NORTH AYRSHIRE COUNCIL 
27 August 2024 
Cabinet 
Title:    Regeneration Delivery Plan Action Programme and
Funding Proposals Update 
Purpose:  To seek approval for funding proposals for the Regeneration
Delivery Plan. 
Recommendation:  That Cabinet: 
(a) Approves the Regeneration Delivery Plan funding proposals
as detailed at Appendix One;
(b) Notes the update on previously secured or applied for funds
provided at Appendix Two; and
(c) Provides delegated authority to the Executive Director (Place)
to agree changes to the funding allocations in Appendices
One and Two in consultation with the Portfolio Lead as
required. 
1. Executive Summary 
1.1 The Regeneration Delivery Plan was approved by Cabinet in March 2021. This sets out
our priorities for delivering on the regeneration ambitions of the Council Plan and
Community Wealth Building strategy, working in partnership with communities. 
1.2 The Plan focusses on the delivery of physical regeneration across North Ayrshire
through an ambitious project based rolling action programme. It informs our priorities
for securing and delivering against external funding sources including Scottish and UK
Government funds. This report provides an update on progress to date. The
regeneration funding landscape in 2024/25 has changed considerably compared to
previous years. The delivery of several of the proposals outlined in the report is
therefore subject to the external funds being confirmed within appropriate timescales. 
2. Background 
2.1 The Council has placed the regeneration of communities at the heart of its agenda.
This focus is reflected within the priorities of the Council Plan and Community Wealth
Building Strategy. The Regeneration Delivery Plan sets out our priorities for delivering
on these ambitions and was approved by Cabinet on 23 March 2021. 
2.2 The Plan focuses on the delivery of physical regeneration in the period 2021 to 2026.
Informed by stakeholder consultation, reviewing existing community priorities and the

Page 2

output of previous consultations, it aims to address local priorities, support changes
within communities and deliver a well-being economy. 
2.3 Action in 2023/24 substantially focussed on maximising the impact and leverage of
investment including securing sources of external funding to support and accelerate
delivery. This includes the: 
• Delivery of a 2-storey business pavilion at Annickbank Innovation Campus creating
350 square metres of modern, energy-efficient floorspace with an EPC rating of A+
and Platinum sustainability label.
• Further delivery of Phase One of the Lochshore Park Masterplan including:
planting 17,000 trees; creation of a 2,400 tree community woodland; completion of
the 5km loop; and starting construction of the Play at the Hub facilities. 
• Provision of 9 grant awards to community organisations under Round One of the
Communities and Place Fund as part of the Shared Prosperity Fund (SPF)
Investment Plan. This includes awards to the Scottish Maritime Museum to deliver
a community engagement programme; Ayrshire Community Trust to deliver a
support programme; and Beith Playpark Action Group for a zip wire in Orr’s Park,
Beith.
• Provision of grants to 18 sites through Stage 1 of the Repurposing Property Grant
Fund (RPGF) with a total value of £269,352. Of these, 8 sites have completed their
Stage 1 projects including: Geilsland House Beith; Coach House, Largs; and
Millport Chapel, Beith.
• Upgrade of 27 bus stops throughout North Ayrshire and the creation of 2 new bus
stops and an improved bus turning facility.
• Completion of the £0.964m Ardrossan Low Carbon Hub including Harbour Path,
North Crescent Coastal Path Phase 1, Harbour EV Hub, South Beach EV Hub,
Ardrossan South Beach Bike Hub and Ardeer Peninsula Bike Hub.
• Delivery of the £0.191m ‘Beat the Street’ project through Paths for All’s Active
Nation Fund in collaboration with Argyll and Bute Council to encourage active
travel and physical activity. 
• Delivery of a £1.343m programme of active travel design and works under the
Scottish Government’s Cycling, Walking and Safer Routes programme. 
2.4 The Regeneration Delivery Plan is delivered through an ambitious rolling action
programme. This approach seeks to ensure that the list of projects never exceeds a
realistic assessment of capacity, with projects being prioritised annually. It informs our
priorities for securing and delivering against a range of external funding sources. 
2.5 The action programme approved at Cabinet in June 2023 for 2023/24 and 2024/2025
was prepared to align priorities with resource. This was informed by an assessment of
progress to date, local priorities, project deliverability and funding. The implementation
of action programme projects aligned to competitive funding sources will however be
dependent on the success of the funding applications. 
2.6 Significant levels of funding have been secured or are anticipated to support delivery
in 2024/25. The details of these funds and the proposed approach to their expenditure
are provided at Appendix One. These include the: 
• Scottish Government’s Place Based Investment Programme (provisional)
• Scottish Government’s Vacant and Derelict Land Fund
• Crown Estates Scotland’s Net Revenue Allocation

Page 3

• Scottish Government’s Active Travel Infrastructure Fund and Direct Resource
Grant 
Updates on previously secured or applied for funds are provided at Appendix Two
including the: 
• UK Government’s 5G Innovation Regions Programme
• UK Government’s Smart Infrastructure Pilot Programme
• UK Government’s Shared Prosperity Fund
• Scottish Government’s Regeneration Capital Grant Fund
• Scottish Government’s Vacant and Derelict Land Investment Programme
• UK Government’s Levelling Up Round 3 
• UK Government’s Long-Term Plan for Towns
• Strathclyde Partnership for Transport’s Capital Programme
• Scottish Government’s Community Bus Fund
• Transport Scotland’s People and Places Programme 
2.7 The current economic climate has resulted in several of the external funds that are
available to support the Regeneration Delivery Plan having reduced budgets or being
paused in the current financial year. Combined with increased project costs, this will
potentially result in smaller numbers of projects successfully securing funding and
being delivered. 
2.8 Many of the above funding awards are single year and their formal confirmation has
been delayed. This presents a significant risk to the associated project delivery.
Officers have reviewed proposals informed by this and have undertaken preparatory
works where possible to try and mitigate the impact of this. There will however remain
a risk to delivery given the limited time between approvals being received and delivery
deadlines. 
2.9 Further consultation and engagement will be undertaken with local communities,
stakeholders and Elected Members through the detailed development of any
successful projects. A further report on progress of the RDP will be provided to a
future Cabinet. 
3. Proposals 
3.1  That Cabinet: 
(a) Approves the Regeneration Delivery Plan funding proposals as detailed at
Appendix One;
(b) Notes the updates on previously secured or applied for funds provided at Appendix
Two; and
(c) Provides delegated authority to the Executive Director (Place) to agree changes to
the funding allocations in Appendices One and Two in consultation with the
Portfolio Lead as required.

Page 4

4. Implications/Socio-economic Duty 
Financial 
4.1 The Regeneration Delivery Plan aims to build on and maximise the impact of the
investment being made through a variety of sources including the Ayrshire Growth
Deal, the Council’s Capital Programme, and the Strategic Housing Investment
Programme (SHIP). It also seeks to lever private funding and investment into North
Ayrshire. It informs priorities for securing and delivering against external funding
sources. The implementation of action programme projects aligned to competitive
funding sources will be dependent on the success of the funding applications. Whilst
resource costs can be capitalised to support delivery, future ongoing revenue
implications need be fully considered on a project by project basis. 
Human Resources 
4.2 The Regeneration Delivery Plan projects will be delivered through the existing
Regeneration Team resource. Opportunities to secure funding for additional staff
resource to support delivery will be investigated on a project by project basis as
required. 
Legal 
4.3 The legal implications of all Regeneration Delivery Plan projects will be considered
through their development. Legal agreements will be developed on a project by
project basis as required with support from Legal Services. Negotiation will be
required in relation to land and building acquisitions with support from the Council’s
Legal Services and Property Management and Investment Service. Mechanisms such
as Compulsory Purchase Orders will be considered on a case by case basis, where
considered appropriate. 
Equality/Socio-economic 
4.4 The Regeneration Delivery Plan assists in meeting our socio-economic duty as set out
in the Fairer Scotland Duty. It seeks to reverse economic, social and physical decline
and reduce socio-economic disadvantage. It will tackle long-term vacant and derelict
land and buildings thereby reducing their levels and impact on communities. It aims to
build community wealth and tackle local deprivation through the regeneration of our
communities by maximising the potential of our land and assets and those of anchor
institutions. 
An initial screening will be undertaken to establish if an Equality and Children’s Rights
Impact Assessment is required for projects on a case by case basis. 
Climate Change and Carbon 
4.5 The Regeneration Delivery Plan aligns with the Sustainable North Ayrshire Strategy
for 2024-2027. Furthermore, it aligns with the commitment to reduce carbon
emissions through declaration of a Climate Emergency.

Page 5

Key Priorities 
4.6 The Regeneration Delivery Plan has been informed by the priorities identified within
the Local Outcomes Improvement Plan and Locality Partnership priorities. The
implementation of the Plan will contribute to achieving the Council Plan priorities that
focus on Wellbeing, Communities and Local Democracy, Climate Change, and A
Sustainable Council. 
Community Wealth Building 
4.7 The Regeneration Delivery Plan sets out our priorities for delivering on the ambitions
within the 2024-2027 Community Wealth Building Strategy. Its delivery will have a
significant positive impact on the Council’s ambitions across the pillars of: 
• Land and Assets: by supporting equitable land development and the development
of underutilised assets for community and business use.
• Procurement: by contributing to the development of the procurement wave plan;
through the inclusion of appropriate community benefit of local supplier clauses
within projects; and by considering phasing and programming of projects to create
local supply chain opportunities and support delivery by smaller scale and local
contractors where appropriate.
• Fair Employment: by supporting the creation of employment opportunities
particularly within the construction sector. Where North Ayrshire is procuring
services, through our enhanced Community Benefits approach we will seek to
ensure the creation of local training and work experience opportunities.
Consideration will also be given to delivery through employability programmes
where appropriate.
• Financial Power: by investing in localities and leveraging external national
investment into North Ayrshire.  
5. Consultation 
5.1  The Regeneration Delivery Plan was the subject of extensive consultation including
workshops with Council Officers; workshops with Elected Members; reports to and
feedback from North Ayrshire Ventures Trust and the Community Wealth Building
Expert Panel; and public engagement via Consul. It was also informed by the Locality
Partnerships’ priorities and previous public consultation exercises including Charettes. 
5.2 The funding proposals outlined at Appendix One have been informed by this
consultation. Further consultation and engagement will be undertaken with local
communities, stakeholders and Elected Members through the detailed development of
the identified projects. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Claire Fitzsimmons, Senior Manager,
Regeneration, on 01294 324766.

Page 6

Background Papers
Cabinet Report – Regeneration Delivery Plan, 23 March 2021 
Cabinet Report – Levelling Up Fund, 15 June 2021
Cabinet Report – Levelling Up Fund – Round 2, 2 November 2021 
Cabinet Report – Regeneration Delivery Plan Update, 22 February 2022
Cabinet Report – Regeneration Delivery Plan Funding Proposals, 07 June 2022
Cabinet Report – Regeneration Delivery Plan Action Programme and Funding Proposals,
30 May 2023
Cabinet Report – Local Transport and Active Travel Strategy 2023-2028, 3 October 2023
Cabinet Report – Vacant and Derelict Land Strategy 2023-2028, 3 October 2023
Cabinet Report – Long-Term Plan for Towns, 5 December 2023
Cabinet Report – Levelling Up Round 3, 23 January 2024

Page 7

Appendix One – Regeneration Delivery Plan Funding Proposals 
The following provides a summary of each of the funds and the proposed approach for
2024/25. The proposals have been identified from the Regeneration Delivery Plan action
programme and an assessment of the: 
- Projects’ stage of development;
- Fit with the fund objectives and priorities;
- Potential benefits;
- Budget available;
- Ability to secure match funding; and
- Deliverability of the project(s) within funders’ timescales. 
This approach aims to implement a range of projects that deliver impactful improvements in
line with the Regeneration Delivery Plan and the various funding streams’ ambitions. Where
there is an underspend within one of the allocations in 2024/25, it is proposed that the
Executive Director (Place) will reallocate any underspend across the other identified actions
following engagement with the Portfolio Lead. 
Place Based Investment Programme 
The Scottish Government established the five-year £325m Place Based Investment
Programme (PBIP) in 2021/22. Underpinned by the Place Principle, this aims to support
community-led regeneration, town centres and the 20-minute neighbourhood ambitions.
The main objectives of the Programme are to: 
• Link and align place-based initiatives and establish a coherent local framework to
implement the Place Principle;
• Support place policy ambitions such as town centre revitalisation, community led
regeneration, 20-minute neighbourhoods and Community Wealth Building;
• Ensure that all place-based investments are shaped by the needs and aspirations of
local communities; and
• Accelerate the ambitions for tackling inequality and disadvantage, wellbeing and
inclusive economic development, net zero, community involvement and ownership 
A £0.761m allocation was anticipated for the current financial year. In June 2024, however,
Scottish Government advised that unfortunately they are not yet able to confirm the Place
Based Investment Programme (PBIP) allocation of capital funding for local authorities for
2024/25. 
In July 2024, Scottish Government further advised that Ministers had authorised the release
of an element of the funding, up to a maximum value of 50%, to protect the value for money
of projects already in progress. This would equate to c.£0.380m for North Ayrshire noting
that at this time funding will not be released to support any new projects. Councils were
asked to submit a list of which priority regeneration projects that are active and in need of
funding to ensure continued progress or completion. 
The following projects were submitted to Scottish Government for consideration, with an
outcome anticipated Autumn 2024.

Page 8

Project 2024/25
Request
2025/26
Request
Total
Request
Kyle Road Phase 2
To support the delivery of 1200m² new Class 4/5/6
business space capable of sub-division. Funding
required to support delivery due to the Scottish
Government decision to pause the VDLIP for
2024/25. Match funding provided by LUF3 (subject to
award confirmation) and VDLF. 
£100,000 £75,000 £175,000
Lochshore Improvements
To support works to conclude Phase 1 of the
Lochshore Masterplan, including detailed design and
delivery of access, green space, infrastructure and
facility improvements and to support environmental
improvements and activity undertaken by the Friends
of Lochshore community group and Community
Engagement Officer. 
£75,000 £100,000 £175,000
Repurposing Property Grant Fund
To continue the implementation of the Repurposing
Property Grant Fund which support landowners and
community groups to bring back vacant land and
properties to positive use by funding feasibility
studies, investigation work, detailed designs,
statutory approvals and delivery. 
£75,000 £125,000 £200,000
Local Place Plan Support
Per the Local Place Plan ‘Handbook’, this funding will
provide support to communities to enable them to
prepare a Local Place Plan. New planning legislation
introduces a right for communities to produce Local
Place Plans, providing the opportunity for
communities to feed into the planning system with
their own ideas and proposals for the development
and use of land. This will provide community bodies
with financial support for a range of expenses and/or
specialist support, including for community and
stakeholder engagement and facilitation; plan
preparation; and specialist advice. 
£50,000 £0 £50,000
Garnock Valley Place Framework Project Support
To provide funding to community organisations to
conclude the development of priority projects
identified through the Place Framework. 
£50,000 £0 £50,000
Workplace Active Travel Development Fund
To continue the implementation of the Workplace
Development Fund to support existing workplaces
engaged with the Travel Smart project and are
looking to install eligible items to support Active
Travel within the workplace. This will support Net
£30,000 £30,000 £60,000

Page 9

Zero targets by reducing car use within the
workplace for one day a week, our target audience
would also be employees commuting by car within a
20 minute neighbourhood distance to their
workplace. 
Kilwinning Abbey Tower
To support repairs to Kilwinning Abbey informed by
the Kilwinning Charrette and Place Framework. 
£50,000 £50,000
Total £0.380m £0.380m £0.760m 
Vacant and Derelict Land Fund 
The Scottish Government's Vacant and Derelict Land Fund (VDLF) aims to tackle the
presence of long-term vacant, for 15 years or longer, and derelict land in Scotland. In doing
so, it aims so stimulate economic growth, job creation, an improved environment and
quality of life. From its inception in 2007, access to the Fund was restricted to 5 local
authorities to focus the available financial resource and prioritise authorities most impacted
by both the extent of vacant and derelict land and levels of deprivation. 
A review in 2015, resulted in North Ayrshire Council benefitting from access to the Fund
from the financial year 2016/17. The other four authorities which currently benefit are South
Lanarkshire, North Lanarkshire, Fife and Glasgow City Councils. Funding is limited to sites
that have been vacant for at least 15 years and are between 0.1ha and 99ha in size, with a
preference of Council ownership or a landowner agreement in place. It cannot be used on
housing or infrastructure projects such as transport or flooding. 
A Local Delivery Plan requires to be submitted to the Scottish Government to allow
Ministerial approval of the expenditure of the funding in 2024/25. In developing the
proposals for this, several factors have been considered, including the: 
• Scottish Government funding criteria;
• Economic development focus of the funding;
• The priority sites identified of Irvine Enterprise Area, Ardrossan Campus Site, Lochshore
and Irvine Harbourside and their stage of development;
• Alignment with the North Ayrshire Regeneration Delivery Plan (2021) and Vacant and
Derelict Land Strategy (2023);
• Deliverability of projects within the funding timescales;
• Need to balance feasibility and site preparation work, with interventions that see
physical space and employment created;
• Need to secure a spread of interventions in terms of type and geography; and
• Scottish Government’s aspiration for circa 25% to be spent on greening projects. 
An allocation of £0.963m has been confirmed for 2024/25. Aligned with the actions
identified in the Regeneration Delivery Plan and Vacant and Derelict Land Strategy, the
following projects are proposed for submission as local delivery plans. These will be
formatted as delivery plans and submitted to the Scottish Government, subject to Cabinet
approval:

Page 10

Project Allocation
Kyle Road Phase 2
To support the delivery of 1200m² new Class 4/5/6 business space
capable of sub-division. Funding required to support delivery due to the
Scottish Government decision to pause the VDLIP for 2024/25. 
£600,000
Lochshore Improvements
To support to detailed design and delivery of access, green space,
infrastructure and facility improvements and to support environmental
improvements and activity undertaken by the Friends of Lochshore
community group and Community Engagement Officer. 
£150,000
Stalled Spaces Fund
To support the visual improvement or naturalisation of sites, including
grant funding to community groups for temporary repurposing of sites. 
£113,000
Development Funding
To support development work to inform proposals for implementation in
future years. This will include a further allocation to the Repurposing
Property Grant Fund. 
£75,000
Digital Improvements
To improve the digitisation of Vacant and Derelict Land information and
improve accessibility to customers. 
£25,000
Total £963,000 
Should funding not be forthcoming from the PBIP, it is proposed that £175,000 of the VDLF
allocations across the projects be reallocated to Kyle Road Phase 2. 
Crown Estates Scotland Net Revenue Allocation 
This is the fifth tranche of payments to local authorities from the net revenue generated by
the Crown Estate Scotland’s marine assets out to 12 nautical miles. Allocations should be
used to deliver coastal community benefit and offer a high level of flexibility. Effectively, the
money can be used in any way that contributes to the benefit of coastal communities.
Payments are made in arrears following the finalisation of Crown Estate Scotland’s annual
accounts. The 2023/24 allocation (to be spent in 2024/25) is £214,699. 
An annual report is required by CES on the benefits to the blue economy that the funding
has supported. These can include: 
• Environmental Enhancement
• Emissions Reduction or Removal of Waste
• Jobs
• Tourism
• Skills Development
• Diversification Projects
• Investment For Community Purpose
• Climate Change Adaptation

Page 11

The table below outlines the proposal for the expenditure of £164,699 of the allocation. The
proposals aim to support the delivery of actions identified in the Regeneration Delivery Plan
that align with the blue economy benefits identified in the annual report. A further report will
be brought to Cabinet for approval of the expenditure for the balance of the funding. 
Project Allocation
SMART Infrastructure Pilot Programme (SIPP) – Great Harbour 
To establish a digitally advanced and sustainable destination. Additional
funding will build on this investment in passive SMART poles and support
advanced connectivity solutions for tourism, active travel, augmented reality
and STEM trails. If funds allow, these solutions will be scaled across other
key tourism sites. 
£64,699
Local Heritage Centre Asset Improvements
To support proactive improvement works to NAC heritage centre assets to
preserve the assets and ensure it is available for generations to come.
Assessment to be undertaken to prioritise interventions. 
£50,000
Millport Marina Project Masterplan
To advance a master plan for the Millport harbour. This wider piece of
regeneration work is outwith the AGD allocated funds and direct scope of
the marina project. The site’s relationship with Millport town centre is critical,
requiring masterplanning and consultation. 
£25,000
Irvine Beach Pavilion Redevelopment 
To develop design proposals for the redevelopment of the Pavilion to inform
the business case. The Ayrshire Growth Deal Great Harbour development
recognised the building within its setting as a significant market opportunity
for a coastal restaurant/café, whilst retaining the current provisions. A
proposal was developed for a shared community and commercial facility,
taking advantage of the location and vistas. 
£25,000
Total £164,699 
Active Travel Infrastructure Fund (ATIF) Tier 1 and Direct Resource Grant (DRG)
Transport Scotland (TS) on behalf of the Scottish Government established the Active Travel
Transformation Project to ensure that their increasing investment in Active Travel results in
transformative change. The previous Cycling, Walking and Safer Routes (CWSR)
programme and Sustrans’ Places for Everyone Programme have been replaced with a new
3-tier delivery model under the umbrella of Active Travel Infrastructure Fund. These are: 
• Tier 1: All Local Authorities to receive capital funding through block grant allocation
(previously CWSR). Fund objectives are to design, develop and deliver Active Travel
interventions that will enhance the safety and accessibility of existing infrastructure, or
introduce new provision to travel safely and more conveniently. Active Travel
infrastructure delivered through Tier 1 funding should adhere to the principles outlined in
the Active Travel Framework and Cycling by Design and should enable people to move
more safely between settlements and key amenities on foot, cycling or wheeling.
• Tier 2: A national annual application process for construction ready active travel projects
• Tier 3: This is still in development by TS and is likely to be similar to Tier 2, a national,

Page 12

competitive fund for the most ambitious and strategic projects. Initial indications are that
this may include public transport integration. 
The new tiered model was introduced from April 2024. As part of the transition, TS has
started to wind-down Sustrans’ Places for Everyone Programme. This will be completed by
December 2025. It is expected that Sustrans will continue to manage existing construction
projects which are programmed for completion by December 2025. During 2024/25,
Sustrans will continue to fund and manage the concept to design stages of existing
projects. 
TS will also continue to support the Direct Resource Grant (Capital) grant which allows
Local Authorities to fund a small number of capital projects such as an asset register of
active travel infrastructure and ensuring infrastructure is maintained to safe standards of
use all year round. 
A £906,949 award has been secured through ATIF Tier 1 alongside £35,452 from the
Direct Resource Grant. The table below sets out the 2024/25 proposals based on the
award value. This approach aims to support a range of eligible projects across North
Ayrshire and secure additional funding to maximise and accelerate delivery. 
Project Allocation
ATIF Tier 2 Readiness:
To finalise projects to construction ready status to enable bids to ATIF Tier
2. For example, B714 Active Travel Links, Brodick to Corrie Active Travel
Route and Eglinton Park to Irvine Road, Kilwinning. 
£132,401
Local Transport and Active Travel Strategy Delivery: 
To support delivery and implementation of the active travel strategy action
plan. For example, Stevenston to NCN73  
£340,000 
Active Travel Route Construction: 
To provide match funding to support applications to Sustrans Places for
Everyone, for example Links to Eglinton, and LUF Match Funding. It will also
support the delivery of other local active travel infrastructure. 
£245,000 
Future Years Feasibility Studies and Design Development: 
To support the preparation of feasibility studies and preliminary designs for
active travel projects. For example, Cumbrae Active Travel Study, Sharphill
to Saltcoats Railway Station, B714 Active Travel Route and Drybridge to i3
Active Travel Route. 
£140,000 
Route Monitoring: 
To support the network of pedestrian and cycle counters across North
Ayrshire including the installation of new infrastructure. 
£25,000 
Staff costs and resourcing:
To support the existing externally funded posts within the Active Travel and
Transport Team. 
£60,000 
Total £942,401 
Active Travel Infrastructure Fund (ATIF) Tier 2

Page 13

The following projects were submitted for ATIF Tier 2 funding. The outcome of the bid
assessments will be announced in due course. It is anticipated that not all the projects
below will be successfully funded as they are differing stages of readiness. Submitting
these applications however sets out the Council’s ambitions to Transport Scotland and
provides an overview of the long-term active travel pipeline projects for future delivery. 
Project Allocation
B714 Active Tavel Corridor Phase 1 £1,500,000
B714 Active Travel Links £300,000
Brodick to Corrie Cycle Path £400,000
McGavin Park £165,000
North Crescent Coastal Path - Phase 2 £450,000
Total £2,815,000

Page 14

Appendix Two – Project Updates 
5G Innovation Regions (5GIR)
North Ayrshire is the lead authority for the Ayrshire 5GIR initiative on behalf of the regional
Digital Economy workstream, the three Ayrshire councils and associated partners, including
the University of the West of Scotland (UWS), Ayrshire College, the Scotland 5G Centre
(S5GC) and the National Manufacturing Institute Scotland (NMIS). The project was
successfully awarded £3,791,000 by the UK Government’s Department of Science,
Innovation and Technology (DSIT) in 2023. All funds need to be spent by March 2025. 
The Ayrshire 5GIR vision is to become the “UK’s premier manufacturing-focused 5G hub”.
This will be driven by five transformative principles: technological excellence, a thriving
innovation ecosystem, sustainable economic growth, skills and talent development, and
influential investment strategies. Investment will be centred around three strategic
locations: the Digital Processing Manufacturing Centre (DPMC) in Irvine, the Aerospace
Innovation Hub (AIH) in Prestwick, and the Ayrshire Innovation Park (AIP) in Moorfield,
Kilmarnock. The overall project comprises the following six workstreams, three of which are
led by NAC: 
Workstream Title Lead
Organisation
Allocation
1 Digital Process Manufacturing Centre (DPMC) NAC £1m
2 Aerospace Innovation Hub SAC £0.9m
3 Small to Medium Enterprises Internet of
Things Adoption
EAC £0.45m
4 Tourism Events NAC £0.5m
5 Digital Ambassador / Immersive Learning SAC £0.3m
6 Ecosystem Development NAC - 
Smart Infrastructure Pilot Programme
£242,000 was secured from the UK Government’s Department of Science, Innovation and
Technology (DSIT), to enhance the £14m Ayrshire Growth Deal Great Harbour project. The
Great Harbour SIPP project is a transformative Digital Infrastructure initiative designed to
integrate innovative technology with our rich maritime history, creating a sustainable,
connected, and thriving waterfront destination. 
Key components include the provision of Internet of Things (IoT) sensors, CCTV
enhancements, and intelligent lighting systems. Future considerations also encompass
integrating advanced wireless connectivity solutions 5G, advanced Wi-Fi, EV charging
points and augmented reality experiences, further elevating the region's digital capabilities. 
The project aims to catalyse economic growth, enhance connectivity, attract investment
and interest from Mobile Network Operators (MNOs). It will adopt a learning-by-doing
approach which will inform a future SMART place strategy. 
Shared Prosperity Fund
The Communities and Place investment priority of the Shared Prosperity Fund aims to
enable places to invest to restore their community spaces and relationships and create the
foundations for economic development at the neighbourhood-level. Its objectives are to
strengthen the social fabric and foster a sense of local pride and belonging and build
resilient, healthy and safe neighbourhoods.

Page 15

The investment priority requires Councils to be mindful of how interventions under this
priority align with the existing funding streams received from the Scottish Government
including the Place Based Investment Programme. The alignment with Scotland’s National
Strategy for Economic Transformation (NSET) also requires to be considered to ensure that
they contribute to a fairer and more equal society, new market opportunities and productive
businesses and regions. 
Thirteen interventions are identified under the investment priority. The approved North
Ayrshire Investment Plan supports delivery of projects across the range of interventions.
The approved Investment Plan outlined that the Communities and Place investment priority
would be comprised of a: Participatory Budgeting programme; Competitive grant scheme
for communities; and Funding allocation for Council projects. 
As noted in the January 2024 Cabinet report, £160,330 was awarded to nine projects
across the competitive grant scheme at Round One. Round Two of the funding for 2024/25
had a budget of £600,000. A total of 52 applications were received with a value of £2.2M
requested.  Awards have been made to 18 groups across North Ayrshire with grants
ranging from £9,200 to £100,000. Participatory budgeting will take place in 2024, as in
2023, with support for partnership work with up to £5,000 available per project. 
Council led projects have a total budget of £219,867. These will support, as noted in the
May 2023 Cabinet report, projects which support the Regeneration Delivery Plan. An
expression of interest process has been undertaken to identify appropriate council led
projects which meet the UKSPF interventions. 
Regeneration Capital Grant Fund
The Scottish Government’s Regeneration Capital Grant Fund (RCGF) has been delivered
annually in partnership with COSLA and local government. It supports locally developed
place-based regeneration projects that involve local communities, help to tackle inequalities
and deliver inclusive growth in deprived, disadvantaged and fragile remote communities
across Scotland. 
In March 2024, Scottish Government advised that, due to the challenges which have been
set out in the Scottish Budget, the regeneration capital budget for 2024/25 would be
reduced from £62.5m to £45.8m. This has had a significant impact on the delivery of the
Scottish Government regeneration programmes including the Vacant and Derelict Land
Investment Programme (VDLIP) and the Regeneration Capital Grant Fund (RCGF).
Ministers have paused both VDLIP and RCGF in 2024/25. 
Vacant and Derelict Land Investment Programme
The Scottish Government announced a 5-year £50M competitive Vacant and Derelict Land
Investment Programme (VDLIP) in 2021/22. This aims to tackle persistent vacant and
derelict land and support place-based approaches to delivering regeneration and
sustainable inclusive growth, as part of a ‘just transition’ to net-zero by 2045. The fund
complements the Place Based Investment Programme and is open for all local authorities
in Scotland to apply. 
Potential projects were previously identified for the 2024/25 round based on the funding
criteria, level of project development and delivery timescales with Council Services. The
following applications were submitted in order of priority and invited to Stage 2 assessment: 
i. Kyle Road Phase 2 (£892,990)

Page 16

ii. 36 Bank Street Town Centre Living Pilot (£1.45M) 
In March 2024, Scottish Government advised that due to the challenges which have been
set out in the Scottish Budget the regeneration capital budget for 2024/25 has been
reduced from £62.5m to £45.8m. 
This has had a significant impact on the delivery of the Scottish Government regeneration
programmes including the Vacant and Derelict Land Investment Programme (VDLIP) and
the Regeneration Capital Grant Fund (RCGF). Ministers have now made the decision to
pause the VDLIP and RCGF for 2024/25. This means that no new VDLIP projects will be
offered funding from the 4th application round in 2024/25. The approach to the Stage 2
submissions is unconfirmed at this stage however these will be considered for
resubmission should the fund reopen. 
Levelling Up Fund Round 3
Further to the January 2024 Cabinet, an update is provided on the provisional UK
Government Levelling Up Fund Round 3 award for the Levelling Up for Ayrshire –
Commercial and Low Carbon Infrastructure project. The project seeks to deliver new
energy efficient commercial property and associated access, active travel and electric
vehicle charging infrastructure at key employment locations. 
Additional information was submitted in February and June 2024 to be assessed by the
Ministry of Communities, Housing and Local Government. The validation and onboarding
process is ongoing. In the interim, further project development has been undertaken using
existing funding sources to support the project timeline. 
Long-Term Plan for Towns
On 30 September, the UK Government announced that fifty-five towns across the UK would
benefit from up to £20 million of investment through endowment style funding over a 10-
year period. Irvine was identified as one of seven towns in Scotland to benefit from this
funding under the Levelling Up Fund. The award has now been confirmed at £19.509m. 
The Long-Term Plan for Towns seeks to place communities at the heart of the decision-
making process and to provide the funding to support delivery. The prospectus provides a
high-level framework for the investment which includes the: 
• Development of a Long-Term Plan to invest in and regenerate the town, based on
the priorities of local people and put to local people for consultation.
• Provision of £19.509M in endowment-style funding and support over ten years to
support the Plan’s delivery. This includes capital and revenue funding to provide
support and long-term certainty to deliver projects over multiple years and the
flexibility to invest in interventions based on evolving local needs and priorities. This
aims to ensure a focus on long-term strategic transformation as well as shorter-term
improvements. 
• Establishment of a Town Board including broad representation across the
community, local business, social enterprise, local authority and public sector
interests to oversee the development and delivery of the Long-Term Plan. 
• Provision of a toolkit of powers in relation to anti-social behaviour, licensing and town
centre living. 
To ensure that Long-Term Plans reflect local priorities, improvements can be identified
under three broad investment themes:

Page 17

• Safety and Security for example security infrastructure; 
• High Streets, Heritage and Regeneration such as repurposing vacant commercial
units or improving greenspaces; and
• Transport and Connectivity such as active travel or public transport infrastructure. 
Work has been undertaken to establish the Town Board and appoint a Chair to inform the
development of a Long-Term Plan for Irvine. The first Town Board met on 1 August 2024.
UK Government advised in July 2024 that the submission deadlines will be extended. We
are currently awaiting more detail on this. A report will be brought to Cabinet on the
progress of the Fund and to seek approval for the submission of the Long-Term Plan in due
course. 
Strathclyde Partnership for Transport Capital Programme
Strathclyde Partnership for Transport’s (SPT) Capital Plan sets out the funding programme
for projects to be delivered by SPT and partners on an annual basis. Priorities for funding
are informed by the National, Regional and Local Transport Strategies. For 2024/25, the
Scottish Government is currently not providing a capital allocation to support this
programme. Discussions are ongoing between SPT and the Scottish Government. 
SPT has released an indicative programme, should the Scottish Government reinstate the
funding for 2024/25. They have redefined their Category 1 and 2 criteria as follows:  
• Cat 1 – those projects deemed legally committed and/or operationally essential.
• Cat 2 – those projects not deemed legally committed or operationally essential. 
If funding becomes available during 2024/25 this will initially fund Cat 1 projects for which
funding has not yet been identified. If further funding becomes available, SPT would then
consider supporting Cat 2 projects. Bids were submitted in November 2023 and the
following projects have since been identified by SPT as Cat 2 priorities: 
Project Allocation
A841 Brodick to Lochranza Bus Route Improvements £800,000
Ardrossan Harbour Interchange £50,000
Bus Corridor Improvements £370,000
Cumbrae Ferry Bus Stop and Queuing Facilities £250,000
Irvine Station Interchange Improvements £50,000
Total £1,520,000 
Community Bus Fund
In 2023/24, Transport Scotland established the Community Bus Fund to support local
transport authorities to improve local public transport in their areas. This seeks to support
local authorities to explore the full range of options set out in the Transport (Scotland) Act
2019, including municipal bus services. It is expected that additional funding will be
provided in 24/25 however details of this are still unknown. Proposals will be developed
once further details on the level of funding and the timescales are known. 
People and Places Programme
The long-term success of Active Travel depends on a closer relationship between
infrastructure delivery and behaviour change activities. Behaviour Change programmes
remain central to the delivery of the visions set out in the Local Transport and Active Travel
Strategy, the national Active Travel Framework, and the more recently published Cycling
Framework for Active Travel.

Page 18

Transport Scotland has closed the previous Smarter Choices Smarter Places Programme
managed by Paths for All. This has been replaced by the following programmes: 
• People and Places Programme – Local Authority Direct Award (Revenue) funding to
local authorities for the purpose of maintaining support for existing roles and projects or
creating support for those deemed essential to the delivery of active travel outcomes
(primarily effecting a modal shift toward active travel for everyday journeys). 
• People and Place Programme – SPT (Revenue) funded through the Regional Transport
Partnership. SPT has agreed the priority behaviour change and access to bikes
interventions (referred to as the ‘People and Place’ programme) required for North
Ayrshire. This allows for the continuation of our Travel Smart Workplaces, General
Travel Smart Delivery and Travel Smart Communities programmes. 
• Community Projects Transition Fund: managed by Paths for All, a one-year programme,
aligned with the themes of the People and Place programme, that ensures a route to
funding for community-led projects that would previously have been supported by the
Open Fund. 
The following funding has been awarded to continue the delivery of the Travel Smart
programme. 
Fund Allocation
People and Places – SPT £157,200
People and Places – Local Authority Direct Award Fund £70,905
Total £228,105