health, wellbeing and educational attainment,
are well documented. New housing will also support our island communities and their
economies. A reduction in new build completions will have a negative impact on these
groups. 
Climate Change and Carbon 
4.5 New homes should have a low environmental impact, with the aim of reducing fuel use
and associated fuel costs. All projects within the SHIP will be delivered in accordance
with Building Standards regulations for energy efficiency. In addition, the majority of the
new projects incorporated into the plan will be delivered to Section 7, Silver Level, of
the 2019 Building Regulations in respect of Energy for Space Heating. Innovative
approaches to fuel efficient development will be considered on a site-by-site basis (e.g.
zero direct emissions heating systems, solar photovoltaic panels, smart technologies
etc). New Council homes contribute significantly to the Council’s Sustainability agenda.
New housing is more energy efficient, better ventilated, and has higher levels of thermal
comfort, which supports improved health and well-being. 
Key Priorities 
4.6 The provision of new affordable housing supports the Council Plan strategic priorities:
‘Wellbeing’; ‘Climate Change’; ‘A Sustainable Council’: and ‘Communities and Local
Democracy’. It supports the ambitions of the Council’s Regeneration Delivery Plan to
drive forward development on strategic regeneration sites, including town centres. 
There is also evidence that children and young people can benefit from improved
cognitive development and a reduction in behavioural issues through living in a more
attractive, warmer, and better ventilated environment and the provision of new
affordable housing also supports the Council Plan priority that children and young
people experience the best start in life. New housing will also support our island
communities and their economies. A reduction in new build completions will have a
negative impact on these groups. 
Community Wealth Building 
4.7 The delivery of the Strategic Housing Investment Plan, alongside investment in land
and asset maintenance, plays a key role in community wealth building. Effective use of
community benefit clauses in development contracts, and partnership work with
colleagues in Economic Development to support local construction and supply chain
companies to bid for this work, can secure many of these jobs for local people and
support the Council’s Community Wealth Building Strategy. For example, the contractor
for the Ayrshire Central, Irvine development will engage with local Primary schools,
secondary schools, colleges, the Council, and CEIS. They will assist with STEM events,
career events, mock interviews, CV advice, and arrange work experience. The
contractor will also engage with local community groups and assist them where
possible.

Page 16

5. Consultation 
5.1 The Council has taken a collaborative approach to the preparation of the SHIP, and the
following stakeholders have been involved in the process: 
• ANCHO in partnership with Cairn
• Cunninghame Housing Association
• Riverside Scotland
• Link Group Ltd
• Trust Housing Association
• The Scottish Government
• North Ayrshire Council Officers (Economic Growth, Education, Finance, Housing,
Planning, Property Management and Investment, Active Travel & Transport, Roads,
and the Health and Social Care Partnership). 
5.2 Regular meetings are held with developing organisations, the Council and the Scottish
Government as part of the SHIP governance process. The meetings will continue to be
convened on a quarterly basis each year, to ensure that partners’ requirements are
identified, and the development programme delivered. 
DAVID W. HAMMOND
Executive Director (Communities and Housing) 
For further information please contact Fiona Ellis, Senior Manager, Housing Strategy and
Development, on 01294 324031. 
Background Papers
Local Housing Strategy 2023 – 2028

Page 17

Page 1
North Ayrshire Council   
Strategic Housing Investment Plan       
2025 to 2030

Page 18

Page 2
Contents
Contents.................................................................................................................................................................................................................... 2
Introduction ............................................................................................................................................................................................................ 4
Strategic Policy Context ..................................................................................................................................................................................... 5
Equalities ........................................................................................................................................................................................................... 6
Childrens rights and wellbeing ........................................................................................................................................................................... 6
Environment ....................................................................................................................................................................................................... 7
Collaboration ...................................................................................................................................................................................................... 7
Investment Priorities .............................................................................................................................................................................................. 8
More homes at the heart of great places ........................................................................................................................................................... 8
Affordability and choice .................................................................................................................................................................................... 11
Affordable warmth and zero emissions ............................................................................................................................................................ 20
Improving the quality of our homes .................................................................................................................................................................. 21
Prioritising projects .......................................................................................................................................................................................... 25
SHIP funding streams .......................................................................................................................................................................................... 25
Affordable housing supply programmes ........................................................................................................................................................... 25
Reserves and balances ................................................................................................................................................................................... 26
Borrowing ......................................................................................................................................................................................................... 26

Page 19

Page 3
Affordable housing policy developer contribution ............................................................................................................................................. 26
Other funding sources ...................................................................................................................................................................................... 27
Council tax on second and empty homes ........................................................................................................................................................ 27
Planning and other regulatory matters ................................................................................................................................................................ 28
Delivery risks ....................................................................................................................................................................................................... 29
Amendments or additions to the plan .................................................................................................................................................................. 29
Development projects .......................................................................................................................................................................................... 30
Irvine & Kilwinning ........................................................................................................................................................................................... 30
Three Towns .................................................................................................................................................................................................... 31
North Coast ...................................................................................................................................................................................................... 32
Garnock Valley ................................................................................................................................................................................................. 32
Arran ................................................................................................................................................................................................................ 33
Progress update .................................................................................................................................................................................................. 34

Page 20

Page 4
Introduction
The Strategic Housing Investment Plan 2025-2030 sets out the priorities for affordable housing investment in North Ayrshire over the next five
years and outlines how the Council and its partners will deliver these priorities. The focus of the plan is to support the Scottish Government’s
Affordable Housing Supply Programme (AHSP) to deliver affordable housing in North Ayrshire. 
The provision of new build housing has many benefits, including, helping to regenerate the area, providing sustainable housing solutions which
help to address fuel poverty and support educational attainment, and supporting the ageing population and people with accessible housing and
particular needs to live more independently.
The Council and its registered social landlord partners have experienced significant affordability challenges and pressures. The rate of inflation,
cost of borrowing, and rising material costs have significantly impacted upon construction costs and project viability. The recent reductions to the
Affordable Housing Supply Programme has further compounded these issues and meant that some schemes have had to be removed from the
programme, with other sites moved to a shadow programme to manage priorities within the currently
anticipated grant funding envelope.
Increasing standards and emerging legislation also impact upon project costs and timelines as options
appraisals and financial modelling are required prior to implementation. For example, the cost to
tenants and future maintenance and replacement costs of zero direct emissions systems had to be
reviewed with solutions considered on a site-by-site basis to ensure that they were affordable to install
and for tenants to utilise. The Council’s standard house types had to be revised to accommodate new
equipment to support the heating systems. Further implications are likely to be experienced as
Housing for Varying Needs and Building Standards are revised to enhance accessibility and
adaptability of housing stock. These changes are likely to impact upon the Council’s standard house
types and construction costs.
Development is not the only policy intervention being explored by the Council. It would be very difficult
for the Council and its partners to meet housing need only through investment in new homes. Work to
maintain and improve the condition of existing social housing stock, provide aids and adaptations and
improve the private rented sector are all intended to address the housing needs of the local population.
The Council and developing registered social landlord partners with stock in North Ayrshire all have
buyback programmes within the plan to increase affordable housing in the area and contribute to wider
regeneration and estate management.

Page 21

Page 5
Strategic Policy Context
Housing to 2040, Scotland’s first 20-year housing strategy, was announced in March 2021. The strategy committed to providing around £16bn of
investment to support the delivery of 100,000 new homes by 2032, with at least 70% for social rent. The Scottish Government’s Affordable Housing
Supply Programme comprises a range of funding mechanisms to enable affordable housing providers to deliver homes in communities across
Scotland to support local authorities’ Local Housing Strategies. The Scottish Government allocated Resource Planning Assumptions for the full
five-year period of the current parliament to deliver the ambitious affordable homes target set out in Housing to 2040. 
In May 2024, the Council was advised of reductions to the previously committed Resource Planning Assumptions which has had implications
particularly for larger projects which require an up-front funding commitment. The impact of the funding reduction has been considered through the
preparation of the Strategic Housing Investment Plan 2025-2030.
The Council’s Cabinet approved the latest Local Housing Strategy 2023-28 on 13 June 2023. The Local Housing Strategy sets out the Council’s
ambition:
‘We want all our people to live in the right homes, in great places, with access to any support services they need.”
The strategy mirrors the format of Housing to 2040 and sets out four overarching outcomes which align to the four key strategies in Housing to
2040 as detailed below. 
The Strategic Housing Investment Plan is an extension of, and aligns to, the Local Housing Strategy. In preparing the plan, the Council has referred
to the outcomes identified in the Local Housing Strategy, which support the objectives of the Council Plan. 
The Strategic Housing Investment Plan also aligns with the Council’s Community Wealth Building Strategy, which sets out how the Council, in
conjunction with communities and businesses, will build a strong local economy and address wealth inequality by supporting fair work, encouraging
local spend, and using the land and property we own.

Page 22

Page 6
Equalities
In line with the Council Plan,
fairness and equity is core to the
Strategic Housing Investment
Plan. It strives for a North Ayrshire
where everyone has the same life
chances to grow, prosper and
have fulfilling and healthy lives.
The Council Plan priorities are
detailed in figure 1. An Equality
Impact Assessment has been
undertaken for the Strategic
Housing Investment Plan. It found
that there are no negative or
discriminatory effects on any
equality groups.
The provision of new social
housing will have a positive impact
on those who require specialist
accommodation, older people,
those who are homeless, or at risk of homelessness, and those for whom purchasing a home is not an affordable option. The benefits of new build
housing in relation to health, wellbeing and educational attainment, are well documented. Public Health Scotland’s Healthy housing for Scotland
report recognises that adequate housing which is safe, accessible, available, appropriate and high quality is key to us achieving the highest
attainable standard of health.
Childrens rights and wellbeing 
The North Ayrshire Child Poverty Action Plan 2023 notes that North Ayrshire has the second highest level of child poverty of any area in Scotland.
Access to good quality and affordable housing is a key asset in addressing child poverty, and poverty overall. Research undertaken by Shelter
suggests children can benefit from improved cognitive development and a reduction in behavioural issues through living in a more attractive,
warmer, and better ventilated environment. All new build Council family homes have study space and private gardens.

Page 23

Page 7
Environment
A Strategic Environmental Assessment pre-screening
questionnaire undertaken confirmed that there would be no
likely significant adverse environmental effects from the
activities set out within the Local Housing Strategy (which are
not already subject to Strategic Environmental Assessment
elsewhere), and for this reason a full strategic environmental
assessment was not required. The likely environmental
impact of development proposals (both positive and adverse)
are scoped within the Strategic Environmental Assessment
for the North Ayrshire Local Development Plan.
Collaboration
As the strategic housing authority, the Council is committed
to supporting partners to deliver affordable housing
development within North Ayrshire. The Council adopts a
collaborative approach in the preparation of the Strategic
Housing Investment Plan. The key stakeholders listed below
have influenced the final programme.
Local registered social landlord partners, including ANCHO, Cairn, Cunninghame Housing Association, Link Group Ltd, Riverside
Scotland and Trust Housing Association
North Ayrshire Council services, including Economic Growth, Education, Finance, Housing, Planning, Property Management and
Investment, Active Travel and Transport, Roads, and the Health and Social Care Partnership
The Scottish Government
The Council and its partners engage with communities when developing new build sites in the Strategic Housing Investment Plan. For Council
projects, local residents are invited to review and comment upon the draft plans for the site. Thereafter the final plans are presented to the
community and local residents are also invited to ‘Meet the Builder’ when a contractor has been appointed. Following the completion of each new
site, design teams assess each project’s success in delivering places people can be proud of, as part of the ‘lessons learned’ review.

Page 24

Page 8
Developing the Strategic Housing Investment Plan
The priorities set out within the Strategic Housing Investment Plan were developed with partners and the local community through the preparation
of the Local Housing Strategy. 
Due to the current affordability challenges, the Council did not invite new site nominations for the plan from its registered social landlord partners.
Instead, the Council met with each developing RSL to discuss the progress towards the current programme and future development plans. All
existing developments were considered on their individual merits, with reference to the development priorities set out within the Local Housing
Strategy, deliverability, and any known constraints. Thereafter, the Council discussed the revised plan with partners. The Council will continue to
monitor the development programme and new opportunities at quarterly meetings with developing landlords and the Scottish Government.
Council Officers monitor the impact of the new build programme on education facilities and other services through the monthly Strategic Housing
Investment Plan project board. If any project becomes delayed or non-viable, the Council will work with registered social landlord partners and the
Scottish Government to ensure that new homes are delivered by accelerating other projects within the plan.
Continual improvement
The Council regularly meets the Scottish Government and partner landlords to review the progress of the Strategic Housing Investment Plan and
share good practice. The Council holds ‘lessons learned’ meetings and undertakes tenant satisfaction surveys for each site.
Investment Priorities
The Local Housing Strategy notes that the Strategic Housing Investment Plan will be reviewed annually to establish affordable housing investment
priorities for the Council and its partners which seek to address the key priorities established within the Local Housing Strategy, set out below.
More homes at the heart of great places
The places we live have a significant impact on wellbeing. High quality places are safe, provide access to services and can help to reduce isolation
and enhance communities. Place making principles form the foundation of project development, informing site selection (where appropriate) and
the design process. 
North Ayrshire has a diverse housing market comprising rural, urban and island communities. The Council has established six localities:

Page 25

Page 9
Community Wealth Building & Fair Work First
The Council’s Community Wealth Building Strategy introduced a new model to develop resilient, inclusive local economies, with more local
employment and a larger and more diverse business base, ensuring that wealth is locally owned and benefits local people. Through the Strategic
Housing Investment Plan, contractors are expected to participate in the Council (or partners’) Community Benefits scheme, providing
apprenticeships to young people, skilling up the local workforce and supporting economic growth. Homes for Scotland suggests there are 4.1 jobs
created for every new home constructed. Effective use of community benefit clauses in development contracts, and partnership work with
colleagues in Economic Development to support local construction and supply chain companies to bid for this work, can secure many of these jobs
for local people.
The Council’s housebuilding programme can support the Council’s ambitions to encourage more young people into training and employment. The
North Ayrshire Local Employability Partnership Delivery Plan 2022 – 2026 sets out the intentions to help people of all ages to gain skills for
employment. It will prepare people for employment, training, education and/ or volunteering, with the aim of increasing qualification levels and job
prospects as well as reducing unemployment. Developing the Young Workforce have launched an online Skills Academy to support school leavers
and job seekers.
The Council’s Fair Work First Statement sets out the commitment to ensuring that fair
working practices are in place to support ‘Fair Work First’.
20-minute neighbourhoods
The provision of housing within 20-minute neighbourhoods allows people to meet their
needs locally and encourages active transport. The goal is to support a better quality of life
in places, whilst making towns and villages more resilient. The Strategic Housing
Investment Plan will prioritise new social housing developments which support the
principles of 20-minute neighbourhoods, where feasible.
Regeneration and town centres
Public sector investment can have a transformational impact for communities, and there
are cumulative benefits through considering how this can be coordinated with developing
partners and the private sector. The Council explores site and area specific opportunities
with partners to secure maximum regeneration benefits. This supports the ambitions of the
Council’s Regeneration Delivery Plan to drive forward place-based development on
strategic regeneration sites, including town centres.

Page 26

Page 10
Town centre regeneration is a primary focus of the Strategic Housing Investment Plan, with several projects completed to date within, or near, town
centres. The plan supports major housing led regeneration in North Ayrshire, an example being provision for the replacement of the 275 homes in
the Fullarton tower blocks which have been demolished in Irvine. Regeneration often results in higher development costs as sites require demolition,
refurbishment or have significant constraints/ abnormal costs.
The Strategic Housing Investment Plan also includes the provision of funding for 242 units to assist the delivery of Housing’s Estate Based
Regeneration Programme. This investment aims to provide new homes to replace any stock which requires to be demolished or reconfigured as
part of the Estate Based Regeneration Programme.
Island communities
The Council is committed to supporting island communities. General needs houses, amenity bungalows and homes for wheelchair users were
provided on the Isle of Cumbrae during summer 2021 (18 homes) and at Brathwic Terrace on the Isle of Arran during summer 2022 (34 homes). A
‘Local Lettings Initiative’ was introduced for Arran prior to the allocation of the new Council homes. 
The Local Lettings Initiative gives additional priority to island residents and key workers. Arran Development Trust has secured funding from the
Rural and Island Housing Fund to deliver 18 new affordable homes in Lamlash and Trust Housing Association is currently developing proposals
for a further 26 new homes in Brodick.  
The Council has established the Arran Housing Task Force to quantify demand for affordable housing on Arran and identify issues that may be
limiting economic growth. A quantitative study has been undertaken to determine affordable housing demand on the island, recognising the
assessed housing demand information from the North Ayrshire Housing Register and community feedback. The study is awaiting formal sign off
by the Taskforce and will be published thereafter. An action plan has been developed and three subgroups have been formed (funding, supply and
research) to address the report findings. The task force membership includes the Scottish Government, Highlands and Islands Enterprise, local
community groups and Arran registered social landlords.

Page 27

Page 11
A post has been funded for the Council’s Housing Strategy Team from the income from the reduction in discount for empty and second homes
Council Tax in North Ayrshire from April 2024 to support the work of the Arran Housing Task Force and the delivery of the group action plan. 
The Local Housing Strategy recognises that it is more expensive to build new homes on islands, compared to the mainland. Higher living, transport,
infrastructure, and fuel costs alongside limited on-island construction companies are identified as contributing factors to this issue. These issues
are being explored as part of the Community Wealth Building ambitions and Local Island Plans.
Green space
Research shows that where people have access to good quality outdoor green space, there is a corresponding positive and lasting impact on
public health. The Strategic Housing Investment Plan will prioritise new social housing developments which include the provision of outdoor green
space for residents.
Affordability and choice
Housing demand
The Local Housing Strategy has set a target of
1,625 new social housing units and a private
rented sector target of 1,300 new units. There
were 6,349 applicants on the North Ayrshire
Housing Register on 6 June 2024, of these,
3,575 applicants had an assessed housing need.
When transfer applicants are deducted 3,022
applicants remain (transfer applicants leave an
existing social tenancy behind for reallocation
when they are rehoused). Figure 1 details
housing register applicant needs. Please note
that the numbers are not mutually exclusive, for
example, applicants can request both amenity
and sheltered homes. 
3,575 applicants
with an assesed
housing need
215 requests for
wheelchair
accessible
homes 120 require
larger homes (6
people or more)
1,084 requests
for amenity
housing
412 requests
for sheltered
housing
346 homeless
applicants
64 require OT
assessed adapted
homes
Figure 1: Applicant Needs (Source: Housing Register June 2024)

Page 28

Page 12
Location
There is no limit to the number of letting areas applicants can select when making a housing application and demand has therefore been assessed
proportionately in Figure 2 to reduce double counting. It is important to note that individual housing allocations can impact upon demand within
areas. For example, if an applicant housed in the Three Towns also had Arran as an area of preference this would reduce demand for housing in
Arran.
Three Towns, Irvine and Kilwinning are the most pressured localities. Further analysis is required to determine housing pressures within the Arran
and Cumbrae localities as the proportionate analysis is not effective in determining pressure within smaller localities. 
This work is ongoing for Arran through
the Arran Housing Task Force,
previously referenced in the ‘Island
communities’ section of this document.
The demand for further new build
development on Cumbrae will be
considered annually as part of the
review of the Strategic Housing
Investment Plan.
The total number of homes which will be
developed over the lifetime of the
Strategic Housing Investment Plan have
been plotted by locality in figure 3.
These new supply figures illustrate the
aspiration to plan for a growing
population, and to seek continued
investment in housing stock to improve
overall stock condition. They have been
plotted alongside the net gain for the
same period, proportionate demand
from the housing register as at June
2024 and historic new build completions
from April 2013 to March 2024.

Page 29

Page 13
Figure 3: Completions, net gain, proportionate demand, and historic completions 
The 'net gain' column indicates the additional homes available per locality following completion of the developments, minus the strategic demolitions
set out in the Strategic Housing Investment Plan.
Size
Applicant house size requirements are determined by the strategic bedroom need which is the minimum number of bedrooms required based on
household composition. The proportion of homes by bedroom size is noted by locality in Table 1 based on proportionate demand.

Page 30

Page 14
Table 1: Proportionate housing demand by strategic bedroom need and locality (Source: North Ayrshire Housing Register, June 2024)
Analysis of the North Ayrshire Housing Register identifies demand trends for properties. House size has been identified by considering the minimum
accommodation size suitable for the household; this is referred to as the 'strategic bedroom need’.  
The strategic bedroom need is used for planning purposes only. Generally, one-bedroom homes are found to be of lower demand. Two-bedroom
homes are a more popular option for smaller households and are more flexible in meeting households’ future needs. An additional bedroom can
also provide study space, or space for home working. 
An indicative size mix (table 2) for developments across North Ayrshire has been prepared by uplifting the two-bedroom provision and reducing
the one-bedroom, thus meeting tenant aspirations and providing flexibility in terms of property sizes as households change composition over time.
Table 2: Altered demand by bedroom size (reflecting aspiration) and locality
This mix is intended as a guide only; each project will be considered on a site-by-site basis by the developing organisation, before being approved
by the Council.
The Council currently has plans to build four, five and six-bedroom homes for larger families within its development programme. The need for
further housing for larger families will be considered on a site-by-site basis as the housing mix is agreed for emerging projects.
Number of
Beds Arran Garnock
Valley Irvine Kilwinning North Coast Three Towns North Ayrshire
1 65% 57% 58% 56% 65% 60% 59%
2 13% 14% 15% 14% 12% 15% 14%
3 14% 18% 14% 16% 14% 13% 15%
4+ 8% 11% 13% 14% 9% 12% 12%
Number of
Beds Arran Garnock
Valley Irvine Kilwinning North Coast Three Towns North Ayrshire
1 13% 14% 15% 14% 12% 15% 14%
2 65% 57% 58% 56% 65% 60% 59%
3 14% 18% 14% 16% 14% 13% 15%
4+ 8% 11% 13% 14% 9% 12% 12%

Page 31

Page 15
Homelessness
North Ayrshire Council’s Rapid Rehousing Transition Plan was approved in 2019 and sets out how the Council and its partners will work together
to implement a housing led approach to meeting the needs of homeless households. Where it is not possible to prevent homelessness, the priority
is to secure a settled housing option for every homeless household as quickly as possible. The plan aligns with the housing supply priorities set
out within the Strategic Housing Investment Plan. The Rapid Rehousing Transition Plan priorities are to: 
The provision of new affordable housing which meets housing applicants needs and aspirations through the Strategic Housing Investment Plan
will continue to support the delivery of the Rapid Rehousing Transition Plan. The Council and its partners have also established the North Ayrshire
Homelessness Taskforce to review homelessness risk factors and inform homelessness prevention work. The groups findings will inform the new
North Ayrshire Homelessness Strategy which is being developed to align to the homelessness prevention duties set out within the proposed
Housing (Scotland) Bill 2024.
Gypsy/ travellers
The Council has not identified any additional demand issues in relation to accommodation for gypsy/ travellers. The Council has reviewed the
condition of the permanent site at Redburn Grove, Irvine in consultation with residents to identify any future maintenance and investment works.
An options appraisal is underway to develop plans and a business case for site improvements. The Council will make an application to the Scottish
Government to seek funding for any necessary renovation or improvements when this is complete.
Housing for key workers
The Council will work with its partners to make bids to the Scottish Governments five year £25m Rural Key Workers Housing Fund for appropriate
projects to provide affordable housing for key workers in rural areas. Trust Housing Association has already made a successful bid to the fund, to
acquire homes for key workers on Arran. The Arran Housing Task Force will continue to work collaboratively to identify and discuss potential
opportunities to utilise the fund.

Page 32

Page 16
Ensuring best value
As part of the tendering process, the Council prepares minimum specifications for materials utilised in the new build developments to ensure that
they align to current lifecycle replacement and maintenance programmes. A suite of standard house types has also been developed to further
assist with maintenance programmes and reduce project design costs. 
The Council is committed to making efficiency savings through strategic procurement arrangements in the delivery of the new build affordable
housing programme, to ensure value for money for tenants. Several Strategic Housing Investment Plan projects have been procured through Hub
South-West, as part of a procurement strategy to achieve cost and time savings through economies of scale.  
The Council has also, with ten local authority partners, worked with Scotland Excel to develop a New Build Residential Construction Framework
Agreement available for use by all Scottish local authorities and registered social landlords. 
The Council has been utilising off site construction following a successful pilot scheme at Ardrossan Road, Seamill. During 2023, six new amenity
bungalows were developed in Stevenston town centre. A further 14 homes are expected to be delivered by early 2025 at Laburnum Avenue in
Beith and Newhouse Drive in Kilbirnie. The construction method results in less waste and has sustainability benefits. It also reduced the construction
time on site, and in turn, reduced disruption for local residents and businesses from site traffic and works.

Page 33

Page 17
Figure 4: Afton Court development of six amenity bungalows utilising off site construction in Stevenston town centre 
Rent levels and affordability 
The Scottish Housing Regulator expects social landlords to be able to demonstrate affordability and engage meaningfully with tenants on rent
increases. Increasing costs and inflation mean that retaining affordable rent levels is a significant challenge for the Council and its partners.
The Council is committed to working with its partners to find sustainable routes out of poverty for children and their families. The Council Plan 2023-
28, has addressing inequalities at its core, and aims for “a North Ayrshire that is fair for all”. Budget decisions directly align to Council Plan
priorities. The most recent Year End Progress Reports for 2023-24 demonstrate the impact of the action taken across services and with partners
to address inequalities and inequity in North Ayrshire.  
In August 2024, the Council’s Cabinet approved the publication of the Child Poverty Action Plan Report 2023-24, which shows progress against
the Child Poverty Action Plan 2023-26, aligned to Scotland’s Child Poverty Plan “Bright Start, Better Futures 2022-26”. The progress report
highlights action that has been taken throughout 2023 and 2024, based on the three key drivers of child poverty - income from employment, income
from social security and the cost of living. This action has been informed by consultation with residents and their community groups, ensuring real
lived experience informs the approach. The Council is continuing to align delivery to target the six priority families as outlined in the national plan.

Page 34

Page 18
Empty homes and second home buy backs
Empty homes are detrimental to the local environment, often the target of antisocial behaviour, and are more likely to fall into disrepair. The Council
and its partners recognise that bringing former social housing stock into ownership can assist with housing management and maintenance issues
and increase housing available through the North Ayrshire Housing Register. 
All developing registered social landlord
partners with stock in North Ayrshire now
have provision for buyback programmes
within the Strategic Housing Investment
Plan. 
The Council has acquired four empty
homes over the past four financial years
which have been brought back into use as
Council stock. Table 3 details the number of
empty homes brought back into use in
North Ayrshire from April 2020 until March
2024, all of these homes were subject to
the Council Tax levy (this is where the
Council currently focuses empty homes resources).  A post has been funded for the Council’s Private Sector Advice Team from the reduction in
discount for empty and second homes Council Tax in North Ayrshire since April 2022 to focus on bringing empty homes back into use. 
Table 3: Empty homes brought into use per annum 2020/21 to 2023/24 
Duration empty Under 6 months 6 to 12 months 1 to 2 years 2 to 5 years 5 to 10 years 10+ years Total
2020/21 35 61 15 10 0 0 121
2021/22 18 71 136 109 0 0 334
2022/23 23 3 31 64 2 0 123
2023/24 259 66 5 39 9 0 378

Page 35

Page 19
Private sector support
The Council’s Private Sector Advice Team provide advice on private sector housing issues in North Ayrshire. The service is part of the revised
Scheme of Assistance 2019 which introduced a range of new measures to improve private sector housing condition, including: 
A ‘pre-tenancy support service’ for landlords to aid the prevention of future property condition issues. 
A ‘missing shares scheme’ to remove barriers where a property owner refuses to meet their common repair obligations. 
Use of the Council’s powers for Compulsory Purchase Orders (CPOs) where appropriate to acquire empty properties in poor
condition, bringing them back into mainstream housing stock. 
An Empty Homes Loan Fund to assist property owners to bring properties back into effective use. 
Second homes
The Council’s Local Housing Strategy notes that there are 1,500 second homes in the area, almost all of which are located on the islands. On
Arran, 25% of privately owned houses are second homes; on Cumbrae this rises to 43%. This reduces the number of homes available for local
people, and in turn pushes up house prices and private rent charges. 
The Council is currently undertaking a community consultation on proposals to implement an additional Council Tax levy on second homes from 1
April 2025.
Alternative models of affordable housing delivery
The Council and our partner registered social landlords will continue to review alternative housing models which could be utilised to increase
affordable housing supply during the lifetime of the Strategic Housing Investment Plan.

Page 36

Page 20
Affordable warmth and zero emissions
Sustainability
The Council’s Sustainable North Ayrshire Strategy 2024-2027 includes
actions to achieve net-zero carbon emissions by 2030. New housing
has a key role to play in carbon reduction, climate change mitigation,
and alleviation of fuel poverty.
The Council and its partners will continue to consider innovative and
sustainable approaches to heat and power, such as low carbon heat,
solar photovoltaic panels and smart technologies. The Council will
ensure that all new build housing utilises Net Zero Direct Emissions
heating systems in accordance with building standards. In advance of
the new regulations the Council installed three biomass district heating
schemes in Stevenston, Dalry and Largs. A bespoke energy strategy
has been created for each emerging new housing development to
ensure that the heating options for the sites are both energy efficient
and affordable for tenants. 
The Council recognises that a ‘fabric first’ approach to sustainability can provide
benefits to tenants, in terms of reducing heating costs. It also benefits the
environment as all homes are designed to minimise heat loss.
The Council completed two ‘sustainable demonstrator homes’ within Dickson
Drive, Irvine in 2020 to highlight best practice in design and innovation, ensuring
benefits from sustainable technologies are maximised. 
Also, in recognition of the safety benefits of sprinkler systems, the Council
installed sprinklers in all new build housing proposals which reached technical
design stage after October 2019, prior to the introduction of Building Standards
legislation in March 2021.

Page 37

Page 21
Secure by design
Successful design can contribute to community stability and promote feelings of safety and inclusion. All Council developments are planned utilising
‘secure by design’ principles.
Active Travel
Access to safe walking networks, cycle pathways and public transport connects communities
to local amenities and services. In turn, these can result in direct health benefits, through
increased physical activity and reduced air pollution. They can also lead to indirect health
benefits by providing improved access to opportunities for employment, leisure, and
healthcare services.
The sustainable travel hierarchy, illustrated in figure 5 opposite, sets out the transport
priorities for sustainable transport in development.
Improving the quality of our homes
Over 40% of the stock developed by the Council and its partners since April 2013 has
addressed particular housing needs, demonstrating the commitment to supporting tenants to
live independently. The cost of particular needs housing is often more expensive than general
needs housing, for example, housing for wheelchair users has a larger ground floor footprint,
increasing construction costs and reducing economies of scale as site densities are reduced.
Similarly, supported accommodation and sheltered housing require communal space which also increases costs.
Wheelchair accessible accommodation 
All amenity and sheltered housing in North Ayrshire should be built to an ambulant housing standard as a minimum. To ensure need is met now
and in the future, the new Local Housing Strategy increased the target to ensure at least 10% of all tenure new build stock is suitable for wheelchair
users (increased from 7% in the previous strategy). In recognition of the benefits of providing adaptable housing, and to address demand from the
North Ayrshire Housing Register, the Council and registered social landlord partners developed 189 (11% of new supply) new build homes suitable
for wheelchair users since April 2013. The Strategic Housing Investment Plan 2025 – 2030 estimates the delivery of a further 160 (14% of new
supply) homes suitable for wheelchair users. 
In addition, a set of standard house types for Council developments were designed in partnership with Housing Services Occupational Therapists
which are of an accessible design to make best use of assets and adapt to tenants’ changing mobility needs.

Page 38

Page 22
In preparing North Ayrshire’s third Local Development Plan, the
Council will further consider the housing needs of older people and
disabled people in the area and the establishment of an
appropriate target for the delivery of accessible or adaptable
homes, including wheelchair housing and intergenerational
homes within the private sector, to support independent living
particularly although not exclusively among older or disabled
people. 
The Government has committed to a new ‘Scottish Accessible
Homes Standard’ which will be part of national building standards
by 2025/26, and in turn increase the provision of accessible
homes in the private sector. The accessible standard will see
accessibility designed and built into all new homes, increasing the
housing choices for people with disabilities and reducing the need
for expensive retrofitting as people age or their needs change.
Occasionally it may be necessary to build larger specialist housing to meet the specific needs of individual households. Where this is provided by
a registered social landlord, the Council will approve the proposals before a planning application is submitted.
Supported accommodation
Officers within the Place Directorate and the Health and Social Care Partnership developed a new supported accommodation housing model which
has been implemented at sites across North Ayrshire. 
The focus is on maximising independence for adults within a homely setting, who require a higher level of support, and who are living with learning
disabilities, or mental illnesses (all ages), or who are under 65 years and have physical disabilities. The new supported accommodation model can: 
The Strategic Housing Investment Plan has supported the Health and Social Care Partnership to meet specialist housing need through four
dedicated supported accommodation projects which have provided 62 (4% of new supply) new homes across North Ayrshire.

Page 39

Page 23 
Housing for older people
The Local Housing Strategy recognises that the proportion of
older people in North Ayrshire is higher than that of Scotland as
a whole (23% compared to 19%). It further predicts that by
2043 the over 75 age group will account for 28% of local
people.
Recognising the need to develop housing solutions appropriate
for the older population, the Council and its partners have
delivered 334 (19% of new supply) amenity homes and 251
(14% of new supply) units of sheltered housing since April
2013. The Council ensures that its sheltered housing is
developed utilising dementia friendly design principles. The
Strategic Housing Investment Plan 2025 – 2030 estimates the
delivery of a further 236 (21% of new supply) amenity homes.
Alongside the new build programme, the Council will continue
to deliver its sheltered housing re-provisioning programme,
which includes £38m investment in the refurbishment of
sheltered housing units out with the Strategic Housing
Investment Plan.

Page 40

Page 24
Extra care housing
Housing Services and the Health and Social Care Partnership worked together over the last few years to develop a model for Extra Care Sheltered
Housing. The vision was to create safe, affordable homes for tenants who require additional support, with extra services to promote independent
living, such as assistance with meals or welfare checks, to be available to tenants for an additional fee. 
Following development of the outline model, demand analysis was undertaken by the Health and Social Care Partnership in 2021 alongside
engagement with other areas in Scotland where similar housing models operate. At that time, it was determined as an outcome of the analysis that
there was not sufficient demand to integrate the extra care model into a new sheltered housing complex. The Council has, however, incorporated
flexibility into some new build sheltered complexes to allow this model to be reconsidered in the future should the Health and Social Care
Partnership choose to develop this further.
Assistive technology
The Flatt Road development in Largs provides an exemplar for assistive technology to promote independent living. Features that can be installed
within the sheltered housing complex and supported accommodation, where required, to support tenants’ individual needs include:

Page 41

Page 25 
Prioritising projects 
All projects which meet the criteria outlined above will be ‘high priority’. In the case of developments by registered social landlords the housing mix
and type for each individual development site and the proposed rent levels for the new homes should be formally agreed with the Council prior to
the submission of a planning application.
Due to the funding reductions, existing projects have had to be prioritised based upon deliverability, strategic alignment, value for money, and their
impact upon community regeneration in order to align with the grant funding envelope currently available. Projects which cannot be supported in
the main programme, due to the current anticipated funding envelope, have been moved to a shadow programme which will be accelerated, should
slippage occur in the main programme, and/or if additional funding becomes available.
SHIP funding streams
Affordable housing supply programmes
The main SHIP programme is based upon assumed grant funding of £71.573m for North Ayrshire from April 2024 to March 2030 (see table 4).
Funding for Council projects in the main programme not yet at tender stage has been assumed at benchmark plus annual Scottish Social Housing
Tender Price Index inflation which has been assumed at 3.1% per annum. The Council projects in the SHIP shadow programme have grant funding

Page 42

Page 26
set at levels which will allow the schemes to be wholly funded with borrowing costs offset by rental income. The Council will seek grant funding
above these levels on a site-by-site basis, as required. The registered social landlord funding rates have been included as requested by each
developing organisation and will be subject to Scottish Government authorisation.     
The sites within the SHIP shadow programme will assist the Council to meet the requirement for ‘slippage’ in accordance with Scottish Government
guidance. The slippage requirement is to ensure that the allocation is fully spent even if delays or constraints emerge on other development sites,
and to provide the opportunity for North Ayrshire to absorb slippage from other local authority areas.
Table 4: North Ayrshire Resource Planning Assumption (RPA) per annum 2024/25 and assumptions for 2025/26 to 2029/30 (£m) 
Reserves and balances
All developing organisations will utilise available reserves and balances to support the development programme.
Borrowing
A large portion of development funding is secured from borrowing. Private finance supports registered social landlords development programme,
and prudential borrowing supports local authority new build projects.
Affordable housing policy developer contribution 
The Council’s previous Affordable Housing Policy (RES4), which required contributions to affordable housing provision from specified private
developments within North Ayrshire, was removed within the new Local Development Plan (LDP2) adopted on 28 November 2019.  
Developer contributions, in the form of commuted sums, received through the application of the Affordable Housing Policy under the previous Local
Development Plan, will be utilised to fund projects being delivered through the Strategic Housing Investment Plan, when required.
The Council had an on-site contribution through the affordable housing policy at the 31-unit Ardrossan Road, Seamill development. Table 5 details
the number of units supported per annum and the value of these contributions. All projects supported were delivered as part of the Affordable
Housing Supply Programme.
Financial Year  2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Total
RPA £12.173 £11.880 £11.880 £11.880 £11.880 £11.880 £71.573

Page 43

Page 27
Table 5: Projects supported by developer contributions April 2020 to March 2024
Financial Year 2020/21 2021/22 2022/23 2023/24 Total
Number of units supported 0 0 34 34 34*
Funding value 0 0 £47,500 £18,750 £66,250
As at 31 March 2024 the Council had £0m of funding from developer contributions in hand. The Council will utilise any other incoming funds to
support Council projects within the Strategic Housing Investment Plan and partner developments, where appropriate.
*Please note that the project supported spanned two financial years so the total number of units was 34.
Other funding sources
The Council will consider utilising other funding sources to support the Strategic Housing Investment Plan, where appropriate. The Council
successfully secured £0.6m from the Scottish Government’s Low Carbon Vacant and Derelict Land Investment Programme to support the King’s
Arms, Irvine town centre regeneration project. The Council will make applications to the Housing Infrastructure Fund to support the Montgomerie
Park, Irvine and James Reid, Saltcoats sites.
Council tax on second and empty homes
The Council is currently undertaking a community consultation on proposals to implement an additional Council Tax levy on second homes from 1
April 2025. Income received from the reduction in discount for empty and second homes in North Ayrshire is held in the Council’s Affordable
Housing Account. Table 6 details the number of units supported per annum and the value of these contributions. All projects supported were
delivered as part of the Affordable Housing Supply Programme. The account also funds two posts as detailed within the ‘Island communities’ and
‘Empty homes and second home buy backs’ sections above. 
Table 6: Projects supported by Council Tax on empty and second homes April 2020 to March 2024
Intentionally blank 2020/21 2021/22 2022/23 2023/24 Total
Number of units supported 191 469 321 539 1,267*
Funding from Council Tax levy on
second homes and empty homes £1,252,078 £2,024,139 £541,320 £1,147,139 £4,964,676
*Please note that a number of the projects supported spanned two financial years so the total number of units was 1,267.

Page 44

Page 28
As at 31 March 2024 the Council had £1.925m of funding from the Council Tax levy on second and empty homes and an estimated annual income
of £1.034m. The Council will utilise the funds to support Council projects within the Strategic Housing Investment Plan and partner developments,
where appropriate.
Planning and other regulatory matters
In 2014, the Council’s Cabinet approved the House Building Protocol, to be used in
all Council housing development projects that meet the criteria for permitted
development. Class 33 of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, as amended, enables local authorities to carry
out works, within their district, for the erection of dwellings so long as the development
conforms with the Local Development Plan.
In 2019, it was agreed that all future Council housing developments progressed as
permitted development will be required to obtain a ‘Certificate of Lawfulness’ from the
Council’s Planning Service. This will certify that each site within the SHIP has been
considered against the full terms of the adopted Local Development Plan. Housing
development proposals by the Council which do not fall within the scope of permitted
development, including schemes which require an Environmental Impact Assessment
(EIA) will require planning permission. Proposals over 0.5 hectares in area will require
to be screened for the purposes of EIA.

Page 45

Page 29
Delivery risks
Through experience, and engagement with registered social landlords and other developers,
development constraints or risks to delivery of the programme have been identified as:
• Inflation of building costs and rising tender prices
• Shortages of materials
• Capacity within the building and development industry across the country
• Costs of infrastructure and ground remediation
• Delays obtaining statutory utility consents
• Emerging costs relating to legislative and building standards regulations amendments
• Availability of grant funding
The Council and its partners will continue to work closely to monitor and actively manage these
risks through the period of the Strategic Housing Investment Plan. 
Amendments or additions to the plan
The delegated authority to accelerate any project detailed within the main SHIP programme is held by the Executive Director (Communities and
Housing) and the Cabinet Member for Communities and Islands.
North Ayrshire Council Cabinet approval will be required to accelerate projects within the SHIP shadow programme or for the addition of any new
projects to the plan.

Page 46

Page 30
Development projects
An overview of projects detailed in the Strategic Housing Investment Plan tables is provided below by locality.
Irvine & Kilwinning 
Project Estimated timeline Site Information
Stanecastle, Irvine
(NAC) 
31 units
Site start: 25 March 2024
Expected completion: 
Autumn 2025
Work is underway to deliver a mix of general needs, amenity, and wheelchair user
accommodation on the site of the former Stanecastle School.
King’s Arms, Irvine
(NAC)
6 units
Site start: 13 May 2024
Expected completion: 
Winter 2025
Works have commenced on site to regenerate a prominent town centre building to deliver
six amenity flats, retaining the original building façade.
Ayrshire Central, Irvine
(NAC)
202 units
Site start: 4 November 2024
Expected completion: 
Winter 2027
Work is underway on this site, which is in a high demand area, to deliver a mix of general
needs, amenity, and wheelchair user properties.  
Montgomerie Park,
Irvine (NAC)
188 units
Site start: Spring 2026
Expected completion: 
Spring 2029  
This development will provide a mix of general needs, amenity, and wheelchair user
accommodation. The site forms part of a wider masterplan area comprising private
development, affordable housing, a new school, and new retail provision.  
Fullarton Street, Irvine
(NAC) 
43 units
Site start: Summer 2026
Expected completion: 
Summer 2028
This project will redevelop the site of the former Irvine high flats which have now been
demolished. The centrally located site will deliver a mix of general needs, amenity, and
wheelchair user accommodation.
Corsehillhead,
Kilwinning (NAC)
7 units
Site start: Summer 2027 
Expected completion: 
Autumn 2028
This development will provide a mix of general needs, amenity, and wheelchair user
accommodation in Kilwinning. The site will complete the redevelopment of the former
school site where two previous phases of social housing have been developed.  
St Michael’s Wynd,
Kilwinning (NAC)
46 units
Site start: Autumn 2027 
Expected completion: 
Spring 2029
The project will deliver a mix of general needs and amenity accommodation in the Corsehill
area of Kilwinning. An options appraisal is required for this site to review its financial
viability.
Bourtreehill Village,
Irvine (NAC)
32 units
Site start: Autumn 2028 
Expected completion:  Autumn
2029
The site will see the regeneration of the Bourtreehill Village area of Irvine. The site is
expected to deliver new retail provision and 32 new homes.

Page 47

Page 31
Project Estimated timeline Site Information
Redburn Place, Irvine
(Cairn) 
10 units
Site start: Autumn 2025
Expected completion: 
Autumn 2026
This development will provide general needs, amenity, and wheelchair accommodation.
This site was formerly known as Confidential Site 1.
Confidential site 3
(Cairn) 
4 units
Site start: Spring 2027
Expected completion: 
Spring 2028
This site has the capacity for 4 affordable, general needs homes.  This site is currently
confidential due to a requirement for planning consent and for acquisition of land. 
Confidential site 12,
Kilwinning (CHA) 
25 units
Site start: Spring 2026
Expected completion: Spring
2027
The 92 unit former ‘unallocated block’ has been reduced to 25 units and a site has been
identified within Kilwinning which remains confidential whilst project viability is assessed. 
Bank Street, Irvine
(CHA)
16 units
Site start: Spring 2027
Expected completion: 
Spring 2028
This town centre regeneration project in Irvine aims to provide 16 new homes for
affordable rent.
Regeneration project
3, Kilwinning
(Riverside) 
30 units
Site start: Spring 2028
Expected completion: 
Spring 2030
This project involves the regeneration of 30 properties to deliver a mix of general needs
houses, amenity properties and homes suitable for wheelchair users. The location has still
to be finalised. 
Three Towns
Project Timeline Site Information
James McFarlane,
Ardrossan (NAC)
19 units
Site start: 25 March 2024
Expected completion: 
Summer/autumn 2025
The Council is currently redeveloping the former James McFarlane school to provide
general needs, amenity, and homes suitable for wheelchair users. The site is located close
to Ardrossan town centre. 
Nursery Place (Regen
1e), Ardrossan (NAC)
6 units
Site start: Spring 2026
Expected completion: 
Spring 2027
This Estate Based Regeneration Programme redevelopment will see 12 properties in
Ardrossan demolished to be replaced with approximately six new affordable homes. 
Grange Court,
Stevenston (NAC)
6 units
Site start: Spring 2026
Expected completion: 
Spring 2027
This Estate Based Regeneration Programme redevelopment will see 16 properties
demolished near Stevenston town centre to be replaced with approximately six new
affordable homes.
James Reid, Saltcoats
(NAC)
46 units
Site start: Summer 2027
Expected completion: 
Early 2029
The site of the former James Reid school and the former Focus Centre will provide general
needs, amenity, and wheelchair accommodation. Issues with a culvert are impacting
Scottish Water approval, options are being reviewed to resolve this matter.

Page 48

Page 32
Project Timeline Site Information
Regeneration Project
1d, Ardrossan (NAC)
36 units
Site start: Early 2028
Expected completion: 
Winter 2029
This project provides a regeneration opportunity for 36 affordable homes, comprising
general needs, amenity, and wheelchair user accommodation. 
Garven Road,
Stevenston (CHA)
20 units
Site start: 25 September 2023
Completion: 
1 October 2024
This site has delivered 20 new general needs, amenity, and wheelchair user homes.
Sharphill Phase 5,
Saltcoats (CHA)
100 units
Site start: Winter 2028
Expected completion: Spring
2030
The next phase of the Sharphill site will deliver an additional 100 new homes, providing a
mix of general needs, amenity, and wheelchair user homes. The scheme has been paused
whilst the financial viability is assessed.
Confidential Site 10,
Ardrossan (CHA) 
50 units
Site start: Spring 2029
Expected completion: 
Winter 2030
This project has capacity for up to 50 homes and is confidential until site feasibility can be
confirmed.
Parkend Gardens,
Saltcoats (Link)
12 units
Site start: Early 2029
Expected completion: 
Early 2030
This development is in close proximity to Saltcoats town centre and adjacent to the
Council’s Kyleshill Court. It will deliver a mix of general needs, amenity and wheelchair
accommodation. The financial viability of the scheme is currently being assessed.
North Coast
Project Timeline Site Information
Former St Mary’s
Primary, Largs (NAC)
26 units
Site start: 15 January 2024
Expected completion: 
Early 2025
Works are well advanced at the former school site which will deliver general needs houses
and amenity properties.  
Nelson Street, Largs
(NAC)
3 units
Site start: 15 January 2024
Expected completion: 
Early 2025
This site will see empty homes refurbished at the site which is in close proximity to Largs
town centre.
Garnock Valley
Project Timeline Site Information
Newhouse Drive,
Kilbirnie (NAC)
7 units
Site start: 15 January 2024
Expected completion: 
Early 2025
Low demand flatted accommodation has been demolished and work is well advanced to
deliver 7 new affordable homes on the Kilbirnie site. Modular construction was utilised to
reduce the time on site and the impact of works on surrounding residents and businesses.

Page 49

Page 33
Project Timeline Site Information
Laburnum Avenue, Beith
(NAC)
7 units
Site start: 15 January 2024
Expected completion: 
Early 2025
Low demand flatted accommodation has been demolished and work is well advanced to
deliver 7 new affordable homes on the Beith site. Modular construction was utilised to
reduce the time on site and the impact of works on surrounding residents and businesses.  
Former Garnock
Academy, Kilbirnie (NAC)
50 units
Site start: 17 June 2024
Expected completion: 
Early 2026
Work is underway at the site of the former Garnock Academy to deliver a mixture of
general needs homes, amenity bungalows and homes suitable for wheelchair users. 
Arran
Project Timeline Site Information
Springbank, Brodick
(Trust HA)
26 units
Site start: Winter 2025
Expected completion: 
Autumn 2027
Trust Housing Association are exploring the viability of developing 26 homes at this Brodick
site. This site was formerly known as Confidential Site 4. The access point for this
development should be agreed with NAC Roads as the existing road network may not cope
with the additional units

Page 50

Page 34
Progress update
The Council has made a commitment to develop 1,643 new homes by 2030. Good progress has been made towards achieving this target, with
885 new Council homes built as at 31 March 2024. The tables below detail the Council and its partners progress to date (excluding sites which
are noted for completion during 2024/25 within the Strategic Housing Investment Plan 2025 – 2030).
Table 7: Social housing new build completions by locality and financial year
Locality Pre 2018/19 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Total
Arran 56 0 0 0 19 15 0 90
Garnock Valley 24 0 0 49 0 0 0 73
Irvine 250 0 111 0 83 35 113 592
Kilwinning 68 64 0 0 24 127 0 283
North Coast 85 26 58 0 141 29 12 351
Three Towns 84 126 0 28 105 16 30 389
Total Units 567 216 169 77 372 220 155 1,778 
Table 8: Social housing new build completions by type
House type General
needs
Amenity
housing
Sheltered
housing
Supported
accommodation
Wheelchair
user
Ground
floor living
(wheelchair
user)
Other
adapted Other
New
Supply
Shared
Equity
(NSSE)
Total
Units 958 334 251 62 90 49 10 8 16 1,778
Percentage 53.9% 18.8% 14.1% 3.5% 5.1% 2.7% 0.6% 0.4% 0.9% 100%
It should be noted that 50 of the amenity, sheltered and supported accommodation units detailed above are suitable for wheelchair users.

Page 51

Page 35 
Completed North Ayrshire
Council projects Locality General
Needs Amenity Sheltered Supported Wheelchair
User 
Ground
Floor
Living
Other Total
Units
Completion
year
Copeland Crescent, Millport North Coast 0 11 0 0 1 0 0 12 2013/14
Redstone Avenue, Kilwinning Kilwinning 37 3 0 0 2 4 0 46 2014/15
John Galt PS, Irvine Irvine 64 10 0 0 6 0 0 80 2014/15
Stevenston Institute, Largs North Coast 0 11 0 0 0 0 0 11 2015/16
Dickson Drive, Irvine Irvine 6 2 0 0 0 0 0 8 2015/16
Kiln Court, Irvine Irvine 0 0 16 0 0 0 0 16 2015/16
Montgomery Court, Kilbirnie Garnock Valley 0 8 16 0 0 0 0 24 2016/17
Fencedyke, Irvine Irvine 19 10 0 0 3 3 0 35 2017/18
Glencairn House, Stevenston Three Towns 0 0 28 0 0 0 0 28 2018/19
Canal Court, Saltcoats Three Towns 0 0 36 0 0 0 0 36 2018/19
Ardrossan Road, Seamill North Coast 25 5 0 0 1 0 0 31 2019/20
Dickson Drive, Irvine  Irvine 14 3 0 0 4 3 0 24 2019/20
Watt Court & Dalry Primary  Garnock Valley 0 8 22 15 0 0 4 49 2020/21
Dalrymple Place, Irvine Irvine 0 0 24 0 9 0 0 33 2021/22
St Beya, Cumbrae North Coast 3 9 0 0 3 3 0 18 2021/22
Springvale, Saltcoats Three Towns 6 2 0 0 2 4 0 14 2021/22
Flatt Road, Largs North Coast 49 16 28 22 5 2 1 123 2021/22
Towerlands, Irvine Irvine 20 12 0 0 5 13 0 50 2021/22
Brathwic Terrace, Arran Arran 17 8 0 0 2 7 0 34 2022/23
St Michael's Wynd, Kilwinning Kilwinning 34 2 24 10 2 6 1 79 2022/23
St Colm's Place, Largs North Coast 0 0 29 0 0 0 0 29 2022/23
Caley Court, Stevenston Three Towns 0 0 0 15 0 0 1 16 2022/23
Harbourside, Irvine Irvine 24 10 28 0 4 4 1 71 2023/24
Afton Court, Stevenston Three Towns 0 6 0 0 0 0 0 6 2023/24
Largs Police Station North Coast 0 12 0 0 0 0 0 12 2023/24
Total  Locality 318 148 251 62 49 49 8 885 Completion
Year

Page 52

Page 36
Arran Development Trust has also secured funding from the Rural and Island Housing Fund to deliver 18 new affordable homes in Lamlash as
detailed in table 9 below.
Completed Registered Social
Landlord projects Locality General
needs Amenity Wheelchair Other
adapted NSSE Total
units
Completion
Year
Flatt Farm, Largs (CHA) North Coast 16 10 0 0 0 26 2013/14
Vineburgh Phase 3, Irvine (CHA) Irvine 43 10 0 0 10 63 2013/14
Jetty Road, Fairlie (CHA) North Coast 10 3 0 0 0 13 2014/15
Benlister Road, Lamlash (Riverside) Arran 50 0 0 0 6 56 2014/15
Vineburgh Phase 4, Irvine (CHA) Irvine 41 6 1 0 0 48 2014/15
Pennyburn, Kilwinning (Riverside) Kilwinning 21 0 1 0 0 22 2015/16
Waterside Street, Largs (CHA) North Coast 0 12 0 0 0 12 2015/16
Seamore Street, Largs (CHA) North Coast 8 3 0 0 0 11 2016/17
Ardrossan Harbour Phase 1 (CHA) Three Towns 55 13 2 0 0 70 2017/18
New Street, Stevenston (CHA) Three Towns 7 7 0 0 0 14 2017/18
Nelson Street, Largs (CHA) North Coast 7 5 2 0 0 14 2018/19
Corsehillhead, Kilwinning (CHA) Kilwinning 57 5 2 0 0 64 2018/19
Ardrossan Harbour Phase 2 (CHA) Three Towns 2 4 4 0 0 10 2018/19
Sharphill Phase 3, Saltcoats (CHA) Three Towns 19 3 2 0 0 24 2018/19
Stanley P.S., Ardrossan (CHA) Three Towns 24 2 2 0 0 28 2018/19
Victoria Hotel, Largs (CHA) North Coast 0 12 0 0 0 12 2018/19
Balnagowan, Skelmorlie (CHA) North Coast 25 0 2 0 0 27 2019/20
Tarryholm Phase 1, Irvine (Riverside) Irvine 61 14 2 10 0 87 2019/20
Ardoch Court, Stevenston (CHA) Three Towns 26 0 2 0 0 28 2020/21
Corrie Crescent (Charitable Bond) (CHA) Three Towns 12 1 0 0 0 13 2021/22
Glebe, Saltcoats (CHA) Three Towns 0 0 2 0 0 2 2021/22
Sharphill Phase 4, Saltcoats (CHA) Three Towns 65 5 6 0 0 76 2021/22
West Byrehill, Kilwinning (CHA) Kilwinning 59 8 5 0 0 72 2022/23
Tarryholm Phase 2, Irvine (Riverside) Irvine 32 40 5 0 0 77 2023/24
Green Street, Saltcoats (CHA) North Coast 0 23 1 0 0 24 2023/24
Total Locality 640 186 41 10 16 893 Completion
Year

Page 53

Page 37
Table 9: Community housing new build completions
Project Locality Developer Tenure General Needs Other Total Units Completion Year
Rowarden, Lamlash Arran Arran Development Trust Affordable private rent 18 0 18 2024/25

Page 54

Official‐Protect#
CONFIDENTIAL DRAFT SHIP 2025‐2030
Pre 2025/26
2025/26
2026/27
2027/28
2028/29
2029/30
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30
General
Needs
Amenity
Supported
W
heelchair
Ground
Floor
Sheltered
Afton Court Stevenston NAC ‐ New Build ‐ ‐ ‐ £90,678 £0 £90,678 £0 £0 £0 £0 £0 £0
Buy Backs 2023/2024 ! NAC ‐ Buy Back 01 Apr 23 31 Mar 24 ‐ £213,863 £0 £213,863 £0 £0 £0 £0 £0 £0
Buy Backs (Ukraine) 2023/2024 ! NAC ‐ Buy Back 14 Nov 23 31 Mar 24 ‐ £1,927,200 £0 £1,927,200 £0 £0 £0 £0 £0 £0
Refurbishment Project 8 Irvine TBA NAC ‐ Refurb ‐ ‐ ‐ £0 £0 £0 £0 £0 £0 £0 £0 £0
Glebe Place Saltcoats X: 224700 Y: 641700 NAC ‐ New Build ‐ ‐ ‐ £0 £0 £0 £0 £0 £0 £0 £0 £0
cost overruns Sharphill 4 CHA ‐ New Build ‐ ‐ ‐ £295,858 ‐ £295,858 £0 £0 £0 £0 £0 £0
Unallocated Regeneration Block TBA TBA NAC ‐ New Build ‐ ‐ 2025/26 £0 £0 £0 £0 £0 £0 £0 £0 £0
2nd Hand & Empty Home Buy Backs ! ! NAC 60 Buy Back 01 Apr 24 31 Mar 29 2024/25 5 8 9 9 9 20 5 8 9 9 9 20 £2,400,000 60 £0 £0 £333,000 £320,000 £360,000 £360,000 £360,000 £667,000
Laburnum Avenue (Regen 1a)  Beith X: 234170 Y: 653640 NAC 7 New Build 15 Jan 24 17 Jan 25 2023/24 7 7 £699,468 4 3 £0 £620,701 £78,767 £0 £0 £0 £0 £0
Newhouse Drive (Regen 1b)  Kilbirnie X: 230940 Y: 653815 NAC 7 New Build 15 Jan 24 17 Jan 25 2023/24 7 7 £699,468 4 3 £0 £620,701 £78,767 £0 £0 £0 £0 £0
Former St Mary's school Largs X: 220995 Y: 659630 NAC 26 New Build 15 Jan 24 31 Jan 25 2023/24 26 26 £3,976,743 14 12 £0 £2,457,542 £1,519,201 £0 £0 £0 £0 £0
James McFarlane (Redev 8a) Ardrossan X: 223300 Y: 643345 NAC 19 New Build 25 Mar 24 18 Jul 25 2023/24 19 19 £1,993,029 10 4 1 4 £291,370 £510,102 £1,191,558 £0 £0 £0 £0 £0
Stanecastle (Redev 11a) Irvine X: 234070 Y: 640150 NAC 31 New Build 25 Mar 24 18 Sep 25 2023/24 31 31 £3,204,355 17 7 3 4 £575,543 £506,031 £2,122,781 £0 £0 £0 £0 £0
King's Arms (Regen 1c) Irvine X: 232090 Y: 638935 NAC 6 New Build 13 May 24 01 Dec 25 2023/24 6 6 £769,055 6 £288,868 £24,131 £456,056 £0 £0 £0 £0 £0
Garnock Academy (Redev 9) Kilbirnie X: 231290 Y:654800 NAC 50 New Build 17 Jun 24 31 Jan 26 2023/24 50 50 £5,306,966 28 13 2 7 £530,177 £0 £3,308,000 £1,468,789 £0 £0 £0 £0
Ayrshire Central (Redev 12) Irvine X: 232105 Y: 640785 NAC 202 New Build 04 Nov 24 30 Nov 27 2024/25 202 202 £24,355,655 65 85 26 26 £2,252,936 £0 £2,348,508 £7,874,211 £7,128,000 £4,752,000 £0 £0
Nelson Street Largs X: 220655 Y: 659595 NAC 3 Refurb 01 Apr 25 01 Dec 26 2024/25 3 3 £171,000 3 £0 £0 £10,000 £161,000 £0 £0 £0 £0
Montgomerie Park Irvine X: 233060 Y: 641300 NAC 188 New Build 01 Mar 26 30 Apr 29 2025/26 188 188 £24,822,268 121 32 19 16 £4,579,235 £0 £0 £280,000 £740,000 £2,500,000 £4,894,831 £11,828,202
Nursery Place (Regen 1e) Ardrossan X: 223735 Y: 642845 NAC 6 New Build 01 Apr 26 30 Apr 27 2026/27 6 6 £796,362 4 2 £0 £0 £0 £0 £250,000 £546,362 £0 £0
Grange Court (Regen) Stevenston X: 226485 Y: 642150 NAC 6 New Build 01 Apr 26 30 Apr 27 2026/27 6 6 £823,563 6 £0 £0 £0 £0 £250,000 £573,563 £0 £0
Fullarton Street (HF) Irvine X: 232050 Y: 638550 NAC 43 New Build 12 Jul 26 31 Jul 28 2024/25 43 43 £5,902,198 36 4 1 2 £0 £0 £0 £0 £500,000 £812,029 £4,590,169 £0
Bourtreehill Village (Redev 7) Irvine X: 234475 Y: 639220 NAC 32 New Build 01 Aug 28 31 Aug 29 2024/25 32 32 £4,630,312 24 6 1 1 £0 £0 £0 £0 £0 £0 £2,000,000 £2,630,312
Cairn Buy Back Programme ! ! Cairn 2 Buy Back 01 Apr 24 31 Mar 26 2024/25 2 2 £85,000 2 £0 £0 £80,000 £5,000 £0 £0 £0 £0
Garven Road (Confidential Site 8)  Stevenston X: 227180 Y: 641075 CHA 20 New Build 25 Sep 23 01 Oct 24 2023/24 20 20 £3,200,000 18 1 1 £0 £2,691,071 £508,929 £0 £0 £0 £0 £0
CHA Buy Back Programme ! ! CHA 6 Buy Back 01 Nov 23 31 Mar 30 2023/24 1 1 1 1 1 1 1 1 1 1 1 1 £240,000 6 £0 £0 £45,000 £40,000 £40,000 £80,000 £35,000 £0
Unallocated CHA Block (67 units) TBA TBA CHA ‐ New Build ‐ ‐ 2025/26 £0 £0 £0 £0 £0 £0 £0 £0 £0
Riverside Buy Back Programme Kilwinning ! Riverside 15 Buy Back 01 Apr 23 01 Mar 27 2023/24 2 3 5 5 2 3 5 5 £1,367,730 15 £0 £80,000 £92,434 £400,000 £400,000 £395,296 £0 £0
Springbank (Confidential site 4) ₳  Arran X: 202088 Y: 635639 Trust 26 New Build 01 Dec 25 30 Sep 27 2024/25 26 26 £5,000,000 26 £0 £0 £0 £1,231,000 £2,112,000 £1,657,000 £0 £0
Trust Buy Back Programme Arran ! Trust 6 Buy Back 01 Nov 23 31 Mar 29 2023/24 2 1 1 2 2 1 1 2 £600,000 6 £0 £196,250 £0 £100,000 £100,000 £203,750 £0 £0
761 380 230 71 17 42 21 70 121 19 257 53 241 £93,570,771 469 178 0 54 60 0 £8,518,129 £10,234,129 £12,173,000 £11,880,000 £11,880,000 £11,880,000 £11,880,000 £15,125,514
CONFIDENTIAL DRAFT SHIP Shadow Programme 2025‐2030
Pre 2025/26
2025/26
2026/27
2027/28
2028/29
2029/30 +
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30 +
General Needs
Amenity
Supported
W
heelchair
Ground Floor
Living
Sheltered
Corsehillhead Kilwinning X: 231315 Y: 643095 NAC 7 New Build 01 Jul 27 01 Aug 28 2027/28 7 7 £1,908,397 5 2 £202,654 £0 £0 £0 £0 £900,000 £805,743 £0
James Reid & FC (Redev 8b) Saltcoats X: 225511 Y: 642690 NAC 46 New Build 01 Jul 27 01 Jan 29 2027/28 46 46 £7,215,204 26 11 4 5 £829,748 £0 £0 £0 £0 £2,500,000 £3,885,456 £0
St Michael's Phase 3 (NAC unallocated) Kilwinning X: 229300 Y: 643040 NAC 46 New Build 01 Oct 27 01 Apr 29 2027/28 46 46 £7,432,515 26 10 4 6 £0 £0 £0 £0 £0 £1,500,000 £5,000,000 £932,515
Regeneration Project 1d Ardrossan TBA NAC 36 New Build 01 Jan 28 31 Oct 29 2027/28 36 36 £7,246,166 20 5 11 £0 £0 £0 £0 £0 £750,000 £3,733,812 £2,762,354
Redburn Place (Confidential site 1) Irvine TBA Cairn 10 New Build 01 Oct 25 01 Aug 26 2025/26 10 10 £1,800,000 6 2 2 £0 £0 £0 £700,000 £1,100,000 £0 £0 £0
Confidential Site 3 Kilwinning TBA Cairn 4 New Build 01 Apr 27 01 Apr 28 2027/28 4 4 £407,000 4 £0 £0 £0 £0 £0 £207,000 £200,000 £0
Confidential Site 12 (CHA unallocated) Kilwinning TBA CHA 25 New Build 01 Apr 26 30 Apr 27 2026/27 25 25 £4,000,000 20 2 2 1 £0 £0 £0 £0 £4,000,000 £0 £0 £0
Bank Street (111) Irvine X: 232720 Y: 639260 CHA 16 New Build 01 Apr 27 30 Apr 28 2027/28 16 16 £2,560,000 16 £0 £0 £0 £0 £0 £1,750,000 £810,000 £0
Sharphill (Ph 5) Saltcoats X: 225351 Y: 643409 CHA 100 New Build 01 Oct 28 01 Mar 30 2028/29 100 100 £14,800,000 78 17 5 £1,277,000 £0 £0 £0 £0 £0 £5,000,000 £8,523,000
Confidential Site 10 Ardrossan TBA CHA 50 New Build 01 Apr 29 31 Oct 30 2029/30 50 50 £8,000,000 45 3 2 £0 £0 £0 £0 £0 £0 £0 £8,000,000
Parkend Gardens Saltcoats X: 225165 Y: 641130 Link 12 New Build 10 Jan 29 10 Jan 30 2028/29 12 12 £1,909,931 8 3 1 £83,625 £0 £0 £0 £0 £0 £100,000 £1,726,306
Regeneration Project 3 Kilwinning TBA Riverside 30 New Build 01 Apr 28 01 Mar 30 2028/29 30 30 £2,833,680 24 3 1 2 £0 £0 £0 £0 £0 £0 £0 £2,833,680
382 0 10 25 155 142 50 0 0 10 25 73 274 £60,112,893 278 58 0 21 25 0 £2,393,027 £0 £0 £700,000 £5,100,000 £7,607,000 £19,535,011 £24,777,855
#REF! £0 £0
₳ The access point for this development should be agreed with NAC Roads as the existing road network may not cope with the additional units
Confidential Sites
Sites removed from SHIP 2024 ‐ 2029
Estimated
SHIP Spend
Year 5
Estimated
SHIP Spend
Year 6
Site Starts Site Completions
Scottish
Government
Grant
Type Estimated
Site Start
Estimated
Practical
Completion
SHIP 2024 ‐ 2029
Added to SHIP November 2023
Estimated
SHIP Spend
Year 2
Estimated
SHIP Spend
Year 3
Estimated
SHIP Spend
Year 4
House Types
Pre 2023/24
Spend
SHIP Spend
2023/24
Estimated
SHIP
Spend Year
1
SHIP
Approval
Year
Site Coordinates Developer Units
Estimated
SHIP Spend
2028/29
Estimated
SHIP Spend
2029/30
Site Town
Estimated
SHIP Spend
2025/26
Estimated
SHIP Spend
2026/27
Estimated
SHIP Spend
2027/28
Estimated
SHIP
Spend
2024/25
SHIP
Approval
Year
Site Starts Site Completions
Scottish
Government
Grant
House Types
Pre 2023/24
Spend
SHIP Spend
2023/24Site Coordinates Developer Units Type Estimated
Site Start
Estimated
Practical
Completion
Site Town
#Official‐Protect