Page 1

NORTH AYRSHIRE COUNCIL 
27 August 2024 
Cabinet 
Title:    Capital Programme and Treasury Management Performance
to 30 June 2024 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2024/25 and the associated Treasury
Management performance to 30 June 2024. 
Recommendation:  That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30
June 2024; and (ii) the forecast expenditure to 31 March
2025; and
(c) approve the virement proposal noted within the HRA
programme detailed in appendix 2; and
(d) note the estimated performance against the Prudential
Indicators set out in the Treasury Management and
Investment Strategy. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2024/25 to 2033/34 was
approved by Council on 28 February. The Housing Revenue Account (HRA) Capital
Investment Programme 2024/25 sits within the updated HRA Business Plan and was
approved by Council on 14 February 2024. 
1.2  This report identifies the current programme for 2024/25, taking account of adjustments
made to the initial budgets. The report presents the revised budgets at 30 June 2024
(Period 3) and forecast expenditure to 31 March 2025. 
1.3  At Period 3 the General Fund is forecasting a net underspend of (£0.001m) against a
revised budget of £128.134m. The HRA is forecasting a projected underspend of
(£0.771m) against a revised budget of £50.118m. 
1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £1.169m, including Shared Prosperity funding and
Scottish Government funding in relation to the Active Travel programme. 
1.5 Reviews of individual project plans have identified a number of adjustments to the
current profiles. As a result, £8.092m in relation to previously reported re-profiling from
2023/24 to 2024/25 and the acceleration of £17.891m to 2024/25 from future years has
been partly offset by the re-profiling of (£3.673m) for delivery in 2025/26 and beyond.

Page 2

1.6 Within the HRA, the Scottish Government has confirmed a £3.991m reduction in
available grant funding for the current year. The resultant reduction in expenditure
budgets has been included within the revised budget. However, detailed options to
address the impact on the Strategic Housing Investment Plan will be developed for
consideration by Cabinet during the Autumn. It is anticipated that further information will
be available from Scottish Government at that time. 
1.7 In addition, a review of delivery timescales has identified a requirement to re-profile
(£2.742m) of works for delivery in 2025/26 and beyond. This is partly offset by £0.031m
previously re-profiled from 2023/24 to 2024/25 and the acceleration of £0.052m to
2024/25 from future years. 
1.8 Ongoing uncertainty arising from inflationary pressures and other externalities continue
to impact on tender returns, the cost of materials and the cost of borrowing. Financial
risks have been identified across a number of high value projects, including the Upper
Garnock Flood Protection Scheme, Moorpark Primary School, Ardrossan Harbour
Landside works and Ardrossan North Shore development, incorporating the new
campus, however, full quantification of these risks remains an ongoing process. Council
has provided for a degree of mitigation within the overall 10-year General Services
Capital Investment Programme and the HRA Capital Investment Programme, with
significant additional revenue supports identified within the 2024/25 to 2026/27 General
Services Revenue budget. Projects will continue to be monitored closely with cost
increases met initially from the additional flexibility built into the programme. However,
any requirement for further borrowing not met from a funding source will be a matter for
Council to consider. 
1.9 The Treasury Management and Investment Strategy (TMIS) for 2024/25 was approved
by Council on 28 February 2024 and detailed the key performance indicators under the
Prudential Code for Capital Finance in Local Authorities (2021 edition). The current
estimated performance indicates that North Ayrshire Council has operated within the
treasury limits and performance indicators set out in the TMIS and the current capital
investment plans remain affordable. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2024/25 General Services budget: 
General Services Capital  2024/25
£ million
Budget as at 1 April 2024 104.655
Changes to Funding 1.066
Other Revisions to the Programme 0.103
Revised Budget 105.824
Alterations to phasing of projects 2023/24 to 2024/25 8.092
Alterations to phasing of projects 2024/25 to 2025/26 (3.673)
Alterations to phasing of projects 2025/26 to 2024/25 17.891
Budget as at 30 June 2024 128.134

Page 3

2.2 Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
Funding Body
Amount
£ million Project
UK Government 0.651 UK Shared Prosperity Fund
Scottish Government 0.320 Active Travel Tier 1
Sustrans 0.095 Links to Eglinton Park
Total Funding Adjustments 1.066   
2.3 Other Revisions to the Programme 
The programme has also been updated to reflect the undernoted adjustments: 
Funding Source
Amount
£ million Project
CFCR 0.080 Largs Seawall
CFCR 0.017 Street Furniture
Receipts 0.006 Insurance Recoveries (Vehicles)
Total Other Adjustments 0.103   
2.4 Alterations to the Phasing of Projects 
The reprofiling of £8.092m from 2023/24 to 2024/25 reflects projects not completed
within the year, or accelerated from future years, and incorporated within the 2024/25
capital programme. These were previously reported within the 2023/24 Capital
Programme performance reports: 
Project Amount
£ million
Moorpark Primary 0.683
Ardrossan New Build 0.553
Other minor adjustments (0.015)
Montgomerie Park School (4.931)
Total Education (3.710)
Other minor adjustments 0.106
Total Communities & Housing 0.106
ICT Projects 0.026
Total Corporate Services 0.026
Carefirst Replacement 0.268
Other minor adjustments (0.051)
Total HSCP 0.217

Page 4

Project Amount
£ million
Ardrossan North Shore 9.173
Largs Prom Seawall 0.711
Garrison House Project 0.634
Ardrossan Promenade 0.578
Millport Town Hall Phase 2 0.284
Vehicles 0.276
Nature Restoration Fund 0.200
Panel Reinstatement Works 0.148
Roads Remediation Works 0.106
Parking Charges & DPE 0.106
Solar PV Nethermains (0.118)
B714 Upgrade (0.156)
Roads Improvements (0.172)
AGD I3 Flexible Business Space Ph1 (0.759)
Millport Coastal FPS (2.591)
Other minor adjustments 0.889
Total Place 9.309
Flexibility Fund 1.793
Core Infrastructure 0.351
Total Other 2.144
Alterations 2023/24 to 2024/25 8.092 
A further review of individual project plans, taking cognisance of the current levels of
volatility within the construction sector, has identified a requirement to re-profile
(£3.673m) of works for delivery in 2025/26 and beyond. 
Project Amount
£ million
Ardrossan New Build (0.426)
Other minor adjustments (0.071)
Total Education (0.497)
PLI (0.107)
AGD Hunterston (0.172)
Ardrossan Cemetery Extension (0.450)
VDLF Kyle Road PH2 (0.853)
Millburn FPS (1.386)
Other minor adjustments (0.208)
Total Place (3.176)
Alterations 2024/25 to 2025/26 (3.673)

Page 5

These adjustments have been offset by the acceleration of £17.891m of expenditure to
2024/25 from future years. 
Project Amount
£ million
Kilwinning Learning Environment 0.240
Maress House 0.223
School ICT Investment 0.200
CO2 Monitors 0.103
Lockhart Campus 0.100
Other minor adjustments 0.146
Total Education 1.012
CCTV Review 0.350
Total Communities & Housing 0.350
ICT Projects 0.206
Total Corporate Services 0.206
Residential & Respite Unit 0.355
47 West Road 0.254
Other minor adjustments 0.017
Total HSCP 0.626
Solar PV Nethermains 6.042
Ayrshire 5GIR 3.791
Solar PV Shewalton 1.356
Fleet Decarbonisation 0.530
Nature Restoration Fund 0.511
Kilbirnie Cemetery 0.437
Lochshore Hub 0.395
Lighting 0.380
PBIP Kilwinning Abbey 0.235
Access Path Network Prog 0.180
AGD Great Harbour 0.155
Montgomerie Park Neighbourhood Centre 0.140
VDLF Harbour Master Office 0.132
VDLF Kyle Road Ph2 0.130
Digital SIPP Great Harbour 0.115
Dockhead St Saltcoats 0.100
Other minor adjustments 1.068
Total Place 15.697
Alterations 2025/26 to 2024/25 17.891 
2.5 These adjustments have resulted in a revised 2024/25 budget at 30 June 2024 of
£128.134m.

Page 6

2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is an increase of £23.479m from the revised budget,
including: 
Category
Amount
£ million Comments
Borrowing 7.226 Rephased aligned to projected
expenditure
CFCR 0.017 Additional CFCR Contribution
Capital Grants 15.981 Rephased and additional
government grants
Other Grants 0.255 Rephased and revised contributions
Total Funding Adjustments 23.479   
0.338 - 21.871 0.569 79.877 2.000 104.655
0.570 0.456 18.676 1.412 102.876 4.144 128.134
0.232 0.456 (3.195) 0.843 22.999 2.144 23.479
Approved
Movement
Programme @ P3

Page 7

2.8 Projected Capital Expenditure to 31 March 2025 
The projections are summarised by service in the following table:   
Service / Category
Approved
Budget
2024/25
£ million
Carry
Forwards
and
Adjustments
£ million2
Revised
Budget
2024/25
£ million
Projected
Expenditure
/ Income to
31 March
2025
£ million
Projected
Variance
Over /
(Under)
£ million
Corporate Services 0.338 0.232 0.570 0.570 0.000
Communities &
Housing 0.000 0.456 0.456 0.456 0.000
Education 21.871 (3.195) 18.676 18.675 (0.001)
HSCP 0.569 0.843 1.412 1.412 0.000
Place 79.877 22.999 102.876 102.876 0.000
Other Items 2.000 2.144 4.144 4.144 0.000
Total Expenditure 104.655 23.479 128.134 128.133 (0.001)
General Grants (8.728) 0.000 (8.728) (8.728) 0.000
Specific Grants (13.049) (15.981) (29.030) (29.030) 0.000
CFCR (3.480) (0.017) (3.497) (3.497) 0.000
Capital Receipts (0.100) 0.000 (0.100) (0.100) 0.000
Other Grants &
Contributions (0.998) (0.255) (1.253) (1.253) 0.000
Prudential Borrowing (78.300) (7.226) (85.526) (85.525) 0.001
Total Income (104.655) (23.479) (128.134) (128.133) 0.001 
2.9 An underspend of (£0.001m) is projected within the General Fund capital programme
for 2024/25 in relation to the completed Early Years provision at Annick Primary
School. These funds will be transferred to the Flexibility budget to offset anticipated
budget pressures elsewhere in the programme. Information on the progress of all
projects can be found in Appendix 1. 
2.10 Signfiicant ongoing uncertainty and areas of cost risk have been identified as a result of
cost volatility arising from inflationary pressures, outstanding contractor claims and
supply chain issues which are impacting on tender returns and the cost of materials
across a number of projects. Specific projects where cost risks have been identified, or
are anticipated, include Moorpark Primary, Ardrossan Campus, Upper Garnock Flood
Prevention Scheme, Ardrossan North Shore and Ardrossan landside works. While
some mitigation has been built into the Capital Programme in the form of flexibility
budgets, totalling £10m over the next few years, cost pressures may exceed this
provision. These risks will be quantified as individual projects are completed and
tendering exercises are finalised, with the impact on the costs of the programme being
monitored and reported to Cabinet as appropriate. It is recognised, however, with a
significant budget gap being forecast over the medium term, any requirement for further
borrowing not met from a funding source will be a matter for Council to consider.

Page 8

Housing Revenue Account 
2.11 The following table outlines the movements in the 2024/25 HRA Capital budget: 
Housing Revenue Account  2024/25
£m
Budget as at 1 April 2024 52.777
Revised Funding (3.991)
Revised Budget 48.786
Alterations to phasing of projects 2023/24 to 2024/25 0.031
Alterations to phasing of projects 2024/25 to 2025/26 (2.742)
Alterations to phasing of projects 2025/26 to 2024/25 0.052
Budget as at 30 June 2024 46.127 
2.12  Revised Funding 
The Scottish Government has confirmed a 24% reduction in the Resource Planning
Assumption for 2024/25. This has resulted in a £3.991m reduction in projected grant
income for the year. A review of the Strategic Housing Investment Plan 2024 – 2029
identifying the options to address the impact of this reduction will be presented for
consideration by Cabinet in the autumn. It is anticipated that further information will be
available from Scottish Government at that time.   
2.13 Alterations to the Phasing of Projects 
Net planned expenditure of £0.031m has been reprofiled from 2023/24 to 2024/25,
reflecting projects not completed within the year which have been incorporated within
the 2024/25 capital programme. These were previously reported within the 2023/24
Capital Programme performance reports: 
Project Amount
£ million
Laburnum Ave/Newhouse Dr (0.992)
James Reid Site (0.102)
Corsehillhead  (0.050)
Stanecastle (0.050)
Contingencies 0.078
Kings Arms  0.155
Other Minor Adjustments 0.058
Total Alterations to New Builds (0.903)
HRA stock improvements slippage (3.085)
Traditional Rendering 0.166
Energy Efficiency  0.246
Pathfinder Project 0.250
Roofing  0.261
Bathroom Programme 0.280

Page 9

Project Amount
£ million
Insulated Rendering (EWI) 0.282
Saltcoats MSF 0.467
Central Heating 0.546
Kitchen Programme 0.586
Solar Panels 0.924
Other Minor Adjustments 0.040
Total Alterations to Stock Improvements 0.963
Sheltered Housing Unit Refurbs (0.799)
Lift Replacement 0.050
Estates Based Regeneration Programme 0.720
Total Alterations to Other Capital Works (0.029)
Alterations 2023/24 to 2024/25 0.031 
A review of the timescale for delivery of capital projects has identified a requirement to
re-profile (£2.742m) of works for delivery in 2025/26 and beyond, including: 
Project Amount
£ million
Montgomerie Park (1.480)
St Mary's Primary (0.958)
Total Alterations to New Builds (2.438)
Energy Efficiency (1.414)
Solar Panels (0.633)
Path Finder Project (0.400)
Wallfloor rendering (0.206)
Window Replacement (0.119)
Heating (0.103)
Roofing (0.022)
Rewiring 0.051
EWI 0.238
HRA stock improvements slippage 2.608
Total Alterations to Stock Improvements 0.000
Lift Replacement (0.304)
Total Alterations to Other Capital Works (0.304)
Alterations 2024/25 to 2025/26 (2.742)

Page 10

This has been partly offset by the acceleration of £0.052m of project expenditure for
delivery during 2024/25, including: 
Project Amount
£ million
Corsehillhead 0.050
Other minor adjustments 0.002
Total Alterations to New Builds 0.052
Alterations 2025/26 to 2024/25 0.052 
2.14 These adjustments have resulted in a revised 2024/25 budget at 30 June 2024 of
£46.127m. 
2.15 The impact on budgeted funding is a reduction of £6.650m from the approved budget: 
Category
Amount
£ million Comments
Capital Grants 3.991 Reduction in Resource Planning
Assumption
Borrowing 2.659 Aligned to projected expenditure
Total Funding Adjustments 6.650   
2.16  Projected Capital Expenditure to 31 March 2025 
The projections are summarised in the following table:   
Service /
Category
Approved
Budget
2024/25
£ million
Carry
Forwards
and
Adjustments
£ million
Revised
Budget
2024/25
£ million
Projected
Expenditure
/ Income to
31 March
2025
£ million
Projected
Variance
Over /
(Under)
£ million
Housing Revenue
Account 52.777 (6.650) 46.127 45.356 (0.771)
Total Expenditure 52.777 (6.650) 46.127 45.356 (0.771)
CFCR (11.492) - (11.492) (11.492) -
Capital Grants (16.471) - (16.471) (12.480) 3.991
Use of Reserves (0.544) - (0.544) (0.544) -
Affordable Housing
Contribution (0.394) - (0.394) (0.394) -
Prudential
Borrowing (23.876) 6.650 (17.226) (20.446) (3.220)
Total Income (52.777) 6.650 (46.127) (45.356) 0.771

Page 11

2.17 An underspend of (£0.771m) is projected within the HRA capital programme for
2024/25 arising from revisions to a number of projects, including: 
Project Variance
£ million Comments
Bathrooms / Wet Rooms (0.315) Lower number of void replacements
Kitchens (0.456) Lower number of void replacements
Total Variance (0.771)   
2.18 In addition to the adjustments noted above Appendix 2 highlights a proposed virement
which is required to transfers budgets between Contingency and individual projects,
aligning the budgets with the projected expenditure. 
2.19 Cost pressures will continue to be monitored and a review of any potential impact on
the Business Plan and Capital Programme will be undertaken to address any identified
issues. Further information on the progress of all projects can be found in Appendix 2. 
Treasury Management and Investment 
2.20 The Prudential Code for capital finance in local authorities (2021 edition) requires the
Council to set and monitor performance against specified prudential indicators. The
indicators for the current year were set out in the Treasury Management and
Investment Strategy 2024/25, approved by Council on the 28 February 2024. A
summary of the key indicators and our current estimated performance against them is
shown in the following table. Further details of all the Prudential and Treasury indicators
can be found in appendix 3. 
Prudential and Treasury Indicators
2024/25
Approved
Estimate
£ million
2024/25
Revised
Estimate
£ million
Movement
£ million
General Services Capital Financing Requirement 346.096 345.006 (1.090)
HRA Capital Financing Requirement 198.552 202.804 4.252
Total Loans Capital Financing Requirement 544.648 547.810 3.162
Gross Borrowing 478.337 484.716 6.379
Operational Boundary for Borrowing 558.072 571.374 13.302
Authorised Limit for Borrowing 613.879 628.511 14.632
Total Operational Boundary (incl. PPP/NPD) 641.366 654.668 13.302
Total Authorised Limit (incl. PPP/NPD) 697.173 711.805 14.632
Investments 30.000 30.000 0.000

Page 12

2.21 Loans Capital Financing Requirement 
The Loans Capital Financing Requirement (CFR) is the underlying borrowing
requirement of the Council. This is currently higher than the approved estimate as a
result of the change in profiled use of HRA reserves during 2023/24 resulting in a
greater borrowing requirement in that year. 
2.22 Gross Borrowing 
Gross Borrowing is projected to be higher than anticipated due to the revised profile of
capital projects partially offset by the continued strategy to utilise internal funds to
minimise borrowing. 
2.23 Operational Boundary 
The Operational Boundary is the maximum which the Council anticipates borrowing to
fund the current year capital programme, building in flexibility for the timing of the
different funding streams and principal repayments. The in-year variance is linked to
the continued use of internal funds and the re-profiling of the capital programme. 
2.24 Investments 
It is estimated that the Council will maintain an average balance of £30.000m of
internally managed funds and utilise cash balances during the year in support of the
under-borrowed position.  The internally managed funds are primarily invested in call
accounts with banks, Money Market Funds and other UK local authorities. 
2.25 It is critical that the Council ensures that its capital investment plans are affordable.
Affordability of borrowing is measured by the percentage of financing costs relative to
the net revenue stream of the General Fund and the Housing Revenue Account (HRA).
As at 30 June, the estimated percentages for 24/25 are 3.1% and 23.2% for the
General Fund and HRA respectively. Capital expenditure impacts on the revenue
budget through financing charges so it is essential the Council ensures the financing
costs remain affordable and do not constitute an excessive proportion of the revenue
resources available. From a General Fund perspective, the Scottish Local Authority
average in 2022/23 was 5.4%, therefore demonstrating by comparison the prudent
nature of the current borrowing policy. For the HRA, the Scottish average was 21.3%.
The level of loan charges is deemed prudent and affordable within the framework of the
30-year Housing business plan. 
3. Proposals 
3.1 That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30 June 2024; and (ii)
the forecast expenditure to 31 March 2025; 
(c)  approve the virement proposal noted within the HRA programme detailed in
appendix 2; and
(d) note the estimated performance against the Prudential Indicators set out in the
Treasury Management and Investment Strategy.

Page 13

4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected underspends
or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None. 
Environmental and Sustainability 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our investment
on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact David Forbes, Senior Manager (Strategic Business
Partner), on 01294 324551. 
Background Papers
Capital Investment Programme 2024/25 to 2033/34 - Council 28 February 2024
Housing Revenue Account (HRA) Capital Investment Plan, Revenue Budget and Rent
Levels for 2024/25 – Council 14 February 2024 
Treasury Management and Investment Strategy 2024/25 – Council 28 February 2024

Page 14

North Ayrshire Council Capital Statement 2024/25 Appendix 1
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2024/25
Brought / Carry Forward
to 2025/26
Total Revised
Budget 2024/25
Actual Expenditure to
30th June 2024
Projected Expenditure to
31st March 2025
Actual Over/
(Under) Spend for
2024/25
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Communities
Nursery Education 12,040,489 11,830,525 12,039,019 (1,470) 150,052 0 150,052 (59,912) 148,582 (1,470) (1,470)
Primary Schools 43,355,442 31,814,598 43,355,442 0 9,383,591 88,129 9,471,720 4,343,874 9,471,720 0 0
Secondary Schools 89,641,568 5,781,872 89,641,568 0 7,501,603 0 7,501,603 670,011 7,501,603 0 0
Special Education 25,343,637 25,246,058 25,343,637 0 97,579 0 97,579 0 97,579 0 0
Schools Other 1,449,979 432,833 1,449,979 0 1,254,999 200,000 1,454,999 237,853 1,454,999 0 0
Completed Projects 43,415,700 43,394,998 43,415,700 0 0 0 0 (20,702) 0 0 0
SUB TOTAL 215,246,814 118,500,885 215,245,344 (1,470) 18,387,824 288,129 18,675,953 5,171,124 18,674,483 (1,470) (1,470)
Communities & Housing
Information & Culture 112,479 8,898 112,479 0 105,916 0 105,916 2,335 105,916 0 0
Other Housing 350,000 0 350,000 0 350,000 0 350,000 0 350,000 0 0
SUB TOTAL 462,479 8,898 462,479 0 455,916 0 455,916 2,335 455,916 0 0
Corporate Services
Council IT Strategy 8,797,380 3,015,404 8,797,380 0 570,334 0 570,334 51,658 570,334 0 0
SUB TOTAL 8,797,380 3,015,404 8,797,380 0 570,334 0 570,334 51,658 570,334 0 0
Health & Social Care
Management & Support 1,832,058 1,258,554 1,832,058 0 573,407 0 573,407 68,880 573,407 0 0
Housing Non HRA 469,775 144,172 469,775 0 469,775 0 469,775 144,172 469,775 0 0
Adults 4,608,078 4,594,773 4,608,078 0 13,305 0 13,305 0 13,305 0 0
Young People 5,579,718 5,224,534 5,579,718 0 355,184 0 355,184 0 355,184 0 0
SUB TOTAL 12,489,628 11,222,033 12,489,628 0 1,411,671 0 1,411,671 213,052 1,411,671 0 0
Place
Roads 112,977,579 65,545,881 112,977,579 0 29,346,159 (1,386,098) 27,960,061 6,213,477 27,960,061 0 0
Streetscene 7,758,871 4,412,929 7,758,871 0 1,485,463 119,696 1,605,159 96,363 1,605,159 0 0
Transport 7,852,877 375,421 7,852,877 0 4,130,418 0 4,130,418 262,962 4,130,418 0 0
Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 0
Renewable Energy 14,660,789 2,982,344 14,660,789 0 10,144,004 0 10,144,004 551,657 10,144,004 0 0
Office Accommodation 1,030,196 97,106 1,030,196 0 1,030,196 0 1,030,196 97,106 1,030,196 0 0
Other Property 3,558,641 212,906 3,558,641 0 713,173 0 713,173 0 713,173 0 0
Economic Development & Regeneration 172,200,127 37,827,093 172,200,127 0 58,749,457 (984,664) 57,764,793 3,454,376 57,764,793 0 0
Completed Projects 6,355,261 6,286,842 6,355,261 0 29,376 0 29,376 (39,043) 29,376 0 0
SUB TOTAL 339,715,832 131,013,063 339,715,832 0 105,628,246 (2,251,066) 103,377,180 10,636,896 103,377,180 0 0
Other
Other 9,925,617 0 9,925,617 0 3,643,679 0 3,643,679 0 3,643,679 0 0
SUB TOTAL 9,925,617 0 9,925,617 0 3,643,679 0 3,643,679 0 3,643,679 0 0
Total Project Expenditure 586,637,750 263,760,282 586,636,280 (1,470) 130,097,670 (1,962,937) 128,134,733 16,075,065 128,133,263 (1,470) (1,470)
Total Project Income (130,097,670) 1,962,937 (128,134,733) (12,646,386) (128,133,263) 1,470 1,470
Total Net Expenditure 0 0 0 3,428,679 0 0 0
On Target (+0.5% of budget) On Target (up to  5% delay of original timescales)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Slightly off target  (+ 5% to 10% of original timescales)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less) Significantly off target (+10% or more of original timescales)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2024/25
Year Ended 31st March 2025
Period 3
The following classifications have been used to
highlight delivery performance against original
timescales set

Page 15

Revised Budget
24/25 Variance
£ £ £ £
CAPITAL BORROWING
Prudential Borrowing 95,183,784 94,120,038 (1,063,746)
SUB TOTAL 95,183,784 0 94,120,038 (1,063,746)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Active Travel Tier 1 942,401 0 942,401 0
Vacant & Derelict Land Funding 2,929,495 1,966,494 2,028,834 (900,661)
UK Government Grant - AGD i3 Flexible Space 1,251,416 0 1,251,416 0
UK Government Grant - AGD Great Harbour 1,377,971 0 1,377,971 0
Millport Town Hall Phase 2 284,120 284,120 284,120 0
Garrison House Project 633,613 633,613 633,613 0
Ardrossan Promenade 578,499 578,499 578,499 0
Islands Pit Stops 540,000 540,000 540,000 0
Place Based Investment Programme 1,276,882 1,276,882 1,276,882 0
UK Shared Prosperity Fund 728,770 728,770 728,770 0
Island Infrastructure Fund 68,966 68,966 68,966 0
B714 Improvements 5,201,946 0 5,201,946 0
Digital-SIPP Great Harbour 242,765 114,883 242,765 0
Ayrshire 5GIR 3,771,065 3,771,066 3,771,065 0
Renewal of Play Parks 0 0 0 0
CO2 Monitors in Schools 33,128 33,128 33,128 0
Capital Grants
General Capital Grant 9,607,000 2,401,749 9,607,000 0
SUB TOTAL 29,468,037 12,398,169 28,567,376 (900,661)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 3,479,853 0 3,479,853 0
CFCR 97,366 97,366 97,366 0
Grants & Contributions 1,459,325 106,731 1,459,325 0
Capital Receipts 409,305 44,120 409,305 0
SUB TOTAL 5,445,849 248,217 5,445,849 0
TOTAL CAPITAL PROGRAMME FUNDING 130,097,670 12,646,386 128,133,263 (1,964,407)
Capital Programme Funding 2024/25
Projected Income
to 31st March
2025
Actual Income to
30th June 2024Funding Description

Page 16

EDUCATION
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure
to 30th June 2024
Projected
Expenditure to 31
March 2025
Actual Over/ (Under)
Spend for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
KILMORY EARLY YEARS 72,418 70,520 72,418 0 0 (1,898) 0 0 0 Complete Complete Complete Complete Complete
CORRIE EARLY YEARS 29,337 29,359 29,337 0 0 22 0 0 0 Complete Complete Complete Complete Complete
BRODICK EARLY YEARS 364,721 364,885 364,721 0 0 164 0 0 0 Complete Complete Complete Complete Complete
MARRESS HOUSE 4,010,310 3,804,058 4,010,310 0 148,052 (58,200) 148,052 0 0 22-Jul-22 18-Jul-24 Construction On Target Significantly off target Final handover has now been confirmed as 18/7/24
ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,085,147 3,083,147 3,083,677 (1,470) 2,000 0 530 (1,470) (1,470) 0 Complete Complete Complete Complete Complete
Total Nursery Education 12,040,489 11,830,525 12,039,019 (1,470) 150,052 (59,912) 148,582 (1,470) (1,470) 0
Primary Schools
MOORPARK PRIMARY 12,149,441 12,147,660 12,149,441 0 683,440 681,659 683,440 0 0 31-Jan-24 02-Aug-24 Construction On Target Slightly off target  Further contractor delays anticipated. Contingency
arrangements are being developed.
MONTGOMERIE PARK SCHOOL 23,448,999 18,994,601 23,448,999 0 8,109,614 3,655,216 8,109,614 0 0 01-Aug-24 12-Aug-24 Construction On Target On Target
UNIVERSAL FREE SCHOOL MEALS EXPANSION 471,587 0 471,587 0 89,677 0 89,677 0 0 31-Mar-25 31-Mar-25 Tender On Target On Target
UFSM ARDEER PRIMARY SCHOOL 24,211 3,917 24,211 0 20,494 200 20,494 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM BRODICK PRIMARY SCHOOL 124,101 124,209 124,101 0 0 107 0 0 0 Complete Complete Complete Complete Complete
UFSM CORRIE PRIMARY SCHOOL 53,977 54,007 53,977 0 0 30 0 0 0 Complete Complete Complete Complete Complete
UFSM CORSEHILL PRIMARY SCHOOL 139,074 11,743 139,074 0 69,819 2,488 118,146 48,327 48,327 30-Sep-24 30-Sep-24 Construction On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 90,000 7,579 90,000 0 37,841 420 64,334 26,493 26,493 30-Sep-24 30-Sep-24 Construction On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 22,500 3,853 22,500 0 18,847 200 18,847 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM HAYOCKS PRIMARY SCHOOL 133,427 11,275 133,427 0 82,027 1,125 103,906 21,879 21,879 30-Sep-24 30-Sep-24 Development On Target On Target
UFSM KILMORY PRIMARY SCHOOL 60,000 54,987 60,000 0 2,527 (2,486) 2,527 0 0 31-Aug-24 31-Aug-24 Tender On Target On Target
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,541 1,463 2,082,541 0 186,181 0 186,181 0 0 31-Aug-28 31-Aug-28 Tender On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 22,500 3,760 22,500 0 18,940 200 18,940 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,252,503 209,703 2,252,503 0 15,918 1,106 2,136 (13,782) (13,782) 31-Jul-27 31-Jul-27 On Site On Target On Target
UFSM WHITEHIRST PARK PRIMARY 56,212 7,259 56,212 0 47,266 4,525 52,478 5,212 5,212 31-Aug-24 31-Aug-24 Construction On Target On Target
UFSM WHITING BAY PRIMARY SCHOOL 22,822 20,906 22,822 0 1,000 (916) 1,000 0 0 30-Sep-23 31-May-24 Construction On Target On Target
Total Primary Education 43,355,442 31,814,598 43,355,442 0 9,383,591 4,343,874 9,471,720 88,129 0 88,129 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,805,435 2,700,139 2,805,435 0 271,377 166,082 271,377 0 0 31-Mar-24 30-Aug-24 Construction On Target On Target
ARDROSSAN NEW BUILD 86,836,133 3,081,733 86,836,133 0 7,230,226 503,929 7,230,226 0 0 31-Aug-26 31-Aug-26 In Development On Target On Target
Total Secondary Education 89,641,568 5,781,872 89,641,568 0 7,501,603 670,011 7,501,603 0 0 0
Special Education
LOCKHART CAMPUS 25,343,637 25,246,058 25,343,637 0 97,579 0 97,579 0 0 Complete Complete Snagging Complete Complete
Total Special Education 25,343,637 25,246,058 25,343,637 0 97,579 0 97,579 0 0 0
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 197,351 298,000 0 103,020 2,372 103,020 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 1,151,979 235,482 1,151,979 0 1,151,979 235,482 1,351,979 200,000 200,000 31-Mar-25 31-Mar-25 On-going On Target On Target
Total Schools Other 1,449,979 432,833 1,449,979 0 1,254,999 237,853 1,454,999 200,000 0 200,000
Completed Projects
GARNOCK CAMPUS 40,304,366 40,283,664 40,304,366 0 0 (20,702) 0 0 0 Complete Complete Complete Complete Complete
Total Completed Projects 43,415,700 43,394,998 43,415,700 0 0 (20,702) 0 0 0 0
Total Communities 215,246,814 118,500,885 215,245,344 (1,470) 18,387,824 5,171,124 18,674,483 286,659 (1,470) 288,129
CAPITAL MONITORING 2024/25
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2024/25 BUDGETS

Page 17

COMMUNITIES & HOUSING
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure
to 30th June 2024
Projected Expenditure
to 31 March 2025
Actual Over/ (Under)
Spend for 2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 38,303 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 74,176 8,898 74,176 0 67,613 2,335 67,613 0 0 31-Mar-25 31-Mar-25 Planning On Hold On Hold
Total Information & Cultural 112,479 8,898 112,479 0 105,916 2,335 105,916 0 0 0
Other Housing
CCTV REVIEW 350,000 0 350,000 0 350,000 0 350,000 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
Total Other Housing 350,000 0 350,000 0 350,000 0 350,000 0 0 0
Total Communities & Housing 462,479 8,898 462,479 0 455,916 2,335 455,916 0 0 0
Comments
CAPITAL MONITORING 2024/25
Project Description
TOTAL PROJECT 2024/25 BUDGETS COMPLETION DATES DELIVERY STATUS

Page 18

Corporate Services
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual
Expenditure to
30th June 2024
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 4,065,580 1,179,748 4,065,580 0 437,709 50,177 437,709 0 0 31-Mar-26 31-Mar-26 On-going On Target On Target
WAN 912,107 412,107 912,107 0 0 0 0 0 0 Complete Complete Complete Complete Complete
LAN/WiFi 2,673,000 1,171,470 2,673,000 0 2,958 1,428 2,958 0 0 Complete Complete Complete Complete Complete
TELEPHONY 1,146,693 252,079 1,146,693 0 129,667 53 129,667 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target
Total IT Strategy 8,797,380 3,015,404 8,797,380 0 570,334 51,658 570,334 0 0 0
Total Chief Executive 8,797,380 3,015,404 8,797,380 0 570,334 51,658 570,334 0 0 0   
CAPITAL MONITORING 2024/25
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2024/25 BUDGETS

Page 19

HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure
to 30th June 2024
Projected Expenditure
to 31 March 2025
Actual Over/
(Under) Spend for
2024/25
True Over/(Under)
Spend            
Brought / Carry
Forward to 2025/26 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £
Management & Support
COMMUNITY ALARMS - ANALOGUE TO DIGITAL 996,000 906,518 996,000 0 20,505 0 20,505 0 0 31-Dec-24 31-Dec-24 In progress On Target On Target
CAREFIRST REPLACEMENT 536,058 267,993 536,058 0 268,065 0 268,065 0 0 31-Aug-24 31-Mar-25 In development On Target On Target
47 WEST ROAD 300,000 84,043 300,000 0 284,837 68,880 284,837 0 0 21-Jun-24 21-Jun-24 Refurbishment On Target On Target
Total Management & Support 1,832,058 1,258,554 1,832,058 0 573,407 68,880 573,407 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 469,775 144,172 469,775 0 469,775 144,172 469,775 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target 
Total Housing Non HRA 469,775 144,172 469,775 0 469,775 144,172 469,775 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,594,773 4,608,078 0 13,305 0 13,305 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,594,773 4,608,078 0 13,305 0 13,305 0 0 0
Young People
RESIDENTIAL & RESPITE UNIT 5,579,718 5,224,534 5,579,718 0 355,184 0 355,184 0 0 Complete Complete Snagging Complete Complete
Total Young People 5,579,718 5,224,534 5,579,718 0 355,184 0 355,184 0 0 0
Total Health & Social Care 12,489,628 11,222,033 12,489,628 0 1,411,671 213,052 1,411,671 0 0 0
Project Description
DELIVERY STATUS
CAPITAL MONITORING 2024/25
2024/25 BUDGETSTOTAL PROJECT COMPLETION DATES
Comments

Page 20

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual
Expenditure to
30th June 2024
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 3,675,899 3,675,899 3,675,899 0 3,675,899 199,037 3,675,899 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
ROAD SAFETY IMPROVEMENT FUND 0 0 0 0 0 20,000 0 0 0 Complete Complete Complete Complete Complete
PANEL REINSTATEMENT WORKS 148,494 148,494 148,494 0 148,494 0 148,494 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
ROADS REMEDIATION WORKS 106,183 106,183 106,183 0 106,183 0 106,183 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
TRAFFIC CALMING 175,000 92,047 175,000 0 82,953 0 82,953 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 100,000 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
LIGHTING * 1,409,072 39,996 1,409,072 0 1,409,072 39,996 1,409,072 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
LED LIGHTING REPLACEMENT 695,000 2,284 695,000 0 12,754 2,284 12,754 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target
UPPER GARNOCK FPS 18,503,801 18,113,552 18,503,801 0 390,335 87 390,335 0 0 Complete Complete Complete Complete Complete
MILLPORT COASTAL FPS 48,599,796 36,039,114 48,599,796 0 17,444,119 4,883,436 17,444,119 0 0 31-Aug-24 30-Sep-24 Construction On Target On Target
MILLBURN FPS 1,757,000 295,902 1,757,000 0 1,461,098 0 75,000 (1,386,098) (1,386,098) 31-Jul-24 31-Jul-25 In Development On Target Slightly off target  Delays in getting third party agreement
MILLPORT PIER 500,000 150,080 500,000 0 60,000 0 60,000 0 0 31-Dec-25 31-Dec-25 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 899,665 44,455 899,665 0 899,665 44,455 899,665 0 0 31-Mar-25 31-Mar-25 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 4,329,001 4,254,260 4,329,001 0 841,034 816,294 841,034 0 0 Complete Complete Complete Complete Complete
COASTAL ADAPTATIONS 198,727 0 198,727 0 198,727 0 198,727 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
B714 UPGRADE 31,693,443 2,495,601 31,693,443 0 2,409,350 199,897 2,409,350 0 0 31-Jul-26 30-Nov-26 In Development On Target Significantly off
target
Work is ongoing to develop the full business case
required to confirm LUF contribution.
PARKING CHARGES & DPE 186,501 88,015 186,501 0 106,476 7,990 106,476 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target
Total Roads 112,977,579 65,545,881 112,977,579 0 29,346,159 6,213,477 27,960,061 (1,386,098) 0 (1,386,098)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 368,282 0 368,282 0 (41,207) 0 0 41,207 41,207 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, ARDROSSAN - PLOTS/WALLS 217,921 160,857 217,921 0 58,387 1,323 58,387 0 0 Complete Complete Complete Complete Complete
CMTY, KILWINNING - NEW 1,404,577 1,375,502 1,404,577 0 440 (28,635) 440 0 0 Complete Complete Complete Complete Complete
CMTY, KNADGERHILL - EXTENSION 416,470 415,470 416,470 0 1,000 0 1,000 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WORKS 398,033 371,493 398,033 0 18,149 (8,391) 18,149 0 0 Complete Complete Complete Complete Complete
CMTY, STEV HIGH ROAD - WORKS 519,641 496,535 519,641 0 12,363 (10,743) 12,363 0 0 Complete Complete Complete Complete Complete
CMTY, BRODICK - NEW 12,000 10,341 12,000 0 1,659 0 1,659 0 0 On Hold On Hold On Hold On Hold On Hold
CMTY, KILBIRNIE - WALLS 136,138 75,378 136,138 0 61,405 36,718 88,477 27,072 27,072 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, BEITH - WALLS 185,581 142,256 185,581 0 32,844 40,936 84,261 51,417 51,417 31-Mar-25 31-Mar-25 Tender awarded On Target On Target
CMTY, ABBEY TOWER - WALLS 147,337 11,337 147,337 0 91,531 0 91,531 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target
CMTY, STEV HAWKHILL - WALLS 126,340 9,840 126,340 0 65,304 0 65,304 0 0 31-Aug-25 31-Aug-25 Tender awarded On Target On Target
CMTY, WEST KILBRIDE - WALLS 99,528 7,424 99,528 0 45,282 460 45,282 0 0 On Hold On Hold Tender awarded On Hold On Hold
CMTY, DREGHORN - WALLS 13,175 12,928 13,175 0 4,935 4,688 4,935 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 1,051,663 37,443 1,051,663 0 725,303 0 725,303 0 0 31-Mar-26 31-Mar-26 Feasibility Works On Target On Target
CMTY, SHEWALTON - WALLS 2,235 2,123 2,235 0 2,235 2,123 2,235 0 0 On Target On Target
COASTAL PLAY PARKS 420,065 433,791 420,065 0 0 13,725 0 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
STREET FURNITURE IMPROVEMENT 193,670 211,995 193,670 0 17,366 35,691 17,366 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PARK ENABLING WORKS 149,895 149,278 149,895 0 1,217 600 1,217 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,391,000 433,618 1,391,000 0 387,250 7,868 387,250 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
Total Streetscene 7,758,871 4,412,929 7,758,871 0 1,485,463 96,363 1,605,159 119,696 0 119,696
Transport
VEHICLES * 1,555,785 253,920 1,555,785 0 1,555,785 253,920 1,555,785 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target 
FLEET DECARBONISATION 6,297,092 121,501 6,297,092 0 2,574,633 9,043 2,574,633 0 0 31-Mar-25 31-Mar-25 Ongoing On Target On Target
Total Transport 7,852,877 375,421 7,852,877 0 4,130,418 262,962 4,130,418 0 0 0
Renewable Energy
SOLAR PV RETROFIT EXTENSION 120,000 145,218 120,000 0 77,365 102,582 77,365 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target 
SOLAR PV INVESTMENT - NETHERMAINS 7,289,441 1,141,252 7,289,441 0 6,184,882 297,414 6,184,882 0 0 31-Dec-24 31-Dec-24 Work Ongoing On Target On Target
SOLAR PV INVESTMENT - SHEWALTON 5,540,347 670,785 5,540,347 0 3,107,168 62,983 3,107,168 0 0 31-Dec-24 31-Dec-24 Work Ongoing On Target On Target
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,000 925,089 1,000,000 0 63,589 (11,323) 63,589 0 0 31-Mar-25 31-Mar-25 Work Ongoing On Target On Target 
NATURE RESTORATION FUND 711,000 100,000 711,000 0 711,000 100,000 711,000 0 0 31-Aug-24 31-Mar-25 Planning On Target On Target 
Total Renewable Energy 14,660,789 2,982,344 14,660,789 0 10,144,004 551,657 10,144,004 0 0 0
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS

Page 21

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual
Expenditure to
30th June 2024
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT * 240,355 0 240,355 0 240,355 0 240,355 0 0 31-Mar-25 31-Mar-25 Mulitple projects On Target On Target 
PLI TRINITY CHURCH ANNEX 3,000 0 3,000 0 3,000 0 3,000 0 0 31-Jul-24 31-Jul-24 Construction On Target On Target
PLI CALEY COURT RESOURCE CTR 4,800 0 4,800 0 4,800 0 4,800 0 0 30-Jun-24 31-Aug-24 Construction On Target On Target
PLI CASTLEVIEW DAY SERVICES 64,651 51,624 64,651 0 64,651 51,624 64,651 0 0 31-May-24 31-Oct-24 Construction On Target On Target
PLI WEST BYREHILL DEPOT 0 7,661 0 0 0 7,661 0 0 0 Complete Complete Complete Complete Complete
PLI GOLDCRAIGS DEPOT 109,139 0 109,139 0 109,139 0 109,139 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PLI DALRY PRIMARY SCHOOL 68,314 0 68,314 0 68,314 0 68,314 0 0 Complete Complete Complete Complete Complete
PLI DREGHORN PRIMARY SCHOOL 0 (1,344) 0 0 0 (1,344) 0 0 0 Complete Complete Complete Complete Complete
PLI HAYOCKS PRIMARY SCHOOL 1,000 0 1,000 0 1,000 0 1,000 0 0 30-Sep-24 30-Sep-24 Planning On Target On Target
PLI PENNYBURN PRIMARY 0 21,038 0 0 0 21,038 0 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL 494,500 3,090 494,500 0 494,500 3,090 494,500 0 0 31-Oct-24 31-Oct-24 Planning On Target On Target
PLI AUCHENHARVIE ACADEMY* 0 (22,979) 0 0 0 (22,979) 0 0 0 Complete Complete Complete Complete Complete
PLI KILWINNING ACADEMY 0 21,866 0 0 0 21,866 0 0 0 Complete Complete Complete Complete Complete
PLI DALRY EYC 11,000 0 11,000 0 11,000 0 11,000 0 0 Complete Complete Complete Complete Complete
PLI SPRINGVALE EYC 6,895 0 6,895 0 6,895 0 6,895 0 0 30-Jun-24 31-Jul-24 Construction On Target On Target
PLI CUNNINGHAME HOUSE 0 125 0 0 0 125 0 0 0 Cancelled On Target On Target
PLI ABBEYCROFT 12,000 11,843 12,000 0 12,000 11,843 12,000 0 0 Complete Complete Complete Complete Complete
PLI ANAM CARA 3,542 3,542 3,542 0 3,542 3,542 3,542 0 0 Complete Complete Complete Complete Complete
PLI EGLINTON CASTLE 0 640 0 0 0 640 0 0 0 31-Oct-24 31-Oct-24 Cancelled On Target On Target
PLI GARNOCK CAMPUS 11,000 0 11,000 0 11,000 0 11,000 0 0 30-Jun-24 30-Jun-24 Construction On Target On Target
Total Office Accommodation 1,030,196 97,106 1,030,196 0 1,030,196 97,106 1,030,196 0 0 0
Other Property
EMERGENCY CONTROL CTR 158,000 67,191 158,000 0 90,809 0 90,809 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
GOLDCRAIGS REFURBISHMENT 766,000 36,650 766,000 0 596,788 0 596,788 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 109,065 134,641 0 25,576 0 25,576 0 0 Complete Complete Complete Complete Complete
Total Property 3,558,641 212,906 3,558,641 0 713,173 0 713,173 0 0 0   
Ayrshire Growth Deal
AGD - I3 DPMC PHASE 1 1,000,000 0 1,000,000 0 423,749 (276,251) 423,749 0 0 31-Mar-26 31-Mar-26 Delivery On Target On Target
AGD - I3 DPMC PHASE 2 5,000,001 295,925 5,000,001 0 95,480 6,540 95,480 0 0 31-Mar-29 31-Mar-30 Feasibility On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 4,855,546 4,081,474 4,855,546 0 1,397,711 623,639 1,397,711 0 0 31-Oct-24 31-Oct-24 Construction On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 10,862,023 52,827 10,862,023 0 511,183 1,987 511,183 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR
ECONOMY
18,040,000 254,762 18,040,000 0 671,560 5,202 500,000 (171,560) (171,560) 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - GREAT HARBOUR 14,230,849 1,104,432 14,230,849 0 1,332,369 85,065 1,487,013 154,644 154,644 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - IMSE 10,500,000 156,450 10,500,000 0 477,266 5,202 477,266 0 0 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - MARINE TOURISM ARDROSSAN 5,000,002 275,717 5,000,002 0 (60,673) (60,673) (60,673) 0 0 Complete Complete Complete Complete Complete
AGD - MARINE TOURISM ARRAN 2,047,212 139,056 2,047,212 0 96,439 45,057 96,439 0 0 31-Mar-29 31-Mar-29 Feasibility On Target On Target
AGD - MARINE TOURISM CUMBRAE 4,547,212 167,457 4,547,212 0 296,424 37,923 229,337 (67,087) (67,087) 31-Mar-29 31-Mar-29 Design On Target On Target
Total Ayrshire Growth Deal 76,082,844 6,528,100 76,082,844 0 5,241,508 473,693 5,157,505 (84,003) 0 (84,003)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,127,113 563,680 4,127,113 0 902,508 12,256 902,508 0 0 1st Qtr 2026 1st Qtr 2026 Design On Target On Target
IRVINE ENTERPRISE AREA 10,746,072 0 10,746,072 0 51,539 0 51,539 0 0 Ongoing Ongoing Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 46,242,720 7,934,959 46,242,720 0 38,586,307 2,008,850 38,586,307 0 0 27-May-24 31-Mar-25 Construction On Target On Target
VDLF - HARBOUR MASTERS OFFICE 157,499 28,638 157,499 0 131,121 2,260 131,121 0 0 31-Mar-24 31-Mar-25 Design On Target On Target
VDLF - I3 IRVINE ENTERPRISE 279,411 257,020 279,411 0 22,391 0 22,391 0 0 31-Mar-24 31-Mar-25 Design On Target On Target
Other Growth & Investment 61,552,816 8,784,298 61,552,816 0 39,693,866 2,023,366 39,693,866 0 0 0

Page 22

PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual
Expenditure to
30th June 2024
Projected
Expenditure to 31
March 2025
Actual Over/
(Under) Spend for
2024/25
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2025/26
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2024/25
COMPLETION DATES
Project Description
TOTAL PROJECT 2024/25 BUDGETS DELIVERY STATUS
Regeneration
REPURPOSING PROPERTY GRANT FUND 254,179 4,950 254,179 0 253,499 4,270 253,499 0 0 30-May-25 30-May-25 In development On Target On Target
MILLPORT TOWN HALL PHASE 2 784,120 200,843 784,120 0 784,120 200,843 784,120 0 0 31-May-23 31-Dec-24 Construction On Target Significantly off
target
Community led regeneration project by Millport Town
Hall Charity. Project has been delayed due to challenges
with contractor and work needing redone as did not met
a satisfactory standard.  Regeneration team continues to
support MTHC in the delivery of the project.
GARRISON HOUSE PROJECT 633,613 800 633,613 0 633,613 800 633,613 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
ISLANDS PIT STOPS 540,000 0 540,000 0 540,000 0 540,000 0 0 31-Jul-24 31-Mar-25 In development On Target On Target
ISLAND INFRASTRUCTURE FUND 187,592 118,939 187,592 0 68,966 313 68,966 0 0 31-Mar-24 31-Dec-24 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 424,401 101,700 424,401 0 393,624 70,923 393,624 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 728,770 266,101 728,770 0 728,770 266,101 728,770 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
DIGITAL - SIPP GREAT HARBOUR 242,765 0 242,765 0 242,765 0 242,765 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
AYRSHIRE 5GIR 3,791,001 28,710 3,791,001 0 3,771,066 8,775 3,771,066 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
PBIP – KILWINNING ABBEY IMPROVEMENTS 235,354 0 235,354 0 235,354 0 235,354 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
LOCHSHORE HUB PLAY AREA 445,000 90,705 445,000 0 402,817 48,522 402,817 0 0 30-Jun-24 31-Aug-24 Construction On Target On Target
PBIP 36 BANK STREET 169,999 110,138 169,999 0 62,761 2,900 62,761 0 0 31-Dec-25 31-Dec-25 In development On Target On Target
PBIP GALT HOUSE 50,000 4,125 50,000 0 45,875 0 45,875 0 0 31-Mar-24 31-Mar-25 In development On Target On Target
IRVINE HIGH STREET 2,837,315 2,721,001 2,837,315 0 101,314 (15,000) 101,314 0 0 Complete Complete Complete Complete Complete
MILLPORT CARS 10,993 0 10,993 0 10,993 0 10,993 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
MONTGOMERIE PARK MASTERPLAN 4,218,598 1,807,527 4,218,598 0 199,258 15,688 199,258 0 0 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 1,961,138 1,878,138 1,961,138 0 57,122 (25,878) 57,122 0 0 31-May-25 31-May-25 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,145,999 4,087,907 4,145,999 0 58,991 899 58,991 0 0 Complete Complete Complete Complete Complete
VDLF 2024/25 ALLOCATION 963,000 0 963,000 0 963,000 0 963,000 0 0
VDLF - KYLE ROAD PHASE 2 1,398,066 145,155 1,398,066 0 1,253,061 150 400,000 (853,061) (853,061) 31-Mar-24 31-Mar-26 In development On Target On Target
VDLF - ANNICKBANK PH 3* 1,988,996 1,888,806 1,988,996 0 96,210 (3,980) 96,210 0 0 31-Mar-25 31-Mar-25 Construction On Target On Target
LUF3 - ANNICKBANK 50,000 31,478 50,000 0 50,000 31,478 50,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
VDLF - DEVELOPMENT WORK* 214,326 95,916 214,326 0 120,859 2,449 120,859 0 0 31-Mar-25 31-Mar-25 In development On Target On Target
VDLF - TREE PLANTING 50,000 2,400 50,000 0 47,600 0 0 (47,600) (47,600) 31-Dec-24 31-Dec-25 In development On Target On Target
MONTGOMERIE PARK NEIGHBOURHOOD CTR 288,203 0 288,203 0 288,203 0 288,203 0 0 31-Mar-24 31-Dec-24 In development On Target On Target
QUARRY ROAD PHASE 2 5,209,497 5,204,719 5,209,497 0 4,778 0 4,778 0 0 Complete Complete Complete Complete Complete
ACTIVE TRAVEL TIER 1 942,401 2,192,220 942,401 0 942,401 56,797 942,401 0 0 31-Mar-25 31-Mar-25 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME * 712,709 712,709 712,709 0 712,709 23,138 712,709 0 0 31-Mar-25 31-Mar-25 Various On Target On Target
ARDROSSAN PROMENADE 578,499 461,336 578,499 0 578,499 251,834 578,499 0 0 31-Mar-24 31-Dec-24 Construction On Target On Target
B777 CORRIDOR IMPROVEMENTS 95,965 84,569 95,965 0 11,396 0 11,396 0 0 Complete Complete Complete Complete Complete
LINKS TO EGLINTON PARK 183,874 88,874 183,874 0 95,000 0 95,000 0 0 31-Jul-24 31-Jul-24 Construction On Target On Target
COMMUNITY BUS FUND 146,000 102,838 146,000 0 59,459 16,297 59,459 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target
Total Regeneration 34,564,466 22,514,696 34,564,466 0 13,814,083 957,318 12,913,422 (900,661) 0 (900,661)
Total Economic Development & Regeneration 172,200,127 37,827,093 172,200,127 0 58,749,457 3,454,376 57,764,793 (984,664) 0 (984,664)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,163 3,378,163 0 0 (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,977,098 2,909,679 2,977,098 0 29,376 (38,043) 29,376 0 0 Complete Complete Defects Period Complete Complete
Total Completed Projects 6,355,261 6,286,842 6,355,261 0 29,376 (39,043) 29,376 0 0 0
Total Place 339,715,832 131,013,063 339,715,832 0 105,628,246 10,636,896 103,377,180 (2,251,066) 0 (2,251,066)

Page 23

OTHER BUDGETS
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2024/25
Actual Expenditure
to 30th June 2024
Projected
Expenditure to 31
March 2025
Over/ (Under)
Spend for 24/25
£ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 9,925,617 0 9,925,617 0 1,292,679 0 1,292,679 0
CORE INFRASTRUCTURE INVESTMENT 2,351,000 0 2,351,000 0 2,351,000 0 2,351,000 0
Total Other Budgets 12,276,617 0 12,276,617 0 3,643,679 0 3,643,679 0
2024/25 BUDGETS
CommentsProject Description
TOTAL PROJECT

Page 24

HRA Capital Statement 2324 Appendix 2
TOTAL PROJECT CURRENT YEAR 2024/25 - Period 2
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure to
30 May 2024 P2 Projection Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
EXPENDITURE
Council House Building
Afton Court 1,335,654 1,268,527 1,335,654 (67,127) 0 (29,057) On Target Complete Complete, project contingency not required.
Ayrshire Central Site 51,235,455 3,208,079 51,235,455 0 5,709,900 150,214 5,709,900 On Target On Target Tender award to be issued imminently.  Projected expenditure to be reprofiled to reflect
tender return figures.  Project due to commence on site August 2024.
Bourtreehill Village 9,924,743 190,985 9,924,743 0 103,797 4,975 103,797 On Target On Target Projected spend for 24/25 is for consultancy fees, utility disconnections and
commencement of the demolition of Crofthead Court.
Corsehillhead 2,032,906 262,558 2,032,906 0 (49,959) 0 49,959 On Target On Target Options appraisal currently being carried out for the site due to projected costs being
significantly higher than previously projected.
Flatt Road 20,178,000 19,708,540 19,934,544 (469,460) 0 1,795 0 On Target Complete Complete
Fullarton Street (High Flats) 12,073,511 33,330 12,073,511 0 182,605 182,605 On Target On Target New build project due to commence on site Jan 2026. Projected spend for 24/25 is for
consultancy fees and statutory consents.
Garnock Academy Site 12,092,889 687,610 12,092,889 0 5,762,674 4,676 5,762,674 On Target On Target Project commenced on site 17 June 2024.
Garrier Court 2,335,551 2,382,239 2,348,027 12,476 0 0 On Target Complete Complete
James McFarlane Site 4,784,118 849,535 4,784,118 0 2,132,821 320,130 2,132,821 On Target On Target Project commenced on site 25 March 2024.
James Reid Site 11,820,675 967,814 12,279,460 458,785 2,832,082 2,832,082 Significantly off
target
On Target Project site start delayed due to non resolution of culvert maintenance issue.
Kings Arms (113-115 High Street) 2,904,416 334,141 2,904,416 0 1,635,733 6,460 1,635,733 On Target On Target Project commenced on site 13 May 2024.
Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 2,188,354 2,953,447 (321,059) 1,427,383 898,220 1,427,383 On Target On Target Projects commenced on site 15 January 2024.
Largs Police Station 2,769,301 2,781,614 2,769,301 0 21,157 (33,117) 21,157 On Target Complete Complete
Montgomerie Park (Both Phases) 46,322,381 5,072,415 46,322,381 0 4,245,245 546,563 2,765,315 (1,479,930) On Target Slightly off target  Ground remediation works commenced on site March 2024 with main contract scheduled
to commence towards the end of 2024.
Stanecastle Site 7,768,147 1,120,328 7,768,147 0 4,020,327 494,565 4,020,327 On Target On Target Project commenced on site 25 March 2024.
St Beya Gardens 3,691,052 3,689,346 3,691,052 0 1,706 1,706 On Target Complete Complete 
St Michael's Wynd 13,996,769 13,908,729 14,087,664 90,895 0 (188,682) 0 Slightly off target  Complete Complete 
Nelson Street Regeneration 622,116 4,470 622,116 0 310,698 6,315 310,698 On Target On Target Tender documentation being prepared.
Acquisition Houses-Open Market 1,273,080 147 1,273,080 0 1,273,080 147 1,273,080 On Target On Target
Ukraine Buy Backs 0 121,953 0
Harbour Street 0 0 0 0 3,000 5,000 2,000 On Target On Target Options appraisal currently being carried out for the site due to projected costs being
significantly higher than previously projected.
Sy Mary's Primary, Largs 6,092,975 2,553,324 6,092,975 4,334,000 591,285 3,449,958 74,363 (958,405) On Target Slightly off target  Project commenced on site 8 January 2024.
Internal Management Charges 1,757,259 1 1,757,259 0 1,489,000 1,489,000 On Target On Target
SHIP Review Requirement (3,991,000) (3,991,000) 0 (3,991,000) (3,991,000) A review to be undertaken as part of the SHIP to identify options to address the reduction in
Scottish Government Grant.
Contingency 2,611,322 2,611,322 2,611,322 2,536,959 (74,363)
SUB TOTAL 242,308,139 86,228,948 242,193,084 (404,965) 34,055,571 2,726,661 31,669,195 0 (2,386,376) 0
DELIVERY STATUS

Page 25

TOTAL PROJECT CURRENT YEAR 2024/25 - Period 2
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2024/25
Actual Expenditure to
30 May 2024 P2 Projection Virement Request
Carry /Brought
Forward to /From
2024/25
True Over/ (Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
DELIVERY STATUS
Improvements to existing stock
Wet Room - Void 248,422 57,058 386,904 248,422 57,058 386,904 138,482 On Target On Target Higher number of void replacments being projected than budgeted offset by reduction in
void bathrooms
Bathrooms - Void 978,665 22,182 524,790 978,665 22,182 524,790 (453,875) On Target On Target Lower number of void replacments being projected than budgeted
Wet Room - Planned 66,246 0 66,246 66,246 66,246 On Target On Target
Bathrooms - Planned 141,069 13,224 141,069 141,069 13,224 141,069 On Target On Target
Electrical Rewiring 172,236 102,375 222,869 172,236 102,375 222,869 50,633 On Target On Target Additional units required in year.
Heating 1,916,920 494,985 1,814,021 1,916,920 494,985 1,814,021 (102,899) On Target On Target Number of units requiring full central heating replacments is less than anticipated.
Kitchens 1,523,166 142,909 1,523,166 1,523,166 142,909 1,523,166 On Target On Target
Kitchens - Void 1,497,340 92,909 1,041,824 1,497,340 92,909 1,041,824 (455,516) On Target On Target Lower number of void replacments being projected than budgeted
Roofing 755,136 3,249 733,500 755,136 3,249 733,500 (21,636) On Target On Target
Wallfloor rendering 452,189 (441,038) 246,000 452,189 (441,038) 246,000 (206,189) On Target On Target
EWI 677,882 0 916,000 677,882 916,000 238,118 On Target On Target Additional addresses requiring EWI works.
Window Replacement 529,935 0 411,008 529,935 411,008 (118,927) On Target On Target
Saltcoats MSF Investment 466,625 4,969 466,625 466,625 4,969 466,625 On Target On Target
Smoke Detector Programme 241,682 26,314 241,682 241,682 26,314 241,682 On Target On Target
Energy Efficiency 1,414,745 0 0 1,414,745 0 (1,414,745) On Target On Target Underspend due to slippage on SHU programme and awaiting outcome  of SHNZS
consultation to progress pathfinder project and allow development of programme.
Path Finder Project 500,000 0 100,000 500,000 100,000 (400,000) On Target Significantly off target Awaiting outcome  of SHNZS consultation to progress
Solar Panels 3,527,859 364,892 2,895,000 3,527,859 364,892 2,895,000 (632,859) On Target On Target
HRA Slippage (3,085,000) 0 (3,085,000) (3,085,000) (476,496) 2,608,504
SUB TOTAL 15,110,117 884,028 11,730,704 0 12,025,117 884,028 11,254,208 0 0 (770,909)
Other Capital works
Estate Based Regeneration 1,453,809 10,805 1,453,809 1,453,809 10,805 1,453,809 On Target On Target
Lift Replacement 454,000 0 150,000 454,000 150,000 (304,000) On Target On Target Contract being re-tendered
Sheltered Housing Units 828,944 128 828,944 828,944 128 828,944 On Target On Target
SUB TOTAL 5,105,723 1,714,203 4,158,571 (643,152) 2,736,753 2,065 2,432,753 0 (304,000) 0
Total Expenditure 247,413,862 87,943,151 246,351,655 (1,048,117) 48,817,441 3,612,754 45,356,156 0 (2,690,376) (770,909)
Income
Affordable Housing Contributn (394,000) (394,000)
CFCR (11,492,000) (11,492,000)
Capital Grants (11,880,000) (1,711,703) (11,880,000) 0 A reduction in anticipated grant as advised by Scottish Government.
Prudential Borrowing (23,907,441) (20,446,156) 2,690,376 770,909 Reduced borrowing required to reflect rephasing and projected underspends
Council HB fund contribution (544,000) (544,000)
Sale of Assets (1,000) 0
Other Capital Income (600,000) (600,000) Income from Vacant and Derelict Land Fund (VDLF) in relation to Kings Arms
SUB TOTAL
Total Project Expenditure 247,413,862 87,943,151 246,351,655 (1,048,117) 48,817,441 3,612,754 45,356,156 0 (2,690,376) (770,909)
Total Project Income (48,817,441) (1,712,703) (45,356,156) 0 2,690,376 770,909
Total Net Expenditure 0 1,900,051 0 0 0 0
Check Total
On Target (+0.5% of budget)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less)
The following classifications have been used to highlight financial performance against
budget

Page 26

Appendix 3
Treasury Management Performance to 30 June 2024    
Capital Expenditure for both the General Fund and HRA vary from original estimates
due to changes in the profile of projects. Full details of all movements in the capital
expenditure budgets are included in this report.  
The reduction to the General fund Capital Financing Requirement reflects the
change in profile of the capital programme. The increase to the HRA Capital
Financing requirement is a result of a reprofiling of the use of reserves during 23/24. 
Capital expenditure impacts on the revenue budget through financing charges so it is
essential the Council ensures the financing costs remain affordable and do not
constitute an excessive proportion of the revenue resources available.   From a
General Fund perspective, the latest Scottish Local Authority average was 5.4%,
thereby demonstrating a prudent borrowing policy.   For the HRA, the Scottish
average was 21.3%. The level of loan charges is deemed prudent and affordable
within the framework of the 30 year Housing business plan.  
2024/25 2024/25 2024/25
Original Estimate P3 Projection Movement
£m £m £m
General Services Capital expenditure                   104.655                    128.133                      23.478
Funded by:
Borrowing                     78.300                      94.120                      15.820
Receipts / Grants                     22.875                      30.436                        7.561
Funded from Revenue                            -                           0.097                        0.097
Funded from Reserves                       3.480                        3.480                             -   
Total                   104.655                    128.133                      23.478
HRA Capital expenditure                     52.417                      49.347                       (3.070)
Funded by:
Borrowing                     24.116                      24.437                        0.321
Receipts / Grants                     15.871                      12.480                       (3.391)
Funded from Revenue                     11.492                      11.492                             -   
Funded from Reserves                       0.938                        0.938                             -   
Total                     52.417                      49.347                       (3.070)
Estimates of Capital Expenditure and Income
2024/25 2024/25 2024/25
Original Estimate P3 Projection Movement
£m £m £m
General Services                   429.390                    428.300                       (1.090)
HRA                   198.552                    202.804                        4.252
Sub-total                   627.942                    631.104                        3.162
Less PPP/NPD long-term liability                    (83.294)                    (83.294)                            -   
Loans Capital Financing Requirement (CFR)                   544.648                    547.810                        3.162
Capital Financing Requirement (CFR)
2024/25 2024/25
Original Estimate P3 Projection
% %
General Services 3.5% 3.1%
HRA 24.0% 23.2%
Proportion of financing costs to net revenue
stream

Page 27

The Council is currently projecting an under-borrowed position of £63.094m due to
the continuing strategy to delay long-term external borrowing by utilising internal
cash balances. 
Liability Benchmark
The liability benchmark is an important tool to help establish whether the Council is
likely to be a long-term borrower or long-term investor in the future, and so shape its
strategic focus and decision making. 
The Liability benchmark graph above is used to inform the Council’s borrowing
strategy.  The shaded grey area shows the Councils current debt and the gap
between this and the Liability benchmark line is how much more borrowing the
Council likely needs to undertake to support its current capital plans once taking into
account its balance sheet resources including the net debtor / creditor and useable
reserves.  The above graph indicates that long term borrowing for the period of
around 20 years would be most appropriate to meet the Councils borrowing needs
and mitigate against interest rate risk.
2024/25 2024/25 2024/25
Original Estimate P3 Projection Movement
£m £m £m
Gross Debt at 31 March                   478.337                    484.716                        6.379
CFR                   544.648                    547.810                        3.162
(Under)/Over Borrowed Position                    (66.311)                    (63.094)                       3.217
Current Portfolio Position (excluding PPP/NPD)

Page 28

The maturity structure of the debt portfolio at 30 June 2024 is shown below and
shows the period when the Council is required to repay and/or refinance debt. It is
important to ensure a reasonable spread of debt to mitigate against high exposure
levels in respect of refinancing.  The current profile ensures this: 
The increase in the external borrowing since 31 March is largely in relation to
additional temporary borrowing undertaken of £15m. This is partially offset by
maturing loans during the period to 30 June including a £5m LOBO loan which was
repaid when called in May.
2024/25 2024/25 2024/25
Original Estimate
£m
P3 Projection
£m
Movement
£m
Loans CFR                   544.648                    547.810                        3.162
Less Balance sheet resources                    (78.200)                  (109.600)                    (31.400)
Net loans requirement                   466.448                    438.210                     (28.238)
Liquidity allowance                     10.000                      10.000                             -   
Liability Benchmark                   476.448                    448.210                     (28.238)
Liability Benchmark
31-Mar-24 30-Jun-24
Maturity Profile of Borrowing (Indicator 10) Actual Actual Movement
£m £m £m
Under 12 months                      62.650                      58.549                       (4.101)
12 months and within 24 months                       2.950                        1.594                       (1.356)
24 months and within 5 years                     13.845                      13.663                       (0.182)
5 years and within 10 years                     31.439                      34.439                        3.000
10 years and within 20 years                     83.189                      81.177                       (2.012)
20 years and within 30 years                     20.125                      20.525                        0.400
30 years and within 40 years                     92.588                      92.587                       (0.001)
40 years and within 50 years                            -                         10.000                      10.000
50 years and above                     10.000                      10.000                             -   
Total Borrowing                   316.786                    322.534                        5.748