NORTH AYRSHIRE COUNCIL 
2 June 2026 
Cabinet 
Title:    Ayrshire Growth Deal: International Marine Science and
Environment Progress (IMSE) Update 
Purpose:  To provide an update on progress on the International Marine
Science and Environment project, to seek approval for the
strategic direction and to note the development of a
Collaboration Agreement with partners Field Studies Council
and Community of Arran Seabed Trust to support the further
development of the project. 
Recommendation:  That Cabinet: 
a) Notes the progress to date and approves the strategic
direction for the International Marine Science and
Environment project;
b) Notes the development of a Collaboration Agreement with
the Field Studies Council and the Community of Arran
Seabed Trust to progress the project and develop the full
business case; and
c) Notes the progression of the change management
requirements and Outline Business Case for the project,
informed by feedback from the Scottish and UK
Governments. 
1. Executive Summary 
1.1 The International Marine Science and Environment project forms part of the Ayrshire
Growth Deal with an initial commitment of £10.5m investment towards marine
research, education and industry collaboration. This forms part of the wider £251m
investment under the Ayrshire Growth Deal which is a partnership between the UK
and Scottish Governments and the three Ayrshire Authorities. 
1.2 The report provides an update on the progress on the International Marine Science
and Environment project, which has evolved towards a partnership-led, networked
model, maximising outputs and outcomes through collaboration with established
delivery partners, the Field Studies Council and the Community of Arran Seabed
Trust. It seeks approval for the strategic direction and notes the development of a
Collaboration Agreement with the project partners and the draft Outline Business
Case, subject to feedback from the UK and Scottish Governments.

Page 2

2. Background 
2.1 Through the £251m Ayrshire Growth Deal (AGD) investment programme, the UK
Government provided a commitment of £6.5m matched by £4m from North Ayrshire
Council to the International Marine Science and Environment project. This was
through the Energy, Circular Economy and Environment Programme which seeks to
unlock the benefits of developing low carbon energy technologies and solutions. 
2.2 The project aimed to create a world-class centre of excellence to drive innovation in
marine science and establish the Firth of Clyde as an exemplar of marine
sustainability in Scotland’s blue economy. It was originally envisaged that this would
include a flagship building at Ardrossan’s Coastal Quarter managed by a single
University with dedicated staff to promote entrepreneurship and innovation projects
with emerging and established businesses. 
2.3 Since 2020, North Ayrshire Council has explored opportunities to develop a blue
economy innovation programme and associated collaboration opportunities. A pathway
finder analysis report prepared by the University of Stirling in 2021, identified the
potential for a nationally and globally significant blue economy innovation programme. 
2.4 Cabinet approved a timebound Collaborative Agreement with the University of Stirling
and FSC for two years in February 2024. This sought to achieve the submission of an
outline business case to UK and Scottish Government, create a plan of works required
for the creation of the full business case, or phased full business cases, and
corresponding procurement works. Following the sad loss of Dr John Rogers, the
Executive Director of Research, Innovation and Business Engagement, it was
established that the University was no longer in a position to progress with its
anticipated role in project. 
2.5 To advance the concept of the programme and to support the development of a
business case further collaboration has progressed between the Council, Field
Studies Council (FSC) on Cumbrae and Community of Arran Seabed Trust (COAST)
on Arran. This has strengthened the opportunity, providing a cost-effective, lower-risk
delivery route building on existing infrastructure and expertise. This has recognised
that enhancing the existing offering at both locations and forging strong partnerships
could significantly contribute to marine science, and blue economy research,
development, and innovation in the region. 
2.6 Through a programme deliverability review led by the AGD’s Programme
Management Office (PMO), the allocations under the Energy, Circular Economy and
Environment Programme were reviewed to ensure that the identified projects could
achieve their scope and intended outcomes. Further engagement with the UK and
Scottish Governments provisionally confirmed a reapportionment under this
programme increasing IMSE’s UK Government allocation to £11.275m. The formal
approval of this is subject to the submission and approval of the change management
requirements and Business Case. This requires to be progressed through the Ayrshire
Growth Deal’s governance processes. 
2.7 The collaboration with FSC and COAST is being formalised through a Collaboration
Agreement to develop and maintain a partnership supporting the delivery of the IMSE

Page 3

project and business case progression. The partnership will undertake further work to
refine interventions including: 
• Research and analysis;
• Concept design and infrastructure options;
• Development of innovation and challenge-led programmes; and
• Long and shortlisting in line with HM Treasury Green Book requirements. 
2.8 The partners have agreed to contribute up to a maximum of £50,000 to support the
work required by this agreement with roles defined as follows: 
Partner Role(s)
North Ayrshire
Council
Senior Responsible Officer (SRO)
Project Management and Project Management Office Liaison
AGD reporting to Scottish and UK Government
Funder
Business Case development
Growth Deals link (Ayrshire Growth Deal)
Field Studies
Council
Site Operator expertise
Landowner
Academic, innovation and enterprise expertise
Business Case development
Island community engagement on Cumbrae
Community of
Arran Seabed
Trust
Academic, innovation and enterprise expertise 
Business Case development
Island community engagement on Arran 
2.9 Significant progress has been made in advancing the vision, with a strong emphasis
on collaborative planning and strategic alignment with the partners. The project is
being designed to harness the combined strengths of industry, academia, and
environmental organisations. Efforts have concentrated on the co-design of detailed
plans with stakeholders, laying the groundwork for a transformative project that will
drive forward marine science, technology and sustainability. 
2.10 The Outline Business Case (OBC) is being developed in partnership with FSC and
COAST. The proposed approach aligns with national and regional policy priorities and
responds to market failures in the Ayrshire marine sector, where significant economic
potential remains underdeveloped. It positions the region’s marine environment as an
undercapitalised asset and proposes a coordinated cluster linking research
institutions, businesses and communities and offering longer term sustainability. 
2.11 The IMSE project will focus on applied sciences and bring together research and
innovation activities alongside work undertaken by the partners. The project will
support investment in these facilities to strengthen collaborations with universities and
research organisations. These organisations already support significant grant-funded
research and provide a strong foundation for future growth. By fostering collaboration
and investment, the IMSE project will address the current lack of a definable research
hub and limited cross-sectoral working. 
2.12 The preferred option for the project is a networked hub model building on and
enhancing existing assets and the marine science activities delivered at FSC in
Millport and COAST in Lamlash. This offers the best value approach, managing risk

Page 4

while maximising impact. It is anticipated that this approach will deliver strong long-
term value, with benefits significantly outweighing costs and building on existing
research capacity. 
2.13 The IMSE project aims to: 
• Develop a long-term partnership with Scotland’s Universities, the Scottish
Association for Marine Science, Marine Alliance for Science and Technology for
Scotland.
• Grow the number of universities that collaborate with FSC and COAST and use
the facilities at Millport Field Studies Centre and COAST in Lamlash from across
Scotland, the UK and internationally.
• Provide employment and training opportunities for communities and attract
professionals to train, develop new industries and encourage innovation and
investment in Ayrshire.
• Provide educational and vocational training opportunities in partnership with
Glasgow university, other university partners and Ayrshire College as well as
attracting schools from across Scotland.
• Further develop the islands as visitor attractions, build links with the Marine
Tourism project and use existing and new tourist operations to showcase the
island’s research and innovation activities and natural heritage.
• Extend the tourism offer and the average length of stay on Cumbrae by
developing a marine, nature-based and heritage visitor attraction. Longer term
there is an ambition to host training events for working in the blue economy and
tourism sector. 
2.14 Delivery will build on established partner capacity, ensuring confidence and reducing
delivery risk. Procurement will follow established processes, with risks relating to
contractor availability and compliance with subsidy control requirements identified and
managed. The project is affordable within the revised AGD allocation, supporting
investment in infrastructure such as laboratories, accommodation and monitoring
equipment. It is anticipated that the project will deliver significant long-term monetised
and non-monetised benefits, including increased investment in the blue economy, job
creation, reputational gains and improved ecosystem health, building on existing
research activities. 
2.15 The formal approval of the reapportionment of funding under the Energy, Circular
Economy and Environment Programme to IMSE will be progressed through the
Ayrshire Growth Deal’s governance processes. The draft OBC will be updated
informed by feedback from the UK and Scottish Government. Thereafter the final OBC
will be formally submitted to UK and Scottish Government and create a plan of works
required for the creation of the Full Business Case (FBC), or phased FBCs and
corresponding procurement works. 
3. Proposals 
3.1 That Cabinet: 
a) Notes the progress to date and approves the strategic direction for the
International Marine Science and Environment project;

Page 5

b) Notes the development of a Collaboration Agreement with the Field Studies
Council and the Community of Arran Seabed Trust to progress the project and
develop the full business case; and
c) Notes the progression of the change management requirements and Outline
Business Case for the project, informed by feedback from the Scottish and UK
Governments. 
4. Implications/Socio-economic Duty 
Financial 
4.1 There are no financial implications associated with the Collaboration Agreement.
Project development activity related to the proposals may require advance funding
through the Ayrshire Growth Deal, as allocated within approved capital budgets.   
Human Resources 
4.2 None. 
Legal 
4.3 The Collaboration Agreement partnership with the Field Studies Council and
Community of Arran Seabed Trust, has been developed with support from Legal
Services. The draft Outline Business Case has been developed in line with
Government Green Book guidance and subsidy control requirements. 
Equality/Socio-economic 
4.4 An Equality and Children’s Rights Impact Assessment will be undertaken for the project. 
Climate Change and Carbon 
4.5 The ambitions of the project align with the adopted Sustainable North Ayrshire
Strategy. Any statutory requirements related to environmental impact will be
undertaken during the project’s development. In addition, the Ayrshire Growth Deal
business case requirements include carbon scoring and measures to mitigate and
carbon increases. 
Key Priorities 
4.6 The project will contribute to achieving Council Plan priorities and the vision and
priorities of the Ayrshire Regional Economic Strategy. 
Community Wealth Building 
4.7 The project will contribute to the Council’s Community Wealth Building ambitions by
supporting the use of land and assets, supporting job creation and skills and
employability opportunities, supporting investment in North Ayrshire, supporting a just
transition to net zero and securing anchor institutions within North Ayrshire.

Page 6

Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 The Business Case has been developed and informed by engagement with sector
leads from and academia, private and public sector stakeholders. Wider stakeholder
and community engagement will be undertaken to inform the next phase of the
project’s development. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Bruce McClure, Senior Manager, Growth &
Investment on brucemcclure@north-ayrshire.gov.uk. 
Background Papers
Cabinet Report, 20 February 2024: International Marine Science & Environment (IMSE)
Ayrshire Growth Deal project - Collaboration Agreement