Page 1

NORTH AYRSHIRE COUNCIL 
1 September 2026 
Cabinet 
Title:    Capital Programme and Treasury Management
Performance to 30 June 2026 
Purpose:  To advise Cabinet of progress in delivering the Capital
Investment Programme 2026/27 and the associated Treasury
Management performance to 30 June 2026 
Recommendation:  That Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30
June 2026; and (ii) the forecast expenditure to 31 March
2027; and
(c) approve the virement proposal noted within the HRA
programme detailed in appendix 2; and
(d) note the estimated performance against the Prudential
Indicators set out in the Treasury Management and
Investment Strategy. 
1. Executive Summary 
1.1 The General Services Capital Investment Programme 2026/27 to 2033/34 was
approved by Council on 25 February 2026. The Housing Revenue Account (HRA)
Capital Investment Programme 2025/26 sits within the updated HRA Business Plan
and was approved by Council on 11 February 2026. 
1.2  This report identifies the current programme for 2026/27, taking account of
adjustments made to the initial budgets. The report presents the revised budgets at 30
June 2026 (Period 3) and forecast expenditure to 31 March 2027. 
1.3  At Period 3 the General Fund is forecasting a break even position against a revised
budget of £139.172m. The HRA is forecasting a projected underspend of (£0.183m)
against a revised budget of £52.815m. 
1.4  Within the General Fund, adjustments to funding have resulted in net additions to the
overall capital programme of £3.822m, including NAVT Funding for AGD Great
Harbour, Scottish Government Funding for Bourtree Hill Village Regeneration and an
adjustment to VDLF previously assumed within our General Capital Grant.

Page 2

1.5 Reviews of individual project plans have identified a number of adjustments to the
current profiles. As a result, £12.884m in relation to previously reported re-profiling
from 2025/26 to 2026/27 and the acceleration of £19.585m to 2026/27 from future
years has been fully offset by the re-profiling of (43.242m) for delivery in 2027/28 and
beyond. This primarily relates to the revised programme for the delivery of Ardrossan
New Build, AGD Projects, Ardrossan Harbour Interchange, B714 Improvements
alongside smaller revisions. 
1.6  Following the recent Council structure change for the Economic Development Shared
Service, budgets have been realigned within the Place and Communities and Housing
Directorates.  This realignment has no impact on overall budget available. 
1.7 Within the HRA Capital Programme, a review of delivery timescales has identified
£2.235m previously re-profiled from 2025/26 to 2026/27. In addition, £0.270m has
been accelerated to 2026/27 from future years. This has been partly offset by the re-
profiling of (£9.037m) of works for delivery in 2027/28 and beyond. Sheltered Housing
and Estates based regeneration projects have also been reprofiled to reflect the most
up to date delivery programme and this has resulted in (£10.757m) being reprofiled
into later financial years.   
1.8 Ongoing uncertainty arising from inflationary pressures and construction cost volatility
continue to impact on the Capital Programme. Financial risks have been identified
across several high value projects. Council has provided for a degree of mitigation
within the overall 10-year General Services Capital Investment Programme and the
HRA Capital Investment Programme. Projects will continue to be monitored closely
with cost increases met initially from the additional flexibility built into the programme.
However, any requirement for further borrowing not met from a funding source will be
a matter for Council to consider. The use of capital flexibility of £12.400m has been
realigned across other projects. The projects include the new Ardrossan Campus and
Upper Garnock Flood Prevention Scheme. 
1.9 The Treasury Management and Investment Strategy (TMIS) for 2026/27 was
approved by Council on 25 February 2026 and detailed the key performance
indicators under the Prudential Code for Capital Finance in Local Authorities (2021
edition). The current estimated performance indicates that North Ayrshire Council has
operated within the treasury limits and performance indicators set out in the TMIS and
the current capital investment plans remain affordable. 
2. Background 
General Fund 
2.1 The following table outlines the movements in the 2026/27 General Services budget:

Page 3

General Services Capital 
2026/27
£
million
Budget as at 1 April 2026 146.123
Changes to Funding 3.539
Other Revisions to the Programme 0.283
Revised Budget 149.945
Alterations to phasing between 2025/26 and 2026/27 12.884
Alterations to phasing of projects 2026/27 to 2027/28 (43.242)
Alterations to phasing of projects 2027/28 to 2026/27 19.585
Budget as at 30 June 2026 139.172 
2.2 Changes to Funding 
The capital programme has been updated to reflect the following changes to funding: 
Funding Body
Amount
£ million Project
Scottish Government GCG 1.019 Active Travel Tier 1
Scottish Government GCG (1.561) VDLF Removed Circular 2/2026
Scottish Government
Specific Grant 1.169 Bourtree Hill Village Regeneration
Scottish Government
Specific Grant 0.280 20mph Implementation
Scottish Government
Specific Grant 0.041 LA Direct Award
UK Government Grant 0.360 Irvine Pride in Place
UK Government Grant 0.118 Three Towns Prode in Place
Persimmons 0.130 UFSM West Kilbride
KA Leisure return unspent (0.004) Brodick Tennis 
NAVT Funding 1.830 AGD Great Harbour
SPT Grant 0.150 Bus Corridor Improvements
Walk Wheel Cycle Trust
Grant 0.007 NCN7 Valefield/Glengarnock Bridge
Total Funding
Adjustments 3.539   
2.3 Other Revisions to the Programme 
The programme has also been updated to reflect the undernoted adjustments: 
Funding Source
Amount
£ million Project
Borrowing 0.279 Bourtree Hill Village
Regeneration
Receipts 0.004 Insurance Recoveries (Vehicles)
Total Other Adjustments 0.283

Page 4

2.4 Alterations to the Phasing of Projects 
The reprofiling of £12.884m between 2025/26 and 2026/27 reflects projects not
completed within the year, or accelerated from future years, and incorporated within
the 2026/27 capital programme. These were previously reported within the 2025/26
Capital Programme performance reports: 
Project Amount
£ million
Ardrossan New Build 4.608
UFSM 0.106
Other Minor Movements 0.028
Total Education 4.742
Arran Youth Foundation Centre 0.382
CCTV Review 0.251
Long Drive 0.202
UK Shared Prosperity 0.160
Irvine High Street 0.099
Access Path Network Programme 0.089
Montgomerie Park Neighbourhood Ctr 0.081
Lochshore Garden Activity Hub 0.080
Abbey Tower 0.067
PBIP 0.062
Montgomerie Park Masterplan 0.062
Lochshore Garnock Hub 0.060
PBIP Public Space Camera 0.050
Portland Road Redevelopment 0.050
Active Travel Tier 1 (0.225)
Other Minor Movements 0.214
Total Communities & Housing 1.684
ICT Minor Movements 0.031
Total Corporate Services 0.031
Eclipse 0.153
Minor Movements 0.033
Total HSCP 0.186

Page 5

AGD Coastal Hub 0.441
AGD I3 DPMC Phase 1 0.337
Brodick Hall 0.324
LBPR Cunninghame House 0.281
Cemetery Extensions 0.266
Locality Based Property Review (LBPR) 0.266
Millport Pier 0.215
Bridges Infrastructure 0.211
Nature Restoration Fund 0.175
PLI Projects 0.170
Marine Tourism Lochranza 0.130
Goldcraigs Refurbishment 0.128
Fleet Decarbonisation 0.080
Lighting 0.071
LBPR The Circuit 0.063
Parking Charges & DPE 0.054
Roads Improvements (0.071)
B714 (0.145)
Millburn FPS (0.635)
Other Minor Movement 0.142
Total Place 2.503
Transfer to Flexibility 3.737
Core Infrastructure Fund 0.001
Total Other 3.738
Alterations 2025/26 to 2026/27 12.884  
A further review of individual project plan has identified a requirement to re-profile
(£43.242m) of works for delivery in 2027/28 and beyond. 
Project Amount
£ million
Bourtreehill Village (3.045)
VDLF Kyle Road (1.585)
LUF3 Annickbank (0.884)
Strategic Investment Route (0.600)
North Shore Residential (0.110)
Active Travel Tier 1 (0.063)
Total Communities & Housing (6.287)
Ardrossan New Build (36.088)
Total Education (36.088)
Improvement Grants (0.070)
Total HSCP (0.070)
Millport Pier (0.707)
Other Minor Movements (0.090)
Total Place (0.797)
Alterations 2026/27 to 2027/28 (43.242)

Page 6

These adjustments have been partly offset by the acceleration of £19.585m of   
expenditure to 2026/27 from future years. 
Project Amount
£ million
Adrossan New Build 3.282
Montgomerie Park School 0.687
Schools ICT 0.127
Other Minor Movements 0.017
Total Education 4.113
Data Centre Relocation 0.185
Connectivity 0.043
Total Corporate Services 0.228
Pride in Place Impact Fund 1.500
VDLF Kyle Road 0.925
Island Pit Stops 0.182
Montgomerie Park Masterplan 0.132
Strategic Investment Route 0.073
Lochshore, Kilbirnie 0.072
VDLF Development Work 0.070
Repurposing Property Grant Fund 0.052
PBIP Dockhead St 0.050
Other Minor Movements 0.215
Total Communitites & Housing 3.271
Ardrossan Harbour Interchange 3.518
B714 Improvements 1.713
Millburn FPS 0.911
AGD Coastal Hub 0.682
Renewal of Playparks 0.563
Lighting 0.297
Bridges Infrastructure 0.172
Irvine Enterprise Area 0.103
AGD Marine Toursim Cumbrae 0.090
Other Minor Movements 0.157
Total Place 8.206
Flexibility Fund 3.767
Total Other 3.767
Alterations 2027/28 to 2026/27 19.585

Page 7

2.5 These adjustments have resulted in a revised 2026/27 budget at 30 June 2026 of
£139.152m, a net decrease of (£6.951m). 
2.6 The following graph illustrates the movement in each programme on a service basis
compared to the revised programme: 
Approved 0.607 0.088 78.809 1.094 58.365 7.160 146.123
Programme @
P3 0.866 20.519 61.676 1.210 51.835 3.066 139.172
Movement 0.259 20.431 (17.133) 0.116 (6.530) (4.094) (6.951) 
2.7  The impact on budgeted funding, elements of which are related to the profile of
expenditure reported above, is a decrease of (£6.951m) from the revised budget,
including: 
Category
Amount
£ million Comments
Borrowing 12.354 Rephased aligned to projected
expenditure
Specific Grant (2.836) Rephased and revised contributions
Capital Grants (1.544) Rephased and additional
government grants
Other Grants (0.479) Rephased and revised contributions
Capital Receipts (0.544) Realigned capital receipts
Total Funding
Adjustments 6.951

Page 8

2.8 Projected Capital Expenditure to 31 March 2027 
The projections are summarised by service in the following table:   
Service /
Category
Approved
Budget
2026/27
£ million
Carry
Forwards
and
Adjustment
s
£ million
Revised
Budget
2026/27
£ million
Projected
Expenditure
/ Income to
31 March
2026
£ million
Projected
Variance
Over /
(Under)
£ million
Corporate
Services 0.607 0.259 0.866 0.866 0.000
Communities &
Housing 0.088 20.431 20.519 20.519 0.000
Education 78.809 (17.133) 61.676 61.676 0.000
HSCP 1.094 0.116 1.210 1.210 0.000
Place 58.365 (6.530) 51.835 51.835 0.000
Other Items 7.160 (4.094) 3.066 3.066 0.000
Total
Expenditure 146.123 (6.951) 139.172 139.172 0.000
General Grants (8.545) (1.544) (10.089) (10.089) 0.000
Specific Grants (30.184) (2.836) (33.020) (33.020) 0.000
Use of Reserve
Funds (0.355) 0.000 (0.355) (0.355) 0.000
Capital Receipts (0.865) (0.544) (1.409) (1.409) 0.000
Other Grants &
Contributions 0.000 (0.479) (0.479) (0.479) 0.000
Prudential
Borrowing (106.174) 12.354 (93.820) (93.820) 0.000
Total Income (146.123) 6.951 (139.172) (139.172) 0.000 
2.9 Significant ongoing uncertainty and areas of cost risk have been identified as a result
of cost volatility arising from inflationary pressures and supply chain issues which are
impacting on tender returns and the cost of materials across a number of projects.
While some mitigation has been built into the Capital Programme in the form of
flexibility budgets, cost pressures may exceed this provision. These risks will be
quantified as individual projects are completed and tendering exercises are finalised,
with the impact on the costs of the programme being monitored and reported to
Cabinet as appropriate. Any requirement for further borrowing not met from a funding
source will be a matter for Council to consider. The use of capital flexibility of
£12.400m has been realigned across other projects. The projects include the new
Ardrossan Campus and Upper Garnock Flood Prevention Scheme with full details
summarised in the undernoted table:

Page 9

Re-alignment From Capital Flexibility Amount
£ million
Adrossan New Build 9.970
Upper Garnock Flood Prevention Scheme 1.612
Quarry Road Phase 1 0.004
Salt Dome 0.014
Bridgegate House Demolition 0.800
Total Education 12.400 
Housing Revenue Account 
2.10 The following table outlines the movements in the 2026/27 HRA Capital budget: 
Housing Revenue Account  2026/27
£m
Budget as at 1 April 2026 70.104
Alterations to phasing between 2025/26 and 2026/27 2.235
Alterations to phasing of projects 2026/27 to Future
Years (10.757)
Alterations to phasing of projects 2026/27 to 2027/28 (9.037)
Alterations to phasing of projects 2027/28 to 2026/27 0.270
Budget as at 30 June 2026 52.815 
2.11  Alterations to the Phasing of Projects 
Sheltered Housing and Estates based regeneration projects have also been reprofiled
to reflect the most up to date delivery programme and this has resulted in (£10.757m)
being reprofiled into later financial years.   
Net planned expenditure of £2.235m has been reprofiled from 2025/26 to 2026/27,
reflecting projects not completed within the year which have been incorporated within
the 2026/27 capital programme. These were previously reported within the 2025/26
Capital Programme performance reports: 
Project Amount
£ million
Garnock Academy 0.577
Kings Arms, Irvine 0.490
Harbourside Irvine 0.152
James MacFarlane 0.064
Stanecastle, Irvine 0.048
Total Alterations to New Builds 1.331
Pathfinder Project 0.460
EWI 0.164
Total Alterations to Stock Improvements 0.624
Window Replacement High Flats 0.187

Page 10

Lift Replacement 0.093
Total Alterations to Other Capital Works 0.280
Alterations 2025/26 to 2026/27 2.235 
A further review of the timescale for delivery of capital projects has identified a
requirement to re-profile (£9.037m) of works for delivery in 2027/28 and beyond,
including: 
Project Amount
£ million
Montgomerie Park (7.550)
Grange Court. Stevenston (0.578)
Bourtreehill Village (0.371)
Regeneration project, Consultant Fees (0.167)
Fullarton Street High Flats (0.052)
Total Alterations to New Builds (8.718)
Kitchens (0.101)
Windows (0.095)
Bathrooms (0.090)
Other Minor Movements (0.033)
Total Alterations to Stock Improvements (0.319)
Alterations 2026/27 to 2027/28 (9.037)   
This has been partly offset by the acceleration of £0.270m of project expenditure for
delivery during 2026/27, including: 
Project Amount
£ million
St Michaels Phase 3 0.050
Corsehillhead  0.050
Redburn 0.050
Minor Movements 0.070
Total Alterations to New Builds 0.220
Redburn Grove 0.050
Total Alterations to Existing Stock 0.050
Alterations 2027/28 to 2026/27 0.270 
2.12 These adjustments have resulted in a revised 2026/27 budget at 30 June 2026 of
£52.815m. 
2.13 The impact on budgeted funding is a decrease of £17.289m from the approved budget
which will be met from reduced prudential borrowing. 
2.14  Projected Capital Expenditure to 31 March 2027 
The projections are summarised in the following table:

Page 11

Service /
Category
Approved
Budget
2026/27
£ million
Carry
Forwards and
Adjustments
£ million
Revised
Budget
2026/27
£ million
Projected
Expenditure
/ Income to
31 March
2027
£ million
Projected
Variance
Over /
(Under)
£ million
Housing
Revenue
Account
70.104 (17.289) 52.815 52.632 (0.183)
Total
Expenditure 70.104 (17.289) 52.815 52.632 (0.183)
CFCR (5.580) - (5.580) (5.580) -
Capital
Grants (12.872) - (12.872) (12.872)  
Use of
Reserves (1.580) - (1.580) (1.580) -
Affordable
Housing
Contribution
(1.202) - (1.202) (1.202) -
Prudential
Borrowing (48.870) 17.289 (31.581) (31.398) 0.183
Total Income (70.104) 17.289 (52.815) (52.632) 0.183 
2.15 A net underspend of (£0.183m) is projected within the HRA capital programme for
2026/27 arising from revisions to a number of projects, including: 
Project Variance
£ million Comments
Laburnum Avenue 0.108 Project complete
Bathrooms 0.078 Higher numbers projected
Roofing (0.039) Reduction in Costs
Wallfloor Rendering (0.330) Reduction in Cost per unit
Total Variance (0.183)   
2.16 In addition to the adjustments noted above, Appendix 2 highlights a proposed
virement which is required to transfer budget from Contingency to meet the additional
costs within the Garnock Academy site project, £0.898m and the James Reid project,
£0.050m. 
2.17 Cost pressures will continue to be monitored and a review of any potential impact on
the Business Plan and Capital Programme will be undertaken to address any
identified issues. Further information on the progress of all projects can be found in
Appendix 2.

Page 12

Treasury Management and Investment 
2.18 The Prudential Code for capital finance in local authorities (2021 edition) requires the
Council to set and monitor performance against specified prudential indicators. The
indicators for the current year were set out in the Treasury Management and
Investment Strategy 2026/27, approved by Council on the 25 February 2026. A
summary of the key indicators and our current estimated performance against them is
shown in the following table. Further details of all the Prudential and Treasury
indicators can be found in appendix 3. 
Prudential and Treasury Indicators
2026/27
Approved
Estimate
£ million
2026/27
Revised
Estimate
£ million
Movement
£ million
General Services Capital Financing
Requirement 470.500 441.379 (29.121)
HRA Capital Financing Requirement 256.479 227.339 (29.140)
Total Loans Capital Financing
Requirement 726.979 668.718 (58.261)
Gross Borrowing 683.675 622.215 (61.460)
Operational Boundary for Borrowing 740.741 683.072 (57.669)
Authorised Limit for Borrowing 814.815 751.379 (63.436)
Total Operational Boundary (incl.
PPP/NPD) 814.458 756.789 (57.669)
Total Authorised Limit (incl. PPP/NPD) 888.532 825.096 (63.436)
Investments 30.000 30.000 0.000 
2.19 Loans Capital Financing Requirement 
The Loans Capital Financing Requirement (CFR) is the underlying borrowing
requirement of the Council. This is currently lower than the approved estimate as a
result of the changes in the profiles of the capital programmes, resulting in a reduced
borrowing requirement for the year. 
2.20 Gross Borrowing 
Gross Borrowing is projected to be lower than anticipated due to the revised profile of
capital projects and the continued strategy to utilise internal funds to minimise
borrowing. 
2.21 Operational Boundary 
The Operational Boundary is the maximum which the Council anticipates borrowing to
fund the current year capital programme, building in flexibility for the timing of the
different funding streams and principal repayments. The in-year variance is linked to
the continued use of internal funds and the re-profiling of the capital programme.

Page 13

2.22 Investments 
It is estimated that the Council will maintain an average balance of £30.000m of
internally managed funds and utilise cash balances during the year in support of the
under-borrowed position.  The internally managed funds are primarily invested in call
accounts with banks, Money Market Funds and other UK local authorities. 
2.23 It is critical that the Council ensures that its capital investment plans are affordable.
Affordability of borrowing is measured by the percentage of financing costs relative to
the net revenue stream of the General Fund and the Housing Revenue Account
(HRA). As at 30 June, the estimated percentages for 2025/26 are 3.8% and 25.2% for
the General Fund and HRA respectively. Capital expenditure impacts on the revenue
budget through financing charges so it is essential the Council ensures the financing
costs remain affordable and do not constitute an excessive proportion of the revenue
resources available. From a General Fund perspective, the latest Scottish Local
Authority average was 6.0%, thereby demonstrating by comparison the prudent
nature of the current borrowing policy. For the HRA, the Scottish average was 20.7%.
The level of loan charges is deemed prudent and affordable within the framework of
the 30-year Housing business plan. 
3. Proposals 
3.1 It is proposed that Cabinet agrees to:
(a)  note the revisions to budgets outlined in the report; 
(b)  note (i) the General Services and HRA revised budgets at 30 June 2026; and (ii)
the forecast expenditure to 31 March 2027; 
(c)  approve the virement proposal noted within the HRA programme detailed in
appendix 2; and
(d) note the estimated performance against the Prudential Indicators set out in the
Treasury Management and Investment Strategy. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are as outlined in the report. Expenditure will continue to be
closely monitored to ensure early action is taken regarding any projected
underspends or overspends. 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None.

Page 14

Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by focusing our
investment on priorities, managing risk and supporting delivery of key priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Natalie Graham, Senior Manager (Corporate
Finance), Financial Management, on 01294 324533. 
Background Papers
Capital Investment Programme 2026/27 to 2033/34 - Council 25 February 2026
Housing Revenue Account (HRA) Capital Investment Plan, Revenue Budget and Rent
Levels for 2026/27 – Council 11 February 2026
Treasury Management and Investment Strategy 2026/27 – Council 25 February 2026

Page 15

OFFICIAL INFORMATION#
TOTAL PROJECT
Project Description Total Project Budget            Cumulative Expenditure
to date Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised
Budget 2026/27
Brought / Carry
Forward to 2027/28
Total Revised
Budget 2026/27
Actual Expenditure to
30th June 2026
Projected Expenditure
to 31st March 2027
Actual Over/
(Under) Spend for
2026/27
True Over/
(Under) Spend
£ £ £ £ £ £ £ £ £ £ £
EXPENDITURE
Education
Nursery Education 4,076,308 4,030,786 4,076,308 0 0 0 0 (45,522) 0 0 0
Primary Schools 45,897,652 38,020,440 45,897,652 0 4,993,933 0 4,993,933 (479,944) 4,993,933 0 0
Secondary Schools 127,328,721 33,066,549 127,328,721 0 91,377,761 (36,088,382) 55,289,379 7,658,844 55,289,379 0 0
Schools Other 1,658,495 388,994 1,658,495 0 1,391,994 0 1,391,994 122,492 1,391,994 0 0
SUB TOTAL 178,961,176 75,506,768 178,961,176 0 97,763,688 (36,088,382) 61,675,306 7,255,871 61,675,306 0 0
Communities & Housing
Information & Culture 643,522 404,867 643,522 0 504,224 0 504,224 265,568 504,224 0 0
Other Housing 338,805 0 338,805 0 338,805 0 338,805 0 338,805 0 0
Economic Development & Regen 43,720,528 16,080,570 43,720,528 0 25,962,458 (6,285,954) 19,676,504 396,060 19,676,504 0 0
SUB TOTAL 44,702,855 16,485,436 44,702,855 0 26,805,487 (6,285,954) 20,519,533 661,628 20,519,533 0 0
Corporate Services
Council IT Strategy 9,521,391 3,060,081 9,521,391 0 866,365 0 866,365 16,755 866,365 0 0
SUB TOTAL 9,521,391 3,060,081 9,521,391 0 866,365 0 866,365 16,755 866,365 0 0
Health & Social Care
Management & Support 1,165,484 382,993 1,165,484 0 747,496 0 747,496 0 747,496 0 0
Housing Non HRA 450,766 121,489 450,766 0 450,766 0 450,766 121,489 450,766 0 0
Adults 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 11,926 0 0
SUB TOTAL 6,224,328 5,100,634 6,224,328 0 1,210,188 0 1,210,188 121,489 1,210,188 0 0
Place
Roads 72,293,144 32,681,571 72,293,144 0 27,712,000 (707,440) 27,004,560 5,236,734 27,004,560 0 0
Streetscene 5,408,446 3,475,749 5,408,446 0 1,920,843 0 1,920,843 47,236 1,920,843 0 0
Transport 8,354,938 2,282,337 8,354,938 0 5,032,487 0 5,032,487 1,661,886 5,032,487 0 0
Waste Services 13,321,491 13,272,542 13,321,491 0 0 0 0 0 0 0 0
Renewable Energy 14,956,435 14,249,807 14,956,435 0 213,201 0 213,201 (493,427) 213,201 0 0
Office Accommodation 2,235,012 139,637 2,235,012 0 2,065,125 0 2,065,125 139,637 2,065,125 0 0
Other Property 4,504,529 3,469,590 4,504,529 0 1,147,942 0 1,147,942 113,003 1,147,942 0 0
Growth & Investment 148,064,798 60,389,091 148,064,798 0 14,446,843 0 14,446,843 (316,198) 14,446,843 0 0
Completed Projects 6,512,081 6,516,841 6,512,081 0 4,000 0 4,000 8,760 4,000 0 0
SUB TOTAL 275,650,874 136,477,165 275,650,874 0 52,542,441 (707,440) 51,835,001 6,397,632 51,835,001 0 0
Other
Other 12,459,553 0 12,459,553 0 (1,500,999) 4,567,377 3,066,378 0 3,066,378 0 0
SUB TOTAL 12,459,553 0 12,459,553 0 (1,500,999) 4,567,377 3,066,378 0 3,066,378 0 0
Total Project Expenditure 527,520,177 236,630,084 527,520,177 0 177,687,170 (38,514,399) 139,172,771 14,453,374 139,172,771 0 0
Total Project Income (177,687,170) 38,514,399 (139,172,771) (41,672,190) (139,172,771) 0 0
Total Net Expenditure 0 0 0 (27,218,815) 0 0 0
On Target (+0.5% of budget)
Slightly off target  (+ 0.5% to 2% of budget, or £0.125m, whichever is less)
Significantly off target (+2% or more of budget, or £0.500m, whichever is less)
The following classifications have been used to highlight financial performance against
budget
CURRENT YEAR 2026/27
North Ayrshire Council Capital Statement 2026/27
Year Ended 31st March 2027
Period 3
The following classifications have been used to
highlight delivery performance against original
timescales set
# OFFICIAL INFORMATION
Appendix 1

Page 16

OFFICIAL INFORMATION#
Revised Budget
26/27 Variance
£ £ £ £ £ £ £ £ £
CAPITAL BORROWING
Prudential Borrowing 106,173,876 10,075,100 11,114,546 127,363,522 (973,597) 126,389,925 93,819,391 (32,570,534)
SUB TOTAL 106,173,876 10,075,100 11,114,546 127,363,522 (973,597) 0 126,389,925 0 93,819,391 (32,570,534)
SCOTTISH GOVERNMENT FUNDING
Specific Capital Grants
Local Authority Direct Award 0 0 41,729 41,729 0 41,729 0
Vacant & Derelict Land Funding 5,106,031 254,137 91,621 5,451,789 (1,561,000) 3,890,789 3,890,788 1,685,265 (2,205,524)
Vacant & Derelict Land Investment Funding 0 892,990 892,990 0 892,990 892,990 892,990 0
Scottish Government Grant - AGD Great Harbour Ph 1 0 381,488 673,772 1,055,260 0 1,055,260 0 1,055,260 0
Scottish Government Grant - AGD Great Harbour Ph 2 500,000 500,000 0 500,000 0 500,000 0
UK Government Grant - AGD DPMC Ph 1 0 337,440 337,440 0 337,440 0 337,440 0
UK Government Grant - AGD Building Digital Capital 0 25,000 25,000 0 25,000 0 25,000 0
Islands Pit Stops 0 3,046 181,501 184,547 0 184,547 184,547 184,547 0
Place Based Investment Programme 608,628 128,073 243,952 980,653 0 980,653 980,654 980,653 0
UK Shared Prosperity Fund 0 159,900 159,900 0 159,900 159,900 159,900 0
UK Government Grant - B714 Improvements 7,605,697 (144,758) 598,324 8,059,263 0 8,059,263 15,664,961 8,059,263 0
UK Government - Local Regeneration Fund Funding 16,363,134 287,679 93,000 16,743,813 0 16,743,813 14,211,929 15,770,672 (973,141)
UK Government - Pride in Place Impact Fund 0 1,500,000 1,500,000 0 1,500,000 1,500,000 1,500,000 0
UK Government - Irvine Pride in Place Fund 0 360,000 360,000 360,000 360,000 0
UK Government -3 Towns Pride in Place Fund 0 117,604 117,604 117,604 117,604 0
Scottish Government Grant - Bourtreehill Village 0 1,169,000 1,169,000 0 233,800 (935,200)
20 mph Implementation 0 280,000 280,000 0 280,000 0
Marine Tourism Lochranza 0 129,718 129,718 0 129,718 129,718 129,718 0
Brodick Hall 323,925 323,925 0 323,925 323,925 323,925 0
Arran Youth Foundations Centre 382,299 382,299 0 382,299 382,299 382,299 0
Capital Grants
Flooding (895,880) (895,880) 0 (895,880) 0 (895,880) 0
General Capital Grant 9,441,000 77,000 9,518,000 1,467,866 10,985,866 3,343,000 10,985,866 0
SUB TOTAL 38,728,610 2,242,947 4,377,160 45,348,717 1,875,199 0 47,223,916 42,142,315 43,110,051 (4,113,865)
OTHER INCOME TO PROGRAMME
Use of Funds :-
Capital Fund 355,090 0 0 355,090 0 0 355,090 0 355,090 0
Grants & Contributions 0 30,069 166,119 196,188 2,112,776 0 2,308,964 (478,259) 478,964 (1,830,000)
Lochshore Garnock Hub - Garnock Rugby Club 0 0 0 (200,000) 0 0
AGD - Great Harbour - Sportscotland 0 0 (135,000) 0 0
Irvine Enterprise Area - NAVT 101,099 101,099 0 101,099 0 101,099 0
Bus Corridor Improvements - SPT 0 150,000 150,000 0 150,000 0
NCN7 Crossing Improvements Walk Wheel Cycle Trust 0 0 (18,224) 0 0
NCN7 Valefield/Glengarnock Bridge - Walk Wheel Cycle Trust 6,534 6,534 0 6,534 0
Brodick Tennis Courts - KA Leisure Contribution 20,319 20,319 (3,941) 16,378 16,378 16,378 0
UFSM West Kilbride PS - Persimmons Contribution 0 130,183 130,183 130,183 130,183 0
Depot Charging Scheme - Department of Transport 0 0 0 (271,597) 0 0
Bourtreehill Village Regeneration - NAVT 1,830,000 1,830,000 0 0 (1,830,000)
Repurposing Property Grant Fund - NAVT 9,750 65,020 74,770 0 74,770 0 74,770 0
Capital Receipts 865,000 536,140 0 1,401,140 8,135 0 1,409,275 8,135 1,409,275 0
Sale of Land and Buildings 865,000 536,140 1,401,140 0 1,401,140 0 1,401,140
Sale of Vehicles 0 4,080 4,080 4,080 4,080
Insurance Recoveries (Vehicles) 0 4,055 4,055 4,055 4,055
SUB TOTAL 1,220,090 566,209 166,119 1,952,418 2,120,911 0 4,073,329 (470,125) 2,243,329 (1,830,000)
TOTAL CAPITAL PROGRAMME FUNDING 146,122,576 12,884,256 15,657,825 174,664,657 3,022,513 0 177,687,170 41,672,190 139,172,771 (38,514,399)
Approved Budget
at Cabinet Feb
2026
Capital Programme Funding 2026/27
Projected Income
to 31st March
2027
Approved budget
at Period 1 used
as revised starting
point 2026/27
Actual Income to
30th June 2026Funding Description
Carry Forward
from 2025/26
Changes after
Capital Refresh Feb
2026
Total Changes in
Year
Changes at
Capital Refresh
Feb 2027
# OFFICIAL INFORMATION

Page 17

OFFICIAL INFORMATION#
EDUCATION
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual Expenditure
to 30th June 2026
Projected
Expenditure to 31
March 2027
Actual Over/ (Under)
Spend for 2026/27
True Over/(Under)
Spend            
Brought / Carry
Forward to 2027/28 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Nursery Education
Early Years Programme
MARRESS HOUSE 4,076,308 4,030,786 4,076,308 0 0 (45,522) 0 0 0 Complete Complete Complete Complete Complete
Total Nursery Education 4,076,308 4,030,786 4,076,308 0 0 (45,522) 0 0 0 0
Primary Schools
MOORPARK PRIMARY 14,885,024 14,708,340 14,885,024 0 0 (176,683) 0 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK SCHOOL 22,848,999 21,856,070 22,848,999 0 684,030 (308,898) 684,030 0 0 Complete Complete Complete Complete Complete
FAIRLIE PRIMARY SCHOOL 542,444 101,215 542,444 0 441,732 503 441,732 0 0 31-Aug-26 31-Aug-26 Feasibility On Target On Target
UNIVERSAL FREE SCHOOL MEALS EXPANSION 513,160 0 513,160 0 513,160 0 513,160 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
UFSM ARDEER PRIMARY SCHOOL 17,634 16,548 17,634 0 783 (303) 783 0 0 Complete Complete Complete Complete Complete
UFSM CORSEHILL PRIMARY SCHOOL 147,940 144,680 147,940 0 0 (3,260) 0 0 0 Complete Complete Complete Complete Complete
UFSM FAIRLIE PRIMARY SCHOOL 30,000 0 30,000 0 30,000 0 30,000 0 0 31-Aug-26 31-Aug-26 Feasibility On Target On Target
UFSM GLENCAIRN PRIMARY SCHOOL 11,203 10,256 11,203 0 783 (164) 783 0 0 Complete Complete Complete Complete Complete
UFSM HAYOCKS PRIMARY SCHOOL 94,984 93,061 94,984 0 0 (1,923) 0 0 0 Complete Complete Complete Complete Complete
UFSM KILMORY PRIMARY SCHOOL 65,654 57,473 65,654 0 8,181 0 8,181 0 0 Complete Complete Complete Complete Complete
UFSM LOUDOUN-MONTGOMERY PRIMARY SCHOOL 2,082,540 139,905 2,082,540 0 1,721,921 10,933 1,721,921 0 0 31-Dec-26 31-Dec-26 Feasibility On Target On Target
UFSM PENNYBURN PRIMARY SCHOOL 10,455 9,523 10,455 0 784 (148) 784 0 0 Complete Complete Complete Complete Complete
UFSM WEST KILBRIDE PRIMARY SCHOOL 4,177,947 413,700 4,177,947 0 1,592,559 0 1,592,559 0 0 31-Aug-27 31-Aug-27 On Site On Target On Target
Total Primary Education 45,897,652 38,020,440 45,897,652 0 4,993,933 (479,944) 4,993,933 0 0 0
Secondary Schools
ARDROSSAN NEW BUILD 124,558,601 30,296,428 124,558,601 0 91,377,761 7,658,844 55,289,379 (36,088,382) (36,088,382) Winter 2027 26-May-28 On Site On Target Significantly off target
Total Secondary Education 127,328,721 33,066,549 127,328,721 0 91,377,761 7,658,844 55,289,379 (36,088,382) 0 (36,088,382)
Schools Other
CO2 MONITORS IN SCHOOLS 298,000 284,408 298,000 0 31,499 17,907 31,499 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
SCHOOLS ICT INVESTMENT * 1,360,495 104,586 1,360,495 0 1,360,495 104,586 1,360,495 0 0 31-Mar-27 31-Mar-27 On-going On Target On Target
Total Schools Other 1,658,495 388,994 1,658,495 0 1,391,994 122,492 1,391,994 0 0 0
Total Education 178,961,176 75,506,768 178,961,176 0 97,763,688 7,255,871 61,675,306 (36,088,382) 0 (36,088,382)
CAPITAL MONITORING 2026/27
CommentsProject Description
TOTAL PROJECT COMPLETION DATES DELIVERY STATUS2026/27 BUDGETS
# OFFICIAL INFORMATION

Page 18

OFFICIAL INFORMATION#
COMMUNITIES & HOUSING
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual Expenditure
to 30th June 2026
Projected
Expenditure to 31
March 2027
Actual Over/ (Under)
Spend for 2026/27
True Over/(Under)
Spend            
Brought / Carry
Forward to 2027/28 Original Target Revised Forecast Current Project Stage Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Information & Culture
CASTLES & HISTORIC MONUMENTS 38,303 0 38,303 0 38,303 0 38,303 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
ABBEY TOWER 73,807 255,753 73,807 0 67,244 249,190 67,244 0 0 31-Jul-26 31-Jul-26 Procurement On Target On Target
BRODICK TENNIS COURTS 149,114 149,114 149,114 0 16,378 16,378 16,378 0 0 30-Sep-25 31-May-26 Construction On Target On Target
ARRAN YOUTH FOUNDATIONS CENTRE 382,299 0 382,299 0 382,299 0 382,299 0 0 31-Mar-27 31-Mar-27 In Development On Target On Target
Total Information & Cultural 643,522 404,867 643,522 0 504,224 265,568 504,224 0 0 0
Other Housing
CCTV REVIEW 338,805 0 338,805 0 338,805 0 338,805 0 0 30-Jun-26 30-Oct-26 Ongoing On Target On Target
Total Other Housing 338,805 0 338,805 0 338,805 0 338,805 0 0 0
Regeneration
REPURPOSING PROPERTY GRANT FUND 508,854 12,975 508,854 0 508,174 12,295 508,174 0 0 30-May-25 31-Mar-27 In development On Target On Target
MILLPORT TOWN HALL PHASE 2 9,088 (55,938) 9,088 0 9,088 (55,938) 9,088 0 0 Complete Complete Complete Complete Complete Community led regeneration project
b ill ll h i jISLANDS PIT STOPS 218,321 110,385 218,321 0 184,547 76,611 184,547 0 0 31-Jul-25 31-Dec-26 In development On Target On Target
PLACE BASED INVESTMENT PROGRAMME (PBIP) 205,550 50,823 205,550 0 156,177 1,450 156,177 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
UK SHARED PROSPERITY FUND (SPF) 159,900 54,470 159,900 0 159,900 54,470 159,900 0 0 31-Mar-26 30-Sep-26 In development On Target On Target
PBIP – KILWINNING ABBEY IMPROVEMENTS 264,559 201,266 264,559 0 209,543 146,250 209,543 0 0 31-Mar-25 31-Dec-26 Construction On Target On Target
LOCHSHORE HUB PLAY AREA 354,999 308,077 354,999 0 17,847 4,485 17,847 0 0 Complete Complete Complete Complete Complete
PBIP 36 BANK STREET 139,999 120,162 139,999 0 19,837 0 19,837 0 0 Complete Complete Complete Complete Complete
IRVINE HIGH STREET 2,837,315 2,723,228 2,837,315 0 99,087 (15,000) 99,087 0 0 Complete Complete Complete Complete Complete
MONTGOMERIE PARK MASTERPLAN 4,218,598 1,963,607 4,218,598 0 269,362 4,372 269,362 0 0 31-Mar-30 31-Mar-30 In development On Target On Target
LOCHSHORE, KILBIRNIE 2,101,881 2,015,480 2,101,881 0 86,401 0 86,401 0 0 31-May-25 01-Dec-26 In development On Target On Target
LOCHSHORE GARNOCK HUB 4,170,999 4,125,112 4,170,999 0 60,492 14,605 60,492 0 0 Complete Complete Complete Complete Complete
VDLF - KYLE ROAD PHASE 2 4,525,506 190,782 4,525,506 0 4,334,724 0 2,750,000 (1,584,724) (1,584,724) 31-Mar-27 31-Mar-28 In development On Target On Target
VDLF - ANNICKBANK PH 3 1,948,996 1,944,450 1,948,996 0 4,546 0 4,546 0 0 Complete Complete Complete Complete Complete
LUF3 - ANNICKBANK 5,024,602 216,861 5,024,602 0 4,883,941 76,201 4,000,000 (883,941) (883,941) 31-Mar-27 31-Mar-28 Construction On Target On Target
VDLF - DEVELOPMENT WORK 199,979 100,569 199,979 0 106,512 7,102 106,512 0 0 31-Mar-26 31-Dec-26 In development On Target On Target
VDLF - TREE PLANTING 50,000 2,400 50,000 0 47,600 0 47,600 0 0 31-Dec-24 31-Dec-26 In development On Target On Target
MONTGOMERIE PARK NEIGHBOURHOOD CTR 260,384 179,307 260,384 0 81,077 0 81,077 0 0 30-Sep-24 31-Mar-27 Construction On Target On Target
LOCHSHORE GARDEN/ACTIVITY HUB 827,075 79,809 827,075 0 782,158 34,891 782,158 0 0 31-Dec-26 31-Mar-27 In development On Target On Target
NORTH SHORE RESIDENTIAL 150,000 0 150,000 0 150,000 0 40,000 (110,000) (110,000) 31-Mar-29 31-Mar-29 In development On Target On Target
PBIP DOCKHEAD STREET 331,893 10,323 331,893 0 323,535 1,965 323,535 0 0 31-Mar-26 31-Mar-27 In development On Target On Target
PBIP PUBLIC SPACE CAMERA 50,000 0 50,000 0 50,000 0 50,000 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP BEITH KIRK 39,500 0 39,500 0 39,500 0 39,500 0 0 31-Mar-26 31-Dec-26 In development On Target On Target
PBIP HAYOCKS HALL COMMUNITY LARDER 32,500 806 32,500 0 31,694 0 31,694 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP CRANBERRY MOSS COMMUNITY CENTRE 32,500 131 32,500 0 32,369 0 32,369 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP SHEWALTON POND ACCESS IMPROVEMENTS 27,500 933 27,500 0 27,500 933 27,500 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PBIP EGLINTON PARK IMPROVEMENTS 10,000 9,731 10,000 0 9,167 8,898 9,167 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
PRIDE IN PLACE IMPACT FUND 1,500,000 0 1,500,000 0 1,500,000 0 1,500,000 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
IRVINE PRIDE IN PLACE FUND 360,000 0 360,000 0 360,000 0 360,000 0 0 31-Mar-36 31-Mar-36 Planning On Target On Target
THREE TOWNS PRIDE IN PLACE FUND 117,604 0 117,604 0 117,604 0 117,604 0 0 31-Mar-37 31-Mar-37 Planning On Target On Target
BOURTREEHILL VILLAGE REGENERATION 3,278,483 0 3,278,483 0 3,278,483 0 233,800 (3,044,683) (3,044,683) 31-Dec-27 31-Dec-27 Planning On Target On Target
ACTIVE TRAVEL TIER 1 1,153,970 21,331 1,153,970 0 1,153,970 21,331 1,091,364 (62,606) (62,606) 31-Mar-27 30-Sep-27 Various On Target On Target
ACCESS PATH NETWORK PROGRAMME 538,854 46 538,854 0 488,854 46 488,854 0 0 31-Mar-27 31-Mar-27 Various On Target On Target
BUS CORRIDOR IMPROVEMENT GRANT 150,000 0 150,000 0 150,000 0 150,000 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
NCN7 VALEFIELD/GLENGARNOCK BRIDGE 6,534 0 6,534 0 6,534 0 6,534 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
LOCAL AUTHORITY DIRECT AWARD 41,729 0 41,729 0 41,729 0 41,729 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
FAIRLIE COASTAL PATH 0 (12,091) 0 0 0 (12,091) 0 0 0 Complete Complete Complete Complete Complete
ARDROSSAN PROMENADE 788,000 787,900 788,000 0 100 0 100 0 0 Complete Complete Complete Complete Complete
BUS INFRASTRUCTURE FUND 288,000 246,993 288,000 0 41,007 0 41,007 0 0 31-Mar-26 30-Sep-26 In development On Target On Target
LONG DRIVE 956,620 357,745 956,620 0 607,047 8,172 607,047 0 0 31-Mar-28 31-Mar-28 In development On Target On Target
RIVERSIDE WAY 867,180 9,814 867,180 0 861,518 4,152 861,518 0 0 31-Dec-26 31-Dec-26 In development On Target On Target
STRATEGIC INVESTMENT ROUTE 2,386,827 189,527 2,386,827 0 2,198,160 860 1,598,160 (600,000) (600,000) 31-Mar-28 31-Mar-28 Construction On Target On Target
KYLE ROAD AT ROUTE 1,073,678 64,111 1,073,678 0 1,009,567 0 1,009,567 0 0 31-Mar-26 31-Aug-26 In development On Target On Target
PORTLAND RD REDEVELOPMENT 1,463,107 0 1,463,107 0 1,463,107 0 1,463,107 0 0 31-Mar-28 31-Mar-28 Planning On Target On Target
Total Regeneration 43,720,528 16,080,570 43,720,528 0 25,962,458 396,060 19,676,504 (6,285,954) 0 (6,285,954)
Total Communities & Housing 44,702,855 44,125,395 17,062,897 43,720,528 26,805,487 661,628 20,519,533 (6,285,954) 0 (6,285,954)
Comments
CAPITAL MONITORING 2026/27
Project Description
TOTAL PROJECT 2026/27 BUDGETS COMPLETION DATES DELIVERY STATUS
# OFFICIAL INFORMATION

Page 19

OFFICIAL INFORMATION#
CORPORATE SERVICES
MILESTONE
Total Project Budget                   
Cumulative
Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual
Expenditure to
30th June 2026
Projected
Expenditure to 31
March 2027
Actual Over/
(Under) Spend for
2026/27
True Over/(Under)
Spend            
Brought / Carry
Forward to
2027/28
Original Target Revised Forecast Current Project
Stage
Delivery Status
Financial Delivery Status Physical
£ £ £ £ £ £ £ £ £ £
Council IT Strategy
ICT INVESTMENT FUND 5,315,581 1,871,826 5,315,581 0 483,555 1,500 483,555 0 0 31-Mar-27 31-Mar-27 On-going On Target On Target
CONNECTIVITY 1,347,810 11,484 1,347,810 0 197,810 11,484 197,810 0 0 31-Mar-28 31-Mar-28 Planning On Target On Target
DATA CENTRE COLOCATION 185,000 3,770 185,000 0 185,000 3,770 185,000 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
Total IT Strategy 9,521,391 3,060,081 9,521,391 0 866,365 16,755 866,365 0 0 0
Total Corporate Services 9,521,391 3,060,081 9,521,391 0 866,365 16,755 866,365 0 0 0
CAPITAL MONITORING 2026/27
CommentsProject Description
COMPLETION DATESTOTAL PROJECT DELIVERY STATUS2026/27 BUDGETS
# OFFICIAL INFORMATION

Page 20

OFFICIAL INFORMATION#
HEALTH & SOCIAL CARE
MILESTONE
Total Project
Budget                   
Cumulative
Expenditure to date                  Total Project Forecast                  Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual Expenditure
to 30th June 2026
Projected Expenditure
to 31 March 2027
Actual Over/
(Under) Spend for
2026/27
True Over/(Under)
Spend            
Brought / Carry
Forward to 2027/28 Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £
Management & Support
ECLIPSE 536,058 382,993 536,058 0 153,065 0 153,065 0 0 14-Jan-27 31-Mar-27 Construction On Target On Target
CARE AT HOME MANAGEMENT SYSTEM 629,426 0 629,426 0 594,431 0 594,431 0 0 31-Mar-28 31-Mar-28 Planning On Target On Target
Total Management & Support 1,165,484 382,993 1,165,484 0 747,496 0 747,496 0 0 0
Housing Non HRA
IMPROVEMENT GRANTS * 450,766 121,489 450,766 0 450,766 121,489 450,766 0 0 31-Mar-27 31-Mar-27 Ongoing On Target On Target
Total Housing Non HRA 450,766 121,489 450,766 0 450,766 121,489 450,766 0 0 0
Adults
TRINDLEMOSS 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 0 Complete Complete Complete Complete Complete
Total Older People 4,608,078 4,596,152 4,608,078 0 11,926 0 11,926 0 0 0
Total Health & Social Care 6,224,328 5,100,634 6,224,328 0 1,210,188 121,489 1,210,188 0 0 0
Project Description
DELIVERY STATUS
CAPITAL MONITORING 2026/27
2026/27 BUDGETSTOTAL PROJECT COMPLETION DATES
Comments
# OFFICIAL INFORMATION

Page 21

OFFICIAL INFORMATION#
PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual
Expenditure to
30th June 2026
Projected
Expenditure to 31
March 2027
Actual Over/
(Under) Spend for
2026/27
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2027/28
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
£ £ £ £ £ £ £ £ £ £
Roads
ROADS IMPROVE/RECONSTRUCTION * 7,729,428 271,738 7,729,428 0 7,729,428 271,738 7,729,428 0 0 31-Mar-27 31-Mar-27 Multiple Projects On Target On Target
ROAD SAFETY IMPROVEMENT FUND 0 (4,100) 0 0 0 (4,100) 0 0 0 Complete Complete Complete Complete Complete
20MPH IMPLEMENTATION 280,000 96,180 280,000 0 280,000 96,180 280,000 0 0 Complete Complete Complete Complete Complete
TRAFFIC CALMING 175,000 0 175,000 0 82,953 0 82,953 0 0 31-Mar-27 31-Mar-27 In Development On Target On Target
CYCLICAL REPLACEMENT OF TRAFFIC SIGNALS 275,000 0 275,000 0 100,000 0 100,000 0 0 31-Mar-29 31-Mar-29 Planning On Target On Target
DOCKHEAD STREET SALTCOATS 100,000 0 100,000 0 100,000 0 100,000 0 0 31-Mar-27 31-Mar-27 In development On Target On Target
LIGHTING * 1,367,349 60,665 1,367,349 0 1,367,349 60,665 1,367,349 0 0 31-Mar-27 31-Mar-27 Multiple Projects On Target On Target
UPPER GARNOCK FPS 20,190,489 20,102,374 20,190,489 0 1,611,404 1,523,288 1,611,404 0 0 Complete Complete Complete Complete Complete
MILLBURN FPS 4,684,650 2,814,034 4,684,650 0 3,113,825 1,243,209 3,113,825 0 0 15-Sep-26 15-Sep-26 Construction On Target On Target
MILLPORT PIER 1,350,000 150,080 1,350,000 0 707,440 0 0 (707,440) (707,440) 31-Dec-27 31-Dec-27 In Development On Target On Target
BRIDGES INFRASTRUCTURE PROG * 942,334 153,813 942,334 0 942,334 153,813 942,334 0 0 31-Mar-27 31-Mar-27 Multiple Projects On Target On Target
COASTAL ADAPTATIONS 315,000 52,269 315,000 0 73,930 11,199 73,930 0 0 31-Mar-29 31-Mar-29 In Development On Target On Target
B714 UPGRADE 34,733,443 8,902,367 34,733,443 0 11,532,910 1,878,615 11,532,910 0 0 31-Aug-27 31-Aug-27 Tender On Target On Target
B714 PROJECT MANAGEMENT SYSTEM 16,192 0 16,192 0 16,192 0 16,192 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
PARKING CHARGES & DPE 134,260 82,152 134,260 0 54,235 2,128 54,235 0 0 31-Mar-27 31-Mar-27 In Development On Target On Target
Total Roads 72,293,144 32,681,571 72,293,144 0 27,712,000 5,236,734 27,004,560 (707,440) 0 (707,440)
Streetscene
CEMETERY EXTNS, WALLS & INFRA * 457,661 0 457,661 0 398,571 0 398,571 0 0 Holding Code Holding Code Holding Code Holding Code Holding Code
CMTY, KILBIRNIE - WALLS 119,675 119,140 119,675 0 0 (535) 0 0 0 Complete Complete Complete Complete Complete
CMTY, BEITH - WALLS 162,395 159,516 162,395 0 0 (2,879) 0 0 0 Complete Complete Complete Complete Complete
CMTY, ABBEY TOWER - WALLS 159,357 156,149 159,357 0 0 (3,208) 0 0 0 Complete Complete Complete Complete Complete
CMTY, STEV HAWKHILL - WALLS 89,670 87,930 89,670 0 0 (1,740) 0 0 0 Complete Complete Complete Complete Complete
CMTY, WEST KILBRIDE - WALLS 110,397 107,991 110,397 0 0 (2,406) 0 0 0 Complete Complete Complete On Target On Target
CMTY, IRVINE OP CHURCH - WALLS 15,243 6,998 15,243 0 8,245 0 8,245 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, STEV HIGH KIRK - WORKS 30,802 33,117 30,802 0 5,070 7,385 5,070 0 0 Future years Future years Feasibility Works On Target On Target
CMTY, KILBIRNIE - NEW 1,501,663 585,627 1,501,663 0 947,142 31,106 947,142 0 0 01-Oct-26 01-Oct-26 Construction On Target On Target
PARK ENABLING WORKS 149,895 149,415 149,895 0 480 0 480 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
RENEWAL OF PLAY PARKS 1,411,000 869,178 1,411,000 0 561,335 19,513 561,335 0 0 31-Mar-27 31-Mar-27 Construction On Target On Target
Total Streetscene 5,408,446 3,475,749 5,408,446 0 1,920,843 47,236 1,920,843 0 0 0
Transport
VEHICLES * 3,328,073 1,660,387 3,328,073 0 3,328,073 1,660,387 3,328,073 0 0 31-Mar-27 31-Mar-27 Ongoing On Target On Target
FLEET DECARBONISATION 5,026,865 621,950 5,026,865 0 1,704,414 1,499 1,704,414 0 0 31-Mar-27 31-Mar-27 Ongoing On Target On Target
Total Transport 8,354,938 2,282,337 8,354,938 0 5,032,487 1,661,886 5,032,487 0 0 0
Renewable Energy
SOLAR PV INVESTMENT - NETHERMAINS 8,290,950 7,998,830 8,290,950 0 0 (292,121) 0 0 0 Complete Complete Complete Complete Complete
SOLAR PV INVESTMENT - SHEWALTON 5,954,484 5,714,172 5,954,484 0 38,510 (201,802) 38,510 0 0 Complete Complete Complete Complete Complete
NATURE RESTORATION FUND 711,000 536,806 711,000 0 174,691 496 174,691 0 0 31-Aug-24 31-Mar-27 Planning On Target On Target
Total Renewable Energy 14,956,435 14,249,807 14,956,435 0 213,201 (493,427) 213,201 0 0 0
Office Accommodation
PROPERTY LIFECYCLE INVESTMENT 66,476 0 66,476 0 66,476 0 66,476 0 0 31-Mar-27 31-Mar-27 Mulitple projects On Target On Target
PLI WEST BYREHILL DEPOT 90,000 0 90,000 0 90,000 0 90,000 0 0 30-Nov-26 30-Nov-26 Planning On Target On Target
PLI GOLDCRAIGS DEPOT 169,887 (6,252) 169,887 0 0 (6,252) 0 0 0 Complete Complete Complete Complete Complete
PLI CALEDONIA PRIMARY 1,038,355 137,567 1,038,355 0 1,038,355 137,567 1,038,355 0 0 31-Mar-27 31-Mar-27 Construction On Target On Target
PLI CORSEHILL PRIMARY 150,000 0 150,000 0 150,000 0 150,000 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
PLI DALRY PRIMARY SCHOOL 697,244 0 697,244 0 697,244 0 697,244 0 0 31-Mar-27 31-Mar-27 Construction On Target On Target
PLI HAYOCKS PRIMARY SCHOOL 3,292 0 3,292 0 3,292 0 3,292 0 0 Complete Complete Complete Complete Complete
PLI PENNYBURN PRIMARY 0 (3,727) 0 0 0 (3,727) 0 0 0 Complete Complete Complete Complete Complete
PLI SKELMORLIE PRIMARY SCHOOL 0 (7,708) 0 0 0 (7,708) 0 0 0 Complete Complete Complete Complete Complete
PLI THE PORTAL 19,758 19,758 19,758 0 19,758 19,758 19,758 0 0 Complete Complete Complete Complete Complete
Total Office Accommodation 2,235,012 139,637 2,235,012 0 2,065,125 139,637 2,065,125 0 0 0
Other Property
LOCALITY BASED PROPERTY REVIEW 265,667 0 265,667 0 265,667 0 265,667 0 0 31-Mar-25 31-Mar-27 In development On Target On Target
LBPR CUNNINGHAME HOUSE 238,000 139,028 238,000 0 128,708 29,736 128,708 0 0 31-Mar-27 31-Mar-27 Construction On Target On Target
Comments
CAPITAL MONITORING 2026/27
COMPLETION DATES
Project Description
TOTAL PROJECT 2026/27 BUDGETS DELIVERY STATUS
# OFFICIAL INFORMATION

Page 22

OFFICIAL INFORMATION#
PLACE
MILESTONE
Total Project Budget                    Cumulative
Expenditure to date                  Total Project Forecast Projected Over/
(Under) Spend               
Total Revised Budget
2026/27
Actual
Expenditure to
30th June 2026
Projected
Expenditure to 31
March 2027
Actual Over/
(Under) Spend for
2026/27
True
Over/(Under)
Spend            
Brought / Carry
Forward to
2027/28
Original Target Revised Forecast Current Project Stage Delivery Status
Financial
Delivery Status
Physical
Comments
CAPITAL MONITORING 2026/27
COMPLETION DATES
Project Description
TOTAL PROJECT 2026/27 BUDGETS DELIVERY STATUS
LBPR CUNNINGHAME HOUSE GRD EAST/4TH WEST 1,248,118 1,178,614 1,248,118 0 152,573 83,069 152,573 0 0 Complete Complete Complete Complete Complete
LBPR CUNNINGHAME HOUSE GRD WEST 201,777 173,673 201,777 0 28,104 0 28,104 0 0 Complete Complete Complete Complete Complete
LBPR - THE TOWNHOUSE 24,999 23,486 24,999 0 15,639 14,126 15,639 0 0 Complete Complete Complete Complete Complete
LBPR THE CIRCUIT 311,571 248,327 311,571 0 63,244 0 63,244 0 0 31-Mar-27 30-Sep-26 Construction On Target On Target
EMERGENCY CONTROL CTR 158,000 152,136 158,000 0 4,562 (1,302) 4,562 0 0 Complete Complete Complete Complete Complete
GOLDCRAIGS REFURBISHMENT 1,163,495 1,010,926 1,163,495 0 128,049 (24,520) 128,049 0 0 Complete Complete Complete Complete Complete
SALT DOME GOLDCRAIGS 360,468 360,468 360,468 0 13,952 13,952 13,952 0 0 Complete Complete Complete Complete Complete
BRODICK HALL 323,925 0 323,925 0 323,925 0 323,925 0 0 31-Mar-27 31-Mar-27 Planning On Target On Target
WOODLANDS PRIMARY PLAYINGFIELD DRAINAGE 134,641 109,065 134,641 0 23,519 (2,057) 23,519 0 0 Complete Complete Complete Complete Complete
Total Property 4,504,529 3,469,590 4,504,529 0 1,147,942 113,003 1,147,942 0 0 0
Ayrshire Growth Deal
AGD - I3 DPMC PHASE 1 1,000,000 897,484 1,000,000 0 337,440 234,925 337,440 0 0 31-Mar-26 31-Mar-26 Delivery On Target On Target
AGD - I3 DPMC PHASE 2 6,224,999 346,615 6,224,999 0 102,443 9,691 102,443 0 0 31-Mar-29 31-Mar-30 Feasibility On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 1 4,897,985 4,833,238 4,897,985 0 0 (64,747) 0 0 0 Complete Complete Complete Complete Complete
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 2 6,156,259 542,798 6,156,259 0 4,574,700 55,589 4,574,700 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - I3 FLEXIBLE BUSINESS SPACE PHASE 3 9,369,585 6,767 9,369,585 0 369,585 6,767 369,585 0 0 31-Mar-29 31-Mar-29 Multiple Projects On Target On Target
AGD - HUNTERSTON - CENTRE OF LOW CARBON ENERGY & CIRCULAR 12,040,000 321,503 12,040,000 0 315,003 18,773 315,003 0 0 31-Mar-30 30-Nov-30 Feasibility On Target On Target
AGD - GH PHASE 1 COASTAL HUB 6,510,768 5,044,603 6,510,768 0 1,636,822 454,752 1,636,822 0 0 31-Mar-29 31-Mar-27 Delivery On Target On Target
AGD - GH PHASE 2 MARITIME MILE 7,996,866 166,841 7,996,866 0 520,561 55,029 520,561 0 0 31-Mar-29 31-Mar-29 Design On Target On Target
AGD - IMSE 15,275,000 250,731 15,275,000 0 281,441 7,565 281,441 0 0 31-Mar-30 31-Mar-30 Feasibility On Target On Target
AGD - MARINE TOURISM ARRAN 4,571,991 305,653 4,571,991 0 333,902 12,545 333,902 0 0 31-Mar-29 31-Mar-30 Feasibility On Target On Target
AGD - MARINE TOURISM CUMBRAE 4,796,278 345,235 4,796,278 0 458,455 35,055 458,455 0 0 31-Mar-29 31-Mar-30 Design On Target On Target
AGD -BUILDING DIGITAL CAPITAL 4,630,000 19,025 4,630,000 0 13,118 7,143 13,118 0 0 31-Mar-30 31-Mar-30 Design On Target On Target
Total Ayrshire Growth Deal 83,745,448 13,356,211 83,745,448 0 8,943,470 833,086 8,943,470 0 0 0
Growth & Investment
ARDROSSAN HARBOUR INTERCHANGE 4,127,113 608,920 4,127,113 0 3,519,122 929 3,519,122 0 0 1st Qtr 2026 TBC Design On Hold On Hold
IRVINE ENTERPRISE AREA 10,736,892 0 10,736,892 0 103,079 0 103,079 0 0 Ongoing Ongoing Multiple Projects On Target On Target
ARDROSSAN NORTH SHORE 48,888,716 46,008,199 48,888,716 0 1,730,304 (1,150,214) 1,730,304 0 0 Complete Complete Complete Complete Complete
VDLF - I3 IRVINE ENTERPRISE 278,170 257,020 278,170 0 21,150 0 21,150 0 0 31-Mar-26 31-Mar-26 Design On Target On Target
MARINE TOURISM LOCHRANZA 129,718 0 129,718 0 129,718 0 129,718 0 0 31-Mar-26 31-May-26 Development On Target On Target
Other Growth & Investment 64,319,350 47,032,879 64,319,350 0 5,503,373 (1,149,284) 5,503,373 0 0 0
Total Growth & Investment 148,064,798 60,389,091 148,064,798 0 14,446,843 (316,198) 14,446,843 0 0 0
Completed Projects
BIOMASS RETROFIT PROGRAMME 3,378,163 3,377,163 3,378,163 0 0 (1,000) 0 0 0 Complete Complete Complete Complete Complete
QUARRY ROAD PHASE 1 3,133,918 3,139,678 3,133,918 0 4,000 9,760 4,000 0 0 Complete Complete Defects Period Complete Complete
Total Completed Projects 6,512,081 6,516,841 6,512,081 0 4,000 8,760 4,000 0 0 0
Total Place 275,650,874 136,477,165 275,650,874 0 52,542,441 6,397,632 51,835,001 (707,440) 0 (707,440)
# OFFICIAL INFORMATION

Page 23

OFFICIAL INFORMATION#
OTHER BUDGETS
AE
Total Project Budget                    Cumulative Expenditure to
date                 
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2026/27
Actual Expenditure
to 30th June 2026
Projected
Expenditure to 31
March 2027
Over/ (Under)
Spend for 26/27
£ £ £ £ £ £ £ £
FLEXIBILITY / IMPROVEMENT FUND 12,459,553 0 12,459,553 0 (3,501,999) 0 1,065,378 4,567,377
CORE INFRASTRUCTURE INVESTMENT 2,001,000 0 2,001,000 0 2,001,000 0 2,001,000 0
Total Other Budgets 14,460,553 0 14,460,553 0 (1,500,999) 0 3,066,378 4,567,377
2026/27 BUDGETS
CommentsProject Description
TOTAL PROJECT
# OFFICIAL INFORMATION

Page 24

OFFICIAL-PROTECT INFORMATION#
HRA Capital Statement 2627 Appendix 2
TOTAL PROJECT CURRENT YEAR 2026/27 - Period 2
Project Description Total Project
Budget           
Cumulative
Expenditure to
date
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2026/27
Actual Expenditure to 31
May 2026 P2 Projection Virement
Request
Carry /Brought
Forward to
/From Future
Years
True Over/
(Under) Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
EXPENDITURE
Council House Building
Afton Court 1,335,654 1,249,279 1,249,898 (85,756) Complete Complete Complete.
Flatt Road 20,178,000 19,706,151 19,709,046 (468,954) 0 Complete Complete Complete
Friars Lawn 2,199,628 2,085,562 2,085,598 (114,030) 0 Complete Complete Complete
Garrier Court 2,335,551 2,414,910 2,348,027 12,476 0 Complete Complete Complete
0 0 500 14,282,715 14,282,715 152,030 0 152,030 0 Complete Complete Complete - 2526 carry forward required due to reimbursement of funds to the general
fund and Scottish Government for abnormal works that cost less than projected.
James McFarlane Site 4,784,118 988,307 4,784,118 0 64,589 (53,701) 64,589 Complete Complete Complete - project still under DLP, carry forward required to cover any additional works
which may be required during this period.
Laburnum Ave/Newhouse Dr (Regen 1a&b) 2,953,447 1,388,824 2,953,449 2 0 (1,946) 108,033 108,033 Complete Complete Complete - not financially complete due to contractor going in to administration.
Largs Police Station 2,769,301 2,749,750 2,759,323 (9,978) (12) Complete Complete Complete
Stanecastle Site 7,854,314 1,307,586 7,854,314 0 47,707 (102,737) 47,707 Complete Complete Complete - project still under DLP, carry forward required to cover any additional works
which may be required during this period.
St Beya Gardens 3,691,052 3,689,345 3,691,052 0 0 Complete Complete Complete 
St Michael's Wynd 13,996,769 14,097,411 14,087,664 90,895 0 Complete Complete Complete
Ukraine Buy Backs 498 498 Complete Complete Complete
St Mary's Primary, Largs 6,528,399 8,894 6,553,916 25,517 0 (38,671) 29,624 29,624 Complete Complete Complete
Towerlands Primary School 8,579,943 8,574,482 8,579,943 0 0 Complete
Ayrshire Central Site 49,841,415 21,707,241 49,841,415 0 14,231,967 3,237,581 14,231,967 0 On Target On Target Project delayed due to additional services not picked up on the GRP survey, the
requirement to dewater the site, and breaking out concrete to allow foundations to
progress.
Bourtreehill Village 10,037,524 311,017 10,037,524 0 421,308 950 50,000 (371,308) On Target On Target Main spend anticipated 2829. CF to be reprofiled to future years.
Fullarton Street (High Flats) 13,302,808 151,688 13,302,808 0 1,027,925 36,995 975,760 (52,165) On Target On Target
Garnock Academy Site 12,286,082 6,397,893 12,719,371 433,289 576,646 562,847 1,474,709 898,063 On Target On Target
Overspend due to pumping station, water supply infrastructure works and additional road construction works
Kings Arms (113-115 High Street) 2,982,159 1,653,504 2,982,159 0 490,299 138,210 568,041 77,742 On Target Significantly off target
Montgomerie Park (Both Phases) 49,739,946 5,320,089 49,739,946 0 10,528,206 119,575 2,978,340 (7,549,866) On Target Slightly off target  Delay in issuing tender due to ongoing discussions ongoing the delivery of the road and
pumping station
St Michaels Phase 3 13,996,769 28,710 13,996,769 28,710 50,000 50,000
Nelson Street Regeneration 1,079,858 10,420 1,079,858 0 857,456 6,694 887,806 30,350 On Target On Target Confirmation of SG funding delayed acceptance of the tender
Acquisition Houses-Open Market 1,273,080 462,096 1,273,080 0 1,341,270 134,827 1,341,270 0 On Target On Target
Harbour Street 0 0 0 0 0 On Target On Target
Grange Court, Stevenston 1,532,642 29,337 1,532,642 628,184 8,455 50,000 (578,184) On Target On Target Ownership of boundary to be clarified
Future Years Projects 0 0
Nursery Place 0 0 0
Guthrie Road 1,859,200 0 1,859,200 0 10,000 10,000
Redburn 4,436,146 0 4,436,146 0 50,000 50,000
Corsehillhead (Shadow Programme) 350,686 0 2,815,278 2,464,592 0 0 50,000 50,000 On Target On Target Project in SHIP 2026-2031 Shadow Programme
James Reid Site (Shadow Programme) 11,820,675 19,957 11,820,675 0 0 2,931 50,000 50,000 On Target On Target Project in SHIP 2026-2031 Shadow Programme
Internal Management Charges 1,489,046 1 1,489,046 0 1,630,441 0 1,630,441 On Target On Target
Regeneration Project 1e Consultants Fees 1,775,219 31,849 1,775,219 729,258 6,200 562,009 (167,249)
Contingency 4,012,524 0 2,988,321 2,816,575 0 1,868,512 (948,063)
House Building - General 3,210 0
SUB TOTAL 259,021,955 94,385,301 274,628,520 16,630,769 35,543,861 4,087,408 27,230,838 0 (8,498,798) 185,775
DELIVERY STATUS
# OFFICIAL-PROTECT INFORMATION

Page 25

OFFICIAL-PROTECT INFORMATION#
TOTAL PROJECT CURRENT YEAR 2026/27 - Period 2
Project Description Total Project
Budget           
Cumulative
Expenditure to
date
Total Project
Forecast                 
Projected Over/
(Under) Spend               
Total Revised
Budget 2026/27
Actual Expenditure to 31
May 2026 P2 Projection Virement
Request
Carry /Brought
Forward to
/From Future
Years
True Over/
(Under) Spend
Delivery Status
Financial Delivery Status Physical Narrative
£ £ £ £
DELIVERY STATUS
Improvements to existing stock
Wet Room - Void 374,000 67,156 373,844 (156) 374,000 67,156 373,844 (156) On Target On Target
Bathrooms - Void 493,000 45,812 492,930 (70) 493,000 45,812 492,930 (70) On Target On Target
Wet Room - Planned 102,000 0 101,957 (43) 102,000 0 101,957 (43) On Target On Target
Bathrooms - Planned 374,505 0 284,017 (90,488) 374,505 0 284,017 (90,488) On Target On Target
Secondary bathrooms planned 0 0 0 0 0 0 0
Electrical Rewiring 687,988 52,330 687,988 0 687,988 52,330 687,988 On Target On Target Full budget spend projected
Heating 2,573,780 360,949 2,573,780 0 2,573,780 360,949 2,573,780 On Target On Target Full budget spend projected
Kitchens 2,114,658 359,805 2,013,985 (100,673) 2,114,658 359,805 2,013,985 (100,673) On Target On Target
Kitchens - Void 1,123,080 126,036 1,123,080 0 1,123,080 126,036 1,123,080 On Target On Target
Roofing 1,362,876 54,332 1,324,000 (38,876) 1,362,876 54,332 1,324,000 (38,876) On Target On Target underspend due to reduction in costs
Wallfloor rendering 2,500,362 32,899 2,170,500 (329,862) 2,500,362 32,899 2,170,500 (329,862) On Target On Target Cosr per unit reductions.
EWI 763,752 36,951 763,752 0 763,752 36,951 763,752 On Target On Target
Window Replacement 850,052 51,729 755,802 (94,250) 850,052 51,729 755,802 (94,250) On Target On Target
Saltcoats MSF Investment 186,821 29,537 186,821 0 186,821 29,537 186,821 On Target On Target Remedial work ongoing
Smoke Detector Programme 1,091,337 77,745 1,059,035 (32,302) 1,091,337 77,745 1,059,035 (32,302) On Target On Target
Energy Efficiency 2,180,905 0 2,180,905 0 2,180,905 0 2,180,905 On Target On Target may be a future carry forward beyond 2627. Still awaiting updated guidance from
Scottish Govt re SHNZS
Path Finder Project 459,856 0 459,856 0 459,856 0 459,856 On Target On Target
Solar Panels 3,112,160 36,087 3,112,160 0 3,112,160 36,087 3,112,160 0 On Target On Target
Redburn Grove 0 9,149 50,000 9,149 50,000 50,000
HRA Slippage (1,073,280) 0 (1,073,280) 0 (1,073,280) 0 (1,073,280)
SUB TOTAL 20,351,132 1,331,367 19,664,412 (686,720) 19,277,852 1,340,516 18,641,132 0 (267,756) (368,964)
0
Other Capital works 0
Estate Based Regeneration 1,309,165 186,576 1,309,165 0 1,309,165 186,576 1,309,165 0 On Target On Target
Lift Replacement 92,970 720 92,970 0 92,970 720 92,970 On Target On Target
Sheltered Housing Units 5,357,945 (45,816) 5,357,945 0 5,357,945 (45,816) 5,357,945 0 Slightly off target  On Target Vineburgh Court out to tender, Laigh Court on site
High Flats Demolition 0 0 0 0 0 On Target On Target Complete
Other Capital Works 0 0 0 0 0
SUB TOTAL 6,760,080 141,481 6,760,080 0 6,760,080 141,481 6,760,080 0 0 0
Total Expenditure 265,782,035 94,526,782 281,388,600 16,630,769 61,581,793 5,569,405 52,632,050 0 (8,766,554) (183,189)
Income
Affordable Housing Contributn (1,201,583) (1,201,583)
CFCR (5,580,084) (5,580,084)
Capital Grants (12,872,329) (1,459,186) (12,872,329)
Prudential Borrowing (40,347,569) (31,397,826) 8,766,554 183,189 Reduced borrowing required to reflect rephasing and projected underspends
Use of Reserves (1,580,228) (1,580,228)
Sale of Assets (12,597) Capital receipts.
Other Capital Income 95,500
SUB TOTAL
Total Project Expenditure 265,782,035 94,526,782 281,388,600 16,630,769 61,581,793 5,569,405 52,632,050 0 (8,766,554) (183,189)
Total Project Income (61,581,793) (1,376,283) (52,632,050) 0 8,766,554 183,189
# OFFICIAL-PROTECT INFORMATION

Page 26

Appendix 3
Treasury Management Performance to 30 June 2026    
Capital Expenditure for both the General Fund and HRA vary from original estimates
due to changes in the profile of projects. Full details of all movements in the capital
expenditure budgets are included in this report.  
The reduction to the Capital Financing Requirement for both the General Fund and
the HRA reflect the change in profile of the capital programme. 
Capital expenditure impacts on the revenue budget through financing charges so it is
essential the Council ensures the financing costs remain affordable and do not
constitute an excessive proportion of the revenue resources available.   From a
General Fund perspective, the latest Scottish Local Authority average was 6.0%,
thereby demonstrating a prudent borrowing policy.   For the HRA, the Scottish
average was 20.7%. The level of loan charges is deemed prudent and affordable
within the framework of the 30 year Housing business plan.  
2026/27 2026/27 2026/27
Original Estimate P3 Projection Movement
£m £m £m
General Services Capital expenditure                   142.123                    139.172                       (2.951)
Funded by:
Borrowing                   102.174                      93.819                       (8.355)
Receipts / Grants                     39.949                      44.998                        5.049
Funded from Revenue                            -                                -                                -   
Funded from Reserves                            -                           0.355                        0.355
Total                   142.123                    139.172                       (2.951)
HRA Capital expenditure                     70.103                      52.632                     (17.471)
Funded by:
Borrowing                     48.869                      31.398                     (17.471)
Receipts / Grants                     12.872                      12.872                             -   
Funded from Revenue                       5.580                        5.580                             -   
Funded from Reserves                       2.782                        2.782                             -   
Total                     70.103                      52.632                     (17.471)
Estimates of Capital Expenditure and Income
2026/27 2026/27 2026/27
Original Estimate P3 Projection Movement
£m £m £m
General Services                   544.217                    515.095                     (29.122)
HRA                   256.479                    227.339                     (29.140)
Sub-total                   800.696                    742.434                     (58.262)
Less PPP/NPD long-term liability                    (73.717)                    (73.717)                            -   
Loans Capital Financing Requirement (CFR)                   726.979                    668.717                     (58.262)
Capital Financing Requirement (CFR)
2026/27 2026/27
Original Estimate P3 Projection
% %
General Services 4.6% 3.8%
HRA 31.5% 25.2%
Proportion of financing costs to net revenue
stream

Page 27

The Council is currently projecting an under-borrowed position of £46.503m due to
the continuing strategy to delay long-term external borrowing by utilising internal
cash balances.
Liability Benchmark
The liability benchmark is an important tool to help establish whether the Council is
likely to be a long-term borrower or long-term investor in the future and so shape its
strategic focus and decision making.
The Liability benchmark graph above is used to inform the Council’s borrowing
strategy.  The shaded grey area shows the Councils current debt and the gap
between this and the Liability benchmark line is how much more borrowing the
Council likely needs to undertake to support its current capital plans once taking into
account its balance sheet resources including the net debtor / creditor and useable
reserves.  The above graph indicates that long term borrowing for the period of
around 20 years would be most appropriate to meet the Councils borrowing needs
and mitigate against interest rate risk.
2026/27 2026/27 2026/27
Original Estimate P3 Projection Movement
£m £m £m
Gross Debt at 31 March 683.675 622.214 (61.461)
CFR 726.979 668.717 (58.262)
(Under)/Over Borrowed Position (43.304) (46.503) (3.199)
Current Portfolio Position (excluding PPP/NPD)

Page 28

The maturity structure of the debt portfolio at 30 June 2026 is shown below and
shows the period when the Council is required to repay and/or refinance debt. It is
important to ensure a reasonable spread of debt to mitigate against high exposure
levels in respect of refinancing.  The current profile ensures this: 
The reduction in the external borrowing since 31 March relates to maturing loans
during the period to 30 June including £11.5m LOBO loans which were repaid in April
and May.  
2026/27 2026/27 2026/27
Original Estimate
£m P3 Projection Movement
£m
Loans CFR                   726.979                    668.717                     (58.262)
Less Balance sheet resources                    (95.242)                  (110.088)                    (14.846)
Net loans requirement                   631.737                    558.629                     (73.108)
Liquidity allowance                     10.000                      10.000                             -   
Liability Benchmark                   641.737                    568.629                     (73.108)
Liability Benchmark
31-Mar-26 30-Jun-26
Maturity Profile of Borrowing (Indicator 10) Actual Actual Movement
£m £m £m
Under 12 months                      25.996                      14.568                     (11.428)
12 months and within 24 months                     26.441                      35.857                        9.416
24 months and within 5 years                     54.321                      54.071                       (0.250)
5 years and within 10 years                   108.343                    108.343                             -   
10 years and within 20 years                     88.335                      88.335                             -   
20 years and within 30 years                     25.925                      25.925                             -   
30 years and within 40 years                     82.587                      82.587                             -   
40 years and within 50 years                            -                                -                                -   
50 years and above                     10.000                             -                        (10.000)
Total Borrowing                   421.948                    409.686                     (12.262)