North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Cabinet 
A Meeting of the Cabinet of North Ayrshire Council will be held in the Council
Chambers, Ground Floor, Cunninghame House, Irvine, KA12 8EE on Tuesday,
29 October 2024 at 14:30 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  Where possible, the meeting will be live-streamed
and available to view at https://north-ayrshire.public-
i.tv/core/portal/home.   
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
2 Minutes
The accuracy of the minutes of meeting of the Cabinet held on 1 October
2024 will be confirmed and the Minutes signed in accordance with
Paragraph 7 (1) of Schedule 7 of the Local Government (Scotland) Act
1973 (copy enclosed).  
Reports by the Chief Executive 
3 Treasury Management and Investment Mid-Year Report 2024/25
Submit a report by the Head of Finance to provide a Treasury
Management update for the period 1 April to 30 September 2024 (copy
enclosed). 
4 Revenue Budget 2024/25 : Financial Performance to 31 August 2024
Submit a report by the Head of Finance to advise of the financial
performance for the Council at 31 August 2024 (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 Capital Programme Performance to 31 August 2024
Submit a report by the Head of Finance to advise of progress in
delivering the Capital Investment Programme 2024/25 (copy enclosed).  
Reports by the Executive Director (Communities and Housing) 
6 Cost of Living Support Update
Submit a report by the Executive Director (Communities and Housing) to
provide a further progress report on the response to the cost-of-living
crisis (copy enclosed). 
7 North Ayrshire Council Community Learning and Development Plan
2024-27
Submit a report by the Executive Director (Communities and Housing) to
seek approval of the North Ayrshire Council Strategic Community
Learning and Development Plan 2024-2027 (copy enclosed). 
8 Proposal for Community Investment Fund (CIF) Expenditure
Submit a report by the Executive Director (Communities and Housing) to
determine applications by Locality Partnerships to allocate CIF funding to
proposed projects (copy enclosed). 
9 Urgent Items
Any other items which the Chair considers to be urgent.
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE  
Webcasting  
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at https://north-ayrshire.public-
i.tv/core/portal/home, where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.  
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.  
Generally, the press and public will not be filmed. However, by entering the
Council Chambers and using the press or public seating area, you
acknowledge that you may be filmed and that any information pertaining to
you contained in the video and oral recording of the meeting will be used
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. In
making this use of your information the Council is processing data which is
necessary for the performance of a task carried out in the public interest.  
If you have any queries regarding this and, in particular, if you believe
that use and/or storage of any particular information would cause, or be
likely to cause, substantial damage or distress to any individual, please
contact dataprotectionofficer@north-ayrshire.gov.uk 
3

Page 4

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Cabinet Sederunt 
Marie Burns (Chair)
Shaun Macaulay (Vice-Chair)
Tony Gurney
Alan Hill
Margaret Johnson
Christina Larsen 
Chair: 
Apologies: 
Attending: 
4

Page 5

Cabinet
1 October 2024 
IRVINE, 1 October 2024 - At a Meeting of the Cabinet of North Ayrshire Council at
2.30 p.m. 
Present (Physical Participation)
Marie Burns, Tony Gurney, Margaret Johnson, Christina Larsen and for
consideration of Education Authority Business Elizabeth Turbet and Jacqui
McKenzie.
In Attendance
C. Hatton, Chief Executive; D. Hammond, Executive Director Communities and
Housing); C. Cameron, Director; and P. McArthur, Senior Manager (Addictions)
(Health and Social Care Partnership); S. Anson, Executive Director; and A.
McClelland, Head of Service (Education); M. Boyd, Head of Service (Finance);
Russell McCutcheon, Executive Director; L. Kirk, Head of Service; and M. Ritchie
(Hunterston, Great Harbour and Tourism) (Economic Development, Growth and
Regeneration); and T. Reaney, Head of Service (Neighbourhood Services); D.
Mackay, Senior Manager (Waste Resources) (Place); F. Walker, Head of Service
(People & ICT); R. Lynch, Senior Manager (Legal) J. Hutcheson, Senior
Communications Officer; and H. Young, Senior Committee Services Officer
(Democratic Services). 
Chair
Marie Burns in the Chair. 
Apologies
Alan Hill and Shaun Macaulay.
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11 and
Section 5 of the Code of Conduct for Councillors. 
2. Minutes 
The Minutes of the Meeting of the Cabinet held on 27 August 2024 were confirmed
and the Minutes signed in accordance with Paragraph 7 (1) of Schedule 7 of the
Local Government (Scotland) Act 1973. 
3. Proposal to Limit P1 Intake at Mayfield Primary School to 25 Children 
Submitted a report by the Executive Director (Education) providing information on the
roll at Mayfield Primary School seeking approval to limit the P1 number to 25 children,
for each school session, from the August 2025 intake. 
The Cabinet agreed to limit the number of P1 children at Mayfield Primary School to
25 for each school session intake. 
Agenda Item 2
5

Page 6

4. Collaborating for Health Equity in Scotland 
Submitted a report by the Executive Director (Education) providing initial information
on our bid to become a participant in the Collaborating for Health Equity in Scotland
(CHES) programme and next steps. 
The Cabinet agreed to note the update and endorse the bid to participate in the
programme. 
5. Health Performance Information and Update – Drug and Alcohol Services –
2023/24 
Submitted a report by the Director (Health and Social Care Partnership) providing (i)
an update on the national and local drug and alcohol related targets and standards
and performance in North Ayrshire; (ii) information of the ongoing successful
implementation of the Medication Assisted Treatment Standards; and (iii) assurance
to Members of the performance, actions and service developments being progressed
to address the significant challenges for our communities. The North Ayrshire
Performance Management Report Alcohol and Drug Services 2023-24 and
Medication Assisted Treatment Progress Report 2023-24 were set out at Appendices
1-2, respectively, to the report. 
Officers responded to Members’ questions and the Cabinet agreed to note the update
on performance and improvement actions contained within the report. 
The following item was subject to the call-in procedure per the Council's
Scheme of Administration and will be considered at the 31 October 2024
meeting of the Audit and Scrutiny Committee. 
6. Household Waste Recycling Centre (HWRC) Digital Booking System 
Submitted a report by the Head of Neighbourhood Services seeking approval to
implement a digital Household Waste Recycling Centre (HWRC) booking system at all
sites. 
Officers responded to Members’ questions and the Cabinet agreed to the proposal to
procure and implement a digital booking system within all Household Waste Recycling
Centres (HWRCs) on the mainland and the Isle of Arran. 
7. Scottish Government Consultation: Changing the International Territorial
Level Geography for Scotland 
Submitted a report by the Head of Economic Development, Growth and Regeneration
seeking approval for the submission of the proposed response to the consultation on
Changing the International Territorial Level Geography for Scotland attached at
Appendix 1 to the report. 
Officers responded to Members’ questions and the Cabinet agreed to (a) approve 
the submission of the proposed consultation response provided at Appendix 1 to the
report; and (b) note (i) the engagement with Scottish Government officers and
Highlands and Islands Regional Economic Partnership to inform the consultation
response; and (ii) that responses to the consultation were also submitted by
Highlands and Islands Regional Economic Partnership and Highlands and Islands
Enterprise. 
6

Page 7

8. The Great Harbour, Irvine: Phase 1 Coastal Hub Full 
Submitted a report by the Head of Economic Development, Growth and Regeneration
seeking endorsement of the Full Business Case for Phase 1 of the Great Harbour,
Irvine, attached at Appendix 1 to the report, and approval for its submission to the
Ayrshire Economic Joint Committee. 
Officers responded to Members’ questions and the Cabinet agreed to (a) endorse the
Full Business Case (FBC) provided at Appendix 1 to the report for Phase 1 Coastal
Hub of the Great Harbour, subject to feedback from the Scottish Government; and (b)
approve the submission of the FBC to the Ayrshire Economic Joint Committee
(AEJC). 
9. Urgent Items 
There were no urgent items. 
The meeting ended at 3:25 p.m 
7

Page 8

8

Page 9

NORTH AYRSHIRE COUNCIL 
29 October 2024 
Cabinet 
Title:    Treasury Management and Investment Mid-Year Report
2024/25 
Purpose:  To provide Cabinet with a Treasury Management update for the
period 1 April to 30 September 2024. 
Recommendation:  That Cabinet agrees to (a) endorse the contents of the Treasury
Management and Investment Mid-Year Report for 2024/25
(Appendix 1); and (b) note the Prudential and Treasury
Indicators contained therein. 
1. Executive Summary 
1.1 The Treasury Management and Investment Strategy and treasury management
indicators provide a framework for the Council's treasury activities to ensure the
effective control of the risks associated with those activities and the pursuit of
optimum performance consistent with those risks.   
1.2 This mid-year review report: 
• provides an update on performance to 30 September 2024; 
• updates the annual prudential indicators to reflect the latest information available
to the Council; 
• demonstrates that the treasury management activities carried out during the
period 1 April to 30 September 2024 have been consistent with the Treasury
Management and Investment Strategy 2024/25 and have complied with the
treasury management indicators set out in the Strategy. 
2. Background 
2.1 The Chartered Institute of Public Finance and Accountancy’s Treasury Management in
the Public Services: Code of Practice 2021 Edition (the CIPFA Code) requires that
Elected Members are provided with regular monitoring reports on treasury
management activities.  The Treasury Management Strategy for 2024/25 was
approved by Council on 28 February 2024. 
Agenda Item 3
9

Page 10

This report is the Mid-Year Report, providing Cabinet with an update on treasury
management activities for the period 1 April to 30 September 2024.   
An annual report on the treasury management activities for the year will be presented
to Council following the end of the financial year. 
These reports ensure that the Council is meeting best practice in accordance with
CIPFA's Code of Practice. 
2.2 The 2024/25 Mid-Year Report is attached at Appendix 1 and covers: 
• Prudential and treasury indicators; 
• Borrowing and associated rates; and 
• Investments and associated rate of return. 
2.3 This report provides an update on performance to 30 September 2024 and the annual
prudential indicators to reflect the latest information.  It is a statutory duty for the
Council to determine and keep under review its approved borrowing limits and
prudential indicators.  Details within the report demonstrate that, during the period 1
April to 30 September 2024, the Council has operated within the authorised and
operational limits and prudential indicators as set out in the Council's 2024/25 Annual
Treasury Management Strategy Statement (TMSS). 
2.4 The Executive Summary of the Mid-Year Report provides a high level overview of
treasury management and performance, with more detail provided in the body of the
report.  Key points to note are: 
• changes in the profile of capital projects has had an impact on all of the
prudential indicators; 
• PWLB interest rates have remained relatively steady during the period in both
the long and short term. 
• during the year to date the Council has undertaken £25m Long-term borrowing
and £15m Short-term borrowing . The Council continues to utilise internal short-
term cash reserves to minimise borrowing costs; and 
• investment returns are above the target and this is reflective of the higher than
anticipated Bank of England base rate which remained steady at 5.25% before
reducing to 5% in August 2024. 
3. Proposals 
3.1 It is proposed that Cabinet (a) endorse the contents of the Treasury Management and
Investment Mid-Year Report for 2024/25 (Appendix 1); and (b) note the Prudential and
Treasury Indicators contained therein. 
10

Page 11

4. Implications/Socio-economic Duty 
Financial 
4.1 General Services 
Capital Financing Costs - the Council budgeted £22.569m for financing costs and
expenses on debt for 2024/25.  It is currently estimated that actual costs will total
£15.560m. This underspend will be transferred to the Loans Fund Reserve in line
with the previously agreed policy to support delivery of the capital investment
programme. 
Housing Revenue Account 
Capital Financing Costs - the Council budgeted £15.034m for financing costs and
expenses for debt in 2024/25. It is currently estimated that actual costs will total
£13.064m.   
The main reason for the underspends is the current strategy to utilise cash balances,
resulting in savings on external interest costs. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
Community Wealth Building 
4.7 None. 
11

Page 12

5. Consultation 
5.1 The Council's treasury advisors, Arlingclose Ltd, were consulted in the preparation of
this report. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Treasury Management and Investment Strategy 2024/25 – Council 28 February 2024 
12

Page 13

Treasury Management and
Investment Mid-Year Report 
2024/25 
13

Page 14

2 
Contents
1. Purpose 3 
2. Executive summary 4 
3. Prudential and treasury indicators 6
a. The Council’s Capital expenditure and financing 2024/25 6
b. The Council’s overall borrowing need  7
c. Limits to borrowing activity 8
d. Treasury position at 30 September 2024 9
e. Affordability PIs 13 
4. Investment rates in 2024/25 13 
5. Investment position for 2024/25 14 
6. Review of Loans Fund Advances 15 
14

Page 15

3
Treasury Management and Investment Mid-Year
Review 2024/25
1. Purpose
The Council is required by regulations issued under the Local Government in Scotland Act 2003 and
the Chartered Institute of Public Finance and Accountancy’s (CIPFA) Code of Practice on Treasury
Management (revised 2021) to produce a mid-year review of treasury management activities.  The
purpose of this mid-year review is to report the performance of the Council’s treasury operation and
how this measures up against the Council’s Treasury Management and Investment Strategy.  This is
done through the publication of updated prudential and treasury indicators for 2024/25.  
This report meets the requirements of both the CIPFA Code of Practice on Treasury Management (the
Code) and the CIPFA Prudential Code for Capital Finance in Local Authorities (the Prudential Code). 
During 2024/25, to meet the minimum reporting requirement, the following reports should be
submitted to Elected Members: 
• an annual treasury management and investment strategy (submitted to the Council on 28
February 2024)
• the capital strategy (submitted to the Council on 28 February 2024)
• a mid-year treasury update report (this report)
• an annual review following the end of the year describing the activity compared to the strategy
(will be submitted to Council in June 2025) 
Regulations place responsibility on members for the review and scrutiny of treasury management
policy and activities.  This report is, therefore, important in that respect, as it provides details of
treasury activities for the six months to 30 September 2024 and highlights performance against the
Council’s policies previously approved by members.   
15

Page 16

4
2. Executive Summary
During the six month period to 30 September 2024, the Council complied with its legislative and
regulatory requirements.   
The key prudential and treasury indicators for 2024/25 have been updated based on the latest
available information and will be used to assess performance at the end of the year. 
TABLE 1 
A summary of performance is provided below with more detailed information provided in the body of
the report. 
Capital Expenditure for both the General Fund and HRA vary from original estimates due to changes in
the profile of projects. Full details of all movements in the capital expenditure budgets are included in
the capital programme performance reports submitted to Cabinet throughout the year. 
The Capital Financing Requirement (CFR) is the underlying borrowing requirements of the Council. 
The increase to the requirement during 2024/25 reflects the change in profile of the capital
programme. 
Gross Borrowing reflects the actual borrowing which has been undertaken. This is projected to be
higher than anticipated due to the revised profile of capital projects. 
The Operational Boundary is the maximum we would anticipate borrowing to fund the current year
capital programme building in flexibility for the timing of the different funding streams and principal
repayments.  The in-year variance is linked to the re-profiling of the capital programme. 
The Authorised Limit is set at 10% above the Operational Boundary to give some flexibility to raise
funds for future year capital investment. 
2024/25 2024/25
Prudential and treasury indicators Original Estimate Revised Estimate
£m £m
Capital expenditure (Indicator 1)
·             Non-HRA                   104.655                    129.057
·             HRA                     52.417                      51.793
·             Total                   157.072                    180.850
Capital Financing Requirement (CFR):
·             Non-HRA                   346.096                    341.864
·             HRA                   198.552                    204.689
·             Total                   544.648                    546.553
Gross borrowing (Indicator 4)                   478.337                    504.553
Operational Boundary (Indicator 5)                   558.072                    565.760
Authorised Limit (Indicator 6)                   613.880                    622.336
Investments (Indicator 8)
·             Longer than 1 year -  -
·             Under 1 year                     30.000                      35.250
·             Total                     30.000                      35.250
16

Page 17

5
The Council has a strategy of taking a combination of temporary and permanent borrowing in
recognition of the Council’s longer term borrowing requirements and the market rates available at
that time. This balances short term financial savings with longer term security of costs. During the
period 1 April to 30 September 2024 the Council undertook £25m Long term borrowing and £15m
Short term borrowing. 
Affordability of borrowing is measured by a number of indicators, including the impact of: 
• Percentage of financial costs relative to the net revenue stream of the General fund and
Housing Revenue Account. 
As at 30 September 2024 the above indicator shows estimated ratios of 3.1% and 33.3% for General
Fund and HRA respectively. Capital expenditure impacts on the revenue budget through financing
charges so it is essential the Council ensures the financing costs remain affordable and do not
constitute an excessive proportion of the revenue resources available. From a General Fund
perspective, the latest Scottish Local Authority average was 5.4%, therefore demonstrating a prudent
borrowing policy. For the HRA, the latest Scottish average was 21.3%. The level of loan charges is
deemed prudent and affordable within the framework of the 30 year Housing business plan. 
The average investment rate to 30 September 2024 was 5.12%, compared to a target of 4.25% and
actual in 2023/24 of 4.81%. The return secured this year to date reflects the Bank of England base rate
which has remained steady at 5.25% before reducing to 5% in August 2024.  The Council’s objective
when investing money is to strike an appropriate balance between risk and return, minimising the risk
of incurring losses from defaults and the risk of receiving unsuitably low investment income.   
Other prudential and treasury indicators and supporting information can be found in the main body of
this report. 
Conclusion 
The Head of Finance confirms that long-term borrowing is only undertaken for a capital purpose and
the statutory borrowing limit (the authorised limit) has not been breached. 
17

Page 18

6
3. Prudential and Treasury Indicators for 2024/25 
The Prudential Code establishes a framework to ensure Councils demonstrate effective control over
levels of, and decisions relating to, capital investment activity including borrowing.  The Treasury
indicators are used to ensure that risk is managed and controlled effectively.  Together the Prudential
and Treasury Indicators consider the affordability and impact of capital expenditure decisions and set
out the Council’s overall capital framework. 
These indicators help the Council to demonstrate public accountability in relation to borrowing and
investments.  As part of this accountability this report will summarise the following: - 
• Capital activity during the year (section a);
• Impact of this activity on the Council’s underlying debt (the Capital Financing Requirement)
(section b);
• The actual prudential and treasury indicators (section a – e);
• Overall treasury position identifying how the Council has borrowed in relation to this debt, and
the impact on investment balances (section e);
• Detailed debt activity (section e); and
• Summary of interest rate movements in the year (section 4);
• Detailed investment activity (section 5). 
(a)  The Council’s Capital Expenditure and Financing 2024/25
(Prudential Indicator 1)
The Council incurs capital expenditure when it invests in its long term assets.  Capital Expenditure can
be funded in two main ways: 
• Financed immediately through the application of capital or revenue resources (capital receipts,
capital grants, revenue contributions etc.), which has no resultant impact on the Council’s
borrowing need; or
• If insufficient financing is available, or a decision is taken not to apply other resources, the
capital expenditure will give rise to borrowing, which is approved as part of the Council’s
investment plans.   
The tables below show the planned capital expenditure for 2024/25 and the latest forecast, alongside
the amount estimated to be financed in year and the amount which will give rise to borrowing. 
TABLE 2 
2024/25 2024/25
General Fund Original Estimate Revised Estimate
£m £m
Capital expenditure (Indicator 1)                   104.655                    129.057
Financed in year from external funding and reserves                     26.355                      38.078
Unfinanced capital expenditure                      78.300                      90.979
2024/25 2024/25
HRA Original Estimate Revised Estimate
£m £m
Capital expenditure (Indicator 1)                     52.417                      51.793
Financed in year from external funding and reserves                     28.301                      25.470
Unfinanced capital expenditure                      24.116                      26.323
18

Page 19

7
(b) The Council’s Overall Borrowing Need (the Capital Financing
Requirement) (Prudential Indicators 2 and 3)
This indicator outlines the Council’s Capital Financing Requirement (CFR).  The CFR is simply the total
historic outstanding capital expenditure which has not been paid from either a capital or revenue
resource and therefore needs to be funded from borrowing.  It is essentially a measure of the Council’s
underlying borrowing need. 
Part of the Council’s treasury activity is to meet the funding requirements for this borrowing need. 
The treasury management section organises the Council’s cash position to ensure that sufficient cash
is available to meet the capital plans and cash flow requirements.  This may be sourced through
borrowing from external bodies (such as the Government through the Public Works Loan Board
[PWLB] or the money markets), by utilising temporary cash resources within the Council or through
temporary borrowing from other local authorities. 
The Council’s underlying borrowing need (CFR) is not allowed to rise indefinitely.  The Council is
required to make an annual revenue charge, called the Loan Fund Principal Repayment.  This is
effectively a repayment of the borrowing need and it is charged to revenue over the life of the asset. 
This charge reduces the CFR each year. This differs from the treasury management arrangements
which ensure that cash is available to meet capital commitments.  External debt can also be borrowed
or repaid at any time, but this does not change the CFR. 
The total CFR can also be reduced by: 
• the application of additional capital financing resources (such as unapplied capital receipts); or 
• increasing the annual revenue charge 
The Council’s CFR for the year is shown in the following table and is a key prudential indicator.  The
opening balance excludes the PPP / NPD schemes because no borrowing is actually required against
these schemes, as a borrowing facility is included in the contract. 
Table 3 shows that, based on historic capital expenditure and this year’s capital expenditure, the
Council has a cumulative underlying borrowing need of £546.553m forecast at 31 March 2025.  This is
higher than the original estimate largely as a result of changes in the profile of capital projects. 
TABLE 3 
2024/25 2024/25
CFR Original Estimate Revised Estimate
£m £m
Opening Balance                   450.140                    436.886
Add unfinanced capital expenditure (General Fund and HRA per
Table 2)                   102.416                    117.302
Less Loans Fund Principal Repayments                     (7.908)                     (7.635)
Closing balance (Indicator 2)                   544.648                    546.553
Annual Change (Indicator 3)                     94.508                    109.667
19

Page 20

8
c) Limits to Borrowing Activity (Prudential Indicators 4 - 6)
Borrowing activity is constrained by the prudential indicators for CFR, gross borrowing and by the
authorised limit to ensure the Council operates its activities within well-defined limits. 
Gross borrowing and the CFR 
There is a need to ensure that gross debt does not, except in the medium term, exceed the total CFR
(i.e. the Council does not borrow more than it needs to fund its capital programme).  In exceptional
circumstances Councils are allowed to borrow to cover the current financial year plus the next two
financial years (i.e. to 2026/27).  This provides some flexibility to borrow in advance where this is
appropriate.   
Table 4 highlights the Council’s forecast gross borrowing position against the CFR and confirms that at
30 September 2024 the Council has complied with this prudential indicator as gross borrowing is
currently within its CFR.  The Council is currently under-borrowed by £209.316m due to the continuing
strategy to delay long-term external borrowing by utilising internal cash balances. 
TABLE 4 
As part of its annual Treasury Management and Investment Strategy the Council sets limits for external
borrowing which it is not normally expected to exceed.  These limits are explained below. 
The Operational Boundary 
The operational boundary is the expected maximum borrowing position of the Council during the year,
taking account of the timing of various funding streams and the recharge of principal repayments from
the revenue account.  Periods where the actual position varies from the boundary is acceptable
subject to the authorised limit not being breached. 
The Authorised Limit 
The authorised limit represents a limit beyond which external debt is prohibited.  Performance against
the approved strategy is monitored throughout the year and reported to Cabinet as appropriate.
However, ultimate responsibility for setting or adjusting this limit lies with full Council.  The current
limit is set at 10% of the Operational Boundary. 
Table 5 demonstrates that between 1 April and 30 September 2024 the Council’s gross borrowing was
within both the operational boundary and its authorised limit, by a significant margin due to the
continuing strategy to delay new external borrowing by utilising internal cash balances and changes in
the capital programme that have resulted in a reduced borrowing requirement.    
2024/25 2024/25 30 September 2024
Original Estimate Revised Estimate Actual
£m £m £m
Gross borrowing position (Indicator 4)                   478.337                    504.553                    337.237
CFR                   544.648                    546.553                    546.553
(Under)/Over Borrowed Position                   (66.311)                   (42.000)                  (209.316)
20

Page 21

9
TABLE 5   
(d) Treasury Position at 30 September 2024 (Prudential Indicators
7 - 11)
The Council’s debt and investment position is organised by the treasury management service to ensure
adequate liquidity for revenue and capital activities, security for investments and to manage risks within
agreed parameters.  Procedures and controls to achieve these objectives are well established through both
Member reporting and the Council’s Treasury Management Practices. 
Borrowing Strategy for 2024/25 
The Borrowing Strategy for 2024/25 anticipated bank interest rates declining in the latter half of 2024
and then continuing to decline until December 2025 before settling at 3%. Fixed borrowing rates were
anticipated to remain steady.  Variable, or short-term rates, were expected to be the cheaper form of
borrowing over the period.  Continued economic uncertainty has promoted a cautious approach,
whereby investments continue to be dominated by low counterparty risk considerations, resulting in
relatively low returns compared to borrowing rates. 
During the period April to September, UK gilt yields were volatile and have reduced slightly between
April and September 2024. Much of the downward pressure from lower inflation figures was
counteracted by upward pressure from positive economic data.  The PWLB certainty rate for 10-year
maturity loans was 4.80% at the beginning of the half year and 4.79% at the end. The lowest available
10-year maturity rate was 4.52% and the highest was 5.18%. Rates for 20-year maturity loans ranged
from 5.01% to 5.57% during the half year, and 50-year maturity loans from 4.88% to 5.40%. 
The PWLB HRA rate which is 0.4% below the certainty rate remains available up to June 2025. This
discounted rate is to support local authorities borrowing for the Housing Revenue Account and for
refinancing existing HRA loans. The Council has borrowed £25m at the HRA rate between April and
September 2024. 
As a result of the higher borrowing rates, the Council’s current strategy is to use internal funds instead of
borrowing. 
The following graph demonstrates that PWLB rates have remained relatively steady during the period April
to September 2024.   
Estimated Revised
£m £m
Average gross borrowing position 1 April to 30 September 2024 326.533
Maximum gross borrowing position 1 April to 30 September 2024 343.415
Operational boundary per Treasury Strategy 2024/25
(Indicator 5) 558.072 565.760
Authorised limit per Treasury Strategy 2024/25
(Indicator 6) 613.880 622.336
21

Page 22

10 
CIPFA’s 2021 Prudential Code is clear that local authorities must not borrow to invest primarily for financial
return and that it is not prudent for local authorities to make any investment or spending decision that will
increase the capital financing requirement, and so may lead to new borrowing, unless directly and primarily
related to the functions of the Council. 
Local authorities can borrow from the PWLB provided they can confirm they are not planning to purchase
‘investment assets primarily for yield’ in the current or next two financial years, with confirmation of the
purpose of capital expenditure from the Section 95 Officer.  Authorities that are purchasing or intending to
purchase investment assets primarily for yield will not be able to access the PWLB except to refinance
existing loans or externalise internal borrowing. 
The Council is not planning to purchase any investment assets primarily for yield within the next three years
and so is able fully access the PWLB. 
Borrowing Position for 2024/25 
To date in 2024/25, the Council has undertaken £25m Long term borrowing and £15m Short term
borrowing. The Council continues to utilise internal short-term cash reserves to minimise borrowing
costs. 
In terms of outlook for the remainder of the year, based on current capital plans and replacement
borrowing requirements, it is estimated that the Council will borrow £181.691m this financial year,
with a forecasted planned under borrowed position of £42.000m at the end of March 2024. 
Loans Restructuring 
No rescheduling has taken place between 1 April 2024 and 30 September 2024.  The continuing rise in
gilt yields since early 2022 may result in some of the Council’s PWLB loans being in or close to a
discount position if repaid early. The Council continues to monitor the position. 
22

Page 23

11
LOBO Loans 
The Council has £28.6m of LOBO loans with call dates within the next 12 month. The Council has
liaised with its treasury management advisors, Arlingclose, over the likelihood of the options being
exercised. If the option is exercised and an increased rate proposed, the Council currently plans to
repay the loan at no additional cost as accepting the revised terms would mean the Council would still
have refinancing risk in later years. If applicable, the Council will repay the LOBO loans with available
cash or by borrowing, either from other local authorities or from the PWLB. A £5m LOBO loan was
called and repaid in May 2024. 
The Council’s treasury position (excluding borrowing by PPP/NPD and finance leases) at the 31 March 2024
and 30 September 2024 was as follows: 
TABLE 6 
All investments at 30 September 2024 mature within one year in line with the Treasury Management and
Investment Strategy (Indicator 9). 
The Liability Benchmark compares the Council’s actual existing borrowing against a liability benchmark that
has been calculated to show the lowest risk level of borrowing. The liability benchmark is an important tool
to help establish whether the Council is likely to be a long-term borrower or long-term investor in the future,
and so shape its strategic focus and decision making. It represents an estimate of the cumulative amount of
external borrowing the Council must hold to fund its current capital and revenue plans while keeping
treasury investments at the minimum level of £10m required to manage day-to-day cash flow. 
Following on from the medium-term forecasts in the table above, the long-term liability benchmark assumes
capital expenditure funded by borrowing will be in line with the 10 year capital plan and 30 year HRA
business plan respectively, loans fund advances on new capital expenditure based on asset life and income,
expenditure and reserves all increasing by inflation of 2.5% a year with any specific adjustments made for
planned use of reserves. This is shown in the following chart together with the maturity profile of the
Council’s existing borrowing:
31 March 2024 30 September
Principal Rate/ Return Principal Rate/ Return
£m % £m %
Fixed rate funding:
-PWLB                   245.280 4.77%                   268.835 4.80%
-Other Local Authorities                     21.250 4.27%                     23.177 3.63%
-Market                       1.306 9.79%                       1.275 10.03%
Variable rate funding:
-Market                     48.950 5.10%                     43.950 5.14%
Total debt (Indicator 7)                   316.786 4.81%                   337.237 4.78%
CFR                   436.886                    546.553
Over / (under) borrowing                 (120.100)                  (209.316)
Investments:
- internally managed                     40.105 4.81%                     35.250 5.12%
Total investments (Indicator 8)                     40.105                      35.250
2023/24 2024/25 2025/26 2026/27
Actual
£m
Estimate
£m
Forecast
£m
Forecast
£m
Loans CFR       436.9        546.6        613.1        696.2
Less Balance sheet resources      (157.5)      (109.6)       (94.8)       (80.4)
Net loans requirement       279.4        436.9        518.3        615.7
Liquidity allowance         10.0          10.0          10.0          10.0
Liability Benchmark       289.4        446.9        528.3        625.7
Existing Borrowing      (317.1)      (329.1)     (316.2)     (311.8)
Liability Benchmark
23

Page 24

12 
The maturity structure of the debt portfolio (Indicator 10) at 30 September 2024 is shown below and shows
the period when the Council is required to repay and/or refinance debt. It is important to ensure a
reasonable spread of debt to mitigate against high exposure levels in respect of refinancing.  The current
profile ensures this: 
TABLE 7 
The next indicator is used to manage risk and reduce the impact of adverse movement in interest rates.  This
sets a limit on the Council’s exposure to fixed and variable interest rates (Indicator 11). The Council
approved a limit on variable borrowing of £60.000m in the Treasury Management Strategy 2024/25.   
TABLE 8 
31-Mar-24 30 September 2024
Maturity Profile of Borrowing (Indicator 10) Actual Actual
£m £m
Under 12 months                      62.650                      53.252
12 months and within 24 months                       2.950                        1.594
24 months and within 5 years                     13.845                      13.663
5 years and within 10 years                     31.439                      39.439
10 years and within 20 years                     83.189                      96.177
20 years and within 30 years                     20.125                      20.525
30 years and within 40 years                     92.588                      92.587
40 years and within 50 years                            -                         10.000
50 years and above                     10.000                      10.000
Total Borrowing                   316.786                    337.237
2024/25 30 September 2024
Original Limits Actual
£m £m
Limits on fixed interest rates based on net debt (Indicator 11)                   613.880                    622.336
Limits on variable interest rates based on net debt (Indicator 11)                     60.000                      43.950
24

Page 25

13
(e)  Affordability Prudential Indicators (Prudential Indicator 12 - 14)
These Prudential Indicators assess the affordability of capital investment plans and provide an indication of
the impact of capital investment plans on the Council’s overall finances. The cost impact of borrowing
decisions are reflected in the Council’s budget as loan charges. 
The actual and estimates of the ratio of financing costs to net revenue stream indicator identifies the trend
in the cost of capital (borrowing and other long-term liabilities net of investment income) against the net
revenue stream. 
TABLE 9 
Capital expenditure impacts on the revenue budget through financing charges so it is essential the
Council ensures the financing costs remain affordable and do not constitute an excessive proportion of
the revenue resources available. 
From a General Fund perspective, the latest Scottish Local Authority average was 5.4%, thereby
demonstrating a prudent borrowing policy. 
For the HRA, the latest Scottish average was 21.3%. The level of loan charges is deemed prudent and
affordable within the framework of the 30 year Housing business plan. 
4. Investment Rates in 2024/25 
The Bank Rate has reduced from 5.25% to 5.00% during the period April to September. The Council’s
treasury advisers, Arlingclose, currently project that the bank rate will steadily fall taking Bank Rate down to
around 3% by the end of 2025.  
Estimate of ratio of financing costs to net revenue stream 2024/25 2024/25
(Indicator 14) Original Estimate Revised Estimate
£m £m
General Services 3.5% 3.1%
HRA 24.0% 33.3%
25

Page 26

14 
5. Investment Position for 2024/25 
Investment Policy 
The Council’s investment policy is governed by Scottish Government investment regulations, which have
been implemented in the annual treasury management and investment strategy, approved by Council on 28
February 2024.  This policy sets out the approach for choosing investment counterparties, based on credit
ratings provided by the three main credit rating agencies and supplemented by additional market data (such
as rating outlooks, credit default swaps, bank share prices etc.).   
All investments during 2024/25 have complied with our investment policy. 
Resources 
The Council’s cash balances comprise revenue and capital resources and cash flow monies.  The Council’s
cash resources at 30 September 2024 were as follows: 
TABLE 10 
Investments held by the Council 
The Council has maintained an average balance of £39.469m of invested funds and utilised cash balances
during the year in support of the under-borrowed position.   
The Council’s treasury management advisors, Arlingclose Limited, have five Scottish unitary authorities in
their client group and provide regular investment benchmarking information to the Council. North Ayrshire
Council’s average weighted rate of return on investments during the period 1 April 2024 to 30 September
2024 was 5.12% (4.47% for the period to 30 September 2023).  The actual rate of return on investments as
at 30 September for North Ayrshire Council was 4.98%.  Benchmarking information, comparing the Council’s
performance with the other Scottish Unitary authorities within the client group of Arlingclose, as at 30
September has not currently been published and will be presented as part of the annual review report to
Council in June 2024. 
The target investment rate for 2024/25 was 4.25% and the higher weighted average return in the first
half of the year reflects the Bank of England base rate which has remained steady at 5.25% before
reducing to 5% in August 2024. 
We will continue to invest with approved counterparties in accordance with the approved strategy. 
Cash Balances 2024/25 Actual
£m
1 April 2024                     40.105
30 September 2024                     35.250
Change within 6 months                     (4.855)
26

Page 27

NORTH AYRSHIRE COUNCIL 
29 October 2024 
Cabinet 
Title:    Revenue Budget 2024/25: Financial Performance to 31
August 2024 
Purpose:  To advise Cabinet of the financial performance for the Council
at 31 August 2024. 
Recommendation:  That Cabinet agrees to: 
(a) note the information and financial projections outlined in the
report; and
(b) note the latest financial projection for the Health and Social
Care Partnership highlighted at 2.5. 
1. Executive Summary 
1.1 The General Services Revenue Estimates for 2024/25 were approved by Council on
28 February 2024. The Housing Revenue Account (HRA) Revenue Budget for
2024/25 was approved by Council on 14 February 2024. 
1.2  As part of the monitoring procedures to keep the Cabinet informed of the financial
performance of the Council, financial performance reports are presented on a regular
basis. This is the second report for 2024/25 and covers the period to the end of
August 2024 (Period 5). Projections have been made to the year-end. 
1.3  At Period 5 the General Fund is forecasting a net in-year overspend of £1.257m,
(0.3%), after transferring resources to/from earmarked reserves. This is an
improvement of (£0.752m) from that reported at Period 3. 
1.4  The Housing Revenue Account is forecasting a net breakeven position. This is a
£0.266m reduction from the previously reported underspend. 
1.5  The Health and Social Care Partnership is projecting a year-end overspend of
£6.697m, (2.1%), for 2024/25. The Council services element is reporting a projected
overspend of £5.840m and the Health services element is reporting a projected
overspend of £0.857m. However, previously identified financial recovery actions have
reduced the projected overspend to £2.995m, £2.507m for Council Services, which is
an improvement of (£0.431m) from the previously reported overspend, and £0.488m
for Health services, which is a £0.283m increase to the previously reported
overspend.
Agenda Item 4
27

Page 28

1.6 Significant risks to the reported position have been identified in relation to the reported
HSCP position which requires measures to be put in place by the HSCP to address
these risks. However, this position may have an impact on the level of financial
contributions from the funding parties. This presents a material risk to the financial
sustainability of the Council. 
2. Background 
General Fund 
2.1 The Council set a breakeven budget for 2024/25. In addition to the budget approved
on 28 February 2024, earmarked funds of £84.940m were carried forward from
2023/24 for service expenditure in 2024/25 and beyond. These funds are reflected in
the figures within the 2024/25 financial performance reports as they are drawn down. 
2.2 Current financial projections indicate that a net in-year overspend of £1.257m, (0.3%),
net of transfers to/from reserves, is anticipated for the year to 31 March 2025. The
forecast position will continue to be monitored throughout the year. However, any final
overspend will require the utilisation of Council reserves and may negatively impact
on future budget gaps in the medium term. 
2.3 Details of the current financial projections are summarised in the following table: 
Service Expenditure
App
No.
Annual
Budget
£ million
Projection
to 31 March
2025
£ million
Projected
Variance
for year
(Fav)/Adv
£ million
Projected
Variance
at P3 
(Fav)/Adv 
£ million Movement Note 
Corporate Services 1 18.558 18.436 (0.122) (0.052) (0.070)  
Education 2 173.932 176.753 2.821 3.003 (0.182) (i)
Place 3 52.721 53.582 0.861 0.956 (0.095) (ii)
Communities &
Housing 4 13.870 13.870 0.000 0.047 (0.047)  
Other Corporate Items 5 30.003 27.964 (2.039) (1.664) (0.375) (iii)
Sub Total   289.084 290.605 1.521 2.290 (0.769)  
Health and Social
Care Partnership 9 131.470 131.470 0.000 0.000 0.000  
Balance for Services   420.554 422.075 1.521 2.290 (0.769)  
Financing Charges 6 15.692 15.692 0.000 0.000 0.000  
Contribution to Loans
Fund Reserve 6 7.010 7.010 0.000 0.000 0.000  
Total Planned
Expenditure   443.256 444.777 1.521 2.290 (0.769)  
Aggregate External
Finance 6 (369.870) (369.870) 0.000 0.000 0.000  
Council Tax 6 (65.681) (65.945) (0.264) (0.281) 0.017  
Use of Earmarked
Funds 6 (7.705) (7.705) 0.000 0.000 0.000  
Total Planned
Income   (443.256) (443.520) (0.264) (0.281) 0.017  
Net Expenditure/
(Income)   0.000 1.257 1.257 2.009 (0.752)  
28

Page 29

2.4 Commentary on Significant Movements from Period 3 
The Council's overall financial forecast against the revised budget is an improvement
of (£0.752m) from the previously reported position. A brief explanation of the
significant movements at service level are outlined as follows: 
(i) Education – overspend of £2.821m, an improvement of (£0.182m) from the
previously reported overspend 
The movements are primarily related to: 
• Further projected underspend in relation to facilities management catering
operations across schools, taking account of uptake projections, food and
staffing costs and funding, (£0.347m). 
This has been partly offset by: 
• Increased employee cost projections related to unachieved turnover across the
service, £0.145m.
(ii) Place – overspend of £0.861m, an improvement of (£0.095m) from the
previously reported overspend 
The movement is primarily related to: 
• Revised timetable for the completion of property remedial works, (£0.100m);
• Utilisation of earmarked reserves within Property Maintenance, (£0.071m); and 
• Vacancy management across services, (£0.062m). 
These have been partly offset by additional costs in relation to waste disposal
contracts and unfunded legislative requirements, £0.163m. 
(iii) Other Corporate Items – underspend of (£2.039m), an improvement of
(£0.375m) from the previously reported underspend 
The movement is primarily related reduced inflationary pressures arising from
utility contracts across all services, (£0.350m). 
Health and Social Care Partnership 
2.5 A copy of the HSCP financial performance report as at the end of July 2024 is
attached at Appendix 9. The report highlights the key challenges and variances for the
Partnership. 
The key points for Cabinet to note are summarised below: 
• The projected outturn is a year-end overspend of £6.697m for 2024/25. However,
this has been reduced to £2.995m due to previously identified financial recovery
actions. This is a reduction of (£0.148m) since the previous reporting period.
• The projected overspend on the Council Services element is £5.969m over the
same period, reduced to £2.938m following the identified financial recovery
actions. This is a reduction of (£0.431m) since the previous reporting period;
29

Page 30

• The most significant areas of overspend include care at home, residential
placements for children, physical and learning disability care packages,
supplementary staff in wards, staff costs in Montrose House and unplanned
activities within the lead partnership for mental health.  Further detail is included in
the report at Appendix 9. 
The main areas of risk identified include: 
• The recent announcements by Scottish Government in relation to public sector
finances and in-year spending reductions will impact on current and future funding;
• Continued growing demand for services;
• Staff recruitment and retention challenges across a number of service areas;
• The provider market and the ongoing ability to source packages of care for service
users;
• The expectation that performance will continue to be maintained or improved
despite the significant resource challenges, for example the joint mission for
delayed discharge improvement;
• Ongoing delivery costs of Scottish Government policy directives, particularly where
these are not fully funded or inflation proofed;
• The ongoing review of the Integration Scheme;
• Progress with the work to develop set aside arrangements and the risk sharing
arrangements agreed as part of this;
• The wider system financial challenges, especially the financial position of NHS
Ayrshire and Arran Health Board, their financial deficit and the risks around further
escalation in the national framework for financial escalation.  North Ayrshire IJB
have already discussed our position in relation to the request for payment for
delayed discharges last financial year;
• The underlying levels of overspend which are recurring into 2024-25 and may
impact on the Partnership’s ability to continue to sustain service levels in the future.
• The IJB free general fund reserves are estimated to be fully utilised during this
financial year, leading to an increased risk of requiring additional in-year financial
contributions from NHS Ayrshire and Arran and North Ayrshire Council to break
even; 
• High risk areas of low volume / high-cost services areas e.g. Children’s residential
placements, Learning Disability care packages and complex care packages; 
• Lead / hosted service arrangements, including managing pressures and reporting
this across the 3 IJBs;
• The impact on Lead Partnership and acute services from decisions taken by other
Ayrshire areas;
• The use of supplementary staffing for enhanced observations across a number of
service areas;
• The use of high-cost agency staff to support frontline service delivery in areas where
there are recruitment challenges;
• Agenda for Change Pay Reform programme – including Nursing Band 5-6 re-grade,
protected learning time and reduction to the working week. Non-recurring funding
has been provided to meet costs associated with this but it is unclear whether this
will be sufficient. 
These risks and progress against the financial recovery plan will continue to be
monitored during 2024-25.
30

Page 31

Risks 
2.6 Under the terms of the Health and Social Care Integration Scheme, a recovery plan
must be agreed to address the projected overspend. There is a risk that, if the
recovery plan is not successful, this could have an impact on the level of financial
contributions from the funding parties. Although there would be an expectation that
any additional contributions would be repaid, this could have a knock on effect on the
level of reserves available to address future Council budget gaps as provision would
be required for the potential non-recovery of these funds within a reasonable
timeframe. This position presents a material risk to the financial sustainability of the
Council. 
Housing Revenue Account 
2.7  The Housing Revenue Account budgeted for a breakeven position in 2024/25 and is
currently projecting to outturn in line with this. This is a reduction of £0.266m from the
previously reported underspend position. The projected position is summarised in the
following table with further details provided in Appendix 7. 
Housing Revenue
Account Annual
Budget
£
million
Projection
to 31 March
2025
£ million
Projected
Variance
for year
(Fav)/Adv
£ million
Projected
Variance
at P3
(Fav)/Adv 
£ million Movement Note 
Employee Costs 5.118 5.118 0.000 0.000 0.000  
Property Costs 22.694 24.217 1.523 0.840 0.683 (i)
Supplies and Services 2.353 2.351 (0.002) (0.005) 0.003  
Transport and Plant
Costs 0.021 0.021 0.000 0.000 0.000  
Administration Costs 1.756 1.770 0.014 0.006 0.008  
Third Party Payments 3.752 3.801 0.049 0.048 0.001  
Transfer Payments 0.163 0.163 0.000 0.000 0.000  
Other Expenditure 0.490 0.503 0.013 0.013 0.000  
Capital Financing 26.526 24.556 (1.970) (1.811) (0.159) (ii)
Gross Expenditure 62.873 62.500 (0.373) (0.909) 0.536  
Income (62.873) (62.500) 0.373 0.643 (0.270) (iii)
Net Expenditure 0.000 0.000 (0.000) (0.266) 0.266   
2.8 Commentary on Significant Movements from Period 3 
A brief explanation of the significant movements is outlined as follows: 
(i) Property Costs – overspend of £1.523m, an increase of £0.683m from the
previously reported overspend 
The movement reflects increased expenditure across all categories, including
Responsive Repairs reflecting increased costs for timber and damp works,
£0.138m, Void Repairs, £0.261m, Planned and Cyclical Maintenance, £0.147m,
and Other Property Costs £0.138m. 
31

Page 32

(ii) Capital Financing – underspend of (£1.970m), an increase of (£0.159m) from
the previously reported underspend 
The movement reflects the current treasury strategy of delaying external
borrowing through the utilisation of cash balances, combined with adjustments to
profiling within the HRA Capital programme. These funds will be required to
support the HRA capital programme in future years. 
(iii) Income – under recovery of £0.373m, a reduction of (£0.270m) from the
previously reported 
The movement is primarily related to increased income from Recharges,
(£0.257m), and improved Council House rent income, (£0.071m). These have
been partly offset by a reduction in other income, £0.059m. 
3. Proposals 
3.1 It is proposed that Cabinet agrees to: 
(a)  note the information and financial projections outlined in the report; and
(b)  note the latest financial projection for the Health and Social Care Partnership
highlighted at 2.5. 
4. Implications/Socio-economic Duty 
Financial 
4.1 General Services
The net projection for the year as at 31 August 2024 is a net overspend of £1.257m.
Further in-year measures will require to be put in place across Directorates to address
this. 
Housing Revenue Account
A net breakeven position is forecast for the year as at 31 August 2024. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
32

Page 33

Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic
Business Partner), on 01294 324551. 
Background Papers
Revenue Budget 2024/25: Financial Performance to 30 June 2024 – Cabinet 27 August
2024
33

Page 34

Appendix 1
CHIEF EXECUTIVES
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Chief Executive
Chief Executive 137              143              6                      4%
Total for Chief Executive 137              143              6                      4%
Financial Services
Change Programme 109              109              -                      0%
Audit, Fraud, Safety & Insurance 622              599              (23)                  (4%)
Corporate Procurement 893              827              (66)                  (7%) 1         
Financial Services 1,363           1,363           -                      0%
Revenues (616)             (616)             -                      0%
Transformation 669              669              -                      0%
Total for Financial Services 3,040           2,951           (89)                  (3%)
People & ICT
Employee Services 816              816              -                      0%
HR & Organisational Development 1,061           1,073           12                    1%
ICT 4,877           4,877           -                      0%
Business Support 1,064           1,064           -                      0%
Customer Services 3,856           3,856           -                      0%
Total for People & ICT 11,674         11,686         12                    0%
Democratic Services
Legal & Licensing 407              407              -                      0%
Policy, Performance & Elections 542              497              (45)                  (8%)
Communications 447              455              8                      2%
Civil Contingencies 60                60                -                      0%
Committee Services 409              409              -                      0%
Member Services 1,311           1,316           5                      0%
Ayrshire Support Service 479              465              (14)                  (3%)
Information Governance 52                47                (5)                    (10%)
Total for Democratic Services 3,707           3,656           (51)                  (1%)
Totals 18,558         18,436         (122)                (1%)
34

Page 35

Appendix 1
Subjective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
£000  £000  £000
Employee Costs 15,901         15,784         (117)                (1%)
Property Costs 68                68                -                      0%
Supplies and Services 3,006           3,006           -                      0%
Transport and Plant Costs 22                22                -                      0%
Administration Costs 1,338           1,343           5                      0%
Other Agencies & Bodies 1,937           1,937           -                      0%
Transfer Payments 853              853              -                      0%
Other Expenditure -                   -                   -                      -
Capital Financing -                   -                   -                      -
Gross Expenditure 23,125         23,013         (112)                (0%)
Income (4,567)          (4,577)          (10)                  0%
Net Expenditure 18,558         18,436         (122)                (1%)
35

Page 36

Appendix 1a
CHIEF EXECUTIVES
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000 
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Finance - Corporate Procurement
Movement - There has been a favourable movement of £0.018m since P3 due to extended vacancy
management.
925 (66) -7% Employee costs - There is a projected underspend of £0.066m due to vacancy management.
(66)                 
36

Page 37

Appendix 2
EDUCATION
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Early Years Education 21,281         21,143            (138)                (1%) 1         
Primary Education 49,839         50,390            551                 1% 2         
Secondary Education 62,869         62,567            (302)                (0%) 3         
Additional Support Needs 14,988         16,389            1,401              9% 4         
Central Education 3,730           6,132              2,402              64% 5         
Pupil Equity Fund 4,367           4,367              -                      0%
Facilities Management 16,751         15,658            (1,093)             (7%) 6         
Net Total 173,932       176,753          2,821              2%
Subjective Summary
Annual
Budget
Final  Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs - Teachers 98,002         100,294          2,292              2%
Employee Costs - Non Teachers 47,191         46,809            (382)                (1%)
Property Costs 1,082           1,151              69                   6%
Supplies and Services 25,125         24,854            (271)                (1%)
Transport and Plant Costs 121              132                 11                   9%
Administration Costs 434              459                 25                   6%
Other Agencies & Bodies 8,687           10,439            1,752              20%
Transfer Payments 580              580                 -                      0%
Other Expenditure -                   -                      -                     
Capital Financing 71                71                   -                      0%
Gross Expenditure 181,293       184,789          3,496              2%
Income (7,361)          (8,036)             (675)               
Net Expenditure 173,932       176,753          2,821              2%
37

Page 38

Appendix 2a
EDUCATION
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Early Years Education
Movement: There has been a favourable movement of £0.044m compared to P3 due to a projected decrease
in employee costs.
15,919 (138) -1%
Employee Costs : Overall an estimated underspend of £0.138m.
- Teachers:- projected underspend of £0.008m due to absence.
- Non Teachers:- projected underspend of £0.214m as a result of vacancy management offset by a budgeted
turnover target of £0.084m resulting in a net underspend of £0.130m
A reduction to the budget of £1.198m in 23/24 necessitated a drawdown from Education earmarked funds of
£0.507m pending permanent savings to be implemented for 24/25. The Service redesign has been developed
and will be  implemented by August 2024. The position will be further reviewed from August onwards to assess
costs associated with the new model.
(138)
Note 2 Primary Education
Movement: There has been an unfavourable movement of £0.254m compared to P3 due to a projected
unachieved turnover in employee costs.
47,469 551 1%
Employee Costs : Overall an estimated overspend of £0.551m.
- Teachers:- projected overspend of £0.029m together with a budgeted turnover target of £0.493m resulting in
a net overspend of £0.522m
- Non Teachers:- projected underspend of £0.227m offset by a budgeted turnover target of £0.256m resulting
in a net overspend of £0.029m.
551
Note 3 Secondary Education
Movement: There has been an favourable movement of £0.101m compared to P3 due to a projected decrease
in employee costs.
47,176 (340) -1%
Employee Costs : Overall an estimated underspend of £0.340m.
- Teachers:- projected underspend of £0.844m offset by a budgeted turnover target of £0.535m resulting in a
net underspend of £0.310m
- Non Teachers:- projected underspend of £0.217m offset by a budgeted turnover target of £0.187m resulting
in a net underspend of £0.030m
38 Other minor movements
(302)
Note 4 ASN
Movement: There has been a favourable movement of £0.123m compared to P3. This is mainly due to a
£0.143m increase in employee costs underspends. Day placement fees have increased by £0.032m, partly due
to an additional young person accessing day placement provision. This is partly offset with decreased
residential placement fees of £0.005m and a decrease of £0.013m for payments to other local authorities for
children accessing placements in their establishments.
14,988 (230) -2%
Employee Costs : Overall an estimated underspend of £0.230m.
- Teachers:- projected underspend of £0.189m offset by a budgeted turnover target of £0.073m resulting in a
net underspend of £0.116m
- Non Teachers:- projected underspend of £0.278m offset by a budgeted turnover target of £0.165m resulting
in a net underspend of £0.113m
355 (129) -36% There is a projected underspend of £0.129m on payments to Other Local Authorities due to a reduction in the
number of NAC children accessing placements in their establishments.
1,010 453 45%
There is a projected overspend of £0.453m on external day placements as a result of additional children
requiring this level of support and an increase in rates from these establishments.  Currently there are 29
children in, or expected in, day placement provision. A further review of the process for authorising placements
will be carried out by the service.
543 1,427 263%
There is a projected overspend of £1.427m on external specialist residential placements.  Currently there are
16 children in, or expected in, accommodation.  Increased pressures on internal care settings as well as
changing needs of children and young people have resulted in an increase in the need for external residential
settings. Joint working is ongoing with HSCP to ensure that all options are fully explored to ensure that all
options are considered to retain young people within their local community where possible.  Where this is not
possible, a forum has been set up to further discuss those young people who will require care and education
provision to support them appropriately. Any future additional children who enter Residential Accommodation
will increase the future projected overspend.
(264) (120) There is a projected over recovery of £0.120m in Other Local Authorities income due to the number of other
authority children accessing a place in NAC establishments.
1,401
38

Page 39

Appendix 2a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 5 Central Education
Movement: There has been a unfavourable movement of £0.179m compared to P3 mainly due to a projected
increase in teacher cover costs.
2,767 2,203 80%
Employee costs: There is a projected overspend of £2.298m mainly as a result of significant increase in costs
associated with mandatory cover for teacher maternity cover and sickness absence. There are currently 41
Teachers (36.9 FTE) on maternity leave as well as 8 Early Years Practitioners and 4 Classroom Assistants
(11.2 FTE).  Absence levels are subject to regular review across the service and appropriate actions are taken
to maximise attendance. Average days lost per FTE is 3.86 for the period April-August compared to 2.83 days
lost for same period last year. Average days lost last year was 11 related to the whole service compared to an
estimated 13 days for this year. This is offset by projected underspend in Leadership & Music services of
£0.207m
- 302
There is a projected under recovery of teacher induction grant funding linked to a reduction in the number of
probationary teachers allocated to North Ayrshire by the Scottish Government. Core placement allocations
have been reduced from 51 FTE to 34 FTE resulting in a £0.302m reduction in anticipated grant funding.
(1,120) (106) 9% Income: PPP insurance rebate £0.068m and PPP deductions of £0.038m in excess of budget
3 Other minor movements.
2,402
Note 6 Facilities Management
Movement: There has been an favourable movement of £0.347m compared to P3 mainly due to further
projected underspends in relation catering operations across schools, taking account of uptake projections,
food and staffing costs and funding.
13,744 (439) -3% Employee Costs: There is a projected underspend of £0.439m primarily due to recruitment challenges and a
targeted reduction of overtime and casual costs.
942 69 7% Property Costs: There is a projected overspend of £0.069m mainly in washroom supplies
4,639 (312) -7% Supplies and services: There is a projected overspend of £0.087m in food costs.This has been offset by a
projected underspend of £0.400m across supplies and services in relation to school meal uptake.
(2,621) (448) 17% Income: There is a projected over-recovery of cleaning and janitorial income of £0.060m and a projected over-
recovery of school meals income of £0.388m
- 37 Other minor movements
(1,093)
Note 7 General
Management action to scrutinise all recruitment verification processes has now started in an attempt to reduce
the overall overspend across all employee costs.
39

Page 40

Appendix 3
PLACE
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Directorate and Support 184              184               -                      0%
Neighbourhood Services
Roads 6,844           6,844            -                      0%
Streetscene 4,841           4,850            9                     0%
Waste Resources 9,321           9,834            513                 6% 1         
Municipalisation Advertising (123)             (73)                50                   (41%) 2         
Total for Neighbourhood Services 20,883         21,455          572                 3%
Economic Development, Growth and
Investment
Economic Policy 264              264               -                      0%
Employability & Skills 1,795           1,782            (13)                  (1%)
Regeneration 886              886               -                      0%
Business 878              878               -                      0%
Growth & Investment 247              247               -                      0%
Total for Economic Development, Growth and
Investment 4,070           4,057            (13)                  (0%)
Sustainability, Transport and Corporate
Property
Property Management & Investment 1,412           1,403            (9)                    (1%) 3         
Housing Assets & Investment (1)                 (1)                  -                      0%
Property Maintenance 3,694           3,694            -                      0% 4         
Property Running Costs 4,951           4,971            20                   0% 5         
Energy and Sustainability 7,260           7,260            -                      0%
Internal Transport 10,268         10,559          291                 3% 6         
Total for Sustainability, Transport and Corporate
Property 27,584         27,886          302                 1%
Net Total 52,721         53,582          861                 2%
40

Page 41

Appendix 3
Subjective Summary
Annual
Budget
Projected
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 27,311         27,621          310                 1%
Property Costs 21,742         21,761          19                   0%
Supplies and Services 4,243           4,271            28                   1%
Transport and Plant Costs 9,404           9,766            362                 4%
Administration Costs 556              560               4                     1%
Other Agencies & Bodies 14,968         15,045          77                   1%
Transfer Payments -                   -                    -                      0%
Other Expenditure 78                67                 (11)                  (14%)
Capital Financing -                   -                    -                     
Gross Expenditure 78,302         79,091          789                 1%
Income (25,581)        (25,509)         72                   (0%)
Net Expenditure 52,721         53,582          861                 2%
41

Page 42

Appendix 3a
PLACE
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Waste Services
Movement: There has been an unfavourable movement of £0.163m since P3 due to increased costs within
Third Party Payments mostly from the Clyde Valley and Bulky Waste contracts. The increase for the Clyde
Valley contract was caused by an increase in tonnages, this will be monitored throughout the remainder of the
year. In respect of bulky waste, due to an unfunded legislative change Persistent Organic Pollutants (POPs)
materials at Household Waste Recycling Centres have to be separated and disposed of separately, which
results in a significantly higher gate fee/disposal cost. Increases in contamination levels has also been
identified and to counter this the Waste Awareness Team are promoting a Right Stuff Right Bin comms
campaign and also putting new stickers on bins to remind residents what each bin should be used for.
4,916 422 9%
Employee Costs: The overspend includes the temporary additional resources required to address the current
significant and challenging cumulative sickness absence rate of 15.21 days per FTE from April 2024 to August
2024, if this level continues this would result in an annual rate of 36.5 days per year per FTE. In context, the
absence rate for the same period in 2022/23 was 7.5 days per FTE, resulting in 23.64 days per year per FTE,
and in 2023/24 9.01 days per FTE, resulting in 28.64 days per year per FTE. A robust absence monitoring
process is in place and a dedicated resource has been recruited to monitor and review the absence
management process in Waste, through assisting supervisors with absence management meetings, referrals
to occupational health etc and to support employees return to work. The statutory nature of the service requires
additional resources to cover unforeseen absences. Additional costs are incurred as a result of this and
servicing the bins on overtime attracts enhanced rates. To help mitigate against these additional costs,
resources are being deployed from other services to assist in the Monday to Friday collections reducing the
requirement for overtime. Additionally, resources out-with Waste Collections have received HGV training to
help provide cover for collections. Weekly budget meetings are also being held between the Waste Ops
Management Team and Finance.  An overall review of the Waste service in light of legislative changes and
current service demands is ongoing. This will also take account of waste compositional analysis, presentation
rates, tonnages etc.
214 70 33% Transport Costs: Additional vehicles are in place to deal with ongoing pressures and demands.
21 Other minor movements
513
Note 2 Municipalisation Advertising
Movement: There has been no movement from P3.
(123) 50 (41%) Income: An under recovery of £0.050m primarily due to lead in time for vehicle advertising and unfavourable
market conditions.
50
Note 3 Property Management and Investment
Movement:  There has been a favourable movement of £0.062m since P3 primarily due to vacancy
management.
2,433 (62) (3%) Employee Costs: There is a projected underspend of £0.062m due to vacancy management.
40 Income: There is a projected under-recovery of fee income of £0.040m.
13 Other minor movements
(9)
Note 4 Property Maintenance Costs
Movement: There has been a favourable movement of £0.100m since P3 in relation to property remedial works
which are now anticipated to be undertaken during 2025/26.
Note 5 Property Running Costs
Movement: There has been a favourable movement of £0.072m since P3 primarily due to utilising earmarked
reserves to meet the repair obligations across the commercial estate.
20 Other minor movements
20
Note 6 Internal Transport
Movement: There has been a favourable movement of £0.020m since P3.
1,680 42 3% Employee Costs: There is a projected overspend of £0.042m due to unachieved turnover.
4,682 288 6% Transport Provision Costs: There is a projected overspend of £0.288m due to a higher number of pupils
requiring transport and an increase in tendered costs in Private Contracts for the provision.
1,769 (101) (6%) Fuel: There is a projected underspend in fuel of £0.101m due to a decrease in fuel prices.
1,228 50 4% Repairs & Maintenance: There is a projected overspend of £0.050m in repairs and maintenance as a result of
price increases and maximising the life of assets due to replacement vehicle lead times. 
12 Other minor movements
291
42

Page 43

Appendix 4
COMMUNITIES AND HOUSING
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Directorate and Support 117              117               -                      0%
Housing and Public Protection
Building Services (2,550)          (2,550)           -                      0% 1         
Property Governance -                   -                    -                     
Planning Services 283              145               (138)                (49%) 2         
Protective Services 1,616           1,616            -                      0%
Other Housing 2,615           2,676            61                   2% 3         
Total for Housing and Public Protection 1,964           1,887            (77)                  (4%)
Connected Communities 11,789         11,866          77                   1% 4         
Net Total 13,870         13,870          -                      0%
Subjective Summary
Annual
Budget
Projected
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 24,130         24,246          116                 0%
Property Costs 2,979           2,984            5                     0%
Supplies and Services 7,085           7,086            1                     0%
Transport and Plant Costs 974              977               3                     0%
Administration Costs 215              225               10                   5%
Other Agencies & Bodies 11,043         11,044          1                     0%
Transfer Payments -                   -                    -                      0%
Other Expenditure 171              172               1                     1%
Capital Financing -                   -                    -                     
Gross Expenditure 46,597         46,734          137                 0%
Income (32,727)        (32,864)         (137)                0%
Net Expenditure 13,870         13,870          -                      0%
43

Page 44

Appendix 4a
COMMUNITIES AND HOUSING
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Building Services
Movement: There has been no movement since period 3.
5,641 (92) (2%) Supplies & Services: An underspend of £0.092m in supplies and services. This is primarily due to an
underspend in materials as a result of a reduction in void kitchen and bathroom works.
3,194 45 1% Third Party Payments: An overspend in third party payments of which £0.023m relates to agency workers and
£0.022m in subcontractor costs.
884 34 4% Transport: A projected overspend in transport costs due to increased external vehicle hire costs.
13 Other minor movements
-
Note 2 Planning Services
Movement: There has been a favorable movement since period 3 of £0.044m, due to an increase in planning
application fee income
(584) (138) 24% Income: Forecasted over recovery of £0.138m due to additional planning fee application income.
(138)
Note 3 Other Housing
Movement: There has been a favourable movement of £0.004m since period 3.  A £0.021m increase in
Employee costs has been offset by the utilisation of earmarked reserves to meet additional bad debt provision.
3,364 40 1% Employee Costs: Projected overspend due to £0.020m of partially unachieved turnover and a forecasted
overspend of £0.020m in casual staff in relation to Ardrossan Hostel.
21 Other minor movements
61
Note 4 Connected Communities
Movement: There have been no significant movements since period 3.
6,353 77 1% Employee Costs: Overspend of £0.077m is primarily as a result of revised programming of implementation of
the approved saving to reduce library opening hours by 20%.
77
44

Page 45

Appendix 5
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance Note No
£000 £000 £000
Strathclyde Passenger Transport 2,331 2,231 (100)             (4%)
SPT Concessionary Fares 286 286 -                   0%
Ayrshire Joint Valuation Board 973 932 (41)               (4%)
3,590 3,449 (141)             (4%) 1           
Other Corporate Costs
Pension Costs 1,895 1,895 -                   0%
Central Telephones 350 350 -                   0%
Other Corporate Items (incl Transformation
Costs, Bad Debt Provision, External Audit fees
and other centrally held funding.)
24,219 22,255 (1,964)          (8%) 2           
Housing Benefits (51)               15                66                -129% 3           
30,003 27,964 (2,039)          (7%)
45

Page 46

Appendix 5a
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Joint Boards
There has been no movement from Period 3
3,590 (141)                -4% Projected underspend of (£0.140m) due confirmation of annual requisitions and applicable refunds.
(141)
Note 2 Other Corporate Items
There has been a favourable movement of £0.374m due to a reduction in utility cost inflation provision,
£0.350m, and increased income from employee benefit schemes, £0.024m.
24,219 (1,964)             -8%
The projected underspend is primarily related to centrally held inflationary cost provisions, which are being
applied to offset pressures reported across other services (£0.513m), additional income from employee benefit
schemes (£0.319m)and additional Scottish Government grant income not required in year (£0.758m).
(1,964)
Note 3 Housing Benefit
There has been no movement from Period 3
(51)             66                   -129% Projected overspend of £0.066m due to Housing Benefit Overpayment Recovery
66
46

Page 47

Appendix 6
MISCELLANEOUS ITEMS
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable) % variance Note No
£000 £000 £000
Financing Charges 15,692 15,692 - -
Contribution to Loans Fund Reserve 7,010 7,010 - -
Scottish Government Funding (369,870) (369,870) - -
Council Tax (65,681) (65,945) (264) 0% 1
Use of Earmarked Funds (7,705) (7,705) - -
Net Total (420,554) (420,818) (264) 0%
Growth in the Council Tax base (£0.637m) has been partly offset by an increase in the value of CTR claims
received, £0.274m, and adjustment for prior years, £0.099m. Reported collection rates have shown an initial
improvement and are line with pre pandemic levels.
Note 1 Council Tax
Movement: There has been a minor movement of £0.017m since period 3, primarily related to adjustments to our
Council Tax base, £0.065m, partly offset by a reduction in forecast CTR claims, (£0.073m).
47

Page 48

Appendix 7
HOUSING REVENUE ACCOUNT
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
Note
No
£  £  £
Employee Costs 5,118 5,118 - 0%
Property Costs
Responsive Repairs 7,670 8,088 418 5%
Void Repairs 4,192 4,545 353 8%
Planned and Cyclical Maintenance 5,544 6,176 632 11%
Aids and Adaptions 1,617 1,617 - 0%
Other property costs 3,671 3,791 120 3%
Total for Property Costs 22,694 24,217 1,523 7% 1
Supplies & Services 2,353 2,351 (2) (0%)
Transport Costs 21 21 - 0%
Administration Costs 1,756 1,770 14 1%
Third Party Payments 3,752 3,801 49 1%
Transfer Payments 163 163 - 0%
Other Expenditure 490 503 13 3%
Capital Financing Costs 26,526 24,556 (1,970) (7%) 2
Gross Expenditure 62,873 62,500 (373) (1%)
Income
Council House Rents (60,202) (60,216) (14) 0%
Other Rents (473) (67) 406 (86%)
Recharges (1,082) (1,160) (78) 7%
Other Income (1,116) (1,057) 59 (5%)
Total Income (62,873) (62,500) 373 (1%) 3
Net Expenditure - - -
48

Page 49

Appendix 7a
HRA
BUDGETARY CONTROL 2024/25
REPORT FOR THE 5 MONTHS TO 31 AUGUST 2024
Budget
£000
Variance
£000
Variance
as % of
budget
Note 1
22,694 1,523 7%
1,523
Note 2
26,526 (1,970) -7%
(1,970)
Note 3
(62,873) 373 -1%
373
B/fwd from
2023/24
Transfer to /
from Reserves
Use of
Earmarked sums
Earmarking of in
year surplus
Funding of
Capital Projects
Projected
Balance at
31/03/25
£m £m £m £m £m £m
11.590 - - - - 11.590
5.000 - - - (1.104) 3.896
2.000 - - - - 2.000
1.553 - - - - 1.553
0.300 - - - - 0.300
0.123 - - - - 0.123
20.566 - - - (1.104) 19.462
HRA reserves and balances
An under recovery in income of £0.373m. This is due to an under recovery of £0.406m in Other Rents and £0.059m
in other income, partially offset by an over recovery of £0.078m in recharges.
Capital Financing Costs
Movement - there has been a favourable movement of £0.159m since Period 3.
A projected underspend of £1.970m in capital financing costs reflects continuing strategy to delay new external
borrowing by utilising cash balances, resulting in savings on external interest costs and changes in the profile of the
capital programme.
Section
Income
Movement - there has been a favourable movement of £0.270m since Period 3. This mainly due to a favourable
movement of £0.071m in Council House Rents and £0.257m in Recharges, partially offset by an adverse
movement of £0.059m in Other Income.
Property Costs
Movement - there has been an adverse movement of £0.683m since Period 3. This is due to an increase of
£0.138m in Responsive Repairs, £0.261m in Void Repairs, £0.147m in Planned and Cyclical Maintenance and
£0.138m in other property costs.
There is a projected overspend of £0.418m in Responsive Repairs due to the volume and scope of the works. A
projected £0.632m overspend in relation to Planned and Cyclical Maintenance, largely due to £0.226m costs in
relation to storm damage works resulting from adverse weather conditions early in 2024 and £0.317m projected
overspend due to increased costs in relation to timber and damp works. A projected overspend of £0.120m in other
property costs, largely relating to an overspend of £0.067m in void rent loss. In addition there are projected
overspends of £0.353m in Void Repairs.
Council House Building Fund
Sustainability Fund
Software licences
Transformation Programme
Tenant led budget
Unearmarked
49

Page 50

Appendix 8
Integration Joint Board
19th September 2024
Subject : 2024-25 – Month 4 Financial Performance 
Purpose : To provide an overview of the IJB’s financial performance as at
Month 4 (July). 
Recommendation : It is recommended that the IJB: 
(a) notes the overall integrated financial performance report for
the financial year 2024-25 and the current overall projected year-
end overspend of £6.697m, reduced to £2.995m through already
identified financial recovery actions;
(b) notes the progress with delivery of agreed savings;
(c) approves the actions which are being taken to progress
financial recovery and that a further recovery plan will be
presented to the next IJB;
(d) notes the Care at Home recovery actions detailed at Appendix
F
(d) notes the remaining financial risks for 2024-25; and
(e) approves the budget reductions which are detailed at
paragraph 2.10 
Direction Required to
Council, Health Board or
Both 
Direction to :- 
1. No Direction Required X
2. North Ayrshire Council 
3. NHS Ayrshire & Arran 
4. North Ayrshire Council and NHS Ayrshire & Arran 
Glossary of Terms 
NHS AA NHS Ayrshire and Arran
HSCP Health and Social Care Partnership
MH Mental Health
CAMHS Child & Adolescent Mental Health Services
BRAG Blue, Red, Amber, Green
UNPACS UNPACS, (UNPlanned Activities) – Extra Contractual Referrals
NRAC NHS Resource Allocation Committee
PAC Performance and Audit Committee
MHOF Mental Health Outcome Framework 
50

Page 51

1. EXECUTIVE SUMMARY 
1.1 The report provides an overview of the financial position for the Partnership and
outlines the projected year-end outturn position informed by the projected
expenditure and income commitments; these have been prepared in conjunction with
relevant budget holders and services.   It should be noted that, although this report
refers to the position at the end of July, further work is undertaken following the month
end to finalise projections, therefore the projected outturn position is as current and
up to date as can practicably be reported. 
1.2  The projected outturn is a year-end overspend of £6.697m (2.1%) for 2024-25,
reduced to £2.995m through already identified financial recovery actions.    There is
an increasing risk to achieving financial balance during 2024-25, the projected
outturn position is summarised below with the residual risk following already
identified financial improvement actions: 
Split 
TOTAL Health/
NHS AA
Social
Care/NAC
Projected Overspend @ mth4 £6.697m £0.857m £5.840m
Less Financial Recovery Plan Projections £3.702m £0.369m £3.333m
Residual Risk £2.995m £0.488m £2.507m 
1.3  From the core projections, overall, the main areas of pressure are: care at home,
residential placements for children, physical and learning disability care packages,
supplementary staff in wards, staff costs in Montrose House and Unplanned Activities
(UnPACs) within the lead partnership for mental health. 
1.4 Whilst the overall projected outturn position has not significantly changed, there are
material movements within services, the main movements in the overall projected
position and recovery plan are summarised below: 
Improvement:
• Children’s residential places £0.352m 
Deterioration:
• Care Home places £0.063m
• LD placements £0.320m 
1.5 The Integration Scheme describes the required approach where there is a projected
overspend on the IJB integrated budget, which includes the requirement to agree a
recovery plan to balance the overspending budget.  Only if the recovery plan is
unsuccessful will the Health Board and Council consider making available interim
funds.  NHS Ayrshire and Arran and North Ayrshire Council are not in a financial
position to make interim funds readily available, therefore it is imperative that the IJB
continues to support the process of development of the Financial Recovery Plan and
the actions required to work towards financial balance by the year-end. 
51

Page 52

1.6 The projected IJB outturn position has been adjusted to reflect the impact of Lead
Partnership services. The underspend in relation to North Lead Partnership services
for Mental Health is not fully attributed to the North HSCP as a share has been
allocated to East and South HSCPs, similarly the impact of the outturn on East and
South led services has been shared with North, both on an NRAC basis in line with
the agreed risk sharing mechanism. 
1.7 The Scottish Government have recently announced the 2024/25 funding for the
Mental Health Outcome bundle which estimates a 4.5% reduction from 2023/24. 
Formal confirmation of the funding allocation has not yet been received, but this
would equate to £0.450m and the service are currently working through the
implications of this reduction. 
2. CURRENT POSITION 
2.1 The report includes an overview of the financial position including commitments
against the available resource, explanations for the main budget variances and an
update on progress in terms of savings delivery.   
2.2 FINANCIAL PERFORMANCE – AT MONTH 4 
At month 4 against the full-year budget of £321.083m there is a projected year-end
overspend of £6.697m (2.1%).  The Integration Scheme outlines that there is an
expectation that the IJB takes account of the totality of resources available to balance
the budget in year.   Following this approach, an integrated view of the financial
position should be taken, however it is useful to note that this overall position consists
of a projected overspend of £5.840m in social care services and a projected
overspend of £0.857m in health services.     
Appendix A provides the financial overview of the Partnership position. The sections
that follow outline the significant variances in service expenditure compared to the
approved budgets. 
The projections for some areas will be subject to fluctuations as they depend on
recruitment plans for new funding and also the capacity of providers to take on work. 
Appendix G provides information on the costs of bank and agency staff as requested
at the August IJB. 
2.3 Health and Community Care Services 
Against the full-year budget of £90.116m there is a projected overspend of £6.049m
(6.7%) (£0.062m adverse movement) and the main variances are: 
52

Page 53

a) Care home placements - the budgeted number of permanent placements was
765 and at month 4 there were 789 placements. The projected overspend is
£0.614m (£0.063m adverse) on permanent placements and respite placements
are projected to be online (£0.023m adverse movement). A plan is in place to
manage down the number of permanent placements to reach the target, however
this is challenging due to the need to minimise delayed discharge from hospital
and to continue to support those in critical and substantial need in the community. 
Income recovered from charging orders is projected to be £0.550m over
recovered. This income is challenging to predict as it depends on the length of
the legal process and time taken to sell the property that the charging order is
registered to. 
b) Care at home (now all in house) is projected to be £3.254m overspent (no
movement). The position reflects the cost of meeting the significant demand and
level of provision for care at home support.   
These projections include the estimated cost of bringing the purchased services
inhouse.  The projection is complex due to services being brought in-house at
different times, the number of posts and vacancies transferred, the estimated time
to fill all of the posts and the costs of covering the required hours (plain time
versus overtime) until the posts are filled.  The projection is historically based on
average costs to date but the data for month 1 – 4 is skewed because of the
transfer of the purchased service at different points so this will be reviewed and
refined in month 6 when there will be more representative data. 
c) Physical Disability Services – projected overspend of £0.682m (£0.030m
adverse) split as follows: £1.007m over in residential placements, £0.027m over
in direct payments and £0.352m under in community care packages. 
d) Integrated Island Services is projected to overspend by £0.752m.  The most
significant variance is a projected overspend at Montrose House of £0.561m
which relates to the net overspend on agency staff (i.e. net of underspend on
employee costs). 
e) Specialist Rehab wards – projected overspend of £0.126m (£0.009m favourable)
(Redburn ward £0.152m overspend and Douglas Grant £0.026m underspend). 
The overspend is due to cover costs for vacancies as well as supplementary
staffing for patients who require one to one support. 
f) Wards 1 and 2 – Projected overspend of £0.762m (£0.003m favourable) due to
use of supplementary staffing.
2.4 Mental Health Services 
Against the full-year budget of £107.531m there is a projected overspend of £1.069m
(1%) (adverse movement of £0.478m) prior to the reallocation of the Lead
Partnership variance to East and South HSCP.  The main variances are: 
53

Page 54

• Learning Disabilities are projected to overspend by £0.916m (£0.320m
adverse movement) across community care packages, direct payments and
residential placements. 
• Community Mental Health services are projected to underspend by £0.411m
(£0.011m favourable) which is mainly due to a projected underspend of
£0.541m in community packages and overspends in residential placements of
£0.093m and direct payments of £0.055m. The main reason for underspend
is the availability and capacity of adult community providers to deliver new
packages of care. 
• There is a projected underspend of £0.106m (£0.035m adverse) in relation to
the cost of Hospital Based Complex Continuing Care (HBCCC), this reflects
the impact of change in provision for these services. 
• The Lead Partnership for Mental Health is projected to be £0.658m overspent
(£0.137m adverse movement) and the main variances are as follows: 
• Adult Inpatients – overspent by £0.442m (£0.058m adverse) due to
overspends in supplementary staff for enhanced observations (1:1 and
2:1) and use of bank staff.   
• The UNPACS (Unplanned Activities) budget – projected overspend is
£0.679m (£0.048m favourable movement) based on current
placements and an allowance for one further placement. The actual
cost of the future placements may be different from the estimated cost
assumed in the projection.  These placements are for individuals with
very specific needs that require a higher level of security and/or care
from a staff group with a particular skill set/competence.  There are no
local NHS secure facilities for women, people with a learning disability
or people with neurodevelopmental disorder. This can necessitate an
UNPACs placement with a specialist provider which can be out-of-area. 
The nature of mental health UNPACs spend is that it is almost
exclusively on medium or long term complex secure residential
placements which are very expensive so a small change in placements
can have a high budgetary impact. Due to the complexity and risk
involved, transitions between units or levels of security can take many
months. Applications to approve a placement are made to the
Associate Medical Director for Mental Health who needs to be satisfied
that the placement is appropriate and unavoidable prior to this being
agreed. A new group has been established to review the UnPACS
budget and placements with a wider service representation. 
• Learning Disability Services – projected to underspend by £0.538m
(£0.011m adverse movement). This position is after recharging other
areas on a cost basis for two outwith authority placements which have
incurred additional costs in relation to usage of supplementary staffing
due to sustained enhanced observations. There is a risk in relation to
recovering this income as the two areas receiving the charges are
currently refusing to pay and legal advice is being sought.
54

Page 55

• Elderly Inpatients – projected overspend of £0.415m (£0.004m
adverse) due to the use of supplementary staffing.  There are several
patients who are on enhanced observations and bank costs remain
high. 
• MH Pharmacy – is projected to overspend by £0.585m (£0.099m
adverse) due to increased demand and cost of medicines. 
▪ Innovation Fund – projected underspend of £0.112m (no change) due
to slippage within some of the projects and not all of the funding has
been allocated. 
▪ Action 15 – projected online as any underspend will be carried forward
for use in 25-26.   
• The turnover target for vacancy savings for the Lead Partnership is held
within the Lead Partnership as this is a Pan-Ayrshire target.  There is a
projected over recovery of the vacancy savings target of £0.819m in
2024-25.  Further information is included in the table below: 
Vacancy Savings Target (£1.116m)
Projected to March 2025 £1.935m
Over/(Under) Achievement £0.819m
2.5 Children and Justice Services 
Children’s Services
Against the full-year budget of £44.045m there is a projected overspend of £1.134m
(2.6%) (£0.449m favourable movement) pre earmarking and the main variances are: 
a) Care Experienced Children and Young People is projected to overspend by
£1.369m (£0.352m favourable movement). The main areas within this are noted
below: 
• Following budget investment of £4m the children’s residential placements are
overspent by £1.539m based on 33 placements at month 4 and assumes a
reduction to 32 places by month 6. This demonstrates a reduction of 5 places
since the start of the financial year. There are a number of factors leading to
this challenging position: 
• We have 32 places available in our internal children’s houses, due to
demand these have been operating at 100% occupancy for some
time, leading to increased use of external placements where
residential care is required.
• The requirement to support Unaccompanied Asylum-Seeking
Children (UASC) under the National Transfer Scheme and to support
trafficked young people who have been identified in North Ayrshire.
55

Page 56

• A number of young people in residential care have requested
Continuing Care, whereby a young person can remain in their
placement until age 21.
• Where appropriate young people are placed to meet their educational
needs, the cost of Residential School Placements in the most cases
is shared 50/50 with Education services. 
Children’s Services are continuing to work with other services including
Education and Housing to address the challenges through the work of the
‘Brighter Pathways’ Programme Board and associated workstreams. This
forms part of the Transformation Plan which was approved at the March IJB. 
• Looked After and Accommodated Children (fostering, adoption, kinship etc)
is projected to be £0.728m underspent (£0.027m favourable movement). 
• Children with disabilities – there is a net projected overspend of £0.256m
(£0.132m adverse movement) across residential placements, direct
payments and community packages. 
• Residential respite – placements are overspent by £0.058m. These short-
term placements are used to prevent an admission to full time care or to avoid
placement breakdown. 
• Employee costs – are projected to overspend by £0.216m, largely due to
overspends in the children’s houses. 
b) Head of Service – is projected to underspend by £0.524m (£0.053m favourable
movement). This is made up a projected overspend due to the planned saving of
£0.233m in relation to the staff reconfiguration in the children’s houses which was
not achieved in 23-24 and this is offset by the grant funding in relation to
Unaccompanied Asylum-Seeking Children, which is projected to over-recover by
£0.819m and which covers costs incurred across a number of C&F service areas.   
c) C&F Health Team – is projected to overspend by £0.246m (£0.015m favourable)
mainly in relation to the Band 6 to 7 regrade for Health Visitors and the
progression of posts up the Band 7 scale. 
2.6 ALLIED HEALTH PROFESSIONALS (AHP) 
The non-employee costs element of the AHP services are projected to be on-line. 
All underspends in employee costs have contributed to payroll turnover. 
2.7 CHIEF SOCIAL WORK OFFICER 
There is a projected underspend of £0.012m mainly due to a delay in spend in the
Carers Strategy funding. 
2.8 MANAGEMENT AND SUPPORT 
56

Page 57

Management and Support Services are projected to underspend by £1.293m
(£0.068m adverse) and the main areas of underspend are:
• There is projected slippage on the LD and MH transition funding of £0.661m
due to delays in children transitioning into adult services and actual costs
being less than estimated.  This involves complex planning by services with
service users and families and can change over time based on assessed need
when moving into adult services.
• The 2024-25 budget included a budgeted deficit on the social care side of
£0.437m which is offset by a budgeted surplus of £0.437m on the health side
of the budget.   The net impact is neutral, but Appendix A shows this position
for each element.
• An over-recovery of payroll turnover of £0.500m for social care services and
an over-recovery of payroll turnover of £0.296m for health services as outlined
in the table below.   
The turnover targets and achievement for the financial year for Health and Social
Care services outwith the Lead Partnership is noted below: 
Social Care Health
Vacancy Savings Target (3.301m) (1.522m)
Achieved to March 2025 3.801m 1.818m
Over/(Under) Achievement 0.500m 0.296m 
The areas contributing to the health and social care vacancy savings are spread
across a wide range of services with vacancy savings being achieved in most areas.   
The partnership significantly over-achieved on turnover targets last financial year
which helped greatly to support the overall financial position.  The early projections
for 2024-25 indicate a reduction in the turnover being projected, which reflects a more
optimistic position for recruitment and reduced vacancies but clearly has an impact
on the ability to use this to offset overspends in other budget areas. 
As part of the recovery plan, the vacancy scrutiny group has been enhanced with the
Heads of Service and professional leads attending.  Each post is scrutinised and
filled only where deemed necessary with a recruitment freeze now implemented for
all non-essential posts. 
The turnover target for the North Lead Partnership for Mental Health services is
detailed within the Lead Partnership information at section 2.4. 
2.9 Savings Progress 
a) The approved 2024-25 budget included £10.290m of savings. 
BRAG Status Position at
Budget Approval
£m
Position at
Month 4
£m
Red - -
Amber 0.523 0.675
57

Page 58

Green 9.767 0.600
Blue - 9.015
TOTAL 10.290 10.290 
b) The main area to note is that the amber savings have increased as the care
home budget is currently projecting an overspend but this will be managed
into an online position. 
Appendix B provides an overview of those service changes which do have financial
savings attached to them and the BRAG status around the deliverability of each
saving. 
2.10 Budget Changes 
The Integration Scheme states that “either party may increase it’s in year payment to
the Integration Joint Board.  Neither party may reduce the payment in-year to the
Integration Joint Board nor Services managed on a Lead Partnership basis….
without the express consent of the Integration Joint Board.” Appendix C highlights
the movement in the budget position following the initial approved budget. 
Reductions Requiring Approval: 
Ref Description  Amount (£000)
1 Post to medical records (37) 
2.11 Pan Ayrshire Lead Partnership services and Large Hospital Set Aside 
Lead Partnerships: - The IJB position is adjusted to reflect the impact of Lead
Partnership services. The outturn for all Lead Partnership services is shared across
the 3 Partnerships on an NRAC basis. 
The outturn in relation to North Lead Partnership services is not fully attributed to the
North IJB as a share is allocated to East and South Partnerships; similarly, the impact
of the outturn on East and South led services is shared with North. At Month 4 the
MH lead partnership is projected to overspend by £0.658m (£0.215m NRAC share
for East and £0.188m for South). 
South HSCP (month 3 info) – projected overspend of £0.551m of which £0.204m will
be allocated to North. The variance is mainly due to an overspend of £0.512m in the
community store.  This includes the costs of replacing mattresses, repairs and
maintenance contract and equipment costs. There is also a projected overspend of
£0.069m in the continence service and an underspend £0.030m in the Family Nurse
Partnership.   
East HSCP - projected underspend of £0.208m (£0.176m favourable movement) in
total (of which £0.077m will be allocated to North). The main variances are: 
Allied Health Professions (Lead Partnership)
58

Page 59

There is a projected underspend of £0.431m on AHPs services hosted by East
Ayrshire for the current year, which mainly relates to staffing savings in
Physiotherapy / MSK and Podiatry services and is partially offset by increased
Orthotics costs. 
Primary Care and Out of Hours Services (Lead Partnership) 
There is a small projected overspend of £0.023m on the Primary Care Lead
Partnership budget and additional costs in Out of Hours services £0.371m, with work
ongoing to mitigate increased costs as far as possible over the course of the 2024/25
financial year and going forward, as well as additional Primary Care contracting and
support costs £0.024m. These additional costs are largely offset by a projected
underspend in Dental services totalling £0.219m, where staffing numbers are running
at less than establishment. Recruitment over the remainder of the financial year has
the potential to impact further on the projected outturn position at month 4. In addition,
there is a small saving on Primary Medical Services costs £0.152m. 
Prison and Police Healthcare (Lead Partnership) 
The £0.043m projected underspend at month 4 is largely due reduced staffing costs. 
Other Services (Lead Partnership) 
The £0.243m projected overspend is due to increased Area Wide Evening Services
costs, mainly due to additional staffing costs including high use of bank staff, which
will require to be addressed going forward. 
Set Aside: - Work has been undertaken with partnerships to progress and develop
set aside arrangements to fully implement the legislative requirement.  This includes
arrangements in relation to the use of Directions, Joint Commissioning Plans and
overall progression towards fair share allocations of resources. 
1. Further work has been undertaken through the Ayrshire Finance Leads group to
establish baseline resources for each partnership and how this compares to the
NRAC “fair share” of resources. Ayrshire Finance Leads have now agreed a
baseline methodology for set aside budgets which involves using the four full years
prior to the pandemic, 2016/17 – 2019/20 inclusive. 
The 2023/24 usage is now available as is Q1 of 2024/25 and these will be presented
to Ayrshire Finance Leads for validation. 
IJB
Baseline at
2022/23
prices (£)
East 26,215,888
North 35,007,962
59

Page 60

South 28,371,789
Total 89,595,639 
The annual budget for Acute Services is £432.3m.  The directorate overspent by
£11.2 million after 4 months. This was caused by overspends on agency medical
and nursing staff, together with drug expenditure including the New Medicines Fund,
equipment and supplies. These have been required due to the level of operational
pressure being experienced, in common with many other areas in Scotland. 156
additional unfunded beds remained open across both main hospital sites during
July.
There is a material underlying deficit caused by: 
• Unachieved efficiency savings
• Length of Stay (LoS) and emergency admission rates in NHS Ayrshire and
Arran acute hospitals are above the Scottish average.
• High expenditure on medical and nursing agency staff, high rates of absence
and vacancies causing service pressure.
• Delayed transfers of care and high acuity of patients.
The IJBs and the Health Board work closely in partnership to maintain service and
improve performance. Initial work has commenced to develop a joint strategic
commissioning plan for the provision of unscheduled care services, which will
outline these services will be delivered over the medium-term using the set aside
resources available. This will support a shift in the balance of care into the
community and support a reduction in the number of acute beds. 
2.12 FINANCIAL RISKS 
There are a number of financial risk areas that impact or may impact on the financial
position. 
• The recent announcements by Scottish Government in relation to public
sector finances and in-year spending reductions will impact on current and
future funding, including for 2024-25 pay awards, which have not yet been
settled for local government or NHS.
• Continued growing demand for services.
• Staff recruitment and retention challenges across a number of service areas.
• The provider market and the ongoing ability to source packages of care for
service users.
• The expectation that performance will continue to be maintained or improved
despite the significant resource challenges, for example the joint mission for
delayed discharge improvement.
• Ongoing delivery costs of Scottish Government policy directives, particularly
where these are not fully funded or inflation proofed.
• The ongoing review of the Integration Scheme.
• Progress with the work to develop set aside arrangements and the risk
sharing arrangements agreed as part of this.
60

Page 61

• The wider system financial challenges, especially the financial position of
NHS Ayrshire and Arran Health Board, their financial deficit and the risks
around further escalation in the national framework for financial escalation. 
North Ayrshire IJB have already discussed our position in relation to the
request for payment for delayed discharges last financial year.
• The underlying levels of overspend which are recurring into 2024-25 and may
impact on the Partnership’s ability to continue to sustain service levels in the
future.
• The IJB free general fund reserves are estimated to be fully utilised during
this financial year, leading to an increased risk of requiring additional in-year
financial contributions from NHS Ayrshire and Arran and North Ayrshire
Council to break even. 
• High risk areas of low volume / high-cost services areas e.g. Children’s
residential placements, Learning Disability care packages and complex care
packages; 
• Lead / hosted service arrangements, including managing pressures and
reporting this across the 3 IJBs.
• The impact on Lead Partnership and acute services from decisions taken by
other Ayrshire areas.
• The use of supplementary staffing for enhanced observations across a
number of service areas.
• The use of high-cost agency staff to support frontline service delivery in areas
where there are recruitment challenges.
• Agenda for Change Pay Reform programme – including Nursing Band 5-6 re-
grade, protected learning time and reduction to the working week. Non-
recurring funding has been provided to meet costs associated with this but it
is unclear whether this will be sufficient. 
These risks will continue to be monitored during 2024-25. 
2.13 RESERVES 
The IJB reserves position is summarised in the table below. 
General Fund
Reserve Earmarked Reserves
Total 
Unearmarked  External
Funding                      HSCP 
£m  £m £m £m
Balance – 1 April 2024 0.357  3.379 1.774 5.510
Anticipated Drawdown (0.357)  (3.379) (1.202) (4.938)
Balance – 31 March 2025 -  - 0.572 0.572 
The £1.774m HSCP earmarked reserve relates to the Service Redesign and Change
Fund; of this total only £0.096m currently remains uncommitted with the balance
being committed to investment in an early intervention approach within Children and
Families social work and supporting the delivery of the transformation programme
across 2024-25 and 2025-26. 
61

Page 62

Further detail on the reserves is given in Appendix D. 
2.14 Financial Recovery Plan 
The IJB set a balanced budget for 2024/25 on 14th March 2024. This did not require
any draw on reserves but did include the approval of £10.290m of savings to achieve
financial balance. 
Following the finalisation of the 2023/24 outturn position, the IJB agreed some initial
recovery actions at the meeting in June. In line with the requirements of the
integration scheme, work has continued to develop the financial recovery plan and
identify further targets for financial improvements. The current plan is outlined in full
at Appendix E. 
There has been progress towards some of the targets, and these are already
reflected in the current projected outturn of £6.697m overspend. Further work is
required to deliver on the balance of these targets as well as the additional targets
which have now been identified. 
Services will work towards implementing the recovery plan to deliver on these cost
reduction targets while carefully managing the level of risk. This will include the
preparation of equality impact assessments. 
It is recognised that there needs to be further savings identified to move towards a
breakeven position. Any decisions to implement changes which have significant
impact on service delivery and the wider system will be discussed at the Finance
Working Group before being brought back to the IJB for further approval as part of
the financial recovery plan. A summary of the Care at Home plan is included at
Appendix F. 
MANAGEMENT ACTIONS/CONTROLS: 
Other management actions which have been implemented include: 
• Review of expenditure authorisation levels across the Partnership and
escalation of specific decisions to senior officers. In particular, a new
governance group has been introduced, involving the Director and Heads of
Service, to oversee the agreement of higher value packages of care (above
£40,000 per annum).
• Staff communication in relation to discretionary/non-essential spend.
• Review of temporary posts and robust vacancy management/approval.  The
vacancy scrutiny group now has representation from all of the Heads of
Service and a recruitment freeze will be implemented for all but essential
frontline posts.
• Restrictions on all but essential overtime working.
• Ongoing review of future year savings or transformation programmes to
identify scope for acceleration.
• Maximise opportunities from the recently reopened Independent Living Fund
(ILF) Scotland. 
62

Page 63

GOVERNANCE: 
• In order to facilitate greater scrutiny of the financial position and the delivery
of the financial recovery plan during 2024/25, the IJB agreed at the June
meeting to establish a ‘Finance Working Group’, chaired by the IJB Vice Chair.
The Director and Heads of Service will be members of the group. This will
meet monthly to facilitate increased oversight and scrutiny of the financial
position and transformation programme as well as detailed budget planning
for future financial years. Meetings have now been scheduled to the end of
the year and the first meeting took place on 9th September. 
• Strengthened support from Finance Team to front line services and increased
engagement with Heads of Service and Senior Management Teams, including
line by line reviews of all budget areas.  Review and enhancement of
frequency and level of financial information provided to support oversight and
decision making in line with financial constraints, with an added focus on areas
of underspend to maximise opportunities to delay or stop spend and contribute
to the overall financial challenge. 
INTEGRATION SCHEME 
The Integration Scheme describes the required approach where there is a projected
overspend: 
The Chief Officer will deliver the Outcomes within the total delegated resources (paid
and Set Aside) and where there is a forecast overspend against an element of the
operational budget, the Chief Officer, the Chief Finance Officer of the Integration
Joint Board and the appropriate finance officers of the Parties must agree a recovery
plan to balance the overspending budget, which recovery plan shall be subject to the
approval of the Integration Joint Board. If the recovery plan is not successful the
Parties will consider making interim funds available based on the agreed percentage 
contribution for joint responsibilities, as outlined above, with repayment in future
years on the basis of a revised recovery plan agreed by the Parties and Integration
Joint Board. 
There is an increasing risk to achieving financial balance during 2024-25, the
projected outturn position is summarised below with the residual risk following
already identified financial improvement actions and illustrates the current estimated
risk exposure to the IJBs funding partners: 
Split 
TOTAL Health/NHS
AA
Social
Care/NAC
Projected Overspend @ mth4 £6.697m £0.857m £5.840m
Less Financial Recovery Plan Projections £3.702m £0.369m £3.333m
Residual Risk £2.995m £0.488m £2.507m 
3.  PROPOSALS 
3.1 Anticipated Outcomes
63

Page 64

Continuing to closely monitor the financial position will allow the IJB to take corrective
action where required to deliver services in 2024-25 from within the available
resource, thereby limiting the financial risk to the funding partners. 
The transformational change programme will have the greatest impact on the
financial sustainability of the partnership, the IJB require to have a clear
understanding of progress with the delivery of the transformation plan. 
3.3 Measuring Impact 
Ongoing updates to the financial position will be reported to the IJB throughout 2024-
25. 
4. IMPLICATIONS  
4.1 Financial
The outturn is an overall year-end overspend of £6.697m (2.1%). The report outlines
the main variances for individual services.  There IJBs unearmarked reserve balance
is projected to be zero by the end of the financial year and there is an ongoing risk in
relation to the £2.995m of the overspend where financial recovery improvement
actions require to be identified.  This current position poses a financial risk to North
Ayrshire Council and NHS Ayrshire and Arran. 
4.2 Human Resources
The report highlights vacancy or turnover savings achieved during the year. Services
will review any staffing establishment plans and recruitment in line with normal
practice when implementing service change and reviews as per agreement with the
IJB.  Tight vacancy scrutiny management arrangements are in place for the HSCP. 
4.3 Legal
None. 
4.4 Equality/Socio-Economic
None. 
4.5 Risk
Para 2.12 highlights the financial risks.
The report falls in line with the agreed risk appetite statement which is a low-risk
appetite in respect to adherence to standing financial instructions, financial controls
and financial statutory duties and a high-risk appetite in relation to finance and value
for money.
The ‘financial viability of the HSCP’ risk on our strategic risk register has increased
the risk score to reflect the 23/24 outturn and current projected 24/25 overspend. 
4.6 Community Wealth Building
None. 
4.7 Key Priorities
The ability to deliver on our strategic priorities may be compromised due to the
greater financial risk faced in 2024-25 and the increased focus required on financial
rather than service improvement. This will be kept under close scrutiny throughout
64

Page 65

2024-25. If we are unable to successfully develop a financial recovery plan to achieve
financial balance, consideration may be given to revising the strategic commissioning
plan. 
5. CONSULTATION
5.1 This report has been produced in consultation with relevant budget holders and the
Partnership Senior Management Team. 
5.2 The IJB financial monitoring report is shared with the NHS Ayrshire and Arran
Director of Finance and North Ayrshire Council’s Head of Finance after the report
has been finalised for the IJB. 
Caroline Cameron, Director 
Author – Paul Doak, Head of Finance and Transformation
Eleanor Currie, Principal Manager Finance 
[pdoak@north-ayrshire.gov.uk/eleanorcurrie@north-ayrshire.gov.uk]- 
65

Page 66

PUBLIC INFORMATION
2024-25 Budget Monitoring Report–Objective Summary as at 31st July 2024                                                                 Appendix A 
Budget Outturn 
Over/
(Under)
Spend
Variance
Budget Outturn 
Over/
(Under)
Spend
Variance
Budget Outturn 
Over/
(Under)
Spend
Variance
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
COMMUNITY CARE AND HEALTH 71,300 76,257 4,957 18,816 19,908 1,092 90,116 96,165 6,049 5,987 62
: Locality Services 30,392 31,227 835 5,366 5,410 44 35,758 36,637 879 795 84
: Community Care Service Delivery 36,732 40,208 3,476 0 36,732 40,208 3,476 3,447 29
: Rehabilitation and Reablement 2,099 2,116 17 0 2,099 2,116 17 35 (18)
: Long Term Conditions 987 997 10 9,459 10,373 914 10,446 11,370 924 927 (3)
: Community Link Workers 358 358 0 0 0 0 358 358 0 1 (1)
: Integrated Island Services 732 1,351 619 3,991 4,125 134 4,723 5,476 753 782 (29)
MENTAL HEALTH SERVICES 34,339 34,858 519 73,192 73,742 550 107,531 108,600 1,069 591 478
: Learning Disabilities 25,723 26,640 917 556 555 (1) 26,279 27,195 916 596 320
: Community Mental Health 6,575 6,165 (410) 1,739 1,738 (1) 8,314 7,903 (411) (400) (11)
: Addictions 2,041 2,053 12 1,899 1,899 0 3,940 3,952 12 15 (3)
: HBCCC 0 0 0 353 247 (106) 353 247 (106) (141) 35
: Lead Partnership Mental Health NHS Area Wide 0 0 0 68,645 69,303 658 68,645 69,303 658 521 137
CHILDREN & JUSTICE SERVICES 39,130 40,018 888 4,915 5,161 246 44,045 45,179 1,134 1,583 (449)
: Irvine, Kilwinning and Three Towns 3,054 3,086 32 0 0 0 3,054 3,086 32 25 7
: Garnock Valley, North Coast and Arran 3,206 3,249 43 0 0 0 3,206 3,249 43 40 3
:Intervention Services 1,716 1,715 (1) 0 0 0 1,716 1,715 (1) 7 (8)
: Care Experienced Children & Young people 27,185 28,554 1,369 0 0 0 27,185 28,554 1,369 1,721 (352)
: Head of Service - Children & Families 1,082 558 (524) 0 0 0 1,082 558 (524) (471) (53)
: Justice Services 2,472 2,472 0 0 0 0 2,472 2,472 0 0 0
: C&F Health Team 415 384 (31) 4,203 4,449 246 4,618 4,833 215 261 (46)
: Lead Partnership NHS Children's Services 0 0 0 712 712 0 712 712 0 0 0
CHIEF SOCIAL WORK OFFICER 1,561 1,573 12 0 0 0 1,561 1,573 12 (62) 74
PRIMARY CARE 0 0 0 53,109 53,109 0 53,109 53,109 0 (42) 42
ALLIED HEALTH PROFESSIONALS 0 10,306 10,306 0 10,306 10,306 0 0 0
MANAGEMENT AND SUPPORT COSTS 9,038 8,500 (538) 4,407 3,652 (755) 13,445 12,152 (1,293) (1,361) 68
FINANCIAL INCLUSION 970 972 2 0 0 0 970 972 2 (13) 15
OUTTURN ON A MANAGED BASIS 156,338 162,178 5,840 164,745 165,878 1,133 321,083 328,056 6,973 6,683 290
Over/
(Under)
Spend
Variance at
Period 3
Movement in  
variance
from Period
3
TOTAL
Partnership Budget - Objective Summary
Council Health
2024/25 Budget
66

Page 67

PUBLIC INFORMATION 
Budget Outturn 
Over/
(Under)
Spend
Variance
Budget Outturn 
Over/
(Under)
Spend
Variance
Budget Outturn 
Over/
(Under)
Spend
Variance
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Return Hosted Over/Underspends East 0 0 0 0 (215) (215) 0 (215) (215) (171) (44)
Return Hosted Over/Underspends South 0 0 0 0 (188) (188) 0 (188) (188) (149) (39)
Receive Hosted Over/Underspends South 0 0 0 0 204 204 0 204 204 204 0
Receive Hosted Over/Underspends East 0 0 0 0 (77) (77) 0 (77) (77) (12) (65)
OUTTURN ON AN IJB BASIS 156,338 162,178 5,840 164,745 165,602 857 321,083 327,780 6,697 6,555 142
Over/
(Under)
Spend
Variance at
Period 3
Movement in  
variance
from Period
3
Partnership Budget - Objective Summary
2024/25 Budget
Council Health TOTAL
67

Page 68

PUBLIC INFORMATION
2024-25 Savings Tracker          Appendix B 
Social Care:
Description
Deliverability
Status at
budget
setting
Deliverability
Status at
Month 4
2024/25
Saving
Description of the Saving
Children, Families & Criminal Justice
Service redesign Amber Blue 0.123 Restructure areas of specialist service provision including
substance use and corporate parenting, embedding the roles and
functions of those teams within our locality-based early intervention
approaches and strategic planning including engagement.
Community Care & Health
Review of Day Care provision Amber Blue 0.100 Carry out a review and streamline day care provision.
Sensory Impairment Team Green Blue 0.062 Remove the dedicated management post and realign the team into
core social work teams.
Care Home places Green Amber 0.375 Reduce the number of funded care home places by 15, leaving
budgetary provision for 765 places at average cost.
Charging for community alarm provision
to sheltered housing tenants
Amber Amber 0.200 Introduce a charge for community alarm provision in council
sheltered housing units to ensure an equitable approach across all
housing tenures.
Montrose House capacity Green Blue 0.111 Restrict the capacity at Montrose House care home to the current
level of residency.
Voluntary Early Release Green Blue 0.174 Recurring savings achieved by the release of back-office staff
through the council's voluntary early release scheme.
Carers Strategy funding Green Blue 0.384 Utilise the remaining Carer's Strategy funding to invest in respite
provision and short breaks for carers and to support existing
investments in services which support unpaid carers.
Increase to charging Green Blue 0.131 Increase charges for non-residential care by 10% and charges for
residential care by 5%
Remove vacant posts Green Blue 0.280 Remove a number of vacant posts across support services.
Employers' superannuation contributions Green Blue 7.238 Align the budget to the new employer superannuation contribution
rates from 1st April 2024.
Payroll Turnover Green Blue 0.077 Increase targets for payroll turnover through the recruitment
process.
TOTAL SOCIAL CARE SAVINGS 9.255
North Ayrshire Health and Social Care Partnership
2024/25 Savings
Support Services and Partnership-wide savings
68

Page 69

PUBLIC INFORMATION 
Health:
Description
Deliverability
Status at
budget
setting
Deliverability
Status at
Month 4
2024/25
Saving
Description of the Saving
Hospital Based Complex Continuing
Care (HBCCC) provision
Green Green 0.500 Align the budget to the level of ongoing need for HBCCC provision.
Increase recharge to East Ayrshire for
beds at Woodland View
Green Blue 0.021 Apply an inflationary increase to the recharge to East Ayrshire
HSCP.
Community Recovery and Rehab
provision
Amber Amber 0.100 Review and streamline a range of current provisions to remove
duplication.
Enhanced ICT Green Green 0.100 Carry out a review of the service delivery model and release
recurring staffing savings.
Payroll Turnover Green Blue 0.314 Increase targets for payroll turnover through the recruitment
process.
TOTAL HEALTH SAVINGS 1.035
TOTAL NORTH HSCP SAVINGS 10.290
69

Page 70

PUBLIC INFORMATION
2024-25 Budget Reconciliation               Appendix C 
COUNCIL Period 
Permanent
or
Temporary
£'m
Initial Approved Budget     156.190
Adjustments to baseline     (0.574)
Less Resource Transfer 23/24     (24.640)
Revised Budget     130.976
Resource Transfer 24/25 1-3 P 24.861
Realign Girfec Team To Connected
Communities 1-3 P (0.073)
ICT Budget Transfers 1-3 P (0.006)
CJSW Funding 2425 1-3 T 0.053
Children’s Living Wage Allocation 1-3 T 0.525
Roundings 1-3   0.002
Social Care Budget Reported at Month 3 156.338
HEALTH Period 
Permanent
or
Temporary
£'m
Initial Budget exc set aside     157.894
Add Resource Transfer 23/24     24.640
Month 10-12 Adjustments and adjusting for the
full year impact of part years amounts and
temporary funding.    
(0.033)
Revised Budget   P 182.501
Add resource Transfer 24/25     (24.861)
North Superannuation 24/25 uplift 1   1.134
MH: Anticipate Hollybush Combat Stress 24/25 1   1.424
MH: Anticipate Delivery of Veteran Funding 24/25 1   0.105
MH: Anticipate Perinatal MH, Infant MH (inc MNPI)
24/25 1   0.750
Training grade ADJ - April 1   0.063
Pecos Nurse Post  1   (0.018)
Script Switch To Pharmacy 1   (0.002)
Breastfeeding Pay Award - South 2   0.005
Nest - South 2   0.066
24-25 Foxgrove North 2   0.033
24-25 Breast Feeding - North 2   0.005
24-25 Huntingtons North 2   0.005
24-25 NEST North 2   0.066
Phlebotomy Admin Returned 2   0.005
70

Page 71

PUBLIC INFORMATION
23-24 - 50% North Share to East - Tier 3 Weight
Management 2   (0.077)
24-25 North Share to East - Tier 3 Weight
Management 2   (0.022)
Anticipate ADP Afc Pay Uplift 3   0.091
Anticipate ADP Drug Prevalence 3   0.084
Anticipate ADP Lived & Living Exp 3   0.013
Anticipate ADP Mat 3   0.250
Anticipate ADP National Mission 3   0.296
Anticipate ADP Residential Rehab 3   0.134
Anticipate ADP Whole Family Approach 3   0.094
Training Grade Adj - Jun 3   (0.054)
Prescribing (Ambush) North Rx 3   1.573
Prescribing (Ambush) North Rx Cres 3   (1.477)
24-25 North Budget Paper - Office 365 (to East) 3   (0.073)
24-25 North Budget Paper - Prison Pharm Contract
(to East) 3   (0.093)
South Mat Funding - Psychiatrist 3   0.029
Hd198: Early Intervention In Psychosis/ Body
Image And Social Media Resource 3   0.242
Hd203: Digital Mental Health Programme Licence
& Support 3   0.005
Reduction to the Working Week (mth 2 - 4)  4  0.105
Post to medical records 4  (0.037)
HD107: breast Feeding project funds 4  0.056
BBV 4  0.280
Anticipated budgets assumed in the report but not
yet allocated  4   2.045
Health Budget Reported at Month 4 164.745
TOTAL COMBINED BUDGET      321.083 
71

Page 72

PUBLIC INFORMATION
24-25 IJB Reserves Position      Appendix D 
Area of Reserves
Balance at
31 March
2024
2024-25
Anticipated
Draw Downs
Projected
Balance at
31 March
2025
: Alcohol & Drug Partnership 641 (641) 0
: Mental Health Action 15 57 (57) 0
: Service Redesign / Challenge Fund 1,774 (1,202) 572
: Community Living Change Fund 377 (377) 0
: Family Wellbeing Fund 1,313 (1,313) 0
: Wellbeing Fund 50 (50) 0
: Breast Feeding Network 26 (26) 0
: MH Recovery and Renewal 546 (546) 0
: Buvidal 23 (23) 0
: Brooksby 5 (5) 0
: Cossette Funding 4 (4) 0
: Expansion of Primary Care Estates 55 (55) 0
: GP Premises Improvements - tranches 1 and
2 63 (63) 0
: Mental Health Wellbeing in Primary Care 81 (81) 0
: Dental Practice Improvement 29 (29) 0
:Appropriate Adult Scheme 2 (2) 0
:Adult Tier 3 Weight Management Service 19 (19) 0
: Phlebotomy 22 (22) 0
: LD Health Checks 66 (66) 0
Total Earmarked 5,153 (4,581) 572
Unallocated General Fund 357 (357) 0
General Fund 5,510 (4,938) 572
Earmarked Funds
72

Page 73

PUBLIC INFORMATION
Financial Recovery Action Plan          Appendix E 
FINANCIAL RECOVERY PLAN £m £m £m
Projected Overspend at Month 4 6.697
SERVICE AREA
Cost
reduction
target
Achieved in
projected
outturn
Still to be
achieved Target set?
Health and Community Care
Reduce care home placements in line with
budget saving (0.700) (0.086) (0.614) June IJB
Reduce CAH capacity/delay recruitment/in-
house efficiencies (0.850) 0.000 (0.850) June IJB
Community Wards - reduce supplementary
staffing and review bed capacity (0.500) (0.247) (0.253) June IJB
MH and LD (North Ayrshire)
Freeze adult community support approvals
outwith transitions 0.000 0.000 0.000 June IJB
Respite provision - ensure use of in-house
capacity is maximised 0.000 0.000 0.000 June IJB
HBCCC mitigation plan (0.106) (0.106) 0.000 August IJB
MH and LD (Lead Partnership)
Ward staffing (adults/elderly inpatients) (0.300) 0.000 (0.300) August IJB
Psychiatry (use of agency) (0.312) (0.312) 0.000 August IJB
CEDS/CAMHS (0.202) (0.202) 0.000 August IJB
North Ayrshire share (38.6%) (0.314) (0.198) (0.116)
Children and Families
Reduce children's external placements -
early reduction from Brighter Pathways work (0.500) (0.500) 0.000 June IJB
Additional target re-residential placements (0.500) (0.229) (0.271) August IJB
Additional target re-residential placements (0.225) 0.000 (0.225) September IJB
Reduce investment in C&F social work via
service redesign fund (0.300) 0.000 (0.300) September IJB
Cross Partnership
Vacancy management and temporary posts (0.500) 0.000 (0.500) June IJB
Use of remaining reserve balance (0.357) 0.000 (0.357) August IJB
Review of earmarked reserves (0.216) 0.000 (0.216) September IJB
Target Achieved Outstanding
(5.068) (1.366) (3.702)
Remaining projected overspend 2.995
73

Page 74

PUBLIC INFORMATION
Appendix F - Care at Home Recovery Plan 
1. Situation  
The overspend on Care at Home is reflective of an increase in the overall capacity
and complexity of need within the service, alongside a rise in service costs, as we
strive to meet the growing level of demand in our communities and to support hospital
discharge(s).  The Care at Home Service in North Ayrshire has seen a 50% increase
in the number of annual care visits in the last 4 years.   
Below summarises the budget and spend position for Care at Home Services since
2019.   
The Care at Home budget has increased significantly since 2019-20 with an overall
increase of £9.8m over that period, however most of this increase is directly related
to pay inflation with the only additional funding for additional capacity being £3.4m to
support with winter pressures.  The Care at Home budget has been relatively static
in real terms against a backdrop of a significant increase in demand. 
The Care at Home service has a budget of £30.061m for 24/25.  This is inclusive of
Care at Home services delivered via SDS Option 2 and 3.  Currently this is projecting
an overspend of £3.255m for 2024/25 financial year.   
As part of the overall Financial Recovery Plan for the IJB there is a requirement for
a reduction in current spend in-year, with a move to working towards delivering
services within budget thereafter.  A £1m savings target was identified for the Care
at Home service to deliver in 2024-25. 
74

Page 75

PUBLIC INFORMATION
2. Background  
Self-Directed Support is the way that care and support is delivered in Scotland,
providing people with options, choice and control.  From 2019 to 2023, the landscape
for Care at Home delivery in North Ayrshire has been very fragile with 5 Care at
Home providers exiting the market for the provision of care in an unplanned basis. 
In July 2024 the delivery of Care at Home supports in North Ayrshire, via Self
Directed Support Option 3, moved to a fully inhouse model.  This change in the way
care is delivered was reflective of a number of factors including quality and the safe
delivery of care and support. 
Currently there are over 2,000 people in receipt of care and support via Care at
Home, with 92% receiving services through the Partnership’s inhouse Care at Home
service.  The Partnership utilises eligibility criteria to deploy its available resources,
with priority given to those adults with the greatest need. 
Care at Home supports are provided across the 4 mainland localities in North
Ayrshire, and on the islands of Arran and Cumbrae.  Since 2020, to date, there has
been a 40% increase in the planned hours of care delivered by the inhouse Care at
Home service, with a 50% increase in the individual number of care visits provided
over this same period. Staffing levels for the Partnership’s inhouse Care at Home
service have also increased over this same period by 50% from 653 contracted staff
in 2020 to 981 in August 2024. 
Whilst the growth in the Partnership’s Care at Home service is evident, demand for
Care at Home supports has risen by around 30% from pre pandemic levels.  Whilst
there is robust application of criteria to access services, and use of initiatives such
as reablement designed to only provide shorter term supports and to reduce levels
of dependency, social work and service delivery teams report significant changes in
the complexity of need required in supporting people in the community.  This is
demonstrated by the Job Evaluation and regrading of the Partnership’s Care at Home
Assistant role in 2023, which reflected the change in the role and the skills required
to provide more complex and intensive community Care at Home supports. 
Unfortunately, Health and Community Care teams continue to manage a significant
waiting list for community and hospital referrals which is a result of aforementioned
increase in referral activity and complexity of need. Given the waiting list for supports,
and levels of unmet need, a priority of need is applied to those who are waiting
supports – this prioritises people with care needs associated with end-of-life care,
public protection and hospital discharges.  Levels of unmet need can fluctuate and
are influenced by peaks in demand.   
Below illustrates the priority of need framework used by Care at Home services to
prioritise demand, unmet need and waiting lists from the Community and Hospital: 
75

Page 76

PUBLIC INFORMATION 
Positively, community unmet need has reduced since December 2023 when 193
people in the community were awaiting a new package of care, with 166 waiting as
at August 2024.  Levels of delayed discharge associated with Care at Home had
shown signs of improvement earlier in 2024, however this improvement wasn’t
sustained and as at reporting in August 2024, 24 people were a delayed discharge
awaiting a package of care.  Overall, 76% of unmet need for care at home is for
people waiting in the community for care. 
The Partnership also provides a Community Alarm and Telecare service to over
4,000 people across Ayrshire.  The alarm service generates around 450k activations
on an annual basis with requests for support directed to identified contacts and,
where appropriate, to the Partnership’s responder service who provide approximately
6,000 physical responses to North Ayrshire service users on a monthly basis.  The
Community Alarm and Telecare service is in the process of transitioning from
analogue to digital technology. 
3. Plan 
As part of the financial recovery plan, targeted savings for the remainder of the
financial year 2004-25, have been identified from the Care at Home service.  The
vast majority of the service cost is workforce and any reduction in workforce will
inevitably result in reduced service capacity. 
The required service changes include a reduction in the inhouse workforce (circa
1,062 weekly hours), reduction in Self Directed Support (Option 2) spend and actions
related to the management of spend and approval of additional staffing costs linked
to vacancies and sickness absence.  It is proposed that workforce changes will be
achieved by natural turnover and a targeted recruitment freeze, alongside careful
future targeted recruitment activity to maintain safe care delivery.
76

Page 77

PUBLIC INFORMATION 
The planned reduction is estimated to deliver an in-year 2024-25 reduction of
£0.850m against an original target of £1m, this is deemed to be the maximum
reduction which can safely be delivered in-year. 
The reduction in Care at Home workforce will result in an overall reduction in Care
at Home capacity within the service.  Whilst efforts will be made to minimise the
impact of this and to manage any resultant risks and challenges.   
A summary of these is provided below: 
Risks/Impacts 
• Reduction in capacity will reduce the volume of Care at Home supports which
the Partnership can provide and may result in longer waiting times to receive
care
• A disproportionate impact on people awaiting services in the community as
we continue to prioritise urgent referrals and hospital discharge
• Reduction in capacity may result in increased delays in people being able to
access Care at Home supports, both from the community and to support
hospital discharge - approximate increase to the waiting list(s) combined of 56
people (3%) however this may vary dependent on hours/care requirements
• Impact on other people and services – for example length of stay in hospital,
access to community rehab beds, requirement for access to long term care
settings
• Increased reliance on informal supports and carers
• The service may be less flexible/responsive to critical care requests
• Seasonal/Winter responsiveness
• Greater risk of workforce pressures
• There will not be the same level of capacity to absorb and respond to any
potential future unplanned care provider market issues 
Whilst the above outlines the potential impact of this change and reduction in care
capacity, the below are a range of management mitigations either in place or
proposed to reduce this and to manage risk. 
Mitigations 
• Continue to follow the existing priority of need framework which ensures those
most in need of the service will be prioritised
• Weekly unmet need oversight and assurance group, which includes
arrangements for how service users are contacted whilst they wait
• Recruitment to 6-month reablement lead to re-establish and promote
reablement service provision
• Reablement Service Access pilot expansion
• Consider wider ‘access to service’ opportunities for demand management
• Care Monitoring System review to maximise efficiency in existing service
delivery
• Programme of Care at Home reviews for existing users
77

Page 78

PUBLIC INFORMATION
• Scaling up use of technology and Community Alarm/Telecare
• Closely monitor absence and vacancy levels on a weekly basis
• Continue to recruit to casual workforce to promote and develop contingency
options
• Refresh service wellbeing at work strategy to minimise staff absence levels
through sickness
• Protect and promote the Community Alarm and Telecare Service, particularly
to those service users awaiting a service 
78

Page 79

PUBLIC INFORMATION
Bank and Agency Costs to Month 4      Appendix G 
1) NHS
4863
(Registered)
4864
(Unregistered)
4853
(Registered)
4854
(Unregistered) TOTAL
AAC074 NORTH CORE SLT ADULT 5,412 5,412
AAC403 WARD 1 WOODLANDS VIEW 25,510 137,942 163,452
AAC406 WARD 2 WOODLANDS VIEW 15,759 93,103 108,861
AAC410 ACH REDBURN REHAB WARD NRS 1,587 39,712 41,299
AAC412 ACH DOUGLAS GRANT REHAB WD NRS 6,446 33,955 40,400
AAD401 WARD 3 WOODLANDS VIEW NURSING 17,386 117,487 447 135,320
AAD402 WARD 4 WOODLANDS VIEW NURSING 21,871 101,551 185 123,607
AAH047 NEW CLONBEITH NURSING(JURA) 51,193 34,734 85,927
AAH415 WVIEW THE GLEN ECT 1,611 1,611
AAH417 WVIEW WARD 10 ACUTE MH NRS 22,585 31,444 54,029
AAH423 WVIEW WARD 8 ACUTE MH NRS 10,300 303,301 251 313,852
AAH460 WARD 5 WOODLANDS VIEW 5,940 9,978 15,919
AAH466 WVIEW WARD 7B REHAB MH NRS 2,103 2,103
AAH492 NEW DUNURE NURSING(CLONBEITH) 17,669 56,237 73,905
AAT001 TRINDLEMOSS 26,773 46,783 73,556
AAW047 ARRAN HOSPITAL NURSING 11,398 16,007 5,717 33,122
ACN004 PACKAGE OF CARE (P) - CY 10,198 10,198
ACN012 PACKAGE OF CARE (P) - AMG 18,187 18,187
ACN013 PACKAGE OF CARE (P) - LMO 3,368 3,368
ACP003 NC POC TEAM 3 966 966
ACA412 CAMHS UNSCHEDULED CARE 1,703 1,703
ACF002 EARLY YRS-C/F TEAM 2 290 290
ACN047 ARRAN DN 235 235
ADN000 THREE TOWNS DN 4,284 161 4,446
ADN033 IRVINE DN 9,597 9,597
ADN042 NORTH WEST COAST DN 235 99 334
ADN075 GARNOCK VALLEY DN 38,464 38,464
ADN080 NORTH DN TEAM LEADERS 3,360 3,360
ALA047 LADY MARGARET NURSING 5,935 2,012 7,947
AMA408 PREVENTION + SERVICES SPT TEAM 1,481 1,481
AML102 MH UNPACS (PRIVATE) 0 0
AML146 LD HEALTH CHECKS 51,594 51,594
AML392 NORTH CLDT 157 157
AML402 LDS MANAGEMENT 2,129 2,129
AML500 MHS INPATIENT MGT 13,137 13,137
AMN412 CMHT NURSING-NORTH AYRSHIRE 6,609 6,609
AMN415 WVIEW WARD 7C FORENSIC REHAB N 1,950 45,193 47,143
AMN419 DAY ACTIVITIES TEAM 227 227
AMN425 INTENSIVE COMMUNITY NURSING TEAM 8,845 8,845
AMN431 ADULT MENTAL HEALTH LIASION TEAM 2,295 2,295
AMN433 PCMHT NORTH 1,663 1,663
AMN446 WVIEW WARD 6 LOW SECURE NRS 27,425 79,182 106,607
AMN454 WARRIX AVE 6,071 7,342 13,413
AMN468 ACTION 15 - ADULT LIAISON 2,951 2,951
ANU632 ICFN - COMMUNITY PHLEBOTOMY 5,860 5,860
AWV438 WVIEW WARD 7A LD A+T NRS 5,532 211,353 250 217,136
AXC407 WVIEW WARD 9 ACUTE MH NRS 16,258 54,635 70,894
AXC418 WVIEW WARD 11 ACUTE MH NRS 35,370 129,107 257 164,734
TOTAL 477,553 1,603,525 5,878 1,391 2,088,346
2) SOCIAL CARE
Agency Cost
Montrose House 252,121       
Acm - Irvine 1,188          
Mh Acm 15,895        
Ld Acm 7,826          
TOTAL 277,030       
Bank Agency
79

Page 80

80

Page 81

NORTH AYRSHIRE COUNCIL 
29 October 2024 
Cabinet 
Title:    Capital Programme Performance to 31 August 2024 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2024/25. 
Recommendation:  That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 31
August 2024; and (ii) the forecast expenditure to 31 March
2025; and
(c) approve the virement proposal noted within the HRA
programme detailed in appendix 2. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2024/25 to 2033/34 was
approved by Council on 28 February. The Housing Revenue Account (HRA) Capital
Investment Programme 2024/25 sits within the updated HRA Business Plan and was
approved by Council on 14 February 2024. 
1.2  This report identifies the current programme for 2024/25, taking account of adjustments
made to the initial budgets. The report presents the revised budgets at 31 August 2024
(Period 5) and forecast expenditure to 31 March 2025. 
1.3  At Period 5 the General Fund is forecasting a net breakeven position against a revised
budget of £129.057m. The HRA is forecasting a projected underspend of (£0.408m)
against a revised budget of £52.201m. 
1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £0.769m, including additional Scottish Government
funding in relation to the Road Safety Improvement and Nature Restoration
programmes and additional SUSTRANS funding for the Fairlie Coastal Path. 
1.5 Reviews of individual project plans have identified a number of adjustments to the
current profiles. As a result, £1.911m has been accelerated to 2024/25 from future
years. This has been partly offset by the reprofiling of (£1.757m) for delivery in 2025/26
and beyond. 
Agenda Item 5
81

Page 82

1.6 Within the HRA, additional prudential borrowing of £0.530m has been identified in
relation to the Council house buy-back programme to accommodate Ukrainian
Displaced People. 
1.7 In addition, a review of delivery timescales has identified a requirement to accelerate
£10.054m of expenditure to 2024/25 from future years. This is partly offset by the re-
profiling of (£4.510m) for delivery in 2025/26 and beyond.   
1.8 Ongoing uncertainty arising from inflationary pressures and other externalities continue
to impact on tender returns, the cost of materials and the cost of borrowing. Financial
risks have been identified across a number of high value projects, including the Upper
Garnock Flood Protection Scheme, Moorpark Primary School, Ardrossan Harbour
Landside works and Ardrossan North Shore development, incorporating the new
campus, however, full quantification of these risks remains an ongoing process. Council
has provided for a degree of mitigation within the overall 10-year General Services
Capital Investment Programme and the HRA Capital Investment Programme, with
significant additional revenue supports identified within the 2024/25 to 2026/27 General
Services Revenue budget. Projects will continue to be monitored closely with cost
increases met initially from the additional flexibility built into the programme. However,
any requirement for further borrowing not met from a funding source will be a matter for
Council to consider. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2024/25 General Services budget:  
General Services Capital  2024/25
£ million
Budget as at 30 June 2024 128.134
Changes to Funding 0.726
Other Revisions to the Programme 0.043
Revised Budget 128.903
Alterations to phasing of projects 2024/25 to 2025/26 (1.757)
Alterations to phasing of projects 2025/26 to 2024/25 1.911
Budget as at 31 August 2024 129.057 
2.2 Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
Funding Body
Amount
£ million Project
Scottish Government 0.225 Road Safety Improvement Fund
Scottish Government  0.179 Nature Restoration Fund
Sustrans (0.012) B777 Corridor Improvements
Sustrans 0.334 Fairlie Coastal Path
Total Funding Adjustments 0.726  
82

Page 83

2.3 Other Revisions to the Programme 
The programme has also been updated to reflect the undernoted adjustments:  
Funding Source
Amount
£ million Project
Receipts 0.007 Insurance Recoveries - Vehicles
CFCR 0.022 Street Furniture
CFCR 0.014 Coastal Playparks
Total Other Adjustments 0.043   
2.4 Alterations to the Phasing of Projects 
A review of individual project plans, taking cognisance of the current levels of volatility
within the construction sector, has identified a requirement to accelerate £1.911m of
expenditure to 2024/25 from future years. 
Project Amount
£ million
Community Alarms 0.069
Total HSCP 0.069
Nethermains Solar PV 0.600
Shewalton Solar PV 0.373
Flexibility 0.332
Total Other 1.305
LBPR Cunninghame House 0.315
LBPR The Circuit 0.123
Other minor adjustments 0.099
Total Place 0.537
Alterations 2025/26 to 2024/25 1.911 
These adjustments have been partly offset by the reprofiling of (£1.757m) for delivery in
2025/26 and beyond. 
Project Amount
£ million
Telephony (0.080)
Total Corporate Services (0.080)
Roads Improve/Reconstruction (0.100)
Dockhead Street Saltcoats (0.100)
Ardrossan North Shore (0.175)
PBIP Kilwinning Abbey Improvements (0.200)
VDLF Kyle Road PH2 (0.300)
Ardrossan Harbour Interchange (0.802)
Total Place (1.677)
Alterations 2024/25 to 2025/26 (1.757) 
83

Page 84

2.5 These adjustments have resulted in a revised 2024/25 budget at 31 August 2024 of
£129.057m. 
2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
Approved 0.338 - 21.871 0.569 79.877 2.000 104.655
Programme @ P3 0.570 0.456 18.676 1.412 102.876 4.144 128.134
Programme @ P5 0.490 0.456 18.676 1.481 103.478 4.476 129.057
Movement 0.152 0.456 (3.195) 0.912 23.601 2.476 24.402 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is an increase of £0.923m from the revised budget,
including: 
Category
Amount
£ million Comments
Prudential Borrowing 3.141 Rephased aligned to projected
expenditure
General Capital Grant (1.086) Rephased and additional
government grants
Specific Grants 1.182 Rephased and additional
government grants
CFCR (0.036) Additional CFCR Contribution
Other Grants & Contributions (0.322) Rephased and revised contributions
Capital Receipts (3.802) Rephased and realigned capital
receipts
Total Funding Adjustments (0.923)   
84

Page 85

2.8 Projected Capital Expenditure to 31 March 2025 
The projections are summarised by service in the following table:   
Service / Category
Approved
Budget
2024/25
£ million
Carry
Forwards
and
Adjustments
£ million
Revised
Budget
2024/25
£ million
Projected
Expenditure
/ Income to
31 March
2025
£ million
Projected
Variance
Over /
(Under)
£ million
Corporate Services 0.570 (0.080) 0.490 0.490 0.000
Communities &
Housing 0.456 0.000 0.456 0.456 0.000
Education 18.676 0.000 18.676 18.676 0.000
HSCP 1.412 0.069 1.481 1.481 0.000
Place 102.876 (0.371) 102.505 102.505 0.000
Other Items 4.144 1.305 5.449 5.449 0.000
Total Expenditure 128.134 0.923 129.057 129.057 0.000
General Grants (9.607) (1.086) (10.693) (10.693) 0.000
Specific Grants (18.960) 1.182 (17.778) (17.778) 0.000
Use of Reserve
Funds (3.480) 0.000 (3.480) (3.480) 0.000
CFCR (0.097) (0.036) (0.133) (0.133) 0.000
Capital Receipts (0.409) (3.802) (4.211) (4.211) 0.000
Other Grants &
Contributions (1.460) (0.322) (1.782) (1.782) 0.000
Prudential Borrowing (94.121) 3.141 (90.980) (90.980) 0.000
Total Income (128.134) (0.923) (129.057) (129.057) 0.000 
Information on the progress of all projects can be found in Appendix 1. 
2.9 Significant ongoing uncertainty and areas of cost risk have been identified as a result of
cost volatility arising from inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials
across a number of projects. Specific projects where cost risks have been identified, or
are anticipated, include Moorpark Primary, Ardrossan Campus, Upper Garnock Flood
Prevention Scheme, Ardrossan North Shore and Ardrossan landside works. While
some mitigation has been built into the Capital Programme in the form of flexibility
budgets, totalling £10m over the next few years, cost pressures may exceed this
provision. These risks will be quantified as individual projects are completed and
tendering exercises are finalised, with the impact on the costs of the programme being
monitored and reported to Cabinet as appropriate. It is recognised, however, with a
significant budget gap being forecast over the medium term, any requirement for further
borrowing not met from a funding source will be a matter for Council to consider. 
85

Page 86

Housing Revenue Account 
2.10 The following table outlines the movements in the 2024/25 HRA Capital budget: 
Housing Revenue Account  2024/25
£m
Budget as at 30 June 2024 46.127
Revised Funding 0.530
Revised Budget 46.657
Alterations to phasing of projects 2024/25 to 2025/26 (4.510)
Alterations to phasing of projects 2025/26 to 2024/25 10.054
Budget as at 31 August 2024 52.201 
2.11  Revised Funding 
The HRA capital programme has been updated to include additional prudential
borrowing to support the Council house buy-back programme to accommodate
Ukrainian Displaced People, as approved by Cabinet on 7 November 2023. 
2.12 Alterations to the Phasing of Projects 
A review of the timescale for delivery of capital projects has identified a requirement to
accelerate of £10.054m of project expenditure for delivery during 2024/25, including:
Project Amount
£ million
Towerlands 2.765
Garnock Academy Site 2.576
Stanecastle Site 1.793
James McFarlane Site 0.927
Kings Arms (High Street) 0.480
Laburnum Avenue 0.284
St Marys Largs 0.233
Other minor adjustments 0.060
Total Alterations to New Builds 9.118
Roofing 0.152
Window Replacement 0.119
Solar Panels 0.044
Total Alterations to Stock Improvements 0.315
Sheltered Housing Units 0.621
Total Alterations to Stock Improvements 0.621
Alterations 2025/26 to 2024/25 10.054 
86

Page 87

This has been partly offset by the re-profiling of (£4.510m) of works for delivery in 2025/26
and beyond, including: 
Project Amount
£ million
James Reid Site (2.832)
Ayrshire Central Site (0.737)
Nelson Street Regeneration (0.274)
Fullarton Street High Flats (0.133)
Total Alterations to New Builds (3.976)
Smoke Detector Programme (0.090)
Path Finder Project (0.050)
Total Alterations to Stock Improvements (0.140)
Estate Based Regeneration (0.394)
Total Alterations to Other Capital Works (0.394)
Alterations 2024/25 to 2025/26 (4.510) 
2.13 These adjustments have resulted in a revised 2024/25 budget at 31 August 2024 of
£52.201m. 
2.14 The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is an increase of £6.074m from the revised budget,
including: 
Category
Amount
£ million Comments
Prudential Borrowing (5.514) Rephased aligned to projected
expenditure
Use of Reserves (0.560) Revised utilisation
Total Funding Adjustments (6.074)   
87

Page 88

2.15  Projected Capital Expenditure to 31 March 2025 
The projections are summarised in the following table:   
Service / Category
Approved
Budget
2024/25
£ million
Carry
Forwards
and
Adjustments
£ million
Revised
Budget
2024/25
£ million
Projected
Expenditure
/ Income to
31 March
2025
£ million
Projected
Variance
Over /
(Under)
£ million
Housing Revenue
Account 46.127 6.074 52.201 51.793 (0.408)
Total Expenditure 46.127 6.074 52.201 51.793 (0.408)
CFCR (11.492) - (11.492) (11.492) -
Capital Grants (16.471) - (16.471) (16.471) -
Use of Reserves (0.544) (0.560) (1.104) (1.664) (0.560)
Affordable Housing
Contribution (0.394) - (0.394) (0.394) -
Prudential Borrowing (17.226) (5.514) (22.740) (21.772) 0.968
Total Income (46.127) (6.074) (52.201) (51.793) 0.408 
2.16 A net underspend of (£0.408m) is projected within the HRA capital programme for
2024/25 arising from revisions to a number of projects, including: 
Project Variance
£ million Comments
Bathrooms / Wet Rooms (0.424) Lower number of void replacements
Kitchens (0.534) Lower number of void replacements
St Michaels Wynd  (0.010) Project complete
EWI 0.560 Additional properties
Total Variance (0.408)   
The additional expenditure on EWI has been supported by an additional draw on the
HRA Sustainability Fund. 
2.17 In addition to the adjustments noted above Appendix 2 highlights a proposed virement
which is required to transfers budgets between Contingency and individual projects,
aligning the budgets with the projected expenditure. 
2.18 Cost pressures will continue to be monitored and a review of any potential impact on
the Business Plan and Capital Programme will be undertaken to address any identified
issues. Further information on the progress of all projects can be found in Appendix 2. 
88

Page 89

3. Proposals 
3.1 That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 31 August 2024; and
(ii) the forecast expenditure to 31 March 2025; and
(c)  approve the virement proposal noted within the HRA programme detailed in
appendix 2. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected underspends
or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our investment
on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None. 
89

Page 90

5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic Business
Partner), on 01294 324551. 
Background Papers
Capital Programme and Treasury Management Performance to 30 June 2024 – Cabinet 28
August 2024 
90

Page 91

TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2024/25
Brought / Carry Forward
to 2025/26
Total Revised
Budget 2024/25
Year to Date Budget
2024/25
Actual Expenditure to
31st August 2024
Year to date
Variance 2024/25
Projected Expenditure to
31st March 2025
Actual Over/
(Under) Spend for
2024/25
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 12,039,019 11,863,732 12,039,019 0 148,582 0 148,582 0 (26,705) (26,705) 148,582 0 0
Primary Schools 44,571,165 34,678,868 44,571,165 0 10,687,443 0 10,687,443 0 7,208,143 7,208,143 10,687,443 0 0
Secondary Schools 89,641,568 5,888,341 89,641,568 0 7,501,603 0 7,501,603 0 776,480 776,480 7,501,603 0 0
Special Education 25,343,637 25,246,058 25,343,637 0 97,579 0 97,579 0 0 0 97,579 0 0
Schools Other 1,649,979 389,681 1,649,979 0 1,454,999 0 1,454,999 0 194,701 194,701 1,454,999 0 0
Completed Projects 43,415,700 43,394,998 43,415,700 0 0 0 0 0 (20,702) (20,702) 0 0 0
SUB TOTAL 216,661,067 121,461,678 216,661,067 0 19,890,206 0 19,890,206 0 8,131,917 8,131,917 19,890,206 0 0
Communities & Housing
Information & Culture 112,479 11,585 112,479 0 105,916 0 105,916 0 5,023 5,023 105,916 0 0
Other Housing 350,000 0 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0
SUB TOTAL 462,479 11,585 462,479 0 455,916 0 455,916 0 5,023 5,023 455,916 0 0
Corporate Services
Council IT Strategy 8,797,380 3,026,738 8,797,380 0 570,334 (80,000) 490,334 0 62,992 62,992 490,334 0 0
SUB TOTAL 8,797,380 3,026,738 8,797,380 0 570,334 (80,000) 490,334 0 62,992 62,992 490,334 0 0
Health & Social Care
Management & Support 1,865,720 1,505,703 1,865,720 0 607,069 68,977 676,046 0 316,029 316,029 676,046 0 0
Housing Non HRA 469,775 193,504 469,775 0 469,775 0 469,775 0 193,504 193,504 469,775 0 0
Adults 4,608,078 4,596,152 4,608,078 0 13,305 0 13,305 0 1,379 1,379 13,305 0 0
Young People 5,579,718 5,224,837 5,579,718 0 355,184 0 355,184 0 303 303 355,184 0 0
SUB TOTAL 12,523,290 11,520,195 12,523,290 0 1,445,333 68,977 1,514,310 0 511,215 511,215 1,514,310 0 0
Place
Roads 113,391,405 65,774,246 113,391,405 0 28,373,887 (200,000) 28,173,887 0 10,245,427 10,245,427 28,173,887 0 0
Streetscene 7,794,821 4,624,186 7,794,821 0 1,641,109 18,866 1,659,975 0 307,620 307,620 1,659,975 0 0
Transport 7,859,702 789,471 7,859,702 0 4,137,243 0 4,137,243 0 677,012 677,012 4,137,243 0 0
Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 0 0 0
Renewable Energy 15,812,597 3,221,539 15,812,597 0 11,295,812 0 11,295,812 0 790,851 790,851 11,295,812 0 0
Office Accommodation 1,021,196 196,023 1,021,196 0 1,030,196 0 1,030,196 0 196,023 196,023 1,030,196 0 0
Other Property 3,908,641 213,141 3,908,641 0 1,063,173 518,000 1,581,173 0 235 235 1,581,173 0 0
Economic Development & Regeneration 172,523,090 51,601,751 172,523,090 0 58,087,756 (1,477,228) 56,610,528 0 17,918,604 17,918,604 56,610,528 0 0
Completed Projects 6,355,261 6,288,872 6,355,261 0 29,376 0 29,376 0 (37,013) (37,013) 29,376 0 0
SUB TOTAL 341,988,204 145,981,769 341,988,204 0 105,658,552 (1,140,362) 104,518,190 0 30,098,758 30,098,758 104,518,190 0 0
Other
Other 8,488,702 0 8,820,276 331,574 1,856,764 331,574 2,188,338 0 0 0 2,188,338 0 0
SUB TOTAL 8,488,702 0 8,820,276 331,574 1,856,764 331,574 2,188,338 0 0 0 2,188,338 0 0
Total Project Expenditure 588,921,122 282,001,965 589,252,696 331,574 129,877,105 (819,811) 129,057,294 0 38,809,905 38,809,905 129,057,294 0 0
Total Project Income (129,877,105) 819,811 (129,057,294) (16,133,616) (16,133,616) 0 (129,057,294) 0 0
Total Net Expenditure 0 0 0 (16,133,616) 22,676,289 38,809,905 0 0 0
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2024/25
North Ayrshire Council Capital Statement 2024/25
Year Ended 31st March 2025
Period 5
The following classifications have been used to highlight delivery
performance against original timescales set
91

Page 92

Revised Budget
24/25 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 78,300,250 6,518,408 10,356,808 95,175,466 (3,876,263) 91,299,203 90,979,392 (319,811)
SUB TOTAL 78,300,250 6,518,408 10,356,808 95,175,466 (3,876,263) 0 91,299,203 0 90,979,392 (319,811)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Active Travel Tier 1 587,000 35,452 622,452 (587,000) 35,452 0 35,452 0
Vacant & Derelict Land Funding 2,376,630 40,544 512,321 2,929,495 (900,661) 2,028,834 1,966,494 1,728,834 (300,000)
UK Government Grant - AGD i3 Flexible Space 3,403,891 (759,412) (6,774) 2,637,705 (1,386,289) 1,251,416 623,639 1,251,416 0
UK Government Grant - AGD Great Harbour 0 1,377,971 1,377,971 0 1,377,971 0
Millport Town Hall Phase 2 0 284,120 284,120 0 284,120 284,120 284,120 0
Garrison House Project 0 633,613 633,613 0 633,613 633,613 633,613 0
Ardrossan Promenade 0 578,499 578,499 0 578,499 578,499 578,499 0
Islands Pit Stops 500,000 40,000 540,000 0 540,000 540,000 540,000 0
Place Based Investment Programme 505,000 151,416 620,466 1,276,882 0 1,276,882 1,276,882 1,076,882 (200,000)
UK Shared Prosperity Fund 0 77,976 77,976 650,794 728,770 728,770 728,770 0
Island Infrastructure Fund 0 (11,408) 80,374 68,966 0 68,966 68,966 68,966 0
B714 Improvements 5,201,946 5,201,946 0 5,201,946 0 5,201,946 0
Digital-SIPP Great Harbour 127,882 114,883 242,765 0 242,765 242,765 242,765 0
Ayrshire 5GIR 0 (19,935) 3,791,000 3,771,065 0 3,771,065 3,771,066 3,771,065 0
Renewal of Play Parks 347,000 (347,000) 0 0 0 0 0 0
Road Safety Improvement Fund 224,826 224,826 0 224,826 0
CO2 Monitors in Schools 0 33,128 33,128 0 33,128 33,128 33,128 0
Capital Grants
Flooding (440,000) 440,000 0 0 0 0 0 0
General Capital Grant 9,167,727 439,273 9,607,000 1,086,000 10,693,000 5,088,915 10,693,000 0
SUB TOTAL 21,777,076 1,015,413 5,713,123 28,505,612 465,641 0 28,971,253 15,836,857 28,471,253 (500,000)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 3,479,853 0 0 3,479,853 0 0 3,479,853 0 3,479,853 0
CFCR 0 0 0 0 133,316 0 133,316 133,316 133,316 0
Grants & Contributions 998,087 254,676 111,562 1,364,325 417,912 0 1,782,237 106,731 1,782,237 0
Capital Receipts 100,000 303,480 0 403,480 3,807,763 0 4,211,243 56,712 4,211,243 0
SUB TOTAL 4,577,940 558,156 111,562 5,247,658 4,358,991 0 9,606,649 296,759 9,606,649 0
TOTAL CAPITAL PROGRAMME FUNDING 104,655,266 8,091,977 16,181,493 128,928,736 948,369 0 129,877,105 16,133,616 129,057,294 (819,811)
Approved Budget
at Cabinet Feb
2024
Capital Programme Funding 2024/25
Projected Income
to 31st March
2025
Approved budget
at Period 1 used
as revised starting
point 2024/25
Actual Income to
31st August 2024Funding Description
Carry Forward
from 2023/24
Changes after
Capital Refresh Feb
2024
Total Changes in
Year
Changes at Capital
Refresh Mar 2025
92

Page 93

EDUCATION
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date Budget
2024/25
Actual Expenditure
to 31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/ (Under)
Spend for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
ST BRIDGETS EARLY YEARS 787,477 787,477 787,477 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
KILMORY EARLY YEARS 72,418 70,645 72,418 0 0 0 (1,773) (1,773) 0 0 0 Complete Complete Complete Complete Complete
ST PETERS EARLY YEARS 1,273,594 1,273,594 1,273,594 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ST JOHN OGILVIE EARLY YEARS 177,415 177,415 177,415 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MAYFIELD PS EARLY YEARS 215,710 215,710 215,710 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
BEITH PS EARLY YEARS 341,180 341,180 341,180 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
SKELMORLIE PS EARLY YEARS 358,835 358,835 358,835 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
WEST KILBRIDE EARLY EARLY YEARS 227,913 227,913 227,913 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
GATESIDE EARLY YEARS 407,764 407,764 407,764 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
GARNOCK CAMPUS EARLY YEARS 58,755 58,755 58,755 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
FAIRLIE EARLY YEARS 208,220 208,220 208,220 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ELDERBANK EARLY YEARS 22,983 22,983 22,983 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
DREGHORN EARLY YEARS 82,940 82,940 82,940 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
CUMBRAE EARLY YEARS 41,339 41,339 41,339 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
LARGS CAMPUS EARLY YEARS 45,836 45,836 45,836 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
MOORPARK EARLY YEARS 182 182 182 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
PIRNMILL EARLY YEARS 79,223 79,348 79,223 0 0 0 125 125 0 0 0 Complete Complete Complete Complete Complete
SHISKINE EARLY YEARS 139,088 139,213 139,088 0 0 0 125 125 0 0 0 Complete Complete Complete Complete Complete
CORRIE EARLY YEARS 29,337 29,359 29,337 0 0 0 22 22 0 0 0 Complete Complete Complete Complete Complete
LAMLASH EARLY YEARS 10,104 10,229 10,104 0 0 0 125 125 0 0 0 Complete Complete Complete Complete Complete
BRODICK EARLY YEARS 364,721 364,885 364,721 0 0 0 164 164 0 0 0 Complete Complete Complete Complete Complete
MARRESS HOUSE 4,010,310 3,836,765 4,010,310 0 148,052 0 (25,493) (25,493) 148,052 0 0 Complete Complete Complete Complete Complete
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,083,677 3,083,147 3,083,677 0 530 0 0 0 530 0 0 Complete Complete Complete Complete Complete
Total Nursery Education 12,039,019 11,863,732 12,039,019 0 148,582 0 (26,705) (26,705) 148,582 0 0 0
Primary Schools
MOORPARK PRIMARY 13,365,164 12,287,570 13,365,164 0 1,899,163 0 821,568 821,568 1,899,163 0 0 31-Jan-24 30-Sep-24 Construction On Target Significantly off target Further contractor delays
experienced. Contingency
arrangements have been developed.
MONTGOMERIE PARK SCHOOL 23,448,999 21,470,410 23,448,999 0 8,109,614 0 6,131,026 6,131,026 8,109,614 0 0 Complete Complete Complete Complete Complete
UNIVERSAL FREE SCHOOL MEALS EXPANSION 472,450 0 472,450 0 90,540 0 0 0 90,540 0 0 31-Mar-25 31-Mar-25 Tender On Target On Target
UFSM ARDEER PRIMARY SCHOOL 24,211 10,586 24,211 0 20,494 0 6,869 6,869 20,494 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BEITH PRIMARY SCHOOL 0 0 0 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
UFSM BRODICK PRIMARY SCHOOL 124,208 124,209 124,208 0 107 0 107 107 107 0 0 Complete Complete Complete Complete Complete
UFSM CORRIE PRIMARY SCHOOL 54,007 54,007 54,007 0 30 0 30 30 30 0 0 Complete Complete Complete Complete Complete
UFSM CORSEHILL PRIMARY SCHOOL 139,074 99,592 139,074 0 118,146 0 90,338 90,338 118,146 0 0 30-Sep-24 30-Sep-24 Construction On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 90,000 61,244 90,000 0 64,334 0 54,085 54,085 64,334 0 0 30-Sep-24 30-Sep-24 Construction On Target On Target
UFSM GLEBE PRIMARY SCHOOL 2,046,397 2,528 2,046,397 0 0 0 0 0 0 0 0 31-Jul-28 31-Jul-28 Tender On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 22,500 10,092 22,500 0 18,847 0 6,438 6,438 18,847 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM HAYOCKS PRIMARY SCHOOL 133,427 63,652 133,427 0 103,906 0 53,501 53,501 103,906 0 0 30-Sep-24 30-Sep-24 Development On Target On Target
UFSM KILMORY PRIMARY SCHOOL 60,000 54,987 60,000 0 2,527 0 (2,486) (2,486) 2,527 0 0 31-Aug-24 31-Aug-24 Construction On Target On Target
UFSM LARGS PRIMARY SCHOOL 148,533 148,533 148,533 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,541 1,463 2,082,541 0 186,181 0 0 0 186,181 0 0 31-Aug-28 31-Aug-28 Tender On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 22,500 10,322 22,500 0 18,940 0 6,762 6,762 18,940 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM SHISKINE PRIMARY SCHOOL 6,616 6,616 6,616 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,252,503 208,779 2,252,503 0 2,136 0 181 181 2,136 0 0 31-Jul-27 31-Jul-27 On Site On Target On Target
UFSM WHITEHIRST PARK PRIMARY 56,212 43,373 56,212 0 52,478 0 40,639 40,639 52,478 0 0 31-Aug-24 31-Aug-24 Construction On Target On Target
UFSM WHITING BAY PRIMARY SCHOOL 21,822 20,906 21,822 0 0 0 (916) (916) 0 0 0 Complete Complete Complete Complete Complete
Total Primary Education 44,571,165 34,678,868 44,571,165 0 10,687,443 0 7,208,143 7,208,143 10,687,443 0 0 0
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,741,318 2,805,435 0 271,377 0 207,260 207,260 271,377 0 0 31-Mar-24 30-Aug-24 Construction On Target On Target
ARDROSSAN NEW BUILD 86,836,133 3,147,024 86,836,133 0 7,230,226 0 569,220 569,220 7,230,226 0 0 31-Aug-26 31-Aug-26 In Development On Target On Target
Total Secondary Education 89,641,568 5,888,341 89,641,568 0 7,501,603 0 776,480 776,480 7,501,603 0 0 0
CAPITAL MONITORING 2024/25
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2024/25 BUDGETS
93

Page 94

EDUCATION
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date Budget
2024/25
Actual Expenditure
to 31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/ (Under)
Spend for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
CAPITAL MONITORING 2024/25
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2024/25 BUDGETS
Special Education
LOCKHART CAMPUS 25,343,637 25,246,058 25,343,637 0 97,579 0 0 0 97,579 0 0 Complete Complete Snagging Complete Complete
Total Special Education 25,343,637 25,246,058 25,343,637 0 97,579 0 0 0 97,579 0 0 0
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 239,743 298,000 0 103,020 0 44,764 44,764 103,020 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 1,351,979 149,938 1,351,979 0 1,351,979 0 149,938 149,938 1,351,979 0 0 31-Mar-25 31-Mar-25 On-going On Target On Target
Total Schools Other 1,649,979 389,681 1,649,979 0 1,454,999 0 194,701 194,701 1,454,999 0 0 0
Completed Projects
GARNOCK CAMPUS 40,304,366 40,283,664 40,304,366 0 0 0 (20,702) (20,702) 0 0 0 Complete Complete Complete Complete Complete
AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,111,334 3,111,334 3,111,334 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 43,415,700 43,394,998 43,415,700 0 0 0 (20,702) (20,702) 0 0 0 0
Total Communities 216,661,067 121,461,678 216,661,067 0 19,890,206 0 8,131,917 8,131,917 19,890,206 0 0 0
94

Page 95

COMMUNITIES & HOUSING
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date Budget
2024/25
Actual Expenditure
to 31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/ (Under)
Spend for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 0 0 38,303 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 74,176 11,585 74,176 0 67,613 0 5,023 5,023 67,613 0 0 31-Mar-25 31-Mar-25 Planning On Hold On Hold
Total Information & Cultural 112,479 11,585 112,479 0 105,916 0 5,023 5,023 105,916 0 0 0
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
Total Other Housing 350,000 0 350,000 0 350,000 0 0 0 350,000 0 0 0
Total Communities & Housing 462,479 11,585 462,479 0 455,916 0 5,023 5,023 455,916 0 0 0
Comments
CAPITAL MONITORING 2024/25
Project Description
TOTAL PROJECT 2024/25 BUDGETS COMPLETION DATES DELIVERY STATUS
95

Page 96

CORPORATE SERVICES
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual
Expenditure to
31st August 2024
Year to date
Variance
2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend
for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 4,065,580 1,190,012 4,065,580 0 437,709 0 60,441 60,441 437,709 0 0 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 912,107 412,107 912,107 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
LAN/WiFi 2,673,000 1,172,540 2,673,000 0 2,958 0 2,498 2,498 2,958 0 0 Complete Complete Complete Complete Complete
TELEPHONY 1,146,693 252,079 1,146,693 0 129,667 0 53 53 49,667 (80,000) (80,000) 31-Mar-28 31-Mar-28 On-going On Target On Target
Total IT Strategy 8,797,380 3,026,738 8,797,380 0 570,334 0 62,992 62,992 490,334 (80,000) 0 (80,000)
Total Corporate Services 8,797,380 3,026,738 8,797,380 0 570,334 0 62,992 62,992 490,334 (80,000) 0 (80,000)   
CAPITAL MONITORING 2024/25
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2024/25 BUDGETS
96

Page 97

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual Expenditure
to 31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £ £ £
Management & Support
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 1,029,662 1,029,662 1,029,662 0 54,167 0 123,144 123,144 123,144 68,977 68,977 31-Dec-24 31-Dec-24 In progress On Target On Target
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 268,065 0 0 0 268,065 0 0 31-Aug-24 31-Mar-25 In development On Target On Target
47 WEST ROAD 300,000 208,048 300,000 0 284,837 0 192,885 192,885 284,837 0 0 21-Jun-24 21-Jun-24 Refurbishment On Target On Target
Total Management & Support 1,865,720 1,505,703 1,865,720 0 607,069 0 316,029 316,029 676,046 68,977 0 68,977
Housing Non HRA
IMPROVEMENT GRANTS * 469,775 193,504 469,775 0 469,775 0 193,504 193,504 469,775 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target 
Total Housing Non HRA 469,775 193,504 469,775 0 469,775 0 193,504 193,504 469,775 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,596,152 4,608,078 0 13,305 0 1,379 1,379 13,305 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,596,152 4,608,078 0 13,305 0 1,379 1,379 13,305 0 0 0
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,224,837 5,579,718 0 355,184 0 303 303 355,184 0 0 Complete Complete Snagging Complete Complete
Total Young People 5,579,718 5,224,837 5,579,718 0 355,184 0 303 303 355,184 0 0 0
Total Health & Social Care 12,523,290 11,520,195 12,523,290 0 1,445,333 0 511,215 511,215 1,514,310 68,977 0 68,977
CommentsProject Description
DELIVERY STATUS
CAPITAL MONITORING 2024/25
2024/25 BUDGETSTOTAL PROJECT COMPLETION DATES
97

Page 98

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual
Expenditure to
31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 3,675,899 1,497,149 3,675,899 0 3,675,899 0 1,497,149 1,497,149 3,575,899 (100,000) (100,000) 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
ROAD SAFETY IMPROVEMENT FUND 224,826 20,000 224,826 0 224,826 0 20,000 20,000 224,826 0 0 Complete Complete Complete Complete Complete
PANEL REINSTATEMENT WORKS 148,494 0 148,494 0 148,494 0 0 0 148,494 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
ROADS REMEDIATION WORKS 106,183 0 106,183 0 106,183 0 0 0 106,183 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
TRAFFIC CALMING 175,000 0 175,000 0 82,953 0 0 0 82,953 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 0 0 0 (100,000) (100,000) 31-Mar-25 31-Mar-25 In development On Target On Target
LIGHTING * 1,409,072 219,031 1,409,072 0 1,409,072 0 219,031 219,031 1,409,072 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 695,000 2,284 695,000 0 12,754 0 2,284 2,284 12,754 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target
UPPER GARNOCK FPS 18,503,801 18,187,694 18,503,801 0 390,335 0 74,229 74,229 390,335 0 0 Complete Complete Complete Complete Complete
MILLPORT COASTAL FPS 48,599,796 37,968,292 48,599,796 0 17,444,119 0 6,812,614 6,812,614 17,444,119 0 0 31-Aug-24 30-Sep-24 Construction On Target On Target
MILLBURN FPS 1,757,000 317,445 1,757,000 0 75,000 0 21,543 21,543 75,000 0 0 31-Jul-24 31-Jul-25 In Development On Target Slightly off target  Delays in getting third party agreement
MILLPORT PIER 500,000 150,080 500,000 0 60,000 0 0 0 60,000 0 0 31-Dec-25 31-Dec-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 899,665 31,871 899,665 0 899,665 0 31,871 31,871 899,665 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 4,617,728 4,609,416 4,617,728 0 1,129,761 0 1,171,449 1,171,449 1,129,761 0 0 Complete Complete Complete Complete Complete
COASTAL ADAPTATIONS 99,000 0 99,000 0 99,000 0 0 0 99,000 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
B714 UPGRADE 31,693,443 2,681,535 31,693,443 0 2,409,350 0 385,832 385,832 2,409,350 0 0 31-Jul-26 30-Nov-26 In Development On Target Significantly off target Work is ongoing to develop the full business case
required to confirm LUF contribution.
PARKING CHARGES & DPE 186,501 89,450 186,501 0 106,476 0 9,425 9,425 106,476 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
Total Roads 113,391,405 65,774,246 113,391,405 0 28,373,887 0 10,245,427 10,245,427 28,173,887 (200,000) 0 (200,000)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 447,894 0 447,894 0 0 0 0 0 0 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, ARDROSSAN - PLOTS/WALLS 217,921 160,857 217,921 0 58,387 0 1,323 1,323 58,387 0 0 Complete Complete Complete Complete Complete
CMTY, KILWINNING - NEW 1,404,577 1,375,502 1,404,577 0 440 0 (28,635) (28,635) 440 0 0 Complete Complete Complete Complete Complete
CMTY, KNADGERHILL - EXTENSION 416,470 415,470 416,470 0 1,000 0 0 0 1,000 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WORKS 398,033 393,954 398,033 0 18,149 0 14,070 14,070 18,149 0 0 Complete Complete Complete Complete Complete
CMTY, STEV HIGH ROAD - WORKS 519,641 522,352 519,641 0 12,363 0 15,074 15,074 12,363 0 0 Complete Complete Complete Complete Complete
CMTY, BRODICK - NEW 12,000 10,341 12,000 0 1,659 0 0 0 1,659 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, KILBIRNIE - WALLS 136,138 105,997 136,138 0 88,477 0 67,336 67,336 88,477 0 0 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, BEITH - WALLS 185,581 153,580 185,581 0 84,261 0 52,260 52,260 84,261 0 0 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, ABBEY TOWER - WALLS 147,337 19,378 147,337 0 91,531 0 8,040 8,040 91,531 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, STEV HAWKHILL - WALLS 91,088 54,000 91,088 0 65,304 0 44,160 44,160 81,248 15,944 15,944 20-Sep-24 20-Sep-24 Tender awarded On Target On Target
CMTY, WEST KILBRIDE - WALLS 55,168 41,054 55,168 0 45,282 0 34,090 34,090 48,204 2,922 2,922 30-Aug-24 30-Aug-24 Tender awarded On Target On Target
CMTY, MILLPORT - WALLS 2,846 2,846 2,846 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, ARDROSSAN - WALLS 4,338 4,338 4,338 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, IRVINE OP CHURCH - WALLS 2,775 2,775 2,775 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, DREGHORN - WALLS 13,175 12,928 13,175 0 4,935 0 4,688 4,688 4,935 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE BARONY - WALLS 1,828 1,828 1,828 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, LAMLASH - WALLS 3,627 3,627 3,627 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, STEV HIGH KIRK - WORKS 22,754 22,754 22,754 0 0 0 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 1,051,663 39,443 1,051,663 0 725,303 0 2,000 2,000 725,303 0 0 31-Mar-26 31-Mar-26 Feasibility Works On Target On Target
CMTY, DALRY - WALLS 2,450 2,450 2,450 0 0 0 0 0 0 0 0 On Target On Target
CMTY, ARDROSSAN - EXTENSION 464,703 14,703 464,703 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
CMTY, SHEWALTON - WALLS 2,235 2,123 2,235 0 2,235 0 2,123 2,123 2,235 0 0 Complete Complete Complete Complete Complete
COASTAL PLAY PARKS 433,790 433,791 433,790 0 13,725 0 13,725 13,725 13,725 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
STREET FURNITURE IMPROVEMENT 215,895 219,990 215,895 0 39,591 0 43,686 43,686 39,591 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PARK ENABLING WORKS 149,895 149,278 149,895 0 1,217 0 600 600 1,217 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,391,000 458,829 1,391,000 0 387,250 0 33,079 33,079 387,250 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
Total Streetscene 7,794,821 4,624,186 7,794,821 0 1,641,109 0 307,620 307,620 1,659,975 18,866 0 18,866
Transport
VEHICLES * 1,562,610 667,970 1,562,610 0 1,562,610 0 667,970 667,970 1,562,610 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target 
FLEET DECARBONISATION 6,297,092 121,501 6,297,092 0 2,574,633 0 9,043 9,043 2,574,633 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target
Total Transport 7,859,702 789,471 7,859,702 0 4,137,243 0 677,012 677,012 4,137,243 0 0 0
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
98

Page 99

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual
Expenditure to
31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
Waste Services
SHEWALTON LANDFILL 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
Total Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 0 0
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 145,218 120,000 0 77,365 0 102,582 102,582 77,365 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 7,889,153 1,374,240 7,889,153 0 6,784,594 0 530,402 530,402 6,784,594 0 0 31-Dec-24 31-Jan-25 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 5,913,443 674,785 5,913,443 0 3,480,264 0 66,983 66,983 3,480,264 0 0 31-Dec-24 31-Jan-25 Work Ongoing On Target On Target
i3 RENEWABLES 0 0 0 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 927,296 1,000,000 0 63,589 0 (9,116) (9,116) 63,589 0 0 31-Mar-25 31-Mar-25 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 890,000 100,000 890,000 0 890,000 0 100,000 100,000 890,000 0 0 31-Aug-24 31-Mar-25 Planning On Target On Target 
Total Renewable Energy 15,812,597 3,221,539 15,812,597 0 11,295,812 0 790,851 790,851 11,295,812 0 0 0
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * 209,929 0 209,929 0 209,929 0 0 0 209,929 0 0 31-Mar-25 31-Mar-25 Mulitple projects On Target On Target 
PLI TRINITY CHURCH ANNEX 3,000 3,384 3,000 0 3,000 0 3,384 3,384 3,000 0 0 31-Jul-24 31-Jul-24 Construction On Target On Target
PLI CALEY COURT RESOURCE CTR 4,800 0 4,800 0 4,800 0 0 0 4,800 0 0 30-Jun-24 30-Sep-24 Construction On Target On Target
PLI CASTLEVIEW DAY SERVICES 64,651 53,214 64,651 0 64,651 0 53,214 53,214 64,651 0 0 31-May-24 31-Oct-24 Construction On Target On Target
PLI PORTLAND PLACE 21,426 0 21,426 0 21,426 0 0 0 21,426 0 0 30-Nov-24 30-Nov-24 Planning On Target On Target
PLI WEST BYREHILL DEPOT 0 7,661 0 0 0 0 7,661 7,661 0 0 0 Complete Complete Complete Complete Complete
PLI GOLDCRAIGS DEPOT 109,139 0 109,139 0 109,139 0 0 0 109,139 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PLI CALEDONIA PRIMARY 0 2,794 0 0 0 0 2,794 2,794 0 0 0 On Target On Target
PLI DALRY PRIMARY SCHOOL 68,314 0 68,314 0 68,314 0 0 0 68,314 0 0 Complete Complete Complete Complete Complete
PLI DREGHORN PRIMARY SCHOOL 0 (1,344) 0 0 0 0 (1,344) (1,344) 0 0 0 Complete Complete Complete Complete Complete
PLI HAYOCKS PRIMARY SCHOOL 1,000 0 1,000 0 1,000 0 0 0 1,000 0 0 30-Sep-24 30-Sep-24 Planning On Target On Target
PLI PENNYBURN PRIMARY 0 21,038 0 0 0 0 21,038 21,038 0 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL 494,500 93,587 494,500 0 494,500 0 93,587 93,587 494,500 0 0 31-Oct-24 31-Oct-24 Construction On Target On Target
PLI AUCHENHARVIE ACADEMY* 0 (22,979) 0 0 0 0 (22,979) (22,979) 0 0 0 Complete Complete Complete Complete Complete
PLI KILWINNING ACADEMY 0 1,156 0 0 0 0 1,156 1,156 0 0 0 Complete Complete Complete Complete Complete
PLI DALRY EYC 11,000 10,915 11,000 0 11,000 0 10,915 10,915 11,000 0 0 Complete Complete Complete Complete Complete
PLI SPRINGVALE EYC 6,895 0 6,895 0 6,895 0 0 0 6,895 0 0 30-Jun-24 31-Jul-24 Construction On Target On Target
PLI UNIT 83 THIRD AVENUE 9,000 0 0 0 9,000 0 0 30-Nov-24 30-Nov-24 Planning On Target On Target
PLI BRIDGEGATE HOUSE 0 0 0 0 0 0 0 0 0 0 0 Cancelled Cancelled Cancelled Complete Complete
PLI CUNNINGHAME HOUSE 0 0 0 0 0 0 0 0 0 0 0 Cancelled Cancelled Cancelled Complete Complete
PLI ABBEYCROFT 12,000 11,843 12,000 0 12,000 0 11,843 11,843 12,000 0 0 Complete Complete Complete Complete Complete
PLI ANAM CARA 3,542 3,668 3,542 0 3,542 0 3,668 3,668 3,542 0 0 Complete Complete Complete Complete Complete
PLI VIKINGAR 0 1,147 0 0 0 0 1,147 1,147 0 0 0 Complete Complete Complete Complete Complete
PLI EGLINTON CASTLE 0 0 0 0 0 0 0 0 0 0 0 Cancelled Cancelled Cancelled Complete Complete
PLI GARNOCK CAMPUS 11,000 9,940 11,000 0 11,000 0 9,940 9,940 11,000 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 1,021,196 196,023 1,021,196 0 1,030,196 0 196,023 196,023 1,030,196 0 0 0
Other Property
LOCALITY BASED PROPERTY REVIEW 2,500,000 0 2,500,000 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
LBPR IRVINE LIBRARY 0 35 0 0 0 0 35 35 50,000 50,000 50,000 31-Mar-25 31-Mar-25 In development On Target On Target
LBPR BRIDGEGATE HOUSE 0 0 0 0 0 0 0 0 30,000 30,000 30,000 31-Mar-25 31-Mar-25 In development On Target On Target
LBPR CUNNINGHAME HOUSE 0 200 0 0 0 0 200 200 315,000 315,000 315,000 31-Mar-27 31-Mar-27 In development On Target On Target
LBPR THE CIRCUIT 0 0 0 0 0 0 0 0 123,000 123,000 123,000 31-Mar-27 31-Mar-27 In development On Target On Target
EMERGENCY CONTROL CTR 158,000 67,191 158,000 0 90,809 0 0 0 90,809 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 1,116,000 36,650 1,116,000 0 946,788 0 0 0 946,788 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 109,065 134,641 0 25,576 0 0 0 25,576 0 0 Complete Complete Complete Complete Complete
Total Property 3,908,641 213,141 3,908,641 0 1,063,173 0 235 235 1,581,173 518,000 0 518,000   
99

Page 100

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual
Expenditure to
31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
Regeneration
REPURPOSING PROPERTY GRANT FUND 254,179 25,380 254,179 0 253,499 0 24,700 24,700 253,499 0 0 30-May-25 30-May-25 In development On Target On Target
MILLPORT TOWN HALL PHASE 2 784,120 466,994 784,120 0 784,120 0 466,994 466,994 784,120 0 0 31-May-23 31-Dec-24 Construction On Target Significantly off target Community led regeneration project by Millport
Town Hall Charity. Project has been delayed due
to challenges with contractor and work needing
redone as did not met a satisfactory standard. 
Regeneration team continues to support MTHC
in the delivery of the project.
GARRISON HOUSE PROJECT 633,613 28,695 633,613 0 633,613 0 28,695 28,695 633,613 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
ISLANDS PIT STOPS 540,000 0 540,000 0 540,000 0 0 0 540,000 0 0 31-Jul-24 31-Mar-25 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 187,592 123,046 187,592 0 68,966 0 4,420 4,420 68,966 0 0 31-Mar-24 31-Dec-24 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 424,401 114,657 424,401 0 393,624 0 83,880 83,880 393,624 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 728,770 424,072 728,770 0 728,770 0 424,072 424,072 728,770 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
DIGITAL - SIPP GREAT HARBOUR 242,765 0 242,765 0 242,765 0 0 0 242,765 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
AYRSHIRE 5GIR 3,791,001 53,184 3,791,001 0 3,771,066 0 33,249 33,249 3,771,066 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PBIP – KILWINNING ABBEY IMPROVEMENTS 235,354 0 235,354 0 235,354 0 0 0 35,354 (200,000) (200,000) 31-Mar-25 31-Dec-25 In development On Target On Target
LOCHSHORE HUB PLAY AREA 355,000 202,438 355,000 0 312,817 0 160,255 160,255 312,817 0 0 Complete Complete Complete Complete Complete
PBIP 36 BANK STREET 169,999 110,138 169,999 0 62,761 0 2,900 2,900 62,761 0 0 31-Dec-25 31-Dec-25 In development On Target On Target
PBIP GALT HOUSE 50,000 4,125 50,000 0 45,875 0 0 0 45,875 0 0 31-Mar-24 31-Mar-25 In development On Target On Target
IRVINE HIGH STREET 2,837,315 2,721,851 2,837,315 0 101,314 0 (14,150) (14,150) 101,314 0 0 Complete Complete Complete Complete Complete
MILLPORT CARS 10,993 0 10,993 0 10,993 0 0 0 10,993 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK MASTERPLAN 4,218,598 1,871,025 4,218,598 0 199,258 0 79,185 79,185 199,258 0 0 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 2,051,138 1,890,405 2,051,138 0 147,122 0 (13,611) (13,611) 147,122 0 0 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,145,999 4,087,907 4,145,999 0 58,991 0 899 899 58,991 0 0 Complete Complete Complete Complete Complete
VDLF 2024/25 ALLOCATION 963,000 0 963,000 0 963,000 0 0 0 963,000 0 0
VDLF - KYLE ROAD PHASE 2 1,398,066 145,155 1,398,066 0 400,000 0 150 150 100,000 (300,000) (300,000) 31-Mar-24 31-Mar-26 In development On Target On Target
VDLF - ANNICKBANK PH 3 1,948,996 1,889,896 1,948,996 0 56,210 0 (2,890) (2,890) 56,210 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
LUF3 - ANNICKBANK 190,000 98,646 190,000 0 190,000 0 98,646 98,646 190,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
VDLF - DEVELOPMENT WORK 114,326 104,321 114,326 0 20,859 0 10,854 10,854 20,859 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
VDLF - STRATEGY 0 0 0 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
VDLF - TREE PLANTING 50,000 2,400 50,000 0 0 0 0 0 0 0 0 31-Dec-24 31-Dec-25 In development On Target On Target
MONTGOMERIE PARK NEIGHBOURHOOD CTR 288,203 0 288,203 0 288,203 0 0 0 288,203 0 0 31-Mar-24 31-Dec-24 In development On Target On Target
VDLF STALLED SPACES FUND 0 0 0 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-26 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 4,778 0 0 0 4,778 0 0 Complete Complete Complete Complete Complete
ACTIVE TRAVEL TIER 1 942,452 2,194,839 942,452 0 942,452 0 59,416 59,416 942,452 0 0 31-Mar-25 31-Mar-25 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 712,709 24,188 712,709 0 712,709 0 24,188 24,188 712,709 0 0 31-Mar-25 31-Mar-25 Various On Target On Target
FAIRLIE COASTAL PATH 334,308 138,726 334,308 0 334,308 0 138,726 138,726 334,308 0 0 31-Dec-23 01-Sep-24 Construction On Target On Target
ARDROSSAN PROMENADE 578,499 694,592 578,499 0 578,499 0 485,091 485,091 578,499 0 0 31-Mar-24 31-Dec-24 Construction On Target On Target
KILBIRNIE TO KILWINNING 18,333 18,333 18,333 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
B777 CORRIDOR IMPROVEMENTS 84,569 84,569 84,569 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
NCN73 ACCESSABILITY IMPROVEMENTS 15,882 15,882 15,882 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
LINKS TO EGLINTON PARK 183,874 198,666 183,874 0 95,000 0 109,793 109,793 95,000 0 0 Complete Complete Complete Complete Complete
COMMUNITY BUS FUND 146,000 135,275 146,000 0 59,459 0 48,734 48,734 59,459 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
SALTCOATS OLD CAL RAILWAY PH2 47,880 47,880 47,880 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete
Total Regeneration 34,887,429 23,122,003 34,887,429 0 13,236,385 0 2,254,196 2,254,196 12,736,385 (500,000) 0 (500,000)
Ayrshire Growth Deal
AYRSHIRE GROWTH DEAL 0 0 0 0 0 0 0 0 0 0 0 31-Mar-26 31-Mar-26 On Target On Target
AGD - I3 DPMC PHASE 1 1,000,000 0 1,000,000 0 423,749 0 (276,251) (276,251) 423,749 0 0 31-Mar-26 31-Mar-26 Delivery On Target On Target
AGD - I3 DPMC PHASE 2 5,000,001 295,925 5,000,001 0 95,480 0 6,540 6,540 95,480 0 0 31-Mar-29 31-Mar-30 Feasibility On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 4,855,546 4,797,935 4,855,546 0 1,397,711 0 1,340,100 1,340,100 1,397,711 0 0 31-Oct-24 31-Oct-24 Construction On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 10,862,023 53,777 10,862,023 0 511,183 0 2,937 2,937 511,183 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,000 254,762 18,040,000 0 500,000 0 5,202 5,202 500,000 0 0 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - GREAT HARBOUR 14,230,849 1,128,641 14,230,849 0 1,487,013 0 109,274 109,274 1,487,013 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - IMSE 10,500,000 156,465 10,500,000 0 477,266 0 5,217 5,217 477,266 0 0 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - MARINE TOURISM ARDROSSAN 5,000,002 275,717 5,000,002 0 (60,673) 0 (60,673) (60,673) (60,673) 0 0 Complete Complete Complete Complete Complete
AGD - MARINE TOURISM ARRAN 2,047,212 160,542 2,047,212 0 96,439 0 66,543 66,543 96,439 0 0 31-Mar-29 31-Mar-29 Feasibility On Target On Target
AGD - MARINE TOURISM CUMBRAE 4,547,212 170,894 4,547,212 0 229,337 0 41,359 41,359 229,337 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 76,082,844 7,294,657 76,082,844 0 5,157,505 0 1,240,250 1,240,250 5,157,505 0 0 0
100

Page 101

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Year to Date
Budget 2024/25
Actual
Expenditure to
31st August 2024
Year to date
Variance 2024/25
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,127,113 564,680 4,127,113 0 902,508 0 13,256 13,256 100,630 (801,878) (801,878) 1st Qtr 2026 1st Qtr 2026 Design On Target On Target
IRVINE ENTERPRISE AREA 10,746,072 0 10,746,072 0 51,539 0 0 0 51,539 0 0 Ongoing Ongoing Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 46,242,720 20,277,201 46,242,720 0 38,586,307 0 14,351,092 14,351,092 38,410,957 (175,350) (175,350) 27-May-24 30-Apr-25 Construction On Target On Target
LOW CARBON HUB 0 0 0 0 0 0 0 0 0 0 0 Complete Complete Complete On Target On Target
VDLF - HARBOUR MASTERS OFFICE 157,499 86,189 157,499 0 131,121 0 59,811 59,811 131,121 0 0 31-Mar-24 31-Mar-25 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 279,411 257,020 279,411 0 22,391 0 0 0 22,391 0 0 31-Mar-24 31-Mar-25 Design On Target On Target
Other Growth & Investment 61,552,816 21,185,090 61,552,816 0 39,693,866 0 14,424,158 14,424,158 38,716,638 (977,228) 0 (977,228)
Total Economic Development & Regeneration 172,523,090 51,601,751 172,523,090 0 58,087,756 0 17,918,604 17,918,604 56,610,528 (1,477,228) 0 (1,477,228)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,163 3,378,163 0 0 0 (1,000) (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,911,709 2,977,098 0 29,376 0 (36,013) (36,013) 29,376 0 0 Complete Complete Defects Period Complete Complete
Total Completed Projects 6,355,261 6,288,872 6,355,261 0 29,376 0 (37,013) (37,013) 29,376 0 0 0
Total Place 341,988,204 145,981,769 341,988,204 0 105,658,552 0 30,098,758 30,098,758 104,518,190 (1,140,362) 0 (1,140,362)
101

Page 102

OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2024/25
Year to Date Budget
2024/25
Actual Expenditure
to 31st August 2024
Year to date Variance
2024/25
Projected
Expenditure to 31
March 2025
Over/ (Under)
Spend for 24/25
£ £ £ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 8,488,702 0 8,820,276 331,574 (144,236) 0 0 0 187,338 331,574
CORE INFRASTRUCTURE INVESTMENT 2,001,000 0 2,001,000 0 2,001,000 0 0 0 2,001,000 0
Total Other Budgets 10,489,702 0 10,821,276 331,574 1,856,764 0 0 0 2,188,338 331,574
2024/25 BUDGETS
CommentsProject Description
TOTAL PROJECT
102

Page 103

HRA Capital Statement 2425 Appendix 2
TOTAL PROJECT CURRENT YEAR 2024/25 - Period 5
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure to
30 May 2024 P5 Projection Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
EXPENDITURE
Council House Building
Afton Court 1,335,654 653,667 1,249,898 (85,756) 0 On Target Complete Complete, project contingency not required.
Ayrshire Central Site 51,235,455 2,717,081 51,235,455 0 5,709,900 158,430 4,973,026 (736,874) On Target On Target Tender award issued to Ashleigh (Scotland) Ltd.  Scottish Government grant offer received
and approved.  Project due to commence on site prior to 31 October 2024. Project slippage
to be carried forward to future financial years and reprofiled accordingly.
Bourtreehill Village 9,924,743 73,717 9,924,743 0 103,797 7,852 160,000 56,203 On Target On Target Projected spend for 24/25 is for consultancy fees, utility disconnections and the demolition
of Crofthead Court.
Corsehillhead 2,032,906 212,599 2,032,906 0 0 0 On Target On Target Options appraisal currently being carried out for the site due to projected costs being
significantly higher than previously projected.
Flatt Road 20,178,000 19,634,012 19,709,046 (468,954) 0 1,795 2,895 2,895 On Target Complete Complete
Fullarton Street (High Flats) 12,073,511 39,368 12,073,511 0 182,605 13,433 50,000 (132,605) On Target On Target Projected spend for 24/25 is for consultancy fees and statutory consents. Work ongoing
with SEPA re site layout, therefore project has been reprofiled to future years.
Garnock Academy Site 12,092,889 1,022,597 12,092,889 0 5,762,674 427,612 8,339,114 2,576,440 On Target On Target Project commenced on site 17 June 2024. Works progressing well on site. Projected in year
overspend to be accelarated from future years.
Garrier Court 2,335,551 2,382,239 2,348,027 12,476 0 0 On Target Complete Complete
Harbourside 14,622,742 13,768,239 14,622,742 0 0 262,224 262,224 On Target Complete Complete
James McFarlane Site 4,784,118 1,490,035 4,784,118 0 2,132,821 1,113,484 3,060,037 927,216 On Target On Target Project commenced on site 25 March 2024. Works progressing well on site. Projected in
year overspend to be accelarated from future years.
James Reid Site 11,820,675 862,603 11,820,675 0 2,832,082 0 (2,832,082) Significantly off
target
Significantly off target Project site start delayed due to non resolution of culvert maintenance issue.
Kings Arms (113-115 High Street) 2,904,416 509,047 2,904,416 0 1,635,733 202,173 2,115,543 479,810 On Target On Target Project commenced on site 13 May 2024. Works progressing well on site. Projected in year
overspend to be accelarated from future years.
Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 1,241,622 3,274,506 0 1,427,383 1,241,527 1,711,735 284,352 On Target On Target Projects commenced on site 15 January 2024. Works progressing well on site. Projected in
year overspend to be accelarated from future years.
Largs Police Station 2,769,301 1,697,509 2,769,301 0 21,157 (33,117) 21,157 0 On Target Complete Complete
Montgomerie Park (Both Phases) 46,322,381 5,562,146 46,322,381 0 2,765,315 883,004 2,765,315 On Target Slightly off target  Ground remediation works commenced on site March 2024 with works scheduled to
complete during October 2024.
Stanecastle Site 7,768,147 2,428,822 7,768,147 0 4,020,327 1,824,313 5,813,638 1,793,311 On Target On Target Project commenced on site 25 March 2024. Works progressing well on site. Projected in
year overspend to be accelarated from future years.
St Beya Gardens 3,691,052 3,689,346 3,691,052 0 1,706 1,706 0 On Target Complete Complete 
St Michael's Wynd 13,996,769 14,189,085 14,087,664 90,895 0 91,285 (9,747) (9,747) Slightly off target  Complete Complete. Projected underspend includes credit received from Scottish Water.
Nelson Street Regeneration 622,116 11,362 622,116 0 310,698 11,362 36,315 (274,383) On Target On Target Tender documentation being prepared for issue.  Project delayed, works expected to start in
April 25
Acquisition Houses-Open Market 1,273,080 6,764 1,273,080 0 1,273,080 6,764 1,273,080 0 On Target On Target
Ukraine Buy Backs 294,758 529,935 294,758 529,935 0
Harbour Street 0 0 0 0 5,000 5,000 0 On Target On Target Options appraisal currently being carried out for the site due to projected costs being
significantly higher than previously projected.
Sy Mary's Primary, Largs 6,092,975 1,626,112 6,092,975 3,449,958 1,626,112 3,682,776 232,818 On Target On Target Project commenced on site 8 January 2024. Works progressing well on site. Projected in
year overspend to be accelarated from future years.
Internal Management Charges 1,757,259 329,990 1,757,259 0 1,489,000 329,990 1,489,000 0 On Target On Target
SHIP Review Requirement (3,991,000) 0 (3,991,000) 0 (3,991,000) (3,991,000) 0 A review to be undertaken as part of the SHIP to identify options to address the reduction in
Scottish Government Grant.
Contingency 2,611,322 0 2,611,322 2,536,959 2,274,735 (262,224) 0
SUB TOTAL 242,308,139 84,982,365 241,744,104 (681,986) 32,199,130 8,200,777 37,331,799 0 5,142,416 (9,747)
DELIVERY STATUS
103

Page 104

TOTAL PROJECT CURRENT YEAR 2024/25 - Period 5
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure to
30 May 2024 P5 Projection Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
DELIVERY STATUS
Improvements to existing stock
Wet Room - Void 248,422 96,948 386,904 248,422 96,948 358,031 109,609 On Target On Target Higher number of void replacments being projected than budgeted offset by reduction in
void bathrooms
Bathrooms - Void 978,665 134,956 524,790 978,665 134,956 444,689 (533,976) On Target On Target Lower number of void replacments being projected than budgeted
Wet Room - Planned 66,246 0 66,246 66,246 66,246 (0) On Target On Target
Bathrooms - Planned 141,069 49,544 141,069 141,069 49,544 141,069 0 On Target On Target
Electrical Rewiring 172,236 141,700 222,869 222,869 141,700 222,869 0 On Target On Target Additional units required in year.
Heating 1,916,920 632,729 1,814,021 1,814,021 632,729 1,814,021 0 On Target On Target Number of units requiring full central heating replacments is less than anticipated.
Kitchens 1,523,166 294,143 1,523,166 1,523,166 294,143 1,523,166 0 On Target On Target
Kitchens - Void 1,497,340 299,442 1,041,824 1,497,340 299,442 962,948 (534,392) On Target On Target Lower number of void replacments being projected than budgeted
Roofing 755,136 39,934 733,500 733,500 39,934 885,179 151,679 On Target On Target
Wallfloor rendering 452,189 (351,359) 246,000 246,000 (351,359) 246,000 0 On Target On Target
EWI 677,882 0 916,000 916,000 1,476,000 560,000 On Target On Target Additional addresses requiring EWI works.
Window Replacement 529,935 529,935 411,008 411,008 529,935 529,935 118,927 On Target On Target
Saltcoats MSF Investment 466,625 5,707 466,625 466,625 5,707 466,625 0 On Target On Target
Smoke Detector Programme 241,682 56,459 241,682 241,682 56,459 151,689 (89,993) On Target On Target
Energy Efficiency 1,414,745 0 0 0 0 0 On Target On Target
Path Finder Project 500,000 0 100,000 100,000 50,000 (50,000) On Target Significantly off target Awaiting outcome  of SHNZS consultation to progress
Solar Panels 3,527,859 (453,840) 2,895,000 2,895,000 (453,840) 2,939,000 44,000 On Target On Target
HRA Slippage (3,085,000) 0 (3,085,000) (476,496) (476,496) 0
SUB TOTAL 15,110,117 1,476,299 11,730,704 0 12,025,117 1,476,299 11,800,972 0 174,613 (398,758)
Other Capital works
Estate Based Regeneration 1,453,809 66,198 1,453,809 1,453,809 66,198 1,060,233 (393,576) On Target On Target
Lift Replacement 454,000 0 150,000 150,000 150,000 0 On Target On Target Contract being re-tendered
Sheltered Housing Units 828,944 871,024 828,944 828,944 871,024 1,450,006 621,062 On Target On Target
SUB TOTAL 5,105,723 2,640,492 4,158,571 (643,152) 2,432,753 937,222 2,660,239 0 227,486 0
Total Expenditure 247,413,862 87,622,857 245,902,675 (1,325,138) 46,657,000 10,614,298 51,793,010 0 5,544,516 (408,505)
Income
Affordable Housing Contributn (394,000) (394,000)
CFCR (11,492,000) (11,492,000)
Capital Grants (11,880,000) (4,407,202) (11,880,000)
Prudential Borrowing (21,747,000) (26,323,010) 0 (5,544,516) 968,505 Reduced borrowing required to reflect rephasing and projected underspends
Use of Reserves (544,000) (1,104,000) (560,000) Utilisation to support EWI additional properties
Sale of Assets 0 (1,562)
Other Capital Income (600,000) (600,000) Income from Vacant and Derelict Land Fund (VDLF) in relation to Kings Arms
SUB TOTAL
Total Project Expenditure 247,413,862 87,622,857 245,902,675 (1,325,138) 46,657,000 10,614,298 51,793,010 0 5,544,516 (408,505)
Total Project Income (46,657,000) (4,408,764) (51,793,010) 0 (5,544,516) 408,505
Total Net Expenditure 0 6,205,534 0 0 0 (0)
Check Total
On Target (+0.5% of budget)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less)
The following classifications have been used to highlight financial performance against
budget
104

Page 105

NORTH AYRSHIRE COUNCIL 
29 October 2024 
Cabinet 
Title:    Cost of Living Support Update 
Purpose:  To provide a further progress report on the response to the cost-
of-living crisis. 
Recommendation:  Click here to enter text.It is recommended that Cabinet: 
a) Notes the progress the Council has made in the
development and delivery of support in relation to the cost-
of-living crisis and towards the Council Plan priority of a
wellbeing economy; and
b) Agrees to the provision of future updates through the
Council’s performance management system and the annual
Community Planning Partnership performance report. 
1. Executive Summary 
1.1 Addressing poverty and inequalities is a key priority for North Ayrshire Council. The
Council continues to develop and deliver a range of supports to mitigate the impacts of
the current cost-of-living crisis for residents. 
1.2 Previous progress reports have been presented to Cabinet during 2022 and 2023. This
latest report provides a further update on the current activity relevant to the cost-of-living
crisis and proposed next steps, along with actions taken to support the delivery of the
Council Plan priority of a wellbeing economy, and finally proposals to mainstream future
cost-of-living support reporting through the Council’s performance management
reporting system and annual Community Planning Partnership performance report. 
2. Background 
2.1 The ongoing cost-of-living crisis has resulted in a series of challenges for residents,
communities and businesses in North Ayrshire. Since 2022, the ongoing recovery from
the coronavirus pandemic, conflict in Ukraine and economic unpredictability,
compounded by the energy crisis, increased inflation and increased interest rates, has
resulted in higher household prices which have created hardship and financial
exclusion, including for North Ayrshire residents. 
2.2 Between September 2022 and March 2023, the UK experienced seven months of
double-digit inflation which peaked at 11.1 per cent.  Inflation has now returned to a
more normal rate of 2.2% in the 12 months to August 2024 according to the Office for
Agenda Item 6
105

Page 106

National Statistics (ONS). However, this does not mean that prices for goods and
services have fallen but rather that the costs are rising more slowly than they have
been. This means that households continue to face unprecedented financial
pressures. 
2.3 The International Monetary Fund has upgraded its forecast for UK economic growth in
2024 from 0.5% to 0.7%. In July it reiterated its forecast of 1.5% growth in 2025.
Interest rates, which had peaked at 5.25% for many months, are now at 5% with
further potential rate cuts being seen as possible at the next meeting of the Bank of
England in November. However, the developing conflict in the Middle East and
uncertainty over potential impact on oil prices means economic unpredictability
remains. 
2.4 Against this backdrop, the cost of living remains challenging for many residents of
North Ayrshire. The latest ONS update in May 2024 showed that employment rates
(70.3%) had decreased compared to the previous year (71.3%) and were lower than
across Scotland as a whole in the year ending December 2023. Levels of economic
inactivity, which means those not in employment but not seeking work such as retired
people, those caring for others or people who are unable to work due to sickness and
disability, were 27.7%, a rise from 25.2% in the previous year and again higher than
the Scottish average of 22.5%. This is partly due to the demographics of an aging
population in North Ayrshire. 
2.5 The rate of people claiming unemployment related benefits dropped slightly from 4.6%
in March 2023 to 4.4% in March 2024. 
2.6. In June 2022, Cabinet agreed to set up a new Board, chaired by the Leader of the
Council and comprising senior NAC officers, representatives of the Third Sector
Interface and NHS Ayrshire and Arran to tackle child poverty. With the escalation in
cost-of-living concerns this board was expanded to oversee the Council’s response to
the cost-of -living crisis. The strategic approach to the themes in relation to child
poverty and cost-of living were identified by the Board and explored in conjunction with
Community Planning partners, third sector representatives and residents. 
2.8 In light of the ongoing importance of the work, the CPCOL Board recommends that it
should be mainstreamed as a workstream of the Community Planning Partnership
(CPP), recognising its responsibility to share resources and to improve equality of
outcomes. This change will include the development of a new and robust governance
framework for work around both child poverty and cost of living interventions. It
proposed that future reporting on progress will be captured through regular updates on
specific programmes of work using the Council’s Pentana performance management
system and reported through the CPP’s annual performance reporting. The CPP
representatives will participate in regular topic-based sessions which will focus on
specific areas of interest. Elected members will be further kept up to date through
regular items in North Ayrshire News highlighting any specific projects and pieces of
work. 
2.8 The Council’s three-year Child Poverty Strategy was presented to Cabinet in June
2023.The first yearly progress report was published after Cabinet approval on 27
August 2024. The progress report highlights action that has been taken throughout
2023 and 2024, based on the three key drivers of child poverty - income from
employment, income from social security and the cost of living.
106

Page 107

2.9 The Council has made substantial investments in tackling child poverty and the cost-
of-living crisis. This paper provides an update on present funds and related activity as
detailed in Appendix 1. 
2.10 The themes which work focuses on are Energy Advice and Support; Food, Clothing and
Essentials; Finance and Benefits; Children and Families; Health and Wellbeing;
Business and Community (including transport for work); Support for Communities and
Workforce Wellbeing. 
2.11 Energy Advice and Support is a key area of focus given the ongoing cost of utilities, the
rise of the price cap in October 2024, and recent decision-making in relation to the
Winter Fuel Payment. The Council’s Energy Smart scheme has continued to evolve and
provides three key elements to support residents: 
• Free and impartial energy efficiency advice through the Home Energy Scotland
(HES) helpline. A partnership with the Energy Agency (a charitable organisation
appointed by Scottish Government to manage the HES programme) was launched
on 19 September 2022 and 8,750 North Ayrshire households have received energy
advice since that date to help lower their bills. 
• The Energy Smart Emergency Support scheme launched on 31 October 2022 to
provide financial assistance over the winter periods, in the form of a crisis payment. 
The allocation of support payments is as follows: 
o 2022/23 - £441k to 1,489 households
o 2023/24 - £192k to 1,200 households
o 2024/25 - £342k available 
Posters and awareness materials are provided to various locations including food
larders, libraries, community centres, GP surgeries, churches and community shops,
information is shared with schools via head teachers, and to Council employees through
message on payslips.  Display screens in libraries and offices are also used to promote
the scheme. 
• The creation of a £1.726 million fund to carry out home improvements to improve
energy efficiency and reduce energy bills has enabled the appointment of an
installation contractor.  The scheme offers roof insulation,  cavity wall insulation, floor
insulation, LED bulbs, draft proofing, temperature controls, and/or electric storage
heating. Households where the home is owned or is privately rented and have income
of £43,662 or less can qualify. 
Additionally, there are other energy saving support methods households can utilise: 
• The ‘ECO4 Flex’ and ‘Great British Insulation Scheme’ offer multiple insulation and
decarbonisation measures. Qualifying private households must meet the criteria such
as SAP band D to G and household gross income less than £31.000.
• The ‘Heat and Energy Efficient Scotland - Area Based Scheme’ is Scottish
Government led and includes insulation and decarbonisation measures. Households
in fuel poverty, in deprived areas, with Council tax band A-C will qualify. 
107

Page 108

2.12 Examples of other key areas of progress include: 
• The development of the No Wrong Door approach where all Council staff are
encouraged to ensure residents reach the support and advice which they need
continues to be developed. Actions include the development of a lanyard card with
the Customer Services number on it which will slide into staff lanyards behind their
ID. These can also be kept in car glove boxes, laptop bags, kit bags etc. The lanyard
card is for colleagues to hand over to clients/residents they meet who ask how to
access Cost-of-Living support. Trials of the approach are being held by some Care
at Home teams and schools. A No Wrong Door Toolbox Talk has been created to
help managers explain the approach to teams. A video was also created to help
managers explain the policy to staff. 
• A total of 10,000 Cost of Living information leaflets have now been distributed to
venues across North Ayrshire. These are now in a range of places and venues,
including community centres, libraries, GP surgeries, KA Leisure venues, schools
and community larders. The aim of the leaflets is to get information to the most hard-
to-reach people in our communities. There is also a digital version of the leaflet which
is available. 
• Ongoing information/features/videos/graphics are posted on social media channels
on helpful issues like employability support, the free reusable nappy scheme, benefit
and grant advice, the Fairer Food network, free family activities and national
campaigns including Challenge Poverty Week during October 2024. 
• Largs Food Hub opened in February 2024 and Millport Community Shop opened in
July 2024, taking the total to 16 larders across the authority and a supported Waste
Food Café model on Arran. Work is ongoing to support the IMC Project who operate
a Community Fridge in Saltcoats, to become part of the Fairer Food Network and
receive financial support. 
• Extension of the £50 early years clothing grant for eligible families. 
• Expansion of the Winter Warmer Breakfast initiative in secondary schools for
2024/25. This is a service which has been offered over the last two winter periods
and is free to all secondary school pupils. 
2.13 While the focus of this report is primarily on the response to the cost-of living-crisis, that
programme of work operates hand-in-hand with our child poverty interventions (see
paragraph 2.8 above) and should also be viewed in the wider context of our strategic
priority to transition to a wellbeing economy. 
2.14 Some of the wider actions taken to progress our Wellbeing ambitions and contribute to
action on child poverty and the cost-of-living agenda include: 
• During 2023/24 our Money Matters Team supported residents to access
£20,081,590 in financial gains from 5,739 referrals. 
• We are funding two additional School Welfare Rights Officers providing financial
advice and assistance to parents and carers. This is based on strong evidence,
108

Page 109

with our current School Welfare Rights Officer obtaining £560,509 for secondary
school parents during 2023/24. This is an average of £5,387 per referral.   
• 20,037 young people have a valid Young Scot National Entitlement Card (NEC)
in North Ayrshire. This represents 90% of the estimated population of 11 to 25
year olds in the area. This is a high level of uptake and enables access to free
bus transport and a range of discounts on products and services. 
• Active Schools’ extracurricular clubs are free of charge across all school settings,
supporting over 9,000 young people across the last year to be active. 
• All eight mainland Secondary Schools now have access to mentoring services
following the successful recruitment of MCR Pathway Co-ordinators with
discussions in progress to deliver the service to Arran High School. 
• Our Community Investment Fund has approved funding for 13 applications over
the year, totalling £721,912.   
• To date, 53 council assets are now owned, leased or managed by community
groups.   
• As part of a circular economy approach, 2,015 households were assisted to
furnish their homes in North Ayrshire due to our bulky waste reuse partner
Cunninghame Furniture Recycling Company collecting and processing reusable
items such as mattresses and furniture.   
• As part of our ‘No Wrong Door’ approach, we have created a new streamlined
customer referral process. This new process will ensure that customers only
share their information with us once and are directed to the most appropriate
service provider (internal council services and external support services).   
• We were recently successful in our bid to participate in the Scottish
Government’s Fairer Futures Partnership (FFP) (the next phase of the Child
Poverty Pathfinder) aligned to our no wrong door and single shared assessment
work noted above. 
2.15 Real lived experience remains at the heart of the design of policy and activities. A Parent
Group has been established in Employability and a Champion’s Board network of over
30 care experienced young people has been developed. This is in addition to
established approaches such as our Joint Cabinet (attended by 110 young people). 
2.16 Going forward, alongside continued development and delivery of the range of support
at Appendix 1 to embed delivery as business-as-usual, key areas of focus will include:
• ensuring residents can access available Cost-of-Living support quickly 
• improving out-of-school care provision; and
• improving the data that is gathered on the six priority groups of families so that
support resources can be better targeted 
3. Proposals 
109

Page 110

3.1 It is recommended that Cabinet: 
a) Notes the progress the Council has made in developing support in relation to the cost-
of-living crisis and towards the Council Plan priority of a wellbeing economy; and
b) Agrees to the provision of future updates through the Council’s performance
management system and the annual Community Planning Partnership performance
report. 
4. Implications/Socio-economic Duty 
Financial 
4.1 None – all work is financed through previously agreed funding streams or existing
resources. 
Human Resources 
4.2 None. 
Legal 
4.3 The Council has a duty to produce a Child Poverty Strategy and Report and to ensure
that inequalities are addressed and outcomes improved through its work, including its
Community Planning Partnership work. 
Equality/Socio-economic 
4.4 This workstream is centred on reducing inequalities. Mainstreaming to the CPP aligns
it with their overarching objective to tackle inequalities. 
Climate Change and Carbon 
4.5 Energy Smart advice not only helps residents to reduce their utilities bills but also to
reduce their use of energy potentially reducing carbon emissions from their household. 
Key Priorities 
4.6 The proposals within the report help to deliver the North Ayrshire Council Plan priority
of Wellbeing through ensuring that people have access to the support and advice they
need. 
Community Wealth Building 
4.7 This work supports the principles of Community Wealth Building by increasing the
money in local residents budgets and communities through maximising income. 
5. Consultation 
5.1 Our work around the cost of living is co-designed with our partners, communities and
those with lived experience. 
110

Page 111

David W. Hammond
Executive Director, Communities and Housing 
For further information please contact Rhonda Leith, Head of Service, Connected
Communities, on Insert author’s phone number. 
Background Papers
Appendix 1 – Cost of Living Progress Update October 2024
111

Page 112

112

Page 113

NORTH AYRSHIRE COUNCIL
29 October 2024
Cabinet
Title: North Ayrshire Council Community Learning and
Development Plan 2024-2027
Purpose: To seek approval of the North Ayrshire Council Strategic
Community Learning and Development Plan 2024-2027
Recommendation: That Cabinet:
a) Approves the North Ayrshire Council Strategic Community
Learning and Development Plan 2024-2027 at Appendix
1; and
b) Authorises officers to take forward the year one Outcome
Plan with a view to targeting resources to address the
identified unmet needs.
1. Executive Summary
1.1 The North Ayrshire Council Strategic Community Learning and Development (CLD)
Plan 2024-2027 was developed in accordance with the Education Scotland
guidance and the continued engagement and professional guidance from CLD
Managers Scotland.
1.2 This CLD Plan (Appendix 1) builds on the previously refreshed plan of 2021-2024.
Key themes have been identified and commitments made to the communities of
North Ayrshire which will be realised throughout the three-year life of the plan and
year one outcome plan. 
1.3 The CLD Plan makes a commitment that communities of North Ayrshire, communities
of place and communities of interest, will have access to the CLD support they need.
It has been informed through consultation and engagement with communities where
needs have not been met. These are included in the action plan, with a clear focus of
action to close the gap between need and delivery.
1.4 Adult Learning, Youth Work and Capacity Building are the foundation of the CLD Plan,
with themes of health and wellbeing, Community Wealth Building and workforce
development woven in. It also covers inequalities and the targeting of resources, as
well as describing unmet need and governance. An Outcome Plan for year one is
included.
1.5 This CLD Plan has been developed through a co-production approach, as outlined
in the process section. This includes the development of a Equality and Children’s
Rights Impact Assesment. The voice, experience and aspiration of communities,
partners and staff is the scaffold on which this plan has been built.
Agenda Item 7
113

Page 114

2. Background
2.1 In June 2012, the Scottish Government issued Strategic Guidance for Community
Planning Partnerships (CPPs) on the provision of Community Learning and
Development (CLD) services. This guidance was followed by the CLD Regulations
(Scotland) in 2013, which placed a legislative duty upon local authorities to
develop a three-year Strategic CLD Plan.
2.2 The Scottish Government introduced further legislation in 2015 in the form of the
Community Empowerment (Scotland) Act, designed to give greater powers to local
communities and by December 2016, new guidance was published as part of the Act
which placed CPPs on a statutory footing and imposed a duty on them for the
delivery of a local outcomes improvement plan (LOIP), with the involvement of
community bodies at all stages of community planning.
2.3 The CLD plan should provide a framework to empower people of all ages,
individually and collectively, to make positive changes in their lives and in their
communities, through learning, personal development and active citizenship.
2.4 The proposed CLD Plan at Appendix 1 is informed by the learning from North
Ayrshire’s Education Scotland CLD progress visit, which took place in October 2023,
and the recently published ‘Learning: For All. For Life.’ Report which sets out the
findings and recommendations of the national review of CLD led by Kate Still.  The
CLD Plan has been developed according to the Education Scotland guidance and the
continued engagement and professional guidance from CLD Managers Scotland.
Throughout the plan, key themes have been clearly identified and commitments
made to the communities of North Ayrshire. These commitments will be realised
throughout the life of the plan, with recognition that the levels of delivery will differ
from year to year, and an annual action plan will be created to reflect this.
2.5 There is an expectation that the CLD plan will recognise the integration and impact of
CLD practice across services within the local authority area. This work will include
services provided by the CLD workforce employed and volunteering within the local
authority, as well as CLD provision within schools, colleges, third sector
organisations and other community planning partners. In summary, the expectation
is for education authorities to:
• Co-ordinate the provision of community learning and development with
stakeholders;
• Describe the actions that will be taken to provide and coordinate community
learning and development between 1 September 2024 and 31 August 2025;
• Describe the actions of partners for the provision of community learning and
development from 1 September 2024 to 31 August 2025; and
• Describe any needs for providing community learning and development that will
not be met between 1 September 2024 to 31 August 2025.
2.6 The development of the CLD Plan requires a collaborative approach to the delivery of
CLD in Scotland’s communities, schools, colleges and third sector organisations.
This requires coordination in  the delivery of CLD practice across the local authority
area and consultation with partners and learners in communities, schools, colleges,
third and voluntary sector organisations with a particular emphasis on people who
are vulnerable or marginalised. This CLD Plan has been developed in a co-
production approach which is evident and detailed in the process section.  The voice,
experience and aspiration of communities, partners, staff and volunteers is the
scaffold on which this plan has been built.
114

Page 115

2.7 Reducing inequalities and ensuring no one is left behind are integral to achieving the
equity focus of the plan. CLD provision is targeted to those most in need whilst
ensuring communities also have a universal offer of access to learning opportunities
and activities. This is achieved through a partnership approach and empowering
communities and individuals to have their place within the delivery of services. The
CLD Plan brings together the range of partners necessary to address the inequalities
and the governance of the plan ensures the voices, needs and aspirations of the
communities inform the operational delivery and targeting of resources.
2.8 The needs of the workforce will inform the future work of the Leadership Collective,
North Ayrshire’s community-based adult learning and capacity-building programme,
which is developed and delivered with partners and learners. The Leadership
Collective provides the opportunity for access to training and learning opportunities,
to partners, community learners and volunteers, ensuring they are equipped with the
skills and knowledge to develop their practice. Increased community activity relating
to Community Wealth Building, community asset transfer, community food networks,
participatory budgeting and the Community Investment Fund add new contexts for
skills and learning development. This adds pressure on the workforce’s skills and
capacity, which is monitored through existing structures.
2.9 The priorities for Community Wealth Building, including proactive engagement with
our communities and Third Sector organisations to provide a voice within CWB
activities to develop, co-produce and maximise CWB opportunities, are also a
focus of each of the three domains of practice of CLD (youth work, adult learning
and community development) and outlined in the CLD Plan at Appendix 1.
2.10 Particular achievements from the previous CLD Strategic Plan, covering the period
2021 – 2024, include the development of work with older people and in particular
the Older People’s Voice network, as well as a range of targeted learning activities
for older people mostly based within the sheltered housing engagement hubs. In
addition, the ongoing development of the North Ayrshire Fairer Food Network,
providing a dignified and community led response to food insecurity, has helped
ensure our most vulnerable are supported not only with their basic needs but with
access to a range of support and learning opportunities.
2.11 The purpose of CLD is to enable people to identify their own individual and
collective goals, to engage in learning and take action to bring about change for
themselves and their communities. The Strategic Plan indicates the priorities which
will enable us to do this at a North Ayrshire level. Within the first year of the plan,
outcomes have been identified which will help to meet the priorities. Delivery of
these outcomes will be developed alongside our partners, learners and
communities with the strategic plan underpinned by locality plans, team plans and
individual staff action plans reflecting the specific needs of each community to help
them achieve their potential. This governance approach of shared and localised
co-design of services was highlighted in the Education Scotland Progress Visit of
September 2023 as ensuring that services are responsive to local need.
2.12 In addition to the priorities, key areas of unmet need have been identified through
community engagement with learners, partners and informed by the area for
recommended by the Education Scotland CLD progress report of the CLD plan in
October 2023. These are:
• Pathways for Learning
• Establishing new protocols and processes for data sharing by introducing a new
management information system
• The celebration of community achievement in CLD events and awards
115

Page 116

2.13 Six monthly performance reports on the delivery of the plan will be provided to the
Community Planning Senior Officers Group. Annual reports will be reviewed by the
Community Planning Board and the six Locality Partnerships.
3. Proposals
3.1 That Cabinet:
a) Approves the North Ayrshire Council Strategic Community Learning and
Development Plan 2024-2027; and
b) Authorises officers to take forward the year one Outcome Plan with a view
to targeting resources to address the identified unmet needs.
4. Implications/Socio-economic Duty
Financial
4.1 The CLD Plan is delivered from within existing resources, with some additional
support for English to Speakers of Other Languages (ESOL) to support New Scots.
Human Resources
4.2 There are no direct human resource implications for North Ayrshire Council staff, who
continue to work within locality approaches to deliver across the three domains of
adult learning, youth work and capacity building. The needs of the workforce will be
addressed via the Leadership Collective to ensure that the workforce is equipped
with the skills and knowledge to develop their practice. The pressure of increased
community activity and corresponding support needs on the workforce’s skills and
capacity will be monitored through existing structures.
Legal
4.3 None.
Equality/Socio-economic
4.4 Reducing inequalities and ensuring no one is left behind are integral to achieving the
equity focus. CLD provision is targeted to those most in need whilst ensuring
communities also have a universal offer of access to learning opportunities and
activities, this achievable by the partnership approach, through empowering
communities and individuals to have their place within the delivery of services. The
CLD Plan brings together the range of partners necessary to address the
inequalities and the governance of the plan ensures the voices, needs and
aspirations of the communities inform the operational delivery and targeting of
resources.
Environmental and Sustainability
4.5 Environmental and sustainability issues provide opportunities for skills and learning
development. With rich and diverse spaces, North Ayrshire offers opportunities for
involvement in marine, coastal and woodland activities; tree-planting; growing and
food production; and community environment projects.
116

Page 117

Key Priorities
4.6 The proposals contained within the report support the North Ayrshire Council Plan
priorities:
• Wellbeing through helping people to develop connections and networks which encourage
their resilience.
• Communities and Local Democracy through supporting communities more opportunities
to lead in local decision making such as participatory grant making.
• Climate Change – achieving net-zero by 2030.
• A Sustainable Council through encouraging young people, adults and communities to
articulate their priorities and assist with focusing our resources where they matter.
Community Wealth Building
4.7 The applications support the following pillars of community wealth building:
• Creating volunteering and skills development opportunities;
• Sustaining local employment through skills development;
• Advancing community enterprises, such as food pantries, community centre
ownership and community sports clubs; and
• Advancing local ownership of underused land and buildings.
5. Consultation
5.1 The consultation is outlined in the plan, with the learner at the centre, involvement
across all Locality Partnerships and Locality Forums, and a "co-define, co-design and
co-deliver" model. This has been established in partnership with the Consultation
Institute and in line with the National Standards for Community Engagement. The
Community Engagement Network (CEN) is hosted by North Ayrshire Community
Planning Partnership and meets quarterly. It is the community engagement reference
group for this toolkit/hub, support and development forum for the Engagement
Champions and a networking opportunity for all partners involved in community
engagement. Engagement Champions are representatives from all partners,
departments or organisations.
5.2 The requirements of the CLD Plan were outlined to all six Locality Partnerships
in June 2024, along with a draft process and draft stakeholder mapping. A
stakeholder reference group was established, identifying consultation and focus
groups. A joint approach of targeted and universal engagements for learners
was agreed and implemented. 
5.3 Work continued to promote engagement through the Consul platform as a digital
engagement tool and was supported by the development of an animation. A
workforce survey was carried out and case studies and equality impact assessment
created. One of the key priorities through out this work was the use of plain English
and Dyslexia Scotland have supported the drafting of the plan.
5.4 Participants involved in youth work, adult learning and community capacity across 117

Page 118

the six localities of North Ayrshire took part in workshops and engagements. This
included the Adult Learners Voice and the Youth Participation Engagement Structure.
The results of both the targeted and universal consultation enabled the identification
of gaps and feedback on the priorities which ultimately informed the plan.
David W. Hammond 
Executive Director of Communities and Housing
For further information please contact Rhonda Leith, Head of Service (Connected
Communities),
on 01294 324415.
Background Papers
Appendix 1: North Ayrshire Council Strategic Community Learning and Development Plan
2024-202
118

Page 119

STRATEGIC COMMUNITY LEARNING
AND DEVELOPMENT PLAN 
2024 - 2027
Appendix 1
119

Page 120

04
Foreword
06
Introduction 
08
What is Community Learning
and Development?
10
North Ayrshire context
12
Learning from 
the previous plan
14
Creating the Plan
16
Third Sector Chief
Officers Group
18
North Ayrshire policy context
22
Connected Communities in
Locality Planning
24
Profile of communities
in North Ayrshire 
28
Community engagement
and volunteering 
32
Community Wealth Building 
36
Health and Wellbeing
38
Workforce Development
54
Targeting Unmet Need within
North Ayrshire
42
The North Ayrshire CLD
domains of practice
priorities
I. Youth Work
II. Community Capacity
Building and Community
Development
III. Adult Learning
52
Governance of the Plan &
Quality Assurance
55
Conclusion 
58
Outcomes for year one
Index
65
Documents and policies
120

Page 121

I am delighted to present the North Ayrshire Council
Strategic Community Learning and Development
(CLD) Plan 2024 to 2027, which builds on the
refreshed 2021 to 2024 plan.
CLD services and approaches have never
been so evident across council services and
partnerships. The CLD approach led the way
in terms of our response to the COVID-19
pandemic, with the establishment of
community and locality hubs supporting
local people in response to their
communities' needs.
In a North Ayrshire Council context, the  CLD
service sits within Connected Communities
within the Communities & Housing
Directorate. The planning and delivery 
of CLD approaches and provision is jointly
planned with our Information and Culture
teams, which incorporates Active Schools
and Outdoor Education.
Recruiting and supporting volunteers,
ensuring communities had access to
essentials such as food and medicine 
and access to specialist services, the CLD
team in North Ayrshire quickly adapted 
to delivering services through a digital
platform and led the way in terms of
creating Virtual Community Centres.
The learning from the CLD response 
has informed this plan and our services
as we move forward.
I would like to personally thank all the
learners, including young people and our
partners, for their support and influence in
shaping this strategic plan and for your
commitment to ensuring communities 
have access to CLD services that they 
need, supporting us to be able to identify
the gaps.
As we move forward, we know that
targeting resources where they are most
needed is an important part of equitable
planning, and here in North Ayrshire, we
know that this vital planning is based on 
the lived experience of our communities.
Foreword
North Ayrshire Council Leader Marie
Burns 
The previous plan made commitments to ensure that learners and
participants' voices were central to the CLD planning process. This
commitment has been realised in this plan and is evident in the
approach to its development. Built upon the principles of co-production
we, as a Council, have emphasised the Customer to Citizen journey and
our Child Centred Council culture.
04 05
Marie Burns
121

Page 122

In June 2012, the Scottish Government issued
Strategic Guidance for Community Planning
Partnerships (CPP) on the provision of CLD services.
This guidance was followed by the CLD Regulations
(Scotland) in 2013, which placed a legislative duty
upon local authorities to put in place a three year
strategic CLD plan.
This plan will build on the previously
refreshed plan of 2021 to 2024. It is
informed by the learning from the COVID-19
pandemic in terms of response and needs. It
has been developed in line with the
Education Scotland guidance and the
continued engagement and professional
guidance from Community Learning
Development Managers Scotland (CLDMS).
Throughout the plan we have identified the
key themes and have made commitments to
the communities of North Ayrshire.
Commitments that will be realised
throughout the life of the plan with
recognition that the levels of delivery will
differ from year one to years two and three.
We make the commitment that communities
of North Ayrshire, communities of place and
communities of interest, will have access to
the CLD support they need. 
We have identified, through consultation
and engagement with our communities,
where needs have not been met and they
have been included within the action plan,
with a clear focus of action to close the gap
between needs and delivery. All provision
aims to be free at the point of access for all
learners.
This plan has been developed through a 
co-production approach, which is evident
and detailed in our process section. The
voice, experience and aspiration of
communities, partners and staff is the
scaffold on which this plan has been built.
Throughout the plan we will use the terms
‘Learners’ and ‘Communities’. These terms
are all encompassing and reflect all our
citizens of North Ayrshire.
Introduction
Executive Director
Communities & Housing
The Government introduced further legislation in 2015 in the form of the
Community Empowerment (Scotland) Act, designed to give greater
powers to local communities, and by December 2016, new guidance
was published as part of the Act which placed CPPs on a statutory
footing and imposed a duty on them for the delivery of a Local
Outcomes Improvement Plan (LOIP), with the involvement of community
bodies at all stages of community planning.
06 07
David Hammond
122

Page 123

Youth Work
Supporting young people in their personal
and social development through various
programmes and activities.
There are three domains of practice
within the CLD context:
Adult Learning
Providing opportunities for adults to enhance
their skills, gain qualifications and engage in
lifelong learning.
08 09
Community Development /
Capacity Building
Empowering communities to take collective
action on issues that matter to them,
fostering social inclusion and community
cohesion.
What is Community 
Learning and Development?
Community Learning and Development (CLD) is a field of 
professional practice that enables people to identify their own
individual and collective goals, to engage in learning, and take 
action to bring about change for themselves and their communities.
CLD uses a range of formal and informal methods of learning and
social development with individuals and groups in their communities.
The Scottish Government’s National Performance Framework sets
out the strategic objectives for all public services, including those
delivering CLD. Within this CLD’s specific focus is to improve life
chances for people of all ages through learning, personal 
development and active citizenship creating stronger, more 
resilient, supportive, influential and inclusive communities.
The recent report on the idependent national review of CLD led by Kate
Still, "Learning: For All. For Life." identified tha there is strong evidence
showing that CLD is delivering positive outcomes and improved life
chances for marginalised and vulnerable learners.
In North Ayrshire, CLD provision contributes to raising attainment for our
young people, supporting communities in tackling poverty related issues,
delivering community led regeneration initiatives, integrating New Scots into
our communities and improving health and wellbeing for residents, as well
as other outcomes.
123

Page 124

Community Learning
and Development in
North Ayrshire
CLD practitioners work in partnership with local
authorities, voluntary organisations, and other
agencies to deliver these services, ensuring they
meet the needs of the community. The desired
outcome is to enable individuals and communities
to achieve their full potential and contribute
positively to society.
Community Learning and Development (CLD) in
North Ayrshire focuses on improving the quality of
life and opportunities for individuals and
communities. It encompasses a wide range of
activities and services that aim to support lifelong
learning, personal development and active
citizenship.
The lead responsibilities within the local authority
for the CLD regulations and developing a new plan
sit with the Communities and Housing Directorate,
Connected Communities. However, the work is very
much led and driven through the Community
Planning Partnership and its robust structures,
incorporating the six Locality Partnerships.
The authority has a vibrant and well established
third sector who deliver key components of the CLD
offer, working in partnership with the CLD Locality
and Thematic Teams.
10 11124

Page 125

Learning From 
The Previous Plan
Review of unmet need within the
CLD Strategic Plan 2021 to 2024
Through a process of community engagement with learners, partners, staff and
volunteers we have reviewed the unmet need in our CLD Strategic Plan 2021 to 2024.
Good progress has been made across the three previously identified priorities of
unmet needs.
Creating an engagement and 
participation structure for older people
There has been an increase in provision for older people across North Ayrshire,
utilising the engagement hubs within amenity housing complexes. The Discovery
Award across localities, a refresh of Older People’s Forums and an Older People’s
Conference have been introduced. The structure is now well established and has a
representative Executive Group to ensure the voice, experience and aspirations of
older people informs service delivery with an annual Older People's Conference now
established.
Addressing the digital gap
Funding was identified and, through a process of engaging with Community
Associations and community groups, a digital grant was created to ensure that
appropriate resources were available to our community partners. A programme of
training was delivered, including cyber awareness, to ensure safe use of
equipment. Young people are supported to gain qualifications and learn invaluable
information on cyber resilience, digital literacy and digital employability skills.
Libraries in partnership with third sector providers provide a comprehensive
programme of digital learning, which is now established as a core programme.
Implementing the 
engagement hub 
and toolkit resources
All resources were refreshed 
and tested to ensure they were fit 
for purpose, both in content and 
accessibility, and will feature within the 
refreshment of the Community Planning 
website. The Community Engagement 
Network (CEN) is an active and robust 
network hosted by North Ayrshire Community 
Planning.  It plays a key role in the promotion 
and monitoring of the toolkit and the hub, which 
supports the resources. The development of a 
forum for the Engagement Champions has provided 
a networking opportunity for all partners involved in 
community engagement. Additional toolkits and 
resources have been co-produced, including a Good 
Governance Toolkit for community organisations, a 
refresh of the community contract for Community 
Associations, and the Community Association Handbook.
12 13
IT Computer Group
Dragged kicking and screaming 
into the world of Information and
Technology. Our tutor is so patient 
and understanding. Love this group.”
“
125

Page 126

Creating
the Plan
The creation of the North Ayrshire CLD Strategic Plan, and the Action
Plan for year one, has been informed by the findings of the Education
Scotland Progress Visit 2023, in which the areas recommended for
development have informed the identification of unmet need and
subsequent actions for this plan.
The plan has benefited from the findings and recommendations from
‘Learning For All For Life’, a report from the Independent Review of
Community Learning and Development (CLD).
There has been a co-production approach to the creation of the plan,
including a review of the priorities. Setting the priorities for year 
one actions and a focus on viewing data and learning from the 
unmet need from the previous plan, ensures ownership across 
partners, learners, staff and volunteers.
As identified in the progress visit report, CLD practices and principles are
embedded within the work of North Ayrshire Council and the Community
Planning Partnership. Therefore, the production of the plan followed the
route map used in creating the CLD Strategic Plan 2021 to 2024.
In June 2024, all six Locality Planning Partnerships and the Community
Planning Board were informed of the requirements for a refresh of the CLD
Strategic Plan. An online questionnaire was created to gather views of
partners for the refresh of the plan. All groups undertook a review of the key
priorities of the CLD strategic Plan 2024 to 2027. 
The following groups were part of this evaluative conversation to focus on
the previous priorities, ensuring that they continue to be reflective of our
communities’ needs and aspirations.
Young People
New Scots
Older People
North Ayrshire Federation of Community Associations
North Ayrshire Fairer Food Network
Equalities Forum
14 15126

Page 127

Third Sector Chief 
Officers Group 
The Third Sector Chief Officers Group also played a key role as our
critical friend, providing guidance and sharing their experiences of
how the Action Plan will inform their organisations’ delivery. The
relationship with our Third Sector Interface is robust and the joint
approach to community-based delivery of the CLD provision maximises
the resources available. 
Many staff and volunteers were involved in focus groups, and online
questionnaires helped identify priorities and gaps in workforce
development with the recommendations from the Learning for Life
report providing additional guidance. 
CLD staff and partners are committed to the highest standards of
consultation and community engagement, which has been supported by
our continuing relationship with the Consultation Institute and in
accordance with the National Standards developed by the Scottish
Government. Following this model fulfils our promise of a high level of
community and partner engagement.
Co-Defining the plan:
Identification of assets,
issues and opportunities
e.g. using the family
resilience profiles, other
partner data and
community assets.
Co-Delivering the plan:
Agree the actions to be
contained within the Plan
with learners/communities
and other stakeholders,
implement the Plan and
review the impact of 
the Plan.
Co-Designing the plan:
Considering and preparing
the response in relation to
the findings with
learners/communities and
other partners.
16 17127

Page 128

North Ayrshire
Council Plan
The 2023 - 2028 Council Plan outlines how we will deliver the priorities of our
communities during the next five years. It was developed alongside North
Ayrshire communities and outlines our four key priorities:
Wellbeing – to transition to a wellbeing economy, delivering prosperity,
wellbeing, and resilience for local people.
Communities and Local Democracy – we will have active, inclusive and
resilient communities.
Climate Change – achieving net-zero by 2030.
A Sustainable Council – a Community Wealth Building Council that is efficient
and accessible, maximising investment and focusing resources towards our
priorities. 
This plan draws from and links to a wide range of national and local policies,
drivers and plans. They are intrinsically linked and inform the identification of
the priorities, our delivery, evaluation and governance.
North Ayrshire
Policy Context
The Local Outcomes Improvement Plan (LOIP) sets out what we want to
achieve together as a Community Planning Partnership (CPP) in North Ayrshire.
It is a binding plan on all community planning partner organisations and will
influence how all partners operate locally. It is a requirement under the
Community Empowerment (Scotland) Act 2015 to create these plans.
It will deliver on our vision of “North Ayrshire – Fair for All” and has three
key themes:
Wellbeing – We will address inequalities. We will promote children 
and young people’s wellbeing. We will enable community wellbeing.
Work – We will increase employment. We will develop volunteering.
We will better support our young people.
World – We will work together to reduce carbon emissions and 
mitigate the impacts of climate change. We will increase active 
travel. We will increase carbon literacy within our organisations
and communities.
This is supported by Thematic and Partner Plans,
including the North Ayrshire Council Plan.
18 19128

Page 129

National
Community Empowerment
(Scotland) Act 2015 
Strategic Guidance for CPPs: Community
Learning and Development 2012 
Adult Literacies in Scotland 2020
Requirements for Community Learning and
Development (Scotland) Regulations 2013 
Welcoming our Learners: Scotland's ESOL
Strategy 2015 - 2020
The Scottish Government’s National Adult
Learning Strategy 2022 - 2027 
Mental Health and Wellbeing Strategy:
Delivery Plan 2023 - 2025
Regional
Ayrshire Growth Deal
Community Wealth Building
Ayrshire and Local Police Plans
North Ayrshire
Local Outcomes Improvement Plan
North Ayrshire Council Plan
North Ayrshire Child Poverty Action Plan
Youth Participation & Citizenship Strategy
North Ayrshire Participation Strategy
Children's Services Strategic Plan
Gaelic Language Plan
Connected Communities Operational Plan
Community Wealth Building Strategy 
Digital North Ayrshire Strategy
Sustainable North Ayrshire Strategy
Scottish Attainment Challenge - Local
Stretch Aims: 2023/24 to 2025/26
National Improvement
Framework for 2023
Education Service Improvement
Plan 2023 - 2026
Locality
Locality Partnership Plans
CLD Team Plans
School Improvement Plans
20 21129

Page 130

Connected Communities
CLD in Locality Planning
The Connected Communities CLD teams play a significant role in
supporting locality planning in North Ayrshire.  It is the locality CLD
teams that provide the crucial support to ensure that the Locality
Plans reflect the diverse voices and experiences of community
members. They organise and facilitate the structures that are the
framework for the Locality Partnerships, such as Chit Chats,
subgroups and locality networking. 
They work across a range of council services and advocate for 
the needs of the local communities within the broader planning
and policy framework. They gather data, assess the impact of
initiatives and provide feedback to ensure continuous 
improvement and accountability.
Community Learning and
Development is a vital
thread in the fabric of
Community Planning 
in North Ayrshire. 
It empowers our
communities and partners
to link and grow, making
Community Planning more
effective and inclusive and
helping to ensure everyone
has a voice.”  
Jacqui Greenlees - 
Community Planning Manager
“
22 23130

Page 131

Profile and Context
of the Communities
of North Ayrshire
The latest 2020 Scottish Index of Multiple Deprivation (SIMD) highlighted continuing
levels of deprivation in North Ayrshire. 52 of our 186 data zones now fall within the 15%
most deprived in Scotland. 39,139 people live within these deprived areas representing
28.8% of North Ayrshire’s population, significantly above the Scottish average. 
High levels of inequality exist in North Ayrshire, particularly poverty
and the associated effects this has on our communities. 
North Ayrshire has one of the lowest
job densities in Scotland (ranked 4th
lowest in Scotland)
Island specific challenges – access to
affordable housing, 
higher costs of living, doing business
and connectivity.
28.6% of children in North Ayrshire
live in relative poverty 
(after housing costs). This is the
second highest rate in Scotland.
27.4% of P6 and P7 pupils in North
Ayrshire are eligible for free school
meals.
27.6% of residents are
economically inactive. 
This is one of the highest rates in
Scotland.
38% of households are in fuel
poverty or extreme fuel poverty.
39.8% of our residents live in the
most deprived areas as 
defined by the Scottish Index of
Multiple Deprivation.
It is these high levels of inequality that informed our
Community Partnership Plan and we continue our
focus on child poverty.
24 25131

Page 132

Profile and Context 
of the Communities 
of North Ayrshire (cont)
Identifying priority groups and targeting the most vulnerable will
ensure this plan will deliver positive outcomes and improved life
chances for marginalised and vulnerable learners in our communities.
A collaborative approach to the sharing of data, resources and
knowledge of our Community Planning partners will support and
monitor the delivery.
Our CLD service and partners are key contributors to the actions
in our Child Poverty Action Plan.  The targets within the plan 
inform the operational plan of the CLD service and its partners.
Inequalities in outcomes can be seen across all sectors 
including education, employment, income and health and
wellbeing. They are the result of an imbalance in power, 
money and resources across society, further compounded
by the recent economic conditions of recession, austerity 
and welfare reform.
Inequalities in outcomes can be seen across all sectors including education,
employment, income and health and wellbeing. They are the result of an
imbalance in power, money and resources across society, further
compounded by the recent economic conditions of recession, austerity 
and welfare reform.
This sets the context for service delivery
and allocation of resources throughout our
Council and partner services. It is this
partnership approach to service and
delivery, and the culture of co-production
that has ensured that the CLD community
empowerment agenda has been
recognised and featured in national reports
and audits: 
"The council is committed to community
empowerment and is recognised by the
Scottish Government and COSLA as a sector
leader. The council’s approach is focused
on embedding community empowerment in
everyday business. The council works well
with a wide number of communities and
groups including young people and
tenants." Best Value Assurance Report:
North Ayrshire Council, Accounts
Commission 2020.
Reducing inequalities and ensuring no one
is left behind are integral to achieving our
equity focus within this plan. 
CLD provision is targeted to those most in
need whilst ensuring communities also have
a universal offer of free access to learning
opportunities and activities. 
This is achievable by the partnership
approach and through empowering
communities and individuals to have their
place within the delivery of services. This is
realised through the policy and strategy
developments that have the principles of
equity at the very core of resource
allocation. Inequality within, and among,
the communities of North Ayrshire is a
persistent cause for concern and remains a
focus of strategy developments. 
The CLD Strategic Plan brings together the
range of partners necessary to address the
inequalities and the governance of the
plan. This ensures the voices, needs and
aspirations of the communities inform the
operational delivery and targeting of
resources.
26 27132

Page 133

Community 
Engagement and
Volunteering
The co-production approach to this plan is a key strength and
is reflective of the way we work in North Ayrshire, engaging
with our communities to understand their needs and ensuring
they are involved in the decision-making process and service
design.  The value of lived experience informing service delivery
is evident across all our partnerships, as detailed in our North
Ayrshire planning model.
We are committed to the development of a coherent
Participation Strategy that is open and transparent, providing
a range of participation options. This work underpins the
principles of the CLD Strategic Plan 2024 - 2027.
Examples of participation and community influence
opportunities include: 
Conversation Café
A method which makes use of an informal
café setting for participants to explore
issues by discussing them in small table
groups.  Discussion is held in multiple
rounds of 20-30 minutes, with the café
ambiance intended to allow for more
relaxed and open conversations to take
place. 
Where do we 
use this method?
Joint Cabinet
Penny for Your Thoughts
A method that asks participants 
to either note down or exchange 
with a facilitator their thoughts on
a topic for a penny.
This could be figuratively, or young people
can use a chocolate coin.
Where do we use
this method? 
Arran Locality Partnership
priorities engagement
Discussion Dinners
A method which makes use of a dinner
setting for participants to explore an
issue by posing a different discussion 
point for each course of the dinner.
Discussion happens
in small groups.
Where do we 
use this method?
North Ayrshire (NA) 
Family Learning Team
- Kilwinning Academy
Breakfast Blethers
A method which makes use 
of a breakfast setting for participants
to explore an issue by discussing it in
small table groups over breakfast.
Where do we use
this method? 
NA Family Learning Team
- Kilwinning Academy
Irvine Youth Forum-
Saturday Breakfast Club
28 29
Friends of Redburn
The sewing/ craft group is a wonderful
way of meeting people and having a
cuppa and a chat with the added bonus
of making things we can use or sell.”
“
133

Page 134

We recognise the value of volunteering to
support these pathways to participation. We
are committed to continuing to support all
our volunteers and promote the benefits of
volunteering in terms of skills development,
upskilling, improved wellbeing and the
connectivity and sense of belonging to their
communities. Ensuring that their voice and
experiences shape service delivery for
communities, learning and services is crucial.
The North Ayrshire Community Trust (Third
Sector Interface) is a key partner of the
Community Planning Partnership at all levels.
They ensure that the Third Sector Chief
Officers Group and all community
organisations have a coherent information
and influence pathway.
This Plan is committed to the National
Performance Framework volunteering
outcomes;
Volunteering and participation are valued,
supported and enabled from the earliest
possible age and throughout life.
Volunteering in all its forms is integrated and
recognised in our lives through national and
local policy.
There is an environment and culture which
celebrates volunteering and all its benefits.
The places and spaces where we volunteer
are developed, supported and sustained.
There are diverse, quality and inclusive
opportunities for everyone to get involved
and stay involved. 
Chit Chats
An informal method where you listen and
consider the views of local people in small
groups. There is a facilitator at each group
to take notes and support the conversation. 
Where do we use this method?
North Ayrshire 
CLD Locality Teams
A method of deliberation developed by
the Jefferson Centre where a small group
of people (between 12 and 24),
representative of the demographics of a
given area, come together to deliberate
on an issue (generally one clearly framed
question), over the period of 2 to 7 days.
Citizens’ Jury involve.org.uk
Where do we use this method?
Locality Partnership
Priority Identifications
Police Scotland EVA’s
People’s Panel
This is a representative, consultative body
of local residents. They are typically used
by statutory agencies, particularly local
authorities and their partners, to identify
local priorities and to consult service users
and non-users on specific issues.
Where do we use this method?
People’s Panel
This is an assembly of citizens,
demographically representative of the
larger population, brought together to learn
and deliberate on a topic in order to inform
public opinion and decision making.
Where do we use this method?
North Ayrshire Council (NAC)
Budget Engagement
New School Development
Engagement
NAC Locality Planning
Participatory Budgeting (PB)
This is a method which enables 
people to directly vote on how local
money should be spent. 
Where do we use this method?
North Ayrshire Locality PB
North Ayrshire Youth PB
North Ayrshire Street Scene PB
Garnock Valley Community Council PB
Questionnaire
This is a method that consists of a set 
of questions or other types of prompts
that aims to collect information from a
respondent. A questionnaire may or may
not be delivered in the form of a survey,
but a survey always consists of a
questionnaire.
Where do we use this method?
NAC Period Poverty engagement
NA Local Outcomes Improvement Plan
Citizens
Jury
Mini
Publics
30 31134

Page 135

Community 
Wealth Building
North Ayrshire Council became Scotland’s first Community
Wealth Building Council in 2020, launching a Community
Wealth Building Strategy that set out our aspirations to
create a resilient, fair and local economy. Community
Wealth Building (CWB) is a people centered approach to
local economic development, which redirects wealth back
into the local economy and places control and benefits 
into the hands of local people. 
A refreshed strategy was published in 2024, which centres
around the Wellbeing Economy in Community Wealth
Building and the impact of strong community led initiatives
to achieving a fairer distribution of wealth. By “increasing
community ownership and control of assets; developing
and growing more ‘generative’ enterprises such as small,
locally owned enterprises, co-operatives and social
enterprises which lock and share wealth within the local
area”. 
Community Wealth Building (CWB) creates stronger local
economies that are more resilient to external shocks 
like COVID and supports the creation of progressive 
jobs with fair pay.
C B
COMMUNITY WEALTH BUILDING
32 33135

Page 136

Community 
Wealth Building (cont)
Connected Communities has strong links to the Third Sector, and the
shared focus on Capacity Building is central to creating the conditions
for local people to own and shape their community through processes
such as Community Asset Transfer, Participatory Budgeting and
mechanisms such as Locality Planning Partnerships. 
We will continue to work on a co-production and co-design basis
with the wide range of people we support, building experience,
confidence and knowledge to maximise the impact that our
communities can have as part of the Community Wealth 
Building agenda.
CLD Priorities of CWB Strategy
Continue to support Community Asset Transfers and support community
Capacity Building to grow community ownership.
Continue to empower our communities through our Community Investment
Fund (CIF).
Develop our progressive and leading approach to Participatory Budgeting
by moving towards mainstreaming participatory budgets, including our
approach to allocating external funding and further empowering our local
communities.
Proactively engage with our communities and Third Sector organisations, for
example Community Development trusts, to provide a voice within CWB
activities and support to develop, co-produce and maximise CWB
opportunities.
We recognise the huge potential of North Ayrshire’s Third Sector to lead the
way in realising Community Wealth Building for communities across North
Ayrshire.  We will work with them to raise the profile and voice of local
projects that are achieving Community Wealth Building’s aims in practice. A
strong, collaborative, and innovative Third Sector enables alternative ways
of working to grow, and we will co-design and test creative approaches to
Community Wealth Building in partnership with the sector, drawing on our
shared strengths and learning what works for North Ayrshire.
34 35136

Page 137

Health and
Wellbeing
The CLD Strategic Plan 2024 - 2027 continues to have a
significant role in promoting the health and wellbeing of our
communities, including children and young people. Placing
health and wellbeing in a learning context ensures that we
support our communities to develop the knowledge,
understanding and skills needed for good health and
wellbeing. 
In North Ayrshire, the Health and Social Care Partnership and
Public Health are key partners, and the work of CLD is
intrinsically linked through our Community Planning
Partnership. We have a productive and effective relationship
with KA Leisure Trust and CLD have been a key partner in the
creation of a Health and Wellbeing Alliance, aligned to North
Ayrshire’s Community Planning Partnership Plan 2022 - 2030
with three key areas of world, work and wellbeing. 
To bring different people and organisations together to develop inventive
ways of working together that give people in our communities opportunities
to live the life they want.
We have a whole systems approach to
health and wellbeing and this plan, and the
co-produced priorities, addresses the
interconnected factors that influence the
health and wellbeing of the individuals and
the communities of North Ayrshire. Our
asset-based approach is evident across all
service delivery and engagement and
learning about health and wellbeing
enables adults, children and young people
to make informed decisions about their
health. 
Outdoor Learning is integral for community
health and wellbeing, this is amplified by
the offer at our Arran Outdoor Education
Centre, which provides outdoor learning
opportunities to communities, children and
young people. They also work very closely
with Health and Social Care colleagues to
provide a bespoke offer to foster parents,
carers and care experienced young people.
The introduction of the Discovery Award
across localities has provided a valuable
opportunity for improving the health and
wellbeing of older people.
CLD approaches and services have a clear
contribution to make to the Education
Improvement Plan 2023 - 2026 with joint
work in progressing the outcomes of priority
four: Improvement in children and young
people’s health and wellbeing. Our work
with schools and whole communities
includes supporting wellbeing models in
schools, mental health walks and talks,
links to employability, staff training and
support to community groups. 
Support for our young people also includes
accredited wellbeing training, young people
from aged frpm 5 to 25 are supported
through groups, activities and one-off
events focusing on early intervention,
resilience and positive mindset. 
The Health and Wellbeing Alliance has co-produced a mission statement
which aligns with this CLD Strategic Plan with an overall mission statement:
36 37
Liam Group
I am more comfortable and able to stay
calm when going into different new
situations.”
“
137

Page 138

Workforce 
Development 
North Ayrshire's CLD workforce is a diverse landscape. The CLD
Standards Council Scotland defines Community Learning and
Development as “a field of professional practice that enables people
to identify their own individual and collective goals, to engage in
learning and take action to bring about change for themselves and
their communities.” 
By nature, CLD is varied and wide-ranging, including those involved in
community development, youth work, community-based adult learning,
learning for vulnerable and disadvantaged groups, health and
wellbeing work for communities and volunteer development. This
definition is an accurate description of the CLD workforce in North
Ayrshire and there is a well-established partnership with a range 
of services and organisations. 
A multi-agency approach to workforce development continues 
to be evident across such areas as:
Know and
understand the
community in
which we work
Build and
maintain
relationships
with individuals
and groups
Evaluate and
inform practice
Organise and
manage
resources
Facilitate and
promote
community
development
Develop and
support
collaborative
working
Provide learning
and development
opportunities in
a range of
contexts
Competent
Practitioner
Knowledge and
understanding
Values and 
principles
Attitude and
behaviour
Skills and
process
Reflection
and action
Alcohol and Drug
Partnership 
Health and Wellbeing 
ESOL
Employability
Mediation 
40 41
Writing for Wellbeing
Each session was interesting and
encouraged lots of great conversation.
Lots of great information, thought
provoking and educational.”
“
138

Page 139

The Workforce Development has been enhanced through the joint
approach to training as identified in the Southwest Collaborative Action
Plan, and the programmes and opportunities this has provided to staff and
partners at all levels. The sharing of resources, ideas and knowledge has
produced synergy and developed relationships across the Southwest.
The workforce survey to inform this Plan 
has highlighted the benefits of the joint
approach to staff and volunteer training,
and it is evident that we have a highly
skilled, motivated workforce. Staff
understand their role well in delivering
against CLD Plan priorities as highlighted in
the Education Scotland Progress Visit 2023.
The needs of the workforce will inform the
training offer, which is developed and
delivered with partners and learners,
providing a rich menu of opportunities to
access training and learning opportunities
to partners, community learners and
volunteers. 
This ensures they have the skills and
knowledge to develop their practice as
recommended in the Learning: For All, For
Life - a report from the Independent Review
of Community Learning and Development.
We will strive to promote the
recommendation of “a progressive
requirement for all those working 
or volunteering in CLD roles to be 
members of the CLD Standards 
Council.”
As highlighted in the Progress Visit
Report 2023, as an area to share
good practice, the authority CLD has
a culture of “grow your own”, being an
approved provider for SQA delivering
a SCQF Level 7 in Youth Work, which
enables the continued growth of a
robust Modern Apprenticeship
programme. As a council we 
continue to support one of the
highest numbers of Modern
Apprenticeships in Youth Work,
providing a learning pathway 
for young people. 
The apprenticeship is delivered
across the learning partners,
providing experience across a 
range of youth work providers. 
Our CLD service also has a 
strong commitment to supporting
unqualified staff through a range 
of qualifications, including the
opportunity to access the work-based
degrees of Community Education
(UWS) and Community Learning and
Development (Glasgow University). 
We provide placement opportunities
for students across a range of further
and higher education providers.
The focus of the workforce
development is informed by the
professional competences for CLD
which include ‘know and understand
the community in which we work’ and
‘develop and support collaborative
working.’
Following the workforce survey the
following priority areas has informed
our year one action plan:
Managing challenging behavior
Intergenerational working
Digital upskilling
Naloxone training
Men’s health and wellbeing
Governance for community
organisations
40 41
MA Programme
Over the course of the apprenticeship, I have developed so many
new skills and built amazing relationships with my colleagues and
people within the community I had no idea the number of skills and
opportunities it would provide me with and how much I’d thrive in
the type of environment the team has created. 
As much as my apprenticeship has come to an end, I know the
support within the team goes further than the 18 months and I
always have a group of people to come back to ready to help and
celebrate the wins with.”
“
139

Page 140

North Ayrshire
CLD Plan - 
Youth Work
North Ayrshire’s youth work practice promotes values of
inclusion, mutual respect, equality, and the involvement of 
young people in decision-making. As Scotland's first Child
Centred Council we are committed to taking our young people on
a journey with us, being involved in all parts of decision making
whilst building relationships that are based on trust and shared
understanding. Using the strength of these relationships
develops a person-centred approach to their development.
Our Active Schools team, with a dedicated coordinator for 
each school cluster, aims to provide more and higher quality
opportunities to take part in sport and physical activity before,
during and after school. It also looks to develop effective
pathways between schools and sports clubs in the local
community. 
The team provide opportunities for children and young people 
to access and stay involved in sport and will continue to make 
a significant contribution to a world class sporting system in
Scotland. Within Active Schools we have dedicated staff, funded
through Sports Scotland, who provide health and wellbeing
support, and specific activities targeted at our care experienced
young people.
An understanding of youth work’s essential role across
public policy areas and recognition of the benefits of 
taking a youth work approach as a key component 
towards achieving positive outcomes for our 
young people. 
Article 12 focusses on every child having the
right to express their views, feelings and
wishes in all matters affecting them, and to
have their views considered and taken
seriously. In North Ayrshire, and through our
youth participation framework, we have a
robust structure of youth voice opportunities
and events that only highlight further the
rights-based approach to any work we do in
partnership with our young people. 
Within Curriculum for Excellence, youth work
complements and enhances our formal
curriculum, improving readiness to learn,
health and wellbeing and educational
outcomes for learners. CLD approaches and
services contribute to the Education
Improvement Plan 2023 - 2026. 
There are clear work plans for joint delivery
across the five priority areas, with a
particular focus on:
Placing human rights and needs of every
child and young person at the centre of
education.
Improvement in children and young people’s
health and wellbeing.
Working with the most vulnerable and
marginalised in our communities remains a
priority for us across all key themes.  As such
we are committed to supporting our New
Scots young people, focusing on equalities-
based work and a commitment to provide
specific opportunities and activities for our
care experienced young people.
This is especially important as Scottish Government has directly incorporated the
United Nations Convention on the Rights of the Child (UNCRC) into Scots Law.
42 43140

Page 141

Positive Destinations for 16-19 Year Olds -
Through the work of our Modern Apprenticeship programme, we will continue to take
young people through their SCQF Level 7 in Youth Work. We will strengthen our
employability programmes in partnership with schools and further learning
establishments to offer a range of educational experiences, group work and
signposting services. A programme of work experience opportunities are available
for young people within our school based youth work offer.
Attainment and Wider Achievement -
We will continue to provide a wide variety of youth work opportunities to young
people based on local need and in partnership with young people. Young people will
have access to various awards and wider achievement and certification though our
programmes. Working in partnership with schools, we will provide a menu of
curriculum enhancing activities.
Health and Wellbeing -
We will continue the development of our equalities specific work across localities and
maintaining the LGBT Charter Mark. We will develop and deliver issue-based
resources, projects and programmes on health and wellbeing including early
intervention, resilience and positive wellbeing, suicide prevention and promote
wellbeing groups, tools and resources.
Climate Action -
We are committed to ensuring that young people are involved and engaged at all
stages of our Climate Change journey, where our climate action work is co-produced
and co-delivered with our young people for a greener North Ayrshire.
Young People’s Voice and UNCRC -
Ensuring young people have structures in place to use their voice through our Youth
Participation and Citizenship Strategy. Strengthening the voice of seldom asked
young people with focused work with care experienced young people, Travelers,
Young Carers and New Scots. With a focused approach to implementing the key
outcomes of The Promise, a rights-based approach to all of our programme delivery
ensures that young people's rights are being upheld and respected.
Poverty and Inequality -
All local authority youth work opportunities are free at the point of access.  
We will work on ensuring equity of opportunities and activities across schools 
and community. Our youth work practice recognises the importance of collaboration
between local and national partners in delivering transformative change in public
services to alleviate child poverty. We will continue to provide food with dignity
through our activities, events, holiday programmes and weekend and evening
provision.
Digital Connectivity -
We will work with partners to ensure that young people most disproportionately
affected by digital poverty to have the necessary tools, skills and support to access
digital services and the crucial connectivity to their peers.  We will provide training,
accreditation and information for young people enabling them to be digitally secure
and resilient through cyber resilience. We will use a variety of digital platforms and
tools enabling young people to engage with our service, partners, and their peers
safely. This will be further enhanced with funding from the UK Government for its first
of a kind community led Cyber Explorers programme.
We have agreed on the following priorities
for Youth Work for the three-year plan:
44 45141

Page 142

North Ayrshire CLD Plan - 
Community Capacity Building
& Community Development
Community Capacity Building is the support that community groups access to help them
address issues which are important to them. ‘Capacity’ describes the range of resources
that people have – knowledge about their area or common interest, skills and ideas,
shared experiences, and material resources like funding and community spaces.
Community Development is building the capacity of communities to meet their own
needs, engaging with, and influencing decision makers.  This can be with communities 
of place/geography or communities with a shared interest. Community development is
a process where people come together to act on what’s important to them.
In North Ayrshire we will continue to develop our sector, leading Participatory
Budgeting (PB) and wider participatory and engagement approaches.  We will also
support our community groups in their ambitions to own and lease assets via our
Community Asset Transfer Policy. Our hope is to transform community interaction 
with the Council procurement process through improved delivery of 
Community Benefits.
Supporting the sustainability and development of groups/organisations
and community ambitions will be provided through a range of grant 
supports including our transformational Community Investment Fund.
We are continuing to develop sustainable, dignified food systems
that are locally sourced, offer good value for money and are led 
by our communities’ needs.
We will continue to deliver capacity and learning opportunities built on the expressed
needs of our communities. We will support our environmental capacity projects such as
tree planting, coastal care and our growers' programmes.
We have agreed the following priorities for Community Capacity Building and Community
Development for the three year plan:
Participation and Democracy -
To extend our participatory approaches,
offering communities more opportunities to
lead in local decision making, including grant
making (youth and locality) and
mainstreaming PB. To build on the projects
funded via the devolved Community
Investment Fund.
o self- assess our locality planning
partnerships with our partners and improve
our processes based on feedback
Food Insecurities -
To continue to develop our food with
dignity approach to food
poverty/insecurity working in partnership
with the Fairer Food Network. We will
support access to a range of funding
options and models to support the
network to achieve sustainability .
Community Engagement -
To continue to develop and enhance
opportunities for community
engagement/involvement, through the
development of the Participation and
Citizenship Strategy, Community
Engagement Hub/Toolkit and the older
people's voice structure.
Networking and Funding -
To provide capacity building support to
key community anchor organisations. We
will continue to support communities to
achieve what’s important to them through
strong local networks. Supporting groups
to generate sustainable income, through
successful grant funding applications.
46 47
Grandparents Group
The group has helped me with my confidence with maths and
money handling. Completing the qualifications and receiving
my certificate made me feel amazing. Having left school with
no qualifications at all, coming here has made me feel
included and worthy.”
“
Community Leadership -
To support volunteers, individuals, and
community groups, to develop the
required skills and knowledge to achieve
their ambitions, through opportunities 
co-produced and offered through our
community leadership training offer.
142

Page 143

North Ayrshire 
CLD Plan - 
Adult Learning
Adult learning in North Ayrshire offers accessible opportunities for individuals
to engage in lifelong learning. The focus is on empowering adults through
education, skill development, and confidence building, thereby fostering
inclusive and connected communities. Our approach ensures that learning 
is not a one-time event but a continuous journey available to all adults,
regardless of their circumstances.
In North Ayrshire, adult learning encompasses a broad spectrum of
opportunities developed to address the needs of learners. Using a Social
Practice Model, our adult learning offer is built around the experiences and
needs of the learners. 
It is a learner centred approach that ensures education is not only lifelong but
also life-wide, integrating learning into all aspects of an individual’s daily life
and underpinned by the Scottish Governments strategy for adult learning 2022
- 2027 three core principles - learning is lifelong, learning is life-wide, and
learning is learner-centered.
Through these principles, we aim to develop a skilled, confident and
empowered population. 
48 49
Multiply
I'm slowly getting better at maths 
and figuring out long words. I'm really
enjoying it.”
“
ESOL
Being invovled in CLD made me realise
learning is not age-bound; a person can
learn at any stage of life.”
“
143

Page 144

We work in partnership with a variety of organisations to enable,
encourage and improve participation in community-based adult
learning. These collaborations include Third Sector Interface (TSI), the
NHS, Health and Social Care Partnership (HSCP), Ayrshire College and
several local and national organisations. 
This partnership approach ensures the maximisation of local and
regional resources, the sharing of expertise and the planning of
progression for learners. 
Digital learning plays a role in supporting community-based 
adult learning, ensuring that our adult learning offer meets the 
diverse needs of learners, and the use of digital platforms make
adult learning more inclusive and flexible. Our innovative North
Ayrshire Virtual Community Centre provides an opportunity for 
learners to engage with Community Learning and Development 
(CLD) services from anywhere. 
This virtual hub allows individuals to access a wide range
of resources and information, participate in interactive 
learning sessions, and connect with staff and 
other learners. 
Through digital learning, we break down geographical and 
physical barriers, making education more accessible and 
empowering learners to take control of their learning journeys.
Core Skills - To work with our partners and organisations in localities to
ensure adult literacy, numeracy and core skills support given is learner
centred, using a collaborative approach to develop staff, volunteers and
programmes to best support learners.
We have agreed on the following priorities for Community Capacity Building
and Community Development for the three-year plan:
Poverty and Equalities - To support our learners to become active members
of our community, building social relationships. Through our work we will
ensure equity of opportunities and activities across adult learning,
addressing additional support needs with a key focus on support for New
Scot Learners.
Adult Voice and Participation - To continue to provide opportunities, in
partnership with learners, to participate in community-based adult learning
including activities that promote health and wellbeing and tackle isolation.
Skills for Work - To work with partners and organisations to deliver skills for
work providing opportunities to learn for work to achieve stronger
employability outcomes for learners.
Digital Learning - To provide digital learning and digital literacy support to
help communities to develop digital skills and confidence. Encouraging and
supporting people to get online and enjoy the opportunities offered by
digital technology. We will take appropriate action to support those most
disproportionately affected by digital poverty ensuring they have the
necessary tools, skills and support to access digital services.
50 51
Young Parents
This group has been a lifeline to me as we
don't get to see anyone anymore since
baby came along, the group is the thing
that I look forward to every week.”
“
144

Page 145

Governance of the
Plan and Quality 
Assurance
This Community Learning and Development Plan fits within a landscape of community
and locality planning, with strong relationships in place with partners, including
community groups. You can find out more about community and locality planning 
at Northayrshire Community 
The delivery of the CLD Strategic Plan is
essential in achieving the aims of the
North Ayrshire Community Planning
Partnership (CPP), in that every person in
North Ayrshire should have the best
opportunities to live their life to their full
potential. In acknowledgement of these
interdependencies, and in accordance
with national requirements, our
governance arrangements are
implemented by reporting to the
Community Planning Board and 
Locality Partnerships.
The governance of the previous plan will
continue throughout the life of this plan,
with six monthly performance reports
provided to the Community Planning
Senior Officers Group. Annual reports will
be discussed by the Community Planning
Board and the six Locality Partnerships. 
This plan provides the strategic direction
for the CLD operational plan, which
includes the CLD Key Performance
Indicators (KPIs). There has been an
increase in Third Sector reporting on CLD
KPI’s which encourages the ownership of
them outwith the North Ayrshire Council
CLD service. Reported on with the CLD
Partners as part of the process of shaping
the plan, this enhances the performance
reporting to the CPP to capture the CLD
landscape. 
The action plan for year one will be
reviewed, and the year 2 action plan
will be presented to the Cabinet 
in September 2025.
Quality Assurance
We will continue to foster a culture of
continuous improvement.  This will be
enhanced by the introduction of a new
management information system, which is
being developed with a greater emphasis on
systems which track learner journeys and
capture their experiences in a systematic way.
Providing data analysis will help to inform
improvements - planning for improvement
across partners is the governance’s core role. 
We have strong and effective arrangements
in place to measure progress against the
annual CLD Action Plan. This will demonstrate
the impact of the CLD partnership and will
support improvement.
52 53145

Page 146

There has been good progress in the
previous strategies’ key priorities and
within unmet need there has been a
significant increase in community
participation and community
engagement. This is reflected and
reported on through our governance
arrangements, Council Plan reporting
and the national CLD KPIs. This has
been achieved within a backdrop of
reduced resources and a number of
services redesigns within North
Ayrshire Council and partner
organisations. The alignment of
partners and council services to our
locality approach has ensured
localised responses to challenges and
has increased community influence in
decision making.
These partnerships have enhanced
resource sharing, coordination and
support leading to more effective
outcomes against the priorities
identified in the previous plan.
We continue to have confidence in the
delivery of this refreshed CLD Strategic
Plan 2024 - 2027 and the continuation
of joint working with partners in terms
of sharing resources and knowledge.
This means that we are better
equipped to work in a challenging
landscape with reduced budgets. 
We have taken the approach to
provide an annual action plan for the
lifespan of the Strategic Plan. This
enhances the governance of the plan
and is reflective of the resource
landscape. We will continue to ensure
our CLD work is always focused on the
greatest need and where our resources
can be of most benefit.
Community Learning and Development
primarily supports disadvantaged or
vulnerable groups and individuals of
all ages to engage in learning,
personal development and active
citizenship with a focus on bringing
about change in their lives and
communities.
Targeting Unmet Need Within North
Ayrshire Communities 2024 - 2027
The identification of unmet need for the plan has been informed by the Education
Scotland Progress Visit 2023, areas for development highlighted in the report and the
recommendations from the ‘Learning For Life’. They have been co-produced and agreed
with the range of partners and focus groups. These were shared and further enhanced
by the children’s rights and equalities impact assessment of the plan resulting in the
following areas agreed for unmet need:
Pathway for learning
CLD partners will work together to co-produce with learners an offer to ensure that
prospective and current adult learners are clear about the programmes and pathways
available and evident to them. We will use a range of methodologies to promote the
pathways and the offer.
Establish new protocols and processes for data sharing by 
introducing a new management information system
CLD partners will review how we can use the data and other information, to 
better demonstrate their collective impact and progress over time. We will create
approaches to extend data sharing, analysis, and reporting across all CLD partners.
Celebration of community achievement in CLD events and awards
CLD partners will adopt a collective approach to the promotion and 
recognition of CLD in North Ayrshire and the impact of the work. We will 
provide a clearer picture of the difference CLD is making in North Ayrshire 
for senior leaders, funders, staff and volunteers.
Conclusion
The refresh of the Community Learning and Development Strategic
Plan 2021 - 2024, and the co-production of this plan for 2024 0
2027 has been instrumental in further fostering collaboration across
partners, communities, volunteers and staff. We have collectively
discussed and identified key achievements.
54 55146

Page 147

56 57
Year One
Outcomes
147

Page 148

Priority: Health and Wellbeing
We will continue to develop our health and wellbeing
specific work across localities by delivering issue-based
resources, projects and programmes including early
intervention, resilience and positive wellbeing, suicide
prevention and promoting wellbeing groups, tools and
resources.
Increase the number of young
people accessing health and
wellbeing support and ensure
there are opportunities for lived
experience to inform delivery.
Participant data through our
management information system
Learner’s awards
Active Schools data (ASMO)
D of E data
School reporting
Priority: Attainment and Wider Achievement
Priority: Positive Destinations for 16-19 Year Olds
We will strengthen our employability programmes in
partnership with schools and further learning
establishments to offer a range of educational
experiences, group work and signposting services.
Improve and promote CLD
contribution to positive
destinations for 16-19 year olds.
Local Employability Partnership
Plan data
Participant engagement data
Case studies
Impact statements
We will continue to provide a wide variety of youth work
opportunities to young people based on local need and
in partnership with young people.
Working in partnership with schools and Youth
organisations, we will provide a menu of curriculum
enhancing activities. 
Increase young people’s access
to various awards and wider
achievement and certification.
Participant data through our
management information system
Learner’s journey
Learners awards
Active Schools data (ASMO)
D of E data
Youth Scotland data
What we will do What we aim to improve How will we measure
Year 1 Outcomes – Youth Work
Priority: Young Peoples' Voice and UNCRC
Continue to ensure a rights-based approach to all of our
programme delivery by the promotion of participation in
the structures that support our Youth Participation and
Citizenship Strategy, including a programme of
strengthening the voice of seldom asked young people. 
Implement the key outcomes of The Promise. 
Ensure all young people have
access to the structures in place
to use their voice through our
Youth Participation and
Citizenship Strategy.
Young people understand the
UNCRC and the reporting
mechanism that upholds these
rights.
Participant numbers in engaging
in rights-based work
Youth Forums
Youth Council
Joint cabinet
UNCRC surveys and reporting.
Priority: Poverty and Inequality
What we will do What we aim to improve How will we measure
Priority: Climate Action
We will implement a programme of opportunities to
ensure that young people are informed, involved and
engaged at all stages of our climate change journey,
where our climate action work is co-produced and co-
delivered with our young people.
Young people’s views and
aspirations for a greener North
Ayrshire inform the climate
change journey.
North Ayrshire Climate Action
Plan
Participation in climate change
opportunities.
Participation and achievement of
relevant awards
All youth work opportunities are free at the point of
access.  We will work on ensuring equity of opportunities
and activities. 
We will support the ongoing work to address child
poverty
Young people are able to access
our range of offers including:
Preloved clothing
Food with dignity
Support for transport
Child poverty action plan
reporting.
Postcode participation data
across all CLD programmes
Priority: Digital Connectivity
We will work with partners to target young people most
disproportionately affected by digital poverty.  
We will provide training, accreditation and information
for young people. 
We will use a variety of digital platforms and tools
enabling young people to engage with our service,
partners, and their peers safely. 
This will be further enhanced with funding from the UK
Government for its first-of-a-kind community-led Cyber
Explorers programme.
Ensure Young people have the
necessary tools, skills and
support to access digital services
and the crucial connectivity to
their peers.
Enable young people to be
digitally secure and resilient
through cyber resilience.
Cyber Explorer reporting
Participant data
Award achievements
Case studies
Impact statements
58 59148

Page 149

We will work with our partners and organisations in
localities to ensure adult literacy, numeracy and core
skills support given is learner centred, using a
collaborative approach to develop staff, volunteers and
programmes to best support learners.
Pathways to provide bespoke
core skills support are accessible
to learners.
Core skills needs and
achievements will feature within
new participant registration and
progress system
Case studies
Impact statements
CLD KPI’S
Quarterly LPP reports
Priority: Participation and Democracy
To extend our participatory approaches, offering
communities more opportunities to lead in local decision
making, including grant making (youth and locality) and
mainstreaming PB. 
To build on the projects funded via the devolved
Community Investment Fund. 
The active participation and co-
production of PB process for
communities. The range of
experiences and learning for our
Community PB Champions.
Evaluations of PB processes
through the PB champions
network.
Number of PB applications
Number of votes cast
What we will do What we aim to improve How will we measure
Year 1 Outcomes – Community Capacity and Development
Priority: Food Insecurities
To continue to develop our food with dignity approach to
food poverty/insecurity – working in partnership with the
Fairer Food Network.
We will support access to a range of funding options and
models to support the network.
Improved access to the Fairer
Food Network offer and the
sustainability of the models.
Cost of basket offer across larder
network
Footfall of each offer
Locality partnership quarterly
reports
Impact statements
Case studies
Priority: Community Leadership
To continue to support volunteers, individuals, and
community groups, to develop the required skills and
knowledge to achieve their ambitions, through
opportunities co-produced and offered through our
‘Leadership Collective’.
Improve the promotion of the
learning offer, representing all
partner’s contributions and aim
to meet the need with sharing of
resources through increased joint
planning with all partners.
Participation levels recorded
through the management
information system
Awards and accreditation
achieved
Priority: Community Engagement
To continue to develop and enhance opportunities for
community engagement/involvement through the
completion and promotion of the Participation and
Citizenship Strategy.
Increase the involvement of the
seldom heard in our participation
models of delivery.
Increased participation in
community chit chats.
Management and information
data will identify postcode and
participants, which will be
reported through the quarterly
locality planning reports
Case studies 
Impact statements
Priority: Networking and Funding
To provide capacity building support to key community
anchor organisations.  
We will continue to support communities to achieve
what’s important to them through strong local networks.
Support groups to generate sustainable income, through
successful grant funding applications. 
Improve the range of the offer to
reflect the needs of organisations
and communities.
Funding applications applied for
Business plans created
Reports from the Third Sector
Interface presented to CPP Board
Quarterly Locality Planning
reports
Attendance at funding
workshops
Priority: Core Skills
What we will do What we aim to improve How will we measure
Year 1 Outcomes – Adult Learning
Priority: Poverty and Equality
Adult education offer will promote social inclusion by
targeting resources and learning to those most in need.
Reduce social and economic
disparities across communities of
North Ayrshire.
Participation levels and learner
journey data
Case studies
Impact statements
CLD KPI’S
Quarterly LPP reports
Priority: Adult Voice and Participation
Pathways to engage in adult learning offer and civic
activities are promoted and co-produced with learners.
Learning pathways and civic
opportunities to engage are
evident to learners and potential
learners.
Participation levels and co-
produced offers recorded in
registration and management
information system
Case studies
Impact statements
Priority: Skills for Work
Learning offer for adults will focus on skills development
to enable adults to adapt to changing job markets.
Active participation of partners
delivering adult education in the
Local Employment Partnership.
Local Employability Partnership
quarterly reporting
Participation journey data and
accreditations achieved
identified through our
management information system
Priority: Digital Learning Connectivity
Support learners to have access to equipment and digital
learning opportunities that equip them to develop digital
skills.
Digital learning offer provided by
all partner’s will be jointly
planned and gaps identified.
Participation levels and learner
journey data
Case studies
Impact statements
CLD KPI’S
Quarterly LPP reports
60 61149

Page 150

Priority: Community Asset Transfer Support to Grow Community Ownership
Provide a learning offer including workshops on the CAT
Process to community organisations.
Understanding and support of
the CAT process.
Quarterly reporting on training
participation and CAT reporting
Case studies
Impact statements
Quarterly LPP reports
Priority: Continue to develop our progressive Participatory Budgeting approaches
What we will do What we aim to improve How will we measure
Priority: Empower our Communities Through our Community Investment Fund
Continue to provide support for co- produced CIF
applications based on locality need and gaps identified
by lived experience.
Response to community need
identified at a locality level
based on locality priorities.
Reporting on CWB Strategy
action plan
CWB Board minutes
CIF applications and monitoring
reports
Cabinet reports
Quarterly locality reports
Case studies
Impact statements
Provide information workshops to partners in terms of
mainstreaming opportunities and implement PB plan for
2024.
Learning pathways and civic
opportunities to engage are
evident to learners and potential
learners.
Reporting on CWB Strategy
action plan
CWB Board minutes
Participation levels and co-
produced offers recorded in
registration and management
information system
PB national reporting
Priority: Third Sector Involvement in Community Wealth Building
Work with Third Sector Chief Officers’ Group and other
community organisations to identify opportunities to
build CWB knowledge and co-develop CWB initiatives.
Increase the knowledge,
understanding and co-
production opportunities for
Third Sector organisations in
Community Wealth Building
activities.
Reporting on CWB Strategy
action plan
CWB Board minutes
Participation levels and co-
produced offers recorded in
registration and management
information system. 
Case studies
Impact statements
Year 1 Outcomes – Community Wealth Building
Priority: Celebration of Community Achievement in CLD events and Awards
CLD partners will adopt a collective approach to the
promotion and recognition of CLD in North Ayrshire and
the impact of the work. 
We will provide a clearer picture of the difference CLD is
making in North Ayrshire for senior leaders, funders, staff
and volunteers. 
We will improve the profile of the
impact of CLD and the offer
provided by partners.
CLD will be more visible and
recognisable to learners and
partners.
Participation levels in CLD across
all domains of practice, through
the management and
information data
Annual celebration and awards
event
Priority: Establish New Protocols and Process for Data Sharing by Introducing New Management Information System
Priority: Pathway for Learning
CLD partners will work together to co-produce with
learners an offer to ensure that prospective and current
adult learners are clear about the programmes and
pathways available and evident to them. 
We will use a range of methodologies to promote the
pathways and the offer.
We will improve the pathway to
the learning offer to current and
new learners to increase their
knowledge of the offer which is
co-produced based on expressed
need and the range of
methodologies.
Participation levels and learners
journeys data.
Case studies
Impact statements
CLD KPI’S
Quarterly LPP reports
Implement the new management information system.
CLD partners will review how we can use the data and
other information.
We will create approaches to extend data sharing,
analysis, and reporting across all CLD partners.
CLD partners will make
improvements to better
demonstrate their collective
impact and progress over time.
Quarterly LPP reports
6-month review of the new
management information system
What we will do What we aim to improve How will we measure
Year 1 Outcomes – Unmet Need
62 63150

Page 151

64 65
Priority: Staff and Volunteer Development
Ensure that our workforce including our volunteers, are
supported to know and understand the community in
which we work and develop and support collaborative
working approaches.
Encourage and promote the opportunities that
registration with the CLD standards Council provides to
members.
Provide a menu of training opportunities as identified in
the workforce survey.
Managing challenging behavior 
Intergenerational working 
Digital upskilling 
Naloxone Training 
Mens health and wellbeing 
Governance for Community organisations
To improve staff and volunteers
confidence and skills
development. 
The opportunity for personal and
professional growth.
Training offer and participation
Number of staff and volunteers
accessing further and higher
education
Number of CLD staff and
volunteers registered with CLD
Standards Council
What we will do What we aim to improve How will we measure
Year 1 Outcomes – Workforce Development
Documents
& Policies
151

Page 152

66 67
A Changing Nation: How Scotland
will thrive in a digital world 
DigiStrategy.FINAL.APR21.pdf (www.gov.scot)
Adult Learning Strategy 2022 – 2027
The National Performance Framework and
Understanding the Impact of Community-Based
Adult Learning - Adult learning strategy 2022 to
2027 - gov.scot (www.gov.scot)
Community Learning and 
Development Case Studies
Link to host on the CPP website
Cyber Resilient Scotland: strategic framework:
Action Plan 2021 – 2023 
Annex C: Action Plans 2021-23 - Cyber Resilient
Scotland: strategic framework - gov.scot
(www.gov.scot)
Education Scotland CLD Progress visit report for
North Ayrshire 2023
Progress Visit Report - 31/10/23
(education.gov.scot)
Education Service Improvement
Plan 2023-26
Document.ashx (cmis.uk.com)
North Ayrshire Council Intergrated Impact
Assessment
North Ayrshire Children’s 
Services Plan 2023 - 2026
2023-12-04-BM-P16-NA-CSP-Plan-2023-2026.pdf
(nhsaaa.net)
North Ayrshire Child Poverty Action Plan
NACChildPovertyReport22.pdf
(northayrshire.community)
North Ayrshire Community Planning Partnership
- Local Outcomes Improvement Plan 2022 –
2030
LOIP 2023 (northayrshire.community)
North Ayrshire Corporate 
Parenting Plan 2023 – 2026
North Ayrshire's Corporate Parenting Plan (north-
ayrshire.gov.uk)
North Ayrshire Council Plan 2023 – 2028
Our Council Plan (north-ayrshire.gov.uk)
North Ayrshire Environment Sustainability and
Climate Change Strategy
Environmental Sustainability & Climate Change
Strategy (north-ayrshire.gov.uk)
North Ayrshire Youth Citizenship and
Participation Strategy 2021 – 2025
Youth Participation Strategy (north-
ayrshire.gov.uk)
Planning for Change a Review of Community
Learning and Development Plans in Scotland
2018 – 2021 
Planning for Change, A Review of Community
Learning and Development Plans in Scotland
2018 – 21 | Resources | National Improvement
Hub (education.gov.scot)
Scotland’s Public Health Priorities
Scotland's public health priorities - gov.scot
(www.gov.scot)
152

Page 153

153

Page 154

154

Page 155

NORTH AYRSHIRE COUNCIL
29 October 2024
Cabinet
Title: Proposals for Community Investment Fund (CIF)
Expenditure
Purpose: To determine applications by Locality Partnerships to allocate
CIF funding to proposed projects.
Recommendation: That Cabinet:
a) Reviews the enclosed applications from the North Coast
and Cumbraes and Three Towns Locality Partnerships
in line with CIF criteria;
b) Approves the CIF application in relation to Largs
Development Trust; and
c) Approves the CIF application in relation to Ardrossan
Winton Rovers Community Interest Company.
1. Executive Summary
1.1 Within its budget for 2017-18, North Ayrshire Council provided a funding allocation for
the creation of an innovative fund to enable communities to address the priorities they
have identified through Local Planning Partnerships and within the context of North
Ayrshire Community Planning Partnership’s Fair for All Strategy and the Council’s
Community Wealth Building Strategy. In June 2021, Cabinet approved a further £1m
top-up for the funding, with a further £2m added in November 2021.
1.2 Locality Partnerships have subsequently continued to work on their local action plans
and are refining proposals for expenditure in line with their locally identified needs. It is
a testament to the dedication of the Locality Partnerships and their community partners
that proposals are continuing to emerge to provide creative approaches to addressing
local challenges.
1.3 This report brings forward proposals which respond to the specific needs of the local
community, and which have been developed based on local circumstances and
opportunities.
2. Background
2.1 Within its budget for 2017-18, North Ayrshire Council provided an allocation for the
creation of an innovative fund to enable communities to address the priorities they have
identified through Locality Planning Partnerships and within the context of North
Ayrshire Community Planning Partnership’s Fair for All Strategy and the Council’s
Agenda Item 8
155

Page 156

Community Wealth Building Strategy. A further £3m was added to the funding in 2021,
to be distributed among Localities as follows: 
2.2 It was agreed that the CIF awards would range between £5,000 and £100,000 for the
community organisations, as defined in the CIF guidance, in order to support
proposals and projects that connect with: 
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis;
• The Community Planning Partnership and Locality priorities;
• North Ayrshire Council’s values, priorities, and business objectives; and
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies; 
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities;
• Provide long-term, sustainable, positive results for the greatest number of people
possible;
• Exhibit project and/or organisational innovation in their approaches to their work in
their way of addressing community challenges and in their request to Locality
Partnerships and the Council;
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon requests) and efficiently and effectively managed. This can
include an organisation to be created to deliver the project;
• Include options or potential for NAC and CPP employee engagement and
volunteering where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular
basis.
Locality Value of
CIF from
first funding
allocation
(2017-18)
Expenditure
to date
Value of CIF
from second
funding
allocation
(June 2021)
Value of CIF
from third
funding
allocation
(Nov 2021)
Total balance
available
Irvine £754 000 £958 358 £290 000 £580 000 £665 642
Kilwinning £286 000 £322 190 £120 000 £240 000 £323 810
Three
Towns
£598 000 £994 411  £240 000 £480 000 £323 589
Garnock
Valley
£390 000 £456 103.04 £150 000 £300 000 £383 896.96
North Coast £468 000 £595 852 £170 000 £340 000 £382 148
Arran £104 000 £125 079 £30 000 £60 000 £68 921
TOTAL £2 600 000 £3 455 993.04 £1 000 000 £2 000 000 £2 147 827.96
156

Page 157

2.3 The proposal development and application process has been agreed as follows: 
• Locality Partnerships should continue to engage with their communities
and stimulate interest in the CIF. Each Locality Partnership will then
strategically access the applications, make links, and look at the funding
‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a
full application form, which they will decide upon before making a proposal to
Cabinet for final approval.
• The proposal will go to the next suitable Cabinet for final approval. 
2.4 The enclosed applications at Appendices 1 and 2 have been developed by
community partners and North Ayrshire Council officers and are now
recommended for approval by Cabinet. 
2.5 The North Coast & Cumbraes Locality Partnership 
The allocation and funds committed to date are outlined in the table below. 
The North Coast & Cumbraes Locality Partnership CIF
allocation to date    
£978,000 
Organic Growers of Fairlie  £22,800  
Clearer Minds    £30,200  
Millport Town Hall   £200,000  
Sing Your Song (WKCIL)   £14,892  
Locality Priorities Worker   £35,948  
West Kilbride Technical & Creative Training Programme   £76,605  
Locality Priorities Worker - extension of support   £41,871  
West Kilbride Sports Club  £6,750
Largs Scottish Women’s Institute  £15,393
Locality Priorities Worker - extension of support  £52,000
Parent Network Scotland  £99.393 
Balance  £382,148 
2.6 Proposal: Largs Development Trust (£92,865) (see Appendix 1) 
2.6.1 Largs Development Trust (LDT) are currently in the process of becoming a Scottish
Charitable Incorporated Organisation (SCIO). Their membership includes individuals who are
part of Largs Community Council, Largs First Responders, Largs Thistle Community Club,
Green Futures, the Visit Largs Group and other local people who are interested in the objective
of promoting the area for the benefit of the inhabitants. 
2.6.2  The group are requesting funding to develop a community space and services within
a town centre retail unit, and for equipment to improve access to Largs Vikingar swimming
pool. 
2.6.3  The community space they plan to open, which will be called “The Space”, will have
the following aims:
157

Page 158

• To provide a physical space for community activities and accessible advice services
• To provide credit union services 
• To host and operate a community radio station
The Space will be a base for initiatives by LDT to take place, as well as to provide access to
and signposting to other vital services such as Debt Advice and Women’s Aid, as well as the
opportunity to hire meeting rooms or desk space. The Credit Union will operate a satellite
service from here and the community radio will be based within it. Overall it will offer a physical
space where community members can come together to connect, share resources, collaborate
on projects, and engage on projects that will benefit the community as a whole. 
2.6.4  In addition, the funding requested would support the installation of a set of custom-
made, double-width removable pool steps in the Largs Vikingar pool, which will allow a greater
number of Largs residents to enter the pool independently and discreetly. At present, those
who cannot access the pool using its existing pool ladders have to travel around an hour to the
nearest accessible pool, or use an “Oxford Dipper” system which requires staff to operate and
takes around 20 minutes to enter the pool. The new removable pool steps would offer a more
dignified and independent way for people with disabilities to enter the pool. 
2.6.5  The funding would be used for set up and three years of operating costs for The Space
and the community radio station, as well as the cost of purchasing the pool steps. A full budget
breakdown is provided as part of the application at Appendix 1. Funding will be released in
phases over the three years of the project as outlined in this breakdown. LDT has carried out
engagement with local groups and potential partners who would make use of The Space, and
the intention is to engage further with the community to shape the programme of services
offered to them. 
2.6.7  The proposal support the Locality Partnership’s priorities, in particular those relating to
improving access to financial services, increasing social inclusion and improving mental
wellbeing as well as directly supporting the Community Planning Partnership’s priority of
wellbeing. 
2.7. The Three Towns Locality Partnership 
The allocation and funds committed to date are outlined in the table below. 
The Three Towns Locality Partnership CIF allocation to date:  £1,318,000
Ardrossan Community Development Trust   £25,000 
Three Towns Growers £100,000 
The Training Station £50,000 
Ardrossan Castle Heritage Society £17,912 
Raise Your Voice For Ardeer  £100,000 
Ardrossan Community Sports Hub  £43,320 
Winton Circus Playpark  £48,288 
Ardrossan Community Development Trust - Development Officer  £53,100 
Raise Your Voice For Ardeer – increased cost for multipurpose hub) £130,000 
Ardrossan Community Association (Whitlees) 
£48,586
Ardrossan Community Sport - Winton Park 3G £100,000 
CHAP – Advice Outreach 
£45,767 
Ardrossan Scouts  £100,000 
Saltcoats Active Lifestyle Group (SALT)  £45,600
Stevenston Community Council – Street Signage  £29,988
Three Towns Community Shed  £56,850 158

Page 159

Balance £323,589
Hayhocks Tenants and Residents Association project – funding
ringfenced by Locality Partnership while match funding sought  £100,000
Uncommitted Balance £232,589
2.8.Proposal: Ardrossan Winton Rovers Community Interest Company (£100,000) (See
Appendix 2) 
2.8.1. Ardrossan Winton Rovers Community Interest Company are a long established
community based football club, providing access to football activities from Mini Kickers for
toddlers through to senior Mens’ and Womens’ teams. At present they have 171 players, with
a further 58 projected new youth players in the coming season. The club have been in existence
for 124 years. 
2.8.2. They are seeking funding to replace the stand roof, which is currently in a state of
disrepair and corrosion. This would mean not only improved facilities for viewing, but also
continued access to physio, changing & referee rooms, showers, toilets, and the pitch entrance
area along with 2 meeting rooms. This would form part of an updated 3G facility in development
which will also be available to other groups and clubs within the Ardrossan community to make
use of. The group recognise the need to ensure that the facility will offer real opportunities for
children and young people to become engaged in football and other sporting activities - not
only within their Club structure but also in the wider community. 
2.8.3. At present, the youth teams travel outwith the Ardrossan area to train. This creates
additional expense as well as travel time in an area where many people are on low incomes.
Engagement carried out through a survey established likely positive impacts on participation
on sports and physical activity generally (92%), on pride in the area (90%) and on the health
and wellbeing of people in the community (92%). 
2.8.4. The proposal supports the Locality Partnerships aims of promoting the local economy
and tourism, regenerating community facilities, increasing civic pride and community
engagement and improving community wellbeing, also linking to the Community Planning
Partnership priority of wellbeing. 
3. Proposals 
That Cabinet:
(a) Reviews the enclosed applications from the North Coast and Cumbraes and
Three Towns Locality Partnerships in line with CIF criteria; 
(b) Approves the CIF application in relation to Largs Development Trust; and
(c) Approves the CIF application in relation to Ardrossan Winton Rovers. 
4. Implications/Socio-economic
Duty Financial
4.1 CIF funding is allocated within existing resources. 
Human Resources 
4.2 None. 
159

Page 160

Legal 
4.3 None. 
Equality/Socio-economic
4.4 The purpose of Locality Planning is to reduce inequalities, increase community
cohesion and advance community empowerment. Each of the CIF proposals is
tested against that purpose before being presented to Cabinet. 
Climate Change and Carbon 
4.5 Environmental and sustainability along with climate change and carbon reduction
opportunities are considered in relation to each CIF application. This proposal
supports recycle and re- use principles. 
Key Priorities 
4.6 The proposals contained within the report support the North Ayrshire Council Plan
strategic aims: 
• To transition to a wellbeing economy, delivering prosperity, wellbeing and
resilience for local people.
• We will have active, inclusive, and resilient communities.
• A Community Wealth Building Council that is efficient and accessible,
maximising investment and focusing resources towards our priorities. 
Community Wealth Building 
4.7 The application supports the following pillars of community wealth building: 
• Financial Power: Listening to communities and local enterprises to maximise
the impact of financial investment and grow local business, enhance innovation
and empower communities.
• Land and Assets: Maximising the function and ownership of local physical
assets for the benefit of communities and enterprises. 
5. Consultation 
5.1 The proposals contained within this report have been developed by the Locality
Partnerships, through consultation with local people, including young people. 
David W. Hammond 
Executive Director (Communities and
Housing) 
For further information please contact Rhonda Leith, Head of Service
160

Page 161

(Connected Communities), on 01294 324415. 
Background Papers
Appendix 1: CIF Application Largs Development Trust
Appendix 2: CIF Application Ardrossan Winton Rovers Community Interest Company
161

Page 162

The CIF will support proposals and projects that:
 Connect with:
o The North Ayrshire Fair for All Inequalities Strategy;
o the Community Planning Partnership (CPP) and Locality priorities; and
o North Ayrshire Council’s (NAC) values, priorities and business objectives.
 Fulfil a compelling need and do not duplicate existing services or facilities;
 Provide long-term, sustainable, positive results for the greatest number of people
possible;
 Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council;
 Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project;
 Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
 Include measurable outcomes and can report to NAC on outcomes on a regular basis.
When to apply and how?
 LPs should continue to engage with their communities, and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’.
 If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval.
 The finalised proposal will go to the next suitable Cabinet for final approval.
 Forms should be returned to your Locality Officer, by email if possible:
Louise Riddex
Locality Officer (Kilwinning & North Coast)
Economy and Communities
Community Development Team
St John's Primary School
Morrison Avenue
Stevenston
KA20 4HH
Email: lriddex@north-ayrshire.gov.uk
Tel: 01294475913
Mob: 07980964858
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf
1. Details of your organisation
Appendix 1
162

Page 163

Name of Organisation
Largs Community Development trust 
Postal Address for Correspondence
Click or tap here to enter text. 
Name of Contact Person  Alex Rhind/ Heather Meldrum 
Position in Organisation  Treasurer 
Telephone Number 
Email Address 
2. Brief description of your organisation 
Please include its legal status, aims and objectives, activities or services provided and how
long it has been in existence. 
Largs Community Development Trust :(LCDT) The Trust is in the process of completing
its application to become a SCIO. Membership at the moment consists of individual
members of Largs Community Council and other interested parties including people from
Largs First Responders, Largs Thistle Community Club, Green Futures, Visit Largs group
and other. 
The group meet monthly in the Vikingar, Largs. There are currently 10-14 attending the
meetings with an additional 6-8 non attending people who are assisting with the work of the
group. 
The principal objectives of the Trust are to promote the area for the benefit of the
inhabitants. This includes areas such as education, culture and leisure, tourism and social
facilities, development of local businesses and the protection and enhancement of the
natural environment. To date the activities of the group have been focused on enhancing the
local environment and a mapping exercise of issues affecting local businesses. 
3.Title and summary of proposal 
Tell us about your idea. Please describe in as much detail as possible, what the funding will
be used for. 
Please include: 
• where it will be held / delivered
• who is your target audience
• who will benefit from it and how
• any partners that are involved. 
Funding will cover a Community space and services { as detailed below}
Plus equipment to improve access for Largs Vikingar swimming pool. 
163

Page 164

The funding will cover a three year period enabling the LCDT to lease and operate an
intergenerational Community space at 36 Boyd Street Largs.(THE SPACE). The space will
primarily be for the use of local residents and organisations to connect, share resources,
collaborate on projects, engage in activities that benefit Largs as a whole, and access
services missing in Largs since CAB closed. 
The Space will have three main aims: 
• To provide a physical space for community activities and accessible advice services.
• To provide credit union services
• To host and operate a community radio station. 
Together with community organisations and residents we aim to deliver an inclusive
programme of activities and services. 
The location– The Space will be located on Boyd Street, Largs. This location was chosen
for the following reasons: 
• It is an area in need of regeneration. It has a number of vacant shop units and we
predict The Space will increase footfall and give the area a lift.
• Clients accessing services such as debt management and Women's aid wish to do
so in a discreet manner and not on the High Street.
• Value for money- the cost per square footage of property was substantially cheaper
on Boyd Street. 
The property; 
The property currently consists of a reception area and 3 separate rooms. LCDT continues
to consult with the landlord over the final design to ensure that the final room specifications
are relevant to the programme of use. As a consequence, there are a number of changes
and improvements that are anticipated including
• Consultation booth/room(s) offering confidential areas
•  General access and security arrangements
• Soundproofing. 
The Space will provide: 
• Available safe meeting space for community organisations and volunteers. 
• A place for / Information / Signposting. 
• A base for the LCDT to “to undertake initiatives throughout Largs to enhance the
educational, economic, cultural, environmental and social potential of residents
enabling them to turn the community’s vision into reality. 
• A space to develop appropriate links / engage with other community based
organisations. i.e. OIR/ CC.
164

Page 165

•  A space to provide services from third party organisations such as Debt
management/ Citizens Advice and Women's Aid making access to these services
more accessible. 
• Desk / room  hire by the hour. To offer well presented, accessible spaces with good
access to internet at reasonable rates. 
• To place to provide satellite space for Credit Union services. 
• A place to host and operate Largs community radio station. 
The Space will offer: 
• A welcoming, friendly, fun and positive place to meet for any social demographic. 
• A safe place that can help lessen loneliness and social isolation of individuals in the
community.  
• A place to hot desk/ room hire by the hour available at affordable cost in line with the
ethos and values of the Trust.  There are no such facilities available in Largs that
offer desk/ room rental.   
• A point of contact for information sharing and signposting. 
• Offer a job club. 
•  Access to volunteering opportunity. 
• A place to engage with local young people to develop initiatives targeted at their own
age group including training etc. 
• An environment where residents young and old can  work together, learn new skills
and build confidence. 
• A service to assist local residents build savings and financial resilience. 
We will access the collective knowledge, expertise and experience of members of the
community so that they can help each other deliver a successful community resource. 
165

Page 166

4. What difference will this project make within the locality and to local
services and programmes? 
Please include: 
 The outcomes you aim to achieve
 How you will approach reducing inequality
 How this proposal fits with the Locality Partnership priorities of 1. Improving access to
financial services 2. Increasing social inclusion 3. Improving mental well-being 4.
Supporting skills and work opportunities 
The Space will: 
Offer a physical space where community members can come together  to connect, share
resources, collaborate on projects, and engage on projects that will benefit the community as
a whole. The range of services offered are listed above and are not exhaustive. 
The Credit Union will: 
Working alongside Scot West Credit Union (our chosen organisation responsible for
delivering credit union services) we will improve access to financial services  and provide
volunteering opportunities, supporting skills and opportunities. The credit union will signpost
people to other organisation who can provide debt or benefit advice. 
We will encourage those who live or work within the common bond (as defined by Scot West
Credit Union} to join and aim to assist people who have difficulty opening or accessing a
high street bank account. We will encourage children's accounts and promote regular
savings habits. We would like to explore ways of working with the local schools around this.
We will encourage responsible borrowing. 
The aims of Scot west Credit Union are not commercial (although they must be solvent and
operate on a sound commercial footing); they will help its members save and borrow –
especially people with very little money, who might be excluded from saving or borrowing
with more conventional financial institutions. 
The Credit Union will provide: 
•  A physical place to encourage members to save regularly and build financial
resilience. 
•  Signpost members in need of financial advice and help.
•  Provide loans at low interest rates. 
166

Page 167

The Credit Union will offer:
•  Flexibility to save what you can, however small, when you want to. 
• It will provide an alternative to payday loans. 
• The Credit union will be open to assisting members on a low income 
• People without a previous borrowing history.
• People with a poor credit history.
• It will provide volunteering opportunities. 
The radio station will: 
The radio station will be at the heart of the community and will support the local economy
with outside broadcasts at local event e.g. Viking festival / food festival and the switching on
of the Christmas lights etc. Hopefully we can reach more people and inspire them to attend
these events. 
We will encourage all demographic groups to participate in the running and presenting of
Largs Radio Station. The radio station will be housed within The Space however we
envisage that a satellite studio will be established within Largs Academy. 
Radio station engagement 
Communication with Glyn Roylance form Associated Broadcast Consultants
suggests that we would be best running an initial pilot using internet radio and podcasts.
This give us a feel for engagement: we are therefore seeking seed funding for this element
of the project. It would require software, PC’s and mixing equipment within The Space and
the Largs Academy studio. We are also seeking to engage local radio producers on the
project to get input and help with planning and technical skills, and possibly training if they
are willing. Initial contact has been made with IrvineBeat FM who started on their journey ten
years ago and now have a very successful station. 
We could utilise the helter skelter funding which is currently waiting to find a suitable project,
and have engagement from Largs Academy staff who wish to be fully involved with a
satellite studio in the school. As well as working with Largs Academy we also aim to
encourage young people who have previously disengaged from formal education to come
and participate/ volunteer with the radio station, enhancing their employability, critical
analysis and communication skills, building confidence, self-esteem, and motivation which
will support them into employment or further education 
To ensure all local residents have the opportunity to participate we will work in conjunction
with other local organisations and will have an intergenerational ‘open door’ policy that
serves to bring the community together in one location. 
167

Page 168

We will encourage a wide range of topics to be broadcast i.e., 
1) Local music groups
2) Offering our local churches the opportunity to have their sermon broadcast on Sundays.)
3) Radio book club.
4) Live outdoor broadcasts at events.
5) Largs players performing radio plays.
6) Phone in / chat show.
7) Local information/ traffic news etc. 
The programmes will be inclusive and content directed by the community led by LCDT. 
What engagement has taken place in relation to the project? 
Please include the number of people who have been engaged with or consulted as well as
the range of people.
We have engaged and had positive discussions with Largs Action Group (the group set up
for the business meetings) . 
We have also engaged with the Largs Writers group again with very positive feedback.  Also,
the group set up to look at what we can do to improve the footfall around the Boyd Street/
Nelson Street area. ( The Brisbane Quarter) have been very encouraging in their enthusiasm
for the project. 
Discussions have also taken place with OIR who want more detailed information on what
services would be offered. 
It is the intention to put some information in the library this week with contact details should
anyone wish to get in touch. 
Should our bid be successful we intend to ask residents what additional services they would
like to see The Space host, and be guided by their suggestions. 
Credit Union engagement 
We have identified a lack of banking facilities for people who have issues accessing
mainstream banking and lending. Largs Foodbank and Scot West Credit union have told us
that there is a need which is only going to increase. We are also aware that mainstream
banks are closing, with RBS closing 2 October. This will leave Largs and North Coast with
only Bank of Scotland. 
We know that IT and online literacy, as well as use and access to technology by
disadvantaged groups and older people are huge barriers to banking access. The Credit
Union would be able to make a real difference to this situation which is likely to just get
worse. 
The project has been discussed at LCDT meetings and meetings organised by the business
group and the Brisbane Quarter group. In addition the free press has ran articles about the
proposal.
168

Page 169

3. How will the project be managed? 
Please include: 
 How the finances will be managed
 Does the proposed project contribute to volunteering or employment opportunities in
North Coast? Please include the number of volunteering opportunities and
employment opportunities
 If there are any staff requirements, please outline your HR plans 
• As The Space  is made up from a constituent range of facilities and services yet to
be constructed there is no relevant or trading history to draw on. All finances
associated with The Space will be run and managed by the Community led by a
vibrant and active development trust ( LCDT). 
•  Accounts  for LCDT will be produced in line with the requirements of the charity
Commission. All regulatory obligations will be adhered to. 
• The group aims to generate a range of income sources to cover its running cost
including grants, donations stemming from LCDT membership and other funding
sources. 
• The Credit Union run by Scot West ( hosted within The Space and supported by
Largs volunteers) will be managed in accordance with their regulatory requirements. 
• LCDT will manage the other projects and are currently seeking opportunities to
initiate a number of social action projects which may attract third party resources.
Examples include funding for crime reduction initiatives, postcode and big lottery
169

Page 170

funding, wind farm funds, local supermarket funds. A small income could be generate
by room/ desk hire. 
• The Space will open up volunteering opportunities in terms of staffing  and more
specific learning and skills opportunities in terms of the credit union and the radio
station. We aim to follow the five key principles set out in the Scottish Governments
Formal Volunteering Framework. 
• Whilst volunteering is the key driver in the setting up and development of The Space
it is the intention to seek funding for a coordinator to be based out of The Space This
post will be critical to act in an overview capacity and coordinate the different
activities and flow of information generated by the Trust, while identifying new
sources of funding and helping to promote The Space. 
Swimming pool steps. 
An ‘Oxford Dipper’ chair hoist is used to give access for people with disabilities 
(bottom left, shown used in another pool).
Typically transfers take up to 20 minutes per person and require one or two pool attendants.
 . Important limitations
Unlike modern infinity pools, the access space around this pool is very tight, measuring 1.5
to 2m wide or even less. (See the terracotta tiled area shown top left for an indication.)
The pool also has an older-style ‘scum channel’ which extends under the access space from
the pool edge by about 20cm.
This makes installing fixings for equipment designed for modern pool environments very
difficult if not impossible. 
170

Page 171

Why is this a problem?
We know that users who can’t manage the pool ladders simply self-select and don’t even
bother visiting this pool: the very groups of people that would benefit most from swimming
are therefore most excluded from it. 
• For many people with disabilities, pool-based exercise may be the only form of
exercise easily open to them.
What are we proposing?
• Installation of a set of custom-made, double-width (970mm+) removable pool
steps will  allow a greater percentage of Largs residents to enter the pool autonomously and
discreetly, even if we can’t fit a more autonomous pool lift at this time.
• Water can be the only place where people who are restricted to sitting much of the
time experience any form of bodily freedom to move independently, offering important
physical and psychological benefits.
• Swimming can be very sociable form of exercise that lends itself to solo and group
activity at individual levels, making it excellent for not only physical but mental health.
Would be-swimmers have to travel an hour’s bus journey to Greenock or Irvine for
alternative facilities with steps and more autonomous access, if they even bother.
4. Amount of funding being requested
Please supply details of funding being requested and any other funding you have had over
the past 5 years, both financially and “in kind”.
Amount of funding requested (£) £92.865.00
Please give a breakdown of cost and recent quotations where appropriate.
See attached budget sheet
Monitoring and evaluation process
Please include detail on the monitoring and evaluation processes planned or in place.
To access progress and identify challenges LCDT will collate data and insight in a timely and
accurate manner each month, quarter and year to permit Trust assessment and feedback for
reporting, planning and decision making purposes.
User satisfaction Issue survey/ feedback forms
171

Page 172

Social impact/ value Total visits/ engagement by
project category
Social demographic
breakdown by project
category
Awareness survey
Engagement in education/
skills learning/ volunteering
Financial performance Monthly review of expenditure
and income.
172

Page 173

1 
Budgetary estimate for Credit union/ Multi use space 
One time set
up costs 
Year 1 Year 2 Year 3 
Computes x 2
stationary etc
printer 
£2.500   
IT maintenance £700 £700 £700 
Brand design/advertising £1.500   
signage £1,000   
Community engagement £250   
training £1,000   
Shop alterations inc. electrical
points/ phone/ internet
IT security
desk locks
£5,000   
furniture £750   
contingency 10% 10% 10% 
£13,970 £770 £770 
TOTAL x 3
years
£15,510     
173

Page 174

2
Budgetary estimate for Pilot Radio station
One time set
up costs 
Year  1 Year 2 Year 3 
OFCOM application £600 £600 £600 
Studio equipment
mixing desk
softwear
screens x3
mix box x2
desk 
£4,000   
Transmission equipment/ indoor/
outdoor £2,000   
Engineer costs £2,000   
signage £1,000   
training £2,000   
Soundproofing room/ booth £2,000   
mast £2,000   
Sockets/ internet £1,000   
contingency 10%   
TOTALx3 years £19580 less £9.580 sought from
other sources     
Centre/ Credit     
174

Page 175

3
union/Radio
station running
costs 
rent £6,000 £6,000 £6,000 
utilities £3,200 £3,200 £3,200 
Stationary/
network area storage  x 4 discs
£2,000 £500 £500 
Broadband
webhosting
365 licence etc
£2,500 £2,500 £2,500 
Security alarm £500 £500 £500 
Monitoring/ evaluation tools/
survey monkey licence £150 £150 £150 
MCPS {copyright)
PPL
£400 £400 £400 
Insurance for property/ fire etc £500 £500 £500 
Professional fees £1,500 £1,500 £1,500 
Employment liability insurance
Public Liability insurance
Professional indemnity insurance
£2.000 £2.000 £2.000 
contingency 10% 10% 10% 
Centre
running
costs X 3
Years
£58,755 £20,620 £18,975 £18,975 
An addition application of £30,000 for a member of staff will be submitted to other
funding streams.
175

Page 176

4
Budgetary estimate for Pool Steps
£8,600 ex VAT (as a budgetary estimate)
Pool steps, 10x tablets and Year 1 ‘Good Boost’ software subscription 
Total
Manufacture and delivery of pool steps to KA Leisure specification £3,600
Specification and installation of steps at Largs Vikingar! pool
Estimated at ONE person, £600 per day: 
• Site inspection, specification and RAMS statement
Half a day’s work £300
• Step installation
Half a day’s work £300
10 x waterproof tablets 
Year 1 ‘Good Boost’ software subscription
£2,400
£2,000
Budgetary estimate £8,600 
1. Estimate of Good Boost ANA programme cost to KA Leisure Year 1+
We anticipate the £2,000 ongoing ‘Good Boost’ software subscription costs and contingency1 for 10x tablets will be
covered by a modest increase in users at the pool: 
(1) 15% contingency allowed annually for tablet repairs and loss  
(2) 10x tablets and Year 1 Subscription funded by this CIF bid 
Estimate of Good Boost ANA programme cost to KA Leisure Year 1+
We anticipate the £2,000 ongoing ‘Good Boost’ software subscription costs and contingency1 for 10x tablets will be
covered by a modest increase in users at the pool: 
Tablet cost Subscription Contingency1 Total KA cost Break-even
(per month)3
Year 1 £2,4002 £2,0002 £360 £360 1 visit 
per tablet
Year 2+ – £2,000 £360 £2,360 7 visits 
per tablet
contingency 10% 15% 15% 15% 
176

Page 177

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
The CIF will support proposals and projects that:
• The North Ayrshire Fair for All Strategy, with consideration for how applications
contribute to community support for the cost-of-living crisis.
• The Community Planning Partnership and Locality priorities.
• North Ayrshire Council’s values, priorities and business objectives.
• The Community Wealth Building and Environmental Sustainability and Climate
Change Strategies.
And will also:
• Fulfil a compelling need and not duplicate existing services or facilities.
• Provide long-term, sustainable, positive results for the greatest number of people
possible.
• Exhibit project and/or organisational innovation in their approaches to their work in their
way of addressing community challenges and in their request to Locality Partnerships
and the Council.
• Come from (an) organisation(s) that is financially viable (can provide financial
statements upon request) and efficiently and effectively managed. This can include an
organisation to be created to deliver the project.
• Include options or potential for NAC and CPP employee engagement and volunteering
where possible; and
• Include measurable outcomes and can report to NAC on outcomes on a regular basis.
When to apply and how?
• LPs should continue to engage with their communities and stimulate interest in the
CIF.  The Locality Partnership will then strategically assess the applications, make
links and look at the funding ‘in the round’.
• If the partnership supports a bid then the group will be encouraged to submit a full
application form (attached), which they will decide upon before making a proposal to
Cabinet for final approval.
• The finalised proposal will go to the next suitable Cabinet for final approval.
• Forms should be returned to your Locality Officer, by email if possible:
Name Gordon Cowan
Locality Officer Interim/Partial(Three Towns Locality)
North Ayrshire Council
St John’s Primary School
Morrison Avenue
Stevenston
KA20 4HH
Email: colinferris@north-ayrshire.gov.uk
Tel: 475912/212
Mob: 0758461250
Appendix 2
177

Page 178

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
For more information see the guidance form here: http://www.northayrshire.community/wp-
content/uploads/sites/60/2018/06/community-investment-fund-guidance-notes-17-12-17.pdf
1. Details of your organisation
Name of Organisation 
Ardrossan Winton Rovers Community Interest Company
Postal Address for Correspondence
Click or tap here to enter text.
Name of Contact Person Edward Gibb
Position in Organisation Company Secretary
Telephone Number Click or tap here to enter text.
Email Address Click or tap here to enter text.
2. Brief description of your organisation
Please include its legal status, aims and objectives, activities or services provided
and how long it has been in existence.
The objects of the Company are to carry on activities which benefit the community
and to carry on the business of a semi professional football club with Adult men’s 24
players, Adult ladies first team ( 23 players), Under 20’s men’s team ( 20 players),
Men’s Saturday Amateur team ( 22 players), Men’s Sunday Amateur team ( 18
players), Under 16 girls(18 players), under 14 girls (20 players), under 12 girls (20
players). Mini kickers and 2020’s teams to be started September/October as is
traditional (players approx, mini kickers 24, 2020’s approx. 18).  We will also be
introducing new teams in September for Girls age under 10’s and under 8’s with
projected combined numbers of 40 players. The numbers using the facility and
associated with the club is projected at 213 with the club building up the boys clubs
over the next few years and projecting future use of 5/6 teams and 100 + players. 
171 players at present, with a further 58 projected new youth players in the coming
season. Total 229 projected associated players.
The facility will also be available for use by other local groups, youth and adult
football teams within the area including teams from TASS Thistle and Ardeer Thistle.
178

Page 179

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
The Community Interest Company will provide at Winton Park a stadium and
recreation ground and prepare such ground for the purposes of sporting &
community activities such as the community fete, fundraising events and school
activities and sports day. To carry out sports coaching and to maintain all properties
associated with the provision of said coaching and activities. To promote for the
benefit of the inhabitants of Ardrossan and environs by associating the residents,
and all local groups including religious and voluntary organisations, educational and
local authorities in a common effort to provide facilities in the interest of social
welfare for recreation and leisure time, with the object of improving the condition of
life for local inhabitants. These facilities are free to use and available to the members
of the public at large and to individuals and groups having need of such facilities as
aforesaid by reason of their youth age, infirmity or disablement, poverty or social and
economic circumstances. 
The organisation has been in existence since 1900, a total of 124 years. 
3. Title and summary of proposal 
Tell us about your idea. Please describe in as much detail as possible, what the
funding will be used for. 
Please include: 
• where it will be held / delivered
• who is your target audience
• who will benefit from it and how
• any partners that are involved. 
The stand roof at Winton Park is in a state of disrepair with roofing being corroded,
the metal pillars which hold the roof in place are corroded and require replacement
rather than repair. We consulted Mr Eric McMillan from McMillan & Cronin architects
who advised replacing the roof and pillars as the only viable option. But that this
would not be financially viable. Mr McMillan has produced plans which have been
agreed by the AWR CIC that will reduce the capacity but make the structure safe and
would provide many years of further use for the facilities contained within. These are
physio, changing & referee rooms, showers, toilets, and pitch entrance area along
with 2 meeting rooms. 
These facilities are also part of the overall project at Winton Park in creating facilities
for the town of Ardrossan that will include a new synthetic floodlight artificial surface
with training equipment and modular changing rooms with areas to meet in. The
179

Page 180

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
following information is taken from members of youth academy members past and
present who are also inhabitants of the 3 towns. 
• A significant majority of AWRYA teams reported great difficulty in hiring
training facilities and a pitch for home games in Ardrossan – none of the 15 teams
plays in Ardrossan itself, the majority playing elsewhere in the Three Towns and 6 of
the teams travelling as far as Kilwinning (6.2 miles), Irvine (8.6 miles) and Kilbirnie
(11.1 miles) to play home matches.
• All 15 Managers reported difficulties travelling to train or play home games -
both logistically and in terms of costs, with lower turnouts when travel is involved as
a result.
• Significant expenditure (c £50-70k pa) is made by the AWYA teams outside of
Ardrossan in facility bookings and ancillary spend whilst teams travel for home
games and training – representing leakage from the local community.
• There are no Astroturf facilities within the Three Towns that are suitable in size
or surface to accommodate 11 aside league games on.
• There is obvious under provision of facilities within Ardrossan and the Three
Towns when mapped against those available in other North Ayrshire towns such as
Kilwinning, Irvine, Dreghorn and Kilbirnie
• Ardrossan contains significant pockets of deprivation with low income and
poverty being a barrier to participation in sport, a factor which must inform our
approach. 55% of Ardrossan’s population live within data zones within the worst 20%
in Scotland and Winton Park itself is located in an area within the worst 2%.
• The development of a new community asset would help give the AWRYA
teams an identity and an affinity to the club and town – with a local survey
establishing likely positive impacts on participation on sports and physical activity
generally (92%), on pride in the area (90%) and on the health and wellbeing of
people in the community (92%). 
4. What difference will this project make within the locality and to local
services and programmes? 
Please include: 
• The outcomes you aim to achieve
• How you will approach reducing inequality
• How this proposal fits with the Locality Partnership priorities 
Project Outcomes 
180

Page 181

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
In developing the proposals we will deliver the following activities and outcomes
within the local community
• Develop and operate a sustainable 3G facility that is able to meet the
requirements of the wider local community as well as the Ardrossan Winton
Rovers Youth Academy for a safe, welcoming and accessible venue
• To promote excellent physical and mental health through participation in football,
sport and physical activity.
• Enable more children and young people to engage in and enjoy positive sporting
and diversionary activity.
• Increase the number of players, coaches and clubs playing football and
progressing through recognized national pathways.
• Design and deliver specific programmes for a range of different groups within the
community and link with related clubs and promote the new facility as a venue for
local social and leisure events
• Create employment and volunteering opportunities, developing skills for life,
learning and work.
The new roof protects the infrastructure contained within i.e. meeting rooms,
toilets, changing rooms which will be used by the wider community. These
facilities will required to be managed and therefore will create employment and
volunteering opportunities.
• To improve access to sport and physical activities facilities and environments.
• Increase the level of community engagement with the Winton Park facility and
establish a reputation for quality and good practice.
• To promote a strong, resilient, sustainable, and supportive community which has
pride in its achievements.
AWR CIC recognize the need to ensure that the facility will offer real opportunities for
children and young people to become engaged in football and other sporting
activities at the facility - not only within their Club structure but also in the wider
community. This is in line with Three Towns Locality Partnership objectives of
regenerating community facilities, improving community well-being and increasing
community engagement and pride.
North Ayrshire Community Planning Partnership - Local Outcomes
Improvement Plan
The Community Planning Partnership for North Ayrshire are the body charged with
ensuring life is "Fair for All" in North Ayrshire. The Improvement Plan has 4 priority
areas:
- A Working North Ayrshire
181

Page 182

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
- A Healthier North Ayrshire
- A Safer North Ayrshire
- A Thriving North Ayrshire - Children and Young People 
Under the Healthier North Ayrshire Priority, the ambition is for all people who live in
North Ayrshire to be able to have a safe, healthy and active life – this includes
building on the strengths of local communities; promoting good physical and mental
health and wellbeing; and supporting more people to be physically active and be at a
healthy weight. 
Under the Safer North Ayrshire Priority, the ambition is for North Ayrshire to be a
safer place to live, residents feel safer and communities are empowered - which
includes supporting communities by an asset based approach. 
How does our application sit within the locality priorities: 
1. Promoting the local economy and tourism
Investing in the infrastructure at the facility will allow the CIC to host
training, matches, football camps, festivals and community activities such
as the Winton Fete, these events bring teams, fans, and tourists to the
area, boosting local businesses. 
2. Regenerating community facilities
Winton Rovers Football club have been in existence for 125 years and are
a much-loved local institution. They have become a Community Interest
Company  and have moved from a grass to a synthetic surface to promote
usage, the facilities within the ground are available for use at a vastly
reduced cost to every communtiy group within the 3 towns and the
regeneration will allow use for generations to come. The regeneration will
provide a community facility that local residents can be proud of, have
ready access to and where cost and travel are no longer real barriers to
participation 
3. Increasing civic pride and community engagement
The project will increase civic pride and community engagement by
providing a sporting facility within the town that is of the highest possible
standard, a facility that local people can be proud of. This will also lead to
local people using the facility through a more active lifestyle and via the
use of meeting rooms and community events that will take place within the
new facility. The CIC will create a community user group that will lead on
use, engagement and future planning. 
182

Page 183

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
4. Improving community wellbeing
The new facilities will encourage the engagement of local people in a more
active lifestyle through sporting activities and community activities such as
football memories and other programmes that will promote not only better
physical health but better mental health through combating social isolation
and providing an inclusive environment where people can meet, feel
welcome and be more involved.
The availability of the Winton 3G facility will make it much easier for young people
and adults to participate in the recommended level of physical activity per week.
Improved self-esteem, confidence, self-efficacy and perceived competence result
from long-term participation in sporting activities and team sports. The project will
also work with local schools to use the appeal of sport within the education
curriculum to engage disaffected pupils and improve academic performance and
commitment to continuing education.
5. What engagement has taken place in relation to the project?
Please include the number of people who have been engaged with or consulted as
well as the range of people.
A professional firm of market researchers IBP Strategy & Research were employed
to carry out a market research survey mid 2022 of Stakeholders &  local residents re:
attitudes to development proposals; and potential community impacts. 189
Responses were received, and Participants were asked to what extent do you think
a project such as this would have an impact on the following things within Ardrossan
and the immediate surrounding area?
The findings were
Across the board, a very substantial proportion of respondents indicated that they
expected the project to have a positive impact on participation on sports and physical
183

Page 184

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
activity generally (92%), on pride in the area (90%) and on the health and wellbeing
of people in the community (92%). A smaller proportion indicated that they felt the
project would have a substantial impact on reducing crime and anti-social behaviour
in the area (73%), whilst 89% felt it would improve the quality of life generally. These
very positive views were reflected across all identified demographic groups. 
We carried out a survey of the Youth academy teams at the time (mid 2022) with
approx. 325 members. The survey showed the following responses:
• No sheltered areas for non-playing staff/volunteers/subs/parents. Cold and
wet days in Scotland can sometimes lead to people not bothering turning up.
• Distance travelling frequently results in non-attendance - we see much better
turn outs when we are local to Ardrossan
• Some Girls can’t pay the expense so unfortunately miss out. It’s a real issue.
• Travelling for home matches should not be happening, it is totally
unacceptable a town the size of Ardrossan, kids cannot play or train in the
town due to lack of appropriate decent facilities
The administrators of these teams also commented when asked if they would like
to see any other facilities on site. Answers included:
• Modular dressing rooms and meeting space to meet up before and after
games/training. 
• Areas to hold fundraising events and meetings with teams and parents.
• Food and beverage machines or place to get snacks.
• Some sort of shelter from the elements as the weather can be brutal
particularly for non-playing people.
• A boot room for the academy players to store their boots and equipment
in. 
• Maybe a laundry area that could be on site so that teams can wash strips.
• Better toilet facilities. 
6. How will the project be managed? 
Please include: 
• How the finances will be managed  
• The finances will be saved in the CIC bank account, and we will hire an
architect to manage the design and construction of the stand roof. This will
184

Page 185

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
involve our architect certifying contractor payments that will then be followed
by an invoice from the contractor to the club who will then release payments.
We will use our accountants Anderson McDonald to manage all monies and
to produce associated financial spreadsheets for the project to ensure prudent
financial management. On top of this our board of directors will sign off any
expenditure.
• Does the proposed project contribute to volunteering or employment
opportunities in Three Towns? Please include the number of volunteering
opportunities and employment opportunities
• If there are any staff requirements, please outline your HR plans 
The replacement stand roof will add to the overall project, the facilities contained
within will remain the responsibility of AWR CIC, they will ensure the maintenance of
the standroof and the facilities contained within. AWR CIC will make the stand and
facilities available on demand to the community at large and via ACSH. 
The overall project will Design and deliver specific programmes for a range of
different groups within the community and link with related clubs and promote the
new facility as a venue for local social and leisure events, create employment and
volunteering opportunities, developing skills for life, learning and work. Improve
access to sport and physical activities facilities and environments and increase the
level of community engagement with the Winton Park facility and establish a
reputation for quality and good practice. Which will create volunteering opportunities
(6-10 positions), developing skills for life, learning and work along with full time
positions (2-3). 
The replacement of the stand roof is a fundamental part of the overall projected
allowing the protection as a roof to the structures underneath and therefore allowing
AWR CIC to provide these facilities for community use and to compliment the wider
project. 
185

Page 186

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
7. Amount of funding being requested 
Please supply details of funding being requested and any other funding you have
had over the past 5 years, both financially and “in kind”. 
Amount of funding requested (£) 100,000 
In the past the CIC received from NAC 
Ardrossan Common Good Fund
2019/20 - £2,000 towards Annual Fete
2023/24 - £4,000 towards Annual Fete 
Three Towns & Arran Community Benefit Fund
2021/22 - £3,900 for club refurbishment Feasibility
2023/24 - £1,969 towards Annual Fete 
RJ McLeod construction are currently carrying out in kind work at the ground as part
of the groundworks in preparation for the placement of new changing rooms. 
Please give a breakdown of cost and recent quotations where appropriate. 
This project has been priced by McMillan Cronin architect, overall project which is expected to
be between £115- £125,000. 
186

Page 187

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP 
187

Page 188

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP 
With VAT Included at 20% of £104,770.00 = £29,540.00. Total project amount £134,310. 
Match funding will be provided from: The CIC £5,000. 
The CIC is VAT registered and will reclaim the VAT to reinvest in the project. 
188

Page 189

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
8. Monitoring and evaluation process 
Please include detail on the monitoring and evaluation processes planned or in
place. 
Ardrossan Winton Rovers Community Interest Company will ensure an effective
monitoring and evaluation programme is in place to provide the feedback necessary
to allow us to run the facility effectively and secure the impacts we want to deliver for
the community. This will include: 
Area What Will be Monitored
Use of the
facility
Weekly recording of:
• No of Games and Training Sessions Users
• No of Players/Participants
• % Occupancy levels in Peak and Off Peak periods 
Use of information to monitor uptake as per business plan
projections and to identify excess demand / access problems 
Beneficiaries Weekly recording of sociodemographic information on
participants including age, gender, residence, disability, protected
characteristics. 
Use of information to test who is using facility, ensuring maximum
penetration within local community; help guide marketing and
promotion activity to underrepresented groups; and identify need
for creation of specific initiatives to address any issues arising. 
Financial
Sustainability
• Monthly financial reports noting Peak and off peak income
from facility hire; event income; grant revenue funding
received – all against target
• Monthly financial reports noting expenditure against budget. 
Use of information to monitor financial position, identify variances
against budget and need to take remedial actions where
required. 
Satisfaction
Levels
Quarterly surveys of facility users to gain feedback on services
provided – from booking systems, access arrangements and
affordability and use of spectator areas. 
189

Page 190

COMMUNITY INVESTMENT FUND 
****  LOCALITY PARTNERSHIP
Use of information to address concerns and review any policies
or procedures necessary to ensure safe, welcoming, affordable
and accessible facility.
Volunteering 6 monthly monitoring of:
• Nos and Characteristics of volunteers; no of volunteer
hours; types of volunteering opportunities
• Questionnaires gathering information from volunteers on
impact of these opportunities on skill levels, confidence,
self-esteem and future aspirations. 
Use of information to ensure facility is creating opportunities
which are vital to long term success and supporting the
development of volunteers. 
Wider
Community
Use
Monthly recording of amount and type of use by different groups
within the community including social and leisure use e.g.
walking football, by local schools, community sessions (e.g.
unemployed groups, walking clubs, youth groups), boot camps,
aerobics, coaching courses etc. 
Use of information to gauge level of wider use made of facility by
community and associated satisfaction levels. 
Impacts Anticipate carrying out annual survey work with facility
users/participants, member clubs, wider community clubs and
other community users. 
Use of information to test if facility has:
• improved access to pitches for training and home games and
resolved current barriers.
• increased participation levels for different groups
• impacted positively on teams/participants affinity and
association with Ardrossan and Winton
• Impacts on participants physical and mental health and
wellbeing 
Beyond this at the end of Year 3 we would anticipate
commissioning a wider, independent community survey to
establish:
• resident’s perceptions of the facility. 
• how well it has been received by local people. 
190

Page 191

COMMUNITY INVESTMENT FUND
****  LOCALITY PARTNERSHIP
• the contribution it has made in terms of terms of increasing
opportunities for participation in football wider physical
activities, community use and in delivering health benefits.
• and whether it has impacted on overall quality of life and pride
in the community.
191

Page 192

192