Page 1

NORTH AYRSHIRE COUNCIL 
2 June 2026 
Cabinet 
Title:    Flexible Advanced Manufacturing Space, i3 Irvine: 
Phase 2, Full Business Case 
Purpose:  To seek endorsement of the Full Business Case for Phase 2 of
the Flexible Advanced Manufacturing Space Project at i3, Irvine. 
Recommendation:  That Cabinet agrees to: 
(a) Endorse the Full Business Case for Phase 2 of the Flexible
Advanced Manufacturing Space project at i3, subject to
feedback from Scottish and UK Governments and the
successful outcome of the tender process;
(b) Delegate authority to the Executive Director (Place) to
update the Full Business Case to reflect the feedback and
outcome of the tender process; and
(c) Approve the submission of the Full Business Case to the
Ayrshire Economic Joint Committee. 
1. Executive Summary 
1.1 The i3 Flexible Advanced Manufacturing Space (flexible space) project is one of two
projects located at i3 Riverside Business Park in Irvine that is benefitting from an
overall investment of over £22M through the Ayrshire Growth Deal. i3 is one of North
Ayrshire’s key strategic sites, designated as an Enterprise Area in 2012 to attract life
science companies. 
1.2 The project is part of a wider programme of new employment space across Ayrshire
funded by £69.5M from the AGD, supporting economic infrastructure and engineering
and manufacturing sectors and through the Local Regeneration Fund that is delivering
additional floorspace in Irvine at Annickbank Innovation Campus on the edge of i3,
and at Kyle Road. The overall aim is to meet an identified demand for modern
business space where there has been a longstanding issue of market failure, to help
grow local businesses and to attract inward investment. Additional funding has also
been secured via the £17.4M award for the Levelling Up for Ayrshire: Commercial and
Low Carbon Infrastructure project from the Local Regeneration Fund, formerly the
Levelling Up Fund. 
1.3 Cabinet previously agreed to support the delivery of Phase One, with the approval of
the Full Business Case on 29 November 2022 and approval of the related lease on 2

Page 2

December 2025. The location of AGD flexible space investment is now focussed
entirely on a cluster entirely at Riverside Way informed by increased construction
costs, market demand and the successful marketing of the Strategic Investment
Campus site for inward investment. 
1.4 The draft Full Business Case provided at Appendix One is under review by the
Scottish and UK Governments. The tender for the design and build contract works has
been published, with receipt of tenders expected in July 2026. Subject to the selection
of a preferred bidder within the available budget, it is intended that the contract will be
awarded following feedback from Governments and any required adjustments, final
endorsement by Cabinet and the approval of the FBC by the Ayrshire Economic Joint
Committee (AEJC). 
2. Background 
2.1 The Ayrshire Growth Deal (AGD) investment in the flexible space project comprises of
£11M from Scottish Government and £4M from North Ayrshire Council, plus additional
funds leveraged from the Local Regeneration Fund (LRF), formerly Levelling Up Fund
(LUF) of £4.706M, and the Vacant and Derelict Land Fund (VDLF) of £0.967M, to help
create commercial space in a variety of formats and over a series of phases. 
2.2 The i3 Flexible Space project is focussed on investing in new business space in a
variety of formats, including large units capable of sub-division and small terraced
units for business start-ups or research and development. The project will help
address the following issues: 
• High local demand for industrial space.
• Low vacancy rates for industrial space of less than 1% for Irvine, 2.4% for North
Ayrshire and 4.4% for West of Scotland (amongst the lowest in the UK).
• Insufficient rental values to support financially viable new-build speculative
development.
• Very limited funding sources available for the public sector to intervene.
• Constraints on indigenous companies seeking to grow and expand within North
Ayrshire.
• Constraints on attracting inward investment through lack of modern premises.
• The need to grow the local economy through adapting to modern industrial
processes linked to Life Science, Advanced Manufacturing and other sectors.
• Ageing stock of existing industrial premises that is facing obsolescence.
• Constraints due to companies being less accessible to disabled or mobility
impaired job seekers / trainees.
• Growing pressure through changes in legislation and customer demand, to create
better configured, more energy efficient building stock and eliminate hazardous
building materials. 
2.3 Phase One of the project involved the construction of an 18,180 square foot (1,690
m2) light industrial unit on a 2.7 acres site with an adjoining yard and parking spaces.
The unit, which is capable of subdivision or extension, benefits from dedicated parking
including EV charging infrastructure, low energy LED lighting, roof mounted
photovoltaic panels and full fibre connectivity. A topping out event was held on 17
February 2026 to celebrate the completion of the project. The property has been
leased through a successful marketing campaign with the tenant, Barony Universal,
now in occupation.

Page 3

2.4 Phase Two will establish an additional unit of similar scale on a site approximately
4.59 acres in size and with a level of fit-out and also includes some development of
the wider site to accommodate a Sustainable Urban Drainage System (SUDS) and
road infrastructure. 
2.5 This Full Business Case (FBC) focusses on Phase Two of the project which requires
an overall estimated capital funding of £6.775M comprised of £4.706M from the LRF
and £2.069M from the Ayrshire Growth Deal. The funding supports the design and
build contract, consultancy costs, fees and staff costs for the development and
delivery of the project. The LRF contribution is assisting to address the increase in
construction costs over the time period of the AGD. 
2.6 The project and wider programme have revenue implications which are set out in
Section 4.1. In summary, there will be revenue costs incurred until the unit is occupied
and in relation to ongoing wider site maintenance. These costs will be met from
existing resources in the short term and recovered through additional rental income,
received once the unit and further developments are occupied. The marketing of the
unit will commence following the award of contract. 
2.7 The key risks related to the project are detailed within the FBC. These include tenders
received being above the available budget, potential delays to the expected timeline
for the approval of the FBC and award of tender, or unforeseen project complexities
that require additional funding. Mitigations include the delivery of Phase One in close
proximity to the Phase Two site and the availability of wider site information and the
approval of Phase One FBC. 
2.8 The draft FBC has been provided at Appendix One for Cabinet’s consideration, whilst
initial feedback from both Governments is awaited and the tender process for the
design and build contract is underway. The FBC will be updated informed by the
feedback and outcome of the tender process for submission to the Ayrshire Economic
Joint Committee (AEJC) for approval. Following the award of the contract, the
contractor will finalise the design, apply for building warrant and commence the
contract works. 
2.9 Progress of Phase Two represents continued positive investment in the i3 area and
the development of an innovation cluster complemented by wider investment in the
Digital Process Manufacturing Centre which adjoins the Phase One and Phase Two
flexible space sites, investment in active travel routes into i3 and the expected major
investment in AI and data centre development at the Strategic Investment Campus
site. 
3. Proposals 
3.1  It is proposed that Cabinet agrees to: 
a) Endorse the Full Business Case for Phase 2 of the Flexible Advanced
Manufacturing Space project at i3, subject to feedback from Scottish and UK
Governments and the successful outcome of the current tender process;

Page 4

b) Delegate authority to the Executive Director (Place) to update the Full Business
Case to reflect the feedback and outcome of the tender process; and
c) Approve the submission of the Full Business Case to the Ayrshire Economic
Joint Committee (AEJC). 
4. Implications/Socio-economic Duty 
Financial 
4.1 The main financial implications of the project are:
i) Capital – An estimated capital investment of £6.775M is required for Phase 2
towards a design and build contract and related costs including staff costs and
fees. This is comprised of £2,068,741 from the AGD and £4,706,259 from LRF.
These budgets are included in the NAC capital programme. The project’s capital
costs will be confirmed in an updated report to Cabinet, following the current
tender process and will be subject to the selection of a preferred contractor within
the available budget. Feedback from Governments will provide confirmation that
Phase Two can proceed and enable the draw down of the Scottish Government
AGD grant as part of the project budget. The LRF monies are being prioritised to
ensure full expenditure within the fund’s timescales.
ii) Revenue – Similar to Phase One, it is anticipated that there will be revenue costs
incurred by the Council until the Phase Two unit is occupied, such as building
and grounds maintenance, security, rates and utility bills, building insurance,
statutory compliance certificates, EPC costs, legal fees and marketing and
promotion. In addition, there will also be costs related to wider site maintenance
for this Phase and future developments at i3. Revenue costs will be met from
existing resources in the short term and will be reimbursed once a tenant is in
place and rental income starts to be received. 
Human Resources 
4.2 None. The project is being managed by the Council’s Property Management and
Investment (PMI) Team with input from the Growth and Investment Project Lead. 
Legal 
4.3 All Statutory consents have been secured with the exclusion of the Building Warrant
which will be secured by the successful contractor. The award of the tender is
required within the 150-day period. Furthermore, the Council will require to ensure
compliance with the conditions set out within the Local Growth Fund award. 
Equality/Socio-economic 
4.4 The project seeks to tackle market failure through the provision of much needed new,
modern and more energy efficient business space to help local businesses grow and
expand and to attract inward investment to an area of above average unemployment
and low business investment. It will build on recent investment in Phase One of the
project which is now under tenancy, and complement the Digital Process
Manufacturing Centre (DPMC) pilot project at the adjoining site which is operated by
the National Manufacturing Institute Scotland (NMIS).

Page 5

Climate Change and Carbon 
4.5 An assessment of carbon impact has been undertaken for the project and is included
within the business case. The unit will offer modern sustainable design features
including sustainable urban drainage, solar panels and electric vehicle charging. In
addition, the selected contractor will be required to ensure that the building design will
facilitate the ability to achieve recognised standards for CO2 emissions. 
Key Priorities 
4.6 The project will contribute to a range of Council Plan outcomes including the key
activities to develop infrastructure to support business growth and support local
businesses and economic opportunities. 
Community Wealth Building 
4.7 The project will contribute to Community Wealth Building and will have a significant
positive impact on Council’s ambitions under the Land and Assets pillar. In relation to: 
• Procurement: Local procurement and supply chain opportunities will be created
through the project.
• Fair Employment: The project will create employment opportunities particularly
within the construction sector and wider opportunities when the commercial
space is occupied by a tenant.
• Land and Assets: The project will regenerate a site which is long term vacant and
derelict land and identified as priorities for investment. This will bring
underutilised land into positive use to support local social, economic and
environmental wellbeing.
• Financial Power: The project will invest in localities and leverage external
national investment into North Ayrshire.
• Plural Ownership: The project will create commercial space to support local
businesses to stay and grow in North Ayrshire. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None.

Page 6

5. Consultation 
5.1 The Council’s PMI, Finance, Legal, Business Support and Development and Estates
Teams have been involved in the development of the project. An updated report for
the Irvine area by property agents has confirmed ongoing demand for the business
space alongside ongoing engagement with local businesses by the Business Support
and Development team. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Bruce McClure, Senior Manager, Growth and
Investment, on 01294 324176. 
Background Papers
Cabinet Report, 29 November 2022, Flexible Advanced Manufacturing Space, i3 Irvine:
Phase 1, Full Business Case
Cabinet Report, 21 March 2021, i3 Advanced Manufacturing Space Project, Irvine

Page 7

NAC Growth and Investment 
AGD Business Case 
1
i3, ADVANCED MANUFACTURING SPACE
Full Business Case, Phase 2 
Version No.2 
Issue Date: 01 May 2026

Page 8

NAC Growth and Investment 
AGD Business Case 
2
VERSION HISTORY 
Version  Date Issued  Brief Summary of Version / Change  Owner’s Name
1 10 April 2026 First draft version – issued to PMO Marnie Ritchie 
2 01 May 2026 Second version addressing initial PMO feedback M Ritchie, L Jamieson, K
MacDonald

Page 9

NAC Growth and Investment 
AGD Business Case 
3
Table of Contents 
Part A  Project Description 
Part B  The Five Cases 
1. EXECUTIVE SUMMARY .............................................................................................. 11
1.1 Introduction .............................................................................................. 11
1.1.1 Project aims & objectives ...................................................................... 12
1.1.2 Project scope ........................................................................................ 12
1.1.3 Project phases ...................................................................................... 14
1.1.4 Structure and content ........................................................................... 18
1.2 Strategic case .......................................................................................... 18
1.2.1 The strategic context ............................................................................ 18
1.2.2 The case for change ............................................................................. 20
1.3 Economic case ........................................................................................ 21
1.3.1 OBC long list and short list ................................................................... 21
1.3.2 The procurement .................................................................................. 23
1.3.3 Key findings and the preferred option ................................................... 23
1.4 Commercial case ..................................................................................... 24
1.4.1 Agreed products and services .............................................................. 24
1.4.2 Agreed risk allocation and charging mechanism .................................. 24
1.4.3 Key contractual arrangements .............................................................. 24
1.4.4 Agreed implementation timescales ....................................................... 24
1.4.5 Accountancy treatment ......................................................................... 25
1.5 Financial case .......................................................................................... 25
1.5.1 Financial expenditure ........................................................................... 26
1.5.2 Overall affordability and balance sheet treatment ................................. 26
1.6 Management case ................................................................................... 27
1.6.1 Project management arrangements ..................................................... 27
1.6.2 Benefits Realisation and Risk Management ......................................... 27
1.6.3 Post project evaluation arrangements .................................................. 27
1.7 Recommendation ..................................................................................... 27
2. THE STRATEGIC CASE ................................................................................................ 29
2.0 Introduction .............................................................................................. 29
2.1 Organisational overview ........................................................................... 30
2.2 Business strategies .................................................................................. 30
2.3.2 Regional Policy Context ........................................................................ 34

Page 10

NAC Growth and Investment 
AGD Business Case 
4
2.4 Investment objectives .............................................................................. 36
2.4.1 Strategic need ...................................................................................... 37
2.5 Existing arrangements ............................................................................. 38
2.6 Business needs ....................................................................................... 38
2.6.1 Property market assessment ................................................................ 39
2.7 Potential business scope and key service requirements .......................... 39
2.8 Main benefits criteria ................................................................................ 40
2.9 Main risks ................................................................................................. 41
2.10  Constraints .............................................................................................. 46
2.11 Dependencies .......................................................................................... 46
3. THE ECONOMIC CASE ............................................................................................... 47
3.1 Introduction .............................................................................................. 47
3.2 Critical success factors ............................................................................ 47
3.3 The long-listed options, Flexible Space Programme ................................ 48
3.4 Short-listed options, Flexible Space Programme ..................................... 50
3.5 The procurement process ........................................................................ 56
3.5.1 The Long List Criteria ........................................................................... 56
3.5.2 Long list ................................................................................................ 56
3.5.3 Short list criteria .................................................................................... 57
3.5.4 Short list ................................................................................................ 57
3.6 Economic appraisal .................................................................................. 57
3.6.1 Introduction ........................................................................................... 57
3.6.2 Estimating benefits ............................................................................... 57
3.6.3 Estimating costs ................................................................................... 59
3.6.4 Cost appraisal conclusions ................................................................... 59
3.7 Qualitative benefits appraisal ................................................................... 59
3.7.1 Methodology ......................................................................................... 59
3.7.2 Qualitative benefits criteria ................................................................... 60
3.7.3 Qualitative benefits scoring ................................................................... 61
3.7.4 Analysis of key results .......................................................................... 61
3.8 Risk appraisal – unquantifiables .............................................................. 61
3.9 The preferred option – selected supplier .................................................. 61
3.10 Sensitivity analysis ................................................................................... 62
3.11 The preferred option ................................................................................ 62
3.12 Sustainability and carbon ......................................................................... 62

Page 11

NAC Growth and Investment 
AGD Business Case 
5
3.13 Economic / Financial ................................................................................ 62
3.13.1 Embodied Carbon ................................................................................. 62
3.13.2 Operational Carbon .............................................................................. 63
4. THE COMMERCIAL CASE ........................................................................................... 64
4.1 Introduction .............................................................................................. 64
4.2 Required services .................................................................................... 65
4.3 Potential for risk transfer .......................................................................... 67
4.4 Agreed charging mechanism ................................................................... 67
4.5 Agreed contract length ............................................................................. 68
4.6 Key contractual clauses ........................................................................... 68
4.7 Personnel implications (including TUPE) ................................................. 68
4.8 Procurement route and implementation timescales ................................. 68
4.9 FRS 5 accountancy treatment ................................................................. 69
5.0 THE FINANCIAL CASE ................................................................................................ 70
5.1 Introduction .............................................................................................. 70
5.2 Impact on the organisation’s income and expenditure account ............... 71
5.3 Local Regeneration Fund (formerly Levelling Up Fund, 3) ....................... 71
5.4 Impact on the balance sheet .................................................................... 71
5.5 Overall affordability .................................................................................. 72
6.0 THE MANAGEMENT CASE ......................................................................................... 73
6.1 Introduction .............................................................................................. 73
6.2 Programme management arrangements ................................................. 73
6.3 Project management arrangements ......................................................... 74
6.3.1 Project reporting structure .................................................................... 74
6.3.2 Project Roles and Responsibilities ....................................................... 75
6.3.3 Project Plan .......................................................................................... 75
6.4 Use of Special Advisers ........................................................................... 76
6.5 Arrangements for change management ................................................... 77
6.6 Arrangements for benefits realisation ...................................................... 77
6.7 Carbon management ............................................................................... 78
6.8 Arrangements for risk management ......................................................... 78
6.9 Arrangements for contract management .................................................. 79
6.10 Arrangements for post project evaluation ................................................ 79
6.11 OCG Gateway review arrangements ....................................................... 79
6.12 Contingency plans ................................................................................... 80

Page 12

NAC Growth and Investment 
AGD Business Case 
6
Appendices 81
APPENDIX A: INCLUSIVE GROWTH HEAT MAP ............................................................................... 82
APPENDIX B: AGD PROJECT LINKS .................................................................................................. 83
APPENDIX C: BENEFITS REALISATION LOGIC CHAIN ...................................................................... 85
APPENDIX D: ECONOMIC MODELLING, i3 FLEXIBLE SPACE PHASE 2 ............................................. 86
APPENDIX E: RISK REGISTER ......................................................................................................... 104
APPENDIX F: INCLUSIVE GROWTH & COMMUNITY WEALTH BUILDING ..................................... 110
APPENDIX G: COMMUNITY BENEFIT STATEMENT ........................................................................ 111
APPENDIX H: EQUALITY IMPACT ASSESSMENT ............................................................................ 113
APPENDIX I:  CARBON ANALYSIS ................................................................................................. 121
APPENDIX J: AYRSHIRE GROWTH DEAL CHANGE MANAGEMENT PROCESS ............................... 122 
LIST of FIGURES 
1: Flexible Space, Phase 1, (4A Riverside Way, now complete and let)
2: Project location showing area of focus of AGD Investment 
3: Location of Flex Space Phase 1 & DPMC Pilot (within Booth Welsh), on Riverside Way, i3 
4: excerpt from i3 draft masterplan, 2021 
5: Image of proposal at OBC / Phase 1 FBC Stage
6: Updated - Proposed Phases of Flexible Space Programme
7: Updated Flexible Space Masterplan 
8: Active travel path connections to Riverside Way i3, delivered 2021/22
9: Current active travel route improvements in proximity to Ph 1 Flex Space i3 (shown green) 
10: Recent Active Travel Improvements on Long Drive
11: Phase 1, Flex Space (4A Riverside Way), front & rear elevations 
12: RIBA 2030 Climate Change Target Metrics 
13: Phase 2 Unit drawings 
14: Standard AGD Governance approach 
15: Organisational chart, showing governance of the project 
LIST of TABLES 
1: Flex Space Phase 2 Unit Specification 
2: Flexible Advanced Manufacturing Space estimated floorspace profile at OBC stage
3: Flexible Advanced Manufacturing Space profile – reduced and at FBC Ph 1 stage.
4: Flexible Advanced Manufacturing Space profile – at Phase 2 FBC stage. 
5: Strategic Drivers for Investment in Advanced Manufacturing Space at i3
6: Assessment of Options at i3 – Long List at OBC Stage 
7: Assessment of Options for i3 - Short List OBC Stage
8: Phase 2 and Phase 1 Options considered 
9: Flexible Space Phase 2, Project Milestones (working version)
10: Flexible Advanced Manufacturing Space, Phase 2 - Source of Capital Funds 
11: Flexible Space Financial Profile – Capital – updated 
12: National Policy and Strategies

Page 13

NAC Growth and Investment 
AGD Business Case 
7
13: Project’s Relationship to UK’s Modern Industrial Strategy 
14: Project’s Relationship to Scotland’s National Strategy for Economic Transformation  
15: Regional & Local Policy & Strategies 
16: Flexible Space Investment Objectives 
17: Investment Objectives and Stakeholder Benefits 
18: Flexible Advanced Manufacturing Space – Project Risks, Updated  
19: Critical Success Factors 
20: Preferred Way Forward, Flexible Space Programme – OBC Stage
21: Review of Critical Success Factors for Shortlisted Options for Overall Flexible Space Programme at
OBC Stage 
22: High-level Economic Outcomes at OBC Stage 
23: OBC Investment Appraisal Ranking 
24: Flexible Space, Phase 1 - Options 
25: Flexible Space Phase 2 Options 
26: Benefits-Cost Ratio Timeframe - 25 Year Appraisal
27: Benefits-Cost Ratio Timeframe - 25 Year Appraisal (Construction Impacts Removed)
28: Main Benefits
29: i3 Flexible Advanced Manufacturing Space - Outputs, Outcomes and Impacts, Benefits Realisation
Plan 
30: Qualitative Benefits Criteria
31: Estimated Embodied Carbon, Flexible Space Phase 2
32: Estimated Operational Carbon, Flexible Space Phase 2
33: Estimated Whole Life Carbon, Flexible Space Phase 2 
34: FBC Flex Space Phase 2, Risk Transfer Analysis 
35: Key timescales for progress of Phase 2 Unit 
36: Flexible Space Phase 2, Project Spend Profile 
37: Roles & Responsibilities 
38: Special Advisers 
39: Benefits-Cost Ratio Timeframe - 25 Year Appraisal – Sensitivity Testing of Single Unit
40: Benefits-Cost Ratio Timeframe - 25 Year Appraisal (Construction Impacts Removed) - Sensitivity
Testing of Single Unit
41: Economic Outputs – Overall value for money assessment
42: Profile of Benefits Accrued – 5 Year Periods 
43: Green House Gas Accounting

Page 14

NAC Growth and Investment 
AGD Business Case 
8
PART A: Project Description 
What is the project about?
This project is the second phase of the i3 flexible advanced manufacturing space project at i3
Business Park in Irvine, which is a strategic site for North Ayrshire Council and was
designated as a Life Science Enterprise Area in 2012. Phase 1 delivered an advanced
industrial unit of 18,180 ft2 (1,690 m2) GIFA to a shell specification suitable for Classes 4, 5
and 6, capable of subdivision to a maximum of 4 self-contained units with a rear service yard
and parking spaces, on a total site area of 10,972 m2 or 2.7 acres and at a total cost of
£5.147M, which included £0.967M of VDLF funds. The unit is now being leased to Barony
Universal Products Ltd who have recently submitted a planning application for an extension to
accommodate a new production line and related plant. 
The budget for Phase 2 is £6,775,000. It should be noted that Phase 2 is mostly being
funded by £4,706,259 of the Local Regeneration Fund (formerly the Levelling Up 3
funds) from UK Government, with the remaining funds of £2,068,741 covered by the
Ayrshire Growth Deal, comprising £355,650 from North Ayrshire Council and £1,713,091
from Scottish Government. This will deliver a unit of similar size c1,690m2 on a site
approximately 4.59 acres in size but also includes some development of the wider site to
accommodate suds and roads infrastructure. 
The project is being delivered in a number of phases. A third phase of the FBC will be
submitted in 2027 to cover the final phase of the project. 
This Full Business Case (FBC) for Phase 2, follows on from an Outline Business Case (OBC)
for the overall project which was approved in June 2021 and a Full Business Case for Phase 1
which was approved in December 2022. NAC is seeking the timely endorsement of the FBC
for Phase 2 by the Scottish Government and its subsequent approval by the Ayrshire
Economic Joint Committee (AEJC) to enable the construction works contract to be awarded
by September 2026 and the works to be completed by September 2027. The tender is
currently being prepared for publication. Timelines are critical to ensure that the tender award
takes place before the 150-day period expires for tenderers holding their costs. The funds
sourced from the Local Regeneration Fund require to be spent by 31 March 2028. 
Tenders will be received for the Phase 2 contract works and the details will be contained
within the Commercial Case in Section 4 in an updated version of the FBC. It should be noted
that these details will be limited following advice from the Council’s Corporate Procurement
Unit, who advised that the sharing of commercial information should be limited prior to the
award of the tender. 
The project will complement Phase 1 of the programme and also the Digital Process
Manufacturing Centre (DPMC) facility which is being supported by the Ayrshire Growth Deal
(AGD) and has been delivered in partnership with NMIS (National Manufacturing Institute
Scotland), University of Strathclyde and CPI (Centre for Process Innovation). The DPMC is
currently operating as a pilot in close proximity to the location of the Phase 1 Flex Space unit
and the Phase 2 Flex Space site. 
Why is it being undertaken?
Phase 2 of the project will contribute towards meeting current demand for new industrial space
within North Ayrshire and Ayrshire, where there is a longstanding issue of market failure that
discourages the private sector from building new space. It will help grow local businesses and
attract inward investment to an area of above average unemployment and low business
investment. It will also help to address an ongoing issue of ageing, obsolete industrial space.

Page 15

NAC Growth and Investment 
AGD Business Case 
9
The new space also provides the opportunity for interest from businesses linked to the DPMC
project to take up space, helping create a cluster of industry and innovation at i3. 
How does it fit within the wider Deal?
This project contributes to the wider AGD Economic Infrastructure Programme, addressing
economic underperformance by helping position Ayrshire as the go-to region for smart
manufacturing and digital skills and by improving access to employment opportunities. It
complements the Ayrshire Innovation Park development at Kilmarnock and commercial space
proposals at Prestwick and provides opportunities for investment linked to the DPMC and
Building Digital Capital AGD projects.   
What is being proposed?
The original approved OBC estimated that the project would involve the phased delivery of
approximately 9,000 m2 (97,000 sq ft) of floorspace in a variety of building types to suit
varying needs, ranging from larger 20,000 sq ft to 40,000 sq ft units capable of subdivision, to
small, terraced business incubation units and class 4 offices. A draft masterplan was
developed in 2020/21 to show the potential location and scale of development across i3. The
majority of the buildings were proposed to be located within a central area of i3, creating a
cluster area with the proposed DPMC. A small number of units were also proposed at the
large Strategic Investment Campus site at i3, to stimulate interest in this area. 
A review of costs at Phase 1 FBC stage identified that the costs of delivering each phase was
likely to be higher than the estimates contained in the OBC, due to the further development of
the project following OBC stage which provided a more accurate assessment of costs but also
due to cost inflation. It was then highlighted that the level of floorspace that could be delivered
for the available budget would be lower than that approved in the OBC at 9,000 sq m.
Projections at Phase 1 FBC stage estimated that the amount of floorspace that could be
delivered could within the available budget could be 6,000 sq m and this was accounted for in
the economic modelling. In order to offset these increased costs, allocations from the Vacant
and Derelict Land Fund have supported the development and delivery of Phase 1 and the
Local Regeneration Fund (formerly LUF3) is supporting Phase 2. 
How will it be delivered?
The overall project is being delivered in phases, allowing for a review of the market at key
stages.  Each phase will be designed by a professionally qualified team, led by architects and
tendered in packages over a number of phases through either a traditional procurement route
or a design and build route. Phase 2 is the subject of this FBC and has been developed with
support from North Ayrshire Council’s architects and quantity surveyors and is being tendered
as a design and build contract.   
What outcomes will it deliver and by when?
The outcomes anticipated include the delivery of much needed modern business space, new
jobs and construction jobs, support to SMEs, additional GVA, access to related employability
and skills programmes for local people including those from disadvantaged or protected
characteristic groups and removal of sites from the vacant and derelict land register. A
Benefits Realisation Plan has been prepared for the overall project in conjunction with the
Ayrshire Growth Deal PMO and Phase 2 will contribute to these outcomes. 
Who will use it and why?
The project will be marketed widely to local companies, including SME’s looking to grow and
expand and to inward investment companies from Ayrshire, Scotland, the UK and beyond. A
marketing campaign will be prepared for Phase 2. At closing date for marketing, Phase 1
received four bids to lease the premises, providing evidence of demand for Phase 2.

Page 16

NAC Growth and Investment 
AGD Business Case 
10
What are the headline figures around what is being proposed? 
An allocation of £15M from the Ayrshire Growth Deal was agreed for the i3 Flexible Space
project, comprised of £11M from Scottish Government and £4M from North Ayrshire Council.
Overall, £22.225M is being invested at i3 by the Ayrshire Growth Deal, including an allocation
of £7.225M contributing to the DPMC project. This has been added to by £4.706M from the
Local Regeneration Fund from UK Government for Phase 2 of the project, providing an overall
investment of £26.931M. 
Phase 2 is the beneficiary of funding from the Local Regeneration Fund as part of an overall
£17.5M allocation to North Ayrshire, aiming to address market failure through the delivery of
new energy efficient commercial property alongside the provision of low carbon infrastructure
at key employment sites including i3.   
Phase 1 has invested a total of £5.147M, comprising £4.180M of AGD committed capital
funding towards the first unit, supported by £0.967M of Vacant and Derelict Land Funds. 
Figure 1: Flexible Space, Phase 1, (4A Riverside Way, now complete and let)

Page 17

NAC Growth and Investment 
AGD Business Case 
11
PART B: The Five Cases
1. EXECUTIVE SUMMARY   
1.1 Introduction 
This Full Business Case (FBC) seeks approval for investment in Phase 2 of the i3 Flexible
Advanced Manufacturing Space project of up to a maximum of £2.069M of capital, including a
contract with a supplier, to undertake the construction of an 18,191 sq ft (1,690 sq m)
industrial unit as a second phase of the project. The remainder of the required funds of
£4.706M are being covered by the Local Regeneration Fund (formerly LUF3). The delivery of
further phases of the project will be set out in subsequent updates to the FBC. 
This FBC for Phase 2, follows on from the approval of the first FBC for Phase 1 in December
2022, and the project’s original Outline Business Case (OBC) approved in June 2021 for the
investment of £15M in the delivery of approximately 97,000 sq ft (approx. 9,000 sq m) of
flexible advanced manufacturing space at i3. The Phase 1 FBC and related change request
of April 2022 gained approval for a reduction in the anticipated level of floorspace that would
be delivered by the AGD, from 9,000 square metres to 6,000 square metres. Additional funds
secured from the Local Regeneration Fund (formerly LUF3) have sought to offset this risk to
project outcomes. 
The overall project includes the delivery of business space in various configurations, aiming
to meet demand in a series of phases, responding to market requirements and with a focus
on high value sectors. This includes chemical and life science manufacturing, more general
local demand and opportunities for space emerging from the development of the Digital
Process Manufacturing Centre (DPMC) at i3 by NMIS, CPI and NAC. The DPMC is being
delivered as part of the same AGD Economic Infrastructure Programme and is now
operational and engaging with business and industry as an NMIS specialist centre at
Riverside Way in i3. 
Figure 2: Project location showing area of focus of AGD Investment

Page 18

NAC Growth and Investment 
AGD Business Case 
12 
1.1.1 Project aims & objectives
The main investment objectives of the overall project are: 
• To create flexible business space capable of meeting manufacturing requirements for
chemical and life sciences, but also for a wide range of other high value sectors;
• To create a centre of digital innovation which offers digital tools, support and
innovation scaled to a national market supporting a restructure of the regional
economy to deliver advanced manufacturing;
• To create serviced industrial land and capable of immediate development;
• To create opportunities for employment and inclusive growth with particular emphasis
on making connections to local communities, schools and colleges in preparation for
employment, particularly in areas of deprivation and targeting people drawn from
disadvantaged or Protected Characteristic groups including women and young people;
• To attract mobile and private sector investment both from abroad and from indigenous
companies; and
• To create a sustainable, high quality business location and R&D cluster, capable of
meeting and keeping pace with the changing demands of high value manufacturing
sectors and complementing national initiatives including NMIS 
The project is now beginning to deliver on these objectives with the completion of the first
phase of business space and the operation of the DPMC pilot, which is adjacent to flex space,
combining to help enable a small innovation cluster. The project also aligns with Inclusive
Growth & Community Wealth Building objectives (see Appendix F).   
1.1.2 Project scope
The scope of the overall project is to contribute to the AGD’s Economic Infrastructure
Programme using £15M of AGD investment, additional leverage of £4.706M from the UK
Government’s Local Regeneration Fund (formerly LUF 3) and early support funding of
£0.967M from the Scottish Government’s Vacant and Derelict Land Fund (VDLF), to create
modern flexible advanced manufacturing space that addresses the current issues businesses
and inward investors are facing, with lack of modern business space provision in Ayrshire,
impacting on business growth and expansion. 
The project is focused on delivering this space at i3, east of Irvine town centre. The area was
developed as part of Irvine New Town from the early 1970s.  Given that the town was
originally planned with a much higher population than realised, and due to differing industrial
structures at the time, the i3 area is of significant scale and covers around 132 ha. Parts of i3
remain undeveloped and/or are in private ownerships and the flexible space development will
help to address this by focusing AGD development within a central area around Riverside
Way. The inclusion of flexible space and DPMC within this area helps to provide a sense of
consolidation, focus and longer term, presents the opportunity to provide services and
networking opportunities for businesses (see Figure 3). The large SIC site owned by NAC
(see Figure 2) was recently marketed for sale in 2025 and is now in the process of being sold,
subject to suspensive conditions. It has also been put forward for AI Growth Zone status,
which is currently being considered.

Page 19

NAC Growth and Investment 
AGD Business Case 
13 
Figure 3: Location of Flex Space Phase 1 and DPMC Pilot (within Booth Welsh), on Riverside Way, i3 
The advanced manufacturing space proposed will complement the DPMC project and
provide modern space in a number of phases. Now operational as a pilot, the DPMC is
raising the profile of i3 and encouraging business investment and growth with a focus on
Industry 4.0. The proposed investments are part of a strategy for i3 that allows the central
Riverside Way area to be developed as a core commercial space and potential service area
for i3, that includes flexible space and the DPMC facility, with the large Strategic Investment
Campus targeted for major inward investment linked to potential datacentre and AI
development through the sale of the site. 
The proposed Phase 2 unit includes the following specifications: 
Table 1: Flex Space Phase 2 Unit Specification 
ITEM  PROVISION 
GENERAL
• Unit specification suitable for immediate occupation
• GIFA 18,191 ft2 (1690m2)
• Site Area 74,023ft2 (6877m2)
• Steel portal frame
• Profiled and microrib cladding panels to Building Standards Class 1
Storage/Factory Use
• Cat A office fit out
• Fully serviced with water and electricity (metered)
• BT Openreach FTTP fibre connection
• Storage areas for waste collection and provision of infrastructure to
facilitate future installation of sprinkler system tank provided

Page 20

NAC Growth and Investment 
AGD Business Case 
14
ITEM  PROVISION 
POWER
• 100kVA 3-phase supply to each unit
• additional ducts to each sub-divided unit will be installed to allow
future Tenants to apply for individual LV connections based upon their
anticipated design load requirements.
• all apparatus and wiring connected to the low voltage systems shall be
suitable for use with a 3 Phase, 4 Wire, 400 Volt or 230 Volt, Single
Phase, 50 Hertz earthed neutral system.
WAREHOUSE/
FACTORY
• 8m haunch height (9.28m to ridge)
• Concrete floors with 50kN/m2 floor loading
• 10% roof lights
• Powered 4.4m (H) x 4.76m (W) level loading doors
• High bay LED lighting (330 lux)
OFFICE & 
CONVENIENCE
• Suspended ceilings with recessed LED lighting
• Kitchen
• Unisex and accessible WCs
EXTERNAL
• Secure 31.5m deep concrete service yard with gates will be formed to
the rear of the property accessed from a road constructed to
adoptable standards and suitable for RCC (Roads Construction
Consent)
• Dedicated car parking to NRDG Standards
• Covered Bicycle storage to NRDG Standards
SUSTAINABILITY 
• EPC rating "B"
• EV charging points
• Water saving sanitaryware
• Low energy PIR controlled LED lighting
• Air source heat pump for office heating and cooling
• Roof mounted solar PV installed with scope to increase this as
required.
SECURITY 
• gated access,
• intruder alarm 
• internal & external security lighting
• 2.4m high open mesh steel panel Security Fencing to the boundary 
VEHICLE PARKING • 35 spaces for General Industrial (Class 5) use in accordance with
minimum NRDG Standards
DISABLED PARKING  • 4 spaces 
EV PARKING  • 4 active spaces / 8 passive spaces 
CYCLE PARKING  • 12 spaces or 6 cycle stands 
The unit will be constructed north-west of and immediately adjacent to the Phase 1 unit and in
close proximity to the DPMC Phase 1 pilot facility. Phase 1 and 2 of the flex space project and
the DPMC pilot will begin to create the cluster of activity at i3. 
1.1.3 Project phases 
Estimated Floorspace at Outline Business Case Stage 
The original OBC anticipated that the following range of units in Table 2 would be delivered in
a number of phases through the £15M investment. This was informed through market
assessment and includes the Phase 1 unit highlighted in red, which is now complete.

Page 21

NAC Growth and Investment 
AGD Business Case 
15 
Table 2: Flexible Advanced Manufacturing Space estimated floorspace profile at OBC stage
Description  Size - sq m Size – sq ft
Flexible Space Estimated Floorspace at OBC Stage 
Terraced units, capable of subdivision  232 2,500
Terraced units, capable of subdivision  465 5,000
Modular building (capable of subdivision and or expansion) 1,858 20,000
Serviced plot  tbc tbc
Two office pavilions (2 x 425 sq.m.) 850 9,150
Modular building (capable of subdivision and or expansion) 3,716 40,000
Modular building (capable of subdivision and or expansion) 1,858 20,000
Total estimated floorspace  8,979 96,650 
These configurations are shown in the i3 draft Masterplan from 2021. Please see the excerpts
below. Figure 4 shows the proposed buildings in blue as part of the i3 AGD investment and
the potential development in other areas of i3 in red, should funding become available. Figure
5 shows an image of the proposals at that stage. 
Figure 4: excerpt from i3 draft masterplan, 2021 
Figure 5: Image of proposal at OBC / Phase 1 FBC Stage 
Proposed
Flex Space
Phase 1 
Booth Welsh &
DPMC Ph 1
Proposed
terraced units
Proposed DPMC Phase 2

Page 22

NAC Growth and Investment 
AGD Business Case 
16 
Estimated Floorspace at Phase 1, Full Business Case Stage 
The Phase 1 FBC advised that due to cost increases, the scale of floorspace to be delivered
was likely to be reduced and it was assumed that the estimated floorspace that could be
delivered would be in the region of 6,000 m2 for which the profile was shown in the table
below with Phase 1 highlighted again.   
Table 3: Flexible Advanced Manufacturing Space profile – reduced and at FBC Phase 1 stage. 
Description  Size - sq m Size – sq ft
Flexible Space Estimated Floorspace at Phase 1 FBC Stage
Terraced units, capable of subdivision  232 2,500
Terraced units, capable of subdivision  465 5,000
Modular building (capable of subdivision and or expansion) 1,690 18,180
Modular building (capable of subdivision and or expansion) 1,858 20,000
Modular building (capable of subdivision and or expansion) 1,858 20,000
Total estimated floorspace  6,103 65,680 
Estimated Floorspace at Phase 2, Full Business Case Stage 
For the purpose of Phase 2, the scale of floorspace to be delivered has been reviewed again
and the approach to how the AGD investment would be developed has also been reviewed as
part of wider considerations of the land available. The amended plans below show the
development of industrial units off Riverside Way, including the location of the Phase 1 and
Phase 2 units and a proposed Phase 3 which is terraced units and potential future
development plots or a further unit, subject to future funding (Figure 6). A cost plan for Phase
3 is awaited, to establish if additional floorspace can be delivered beyond the terraced units, to
ensure that the floorspace can be achieved that was estimated at Phase 1. Whilst the
Programme has benefited from Local Regeneration Funds, Phase 2 requires to deliver
significant infrastructure for the wider site, as a result of planning requirements. The focus of
development has been intensified around DPMC Phase 1 (Figure 7), with the large SIC site
indicated on the original masterplan now in the process of being sold for redevelopment.
Figure 7 also shows a potential site option for DPMC Phase 2 as part of the cluster. Further
investment is also anticipated as the new tenant of Phase 1 has submitted a planning
application for an extension of approximately 1,200m2.

Page 23

NAC Growth and Investment 
AGD Business Case 
17
Figure 6: Updated - Proposed Phases of Flexible Space Programme 
Figure 7: Updated Flexible Space Masterplan

Page 24

NAC Growth and Investment 
AGD Business Case 
18
Table 4: Flexible Advanced Manufacturing Space profile – at Phase 2 FBC stage. 
Description  Status Square
metres 
Square
feet
Flexible Space Estimated Floorspace at Phase 2 FBC Stage 
Modular building (capable of subdivision & expansion), Phase 1 Complete 1,690 18,180
Modular building (capable of subdivision & expansion), Phase 2 FBC 1,690 18,180
Terraced units (3A), capable of subdivision, proposed Phase 3 Design 642 6,910
Terraced units (3B), capable of subdivision, proposed Phase 3   Design 426 4,585
Remaining floorspace to be achieved to meet current floorspace
target, by serviced plots or additional unit  Design  1,655 17,825
Total estimated floorspace   6,103 65,680 
1.1.4 Structure and content 
This Full Business Case (FBC) sets out details related to Phase 2 of the project. The format
used is the Five Case Model and follows the AGD Project Management Office (PMO)
template. Subsequent updates to this FBC will be submitted for future phases of the project. 
1.2 Strategic case 
1.2.1 The strategic context 
The following table summarises the strategic drivers for this investment with the associated
national, regional and local strategy, plan or policy listed below: 
Table 5: Strategic Drivers for Investment in Advanced Manufacturing Space at i3
UK Policy Agenda Scottish Government Policy  Ayrshire Regional Policy
The UK’s Modern
Industrial Strategy 2025
Scotland’s National Strategy for
Economic Transformation, 2022-2032
Ayrshire Regional Economic Strategy 2023-
2033
UK Life Sciences Sector
Plan 2025
A Manufacturing Future for Scotland,
2016
North Ayrshire Council, Council Plan
2023-2028
Levelling Up the UK:
Executive Summary
Making Scotland’s Future: a recovery
plan for manufacturing & subsequent
programme
Sustainable North Ayrshire Strategy
2024-2027 
Scotland’s 2018 – 2032 Climate
Change Plan, Updated 2020
North Ayrshire Council Community
Wealth Building Strategy 2024-2027 
Life and Chemical Sciences
Manufacturing Strategy for Scotland 
Skills and Investment Plan for
Scotland’s Life and Chemical Sciences
LOIP – Irvine Locality Action Plan 2023/24  
Life Sciences Strategy for Scotland
2025 Vision
Ayrshire Growth Deal Agreement 
Chemical Sciences Scotland Strategic
Plan 2025
North Ayrshire Council Local
Development Plan 2 and emerging LDP3 
Green Data Centres and Digital
Connectivity Vision and Action Plan,
2021 
Shortlist for Data Centre Site Selection
in Scotland 2021 
A changing nation: how Scotland will
thrive in a digital world 
Shaping Scotland’s Economy: Inward
Investment Plan 2020 
Programme for Government, 2024 to
2025 Serving Scotland 
National Planning Framework 4, 2023

Page 25

NAC Growth and Investment 
AGD Business Case 
19 
National Innovation Strategy, 2023-33 
This £15M project is part of an overall investment of £22.225M that is being sought for i3
through the Ayrshire Growth Deal, with committed funding secured from UK Government
(£6.225M), Scottish Government (£11M) and North Ayrshire Council (£5M). £7.225M is
focussed on investment in the Digital Process Manufacturing Centre (DPMC) which is now
operational as a pilot with partners and is assisting in driving demand for space at i3 and
raising the profile of i3. It provides a unique facility and hub for businesses within process
manufacturing sectors (including Pharmaceutical Products, Oil & Gas, Chemicals and
Chemical Products, Agrichemicals (under life sciences), Food & Drink, Fast moving consumer
goods (FMCG) and Water (collection, treatment, supply) that are seeking to improve their
productivity and modernise their processes through digital automation. If the pilot is
successful, Phase 2 will be progressed which can expand on opportunities to provide events
and meeting space, R&D space, bio-manufacturing facilities and sector support. The UK
Government’s £6.225M contribution and a £1M contribution from North Ayrshire Council are
supporting the DPMC project. 
Previously a separate AGD Digital Programme Business Case led by South Ayrshire Council,
had included investment towards a subsea fibre optic cable and associated infrastructure that
may have had opportunities for Irvine as a potential landing point and investment linked to
data centres. However, a commercial case could not be advanced for the project and the
funds for the project have since been reallocated toward the Building Digital Capital
Programme across the three Ayrshire authorities, with North Ayrshire receiving c £4.631M
which could bring further investment to the i3 area. This would complement investment being
made by UK Government as part of the 5G Innovation Regions in partnership with NMIS at
i3, to provide a private 5G network with investment of £0.7M and the ambitions for AI campus
status focussed on the large Strategic Investment Campus. 
The Heat Map at Appendix A illustrates the strengths of relationships between the AGD
projects and the i3 project. The AGD Project Links Table at Appendix B, provides further
detail on particular AGD projects where there are strong links.   
I3 is also the focus of a number of improvements related to active travel to improve
connections to and from i3. Overall, the capital investment spent or planned at i3 through UK
& Scottish Government funds, amounts to approximately £33.5M. 
Figure 8: active travel path connections to
Riverside Way i3, delivered 2021/22 
Figure 9: current active travel improvements in
proximity to Phase 1 Flex Space (shown in green) 
Figure 10: Recent Active Travel Improvements on Long Drive

Page 26

NAC Growth and Investment 
AGD Business Case 
20 
1.2.2 The case for change 
AGD funding is required in order to meet demand for modern industrial accommodation in
the face of acute market failure. This is preventing private sector investment in speculative
industrial development across Ayrshire and most non-prime locations in Scotland. Recent
research commissioned by NAC has identified the following issues that demonstrate the
requirement for investment: 
• High demand for industrial space;
• Low vacancy rates for industrial space of less than 1% for Irvine, 2.4% for North
Ayrshire and 4.4% for West Central Scotland (among the lowest in the UK); 
(These figures were previously 4.5% for Irvine, 4.5% for North Ayrshire and 3.4% for West of
Scotland at Phase 1 FBC stage and 4%, 6% and 4% respectively at OBC stage)
• Insufficient rental values to support financially viable, new-build speculative
development;
• Very limited funding sources available for the public sector to intervene; 
• Constraints on indigenous companies seeking to grow and expand within North
Ayrshire; 
• Constraints on attracting inward investment through lack of modern premises; 
• Ageing building stock of existing industrial premises that is facing obsolescence; 
• Constraints due to companies being less accessible to disabled or mobility impaired
job seekers / trainees; and 
• Growing pressure through changes in legislation and customer demand, to create
better configured, more energy efficient building stock and eliminate hazardous building
materials. 
The overall i3 proposal has included engagement with the following partners and local
stakeholders through discussions and through commissioned research. 
• AGD PMO Team 
• Key Advisors (Scottish Enterprise)
• Local businesses 
• Irvine Locality Planning Partnership 
• Local industry leaders 
• Academia – NMIS, University of Strathclyde, CPI and Ayrshire College
• Other Council teams

Page 27

NAC Growth and Investment 
AGD Business Case 
21
1.3 Economic case 
1.3.1 OBC long list and short list 
In terms of the best option for delivery of the overall programme for this project to meet
demand, a wide range of potential options were considered at OBC stage, in terms of location,
interventions and scale of interventions, funding sources and timescales, shown in the table
below. A preferred option was identified for each category and three options were then
considered in greater detail within the Economic Case: 
• Do Nothing – the Counterfactual Option; 
• The Preferred Option: Flexible Space, Phased; and 
• The Ambitious Option: Flexible Space, Accelerated. 
The Critical Success Factors used when evaluating the long list of options below included: 
• How does the option satisfy the AGD Vision & key themes?
• How does the option provide a holistic fit and synergy with other national, regional and
local strategies?  
• How does the option optimise value for money?
• Is the option viable and can it be delivered?
• Will the option meet an identified market demand, remove a constraint and how will it
affect existing supply?
• Can the option be funded by both the up-front capital and future revenue? 
The long list for the original OBC stage and the overall programme, is shown in the table
below: 
Table 6: Assessment of Options at i3 – Long List at OBC Stage 
OPTIONS 
1. LOCATION 
1.1 i3 Enterprise Area (EA)  1.2 Other North Ayrshire Site  1.3 Other Ayrshire Sites
i3 is one of two locations in
Scotland marketed by SDI for
manufacturing linked to life
sciences & related sectors. It
has key locational benefits for
investors, with existing
established businesses. 
Preferred Option 
A limited number of other North
Ayrshire sites have capacity to
accommodate new development
but are unable to offer the
locational advantages of i3,
installed infrastructure capacity
and existing business base. 
Discounted Option 
Irvine has key sector and cluster
strengths in life sciences, and is
therefore an attractive
proposition for investors in
comparison to other Ayrshire
sites.   
Discounted Option 
2.1 Site Preparation Only 2.2 Flexible Space on all Sites  2.3 Flexible Space 
1.
INTERVENTION  Create prepared site
platforms at i3, ready for
immediate development. This
would offer a low-cost option
but would fail to meet the
needs of life sciences and
related manu-facturing
businesses for premises.
Discounted Option
Flexible space across the whole i3
area, including the large Strategic
Investment Campus could mean
the space would be too
dispersed, reducing its impact
and chance to create a central
cluster of activity.   
Potential Future Option
Delivering flexible space on a
phased basis linked to the
DPMC proposal, and that
addresses market need for
business space with the
opportunity to review the
specification after Phase 1. 
Preferred Option
3. SCALE 3.1 Small-Scale / Cautious 3.2 Mid-Scale Market Ready   3.3 Large-Scale / Ambitious
Developing 1 or 2 shell
buildings to test market
Similar to Option 2.3, a
market-ready proposition that
Similar to Option 2.2, cost
savings could be made if

Page 28

NAC Growth and Investment 
AGD Business Case 
22
interest but discounted due to
value for money factors i.e.
there is clear demand for the
units proposed but developing
in smaller phases will
ultimately increase costs.
Discounted Option
balances forecast demand,
level of risk, cost efficiencies
and future flexibility. 
Preferred Option
large-scale flexible space was
delivered. This could
significantly increase costs
and risks, overstep the known
level of demand and is likely
to be in advance of need.
Discounted Option
4. FUNDING SOURCES 
4.1 Seek AGD Funding  4.2 Seek Other Public Funds  4.3 Seek Private Partner
AGD funding through the
public sector allows business
space to be provided in the
face of market failure as
development is not viable for
the private sector. Consider-
ation to be given to a rolling
development programme
utilising development income. 
Preferred Option 
There are no alternative public
sector funding sources
identified to deliver this scale of
intervention. We will continue
to scan the market to identify
other funding sources and
respond accordingly. 
Potential Future Option 
Attracting private investment
to develop new business space
was considered but has been
discounted due to its lack of
viability in Ayrshire. This
option will be reviewed as a
future option. 
Discounted Option 
5. TIMESCALES
5.1 Immediate 5.2 Phased Approach  5.3 Postpone
Similar to 2.2 and 3.3, there is
potential to develop the whole
of the i3 site immediately. This
would deliver cost savings to
the public sector but would also
increase risk and remove the
option to adapt the size/ layout
of proposed space on demand. 
Discounted Option 
Delivering the AGD investment
through a phased approach
minimises risk – this creates
flexible manufacturing space,
alongside the DPMC project, to
meet immediate demand and
allows further phases of flexible
space, based on take-up of Phase
1.
Preferred Option 
The project could be planned,
designed, costed, approved and
all relevant permissions secured
but construction postponed til
occupier interest is secured.
This option fails to meet the
current market need for good
quality business units that are
ready for occupation 
Discounted Option 
The short-list for the OBC stage is shown in the table below: 
Table 7: Assessment of Options for i3 - Short List OBC Stage
Option 1
Do Nothing 
Option 2 (Preferred)
Flexible Space, Phased  
Option 3 (Ambitious)
Flexible Space, Accelerated
Delivers no additional
floorspace
Attracts 0 occupiers
Delivers 0 gross jobs
Delivers 8,830 sqm floorspace (NIA)
Attracts 8 to 16 occupiers 
Delivers 162 net jobs 
Delivers 8,830 sqm floorspace (NIA)
Attracts 8 to 16 occupiers
Delivers 162 net jobs
Investment Level 
AGD NAC & SG £0
Other Funding £0
Investment Level 
AGD NAC £4M
AGD SG £11M
Investment Level 
AGD NAC £4M 
AGD SG £11M
Delivery Timescale 
N/A
Delivery Timescale 
(21/22) to (27/28)
Delivery Timescale 
(21/22) to (24/25) 
The conclusion of the Economic Appraisal for the OBC was that a phased delivery of the
floorspace was the preferred approach. Phase 1 was progressed as a first unit to accelerate
the programme as much as possible and was developed during the challenges of COVID. 
Whilst Option 2 - Phased Delivery was the preferred option for the OBC, Section 3 provides an
analysis of options specifically for delivering Phase 2, which is the subject of this FBC and
Appendix D provides detail on the economic modelling. The table below provides a summary of
the options considered for Phase 2 and a comparison of the options previously considered for
Phase 1.

Page 29

NAC Growth and Investment 
AGD Business Case 
23
Table 8: Phase 2 and Phase 1 Options considered 
Options Comparison across phases
Options for Phase 1 Options for Phase 2
Option 1 Do nothing  Option 1 Do Nothing 
Option 2:
Preferred
Option 
Preferred Option, Deliver 18,180 sq
ft Phase 1 unit with occupancy
achieved half-way through 24/25
Option 2
Preferred
Option 
Deliver 18,180 sq ft Phase 2 unit
by June 2027, with occupancy
achieved by April 2028. 
Preferred
Option 
Sensitivity Check – Negative Impact
– assumes unit subdivided into 4
with 100% occupancy achieved in
2027/28
Preferred
Option 
Sensitivity Check – Negative
Impact – assumes unit subdivided
into 4 with 100% occupancy
achieved by March 2029.
Preferred
Option 
Sensitivity Check – Positive Impact –
assumes unit fully occupied at the
start of 24/25
Preferred
Option 
Sensitivity Check – Positive Impact
– assumes unit fully occupied by
June 2027.
Option 3 Deliver Phase 2 instead – comprised
of two sets of terraced units and
one modular unit 
Option 3
Subdivided Unit 
Deliver 17,544 sq ft unit
subdivided into 4 lettable units by
30 June 2027 with 100%
occupancy by April 2029. 
Option 4
Terraced Units 
Deliver two sets of terraced units
totaling 11,495 sq ft with 100%
occupancy by April 2029  
Option 5
Smaller Unit,
Local Regen
Fund only 
Deliver smaller single unit within
Local Regeneration Fund cost
envelope (c13,788 sq ft) by April
2027 with occupancy by Jan 2028. 
1.3.2 The procurement 
The procurement for the Phase 2 of the project involves North Ayrshire Council procuring a
contract for the build of the industrial unit and surrounding grounds. The Council is seeking
tenders through the Public Contracts Scotland (PCS) Portal for contractors to undertake the
works Riverside Way, i3 in Irvine. The Council has an available budget of £6.775M for the
project. 
The following paragraph will be updated following the tender process:
A total of xx suppliers submitted tenders and were assessed at the pre-qualification stage by
the NAC’s Corporate Procurement Team, in terms of initial pass / fail criteria and by the
service team, following which the xx suppliers proceeded to the quality evaluation stage. At
the evaluation stage the assessment was made based on 80% cost and 20% quality.
Suppliers were assessed against a number of criterion for quality. The xx suppliers then
proceeded to the commercial envelope stage where they were scored overall and a
competent bid was identified from the highest scoring contractor. 
1.3.3 Key findings and the preferred option 
The findings from the procurement for Phase 2 of the project will relate to the quality and cost
assessment of bids related to capital expenditure. The quality and commercial assessments
will identify a preferred bidder for the works and in accordance with the tender process this
supplier should be the preferred bidder based on their combined scores.

Page 30

NAC Growth and Investment 
AGD Business Case 
24
1.4 Commercial case   
1.4.1 Agreed products and services
Goods and services are being sought as part of one fixed price contract for Phase 2 of the
Advanced Manufacturing Space project. This relates to the construction of an industrial unit,
its associated grounds and suds and roads infrastructure for the wider site. Tenderers will be
invited to submit tenders on a fixed price basis and will then be evaluated by North Ayrshire
Council. It should be noted that the tender remains open for a period of 150 days from the
tender return date (xx xxxxx 2026). The tender will expire on xx xxxx 2026. 
For the overall project commissioned services are likely to include the following:
• Quantity surveying
• Architecture 
• Geotechnical 
• Cost consultants 
• M&E
• Site investigation work
• Land based engineering works
• Industrial building construction company 
1.4.2 Agreed risk allocation and charging mechanism 
Risks that could affect the successful implementation of the project have been identified and
are set out in detail in the risk register attached as Appendix E. This includes details of risk
owners, risk evaluation and mitigation measures. A key risk at the moment is the uncertain
length of time to endorse and approve the FBC prior to the award of the contract within the
required timescale. 
The payment mechanism agreed with the service provider with respect to the planned
construction works will involve submission of invoices by the contractor at agreed stages of
the works, which will be certified for payment by NAC. 
1.4.3 Key contractual arrangements 
The Form of Contract for the project is the SBCC Design and Build Contract for use in
Scotland (DB/Scot), 2016 edition incorporating Amendment 1 February 2018. The key
contractual clauses are as follows: 
• Clause 4.18.1 Retention Percentage – 3%
• Clause 6.4.1 Contractors Insurance – injury to persons or property - £10,000,000
• Clause 6.5.1 Insurance – Liability of Employer - £10,000,000
• Clause 6.7 Insurance of the works – Option A applies (By Contractor)
• Clause 6.15 Contractors Designed Portion Professional Indemnity Insurance - £10M 
There are no personnel implications and TUPE does not apply. 
It would be inappropriate to incorporate contract clauses for occupiers of the completed units.
However, there is an opportunity to work with tenants to maximise impacts and benefits for local
people and local businesses through supply chains and local procurement mechanisms. 
1.4.4 Agreed implementation timescales 
The key milestones and delivery dates for the overall Phase 2 project are shown in detail in
the table below. A Delivery Assurance Implementation Plan (DAIP) was produced by the AGD
PMO in early 2026. The milestones vary slightly from the detail in the DAIP that has been
shared with Governments, following the finalisation of the tender and FBC and this is
illustrated below the first table.

Page 31

NAC Growth and Investment 
AGD Business Case 
25 
Table 9: Flexible Space Phase 2, Project Milestones (working version) and comparisons to DAIP
FLEXIBLE SPACE, PHASE 2: Key Milestones  Estimated
date 
Quarter  
(financial
year)
Status
Flexible Space Outline Business Case  Approved 
Phase 1, Full Business Case granted  Approved 
Planning approval granted for Phase 2 Complete 
NAC Gate 3, Project Board, Investment Decision to tender 23 Jan 26 Q4, 25/26 Complete
NAC publish Invitation to Tender (ITT) (estimate) 06 May 26 Q1, 26/27 Not started
NAC receive tenders (estimate) 01 Jul 26 Q2, 26/27 Not started
NAC tender evaluation period ends  14 Aug 26 Q2, 26/27 Not started
Government endorse Phase 2 FBC 21 Aug 26 Q2, 26/27 Not started
NAC report FBC to Cabinet 01 Sept 26 Q2, 26/27 Not started
AEPB & AEJC approve Phase 2 FBC   11 Sept 26 Q2, 26/27 Not started
NAC award Phase 2 contract, D&B contract commences  16 Sept 26 Q2, 26/27 Not started
NAC commences marketing of the building  Sept 26 Q2, 26/27 Not started
Contractor completes construction works 22 Sept 27 Q2, 27/28 Not started
Contractor handover to NAC  22 Oct 27 Q3, 27/28 Not started
NAC sets closing date for interest and selection of tenant tbc tbc Not started
Current deadline for claiming all Local Regeneration Fund 31 Mar 28 Q4, 27/28 In progress
NAC reports Outputs/Outcomes/CWB  tbc tbc Not started
NAC delivers subsequent Phases and related FBCs.   tbc tbc Not started 
FLEXIBLE SPACE PHASE 2, 
ESTIMATED TIMELINES 
Y7 (2026/27) Y8 (2027/28) Y9 (2028/29)
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Current Delivery Assurance Imp Plan
dates
FBC           
FBC approval by June 26, Q1 
Contract award/delivery phase from Jul 26, Q2, to contract completion in Jul 27, Q2.
Updated FBC milestone dates  FBC           
FBC approval during Sept 26 in Q2
Contract award/delivery phase from Sept 26, Q2, to contract completion in Sept 27, Q2. 
1.4.5 Accountancy treatment 
It is envisaged that the assets underpinning the delivery of the service will be on the balance
sheet of the organisation should the development remain in the ownership of NAC. 
1.5 Financial case 
The financial implication of this procurement is a commitment by North Ayrshire Council, to a
contract with a maximum value within the budget available for the delivery of the Phase 2 over
the course of 2026, into 2027. The capital funds comprise of the following, within the table
below including the Local Regeneration Fund (formerly Levelling Up Funding (LUF) 3). 
Table 10: Flexible Advanced Manufacturing Space, Phase 2 - Source of Capital Funds 
Source  Amount 
North Ayrshire Council AGD contribution £355,650
Scottish Government AGD contribution  £1,713,091
Local Regeneration Fund (Levelling Up Funding (LUF) 3) £4,706,259
Total  £6,775,000

Page 32

NAC Growth and Investment 
AGD Business Case 
26 
1.5.1 Financial expenditure 
The majority of the financial expenditure for this procurement will take place across financial
year 2026/27 (excluding retention) and the contract is expected to be complete by mid to late
2027. 
1.5.2 Overall affordability and balance sheet treatment
The proposed works have been the subject of a best value procurement exercise. The award
of the tender will require to be signed off by the Ayrshire Economic Joint Committee, following
endorsement from NAC’s own Cabinet. The Council has ensured there are sufficient funds in
place to cover the project and will confirm following the process if the tender cost is below the
budget available. 
The table below is a current summary of the project’s financial appraisal. Proposed investment
is in phases. NAC will be responsible for ongoing maintenance and management of the
buildings through an appointed agent, until let. Anticipated rental income for Phase 2 is
£127,400 per annum. 
The project budget includes for clawback costs from Scottish Enterprise, related to the
original sale of land and change in delineation of the defined developable area, following the
decision to focus all AGD investment at Riverside Way. 
Table 11a: Flexible Space Financial Profile – Capital Expenditure 
£'000 Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10
19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30
Phase 1 5,147 34 140 217 403 2,912 1,387 53 0 0 0 0
Phase 2 6,775 0 0 0 0 51 305 132 2,068 4,220 0 0
Phase 3 8,751 0 0 0 0 0 0 0 230 3,655 4,866 0
Total 20,673 34 140 217 403 2,963 1,692 185 2,298 7,875 4,866 0 
Table 11b: Flexible Space Financial Profile – Capital Funding 
£’000 Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10
19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30
Scottish
Government 11,000       307 2,195 1,383 0 0 2,372 2,372 2,372
NAC 4,000 34 83 122 0 51 308 53 230 2,996 2,494 (2,372)
AGD Total  15,000 34 83 122 307 2,246 1,692 53 230 5,368 4,866 0
VDLF 967   56 95 97 718         
LRF 
(Prev LUF3) 4,706             132 2,068 2,507    
Project Total  20,673 34 140 217 403 2,963 1,692 185 2,298 7,875 4,866 0 
It is anticipated that the completed project will generate income from the following: 
• Ongoing rental income through the lease of completed units; and 
• Longer term, One-off capital receipts from the sale of buildings and/or
development plots. 
A draft Risk Register is included at Appendix E. The main financial risks are expected
to be:  
• Design and technical studies result in additional costs beyond the contingencies and
optimism bias allowed for;
• Slippage / delay in the programme that incurs additional costs; 
• Unforeseen project complexities that require additional funding; 
• Insufficient availability of non-financial resources for the delivery of the project;
• Risks that the key milestones are not achieved; and 
• Risk that the project does not proceed as an AGD project.

Page 33

NAC Growth and Investment 
AGD Business Case 
27
1.6 Management case   
1.6.1 Project management arrangements
Phase 2 of the Flex Space Programme, which is the subject of this FBC, will be managed by
the Council’s PMI (Property Management and Investment) team and will follow the PRINCE2
methodology as much as possible. This was the approach taken for Phase 1. Project
Management responsibilities sit with PMI who have led on the development of the design on
behalf of the Growth and Investment Team who have acted as client. PMI will continue this
role as part of the delivery stage and will report to the Council’s internal Project Board for the
contract. Overall responsibility will rest with Executive Director, Place, reporting to the Chief
Executive. All personnel will be experienced and professionally qualified in their respective
roles. 
NAC has established internal governance arrangements for the management of its AGD
project(s) organised through a Project Board, which comprises of officers from Growth and
Investment, PMI, Legal and Finance. The NAC Project Board has overall authority and
responsibility for Project Delivery including the Business Case, prior to submission to the NAC
Executive Leadership Group for approval and prior to submission to the AGD Programme
Management Office (PMO). 
The Board has a Project Management responsibility but no decision-making powers. The
Project Board provides a mechanism for accountable project management delivered by
regular progress reporting and updates and coordination of any aspects of the project
associated with infrastructure, employability, business and innovation strands. 
1.6.2 Benefits Realisation and Risk Management 
The AGD PMO has produced a Benefits Realisation Plan for the AGD projects. The purpose
of the Plan is to demonstrate, to local, regional and national stakeholders, how the AGD will
capture the outputs, outcomes, impacts and community benefits resulting from Deal
investments including the Flexible Advanced Manufacturing Floorspace project at i3. It sets
out approaches to project monitoring and reporting, including definitions guidance and deal
programme and project evaluation. 
The NAC Project Board will be responsible for managing the risks and benefits realisation for
Phase 2 of the project and the remainder of the Flex Space Programme, through reporting to
the PMO and Government. Day to day management will be the responsibility of the Project
Lead and the Council’s PMI Team as Project Manager. 
1.6.3 Post project evaluation arrangements 
Project monitoring and evaluation will be managed through AGD governance arrangements to
monitor the projects outputs and outcomes. The project will be subject to regular review
meetings to discuss progress, programme, financial and technical matters. 
1.7 Recommendation 
It is recommended that the Full Business Case for Phase 2 of the Flexible Advanced
Manufacturing Space project at i3 in Irvine is approved. As the project includes Local
Regeneration Funding (formerly Levelling Up Fund Three), the Council intends to invest its
remaining AGD project funds in the third and final phase of the project programme that will be
subject to the submission of an updated version of the Full Business Case.

Page 34

NAC Growth and Investment 
AGD Business Case 
28
I hereby recommend the approval of the scheme as set out in this Full Business Case to
proceed to the delivery of the scheme. 
Signed:      XX 
Date:     Date / May / 2026 
Senior Responsible Owner 
Louise Kirk, Head of Economic Development, Growth & Regeneration, NAC

Page 35

NAC Growth and Investment 
AGD Business Case 
29
2. THE STRATEGIC CASE   
2.0 Introduction 
This Full Business Case is for the approval of investment in Phase 2 of the Advanced
Manufacturing Flexible Space project at i3 in Irvine. It is focussed on appointing a contractor to
construct an 18,191ft2 (1,690m2) GIFA industrial unit with yard space and supporting
infrastructure for the wider site. 
Structure and content of the document
This FBC has been prepared using the agreed standards and formats for business cases. The
approved format is the Five Case Model, which comprises the following key components: 
• strategic case section. This sets out the case for change, together with the supporting
investment objectives for the project.
• economic case section. This demonstrates that the organisation has selected the most
economically advantageous offer which best meets the existing and future needs of the
service and is likely to optimise value for money (VFM)
• commercial case section. This sets out the content of the proposed deal
• financial case section which confirms funding arrangements, affordability and the effect
on the balance sheet of the organisation
• management case section which details the plans for the successful delivery of the
scheme to cost, time and quality. 
The purpose of the strategic case is to explain and revisit how the scope of the proposed
project or scheme fits within the existing business strategies of the organisation and provides
a compelling case for change, in terms of existing and future operational needs. In this
respect, there is a growing case for the project to provide new energy efficient industrial
building stock in North Ayrshire to support the local Ayrshire economy. In addition, the project
has the potential to support the i3 DPMC Phase 2 project with complementary, supporting
advanced manufacturing space within the DPMC facility. 
The project at i3 is part of a wider strategy to modernise the Council’s commercial estate,
which has also benefited from Local Regeneration Funds from UK Government.   
To note, the Strategic Case remains the same, as set out previously within the approved
Outline Business Case of June 2021 and Full Business Case for Phase 1 of December 2022.
Key scope changes were made in relation to the scale of floorspace estimated to be delivered.
At SOC and included in the Heads of Terms, this was estimated as 150,000 square feet, at
OBC stage 97,000 square feet (approx. 9,000 square metres) was estimated and at Phase 1
FBC stage, 65,000 square feet (approx. 6,000 square metres).   
As part of the development of the Phase 1 scheme, a draft masterplan was prepared, showing
where the overall programme of space could be located at i3 and a Benefits Realisation Plan
was also prepared. Since then, the masterplan has been updated to focus flexible space
investment within a central area or cluster and around the DPMC project, as it was felt that the
original masterplan may not be achieved and the development would be fragmented with less
impact. A draft Strategic Framework was prepared to support this work.   
Ayrshire Growth Deal
The Ayrshire Growth Deal Agreement (November 2020) commits the Scottish Government
and UK Government to work collaboratively with the Ayrshire Councils and regional partners
to deliver the Ayrshire Growth Deal that will help transform the Ayrshire economy. The AGD

Page 36

NAC Growth and Investment 
AGD Business Case 
30
Agreement advises the following regarding i3 projects including the Flexible Space
programme: 
Both Governments and North Ayrshire Council, will support new developments at the i3 Irvine
Enterprise Area Advanced Manufacturing Space in Irvine, which will create a National Digital
Processing Industry Hub and advanced manufacturing flexible space.  This will serve digital
processing industries, building on current Life Science Clustering at the site, and facilitate
R&D activity, start up, spin out, and growth of Life Science businesses and other advanced
manufacturing opportunities. This will see investment of up to £11 million from the Scottish
Government, £6.225 million from the UK Government, and £5 million from North Ayrshire
Council. The National Digital Processing Industry Hub will be developed at i3 with links to the
National Manufacturing Institute Scotland in partnership with Strathclyde University and
industry. The project also includes construction of flexible business space capable of meeting
the requirements of Chemical and Life Sciences manufacturing, Digital Automation and other
advanced manufacturing opportunities. The combined offer at i3, centred round the National
Digital Processing Industry Hub, will attract a range of supply chain and digital technology
SMEs and start-ups and offer strategic capacity to secure major digital process sector
investment at i3. 
Part A: the strategic context 
2.1 Organisational overview 
North Ayrshire Council is delivering Phase 2 of the project and a final third phase and is
seeking other funding support to help deliver as much advanced manufacturing floorspace as
possible, including the Local Regeneration Fund (formerly LUF3). The Council has led on the
following areas of work to progress the project:
• Masterplanning for i3, including planning, masterplanning and conceptual development of
future i3 flexible space and DPMC;
• Targeting Vacant and Derelict Land funding allocations to help support the project; 
• Funding bids to improve the Council’s commercial space for businesses e.g. Local
Regeneration Fund (formerly LUF3); 
• Land assembly in conjunction with Scottish Enterprise to create a cluster of development
within a central area of i3;
• Project management of the design and development of Phase 1 and Phase 2 of the
project and an updated masterplan for the site, by NAC’s architects and surveyors;
• Active travel proposals to improve connections between i3 and Irvine; 
• Securing community benefits outcomes from the Growth Deal projects, aligning with the
Council’s Community Wealth Building Strategy; and  
• Working with East and South Ayrshire teams to develop a collaborative approach to
regional working in Ayrshire in relation to commercial space. 
This will work will complement the DPMC i3 project which is in partnership with University of
Strathclyde, NMIS and CPI. NAC is acting as an enabler and facilitator for the project, using
the Ayrshire Growth Deal investment as a catalyst. 
2.2 Business strategies 
The purpose of the project aligns across a breadth of local, regional, national and UK policies.
Summaries of relevant plans, policies and strategies have been outlined in the tables below.

Page 37

NAC Growth and Investment 
AGD Business Case 
31
2.2.1 Strategic policy context
The broad policy framework is summarised with additional supporting information on specific
policies. The following table provides an overview of relevant policies and strategies. 
Table 12: National Policy and Strategies
National Policy and Strategies 
Policy Objectives Relevance for i3 Project 
The UK’s Modern
Industrial
Strategy 2025
• Position the UK as a leading destination for
investment and innovation
• Increase business investment and provide stability
for long-term investment decisions
• Focus on eight High-Growth Sectors including
Advanced Manufacturing, Digital & Technologies and
Life Sciences with individual sector plans. 
• Using innovation to drive
productivity and high-quality
employment
• A focus on supporting sectors
with high-growth potential, with
Advanced Manufacturing
identified as a key sector. 
UK Life Sciences
Sector Plan 2025
• To support world-class research and development,
attract investment, grow advanced manufacturing,
and accelerate health innovation
• To position the UK as the leading life sciences
economy in Europe by 2030
• Creation of Life Sciences Innovative Manufacturing
Fund (LSIMF) to bring globally mobile manufacturing
investments to the UK
• A commitment to partnering with industry to drive
growth and innovation. 
• The project supports the Life
Sciences Sector Plan by providing
flexible business space capable of
meeting manufacturing
requirements for chemical and life
sciences
Levelling Up the
UK: Executive
Summary 
• Providing a catalyst for delivering a long-term
programme of change to unlock the potential of
people and places in every part of the UK - creating
jobs, driving productivity, improving people’s quality
of life and helping restore pride in places. 
• i3 benefiting from £4.706M
towards commercial space and
funding towards low carbon
infrastructure through the Local
Regeneration Fund (formerly
LUF3).
Scotland’s
National Strategy
for Economic
Transformation,
2022 to 2032
• Identifies five programmes to drive improvements in
Scotland’s economy over the next 10 years –
stimulating entrepreneurship, opening new markets,
increasing productivity, developing skills required for
the next decade and ensuring fairer and more equal
economic opportunities
• The project will support
improvements in the local
economy by providing modern
business space to attract inward
investment and help local
companies grow and expand.
Programme for
Government,
2024 to 2025
Serving Scotland
• 4 Key Priorities including Growing the Economy • The Flexible Space Programme
will provide a source of
employment to communities. 
National Planning
Framework 4,
2023
• Supporting business and industrial development
whilst safeguarding and enhancing the natural and
built environment. 
• The project supports the creation
of high quality, modern, energy
efficient, well-designed business
space as part of a new industrial
cluster. 
National
Innovation
Strategy, 2023-33
• Sets out a vision and road map to transform
Scotland’s economy over the next decade by placing
innovation at the heart of economic growth, societal
prosperity and wellbeing with four key priorities
including growing the economy. 
• The project will seek to supported
economic growth by providing
modern space for businesses to
expand and grow. 
Shaping
Scotland’s
Economy: Inward
Investment Plan
2020
• The Plan focuses efforts on nine areas of opportunity
where Scotland has global strengths.
• The Plan acknowledges that the Covid-19 crisis has
placed digital at the forefront of the response and
subsequent recovery steps across the private, public
and third sectors 
• Key role to grow Scotland’s manufacturing sector,
strengthen supply chain linkages and increase
productivity using advanced manufacturing
• Giving priority to investors who
can build local supply chains,
provide new skills and invest in
research.
• Nine priorities and three themes
underpin Inward Investment. 3
themes all applicable to i3 are:
Digital / High Value Manufacturing
/ Net Zero.

Page 38

NAC Growth and Investment 
AGD Business Case 
32
National Policy and Strategies 
Policy Objectives Relevance for i3 Project 
technologies such as automation, AI and digital
manufacturing techniques
A Manufacturing
Future for
Scotland, 2016
• Innovative manufacturing and utilisation of leading
edge technologies, driving competitive advantage
• Co-ordinating national innovation resources and
assets to be appropriate for manufacturing base
• Creating an environment where businesses of all
sizes, in all manufacturing sectors can innovate and
adopt new novel technologies
• Linking up with NMIS and other
centres of excellence
• Enabling collaboration between
businesses, RTOs & academia by
providing a focal point and
promoting an open innovation
ethos
Making
Scotland's Future
– A Recovery
Plan for
Manufacturing &
related
Programme, 21
• Co-ordinating national innovation resources and
assets to be appropriate for the manufacturing base
• Creating an environment where businesses of all
sizes and in all manufacturing sectors can innovate
and adopt new novel technologies
• Encouraging and supporting our manufacturing
businesses to put investment in the best available
technologies at the core of their business going
forward. 
• Work with Innovate UK to align interventions and
promote opportunities around digital for
manufacturing, driving manufacturing readiness and
stimulating innovation to uncover new sources of
revenue from manufacturing.
• Linking up with NMIS and other
centres of excellence
• Enabling collaboration between
businesses, RTOs and academia by
providing a focal point and
promoting an open innovation
ethos
• Co-ordinating national innovation
resources and assets to be
appropriate for the manufacturing
base. In particular, interaction
with both new and existing
centres of excellence will provide
an environment where innovation
and demonstration opportunities
can be developed.
Scotland’s 2018
to 2032 Climate
Change Plan,
Updated 2020
• Sets out Scotland’s Ambitions to reduce carbon
emissions and achieve net zero emissions by 2045,
set by the Climate Change Act 2019
• The project will contribute
through the provision of modern
and energy efficient commercial
space built on vacant and derelict
land at i3. 
Life and Chemical
Sciences
Manufacturing
Strategy for
Scotland
• Establishing a strong platform for manufacturing
growth through strong communication between the
Life and Chemical Sciences sectors
• Improving the translation of research into application
• Strengthening UK’s case (including supply chains) for
manufacturing businesses
• Enabling commercialisation of
research by providing a focal point
between academia and industry
• Building up service offering at i3
to attract businesses
Skills &
Investment Plan
for Scotland’s Life
and Chemical
Sciences
• Four priority areas: addressing specific skill
shortages, ensuring national coverage of skills and
training provision, increasing exposure to, and
understanding of, industry, enhancing practical
experience
• Developing Scotland’s life and
chemical sciences capability
• Encouraging engagement
between HE/FE and industry 
Life Sciences
Strategy for
Scotland 2025,
Vision
• Making Scotland the location of choice for Life
Sciences businesses, researchers, healthcare
professionals and investors while increasing Life
Sciences contribution to Scotland’s economic growth
• Four key priority areas: business environment,
innovation & commercialisation, internationalisation,
and sustainable production
• Developing Scotland’s life
sciences capability
• Linking with the Life Sciences
Innovation Centres.
Chemical
Sciences Scotland
Strategic Plan
2025
• Establishing Scotland as a world class centre of high
value manufacturing as well as delivering a skill
investment plan to provide easy access to training
and education to support the growth of the chemical
sciences sector
• The project will provide
opportunities for the sector to
locate to i3, in close proximity to
the DPMC project. 
A changing
nation: how
Scotland will
thrive in a digital
world 
• To create a strong digital economy for Scotland
which supports businesses to adapt and be successful
• Create conditions for technology businesses to grow,
thrive, create jobs and attract investment  
• Support for focus on digital
automation at i3 as part of wider
AGD project

Page 39

NAC Growth and Investment 
AGD Business Case 
33
National Policy and Strategies 
Policy Objectives Relevance for i3 Project 
Green Data
Centres and
Digital
Connectivity
Vision and Action
Plan, 2021
• attract new investors that require high-speed data
transit to locate in Scotland and take advantage of
enhanced terrestrial and international fibre
connectivity
• build on its capacity to generate energy from
renewable sources
• ensure that the full economic and social potential of
technologies, such as 5G, Internet of Things (IoT) and
Artificial Intelligence (AI), are realised across all parts
of Scotland
• improve Scottish competitiveness and internet
resilience providing direct links to other countries
and markets
• Potential for i3 to accommodate
such development and build on
opportunities arising from the
subsea cable AGD project 
Shortlist for Data
Centre Site
Selection in
Scotland, 2021
• Joint study by Scottish Futures Trust/Host in
Scotland, Crown Estate Scotland and Scottish
Enterprise, emerging from Green Data Centres and
Digital Connectivity Vision and Action Plan. Providing
an overview of potential data centre locations in
Scotland. 
• Identifies i3, Irvine as one of 10
sites in Scotland where such
development could be
accommodated 
Of specific relevance is the overall project’s relationship to the UK Industrial Strategy 2025 and
Scotland’s National Strategy for Economic Transformation, which are mapped out below. 
Table 13: Project’s Relationship to UK’s Modern Industrial Strategy 
The UK’s MODERN INDUSTRIAL STRATEGY 2025
Relationship to i3 Advanced Manufacturing Space Project 
Key Related Objectives
Prioritise
Business
Investment
Focus on
High-Growth
Sectors
Infrastructure
and Energy
Skills and
Talent
Innovation
and R&D
Net zero
Transition
Regional
Economic
Growth
Providing
certainty and
stability for
long-term
decisions.
Sectors include
Advance
Manufacturing,
Digital &
Technologies
and Life
Sciences
Reduce energy
costs and grid
connection
times
Reform skills
& employment
support
system and
increase
technology
training for
engineering,
digital and
defence
Targeted
investment
into R&D,
leveraging
private
investment
Support
decarbonisation
and a transition
to net zero
Increased
support for
regional
innovation
and creation
of high
quality
employment 
Table 14: Project’s Relationship to Scotland’s National Strategy for Economic Transformation  
SCOTLAND’S NATIONAL STRATEGY FOR ECONOMIC TRANSFORMATION 2022-2032
Relationship to i3 Advanced Manufacturing Space Project
Key Related Objectives  
Entrepreneurial
People and
Culture
New Market
Opportunities
Productive
Businesses and
Regions
Skilled Workforce A Fairer and More
Equal Society
Supporting business
start-ups and building
a culture of
innovation 
Attract inward
investment,
generating good
quality jobs from a
just transition to net
zero
Improving business
efficiency and
productivity and
supporting digital
innovation
Upskill the workforce
to meet emerging
economic needs
Promoting fair work and
increasing employment
and wage growth to
reduce poverty and
improve outcomes for
disadvantaged people
and places

Page 40

NAC Growth and Investment 
AGD Business Case 
34
2.3 Other organisational strategies 
2.3.1 AGD Programme 
The AGD programme links to Governments’ objectives of increased growth and prosperity.
Post the development of NAC’s Strategic Outline Case, NAC has been working closely with
the other Ayrshire Councils regarding the complementarity of projects and has coordinated
activity though the Ayrshire Growth Deal Leadership Group and Project Management Office
(PMO). Appendix F provides an initial analysis of inclusive growth objectives for the project.
The key themes identified as being critical to economic recovery and renewal are: 
Advanced Manufacturing   Aerospace/space Clean Growth
Community Wealth Building  Food & Drink Life Sciences
Visitor Economy  Business  Connectivity
Digital   Innovation  Skills 
The development of detailed actions and subsequent delivery of themes is framed through a
Community Wealth Building approach that seeks to harness assets, resources, community
strength and relationships within Ayrshire to deliver improved outcomes for our communities. 
2.3.2 Regional Policy Context 
The Flexible Space Advanced Manufacturing project has the potential to support two of North
Ayrshire’s economic development objectives: creating employment opportunities and
positioning the area as a leading location for business within the Glasgow city region. 
The project has the potential to deliver against the policy objectives of key strategies set out at
both the Scottish and regional levels. The Ayrshire Regional Economic Strategy was
developed in 2023 and outlines a ten-year economic vision for Ayrshire, providing regional
context for this project. The proposition is also in line with the Scottish Government’s inclusive
growth agenda, targeting regional imbalances in economic activity. The key messages from
these strategies are outlined below. 
Most recently North and East Ayrshire Councils have taken the decision to progress with the
development of a shared Economic Development Service commencing during 2026/27 which
will include the Ayrshire Growth Deal delivery teams from both Councils. 
The overall aim is to deliver greatly enhanced outcomes through: enhanced strategic
leadership, shared resources, enhanced collaborative arrangements, economies of scale,
greater access to specialist skills and expertise, enhanced capacity, and strengthened service
resilience, together with simplification, standardisation, upskilling and best practice sharing. 
Table 15: Regional & Local Policy & Strategies 
Regional and Local Policy and Strategies 
Policy Objectives Relevance for i3 Project 
Ayrshire Growth
Deal Heads of
Terms and
Agreement
• Focus on aerospace, space and life sciences, as well as
building on Ayrshire’s existing strengths in food and
drink, tourism, manufacturing and engineering
• Driving inclusive economic growth through creation of
new high-quality jobs and opportunities 
• Building Digital Capital – replacing the Digital
Infrastructure and Subsea Cable projects to provide
modern digital infrastructure across Ayrshire,
including over £4M for North Ayrshire. 
• Linking in with the digital
infrastructure agenda
• Possible links with the
sustainability agenda
• In partnership with Strathclyde
University and industry, a Digital
Hub facility will be developed at
i3 to incorporate relevant
testing/ R&D equipment and
specialist staff

Page 41

NAC Growth and Investment 
AGD Business Case 
35
Regional and Local Policy and Strategies 
Policy Objectives Relevance for i3 Project 
NAC Local
Development Plan
2 and emerging
LDP3
• Safeguards key business & industrial sites
• Identifies ways to support areas for specific new
residential development to cross fund new or
improved employment space
• i3 is identified as a strategic
business location, including
opportunities for a large single
user or major multiple
investments, as well as a high
amenity business park
NAC Council Plan
–2023-2028
• A key priority of the Council Plan is a transition to a
wellbeing economy which delivers inclusive economic
opportunities, prosperity and enhanced wellbeing for
North Ayrshire. This includes developing infrastructure
to support business growth.
• The i3 project would strongly
support these priority outcomes. 
Sustainable North
Ayrshire Strategy
2024-2027 
•  Setting out targets and priorities to achieve net zero
carbon emissions, halt biodiversity loss and be Nature
Positive by 2030 
• i3 has the potential to support the
strategy by ensuring this project
seeks to provide developments
that generate minimum carbon. 
North Ayrshire
Community
Wealth Building
Strategy 2024-
2027 
• To create an inclusive and wellbeing economy for
North Ayrshire that delivers social, economic and
environmental justice for all 
• Working in partnership with communities and
businesses, the economic levers of Anchor
Institutions are used to support and improve the
local economy and create more benefits for the area. 
• Working within localities to
facilitate place-based Community
Wealth Building activities on
procurement, employment, assets
and ownership. 
• Promote Fair Work practices and
position Ayrshire as a Fair Work
region.
LOIP – Irvine
Locality Action
Plan 2023/24 
The Irvine Locality Partnership has identified their key
priorities as:
• Supporting Skills and Work Opportunities
• Enhancing our Mental Health and Wellbeing
• Alleviating Poverty
• Championing Green Health and the Natural
Environment
• The i3 project will support the
Partnerships priority of
Supporting Skills and Work
Opportunities 
Ayrshire Regional
Economic Strategy
2023-2033
The Regional Economic Strategy for Ayrshire outlines a ten-
year economic vision for Ayrshire, identifying six priority
themes: 
• Support for enterprise
• Fair work
• Innovation
• Good health and wellbeing
• Stronger places and communities
• Enhancing natural capital
• i3 is identified within the strategy
as a site with significant growth
opportunity 
The i3 Advanced Manufacturing Space project fits with these strategies through: 
• supporting the growth of key sectors to build competitive advantage & economic
contribution;
• enabling sector growth by addressing a critical market failure in the provision of high
quality modern business sites and premises to attract and retain business activity;
• creating quality jobs and economic value (GVA), and supporting Community Wealth
Building by filtering through the rest of the economy via sector supply-chain activity;
• enhancing Scotland’s reputation as a key location for life sciences, and attracting
manufacturing activity based on embedded skills and expertise of Ayrshire’s workforce;
• making best use of existing embedded infrastructure assets and investments at i3; 
• positioning i3 as a key strategic location within the Glasgow City Region, providing
opportunities for major investment;
• providing high quality development space and opportunities, set within a highly
competitive infrastructure and quality environment;
• supporting the two overarching goals for economic development in North Ayrshire –
becoming a leading location for doing business – and creating quality, inclusive

Page 42

NAC Growth and Investment 
AGD Business Case 
36
employment opportunities (and multiplier benefits) that will help to reduce worklessness
and inequality;
• delivering economic impacts and outcomes spread across Ayrshire (and beyond) and
contributing to business and job growth targets, through direct and indirect/induced supply
chain linkages; and
• delivering a completed development that meets the LDP site designation for business and
industrial use. 
In summary, as demonstrated, there is a good strategic rationale for the i3 project. It
contributes to the aims, objectives and aspirations of the AGD, and of key Government
strategies linked to industry and achieving a low carbon, inclusive economy. The successful
marketing and letting of Phase 1 of the project (4A Riverside Way), has demonstrated demand
for the project. 
Part B: the case for change 
2.4 Investment objectives 
Investment objectives for the i3 Flexible Advanced Manufacturing Space project were set out
within the OBC and Phase 1 FBC as follows: 
Table 16: Flexible Space Investment Objectives 
Investment Objective 1 
To create flexible business space capable of meeting manufacturing requirements for
chemical and life sciences, but also for a wide range of other high value sectors.
AGD investment will overcome market failure barriers and deliver 65,000 square feet of
high-quality business by 2030. 
Investment Objective 2 
To complement planned AGD investment in a Digital Hub and related services at i3 and the
proposed new National Manufacturing Institute Scotland (NMIS) development.
AGD investment will provide a new focus for modern industry at i3 and for Ayrshire. In
particular, the proposed Digital Hub has the potential to operate as a satellite of NMIS,
focussing on specialised sectors. 
Investment Objective 3 
To create serviced industrial land capable of immediate development.
AGD investment will make best value use of a key asset by enabling prime industrial land to
be developed by 2030.   
Investment Objective 4 
To attract mobile investment both from abroad and from indigenous companies.
AGD investment will meet identified market opportunities for mobile investment and could
accommodate between 8 to 16 companies at i3 by 2030. 
Investment Objective 5 
To create opportunities for employment and inclusive growth with particular emphasis on
making connections to local communities, schools and colleges in preparation for
employment.
AGD investment will create floorspace that will accommodate 162 net jobs by 2031.
Through the wider AGD project activity, businesses will be engaged in activities that seek to

Page 43

NAC Growth and Investment 
AGD Business Case 
37
maximise opportunities for local people and local people will be engaged to ensure they
have the skills, qualifications and aspirations to take advantage of these opportunities. 
Investment Objective 5 
To create a sustainable, high quality business location capable of meeting and keeping pace
with the changing demands of high value manufacturing sectors. 
AGD Investment will remove a market constraint and create modern and flexible business
accommodation that will be attractive to occupiers long into the future. 
Since the approval of the OBC it has been identified that the project will now deliver
approximately 65,000 square feet of business space and the pilot of the Digital Process
Manufacturing Centre (DPMC) referred to in Objective 2, is now delivered and operated by
National Manufacturing Institute Scotland (NMIS), at i3, hosted by engineering company Booth
Welsh. 
2.4.1 Strategic need 
A number of studies were commissioned to inform the development of the i3 AGD projects.
These studies highlighted the key strengths of the local economy in terms of manufacturing
activity (particularly around life sciences and engineering), industrial heritage, the role of
international businesses, key infrastructure assets and proximity to Glasgow. However, it is
well recognised that the area is underperforming economically and has some serious
challenges around depopulation, productivity, economic growth rates, skills levels and lack of
fit for purpose modern business space. 
The priority for the i3 project is to build on the area’s key strengths and help to address these
longer-term challenges. Through the Growth Deal, partners are looking to support
‘transformational’ and ‘catalytic’ projects that can change perceptions and turn around the
long-term economic performance of the area. 
The advanced manufacturing space proposed will complement the DPMC and provide
modern space in a number of phases.  While separate business cases, the two are linked, as
the DPMC project is helping to raise the profile of i3 and to encourage business investment
and growth, with a focus on Industry 4.0. The proposed investments are part of a strategy for
i3 that allows: 
• The central Riverside Way area to be developed as a central area for i3, including the
proposed flexible space and DPMC pilot, with the potential for a second, permanent
DPMC Phase 2, enable through the AGD and subject to Full Business Case
development and approval;
• The large Strategic Investment Campus (SIC) which was marketed for major inward
investment as a separate development and is currently in the process of being sold. 
The previously referred to Digital Outline Business Case which considered investment
towards a subsea fibre optic cable and associated infrastructure, with opportunities for Irvine
as a potential landing point, could not progress as the commercial case was not viable. A
new programme and related business case – Building Digital Capital, is now being taken
forward with workstreams across the three Ayrshire authorities. North Ayrshire holds a
budget of £4.631M with initial focus on progressing the delivery of infrastructure, adoption,
skills and intelligence. This will include consideration of digital infrastructure that can support
development at i3. The project is currently in development. This would build on the
separately funded UK Government 5G Innovation Regions investment. 
Whilst it had been anticipated that the proposed subsea fibre optic cable would help attract

Page 44

NAC Growth and Investment 
AGD Business Case 
38
global businesses and enable the potential creation of a datacentre cluster of national
significance there has been significant interest in data centre development at i3 in relation to
the large Strategic Investment Campus. 
The Heat Map at Appendix A illustrates the strengths of relationships between the AGD
projects and the i3 project. 
2.5 Existing arrangements 
Presently there are no existing arrangements in place to support the supply of new industrial
property in North Ayrshire and Ayrshire, in order to meet the demand from local companies
and potential inward investment companies. This is due to prolonged market failure within the
area making it unviable for the private sector to deliver such development. 
Our strategic objective is to create jobs and bring economic activity to Ayrshire. In order to do
this, we need to improve the offer that we can make to investors by providing well-serviced
development sites and business space that is ready for occupation. 
2.6 Business needs 
AGD funding is required in order to meet demand for modern industrial accommodation in
the face of acute market failure. This is preventing private sector investment in speculative
industrial development across Ayrshire and most non-prime locations in Scotland. Studies
commissioned by NAC have identified the following issues that demonstrate the requirement
for investment and the creation of new modern business space as a priority for the Council.
This was set out within the project’s Outline Business Case and Phase 1 Full Business Case
and has been reaffirmed by more recent reviews by property consultant Ryden. 
• High demand for industrial space;
• Low vacancy rates for industrial space of less than 1% for Irvine, 2.4% for North
Ayrshire and 4.4% for West Central Scotland (among the lowest in the UK); 
(These figures were previously 4.5% for Irvine, 4.5% for North Ayrshire and 3.4% for West of
Scotland at Phase 1 FBC stage and 4%, 6% and 4% respectively at OBC stage)
• Insufficient rental values to support financially viable, new-build speculative
development;
• Very limited funding sources available for the public sector to intervene; 
• Constraints on indigenous companies seeking to grow and expand within North
Ayrshire; 
• Constraints on attracting inward investment through lack of modern premises; 
• Ageing building stock of existing industrial premises that is facing obsolescence; 
• Constraints due to companies being less accessible to disabled or mobility impaired
job seekers / trainees; and 
• Growing pressure through changes in legislation and customer demand, to create
better configured, more energy efficient building stock and eliminate hazardous
building materials. 
A more recent update by Ryden in February 2026 has confirmed this as an ongoing issue for
the area.

Page 45

NAC Growth and Investment 
AGD Business Case 
39 
Figure 11: Phase 1, Flex Space (4A Riverside Way, front & rear elevations 
2.6.1 Property market assessment  
Property market consultants assessed and reviewed the potential to invest in new industrial
and office property at i3 through the AGD funds for the OBC and FBC. This included
assessment of supply and demand in North Ayrshire. An updated survey was done in
February 2026 which re-confirmed this as an ongoing significant issue for the local industrial
property market with vacancy levels being even lower for Irvine and North Ayrshire, with a
slight 1% increase for West Central Scotland. However, whilst there is significant demand, the
report highlights that rental values are insufficient to support financially viable, new build
speculative industrial and office development. 
2.7 Potential business scope and key service requirements 
The project will seek to address the business needs set out in section 2.6 by providing a range
of types of industrial space across the Flexible Space Programme. The proposed units will be
as flexible as possible in their design. Phase 1 was designed with the potential to be
subdivided to a maximum of four units, to easily accommodate a rear extension and the
installation of a mezzanine level. The new tenant has recently taken occupation and has
submitted a planning application for an extension and plans to instal a mezzanine level, taking
full advantage of the flexible features of the building and its plot. 
It has already been highlighted at Phase 1 FBC stage, that the project scope has been
impacted upon by increased costs, affecting the amount of floorspace that can be delivered,
reducing from 9,000 square metres to around 6,000 square metres. Additional funds secured
from the Local Regeneration Fund (formerly LUF 3) will help maintain this revised cost in the
face of further cost increases. 
The project is seeking to attract a wide variety of occupiers, including local SMEs and inward
investors including opportunities through the location of the Digital Processing Manufacturing
Centre (DPMC) in close proximity at i3. Phase 1 has enabled the adjoining business Barony,
to extend their production line and create approximately 50 new jobs as a result of them
securing the lease for the building. 
A refreshed masterplan has been developed to show the proposed location and scale of
development within a central area of i3 with Riverside Way to the south, Long Drive to the
east, A71 to the north and industrial premises to the west. This will create a cluster area with
the proposed DPMC. Previously, it was anticipated that a small number of units could also be

Page 46

NAC Growth and Investment 
AGD Business Case 
40
located at the large Strategic Investment Campus (major inward investment site), however
given the increase in construction costs and reduction in floorspace that could be achieved, it
was decided that the focus of investment should be within a central area. 
Figure 6: Proposed Phases of Flexible Space Programme 
2.8 Main benefits criteria 
This section describes the main outcomes and benefits associated with the implementation of
the potential scope in relation to business needs. These are set out in the table below. In
addition, a Benefits Realisation Plan was prepared for the project, and a Benefits Realisation
Logic Chain is included in Appendix C. 
Table 17: Investment Objectives and Stakeholder Benefits 
Objectives Benefits for Stakeholder Groups 
1. To create flexible business space
capable of meeting manufacturing
requirements for chemical and life
sciences, but also for a wide range
of other high value sectors.
• New business units will be occupied by Ayrshire/ Scottish/ UK/
overseas businesses
• Created/safeguarded jobs will generate economic value – jobs, GVA,
turnover for Ayrshire and Scotland
• Supply chain outcomes will be created for other Ayrshire and Scottish
businesses
• Design and construction contracts will generate turnover for Ayrshire
and Scottish contractors
• Construction jobs and training outcomes will be created ,primarily for
Ayrshire people and particularly drawn from disadvantaged or Protected
Characteristic groups. 
2. Create a centre of digital
innovation which offers digital
tools, support and innovation
scaled to a national market
• University and College presence at i3 offering training and business
development opportunities.
• Cluster of R&D and spin off opportunities
• Providing employment, skills development, community wealth building

Page 47

NAC Growth and Investment 
AGD Business Case 
41
Objectives Benefits for Stakeholder Groups 
supporting a restructure of the
regional economy to deliver
advanced manufacturing. 
and supply chain growth opportunities
• Providing the private sector with opportunities for upskilling, business
transformation and increased productivity 
3. To create serviced industrial land
and capable of immediate
development.
• Development plot will be available for indigenous Ayrshire/ Scottish, UK-
owned and foreign investors
• Design and construction contracts will generate turnover and jobs for
Ayrshire and Scotland
4. To create opportunities for
employment and inclusive growth
with particular emphasis on
making connections to local
communities, schools and colleges
in preparation for employment,
particularly in areas of deprivation.
• New employment outcomes – direct and indirect through supply
chains
• Work experience and training places for school and college students
• Job market entrants and low skilled workers increasing soft and basic
skills through provision of local jobs. 
• Residents of deprived areas gaining access to opportunities 
• University presence enabling additional educational and training
opportunities 
• Delivery of enhanced public transport connection that opens up
employment opportunities
5. To attract mobile and private
sector investment both from
abroad and from indigenous
companies.
• New employment and training outcomes
• Demonstrate attractiveness of Scotland as excellent location for life
sciences manufacturing
• Increased investment confidence 
6. To create a sustainable, high
quality business location and R&D
cluster, capable of meeting and
keeping pace with the changing
demands of high value
manufacturing sectors and
complementing national initiatives
including NMIS. 
• Enhancement and maintenance of attractiveness of Ayrshire as a
location, meeting modern business needs and promoting Industry 4.0
services. 
• Large, visible and modern development that clearly shows Ayrshire is
Open for Business
• Recognised as part of a national strategy for improving digital
technology 
2.9 Main risks 
The main business and service risks associated with the potential scope for this project are
shown in the table below together with their counter measures. A number of these risks are
included as main risks in the most recent Ayrshire Growth Deal Implementation Plan, and
these have been highlighted in the Risk Ref column as (IP). The risk register is included in
Appendix E and listed in Table 18 below. 
The likely increase in costs from the indicative costs included in the approved OBC were
reported to the PMO and Scottish Government at Phase 1 FBC stage, on the basis that that
project was unlikely to deliver the amount of business space set out in the OBC. It was agreed
that Phase 1 of the project should progress to tender stage to test the construction market,
with the outcome that Phase 1 could proceed. In addition, the Council sought Levelling Up
Funding to help mitigate this issue for Phase 2. The tender opportunity for Phase 2 will be
published in May and an updated version of the FBC will report whether the tenders have
come in within the budget available which will enable Phase 2 to progress. 
The risks are based on the following assessment / scores:  
Green   0 - 3
Amber / Green   4 - 9
Amber / Red   10 - 14
Red   15 - 25

Page 48

NAC Growth and Investment 
AGD Business Case 
42
Table 18: Flexible Advanced Manufacturing Space – Project Risks, Updated  
Ref  Category Risk Description Impact Likeli-
hood
RAG Mitigating Actions
I3FL-R01
(IP)
SCOPE
Outputs &
Outcomes 
Anticipated
outputs and
outcomes are not
delivered.
3 3 9 Ensure BC addresses sensitivity of
outcomes 
Clear Evaluation & Monitoring
Framework 
Maximise outcomes through project
suppliers. 
I3FL-R02 QUALITY 
Outputs &
Outcomes 
The project fails to
achieve more
inclusive growth
and/or reduce
poverty by
increasing the
income of people
in deprived areas
or protected
characteristic
groups
3 5 15 Benefits Realisation Plan prepared to
identify targets. 
I3FL-R03 SCHEDULE
Timescales /
Programme 
Delays to overall
project programme
and key milestones
3 3 9 Prepare a detailed project
programme with considered time
allowances and review regularly.  
I3FL-R04
(IP)
SCHEDULE 
Timescales /
Procurement 
Delays to the
submission or
approval of
business cases or
the progress of
tender
procurement,
causes delays to
the award of
contracts for flex
space and the
progress or
claiming AGD
spend or the Local
Regeneration
Fund.
4 3 12 Seek early agreement on appropriate
procurement routes 
Include anticipated tender packages
within the Council’s Procurement
Wave Plan 
Spend aligned against related
funding source deadlines 
Ensure sufficient timeline allocated
to evaluation tender
Ensure response, evaluation and
governance process programme to
enable swift progress to award
I3FL-R05 Timescales /
Environment
Delays caused by
environmental
considerations
3 5 15 Protected Species/Habitat risk has
been assessed at an early stage. 
Review of site studies required at key
stages. 
Ensure seasonal work/study
requirements are accounted for in
programme.  
I3FL-R06 Timescales /
Environment 
Delays caused by
site investigation
work and findings
3 5 15 Instruct SI work at early stage of
project   
I3FL-R07 Timescales /
Regulatory 
Delays caused by
objections
2 4 8 Advance programme of local &
stakeholder engagement.  
I3FL-R08
(IP)
SCHEDULE
Timescales /
Regulatory  
Delays caused by
statutory consent
processes
3 2 6 Zoned & allocated site

Page 49

NAC Growth and Investment 
AGD Business Case 
43
Ref  Category Risk Description Impact Likeli-
hood
RAG Mitigating Actions
Pre-App discussion with NAC
Planning Assess protected
species/habitat risk at early stage
Review planning challenge/appeals
Agree programme for consents 
Advance programme of local
stakeholder engagement  
I3FL-R09
(IP)
SCHEDULE
Timescales /
Regulatory 
Delays caused by
land assembly /
lease agreement
processes.
2 2 4 Early engagement with owners. 
Ensure programme allows for third
party approvals.
Phase 3 layout has been developed
to reduce requirement for private
land.   
I3FL-R10
(IP)
SCHEDULE
Timescale /
Contractor
Delays during
project
construction
phases.
3 3 9 Regular monitoring through site
meetings and reports 
Ensure emphasis through
programme analysis and approach
included in tender documentation
and evaluation. 
I3FL-R11
(IP)
INTERNAL
RESOURCES
Timescale /
Business /
Professional
Staff resources not
sufficient to
manage projects as
they develop.
3 2 6 Risk has reduced as vacant post has
been filled, although impact has
been significant on pushing out
delivery timelines for projects.  
I3FL-R12 Regulatory  Planning/building
warrants are not
granted.
2 5 10 LDP supports development of site for
this use. Ensure local members
briefed/updated on project. 
Hold pre-app discussion with NAC
Planning Assess Protected
Species/Habitat risk 
Formally agree programme for
consents 
Advance programme of stakeholder
engagement  
I3FL-R13
(IP)
EXTERNAL
Regulatory 
Compliance with
Subsidy
regulations.
1 2 3 Regular monitoring and if required,
contact with Subsidy Unit to ensure
no specific risks arising related to
subsidy, due to nature of the project.  
I3FL-R14 Financial  Design and
technical studies
result in additional
costs beyond the
contingencies and
optimism bias
allowed for.
3 4 12 Develop and validate project briefs
and specifications for each phase
Benchmark costs. 
Ensure early infrastructure cost
tested and informed by SI work. 
Provide Optimism Bias allowances
compliant with Green Book
Provide for contingency & inflation.  
I3FL-R15 Financial  Slippage / delay in
the programme
incurs additional
costs.
3 5 15 Instruct appointed project team to
address this within Risk Register. 
Selected procurement route will
seek to ensure contract type has less
risk for client.

Page 50

NAC Growth and Investment 
AGD Business Case 
44
Ref  Category Risk Description Impact Likeli-
hood
RAG Mitigating Actions
I3FL-R16  Financial  There are
unforeseen project
complexities that
require additional
funding.
2 4 8 Provide for contingency 
Provide Green Book compliant
Optimism Bias allowances. 
Similar project has been delivered
previously.  
I3FL-R17  Financial  Rental income
lower than forecast
2 3 6 Market review and comparator
analysis to identify appropriate rent
but ultimately down to actual market
demand on completion  
I3FL-R18 Financial  Lack of budget to
support interested
tenants to fit out
shell of building
4 3 12 Identify at an early stage and with
Business Growth Team, how this can
be supported.   
I3FL-R19 Financial  Lack of budget to
support
maintenance of
buildings until
tenants take
occupancy, if
buildings are
classified and non -
operational.
2 2 4 Identify at an early stage with
Finance and Estates, how this can be
supported.   
I3FL-R20 Professional  Lack of project
management
experience.
2 3 6 Ensure experience project
management team, both in-house
and any external support. 
Budget allows for appointment of
required expertise.  
I3FL-R21 Professional  Poor change
management
procedures.
3 3 6 Clear and agreed procedures set in
place for internal change
management and for external
processes with design team and
contractor.  
I3FL-R22 Professional  Specification –
design issues on-
site
2 4 8 Adopt best practice design and
ensure flexibility for subsequent
division/ alteration of premises.  
I3FL-R23 Contractual /
Political 
Failure to deliver
community
benefits – training,
employment
3 4 12 Incorporate appropriate community
benefits into contract terms and
resource appropriately
I3FL-R24 Contractual  Issues with co-
ordination on-site -
contracts, visitors
2 4 8 Ensure main contractor has
appropriate procedures for site
management
I3FL-R25
(IP)
QUALITY 
Reputational /
Political 
The Flexible Space
Programme’s Full
Business Cases fail.
3 2 6 Development of OBC/FBC in
accordance with Green Book
Flex Space OBC approved June 21
Flex Space Ph1 FBC approved Dec 22
Review capex and opex costs 
Partner/stakeholder risk assessment 
Early market input / partner &
commercial input
Review governance arrangements.

Page 51

NAC Growth and Investment 
AGD Business Case 
45
Ref  Category Risk Description Impact Likeli-
hood
RAG Mitigating Actions
I3FL-R26
(IP)
QUALITY
Reputational 
Demand for the
Flex Space
Programme
diminishes and
there is no interest
from occupiers.
3 2 6 Flexible design to maximise potential
interest from occupiers. 
Marketing and promotion of
floorspace
Continue to establish relationships
with national sectors (incl NMIS) 
Interest in Phase 1 has confirmed
market interest and reduced risk
Review of Ph2&3 prepared by
property agents. 
I3FL-R27 Reputational  Market
expectations are
not met.
2 5 10 Scale/ quality/ design based on
identified market needs
Recent research has established
demand. 
Continue to review demand and
business needs with Partners
including SE and SDI.
Involve relevant business
engagement
partners.
I3FL-R28 Reputational  Businesses
interested in units
decide not to
progress
3 5 15 Ensure ongoing engagement with
businesses to prepare suitable Heads
of Terms. 
I3FL-R29
(IP)
EXTERNAL Project delays due
to external
economic impacts
such as COVID-19
and recovery.
4 2 8 Early analysis has identified that the
need for this project is unlikely to be
diminished and in fact may be even
greater. 
Analysis of external factors will be
monitored that area likely to impact
on the project. 
I3FL -R30
(IP)
SPEND Proposals become
unaffordable and
there are cost
overruns. 
4 3 12 Regular review of design vs budget,
value engineering and impact of
market conditions on costs
Benchmark costs
Ensure early infrastructure cost
tested /informed SI
Provide for contingency and Green
Book compliant optimism bias
allowances 
Ensure project approval processes
are in place to control budget
compliance
Pursue additional funding sources.  
I3FL-R33
(IP)
SCHEDULE 
Timescales /
Financial 
Existing and
proposed utilities
cause issues or
delays e.g. surface
water drainage
connections, sub-
station
requirements. 
3 3 9 Ensure exact locations of existing
infrastructure identified
Early engagement with SPEN,
Scottish Water, BT etc. 
Testing to be carried out and
capacity to be confirmed for water
supply

Page 52

NAC Growth and Investment 
AGD Business Case 
46 
2.10  Constraints 
There are no significant internal constraints to the delivery of the project. North Ayrshire
Council will bring together an experienced delivery team supported by internal or external
design, project management and contract skills as required. The completed units will be
owned and managed by NAC in line with existing estates management and will be marketed
via a number of appropriate sources. 
2.11 Dependencies 
Phase 2 of the project is subject to the following dependencies that will be carefully monitored
and managed throughout this phase of the project: 
• A successful tender process that produces a valid tender outcome within the project’s
cost envelope.
• FBC endorsement by Government 
• FBC Approval by Ayrshire Economic Joint Committee 
• Award of contract by NAC following Joint Committee approval
• Demand from businesses for the space and commitment to a lease 
• Input from local schools and colleges for work placements and training outcomes 
• Availability of skilled workforce to take up job opportunities 
In addition, the success of the main project is dependent on a number of factors including: 
• Input from local schools and college (s) for work placements and training outcomes;
and
• Longer term - seeking the support from a public transport provider for a new bus route
to ensure the location and the job opportunities can be accessible to and affordable for
local people, including people with disabilities.

Page 53

NAC Growth and Investment 
AGD Business Case 
47
3. THE ECONOMIC CASE   
3.1 Introduction 
In accordance with the Capital Investment Manual and requirements of HM Treasury’s Green
Book (A Guide to Investment Appraisal in the Public Sector), this section of the FBC
documents the procurement process and provides evidence to show that we have selected
the most economically advantageous offer, which best meets our service needs and optimises
value for money.  It should be noted that this process relates specifically to Phase 2 of the
Programme, which is for one 18,191ft2 (1,690m2) GIFA industrial unit. The level of information
provided regarding the procurement process has been informed by discussions with NAC’s
Corporate Procurement Unit and is in accordance with the Council’s Standing Order. The
Council’s Corporate Procurement Unit has advised that once the tender process is complete,
details of the bidders, their final costs and the evaluation scores, must be kept confidential
prior to the award of the tender, as this would be a breach of the Council’s Standing Orders.
Details of the contract award will be published on Public Contracts Scotland and North
Ayrshire Council’s contract register when the successful bidder is awarded. 
3.2 Critical success factors 
The AGD has a regional economic vision for Ayrshire that focuses on unlocking local potential
for the wider benefit of the Scottish and UK economies. 
The AGD programme links to Governments’ objectives for increased growth and prosperity.
The programme is based on the achievement of inclusive economic growth with a clear focus
on addressing the issues of relatively poor levels of innovation and productivity, and inequality
across the regional economy. 
Under the Regional Vision, assessed projects are grouped together into five programmes
which have been developed from the Prospectuses ‘Framework for Growth’ and ‘Connecting
Communities to Growth’ with the infrastructure proposals developed from ‘Connections for
Growth’ prospectus. These programmes focus on high growth, high value sectors that
Ayrshire has real opportunities in and are linked to Ayrshire’s general manufacturing strength,
distinctive coastal opportunities and to its communities. 
The AGD aim is to marry business growth opportunities to employment progression, to
developing the future workforce and to community development whereby all communities
benefit from economic growth. 
The AGD programmes reflect the strengths and opportunities of the Ayrshire economy. 
The critical success factors (CSFs) shown within the OBC for the Flexible Space Programme
were as follows in the table below:

Page 54

NAC Growth and Investment 
AGD Business Case 
48
Table 19: Critical Success Factors 
Critical Success Factors Measures to Address Critical Success Factors 
BUSINESS NEEDS:
How does the option satisfy the AGD Vision & key
themes? 
• Supporting economic growth for Ayrshire and
Scotland by attracting next generation
manufacturing businesses. 
STRATEGIC FIT:
How does the option provide a holistic fit and synergy
with other national, regional and local strategies?  
• Supporting growth of the life sciences sector 
• Delivering net additional economic outcomes 
BENEFITS OPTIMISATION:
How does the option optimise value for money? 
• Cost per job for public sector 
POTENTIAL ACHIEVABILITY: 
Is the option viable and can it be delivered? 
• Site capacity to accommodate floorspace 
MARKET CAPACITY:
Will the option meet an identified market demand,
remove a constraint and how will it affect existing
supply? 
• Level of market demand to take the completed
units / development plots 
POTENTIAL AFFORDABILITY:
Can the option be funded both the up-front capital
and future revenue? 
• Availability of AGD or other public / private
funding 
3.3 The long-listed options, Flexible Space Programme   
The longlisted, shortlisted, and preferred options set out in the OBC remain valid, and their
original rankings are unchanged. Since completion of the OBC, no material changes have
arisen that would affect the options appraisal process, the value-for-money assessment of
shortlisted options, or the selection of the preferred option. For clarity, the appraisal work
documented within the OBC has been re-stated in this FBC, while updated economic
modelling has been undertaken to assess the delivery models required to progress Phase
Two. The information presented on procurement reflects advice received from North Ayrshire
Council’s Procurement team and is fully aligned with Council policy. 
In line with Standing Orders, details relating to bidders, final costs, and evaluation scores must
remain confidential until the tender award is confirmed. Following award, details of the
successful contractor will be published on Public Contracts Scotland and the North Ayrshire
Council contract register.

Page 55

NAC Growth and Investment 
AGD Business Case 
49
Table 6: Assessment of Options for i3 Flexible Space Programme at OBC Stage – Long List 
OPTIONS 
1. LOCATION 
1.1 i3 Enterprise Area (EA)  1.2 Other North Ayrshire Site  1.3 Other Ayrshire Sites
i3 is one of two locations in
Scotland marketed by SDI for
manufacturing linked to life
sciences & related sectors. It
has key locational benefits for
investors, with existing
established businesses. 
Preferred Option 
A limited number of other North
Ayrshire sites have capacity to
accommodate new development
but are unable to offer the
locational advantages of i3,
installed infrastructure capacity
and existing business base. 
Discounted Option 
Irvine has key sector and cluster
strengths in life sciences and is
therefore an attractive
proposition for investors in
comparison to other Ayrshire
sites.   
Discounted Option 
2.1 Site Preparation Only 2.2 Flexible Space on all Sites  2.3 Flexible Space 
3
INTERVENTION 
Create prepared site
platforms at i3, ready for
immediate development. This
would offer a low-cost option
but would fail to meet the
needs of life sciences and
related manu-facturing
businesses for premises.
Discounted Option
Flexible space across the whole i3
area, including the large Strategic
Investment Campus could mean
the space would be too
dispersed, reducing its impact
and chance to create a central
cluster of activity.   
Potential Future Option
Delivering flexible space on a
phased basis linked to the
DOMC proposal, and that
addresses market need for
business space with the
opportunity to review the
specification after Phase 1. 
Preferred Option
3. SCALE
3.1 Small-Scale / Cautious 3.2 Mid-Scale Market Ready   3.3 Large-Scale / Ambitious
Developing 1 or 2 shell
buildings to test market
interest but discounted due to
value for money factors i.e.
there is clear demand for the
units proposed but developing
in smaller phases will
ultimately increase costs.
Discounted Option
Similar to Option 2.3, a
market-ready proposition that
balances forecast demand,
level of risk, cost efficiencies
and future flexibility. 
Preferred Option
Similar to Option 2.2, cost
savings could be made if
large-scale flexible space was
delivered. This could
significantly increase costs
and risks, overstep the known
level of demand and is likely
to be in advance of need.
Discounted Option
4. FUNDING SOURCES 
4.1 Seek AGD Funding  4.2 Seek Other Public Funds  4.3 Seek Private Partner
AGD funding through the
public sector allows business
space to be provided in the
face of market failure as
development is not viable for
the private sector. Consider-
ation to be given to a rolling
development programme
utilising development income. 
Preferred Option 
There are no alternative public
sector funding sources
identified to deliver this scale of
intervention. We will continue
to scan the market to identify
other funding sources and
respond accordingly.
Potential Future Option 
Attracting private investment
to develop new business space
was considered but has been
discounted due to its lack of
viability in Ayrshire. This
option will be reviewed as a
future option. 
Discounted Option 
5. TIMESCALES
5.1 Immediate 5.2 Phased Approach  5.3 Postpone
Similar to 2.2 and 3.3, there is
potential to develop the whole
of the i3 site immediately. This
would deliver cost savings to
the public sector but would also
increase risk and remove the
option to adapt the size/ layout
of proposed space on demand. 
Discounted Option 
Delivering the AGD investment
through a phased approach
minimises risk – this creates
flexible manufacturing space,
alongside the DPMC project, to
meet immediate demand and
allows further phases of flexible
space, based on take-up of Phase
1.
Preferred Option 
The project could be planned,
designed, costed, approved and
all relevant permissions secured
but construction postponed til
occupier interest is secured.
This option fails to meet the
current market need for good
quality business units that are
ready for occupation 
Discounted Option

Page 56

NAC Growth and Investment 
AGD Business Case 
50
Preferred way forward – Flexible Space Programme at OBC 
The preferred way forward at SOC and OBC stages was AGD funding (4.1) to deliver flexible
space (2.3) at i3 Enterprise Area (1.1) through a mid-scale intervention (3.2) within a phased
timescale (5.2), as follows: 
Table 20: Preferred Way Forward, Flexible Space Programme – OBC Stage
4.1  Seek AGD Funding  2.3  Flexible Space  1.1  i3 Enterprise
Area 
3.2  Mid-Scale
Market Ready 
5.2  Phased
Approach 
AGD funding through
the public sector
allows business
premises to be
provided in the face
of market failure as
development is not
viable for the private
sector. 
Consideration will be
given to a rolling
development
programme utilising
development income. 
Delivering flexible
space on a phased
basis that
complements the
DPMC proposal,
and that addresses
market need for
business space with
the opportunity to
review the
specification after
Phase 1. 
i3 is one of two
locations in
Scotland
marketed by SDI
for manufacturing
linked to life
sciences &
related sectors. It
has key locational
benefits for
investors, with
existing
established
businesses. 
Similar to
Option 2.3, a
market-ready
proposition
that balances
forecast
demand,
level of risk,
cost
efficiencies
and future
flexibility. 
Delivering the AGD
investment
through a phased
approach
minimises risk –
this creates flexible
manufacturing
space and the
Digital Hub to
meet immediate
demand and
allows further
phases of flexible
space, based on
take-up of Phase 1. 
3.4 Short-listed options, Flexible Space Programme 
The short-listed options shown within the OBC were as follows and are summarised in the
tables below for the overall i3 Flexible Space Programme. 
• Option 1 – do nothing 
• Option 2 – the preferred option – flexible space, phased
• Option 3 – ambitious option – flexible space, accelerated 
Table 7: Assessment of Options for i3 Flexible Space Programme at OBC Stage  - Short List  
Option 1
Do Nothing 
Option 2 (Preferred)
Flexible Space, Phased  
Option 3 (Ambitious)
Flexible Space, Accelerated
Delivers no additional
floorspace
Attracts 0 occupiers
Delivers 0 gross jobs
Delivers 8,830 sqm floorspace (NIA)
Attracts 8 to 16 occupiers 
Delivers 162 net jobs 
Delivers 8,830 sqm floorspace (NIA)
Attracts 8 to 16 occupiers
Delivers 162 net jobs
Investment Level 
AGD NAC & SG £0
Other Funding £0
Investment Level 
AGD NAC £4M
AGD SG £11M
Investment Level 
AGD NAC £4M 
AGD SG £11M
Delivery Timescale 
N/A
Delivery Timescale 
(21/22) to (27/28)
Delivery Timescale 
(21/22) to (24/25) 
In addition, the following table provided a review of each of the short-listed options,
considering how each performed against the Critical Success Factors for the i3 project.

Page 57

NAC Growth and Investment 
AGD Business Case 
51
Table 21: Review of Critical Success Factors for Shortlisted Options for Overall Flexible Space
Programme at OBC Stage 
1. Do Nothing  2. Preferred 3. Accelerated 
BUSINESS NEEDS:
How does the option
satisfy the AGD Vision &
key themes? 
• Delivers no additional
floorspace
• Delivers 8,830 sq
metres (NIA) of
advanced
manufacturing
floorspace that will
support economic
growth
• Delivers 8,830 sq
metres of advanced
manufacturing
floorspace in one
phase.  
STRATEGIC FIT:
How does the option
provide a holistic fit and
synergy with other
national, regional and
local strategies?  
• Attracts no business
occupiers 
• Delivers no jobs
• Attracts approx. 8 to
16 occupiers 
• Delivers 162 net jobs
(Direct & Indirect)
• Strong synergy with
national Advanced
Manufacturing and
Chemical and Life
Science Strategies.
• Attracts 8 to 16
occupiers 
• Delivers 162 net jobs
(Direct & Indirect)
• Strong synergy with
national Advanced
Manufacturing and
Chemical and Life
Science Strategies.
BENEFITS
OPTIMISATION:
How does the option
optimise value for
money? 
• There is no value for
money as the project
is not delivered. 
• The option delivers
floorspace on a phased
basis allowing time for
review and ensuring
the accommodation
meets market
requirements.
• The option delivers
all floorspace within
one phase but at risk
and with possible
financial liabilities.
POTENTIAL
ACHIEVABILITY: 
Is the option viable and
can it be delivered? 
• N/A • This development
option can be
accommodated at i3.
• This development
option can be
accommodated at
i3. 
MARKET CAPACITY:
Will the option meet an
identified market
demand, remove a
constraint and how will
it affect existing supply? 
• Market demand not
met. 
• This development
option has been
profiled against
detailed market
knowledge.
• This development
option is likely to be
in advance of
market need.
POTENTIAL
AFFORDABILITY:
Can the option be
funded both the up-front
capital and future
revenue? 
• N/A • £15m AGD funding is
required. Future
revenue costs will be
met from revenue
returns (rent and plot
sales).
• £15m AGD funding
is required. Future
revenue costs will be
met from revenue
returns (rent and
plot sales). 
It should be noted that the total floorspace stated at OBC was updated at the Phase 1 FBC,
with assumptions that due to cost increases the scale of floorspace was now likely to be
reduced and that the estimated floorspace may be in the region of 6,000m2. (para 1.1.3,
Phase 1 FBC). 
Key Findings from OBC Analysis 
The table below shows the estimated high level economic outcomes at OBC stage.

Page 58

NAC Growth and Investment 
AGD Business Case 
52
Table 22: High-level Economic Outcomes at OBC Stage 
STAGE 1 - Scotland Impacts - Standard Analysis as calculated before (traditional)
Outcome
Short Listed Options 
Option 1
Do
nothing
Option 2
Preferred
Preferred
(sensitivity check -
negative impact)
Preferred
(sensitivity check
- positive impact)
Option 3
(accelerated)
Business space created (NIA) 0 8672 sq m 8672 sq m 8672 sq m 8672 sq m
Capital  Expenditure
n/a
£15,000,000 £15,000,000 £14,000,000 £15,000,000
Net Present Cost £12,764,649 £12,764,649 £11,978,658 £13,545,157
Optimism bias 5% 5% 5% 5%  
Direct Jobs 0 111 100 111 111
Indirect Jobs 0 51 26 51 51
Total Jobs 0 162 126 162 162  
Construction jobs 0 150 150 140 150
Construction GVA £000 £0 £5,008,507 £5,008,507 £4,700,105 £5,314,757  
Direct GVA (Present Value of
Benefits) 25 year NPV £0 £54,552,693 £50,233,326  £55,882,327 £56,223,953
Indirect GVA 25 year NPV £0 £25,428,207 £13,338,450 £26,045,489 £26,184,461
Total GVA 25 year NPV £0 £79,980,900 £63,571,776 £81,927,816 £82,408,414  
Present Value of Costs to
Government n/a
£12,764,649 £12,764,649 £11,978,658 £13,545,157
NPV £41,788,044 £37,468,676 £43,903,669 £42,678,796
BCR 4.27 3.94 4.67 4.15
Rank based on BCR   1 n/a n/a 2
STAGE 2- Scotland Impacts - Spatially Adjusted Analysis to align 'traditional' results with Inclusive Growth approach
within Scottish Government's Economic Strategy
Spatial Adjustment factor
n/a
1.11 1.11 1.11 1.11
NPV £60,376,266 £55,595,800 £61,847,840 £62,225,935
BCR 4.73 4.36 5.16 4.59
STAGE 3- UK Impacts - calculate extent of UK level impacts by taking Scotland level impacts and calculating proportion
of them which remain after applying UKG guidance
Spatial Adjustment factor (d) n/a 1.22 1.22 1.22 1.22
STAGE 4- UK Impacts - A high employment area can be thought of as drawing labour from UK whereas low employment
area will draw from the local area
Steady State Direct
Employment - Jobs 0 111 100 111 111
Steady State GVA £0 £9,377,900 £8,440,110 £9,377,900 £9,377,900
GVA per head for project £0 £84,486 £84,401 £84,486 £84,486
Productivity Adjustment factor
(r)
n/a
2.03 2.03 2.03 2.03
Overall UKG Adjustment Factor
(UKAF) (g) 2.48 2.48 2.48 2.48
Scottish BCR Factor (b) 1.23 1.25 1.21 1.24
Rank based on Overall UKG
Adjustment Factor   1 n/a n/a 2 
The key appraisal assumptions made in the OBC Economic Analysis were as follows:  
• Appraisal period – 25 years
• Discount rate – 3.5%
• Spatially adjusted analysis, using Green Book techniques, to account for the local
income distribution, compared with the country as a whole
• Employment multipliers – taken from the Scottish Government’s Supply, Use and Input
-Output Tables: 1998-2021

Page 59

NAC Growth and Investment 
AGD Business Case 
53
The original short list options appraisal from the OBC resulted in the following overall findings
with the preferred option as flexible space, delivered on a phased basis.   
Table 23: OBC Investment Appraisal Ranking 
Evaluation Results  Option 1
Do Nothing 
Option 2
Preferred (Phased) 
Option 3
Ambitious (Accelerated) 
Economic Appraisal  3 1 2
Benefits Appraisal  3 1 2
Risk Appraisal  3 1 2
Overall Ranking  3 1 2 
Preferred Option – Phase 1 
The preferred and agreed option at OBC stage was a phased approach to flexible space as
shown in the table above. In considering moving forward to deliver the first phase, it was
agreed that the Council would progress an initial unit at i3 that was originally part of the first
Phase, with assistance from internal resources and making use of the Council’s AGD £4M
allocation if required. In scoping out options for delivery of Phase 1, the following options were
considered in the table below with the preferred option in bold. 
Table 24: Flexible Space, Phase 1 - Options 
Flexible Space, Phase 1 – Options 
Business as usual Do Nothing (Counterfactual) 
Preferred Option Deliver 18,180 sq ft (1,690 m2) unit with occupancy
achieved half-way through 24/25
Deliver Phase 2 instead Deliver two sets of terraced units and one modular unit
(2,504 sq m)
Preferred Option Sensitivity Check
– Negative Impact
Unit subdivided into 4 with 100% occupancy achieved in
2027/28
Sensitivity Check – Positive Impact Assumes unit fully occupied at the start of 24/25 
Flexible Space Phase 2 Options Appraisal 
Following approval from the UK and Scottish Governments of the Outline Business Case
(OBC), approved in June 2021, the i3 Flexible Space Programme is being delivered in three
phases, The first phase Full Business Case (FBC) was approved in November 2022 and
constructed in 2025-26. 
This Phase 2 FBC seeks approval for an estimated investment of £6.775M in a single 18,191
sq ft (1,690 sq m) industrial unit with related yard space and parking, and wider suds and
roads infrastructure, funded by the Local Regeneration Fund (formerly Levelling Up Fund 3)
(£4.7M) and Ayrshire Growth Deal (£2.075M). To assess the economic impact of this phase,
updated modelling has been undertaken to compare the delivery of this phase against a ‘do
nothing’ baseline scenario. 
The Glasgow City Region (GCR) Intelligence Hub’s Business Case Economic Model (BCEM)
has been utilised to assess the value for money of the Flex Space Phase 2 project. BCEM
follows the methodology outlined within the GCR’s Programme Management Toolkit –
quantifying Benefit-Cost Ratios (BCRs) using a HM Treasury Green Book approved
methodology. The modelling has assessed five options and these are shown in the table
below.

Page 60

NAC Growth and Investment 
AGD Business Case 
54
Table 25: Flexible Space Phase 2 Options 
Option  Title  Description 
1 Do Nothing. 
2 Single Unit Deliver one 1,690 sqm (18,191 sqft) GIFA unit by 30 June 2027, with
occupancy starting 01 April 2028. – total value £7.65M
3 Subdivided Unit Deliver 1,630 sqm (17,544 sq ft) GIFA of space subdivided into 4
lettable units by 30 June 2027 with 100% occupancy by 01 April
2029.projects as funded by external match-funding – total value
£7.67M
4 Terraced Units Deliver Flex Space Phase 3 earlier by 31 March 2028, which includes
two sets of terraced units totalling 1,068 sqm (11,496 sq ft) with
100% occupancy by 1 April 2029. – total value £7.02M
5 Smaller unit, LUF 3 Deliver a smaller single unit within the LUF 3 budget cost envelope
(estimated at 1,281 m2) by 30 April 2027 with full occupancy by 01
January 2028.   Total value £5.38M 
Table 26 and Table 27 below show the impacts of each option, Table 27 with the construction
impacts removed. Note cost figures inputted into the model are expressed as Present Value
terms, where a 3.5% discount Rate is used as set by the Green Book.
Table 26: Benefits-Cost Ratio Timeframe - 25 Year Appraisal 
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit Sub divided Unit Terraced Unit Small Unit + LUF
PV of Capital Costs All Geographies £0 £6,806,267 £6,817,997 £6,204,841 £4,754,090
PV of Revenue Costs All Geographies £0 £847,851 £859,795 £823,880 £632,261
PV of Total Costs All Geographies £0 £7,654,118 £7,677,791 £7,028,721 £5,386,350
Local Authority £0 39 41 39 28
Ayrshire Growth Deal £0 49 53 49 36
Scotland £0 79 84 79 58
Local Authority - £2,102,108 £2,250,353 £2,064,459 £1,561,971
Ayrshire Growth Deal - £2,669,343 £2,857,591 £2,621,535 £1,983,455
Scotland - £4,279,291 £4,581,076 £4,202,648 £3,179,726
Local Authority £0 19 19 12 15
Ayrshire Growth Deal £0 26 25 16 20
Scotland £0 34 33 22 26
Local Authority - £50,628,932 £48,878,624 £29,253,376 £40,832,926
Ayrshire Growth Deal - £67,318,248 £64,990,968 £38,896,456 £54,293,087
Scotland - £88,822,688 £85,751,972 £51,321,713 £71,636,712
Actual 0 £39,735 £38,001 £8,963 £30,329
Net Impact - £39,735 £38,001 £8,963 £30,329
Local Authority - £6.91 £6.69 £4.49 £7.90
Ayrshire Growth Deal - £9.18 £8.88 £5.96 £10.49
Scotland - £12.22 £11.84 £7.97 £13.96
Person Years of Construction
Employment
Present Value of Net Additional
Construction GVA
Benefit Cost Ratio
Full-time Equivalent Jobs
Present Value of Net Additional
Operational GVA
PV of GHG Carbon Accounting

Page 61

NAC Growth and Investment 
AGD Business Case 
55
Table 27: Benefits-Cost Ratio Timeframe - 25 Year Appraisal (Construction Impacts Removed) 
Key Findings 
The key findings for the options that have been modelled for Phase 2 are as follows: 
Option 1: Do nothing/minimum status quo
Do Nothing 
Option 2: Single Unit: 
• Creates 49 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 79 person years of employment in the Construction sector (Scotland) 
• Supports 26 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £67.318m in net additional GVA over 25 years, £2.669m when construction
impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a of £9.18:£1 Benefit-Cost Ratio (Ayrshire Growth Deal Region) 
Option 3: Sub Divided Unit: 
• Creates 53 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 84 person years of employment in the Construction sector (Scotland) 
• Supports 25 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £64.990m in net additional GVA over 25 years, £2.857m when construction
impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a of £8.88:£1 Benefit-Cost Ratio (Ayrshire Growth Deal Region) 
Option 4: Terraced Unit:
• Creates 39 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 49 person years of employment in the Construction sector (Scotland) 
• Supports 16 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £38.896m in net additional GVA over 25 years, £2.621m when construction
impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a positive rate of return through a £5.96:£1 Benefit-Cost Ratio (Ayrshire
Growth Deal Region) 
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit Sub divided Unit Terraced Unit Small Unit + LUF
PV of Total Costs All Geographies £0 £7,654,118 £7,677,791 £7,028,721 £5,386,350
Local Authority £0 £52,889,911 £51,374,336 £31,575,564 £42,551,916
Ayrshire Growth Deal £0 £70,246,516 £68,211,833 £41,856,541 £56,515,423
Scotland £0 £93,547,670 £90,916,429 £56,013,778 £75,208,127
Local Authority - £50,787,804 £49,123,984 £29,511,105 £40,989,946
Ayrshire Growth Deal - £67,577,173 £65,354,242 £39,235,006 £54,531,968
Scotland - £89,268,380 £86,335,353 £51,811,130 £72,028,400
Actual 0 £39,735 £38,001 £8,963 £30,329
Net Impact - £39,735 £38,001 £8,963 £30,329
Local Authority - £6.64 £6.40 £4.20 £7.61
Ayrshire Growth Deal - £8.83 £8.51 £5.58 £10.12
Scotland - £11.66 £11.24 £7.37 £13.37
Present Value of Net Direct GVA
Present Value of Net Additional
GVA
PV of GHG Carbon Accounting
Benefit Cost Ratio

Page 62

NAC Growth and Investment 
AGD Business Case 
56
Option 5: Small Unit funded by Local Regeneration Fund (formerly LUF3)
• Creates 36 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 58 person years of employment in the Construction sector (Scotland) 
• Supports 20 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £54.293m in net additional GVA over 25 years, £1.983m when construction
impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a positive rate of return through a £10.49: £1 Benefit-Cost Ratio
(Ayrshire Growth Deal Region) 
Economic Modelling Conclusion 
In conclusion, Option 2, the delivery of a Single Unit approach provides overall the greatest
economic benefits. 
Benefit Cost Ratio Analysis
North Ayrshire Council acknowledges that the Benefit Cost Ratio (BCR) for Option 5 the
delivery of a small unit with Local Regeneration Funds provides the best return at £10.49:£1
invested. This reflects the combination of funding e.g. AGD and Local Regeneration Funds,
and the reduced footprint generated e.g. 1,281m2 at a reduced budget of £5.38M. However,
considering the broader gains Option 2 provides a good financial investment return for the
AGD, which includes the creation of a larger footprint of 1,690m2. 
In response, the sensitivity of this preferred option was tested to establish if additional benefits
could be generated when amending variables in the delivery and operation of the project.
Through negative adaptations (e.g. full occupation delayed until 01 October 2028) the BCR for
the Single Unit dropped marginally to £9.25:£1. However, when positive changes are made
(e.g. full occupation brought forward to 01 October 2027) the BCR increased to £9.92:£1, thus
generating an uplift to £71.627m in net additional GVA over 25 years. A projected increase of
£4.309m compared to the unadjusted projection for a Single Unit. 
3.5 The procurement process 
3.5.1 The Long List Criteria 
The Phase 2 Flex Space project is being procured through the Public Contracts Scotland
portal as an open tender for a one-off contract to construct an advanced factory unit within a
total project budget value of £6.775M (including fees, construction cost estimate and other
costs). The tender is expected to be published in May 2026 with returns expected in early July
2026. The bids will be assessed on pass / fail question, following which bids will be
progressed to the quality assessment stage and then to the commercial stage. As mentioned
in paragraph 3.1, the Council’s Corporate Procurement Unit has advised that details of the
bidders, their final costs and the evaluation scores, must be kept confidential prior to the
award of the tender, as this would be a breach of the Council’s Standing Orders. Details of the
contract award will be published on Public Contracts Scotland and North Ayrshire Council’s
contract register when the tender is awarded to the successful bidder. 
3.5.2 Long list
The number of bids received will be assessed on their response to pass/fail questions and as
a result of this assessment, bids will then be assessed in terms of the quality evaluation.

Page 63

NAC Growth and Investment 
AGD Business Case 
57
3.5.3 Short list criteria
The quality evaluation stage will account for 20% of the score. Following the completion of the
quality evaluation, bidders will proceed to the commercial evaluation stage which accounts for
80% of the score. The commercial evaluation involves a review of the bids, including an
arithmetic check, rate analysis and a review of tender qualifications, with any clarifications
sought from bidders where necessary. 
3.5.4 Short list
Following the commercial evaluation bidders will be assessed and scored and ranked
according to the quality and cost assessments. A preferred bidder will be selected that is
within the available budget. 
3.6 Economic appraisal 
3.6.1 Introduction
This section provides an overview of the costs and benefits associated with the main
Advanced Manufacturing Flexible Space project generally, including the focus of this Phase 2
FBC, the delivery of construction contract for an advanced factory unit of 18,191 sq ft (1690 sq
m) and on a total site of 4.59 acres. 
3.6.2 Estimating benefits 
Methodology
The Outline Business Case (OBC) set out the benefits associated with each option for the
main Flexible Space project and the AGD PMO undertook economic modelling for the overall
project. The key findings from this analysis were presented in the OBC. As part of this Full
Business Case, economic modelling has been undertaken for Phase 2 only, the outcome of
which is contained in Appendix D. In addition, a Benefits Realisation Plan has been developed
to add to this work, which is detailed in the paragraphs below. 
Description, sources and assumptions
The benefits identified fell into the following main categories. In each case, the sources and
assumptions underlying their use is explained. 
• Quantitative – cash releasing benefits: financial benefits that the project will help
generate. These include direct benefits such as rental income and indirect benefits -
such as business rate receipts; 
• Quantitative – non-cash releasing benefits: societal benefits which can be
monetised and expressed in Gross Value Added (GVA) terms.
• Qualitative – non-cash releasing benefits: these are assessed separately in
paragraph 3.7.2 
Table 28: Main Benefits
Type Direct to Organisation(s) Indirect to Organisation(s)   To society 
Quantitative
(or quantifiable) 
• Rental income  • Business rates receipts 
• Provision of additional new
space for businesses
• Reduction in area of vacant
and derelict land 
Cash releasing  • Reduction in grounds
maintenance costs once
tenant moves in 
• Accelerated/enabled
construction activity
• Carbon efficiency savings for
tenant.
Non-cash
releasing   
• Productivity gains to existing
businesses 
Qualitative (or
non-quantifiable)  
• Improvement in appearance of
part of business park.

Page 64

NAC Growth and Investment 
AGD Business Case 
58 
The estimated benefits arising from Phase 2 of the project, in relation to this procurement
exercise, relate mostly to the potential for benefits through rental income, the provision of new
space for businesses, the appointment of contractors and enabled construction activity with
the potential to support training places, maintain jobs and support SMEs through the contract.   
The economic modelling for Phase 2 in Appendix D for the Preferred Option, would in summary
deliver the following: 
• Creates 49 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 79 person years of employment in the Construction sector (Scotland) 
• Supports 26 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £67.318m in net additional GVA over 25 years, £2.669m when construction
impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a of £9.18:£1 Benefit-Cost Ratio (Ayrshire Growth Deal Region) 
A Benefits Realisation Plan has been developed for the Ayrshire Growth Deal projects and
has identified the outcomes, outputs and impacts that could be measured for the overall
Flexible Space project. These are listed below, and it’s anticipated that Phase 2, similar to
Phase1, will provide those benefits at a smaller scale. 
Table 29: i3 Flexible Advanced Manufacturing Space - Outputs, Outcomes and Impacts, Benefits
Realisation Plan 
Ref Indicator 
Outputs 
AGD/O/1 Direct/Indirect jobs 
AGD/O/2 Construction jobs 
AGD/O/3 Safeguarded jobs 
AGD/O/4 Community Benefits 
AGD/O/5 Jobs retained 
AGD/O/6 Jobs secured 
AGD/O/7 New or upgraded roads/junctions/cycle pathways 
AGD/O/8 Journey time savings/modal shifts 
AGD/O/9 Development space unlocked 
AGD/O/10 Reduced vacant & derelict land 
AGD/O/11 Digital Infrastructure 
AGD/O/12 New Residential Energy Supply 
AGD/O/13 Visitors 
AGD/O/14 Start-Ups 
AGD/O/15 Private sector investment 
AGD/O/16 Leverage: (including LA, HE/FE, Private Sector and any other leverage 
AGD/O/17 Income Levels 
AGD/CB/O/1 Training places / Weeks 
AGD/CB/O/2 Training places / accredited qualification main-contractor 
AGD/CB/O/3 Training places / accredited qualification sub-contractor 
AGD/CB/O/4 Schools Outreach 
AGD/CB/O/5 CWB Support Places 
AGD/CB/O/6 Fair Work Accreditation 
AGD/CB/O/7 SME’s supported 
AGD/CB/O/8 Regional Supplier Spend 
AGD/CB/O/9 Work Experience 
AGD/CB/O/10 Total jobs created by NSAfC projects (Apprentices)

Page 65

NAC Growth and Investment 
AGD Business Case 
59
AGD/CB/O/11 Total jobs created by NSAfC projects (Graduates) 
AGD/CB/O/12 Total jobs created by NSAfC projects (New Entrants) 
AGD/CB/O/13 Construction Careers Information, Advice & Guidance (CCIAG) Events  
AGD/CB/O/14 Number of learners receiving an Industry certification – main contractor 
AGD/CB/O/15 Number of learners receiving an Industry certification – sub-contractor 
AGD/CB/O/16 Number of Training Plans for sub-contractors  
AGD/CB/O/17 Site visits by Colleges  
AGD/CB/O/18 Supply Chain Briefings to sub-contractors 
AGD/CB/O/19 Business Skills Supports for sub-contractors  
AGD/CB/O/20 Support for the Third Sector 
AGD/CB/O/21 Softer community benefits delivered to Ayrshire as part of the project   
Outcomes 
AGD/OT/1 Job Levels (new and maintained)  
AGD/OT/2 Development Space uptake 
AGD/OT/3 Digital usage patterns 
AGD/OT/4 Reduced (net) Fuel Poverty 
AGD/OT/5 Increase in visitor spend 
AGD/OT/6 Start-up performance/survival 
AGD/OT/7 Additional investment (including FDI) 
AGD/OT/8 Improved business productivity 
AGD/CB/OT/1 CWB participant well-being uplifts 
AGD/CB/OT/2 Fair Work implementation 
Impacts 
AGD/I/1 Net additional jobs created/ maintained 
AGD/I/2 Net additional returns on investment 
AGD/I/3 Net changes in Fuel Poverty 
AGD/I/4 Net additional user productivity 
AGD/I/5 Follow on investment 
AGD/I/6 Reduced levels of deprivation within the region  
AGD/I/7 Increased income levels 
AGD/CB/I/1 Wider uptake of Well Being/Fair work 
AGD/CB/I/2 Net uplifts in regional supplier spend  
AGD/CB/1/3 Case Studies – qualitative community impacts  
In addition, the selected preferred bidder will be asked to commit to a number of Community
Benefits. 
3.6.3 Estimating costs
In terms of Phase 2 of the Flexible Space Programme, a pre-tender estimate was undertaken
by the project that was within the available budget of for the delivery of Phase 2. 
3.6.4 Cost appraisal conclusions 
For the project to proceed, the supplier selected as a result of the cost assessment of the
bidders, will require to have a tender value which is below the overall budget for the contract
tender which is within the overall project budget of £6.775M (excluding consultancy and other
fees).   
3.7 Qualitative benefits appraisal 
The qualitative benefits associated with the Flexible Space Programme generally, were set out
within the Outline Business Case. 
3.7.1 Methodology
The appraisal of the qualitative benefits was undertaken via the following process for the OBC:
• Identifying the benefits criteria relating to each of the investment objectives

Page 66

NAC Growth and Investment 
AGD Business Case 
60
• Weighting the relative importance (in percentage terms) of each benefit criterion in
relation to each investment objective
• Scoring each of the short-listed options against the benefit criteria on a scale of 0-9
• Deriving a weighted benefit score for each option 
3.7.2 Qualitative benefits criteria
The benefits criteria were weighted as follows for each investment objective, as part of the
OBC. Specific qualitative benefits were added for Phase 1 of the Flexible Space but
maintaining the original percentages and the same has been done for Phase 2 which will also
contribute to achieving these benefits. 
Table 30: Qualitative Benefits Criteria
Objectives Qualitative Benefits, Flex Space Programme  Flex Space  Weight   
1 2 %
1. To create flexible
business space capable
of meeting
manufacturing
requirements for
chemical and life
sciences, but also for a
wide range of other high
value sectors.
• New business units will be occupied by Ayrshire/ Scottish/
UK/ overseas businesses   20
• Created/safeguarded jobs will generate economic value –
jobs, GVA, turnover for Ayrshire and Scotland  
• Supply chain outcomes will be created for other Ayrshire
and Scottish businesses  
• Design and construction contracts will generate turnover
for Ayrshire and Scottish contractors  
• Construction jobs and training outcomes will be created,
primarily for Ayrshire people and particularly drawn from
disadvantaged or Protected Characteristic groups.
 
2. Create a centre of
digital innovation which
offers digital tools,
support and innovation
scaled to a national
market supporting a
restructure of the
regional economy to
deliver advanced
manufacturing. 
• University and College presence at i3 offering training and
business development opportunities.  
20
• Cluster of R&D and spin off opportunities  
• Providing employment, skills development, community
wealth building and supply chain growth opportunities
 
• Providing the private sector with opportunities for
upskilling, business transformation and increased
productivity
 
3. To create serviced
industrial land and
capable of immediate
development.
• Development plot will be available for indigenous Ayrshire/
Scottish, UK-owned and foreign investors
  10
• Design and construction contracts will generate turnover
and jobs for Ayrshire and Scotland
 
4. To create opportunities
for employment and
inclusive growth with
particular emphasis on
making connections to
local communities,
schools and colleges in
preparation for
employment, particularly
in areas of deprivation.
• New employment outcomes – direct and indirect through
supply chains  
20
• Work experience and training places for school and
college student.
 
• Job market entrants and low skilled workers increasing
soft and basic skills through provision of local jobs. 
 
• Residents of deprived areas gaining access to
opportunities 
• University presence enabling additional educational and
training opportunities 
 
• Delivery of enhanced public transport connection that
opens up employment opportunities  
5. To attract mobile and
private sector
investment both from
abroad and from
indigenous companies.
• New employment and training outcomes   15
• Demonstrate attractiveness of Scotland as excellent location
for life sciences manufacturing
 
• Increased investment confidence  

Page 67

NAC Growth and Investment 
AGD Business Case 
61
6. To create a sustainable,
high quality business
location and R&D
cluster, capable of
meeting and keeping
pace with the changing
demands of high value
manufacturing sectors
and complementing
national initiatives
including NMIS 
• Enhancement and maintenance of attractiveness of
Ayrshire as a location, meeting modern business needs
and promoting Industry 4.0 services. 
  15
• Large, visible and modern development that clearly
shows Ayrshire is Open for Business 

• Recognised as part of a national strategy for improving
digital technology   
3.7.3 Qualitative benefits scoring
The tender assessment for the refurbishment contract will include a quality assessment of the
bids based on a 20% quality / 80% cost ratio. NAC is anticipating receiving competent
submissions in relation to this aspect and to be able to score bidders against a set of agreed
criterion. 
3.7.4 Analysis of key results
NAC’s Corporate Procurement Unit will provide a completed tender score sheet for the
bidders, providing scores related to the quality and cost aspects, identifying a preferred bidder. 
3.7.5 Carbon Emissions Impact Cost 
Initial carbon analysis has been done for the overall project and is shown in Appendix I. The
project has been categorised as Control (3, then zero) and Influence (B). Further information
is contained in section 3.12 and 3.13. 
3.8 Risk appraisal – unquantifiables 
The tender for Phase 2 poses a number of risks which are contained in the main risk register
for the project. In summary, the main risks related to this project are considered to be: 
• Failure to obtain approval for the project’s Full Business Case.
• All sources of capital and revenue funding for the project are insufficient to deliver and
operate the project. 
• Delays to the project timescales caused by issues such as protected species, statutory
consents, procurement or construction. 
• Delays to the tender award period due to the requirement for various FBC approvals
which takes the timescale beyond the acceptance period, after which the preferred
supplier may increase their costs
• The project fails to attract enough of its target audience to generate sufficient income. 
Key project mitigations included the progress of Phase 1 of the project which is now
completed and has a tenant, therefore confirming demand for new space. For Phase 2, the
market has been tested at tender stage and additional sources of funding (Local Regeneration
Fund) have been sought to address the increases in costs since the estimates were prepared
for the OBC. 
Any additional risks will be highlighted following the tender process, regarding the selection of
a preferred bidder. 
3.9 The preferred option – selected supplier   
The procurement process to select a supplier to undertake the construction of a second
industrial unit, surrounding yard and infrastructure for the wider site at Riverside Way in i3,
Irvine, will commence in April 2026. It is hoped that a preferred supplier will be selected to be

Page 68

NAC Growth and Investment 
AGD Business Case 
62
appointed, who will have submitted a competent bid and will be appointed following the FBC
approval process. 
3.10 Sensitivity analysis 
General Sensitivity analysis has been undertaken as part of the economic modelling for Phase
2 and is set out in Appendix D. This included the full occupation delayed or brought forward.
However generally, the Preferred Option for Phase 2 provided a positive result. 
3.11 The preferred option   
The preferred option for the overall Flexible Space Programme was to deliver the project on a
phased basis. For this FBC, the preferred option is to select a recommended supplier in
accordance with the future tender assessment for the construction of a second industrial unit
at i3. It is anticipated that this option will offer value for money and will be within the available
budget for the project. 
3.12 Sustainability and carbon 
Like the Phase 1 unit, Phase 2 has been designed to be a robust and sustainable building that
is capable of being easily adapted if required, through for example the creation of a platform to
facilitate space for expansion, the ability to subdivide the building into a maximum of four units
or to install a mezzanine level. This approach seeks to reduce potential additional whole life
carbon emissions that could be created through any future adaptations required to the
building. The new occupier of Phase 1 is already proposing to construct an extension and
install a mezzanine level.   
3.13 Economic / Financial 
The Whole Life Carbon Emissions impact associated with the project, including embodied
carbon from construction, has been estimated in tonnes CO2e over the economic appraisal
period of 25 years. This is shown in the tables below in terms of embodied carbon and
operational carbon. 
3.13.1 Embodied Carbon 
No embodied carbon targets were set for the building at the design stage and therefore, the
measurement of embodied carbon has been estimated based on a similar calculation to the
units being constructed at AEP and within the AEP approved OBC of <970kgCO2/m2
referenced from the RIBA 2030 Climate Challenge target. Prior to the construction stage the
contractor will require to investigate and make allowances for the usage of recycled materials
where possible. 
Table 31: Estimated Embodied Carbon, Flexible Space Phase 2
Embodied Carbon 
Unit  Area Embodied
Carbon Target 
kgCO2/m2
Estimated
Embodied
Energy (whole
Life) 
Embodied
Energy per year
(/60) ***
Phase 2 Flex
Space 
1,690 m2 969.0 1,638,579 27,310

Page 69

NAC Growth and Investment 
AGD Business Case 
63 
Figure 12: RIBA 2030 Climate Change Target Metrics 
3.13.2 Operational Carbon 
Operational energy use is not currently known, given the speculative nature of the
development. In this respect, energy demand has been estimated. 
Table 32: Estimated Operational Carbon, Flexible Space Phase 2
Operational Carbon 
No.  Building Use  Calculated Annual
Demand (kWh) 
Area (m2) Demand / m2
Phase 2,
Flexible
Space 
Light
Industrial  204,842* 1,690 m2 121.0
*Sourced from modelling input spreadsheet for preferred option 
Table 33: Estimated Whole Life Carbon, Flexible Space Phase 2 
Whole Life Carbon 
Building  Area Estimated
Energy Use
/ m2 (based
on mean
precedented
use)
Estimated
Annual
Energy
Use
UK Grid Carbon
Factor from
Carbon Trust
‘Conversion
Factors’ 2023
Update
kgCO2e /
year
Whole Life
(60 years)*
Phase 2,
Flexible
Space
1,690  121  204,490 0.20707* 42,344 2,540,640
*Sourced from AEP table

Page 70

NAC Growth and Investment 
AGD Business Case 
64
4. THE COMMERCIAL CASE 
4.1 Introduction   
The overall Advanced Manufacturing Flexible Space Programme is seeking delivery of
floorspace and related works, over a series of phases. This was identified as the preferred
option in the approved Outline Business Case. This FBC is for the second phase of the
programme which is for one 18,191 sqft (1,690m2) GIFA industrial unit. This section of the
FBC sets out the negotiated arrangements for the provision of an industrial unit and related
yard space and infrastructure, under a contract with the selected bidder. The drawings below
show the proposed layout and elevations of the unit which have received planning permission
(25/0299/PP). 
Figure13: Phase2 Unit drawings

Page 71

NAC Growth and Investment 
AGD Business Case 
65 
4.2 Required services 
The products and services under contract are as follows: 
• the design and construction of a new 18,191 ft2 (1,690m2) industrial unit suitable for
class 4,5 & 6 outlined within, The Town and Country Planning (Use Classes)
(Scotland) Order 1997, to be presented to the market with core fitted out to a Category
A level. The remaining space will be subject to subsequent fit out by future tenants. 
The proposed Flex Space Phase 2 unit includes the following specifications and will be
situated immediately adjacent to the recently completed Flex Space Phase1 unit and the
established Digital Process Manufacturing Centre (DPMC) which has been operational since
February 2025. The unit will incorporate sustainable and low carbon components and offers
an impressive specification including secure yardage; dedicated parking including EV
charging; Low energy LED lighting; office heating via air source heat pump; roof mounted PV
panels and FTTP fibre connection. Modifications or complete bespoke solutions have been
considered for the unit, to be easily subdivided into a maximum of 4 no. separately lettable
units and expansion of the unit is possible by a minimum of 50% to the north of the industrial
unit. The quantity of office and ancillary accommodation will generally be around 10% of the
total floor area. Further details are set out within the table below: 
Table 1: Phase 2 Flex Space Specification 
ITEM  PROVISION 
GENERAL  • Unit specification suitable for immediate occupation
• GIFA 18,191 ft2 (1690m2)
• Site Area 74,023ft2 (6877m2)
• Steel portal frame
• Profiled and microrib cladding panels to Building Standards Class 1
Storage/Factory Use
• Cat A office fit out
• Fully serviced with water and electricity (metered)
• BT Openreach FTTP fibre connection

Page 72

NAC Growth and Investment 
AGD Business Case 
66
• Storage areas for waste collection and provision of infrastructure to
facilitate future installation of sprinkler system tank provided 
POWER • 100kVA 3-phase supply to each unit
• additional ducts to each sub-divided unit will be installed to allow future
Tenants to apply for individual LV connections based upon their anticipated
design load requirements.
• all apparatus and wiring connected to the low voltage systems shall be
suitable for use with a 3 Phase, 4 Wire, 400 Volt or 230 Volt, Single Phase,
50 Hertz earthed neutral system.
WAREHOUSE/
FACTORY
• 8m haunch height (9.28m to ridge)
• Concrete floors with 50kN/m2 floor loading
• 10% roof lights
• Powered 4.4m (H) x 4.76m (W) level loading doors
• High bay LED lighting (330 lux)
OFFICE & 
CONVENIENCE
• Suspended ceilings with recessed LED lighting
• Kitchen
• Unisex and accessible WCs
EXTERNAL • Secure 31.5m deep concrete service yard with gates will be formed to the
rear of the property accessed from a road constructed to adoptable
standards and suitable for RCC (Roads Construction Consent)
• Dedicated car parking to NRDG Standards
• Covered Bicycle storage to NRDG Standards
SUSTAINABILITY  • EPC rating "B"
• EV charging points
• Water saving sanitaryware
• Low energy PIR controlled LED lighting
• Air source heat pump for office heating and cooling
• Roof mounted solar PV installed with scope to increase this as required.
SECURITY  • gated access,
• intruder alarm 
• internal & external security lighting
• 2.4m high open mesh steel panel Security Fencing to the boundary 
VEHICLE
PARKING
• 35 spaces for General Industrial (Class 5) use in accordance with minimum
NRDG Standards
DISABLED
PARKING 
• 4 spaces 
EV PARKING
PROVISION 
• 4 active spaces / 8 passive spaces 
CYCLE PARKING
PROVISION 
• 12 spaces or 6 cycle stands 
The Council’s Property Management and Investment (PMI) Team have led on developing the
design of the unit. This has involved mainly architecture and quantity surveying services and
they also procured the following external services: 
• Geotechnical 
• Cost consultants 
• M&E
• Site investigation work
• Land based engineering works
• Ecologists 
• Transport specialists

Page 73

NAC Growth and Investment 
AGD Business Case 
67
4.3 Potential for risk transfer 
Risks that could affect the successful implementation of the project have been identified and
are set out in detail in the Risk Register attached as Appendix E. This includes details of risk
owners, risk evaluation and mitigation measures. In terms of this FBC, the general principle of
‘risk passed to the party best able to manage them’ subject to value for money, has been
applied. For this project it is anticipated that the associated risks may be apportioned between
the Council, design team, contractor and occupier. This is shown in the table below, where we
have agreed that we will apportion service risks in the design build and operational phases as
follows: 
Table 34: FBC Flex Space Phase 2, Risk Transfer Analysis 
Risk Category  Potential Allocation  Comments 
Public  Private Shared 
1. Design Risk     Depends on contract type and
conditions. 
2. Construction &
Development Risk     Depends on contract type and
conditions.
3. Transition &
Implementation Risk     Both parties will establish and agree
change management procedures if
not dictated by contract type. 
4. Availability &
Performance Risk     Performance of design team and
contractor will be monitored by NAC. 
5. Operating Risk     NAC will manage the completed units. 
6. Variability of Revenue
Risks     Rental income profiled at market rate
but NAC will retain risk of variance. 
7. Termination Risks     NAC will hold risk if contractor or
tenant terminates their agreements. 
8. Technology &
Obsolescence Risks     NAC and occupier carry risks relating
to obsolescence of property and
equipment. 
9. Control Risks     NAC holds overall control for the
delivery and ongoing management of
the project. 
10. Residual Value Risks     The completed floorspace will hold a
residual value for which NAC is
responsible for maintaining the value. 
11. Financing Risks     Limited – major costs relate to up-front
capital construction and potentially
empty rates obligation. Tenants will be
responsible for property maintenance.
Issues related to Local Regeneration
Fund (LUF3) grant criteria.   
12. Legislative Risks     N/A. Likely only to apply to initial
planning and building warrant – risks
will be off-set by securing permissions
in advance of construction. 
13. Other Project Risks     Cost inflation. Supply of materials. 
4.4 Agreed charging mechanism 
The payment mechanism agreed with the service provider with respect to the construction of
the industrial unit will involve submission of invoices by the contractor at agreed stages of the
works, which will be certified by the consultant’s team to NAC for payment. In addition, this

Page 74

NAC Growth and Investment 
AGD Business Case 
68
phase will generate ongoing rental income from the lease of the completed unit with rent
charged at appropriate rates in line with market conditions. A valuation prepared in December
2024 for the project suggested a market rent of £7.00 per sq ft. Based on a total development
Gross Internal Area (GIA) of 18,200 sq ft, this would be a total rent of £127,400 per annum.
The valuation is based on the unit, extending to a total of 18,191 sq ft (1,690 sq m) consisting
of an industrial processing packaging/ laboratory/ warehouse area of approximately 16,361 sq
ft (1,520 sq m) and provision for office, reception and meeting areas of approximately 1,830 sq
ft (170 sq m), suitable for Class 4, 5 & 6 uses is to be situated on 16,355 sq m of vacant land. 
It's anticipated that NAC will not consider selling buildings initially, to ensure NAC benefits
from income generated. NAC will also be responsible for any Non-Domestic Rates charges
accruing against any vacant units following handover from the contractor.   
For the Local Regeneration Fund (Levelling Up 3 funding) its anticipated that the Council would
pay the invoices and claim the funds from the UK Government. 
4.5 Agreed contract length 
Building contracts are envisaged to endure for a period of construction only. Occupier
contracts are envisaged to be leases to occupiers on terms that are appropriate to secure the
investment i.e. at the maximum term that the occupier will accept. This is expected to enhance
financial and economic returns to the public sector and provide a return on capital investment. 
4.6 Key contractual clauses 
The Form of Contract for the project is the SBCC Design and Build Contract for use in
Scotland (DB/Scot), 2016 edition incorporating Amendment 1 February 2018. The key
contractual clauses are as follows: 
• Clause 4.18.1 Retention Percentage – 3%
• Clause 6.4.1 Contractors Insurance – injury to persons or property - £10,000,000
• Clause 6.5.1 Insurance – Liability of Employer - £10,000,000
• Clause 6.7 Insurance of the works – Option A applies (By Contractor)
• Clause 6.15 Contractors Designed Portion Professional Indemnity Insurance - £10M 
In addition, the preferred supplier has stated that they will deliver a number of community
benefits. 
It would be inappropriate to incorporate contract clauses for occupiers of the completed units.
However, there is an opportunity to work with tenants to maximise impacts and benefits for
local people and local businesses through supply chains and local procurement mechanisms. 
4.7 Personnel implications (including TUPE) 
It is anticipated that the TUPE – Transfer of Undertakings (Protection of Employment)
Regulations 1981, will not apply to any aspect of this project. 
4.8 Procurement route and implementation timescales 
The procurement of this Phase was through a tender advertised on Public Contracts Scotland. 
The implementation milestones for the scheme are to be discussed with the selected service
provider. The dates shown below are critical in terms of how quickly the FBC can be endorsed
and approved, in order to award the contract before the tender acceptance period expires, to

Page 75

NAC Growth and Investment 
AGD Business Case 
69
enable the works to commence. Indicative Project Milestones are shown at 6.3.3, including
information regarding Levelling Up Fund 3 (LUF2) which is partly funding this project. 
Table 35: Key timescales for progress of Phase 2 Unit 
Stage  Estimated Date 
Full Business Case submitted to AGD PMO 10 April 2026
Tender published  06 May 2026
Tender returns 01 July 2026
Tender evaluation ends 31 July 2026
Final feedback / endorsement from Govt on FBC  21 Aug 2026
Cabinet endorse FBC  01 Sept 2026
AEPB & AEJC approval (special meeting to be set) 11 Sept 2026
Contract award 16 Sept 2026
Contract completion  22 Sept 2027
Deadline for drawing down Local Regeneration Funds  31 March 2028 
4.9 FRS 5 accountancy treatment 
It is envisaged that the assets underpinning the delivery of the service will be on the balance
sheet of the organisation should the development remain in the ownership of NAC.

Page 76

NAC Growth and Investment 
AGD Business Case 
70
5.0 THE FINANCIAL CASE 
5.1 Introduction 
The purpose of this section is to set out firm financial implications of this contracted solution.
At FBC stage for Phase 1, it was noted that there had been changes to the financial
implications, following on from the approval of the Outline Business Case in June 2021.
Adjustments were made to the estimated overall level of floorspace that the Programme was
anticipated to achieve, from 9,000 square metres (97,000 sq ft) to just over 6,000 square
metres (65,000 sq ft). The difference in floorspace estimated was due to a combination of the
OBC costs being early indicative estimates, prepared prior to the development of QS cost
reports for the project, and significant construction cost increases. 
The overall cost of Phase 1, now delivered, is £5.147M, which delivered 1,690m2 of flexible
floorspace. This included support of £0.967M from the Scottish Government’s Vacant and
Derelict Land Fund for the Phase 1 plot and early development work for the overall Flexible
Space Programme. The unit is now let (from mid-March 2026) and will begin to generate
rental income for the Council from June 2026.   
The estimated cost of Phase 2 is £6.775M, including consultants fees, construction estimate
and other costs. This includes not only a unit of a similar size to Phase 1 and related yard
space but also a level of fit out to enable tenants to occupy the unit immediately and suds and
roads infrastructure for Phase 2 and the wider site, to enable future phases. The overall area
for the Phase 2 unit and yard space is 7,322m2. The wider area of the site included in Phase
2 is 18,568m2 (4.59 acres) which is 39% of the area of the Phase 2 site. The projected spend
profile for Phase 2 is shown below, including estimated revenue costs for the Council, prior to
the unit being occupied.   
It’s anticipated that revenue costs will include the following costs listed below until the unit is
occupied. However, these costs will eventually be offset by the additional rental income to the
Council. 
• Maintenance, repair and management
• Rates & utility bills
• Marketing and promotion
• Legal fees
• Building insurance
• Statutory compliance certificates and any associated works
• EPC costs 
Table 36: Flexible Space Phase 2, Project Spend Profile 
Construction
Spend 
Total
Spend
Year 4 Year 5
24/25
Year 6
25/26
Year 7
26/27
Year 8
27/28
Capital spend  £6.775M £0.051m £0.305M £0.132M £2.068M £4.220M
Revenue
spend 
£0.0675M  £0 £0 £0 £0.0675M
Total  £6.8425M £0.051M £0.305M £0.132M £2.068M £4.2875M 
To mitigate the risk of increased costs and the volatility of the construction market, Phase 2 is
being supported with £4.706M of funding leveraged from the Local Regeneration Fund (see
5.3 below).

Page 77

NAC Growth and Investment 
AGD Business Case 
71 
5.2 Impact on the organisation’s income and expenditure account 
The anticipated payment stream for the project over its intended life span is set out in the
following table which shows the overall Flexible Space Programme.   
The payment stream in relation to Phase 2 is also shown in the Table below. It is anticipated
that the tender for the works will come back within the budget available, enabling the works to
progress. 
It should be noted that increased project costs have been mitigated for Phase 2 through the
UK Government’s Local Regeneration Fund, to support this particular phase. 
Table 11a: Flexible Space Financial Profile – Capital Expenditure 
£'000 Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10
19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30
Phase 1 5,147 34 140 217 403 2,912 1,387 53 0 0 0 0
Phase 2 6,775 0 0 0 0 51 305 132 2,068 4,220 0 0
Phase 3 8,751 0 0 0 0 0 0 0 230 3,655 4,866 0
Total 20,673 34 140 217 403 2,963 1,692 185 2,298 7,875 4,866 0 
Table 11b: Flexible Space Financial Profile – Capital Funding 
£’000 Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10
19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30
Scottish
Government 11,000       307 2,195 1,38 0 0 2,372 2,372 2,372
NAC 4,000 34 83 122 0 51 308 53 230 2,996 2,494 (2,372)
AGD Total  15,000 34 83 122 307 2,246 1,692 53 230 5,368 4,866 0
VDLF 967   56 95 97 718         
LRF 
(Prev LUF3) 4,706             132 2,068 2,507    
Project Total  20,673 34 140 217 403 2,963 1,692 185 2,298 7,875 4,866 0 
5.3 Local Regeneration Fund (formerly Levelling Up Fund, 3)   
Phase 2 of the project benefits from an award of £4.706M as part of the UK Government’s
Local Regeneration Fund (formerly LUF 3). The approved Phase 1 FBC had advised of an
application for Levelling Up Funding being considered by the UK Government which, if
successful, could have contributed to Phase 1, however this fund was postponed. As a result,
Phase 2 is now benefitting from the fund, providing crucial leverage for the flexible space
programme, helping to address budget challenges and replacing the majority (69%) of the
AGD funding for Phase 2.  This is part of an overall £17.5M allocation to North Ayrshire,
aiming to address market failure, through the delivery of new energy efficient commercial
property alongside the provision of low carbon infrastructure at key employment sites including
i3. 
5.4 Impact on the balance sheet 
An updated version of this FBC will advise on the outcome of the tender process and whether
the tender costs of the preferred bidder are affordable to deliver Phase 2 and are within the
capital expenditure available within the budget.

Page 78

NAC Growth and Investment 
AGD Business Case 
72
5.5 Overall affordability 
The capital cost of the overall project is £15M from the AGD. Early spend has been supported
by the Vacant and Derelict Land Fund, prior to any draw down of AGD spend. It should be
noted that the capital costs for Phase 2 have not factored in any additional cost for private
sector tenants to fit out a completed unit for their specific purposes but a level of fit out is
being provided to enable immediate occupancy. 
It is anticipated that a tender can be received for Phase 2 which is competent, affordable and
within the available budget. 
NAC will be responsible for ongoing maintenance, marketing and management of the
buildings and any surrounding curtilage, until they are let, and will cover any related costs.
This will be offset by income generated from the completed project from the following: 
• Ongoing rental income through the lease of completed units; and 
• One-off capital receipts from the sale of buildings and/or development plots. 
The approved OBC had estimated overall rental income for the Programme to be in the
region of £400,000 by 2032. However, this is figure is likely to be significantly higher, based
on the known rental income due to be received for the Phase 1 unit from June 2026 onwards,
which will be higher than the rental valuation provided by Colliers of £127,500. In addition, a
valuation for the Phase 2 unit by Ryden in December 2024 estimates rental income of
£127,400 per annum for Phase 2. 
ASSURANCE STATEMENT
This is to confirm that the financial profile for the project outlined in Section 5.2 above reflects the
position of North Ayrshire Council as at the date stated below.
Name of Council’s S95 Officer in block capitals:  MARK BOYD 
Signed: 
Date:  xx May 2026

Page 79

NAC Growth and Investment 
AGD Business Case 
73
6.0 THE MANAGEMENT CASE 
6.1 Introduction 
This section of the FBC addresses how the scheme will be delivered successfully. 
6.2 Programme management arrangements 
The three Ayrshire Councils (East, North and South) have agreed to implement a new
governance structure to oversee the delivery of the Ayrshire Growth Deal and to promote the
main drivers for the Regional Economic Partnership, namely: 
• to promote and deliver regional economic and inclusive growth on an Ayrshire-wide basis,
in line with the Scottish Government’s aim of having a Regional Economic Partnership for
every region of Scotland;
• to provide the robust shared governance which will enable the Scottish and UK
Governments and other funding sources to dispense monies on an Ayrshire basis; 
• To encourage the meaningful involvement of private sector partners as well as the public
sector;
• The structure should be as simple as possible, but be capable of adaptation as required;
and
• To recognise that the funding element is being delivered through Councils, and
consequently democratic accountability will be required for key investment decision. 
The governance for the AGD programme includes the following: 
• The Ayrshire Economic Joint Committee (AEJC) – comprising Elected Members,
representatives from Scottish Enterprise, Skills Development Scotland, business and
education.
• The Ayrshire Regional Economic Partnership Board (AEPB) – comprising Elected
Members, representatives from public sector partners including SE, SDS, HIE,
VisitScotland, HE, FE, the third sector and the business community. 
These committees have oversight of the AGD both at a programme level and in terms of
approval of detailed business cases for individual projects, as well as continued monitoring
and evaluation of the AGD programme post Deal document sign off. Please see Figure 14
below, showing the standard AGD Governance approach. 
The projects also have internal Gateway Review Boards to monitor and review progress and
reach agreement on key aspects of the project. 
It is anticipated that over time the 3 Councils will develop more regional responses to the
needs of our businesses and communities to complement the AGD investment. This is
currently being developed through an agreed proposal between NAC and EAC for an
Economic Development service that includes AGD delivery teams from both Councils.   
The i3 Flexible Space programme including Phase 2, is an integral part of the Ayrshire Growth
Deal Programme of Economic Infrastructure. The Programme will be managed by North
Ayrshire Council in conjunction with the AGD PMO and related Governance structure.

Page 80

NAC Growth and Investment 
AGD Business Case 
74
Figure 14: Standard AGD Governance approach 
6.3 Project management arrangements 
Phase 2 of the Flex Space Programme, which is the subject of this FBC, will be managed by
the Council’s PMI team and will follow the PRINCE2 methodology as much as possible. 
6.3.1 Project reporting structure 
NAC has established internal governance arrangements for the management of its AGD
project(s) organised through a Project Board. The NAC Project Board has overall authority
and responsibility for project delivery including the Business Case, prior to submission to the
NAC Executive Leadership Group for approval and prior to submission to the Programme
Management Office (PMO). 
The Board has a project management responsibility but no decision-making powers. The
Project Board provides a mechanism for accountable project management delivered by
regular progress reporting and updates and coordination of all design teams and initiatives
associated with infrastructure, employability, business and innovation strands. 
The Project Board will co-ordinate the overall delivery of the Phase 2 Flexible Space project.
Project Management responsibilities for Phase 2 sit with the Council’s Property Management
and Investment (PMI) Team who have led on the development of the design on behalf of the
Growth and Investment Team who have acted as client. PMI will continue this role as part of
the delivery stage. Overall responsibility will rest with Director of Growth and Investment
reporting to the Chief Executive. All personnel will be experienced and professionally qualified
in their respective roles. The project will be managed in accordance with NAC project
management procedures. The Senior Responsible Officer for the project in NAC is the Senior
Manager, Growth and Investment, with support from a Growth and Investment Manager as
project lead. A full multi-disciplinary team will advance the project to completion. Regular
monthly updates will also be provided to the PMO and to Governments in accordance with the
required reporting for all Ayrshire Growth Deal projects as defined by the AGD Governance
document.

Page 81

NAC Growth and Investment 
AGD Business Case 
75
As a large percentage of the project is funded by the Local Regeneration Fund, the project is
also subject to providing quarterly progress and programme updates to Government through
an online portal reporting system.   
Figure 15: Organisational chart, showing governance of the project 
6.3.2 Project Roles and Responsibilities 
Phase 2 of the Flex Space Programme is being managed by the Council’s PMI team. For the
purposes of the Ayrshire Growth Deal processes, the SRO is Louise Kirk, Head of Service,
Economic Development, Growth and Regeneration, North Ayrshire Council and Project Lead
is Marnie Ritchie, Regeneration Manager, North Ayrshire Council. The overall Project Team
includes the Council’s Growth and Investment, PMI and Finance teams. The appointed
contractor’s role will be for the completion of the design and build of the Phase 2 unit. The
table below sets out roles and responsibilities for Phase 2 of the project which is the focus of
this FBC: 
Table 37: Roles & Responsibilities 
Senior Responsible Officer  Louise Kirk, Head of Service, Economic Development,
Growth and Regeneration, NAC 
Chief Financial Officer Mark Boyd, Head of Finance, NAC 
Project Manager Alan Martin, Team Leader, PMI, NAC 
Senior Manager Bruce McClure, Snr Manager, Growth & Investment, NAC 
Project Lead (client)  Marnie Ritchie, Manager, Growth & Investment 
Specialist advisors  See para 6.4
Project Contractor Preferred supplier 
6.3.3 Project Plan 
The Project Plan is set out in the table below with a status update for each milestone.
Additional milestones have been added for Phase 2, in particular to reflect the current
approval processes for the FBC and Gateway milestones. A project plan will also be required
from bidders for the construction tender to demonstrate how they can meet the required
timelines. A Delivery Assurance Implementation Plan (DAIP) was produced by the AGD PMO
in early 2026. The milestones vary slightly from the detail in the DAIP that has been shared
with Governments, following the finalisation of the tender and FBC and this is illustrated below
the first table.

Page 82

NAC Growth and Investment 
AGD Business Case 
76
Table 9: Flexible Space Phase 2, Project Milestones (working version) and comparisons to DAIP
FLEXIBLE SPACE, PHASE 2: Key Milestones  Estimated
date 
Quarter  
(financial
year)
Status
Flexible Space Outline Business Case  Approved 
Phase 1, Full Business Case granted  Approved 
Planning approval granted for Phase 2 Complete 
NAC Gate 3, Project Board, Investment Decision to tender 23 Jan 26 Q4, 25/26 Complete
NAC publish Invitation to Tender (ITT) (estimate) 06 May 26 Q1, 26/27 Not started
NAC receive tenders (estimate) 01 Jul 26 Q2, 26/27 Not started
NAC tender evaluation period ends  14 Aug 26 Q2, 26/27 Not started
Government endorse Phase 2 FBC 21 Aug 26 Q2, 26/27 Not started
NAC report FBC to Cabinet 01 Sept 26 Q2, 26/27 Not started
AEPB & AEJC approve Phase 2 FBC   11 Sept 26 Q2, 26/27 Not started
NAC award Phase 2 contract, D&B contract commences  16 Sept 26 Q2, 26/27 Not started
NAC commences marketing of the building  Sept 26 Q2, 26/27 Not started
Contractor completes construction works 22 Sept 27 Q2, 27/28 Not started
Contractor handover to NAC  22 Oct 27 Q3, 27/28 Not started
NAC sets closing date for interest and selection of tenant tbc tbc Not started
Current deadline for claiming all Local Regeneration Fund 31 Mar 28 Q4, 27/28 In progress
NAC reports Outputs/Outcomes/CWB  tbc tbc Not started
NAC delivers subsequent Phases and related FBCs.   tbc tbc Not started 
FLEXIBLE SPACE PHASE 2, 
ESTIMATED TIMELINES 
Y7 (2026/27) Y8 (2027/28) Y9 (2028/29)
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Current Delivery Assurance Imp Plan
dates
FBC           
FBC approval by June 26, Q1 
Contract award/delivery phase from Jul 26, Q2, to contract completion in Jul 27, Q2.
Updated FBC milestone dates  FBC           
FBC approval during Sept 26 in Q2
Contract award/delivery phase from Sept 26, Q2, to contract completion in Sept 27, Q2. 
6.4 Use of Special Advisers 
Special advisers are being used for Phase 2 of the project as follows: 
Table 38: Special Advisers 
Specialist Area Adviser  Detail 
Financial  N/A 
Technical Clancy  Structural Engineers & Civils consultants 
Hulley & Kirkwood Mechanical & Electrical Engineering
Consultants
NAC Property
Management &
Investment (PMI) Team
Architect, Quantity Surveyor, Project
Management Services
Applied Ecology  Ecologists, ongoing input
Colliers  Land & proposed building valuation 
Stantec  Local Transport Strategy 
Procurement &
Legal 
N/A 
Business Assurance  Ryden  Property consultants
Other N/A

Page 83

NAC Growth and Investment 
AGD Business Case 
77 
6.5 Arrangements for change management 
The change control process will be managed by NAC. Arrangements for change management
are set out within the Ayrshire Growth Deal Governance Document (v16) and are summarised
in the flow chart in Appendix J. 
6.6 Arrangements for benefits realisation   
A Benefits Realisation Logic Chain is shown in Appendix C. In addition, a Benefits Realisation
Plan for the Ayrshire Growth has been prepared and has identified the outcomes, outputs and
impacts that could be measured for this project as set out below. This will also ensure
alignment of information across the AGD documentation of the Implementation Plan and
Benefits Realisation Plan.   
Table: i3 Flexible Advanced Manufacturing Space - Outputs, Outcomes and Impacts, Benefits
Realisation Plan 
Ref Indicator 
Outputs 
AGD/O/1 Direct/Indirect jobs 
AGD/O/2 Construction jobs 
AGD/O/3 Safeguarded jobs 
AGD/O/4 Community Benefits 
AGD/O/5 Jobs retained 
AGD/O/6 Jobs secured 
AGD/O/7 New or upgraded roads/junctions/cycle pathways 
AGD/O/8 Journey time savings/modal shifts 
AGD/O/9 Development space unlocked 
AGD/O/10 Reduced vacant & derelict land 
AGD/O/11 Digital Infrastructure 
AGD/O/12 New Residential Energy Supply 
AGD/O/13 Visitors 
AGD/O/14 Start-Ups 
AGD/O/15 Private sector investment 
AGD/O/16 Leverage: (including LA, HE/FE, Private Sector and any other leverage 
AGD/O/17 Income Levels 
AGD/CB/O/1 Training places / Weeks 
AGD/CB/O/2 Training places / accredited qualification main-contractor 
AGD/CB/O/3 Training places / accredited qualification sub-contractor 
AGD/CB/O/4 Schools Outreach 
AGD/CB/O/5 CWB Support Places 
AGD/CB/O/6 Fair Work Accreditation 
AGD/CB/O/7 SME’s supported 
AGD/CB/O/8 Regional Supplier Spend 
AGD/CB/O/9 Work Experience 
AGD/CB/O/10 Total jobs created by NSAfC projects (Apprentices) 
AGD/CB/O/11 Total jobs created by NSAfC projects (Graduates) 
AGD/CB/O/12 Total jobs created by NSAfC projects (New Entrants) 
AGD/CB/O/13 Construction Careers Information, Advice & Guidance (CCIAG) Events  
AGD/CB/O/14 Number of learners receiving an Industry certification – main contractor 
AGD/CB/O/15 Number of learners receiving an Industry certification – sub-contractor 
AGD/CB/O/16 Number of Training Plans for sub-contractors  
AGD/CB/O/17 Site visits by Colleges  
AGD/CB/O/18 Supply Chain Briefings to sub-contractors 

Page 84

NAC Growth and Investment 
AGD Business Case 
78
AGD/CB/O/19 Business Skills Supports for sub-contractors  
AGD/CB/O/20 Support for the Third Sector 
AGD/CB/O/21 Softer community benefits delivered to Ayrshire as part of the project   
Outcomes 
AGD/OT/1 Job Levels (new and maintained)  
AGD/OT/2 Development Space uptake 
AGD/OT/3 Digital usage patterns 
AGD/OT/4 Reduced (net) Fuel Poverty 
AGD/OT/5 Increase in visitor spend 
AGD/OT/6 Start-up performance/survival 
AGD/OT/7 Additional investment (including FDI) 
AGD/OT/8 Improved business productivity 
AGD/CB/OT/1 CWB participant well-being uplifts 
AGD/CB/OT/2 Fair Work implementation 
Impacts 
AGD/I/1 Net additional jobs created/ maintained 
AGD/I/2 Net additional returns on investment 
AGD/I/3 Net changes in Fuel Poverty 
AGD/I/4 Net additional user productivity 
AGD/I/5 Follow on investment 
AGD/I/6 Reduced levels of deprivation within the region  
AGD/I/7 Increased income levels 
AGD/CB/I/1 Wider uptake of Well Being/Fair work 
AGD/CB/I/2 Net uplifts in regional supplier spend  
AGD/CB/1/3 Case Studies – qualitative community impacts  
6.7 Carbon management 
For all AGD projects, procedures will be developed across that apply best practice carbon
management techniques, notably PAS 2080: Carbon Management in Infrastructure, to ensure
that potential carbon emissions resulting from the project will be minimised from the outset.
For planned buildings, the RICS Whole Life Carbon Assessment for the Built Environment
approach will also be applied. These compatible approaches represent the highest standard in
whole life buildings and infrastructure carbon management and will ensure that the potential
carbon emissions impact of the project is demonstrably minimised. 
Embodied carbon (i.e., carbon particularly associated with construction materials and
processes) will be minimised utilising the above carbon management approaches, including
the use of innovative materials, construction techniques  and supply chain procurement
mechanisms to reduce carbon emissions, minimise waste and contribute towards a circular
economy, Design and construction of the project will target net zero operational emissions,
including no use of fossil fuels, at lease in accordance with the Scottish Government’s climate
change plan. 
Initial carbon analysis has been done for the overall project and is shown in Appendix I. The
project has been categorised as Control (3, then zero) and Influence (B). 
6.8 Arrangements for risk management 
The strategy, framework and plan for dealing with the management of risk will be through the
contract with monitoring by the Project Manager within the Council’s PMI Team.

Page 85

NAC Growth and Investment 
AGD Business Case 
79
A copy of the project Risk Register is attached at Appendix E. This sets out who is responsible
for the management of risks and the required counter measures. 
6.9 Arrangements for contract management 
The Phase 2 Flex Space project will be managed by the Council’s PMI team and construction
phase will be delivered by the preferred bidder. Management will include regular progress
meetings and reports by the contractor. The Council’s PMI team will project manage and
oversee the works on behalf of North Ayrshire Council and will be responsible for resolving
any issues that arise with the contractor. 
6.10 Arrangements for post project evaluation 
Project monitoring and evaluation will be managed through AGD governance arrangements,
as established and through the reporting requirements related to the Local Regeneration
Fund. The project will be subject to regular review meetings to discuss progress, programme,
financial and technical matters. 
It will be necessary to monitor the impact of the AGD, including at individual project level. The
flexible space project will be monitored through the various Green Book Business Case
Stages by North Ayrshire Council’s Growth and Investment Team. The Project Lead will report
progress at key stages through a series of Gateway Boards and bi-monthly updates to the
Council’s Executive Leadership Team. Project spend will be monitored on a monthly basis
with the Council’s Finance Team. A monitoring and evaluation framework will be developed to
monitor the project’s outputs and outcomes and ensure that those are included, where
possible, within the procurement process. 
6.11 OCG Gateway review arrangements 
The Office of Government Commerce (OGC) Gateway Process is designed to provide
independent guidance to Senior Responsible Owners (SROs), programme and project teams
and to the departments who commission their work, on how best to ensure that their
programmes and projects are successful. This process examines programmes and projects at
key decision points in their lifecycle. It looks ahead to provide assurance that they can
progress successfully to the next stage. These key stages or ‘Gates’ are: 
• Gate 0 – Strategic Assessment 
• Gate 1 – Business Justification 
• Gate 2 – Delivery Strategy 
• Gate 3 – Investment decision 
• Gate 4 – Ready for Service 
• Gate 5 – Benefits Realisation and Operational Review 
In terms of Phase 2 and this specific FBC, the internal project board will discuss the aspects of
the outcome of the tender process at a meeting in due course, and will require to be satisfied
with the outcome of the process outlined to them at the meeting in order for the proposed
contract award to progress through the next governance stages.

Page 86

NAC Growth and Investment 
AGD Business Case 
80
6.12 Contingency plans 
In the event that this project fails, governance arrangements are in place to allow the Council
to agree an appropriate way forward with the PMO and Governments to ensure that there is
limited impact on the Ayrshire Growth Deal and the main funder for the Phase which is UK
Government, through the Local Regeneration Fund (formerly LUF3 fund). 
Signed:      XX 
Date:     Date / April / 2026 
Senior Responsible Owner 
Louise Kirk, Head of Economic Development, Growth & Regeneration, NAC

Page 87

NAC Growth and Investment 
AGD Business Case 
81
PART C: APPENDICES 
Appendices 
Table 1: List of appendices
Ref. Appendices Referenced
A Heat Map and Inclusive Growth Drivers  1.2.1, 2.4.1  
B Flexible Space Links to AGD Projects  1.2.1
C Benefits Realisation Logic Chain 2.8, 6.6
D Economic Modelling & Technical Detail  1.3.1, 3.6.2, 3.10 
E Risk Register  1.4.2, 1.5.2, 2.9, 4.3, 6.8
F  Inclusive Growth & Community Wealth Building  1.1.1, 2.3.1
G  Community Benefit Statement  For information 
H  Equality Impact Assessment For information 
I Carbon Management  3.7.5, 6.7 
J Ayrshire Growth Deal Change Management Process 6.5

Page 88

NAC Growth and Investment 
AGD Business Case 
82
APPENDIX A: INCLUSIVE GROWTH HEAT MAP

Page 89

NAC Growth and Investment 
AGD Business Case 
83
APPENDIX B: AGD PROJECT LINKS 
Project Link  What is the Link?  Key Actions to Maximise Link  Expected benefits of the link
Digital
Process
Manufacturing
Centre
(DPMC), i3
The DPMC pilot at i3 is operational and
provides a unique facility for processing
manufacturing sector companies to improve
their productivity and modernise their
processes through digital automation. This is
linked to the i3 Flexible space to create a
cluster and accommodate business
opportunities arising from the DPMC project eg
business incubation units. 
• Dialogue required across AGD projects
to established differentiation between
projects, complementarity opportunities
and wider understanding of partner
roles in each project (eg NMIS,
University of Strathclyde, CPI, Ayrshire
College)
• Creation of cluster area at i3 with DPMC and
business space that complements each other
and accommodates spin off opportunities from
the DPMC facility being located at Irvine. 
• Opportunities for referral from DPMC to more
specialised F&D facility at AMIC 
Project Link What is the Link? Key Actions to Maximise Link Expected benefits of the link
Building
Digital Capital
(BDC)
This project replaces the Digital Infrastructure
(£3M) and Subsea Cable (£11M) projects
supporting digital infrastructure across Ayrshire
with an allocation of £4.6M for North Ayrshire
to support digital infrastructure, critical to the
region’s future growth. This will still seek to
improve connectivity for local businesses
including fibre, mobile, 5G and smart poles
infrastructure, building on the recent benefits
of the 5GIR private network pilot delivered at
DPMC. 
• Develop specific digital infrastructure
improvement proposals for i3 with BDC
project lead, Flex Space design team
and NMIS. 
• Information sharing and opportunities for joint
working. 
• Ensuring i3 connectivity requirements,
including that of DPMC partner NMIS, have
high visibility as part of the Digital
Infrastructure project. 
Project Link What is the Link? Key Actions to Maximise Link Expected benefits of the link
Ayrshire
Engineering
Park (AEP)
With potential links to NMIS (National
Manufacturing Institute Scotland) which are
still being explored, the Engineering Park will
provide businesses the opportunity to explore
how to improve process and improve 
engineering/manufacturing excellence to be 
the best in their field. i3 will provide a 
unique facility and hub for businesses 
seeking to improve their productivity and 
modernise their processes through digital 
automation for the chemical and Life 
Sciences sectors which is very much aligned 
• Set up referral routes from the project
• Working group oversees both projects
and responsible for integration.
• Sharing of information and joint
discussions with NMIS to ensure a
collaborative approach and avoid
duplication. 
• Sharing of learnings and studies which
would benefit or transfer across sub
sectors to benefit the wider
manufacturing sector in Ayrshire.
•  Sharing of information and resource. 
• Collaboration on projects which can be
developed with mass benefit to the wider
manufacturing sector in Ayrshire.
• Provision of flexible space in both North and
East Ayrshire which will drive inward
investment to the area providing greater
choice to investors and collaborative working
across the councils.

Page 90

NAC Growth and Investment 
AGD Business Case 
84
with the Engineering Park vision. I3 and the 
Engineering Park will complement the
manufacturing industry in general across 
Ayrshire and the south-west of Scotland 
while focusing on different areas of industry. 
The development of advanced 
manufacturing space in both North and East 
Ayrshire will attract inward investment to 
the Ayrshire Region.
Project Link  What is the Link?  Key Actions to Maximise the Link Expected Benefits of the Link 
Ayrshire
Skills
Investment
Fund 
Ayrshire Skills Investment Fund has established
a responsive skills fund to drive Inclusive
Growth. The fund can help support people on
the programme to develop skills. The Ayrshire
Skills Investment Fund will add flexibility and
responsiveness to the skills system to address
related i3/DPMC industry needs. It can also
ensure that disadvantaged sectors of the
community have access to career opportunities
through the i3/DPMC AGD projects 
• Ensure attendance of Officer
representing Flex Space/DPMC at
relevant working group meetings
• Set up referral routes from project. 
• Joint discussions with local Colleges to
ensure a collaborative approach
• Sharing of information regarding skills
gaps identified through business
engagement
• Direct link to skills training
• Support to prepare those out of labour market
to new jobs
• Achievement of key outcome to raise skills
levels within the local area 
Project Link  What is the Link?  Key Actions to Maximise the Link  Expected Benefits of the Link 
AMIC
(Ayrshire
Manufacturing
Investment
Corridor) 
With links to NMIS the AMIC centre will provide
pilot plant facilities to allow F&D manufactures
to test and development new production and
manufacturing practices. While the DPMC at i3
provides a unique facility for process
manufacturing sector companies to improve
their productivity and modernise their
processes through digital automation. AMIC
and DPMC will complement the manufacturing
industry in general across Ayrshire and the
south-west of Scotland while focusing on
different areas of industry.  The development
of advanced manufacturing space as part of
AMIC, will attract inward investment to the
Ayrshire Region.
• Set up referral routes from the project
• Working group oversees both projects
and responsible for integration.
• Sharing of information and joint
discussions with NMIS to ensure a
collaborative approach and avoid
duplication. 
• Sharing of learnings and studies which
would benefit or transfer across sub
sectors to benefit the wider
manufacturing sector in Ayrshire. 
• Sharing of information and resource. 
• Collaboration on projects which can be
developed with mass benefit to the wider
manufacturing sector in Ayrshire.
• Provision of flexible space in both North and
East Ayrshire which will drive inward
investment to the area providing greater
choice to investors and collaborative working
across the councils.

Page 91

NAC Growth and Investment 
AGD Business Case 
85
APPENDIX C: BENEFITS REALISATION LOGIC CHAIN 
Project Inputs
(resources)
Project Activities (what you
do)
Project Outputs (what is
produced)
Project Outcomes (change expected as
result of outputs/activities)
Programme Objective 
AGD £15million
Scot Govt £11M 
NAC £4M 
Local
Regeneration
Fund (formerly
LUF3) £4.706M 
Vacant &
Derelict Land
Fund (VDLF) 
£0.967M
• Planning applications
submitted
• Site remediation work
• New link/access roads
developed
• Construction of
SUDS/sewerage systems 
• Improved junctions to
enhance access to sites
• New junctions to open up
access to sites
• Construction of flexible
business space in phases. 
• Total Area reclaimed,
(re)developed or assembled (20
Ha) as a result of the project
• Total Area of Opportunity Sites
(20 Ha)
• New Industrial & Business
Space (6,000sq m)
• Individuals supported into work
• Private businesses supported
• Jobs safeguarded
• Wide range of employment
opportunities
• Improved pedestrian linkages 
• Vacant and Derelict Land
brought back into use/removed
from SVDL Register (20 ha)
• Flexible business space for
start-up or needs
• Well-connected flexible
business space within close
proximity to central belt region
supply chains and workforce 
• Altered perception and market sentiment
in regard to Ayrshire’s advance
manufacturing and digital offer
• Improved market sentiment
• 20 Ha land unlocked for development
• Increased levels of investment, including
FDI 
• Uplift in commercial rental/sales values
(£)
• Increased supply of commercial space 
• Strengthening key business clusters 
• Increased employment and
development of skills in local workforce
• Increased GVA 
• Reduced levels of deprivation in local
areas 
• Enhanced accessibility - employment/
business locations
• Widening of labour market
• Improved business productivity
• Strengthening key business clusters 
• Businesses attracted to the locality and
increase in inward investment
• Reduction in level of vacant and derelict
land
• 18-35 People from Employability & Skills
Programme Accessing Jobs
• Sustainable work location with services
and amenities to support employees
(e.g. child care/creche facility/café/retail)
• Increase employment opportunities 
• Increase in GVA across region
• Lever in private sector investment
• Spread the benefits of economic growth
across region, ensuring deprived areas
benefit from this growth.
• Job market entrants and low skilled workers
increasing soft and basic skills through
provision of local jobs 
• Attract skilled workers to the region and
support local people entering skilled
employment opportunities

Page 92

NAC Growth and Investment 
AGD Business Case 
86
APPENDIX D: ECONOMIC MODELLING, i3 FLEXIBLE
SPACE PHASE 2 
The following tables and information set out the approach to and findings of economic
modelling for the Flexible Space Phase 2 project. 
Flexible Space, Phase 2 – Options Summary 
Option  Description  Narrative 
Option 1
Business as
usual 
Do Nothing
(Counterfactual)
DISCOUNTED 
It is estimated that the percentage of economic activity
generated within the project area without any investment
i.e. Deadweight, would be 0%.
Option 2:
Single Unit 
Deliver one 1,690 sqm
(18,191 sqft) GIFA unit
by 30 June 2027, with
occupancy starting 01
April 2028. 
PREFERRED OPTION. 
Delivers additional space with a realistic timeline for
occupation. In addition, Options for positive and negative
sensitivity are provided. 
Option 2a: 
Single Unit 
Preferred Option
Positive Sensitivity
DISCOUNTED 
• Fully occupied earlier – 01 October 2027
• Increased rateable rate from £75 per sqm to £85
per sqm
• Decrease Leakage and Displacement
additionality operational factors. 
Leakage 
Current 
Leakage 
Decrease
Displace-
ment 
Current
Displace-
ment 
Decrease
LA 40% 30% 5% 0%
GCR 20% 15% 10% 5%
Scotland  0% 0% 0% 0%     
Option 2b:
Single Unit 
Preferred Option
Negative Sensitivity 
DISCOUNTED 
• Fully occupied later – 01 October 2028
• Decreased rateable rate from £75 per sqm to £65
per sqm
• Increased Leakage and Displacement
additionality operational factors 
Leakage 
Current 
Leakage 
Increase
Displace-
ment 
Current
Displace-
ment 
Increase 
LA 40% 45% 5% 10%
GCR 20% 30% 10% 15%
Scotland  0% 5% 0% 5% 
Option 3:
Subdivided
Unit 
Deliver 1,630 sqm
(17,544 sq ft) GIFA of
space subdivided into
4 lettable units by 30
June 2027 with 100%
occupancy by 01 April
2029.
DISCOUNTED OPTION. 
Delivers one unit subdivided into smaller units, some of
which may be filled quicker but not necessarily all of
them, meaning that 100% occupancy is likely to be
achieved later. This option may take slightly longer to
deliver due to the difference in format. There is more
need for larger units and the main cost of the
development is being funded through LUF 3, for which
the business case and format of the unit has already
been agreed and aligns with the Preferred Option. 
Option 4:
Terraced
Units 
Deliver Flex Space
Phase 3 earlier by 31
March 2028, which
DISCOUNTED OPTION. 
Delivers Phase 3 Flex Space earlier which are two sets of
smaller terraced incubation units. This option is

Page 93

NAC Growth and Investment 
AGD Business Case 
87
includes two sets of
terraced units totaling
1,068 sqm (11,496 sq
ft) with 100%
occupancy by 
1 April 2029.
discounted as it would take longer to deliver as it has not
yet reached the end of RIBA Stage 4, like Option 2, could
take longer to achieve 100% occupation and the majority
of the development is supported by LUF 3 which requires
the business case and format of the unit to align with the
Preferred Option. 
Option 5:
Smaller
unit, LUF 3 
Deliver a smaller
single unit within the
LUF 3 budget cost
envelope (estimated at
1,281 m2) by 30 April
2027 with full
occupancy by 01
January 2028. 
DISCOUNTED OPTION. 
Delivers a smaller unit only funded by LUF3 funds, that
could be delivered earlier ie 30 April and enables
additional AGD funds to be reallocated from Phase 2 to
Phase 3. This development could be delivered slightly
earlier but would not meet the agreed floorspace level
approved by LUF 3. In addition, the project is already
advanced based on the preferred option and is at tender
stage. 
Additionality Approach 
2.0 Introduction 
This note has been prepared to explain the approach to considering additionality for the
purposes of economic modelling for Phase 2 of the Ayrshire Growth Deal Flexible Advanced
Manufacturing Space project at i3 Business Park in Irvine. The project proposes an
estimated investment of £6.775M in a single 18,191 sq ft (1,690 sq m) industrial unit with
related yard space and parking, funded by Levelling Up Fund 3 (£4.7M) and Ayrshire Growth
Deal (£2.069M). In this respect, benefits are estimated in relation to construction,
operational, land value uplift and carbon accounting. 
2.1 Counterfactual Assessment and Deadweight 
It’s unlikely that any or very limited outputs/outcomes would be secured without the
intervention of the project’s investment through the public sector, as there is market failure
within the area. This means that there is no incentive for the market to deliver modern
industrial units. New, similar developments taking place within the locality have been
supported by the public sector with little or no historical development / investment from the
private sector in this type of project. The significant gap between the construction costs and
asset value is demonstrated in a valuation undertaken for the project by Ryden in December
2024. The valuation estimated the market value of £1,304,000 for the unit, in comparison to
the estimated construction costs, which at the time were estimated to be £6,156,300. In this
respect, it is estimated that the percentage of economic activity that would have been
generated within the project area without any investment i.e. the Deadweight, would
be 5% for North Ayrshire, Ayrshire and Scotland, given the challenges that the private
sector face in delivering commercial floorspace. 
2.2 Construction Benefits 
The project is estimated to generate nearly £6M in construction related benefits through the
creation of an industrial unit and related land remediation, following investment in Phase 1.
The main investment activity takes place during years 2026/27 and 2027/28, after which
some revenue costs are anticipated until the unit is let. It is assumed these revenue costs
will be in the region of £67,500. In this respect the project investment profile is as follows: 
Construction
Spend 
Total
Spend
Year 4 Year 5
24/25
Year 6
25/26
Year 7
26/27
Year 8
27/28
Capital spend  £6.775M £0.051m £0.305M £0.132M £2.068M £4.220M
Revenue
spend 
£0.0675M  £0 £0 £0 £0.0675M
Total  £6.8425M £0.051M £0.305M £0.132M £2.068M £4.2875M

Page 94

NAC Growth and Investment 
AGD Business Case 
88 
Follow on investment from the tenant is anticipated in terms of fit out costs which are
assumed at £500,000 as a rough estimate. There may also be the potential for the tenant to
extend the building as the format allows for this, although this is assumed to be unlikely for
the moment due to the high cost of construction.   
2.2.1 Construction Leakage
The works involve the construction of an industrial unit for which there are probably only a
few companies based locally (i.e. within Ayrshire) that could tender for this work, as it is
considered to be quite specialised.  If the appointed contractor for the works is not based
locally, it is assumed that a very small percentage of construction activity will be delivered by
local businesses that employ local labour.  This was the scenario for Phase 1 Flex Space, as
the contractor was based in Fife and so there were limited job opportunities for local people
with the main contractor but more opportunities related to sub-contracts locally.  However, if
the company awarded the tender is locally based, this could make a significant difference to
the level of construction activity employing local labour. 
2.2.2 Construction Displacement
It is assumed that there will be lower levels of displacement due to lower competition within
the Ayrshire area, as there are not many local contractors within North Ayrshire and the
wider Ayrshire area that specialise in constructing industrial units. 
2.2.3 Construction - Economic Multipliers
It is considered that local business within North Ayrshire will act as a supply chain for the
construction of the industrial unit. For example, within the following trades of groundworks,
fencing, plumbing & heating, joinery, roofing. In addition, community benefits will be included
within the contract to encourage the successful contractor to take on for example local
apprentices. 
2.2.4 Construction Benefits – Additionality Factors 
To summarise, for the project and the preferred option, the additionality factors are set out in
the table below. In addition, the same percentages have been applied to the other options.
Please see overall table in Appendix 1 and comparison to AEP OBC Additionality Factor
percentages in Appendix 2.   
Construction Benefits
Additionality Factors:  Leakage (%) Displacement (%) Multipliers Deadweight (%)
North Ayrshire  30% 10% 1.2 5%
Ayrshire 20% 20% 1.5 5%
Scotland  5% 10% 1.8  5% 
• Leakage - the extent to which the construction benefits of the project will leak out of
the target area into other areas are estimated to be 30% for North Ayrshire, 20% for
Ayrshire and 5% for Scotland.  
• Displacement - the extent to which an increase in the intended construction benefits
is offset by reductions in economic activity elsewhere in the economy is estimated to
be low and 10% for North Ayrshire and Scotland and 20% for Ayrshire. 
• Economic Multipliers – the wider economic benefits generated through the project
into the economy are likely to be 1.2, 1.5 and 1.8 respectively. 
• Deadweight is estimated to be 5% across North Ayrshire, Ayrshire and Scotland
because a very small number, if any, of the economic construction benefits of the
project would've happened without this intervention.

Page 95

NAC Growth and Investment 
AGD Business Case 
89
2.3 Operational Benefits 
The project will create commercial floorspace which has planning permission for use classes
4, 5 and 6.  The unit is speculative, so at this time it is not known what business will occupy
the building and what the operational benefits could be in terms of how many people will be
employed and what GVA it will generate. 
• Leakage - a comparison has been made with the percentages for the AEP OBC
which were 40% for East Ayrshire, 15% for Ayrshire and 0% for Scotland for all
options that included commercial floorspace. For this project its considered that the
figures could be 40% for North Ayrshire, 20% for Ayrshire and 0% for Scotland for all
options.  
• Displacement - the extent to which an increase in the intended operational benefits is
offset by reductions in economic activity elsewhere in the economy is estimated to be
low and 5% for North Ayrshire, 10% for Ayrshire and 0% for Scotland – taking a
similar approach to those percentages applied to the AEP OBC. 
• Economic Multipliers –Reflecting other similar projects in the Ayrshire region and as
a conservative estimate a multiplier of 1.1 have been applied which is the same as
the AEP OBC. 
• Deadweight is estimated to be 5% across North Ayrshire, Ayrshire and Scotland
because a very small number, if any, of the operational benefits of the project
would've happened without this intervention. 
Operational Benefits 
Additionality Factors:  Leakage (%) Displacement (%) Multipliers Deadweight (%)
North Ayrshire  40% 5% 1.0 5%
Ayrshire 20% 10% 1.0 5%
Scotland  0% 0% 1.0  5% 
Options Narrative for Modelling 
Option 2: Single Unit, Preferred Option, plus Options 2a & 2b (Sensitivity) 
Description  Narrative 
Deliver one 1,690 sqm
(18,191 sq ft) unit by 30
June 2027, with occupancy
starting 01 April 2028. 
PREFERRED OPTION. Delivers additional space with a realistic
timeline for occupation. In addition, Options for positive and negative
sensitivity are also provided below comprising of:
Option 1a (positive) – fully occupied by 1 October 2027 (positive)
Rateable rate at £85 per sqm
Leakage and Displacement Additionality Operational factors
decreased to the following: 
Leakage Decrease Displacement Decrease 
LA 30% 0%
GCR 15% 5%
Scotland  0% 0% 
Option 1b (negative) – fully occupied by 1 October 2028 (negative)
Rateable rate at £65 per sqm
Leakage and Displacement Additionality Operational factors
decreased to the following: 
Leakage Increase Displacement Increase 
LA 45% 10%
GCR 30% 15%
Scotland  5% 5%

Page 96

NAC Growth and Investment 
AGD Business Case 
90 
• Assumes single unit, not subdivided. 
• Design and build contract awarded June 2026.
• Unit completed by 30 June 2027.
• Fully occupied starting 01 April 2028. This time period allows for approximately 9
months (July 27 to March 28 inclusive) for conclusion of marketing period, Cabinet
agreement to lease disposal and subsequent conclusion of the lease agreement. 
• Assumes operational year of unit would start in financial year 28/29 ie April 2028 
MODELLING
SPREADSHEETS 
INFORMATION / ASSUMPTIONS 
Costs Capital cost estimates for design, consultancy and contract costs are
grouped together. 
Assumes private sector fit out costs of £500,000. 
Revenue costs assume costs incurred by NAC from handover from
contractor to occupancy by lessee, ie, costs from July 2027 to March 28 (9
months). This would comprise of the following costs per annum based on
previous estimates for the project: 
Electricity and standing charges £60,000 
Maintenance    £10,000
Landscaping    £10,000
Insurance     £5,000
Water     £5,000
Total annual charges   £90,000
This equates to £7,500 per month and £67,500 for 9 months. 
Construction
Benefits 
Assumes design development takes place 24/25, 25/26 and construction
takes place 26/27 and part of 27/28.
Assumes private sector fit out costs of £500,000. 
Operational
Benefits
Assumed light industrial, with full occupancy by April 2028. 
NDR Based on Ryden rental valuation from Dec 2024 of £127,400. Assumes
100% rates relief in first year of occupancy from April 2028 til March 2029.
Works out at a rateable value of £75 per square metre. 
Additionality Factors percentages are assumed to reflect the Operational
Benefits. 
Housing Benefits N/A
Council Tax N/A
Energy
Consumption
Assumes energy consumption of 200,000 kwh (or when building operational,
based on estimates for Phase 1. Assumes energy consumption of 538 kwh
per month (6,456 kwh per annum) when building unoccupied, based on
average taken from invoices for Phase 1 when unoccupied. 
Assumes lower energy consumption between July 2027 and March 2050
which is 4,842 kwh (ie 538 kwh per month for 9 months). 
Assumes energy consumption 200,000 kwh per annum (or 16,667 kwh per
month) from April 2028 onwards.   
Proposed solar PV panels will help off-set emissions. 
Option 2: Sensitivity Testing – Occupation – Positive & Negative Scenarios 
Additional modelling sheets have been provided that have considered the following
variations on Option 1 related to when the unit is fully occupied.

Page 97

NAC Growth and Investment 
AGD Business Case 
91
Option 2a – fully occupied by October 2027 (positive)
This Positive Sensitivity Option assumes that the unit will be occupied earlier by October
2027 rather than by April 2028. This means there will be less revenue costs for the Council
between the handover and letting period i.e. three months of revenue costs at an estimated
£22,500. In addition, the unit will be operational within an earlier financial year 27/28, with
the Council receiving rental income at an earlier stage. 
The rateable value of the Unit once occupied is assumed to increase to £85 per sqm, an
increase of £10 per sqm when compared to the preferred option of £75 per sqm. 
Leakage and Displacement Additionally factors related to the operation of the Unit are
adjusted downwards, with the percentage rate across all three geographical spatial defined
areas when compared to the preferred option. 
Assumes lower energy consumption between July 2027 and Sept 2027 which is 1,614 kwh
(ie 538 kwh per month for 3 months) and from Oct 27 til March 28, 100,002 kwh based on 6
months operational, providing a total of 101,616 kwh consumption for 2027/28.   
Option 2b – fully occupied by October 2028 (negative)
This Negative Sensitivity Option assumes that the unit will be occupied later by October
2028 rather than by April 2028. This means there will be more revenue costs for the Council
between the handover and letting period i.e. 15 months of revenue costs at a total of
£112,500 (£67,500 in 27/28 and £45,000 in 28/29). In addition, as the unit will be operational
later, the Council will begin to receive rental income at a later date.   
The rateable value of the Unit once occupied is assumed to decrease to £65 per sqm, a
decrease of £10 per sqm when compared to the preferred option of £75 per sqm.
Leakage and Displacement Additionally factors related to the operation of the Unit are
adjusted upwards, with the percentage rate across all three geographical spatial defined
areas when compared to the preferred option. 
Assumes lower energy consumption between July 2027 and Sept 2028 which is 8,070 kwh
(ie 538 kwh per month for 15 months) and from Oct 28 til March 2029, 108,172 kwh based
on 6 months operational, providing a total of 101,616 kwh consumption. This works out:
energy consumption of 9 months during 2027/28 (Jul 27 to Mar 28) of 4,842 kwh and energy
consumption during 2028/29 of 6 months of low energy consumption of 3,3228 kwh (Apr 28
to Sept 28) and 6 months of high energy consumption once the unit is occupied from
October 2028 (100,002 kwh) giving a total of 103,230 kwh. 
Leakage 
Current 
Leakage 
Decrease
Displacement 
Current
Displacement 
Decrease
Multipliers  Deadweight
LA 40% 30% 5% 0% 1.0 5%
GCR 20% 15% 10% 5% 1.0 5%
Scotland  0% 0% 0% 0% 1.0 5% 
Leakage 
Current 
Leakage 
Increase
Displacement 
Current
Displacement 
Increase 
Multipliers  Deadweight
LA 40% 45% 5% 10% 1.0 5%
GCR 20% 30% 10% 15% 1.0 5%
Scotland  0% 5% 0% 5% 1.0 5%

Page 98

NAC Growth and Investment 
AGD Business Case 
92
Table 39: Benefits-Cost Ratio Timeframe - 25 Year Appraisal – Sensitivity Testing of Single Unit 
Table 40: Benefits-Cost Ratio Timeframe - 25 Year Appraisal (Construction Impacts Removed) -
Sensitivity Testing of Single Unit 
The sensitivity testing of the preferred option to assess its robustness has demonstrated that
through amendments of the occupation of the built unit, ratebale rates and Additionality
factors during operation will change significantly the Ayrshire BCR of the proposal. An
accumulation of the Negative alterations reduces the BCR to £8.62:£1, whilst accelerating
occupation, increasing rateable rates and softening of Additional factors heightens the BCR
to £11.02:£1. In the meantime, the number of construction and occupational jobs generated
changes principally in response to the positive alterations with an uplift in Ayrshire jobs to 29.
Elsewhere significant change is translated to expected operational GVA generated with a
positive action uplifting the GVA potential to £80.332m when compared against benchmark
preferred option of £67.318 (at an AGD level). 
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit-Pref Option Pref Option Sensitive +A Pref Option Sensitive -B
PV of Capital Costs All Geographies £0 £6,806,267 £6,806,267 £6,806,267
PV of Revenue Costs All Geographies £0 £847,851 £735,412 £815,476
PV of Total Costs All Geographies £0 £7,654,118 £7,541,679 £7,621,744
Local Authority £0 41 41 41
Ayrshire Growth Deal £0 53 53 53
Scotland £0 84 84 84
Local Authority - £2,247,803 £2,247,803 £2,247,803
Ayrshire Growth Deal - £2,854,353 £2,854,353 £2,854,353
Scotland - £4,575,885 £4,575,885 £4,575,885
Local Authority £0 19 24 19
Ayrshire Growth Deal £0 26 29 26
Scotland £0 34 34 34
Local Authority - £50,628,932 £66,156,308 £47,497,335
Ayrshire Growth Deal - £67,318,248 £80,332,659 £63,154,351
Scotland - £88,822,688 £94,509,011 £83,328,657
Actual 0 £491,064 £491,064 £491,064
Net Impact - £491,064 £491,064 £491,064
Local Authority - £6.90 £9.04 £6.48
Ayrshire Growth Deal - £9.16 £11.02 £8.62
Scotland - £12.19 £13.16 £11.52
Person Years of Construction
Employment
Present Value of Net Additional
Construction GVA
Benefit Cost Ratio
Full-time Equivalent Jobs
Present Value of Net Additional
Operational GVA
PV of GHG Carbon Accounting
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit-Pref OptionPref Option Sensitive +APref Option Sensitive -B
PV of Total Costs All Geographies £0 £7,654,118 £7,541,679 £7,621,744
Local Authority £0 £52,810,691 £68,190,851 £49,375,641
Ayrshire Growth Deal £0 £70,106,557 £83,096,150 £65,701,606
Scotland £0 £93,332,529 £99,222,509 £87,789,321
Local Authority - £50,562,888 £65,943,047 £47,127,837
Ayrshire Growth Deal - £67,252,204 £80,241,797 £62,847,252
Scotland - £88,756,644 £94,646,624 £83,213,435
Actual 0 £491,064 £491,064 £491,064
Net Impact - £491,064 £491,064 £491,064
Local Authority - £6.61 £8.74 £6.18
Ayrshire Growth Deal - £8.79 £10.64 £8.25
Scotland - £11.60 £12.55 £10.92
Present Value of Net Direct GVA
Present Value of Net Additional
GVA
PV of GHG Carbon Accounting
Benefit Cost Ratio

Page 99

NAC Growth and Investment 
AGD Business Case 
93
Option 3: Subdivided Unit 
Description  Narrative 
Deliver 1,630 sqm (17,544
sq ft) of space subdivided
into 4 lettable units by 30
June 2027 with 100%
occupancy by 01 April
2029.
DISCOUNTED OPTION. Delivers smaller units within the same
timescale, some of which may be filled quicker but not necessarily all
of them, meaning that 100% occupancy is likely to be achieved later.
There is evidence of more need for larger units and the main cost of
the development is being funded through LUF 3, for which the
business case and format of the unit has already been agreed and
aligns with the Preferred Option. 
• Assumes four units with a rateable value of £8.50 per sq ft based on previous
Colliers valuation.
• Estimated revenue costs based on benchmark from Annickbank proposals (3 units at
500m2, total estimated annual revenue costs whilst vacant are £45,000) works out
four units just over 400m2 each with overall annual revenue vacancy costs of
£48,000 (£12k per unit per annum) 
Unit  Size 
sq ft (GIA)
Size 
sq m
Rental Value  Occupancy Date  Revenue
Costs period
Est Rev
costs 
1 4,445 413 £37,782.50 01 Oct 27 3 months  £3,000
2 4,445 413 £37,782.50 01 Apr 28 9 months  £9,000
3 4,327 402 £36,779.50 01 Oct 28 15 months  £15,000
4 4,327 402 £36,779.50 01 Apr 29 21 months  £21,000 
Electricity Consumption assumptions 
Unit  Size 
sq ft (G
Size 
sq m
Occupancy
Date 
Vacant kwh
27/28
Occupied
kwh 27/28
Vacant kwh
28/29
Occupied
kwh 28/29
1 4,445 413 01 Oct 27 501 kwh 25,002  N/A 50,000
2 4,445 413 01 Apr 28 1,503 kwh N/A N/A 50,000
3 4,327 402 01 Oct 28 1,503 kwh N/A 1,002 25,002
4 4,327 402 01 Apr 29 1,503 kwh N/A 2,004 N/A 
MODELLING
SPREADSHEETS 
INFORMATION / ASSUMPTIONS 
Costs Capital cost estimates for design, consultancy and contract costs are
grouped together. 
Assumes construction costs include a level of fit out works. 
Private sector costs of £500,000 assumed for fit out. 
Revenue costs assume costs incurred by NAC from handover from
contractor to occupancy by lessee, ie, costs from July 2027. 
Estimated revenue costs based on benchmark from Annickbank proposals
(3 units at 500m2, total estimated annual revenue costs whilst vacant are
£45,000). 
Constructions
Benefits
Construction costs and programme – are the same as the preferred option -
design and build contract awarded June 2026 and units completed by 30
June 2027. 
Assumes construction costs also include a level of fit out works. 
Assumes private sector fit out costs of £500,000.
Fully occupied, starting from 01 April 2029. 
This extended time period allows for a longer timescale to market all four
units and for the subsequent conclusion of the lease agreements. It’s

Page 100

NAC Growth and Investment 
AGD Business Case 
94
assumed that the individual rental values would below the threshold for
seeking Cabinet approval as part of this process. 
Assumes design development takes place 24/25, 25/26 and construction
takes place 26/27 and part of 27/28. 
Operational
Benefits
Assumed light industrial, with full occupancy by 01 April 2029.
NDR Colliers valuation of Phase 1 from June 2022 provided a scenario for sub-
division into 4 units at a total of 17,544 sq ft or 1,630 m2, with a completed
development value of £2,095,000, assuming an overall market annual rent
of £149,200 per annum at £8.50 per sq ft or £91.50 per sq m. 
Assumes value of each unit would sit below the 100k value at £37k to £38k.  
Additionality Factors percentages are assumed the same as for the
Operational Benefits spreadsheet.
Housing Benefits  N/A
Council Tax N/A
Energy
Consumption
Assumes energy consumption for a light industrial unit of c410m2 would be
approximately 50,000 kwh per year or 4,167 kwh per month when
operational. 
Assumes when non-operational/vacant, the consumption would be 2,000
kwh per annum or 167 kwh per month. 
Please see assumptions table above. 
Option 4: Terraced Units 
Description  Narrative 
Deliver Flex Space Phase 3
which includes two sets of
terraced units totaling 1,068 sqm
(11,496 sq ft) delivered by 31
March 2028 and with full
occupancy by 01 April 2030.
DISCOUNTED OPTION. Delivers Phase 3 Flex Space earlier
which includes two sets of smaller terraced incubation units.
This option is discounted as it would take longer to deliver as it
has not yet reached the end of RIBA Stage 4 (like Option 2), it
could take longer to achieve 100% occupation and the majority
of the development is supported by LUF 3 which requires the
business case and format of the unit to align with the Preferred
Option and the certainty of LUF3 funds being spent within a
required timeline. 
Assumes the following: 
Terrace*  Size 
sq ft (GIA)
Size 
sq m
Rental Value  Occupancy
Date 
Revenue
Costs period
Est Rev
costs 
3A 6,907.26 641.7 £58,711.71 01 Apr 2029 12 months  £12,000
3B 4,588.70 426.3 £39,003.95 01 Apr 2030 24 months  £24,000 
• terrace 3A – capable of subdivision into 6 units with a combined floorspace of 641.7m2
(6,907.26 sq ft) fully occupied by 01 April 2029. 
• terrace 3B – capable of subdivision into 4 units with a combined floorspace of 426.3m2
(4,588.70 sq ft) fully occupied by 01 April 2030.
• Rateable value of £8.50 per sq ft based on previous Colliers valuation.
• Estimated revenue costs based on benchmark from Annickbank proposals (3 units at
500m2, total estimated annual revenue costs whilst vacant are £45,000) works out four
units just over 400m2 each with overall annual revenue vacancy costs of £48,000 (£12k
per unit per annum)

Page 101

NAC Growth and Investment 
AGD Business Case 
95
MODELLING
SPREADSHEETS 
INFORMATION / ASSUMPTIONS 
Costs Capital cost estimates for design, consultancy and contract costs are
grouped together. 
Revenue costs assume costs incurred by NAC from handover from
contractor in March 2028 to occupancy by businesses, i.e. revenue costs
as follows: 
Unit 3A – revenue costs from 01 Apr 2028 to March 2029 (12 months)
when fully occupied 
Unit 3B – revenue costs from 01 Apr 2028 to March 2030 (24 months)
when fully occupied 
Constructions
Benefits
Whilst overall floorspace is smaller, this option assumes construction costs
are the same, as two individual terraces are being created. 
Assumes contract works commence later than July 2026 and starts Jan
2027, as design has not reached RIBA Stage 4, statutory consents
required and tender pack not prepared. Estimate completion by 31 March
2028, full occupation of terrace 3A by 01 April 2029 and full occupation of
terrace 3B by 01 April 2030. 
Operational
Benefits
Assumes:
• terrace 3A –capable of subdivision into 6 units with a combined
floorspace of 641.7m2 (6,907.26 sq ft) fully occupied by 01 April 2029
• terrace 3B – capable of subdivision into 4 units with a combined
floorspace of 426.3m2 (4,588.70 sq ft) fully occupied by 01 April 2030. 
NDR Assumes 100% rates relief in year 1
Additionality Factors percentages are assumed the same as for the
Operational Benefits spreadsheet.
Housing Benefits  N/A
Council Tax  N/A
Energy
Consumption
Assumes energy consumption for unit 3A is low kwh estimate for 2028/29
(3,006 kwh per annum) when unit vacant and being marketed, with full
energy consumption starting in 2029/30 (75,000 kwh per annum) when unit
becomes occupied. 
Assumes energy consumption for unit 3B 426.3m2 is low kwh estimate for
2028/29 (2,004 kwh per annum) and 2029/30 (2,004 kwh per annum) when
unit vacant and being marketed with full energy consumption starting
2030/31 (50,000 kwh per annum) when unit becomes occupied. 
Option 5: LUF 3 Cost Envelope 
Description  Narrative 
Deliver a single unit within the
LUF 3 budget cost envelope
by 30 April 2027 with full
occupancy achieved by 01
January 2028. 
DISCOUNTED OPTION. Delivers a smaller unit only
funded by LUF3 levered funds, which could be delivered
earlier and enables additional AGD funds to be
reallocated from Phase 2 to Phase 3. This development
could be delivered earlier but would not meet the agreed
floorspace level approved by LUF 3. 
This scenario would be based on the following assumptions: 
• Project overall construction spend would require to be within the LUF3 funding cost
envelope which is £4,706,259 rather than the preferred option which is £6,775,000. 
• Cost estimate:

Page 102

NAC Growth and Investment 
AGD Business Case 
96
Design, PM & consultants fees £394,259
Main contractors  £4,100,000 
Site investigation  £21,000
Utilities  £125,000
Planning and Building warrant fees  £20,000
Other contractors (tree clearance) £30,000
Other capital expenditure  £15,000
Total  £4,705,259 
• Floorspace estimate of 1,281m2 (13,788 sq ft) could be achieved based on
£4,100,000 available main contractors budget divided by estimate cost of £3,200 per
square metre. Similar to floorspace scale being created at Kyle Road (1,200m2 based
on £4.56K budget). 
MODELLING
SPREADSHEETS 
INFORMATION / ASSUMPTIONS 
Costs Sheet  Capital cost estimates for design, consultancy and contract costs are
grouped together. Assumes same spend for preferred option 24/25, 25/26
with majority of spend during 26/27 and smaller allocation in 27/28 to cover
retention and other potential costs. 
Assumes private sector costs of £300,000 for fit out. 
Revenue costs assume costs incurred by NAC from handover from
contractor to occupancy by lessee, ie, costs from May 2027 to January
2028 (8 months). This would comprise of the following costs per annum
based on preferred option estimates with some adjustments as the unit is
smaller: 
Electricity and standing charges £50,000
(assume pay almost the same) 
Maintenance    £7,000
Landscaping    £7,000
Insurance     £4,000
Water     £4,000
Total annual charges   £72,000
This equates to £6,000 per month and £48,000 for 8 months.
Constructions
Benefits 
Assumes design development takes place 24/25, 25/26 and construction
takes place 26/27. 
Assumes private sector costs of £300,000 for fit out. 
Operational
Benefits
Assumed light industrial with full occupancy by January 2028. 
NDR  Based on Ryden valuation from Dec 2024 works out at a rateable value of
£75 per square metre. Assumes 100% rates relief in first year of occupancy
from January 2028 til December 2028. 
Additionality Factors percentages are assumed the same as for the
Operational Benefits spreadsheet.
Housing Benefits  N/A
Council Tax  N/A
Energy
Consumption
Assumes energy consumption for the unit is low kwh estimate from
completion date of 30 April 2027 to occupancy by 01 January 2028 ie 8
months and 3 months at full consumption from January to March 2028. 
Consumption estimates are based on 75% of preferred option low
estimates 538 kwh per month and high estimates 16,667 kwh per month (ie
404 kwh and 12,005 kwh) 
8 months at low is 3,232 kwh and 3 months at high is 36,015 kwh 
Total is 39,247 kwh for 2027/28
Total for 2028/29 is 144,060 kwh

Page 103

NAC Growth and Investment 
AGD Business Case 
97
Background to Economic Modelling 
The economic modelling for the Phase 2 Flexible Space options has been quantified using
the Glasgow City Region Intelligence Hub’s Business Case Economic Model (BCEM).
BCEM was developed following the methodology outlined within the GCR’s Programme
Management Toolkit. 
This approach quantifies Benefit-Cost Ratios (BCRs) using a HM Treasury Green Book
approved methodology and has been used for successful Glasgow City Region City Deal
business cases and Levelling Up Fund applications. 
The benefits that are quantified within BCEM can fall under the broad headings of
Construction, Operational, Housing, and Greenhouse Gas Emissions. Each monetary
benefit is then subject to HM Treasury’s preferred discount rate of 3.5%, moving to 3% after
a 30-year appraisal period, to obtain Present Values (PV). 
As per HM Treasury Green Book compliance, a Counterfactual, otherwise known as a “do
nothing”, scenario is initially established before identifying the costs and benefits of any
subsequent appraised intervention. 
The PV of an intervention’s cumulative benefits are then re-calculated as Net Additional
benefits by subtracting any economic benefits generated in the Counterfactual scenario. A
Benefit-Cost Ratio is then established by dividing the PV of Net Additional Benefits by the
PV of Total Costs. 
For the purposes of modelling for this Ayrshire Growth Deal investment, spatial adjustment
analyses have not been quantified. Spatial adjustment analysis can be used to quantify the
disproportionate impacts that an investment can have on communities with non-typical levels
of productivity or earnings potential. Such disproportionate impacts are not anticipated to
occur from this investment. 
Estimated Benefits and Costs 
METHODOLOGY
This cost benefit analysis has employed appraisal techniques that are consistent with those
outlined in HM Treasury Green Book (HM Treasury, 2022). It considers the range of socio-
economic impacts that the project is forecast to generate at the Local Authority, Growth Deal
Area, and Scotland Geographic levels within the 25-year project appraisal period. This
timeframe aligns with the economic appraisal undertaken at OBC stage and ensures
consistency with the approach adopted by the Glasgow Intelligence Hub for economic
analysis across Ayrshire Growth Deal projects. The timeframe is consistent with estimated
asset lifespans and servicing and maintenance plans. Whilst the modelling has stated a 25
year lifespan, the lifetime of the unit is expected to be longer, due to the quality of the design
and construction including sustainable features. 
The economic outputs for each option displayed within Table 41 below are as of March
2026. As the project develops, these outputs will be updated to take account of current
evidence, changes to the project scope and the associated financial case. 
Costs were estimated based on benchmarking with other Local Authorities and
organisations, feasibility studies and high-level costings from contractor’s and consultants
and evidence of past work examples. Figures have been adjusted for BCIS all in TPI
(Tender Price Index). Consideration is also being given to the cost impact of the buildings
meeting the Scottish Government Net Zero Buildings Standard.

Page 104

NAC Growth and Investment 
AGD Business Case 
98 
OPTIMISM BIAS
The project budget has a significant level of contingency and continues to be given
consideration. Consideration was also given to previous North Ayrshire Council Phase 1
project, now completed spring 2026. 
BCR CALCULATION EXPLANATION
BCRs have been calculated by dividing the PV Net Additional GVA for each option (minus
the PV Carbon Accounting) by the PV Total Cost.
• The Single Unit at Local Authority Geography:
• Net Additional GVA: £2.102m (Construction) + £50.628m (Operational) - £0.039m
(Carbon) = £52.691m
• Divided by the PV Total Cost of £7.654m
• Equals a BCR of £6.91 over a 25-year appraisal period at the local authority level.
BCR Analysis:
The analysis illustrates the robustness of the project and its projected ability to generate
significant economic growth at a local and regional level. This includes not only
demonstrating VfM from the public sector investment but also enable the delivery of both
39 construction and 19 operational jobs. 
25-Year Appraisal
Table 41: Economic Outputs – Overall value for money assessment 
The analysis above identifies the overall value for money assessment benefits that could be
achieved through investment in Flexi Space Phase 2 in and around the Ayrshire area. 
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit Sub divided Unit Terraced Unit Small Unit + LUF
PV of Capital Costs All Geographies £0 £6,806,267 £6,817,997 £6,204,841 £4,754,090
PV of Revenue Costs All Geographies £0 £847,851 £859,795 £823,880 £632,261
PV of Total Costs All Geographies £0 £7,654,118 £7,677,791 £7,028,721 £5,386,350
Local Authority £0 39 41 39 28
Ayrshire Growth Deal £0 49 53 49 36
Scotland £0 79 84 79 58
Local Authority - £2,102,108 £2,250,353 £2,064,459 £1,561,971
Ayrshire Growth Deal - £2,669,343 £2,857,591 £2,621,535 £1,983,455
Scotland - £4,279,291 £4,581,076 £4,202,648 £3,179,726
Local Authority £0 19 19 12 15
Ayrshire Growth Deal £0 26 25 16 20
Scotland £0 34 33 22 26
Local Authority - £50,628,932 £48,878,624 £29,253,376 £40,832,926
Ayrshire Growth Deal - £67,318,248 £64,990,968 £38,896,456 £54,293,087
Scotland - £88,822,688 £85,751,972 £51,321,713 £71,636,712
Actual 0 £39,735 £38,001 £8,963 £30,329
Net Impact - £39,735 £38,001 £8,963 £30,329
Local Authority - £6.91 £6.69 £4.49 £7.90
Ayrshire Growth Deal - £9.18 £8.88 £5.96 £10.49
Scotland - £12.22 £11.84 £7.97 £13.96
Person Years of Construction
Employment
Present Value of Net Additional
Construction GVA
Benefit Cost Ratio
Full-time Equivalent Jobs
Present Value of Net Additional
Operational GVA
PV of GHG Carbon Accounting

Page 105

NAC Growth and Investment 
AGD Business Case 
99 
Table 27: BCRs with Construction Impacts Removed 
Construction Benefits:
• Construction-related benefits are temporary as they only occur during the
construction period of a project. This results in person years of employment (PYE)
being created for construction jobs, rather than full-time equivalent (FTE) jobs.
Outputs are based solely on construction-related expenditure.
• Local authority-level socioeconomic data on turnover per employee and productivity
per employee (measured as gross value added per employee) are used to calculate
the PYE the construction-related expenditure creates and the output (GVA) that each
worker produces.
• Additionality assumptions including leakage, displacement, deadweight, and type ii
economic multipliers are then applied to estimate the net direct benefits of
construction-related activity at three geographic levels: local authority, growth deal
area, and national level. Details of these are already provided.
Operational Benefits:
• Operational benefits are realised through the creation of commercial floorspace and
the utilisation of that floorspace in line with recently completed Phase 1 of Flexi
Space. 
• The creation of commercial floorspace generates FTEs dependent on the final use of
the floorspace. Floorspace density coefficients recommended by the Homes &
Communities Agency are used to derive the number of FTEs per metre-squared (m2)
of floorspace created. These vary depending on the type of floorspace created – with
higher density classifications, like call centres, generating more FTEs than lower
density classifications, such as warehouses. For this Phase of Flexi Space the focus
is upon the creation of light industrial space. 
• The latest local socioeconomic data on employee productivity are then applied to the
FTEs created to calculate the economic benefit of the floorspace occupied. These
benefits are assumed to continue throughout the appraisal period selected and are
subject to the additionality assumptions aforementioned in the construction benefits
section.
Present value of monetised benefits and carbon accounting across 5-year periods to watch
the 25-year appraisal time period. 
Project Start Date: Benefit-Cost Ratio Timeframe:
2025 25 Years
2050
Option 1 Single Unit Sub divided Unit Terraced Unit Small Unit + LUF
PV of Total Costs All Geographies £0 £7,654,118 £7,677,791 £7,028,721 £5,386,350
Local Authority £0 £52,889,911 £51,374,336 £31,575,564 £42,551,916
Ayrshire Growth Deal £0 £70,246,516 £68,211,833 £41,856,541 £56,515,423
Scotland £0 £93,547,670 £90,916,429 £56,013,778 £75,208,127
Local Authority - £50,787,804 £49,123,984 £29,511,105 £40,989,946
Ayrshire Growth Deal - £67,577,173 £65,354,242 £39,235,006 £54,531,968
Scotland - £89,268,380 £86,335,353 £51,811,130 £72,028,400
Actual 0 £39,735 £38,001 £8,963 £30,329
Net Impact - £39,735 £38,001 £8,963 £30,329
Local Authority - £6.64 £6.40 £4.20 £7.61
Ayrshire Growth Deal - £8.83 £8.51 £5.58 £10.12
Scotland - £11.66 £11.24 £7.37 £13.37
Present Value of Net Direct GVA
Present Value of Net Additional
GVA
PV of GHG Carbon Accounting
Benefit Cost Ratio

Page 106

NAC Growth and Investment 
AGD Business Case 
100 
Table 42: Profile of Benefits Accrued – 5 Year Periods 
Green House Gas Accounting:
The table below outlines how monetised carbon savings will accumulate and increase
across five-year periods following pathfinder projects delivery. This analysis reflects the
decarbonisation potential of the interventions and long-term value of avoided emissions. This
will provide a clear framework for tracking progress against climate targets and support
evaluation of scalability of pathfinder models. 
Table 43: Green House Gas Accounting 
Inflation Level 
• All monetary values are expressed as a constant price i.e. expressed as “real price”.
The Office of National Statistics (ONS) publishes time series data for a series of price
indices, and we apply the Gross Domestic Product (GDP) deflator to present all
figures in constant prices. Note that this treatment of financial values differs from the
Financial Case. The financial case presents “nominal prices” with a 2% inflationary
rate applied. 
• The Social Time Preference Rate (STPR) has been applied at 3.5% to discount
monetary values. This rate decreases to 3% after 30 years as per HM Treasury
guidance. 
• Confirmation that BCEM utilises the latest estimates of CPI and GDP deflators
sourced from the ONS and Office for Budget Responsibility. At the time of the
modelling exercise the latest sources for each were:
GDP deflators at market prices, and money GDP September 2024 (Quarterly National
Accounts) – GOV.UK
Consumer price inflation, UK – Office for National Statistics
Distributional Analysis 
• A quantitative distributional analysis (i.e. employing welfare weighting – relative value
of jobs/income based on their geographic distribution) has not been carried out,
though distributional impacts have been considered. This project by nature has not
been designed to have specific distributional impacts on any demographic.
Additionality
• Additionality assumptions including Leakage, Displacement, Deadweight, and Type II
Economic multipliers are applied to estimate the Net Direct benefits of each
shortlisted option. Additionality assumptions have been disaggregated between both
the Construction and Operational activity taking place within the project area –
providing a greater assessment of the net additionality of the project than applying a
blanket set of assumptions across each project element.
2030 2035 2040 2045 2050
Single Unit £2,102,108 £2,102,108 £2,102,108 £2,102,108 £2,102,108
Sub divided Unit £2,250,353 £2,250,353 £2,250,353 £2,250,353 £2,250,353
Terraced Unit £2,064,459 £2,064,459 £2,064,459 £2,064,459 £2,064,459
Small Unit + LUF £1,561,971 £1,561,971 £1,561,971 £1,561,971 £1,561,971
Present Value of Construction-related Benefits - Local Authority
2030 2035 2040 2045 2050
Single Unit £20,789 £34,261 £37,837 £39,097 £39,735
Sub divided Unit £19,055 £32,528 £36,104 £37,364 £38,001
Terraced Unit £4,227 £7,595 £8,489 £8,804 £8,963
Small Unit + LUF £16,682 £26,386 £28,962 £29,870 £30,329
Present Value of GHG Accounting - Local Authority

Page 107

NAC Growth and Investment 
AGD Business Case 
101
• Leakage, Displacement, Deadweight, and Type II Economic multipliers have been
informed through discussion with the project team who hold local knowledge and
similar development across Scotland.
List of additionality assumptions have been used which incorporates displacement, leakage,
economic multipliers and deadweight at each geographic level for relevant appraisal criteria.
Details of the assumptions made are included within this Appendix. 
Conclusion and Quantitative Benefits 
The key findings are as follows: 
Option 1: Do nothing/minimum status quo
Do Nothing 
Option 2: Single Unit: 
• Creates 49 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 79 person years of employment in the Construction sector (Scotland) 
• Supports 26 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £67.318m in net additional GVA over 25 years, £2.669m when
construction impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a of £9.18:£1 Benefit-Cost Ratio (Ayrshire Growth Deal Region) 
Option 3: Sub Divided Unit: 
• Creates 53 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 84 person years of employment in the Construction sector (Scotland) 
• Supports 25 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £64.990m in net additional GVA over 25 years, £2.857m when
construction impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a of £8.88:£1 Benefit-Cost Ratio (Ayrshire Growth Deal Region) 
Option 4: Terraced Unit:
• Creates 39 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 49 person years of employment in the Construction sector (Scotland) 
• Supports 16 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £38.896m in net additional GVA over 25 years, £2.621m when
construction impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a positive rate of return through a £5.96:£1 Benefit-Cost Ratio
(Ayrshire Growth Deal Region)

Page 108

NAC Growth and Investment 
AGD Business Case 
102
Option 5: Small Unit within LUF3 Cost Envelope 
• Creates 36 person years of employment in the Construction sector. (Ayrshire Growth
Deal Region)
• Creates 58 person years of employment in the Construction sector (Scotland) 
• Supports 20 full-time equivalent jobs through commercial development. (Ayrshire
Growth Deal Region) 
• Generates £54.293m in net additional GVA over 25 years, £1.983m when
construction impacts removed. (Ayrshire Growth Deal Region) 
• Demonstrates a positive rate of return through a £10.49: £1 Benefit-Cost Ratio
(Ayrshire Growth Deal Region) 
The BCR figures used for comparison purposes of the options are those excluding
construction impacts, as set out in Table 27. This approach ensures consistency with
appraisal guidance and allows for a like-for-like comparison across options. 
In addition to the quantitative benefits noted above, the following qualitative benefits will be
achieved through investment in Phase 2: 
Qualitative Benefits Appraisal 
The qualitative benefits were considered by the project team to evaluate the benefits.
Delivery of the Phase 2, will deliver the following: 
Table 30: Qualitative Benefits Criteria
Objectives Qualitative Benefits, Flex Space Programme  Flex Space 
Phase
Weight  
1 2 %
7. To create flexible
business space capable
of meeting
manufacturing
requirements for
chemical and life
sciences, but also for a
wide range of other high
value sectors.
• New business units will be occupied by Ayrshire/ Scottish/
UK/ overseas businesses   20
• Created/safeguarded jobs will generate economic value –
jobs, GVA, turnover for Ayrshire and Scotland  
• Supply chain outcomes will be created for other Ayrshire
and Scottish businesses  
• Design and construction contracts will generate turnover
for Ayrshire and Scottish contractors  
• Construction jobs and training outcomes will be created,
primarily for Ayrshire people and particularly drawn from
disadvantaged or Protected Characteristic groups.
 
8. Create a centre of
digital innovation which
offers digital tools,
support and innovation
scaled to a national
market supporting a
restructure of the
regional economy to
deliver advanced
manufacturing. 
• University and College presence at i3 offering training and
business development opportunities.  
20
• Cluster of R&D and spin off opportunities  
• Providing employment, skills development, community
wealth building and supply chain growth opportunities
 
• Providing the private sector with opportunities for
upskilling, business transformation and increased
productivity
 
9. To create serviced
industrial land and
capable of immediate
development.
• Development plot will be available for indigenous Ayrshire/
Scottish, UK-owned and foreign investors
ü ü 10
• Design and construction contracts will generate turnover
and jobs for Ayrshire and Scotland
ü ü

Page 109

NAC Growth and Investment 
AGD Business Case 
103
Objectives Qualitative Benefits, Flex Space Programme  Flex Space 
Phase
Weight  
1 2 %
10. To create
opportunities for
employment and
inclusive growth with
particular emphasis on
making connections to
local communities,
schools and colleges in
preparation for
employment, particularly
in areas of deprivation.
• New employment outcomes – direct and indirect through
supply chains  
20
• Work experience and training places for school and
college student.
ü ü
• Job market entrants and low skilled workers  increasing
soft and basic skills through provision of local jobs. 
ü ü
• Residents of deprived areas gaining access to
opportunities 
• University presence enabling additional educational and
training opportunities 
ü ü
• Delivery of enhanced public transport connection that
opens up employment opportunities  
11. To attract mobile
and private sector
investment both from
abroad and from
indigenous companies.
• New employment and training outcomes   15
• Demonstrate attractiveness of Scotland as excellent location
for life sciences manufacturing
 
• Increased investment confidence  
12. To create a
sustainable, high quality
business location and
R&D cluster, capable of
meeting and keeping
pace with the changing
demands of high value
manufacturing sectors
and complementing
national initiatives
including NMIS 
• Enhancement and maintenance of attractiveness of
Ayrshire as a location, meeting modern business needs
and promoting Industry 4.0 services. 
ü ü 15
• Large, visible and modern development that clearly
shows Ayrshire is Open for Business 
ü
• Recognised as part of a national strategy for improving
digital technology   
Economic Modelling Conclusion – Delivery of Phase 2
In conclusion, Option 2, the delivery of a Single Unit provides the greatest economic
benefits.  
Beyond the economic metrics, this approach delivers transformative benefits such as the
wider infrastructure provided for the site, the opportunity for training placements and
engagement with local schools e.g. through the STEM curriculum and towards the
completion of a cluster of modern industrial space within a central are of i3.

Page 110

NAC Growth and Investment 
AGD Business Case 
104
APPENDIX E: RISK REGISTER 
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
I3FL-R01
(IP)
SCOPE
Outputs &
Outcomes 
Anticipated outputs and outcomes
are not delivered.
3 3 9 Ensure BC addresses sensitivity of outcomes 
Clear Evaluation & Monitoring Framework 
Maximise outcomes through project suppliers
NAC /
Contractor 
Amber 
I3FL-R02 QUALITY 
Outputs &
Outcomes 
The project fails to achieve more
inclusive growth and/or reduce
poverty by increasing the income of
people in deprived areas or
protected characteristic groups
3 5 15 Benefits Realisation Plan prepared to identify
targets. 
NAC  Red
I3FL-R03 SCHEDULE 
Timescales /
Programme 
Delays to overall project
programme and key milestones
3 3 9 Prepare a detailed project programme with
considered time allowances and review
regularly.  
Delivery
Team 
Amber 
I3FL-R04
(IP)
SCHEDULE 
Timescales /
Procure-
ment 
Delays to the submission or
approval of business cases or the
progress of tender procurement,
causes delays to the award of
contracts for flex space and the
progress or claiming AGD spend or
the Local Regeneration Fund.
4 3 12 Seek early agreement on appropriate
procurement routes 
Include anticipated tender packages within
the Council’s Procurement Wave Plan 
Spend aligned against related funding source
deadlines 
Ensure sufficient timeline allocated to
evaluation tender
Ensure response, evaluation and governance
process programme to enable swift progress
to award
NAC  Amber 
I3FL-R05 Timescales /
Environmen
t
Delays caused by environmental
considerations
3 5 15 Protected Species/Habitat risk has been
assessed at an early stage. 
Review of site studies required at key stages. 
NAC  Red

Page 111

NAC Growth and Investment 
AGD Business Case 
105
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
Ensure seasonal work/study requirements are
accounted for in programme.  
I3FL-R06 Timescales /
Environ-
ment 
Delays caused by site investigation
work and findings
3 5 15 Instruct SI work at early stage of project    NAC  Red
I3FL-R07 Timescales /
Regulatory 
Delays caused by objections 2 4 8 Advance programme of local & stakeholder
engagement.  
NAC  Amber 
I3FL-R08
(IP)
SCHEDULE
Timescales /
Regulatory  
Delays caused by statutory consent
processes
3 2 6 Zoned & allocated site 
Pre-App discussion with NAC Planning Assess
protected species/habitat risk at early stage
Review planning challenge/appeals
Agree programme for consents 
Advance programme of local stakeholder
engagement  
NAC  Amber 
I3FL-R9
(IP)
SCHEDULE
Timescales /
Regulatory 
Delays caused by land assembly /
lease agreement processes.
2 2 4 Early engagement with owners. 
Ensure programme allows for third party
approvals.
Phase 3 layout has been developed to reduce
requirement for private land.   
NAC / SE  Amber 
I3FL-R10
(IP)
SCHEDULE
Timescale /
Contractor
Delays during project construction
phases.
3 3 9 Regular monitoring through site meetings and
reports 
Ensure emphasis through programme analysis
and approach included in tender
documentation and evaluation.
Contractor Amber
I3FL-R11
(IP)
INTERNAL
RESOURCES
Timescale /
Staff resources not sufficient to
manage projects as they develop.
3 2 6 Risk has reduced as vacant post has been
filled, although impact has been significant on
pushing out delivery timelines for projects.  
NAC /
Consultant
s /
Contractor 
Amber

Page 112

NAC Growth and Investment 
AGD Business Case 
106
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
Business /
Professional
I3FL-R12 Regulatory  Planning/building warrants are not
granted.
2 5 10 LDP supports development of site for this use.
Ensure local members briefed/updated on
project. 
Hold pre-app discussion with NAC Planning
Assess Protected Species/Habitat risk 
Formally agree programme for consents 
Advance programme of stakeholder
engagement  
NAC  Amber 
I3FL-R13
(IP)
Regulatory  Compliance Subsidy regulations. 1 2 3 Regular monitoring and if required, contact
with Subsidy Unit to ensure no specific risks
arising related to subsidy, due to nature of
the project.  
NAC Green
I3FL-R14 Financial  Design and technical studies result
in additional costs beyond the
contingencies and optimism bias
allowed for. 
3 4 12 Develop and validate project briefs and
specifications for each phase
Benchmark costs. 
Ensure early infrastructure cost tested and
informed by SI work. 
Provide Optimism Bias allowances compliant
with Green Book
Provide for contingency & inflation.  
NAC /
Design
Team 
Amber 
I3FL-R15 Financial  Slippage / delay in the programme
incurs additional costs.
3 5 15 Instruct appointed project team to address
this within Risk Register. 
Selected procurement route will seek to
ensure contract type has less risk for client.  
NAC /
Contractor
Red

Page 113

NAC Growth and Investment 
AGD Business Case 
107
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
I3FL-R16  Financial  There are unforeseen project
complexities that require additional
funding.
2 4 8 Provide for contingency 
Provide Green Book compliant Optimism Bias
allowances. 
Similar project has been delivered previously.  
NAC  Amber
I3FL-R17  Financial  Rental income lower than forecast 2 3 6 Market review and comparator analysis to
identify appropriate rent but ultimately down
to actual market demand on completion.
NAC  Amber
I3FL-R18 Financial  Lack of budget to support
interested tenants to fit out shell of
building
4 3 12 Identify at an early stage and with Business
Growth Team, how this can be supported.   
NAC  Amber
I3FL-R19 Financial  Lack of budget to support
maintenance of buildings until
tenants take occupancy, if buildings
are classified and non -operational.
2 2 4 Identify at an early stage with Finance and
Estates, how this can be supported.   
NAC  Amber
I3FL-R20 Professional  Lack of project management
experience.
2 3 6 Ensure experience project management team,
both in-house and any external support. 
Budget allows for appointment of required
expertise.  
NAC  Amber
I3FL-R21 Professional  Poor change management
procedures.
2 3 6 Clear and agreed procedures set in place for
internal change management and for external
processes with design team and contractor.  
NAC /
Contractor
Amber
I3FL-R22 Professional  Specification – design issues on-site 2 4 8 Adopt best practice design and ensure
flexibility for subsequent division/ alteration
of premises.  
NAC /
Consult-
ants /
Contractor 
Amber

Page 114

NAC Growth and Investment 
AGD Business Case 
108
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
I3FL-R23 Contractual
/ Political 
Failure to deliver community
benefits – training, employment
3 4 12 Incorporate appropriate community benefits
into contract terms and resource
appropriately
NAC /
Contractor 
Amber 
I3FL-R24 Contractual  Issues with co-ordination on-site -
contracts, visitors
2 4 8 Ensure main contractor has appropriate
procedures for site management
Contractor Amber 
I3FL-R25
(IP)
QUALITY 
Reputat-
ional /
Political 
The Flexible Space Programme’s Full
Business Cases fail.
3 2 6 Development of OBC/FBC in accordance with
Green Book
Flex Space OBC approved June 21
Flex Space Ph1 FBC approved Dec 22
Review capex and opex costs 
Partner/stakeholder risk assessment 
Early market input / partner & commercial
input
Review governance arrangements.
NAC  Amber 
I3FL-R26
(IP)
QUALITY 
Reputat-
ional 
Demand for the Flex Space
Programme diminishes and there is
no interest from occupiers.
3 2 6 Flexible design to maximise potential interest
from occupiers. 
Marketing and promotion of floorspace
Continue to establish relationships with
national sectors (incl NMIS) 
Interest in Phase 1 has confirmed market
interest and reduced risk
Review of Ph2&3 prepared by property
agents.
NAC  Amber
I3FL-R27 Reputat-
ional 
Market expectations are not met. 2 5 10 Scale/ quality/ design based on identified
market needs
Recent research has established demand. 
Continue to review demand and business
needs with Partners including SE and SDI.
NAC  Amber

Page 115

NAC Growth and Investment 
AGD Business Case 
109
AYRSHIRE GROWTH DEAL RISK REGISTER:   i3 ADVANCED MANUFACTURING SPACE 
Full Business Case, Phase 2, 08 April 2026       
(IP) denotes risks within Implementation Plan 
Risk
Code 
Risk Type Risk Description  Likeli-
hood
Impact Risk
Score
Internal Controls / Counter Measure Owner Status
Involve relevant business engagement
partners.
I3FL-R28 Reputat
ional 
Businesses interested in units
decide not to progress
3 5 15 Ensure ongoing engagement with businesses
to prepare suitable Heads of Terms. 
NAC  Red 
I3FL-R29
(IP)
EXTERNAL Project delays due to external
economic impacts such as COVID-19
and recovery.
4 2 8 Early analysis has identified that the need for
this project is unlikely to be diminished and in
fact may be even greater. 
Analysis of external factors will be monitored
that area likely to impact on the project.
NAC  Amber 
I3FL-R30
(IP)
EXTERNAL Proposals become unaffordable and
there are cost overruns.
4 3 12 Regular review of design vs budget, value
engineering and impact of market conditions
on costs
Benchmark costs
Ensure early infrastructure cost tested
/informed SI
Provide for contingency and Green Book
compliant optimism bias allowances 
Ensure project approval processes are in place
to control budget compliance
Pursue additional funding sources.  
NAC  Amber 
I3FL – R31
(IP)
Timescales /
Financial 
Existing and proposed utilities cause
issues or delays e.g. surface water
drainage connections, sub-station
requirements.
3 3 9 Ensure exact locations of existing
infrastructure identified
Early engagement with SPEN, Scottish Water,
BT etc. 
Testing to be carried out and capacity to be
confirmed for water supply 
Amber

Page 116

NAC Growth and Investment 
AGD Business Case 
110
APPENDIX F: INCLUSIVE GROWTH & COMMUNITY WEALTH BUILDING 
I3 Flexible Advanced Manufacturing Space: Inclusive Growth and Community Wealth Building 
Inclusive Growth
Ambition/Objective  How?  IG Barrier IG Action Plan  CWB pillar CWB theme Equalities/
Excluded Group
Increase in GVA
across region
Deliver modern, flexible business
space to provide space to market
(65,000 sq ft)
Intermediate &
Advanced Skills, 
Structure of
economy,
Advanced digital
skills, 
Business premises
Inward investment
Maximising benefits for
Ayrshire’s business base.
Maximising benefits for
people – Fair Work.
Maximising benefits for
places/communities. 
Fair
employment 
Land and assets
Promote our
investment
opportunities to
regional and national
institutions to gain
investment in our
communities 
Expenditure in R&D
per head 
Deliver modern business space
which attracts investment from firms
spending in R&D
Structure of economy 
Advanced digital skills 
Business premises
Maximising benefits for
Ayrshire’s business base.
Maximising benefits for
people – Fair Work.
Maximising benefits for
places/communities. 
Fair
employment 
Land and assets
Promote our
investment
opportunities to
regional and national
institutions to gain
investment in our
communities 
Employment
Opportunities 
Create employment opportunities
for groups that most need them eg
disadvantaged groups and protected
characteristic groups including
women and young people. Detail
requirements through Community
Benefits in procurement packages. 
Work with partner organisations to
facilitate recruitment of excluded
groups. 
Intermediate &
Advanced Skills, 
Structure of
economy, 
Maximising benefits for
people – Fair Work.
Maximising benefits for
places/communities. 
Fair
employment 
Procurement 
Promote our
investment
opportunities to
regional and national
institutions to gain
investment in our
communities 
Improving skills 
Creating pre-employment learning
pathways for identified priority
groups eg females, living in Ayrshire. 
Support skills needs of businesses
taking space within i3. 
Intermediate &
Advanced Skills, 
Structure of
economy,
Advanced digital
skills, 
Maximising benefits for
people – Fair Work.
Maximising benefits for
places/communities.
Fair
employment 
supporting in work
progression, and
training and skills
pipeline

Page 117

NAC Growth and Investment 
AGD Business Case 
111
APPENDIX G: COMMUNITY BENEFIT STATEMENT 
AGD Business Cases – Regional Community Benefits Statement 
Community Benefits 
Community Benefits have been a key component of public procurement policy and practice in
Scotland for more than ten years.   
To embed best practice and drive public bodies to consider Community Benefits clauses in
procurement, The Procurement Reform (Scotland) Act 2014 established a national legislative
framework for sustainable public procurement that supports Scotland’s economic growth through
improved procurement practice.   
The Reform Act requires public bodies, including Ayrshire Growth Deal (AGD) Partners, to consider
how their procurement activity can improve the economic, social and environmental wellbeing of
their communities. 
Community Benefits are one of a range of social and environmental requirements that can be included
in public contracts, contributing to national outcomes on sustainability including, but not limited to,
employment, learning, skills, supply chain development and community engagement. 
Contractors, suppliers and Service Providers appointed through AGD projects must demonstrate their
organisations’ commitment to providing Community Benefits within Ayrshire, over and above their
obligations to deliver on the core purpose of a contract. 
In accordance with guidance of the Reform Act and always in a relevant and proportionate manner,
applicable appointments, through AGD projects, which require procurement activity, will be subject
to Community Benefits requirements. 
Community Benefits Themes 
Through their separate procurement activities and where possible, AGD Partners are committed to
assisting both young and unemployed people by encouraging access to quality sustainable
employment and providing skills and training opportunities.  Organisations appointed to AGD projects
must therefore be able to demonstrate their commitment to integrate trainees and long-term
unemployed persons into the labour market, without distinction to sex, marital status, race, ethnic
origin or political or religious beliefs. 
AGD projects will also bring together an extensive range of experienced Professionals who, with
minimal sacrifice of time, could provide useful learning and knowledge exchange opportunities for
various groups of people in our Ayrshire communities and over a wide range of subject areas and

Page 118

NAC Growth and Investment 
AGD Business Case 
112
expertise. Organisations appointed to AGD projects must therefore be able to demonstrate their
commitment in providing learning opportunities across the wider Ayrshire community. 
Community Benefits pledges from AGD projects should also have a focus on supporting and
developing Ayrshire’s existing business base and building on this with the aim of increasing the
number of new business start-ups and growing sustainable businesses.  The long-term sustainable
development of Ayrshire’s SME business base is vital and AGD Partners recognise the need to support
the development of the SME sector through the use of a procurement approach which maximises SME
exposure to procurement opportunities. 
As such and through the procurement phases of any AGD project, contracting organisations will be
asked to consider the following objectives when committing to the delivery of Community Benefits: 
• Improving Education and Skills.  For example, creation of apprenticeships or delivering
knowledge exchange and presentations in schools or community groups.
• Improving Local Employability. For example, creation of new jobs, recruitment of the long-
term unemployed, disadvantaged or young people. 
• Work Experience Placements/Programmes.  For example, providing work experience
placements to those in education.
• Delivering Training and Development in the Community.  For example, mentoring - private
sector suppliers can offer support, normally as part of their CSR activity, where they can offer
training and guidance to local organisations and individuals.
• Community Consultation - giving the local community an opportunity to express an opinion
and possibly influence the design and delivery of a project or service in an area.
• Enhancing & Improving Local Community and Environmental Projects.  For example, providing
volunteers or donations to local initiatives.
• Sponsorship and Charity Work
• Supply Chain, Supported Business, Third Sector and Voluntary Initiatives.  For example,
offering Small and Medium Enterprises and Voluntary Sector organisations opportunities to
provide goods, works and/or services as part of a contract. 
Tracking & Reporting Community Benefits 
Organisations who are successful in being awarded a contract through an AGD project will have their
Community Benefits pledges evaluated on an ongoing basis, throughout the duration of their contract
and through each of the AGD Partners’ contract management procedures, using a shared Community
Benefits tracking system. 
Along with providing an excellent, flexible and accessible record of business information for those
organisations appointed to Growth Deal projects, the AGD Partners’ shared, online Community
Benefits Tracker will ensure a consistent approach is applied to the monitoring of Community Benefits
pledged through AGD procurement.

Page 119

NAC Growth and Investment 
AGD Business Case 
113
APPENDIX H: EQUALITY IMPACT ASSESSMENT 
Ayrshire Growth Deal
Equality Impact Assessment including Fairer Scotland Duty 
Equality Impact Assessment is a legal requirement under the Public Sector Duty to promote equality of the Equality Act 2010. Separate
guidance has been developed on the Equality Impact Assessment’s which will guide you through the process and is available to view here:
https://www.equalityhumanrights.com/en/publication-download/assessing-impact-and-public-sector-equality-duty-guide-public-authorities/ 
The Fairer Scotland Duty (‘the Duty’), Part 1 of the Equality Act 2010, came into force in Scotland from 1 April 2018. It places a legal
responsibility on Councils to actively consider (‘pay due regard to’) how we can reduce inequalities of outcome caused by socio-economic
disadvantage, when making strategic decisions. Interim Guidance for Public Bodies in respect of the Duty was published by the Scottish
Government in March 2018.
Please note that the term ‘project’ is used throughout and applies to policies, strategies, provisions, criteria, functions, practices, budget savings
and activities, including the delivery of services. 
If you require assistance please contact: 
North Ayrshire Council Andrew Hale  andrewhale@north-ayrshire.gov.uk 
Section One: Project Details* 
Name of Project I3 Flexible Advanced Manufacturing Space 
Lead Officer (Name/Position)  Marnie Ritchie, Manager, Growth and Investment 
Support Team (Names/Positions)
including Critical Friend
Growth and Investment Team, North Ayrshire Council 
What are the main aims of the
project?
To deliver approximately 6,000m2 of advanced manufacturing space at i3 over a number of phases, to meet
market demand in an area of market failure and to complement AGD investment in the Digital Process
Manufacturing Centre (DPMC) at i3, in partnership with NMIS and CPI - creating an overall cluster of research,
innovation, accommodation and services for industry and business.  
What are the intended outcomes
of the project
The intended outcomes of the project are the delivery of much needed modern business space, new jobs and
construction jobs, supported SMEs, additional GVA, access to related employability and skills programmes for
local people and removal of sites from the vacant and derelict land register.

Page 120

NAC Growth and Investment 
AGD Business Case 
114 
Section Two: What are the Likely Impacts of the Project? 
Will the project impact upon all three Ayrshire Council
areas or a specific council area and/or particular groups
within the population (please specify the equality groups)
The project has the potential to impact on all three Ayrshire Council areas but mostly
North Ayrshire. It has the potential to positively impact on particular groups in terms of
opportunities for employment and training for disadvantaged people or people within
Protected Characteristic groups. 
Consider the ‘Three Key Needs’ of the Equality Duty 
Which aspects of the project eliminate unlawful discrimination, harassment and victimisation?
Which aspects of the project advance equality of opportunity between people who share a relevant protected characteristic and
those who do not?
The project is about creating new business space, therefore due to the nature of the project, it is not considered that this key need is relevant to the
project. However, the modern design of the buildings and the site will take account of people that have disabilities in a way that existing ageing
business space may not. 
• The design of the project space will be modern and fully accessible, complying with EA 2010 standards and enabling potential employees or
trainees that are mobility impaired or disabled to access the buildings and the surrounding space. 
• The procurement process for the buildings will require construction companies to provide opportunities for trainees and job seekers from
disadvantaged or Protected Characteristic groups. For Phase 1 of the project, contractor Muir Group worked with CEIS Ayrshire to support a
young person from the local area who had been unemployed for approximately 6 months, moving from a work experience placement to a
full-time site labourer for the duration of the contract. 
• Businesses that occupy the space will be encouraged by the Council and its partners to create employment/skills development/ learning
opportunities for people in disadvantaged or Protected Characteristic groups. Phase 1 has only recently been let so and update can be
provided in due course.  
• It is intended that the project will seek to improve active travel links to the site, to make the location more accessible to people without
access to a car and who may be reliant on affordable and accessible public transport services. Active travel route improvements have
recently been made in close proximity to the i3 AGD investment site along Long Drive, linking to Riverside Way, providing wider shared
surface footways and crossing points towards key public transport routes.

Page 121

NAC Growth and Investment 
AGD Business Case 
115
Which aspect of the project foster good relations between people who share a protected characteristic and those who do not? (Does
it tackle prejudice and promote a better understanding of equality issues?) 
Have any cross-cutting impacts been identified from other Council Services or Partner Agencies? (Multiple discrimination or
accumulated effects of multiple proposals on a protected characteristic group) 
Island Proofing  
Island Proofing is about considering the particular needs and circumstances of island communities when public sector organisations exercise
their functions and make decisions.  This process includes a range of issues such as access to services, digital connectivity, employment and
access to education; transport and access to goods and services. 
The project is focussed on a specific location at i3 Business Park in Irvine. It is not considered that the particular needs and circumstances of island
communities would be detrimentally affected by this particular project. 
Considering the following Protected Characteristics and themes, what likely impacts or issues does the project have for the group or
community?   
Please outline evidence in relation to impacts identified. List any likely positive and/or negative impacts. If negative impacts are
identified, can these be mitigated or lessened? 
If you require further information in relation to evidence, the Equality Evidence Finder brings together the latest statistics and research
for Scotland across different themes for age, disability, ethnicity, gender, religion, sexual orientation, socio-economic status and
transgender status. 
The Equality Evidence Finder is updated monthly with a summary of the key official statistics, social research and National
Performance Framework equality analysis. Links to further datasets, statistics and research are provided to help find the full range of
available equality evidence for Scotland.
The design of the buildings and job/skills/training opportunities for protected characteristic groups will help tackle prejudice and promote a better
understanding of equality issues, through the integration of these requirements as standard practice. 
No cross-cutting impacts have been identified at this stage.

Page 122

NAC Growth and Investment 
AGD Business Case 
116
Protected Characteristics Evidence Positive/Negative
Impacts
Mitigating
Factors
Age:  Issues relating to different age groups
eg older people or children and young people
Young people are particularly
excluded from manufacturing growth
areas.  
Opportunities through NAC’s
Employability team to sign post
people seeking employment to
contract opportunities.   
Disability: Issues relating to disabled people  Limited access to employment
opportunities due to limited scope to
work in ageing industrial buildings and
limited access to transport to i3. 
Modern design standards will
ensure this is no longer an
issue. 
Gender Reassignment –
Trans/Transgender: Issues relating to
people who have proposed, started or
completed a process to change his or her sex
No issues identified.   
Marriage and Civil Partnership:
Issues relating to people who are married or
are in a civil partnership
No issues identified.   
Pregnancy and Maternity: Issues relating to
woman who are pregnant and/or on maternity
leave
No issues identified. 
Race: Issues relating to people from different
racial groups,(BME) ethnic minorities,
including Gypsy/Travellers
No issues identified.  
Religion or Belief: Issues relating to a
person’s religion or belief (including non-
belief)
No issues identified.  
Sex: Gender identity: Issues specific to
women and men/or girls and boys 
Women are particularly excluded from
manufacturing growth areas.
Opportunities through STEM
Engagement with local schools
to encourage more girls to
consider certain careers. 
Sexual Orientation: Issues relating to a
person’s sexual orientation i.e. LGBT+,
lesbian, gay, bi-sexual, heterosexual/straight
No issues identified.  
Children’s Rights Issues and impacts
affecting children’s rights*
No issues identified.

Page 123

NAC Growth and Investment 
AGD Business Case 
117
Protected Characteristics Evidence Positive/Negative
Impacts
Mitigating
Factors
*for more information please email – 
andrewhale@north-ayrshire.gov.uk
Health
Issues and impacts affecting people’s health
No issues identified. Wider improvements to active
travel infrastructure enabling
people to walk/cycle/wheel to i3. 
Human Rights: Issues and impacts affecting
people’s human rights such as being treated
with dignity and respect, the right to
education, the right to respect for private and
family life, and the right to free elections.
No issues identified.   
Fairer Scotland Duty – Socio Economic Disadvantage 
Evidence Positive/Negative Impacts Mitigating Factors
Low Income/Income Poverty:
Issues: cannot afford to maintain
regular payments such as bills,
food and clothing. 
No relevant issues identified.  
Low and/or no wealth: Issues:
enough money to meet basic
living costs and pay bills but
have no savings to deal with any
unexpected spends and no
provision for the future 
No relevant issues identified.  
Material Deprivation: Issues:
being unable to access basic
goods and services i.e. financial
No relevant issues identified.

Page 124

NAC Growth and Investment 
AGD Business Case 
118 
Section Three: Evidence Used in Developing the Project 
Involvement and Consultation
In assessing the impact(s) set out above what evidence
has been collected from involvement, engagement or
consultation?
Who did you involve, when and how? 
Data and Research
In assessing the impact set out above what evidence
has been collected from research or other data.  Please
specify what research was carried out or data collected,
when and how this was done. 
Research by Ryden property consultants on demand for commercial space
across Ayrshire and within North Ayrshire. 
Advice from Graham and Sibbald property agents.  
Inward investment inquiries related to available industrial / commercial space or
land to build space, including referrals from Scottish Enterprise. 
Inquiries from local companies seeking to move in order to expand their business
premises.   
Partners data and research Please see above 
products like life insurance,
repair/replace broken electrical
goods, warm home,
leisure/hobbies 
Area Deprivation: Issues:
where you live (rural areas),
where you work (accessibility of
transport) 
Accessibility and affordability of
transport to i3. 
Access to I3 Enterprise Area is
currently limited by public
transport. 
Active travel improvements
(walking/cycling/wheeling) made
from i3 AGD investment site to
public transport routes. 
Action to progress discussions
with public transport provider
to consider improved services. 
Outcome of discussions with
public transport provider
required that improved public
transport to i3 would require
subsidy until there was a level
of demand for the service.
This will be reviewed once the
i3 Flexible Space buildings are
occupied.

Page 125

NAC Growth and Investment 
AGD Business Case 
119
In assessing the impact(s) set out in Section 2 what
evidence has been provided by partners?
Please specify partners 
Gaps and Uncertainties
Have you identified any gaps or uncertainties in your
understanding of the issues or impacts that need to be
explored further? 
No 
Section Four: Detailed Action Plan to address identified gaps in:
a) evidence and 
b) to mitigate negative impacts 
Note: Please add more rows as required. 
Section Five - Performance monitoring and reporting
Considering the project as a whole, including its equality and diversity implications:
No. Action  Responsible Officer(s)  Timescale
1 Ensure the proposed build space and general project location is fully
accessible and where appropriate, compliant with EA2010. 
Project Designers  Over the course of
the various phases
of the project. 
2 Progress discussions with public transport provider 
Discussions have taken place which require that there must be sufficient
demand for an improved bus service, otherwise the route will require to be
subsidised. It is too early in the project for there to be further demand as
the Phase 1 building is not yet occupied.  
AGD Project Lead  December 2022
Review position by
December 2026
3 Develop initiatives with colleagues and other Council teams to ensure
young people and women will benefit from the project.
For Phase 1, Muir Group employed a young unemployed person and made
links with Auchenharvie Academy for STEM engagement activities. 
AGD Project Lead  Over the course of
the various phases
of the project.
When is the project intended to come into effect? The project has started and will be delivered in a series of phases. 
When will the project be reviewed? At various Gateway Stages and at each Phase.
Which Panel will have oversight of the project? The Project Board and particular Gateway Review meetings. 
NAC’s Executive Leadership Team.

Page 126

NAC Growth and Investment 
AGD Business Case 
120 
Section 6 
Ayrshire Growth Deal   
Summary Equality Impact Assessment Implications & Mitigating Actions 
Name of Project:  i3 Flexible Advanced Manufacturing Space project 
Name of Project Lead: Marnie Ritchie 
Email of Project Lead: marnieritchie@north-ayrshire.gov.uk 
Date of Assessment: original assessment for OBC in Feb 2021, reviewed 07 April 2026 
This project will assist or inhibit the Council’s ability to eliminate discrimination; advance equality of opportunity; and foster good relations as
follows: 
Please see information contained above. 
1. Summary of project aims
2. Summary of how the project will eliminate discrimination
3. Summary of how the project will advance equality of opportunity
4. Summary of how the project will foster good relations
5. Summary of how the project considers Socio-Economic Disadvantage (Fairer Scotland Duty)
6. Summary of how the project considers the needs of island communities
7. Summary of Key Action to Mitigate Negative Impacts
a. Actions and Timescales 
Project Lead:  Marnie Ritchie, Manager, Growth and Investment
Signed:   07 April 2026

Page 127

NAC Growth and Investment 
AGD Business Case 
121
APPENDIX I:  CARBON ANALYSIS 
Item  Project Owner Response
1. Project Name  i3 Flexible Advanced Manufacturing Space 
2. Deal Region  Ayrshire 
3. Brief Description of Project  The provision of flexible advanced manufacturing space
to support business growth and inward investment.  
4. Expected Carbon Emissions
Impact CONTROL Category (1-5)
3 – Cap + then Zero
5. Expected Carbon Emissions
Impact INFLUENCE Category (A-C)
B (i.e. will have a negligible effect on wider carbon
emissions) 
6. Justification of Expected Carbon
Emissions Impact Category e.g. a
short narrative outlining the key
carbon emission sources and their
relationship to capital and
operational net zero following the
Deals Carbon Emissions Impact
Categorisation Process.
Carbon emissions through the construction process to
create new industrial buildings and related access
roads, parking, yard space and sustainable urban
drainage areas. The first phase and phase two have
considered measures at the operational stage to
reduce carbon through the installation of solar roof
panels, EV charging points and suds ponds. 
7. Could the Carbon Emissions
Impact Category be improved?
e.g. from Category 4B to Category
3A
It is expected that 3B will be the highest achievable
rating for the project. 
8. Could the carbon performance of
the project be improved? e.g.
reducing emissions further,
achieving net zero faster.
Yes. The project is being delivered in phases and its
anticipated that further knowledge will be gained as
the project develops, to inform adjustments or
improvements to the design. 
9. How will carbon be managed? e.g.
through PAS 2080: Carbon
Management in Infrastructure for
infrastructure projects or the RICS
Whole Life-Cycle Carbon
Professional Statement for
buildings projects
PAS 2080 – check 
10. What other carbon savings are
expected to result from the
project? e.g. wider carbon savings
across the economy resulting from
project output
The new industrial space created through the project
will provide businesses with the opportunity to benefit
from solar panels and electric charging for vehicles on
each site. The wider site will have a network of suds
ponds and links into a separately funded active travel
network of improvements which provides more
sustainable transport options for travelling to and from
the project site. 
There is also the possibility that future tenants could be
involved in activities that contribute to achieving net
zero.

Page 128

NAC Growth and Investment 
AGD Business Case 
122 
APPENDIX J: AYRSHIRE GROWTH DEAL CHANGE
MANAGEMENT PROCESS