NORTH AYRSHIRE COUNCIL 
28 April 2026 
Cabinet 
Title:    Roads, Structures and Street Lighting Maintenance
Programme 2026/27 
Purpose:  To seek Cabinet approval of the proposed Roads, Structures
and Street Lighting Maintenance Programme for 2026/27 
Recommendation:  That the Cabinet (a) notes the approach taken to determining
the asset maintenance programme for roads, structures and
street lighting; (b) approves the maintenance programme for
2026/27, as shown at Appendix 1; and (c) notes that the
programme will be issued to the Locality Planning Partnerships
for information. 
1. Executive Summary 
1.1 North Ayrshire Council has a statutory obligation under the Roads (Scotland) Act 1984
to manage and maintain its public road network. The adopted road network within
North Ayrshire has a total length of 1054km.  The core roads assets are currently
estimated at a value of approximately £1.7billion. 
1.2 The Council’s Roads Service has adopted an asset management approach to road
maintenance to allocate available road maintenance funds to locations that will offer
the most beneficial return on the investment. 
1.3 The Roads Asset Management Plan (RAMP) follows the recommendations contained
within the ‘Well Maintained Highway’s Code of Practice, ensuring that the Council’s
statutory obligations as delegated Roads Authority are met. 
1.4 In complying with the Code of Practice, an effective regime of inspection, assessment
and condition recording is well established which assists in not only providing a road
network for the future but one that promotes social inclusion and contributes to
economic growth within the area. This approach also ensures the Council is providing
value for money on any investment attributed to road maintenance. 
1.5 The proposed Roads, Structures and Street Lighting Maintenance Programme
2026/27 is attached in Appendix 1. The Programme is based Revenue and Capital
budgets approved at the Council’s budget setting meeting on 25 February 2026.

Page 2

2. Background 
2.1 North Ayrshire Council is responsible for the maintenance of the adopted local road
network including lighting and structures assets as well as its other non-adopted road
assets. However, the Council has no responsibility for the maintenance of the Trunk
Road Network which falls to Transport Scotland and their management contractor,
Amey. The Trunk Road network includes the A78, the A737 from Kilwinning to the
Renfrewshire Boundary and A738 from the Pennyburn Roundabout to the A737 Dalry
Road Kilwinning. 
2.2  North Ayrshire Council’s roads are the Council’s largest community asset and play a
vital role in supporting the local and wider economy by facilitating the movement of
people, goods and services and connecting people with economic and social
opportunities. 
2.3  The proposed Roads, Structures and Street Lighting Maintenance Programme for
2026/27 has been developed in accordance with the strategy contained within the
Roads Asset Management Plan (RAMP) to deliver the maximum return on investment
and ensures the provision of an effective road network throughout North Ayrshire. 
2.4  Road Condition is measured nationally through the Scottish Road Maintenance
Condition Survey (SRMCS). The measure in place, the Road Condition Index (RCI),
records the percentage of the Council’s roads which should be considered for
maintenance. North Ayrshire’s RCI has been improving steadily in recent years. The
2023 figure of 34.8%, improved to 32.5% in 2024, and is currently at 30.6%, published
2025 figure. The Council’s ranking amongst the 32 Local Authorities for the Road
Condition Index has also improved from 22nd in 2023 to 10th in 2025. 
2.5 The estimated carriageway maintenance backlog figure for North Ayrshire is currently
£38.5m. The ‘steady state’ figure for maintaining our roads at present condition is
£5.5m per year. The approved capital budget supported by revenue funding is £8.3m
for 2026/27. This level of investment is greater than the ‘steady state’ figure and will
therefore contribute to an improvement of the road network. 
2.6 Road lighting condition is measured through programmes of structural and electrical
assessment and testing and is complemented through the ongoing review of age
profile and material type life expectancy. The results are categorised and recorded in
the lighting asset management database to inform a prioritised list of replacement
schemes. Lighting is allocated an annual Capital budget of £1m to address a ‘steady
state’ position of maintaining our lighting at present annualised depreciation rate. The
programme of carriageway investment will see carriageway investment in locations
yet to be included within the prioritised lighting condition criteria. This will be
addressed by some reprofiling and by the provision within the carriageway works of
installing regular road crossings and ducting to allow lighting improvement works
when reaching prioritisation status based on their condition at future investment
cycles. 
2.7 Bridge and retaining wall condition is also evaluated through a robust inspection
programme. General inspections are undertaken every 2 years, while an in-depth
‘principal inspection’ is carried out every 6 years and the results of the inspections are

Page 3

used to inform work programmes. The results of the inspections are input into a
Structures database which is then used to calculate an average Bridge Structure
Condition Index (BSCIav) based on the total number of assets. The BSCIav is
currently 82.76 (2024/25 figure) which is within the ‘good’ classification of 80 to 90.
Structures have an allocated capital budget of £560,000.
2.8  Details of how condition assessments are carried out and how roads, structures and
lighting locations are prioritised for inclusion in our maintenance programme are
provided in Appendix 2. The assessment matrix used for scoring and ranking
structures for inclusion in the Structures Maintenance Programme is attached in
Appendix 3. 
2.9 The road maintenance programme in 2025/26 mitigated high inflationary cost
increases through two factors - by forecasting higher projected costs and building this
into the programme early in the financial year and, secondly, the Roads Minor Works
Framework Contract price being held for the first 6 months of the year.  Works
completed by the operational team and any works tendered since then were subject to
inflationary rises in material and plant costs as well as contractor price increases.  The
2026/27 road maintenance programme has been prepared using increased rates from
2025/26 costs to allow for further inflationary rises in costs and to ensure that
programmed works can be completed. 
2.10 The following locations are being carried over from the 2025/26 maintenance
programme. This resulted from lack of contractor availability, design changes and ferry
restrictions: 
• Lovat Street, Largs
• B714 Dalry Road, Saltcoats 
• B896, Millport
• Park Terrace, Lamlash 
2.11 The following structures contracts are being carried over from the 2025/26
maintenance programme, with feasibility and design works ongoing. This was due to
adverse weather resulting in various coastal erosion (Ring Road Arran) and landslip
(B871 West Kilbride) issues across the network. These unforeseen activities required
urgent attention, resulting in the need to reallocate funding and staff resource from
these planned projects to design and manage the unplanned repairs. 
• Lynn Drive Footbridge, Kilbirnie
• Kirkland Road Footbridge No.2 Glengarnock (B777)
• Barrie Terrace, Ardrossan 
• Catacol Bridge (C147)
• Culvert West of Ballymeannoch (C147) 
2.12 Given the availability of ferry bookings, programmed works will be restricted to a fixed
number of weeks. As a result of this, the programme for Arran will be limited to five
weeks. Any works that can’t be completed within that time, will be carried over to a
future year’s programme. 
2.13  The roads investment funding agreed at the Councils budget meeting on 25 February
2026 will require significant resource to plan, design and deliver the investment in
2026/27. In addition, and similarly with previous years, unforeseen circumstances, like

Page 4

weather events or land slips may have an impact on the delivery of the programme
together with the availability of contractors and materials required to complete the
programme. Should the service not be able to deliver the full programme in the current
financial year, any works not complete will be carried forward into 2027/28. 
3. Proposals 
3.1 That Cabinet notes the approach taken to determining the asset maintenance
programme for roads, structures and street lighting. 
3.2  That Cabinet approves the maintenance programme for 2026/27, as shown at
Appendix 1. 
3.3  That Cabinet notes that the programme will be issued to Locality Planning
Partnerships for information. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The Roads, Structures and Street Lighting Maintenance Programme will be delivered
from approved 2026/27 Capital and Revenue budgets of £8.3m. Estimated costs are
detailed within the appendices. 
Human Resources 
4.2 Delivery of the programme will be met from existing staff resources and appropriate
contractors. 
Legal 
4.3 North Ayrshire Council has a statutory obligation to manage and maintain its public
road network under the terms of the Roads (Scotland) Act 1984. 
Equality/Socio-economic 
4.4 There are no equality implications. The maintenance programme contributes to the
Council’s socio-economic duty, as well-maintained roads are essential for the social
and economic prosperity of North Ayrshire. 
Climate Change and Carbon 
4.5 Effective programming and management of these assets will assist in reduced carbon
associated with mobilisation of unplanned reactive maintenance resources and
extends the use of assets in a cost effective and sustainable manner.

Page 5

Key Priorities 
4.6 Effective management of these assets contributes to a number of Council plan
objectives ensuring that North Ayrshire is well-connected with effective infrastructure
and that we maximise resources and provide value for money. 
Community Wealth Building 
4.7 The maintenance programme contributes to Community Wealth Building through
community benefits clauses associated with maintenance contracts. It is also the case
that a proportion of the maintenance programme is also delivered in-house by the
Roads Operations Team and Building Services. 
Islands Communities Impact Assessment (ICIA) 
4.8 The works programme on the Isle of Arran will be limited to a 5-week delivery period.
Local stakeholders will be notified once the programme has been confirmed. 
United Nations Rights of the Child (UNCRC) 
4.9 None 
Consumer Duty 
4.10 None 
5. Consultation 
5.1 The maintenance programme will be shared with each Locality Partnership. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Gary Wilson, Senior Manager Neighbourhood
Services (Roads), on 01294 324810. 
Background Papers
0

Page 6

Street Town Location Estimate Cost
B7049 Wilson Street Beith New Street to 30 Wilson Street £110,000
Kings Road Beith B7049 Jct to Muirpark Road £52,500
Glebe Road Beith Glebe Road to Glebelands Way £25,000
Jamieson Way Beith Full Length £27,500
Kirk Road Beith New Street to Scholars Wynd £20,000
Mains Avenue Beith Full Length £40,000
Manuel Avenue Beith Full Length £45,000
Mid Road / Elms Place Beith Mains Avenue to the joint in Elms Place £30,000
Braehead Place Dalry Full Length £30,000
Merksworth Avenue Dalry Full Length £40,000
New Street Dalry Main Street to B714 Townend Street £60,000
St Palladius Terrace Dalry From B714 including section of Courthill Street £40,000
Reek Street Gateside Main Street to Geilsland Junction £55,000
Balgray Road Glengarnock Full Length £30,000
Davidson Avenue Glengarnock B777 to Smith Avenue £27,500
Garnock View Glengarnock B777 to Caledonian Road £47,500
Grahamston Avenue Glengarnock Full Length £95,000
Holms Road Glengarnock Full Length £20,000
Longbar Avenue Glengarnock Full Length £47,500
Smith Avenue Glengarnock Donaldson Ave to Longbar Ave (Inc Cul-de-sac) £47,500
A760 Bridgend Kilbirnie Muirend to Montgomery Court (including tesco ent.) £60,000
A760 Camphill Reservoir Kilbirnie Between Routdaneburn and South Camphill (Half & Full Panels) £60,000
A760 Radio City Roundabout Kilbirnie Full Length £45,000
B780 Newton Street Kilbirnie Ladysmith Road to Bankfaulds Avenue £110,000
Auchenhove Crescent Kilbirnie Full Length (Including Cul-de-sacs) £135,000
Castle Drive Kilbirnie Full Length £60,000
Craigton Road Kilbirnie Full Length £40,000
Munro Drive Kilbirnie Full Length £32,500
B7081 Dreghorn / Springside Roundabout Dreghorn Full Length £42,500
Annick Drive Dreghorn Townfoot to Broomlands Road (Include part of the Townfoot Junction) £32,500
Corsehill Mount road Dreghorn Monach Gardens to Lismore Drive £80,000
A71 Greenwood Interchange Eastbound on slip Irvine Full Length £110,000
A71 Greenwood Interchange Westbound off slip Irvine Full Length £110,000
A735 Irvine EAC Boundary to EAC Boundary £212,500
A736 Bank Street Irvine Woodlands Avenue and Thornhouse Avenue £92,500
B7080 Greenwood Interchange Irvine Both North & South Roundabouts £142,500
B7080 Long Drive Irvine Between Taylor Drive Roundabout and Hill Roundabout £237,500
B7080 Long Drive Irvine Greenwood North to Newmoor Roundabout (include layby 300m2) £117,500
B7080 Long Drive Irvine Northbound between the Greenwood Roundabouts £52,500
B769 Middleton Road to EAC boundary Irvine Part Length Sections £75,000
Shawalton Road Irvine Drybridge towards Shewalton £227,500
Bensley Avenue Irvine Full Length £65,000
Cairnsgarroch Way Irvine Full Length £57,500
Doura Drive Irvine Full Length £12,500
Lamont Drive Irvine Full Length £62,500
Lanfine Way Irvine Full Length    £52,500
Lomond Place Irvine Full Length £105,000
Pladda Crescent Irvine Ppatch in Pladda Wynd Junction & No.9 £12,500
Portland Place Irvine Full Length £72,500
Portland Road Irvine Full Length £185,000
Rubie Crescent Irvine Full Length £65,000
Sourlie Terrace Irvine Full Length £40,000
Towerlands Road Irvine Towerlands Roundabout to Crammond Way £90,000
Braeside Kilwinning Full Length (Including 39 - 49 David Gage Street and to 53 Baid Avenue) £37,500
Burns Place Kilwinning Full Length £20,000
Highfield Street Kilwinning Full Length £30,000
Hillcrest Place Kilwinning Full Length £37,500
Innerwood Road Kilwinning Viaduct Circle to nibs at Woodwynd £60,000
Killermont Place Kilwinning Full Length £67,500
Morville Crescent Kilwinning No 8 to No 32 £37,500
St Winnings Road Kilwinning A738 Byres Road to Road End £47,500
St Winnings Well Kilwinning Full Length £62,500
Waterside Road Kilwinning Full Length £85,000
The Causeway Fairlie A78 to Slipway £22,500
Barr Crescent Largs Full Length £77,500
George Street Largs Full Length £62,500
Harper Crescent Largs Full Length £35,000
Lovat Street Largs Full Length (carry forward from 25/26) £0
Scott Crescent Largs Full Length £15,000
Scott Street Largs A78 to just past Gogoside Drive £135,000
Spalding Drive Largs Full Length £87,500
Balloch Crescent Millport Full Length £65,000
Provost's Loan Millport Full Length £27,500
The Crescent Skelmorlie Halketburn Road to Sandybrae Road £52,500
Corsehill Drive West Kilbride A78 to no.9 £147,500
Glen Road West Kilbride Main Street to Glenside Crescent £25,000
Orchard Street West Kilbride Including Western Terrace Junction & Alton street Junction £85,000
South Road West Kilbride Full Length £20,000
B780 Dalry Road Ardrossan Stanley Road to Chapelhill Mount mini roundabout £180,000
Hunter Avenue Ardrossan
Loanhead Road to North Junction with Barrie Terrace. Include South junct with
Barrie Terrace.
£55,000
Queens Drive Ardrossan Central Quadrant to Stanley Road £50,000
Dockhead Street Saltcoats Full Length £50,000
Argyle Road Saltcoats Sharphill Road to Jacks Road £132,500
Rennie Place Saltcoats Up to the gates at factory place £40,000
Thomas Campbell Street Saltcoats Full Length £40,000
B752 Caledonian Road Stevenston Full Length £122,500
B780 Saltcoats Road / Canal Street Stevenston Full Length £184,500
Afton Road Stevenston New Street to Main Street £65,000
Hayocks Road Stevenston Number 44 to Number 135 £70,000
Hillside Street Stevenston
Three section - Moorpark Road West to Arthur Street, Muir Drive Junction, Ho96 to
Roundabout
£80,000
MAINLAND ROADS PROGRAMME 2026 - 2027
Carriageway Resurfacing

Page 7

Lumsden Place Stevenston Roundabout to School Gates £5,000
Various Various Patching Contract £250,000
£6,452,000

Page 8

Street Town Location Estimate Cost
C99 Dalry Junction with C57 at Blair bridge south to Smithy Cottage West £100,000
C99 Dalry South Lodge to the U16 Cockenzie Junctoin £58,000
C20 Benslie Benslie B785 (Both legs) to Burnbrae Cottage £73,000
C87 Kilwinning Dalgarven through to Gateside Farm £54,000
U22 Kilwinning Lochwood Farm towards U55 £42,000
U29 Kilwinning B778 to Monkreddan Farm £32,000
U46 Moncur Kilwinning End of Previous Surfacing to High Moncur £25,000
U46 Moncur Kilwinning B785 to Mid Moncur Access £6,000
B899 Millport 2 sections - Ballikillet Farm & at Millport speed limit signs £32,000
C118 Meigle Skelmorlie A78 to Meigle House £28,000
£450,000
Street Town Location Estimate Cost
Cheeywood Drive Beith Full Length £44,000
Newton St Kilbirnie Avils Hill to Walker Street £15,000
Castlepark Footpaths Irvine Various sections £40,000
Belleisle Close and Hoylake Square Kilwinning Remote Footpath between belleisle close and hoylake square £30,000
Corsehill Drive West Kilbride odd numbers from A78 trunk road to house number 17 £21,000
Burns Terrace Ardrossan Both Sides (include Afton Place & Armour Place) £65,000
Stanley Drive Ardrossan Slabbed footway both sides £22,000
Mulgrew Avenue Saltcoats Numbers 10 - 32 £13,000
£250,000
Structure Town Project Estimate Cost
Stanley Place Footbridge Saltcoats Refurbishment / repaint £60,000
Lynn Drive Footbridge Kilbirnie Steel repairs and repainting £90,000
Barrie Terrace Ardrossan Strengthening  design   £50,000
Kirkland Road F/B No. 2, Glengarnock Glengarnock Repairs to concrete slab, beam repainting and parapet upgrade £80,000
Bungle Burn Bridge A736 Irvine Parapet upgrade and general repairs £80,000
Dalgarven Mill Bridge Kilwinning Concrete repairs, pier / scour protection works £60,000
South Newmoor Bridge A71 Irvine Expansion Joint Replacement £25,000
£445,000
Area Town Streets Inlcuded Estimate Cost
Bute Terrace / George Street Millport Bute Terrace, George Street, Barend Street £202,155
Milton Quadrant / High Street Kilbirnie Milton Quadrant, High Street,Ladyland Drive £92,311
Northacre / Greystones Kilwinning North Acre, Greystones £47,747
Meadowfoot Road Area West Kilbride Meadowfoot Road, Satirlie Crescent, Curbieshaw Drive, Meadowside £108,227
Pantonville Road West Kilbride Pantonville Road £66,846
Yerton Brae / Overtoun Crescent West Kilbride Yerton Brae, Overton Crescent, Overton Drive £92,311
Victoria Park Area Saltcoats Kerr Avenue, Townhead Road, Millar Road, Smith Drive, Cunninghame Road £105,045
Springvale Place Saltcoats Springvale Place £12,733
Dykesmains Road Saltcoats Dykesmains Road £35,015
Column Structural Testing Various Various Locations £50,000
Lighting Deteriorated Column Replacements Various Various Locations £150,000
£962,390
Lighting Deteriorated Infrastructure Replacements
Structures Projects
Footway Resurfacing
Screeding

Page 9

Street Town Location Estimate Cost
Various Various Jet Patcher £50,000
A841 Main Street Whiting Bay Sections along Main Street £37,000
B880 String Road Brodick to Blackwaterfoot End of New surface at Monyquil to new surface before Glenloig £270,000
B880 String Road Brodick to Blackwaterfoot New surface prior to Glenloig to New surface after Glenloig £115,000
C147 Catacol Craigard to Joint at new surface £57,000
C147 Imachar Downhill S Bends to North of SSE Substation £172,000
C147 Dougarie North of Dougarie (Dougarie Point to Dougarie) £128,000
C147 Machrie At Old Byre Visitor Centre to Machrie Moor Road £188,000
C147 Ross Sliddery C147 at the junction with the Ross Road north to new surface £58,000
C147 Tormore Blackwaterfoot Crochandoon to Rowanbank £183,000
Park Terrace Lamlash A841 to Benlister Road (Carried over from 25/26) £0
Trareoch Road Whiting Bay Full Length £40,000
£1,298,000
Structure Road Project Estimate Cost
Catacol Bridge  C147 Replacement feasibility study £45,000
Culvert West of Ballymeanoch C147 Retaining wall strengthening £70,000
£115,000
Area Town Project Estimate Cost
Invercloy Car Park Brodick LC/01/26 £37,610
£37,610
Carriageway Resurfacing
Structures Projects
ARRAN ROADS PROGRAMME 2026 - 2027
Lighting Deteriorated Infrastructure Replacements

Page 10

Appendix 2 
Condition Assessment and Prioritisation Process 
1.1 The Audit Scotland Follow-up report, Maintaining Scotlands Roads published in
August 2016 stated that Councils should use their RAMPs to establish long
term investment plans for maintaining the road network taking into acount
whole-life costing and treatment options. 
1.2 As part of the Roads Asset Management process, annual condition
assessments are carried out on the public road network as part of the
inspection regime. All locations are assessed using a risk based approach. 
1.3 Condition assessments are carried out simultaneously with the Safety 
Inspections in accordance with the pre-determined timescales contained within
our Safety Inspection Manual. All faults noted during these inspections are
logged within our electronic Routine Maintenance System (RMS). 
1.4 For carriageways, to take account of whole-life and different treatment options
the carriageway maintenance programme is developed using road asset
management principles. Lifecycle planning is at the core of this approach and
takes into account, hierarchies, condition and local community priorities.
Preventative treatments are used to prolong the life of carriageway surfaces
before their condition deteriorates and requires extensive resurfacing.   
1.5 The main factors considered are:- 
• Road Condition – based on detailed visual inspection and the Scottish Road
Maintenance Conditions Survey (SRMCS). 
• Road Hierarchy – this takes account of the strategic importance of the road
and is determined from our Local Transport Plan. 
• Assistance to Council and Community Priorities – this takes account of
other priorities such as economic development,  access to shops, amenity
housing or schools. 
1.6 Carriageways and footways are both condition assessed and scored in
accordance with the assessment table below. These condition scores, RCI
data, road hierarchy information and priorities information as above are utilised
through our electronic WDM Scheme Manager to target locations for
improvement works in order to optimise investment.

Page 11

Appendix 2 
Assessment Table   
CONDITION
Extent 1
(Acceptable)
2
(Safe but poor
appreance)
3
(Minor
deterioration)
4
(Major
deterioration)
1 - Up to 25%  5 9 13
2 – 25% to
50% 
6 10 14
3 – 50% to
75% 
7 11 15
4 – 75% to
100% 
4 8 12 16 
Each location is also reviewed at least once a year depending on its location
within the Roads Hierarchy as part of the routine inspection process. 
1.7 There are various types of surfacing materials and processes available
depending on the particular road type, location and level of existing
deterioration. Options available for treatment include preventative measures
such as surface dressing and resurfacing options such as screeding,
resurfacing (inlay and overlay), depending on the severity of deterioration full
reconstruction may be the most effective option. 
1.8 The level of investment associated with works can vary depending on restricted
working arrangements, traffic management required and the extent of
preparatory works necessary to enable resurfacing.  There is also an additional
uplift for island working of up to 50% for works on Arran and Cumbrae. 
1.9 Street Lighting column replacement is prioritised through non-destructive
strength testing to determine the level of deterioration associated with the
columns. Following testing, columns are categorised within the Asset
Management database for road lighting. 
1.10 Testing is carried out in accordance with the Institute of Lighting Engineer's
Technical Report No.22 Managing a Vital Asset: Lighting Supports as well as
UK Lighting Board Code of Practice: Well-lit Highways. 
1.11 Once results are input, the database then compares these results against the
more general age profile to determine a final list of priority repairs. This
produces recommendations in order of priority for both individual units and
whole streets or areas. 
1.12 Recommendations are generally categorised as Category A through K as
follows:

Page 12

Appendix 2 
A:  Immediate replacement 
B:  Replace urgently or reinspect within 6 months 
C1: Column Material failure, replace as soon as possible or reinspect within
1 year 
C2: Bracket failure, sleeve where possible or replace unit within 1 year 
D:  Foundation failure, realign, reinstate and reinspect within 6 months 
E: Material approaching failure, replace as part of planned maintenance  
programme or reinspect within 2 years 
F:  Material approaching failure, replace as part of planned maintenance  
programme or reinspect within 5 years 
G:  Condition reasonable, but age expired and certified insured for 2 year  
periods until replaced 
H:  Condition reasonable, but age expired and certified insured for 5 year  
periods until replaced 
I:  Acceptable condition but age expired and insured for 5 years  periods
until replaced. 
J:  Sound condition but age expired & visually poor (evidence of concrete  
cracking etc.) 
K:  Sound condition and not age expired – no current requirement for
strength structural inspection, visual only at planned maintenance
cycle. 
1.13 Where non-urgent replacement recommendations (Category F through to J) are
on an individual column basis, the data is further analysed to determine a
percentage value for recommended replacement numbers against the balance
of units in a street. If this figure exceeds 30% then the entire street will be
considered for higher prioritisation which will address the design class standard
of the street beyond individual replacement for safety reasons only. 
1.14 The structures programme is identified based on the structures prioritisation
matrix which ranks assets based on a number of factors including its condition,
safety, and usage.

Page 13

Structure Name: Enter score based on the description in the following coloured cells
Date when the scoring is carried out:
Priority Ranking for structure capital programme Structure Net score % of
Maximum Score total Score
No. Factors Score Input
1
Type of Bridge 1 Score 1 if road bridge and 0
if foot bridge
Culverts, Subways which carry road shall be
considered as road bridge as per this scoring system.
Structures which carry only pedestrians, cyclists and
equestrians shall be considered as footbridge.
NA
2 Route Factor 40 Score based on NAC route hierachy Route hierachy 0 0%
Cat 2 - SPT/ NAC strategic routes - 40
Cat 3a - Main distributor routes - 30
Cat 3b - secondary distributor routes - 20
Any other category - 10
Routes serving fewer than 5 properties - 5
3 HGV Restriction 60 Score based on weight capacity Weight restriction 0 0%
factor 3 tonnes - 60
7.5 to 13 tonnes tonnes - 50
18 tonnes - 40                 
26 tonnes - 30
No weight restriction - 0
4 Condition factor 10 Score based on the condition of the
bridge
Sliding score based on 0 for very good condition to
10 for poor condition. (10 - (BCI crit/ 10)) 0 0%
5
Deterioration
factor
10 Score based on the rate of
deterioration of the structure
Sliding score based on 0 for very slow deterioration
to 10 for rapid deterioration 0 0%
6
Pedestrian
factor
20 Score based on pedestrian usage.
Bridges with footways of heavy
pedestrian usage shall score a
maximum of 30.
Structures with footways in heavily used urban areas
score 20. Score 20 if route is access to a school or
railway station. Apply a sliding scale going down to 0
for rural structures without footways.
0 0%
7
Flooding factor 40 Score based on the potential for the
existing structure to contrubute to
flooding
A structure that makes no contribution to flooding
risk will score 0. Structures that are know to increase
the risk of flooding due to restrictions in width or
soffit height will score 30.
0 0%
8
Scour factor 60 Score based on risk of collapse due
to expose to scour in heavy flow
conditions
Risk of collapse of structure due to scouring.
Structures which have been deterioted severely
because of inadequate scour protection and on verge
of collapse score maximum. Scour risk based on a
sliding scale.
0 0%
9
Parapet Condition
Factor
15 Score based on the condition of the
parapets
Structures with substandard Parapets with poor
conditon will score 15 . Structures with substandard
parapets with a 'monitor only' recommendation will
score 10. Structures which have parapets to current
standards will score 0.
0 0%
10
Parapet Risk
Factor
10 Score based on risk  in the event of a
parapet collapse leading to high risk
injuries and human casualties.
What is the likelihood of severe injury or even death
while the parapet is open to use considering the
condition of the structure. Risk based on a sliding
scale.
-5 100%
Structure Name:
Additional commentry

Page 14

11
Delay factor 10 Score based on whether existing
restrictions such as limited width
cause delays at the structure
Structures where delays are caused by width, weight,
height or other restrictions such as traffic lights will
be given a score higher than zero. Delays less then 2
minutes at peak times will score 5 and longer than 2
minutes will score 10. Score maximum if fire station,
railway station or hospital affected by delay.
0 0%
12
Structure Risk
factor
10 Score based on risk  in the event of a
Structure collapse leading to high
risk injuries and human casualties.
What is the likelihood of someone getting a high risk
injury or even death while the structure is open to
use considering the condition of the structure. Risk
based on a sliding scale.
0 0%
13
Maintenance
factor
20 Score based on maintenance
required to keep the existing
structure open.
Score based on known maintenance history and
requirement. No maintenance requirement will score
0. Listed structures score 15.
0 0%
14
Diversion factor 10 Score based on the length of the
diversion route if the structure is
closed in an unplanned manner with
no finite time limit.
Score based on diversion length. Any diversion equal
to or more than 20 miles scores 20. Score 1 for each
2 miles of diversion up to 20. Score 10 if a road
closure adversly affects a fire or railway station or
hospital. Score 10 if there is no alternative diversion.
0 0%
-5
Note maximum score that can be achieved for road bridge= 500
Priority level Chart Structure Name:
Date of Scoring: 00-Jan-00
Priority Level Indicator Overall works (500) Structure works (100) Parapet works (70) Scour Protection (60)
Level Score Level Score Level Score Level Score
No Action Rquired       
Low Priority       
Medium Priority       
High Priority       
Immediate action required       
Note : Works are divided above into three sub categories as each work can be independent and
each has its own significance in terms of attention required.