North Ayrshire Council · 30 September 2025
Back to Cabinet — 30 September 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

NORTH AYRSHIRE COUNCIL
30 September 2025
Cabinet
Title: Local Housing Strategy 2023–2028: 2024/25 Progress
Update
Purpose: To provide Cabinet with an annual update on progress of
the Local Housing Strategy 2023-2028 and to seek
approval for the update to be submitted to Scottish
Government.
Recommendation(s): It is proposed that Cabinet: (i) notes the content of this
report and progress against the LHS Action Plan, with
further details provided in Appendix 1; (ii) approves the
addition of the three new actions outlined at para 2.48, with
further details provided in Appendix 1; and (iii) approves
submission of the LHS update to the Scottish Government.
1. Executive Summary
1.1. The Housing (Scotland) Act 2001 places a statutory duty on local authorities to
produce a Local Housing Strategy that sets out its strategy, priorities, and plans
for the delivery of housing and related services. 
1.2. The North Ayrshire Local Housing Strategy 2023–2028 was approved by Cabinet
on 13 June 2023 and sets out the strategic priorities for tackling housing issues
in the area during the five-year period. 
1.3. The Local Housing Strategy enables the Council to monitor progress against
national and local priorities. It is a statutory requirement for a Local Housing
Strategy to be kept under review; the Scottish Government expects all local
authorities to review and report on progress annually. 
1.4. This report provides an overview on progress made to 31 March 2025 on the
delivery of the Local Housing Strategy 2023-2028. 
1.5. Cabinet is invited to note the contents of the report; approve the addition of the
three new actions outlined at para 2.48, with further details provided in
Appendix 1; and approve submission of the LHS update 2024/25 to the
Scottish Government. 
2. Background 
2.1. The Housing (Scotland) Act 2001 sets out local authorities’ duties to prepare a
Local Housing Strategy which details the Council’s strategy, priorities, and plans
for the delivery of housing and related services. The 2001 Act states that the
Local Housing Strategy must be: 
• supported by an assessment of housing provision, including the need and
demand for housing-related services;

Page 2

• submitted to Scottish Ministers; and
• kept under review by the Council. 
2.2. The Scottish Government expects all local authorities to review and report on
progress annually. 
2.3. The North Ayrshire Local Housing Strategy 2023-2028 was approved by Cabinet
on 13 June 2023 and sets out the strategic ambition for Housing in North
Ayrshire: “we want all our people to live in the right homes, in great places, with
access to any support services they need”. Four overarching outcomes were
developed to achieve this ambition, which align to our Council Plan and the four
key strategies in the Scottish Government’s ‘Housing to 2040’ vision: 
• Outcome 1: More homes at the heart of great places – Our places
support thriving and inclusive communities; 
• Outcome 2: Affordability and choice – Our people have affordable
homes in the places they choose to live; 
• Outcome 3: Affordable warmth and zero emissions – Our homes are
energy efficient and release less emissions; 
• Outcome 4: Improving the Quality of our Homes – Our homes are in
good condition and people can access any support services they need. 
Achievements to Date 
2.4. To measure the outcomes of the Local Housing Strategy 2023-28 an action plan
was developed (see Appendix 1), with 42 actions each having their own desired
outcome and targeted completion date. The strategy is now in its second year of
implementation and there have been a number of successes within the action
plan to date. These are grouped under each of the approved LHS outcomes
noted at paragraph 2.3: 
Outcome 1 – More homes at the heart of great places 
2.5. The Local Housing Strategy aims to support the Council’s Community Wealth
Building approach and Regeneration Delivery Plan to make our area more
successful for everyone, improving our places, establishing thriving town
centres, supporting health and well-being, and providing more opportunities for
a better quality of life. Housing can make a strong contribution to regeneration
by contributing to positive health outcomes and supporting a sense of
community. During 2024/25 the Council utilised its role as a major house
builder in North Ayrshire to maximise local employment and training
opportunities. For example, two modern apprentices and a graduate apprentice
have been employed at the Council’s Garnock Academy site. The contractor
has also delivered a number of employability and career sessions for school
children via the Council’s Employability team.

Page 3

2.6. A total of 91 new homes were delivered during 2024/25 by the Council and our
Registered Social Landlord (RSL) partners, as follows: 
Development Number
of Homes
Additional Comments
St Mary’s Gardens, Largs 26 This development replaced the former St
Mary's Primary School
Stanecastle, Irvine 18 This development replaced the former
Stanecastle Primary School
James McFarlane,
Ardrossan
17 This development replaced the former
James McFarlane Primary School
Laburnum Avenue, Beith 7 Housing regeneration project
Newhouse Drive, Kilbirnie 3 Housing regeneration project
Garven Road, Stevenston 20 CHA development 
2.7. The Council’s new build project at Stanecastle, Irvine (29 homes, 31 units)
concluded during April 2025. The Newhouse Drive, Kilbirnie (7 units) and
James McFarlane, Ardrossan (19 units) Council projects concluded during May
2025. 
2.8. In addition, works are currently underway at the following new Council
developments: 
• Ayrshire Central Hospital, Irvine (202 units)
• Garnock Academy, Kilbirnie (50 units)
• King’s Arms, Irvine (6 units) 
2.9. The Council developments listed above contribute to the Council’s latest
commitment to deliver 1,643 new homes. The Strategic Housing Investment
Plan (SHIP) 2025-2030, approved by Cabinet on 3 December 2024, sets out
the Council and its partners commitment to deliver new affordable homes in
North Ayrshire, supporting the Scottish Government’s target to deliver 110,000
new affordable homes by 2032. The revised SHIP 2026-2031 will be presented
to Cabinet on 28 October 2025. 
2.10. Private developers delivered 280 new homes during 2024/25 at active sites,
bringing the number of units delivered by the private sector to 528 since April
2023. Development is underway at all five new sites allocated by LDP2, which
together will deliver over 1,000 private sector homes in addition to other active
sites including Montgomerie Park and West Byrehill. Planning Services
submitted the Draft Delivery Programme to Scottish Government on 8 April
2025 - setting out actions required to deliver sites within the housing land
supply - and are progressing towards finalising the 2025/26 Housing Land Audit
and Delivery Programme, which will be published following its approval
alongside the LDP Evidence Report. 
Outcome 2 – Affordability and choice

Page 4

2.11. The Scottish housing system is under significant pressure, with the Scottish
Government having declared a national Housing Emergency on 15 May 2024
and 13 local authorities having declared their own housing emergencies due to
the unprecedented pressure to meet their statutory responsibilities towards
homeless people and other priority groups in housing need. On 2 September
2025, the Scottish Government published its Housing Emergency Action Plan,
with three main areas of focus: 
• Ending children living in unsuitable accommodation.
• Supporting the housing needs of vulnerable communities; and
• Building our future - maximising investment in Scotland’s housing sector. 
Whilst there is increasing pressure on the North Ayrshire housing system, a
range of effective measures are underway, including increasing housing supply,
and managing the demand from homeless people by way of temporary and
permanent accommodation. Details of the housing development programme
and homelessness prevention achievements to date, and further work planned
during 2025/26 are outlined elsewhere in this report. 
2.12. North Ayrshire Council established the Arran Housing Task Force (AHTF) in
2022 to quantify demand for affordable housing on Arran and identify issues
that may be limiting economic growth. A quantitative study was undertaken to
determine affordable housing demand on the island, recognising the assessed
housing demand information from the North Ayrshire Housing Register and
community feedback. Following the study, the AHTF recognised areas that
required further analysis, and the Arran Housing Survey was developed and
launched on 31 January 2025. The survey looked for responses from Arran
households, employees/employers on the island, landlords, second
homeowners, empty homeowners, short-term let owners, and those wishing to
move to the island, to help shape future housing provision on the island.
Following the survey’s closure on 14 April 2025, the results are currently being
analysed by the Council’s Housing Strategy Team and will be presented to the
AHTF in late 2025. The survey report will require formal sign off by the AHTF
and will be published thereafter, with the AHTF action plan amended to reflect
the outcomes. The AHTF membership includes the Scottish Government,
Highlands and Islands Enterprise, local community groups, and Arran
registered social landlords. 
2.13. When the Rapid Rehousing Transition Plan (RRTP) was implemented in 2019,
a target was set for North Ayrshire to create 100 Housing First tenancies over a
five-year period. At end of 2023/24, we had exceeded the target by creating
103 tenancies and by the end of 2024/25 we have successfully created 123
tenancies. Within current budget constraints, we plan to create a further 20
tenancies per annum over the next four years. 
2.14. The Private Sector Advice and Homelessness teams are piloting an approach
where a homeless presentation is due to the tenant being served a Notice to
Leave by their landlord. The Private Sector Advice team contact the landlord to
either mediate or encourage the landlord to use our landlord-to-landlord sales
service with the intention that the tenant can remain in the property. The pilot

Page 5

outcomes will be reviewed with the expectation that the service can be further
evolved to ensure we are supporting private tenants within our communities. 
2.15. It is recognised that purchasing ex-local authority stock is an effective way to
increase social housing stock and provide value for money for the investment
made - the current SHIP 2025-2030 has increased the Council’s buyback
scheme to 60 properties by 2030. The Council’s developing Registered Social
Landlord partners have buyback programmes within the SHIP, aiming to
acquire a further 29 new homes. Due to current housing market conditions, it
has been more challenging to acquire homes that are marketed for sale. As a
result, a new Housing Acquisition Strategy is under preparation (see LHS
Action 32) and will be presented to Cabinet during 2025/26, to identify
potentially new and innovative approaches, ensure that the Council continues
to meet housing need across North Ayrshire, funding is maximised and value
for money is demonstrated across the various funding streams. 
2.16. During 2024/25 Trust Housing Association acquired two homes on Arran
through the Rural Affordable Homes for Key Workers Fund, which is available
until 2028. The Council and RSLs continue to work in partnership to identify
suitable properties that can be bought back using the Rural Affordable Homes
for Key Workers Fund, to increase the affordable housing stock available on
our islands.  
2.17. The ‘Housing and Care Leaver Protocol’ sets out how North Ayrshire HSCP
and Housing Services will work together to achieve the best possible housing
outcomes for care leavers. The protocol has recently been reviewed and
enhancements made, as part of the Brighter Pathways programme. Senior
Housing Officers will continue to carry out enhanced housing options interviews
with care leavers to ensure their housing needs are met and they are supported
to sustain their tenancies. Between April 2024 and March 2025, secure
tenancies were allocated to 14 North Ayrshire care leavers. 
Outcome 3 – Affordable warmth and zero emissions 
2.18. At the design and planning stage for each new build Council development
identified in the SHIP, an options appraisal is carried out to determine the most
appropriate sustainability measures required to reduce fuel poverty for tenants,
as well as contributing towards the Council’s net zero target. 
2.19. Our most recent developments incorporate air source heat pumps alongside
enhanced fabric measures and solar PV panels. An assessment was carried
out for each site and measured to ensure property running costs were
affordable for our tenants while contributing to our net zero target. 
2.20. As part of the capital programme for investment for existing stock, solar PV and
external wall insulation has been included in the re-roofing and re-rendering
measured term contracts where appropriate, to ensure tenants benefit from a
better insulated home, reduced heat loss and the ability to utilise solar panels to
reduce utility bills.

Page 6

2.21. North Ayrshire Council responded to Scottish Government’s consultation on the
new and emerging Social Housing Net Zero Standard (SHNZS) in February
2024. The new standard is likely to require increased fabric performance and
replacement of ‘polluting’ heating systems with ‘clean’ heating systems in our
housing stock. The proposals have significant implications for the Council’s
housing asset management approach and 30-year HRA Business Plan,
including cyclical replacement of heating systems and other fabric elements
e.g., window, roof, and insulation programmes. 
2.22. A pathfinder project is in progress to review the financial, technical and
customer implications associated with the emerging standard. The project
focuses on the traditional housing stock built between 1945 and 1960, which
makes up approximately 75% of the stock profile. The initial properties have
been surveyed; the appointed external architects (MAST) have issued their
recommendations and will agree a proposed scheme of works for each
property. A suitable contractor is currently being procured to provide monitoring
within the properties, with a budget of £0.550m allocated for this project. 
2.23. The Area Based Scheme (ABS) continues to deliver energy efficiency and low
carbon technology to private sector households, in hard-to-treat areas. During
2024/25 this targeted scheme was focused on improving affordable warmth in
island properties i.e. Arran and Great Cumbrae, whilst providing roof mounted
solar PV to properties in the Kilwinning area where ABS has previously been
used to install external wall insulation. 
2.24. Council officers has been working in partnership with Green Home Systems, an
Irvine based company, to access ECO4 Flex funding, and through this
partnership have installed 134 measures, such as ASHP, solar PV, loft, room in
roof, internal wall and cavity wall insulation, boiler upgrades, first time central
heating and TRVs, in 32 properties, generating over £0.900m of additional
funding into North Ayrshire. 
2.25. The Council offers Energy Smart emergency support payments for those
vulnerable to fuel debt, to support a reduction in fuel poverty.  Grants totalling
£0.123m were released during 2024/25. 
2.26. A comprehensive process map has been developed to ensure issues with
damp and mould are effectively addressed. The core elements of this process
have already been implemented and further elements, such as an expansion in
the use of electronic monitoring, are currently being explored. Tenant
engagement has been increased, with regular information provided via
corporate social media channels. These measures will ensure that the Council
is well prepared for the anticipated introduction of Awaab’s Law as part of the
forthcoming Housing (Scotland) Bill. 
Outcome 4 – Improving the quality of our homes 
2.27. The latest Housing Asset Management Plan (HAMP) was approved by Cabinet
in September 2023, and complements the Local Housing Strategy 2023-2028
approved by Cabinet in June 2023. The HAMP is currently being refreshed and

Page 7

will be presented to Cabinet on 28 October 2025. The HAMP aims to ensure
the Council’s housing stock is maintained in a condition compliant with existing
and proposed legislation and building standards. Progress on the action plan is
reported to the Housing Asset Management Board (HAMB) on a bi-monthly
basis to ensure appropriate governance mechanisms are in place to support
the delivery of the action plan. 
2.28. The Estate Based Regeneration Programme (EBRP) continues to deliver
projects to address pockets of low demand stock; antisocial behaviour; external
appearance; parking provision; road and footpath condition; fencing;
landscaping; and general grounds maintenance issues. During 2024/25,  there
has been successful delivery of an additional 16 new in-curtilage parking
spaces at NAC properties, rehoming of tenants and purchase of 3 properties to
allow future works to progress at low demand flatted blocks, external
improvement works at two blocks of amenity bungalows, major repair works to
a Housing owned footbridge, a significant fencing programme, and some
smaller improvement projects. 
2.29. The Sheltered Housing Reprovisioning Programme has delivered the
refurbishment of Barnett Court, Saltcoats, which was completed in January
2024 and works at Cheviot Court, Irvine, completed in November 2024. Work is
anticipated to commence at Vineburgh Court, Irvine and Laigh Court, Beith
during spring 2026. These two complexes will be supplied by a Bivalent heating
and hot water system, which is a combination of ASHP and a gas back-up.
Officers are currently preparing a heating strategy for the remainder of the
complexes on the programme. 
2.30. The Customer Participation Strategy 2023-28 was approved by Cabinet in June
2023. In 2024/25, membership within our Service Improvement Groups
increased, 25 consultations took place, and our tri-annual Tenant Satisfaction
Survey was conducted. The Redburn Grove Gypsy/ Travellers Tenants group
became a Registered Tenant Organisation. 
Areas of Future Focus 
2.31. Priorities that require further action, and will be implemented during the
remaining lifespan of the Local Housing Strategy 2023-2028, are as follows: 
Outcome 1 – More homes at the heart of great places 
2.32. As reported to Cabinet on 3 December 2024, in May 2024 Scottish Government
advised that the North Ayrshire Resource Planning Assumption (RPA) for
2024/25 would be significantly reduced compared to the funding level
previously indicated, with further reductions anticipated in later years. On 4
December 2024, Scottish Government announced a draft £768m budget for the
Affordable Housing Supply Programme, which reinstated the funding for
2025/26. 
2.33. The Council is currently in the process of developing the SHIP 2026-31,
including future Resource Planning Assumptions, pending formal notification of

Page 8

the 2026/27 North Ayrshire Resource Planning Assumption anticipated in
spring 2026. Officers are also working with external partners to explore
alternative and additional mechanisms to support affordable housing delivery. 
Outcome 2 – Affordability and choice 
2.34. A review of the North Ayrshire Common Housing Register (NAHR) Allocation
Policy has recently been completed to ensure that it aligns to emerging issues,
incorporating national and local priorities. Following consultation with
applicants, tenants, tenants’ groups, and key stakeholders, the NAHR partners
have successfully undertaken and concluded remodelling requirements to
assess the potential scale of impact for the proposed changes to the allocation
of housing. The draft North Ayrshire Housing Allocation Policy (NAHAP) has
been reviewed by NAHR partners and is scheduled to be presented to Cabinet
on 30 September 2025. 
2.35. North Ayrshire Council experienced increasing levels of homelessness and a
significant increase in demand for temporary accommodation in 2024/25,
putting additional pressure on general housing supply. The North Ayrshire
Homelessness Taskforce, comprising of the Council and a range of
stakeholders, provides the governance framework for the delivery of the North
Ayrshire Rapid Rehousing Transition Plan, inclusive of Housing First. The
partners are currently working to understand the homelessness risk factors
affecting each of the partner organisations with a role in homelessness
prevention in North Ayrshire. The findings from this work are being used to
develop the North Ayrshire Homelessness Strategy, aligned to the proposed
new homelessness prevention duties detailed within the Housing (Scotland) Bill
2024. 
2.36. Of the 1,184 homeless cases in 2024/25, 171 (14.4%) individuals reported to
be fleeing domestic violence in comparison with 133 in 2023/24. Of the 171,
142 (83%) were females. In early 2025, the Violence Against Women
Partnership was re-established, to bring relevant partners back together to
discuss individual and collective actions in response to national policy and local
challenges. This action was supported by confirmation of a new VAW Lead
Officer post which is currently being recruited. Development of the North
Ayrshire VAW Strategy and Action Plan will be aligned to the Delivering Equally
Safe National Strategy. 
2.37. Following the successful implementation of the Redburn Grove Tenants and
Residents Association (TARA), further engagement work and an associated
action plan requires to be developed to fully identify the needs and aspirations
of Gypsy Travellers, reflecting on feedback from the recent Gypsy/Traveller
Satisfaction Survey. This will not be isolated to Redburn Grove and will include
the management and engagement opportunities when dealing with
unauthorised encampments. 
2.38. On 3 June 2025, Cabinet approved the inclusion of the Redburn Grove
redevelopment within the Strategic Housing Investment Plan 2026-2031, which
will be considered by Cabinet on 30 September 2025.

Page 9

2.39. Housing Services are working to develop an inter-agency hospital discharge
pathway to minimise the risk of homelessness on discharge from hospital.
Through collaboration with partners, we are developing the pathway that will
recognise the proposed “Ask” and “Act” recommendations within the Housing
Bill. The pathway will promote partnership working and encourage early
intervention to prevent homelessness and ensure the housing needs of patients
are identified on admittance. 
2.40. Working in partnership with East and South Ayrshire Council, a prison
discharge outreach service is delivered from within HMP Prison Kilmarnock to
offer advice and assistance to those threatened with homelessness on release.
In addition, the North Ayrshire Homelessness Task Force has developed a
Prison Discharge Protocol aligned to the national ‘Sustainable Housing on
Release for Everyone’ (SHORE) standards, to minimise the risk of crisis for
people being released from prison. The protocol is currently being revised.
During 2024/25, 63 individuals approached for homeless assistance following
prison discharge, which accounts for 5.3% of all approaches. During 2023/24,
77 individuals were homeless following prison discharge, which accounted for
7% of all approaches.   
2.41. Further analysis is required to determine trends and areas for improvement in
relation to homelessness tenancy sustainment. In 2023/24 the average number
of weeks spent in temporary accommodation was 16.4 (115 days) for cases
closed. In 2024/25 this has decreased to 15.8 weeks (111 days). A review of
the Housing Allocation Policy and supporting practices is currently being
undertaken to ensure that the use of Council housing stock is optimised to meet
the needs of tenants and applicants. 
Outcome 3 – Affordable warmth and zero emissions 
2.42. The Social Housing Net Zero Standard (SHNZS) mentioned previously at
paragraph 2.21 is anticipated to be implemented during 2026, although the
exact implementation date has yet to be confirmed by Scottish Government.
Similar to many other local authorities and registered social landlords, the
Council’s 30-year HRA business plan is under significant pressure. Whilst an
increase in emission standards is expected and the HRA Business Plan
includes a budget allocation for energy efficient improvements and heating
systems replacement, it is recognised that this will not be sufficient to fully
retrofit our existing stock. 
2.43. In anticipation of the new SHNZS standards, the Council has appointed a
contractor to undertake a pathfinder project to fully understand the financial,
technical and tenant implications of complying with zero emissions targets. A
sample of properties have been identified to include a range of different
property types with tenant consultation underway. A whole house approach to
retrofit will be undertaken to implement a range of energy efficiency and
decarbonisation measures across Council housing stock to ensure legislative
requirements are met. The project will also consider dampness and mould to
inform the future approach in dealing with these issues, with a specific focus on

Page 10

the use of electronic monitoring. A report with findings and recommendations
will be prepared during 2025 for further consideration. 
Outcome 4 – Improving the quality of our homes 
2.44. Whilst The Council awaits the outcome of the Scottish Government consultation
on SHNZS, our Pathfinder project is underway and will see physical works
conducted during 2025 and 2026; this will inform the Council’s longer-term
strategy in relation to SHNZS. Alongside this, our Capital Programmes continue
to deliver improvements to our stock through investment in Solar PV/EWI and
upgraded central heating systems. Progress in this area will continue to be
reported through our regular Joint Budget Meetings, HAMB and Scottish
Government returns. 
2.45. Actions taken to improve access (e.g., an end-to-end process review; higher
application of the access policy; additional staff resources) have seen an
improvement in statutory compliance. In 2025/2026, the Council will continue its
statutory compliance delivery, similar to that used in 2024/2025 where we saw
increased utilisation of our forced access policy and increased financial
resources to create a dedicated compliance team. This saw substantial
improvement in both gas safety and Electrical Installation Condition Report
compliance, which we wish to sustain. 
2.46. A Housing Evidence Paper, prepared to inform the preparation of the LDP
Evidence Report, was published in December 2024 and reissued in March
2025 for stakeholder comments. The paper considers the requirement for a
target for the delivery of accessible homes within the private sector, noting that
the Government has committed to a new ‘Scottish Accessible Homes Standard’
which will be part of national building standards by 2025/26. The accessible
standard will see accessibility designed and built into all new homes, increasing
the housing choices for people with disabilities and reducing the need for
expensive retrofitting as people age or their needs change. The Council will
review our stakeholder comments and will complete the Evidence Report by
setting out the evidence and position on establishing a target for the delivery of
accessible homes within the private sector. 
2.47. The Scheme of Assistance (for private sector housing) is currently being
reviewed to include the changes to the Repairing Standard, which came into
force on 1 March 2024, and the promotion of positive outcomes for people living
with autism in the private housing sector. An action plan for consultation and
engagement will be prepared thereafter. 
New Actions 
2.48. To ensure the Local Housing Strategy 2023-28 continues to deliver on the
outcomes set out for North Ayrshire, three new actions have been developed
for adoption within the Strategy. These additional actions have their own
desired outcomes and target dates for achieving the desired outcomes. The
additional actions are as follows:

Page 11

LHS_02. Develop Local Housing Plans to better understand the needs of our       
neighbourhoods in North Ayrshire.
Developing local housing plans is an important way to ensure that
neighbourhoods grow in a way that meets community needs while balancing
affordability and sustainability. The aim is to develop housing plans for each
locality which will identify and support the needs of current and future residents
of North Ayrshire and reflect a ‘whole system approach’ as part of the recently
announced Collaboration for Health Equity in Scotland and work to tackle child
poverty as part of the Fairer Futures Partnership. 
LHS_03. Collaborate with the Scottish Government to end the national housing              
emergency.
While there are acute housing pressures locally, a housing emergency has not
been declared in North Ayrshire. However, work is ongoing to support the
Scottish Government in ending the national housing emergency. Following
Scottish Government’s release of the Housing Emergency Action Plan on 2
September 2025, we are currently assessing the Council’s position against the
national actions, with the aim of relieving current pressures and preventing
North Ayrshire Council from requiring to declare a housing emergency in the
future. 
LHS_04. Ensure the Housing (Scotland) Bill 2024 legislation is embedded in all    
our policies and procedures.
The Scottish Government introduced the Housing (Scotland) Bill 2024 to
Parliament on 26 March 2024 to deliver its rented sector strategy, A New Deal
for Tenants, and some policy ideas for housing as set out in Housing to 2040,
while also seeking to deliver on an ambition to end homelessness. The Bill
makes changes in the law in relation to housing and the changes cover
protections for tenants, preventing homelessness, and other housing matters.
The Bill is at Stage 3 of the process, prior to becoming an Act of Parliament. At
Stage 3, MSPs can propose further amendments to the Bill, and these are
debated and decided on in the Debating Chamber. Officers will continue to
monitor and review the amendments agreed at stage 3, with all legislative
changes implemented in North Ayrshire as required. 
3. Proposals 
3.1. It is proposed that Cabinet: 
i. notes the content of this report and progress against the LHS Action Plan
to 31 March 2025;  
ii. approves the addition of the three new actions outlined at para 2.48 and
detailed in Appendix 1;
iii. approves the submission of the LHS update to the Scottish Government. 
4. Implications/Socio-economic Duty 
Financial

Page 12

4.1. Any financial implications arising from the current projects and initiatives
included within the Local Housing Strategy 2023-2028 are reflected within
existing capital and revenue budgets. Business cases will be developed to
support emerging new initiatives, as required. 
Human Resources 
4.2. The Local Housing Strategy 2023-2028 is delivered by North Ayrshire Council
officers and relevant external partners, and is complemented by external
expertise, where required. 
Legal 
4.3. The development and monitoring of the Local Housing Strategy 2023-2028,
which sets out its priorities and plans for the delivery of housing and related
services in North Ayrshire, ensures compliance with the Housing (Scotland) Act
2001. 
Equality/Socio-economic 
4.4. The provision of good quality housing through the actions set out in the Local
Housing Strategy 2023-28 has a positive impact upon older people, children,
younger people, people with disabilities and households in fuel poverty. There
are no negative or discriminatory effects on any of the equality groups as a result
of the implementation of the strategy. 
Climate Change and Carbon 
4.5. The Local Housing Strategy continues to support the Sustainable North
Ayrshire Strategy 2024 - 2027, which aims to eradicate fuel poverty and
achieve net-zero carbon status by 2030. 
Key Priorities 
4.6. The Local Housing Strategy continues to support the Council Plan strategic
priorities: ‘Wellbeing;’ ‘Climate Change;’ ‘A Sustainable Council;’ and
‘Communities and Local Democracy.’ There is evidence that children and
young people can benefit from improved cognitive development and a reduction
in behavioural issues through living in a more attractive, warmer, and better
ventilated environment. The strategy also aims to support our island
communities and their economies. 
Community Wealth Building 
4.7. A number of the initiatives detailed within the Local Housing Strategy continue to
result in North Ayrshire Community Benefits through training and employment
opportunities delivered through the Council’s house building programme; the
wider Strategic Housing Investment Plan; Sheltered Housing reprovisioning
programme; and the Estate Based Regeneration programme.

Page 13

Islands Communities Impact Assessment (ICIA)  
4.8. The Local Housing Strategy recognises that there are unique impacts faced by
our islands and includes measures to address them. Some policy interventions
will be specifically tailored to our islands, to ensure our islands communities
enjoy the same opportunities as those living on the mainland. 
United Nations Rights of the Child (UNCRC)  
4.9. The Local Housing Strategy affects children and young people indirectly. The
following groups of children and young people have been identified as those
potentially affected by the Local Housing Strategy: 
• From low-income households
• Living in deprived areas
• At risk of homelessness or homeless
• Victims of domestic abuse/part of a family affected by domestic abuse
• Looked after/accommodated children and young people
• Care experienced young people/young people leaving care
• Those with a protected characteristic 
Consumer Duty 
4.10.  ‘None’ 
Consultation 
5.1 The 2024/25 update on LHS 2023-2028 has been prepared by gathering
information from various project leads across Council Services, as well as partner
RSLs.
David W. Hammond
Executive Director (Communities & Housing) 
For further information please contact Fiona Ellis, Senior Manager (Housing
Strategy & Development), on 01294 324031. 
Background Papers 
Local Housing Strategy 2023-2028
Customer Participation Strategy 2023-2028
Strategic Housing Investment Plan (SHIP) 2025-2030
Tackling Scotland’s Housing Emergency
Housing (Scotland) Bill as amended at Stage 2

Page 14

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
1
Collaboration 
LHS_01. Review and update our Tenant Participation Strategy to: 
• Ensure inclusive engagement with hard-to-reach groups 
• Ensure our literature is available in a format that is suitable for people with literacy and / or sensory / communication
issues 
Desired
Outcome  Latest update  Next Steps
RAG
Status
Original
due
date 
Revised
due date  Assigned to 
A refreshed Tenant
Participation
Strategy is
adopted by the
Cabinet of North
Ayrshire Council 
Housing Services Customer Participation Strategy 2023-
2028 was approved by Cabinet on 13 June 2023 where
three key priorities were approved. For 2024 the following
took place:  
Priority 1 – Engage and Inform 
• Tenant Satisfaction survey carried out by Knowledge
Partnership on behalf of North Ayrshire Council’s
Housing Service (NAC). Action Plan devised, staff
and North Ayrshire Network informed of results.
• 1932 tenants are currently on the Tenant Panel. A
decrease of 35 since Q4 figure of 1967.
• Annual Return on Charter agreed and approved by
tenants at meeting held on 27/05/2025 with members
of the North Ayrshire Network, North Ayrshire
Inspection Panel and Service Improvement Groups. 
• We have 6145 followers on Facebook. This is a
decrease of eight followers in this quarter from 6153
in Q4.
• We have 686 followers on X. This is a decrease of
four since the last quarter
• Utilised Libraries App and Care Experienced App to
improve communication to customers and include
Housing Services information  
• 25 consultations events were held throughout 2024-
25
• Tenants Chat newsletter issued quarterly 
• Implement Tenant
Satisfaction survey
action plan 
• Engage with seldom
heard groups to
ensure all
communities have a
voice by developing
a new North Ayrshire
Network 
• Build capacity within
communities by
offering training
sessions.
• Review the
Customer
Participation Strategy
2023-2028 action
plan. 
• Develop Service
Improvement Groups
and sustain
membership 
• Devise and deliver
staff Virtual Events
covering Customer
Participation and
Consultation 
2023+  31 March
2026
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Housing,
Customer
Engagement &
Support)

Page 15

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
2
• Annual Performance Matters newsletter issued
September 2024
• 1 Welfare Reform Messenger Session 19/06/2025
• Utilised Libraries App to include Housing Services
information
• Utilised Care Experienced App to include Housing
Services Information
• Social media messenger sessions hosted covering
rent arrears, Welfare Reform and housing support
• Estate management inspections carried out in all
areas where Tenant Groups are in operation annually
• Rent consultation carried out December 2024 with
1473 responses received. This was a 158 increase
on the previous year’s 1315 and the best response
we’ve had to a rent consultation. 
Priority 2 – Empower and Influence
TARA meetings have taken place with Redburn Grove,
Hayocks, Saltcoats High Flats, Castlepark and
Bourtreehill & Broomlands
• Developed Redburn Grove Gypsy/Travellers Tenants
Group to become a Registered Tenants Organisation
• Attendance at quarterly Sheltered Housing Complex
meetings
• A review of the Information Supplied Tenant
Inspection Panel findings and action plan delivery
• Six working group meetings took place with the NAN,
Editorial Panel, Major Works Working Group, Tenant
Event Group and Tenant Inspection Panel.
• Tenant-led scrutiny training provided by the Tenant
Participation Manager to the Tenant Inspection Panel
• Newly recruited Service Improvement Group
members have been trained in Tenant Participation
by the Tenant Participation Manager
• Capacity building within communities by offering a
suite of 15 training sessions, including Keeping Safe
Online; Scam Awareness; Financial Advice; Report

Page 16

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
3
Writing; Tenant Participation Refresher; Microsoft
Teams Refresher; etc.
• Reviewed NAC staff iLearn Customer Participation
module
• Digital methods of contact developed to include SMS
text messaging  
Priority 3 Evolve and Innovate 
• Increased membership within Service Improvement
Groups and Tenant Inspection Panel with 20 new
recruits joining
• Developed partnership working with stakeholders and
other agencies.
• Coordination and delivery support of Saltcoats High
Flats Coffee Morning event
• Sharing good practice presentation delivery at
Scotland's Housing Network – Community &
Resident Engagement Community of Practice on
18/06/2025
• Attendance at People Strategy Network meetings in
Dalry and Beith (June 2025)
• Attendance at Cunninghame Housing Association
Tenants Conference with 4 NAN representatives
24/06/2025
• Attendance at Cost-of-Living events across North
Ayrshire communities
• Two-year Customer Involvement Strategy review  
LHS_02. Develop Local Housing Plans to better understand the needs of our neighbourhoods in North Ayrshire
Desired
Outcome   Latest update   Next Steps 
RAG
Status 
Original
due
date  
Revised
due date   Assigned to  
Development of
local housing plans
for each locality/
town to identify
and support the 
Local housing plans are an important way to ensure that
neighbourhoods grow in a way that meets community
needs, while balancing affordability and sustainability.
• Collaborate with
key partners to
develop LHPs,
aligned with
forthcoming  
31 March
2028 
Senior Manager
(Housing Strategy
& Development)

Page 17

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
4
needs of current
and future
residents of North
Ayrshire
‘Locality
Profiles’, with
further details to
be submitted to
Cabinet in due
course
Team Manager
(Housing
Strategy) 
LHS_03. Collaborate with the Scottish Government to end the national housing emergency
Desired
Outcome   Latest update   Next Steps 
RAG
Status 
Original
due
date  
Revised
due date   Assigned to  
A housing
emergency is not
declared in North
Ayrshire  
The Scottish housing system is under significant
pressure, with the Scottish Government having declared a
national Housing Emergency on 15 May 2024 and 13
local authorities having declared their own housing
emergencies due to the unprecedented pressure to meet
their statutory responsibilities towards homeless people
and other priority groups in housing need. On 2
September 2025, the Scottish Government published the
Housing Emergency Action Plan with 3 main areas of
focus:
• Ending children living in unsuitable
accommodation;
• Supporting the housing needs of vulnerable
communities; and
• Building our future - maximising investment in
Scotland’s housing sector.
• Whilst there is increasing pressure on the North Ayrshire
housing system, a range of measures are being
undertaken across the housing system, including
increasing housing supply, and managing the demand
from homeless people by way of temporary and
permanent accommodation. 
• Assess North
Ayrshire against
the Scottish
Government’s
Housing
Emergency
Action Plan 
• Prepare and
implement the
actions set out
by the Scottish
Government.
• Continue our
good
partnership
working with
RSLs when
reviewing our
lets to homeless  
31 March
2028 
Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Housing
Strategy) 
LHS_04.  Ensure the Housing (Scotland) Bill 2024 legislation is embedded in all our policies and procedures

Page 18

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
5
Desired
Outcome   Latest update   Next Steps 
RAG
Status 
Original
due
date  
Revised
due date   Assigned to  
The new Housing
Act legislation is
implemented in
North Ayrshire  
The Scottish Government introduced the Housing
(Scotland) Bill 2024 to Parliament on 26 March 2024 to
deliver its rented sector strategy, A New Deal for Tenants,
and some policy ideas for housing as set out in Housing
to 2040, while also seeking to deliver on an ambition to
end homelessness. The Bill makes changes in the law in
relation to housing and the changes cover protections for
tenants, preventing homelessness, and other housing
matters. The Bill is at Stage 3 of the process prior to
becoming an Act. At Stage 3, MSPs can propose further
amendments to the Bill, and these are debated and
decided on in the Debating Chamber. The six main parts
(chapters) to the Bill are: 
1. Rent paid by tenants under private residential
tenancies
2. Dealing with evictions
3. Keeping pets and making changes to let property
4. Other matters relating to tenants
5. Homeless Prevention
6. Other housing matters
• Monitor and
review the
amendments
agreed at Stage
3
• Develop an
action plan to
embed the
legislative
changes in
North Ayrshire
Council’s
policies and
practices  
31 March
2028 
Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Housing
Strategy) 
More homes at the heart of great places 
LHS_05. Use our role as a major house builder to maximise local employment and training opportunities, and encourage our
partners to do the same

Page 19

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
6
Desired
Outcome  Latest update  Next Steps
RAG
Status
Original
due
date 
Revised
due date  Assigned to 
Training and
employment
opportunities are
available for local
people 
The Council is committed to improving socio-economic
and environmental outcomes through community benefits
within its procurement activity and has a community
benefits policy in place. The policy aligns with Council
priorities, most notably those captured in the 2024-2027
Community Wealth Building Strategy and Local Outcome
Improvement Plans. 
Community benefits are mandatory for all Council
contracts above £500,000, therefore are included in all
social housing development contracts. 
For example, two modern apprentices and a graduate
apprentice have been employed at the Council’s Garnock
Academy housebuilding site as at May 2025. The
contractor has also delivered a number of employability
and career sessions for school children and via the
Council’s Employability team. 
Our Registered Social Landlord (RSL) partners are
encouraged to use Community Benefits Clauses in
construction and other tenders during scheduled update
meetings and at site nomination. 
• Continue to work
with the
Employability
Team and to
further exp-lore
joint initiatives
and employability
opportunities for
the wider
community. 
• Continue to
collaborate with
our contractors
to ensure local
contractors are
utilised where
possible. 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Affordable
Housing &
Regeneration) 
LHS_06. Deliver 1,643 new units of social housing
Desired
Outcome  Latest update  Next Steps
RAG
Status
Original
due
date 
Revised
due date  Assigned to 
1,643 new homes
are developed
The SHIP 2025-2030 approved at Cabinet 3 December
2024 increased the previous target from 1,641 to 1,643
new homes by 2030. This reflected the addition of the
third phase of the St Michael’s Wynd, Kilwinning
development, utilising the remaining unallocated
regeneration units. 956 new Council homes have been
delivered as at 31 March 2025 against the 1,643 target.
Despite the affordability challenges faced, 91 new homes
were completed by the Council and RSLs during 2024/25.
• Work continues
on site to
progress to
deliver 202 units
at Ayrshire
Central Hospital,
Irvine. 
• Laburnum
Avenue, James 
2028 31 March
2030
Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Affordable
Housing &
Regeneration)

Page 20

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
7
The Council’s Resource Planning Assumption (RPA) for
2025/26 has been confirmed as £15.878m. The uplifted
budget (when compared to the estimate within the
Strategic Housing Investment Plan 2025-2030) will
support delivery of prioritised projects and the shadow
programme. Officers continue to explore
alternative/additional mechanisms to support affordable
housing delivery. 
McFarlane,
Stanecastle,
King’s Arms &
Garnock to
complete during
2025/26.
• Explore
alternative/additi
onal
mechanisms to
support
affordable
housing delivery.
• Deliver
remaining
programme to
achieve 1,643
units by 2030. 
LHS_07. Deliver 1,300 new units of private sector housing
Desired
Outcome  Latest update  Next Steps
RAG
Status
Original
due
date 
Revised
due date  Assigned to 
1,300 new private
homes are
developed
Private developers delivered 280 new homes during
2024/25, bringing the total number of units delivered by
the private sector to 528 since April 2023. 
Development is underway at all five new sites allocated by
LDP2, which together will deliver over 1,000 private sector
homes in addition to other active sites, including
Montgomerie Park and West Byrehill. Successful
completion of these and other smaller sites by 31 March
2028 would result in the 1,300-unit target to that date
being exceeded.  
A Draft Delivery Programme was submitted to Scottish
Government on 8 April 2025, setting out actions required
to deliver sites within the housing land supply.
• Continue to work
with private
developers to
deliver 1,300
new private
homes target by
2028.
• Finalise 2024/25
Housing Land
Audit and
Delivery
Programme (to
be published
following
approval
alongside the 
31 March
2028 
Senior Manager
(Planning) 
Strategic Planning
Manager

Page 21

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
8
LDP Evidence
Report) 
LHS_08. Consider opportunities to provide homes in and around our town centres
Desired
Outcome  Latest update  Next Steps
RAG
Status
Original
due
date 
Revised
due date  Assigned to 
Housing is
developed in or
around town
centres, where
feasible
Work is nearing completion for the Council’s development
of 6 amenity flats in Irvine town centre at the former King’s
Arms public house. The Council also plans to refurbish a
block of flats on Nelson Street, Largs - near the town
centre - to provide three new homes.
• Deliver further town
centre homes, where
feasible, during the
lifespan of the SHIP.
• Continue to work in
partnership with the
Regeneration Team
to identify potential
development
opportunities. 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development) 
Affordability & Choice 
LHS_09. Enforce a zero tolerance approach to harrassment and abuse against equalities groups
Desired 
Outcome   Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Every identified
incidence of
harassment is
investigated and
actioned
All risk assessments/ procedures for lone working have
been updated to reflect added caution due to staff
experiencing an overall increase in health and safety
incidents associated with violence and aggression.
From April 2025, Health and Safety Officers will deliver
bespoke Personal Safety Training to all Housing Staff.
From June 2025, Risk Assessment Training will be
made available to staff. 
In relation to our tenants and communities, our Housing
Officers address any issues of harassment or abuse
involving our tenants through our Estate Management
procedures. 
• Staff encouraged
to log all incidents
on Assure
System, with
debriefing process
established.
• All incidents
outlined within
quarterly Health
and Safety Action
Plan to gain wider
perspective and
actions taken. 
2024 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Neighbourhood
Housing)

Page 22

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
9
The Anti-Social Behaviour Investigation Team work
directly with Police Scotland to address community
issues and cases of tenants that have escalated. 
We work in partnership with Police Scotland and have a
dedicated Police Liaison Officer who provides daily
updates of any reported crimes within our tenancies.
This Officer also assists with other teams such as the
Housing Advice Team for households who advise they
are fleeing external harassment. 
PREVENT Training for Managers has been undertaken
to facilitate full participation in Prevent Multi Agency
Panel meetings. 
• All operational
staff within
Housing Services
will undertake
PREVENT
Awareness
training. 
LHS_10. Train our staff to understand cultural differences and challenges faced by different ethnic groups
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
100% of our staff are
trained
All staff have completed their mandatory North Ayrshire
Council Equality and Diversity 2025 training module on
iLearn. Completion records are recorded centrally on
the HR system CHRIS to ensure 100% completion.
• New staff
members will be
asked to complete
the mandatory
module. All staff
will complete the
2026 module
once this
becomes
available. 
• Internal Learning
Event organised
on Gypsy
Travellers on
10/07/2025 
2024 31 March
2028
Senior Manager
(Housing Strategy
& Development) 
Team Mananger
(Housing
Innovation and
Digital
Development)  
LHS_11. Work with national agencies and local partners to ensure refugees, asylum seekers and other displaced people
affected by conflict are supported to live in safety in our area
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 23

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
10 
100% of refugees
and people
displaced by conflict
who are housed in
our area received
support
Our Refugee Support Team continue to work together
with the CPP partners to provide high quality support to
assist families to integrate into local communities and
access vital services to meet their individual needs.
Following the successful completion of previous
resettlement pledges (2015 – 2025), North Ayrshire
Council’s voluntary involvement in UK Government
Resettlement programmes (UKRS/ARAP/ACRS) has
recently been reviewed and paused for the time being.
However, previously settled refugees and people
displaced by conflict living within North Ayrshire
continue to have access to support services when
required. 
• The Housing
Services Refugee
Resettlement
Transition
Strategy 2025-26
has been agreed
and is currently
being
implemented. The
Strategy includes
an action plan
which has been
developed to
achieve the key
actions which will
be monitored
through the
Refugee
Resettlement Task
Force. 
• The aims and
objectives of the
strategy consider
the progress
made in achieving
and supporting
ongoing
humanitarian
resettlement
across North
Ayrshire’s
communities. In
addition, they take
account the
impact of reducing
demand for
Housing Services 
2023+ 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Housing,
Customer
Engagement &
Support)

Page 24

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
11 
and responsibly
phase out housing
support services
by 31 March
2026, ensuring
continuity for
essential needs
while identifying
non-priority
services for
cessation in a
sustainable and
equitable manner.  
LHS_12. Engage with Gypsy / Travellers to ensure that housing solutions meet their needs
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Gypsy / Travellers
needs and
aspirations are
reflected in all
service provision
We continue to work with partner services delivering
support to the community with MECOPP, Education,
Money Matters, NHS, and the Tenant Participation (TP)
Team. 
The TP Team continues to meet with Redburn
Residents’ Group each month. In January 2025 the
Group held their AGM, with residents showing their
support to the group and maintaining positive
engagement with NAC to ensure they continue to
influence decision-making around site issues. The
group gave their feedback to NAC budget engagement,
Tenant Satisfaction Survey, and 2025-26 rent
consultation.  
NAC/MECOPP/NHS worked in partnership to deliver
services at Redburn, including voicing their concerns to
the COVID 19 inquiry. 
Eglinton Medical Practice offers monthly clinics at
Redburn Grove specifically for the Gypsy/Traveller
• Action plan to be
drafted and
agreed, factoring
into consideration
feedback from the
recent Gypsy /
Traveller
Satisfaction
Survey.
• Ongoing
engagement with
the Redburn
Grove tenants
through monthly
meetings of the
Redburn Grove
Tenants
Association and
additionally via the
Redburn Record
newsletter. 
2023 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Housing,
Customer
Engagement &
Support)

Page 25

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
12 
community. Members of the community gain direct
access to a General Practitioner in the Redburn Grove
Community room. 
Outreach tutors provide education onsite to
Gypsy/Traveller young people every Tuesday in the
Redburn grove community room. Currently there are
two regular students working towards various levels of
education in Maths, English, history, and sciences.
Residents voiced their opinions in January to the
Housing Services satisfaction survey. The results are
being reviewed and acted upon by senior management
team. 
Young people on site were given Christmas gifts and
selection boxes in partnership with Christians Against
Poverty and Random Acts of Kindness. 
In December 2024, power cards became available for
purchase at the new Public Protection office at Maress
House, Irvine. This gives residents the option to
purchase power cards out with office hours.
• Housing Services
to continue to
work in
partnership with
supporting
agencies to
ensure Gypsy /
Traveller needs
and aspirations
are factored into
consideration.  
LHS_13. Listen to Gypsy/Travellers from unauthorised encampments so that we can better understand and respond to
their needs
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 26

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
13 
100% of
Gypsy/Travellers
living in unauthorised
encampments are
approached for a
Support and Needs
Assessment
During 2024/25 officers engaged with and managed 67
unauthorised encampments: 17 of these being between
1 January – 31 March (Q4). Our Gypsy/Traveller Co-
ordinator completed a needs assessment for every
unauthorised encampment site and provided advice
and support to the Gypsy/Traveller community where
required.
Our Gypsy/Traveller Co-ordinator updated relevant
services with any issues raised and liaised with
members of the public to strike a balance between the
travelling and the settled community. We also worked in
partnership with Police Scotland to perform 5 joint visits
to unauthorised encampments. Between 1 April 2024
and 31 March 2025, we responded to 258 concerns
regarding encampments.
• Continue to work
in partnership to
support and
manage
unauthorised
encampments
across North
Ayrshire.
• Consider the
Scottish
Government’s
research on the
‘negotiated
stopping’ model
for supporting
roadside
encampments
pilot report
recommendations. 
2023 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Housing,
Customer
Engagement &
Support) 
LHS_14. Carry out an options appraisal on potential Gypsy / Traveller site improvements
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
The publication of
our findings, and
supporting action
plan (if feasible)
On 3 June 2025 Cabinet approved the inclusion of the
Redburn Grove redevelopment in the Strategic Housing
Investment Plan 2026-2031, which will be considered
by Cabinet in October 2025. 
• Site to be
included within the
SHIP 2026-2031.
• Scottish
Government
Guidance in
relation to funding
for
Gypsy/Traveller
site improvements
awaited 
2024  Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Affordable
Housing &
Regeneration)    
LHS_15. Develop and deliver an LGBTQ+ informed housing service, including:
• Establish LGBTQ+ champions 
• Develop an LGBTQ+ staff training programme

Page 27

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
14 
• Increase private sector awareness of LGBTQ+ housing issues
• Encourage our LGBTQ+ tenants and residents to participate
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
The delivery of an
inclusive housing
service is evidenced
by involvement and
participation in the
delivery and
development of
housing services
An LGBTQ+ awareness session was delivered to staff
in July 2024. This was delivered by the Terrance
Higgins Trust and a copy of the presentation slides are
available for all staff to view. 
All staff have completed the mandatory training module,
Equalities and Diversity 2025. The completion record for
this is saved on the HR System. 
Ongoing engagement with seldom heard groups is
taking place via the Communities Team. 
• The Tenant
Participation
Team will engage
with seldom heard
groups to ensure
all communities
have a voice by
developing a new
North Ayrshire
Network. LGBT+
representation will
form part of this
new wider
inclusive Network. 
2024 31 August
2025
Senior Manager
(Housing Strategy
& Development)
Team Mananger
(Housing
Innovation and
Digital
Development)  
LHS_16. Work in partnership with statutory and third sector agencies to deliver planned national changes to
homelessness prevention legislation
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Publication of our
response
The Housing Bill is currently at Stage 3. 
The North Ayrshire Homelessness Taskforce are
currently working to understand the homelessness risk
factors affecting each of the partner organisations with
a role in homelessness prevention in North Ayrshire.
The findings from this work are being used to develop
the North Ayrshire Homelessness Strategy, aligned to
the proposed new homelessness prevention duties
detailed within the Housing (Scotland) Bill 2024. 
The Task Force identified the priority groups where
further consultation with partners would be required in
relation to the impact of ‘ask’ and ‘act’ and how to
improve partnership working. The agreed groups are as
follows: 
• Domestic abuse
• Continue to work
with the Homeless
Task Force in
partnership to
maximise the
opportunities for
homeless
prevention. Next
Task Force
meeting
03/07/2025.
• The outcome from
these groups is
currently being
utilised to help
inform the 
2023+ 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Homeless
Prevention and
Advice)

Page 28

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
15 
• Communities & education
• Health & complex needs
• Children impacted by homelessness
• Justice & community safety
The groups have all met and the feedback is being
used to inform on the Homeless Prevention Strategy
and associated action plan. 
A Housing Services Partnership awareness event is
being arranged for 30/10/2025. The aim of the event is
to highlight the various areas of Housing, the Housing
Bill (‘Ask’ and ‘Act’) and to promote partnership working.
This will take the format of a ‘conversation café’ and
‘marketplace’ encouraging networking across the
services. A talking wall will be on display and
participants will be asked to provide feedback and
suggestions on how to work better together. 
Co-ordinators and frontline staff are carrying out
scheduled visits to partners frontline services to raise
awareness of the assistance available through the
homeless service, promote joint working, develop
relationships, resources available, and the ‘Ask and Act’
duty. 
strategy and
action plan. 
• These groups can
be reconvened to
carry out targeted
pieces of work.
• Learning from this
event will be used
to inform the
Homeless
Prevention
Strategy. 
• Continue to
schedule sessions
and capture a
wide range of
partners. 
LHS_17. Develop and deliver a North Ayrshire inter-agency strategy to prevent homelessness
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Levels of
homelessness will
reduce
The Homeless Prevention Strategy is currently being
developed with partners input via the Homeless Task
Force. This will be tied into a review the Rapid Re-
housing Plans (RRTP). 
In order to finalise this, we are currently procuring the
service of a Housing Consultant to incorporate a Rapid
Rehousing review and future plans. 
• The strategy
remains in
development
along with the
review of the
RRTP. 
2024 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)  
LHS_18. Through the ‘Violence Against Women Partnership 2021-2026, deliver the North Ayrshire violence against
women and girls action plan aligned to the ‘Equally Safe' strategy

Page 29

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
16 
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
A reduction in
domestic violence
and achievement of
the Violence Against
Women National
Standards
accreditation
North Ayrshire VAW Partnership meetings were re-
established in May 2025 and the VAW National
Improvement Service have agreed to visit North
Ayrshire later this year to undertake member
consultations to inform the local VAW Strategy in
accordance with Delivering Equally Safe priorities.   
A VAW Lead Officer post is currently being recruited.
The 16 Days of Action Operational Group was re-
established in August 2025, with the first meeting
arranged for mid-September. 
Of the 1184 homeless cases in 2024/25, 171 (14.4%)
individuals reported to be fleeing domestic violence in
comparison with 133 in 2023/24. Of the 171, 142 (83%)
were females. 
Temporary Housing and Support Service to Women
experiencing or at risk of violence contract is currently
subject to tender, with the new contract to be effective
from 1 October 2025. 
• Recruitment of
VAW Lead Officer
• Development of
North Ayrshire
VAW Strategy and
Action Plan
aligned to
Delivering Equally
Safe National
Strategy. 
• Conclusion of
tender process for
Women at Risk of
Violence.
• Implementation of
contract and
monitoring
framework. 
2026  Senior Manager
(Neighbourhood
Housing &
Homelessness)
(Temporary
Accommodation,
Resourcing and
Housing Support) 
LHS_19. Work with our partners to develop a hospital discharge pathway
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
0% of those leaving
a health care setting
will be homeless
We are collaborating with partners, to create a hospital
discharge pathway that will recognise the proposed
“Ask” and “Act” recommendations within the Housing
Bill. This will promote partnership working and
encourage early intervention to prevent homelessness
and ensure the housing needs of patients are identified
on admittance.    
• Creation of
hospital discharge
pathway 
2023 31 July 2026 Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)  
LHS_20. Continue to work with the HSCP to support young people make the transition from care to a home of their own
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 30

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
17 
100% of young
people are
supported as they
leave care and move
into their own home
Through the Brighter Pathways group, we have
refreshed the ‘Housing and Care Leaver Protocol’,
which is currently in draft format. 
From April 2024 to end March 2025, 14 tenancies were
allocated to individuals who are in receipt of continued
care through the Local Authority. 
Housing Support for individuals who are in receipt of
continued care is provided solely by the HSCP
Throughcare Team, as outlined within the Housing and
Care Leaver Protocol.
• Enhanced
Housing Options
interviews are
being offered by
Senior Housing
Officers across
localities   to all
Care Leavers to
ensure that their
housing needs
are met and
maximise tenancy
sustainability. 
• Weekly updates
are being
provided to HSCP
regarding
individual
applicant status. 
2024 31 March
2027
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)  
LHS_21. Consider the pathways into housing for young people to maximise housing options specific to their needs and
reduce the risk of homelessness
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Fewer young people
become homeless
We have recruited 2 Housing Advice Officer
(Prevention) posts. 
Initially these posts will concentrate on reducing youth
homeless for individuals leaving the familial home and
those who hold their own tenancies. These officers will
liaise with Partners to create a referral pathway and to
promote homeless prevention. 
Further consideration to be given to piloting housing
First placements for vulnerable youths. 
• Continue to
monitor homeless
statistics and the
impact of the
Prevention Officer
role. 
• Recruit second
officer
• Draft referral
protocol
• Work with
Housing Advice
Officers
(Prevention) to
identify vulnerable
youths for 
2024 31 March
2027
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Homeless
Prevention and
Advice)

Page 31

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
18 
Housing First and
develop criteria  
LHS_22. Implement the integrated prison discharge protocol
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Homelessness as a
result of prison
discharge is reduced
to below 5%
Document is complete but remains in draft format. The
protocol is reflective of the current practices of the
Housing Advice Officer (Prisons). 
During 2024/25 63 individuals approached for homeless
assistance, this accounts for 5.3% of all approaches.
During 2023/24, 77 individuals were homeless following
prison discharge which accounted for 7% of all
approaches. 
• Continue to
monitor statistical
data.
• Draft integrated
prison discharge
protocol to be
reviewed to
ensure it meets
the SHORE
standards. 
2023 31 March
2026
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)  
LHS_23. Implement Housing First for our most disadvantaged service users
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
100 Housing First
Tenancies are
delivered by 2024
By 31 March 2025 we successfully created 123
Housing First tenancies. At 31 March 2024, we had
exceeded the target by creating 103 tenancies. We
have planned within current budget constraints to
continue to create 20 tenancies per annum over the
next 4 years.   
• Continue to create
20 tenancies
annually 
2023  Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager 
(Temporary
Accommodation,
Resourcing and
Housing Support) 
LHS_24. Undertake a review of tenancies which have failed in the previous 12 months following resettlement of
homelessness to inform allocation processes
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 32

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
19 
Increased tenancy
sustainment  Tenancy sustainment for Homeless applicants has
fluctuated considerably over the past few years. In the
reporting year 2022/2023 we achieved 86.5%
sustainment success for tenancies which began 12
months previously, however by the following year
2023/2024 this figure reduced significantly to 84/02%.
By 2024/25 this figure recovered to 86.59%, thus
improving our national sustainment status. 
Further analysis of this marked reduction in 2023/2024
highlighted that 78 of 489 tenancies failed, with 22 of
the 78 being abandoned. Of these 22 tenants, high
levels of need in relation to addiction, poor mental
health, Justice Involvement and instances of domestic
violence were highlighted. A similar exercise undertaken
in June 2025 noted that 65 of 522 tenancies failed, with
23 of these being abandoned. 
Housing Services are working in partnership with
NADARS, Justice Services and Mental Health Services
through the auspices of ADP(Alcohol and Drug
Partnership) to establish sustainment forum.
• Current review of
Housing Support
role to ensure
focus of person
support.
• Current review of
temporary
Accommodation
officer role to
ensure focus of
property support. 
• Workforce
planning to
ensure
appropriate skills/
training and
learning.
• Encourage
partnership
working 
• Development of
screening process
and Information
Sharing
agreement for
multi-agency
sustainment
Forum Review
and establishment
of robust internal
oversight systems
and monitoring. 
2024 31 March
2026
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager  
(Temporary
Accommodation,
Resourcing and
Housing Support)  
LHS_25. Review the Rent Deposit Guarantee Scheme and recommend future approach
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 33

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
20 
Publication of the
review and action
plan (as appropriate)
The Rent Deposit Scheme is currently paused as we
have been unable to encourage landlords to use the
service. The Private Sector Housing Team have been
working with the Housing Advice Team to support
homelessness prevention measures. The team are
currently piloting an approach where a homeless
presentation is due to the tenant being served a Notice
to Leave by their landlord. The Private Sector Advice
team contact the landlord to either mediate or
encourage the landlord to use our landlord-to-landlord
sales service with the intention that the tenant can
remain in the property. The pilot outcomes will be
reviewed with the expectation that the service can be
further evolved to ensure we are supporting private
tenants within our communities.  
• Review outcomes
from the new
approach to
develop the
service.
• Review the Rent
Deposit Scheme
on a yearly basis
due to the
changing
landscape of the
private rented
sector.
• Promote
Landlord-to-
Landlord Sales
service 
2024 31 March
2025
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing
Strategy)  
LHS_26. Align support delivery to prevention activities as identified within the Homelessness Prevention Strategy
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Appropriate levels of
support available to
prevent and alleviate
homelessness
The Housing Advice Team continue to provide advice
and information to households who are homeless or
threatened with such, to maximise the opportunity for
homelessness prevention. Tailored Homelessness
Prevention training to be developed to upskill Housing
staff. 
Two Housing Advice Officer posts have been created,
focussing on targeted prevention for 16- to 24-year-old
households being asked to leave the familial home.
One Officer came into post in February 2025, and
second post came into position in July 2025. 
Housing Support continues to be provided to all in
temporary accommodation during their resettlement
period of 12 months. 
• Implement
Homelessness
Prevention
Strategy
• Training providers
to be approached
and tailored
course to be
produced. 
• Monitor and
review process.
Review outcomes
to measure
success and any
other areas for
targeted
prevention. 
2024 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)

Page 34

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
21 
• Currently
reviewing the role
of housing
support staff to
ensure holistic,
person-centred
partnership
approach is
adopted.
• Increased
opportunities for
learning in
conjunction with
other services.  
LHS_27. Review the proportion of social rented lets to homeless people to minimise the duration of homelessness
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Reduce the length of
stay in temporary
accommodation by
50% from 26 weeks
to 13 weeks 
In 2023/24 the average weeks in temporary
accommodation was 16.4 weeks (115 days) for cases
closed. In 2024/25 this has decreased to 15.8 weeks
(111 days). 
Shared temporary accommodation model explored and
further work to be carried out on the corresponding
financial model. 
• Continue to
streamline service
delivery to ensure
efficiencies and
timescales are
being met. 
• Continue to
benchmark and
learn from other
local authorities
with regards to
alternative models
of temporary
accommodation
and best practice.
• Further consider
the model of
shared
accommodation in
North Ayrshire. 
2024 31 March
2028
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Homeless
Prevention and
Advice)

Page 35

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
22 
LHS_28. Consider introducing alternative housing models to meet local housing needs beyond social rented
accommodation
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
The publication of
the review and any
associated action
plan
Research into the feasibility of mid-market rents for
North Ayrshire has commenced and a report will be
drafted in 2025 with recommendations.  
NAC continue to work with the Scottish Government on
the feasibility of innovative models that are being
developed, including leasing schemes. The Housing
Investment Taskforce was established in April 2024 by
Scottish Government to identify actions that will unlock
both existing and new commitments to investment in
housing across all tenures. The report was published in
June 2025 and identified 28 actions to support
investment in new and existing business models to
deliver at scale across Scotland. 
Funding has been secured for support for social renters
and other priority groups to buy a home on the open
market with support from the Scottish Government’s
LIFT Open Market Shared Equity (OMSE) Scheme.
This helps low to moderate income households buy a
home, often freeing up much-needed social housing or
reducing waiting lists. The fund is administered by Link
Group.
• Research will
continue during
2025, and a paper
will be drafted on
the feasibility of
mid-market rents
for North Ayrshire.
• Review the
Housing
Investment
Taskforce report
and identify
opportunities for
North Ayrshire.
• Raise awareness
of the LIFT Open
Market Shared
Equity Scheme 
31
December
2025 
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing
Strategy)  
LHS_29. Support the Scottish Government's target to deliver 110,000 new affordable homes by 2032 by delivering the
projects set out within the Strategic Housing Investment Plan
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
New affordable
homes are built in
North Ayrshire
From April 2024 to 31 March 2025, 71 new build
Council homes were delivered, and 20 new build homes
were delivered by our Registered Social Landlord
partners (RSLs). 
• Continue to
monitor Council
and Registered
Social Landlord
(RSL) completions
projected for
2025/26. 
2028 2032 Senior Manager
(Housing Strategy
& Development)
Team Manager
(Affordable
Housing &
Regeneration)

Page 36

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
23 
• Continue to
monitor Resource
Planning
Assumption (RPA)
availability and
deliverability of
current SHIP
projects.  
LHS_30. Research barriers to mutual exchange in order to increase its use as a rehousing solution
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
There is an increase
in the number of
mutual exchanges
A review of the Housing Allocation Policy is currently
being conducted to optimise the use of housing stock to
meet the needs of council tenants and housing
applicants. Once this has been completed a relaunch
and promotion of Mutual Exchange option will be
implemented.
• Relaunch &
promotion of
mutual exchange. 
• Feasibility of
creating a Mutual
Exchange Officer
post to be
explored. 
2024 31 December
2026
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Housing,
Customer
Engagement &
Support)   
LHS_31. Work with partners to align the North Ayrshire Allocation Policy to emerging issues, incorporating national and
local priorities
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
The new policy is
published
Following consultation with applicants, tenants, tenants’
groups, and key stakeholders (11 Dec 2023 - 21 Jan
2024), the North Ayrshire Housing Register (NAHR)
partners have successfully undertaken and concluded
remodelling requirements to assess the potential scale
of impact for the proposed changes to the allocation of
housing. The draft North Ayrshire Housing Allocation
Policy (NAHAP) has been reviewed by NAHR partners
and is scheduled to be considered by Cabinet in
September 2025. 
• Due to be
considered by
Cabinet on 30
September 2025,
with full
implementation to
follow by 30
November 2025. 
2023 &
2026
30 November
2025 
Senior Manager
(Neighbourhood
Housing &
Homelessness) 
Team Manager
(Housing,
Customer
Engagement &
Support)   
LHS_32. Increase the social housing supply by buying back former social housing
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 37

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
24 
Former social
housing is brought
back into the
affordable housing
supply
During 2024/25 the Council acquired two properties via
the SHIP and Trust Housing Association acquired two
homes on Arran through the Rural Affordable Homes
for Key Workers Fund which is available to 2028. 
Due to the current pace of the housing market the
Council has been finding it difficult to acquire homes
that are marketed for sale. Officers will look to target
acquisitions to minimise the number of missed
opportunities. 
NAC and RSLs continue to work in partnership to
identify suitable properties that can be bought back
using the Rural Affordable Homes for Key Workers
Fund to increase the affordable housing stock available
on our islands. 
• Continue to buy
back properties,
subject to funding
availability.
• Housing
Acquisition
Strategy is under
preparation and is
expected to
launch in late
2025.
• Identify further
properties that
can be bought
back using the
Rural Key
Workers Housing
Fund and
progress where
feasible. 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Affordable
Housing &
Regeneration)  
LHS_33. Bring empty homes back into use through the buy back scheme
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Empty homes are
purchased and
brought back into
use as affordable
housing
A new process for acquisitions was developed in
2024/25 through consultation with teams in Housing
Services and PMI. The process will launch in 2025 and
has a strategic approach to acquiring properties in our
communities including an increased focus on long-term
empty homes. One empty home was acquired in
2024/25.
• Monitor the
progress of empty
homes
acquisitions
following the
introduction of the
new process.
• Proceed with
empty homes
acquisitions where
the strategic
needs of the
service can be
met by the
property 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing
Strategy)  
LHS_34. Assess the future housing need and demand of our island residents, workers, and key workers

Page 38

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
25 
Desired
Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Island residents’
needs and
aspirations are
reflected in all
service provision
North Ayrshire Council has established the Arran
Housing Task Force (AHTF) to quantify demand for
affordable housing on Arran and identify issues that
may be limiting economic growth. A quantitative study
was undertaken to determine affordable housing
demand on the island, recognising the assessed
housing demand information from the North Ayrshire
Housing Register and community feedback. Following
the study, the AHTF recognised areas that required
further analysis, and the Arran Housing Survey was
developed and launched on 31 January 2025. The
survey looked for responses from Arran households,
employees/employers on the island, landlords, second
homeowners, empty homeowners, short-term let
owners, and those wishing to move to the island, to
help shape future housing provision on the island.
Following the survey closure on 14 April 2025, the
results are being analysed by the Council’s Housing
Strategy Team and will be presented to the AHTF. The
survey report will require formal sign off by the AHTF
and will be published thereafter with the AHTF action
plan amended to reflect the outcomes. The AHTF
membership includes the Scottish Government,
Highlands and Islands Enterprise, local community
groups, and Arran registered social landlords.  
A new temporary post within the Council’s Housing
Strategy Team is being funded from the income from
the reduction in discount for empty and second homes
Council Tax in North Ayrshire to support the work of the
AHTF and the delivery of the Rural and Islands Housing
Action Plan. 
North Ayrshire Council launched the Arran Local
Lettings Initiative in 2021, which awarded Arran
residents and/or workers additional points on their
housing application. As part of the North Ayrshire
Housing Allocation Policy review, it is proposed that the
• Develop and
implement the
action plan for the
AHTF following
the outcomes
from the Arran
Housing Survey.
• Continue to
review the
demand on the
North Ayrshire
Housing Register
for Arran &
Cumbrae to
inform future
priorities. 
31 March
2028 
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing
Strategy)

Page 39

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
26 
Arran LLI is adopted into the policy and would therefore
be used by all partner landlords who have properties on
the island. The draft North Ayrshire Housing Allocation
Policy is scheduled to go to Cabinet in September
2025. 
Affordable Warmth & Zero Emissions 
LHS_35. Support the Environmental Sustainability and Climate Change Strategy to reduce fuel poverty and increase affordable
warmth
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Fuel poverty is
reduced, and
affordable warmth is
increased for North
Ayrshire residents
During the design and planning for each individual
project progressed through out SHIP, an options
appraisal is carried out to determine the most
appropriate sustainability measures required to reduce
fuel poverty for our tenants.  In our most recent
developments, we have opted for air source heat
pumps alongside enhanced fabric measures and solar
PV panels.  An assessment was carried out for each
site and measure to ensure property running costs
were affordable for our tenants alongside contributing
to our net zero target.   
The Area Based Scheme (ABS) continues to deliver
energy efficiency and low carbon technology to private
sector households, in hard-to-treat areas. During
2024/25 this targeted scheme has been focused on
improving affordable warmth in island properties i.e.
Arran and Great Cumbrae, whilst providing roof
mounted solar PV to properties in the Kilwinning area
where ABS has previously been used to install external
wall insulation. 
• Continue to
review each
project on a site-
by-site basis to
ensure the most
appropriate
sustainability
measures are
utilised.
• The Council will
continue to utilise
Scottish
Government
funding through
ABS and is
investigating the
potential to
expand the ECO4
Flex partnership
scheme to
include other
local businesses. 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development) 
Senior Manager
(Property
Management and
Investment)

Page 40

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
27 
In addition, we have been working in partnership with
Green Home Systems, an Irvine based company, to
access ECO4 Flex funding, and through this
partnership have installed 134 measures, such as
ASHP, solar PV, loft, room in roof, internal wall and
cavity wall insulation, boiler upgrade, first time central
heating and TRVs, in 32 properties, releasing over
£900k of additional funding into North Ayrshire. 
The Council also offers Energy Smart emergency
support payments for those vulnerable to fuel debt, to
support a reduction in fuel poverty, with £122,350 of
grants released in 2024/25. The Energy Smart physical
measures programme has also been launched, offering
low-cost energy efficiency measures to private sector
households.
The Council also installs solar PV and EWI as part of
the roof and render scheme for the Council's domestic
stock, supporting a reduction in resident's energy bills
whilst reducing heat loss and improving health and
wellbeing. 
The Energy
Smart schemes
continue to
progress in
2025/26 also.
• Increased
engagement
within
communities via
the Community
Climate Action
Plan programme
of talks is hoped
to increase
uptake of offers
available
residents across
North Ayrshire. 
LHS_36. Implement a range of energy efficiency and decarbonisation measures across Council housing stock to meet EESSH2
requirements informed by an EESH2 pathfinder focusing on a whole-house approach to retrofit
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
A whole house
approach to energy
efficiency and
decarbonisation is
adopted for Council
housing stock
North Ayrshire council have appointed external
architects (MAST) to carry out a pathfinder project, the
purpose of which is to fully understand the financial,
technical and customer implications of complying with
Zero Emission targets. 
The information gained will be used to inform NAC’s
future strategy and business planning assumptions and
provide technical solutions for NAC to facilitate the
retrofitting of zero emissions measures. 
The study focuses on the traditional housing stock built
between1945 and 1960, which makes up
approximately 75% of the stock. 
• Further meeting
with MAST
architect has
taken place to
discuss
environmental
monitoring
requirements and
possible supplier
to allow project to
progress.
Properties will
now be identified
for monitoring
installation and 
2023+ 31
December
2026
Senior Manager
(Property
Management and
Investment)

Page 41

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
28 
The initial properties have been surveyed, and MAST
have issued their recommendations and will agree a
proposed scheme of works for each property. We are
currently seeking a suitable contractor to provide
monitoring within the properties. A budget of £0.550m
has been agreed for this project. 
inclusion in the
next phase.
• Once monitoring
is complete,
installation
programme of
measures
suitable for each
property will be
carried out and a
further monitoring
period will be
undertaken to
ascertain the
impact of
measures and
inform future
strategy in this
area. 
LHS_37. Review our approach to dealing with dampness and mould issues within properties
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
All our properties are
free from dampness
and mould and
advice given to
private sector to
achieve same
outcome
A comprehensive process map has been developed to
ensure issues with damp and mould are effectively
addressed.
The core principles of this process have been
implemented and further elements, such as an
expansion in the use of electronic monitoring, are being
explored.
Tenant engagement has also been increased, with
regular information provided via corporate social media
channels.
Subject to Parliamentary approval, the Scottish
Government have announced within the Housing
Emergency Action Plan that they will implement
Awaab’s Law from March 2026 starting with damp and
mould to ensure landlords promptly address issues
hazardous to tenants in the social and private rented
sectors.
• Continued
development of
surveying and
reporting
methodology
• Joint working with
health
professionals
when required to
progress
escalated cases
(e.g. NHS Nurse
Led Asthma
Clinic) 
2023 31 March
2026
Senior Manager
(Property
Management and
Investment) 
Senior Manager
(Operations –
Building Services)

Page 42

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
29 
Improving the quality of our homes 
LHS_38. Review Census 2022 data to identify any emerging issues which may impact housing and related services
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Develop an action
plan to address any
issues which may
emerge following
review
Economic Policy are currently reviewing the Census
data and are creating an action plan on depopulation
which will include a focus on housing. The Housing
Strategy Team will continue to work closely with
Economic Policy to develop the action plan
• Continue the
joint working
across services
to develop the
depopulation
action plan. 
2024 31
December
2025
Senior Manager
(Housing Strategy
& Development) 
Team Manager
(Housing Strategy) 
LHS_39. Promote and provide a ‘pre-tenancy support service’ for landlords (on tenancy agreements and property standards)
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Landlords are
supported to create
and maintain
tenancies in
accordance with
legislative
requirements
The pre-tenancy support service was established in
April 2019 and is managed by the Private Sector Team.
Uptake has been low, and the team continues to look at
alternative ways to promote the service. 
The team continue to support landlords, owners, and
tenants in North Ayrshire with a range of other services
including tolerable standard inspections, missing shares
assistance, common repairs, resolving disputes, and
empty homes.
• The team will
continue to look
at alternative
ways to promote
the service.
• Review the stage
2 and 3 lead
committee report
on the Housing
(Scotland) Bill
2024 to ensure
the private sector
service remains
fit for purpose. 
2023  Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing Strategy) 
LHS_40. Continue to implement the Housing Asset Management Plan
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Implementation of the
Housing Asset
Management Plan
action plan
PMI and Housing have reviewed the Council’s
approach to asset management against the recent
Scottish Government guidance and have developed an
action plan to assist in the implementation of a best
practice model. 
• We continue to
regularly review
our delivery of
the HAMP -
progress is
regularly 
2027  Senior Manager
(Property
Management and
Investment)

Page 43

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
30 
Scottish Housing Net Zeo Standard (SHNZS)
The Scottish Government published a consultation
paper regarding a new net zero standard for housing.
The proposed standard will replace the former energy
efficiency standards (EESSH and EESSH2) which form
part of the SHQS. 
Key changes to the new standards include:
• A new fabric efficiency rating (which focuses
on the amount of energy for heat consumed by
a property) measured in kWh/m2 /year (level
and date TBC).
• A requirement to replace polluting heating
systems with a clean heating alternative by a
backstop date of 2045 (interim targets TBC). 
Capital Programme Delivery
On-going delivery of the various capital programmes
continues, progress and budget implications are
reported regularly at the Joint Budget meeting and
Housing Asset Management Board. 
Statutory Compliance
Actions taken to improve access (end to end process
review, higher application of access policy, additional
staff resources) have seen an improvement in this area.  
24/25 performance:
Gas Safety: 99.99%
Smoke Detection: 100%
Electrical testing: 97.65% 
23/24 performance: 
Gas Safety: 99.79% 
Smoke Detection: 99.99% 
Electrical testing: 78.71%
monitored
through HAMB
reporting.
Alongside this an
Integrated Asset
Review is
underway with
regular meetings
of all
stakeholders,
and we continue
to work through
our action plan.
• Whilst we await
the outcome of
the Scottish
Government
consultation on
SHNZS, our
Pathfinder
project is
underway and
will see
physically works
carried out in
25/26, this will
inform the
Council’s longer-
term strategy in
relation to
SHNZS.
Alongside this
our Capital
Programmes
continue to
deliver
improvements to
our stock through
investment in
PV/EWI and
upgraded central

Page 44

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
31 
heating systems.
Progress in this
area will continue
to be reported
through our
regular Joint
Budget
Meetings, HAMB
and Scottish
Government
returns.
• In 25/26 we will
continue to
improve our
Statutory
Compliance
delivery, similar
to that used in
24/25 where we
saw increased
utilisation of our
forced entry
policy and
increased
resource to
create a
dedicated
compliance
team. This saw
substantial
improvement in
all areas of
compliance
which we wish to
sustain. 
LHS_41. Prevent housing crisis through early intervention by ensuring housing staff can identify the long term needs of tenants to
ensure housing is sustainable
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to

Page 45

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
32 
All housing staff can
identify the long-term
needs of tenants,
including the
challenges facing
people with
neurodiverse issues
A ‘Home Visit Form’ has been developed that will be
completed by Housing Services staff during visits to
tenants’ homes. Following the completion of the form
the information will be used to update relevant systems
with up-to-date information and will be used to identify
support provision, repairing issues etc., within NAC
mainstream tenancies. 
Homelessness Working Group has been established
that incorporates frontline and management staff from
all Housing teams with a view to reviewing processes
and procedures that will maximise our opportunity to
prevent homelessness and increase sustainability. 
Enhanced housing options are available to all tenants
and applicants within all localities. 
Housing Options Toolkit to be promoted by all
managers and teams to complete all modules. Half day
closures to be used to allow staff time to complete
training. 
Multi-disciplinary teams in locality offices allow pre-
allocation discussions/checks prior to offers to ensure
that the offer is appropriate to the applicants and their
household needs. 
• DPIA form has
been completed
and is awaiting
sign off. When
agreed Officers
will be instructed
to use the new
home visit forms. 
• Homelessness
Strategy &
Prevention
Manager to
obtain current
licence list and
update staff
members. 
2024 31
December
2025
Senior Manager
(Neighbourhood
Housing &
Homelessness)
Team Manager
(Neighbourhood
Housing) 
LHS_42. Complete our Sheltered Housing Reprovisioning Programme by investing in 11 sheltered housing complexes over the
lifetime of this strategy
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Sheltered housing
complexes are
refurbished
The Barnett Court, Saltcoats refurbishment completed
in March 2024 and the Cheviot Court, Irvine
refurbishment completed in November 2024. 
• Refurbishment of
Vineburgh Court,
Irvine and Laigh
Court, Beith with
work anticipated
to start at these
units in early
2026.
• Draft plans
consultation took 
2028 31 March
2029
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Affordable
Housing &
Regeneration)

Page 46

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
33 
place at
Moorburn Park,
Largs in October
2024 and at
Regal Court,
Dalry in
December 2024.
Final plans for
these units are
currently being
prepared. 
LHS_43. Ensure that the Strategic Housing Investment Plan addresses current and future demographic needs
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Housing investment
priorities within the
Strategic Housing
Investment Plan align
to future and current
demographic needs
Demand for social housing is reviewed annually as part
of the development of each new SHIP.
• Development of
a performance
management
framework for
housing need
and demand. 
2023+ 31 March
2028
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Affordable
Housing &
Regeneration) 
LHS_44. Consider establishing a target for the delivery of accessible homes within the private sector
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
Local Development
Plan 3 sets out the
requirement for
accessible private
housing delivery
A Housing Evidence Paper, prepared to inform the
preparation of the LDP Evidence Report, was published
in December 2024 and reissued in March 2025 for
stakeholder comments. The paper considers the
requirement for a target for the delivery of accessible
homes within the private sector, noting that the
Government has committed to a new ‘Scottish
Accessible
Homes Standard’ which will be part of national building
standards by 2025/26. The accessible standard will see
accessibility designed and built into all new homes,
increasing the housing choices for people with
disabilities and reducing the need for expensive
retrofitting as people age or their needs change.
• Review
stakeholder
comments and
complete
Evidence Report,
setting out
evidence and
position on the
establishing a
target for the
delivery of
accessible
homes within the
private sector. 
2024 30 June
2027
Senior Manager
(Planning) 
Strategic Planning
Manager

Page 47

Appendix 1 - Local Housing Strategy 2023 – 2028 
Action Plan – Year 2 (2024/25) 
34 
The views of private sector housebuilders and others
on the need for a target for the delivery of accessible
homes within the private sector 
LHS_45. Review and update our Scheme of Assistance to:
• Ensure the promotion of positive outcomes for people living with autism in the private housing sector
• Ensure inclusive engagement with hard to reach groups 
• Ensure our literature is available in a format that is suitable for people with literacy and / or sensory / communication
issues
Desired Outcome  Latest update  Next Steps RAG
Status
Original
due date 
Revised
due date  Assigned to 
The publication of
information, sign
posting to advice
services and the
planned refresh of
the Scheme of
Assistance
The Scheme of Assistance is currently being reviewed
which will include the changes to the Repairing
Standard which came into force on 1 March 2024 and
the promotion of positive outcomes for people living
with autism in the private housing sector. Following
review, an action plan for consultation and engagement
will be implemented prior to presentation at the
appropriate Committee. The Scheme of Assistance will
be available in a format that is suitable for people with
literacy and/or sensory/communication issues. 
Housing staff, including the Private Sector Advice Team,
participated in an online training session in October
2024 ‘Introduction to Neurodiversity’ delivered by HSCP
and in association with an external partner. 
• Action plan for
consultation and
engagement will
be developed
and
implemented. 
31
December
2025 
Senior Manager
(Housing Strategy
& Development)
Team Manager
(Housing Strategy)