Page 1
NORTH AYRSHIRE COUNCIL 4 June 2024 Cabinet Title: Capital Programme Performance to 31 March 2024 Purpose: To advise Cabinet of progress in delivering the Capital Investment Programme for 2023/24. Recommendation: That Cabinet agrees to (a) note the revisions to budgets outlined in the report; and (b) note the General Services and HRA expenditure to 31 March 2024. 1. Executive Summary 1.1 The General Services Capital Investment Programme 2023/24 to 2030/31 was approved by Council on 1 March 2023. The Housing Revenue Account (HRA) Capital Investment Programme 2023/24 sits within the updated HRA Business Plan and was approved by Council on 15 February 2023. 1.2 This is the final monitoring report for the year which identifies the current programme for 2023/24, taking account of adjustments made to the initial budgets and advises of the actual expenditure to 31 March 2024. 1.3 The final outturn report for the General Fund reports a net breakeven position against a revised budget of £85.250m. The final outturn position for the HRA is an underspend of (£2.897m) against a revised budget of £41.863m. 1.4 Within the General Fund, adjustments to funding have resulted in net reductions to the overall capital programme of (£2.503m). These are primarily related to accounting adjustments to transfer funding to the General Fund Revenue budget. 1.5 Reviews of individual project plans have identified a number of adjustments to the current profiles. As a result, (£8.232m) has been reprofiled for delivery in 2024/25 and beyond. This has been offset by the acceleration of £9.219m to 2023/24 from future years. 1.6 Within the HRA, additional government grants of £1.927m have been received in relation to the Council house buy-back programme to accommodate Ukrainian Displaced People. This has been supported by additional prudential borrowing. A review of delivery timescales has identified a requirement to re-profile (£1.377m) of works for delivery in 2024/25 and beyond. This has been offset by the acceleration of £3.409m to 2023/24 from future years.
Page 2
1.7 Major risks to the forecast position continue to arise from ongoing cost volatility and the uncertainty around potential future changes to local authority capital accounting arrangements. In terms of cost volatility, individual project costs will continue to be monitored closely with cost increases met initially from the additional flexibility built into the programme. Any costs in excess of the current level of flexibility provision will require to be funded from within existing resources. 2. Background General Fund 2.1 The following table outlines the movements in the 2023/24 General Services budget: 2.2 (a) Changes to Funding The capital programme has been updated to reflect the following changes to funding. Downturned funding is primarily related to changes in the scope of works or delays in third party agreements or other information agreed with the funding body: 2023/24 £m Budget as at 31 January 2024 86.766 a) Changes to Funding (0.198) b) Other Revisions to the Programme (2.305) Revised Budget 84.263 c) Alterations to phasing of projects:- 2023/24 to 2024/25 (8.232) 2024/25 to 2023/24 9.219 Budget as at 31 March 2024 85.250 Funding Body Amount Project Developer Contribution £0.148m Panel reinstatement works Developer Contribution £0.106m Roads remediation works Scottish Government £0.043m Road Safety Improvement Fund SPT £0.014m Bus Corridor Improvements SPT Downturned (£0.001m) Brodick to Corrie Cycle Paths SPT Downturned (£0.002m) Irvine Friendly Cycle Town SPT Downturned (£0.007m) Cumbrae Ferry & Bus Stop SPT Downturned (£0.013m) B714 Active Travel SUSTRANS £0.062m B777 Corridor Improvements SUSTRANS £0.002m Access Paths SUSTRANS Downturned (£0.001m) Saltcoats Old Cal Railway Ph2 SUSTRANS Downturned (£0.002m) Kilbirnie to Kilwinning SUSTRANS Downturned (£0.003m) Saltcoats Old Cal Railway Ph1
Page 3
2.3 (b) Other Revisions to the Programme Further additions to the programme of £0.181m have been identified in relation to Capital Funded from Current Revenue (CFCR) transfers across a range of projects. This has been offset by the identification of a number of projects totalling (£2.486m) which, although managed as part of the Capital Programme, have been transferred for inclusion in the year end Revenue Monitoring report in line with accounting requirements. In addition, £0.500m has been applied from the Flexibility Fund to address contractor cost inflation in relation to Millport Townhall. This has been subsequently rephased into future years. Funding Body Amount Project SUSTRANS Downturned (£0.016m) B777 Corridor Improvements SUSTRANS Downturned (£0.019m) NCN73 Accessibility SUSTRANS Downturned (£0.047m) NCN753 Largs Promenade SUSTRANS Downturned (£0.154m) Links to Eglinton Park SUSTRANS Downturned (£0.308m) Fairlie Coastal Path Total (£0.198m) Funding Source Amount Project Transfers to Revenue (£0.687m) Improvement Grants Transfers to Revenue (£0.020m) Workplace Chargers Transfers to Revenue (£0.216m) VDLF Transfers to Revenue (£0.223m) UK Shared Prosperity Fund Transfers to Revenue (£0.002m) CWSR Transfers to Revenue (£0.007m) Town Centre Regeneration Transfers to Revenue (£0.017m) Island Cost Crisis Emergency Fund Transfers to Revenue (£0.071m) Island Infrastructure Fund Transfers to Revenue (£0.097m) Garrison House Transfers to Revenue (£0.149m) Millport Town Hall Ph2 Transfers to Revenue (£0.221m) Millport Town Hall Regeneration Transfers to Revenue (£0.221m) Dyemill Bike Park Transfers to Revenue (£0.555m) PBIP CFCR (£0.083m) Spend doesn’t meet Capital Definition CFCR £0.049m Street Furniture CFCR £0.043m AGD Great Harbour CFCR £0.082m 2-4 Boyle Street Hostel CFCR £0.036m Early Years CFCR £0.022m AGD Marine Tourism Arran CFCR £0.022m AGD Marine Tourism Cumbrae CFCR £0.010m Coastal Play Parks Utilisation of Flexibility £0.500m Millport Townhall Phase 2 Utilisation of Flexibility (£0.500m) Flexibility Fund Total (£2.305m)
Page 4
2.4 (c) Alterations to the Phasing of Projects A further review of individual project plans, taking cognisance of the current levels of volatility within the construction sector, has identified a requirement to re-profile (£8.232m) of works for delivery in 2024/25 and beyond. This includes the reversal of the in-year corporate phasing adjustment which reflected the level of optimism bias included in the expenditure forecasts: Service Amount Project Communities (£0.683m) Moorpark Primary (£0.553m) Ardrossan New Build (£0.068m) Abbey Tower (£0.049m) UFSM (£0.071m) Other minor adjustments (£1.424m) Chief Executives (£0.027m) ICT Investment Fund / LAN / Wifi (£0.027m) HSCP (£0.268m) Carefirst (£0.030m) 47 West Road (£0.298m) Place (£9.174m) Ardrossan north Shore (£0.711m) Largs Prom Seawall (£0.633m) Garrison House (£0.578m) Ardrossan Promenade (£0.784m) Millport Town Hall PH2 (£0.276m) Vehicles (£0.200m) Nature Restoration Fund (£0.177m) AGD Projects (£0.151m) PBIP (£0.149m) Panel reinstatement works (£0.106m) Roads remediation works (£0.106m) Parking Charges & DPE (£0.091m) Emergency Control Centre (£0.078m) UK SPF (£0.077m) Solar PV Retrofit (£0.064m) Non Domestic Energy Efficiency (£0.059m) Community Bus Fund (£0.427m) Other minor adjustments (£13.841m) Other (£1.293m) Flexibility Fund (£0.351m) Core Infrastructure (£1.644m) Corporate £9.002m Uncertainty / Sensitivity Adjustment £9.002m Total (£8.232m)
Page 5
These adjustments have been partly offset by the acceleration of £9.219m of expenditure to 2023/24 from future years. 2.5 These adjustments have resulted in a revised 2023/24 budget at 31 March 2024 of £85.250m. Service Amount Project HSCP £0.048m Community Alarms £0.033m Other minor adjustments £0.081m Place £2.591m Millport Coastal FPS £0.759m AGD I3 DPMC Ph2 £0.172m Roads Improvement £0.156m B714 Upgrade £0.118m Solar PV Nethermains £0.077m Upper Garnock FPS £0.075m Marress House £0.074m Solar PV Shewalton £0.164m Other minor adjustments £4.186m Communities £4.931m Montgomerie Park School £0.021m Other minor adjustments £4.952m Total £9.219m
Page 6
2.6 The following graph illustrates the movement in each programme on a service basis compared to the revised programme: 2.7 The impact on budgeted funding, elements of which are related to the profile of expenditure reported above, is a reduction of (£1.516m) from the revised budget, including: 18.349 0.799 0.757 93.126 2.900 115.931 21.681 0.892 2.265 107.802 (25.388) 107.252 22.099 0.771 2.265 102.971 (22.274) 105.832 18.466 4.711 2.460 84.085 (12.643) 97.079 18.205 0.505 1.834 72.912 (6.690) 86.766 21.654 0.480 0.930 62.186 - 85.250 3.305 (0.319) 0.173 (30.940) (2.900) (30.681) Approved Programme Movement Programme @ P5 Programme @ P3 Programme @ P10 Programme @ P8 Programme @ P12 Category Amount Comments Borrowing £2.178m Rephased aligned to projected expenditure CFCR £0.181m Additional CFCR Contributions Capital Grants (£2.713m) Rephased and revised government grants Other Grants (£1.162m) Rephased and revised contributions Total (£1.516m)
Page 7
2.8 Capital Expenditure to 31 March 2024 The actual expenditure by service is summarised in the following table: Information on the progress of all projects can be found in Appendix 1. 2.9 Although not formally reflected in the financial performance reports at this time due to ongoing uncertainty, areas of cost risk have been identified across a number of projects. These risks are linked to a number of factors, including cost volatility linked to inflationary pressures; limited availability of contractors, supply chain issues and material shortages which are impacting on tender returns and the cost of materials; delays resulting from interaction with external agencies and regulators; and other contract management issues across a number of projects. Specific projects where cost risks have been identified, or are anticipated, include Moorpark Primary, Montgomerie Park Primary, Ardrossan Campus, Upper Garnock Flood Prevention Scheme, Millport Coastal Flood Prevention Scheme, Largs Sea Wall, Ardrossan North Shore and Ardrossan Harbour Interchange. While some mitigation has been built into the Capital Programme in the form of flexibility budgets, totalling £10m over the next few years, cost pressures may exceed this provision. These risks will be quantified as individual projects are completed and tendering exercises are finalised, with the impact on the costs of the programme being monitored and reported to Cabinet as appropriate. It is recognised, however, that any costs in excess of the current level of flexibility provision will require to be funded from within existing resources. Revised Budget 2023/24 Budget Revisions Carry Forwards and Adjustments Revised Budget 2023/24 Expenditure / Income to 31 March 2024 Variance Over / (Under) £m £m £m £m £m £m Expenditure Communities 18.205 (0.078) 3.527 21.654 21.654 - Chief Executive 0.505 0.001 (0.026) 0.480 0.480 - Health and Social Care Partnership 1.834 (0.687) (0.217) 0.930 0.930 - Place 72.912 (1.071) (9.655) 62.186 62.186 - Other including Flexibility (6.690) (0.668) 7.358 - - - Total Expenditure 86.766 (2.503) 0.987 85.250 85.250 - Income General Capital Grant (38.482) - - (38.482) (38.482) - Specific Capital Grant (11.529) 1.736 1.592 (8.201) (8.201) - Capital Funded from Current Revenue (1.405) (0.181) - (1.586) (1.586) - Capital Receipts (0.537) - 0.249 (0.288) (0.288) - Other Grants & Contributions (3.316) 0.948 (0.475) (2.843) (2.843) - Prudential Borrowing (31.497) - (2.353) (33.850) (33.850) - Total Income (86.766) 2.503 (0.987) (85.250) (85.250) -
Page 8
Housing Revenue Account 2.10 The following table outlines the movements in the 2023/24 HRA Capital budget: 2.12 (a) Changes to Funding The HRA capital programme has been updated to include the Council house buy-back programme to accommodate Ukrainian Displaced People, as approved by Cabinet on 7 November 2023. This is funded by additional Scottish Government grant of £1.927m, with the balance of funding supported by prudential borrowing. 2.13 (b) Alterations to the Phasing of Projects A further review of the timescale for delivery of capital projects has identified a requirement to re-profile (£1.377m) of works for delivery in 204/25 and beyond, including: 2023/24 £m Budget as at 31 January 2024 37.372 a) Changes to Funding 2.459 b) Alterations to phasing of projects:- 2023/24 to 2024/25 (1.377) 2024/25 to 2023/24 3.409 Budget as at 31 March 2024 41.863 Category Amount Project New Builds (£0.155m) Kings Arms (£0.078m) Contingency (£0.159m) Other minor adjustments (£0.392m) Improvements (£0.467m) Saltcoats MSF Investment (£0.183m) EWI (£0.135m) Wallfloor Rendering (£0.055m) Roofing (£0.840m) Other (£0.145m) Estate Based Regeneration (£0.145m) Total (£1.377m)
Page 9
This has been offset by the acceleration of £3.409m of project expenditure for delivery during 2023/24, including: 2.14 These adjustments have resulted in a revised 2023/24 budget at 31 March 2024 of £41.863m. 2.15 The impact on budgeted funding, elements of which are related to the profile of expenditure reported above, is an increase of £4.491m: Category Amount Project New Builds £1.796m St Marys Primary £0.792m Laburnum Avenue £0.102m James Reid Site £0.050m Corsehillhead £0.151m Other minor adjustments £2.891m Improvements £0.173m Solar Panels £0.080m Other minor adjustments £0.253m Other £0.265m Sheltered Housing Units £0.265m Total £3.409m Category Amount Comments Sale of Assets (£0.004m) Additional receipts received CFCR (£0.040m) Additional CFCR Contributions Borrowing (£9.214m) Rephased aligned to projected expenditure Use of Reserves £5.404m Rephased aligned to projected expenditure Capital Grants (£0.637m) Rephased aligned to projected expenditure Total (£4.491m)
Page 10
2.16 Capital Expenditure to 31 March 2024 The actual expenditure is summarised in the following table: Further information on the progress of all projects can be found in Appendix 2 2.17 A variance of (£2.897m) is reported within the HRA capital programme for 2023/24 arising from revisions to a number of projects, including: Revised Budget 2023/24 Carry Forwards and Adjustments Revised Budget 2023/24 Actual Expenditure / Income to 31 March 2024 Variance Over / (Under) Service £m £m £m £m £m Expenditure Housing Revenue Account 37.372 4.491 41.863 38.966 (2.897) Total Expenditure 37.372 4.491 41.863 38.966 (2.897) Income Sale of Assets - (0.004) (0.004) (0.004) - CFCR (5.151) (0.040) (5.191) (5.191) - Capital Grants (6.786) (0.637) (7.423) (7.423) - Use of Reserves (4.065) 4.065 - - - Affordable Housing Contribution (2.445) 1.339 (1.106) (1.106) - Prudential Borrowing (18.925) (9.214) (28.139) (25.242) 2.897 Total Income (37.372) (4.491) (41.863) (38.966) 2.897 Project Variance Comments High Flats Demolition (£0.730m) Project Complete Heating (£0.539m) Scope of works reduced Harbourside (£0.374m) Project Complete Wet Rooms & Bathrooms (£0.355m) Scope of works reduced Internal Management charges (£0.318m) Project Complete Flatt Road (£0.228m) Project Complete Health and Safety Works (£0.207m) Budget no longer required Kitchen Voids (£0.136m) Scope of works reduced Friars Lawn (£0.115m) Project Complete Afton Court (£0.086m) Project Complete St Colms Largs (£0.078m) Project Complete Caley Court (£0.037m) Project Complete Garrier Court (£0.034m) Project Complete Other minor variances (£0.012m) Project Complete Brathwic Terrace £0.129m Project Complete Acquisition of Houses £0.223m Project Complete Total (£2.897m)
Page 11
2.18 Further cost pressures resulting from inflationary and supply chain issues continue to be monitored and a review of the potential impact on the Business Plan and Capital Programme will be undertaken to address any identified issues. 3. Proposals 3.1 That Cabinet agrees to (a) note the revisions to budgets outlined in the report; (b) note the General Services and HRA expenditure to 31 March 2024. 4. Implications/Socio-economic Duty Financial 4.1 The financial implications are as outlined in the report. Expenditure will continue to be closely monitored to ensure early action is taken regarding any projected underspends or overspends. Human Resources 4.2 None. Legal 4.3 None. Equality/Socio-economic 4.4 None. Environmental and Sustainability 4.5 None. Key Priorities 4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our investment on priorities, managing risk and supporting delivery of key priorities. Community Wealth Building 4.7 None.
Page 12
5. Consultation 5.1 Progress as outlined in this report has been approved by Executive Directors. Mark Boyd Head of Service (Finance) For further information please contact David Forbes, Senior Manager (Strategic Business Partner), on 01294 324551. Background Papers Capital Programme Performance to 31 January 2024 – Cabinet, 19 March 2024
Page 13
TOTAL PROJECT Project Description Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Brought / Carry Forward to 2024/25 Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend £ £ £ £ £ £ £ £ £ £ EXPENDITURE Communities Nursery Education 16,459,468 16,236,378 16,459,468 0 437,003 (0) 437,003 437,003 0 0 Primary Schools 50,154,297 27,470,725 50,154,297 0 19,303,072 (0) 19,303,072 19,303,072 0 0 Secondary Schools 81,629,839 5,111,862 81,629,839 0 1,195,186 0 1,195,186 1,195,186 0 0 Special Education 25,345,985 25,246,058 25,345,985 0 41,016 (0) 41,016 41,016 0 0 Schools Other 932,123 829,103 932,123 0 677,646 0 677,646 677,646 0 0 Information & Culture 6,563 6,563 6,563 0 0 0 0 0 0 0 Completed Projects 43,415,700 43,415,700 43,415,700 0 0 0 0 0 0 0 SUB TOTAL 217,943,975 118,316,388 217,943,975 0 21,653,923 0 21,653,923 21,653,923 0 0 Chief Executive Council IT Strategy 8,771,296 2,963,746 8,771,296 0 480,011 0 480,011 480,011 0 0 SUB TOTAL 8,771,296 2,963,746 8,771,296 0 480,011 0 480,011 480,011 0 0 Health & Social Care Management & Support 1,581,814 1,189,674 1,581,814 0 917,491 (0) 917,491 917,491 0 0 Housing Non HRA 0 0 0 0 0 0 0 0 0 0 Adults 4,611,528 4,594,773 4,611,528 0 4,742 (0) 4,742 4,742 0 0 Young People 5,579,718 5,224,534 5,579,718 0 7,993 (0) 7,993 7,993 0 0 SUB TOTAL 11,773,060 11,008,980 11,773,060 0 930,226 (1) 930,225 930,225 0 0 Place Roads 115,648,396 62,802,145 115,648,396 0 41,672,458 (0) 41,672,458 41,672,458 0 0 Streetscene 8,402,126 5,058,321 8,402,126 0 1,378,181 1 1,378,182 1,378,182 0 0 Transport 9,915,791 3,455,627 9,915,791 0 3,192,638 0 3,192,638 3,192,638 0 0 Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 Renewable Energy 14,512,381 2,430,687 14,512,381 0 1,208,470 0 1,208,470 1,208,470 0 0 Office Accommodation 2,437,417 1,562,521 2,437,417 0 1,562,521 (0) 1,562,521 1,562,521 0 0 Other Property 1,581,355 826,429 1,581,355 0 329,540 (0) 329,540 329,540 0 0 Other Housing 581,905 231,905 581,905 0 142,930 0 142,930 142,930 0 0 Economic Development & Regeneration 164,088,693 37,894,863 164,088,693 0 12,688,015 0 12,688,015 12,688,015 0 0 Completed Projects 6,355,261 6,325,885 6,355,261 0 11,219 0 11,219 11,219 0 0 SUB TOTAL 336,844,817 133,860,925 336,844,817 0 62,185,972 0 62,185,972 62,185,972 0 0 Other Other 13,777,000 0 13,777,000 0 0 0 0 0 0 0 SUB TOTAL 13,777,000 0 13,777,000 0 0 0 0 0 0 0 Total Project Expenditure 589,110,147 266,150,039 589,110,147 0 85,250,132 0 85,250,132 85,250,132 0 0 Total Project Income (85,250,132) (0) (85,250,132) (85,250,132) 0 0 Total Net Expenditure 0 0 0 0 0 0 On Target (+0.5% of budget) Slightly off target (+ 0.5% to 2% of budget, or £0.125m, whichever is less) Significantly off target (+2% or more of budget, or £0.500m, whichever is less) On Target (up to 5% delay of original timescales) Slightly off target (+ 5% to 10% of original timescales) Significantly off target (+10% or more of original timescales) The following classifications have been used to highlight financial performance against budget CURRENT YEAR 2023/24 North Ayrshire Council Capital Statement 2023/24 Year Ended 31st March 2024 Period 12 The following classifications have been used to highlight delivery performance against original timescales set
Page 14
Revised Budget 23/24 Variance £ £ £ £ £ £ £ £ CAPITAL BORROWING Prudential Borrowing 68,291,931 5,814,577 2,683,086 76,789,594 (42,897,565) (42,461) 33,849,568 33,849,567 (2) SUB TOTAL 68,291,931 5,814,577 2,683,086 76,789,594 (42,897,565) (42,461) 33,849,568 33,849,567 (2) SCOTTISH GOVERNMENT FUNDING Specific Capital Grants Early Learning & Childcare 0 26,594 59,206 85,800 1 85,801 85,801 (0) Cycling / Walking /Safer Streets 1,159,954 (117,150) 271,000 1,313,804 28,522 1,342,326 1,342,326 (0) Vacant & Derelict Land Funding 3,857,216 403,874 198,048 4,459,138 (2,182,969) 2,276,169 2,276,169 0 UK Government Grant - AGD 3,653,000 (98,741) 3,554,259 (1,359,416) 2,194,843 2,194,843 0 Town Centre Regeneration 0 65,691 140,000 205,691 (6,746) 198,945 198,945 0 Annickbank - Vacant & Derelict Land Investment Programme 400,000 400,000 0 400,000 400,000 0 Millport Town Hall Regeneration 0 (31,995) 252,529 220,534 (220,534) 0 0 0 Millport Town Hall Phase 2 94,022 339,498 433,520 (433,520) 0 0 0 Ardrossan Promenade 788,000 788,000 (578,499) 209,501 209,501 0 Islands Pit Stops 20,000 520,000 540,000 (540,000) 0 0 0 Islands Cost Crisis Emergency Fund 17,000 17,000 (17,000) 0 0 0 Place Based Investment Programme 0 622,801 948,836 1,571,637 (1,070,683) 500,954 500,954 (0) UK Shared Prosperity Fund 98,414 98,414 (98,414) 0 0 0 Island Infrastructure Fund 0 140,373 140,373 (140,373) 0 0 0 B714 Improvements 500,000 322,741 822,741 428,054 1,250,795 1,250,795 0 Road Safety Improvement Fund 258,431 258,431 258,431 0 Ayrshire 5GIR 19,935 19,935 19,935 (1) Renewal of Play Parks 231,000 231,000 (231,000) 0 0 0 2-4 Boyle Street Hostel 31,025 31,025 0 31,025 31,025 0 CO2 Monitors in Schools 0 0 43,523 43,523 43,523 (0) Capital Grants Flooding 20,525,000 20,525,000 0 20,525,000 0 0 General Capital Grant 15,179,000 15,179,000 2,167,204 17,346,204 37,871,204 0 SUB TOTAL 45,105,170 1,896,235 3,615,531 50,616,936 (3,933,484) 0 46,683,452 46,683,453 1 OTHER INCOME TO PROGRAMME Use of Funds :- Capital Fund 0 0 0 0 0 0 0 0 0 CFCR 0 0 0 0 1,584,912 0 1,584,912 1,584,912 0 Grants & Contributions 2,068,411 632,323 301,603 3,002,337 (158,983) 0 2,843,354 2,843,354 (0) Capital Receipts 465,555 0 0 465,555 (220,134) 43,425 288,846 288,846 0 SUB TOTAL 2,533,966 632,323 301,603 3,467,892 1,205,795 43,425 4,717,112 4,717,112 0 TOTAL CAPITAL PROGRAMME FUNDING 115,931,067 8,343,135 6,600,220 130,874,422 (45,625,254) 964 85,250,132 85,250,132 (0) 23/24 Budget at Capital Refresh Mar 2023 Capital Programme Funding 2023/24 Approved budget at Period 1 used as revised starting point 2023/24 Actual Income to 31st March 2024Funding Description Carry Forward from 2022/23 Changes after Capital Refresh Mar 2023 Total Changes in Year Changes at Capital Refresh Mar 2024
Page 15
COMMUNITIES MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/(Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical £ £ £ £ £ £ £ £ £ Nursery Education Early Years Programme EARLY LEARNING & CHILDCARE FUTURE PROJECTS 4,073 4,073 4,073 0 0 0 0 0 Complete Complete Complete Complete Complete ST BRIDGETS EARLY YEARS 787,477 787,477 787,477 0 0 0 0 0 Complete Complete Complete Complete Complete KILMORY EARLY YEARS 72,418 72,418 72,418 0 44,231 44,231 0 0 Complete Complete Complete Complete Complete ST PETERS EARLY YEARS 1,273,594 1,273,594 1,273,594 0 29,867 29,867 (0) (0) Complete Complete Complete Complete Complete ST JOHN OGILVIE EARLY YEARS 177,415 177,415 177,415 0 0 0 0 0 Complete Complete Complete Complete Complete MAYFIELD PS EARLY YEARS 215,710 215,710 215,710 0 0 0 0 0 Complete Complete Complete Complete Complete BEITH PS EARLY YEARS 341,180 341,180 341,180 0 1,417 1,417 (0) (0) Complete Complete Complete Complete Complete SKELMORLIE PS EARLY YEARS 358,835 358,835 358,835 0 0 0 0 0 Complete Complete Complete Complete Complete WEST KILBRIDE EARLY EARLY YEARS 227,912 227,913 227,912 0 2,857 2,857 0 0 Complete Complete Complete Complete Complete GATESIDE EARLY YEARS 407,764 407,764 407,764 0 0 0 0 0 Complete Complete Complete Complete Complete GARNOCK CAMPUS EARLY YEARS 58,755 58,755 58,755 0 0 0 0 0 Complete Complete Complete Complete Complete FAIRLIE EARLY YEARS 208,220 208,220 208,220 0 3,100 3,100 0 0 Complete Complete Complete Complete Complete ELDERBANK EARLY YEARS 22,983 22,983 22,983 0 0 0 0 0 Complete Complete Complete Complete Complete DREGHORN EARLY YEARS 82,940 82,940 82,940 0 0 0 0 0 Complete Complete Complete Complete Complete CUMBRAE EARLY YEARS 41,339 41,339 41,339 0 1,155 1,155 0 0 Complete Complete Complete Complete Complete LARGS CAMPUS EARLY YEARS 45,836 45,836 45,836 0 0 0 0 0 Complete Complete Complete Complete Complete MOORPARK EARLY YEARS 182 182 182 0 0 0 0 0 Complete Complete Complete Complete Complete PIRNMILL EARLY YEARS 79,223 79,223 79,223 0 7,377 7,377 (0) (0) Complete Complete Complete Complete Complete SHISKINE EARLY YEARS 139,088 139,088 139,088 0 12,075 12,075 (0) (0) Complete Complete Complete Complete Complete CORRIE EARLY YEARS 29,337 29,337 29,337 0 895 895 (0) (0) Complete Complete Complete Complete Complete LAMLASH EARLY YEARS 10,104 10,104 10,104 0 9,227 9,227 0 0 Complete Complete Complete Complete Complete BRODICK EARLY YEARS 364,721 364,721 364,721 0 10,062 10,062 (0) (0) Complete Complete Complete Complete Complete MARRESS HOUSE 4,085,347 3,862,258 4,085,347 0 301,947 301,948 1 1 22-Jul-22 30-May-24 Construction On Target Significantly off target Contractor Delays Completed Nursery Education GLENCAIRN / LOUDON MONTGOMERY EARLY YEARS 170,429 170,429 170,429 0 0 0 0 0 Complete Complete Complete Complete Complete ARDEER EARLY YEARS 216,819 216,819 216,819 0 0 0 0 0 Complete Complete Complete Complete Complete ST JOHNS EARLY YEARS 283,930 283,930 283,930 0 0 0 0 0 Complete Complete Complete Complete Complete STANLEY EARLY YEARS 27,514 27,514 27,514 0 0 0 0 0 Complete Complete Complete Complete Complete KILWINNING (PENNYBURN SCHOOL) EARLY YEARS 648,135 648,135 648,135 0 0 0 0 0 Complete Complete Complete Complete Complete DALRY EARLY YEARS CENTRE 56,920 56,920 56,920 0 0 0 0 0 Complete Complete Complete Complete Complete SPRINGVALE EARLY YEARS 104,557 104,557 104,557 0 0 0 0 0 Complete Complete Complete Complete Complete ABBEY / ST LUKES PRIMARY SCHOOL EARLY YEARS 64,615 64,615 64,615 0 0 0 0 0 Complete Complete Complete Complete Complete ST LUKES EARLY YEARS 1,966 1,966 1,966 0 0 0 0 0 Complete Complete Complete Complete Complete CASTLEPARK EARLY YEARS 219,376 219,376 219,376 0 0 0 0 0 Complete Complete Complete Complete Complete LAWTHORN EARLY YEARS 201,037 201,037 201,037 0 0 0 0 0 Complete Complete Complete Complete Complete HAYOCKS EARLY YEARS 246,765 246,765 246,765 0 0 0 0 0 Complete Complete Complete Complete Complete WOODLANDS EARLY YEARS 181,546 181,546 181,546 0 0 0 0 0 Complete Complete Complete Complete Complete CORSEHILL EARLY YEARS 536,144 536,144 536,144 0 0 0 0 0 Complete Complete Complete Complete Complete CALEDONIA EARLY YEARS 255,432 255,432 255,432 0 0 0 0 0 Complete Complete Complete Complete Complete BLACKLANDS EARLY YEARS 204,144 204,144 204,144 0 0 0 0 0 Complete Complete Complete Complete Complete WINTON EARLY YEARS 5,290 5,290 5,290 0 0 0 0 0 Complete Complete Complete Complete Complete SPRINGSIDE EARLY YEARS 566,752 566,752 566,752 0 0 0 0 0 Complete Complete Complete Complete Complete ST MARKS EARLY YEARS 350,497 350,497 350,497 0 0 0 0 0 Complete Complete Complete Complete Complete Other Nursery Education ANNICK PRIMARY EXT - EARLY YRS PROVISION 3,083,147 3,083,147 3,083,147 0 12,793 12,793 0 0 Complete Complete Complete Complete Complete Total Nursery Education 16,459,468 16,236,378 16,459,468 0 437,003 437,003 (0) 0 (0) Primary Schools MOORPARK PRIMARY 11,466,001 11,466,001 11,466,001 0 4,929,452 4,929,452 (0) (0) 31-Jan-24 31-Jan-24 Construction On Target Slightly off target Further information on the delivery status is awaited from the contractor CAPITAL MONITORING 2023/24 CommentsProject Description TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2023/24 BUDGETS
Page 16
COMMUNITIES MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/(Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical CAPITAL MONITORING 2023/24 CommentsProject Description TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2023/24 BUDGETS MONTGOMERIE PARK SCHOOL 28,379,987 15,339,385 28,379,987 0 14,243,387 14,243,387 (0) (0) 01-Aug-24 01-Aug-24 Construction On Target On Target UNIVERSAL FREE SCHOOL MEALS EXPANSION 3,054,802 0 3,054,802 0 (1) 0 1 1 31-Mar-24 31-Mar-24 Tender On Target On Target UFSM ARDEER PRIMARY SCHOOL 4,400 3,717 4,400 0 3,717 3,717 (0) (0) 31-Dec-24 31-Dec-24 Tender On Target On Target UFSM BEITH PRIMARY SCHOOL 22,500 0 22,500 0 0 0 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target UFSM BRODICK PRIMARY SCHOOL 124,102 124,101 124,102 0 2,768 2,768 (0) (0) Complete Complete Complete Complete Complete UFSM CORRIE PRIMARY SCHOOL 53,977 53,977 53,977 0 1,182 1,182 0 0 Complete Complete Complete Complete Complete UFSM CORSEHILL PRIMARY SCHOOL 119,880 9,255 119,880 0 9,255 9,255 (0) (0) 31-Aug-25 31-Aug-25 Tender On Target On Target UFSM GARNOCK COMMUNITY CAMPUS 92,159 7,159 92,159 0 7,159 7,159 0 0 31-Aug-25 31-Aug-25 Tender On Target On Target UFSM GLEBE PRIMARY SCHOOL 2,046,397 2,528 2,046,397 0 2,528 2,528 0 0 31-Jul-28 31-Jul-28 Tender On Target On Target UFSM GLENCAIRN PRIMARY SCHOOL 3,653 3,653 3,653 0 3,653 3,653 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target UFSM HAYOCKS PRIMARY SCHOOL 102,240 10,150 102,240 0 10,150 10,150 0 0 31-Aug-25 31-Aug-25 Development On Target On Target UFSM KILMORY PRIMARY SCHOOL 62,486 57,473 62,486 0 57,473 57,473 0 0 31-Aug-24 31-Aug-24 Tender On Target On Target UFSM LARGS PRIMARY SCHOOL 148,533 148,533 148,533 0 0 0 0 0 Complete Complete Complete Complete Complete UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,540 1,463 2,082,540 0 1,463 1,463 (1) (1) 31-Aug-28 31-Aug-28 Tender On Target On Target UFSM PENNYBURN PRIMARY SCHOOL 8,400 3,560 8,400 0 3,560 3,560 0 0 31-Dec-24 31-Dec-24 Tender On Target On Target UFSM SHISKINE PRIMARY SCHOOL 6,616 6,616 6,616 0 544 544 (0) (0) Complete Complete Complete Complete Complete UFSM WEST KILBRIDE PRIMARY SCHOOL 2,251,068 208,597 2,251,068 0 2,226 2,226 (0) (0) 31-Jul-27 31-Jul-27 On Site On Target On Target UFSM WHITEHIRST PARK PRIMARY 102,734 2,734 102,734 0 2,734 2,734 0 0 31-Aug-24 31-Aug-24 Construction On Target On Target UFSM WHITING BAY PRIMARY SCHOOL 21,822 21,822 21,822 0 21,822 21,822 0 0 30-Sep-23 31-May-24 Construction On Target On Target Total Primary Education 50,154,297 27,470,725 50,154,297 0 19,303,072 19,303,072 (0) 0 (0) Secondary Schools KILWINNING LEARNING ENVIRONMENT 2,774,121 2,534,058 2,774,121 0 107,024 107,024 (0) (0) 31-Mar-24 30-Aug-24 Construction On Target On Target ARDROSSAN NEW BUILD 78,855,718 2,577,804 78,855,718 0 1,088,162 1,088,162 0 0 31-Aug-26 31-Aug-26 In Development On Target On Target Total Secondary Education 81,629,839 5,111,862 81,629,839 0 1,195,186 1,195,186 0 0 0 Special Education LOCKHART CAMPUS 25,345,985 25,246,058 25,345,985 0 41,016 41,016 (0) (0) Complete Complete Snagging Complete Complete Total Special Education 25,345,985 25,246,058 25,345,985 0 41,016 41,016 (0) 0 (0) Schools Other CO2 MONITORS IN SCHOOLS 298,000 194,980 298,000 0 43,523 43,523 (0) (0) 31-Mar-25 31-Mar-25 Planning On Target On Target SCHOOLS ICT INVESTMENT * 634,123 634,123 634,123 0 634,123 634,123 0 0 31-Mar-24 31-Mar-24 On-going On Target On Target Total Schools Other 932,123 829,103 932,123 0 677,646 677,646 0 0 0 Information & Culture CASTLES & HISTORIC MONUMENTS 0 0 0 0 0 0 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code ABBEY TOWER 6,563 6,563 6,563 0 0 0 0 0 31-Mar-25 31-Mar-25 Planning On Hold On Hold Total Information & Cultural 6,563 6,563 6,563 0 0 0 0 0 0 Completed Projects GARNOCK CAMPUS 40,304,366 40,304,366 40,304,366 0 0 0 0 0 Complete Complete Complete Complete Complete AUCHENHARVIE SECONDARY ESTATE LEARNING ENVT 3,111,334 3,111,334 3,111,334 0 0 0 0 0 Complete Complete Complete Complete Complete Total Completed Projects 43,415,700 43,415,700 43,415,700 0 0 0 0 0 0 Total Communities 217,943,975 118,316,388 217,943,975 0 21,653,923 21,653,923 0 0 0
Page 17
CHIEF EXECUTIVE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/(Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical £ £ £ £ £ £ £ £ £ Council IT Strategy ICT INVESTMENT FUND 4,041,571 1,129,571 4,041,571 0 219,838 219,838 (0) (0) 31-Mar-26 31-Mar-26 On-going On Target On Target WAN 912,107 412,107 912,107 0 9,910 9,910 (0) (0) 31-Mar-28 31-Mar-28 Implementation On Target On Target LAN/WiFi 2,670,042 1,170,042 2,670,042 0 225,880 225,880 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target TELEPHONY 1,147,576 252,026 1,147,576 0 24,383 24,383 0 0 31-Mar-28 31-Mar-28 Implementation On Target On Target Total IT Strategy 8,771,296 2,963,746 8,771,296 0 480,011 480,011 0 0 0 Total Chief Executive 8,771,296 2,963,746 8,771,296 0 480,011 480,011 0 0 0 CAPITAL MONITORING 2023/24 CommentsProject Description COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2023/24 BUDGETS
Page 18
HEALTH & SOCIAL CARE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/(Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical £ £ £ £ £ £ £ £ £ Management & Support COMMUNITY ALARMS - ANALOGUE TO DIGITAL 1,044,471 906,518 1,044,471 0 902,328 902,328 (0) (0) 31-Dec-24 31-Dec-24 In progress On Target On Target CAREFIRST REPLACEMENT 267,993 267,993 267,993 0 0 0 0 0 31-Aug-24 31-Mar-25 In development On Target On Target 47 WEST ROAD 269,350 15,163 269,350 0 15,163 15,163 (0) (0) 21-Jun-24 21-Jun-24 Refurbishment On Target On Target Total Management & Support 1,581,814 1,189,674 1,581,814 0 917,491 917,491 (0) 0 (0) Housing Non HRA IMPROVEMENT GRANTS * 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-24 Ongoing On Target On Target Total Housing Non HRA 0 0 0 0 0 0 0 0 0 Adults TRINDLEMOSS 4,611,528 4,594,773 4,611,528 0 4,742 4,742 (0) (0) Complete Complete Complete Complete Complete Total Older People 4,611,528 4,594,773 4,611,528 0 4,742 4,742 (0) 0 (0) Young People RESIDENTIAL & RESPITE UNIT 5,579,718 5,224,534 5,579,718 0 7,993 7,993 (0) (0) Complete Complete Snagging Complete Complete Total Young People 5,579,718 5,224,534 5,579,718 0 7,993 7,993 (0) 0 (0) Total Health & Social Care 11,773,060 11,008,980 11,773,060 0 930,226 930,225 0 0 0 CommentsProject Description DELIVERY STATUS CAPITAL MONITORING 2023/24 2023/24 BUDGETSTOTAL PROJECT COMPLETION DATES
Page 19
PLACE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical £ £ £ £ £ £ £ £ £ Roads ROADS IMPROVE/RECONSTRUCTION * 4,571,362 4,571,362 4,571,362 0 4,571,362 4,571,362 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target ROAD SAFETY IMPROVEMENT FUND 258,431 258,431 258,431 0 258,431 258,431 0 0 31-Mar-24 31-Mar-24 In Development On Target On Target A737 DALRY BYPASS 375,735 375,735 375,735 0 375,735 375,735 0 0 Complete Complete Complete Complete Complete PANEL REINSTATEMENT WORKS 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target ROADS REMEDIATION WORKS 0 0 0 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target TRAFFIC CALMING 175,000 92,047 175,000 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 0 0 0 0 31-Mar-25 31-Mar-25 In development On Target On Target LIGHTING * 1,008,270 1,008,270 1,008,270 0 1,008,270 1,008,270 (0) (0) 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target LED LIGHTING REPLACEMENT 682,245 141,415 682,245 0 141,415 141,415 0 0 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target A737 DALRY BYPASS LIGHTING 20,684 16,610 20,684 0 16,610 16,610 0 0 Complete Complete Complete Complete Complete UPPER GARNOCK FPS 18,581,293 18,113,466 18,581,293 0 677,493 677,493 0 0 Complete Complete Complete Complete Complete MILLPORT COASTAL FPS 51,190,678 31,155,677 51,190,678 0 29,315,263 29,315,263 (0) (0) 31-Aug-24 30-Sep-24 Construction On Target On Target MILLBURN FPS 1,749,432 295,902 1,749,432 0 42,432 42,432 (1) (1) 31-Jul-24 31-Jul-25 In Development On Target Slightly off target Delays due to wait for permission from Scottish Water MILLPORT PIER 460,000 150,080 460,000 0 0 0 0 0 31-Dec-25 31-Dec-25 In Development On Target On Target BRIDGES INFRASTRUCTURE PROG * 754,329 754,329 754,329 0 754,329 754,329 (0) (0) 31-Mar-24 31-Mar-24 Multiple Projects On Target On Target LARGS PROMENADE SEAWALL 3,537,966 3,437,967 3,537,966 0 3,104,012 3,104,012 0 0 30-Apr-24 31-Jul-24 Construction On Target On Target COASTAL ADAPTATIONS 198,727 0 198,727 0 0 0 0 0 31-Mar-25 31-Mar-25 In Development On Target On Target B714 UPGRADE 31,849,093 2,295,704 31,849,093 0 1,406,445 1,406,445 0 0 31-Jul-26 30-Nov-26 In Development On Target Significantly off target Confirmation of Levelling Up Fund (LUF) fudning awaiting approval of full Business Case is approved. Completion due by March 2025 but land purchase may be complex and time consuming and construction costs are escalating due to ongoing inflationary pressures. LARGS CAR PARK INFRASTRUCTURE 55,128 55,128 55,128 0 661 661 0 0 Complete Complete Complete Complete Complete PARKING CHARGES & DPE 80,025 80,025 80,025 0 0 (0) (0) (0) 31-Mar-24 31-Mar-24 In Development On Target On Target Total Roads 115,648,396 62,802,145 115,648,396 0 41,672,458 41,672,458 (0) 0 (0) Project Description TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS Comments CAPITAL MONITORING 2023/24 COMPLETION DATES
Page 20
PLACE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical Project Description TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS Comments CAPITAL MONITORING 2023/24 COMPLETION DATES Streetscene CEMETERY EXTNS, WALLS & INFRA * 411,058 0 411,058 0 (1) 0 1 1 Holding Code Holding Code Holding Code Holding Code Holding Code CMTY, LAMLASH - EXTENSION 715,065 715,065 715,065 0 0 0 0 0 Complete Complete Complete Complete Complete CMTY, ARDROSSAN - PLOTS/WALLS 159,535 159,534 159,535 0 3,477 3,477 (0) (0) Complete Complete Complete Complete Complete CMTY, KILBIRNIE - WORKS 25,383 25,383 25,383 0 0 0 0 0 Complete Complete Complete Complete Complete HAYLIE BRAE CEMETERY 455 455 455 0 455 455 0 0 Complete Complete Complete Complete Complete DALRY CEMETERY 250 250 250 0 250 250 0 0 Complete Complete Complete Complete Complete CMTY, KILWINNING - NEW 1,404,137 1,404,137 1,404,137 0 139,609 139,609 0 0 Complete Complete Complete Complete Complete CMTY, KNADGERHILL - EXTENSION 415,470 415,470 415,470 0 660 660 0 0 Complete Complete Complete Complete Complete CMTY, WEST KILBRIDE - WORKS 398,033 379,884 398,033 0 18,743 18,743 (0) (0) Complete Complete Complete Complete Complete CMTY, STEV HIGH ROAD - WORKS 507,277 507,278 507,277 0 137,807 137,807 0 0 Complete Complete Complete Complete Complete ARDROSSAN CEMETERY NEW 603 603 603 0 0 0 0 0 On Hold On Hold On Hold On Hold On Hold CMTY, BRODICK - NEW 10,341 10,341 10,341 0 3,320 3,320 0 0 On Hold On Hold On Hold On Hold On Hold CMTY, KILBIRNIE - WALLS 110,804 38,661 110,804 0 23,035 23,035 0 0 31-Mar-25 31-Mar-25 Tender awarded On Target On Target CMTY, BEITH - WALLS 198,653 101,320 198,653 0 86,685 86,685 0 0 31-Mar-25 31-Mar-25 Tender awarded On Target On Target CMTY, ABBEY TOWER - WALLS 151,812 11,337 151,812 0 5,285 5,285 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target CMTY, STEV HAWKHILL - WALLS 129,840 9,840 129,840 0 3,980 3,980 0 0 31-Aug-25 31-Aug-25 Feasibility Works On Target On Target CMTY, WEST KILBRIDE - WALLS 101,528 6,964 101,528 0 2,360 2,360 0 0 On Hold On Hold On Hold On Hold On Hold CMTY, MILLPORT - WALLS 2,846 2,846 2,846 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, ARDROSSAN - WALLS 4,338 4,338 4,338 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, IRVINE OP CHURCH - WALLS 2,775 2,775 2,775 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, DREGHORN - WALLS 8,240 8,240 8,240 0 4,980 4,980 0 0 Future years Future years Feasibility Works On Target On Target CMTY, KILBIRNIE BARONY - WALLS 1,828 1,828 1,828 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, LAMLASH - WALLS 3,627 3,627 3,627 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, STEV HIGH KIRK - WORKS 22,754 22,754 22,754 0 0 0 0 0 Future years Future years Feasibility Works On Target On Target CMTY, KILBIRNIE - NEW 1,502,525 37,443 1,502,525 0 26,156 26,156 (0) (0) 31-Mar-26 31-Mar-26 Feasibility Works On Target On Target CMTY, DALRY - WALLS 2,450 2,450 2,450 0 0 0 0 0 On Target On Target CMTY, ARDROSSAN - EXTENSION 14,703 14,703 14,703 0 14,703 14,703 (1) (1) 31-Mar-25 31-Mar-25 Planning On Target On Target COASTAL PLAY PARKS 420,065 420,065 420,065 0 420,065 420,065 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target STREET FURNITURE IMPROVEMENT 176,304 176,304 176,304 0 106,835 106,835 (0) (0) 31-Mar-24 31-Mar-24 Planning On Target On Target PARK ENABLING WORKS 148,678 148,678 148,678 0 63,315 63,315 (0) (0) 31-Mar-24 31-Mar-24 Planning On Target On Target RENEWAL OF PLAY PARKS 1,350,750 425,750 1,350,750 0 316,462 316,462 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target Total Streetscene 8,402,126 5,058,321 8,402,126 0 1,378,181 1,378,182 1 0 1 Transport VEHICLES * 3,044,751 3,044,752 3,044,751 0 3,044,751 3,044,752 1 1 31-Mar-24 31-Mar-24 Ongoing On Target On Target WORKPLACE CHARGERS 298,416 298,416 298,416 0 73,013 73,013 (0) (0) Complete Complete Complete Complete Complete FLEET DECARBONISATION 6,572,624 112,459 6,572,624 0 74,874 74,874 (0) (0) 31-Mar-24 31-Mar-24 Ongoing On Target On Target Total Transport 9,915,791 3,455,627 9,915,791 0 3,192,638 3,192,638 0 0 0 Waste Services SHEWALTON LANDFILL 13,321,491 13,272,542 13,321,491 0 0 0 0 0 Complete Complete Complete Complete Complete Total Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 Renewable Energy SOLAR PV RETROFIT EXTENSION 42,635 42,635 42,635 0 621 621 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target SOLAR PV INVESTMENT - NETHERMAINS 7,407,521 843,838 7,407,521 0 698,157 698,157 (0) (0) 30-Apr-24 30-Apr-24 Work Ongoing On Target On Target SOLAR PV INVESTMENT - SHEWALTON 5,614,813 607,802 5,614,813 0 509,692 509,692 0 0 30-Oct-24 30-Oct-24 Work Ongoing On Target On Target NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 936,411 936,411 936,411 0 0 0 0 0 31-Mar-24 31-Mar-24 Work Ongoing On Target On Target NATURE RESTORATION FUND 511,000 0 511,000 0 0 0 0 0 31-Aug-24 31-Aug-24 Planning On Target On Target Total Renewable Energy 14,512,381 2,430,687 14,512,381 0 1,208,470 1,208,470 0 0 0
Page 21
PLACE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical Project Description TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS Comments CAPITAL MONITORING 2023/24 COMPLETION DATES Office Accommodation PROPERTY LIFECYCLE INVESTMENT * (1) 0 (1) 0 (1) 0 1 1 31-Mar-24 31-Mar-24 Mulitple projects On Target On Target PLI CASTLEVIEW DAY SERVICES 75,349 75,349 75,349 0 75,349 75,349 0 0 31-May-24 31-May-24 Construction On Target On Target PLI CENTRAL AVE STREETSCENE DEPOT* 6,325 6,325 6,325 0 6,325 6,325 (0) (0) Complete Complete Complete Complete Complete PLI WEST KILBRIDE CEMETERY 26,399 26,399 26,399 0 26,399 26,399 (1) (1) Complete Complete Complete Complete Complete PLI BEITH CEMETERY 69 69 69 0 69 69 (0) (0) Complete Complete Complete Complete Complete PLI TOWNEND CC 7,949 7,949 7,949 0 7,949 7,949 0 0 Complete Complete Complete Complete Complete PLI WEST KILBRIDE COMMUNITY CENTRE 650 650 650 0 650 650 0 0 Complete Complete Complete Complete Complete PLI PORTLAND PLACE 17,267 17,267 17,267 0 17,267 17,267 0 0 Complete Complete Complete Complete Complete PLI WEST BYREHILL DEPOT 103,115 103,115 103,115 0 103,115 103,115 0 0 Complete Complete Complete Complete Complete PLI GOLDCRAIGS DEPOT 115,517 5,628 115,517 0 5,628 5,628 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target PLI ANNICK PRIMARY SCHOOL 186 186 186 0 186 186 0 0 Complete Complete Complete Complete Complete PLI ARDEER PRIMARY SCHOOL 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete PLI BEITH PRIMARY SCHOOL 1,957 1,957 1,957 0 1,957 1,957 (0) (0) Complete Complete Complete Complete Complete PLI CASTLEPARK PRIMARY SCHOOL 84,253 84,253 84,253 0 84,253 84,253 (0) (0) Complete Complete Complete Complete Complete PLI CUMBRAE PRIMARY 3,867 3,867 3,867 0 3,867 3,867 (1) (1) Complete Complete Complete Complete Complete PLI DALRY PRIMARY SCHOOL 129,299 60,985 129,299 0 60,985 60,985 0 0 Complete Complete Complete Complete Complete Pitch repair work completed. Floor slab repairs now postponed.PLI DREGHORN PRIMARY SCHOOL 65,847 65,847 65,847 0 65,847 65,847 0 0 Complete Complete Complete Complete Complete PLI GLENCAIRN PRIMARY SCHOOL 4,469 4,469 4,469 0 4,469 4,469 (0) (0) Complete Complete Complete Complete Complete PLI LOUDOUN MONTGOMERY PS 2,395 2,395 2,395 0 2,395 2,395 0 0 Complete Complete Complete Complete Complete PLI MAYFIELD PRIMARY 4,850 4,774 4,850 0 4,774 4,774 0 0 Complete Complete Complete Complete Complete PLI PENNYBURN PRIMARY 169,251 169,251 169,251 0 169,251 169,251 (0) (0) Complete Complete Complete Complete Complete PLI SKELMORLIE PRIMARY SCHOOL 531,946 37,446 531,946 0 37,446 37,446 (0) (0) Complete Complete Complete Complete Complete Change in scope. No further work anticiapted for heating replacement.PLI ST BRIDGETS PRIMARY 20,184 20,184 20,184 0 20,184 20,184 (0) (0) Complete Complete Complete Complete Complete PLI ST JOHN OGILVIE PRIMARY SCHOOL 6,744 6,744 6,744 0 6,744 6,744 0 0 Complete Complete Complete Complete Complete PLI AUCHENHARVIE ACADEMY* 429,457 429,457 429,457 0 429,457 429,457 (0) (0) Complete Complete Complete Complete Complete PLI IRVINE ROYAL ACADEMY* 974 974 974 0 974 974 0 0 Complete Complete Complete Complete Complete PLI KILWINNING ACADEMY 187,957 187,957 187,957 0 187,957 187,957 (0) (0) Complete Complete Complete Complete Complete Underlying structural issues identified during constuction work which now requires remedial action. PLI KYLE ROAD UNIT 34 4,069 4,069 4,069 0 4,069 4,069 (0) (0) Complete Complete Complete Complete Complete PLI BRIDGEGATE HOUSE 167,029 12,912 167,029 0 12,912 12,912 0 0 30-Sep-24 30-Sep-24 Planning On Target On Target PLI CUNNINGHAME HOUSE 0 0 0 0 0 0 0 0 On Hold On Hold On Hold On Hold On Hold PLI ACHNAMARA CHILDREN'S UNIT 11,954 11,954 11,954 0 11,954 11,954 (0) (0) Complete Complete Complete Complete Complete PLI THE MEADOWS 39,513 39,513 39,513 0 39,513 39,513 0 0 Complete Complete Complete Complete Complete PLI ANAM CARA 108,259 108,259 108,259 0 108,259 108,259 (0) (0) Complete Complete Complete Complete Complete PLI TAIGH MOR 5,153 5,153 5,153 0 5,153 5,153 0 0 Complete Complete Complete Complete Complete PLI VIKINGAR 3,096 3,096 3,096 0 3,096 3,096 0 0 Complete Complete Complete Complete Complete PLI EGLINTON CASTLE 48,000 0 48,000 0 0 0 0 0 31-Mar-24 31-Oct-24 Planning On Target On Target PLI GARNOCK CAMPUS 6,315 6,315 6,315 0 6,315 6,315 (0) (0) Complete Complete Complete Complete Complete PLI THE PORTAL 47,754 47,754 47,754 0 47,754 47,754 (0) (0) Complete Complete Complete Complete Complete Total Office Accommodation 2,437,417 1,562,521 2,437,417 0 1,562,521 1,562,521 (0) 0 (0) Other Property INDUSTRIAL PORTFOLIO * 0 0 0 0 0 0 0 0 On Hold On Hold On Hold On Hold On Hold HOME 289,971 289,971 289,971 0 1,323 1,323 (0) (0) Complete Complete Complete Complete Complete BUILD 47,749 47,749 47,749 0 1,500 1,500 0 0 Cancelled Cancelled Cancelled Complete Complete EMERGENCY CONTROL CTR 67,191 67,191 67,191 0 65,971 65,971 0 0 31-Mar-24 31-Mar-24 In development On Target On Target GOLDCRAIGS REFURBISHMENT 766,000 36,650 766,000 0 11,650 11,650 0 0 31-Mar-26 31-Mar-26 In development On Target On Target GALLOWGATE TOILETS 275,803 275,803 275,803 0 246,153 246,153 0 0 Complete Complete Complete Complete Complete WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 109,065 134,641 0 2,943 2,943 0 0 Complete Complete Complete Complete Complete Total Property 1,581,355 826,429 1,581,355 0 329,540 329,540 (0) 0 (0) Other Housing CCTV REVIEW 350,000 0 350,000 0 0 0 0 0 31-Mar-25 31-Mar-25 Planning On Target On Target 2-4 BOYLE STREET HOSTEL 231,905 231,905 231,905 0 142,930 142,930 0 0 Complete Complete Complete Complete Complete Total Other Housing 581,905 231,905 581,905 0 142,930 142,930 0 0 0
Page 22
PLACE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical Project Description TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS Comments CAPITAL MONITORING 2023/24 COMPLETION DATES Regeneration TOWN CENTRE REGENERATION 1,177,541 1,177,541 1,177,541 0 181,573 181,573 (0) (0) Complete Complete Complete Complete Complete REPURPOSING PROPERTY GRANT FUND 250,680 680 250,680 0 0 0 0 0 30-May-25 30-May-25 In development On Target On Target MILLPORT TOWN HALL REGENERATION 533,492 533,492 533,492 0 0 0 0 0 Complete Complete Complete Complete Complete MILLPORT TOWN HALL PHASE 2 0 0 0 0 0 0 0 0 31-May-23 31-Mar-24 Construction On Target Significantly off target GARRISON HOUSE PROJECT 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-24 In development On Target On Target ISLANDS PIT STOPS 500,000 0 500,000 0 0 0 0 0 31-Jul-24 31-Jul-24 In development On Target On Target ISLAND INFRASTRUCTURE FUND 199,000 118,626 199,000 0 0 0 0 0 31-Mar-24 31-Dec-24 In development On Target On Target DYEMILL BIKE PARK PROJECT 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target ISLANDS COST CRISIS FUND 0 0 0 0 0 0 0 0 Complete Complete Complete Complete Complete PLACE BASED INVESTMENT PROGRAMME (PBIP) 420,680 30,777 420,680 0 (1) 0 1 1 31-Mar-26 31-Mar-26 In development On Target On Target UK SHARED PROSPERITY FUND (SPF) 0 (0) 0 0 0 (0) (0) (0) 31-Mar-25 31-Mar-25 In development On Target On Target DIGITAL - SIPP GREAT HARBOUR 242,765 0 242,765 0 0 0 0 0 31-Mar-25 30-Jul-25 Planning On Target On Target AYRSHIRE 5GIR 3,810,935 19,935 3,810,935 0 19,935 19,935 (1) (1) 31-Mar-25 31-Mar-25 Planning On Target On Target PBIP – KILWINNING ABBEY IMPROVEMENTS 235,354 0 235,354 0 0 0 0 0 31-Mar-25 31-Mar-25 In development On Target On Target LOCHSHORE HUB PLAY AREA 437,183 42,183 437,183 0 42,183 42,183 0 0 30-Jun-24 30-Jun-24 Construction On Target On Target PBIP 36 BANK STREET 157,238 107,238 157,238 0 24,066 24,066 (0) (0) 31-Dec-25 31-Dec-25 In development On Target On Target PBIP GALT HOUSE 49,125 4,125 49,125 0 4,125 4,125 0 0 31-Mar-24 31-Mar-25 In development On Target On Target IRVINE HIGH STREET 2,813,316 2,736,001 2,813,316 0 14,647 14,647 (0) (0) Complete Complete Complete Complete Complete MILLPORT CARS 0 0 0 0 0 0 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target MONTGOMERIE PARK MASTERPLAN 4,215,504 1,791,840 4,215,504 0 16,907 16,907 0 0 31-Mar-30 31-Mar-30 In development On Target On Target LOCHSHORE, KILBIRNIE 1,993,374 1,904,016 1,993,374 0 262,236 262,236 (0) (0) 31-May-25 31-May-25 In development On Target On Target LOCHSHORE GARNOCK HUB 4,146,387 4,087,008 4,146,387 0 3,238 3,238 (0) (0) Complete Complete Complete Complete Complete VDLF 2024/25 ALLOCATION 963,000 0 963,000 0 0 0 0 0 VDLF - KYLE ROAD PHASE 2 1,362,231 145,005 1,362,231 0 4,165 4,165 0 0 31-Mar-24 31-Dec-26 In development On Target On Target VDLF - ANNICKBANK PH 3* 1,892,786 1,892,786 1,892,786 0 1,816,525 1,816,525 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target LUF3 - ANNICKBANK 50,000 0 50,000 0 0 0 0 0 31-Mar-26 31-Mar-26 In development On Target On Target VDLF - DEVELOPMENT WORK* 227,478 93,467 227,478 0 (1) 0 1 1 31-Mar-25 31-Mar-25 In development On Target On Target VDLF - TREE PLANTING 50,000 2,400 50,000 0 0 0 0 0 31-Dec-24 31-Dec-24 In development On Target On Target MONTGOMERIE PARK NEIGHBOURHOOD CTR 140,000 0 140,000 0 0 0 0 0 31-Mar-24 31-Dec-24 In development On Target On Target VDLF STALLED SPACES FUND 125,000 0 125,000 0 0 0 0 0 31-Mar-24 31-Mar-25 In development On Target On Target QUARRY ROAD PHASE 2 5,204,719 5,204,719 5,204,719 0 0 0 0 0 Complete Complete Complete Complete Complete CYCLING/WALKING/SAFER STREETS * 1,342,326 2,135,422 1,342,326 0 1,342,326 1,342,326 (0) (0) 31-Mar-24 31-Mar-24 Various On Target On Target ACCESS PATH NETWORK PROGRAMME * 23,414 23,415 23,414 0 23,414 23,415 1 1 31-Mar-24 31-Mar-25 Various On Target On Target FAIRLIE COASTAL PATH 191,085 191,085 191,085 0 191,085 191,085 (0) (0) 31-Dec-23 01-Jun-24 Construction On Target On Target IRVINE CYCLE FRIENDLY TOWN 48,505 514,703 48,505 0 48,505 48,505 (0) (0) 31-Mar-24 31-Mar-24 Pre Construction On Target On Target BRODICK TO CORRIE CYCLE PATH 79,192 139,391 79,192 0 79,192 79,192 0 0 31-Mar-24 31-Mar-24 Design On Target On Target ARDROSSAN PROMENADE 209,501 209,501 209,501 0 209,501 209,501 0 0 31-Mar-24 31-Dec-24 Construction On Target On Target BUS CORRIDOR IMPROVEMENTS 215,373 215,374 215,373 0 26,332 26,332 0 0 31-Mar-24 31-Mar-24 Various On Target On Target CUMBRAE FERRY & BUS STOP 212,514 212,514 212,514 0 72,967 72,967 0 0 31-Mar-24 31-Mar-24 Construction On Target On Target KILBIRNIE TO KILWINNING 18,334 18,333 18,334 0 18,334 18,333 (1) (1) 31-Mar-24 31-Mar-24 Planning On Target On Target B714 ACTIVE TRAVEL IMPROVEMENTS 346,710 346,710 346,710 0 246,710 246,710 (0) (0) 31-Mar-24 31-Mar-24 Construction On Target On Target B777 CORRIDOR IMPROVEMENTS 95,965 84,569 95,965 0 79,769 79,769 (0) (0) 31-Mar-24 30-Jun-24 Planning On Target On Target CYCLE SHELTER 11,409 11,409 11,409 0 11,409 11,409 0 0 Complete Complete Complete Complete Complete NCN73 ACCESSABILITY IMPROVEMENTS 15,882 15,882 15,882 0 15,882 15,882 (0) (0) 31-Mar-24 31-Mar-24 Planning On Target On Target NCN753 LARGS PROMENADE 40,034 40,034 40,034 0 40,034 40,034 0 0 31-Mar-24 31-Mar-24 Design On Target On Target LINKS TO EGLINTON PARK 88,874 88,874 88,874 0 88,874 88,874 (0) (0) 31-Mar-24 31-Mar-24 Construction On Target On Target COMMUNITY BUS FUND 86,541 86,541 86,541 0 86,541 86,541 0 0 31-Mar-24 31-Mar-24 Planning On Target On Target SALTCOATS OLD CAL RAILWAY PH1 192,222 192,223 192,222 0 137,147 137,148 1 1 Complete Complete Complete Complete Complete SALTCOATS OLD CAL RAILWAY PH2 47,881 47,880 47,881 0 47,881 47,880 (2) (2) 31-Mar-24 31-Mar-24 Design On Target On Target Total Regeneration 34,463,550 24,465,696 34,463,550 0 5,155,501 5,155,501 (0) 0 (0) Community led regeneration project by Millport Town Hall Charity. Project has been delayed due to construction challenges. The Council's Regeneration team continues to support MTHC in the delivery of the project.
Page 23
PLACE MILESTONE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Actual Over/ (Under) Spend for 2023/24 True Over/ (Under) Spend Brought / Carry Forward to 2024/25 Original Target Revised Forecast Current Project Stage Delivery Status Financial Delivery Status Physical Project Description TOTAL PROJECT 2023/24 BUDGETS DELIVERY STATUS Comments CAPITAL MONITORING 2023/24 COMPLETION DATES Ayrshire Growth Deal AYRSHIRE GROWTH DEAL 0 0 0 0 0 0 0 0 31-Mar-26 31-Mar-26 On Target On Target AGD - I3 DPMC PHASE 1 976,700 276,251 976,700 0 270,802 270,802 (0) (0) 31-Mar-26 31-Mar-26 Delivery On Target On Target AGD - I3 DPMC PHASE 2 5,004,072 289,385 5,004,072 0 49,970 49,970 (0) (0) 31-Mar-26 31-Mar-29 Feasibility On Target On Target AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 5,476,981 3,457,835 5,476,981 0 2,912,412 2,912,412 0 0 31-Oct-24 31-Oct-24 Construction On Target On Target AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 10,950,840 50,840 10,950,840 0 50,840 50,840 0 0 31-Mar-28 31-Mar-28 Multiple Projects On Target On Target AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR ECONOMY 18,037,332 249,560 18,037,332 0 17,332 17,332 (0) (0) 31-Mar-30 31-Mar-30 Feasibility On Target On Target AGD - GREAT HARBOUR 14,223,869 1,019,367 14,223,869 0 421,277 421,277 0 0 31-Mar-28 31-Mar-29 Multiple Projects On Target On Target AGD - IMSE 10,467,734 151,247 10,467,734 0 17,734 17,734 0 0 31-Mar-30 31-Mar-30 Feasibility On Target On Target AGD - MARINE TOURISM ARDROSSAN 5,060,675 336,390 5,060,675 0 1,694 1,694 (0) (0) Complete Complete Complete Complete Complete AGD - MARINE TOURISM ARRAN 1,991,255 93,999 1,991,255 0 33,515 33,515 (0) (0) 31-Mar-29 31-Mar-29 Feasibility On Target On Target AGD - MARINE TOURISM CUMBRAE 4,475,788 129,534 4,475,788 0 61,355 61,355 0 0 31-Mar-29 31-Mar-29 Design On Target On Target Total Ayrshire Growth Deal 76,665,247 6,054,407 76,665,247 0 3,836,931 3,836,931 (0) 0 (0) Growth & Investment ARDROSSAN HARBOUR INTERCHANGE 4,115,083 551,424 4,115,083 0 95,971 95,972 1 1 1st Qtr 2026 1st Qtr 2026 Design On Target On Target IRVINE ENTERPRISE AREA 10,746,072 0 10,746,072 0 0 0 0 0 Ongoing Ongoing Multiple Projects On Target On Target LOW CARBON HUB 613,828 613,827 613,828 0 501,823 501,823 (0) (0) 30-Sep-24 30-Sep-24 Multiple Projects On Target On Target ARDROSSAN NORTH SHORE 37,069,194 5,926,109 37,069,194 0 3,092,343 3,092,343 (0) (0) 27-May-24 31-Mar-25 Construction On Target On Target VDLF - HARBOUR MASTERS OFFICE 158,700 26,378 158,700 0 5,446 5,446 (0) (0) 31-Mar-24 31-Mar-25 Design On Target On Target VDLF - I3 IRVINE ENTERPRISE 257,020 257,020 257,020 0 0 0 0 0 31-Mar-24 31-Mar-25 Design On Target On Target Other Growth & Investment 52,959,897 7,374,760 52,959,897 0 3,695,583 3,695,584 1 0 1 Total Economic Development & Regeneration 164,088,693 37,894,863 164,088,693 0 12,688,015 12,688,015 0 0 0 Completed Projects BIOMASS RETROFIT PROGRAMME 3,378,163 3,378,163 3,378,163 0 0 0 0 0 Complete Complete Complete Complete Complete QUARRY ROAD PHASE 1 2,977,098 2,947,722 2,977,098 0 11,219 11,219 0 0 Complete Complete Defects Period Complete Complete ARDROSSAN HOSTEL 0 0 0 0 Complete Complete Complete Complete Complete Total Completed Projects 6,355,261 6,325,885 6,355,261 0 11,219 11,219 0 0 0 Total Place 336,844,817 133,860,925 336,844,817 0 62,185,972 62,185,972 0 0 0
Page 24
OTHER BUDGETS AE Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Actual Expenditure to 31st March 2024 Over/ (Under) Spend for 23/24 £ £ £ £ £ £ £ FLEXIBILITY / IMPROVEMENT FUND 13,777,000 0 13,777,000 0 0 0 0 CORE INFRASTRUCTURE INVESTMENT 0 0 0 0 0 0 0 Total Other Budgets 13,777,000 0 13,777,000 0 0 0 0 2023/24 BUDGETS CommentsProject Description TOTAL PROJECT
Page 25
HRA Capital Statement 2324 2023-24 Appendix 2 TOTAL PROJECT CURRENT YEAR 2023/24 - Period 12 Project Description Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Revised budget after mgt fees adjustment Actual Expenditure to 31 March 2024 Virement Request Carry /Brought Forward to /From 2024/25 True Over/ (Under) Spend Delivery Status Financial Delivery Status Physical Narrative EXPENDITURE Council House Building Afton Court 1,335,654 1,268,527 1,335,654 0 681,987 701,234 614,860 (86,374) On Target Complete Complete, project contingency not required. Ayrshire Central Site 51,235,455 3,208,079 51,235,455 0 600,000 620,328 649,428 29,100 On Target Significantly off target Tenders received and currently being checked. Project due to commence on site July 2024. Bourtreehill Village 9,924,743 190,985 9,924,743 0 85,000 88,917 125,120 36,203 On Target Significantly off target Project due to commence on site January 2025. Brathwic Terrace 6,674,074 6,683,409 6,683,409 9,335 26,403 31,439 160,891 129,452 On Target Complete Complete Caley Court 3,131,066 3,103,356 3,131,066 0 322,630 331,862 294,921 (36,941) On Target Complete Complete Corsehillhead 2,032,906 262,558 2,032,906 0 0 0 49,959 49,959 On Target Significantly off target Options appraisal currently being carried out for the site due to projected costs being significantly higher than previously projected. Dalrymple Place 5,838,627 5,822,700 5,838,627 0 1,473 1,473 2,212 739 On Target Complete Complete Flatt Road 20,178,000 19,708,540 19,934,544 (243,456) 302,327 304,716 76,323 (228,393) On Target Complete Complete Friars Lawn 2,199,628 2,090,152 2,086,932 (112,696) 231,468 236,025 121,172 (114,853) On Target Complete Complete Fullarton Street (High Flats) 12,073,511 33,330 12,073,511 0 50,000 50,000 7,395 (42,605) On Target Significantly off target New build project due to commence on site July 2025. Garnock Academy Site 12,092,889 687,610 12,092,889 0 138,400 141,299 92,625 (48,674) On Target Significantly off target Project due to commence on site 17 June 2024. Garrier Court 2,335,551 2,382,239 2,348,027 12,476 34,212 34,212 0 (34,212) (34,212) On Target Complete Complete Glebe Place 2,075,877 0 2,075,877 0 0 0 0 On Target On Target Project deferred to 2026/27 following refurbishment of the block for Ukrainian funded by the Scottish Government. Harbourside 14,622,742 14,352,228 14,622,742 0 939,356 957,636 583,989 (373,647) (373,647) On Target Complete Complete James McFarlane Site 4,784,118 849,535 4,784,118 0 450,000 464,806 472,985 8,179 On Target Significantly off target Project commenced on site 25 March 2024. James Reid Site 11,820,675 967,814 12,279,460 458,785 0 3,293 105,211 101,918 On Target Significantly off target Project site start delayed due to non resolution of culvert maintenance issue Kings Arms (113-115 High Street) 2,904,416 334,141 2,904,416 0 182,000 182,000 27,267 (154,733) On Target Significantly off target Project due to commence on site 13 May 2024. Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 1,290,229 2,953,447 (321,059) 450,000 498,517 1,290,134 791,617 On Target Significantly off target Project commenced on site 15 January 2024. Largs Police Station 2,769,301 2,781,614 2,769,301 0 1,038,673 1,072,144 1,050,987 (21,157) On Target Complete Complete Montgomerie Park (Both Phases) 46,322,381 5,072,415 46,322,381 0 352,208 364,518 393,273 28,755 On Target Significantly off target Ground remediation works commenced on site March 2024 with main contract scheduled to commence towards the end of 2024. Regeneration Project 1d 9,965,851 2,750 9,965,851 0 0 0 0 0 On Target Significantly off target Pre Site Regeneration Project 1e 1,658,083 0 1,658,083 0 0 0 0 0 On Target On Target This relates to either Grange or Nursery Court - both of which should be on the appendix as separate projects (as per the SHIP tracker). Both have start dates of 01/04/26. Springvale 2,852,016 2,749,677 2,749,677 (102,339) 0 0 3,682 3,682 On Target Complete Complete Stanecastle Site 7,768,147 1,120,328 7,768,147 0 450,000 466,146 515,819 49,673 On Target Significantly off target Project commenced on site 25 March 2024. St Beya Gardens 3,691,052 3,689,346 3,689,346 (1,706) 1,706 1,706 0 (1,706) On Target Complete Complete St Colm's Largs 4,907,987 4,808,429 4,907,987 0 12,685 12,685 (65,451) (78,136) On Target Complete Complete St Michael's Wynd 13,996,769 14,097,411 13,996,769 0 0 0 (390) (390) On Target Complete Complete Towerlands Primary School 8,579,943 8,574,482 8,579,943 0 9,279 9,279 3,817 (5,462) On Target Complete Complete Unallocated Regeneration Block 8,304,876 0 8,304,876 0 0 0 0 On Target On Target Budget to be transferred to future years as not required for 2023/24. Nelson Street Regeneration 622,116 4,470 622,116 0 50,000 50,168 4,470 (45,698) On Target Significantly off target Tender documentation being prepared. Acquisition Of Land & Buildin 0 (113) 0 0 0 0 (113) (113) On Target On Target House Building - General 1,547,765 0 1,547,765 0 0 0 0 On Target On Target Acquisition Houses-Open Market 254,752 477,287 254,752 0 239,505 254,445 477,287 222,842 (0) 222,842 On Target On Target Ukraine Buy Backs 0 2,458,498 2,458,498 (0) Dickson Drive Phase 2 0 0 0 0 0 0 0 On Target On Target Harbour Street 0 0 0 0 0 0 0 On Target On Target Options appraisal currently being carried out for the site due to projected costs being significantly higher than previously projected. Refurb - Connell Court 0 3 0 0 0 0 3 3 On Target Complete Complete Kinnear Road 2,118 0 2,118 0 2,118 2,118 0 (2,118) On Target Complete Complete Sy Mary's Primary, Largs 6,092,975 2,553,324 6,092,975 676,260 757,074 2,553,324 1,796,250 On Target On Target Works commenced on site 8 January 2024. Contingency 11,000,624 0 11,000,624 0 78,322 0 649,126 (78,322) On Target On Target Internal Management Charges 1,757,259 1 1,757,259 0 1,757,259 317,919 1 (317,919) (317,919) On Target On Target SUB TOTAL 298,871,194 109,166,854 298,570,534 (300,659) 9,084,949 10,492,779 12,069,699 146,190 2,498,759 (921,840) Improvements to existing stock Wet Room - Void 426,386 306,928 306,928 (119,459) 426,386 437,928 306,928 (131,001) On Target On Target Reduction in estimated number of completions based on jobs received to date Bathrooms - Void 770,876 568,698 568,698 (202,178) 770,876 792,262 568,698 (223,564) On Target On Target Reduction in estimated number of completions based on jobs received to date Wet Room - Planned 150,025 162,000 162,000 11,975 150,025 150,025 162,000 11,975 On Target On Target Bathrooms - Planned 341,561 357,517 357,517 0 334,699 354,236 357,517 3,281 On Target On Target Electrical Rewiring 585,710 607,905 607,905 0 580,895 603,756 607,905 4,149 On Target On Target Anticipated slippage due to no access. Heating 2,924,745 2,268,166 2,268,166 (656,579) 2,721,825 2,807,121 2,268,166 (538,955) On Target On Target Scope of works less than budgeted for some properties and reduced numbers resulting in an anticipated underspend. Kitchens 1,581,530 1,537,384 1,537,384 0 1,458,554 1,516,369 1,537,384 21,015 On Target On Target Reduction in estimated number of completions due to no accesses. Kitchens - Void 1,313,771 1,223,772 1,223,772 (89,999) 1,313,771 1,359,792 1,223,772 (136,020) On Target On Target Reduction in estimated number of completions due to no accesses. Roofing 1,105,661 1,439,497 1,439,497 0 1,434,218 1,494,220 1,439,497 (54,724) On Target On Target Wallfloor rendering 62,000 146,843 146,843 0 134,783 282,221 146,843 (135,378) On Target On Target Budget pulled forward to reflect additional addresses EWI 4,473,962 4,316,792 4,316,792 (157,170) 4,473,962 4,499,674 4,316,792 (182,882) On Target On Target Overspend element due to an increase in anticipated unit rate Window Replacement 541,903 440,674 440,674 0 376,925 393,497 440,674 47,177 On Target On Target Work being undertaken in relation to access arrangements. Housing will be reviewing this in order to improve access. Saltcoats MSF Investment 1,314,188 880,682 880,682 (433,506) 1,314,188 1,347,307 880,682 (146,190) (466,625) On Target On Target Projected expenditure includes buy-back houses, budget virement requested. Smoke Detector Programme 250,000 259,060 259,060 9,060 250,000 259,742 259,060 (682) On Target On Target Energy Efficiency 122,610 12,734 12,734 0 10,000 10,479 12,734 2,255 On Target On Target Path Finder Project 250,000 0 0 0 10,000 10,000 0 (10,000) On Target On Target Solar Panels 5,050,000 4,944,308 4,944,308 0 4,560,026 4,771,193 4,944,308 173,115 On Target On Target Recently surveyed houses not suitable. Sent out another batch but unlikely to complete by year end SUB TOTAL 21,264,928 19,472,959 19,472,959 (1,637,856) 20,321,133 21,089,822 19,472,959 (146,190) (587,323) (1,029,540) DELIVERY STATUS
Page 26
TOTAL PROJECT CURRENT YEAR 2023/24 - Period 12 Project Description Total Project Budget Cumulative Expenditure to date Total Project Forecast Projected Over/ (Under) Spend Total Revised Budget 2023/24 Revised budget after mgt fees adjustment Actual Expenditure to 31 March 2024 Virement Request Carry /Brought Forward to /From 2024/25 True Over/ (Under) Spend Delivery Status Financial Delivery Status Physical Narrative DELIVERY STATUS Other Capital works Estate Based Regeneration 2,093,064 621,889 2,093,064 0 740,089 767,158 621,889 (145,269) On Target On Target Skelmorlie parking costs lower than expected. Lift Replacement 454,425 0 454,425 0 0 0 0 On Target On Target Slippage on programme . No returns when tendered. Works now expected to commence late summer. Sheltered Housing Units 12,965,531 5,091,024 12,965,531 0 4,633,521 4,825,489 5,091,024 265,535 On Target On Target Budget pulled forward due to an accleration of works High Flats Demolition 2,368,970 1,703,270 1,725,818 (643,152) 2,368,970 2,433,023 1,703,270 (729,753) On Target On Target Final Account has now been agreed Health and Safety Works 207,000 0 0 (207,000) 207,000 207,000 0 (207,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24. Parkhall & Kirkhall Asbestos 17,358 0 0 (17,358) 17,358 17,358 0 (17,358) On Target On Target Carried forward from 2022/23. Not required for 2023/24. Major Improvements 6,000 0 0 (6,000) 6,000 6,000 0 (6,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24. Newhouse Drive (Regen 1b) 5,000 0 0 (5,000) 5,000 5,000 0 (5,000) On Target On Target Carried forward from 2022/23. Not required for 2023/24. Maress House Refurb (12,540) 0 (12,540) 0 (12,540) (12,540) 0 12,540 On Target On Target Other Capital works 0 0 0 Kilbirnie Housing Office 254 6,749 6,495 Complete Complete SUB TOTAL 18,104,808 7,416,184 17,226,298 (878,510) 7,965,398 8,248,742 7,422,933 0 120,266 (946,076) Total Expenditure 316,976,002 116,583,038 315,796,832 (1,179,169) 37,371,480 39,831,343 38,965,590 0 2,031,702 (2,897,455) Income Affordable Housing Contributn (2,444,930) (2,444,930) (1,105,510) 1,339,420 CFCR (5,151,045) (5,191,128) (5,191,128) 0 Capital Grants (6,785,747) (8,712,947) (7,422,606) 1,290,341 Prudential Borrowing (18,925,091) (19,413,644) (25,242,319) (8,726,129) 2,897,455 Council HB fund contribution (4,064,667) (4,064,667) 0 4,064,667 Sale of Assets (4,027) (4,027) (0) Other Capital Income 0 0 0 SUB TOTAL (37,371,480) (39,831,343) (38,965,590) 0 (2,031,701) 2,897,455 Total Project Expenditure 316,976,002 116,583,038 315,796,832 (1,179,169) 37,371,480 39,831,343 38,965,590 0 2,031,702 (2,897,455) Total Project Income (37,371,480) (39,831,343) (38,965,590) 0 (2,031,701) 2,897,455 Total Net Expenditure 0 0 0 0 0 0