Page 1

NORTH AYRSHIRE COUNCIL 
17 March 2026 
Cabinet 
Title:    Capital Programme Performance to 31 January 2026 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2025/26 to 31 January 2026 
Recommendation:  That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 31
January 2026; and (ii) the forecast expenditure to 31 March
2026; 
(c) approve the virement proposal noted within the HRA
programme detailed in appendix 2; and
(d)   note the estimated performance against the Prudential
Indicators set out in the Treasury Management and
Investment Strategy. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2025/26 to 2033/34 was
approved by Council on 26 February 2025. The Housing Revenue Account (HRA)
Capital Investment Programme 2025/26 sits within the updated HRA Business Plan
and was approved by Council on 12 February 2025. 
1.2  This report identifies the current programme for 2025/26, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 31
January 2026 (Period 10) and forecast expenditure to 31 March 2026. 
1.3  At Period 10 the General Fund is forecasting an underspend position of (£0.011m)
against a revised budget of £68.528m. The HRA is forecasting a projected
underspend of (£0.536m) against a revised budget of £41.958m. 
1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £3.724m, primarily related to UK Government Grant of
£1.500m for Pride in Place Impact Fund, Vacant & Derelict Land Investment Funding
of £0.893m and Scottish Government Grants for Road Safety and 20mph
Implementation of £0.943m. 
1.5 Reviews of individual project plans have identified several adjustments to the current
profiles. As a result, projects totalling (£16.287m) have been reprofiled for delivery in
2026/27 and beyond. This is primarily related to the new Ardrossan Campus build

Page 2

based on revised contractor payment profile, Ardrossan Harbour Interchange awaiting
decisions from CMAL and Transport Scotland, Pride in Place Impact Funding late
notification of grant award and the B714 upgrade tender process. These have been
partly offset by the acceleration of £0.070m to 2025/26 from future years. 
1.6  Following the most recent CPAG meeting, (£0.600m) underspend has now been
identified for Montgomerie Park School.  This will be transferred to flexibility fund in
the next period as part of the CPAG actions. 
1.7 Within the HRA Capital Programme, a review of delivery timescales has resulted in
the re-profiling of (£3.135) of works for delivery in 2026/27 and beyond, partly offset
by the acceleration of £0.014m from future years.   
1.8 Ongoing uncertainty arising from inflationary pressures and construction cost volatility
continue to impact on the Capital Programme. Financial risks have been identified
across several high value projects. Council has provided for a degree of mitigation
within the overall 10-year General Services Capital Investment Programme and the
HRA Capital Investment Programme and through additional investment agreed in
relation to the Ardrossan campus. Projects will continue to be monitored closely with
cost increases met initially from the additional flexibility built into the programme.
However, any requirement for further borrowing not met from a funding source will be
a matter for Council to consider. 
1.9 The Treasury Management and Investment Strategy (TMIS) for 2025/26 was
approved by Council on 26 February 2025 and detailed the key performance
indicators under the Prudential Code for Capital Finance in Local Authorities (2021
edition). The current estimated performance indicates that North Ayrshire Council has
operated within the treasury limits and performance indicators set out in the TMIS and
the current capital investment plans remain affordable. 
2. Background 
General Fund 
2.1  The following table outlines the movements in the 2025/26 General Services budget:  
General Services Capital 
2025/26
£
million
Budget as at 30 November 2025 81.021
Changes to Funding 3.437
Other Revisions to the Programme 0.287
Revised Budget 84.745
Alterations to phasing of projects 2025/26 to
2026/27 (16.287)
Alterations to phasing of projects 2026/27 to
2025/26 0.070
Budget as at 31 January 2026 68.528

Page 3

2.2 Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
Funding Body
Amount
£ million Project
UK Government Grant 1.500 Pride in Place Impact Fund
VDLIF 0.893 Annickbank Phase 4
Scottish Government Grant 0.611 20mph Implementation
Scottish Government Grant 0.332 Road Safety Improvement Fund
Scottish Government Grant 0.030 Garrison House
Scottish Government Grant 0.030 Cumbrae Youth Forum
Scottish Government Grant 0.025 Kildonan Hall
Scottish Government GCG 0.016 Coastal Adaptations
Total Funding Adjustments 3.437   
Funding Source
Amount
£
million Project
CFCR 0.172 Waste Compactors
CFCR 0.115 Salt Dome
Total Other Adjustments 0.287   
2.3 Alterations to the Phasing of Projects 
A review of individual project plans has identified a requirement to re-profile
(£16.287m) of works for delivery in 2026/27 and beyond. 
Project Amount
£ million
Castles & Historic Monuments (0.038)
Total Communities & Housing (0.038)
Ardrossan new Build (3.282)
Montgomerie Park School (1.287)
Schools ICT (0.127)
CO2 Monitors (0.017)
Total Education (4.713)
Ardrossan Harbour Interchange (3.518)
B714 Upgrade (1.697)
Pride in Place Impact Fund (1.500)
Millburn FPS (0.911)
Active Travel Tier 1 (0.891)
AGD Great Harbour (0.682)
Renewal of Playparks (0.563)
Lighting (0.297)

Page 4

LBPR Stevenston Complex (0.185)
PBIP (0.183)
Island Pit Stops (0.182)
Bridges Infrastructure Programme (0.172)
Montgomerie Park Masterplan (0.132)
Irvine Enterprise Area (0.103)
AGD Marine Tourism Cumbrae (0.090)
Strategic Investment Route (0.073)
Lochshore Kilbirnie (0.072)
VDLF Devlopment Work (0.070)
Repurposing Property Grant (0.052)
VDLF Kyle Road Phase 2 (0.034)
AGD I3 DPMC Phase 2 (0.030)
Other Minor Movements (0.056)
Total Place (11.493)
Telephony (0.043)
Total Corporate Services (0.043)
Alterations 2025/26 to 2026/27 (16.287) 
These adjustments have been partly offset by the acceleration of £0.070m of
expenditure to 2025/26 from future years. 
Project Amount
£ million
Improvement Grants 0.070
Total HSCP 0.070
Alterations 2026/27 to 2025/26 0.070 
2.4 These adjustments have resulted in a revised 2025/26 budget at 31 January 2026 of
£68.528m, a net reduction of (£12.493m). 
2.5 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme:

Page 5

2.6  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a reduction of £12.493m from the revised budget,
including: 
Category
Amount
£ million Comments
General Capital Grant 0.016 Rephased and revised contributions
Borrowing (10.815) Rephased aligned to projected
expenditure
Specific Grant (0.838) Rephased and revised contributions
CFCR 0.286 Rephased and revised contributions
Other Grants (0.166) Rephased and revised contributions
Capital Receipts (0.976) Realigned capital receipts
Total Funding
Adjustments (12.493)   
2.7 Projected Capital Expenditure to 31 March 2026 
The projections are summarised by service in the following table:   
(20.000)
0.000
20.000
40.000
60.000
80.000
100.000
120.000
Corporate Communities
& Housing
Education HSCP Place Other items Total
£ million

Page 6

Service /
Category
Approved
Budget
2025/26
£ million
Carry
Forwards
and
Adjustments
£ million
Revised
Budget
2025/26
£ million
Projected
Expenditure
/ Income to
31 March
2026
£ million
Projected
Variance
Over /
(Under)
£ million
Corporate
Services 0.452 (0.043) 0.409 0.409 0.000
Communities
& Housing 0.844 0.022 0.866 0.866 0.000
Education 30.053 (4.678) 25.375 25.375 0.000
HSCP 0.780 0.070 0.850 0.850 0.000
Place 48.875 (7.829) 41.046 41.035 (0.011)
Other Items 0.017 (0.035) (0.018) (0.018) 0.000
Total
Expenditure 81.021 (12.493) 68.528 68.517 (0.011)
General
Grants (10.379) (0.016) (10.395) (10.395) 0.000
Specific
Grants (19.408) 0.838 (18.570) (18.570) 0.000
Use of
Reserve
Funds 0.000 0.000 0.000 0.000 0.000
CFCR (0.072) (0.286) (0.358) (0.358) 0.000
Capital
Receipts (2.626) 0.976 (1.650) (1.650) 0.000
Other Grants
&
Contributions
(1.299) 0.166
(1.133) (1.133)
0.000
Prudential
Borrowing (47.237) 10.815 (36.422) (36.411) 0.011
Total
Income (81.021) 12.493 (68.528) (68.517) 0.011 
2.8 Ongoing uncertainty and areas of cost risk remain across a number of projects. While
some mitigation was built into the Capital Programme in the form of flexibility budgets
at February 2025, totalling £23.6m over the next few years, cost pressures may
exceed this provision. To further address this risk, Council approved additional
flexibility of £15.0m from 2026/27 on 25 February 2026. These risks will be quantified
as individual projects are financially completed and tendering exercises are finalised,
with the impact on the costs of the programme being monitored and reported to
Cabinet as appropriate. Any requirement for further borrowing not met from a funding
source will be a matter for Council to consider. 
2.9   The movement in Capital Receipts projection is based on an current assessment of
the value and timing of land sale receipts. This is a reduction of (£0.979m) which has
been incorporated into the anticipated Capital Receipts position for 2025/26.

Page 7

Housing Revenue Account 
2.10 The following table outlines the movements in the 2025/26 HRA Capital budget: 
Housing Revenue Account  2025/26
£m
Budget as at 30 November 2025 45.079
Alterations to phasing of projects 2025/26 to
2026/27 (3.135)
Alterations to phasing of projects 2026/27 to
2025/26 0.014
Budget as at 31 January 2026 41.958 
2.11 Alterations to the Phasing of Projects 
A review of the timescale for delivery of capital projects has identified a requirement to
re-profile (£3.135m) of works for delivery in 2026/27 and beyond, including: 
Project Amount
£ million
Ayrshire Central Site (1.301)
Acquisition Houses - Open Market (0.652)
Garnock Academy Site (0.433)
Kings Arms (113-115 High St) (0.233)
Nelson Street Regeneration (0.172)
Total Alterations to New Builds (2.791)
Kitchens (0.131)
Other Minor Adjustments (0.006)
Total Alterations to Stock
Improvements (0.137)
Estate Based Regeneration (0.207)
Total Alterations to Other Capital
Works (0.207)
Alterations 2025/26 to 2026/27 (3.135)         
2.12 This has been partly offset by the acceleration of £0.014m of project   
expenditure for delivery during 2025/26, including: 
Project Amount
£ million
Sheltered Housing Units 0.014
Total Alterations to Other Capital
Works 0.014
Alterations 2026/27 to 2025/26 0.014 
2.13 These adjustments have resulted in a revised 2025/26 budget at 31 January 2026 of
£41.958m.

Page 8

2.14 The impact on budgeted funding is a reduction of (£3.121m) from the approved budget
which will be reflected in reduced prudential borrowing. 
2.15  Projected Capital Expenditure to 31 March 2026 
The projections are summarised in the following table:   
Service /
Category
Approved
Budget
2025/26
£ million
Carry
Forwards
and
Adjustments
£ million
Revised
Budget
2025/26
£ million
Projected
Expenditure
/ Income to
31 March
2026
£ million
Projected
Variance
Over /
(Under)
£ million
Housing
Revenue
Account
45.079 (3.121) 41.958 41.422 (0.536)
Total
Expenditure 45.079 (3.121) 41.958 41.422 (0.536)
CFCR (8.349) - (8.349) (8.349) -
Capital
Grants (10.104) - (10.104) (10.104) -
Use of
Reserves (0.722) - (0.722) (0.722) -
Other
Capital
Receipts
(0.091) - (0.091) (0.091) -
Affordable
Housing
Contribution
(0.721) - (0.721) (0.721) -
Prudential
Borrowing (25.092) 3.121 (21.971) (21.435) 0.536
Total
Income (45.079) 3.121 (41.958) (41.422) 0.536 
2.16 A net underspend of (£0.536m) is projected within the HRA capital programme for
2025/26 arising from revisions to a number of projects, including: 
Project Variance
£ million Comments
Electrical Rewiring 0.061 Additional voids
EWI (0.013) Lower costs per unit projected
Kitchens (0.014) Lower numbers projected
Bathrooms (0.147) Lower numbers projected
St Marys, Largs (0.423) Project complete
Total Variance (0.536)

Page 9

2.17 In addition to the adjustments noted above, Appendix 2 highlights a proposed
virement which is required to transfer the projected underspend in budget from the
External Wall Insulation programme to meet the projected overspend in the Roofing
programme. 
2.18 Cost pressures will continue to be monitored and a review of any potential impact on
the Business Plan and Capital Programme will be undertaken to address any
identified issues. Further information on the progress of all projects can be found in
Appendix 2. 
Treasury Management and Investment  
2.19 The Prudential Code for capital finance in local authorities (2021 edition) requires the
Council to set and monitor performance against specified prudential indicators. The
indicators for the current year were set out in the Treasury Management and
Investment Strategy 2025/26, approved by Council on the 26 February 2025. A
summary of the key indicators and our current estimated performance against them is
shown in the following table. Further details of all the Prudential and Treasury
indicators can be found in appendix 3.
Prudential and Treasury Indicators
2025/26
Approved
Estimate
£ million
2025/26
Revised
Estimate
£ million
Movement
£ million
General Services Capital Financing
Requirement 387.496 350.160 (37.336)
HRA Capital Financing Requirement 224.461 211.820 (12.641)
Total Loans Capital Financing
Requirement 611.957 561.980 (49.977)
Gross Borrowing 556.653 506.676 (49.977)
Operational Boundary for Borrowing 625.593 584.141 (41.452)
Authorised Limit for Borrowing 688.152 642.555 (45.597)
Total Operational Boundary (incl.
PPP/NPD) 704.183 662.731 (41.452)
Total Authorised Limit (incl. PPP/NPD) 766.742 721.145 (45.597)
Investments 30.000 30.000 0.000  
2.20 Loans Capital Financing Requirement
The Loans Capital Financing Requirement (CFR) is the underlying borrowing
requirement of the Council. This is currently lower than the approved estimate as a
result of the changes in the profiles of the capital programmes, resulting in a reduced
borrowing requirement for the year.
2.21 Gross Borrowing
Gross Borrowing is projected to be lower than anticipated due to the revised profile of
capital projects and by the continued strategy to utilise internal funds to minimise
borrowing.

Page 10

2.22 Operational Boundary
The Operational Boundary is the maximum which the Council anticipates borrowing to
fund the current year capital programme, building in flexibility for the timing of the
different funding streams and principal repayments. The in-year variance is linked to
the continued use of internal funds and the re-profiling of the capital programme.
2.23 Investments
It is estimated that the Council will maintain an average balance of £30.000m of
internally managed funds and utilise cash balances during the year in support of the
under-borrowed position.  The internally managed funds are primarily invested in call
accounts with banks, Money Market Funds and other UK local authorities.
2.24 It is critical that the Council ensures that its capital investment plans are affordable.
Affordability of borrowing is measured by the percentage of financing costs relative to
the net revenue stream of the General Fund and the Housing Revenue Account
(HRA). As at 31 January 2026, the estimated percentages for 25/26 are 3.5% and
26.3% for the General Fund and HRA respectively. Capital expenditure impacts on
the revenue budget through financing charges so it is essential the Council ensures
the financing costs remain affordable and do not constitute an excessive proportion of
the revenue resources available. From a General Fund perspective, the Scottish Local
Authority average was 6%, therefore demonstrating by comparison the prudent nature
of the current borrowing policy. For the HRA, the Scottish average was 20.1%. The
level of loan charges is deemed prudent and affordable within the framework of the
30-year Housing business plan.
3. Proposals 
3.1 It is proposed that Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 31 January 2026; and
(ii) the forecast expenditure to 31 March 2026; 
(c)  approve the virement proposal noted within the HRA programme detailed in
appendix 2; and 
(d)  note the estimated performance against the Prudential Indicators set out in the
Treasury Management and Investment Strategy.
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None.

Page 11

Legal 
4.3. None. 
Equality/Socio-economic 
4.4 None. 
Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our
investment on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Natalie Graham, Team Manager Corporate
(Financial Management), on 01294 324533. 
Background Papers
Capital Programme and Treasury Management Performance to 30 June 2025 - Cabinet 2
September 2025
Capital Programme and Treasury Management Performance to 31 August 2025 - Cabinet
28 October 2025

Page 12

Capital Programme and Treasury Management Performance to 30 November 2025 -
Cabinet 27 January 2026

Page 13

OFFICIAL INFORMATION#
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2025/26
Brought / Carry
Forward to 2026/27
Total Revised
Budget 2025/26
Actual Expenditure to
31st January 2026
Projected Expenditure
to 31st March 2026
Actual Over/
(Under) Spend for
2025/26
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Education
Nursery Education 4,030,810 4,001,407 4,030,810 0 37,018 0 37,018 7,615 37,018 0 0
Primary Schools 45,942,842 37,508,246 45,942,842 0 3,476,484 (1,286,874) 2,189,610 1,532,190 2,189,610 0 0
Secondary Schools 117,357,107 18,379,140 117,357,107 0 25,388,842 (3,282,356) 22,106,486 10,471,770 22,106,486 0 0
Schools Other 1,448,759 1,039,657 1,448,759 0 1,186,504 (143,785) 1,042,719 777,401 1,042,719 0 0
SUB TOTAL 168,779,518 60,928,449 168,779,518 0 30,088,848 (4,713,015) 25,375,833 12,788,977 25,375,833 0 0
Communities & Housing
Information & Culture 648,470 465,376 648,470 0 641,907 (38,303) 603,604 458,814 603,604 0 0
Other Housing 350,000 0 350,000 0 262,500 0 262,500 0 262,500 0 0
SUB TOTAL 998,470 465,376 998,470 0 904,407 (38,303) 866,104 458,814 866,104 0 0
Corporate Services
Council IT Strategy 8,797,380 3,648,406 8,797,380 0 452,265 (43,000) 409,265 272,090 409,265 0 0
SUB TOTAL 8,797,380 3,648,406 8,797,380 0 452,265 (43,000) 409,265 272,090 409,265 0 0
Health & Social Care
Management & Support 1,027,855 874,386 1,027,855 0 292,709 0 292,709 139,241 292,709 0 0
Housing Non HRA 475,371 463,703 475,371 0 475,371 70,000 545,371 463,703 545,371 0 0
Adults 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 11,926 0 0
SUB TOTAL 6,111,303 5,934,241 6,111,303 0 780,006 70,000 850,006 602,943 850,006 0 0
Place
Roads 108,984,436 75,844,720 108,984,436 0 15,965,609 (3,092,275) 12,873,334 8,459,716 12,873,334 0 0
Streetscene 5,439,175 3,198,865 5,439,175 0 1,623,888 (563,045) 1,060,843 526,052 1,060,843 0 0
Transport 8,444,629 3,304,317 8,444,629 0 3,671,128 0 3,671,128 3,182,816 3,671,128 0 0
Waste Services 13,492,976 13,444,027 13,492,976 0 171,485 0 171,485 171,485 171,485 0 0
Renewable Energy 15,956,436 15,103,223 15,956,436 0 2,580,943 0 2,580,943 1,727,730 2,580,943 0 0
Office Accommodation 1,759,123 693,690 1,759,123 0 1,236,736 2,700 1,239,436 693,690 1,239,436 0 0
Other Property 4,347,632 2,809,790 4,347,632 0 3,498,180 (185,000) 3,313,180 1,960,338 3,313,180 0 0
Economic Development & Regenerat 191,945,136 86,492,865 191,934,143 (10,993) 23,765,538 (7,654,695) 16,110,843 10,026,539 16,099,850 (10,993) (10,993)
Completed Projects 6,355,262 6,334,915 6,355,262 0 24,269 0 24,269 3,922 24,269 0 0
SUB TOTAL 356,724,806 207,226,411 356,713,813 (10,993) 52,537,776 (11,492,315) 41,045,461 26,752,287 41,034,468 (10,993) (10,993)
Other
Other 14,124,882 0 14,124,882 0 (18,614) 0 (18,614) 0 (18,614) 0 0
SUB TOTAL 14,124,882 0 14,124,882 0 (18,614) 0 (18,614) 0 (18,614) 0 0
Total Project Expenditure 555,536,359 278,202,882 555,525,366 (10,993) 84,744,688 (16,216,633) 68,528,055 40,875,111 68,517,062 (10,993) (10,993)
Total Project Income (84,744,688) 16,216,633 (68,528,055) (32,116,835) (68,517,062) 10,993 10,993
Total Net Expenditure 0 0 0 8,758,276 0 0 0
On Target (+0.5% of budget)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2025/26
North Ayrshire Council Capital Statement 2025/26
Year Ended 31st March 2026
Period 10
The following classifications have been used to
highlight delivery performance against original
timescales set
# OFFICIAL INFORMATION

Page 14

OFFICIAL INFORMATION#
Revised Budget
25/26 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 54,463,198 16,882,663 2,656,651 74,002,512 (25,790,093) 48,212,419 36,409,880 (11,802,539)
SUB TOTAL 54,463,198 16,882,663 2,656,651 74,002,512 (25,790,093) 0 48,212,419 0 36,409,880 (11,802,539)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Local Authority Direct Award 41,337 41,337 0 41,337 0
Vacant & Derelict Land Funding 3,397,568 238,809 358,499 3,994,876 (3,543,975) 450,901 3,214,903 359,280 (91,621)
Vacant & Derelict Land Investment Funding 892,990 892,990 0 0 (892,990)
Scottish Government Grant - AGD i3 Flexible Space Ph 1 4,762,045 (131,988) 4,630,057 0 4,630,057 0 4,630,057 0
Scottish Government Grant - AGD Great Harbour Ph 1 2,737,842 (29,141) 451,870 3,160,571 752,528 3,913,099 1,530,185 3,239,327 (673,772)
UK Government Grant - AGD DPMC Ph 2 0 0 1,000,000 1,000,000 0 1,000,000 0
Scottish Government Grant - AGD Marine Tourism Ardrossan 275,717 275,717 0 275,717 0 275,717 0
Scottish Government Grant - AGD Marine Tourism Cumbrae 470,781 470,781 0 470,781 0 470,781 0
Millport Town Hall Phase 2 0 26,469 26,469 0 26,469 26,470 26,469 0
Garrison House Project 0 325,698 325,698 30,000 355,698 325,698 355,698 0
Kildonan Hall 25,000 25,000 0 25,000 0
Cumbrae Youth Forum 30,000 30,000 0 30,000 0
Ardrossan Promenade 0 1,307 1,307 0 1,307 1,306 1,307 0
Islands Pit Stops 0 67,540 440,000 507,540 0 507,540 507,540 326,039 (181,501)
Place Based Investment Programme 316,043 136,857 251,385 704,285 (12,765) 691,520 704,286 447,568 (243,952)
UK Shared Prosperity Fund 576,535 576,535 0 576,535 576,535 576,535 0
UK Government Grant - B714 Improvements 17,553,389 (229,290) 17,324,099 (12,768,660) 4,555,439 4,555,439 3,973,307 (582,132)
UK Government Ayrshire 5GIR 0 281,711 281,711 575,000 856,711 856,711 856,711 0
UK Government - Local Regeneration Fund Funding Commercial 0 0 954,382 954,382 9,017,208 861,382 (93,000)
UK Government - Pride in Place Impact Fund 1,500,000 1,500,000 750,000 0 (1,500,000)
Road Safety Improvement Fund 332,158 332,158 0 332,158 0
20 mph Implementation 611,412 611,412 0 611,412 0
Marine Tourism Lochranza 0 0 129,718 129,718 0 129,718 0
Capital Grants
Flooding (2,206,000) (2,206,000) 0 (2,206,000) 0 (2,206,000) 0
General Capital Grant 10,573,000 (454,000) 10,119,000 2,483,000 12,602,000 9,125,670 12,602,000 0
SUB TOTAL 39,038,920 687,972 1,047,754 40,774,646 (7,549,875) 0 33,224,771 31,191,951 28,965,803 (4,258,968)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 703,707 0 (703,707) 0 0 0 0 0 0 0
General 0 0 0 0 0 0
Recovery & Renewal 703,707 (703,707) 0 0 0 0 0
CFCR 0 0 0 0 358,296 0 358,296 358,296 358,296 0
Vehicles 0 20,650 20,650 20,650 20,650
Locality Based Property Review 49,000 49,000 49,000 49,000
Salt Dome Goldcraigs 115,000 115,000 115,000 115,000
Street Furniture 0 2,161 2,161 2,161 2,161
Waste Compactors 0 171,485 171,485 171,485 171,485
Grants & Contributions 101,099 99,437 85,000 285,536 1,013,233 0 1,298,769 76,485 1,132,650 (166,119)
Quarry Road Phase 1 - IRBC 0 19,827 19,827 0 19,827 0 19,827 0
Lochshore Garnock Hub - Garnock Rugby Club 0 0 0 0 (200,000) 0 0
AGD - Great Harbour - Sustrans 0 0 (10) (10) (10) (10) 0
AGD - Great Harbour - FCC Communities Foundation 0 0 40,000 40,000 0 40,000 0
AGD - Great Harbour - Sportscotland 0 0 135,000 135,000 0 135,000 0
AGD - Great Harbour - LT Funding 0 0 40,000 40,000 0 40,000 0
Irvine Enterprise Area - NAVT 101,099 101,099 0 101,099 0 0 (101,099)
B777 Corridor Improvements - Active Travel Tier 2 0 0 25,996 25,996 0 25,996 0
Old Caledonian Railway Saltcoats Ph 2 - Active Travel Tier 2 49,990 49,990 7,825 49,990 0
B714 Sharphill to NCN AT Route - Active Travel Tier 2 161,240 161,240 0 161,240 0
Cumbrae AT Route - Active Travel Tier 2 50,000 50,000 0 50,000 0
Girdle Toll to Irvine Town AT Route - Active Travel Tier 2 80,000 80,000 25,229 80,000 0
Irvine to Drybridge AT Route - Active Travel Tier 2 8,000 8,000 4,800 8,000 0
Links to Eglinton Park - Active Travel Tier 2 0 0 114,355 114,355 0 114,355 0
NCN7 Valefield/Glengarnock Bridge - Walk Wheel Cycle Trust 0 0 62,000 62,000 0 62,000 0
Panel Reinstatement Works 0 40,189 40,189 0 40,189 40,189 40,189 0
Roads Remediation Works 0 39,651 39,651 0 39,651 39,651 39,651 0
RTPI North Coast and Garnock Valley  - SPT 0 0 6,000 6,000 0 6,000 0
NCN7 Crossing Improvements Walk Wheel Cycle Trust 40,000 40,000 0 40,000 0
Brodick Tennis Courts - LTA Tennis Foundation 0 98,162 98,162 56,301 98,162 0
Brodick Tennis Courts - KA Leisure Contribution 52,500 52,500 52,500 52,500 0
UFSM West Kilbride PS - Persimmons Contribution 50,000 50,000 50,000 50,000 0
Repurposing Property Grant Fund - NAVT 0 (230) 85,000 84,770 0 84,770 0 19,750 (65,020)
Capital Receipts 1,500,000 837,950 0 2,337,950 (687,517) 0 1,650,433 490,103 1,650,433 0
Sale of Land and Buildings 1,500,000 837,950 2,337,950 (979,000) 1,358,950 198,620 1,358,950
Sale of Vehicles 0 0 53,642 53,642 53,642 53,642
Insurance Recoveries (Vehicles) 0 0 10,345 10,345 10,345 10,345
Salt Dome - Insurance Recovery 227,496 227,496 227,496 227,496
SUB TOTAL 2,304,806 937,387 (618,707) 2,623,486 684,012 0 3,307,498 924,884 3,141,379 (166,119)
TOTAL CAPITAL PROGRAMME FUNDING 95,806,924 18,508,022 3,085,698 117,400,644 (32,655,956) 0 84,744,688 32,116,835 68,517,062 (16,227,626)
Approved Budget
at Cabinet Feb
2025
Capital Programme Funding 2025/26
Projected Income
to 31st March
2026
Approved budget
at Period 1 used
as revised
starting point
2025/26
Actual Income to
31st January 2026Funding Description
Carry Forward
from 2024/25
Changes after
Capital Refresh Feb
2025
Total Changes in
Year
Changes at
Capital Refresh
Feb 2026
# OFFICIAL INFORMATION

Page 15

OFFICIAL INFORMATION#
EDUCATION
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual Expenditure
to 31st January
2026
Projected
Expenditure to 31
March 2026
Actual Over/ (Under)
Spend for 2025/26
True Over/(Under)
Spend            
Brought / Carry
Forward to 2026/27 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
MARRESS HOUSE 4,030,810 4,001,407 4,030,810 0 37,018 7,615 37,018 0 0 Complete Complete Complete Complete Complete
Total Nursery Education 4,030,810 4,001,407 4,030,810 0 37,018 7,615 37,018 0 0 0
Primary Schools
MOORPARK PRIMARY 14,460,397 14,467,759 14,460,397 0 1,712,430 1,719,792 1,712,430 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK SCHOOL 23,448,999 21,852,794 23,448,999 0 1,302,286 (293,919) 15,412 (1,286,874) (1,286,874) Complete Complete Complete Complete Complete
FAIRLIE PRIMARY SCHOOL 526,444 67,349 526,444 0 66,533 62,349 66,533 0 0 31-Aug-26 31-Aug-26 Feasibility On Target On Target
UNIVERSAL FREE SCHOOL MEALS EXPANSION 194,913 0 194,913 0 20,000 0 20,000 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
UFSM ARDEER PRIMARY SCHOOL 18,729 16,548 18,729 0 2,690 509 2,690 0 0 Complete Complete Complete Complete Complete
UFSM CORSEHILL PRIMARY SCHOOL 165,691 134,213 165,691 0 28,476 (3,002) 28,476 0 0 Complete Complete Complete Complete Complete
UFSM FAIRLIE PRIMARY SCHOOL 30,000 0 30,000 0 30,000 0 30,000 0 0 31-Aug-26 31-Aug-26 Feasibility On Target On Target
UFSM GARNOCK COMMUNITY CAMPUS 54,901 54,043 54,901 0 896 38 896 0 0 Complete Complete Complete Complete Complete
UFSM GLENCAIRN PRIMARY SCHOOL 11,853 10,256 11,853 0 1,433 (164) 1,433 0 0 Complete Complete Complete Complete Complete
UFSM HAYOCKS PRIMARY SCHOOL 110,404 91,168 110,404 0 17,361 (1,875) 17,361 0 0 Complete Complete Complete Complete Complete
UFSM KILMORY PRIMARY SCHOOL 65,654 57,473 65,654 0 8,181 0 8,181 0 0 Complete Complete Complete Complete Complete
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,541 73,710 2,082,541 0 116,036 22,247 116,036 0 0 31-Dec-26 31-Dec-26 Feasibility On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 12,000 9,523 12,000 0 2,329 (148) 2,329 0 0 Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 2,302,504 258,179 2,302,504 0 164,157 26,401 164,157 0 0 31-Aug-27 31-Aug-27 On Site On Target On Target
UFSM WHITEHIRST PARK PRIMARY 56,212 52,499 56,212 0 3,676 (38) 3,676 0 0 Complete Complete Complete Complete Complete
Total Primary Education 45,942,842 37,508,246 45,942,842 0 3,476,484 1,532,190 2,189,610 (1,286,874) 0 (1,286,874) 
Secondary Schools
KILWINNING LEARNING ENVIRONMENT 2,768,507 2,768,507 2,768,507 0 920 920 920 0 0 Complete Complete Complete Complete Complete
ARDROSSAN NEW BUILD 114,588,600 15,610,633 114,588,600 0 25,387,922 10,470,850 22,105,566 (3,282,356) (3,282,356) Autumn 2027 Winter 2027 On Site Slightly off target  Slightly off target 
Total Secondary Education 117,357,107 18,379,140 117,357,107 0 25,388,842 10,471,770 22,106,486 (3,282,356) 0 (3,282,356)
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 263,446 298,000 0 35,745 1,190 18,588 (17,157) (17,157) 31-Mar-26 31-Mar-26 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 1,150,759 776,211 1,150,759 0 1,150,759 776,211 1,024,131 (126,628) (126,628) 31-Mar-26 31-Mar-26 On-going On Target On Target
Total Schools Other 1,448,759 1,039,657 1,448,759 0 1,186,504 777,401 1,042,719 (143,785) 0 (143,785)
Total Education 168,779,518 60,928,449 168,779,518 0 30,088,848 12,788,977 25,375,833 (4,713,015) 0 (4,713,015)
CAPITAL MONITORING 2025/26
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2025/26 BUDGETS
# OFFICIAL INFORMATION

Page 16

OFFICIAL INFORMATION#
COMMUNITIES & HOUSING
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual Expenditure
to 31st January
2026
Projected
Expenditure to 31
March 2026
Actual Over/ (Under)
Spend for 2025/26
True Over/(Under)
Spend            
Brought / Carry
Forward to 2026/27 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 0 (38,303) (38,303) Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 73,807 6,563 73,807 0 67,244 0 67,244 0 0 31-Mar-26 31-Mar-26 Procurement On Target On Target
BRODICK TENNIS COURTS 150,662 133,116 150,662 0 150,662 133,116 150,662 0 0 30-Sep-25 30-Sep-25 Construction On Target On Target
CUMBRAE YOUTH FORUM 30,000 0 30,000 0 30,000 0 30,000 0 0 31-Mar-26 31-Mar-26 In Development On Target On Target
GARRISON HOUSE PROJECT 355,698 325,698 355,698 0 355,698 325,698 355,698 0 0 31-Mar-26 31-Mar-26 In Development On Target On Target
Total Information & Cultural 648,470 465,376 648,470 0 641,907 458,814 603,604 (38,303) 0 (38,303)
Other Housing
CCTV REVIEW 350,000 0 350,000 0 262,500 0 262,500 0 0 30-Jun-26 30-Jun-26 Planning On Target On Target
Total Other Housing 350,000 0 350,000 0 262,500 0 262,500 0 0 0
Total Communities & Housing 998,470 465,376 998,470 0 904,407 458,814 866,104 (38,303) 0 (38,303)
Comments
CAPITAL MONITORING 2025/26
Project Description
TOTAL PROJECT 2025/26 BUDGETS COMPLETION DATES DELIVERY STATUS
# OFFICIAL INFORMATION

Page 17

OFFICIAL INFORMATION#
CORPORATE SERVICES
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual
Expenditure to
31st January 2026
Projected
Expenditure to 31
March 2026
Actual Over/
(Under) Spend for
2025/26
True Over/(Under)
Spend            
Brought / Carry
Forward to
2026/27
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 4,065,581 1,764,705 4,065,581 0 384,858 252,783 384,858 0 0 31-Mar-26 31-Mar-26 On-going On Target On Target
TELEPHONY 1,146,693 298,594 1,146,693 0 67,407 19,308 24,407 (43,000) (43,000) 31-Mar-28 31-Mar-28 Implementation On Target On Target
Total IT Strategy 8,797,380 3,648,406 8,797,380 0 452,265 272,090 409,265 (43,000) 0 (43,000)
Total Corporate Services 8,797,380 3,648,406 8,797,380 0 452,265 272,090 409,265 (43,000) 0 (43,000)   
CAPITAL MONITORING 2025/26
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2025/26 BUDGETS
# OFFICIAL INFORMATION

Page 18

OFFICIAL INFORMATION#
HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual Expenditure
to 31st January
2026
Projected Expenditure
to 31 March 2026
Actual Over/
(Under) Spend for
2025/26
True Over/(Under)
Spend            
Brought / Carry
Forward to 2026/27 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £
Management & Support
ECLIPSE 536,058 382,993 536,058 0 292,709 139,644 292,709 0 0 14-Jan-27 14-Jan-27 Construction On Target On Target
47 WEST ROAD 491,797 491,393 491,797 0 0 (404) 0 0 0 Complete Complete Complete Complete Complete
Total Management & Support 1,027,855 874,386 1,027,855 0 292,709 139,241 292,709 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 475,371 463,703 475,371 0 475,371 463,703 545,371 70,000 70,000 31-Mar-26 31-Mar-26 Ongoing On Target On Target 
Total Housing Non HRA 475,371 463,703 475,371 0 475,371 463,703 545,371 70,000 0 70,000
Adults
TRINDLEMOSS 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 0 0
Total Health & Social Care 6,111,303 5,934,241 6,111,303 0 780,006 602,943 850,006 70,000 0 70,000
CommentsProject Description
DELIVERY STATUS
CAPITAL MONITORING 2025/26
2025/26 BUDGETSTOTAL PROJECT COMPLETION DATES
# OFFICIAL INFORMATION

Page 19

OFFICIAL INFORMATION#
PLACE
MILESTONE
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual
Expenditure to
31st January 2026
Projected
Expenditure to 31
March 2026
Actual Over/
(Under) Spend for
2025/26
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2026/27
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 3,459,182 3,783,006 0 3,783,006 3,459,182 3,783,006 0 0 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target 
ROAD SAFETY IMPROVEMENT FUND 16,469 332,158 0 332,158 16,469 332,158 0 0 31-Mar-26 31-Mar-26 In Progress On Target On Target
ROADS REMEDIATION WORKS 34,728 39,651 0 39,651 34,728 39,651 0 0 31-Mar-26 31-Mar-26 In Development On Target On Target
20MPH IMPLEMENTATION 38,601 611,412 0 611,412 38,601 611,412 0 0 31-Mar-26 31-Mar-26 In Development On Target On Target
LIGHTING * 506,665 1,268,076 0 1,268,076 506,665 971,076 (297,000) (297,000) 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target 
UPPER GARNOCK FPS 18,530,827 18,503,801 0 130,051 157,078 130,051 0 0 Complete Complete Complete Complete Complete
MILLPORT COASTAL FPS 41,795,225 42,199,797 0 1,389,849 985,278 1,389,849 0 0 Complete Complete Complete Complete Complete
MILLBURN FPS 469,962 3,103,000 0 1,473,000 96,348 562,348 (910,652) (910,652) 31-Jul-26 31-Jul-26 Tender On Target On Target
MILLPORT PIER 150,080 1,350,000 0 214,960 0 214,960 0 0 31-Dec-27 31-Dec-27 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 483,287 654,939 0 654,939 483,287 483,287 (171,652) (171,652) 31-Mar-26 31-Mar-26 Multiple Projects On Target On Target 
LARGS PROMENADE SEAWALL 4,698,483 4,698,482 0 6,581 6,581 6,581 0 0 Complete Complete Complete Complete Complete
COASTAL ADAPTATIONS 41,070 315,000 0 315,000 41,070 299,000 (16,000) (16,000) 31-Mar-29 31-Mar-29 In Development On Target On Target
B714 UPGRADE 5,523,994 31,693,443 0 5,670,278 2,618,307 3,973,307 (1,696,971) (1,696,971) 31-Aug-27 31-Aug-27 Tender On Target On Target
PARKING CHARGES & DPE 96,147 156,673 0 76,648 16,123 76,648 0 0 31-Mar-26 31-Mar-26 In Development On Target On Target
Total Roads 75,844,720 108,984,436 0 15,965,609 8,459,716 12,873,334 (3,092,275) 0 (3,092,275)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 0 470,683 0 265,991 0 265,991 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, STEV HIGH ROAD - WORKS 518,144 519,644 0 0 (1,500) 0 0 0 Complete Complete Complete Complete Complete
CMTY, KILBIRNIE - WALLS 116,974 120,613 0 1,638 (2,001) 1,638 0 0 Complete Complete Complete Complete Complete
CMTY, BEITH - WALLS 158,868 163,875 0 2,240 (2,768) 2,240 0 0 Complete Complete Complete Complete Complete
CMTY, ABBEY TOWER - WALLS 153,715 161,190 0 39,317 31,842 39,317 0 0 Complete Complete Complete Complete Complete
CMTY, STEV HAWKHILL - WALLS 87,859 89,695 0 4,316 2,480 4,316 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WALLS 106,804 109,914 0 35,109 31,999 35,109 0 0 Complete Complete Complete On Target On Target
CMTY, IRVINE OP CHURCH - WALLS 5,998 5,998 0 3,223 3,223 3,223 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, DREGHORN - WALLS 19,227 19,227 0 5,676 5,676 5,676 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, STEV HIGH KIRK - WORKS 24,732 24,732 0 28 28 28 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 328,128 1,501,663 0 435,373 199,620 435,373 0 0 30-Sep-25 30-Sep-26 Tender Awarded On Target On Target
CMTY, NEW STREET STEV - WALLS 1,015 1,015 0 1,015 1,015 1,015 0 0 Complete Complete Complete Complete Complete
STREET FURNITURE IMPROVEMENT 225,511 225,511 0 2,585 2,585 2,585 0 0 31-Mar-26 31-Mar-26 Planning On Target On Target
PARK ENABLING WORKS 149,415 149,895 0 2,180 1,700 2,180 0 0 31-Mar-26 31-Mar-26 Planning On Target On Target
RENEWAL OF PLAY PARKS 837,955 1,411,000 0 825,197 252,152 262,152 (563,045) (563,045) 31-Mar-27 31-Mar-27 Construction On Target On Target
Total Streetscene 3,198,865 5,439,175 0 1,623,888 526,052 1,060,843 (563,045) 0 (563,045)
Transport
VEHICLES * 3,042,506 3,144,225 0 3,144,225 3,042,506 3,144,225 0 0 31-Mar-26 31-Mar-26 Ongoing On Target On Target 
FLEET DECARBONISATION 261,811 5,300,404 0 526,903 140,310 526,903 0 0 31-Mar-26 31-Mar-26 Ongoing On Target On Target
Total Transport 3,304,317 8,444,629 0 3,671,128 3,182,816 3,671,128 0 0 0
Waste Services
WASTE COMPACTORS 171,485 171,485 0 171,485 171,485 171,485 0 0 Complete Complete Complete Complete Complete
Total Waste Services 13,444,027 13,492,976 0 171,485 171,485 171,485 0 0 0
Renewable Energy
SOLAR PV INVESTMENT - NETHERMAINS 7,991,899 8,171,775 0 768,518 588,642 768,518 0 0 Complete Complete Complete Complete Complete
SOLAR PV INVESTMENT - SHEWALTON 5,707,696 6,073,659 0 1,183,498 817,535 1,183,498 0 0 Complete Complete Complete Complete Complete
NON DOMESTIC ENERGY EFFICIENCY PROGRAMME 1,000,001 1,000,001 0 45,951 45,951 45,951 0 0 Complete Complete Complete Complete Complete
NATURE RESTORATION FUND 403,627 711,001 0 582,976 275,602 582,976 0 0 31-Aug-24 31-Mar-26 Planning On Target On Target 
Total Renewable Energy 15,103,223 15,956,436 0 2,580,943 1,727,730 2,580,943 0 0 0
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT 0 (2,700) 0 (2,700) 0 0 2,700 2,700 31-Mar-26 31-Mar-26 Mulitple projects On Target On Target 
PLI GOWANLEA DAY SERVICES 4,357 27,012 0 27,012 4,357 27,012 0 0 Complete Complete Complete Complete Complete
PLI CASTLEVIEW DAY SERVICES (1) 0 0 0 (1) 0 0 0 Complete Complete Complete Complete Complete
Comments
CAPITAL MONITORING 2025/26
COMPLETION DATES
Project Description
TOTAL PROJECT 2025/26 BUDGETS DELIVERY STATUS
# OFFICIAL INFORMATION

Page 20

OFFICIAL INFORMATION#
PLACE
MILESTONE
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual
Expenditure to
31st January 2026
Projected
Expenditure to 31
March 2026
Actual Over/
(Under) Spend for
2025/26
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2026/27
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2025/26
COMPLETION DATES
Project Description
TOTAL PROJECT 2025/26 BUDGETS DELIVERY STATUS
PLI CENTRAL AVE STREETSCENE DEPOT 1,200 1,200 0 1,200 1,200 1,200 0 0 Complete Complete Complete Complete Complete
PLI GOLDCRAIGS DEPOT (8,252) 157,907 0 1,285 (8,252) 1,285 0 0 Complete Complete Complete Complete Complete
PLI CALEDONIA PRIMARY 93,542 670,765 0 450,000 93,542 450,000 0 0 31-Mar-26 30-Jun-26 Planning On Target On Target
PLI DALRY PRIMARY SCHOOL 4,777 220,000 0 75,000 4,777 75,000 0 0 19-Dec-25 31-Aug-26 Planning On Target On Target
PLI FAIRLIE PRIMARY SCHOOL 7,531 7,531 0 7,531 7,531 7,531 0 0 Complete Complete Complete Complete Complete
PLI HAYOCKS PRIMARY SCHOOL 333,945 379,614 0 379,614 333,945 379,614 0 0 30-Sep-25 31-Mar-26 Construction On Target On Target
PLI PENNYBURN PRIMARY (3,727) 0 0 0 (3,727) 0 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL (5,766) 7,200 0 7,200 (5,766) 7,200 0 0 Complete Complete Complete Complete Complete
PLI ST LUKES PRIMARY SCHOOL 21,477 21,500 0 21,500 21,477 21,500 0 0 Complete Complete Complete Complete Complete
PLI ST WINNINGS PRIMARY SCHOOL 27,333 27,500 0 27,500 27,333 27,500 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE PRIMARY SCHOOL 94,562 94,562 0 94,562 94,562 94,562 0 0 Complete Complete Complete Complete Complete
PLI ARDROSSAN ACADEMY 54,005 54,005 0 54,005 54,005 54,005 0 0 Complete Complete Complete Complete Complete
PLI AUCHENHARVIE ACADEMY* 0 269 0 269 0 269 0 0 Complete Complete Complete Complete Complete
PLI WEST KILBRIDE EARLY YEARS 3,232 3,232 0 3,232 3,232 3,232 0 0 Complete Complete Complete Complete Complete
PLI ARRAN OUTDOOR CENTRE 5,181 5,181 0 5,181 5,181 5,181 0 0 Complete Complete Complete Complete Complete
PLI ANAM CARA 50 50 0 50 50 50 0 0 Complete Complete Complete Complete Complete
PLI BRODICK HWRC 0 21,500 0 21,500 0 21,500 0 0 31-Mar-26 31-Mar-26 Planning On Target On Target
PLI THE PORTAL 47,450 50,000 0 50,000 47,450 50,000 0 0 31-Mar-26 31-Mar-26 Construction On Target On Target
PLI IRVINE WASTE TRANSFER 12,795 12,795 0 12,795 12,795 12,795 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 693,690 1,759,123 0 1,236,736 693,690 1,239,436 2,700 0 2,700
Other Property
LOCALITY BASED PROPERTY REVIEW 0 265,667 0 265,667 0 265,667 0 0 31-Mar-25 31-Mar-27 In development On Target On Target
LBPR - TRINITY CHURCH 1,490 1,490 0 630 630 630 0 0 Complete Complete Complete Complete Complete
LBPR STEVENSTON COMPLEX 4,250 189,250 0 185,000 0 0 (185,000) (185,000) 31-Dec-24 31-Aug-26 Planning On Target On Target
LBPR IRVINE LIBRARY 50,968 50,967 0 12,893 12,893 12,893 0 0 Complete Complete Complete Complete Complete
LBPR BRIDGEGATE HOUSE 2,172 2,172 0 197 197 197 0 0 Complete Complete Complete Complete Complete
LBPR CUNNINGHAME HOUSE 106,262 238,000 0 180,447 48,709 180,447 0 0 31-Mar-27 31-Mar-27 Construction On Target On Target
LBPR CUNNINGHAME HOUSE GRD EAST/4TH WEST 855,974 1,248,118 0 1,164,752 772,608 1,164,752 0 0 31-Mar-26 31-Mar-26 Construction On Target On Target
LBPR CUNNINGHAME HOUSE GRD WEST 169,951 201,777 0 37,687 5,862 37,687 0 0 Complete Complete Complete Complete Complete
LBPR - THE TOWNHOUSE 4,280 25,000 0 21,420 700 21,420 0 0 31-Jul-25 31-Mar-26 Planning On Target On Target
LBPR THE CIRCUIT 143,500 311,571 0 290,623 122,552 290,623 0 0 31-Mar-27 31-Mar-26 Planning On Target On Target
EMERGENCY CONTROL CTR 151,476 158,000 0 3,111 (3,413) 3,111 0 0 Complete Complete Complete Complete Complete
GOLDCRAIGS REFURBISHMENT 1,020,013 1,163,495 0 969,738 826,256 969,738 0 0 Complete Complete Complete Complete Complete
SALT DOME GOLDCRAIGS 175,401 342,496 0 342,496 175,401 342,496 0 0 31-Mar-26 31-Mar-26 Planning On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 109,065 134,641 0 23,519 (2,057) 23,519 0 0 Complete Complete Complete Complete Complete
Total Property 2,809,790 4,347,632 0 3,498,180 1,960,338 3,313,180 (185,000) 0 (185,000)   
Regeneration
REPURPOSING PROPERTY GRANT FUND 24,417 419,591 0 118,911 23,737 67,360 (51,551) (51,551) 30-May-25 31-Mar-27 In development On Target On Target
MILLPORT TOWN HALL PHASE 2 (6,896) 58,129 0 58,129 (6,896) 58,129 0 0 Complete Complete Complete Complete Complete Community led regeneration project by Millport Town
H ll Ch it P j t h b d l d d t ISLANDS PIT STOPS 116,039 507,540 0 507,540 116,039 326,039 (181,501) (181,501) 31-Jul-25 31-Jul-26 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 70,979 270,151 0 125,000 40,202 125,000 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 279,008 576,535 0 576,535 279,008 576,535 0 0 31-Mar-26 30-Sep-26 In development On Target On Target
KILDONAN HALL 0 25,000 0 25,000 0 25,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
AYRSHIRE 5GIR 3,819,710 4,366,000 0 856,711 310,421 856,711 0 0 30-Sep-25 31-Mar-26 Construction On Target On Target
PBIP – KILWINNING ABBEY IMPROVEMENTS 356 264,559 0 14,203 0 14,203 0 0 31-Mar-25 31-Dec-26 Construction On Target On Target
LOCHSHORE HUB PLAY AREA 303,592 355,000 0 13,265 4,838 13,265 0 0 Complete Complete Complete Complete Complete
PBIP 36 BANK STREET 120,162 139,999 0 19,837 0 19,837 0 0 31-Dec-25 31-Mar-26 In development On Target On Target
PBIP GALT HOUSE 49,444 49,444 0 8,328 8,328 8,328 0 0 Complete Complete Complete Complete Complete
IRVINE HIGH STREET 2,723,228 2,837,315 0 99,298 (14,789) 99,298 0 0 Complete Complete Complete Complete Complete
MILLPORT CARS 0 0 (10,993) 10,993 0 0 (10,993) (10,993) 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK MASTERPLAN 1,934,777 4,218,597 0 282,207 63,386 150,000 (132,207) (132,207) 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 2,018,849 2,101,881 0 116,825 33,793 45,000 (71,825) (71,825) 31-May-25 01-Dec-26 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,102,507 4,170,999 0 72,430 3,938 72,430 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 166,367 4,525,506 0 81,051 17,212 47,212 (33,839) (33,839) 31-Mar-27 31-Mar-28 In development On Target On Target
VDLF - ANNICKBANK PH 3 1,944,450 1,948,996 0 10,465 5,919 10,465 0 0 Complete Complete Complete Complete Complete
# OFFICIAL INFORMATION

Page 21

OFFICIAL INFORMATION#
PLACE
MILESTONE
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual
Expenditure to
31st January 2026
Projected
Expenditure to 31
March 2026
Actual Over/
(Under) Spend for
2025/26
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2026/27
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2025/26
COMPLETION DATES
Project Description
TOTAL PROJECT 2025/26 BUDGETS DELIVERY STATUS
LUF3 - ANNICKBANK 136,661 6,074,602 0 951,940 56,566 60,950 (890,990) (890,990) 31-Mar-27 31-Mar-28 In development On Target On Target
VDLF - DEVELOPMENT WORK 115,055 229,097 0 135,630 21,588 65,630 (70,000) (70,000) 31-Mar-26 31-Dec-26 In development On Target On Target
MONTGOMERIE PARK NEIGHBOURHOOD CTR 179,307 260,384 0 81,077 0 81,077 0 0 30-Sep-24 31-Mar-26 Construction On Target On Target
VDLF STALLED SPACES FUND 0 113,000 0 25,000 0 0 (25,000) (25,000) 31-Mar-27 31-Mar-27 In development On Target On Target
LOCHSHORE GARDEN/ACTIVITY HUB 68,961 827,075 0 125,000 68,961 125,000 0 0 31-Dec-26 31-Dec-26 In development On Target On Target
NORTH SHORE RESIDENTIAL 0 150,000 0 25,000 0 5,000 (20,000) (20,000) 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP DOCKHEAD STREET 0 250,000 0 50,000 0 0 (50,000) (50,000) 31-Mar-26 31-Mar-27 In development On Target On Target
PBIP COMMUNITY PROJECT FUND 94,521 144,421 0 144,421 94,521 144,421 0 0 31-Mar-26 31-Mar-27 In development On Target On Target
PBIP PUBLIC SPACE CAMERA 0 50,000 0 50,000 0 50,000 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP BEITH KIRK 0 41,000 0 41,000 0 11,000 (30,000) (30,000) 31-Mar-26 31-Dec-26 In development On Target On Target
PBIP HAYOCKS HALL COMMUNITY LARDER 0 32,500 0 32,500 0 0 (32,500) (32,500) 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP CRANBERRY MOSS COMMUNITY CENTRE 0 32,500 0 32,500 0 0 (32,500) (32,500) 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP SHEWALTON POND ACCESS IMPROVEMENTS 0 27,500 0 27,500 0 0 (27,500) (27,500) 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP EGLINTON PARK IMPROVEMENTS 0 10,000 0 10,000 0 0 (10,000) (10,000) 31-Mar-27 31-Mar-27 In development On Target On Target
PRIDE IN PLACE IMPACT FUND 0 1,500,000 0 1,500,000 0 0 (1,500,000) (1,500,000) 31-Mar-27 31-Mar-27 Planning On Target On Target
QUARRY ROAD PHASE 2 5,204,719 5,204,719 0 0 0 0 0 0 Complete Complete Complete Complete Complete
ACTIVE TRAVEL TIER 1 3,099,113 623,927 0 623,927 168,165 623,927 0 0 31-Mar-26 31-Mar-27 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME 9,802 166,760 0 166,760 9,802 166,760 0 0 31-Mar-26 31-Mar-27 Various On Target On Target
LOCAL AUTHORITY DIRECT AWARD 22,934 41,337 0 41,337 22,934 41,337 0 0 31-Mar-26 31-Mar-26 Various On Target On Target
RTPI - NORTH COAST AND GARNOCK VALLEY 2,586 6,000 0 6,000 2,586 6,000 0 0 31-Mar-26 31-Mar-26 Construction On Target On Target
FAIRLIE COASTAL PATH (12,091) 0 0 0 (12,091) 0 0 0 Complete Complete Complete Complete Complete
ARDROSSAN PROMENADE 767,272 1,307 0 1,307 (19,422) 1,307 0 0 Complete Complete Complete Complete Complete
B777 CORRIDOR IMPROVEMENTS 111,771 137,767 0 25,996 0 25,996 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
SALTCOATS OLD CAL RAILWAY PH2 14,085 49,990 0 49,990 14,085 49,990 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
BUS INFRASTRUCTURE FUND 2,586 288,000 0 288,000 2,586 288,000 0 0 31-Mar-26 31-Mar-26 Construction On Target On Target
NCN7 CROSSING IMPROVEMENTS 15,500 40,000 0 40,000 15,500 40,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
B714 SHARPHILL TO NCN AT ROUTE 0 161,240 0 161,240 0 161,240 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
CUMBRAE AT ROUTE 0 50,000 0 50,000 0 50,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
GIRDLE TOLL TO IRVINE TOWN AT ROUTE 25,229 80,000 0 80,000 25,229 80,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
IRVINE TO DRYBRIDGE AT ROUTE 4,800 8,000 0 8,000 4,800 8,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
LINKS TO EGLINTON PARK 168,176 282,531 0 114,355 0 114,355 0 0 31-Dec-25 30-Jan-26 Construction On Target On Target
NCN7 VALEFIELD/GLENGARNOCK BRIDGE 3,500 65,500 0 62,000 0 62,000 0 0 31-Mar-26 31-Mar-26 In development On Target On Target
LONG DRIVE 12,968 956,620 0 551,372 12,968 551,372 0 0 31-Mar-26 31-Mar-26 Construction On Target On Target
RIVERSIDE WAY 2,838 867,180 0 49,010 2,838 49,010 0 0 31-Mar-26 31-Aug-26 In development On Target On Target
STRATEGIC INVESTMENT ROUTE 76,835 2,386,826 0 278,000 76,835 205,000 (73,000) (73,000) 31-Mar-27 31-Mar-27 Construction On Target On Target
KYLE ROAD AT ROUTE 17,037 1,073,678 0 46,000 17,037 46,000 0 0 31-Mar-26 31-Aug-26 In development On Target On Target
HEATHERHOUSE JUNCTION 0 475,000 0 50,000 0 50,000 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
Total Regeneration 27,813,551 49,593,702 (10,993) 8,921,590 1,470,623 5,678,184 (3,243,406) (10,993) (3,232,413)
Ayrshire Growth Deal
AGD - I3 DPMC PHASE 1 662,560 1,000,000 0 727,311 389,871 727,311 0 0 31-Mar-26 31-Mar-26 Delivery On Target On Target
AGD - I3 DPMC PHASE 2 329,870 5,000,000 0 50,000 15,502 20,000 (30,000) (30,000) 31-Mar-29 31-Mar-30 Feasibility On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 4,823,336 4,855,546 0 10,645 (21,564) 24,131 13,486 13,486 Complete Complete Complete Complete Complete
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 422,095 15,568,282 0 139,304 66,446 139,304 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY &
CIRCULAR ECONOMY
291,224 18,040,000 0 50,000 23,491 35,000 (15,000) (15,000) 31-Mar-30 30-Nov-30 Feasibility On Target Slightly off target 
AGD - GREAT HARBOUR 4,034,266 14,338,771 0 4,165,209 2,523,438 3,483,112 (682,097) (682,097) 31-Mar-29 31-Mar-27 Delivery On Target On Target
AGD GH PHASE 2 87,495 122,581 0 122,581 87,495 134,988 12,407 12,407 31-Mar-29 31-Mar-29 Design On Target On Target
AGD GH PHASE 3 1,123 0 0 0 1,123 0 0 0 31-Mar-29 31-Mar-29 Feasibility On Target On Target
AGD - IMSE 208,895 10,500,000 0 100,000 34,287 71,000 (29,000) (29,000) 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - MARINE TOURISM ARRAN 256,015 2,059,242 0 49,000 49,255 68,000 19,000 19,000 31-Mar-29 31-Mar-30 Feasibility On Target Significantly off
t t AGD - MARINE TOURISM CUMBRAE 290,871 4,783,528 0 191,000 84,486 101,000 (90,000) (90,000) 31-Mar-29 31-Mar-30 Design On Target Significantly off
t t Total Ayrshire Growth Deal 11,683,466 79,043,664 0 5,605,050 3,253,831 4,803,846 (801,204) 0 (801,204)
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 607,170 4,127,113 0 3,524,633 4,690 6,634 (3,517,999) (3,517,999) 1st Qtr 2026 TBC Design On Hold On Hold
IRVINE ENTERPRISE AREA 0 10,736,892 0 103,079 0 0 (103,079) (103,079) Ongoing Ongoing Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 45,972,917 47,866,143 0 5,456,598 5,293,676 5,456,598 0 0 Complete Complete Complete Complete Complete
# OFFICIAL INFORMATION

Page 22

OFFICIAL INFORMATION#
PLACE
MILESTONE
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2025/26
Actual
Expenditure to
31st January 2026
Projected
Expenditure to 31
March 2026
Actual Over/
(Under) Spend for
2025/26
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2026/27
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2025/26
COMPLETION DATES
Project Description
TOTAL PROJECT 2025/26 BUDGETS DELIVERY STATUS
VDLF - HARBOUR MASTERS OFFICE 158,740 158,740 0 3,720 3,720 3,720 0 0 Complete Complete Complete Complete Complete
VDLF - I3 IRVINE ENTERPRISE 257,020 278,170 0 21,150 0 21,150 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
MARINE TOURISM LOCHRANZA 0 129,718 0 129,718 0 129,718 0 0 31-Mar-26 31-Mar-26 Development On Target On Target
Other Growth & Investment 46,995,847 63,296,777 0 9,238,898 5,302,086 5,617,820 (3,621,078) 0 (3,621,078)
Total Economic Development & Regeneration 86,492,865 191,934,143 (10,993) 23,765,538 10,026,539 16,099,850 (7,665,688) (10,993) (7,654,695)
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,377,163 3,378,163 0 0 (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 2,957,751 2,977,098 0 24,269 4,922 24,269 0 0 Complete Complete Defects Period Complete Complete
Total Completed Projects 6,334,915 6,355,262 0 24,269 3,922 24,269 0 0 0
Total Place 207,226,411 356,713,813 (10,993) 52,537,776 26,752,287 41,034,468 (11,503,308) (10,993) (11,492,315)
# OFFICIAL INFORMATION

Page 23

OFFICIAL INFORMATION#
OTHER BUDGETS
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2025/26
Actual Expenditure
to 31st January 2026
Projected
Expenditure to 31
March 2026
Over/ (Under)
Spend for 25/26
£ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 14,124,882 0 14,124,882 0 (19,614) 0 (19,614) 0
CORE INFRASTRUCTURE INVESTMENT 2,001,000 0 2,001,000 0 1,000 0 1,000 0
Total Other Budgets 16,125,882 0 16,125,882 0 (18,614) 0 (18,614) 0
2025/26 BUDGETS
CommentsProject Description
TOTAL PROJECT
# OFFICIAL INFORMATION

Page 24

OFFICIAL-PROTECT INFORMATION#
HRA Capital Statement 2526 Appendix 2
TOTAL PROJECT CURRENT YEAR 2025/26 - Period 9
Project Description Total Project
Budget           
Cumulative
Expenditure to
date
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2025/26
Actual
Expenditure
to 31
December
2025
P9 Projection Virement
Request
Carry /Brought
Forward to
/From Future
Years
True Over/
(Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
EXPENDITURE
Council House Building
Afton Court 1,335,654 1,249,903 1,249,898 (85,756) Complete Complete Complete.
Flatt Road 20,178,000 19,709,075 19,709,046 (468,954) 0 0 Complete Complete Complete
Friars Lawn 2,199,628 2,085,565 2,085,598 (114,030) 0 0 Complete Complete Complete
Garrier Court 2,335,551 2,414,910 2,348,027 12,476 0 0 Complete Complete Complete
Harbourside 14,622,742 14,362,889 14,622,742 0 152,530 500 152,530 Complete Complete Complete
James McFarlane Site 4,784,118 4,662,248 4,784,118 0 269,341 110,558 269,341 Complete Complete Complete
Laburnum Ave/Newhouse Dr (Regen 1a&b) 3,274,506 2,850,629 2,953,449 (321,057) 257,091 139,682 257,091 Complete Complete Complete
Largs Police Station 2,769,301 2,759,798 2,769,301 0 1,258 1,997 1,258 Complete Complete Complete
Stanecastle Site 7,768,147 7,768,069 7,768,147 0 349,805 199,361 349,805 Complete Complete Complete
St Beya Gardens 3,691,052 3,705,708 3,691,052 0 0 0 Complete Complete Complete 
St Michael's Wynd 13,996,769 14,676,042 14,087,664 90,895 0 0 Complete Complete Complete
Ukraine Buy Backs 673,961 0 0 Complete Complete Complete
St Mary's Primary, Largs 6,851,623 4,004,232 6,851,623 474,703 (40,152) 51,671 (423,032) Complete Complete Complete
Towerlands Primary School 8,579,943 8,574,482 8,579,943 0 0 0 Complete
Ayrshire Central Site 51,235,455 18,236,694 51,235,455 0 16,653,034 10,702,345 15,352,187 (1,300,847) On Target On Target Work continues to progress on site and is currently expected to complete during winter
2027.
Bourtreehill Village 9,924,743 340,181 9,924,743 0 128,176 90,706 128,176 On Target On Target Demolition of Crofthead Court complete. Professional fees only to be incurred during
2025/26.
Fullarton Street (High Flats) 12,073,511 116,600 12,073,511 0 70,000 52,967 70,000 On Target On Target Projected spend during 2025/26 is for statutory consents & consultancy fees only.
Garnock Academy Site 12,092,889 10,659,263 12,092,889 0 5,650,169 4,017,003 5,216,926 (433,243) On Target On Target Work continues to progress on site and Ashleigh (Scotland) Limited hope to complete works
by late summer 2026, amended from spring 2026 due to utilities delays. First handovers are
expected end February/ beginning March 2026.
Kings Arms (113-115 High Street) 2,904,416 2,268,932 2,904,416 0 1,655,832 1,011,171 1,422,819 (233,013) On Target Significantly off target McLaughlin Construction have submitted an updated programme and now expect to
complete the Irvine town centre project during spring 2026.
Montgomerie Park (Both Phases) 46,322,381 7,491,839 46,322,381 0 250,000 14,028 250,000 On Target Slightly off target  Infrastructure works delay due to phasing of works alongside adjacent sites. Final plan
consultation event took placee in August 2025.
St Michaels Phase 3 627,239 0 0
Nelson Street Regeneration 622,116 33,973 622,116 0 176,772 2,226 5,000 (171,772) On Target On Target Tender application with Scottish Government for review/ approval.
Acquisition Houses-Open Market 1,273,080 445,863 1,273,080 0 1,303,080 280,755 651,074 (652,006) On Target On Target
Harbour Street 0 0 0 0 0 0 On Target On Target Project removed from the SHIP 2025-2030 as at 3 December 2024.
Grange Court, Stevenston 19,854 25,000 19,854 25,000 On Target On Target Demolition of existing flats currently out to tender.
Future Years Projects 13,742 0 0
Nursery Place 0 25,000 0 25,000 Final plans consultation event to be scheduled.
Corsehillhead (Shadow Programme) 2,032,906 87,766 2,032,906 0 0 0 On Target On Target Project in SHIP 2026-2031 Shadow Programme
James Reid Site (Shadow Programme) 11,820,675 320,087 11,820,675 0 501 16,995 501 Significantly off
target
Significantly off target Project in SHIP 2026-2031 Shadow Programme
Internal Management Charges 1,489,046 1,117,464 1,489,046 0 1,489,046 1,117,464 1,489,046 On Target On Target
Regeneration Project 1e Consultants Fees 20,040 0 20,040
Contingency 4,012,524 0 2,988,321 3,306,377 0 3,305,562 (815)
House Building - General 10,890 0 3,210
SUB TOTAL 248,190,776 131,297,046 246,280,147 (886,425) 32,237,715 17,757,499 29,022,987 (815) (2,790,881) (423,032)
DELIVERY STATUS
# OFFICIAL-PROTECT INFORMATION

Page 25

OFFICIAL-PROTECT INFORMATION#
TOTAL PROJECT CURRENT YEAR 2025/26 - Period 9
Project Description Total Project
Budget           
Cumulative
Expenditure to
date
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2025/26
Actual
Expenditure
to 31
December
2025
P9 Projection Virement
Request
Carry /Brought
Forward to
/From Future
Years
True Over/
(Under)
Spend
Delivery Status
Financial Delivery Status Physical Narrative
DELIVERY STATUS
Improvements to existing stock
Wet Room - Void 358,932 184,261 313,441 (45,491) 358,932 184,261 293,674 (65,258) On Target On Target lower projected unit nos than budgeted
Bathrooms - Void 454,905 264,732 278,630 (176,275) 454,905 264,732 373,515 (81,390) On Target On Target lower projected unit nos than budgeted
Wet Room - Planned 119,644 0 119,644 0 119,644 0 119,644 On Target On Target
Bathrooms - Planned 168,315 138,394 168,315 0 168,315 138,394 168,315 On Target On Target
Secondary bathrooms planned 8,542 0 8,542 0 8,542 0 8,542
Electrical Rewiring 835,384 748,565 835,384 0 835,384 748,565 895,915 60,531 On Target On Target Overspend includes anticipated additional voids
Heating 1,734,209 1,381,820 1,734,209 0 1,734,209 1,381,820 1,734,209 On Target On Target
Kitchens 1,779,146 962,284 1,779,146 0 1,779,146 962,284 1,647,750 (131,396) On Target On Target
Kitchens - Void 1,014,043 680,078 1,086,928 72,885 1,014,043 680,078 1,000,478 (13,565) On Target On Target additional projected unit nos
Roofing 583,568 231,620 740,881 157,313 636,619 231,620 727,761 91,142 0 On Target On Target Additional works required
Wallfloor rendering 1,027,725 536,215 1,027,725 0 1,027,725 536,215 1,027,725 On Target On Target
EWI 468,769 44,143 311,456 (157,313) 415,718 44,143 311,456 (91,142) (13,120) On Target On Target
Window Replacement 513,985 121,367 513,985 0 390,985 121,367 390,985 On Target On Target Communal element of works not possible to be carried out before March.
Saltcoats MSF Investment 222,079 (30,527) 222,079 0 222,079 (30,527) 222,079 On Target On Target
Smoke Detector Programme 486,937 314,265 486,937 0 486,937 314,265 486,937 On Target On Target
Energy Efficiency 1,073,280 5,229 0 (1,073,280) 0 5,229 10,000 10,000 On Target On Target may be a future carry forward beyond 2627. Still awaiting updated guidance from Scottish
Govt re SHNZS
Path Finder Project 459,856 0 459,856 0 50,000 0 25,000 (25,000) Significantly off
target
Significantly off target Difficulty in gaining access to properties to allow the work to be carried out. PMI are to
identify new addresses.
Solar Panels 2,648,098 1,144,594 2,648,098 0 2,590,000 1,144,594 2,599,368 9,368 On Target On Target ower anticipated costs
HRA Slippage (3,018,759) 0 (1,945,479) 1,073,280 (1,945,479) 0 (1,945,479)
SUB TOTAL 13,957,417 6,727,041 12,735,256 (1,222,161) 10,347,704 6,727,041 10,097,874 0 (137,028) (112,802)
Other Capital works
Estate Based Regeneration 2,208,307 482,040 1,591,351 (616,956) 1,599,716 482,040 1,392,421 (207,295) On Target On Target Underspend across various projects to be carried forward
Lift Replacement 568,420 286,026 568,420 0 568,420 286,026 568,420 On Target On Target
Sheltered Housing Units 578,939 159,684 497,855 (81,084) 326,099 159,684 340,650 14,551 Slightly off target  On Target Final account agreed for Barnett court. Underspend to be added to overall SHU budget
High Flats Demolition 0 0 0 0 0 0 On Target On Target
Other Capital Works (815) 5,434 (815) 0 (815) 5,434 0 815
Energy Efficiency 5,229 0 5,229
SUB TOTAL 3,355,666 927,750 2,657,626 (698,040) 2,493,420 938,413 2,301,491 815 (192,744) 0
Total Expenditure 251,546,442 132,224,796 248,937,773 (1,584,465) 45,078,839 25,422,954 41,422,352 0 (3,120,653) (535,834)
Income
Affordable Housing Contributn (721,008) (721,008)
CFCR (8,348,729) (8,348,729)
Capital Grants (10,104,000) (9,705,440) (10,104,000)
Prudential Borrowing (25,091,904) (21,435,417) 3,120,653 535,834 Reduced borrowing required to reflect rephasing and projected underspends
Use of Reserves (721,620) (721,620)
Sale of Assets (11,684) (13,244) (11,684) Capital receipts.
Other Capital Income (79,894) (79,894) (79,894) Credit from Scottish water re Harbourside
0
SUB TOTAL (45,078,839) (9,798,578) (41,422,352) 0 3,120,653 535,834
Total Project Expenditure 251,546,442 132,224,796 248,937,773 (1,584,465) 45,078,839 25,422,954 41,422,352 0 (3,120,653) (535,834)
Total Project Income (45,078,839) (9,798,578) (41,422,352) 0 3,120,653 535,834
Total Net Expenditure 0 15,624,376 0 0 0 0
# OFFICIAL-PROTECT INFORMATION

Page 26

OFFICIAL-PROTECT INFORMATION#
# OFFICIAL-PROTECT INFORMATION

Page 27

OFFICIAL-PROTECT INFORMATION#
# OFFICIAL-PROTECT INFORMATION

Page 28

Appendix 3
Treasury Management Performance to 31 January 2026    
Capital Expenditure for both the General Fund and HRA vary from original estimates
due to changes in the profile of projects. Full details of all movements in the capital
expenditure budgets are included in this report.  
The reduction to the Capital Financing Requirement for both the General Fund and
the HRA reflect the change in profile of the capital programme. 
Capital expenditure impacts on the revenue budget through financing charges so it is
essential the Council ensures the financing costs remain affordable and do not
constitute an excessive proportion of the revenue resources available.   From a
General Fund perspective, the latest Scottish Local Authority average was 6.0%,
thereby demonstrating a prudent borrowing policy.   For the HRA, the Scottish
average was 20.1%. The level of loan charges is deemed prudent and affordable
within the framework of the 30 year Housing business plan.  
2025/26 2025/26 2025/26
Original Estimate P10 Projection Movement
£m £m £m
General Services Capital expenditure                     95.807                      68.517                     (27.290)
Funded by:
Borrowing                     54.463                      36.410                     (18.053)
Receipts / Grants                     40.640                      31.749                       (8.891)
Funded from Revenue                            -                           0.358                        0.358
Funded from Reserves                       0.704                             -                          (0.704)
Total                     95.807                      68.517                     (27.290)
HRA Capital expenditure                     46.003                      41.422                       (4.581)
Funded by:
Borrowing                     26.107                      21.435                       (4.672)
Receipts / Grants                     10.104                      10.184                        0.080
Funded from Revenue                       8.349                        8.349                             -   
Funded from Reserves                       1.443                        1.454                        0.011
Total                     46.003                      41.422                       (4.581)
Estimates of Capital Expenditure and Income
2025/26 2025/26 2025/26
Original Estimate P10 Projection Movement
£m £m £m
General Services                   466.086                    428.750                     (37.336)
HRA                   224.461                    211.820                     (12.641)
Sub-total                   690.547                    640.570                     (49.977)
Less PPP/NPD long-term liability                    (78.590)                    (78.590)                            -   
Loans Capital Financing Requirement (CFR)                   611.957                    561.980                     (49.977)
Capital Financing Requirement (CFR)
2025/26 2025/26
Original Estimate P10 Projection
% %
General Services 4.1% 3.5%
HRA 26.5% 26.3%
Proportion of financing costs to net revenue
stream

Page 29

The Council is currently projecting an under-borrowed position of £55.304m due to
the continuing strategy to delay long-term external borrowing by utilising internal
cash balances. 
Liability Benchmark
The liability benchmark is an important tool to help establish whether the Council is
likely to be a long-term borrower or long-term investor in the future and so shape its
strategic focus and decision making. 
The Liability benchmark graph above is used to inform the Council’s borrowing
strategy.  The shaded grey area shows the Councils current debt and the gap
between this and the Liability benchmark line is how much more borrowing the
Council likely needs to undertake to support its current capital plans once taking into
account its balance sheet resources including the net debtor / creditor and useable
reserves.  The above graph indicates that long term borrowing for the period of
around 20 years would be most appropriate to meet the Councils borrowing needs
and mitigate against interest rate risk.
2025/26 2025/26 2025/26
Original Estimate P10 Projection Movement
£m £m £m
Gross Debt at 31 March                   556.653                    506.676                     (49.977)
CFR                   611.957                    561.980                     (49.977)
(Under)/Over Borrowed Position                    (55.304)                    (55.304)                       0.000
Current Portfolio Position (excluding PPP/NPD)
0
200
400
600
800
1,000
1,200
2025 2029 2033 2037 2041 2045 2049 2053 2057 2061 2065 2069 2073
£m Liability Benchmark - North Ayrshire
Fixed rate loans LOBO loans Variable rate loans

Page 30

The maturity structure of the debt portfolio at 31 January 2026 is shown below and
shows the period when the Council is required to repay and/or refinance debt. It is
important to ensure a reasonable spread of debt to mitigate against high exposure
levels in respect of refinancing.  The current profile ensures this: 
The reduction in the external borrowing since 31 March relates to maturing loans
during the period to 31 January including a £5.6m LOBO loan which was repaid
when called in May.  
2025/26 2025/26 2025/26
Original Estimate
£m P10 Projection Movement
£m
Loans CFR                   611.957                    561.980                     (49.977)
Less Balance sheet resources                    (94.794)                  (110.088)                    (15.294)
Net loans requirement                   517.163                    451.892                     (65.271)
Liquidity allowance                     10.000                      10.000                             -   
Liability Benchmark                   527.163                    461.892                     (65.271)
Liability Benchmark
31-Mar-25 31-Jan-26
Maturity Profile of Borrowing (Indicator 10) Actual Actual Movement
£m £m £m
Under 12 months                      44.954                      32.685                     (12.269)
12 months and within 24 months                       4.917                        5.805                        0.888
24 months and within 5 years                     42.049                      69.071                      27.022
5 years and within 10 years                   102.667                      98.343                       (4.324)
10 years and within 20 years                   115.780                    103.335                     (12.445)
20 years and within 30 years                     15.925                      15.925                             -   
30 years and within 40 years                     92.587                      92.587                             -   
40 years and within 50 years                            -                                -                                -   
50 years and above                     10.000                      10.000                             -   
Total Borrowing                   428.879                    427.751                       (1.128)