Agenda Document Pack - Cabinet - 19/06/2026

North Ayrshire Council · 19 June 2026
Back to Cabinet — 19 June 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Cabinet
A Special Meeting of the Cabinet of North Ayrshire Council will be held in the Council
Chambers, Ground Floor, Cunninghame House, Irvine, KA12 8EE on Friday, 19
June 2026 at 15:00 to consider the undernoted business.
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.   Where possible, the meeting will be live-streamed
and available to view at  https://north-ayrshire.public-
i.tv/core/portal/home. 
1 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda.
2 Revenue Budget 2025/26: Financial Performance to 31 March 2026
Submit report by the Head of Democratic Services  informing Cabinet of
the decision of the Audit & Scrutiny Committee following a call-in of the
Cabinet decision on 2 June 2026 to support the recommendations set out
in the report by the Head of Finance, subject to the amendment below:
“Approve subject to the movement of £1.496m of underspend to the
26/27 revenue budget. These funds to be used to create an Our Places,
Our Communities fund designed to benefit all North Ayrshire
communities. The administration will bring details of this fund to council
on the 24th of June for debate and approval.” (copy enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
3 Ardrossan Campus Project Update
Submit report by the Head of Democratic Services  informing Cabinet of
the decision of the Audit & Scrutiny Committee following a call-in of the
Cabinet decision of 2 June 2026 which noted  the current progress of the
Ardrossan Campus project, including current projections in relation to
costs and programme (copy enclosed).
Webcasting
Please note: this meeting may be filmed/recorded/live-streamed to the
Council's internet site and available to view at  https://north-ayrshire.public-
i.tv/core/portal/home,where it will be capable of repeated viewing.  At the
start of the meeting, the Provost/Chair will confirm if all or part of the
meeting is being filmed/recorded/live-streamed.
You should be aware that the Council is a Data Controller under the Data
Protection Act 2018.  Data collected during the webcast will be retained in
accordance with the Council’s published policy, including, but not limited
to, for the purpose of keeping historical records and making those records
available via the Council’s internet site.
Generally, the press and public will not be filmed. However, by entering the
Council Chambers and using the press or public seating area, you
acknowledge that you may be filmed and that any information pertaining to
you contained in the video and oral recording of the meeting will be used
for webcasting or training purposes and for the purpose of keeping
historical records and making those records available to the public. In
making this use of your information the Council is processing data which is
necessary for the performance of a task carried out in the public interest.
If you have any queries regarding this and, in particular, if you believe
that use and/or storage of any particular information would cause, or be
likely to cause, substantial damage or distress to any individual, please
contact  dataprotectionofficer@north-ayrshire.gov.uk
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE
Cabinet Sederunt
Tony Gurney (Chair)
Christina Larsen (Vice-Chair)
Eleanor Collier
Alan Hill
Margaret Johnson
Chloe Robertson
Chair:
Apologies:
Attending:
3

Page 4

4

Page 5

NORTH AYRSHIRE COUNCIL 
19 June 2026 
Cabinet 
Title:    Revenue Budget 2025/26: Financial Performance to 31 March
2026 
Purpose:  To inform Cabinet of the decision of the Audit & Scrutiny
Committee following a call-in of the Cabinet decision of 2 June
2026 to support the recommendations set out in the report by
the Head of Finance, subject to the amendment below: 
“Approve subject to the movement of £1.496m of underspend to
the 26/27 revenue budget. These funds to be used to create an
Our Places, Our Communities fund designed to benefit all North
Ayrshire communities. The administration will bring details of this
fund to council on the 24th of June for debate and approval.” 
Recommendation:  That Cabinet considers the decision and recommendation from
the Audit & Scrutiny Committee and determines: 
(a) whether to accept the recommendation of the Audit &
Scrutiny Committee and refer the matter to Council on that
basis; or 
(b) if it does not accept the recommendation, to refer the matter
to Council for final determination. 
1. Executive Summary 
1.1 At its meeting on 2 June 2026, Cabinet decided to support the recommendations set
out in the report by the Head of Finance, subject to the amendment below: 
“Approve subject to the movement of £1.496m of underspend to the 26/27 revenue
budget. These funds to be used to create an Our Places, Our Communities fund
designed to benefit all North Ayrshire communities. The administration will bring
details of this fund to council on the 24th of June for debate and approval.” 
1.2 Subsequent to the decision taken by Cabinet, a call-in request was received from
Councillors Cullinane, Foster and Montgomerie which was referred to the Audit &
Scrutiny Committee for consideration. 
1.3 At its meeting on 15 June 2026, the Audit and Scrutiny Committee agreed to accept
the call-in request and referred the matter back to Cabinet for further consideration
with the recommendation that the matter is referred to full Council to determine the
Agenda Item 2
5

Page 6

use of the underspend and that Council suspends standing orders to consider the
proposal regarding a Council Tax rebate. 
1.4 Accordingly, Cabinet is asked to consider the decision and recommendation from the
Audit & Scrutiny Committee and determine: 
a) whether to accept the recommendation of the Audit & Scrutiny Committee and refer
the matter to Council on that basis; or 
b) if it does not accept the recommendation, to refer the matter to Council for final
determination. 
2. Background 
2.1 The Cabinet, at its meeting on 2 June 2026, considered a report on the financial
performance for Council 2025/26. A copy of the original report presented to Cabinet
on 2 June 2026 is attached as Appendix 1. 
2.2 Subsequently, a call-in request was received in terms of the call-in procedure set out
in the Council’s Standing Orders. The report to the Audit & Scrutiny Committee and
briefing note provided by the Head of Finance in relation to the call-in are attached at
Appendix 2. 
2.3 The Audit & Scrutiny Committee at its meeting on 15 June 2026 heard from Councillor
Cullinane in relation to the call-in. The Committee also heard from Councillor Larsen,
Depute Leader and Cabinet Member for Finance, in response to the call-in. The Head
of Service (Finance) was also present to provide information on the Cabinet report and
on issues raised by the call-in received. The Committee subsequently agreed to
accept the call-in and referred the matter back to Cabinet for further consideration with
the recommendation that the use of the underspend be referred to full Councill for
determination and that Council suspends standing orders to consider the proposal
regarding a Council Tax rebate. The Minutes of the meeting of the Audit & Scrutiny
Committee are attached at Appendix 3. 
3. Proposals 
3.1 Cabinet is recommended to consider the decision and recommendation from the Audit
& Scrutiny Committee and determine: 
a) whether to accept the recommendation of the Audit & Scrutiny Committee and 
refer the matter to Council on that basis; or 
b) if it does not accept the recommendation, to refer the matter to Council for final
determination. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the Cabinet report attached at Appendix 1. 
6

Page 7

Human Resources 
4.2 The human resource implications are outlined in the Cabinet report attached at
Appendix 1. 
Legal 
4.3 The legal implications are outlined in the Cabinet report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the Cabinet report attached
at Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the Cabinet report
attached at Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the Cabinet report attached at Appendix 1. 
Community Wealth Building 
4.7 The community wealth building implications are outlined in the Cabinet report attached
at Appendix 1. 
Islands Communities Impact Assessment (ICIA) 
4.8 Any ICIA implications are outlined in the Cabinet report attached at Appendix 1. 
United Nations Rights of the Child (UNCRC) 
4.9 Any UNCRC implications are outlined in the Cabinet report attached at Appendix 1. 
Consumer Duty 
4.10 Any consumer duty implications are outlined in the Cabinet report attached at
Appendix 1. 
5. Consultation 
5.1 None concerning this report. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Craig Stewart, Committee Services Officer, on 
01294 324130 or by email, craigstewart@north-ayrshire.gov.uk 
Background Papers
7

Page 8

N/A
8

Page 9

NORTH AYRSHIRE COUNCIL
2 June 2026                                                                                  
Cabinet
Title: Revenue Budget 2025/26 : Financial Performance to 31
March 2026
Purpose: To advise Cabinet of the financial performance for the Council
for 2025/26.
Recommendation: That Cabinet agrees to:
(a) note the information and financial outturn position outlined
in the report;
(b) approve the earmarking of £7.691m identified at 2.4 to
meet future year commitments in accordance with funding
requirements;
(c) note the financial performance for the Health and Social
Care Partnership highlighted at 2.5; and
(d) approve the virements detailed in Appendix 8.
1. Executive Summary
1.1 The General Services Revenue Estimates for 2025/26 were approved by Council on
26 February 2025. The Housing Revenue Account (HRA) Revenue Budget for
2025/26 was approved by Council on 12 February 2025.
1.2  As part of the monitoring procedures to keep the Cabinet informed of the financial
performance of the Council, financial performance reports are presented on a regular
basis. This is the fourth report for 2025/26 and covers the period to the end of March
2026 (Period 12). Projections have been made to the year-end. This is the final
financial performance information on which the annual accounts for the Council will be
prepared.
1.3  At Period 12 the General Fund is reporting a net in-year underspend of (£2.014m),
(0.4%), after transferring resources to/from earmarked reserves This is an
improvement of (£0.334m) from that reported at Period 10 and is primarily related to
additional income, lower than anticipated employee costs within the Facilities
Management and Streetscene linked to staff turnover levels and lower than
anticipated utilisation of inflationary related provisions during the year. In recognising
that there continues to be volatility across certain areas of spend, linked to current
global events, this improved position has been partially offset by additional requests
for earmarking to meet anticipated cost pressures in 2026/27. The underspend will be
added to the General Fund Unearmarked Reserves which would increase the
APPENDIX 1
9

Page 10

available balance to 2.3% the revised General Services Revenue Budget which is
within the recommended range of 2 – 4%.  From the underspend, a total of £0.518m
is required to ensure unearmarked reserves are retained at a minimum level of 2%
within this range. Whilst the current level of unearmarked reserves remains at the
lower end of good practice, this still reflects a prudent position to help address areas
of significant risk to the Council through 2026/27, most notably through the financial
performance of the HSCP.
1.4  The Housing Revenue Account is reporting a net in-year underspend of (£3.943m),
(6.0%). This is a movement of (£1.617m) from the previously reported underspend at
Period 10. The movement is primarily related to reduced expenditure on property
costs and increased income. The underspend will be added to the HRA earmarked
balances to support service delivery in future years.
1.5  Work is ongoing to confirm the final Health and Social Care Partnership out-turn
position for the year, and the final confirmation of the NHS budget outturn is awaited.
The final outturn for the Council services element has been confirmed as an
underspend of £1.818m.  From this, £1.359m will be earmarked to meet future costs.
This leaves a £0.459m surplus to be added to the HSCP’s unearmarked reserves
bringing the reported position to a net break-even position. This is an improvement
of £1.941m from the previously reported Council services position.  A further report
will follow from the HSCP in the new year.
1.6 Management action is ongoing to address absence levels across services. However,
employee absence rates remain above targets, and there has been a marginal 0.9%
increase in days lost during the period when compared to the same period last year.
2. Background
General Fund
2.1   The Council set a balanced budget for 2025/26. In addition to the budget approved on
26 February 2025, earmarked funds of £85.088m were carried forward from 2024/25
for service expenditure in 2025/26 and beyond. These funds are reflected in the
figures within the 2025/26 financial performance reports as they are drawn down.
2.2 A net in-year underspend of £2.014m is reported, net of transfers to/from reserves.
The undernoted table details the final position on a service-by-service basis.
Service Expenditure
App
No.
Annual
Budget
£ million
Actual
Expenditure
to 31 March
2026
£ million
Variance
for year
(Fav)/Adv
£ million
Requests
for Carry
Forwards
£ million
Variance
after
Carry
Forward
(Fav)/Adv
£ million Note
Corporate Services 1 22.748 21.767 (0.981) 0.186 (0.795) (i)
Education 2 191.980 192.050 0.070 (0.193) (0.123) (ii)
Place 3 60.889 58.371 (2.518) 3.363 0.845 (iii)
Communities &
Housing 4 17.116 16.344 (0.772) 0.233 (0.539) (iv)
Other Corporate Items 5 15.971 10.781 (5.190) 3.357 (1.833) (v)
Sub Total 308.704 299.313 (9.391) 6.946 (2.445)
10

Page 11

Health and Social
Care Partnership 9 142.676 140.858 (1.818) 1.818 0.000
Balance for Services 451.380 440.171 (11.209) 8.764 (2.445)
Financing Charges 6 13.751 13.751 0.000 0.000 0.000
Contribution to Loans
Fund Reserve 6 10.187 10.187 0.000 1.500 1.500 (vi)
Total Planned
Expenditure 475.318 464.109 (11.209) 10.264 (0.945)
Aggregate External
Finance 6 (394.613) (394.637) (0.024) 0.000 (0.024)
Council Tax 6 (71.939) (72.984) (1.045) 0.000 (1.045) (vii)
Use of Earmarked
Funds 6 (8.766) (8.766) 0.000 0.000 0.000
Total Planned
Income (475.318) (476.387) (1.069) 0.000 (1.069)
Net Expenditure/
(Income) 0.000 (12.278) (12.278) 10.264 (2.014)
2.3 The reported Aggregate External Finance within Planned Income includes several
adjustments to Scottish Government funding from that reported at Period 10, as
detailed in the following table:
Movements on Planned Income
General
Revenue
Grant
£ million
Non
Domestic
Rates
£ million
Specific
Grants
£ million
TOTAL
AEF
£ million
Revised Budget at P10 (342.866) (42.606) (8.101) (393.573)
Pupil Equity Fund C/F 0.655 0.655
Discretionary Housing Payment
Undistributed (0.781) (0.781)
Teacher Pay Award (0.756) (0.756)
CSC Pay Uplift Adjustment 0.083 0.083
Revised Planned Income (344.320) (42.606) (7.446) (394.372)
2.4 Commentary on Significant Movements from Period 10
The Council's overall financial forecast against the revised budget is an improvement
of (£0.334m) from the previously reported position. A brief explanation of the
significant movements at a service level are outlined as follows:
(i) Corporate Services – underspend of (£0.795m), an improvement of
(£0.200m) from the previously reported underspend
The movement is primarily related to:
• Vacancy management across the services;
• Revisions to Statutory additions (£0.070m);
• Lower than anticipated ICT contract costs in-year (£0.067m).; and
• Underspend in Election costs (£0.081m)
11

Page 12

This has been offset by a request to Earmark £0.283m in relation to anticipated
ICT contract inflation in 26/27 (£0.138m), resources to support the outcome of a
Service review (£0.060m) and the carry forward of Election resources to support
the democratic process (£0.085m).
(ii) Education – underspend of £0.123m, a favourable movement of (£0.724m)
from the previously reported position
The movements are primarily related to:
• Increase in the underspend within Facilities management of £0.679m primarily
relating to vacancy management and reduced expenditure across supplies and
services.
• Reduction in the overspend within ASN of £0.402m as a result of reduced day
placement costs and a reduction in external residential placement numbers and
associated costs, through the work of the Brighter Pathways programme.
This has been offset by increased teacher costs across Primary and Secondary
Schools.
It is requested that £0.010m is earmarked to meet costs in relation to Furniture and
updated equipment for the Visual Impairment team in ASN.
(iii) Place – overspend of £0.845m, an increase of £0.434m from the previously
reported overspend
The movement is primarily related to:
• Funds received from the Extended Producer Responsibility Payment
(£1.087m) in accordance with the payment schedule.
• Increased underspend within Transport of £0.310m due to reduced
expenditure on repairs and maintenance, fuel and additional income.
• A favourable movement within Streetscene of £0.196m largely due to a
reduction in staff costs and increased income
• An over-recovery of Largs car park income as a result of the new pricing
structure.
This is offset by requests to earmark £1.939m, further to the £1.424m previously
approved, to support anticipated additional expenditure during 2026/27 in relation
to:
• Waste pressures and investments in accordance with Extended Producer
Responsibility funding requirements, £0.950m
• Programme of Fire risk Assessments and essential works, £0.400m
• Programme of Water Quality Assessments and essential works, £0.100m
• Largs Car Park income to be retained in Largs Car Park Fund, £0.104m
• Anticipated Fuel cost pressures in view of current global events, £0.274m
• Investment in Car parking infrastructure, £0.076m
• Provision for the Making Waves Festival, £0.035m
12

Page 13

Virements in relation to the realignment of budgets within Roads and
Employability have been included within Appendix 8.
(iv) Communities and Housing – underspend of £0.539m, an improvement of
(£0.139m) from the previously reported underspend
The movement is primarily related to:
• Increase in the underspend within Housing of £0.197m largely relating to
reduced Bad debt provision and write off costs.
• Reduced expenditure within connected communities of £0.261m relating to
lower than anticipated storm damage costs and service management of
budget lines to offset the impact of delay in implementing previously approved
libraries savings.
• Additional income within protective services of £0.255m
• Reduced expenditure on employee costs due to ongoing service redesign of
£0.094m
• An underspend due to the reprofiling of the local development plan into 2026-
27
• A surplus of £0.057m within Building services.
This has been partially offset by :
• An overspend of £0.314m in relation to demolition costs as a result of
significant fire damage at the Forum Centre Irvine.
• Requests to earmark £0.463m to support anticipated additional expenditure
during 2026/27 in relation to:
 Further anticipated costs in relation to the demolition of the Forum
centre following the major fire damage, £0.400m
 Local Development Plan, £0.043m
 Holiday Playschemes and Activities budget as part of a delivery
programme of activities in Summer 2026, £0.020m
(v) Other Corporate Items – underspend of £1.833m, an increase of (£0.757m)
from the previously reported underspend
The movement is primarily related to:
• Centrally held provisions not drawndown during the year, including pay
inflation, energy sustainability funding and energy cost provisions which have
been subject to ongoing volatility, even after allowing for a proportion of
advanced purchasing arrangements, (£2.041m)
• Workforce Planning cost provisions not required in year including Severance
costs and Equal pay £1.257m
• Funding to support ongoing Transformation activity secured as part of the
2025/26 Budget, not utilised in year £0.750m
This is offset by :
13

Page 14

• An overspend on insurance reflecting high level of excesses largely relating to
storm damage. £1.106m
• Requests to earmark £3.496m to support anticipated additional expenditure
during 2026/27 in relation to:
o Equal Pay Provision required to help address future risks, £0.494m
o Workforce Planning and Transformation resources required to
support ongoing programme £1.732m
o Property – Energy sustainability funding to address current volatility,
£0.500m
o DWP Housing Benefit Accuracy award, £0.018m
o Rapid Rehousing Transition Plan rolling programme £0.024m
o SG Resettlement programme funding £0.095m
o SG Nature Restoration funding £0.073m
o SG Island support funding £0.288m
o On-going Service re-design costs £0.031m
o SG NDR Empty Property Relief funding £0.241m
(vi) Contribution to Loans Fund Reserve – Overspend of £1.500m, an increase of
£1.500m from the previously reported position
In view of the current conflict in the middle east and the anticipated inflationary
impacts, the Bank of England forecast for interest rates now reflects an increase
from the current base rate of 3.75% up to 5.25% potentially during 2026/27. In
order to address the impact this will have on borrowing costs through 2026/27, it
is requested that £1.500m is earmarked and transferred to the Loans Fund
reserve.
(vii)Council Tax – over-recovery of (£1.045m), an increase of £0.448m from the
previously reported over-recovery
The movement reflects growth in the Council Tax base from additional new builds,
properties previously registered as self-catering holiday units for NDR purposes
that have come onto the Council tax register, and the impact of the application of
100% premium on Council tax for second homes when measured against the
original financial planning assumptions.
Health and Social Care Partnership
2.5 The final HSCP financial performance report for the year will be presented to the
Integration Joint Board on 18 June 2026 and will outline the 2025/26 financial
performance in more detail. Work is ongoing to confirm the final outturn position for
the year and the HSCP is awaiting final confirmation of the NHS budget outturn. The
final outturn for the Council services element has been confirmed as an underspend
of £1.818m.  £1.359m is to be earmarked to meet costs in relation to ADP, Whole
Family Wellbeing Fund, Community alarms, Magic Notes and Adult Social work
Restructure costs. This leaves a £0.459m surplus which is to be added to the
HSCP’s unearmarked reserves bringing the reported position to a net break-even
position.  This is an improvement of £1.941m from the previously reported Council
services position. A further report will follow from the HSCP in the new year.
14

Page 15

Absence Management 
2.6 The programme of work to monitor absence levels and effectively implement relevant
policies has been ongoing and initially resulted in a significant reduction in reported
absence levels across the Council. However, the year-end position shows a marginal
increase in days lost during 2025/26 when compared to 2024/25 i.e. 12.87 days lost
compared to 12.76 in 2024/25. The absence levels for the year exceed the target of
10.22 days. Within the Education Service, the number of days lost for teaching staff
has reduced by almost 8% when compared to the previous year (5.78 days compared
to 6.25 last year). The HSCP and the Communities and Housing directorate’s number
of days lost have increased by 20% and 4% respectively, with the Place directorate
showing a 14% improvement for the period. 
Risks 
2.7 Due to the anticipated outturn position of the HSCP in 2025/26, from the Council
services element, the level of HSCP unearmarked reserves will increase by £0.459m.
Moving forward into 2026/27, under the terms of the Health and Social Care
Integration Scheme, a recovery plan is required in order to address any projected
shortfalls in future years. There is a risk that, if the recovery plan is not successful, this
would have an impact on the level of financial contributions from the funding parties.
In such a circumstance the Council would be asked to make interim funds available.
The funding could be made available for repayment by the HSCP across a period of
future years or as an additional contribution. This HSCP position will continue to be
monitored through 2026/27, however, in view of the level of pressures faced by the
HSCP and the scale of savings required in 2026/27 to operate within available
resources, there is a risk that spend will exceed available resources. It is recognised
the Council’s underspend position 2025/26 will help provide a level of financial
mitigation to this risk. The other main risks are linked to current global events and the
potential impacts on inflation and interest rates through 2026/27. Again, to address
these, further mitigations through the earmarking of financial resources have been
included in the year end position. 
Housing Revenue Account 
2.8  The Housing Revenue Account budgeted for a breakeven position in 2025/26.  An
underspend of (£3.942m), net of transfers to/from reserves, has been reported. This is
an improvement of (£1.617m) from the previously reported position and is
summarised in the following table with further details provided in Appendix 7. The
underspend will be added to the HRA earmarked balances to support delivery of the
HRA Business Plan. 
15

Page 16

2.9 Commentary on Significant Movements from Period 10 
A brief explanation of the significant movements from the previous forecasts is
outlined as follows: 
(i) Property Costs – underspend of £1.092m, a favourable movement of 
(£1.250m) from the previously reported position
The movement is primarily related to reduced expenditure on Aids and
Adaptation, (£0.191m), Void Repairs (£0.276m), Planned and Cyclical
Maintenance (£0.466m) and Other Property Costs (£0.293m). 
(ii) Administration Costs – underspend of £0.212m, a movement of (£0.208m)
from the previously reported position 
The movement is primarily related to reduced expenditure on legal fees
(£0.103m), Central Recharges (£0.053m) and Insurances (£0.025m) 
(iii) Third Party Payments – underspend of £0.061m, a favourable movement of
(£0.122m) from the previously reported position
The movement is primarily related to reduced recharges from other Council
departments. 
(iv) Transfer payments – underspend of £0.053m, a movement of (£0.053m) from
the previously reported position
The movement is due to an underspend in disturbance allowances. 
(v) Other Expenditure – overspend of £0.398m, a movement of £0.398m from
the previously reported position
Housing Revenue
Account
Annual
Budget
£ million
Actual
Expenditure
to  31 March
2026
£ million
Variance for
year
(Fav)/Adv
£ million
Projected
Variance at
P10 
(Fav)/Adv
£ million Movement Note
Employee Costs 5.294 5.294 0.000 0.002 (0.002)
Property Costs 25.628 24.536 (1.092) 0.158 (1.250) (i)
Supplies and Services 2.145 2.130 (0.015) (0.006) (0.009) (ii)
Transport and Plant Costs 0.016 0.015 (0.001) 0.000 (0.001)
Administration Costs 2.114 1.902 (0.212) (0.004) (0.208) (iii)
Third Party Payments 3.832 3.771 (0.061) 0.061 (0.122) (iv)
Transfer Payments 0.177 0.124 (0.053) 0.000 (0.053)
Other Expenditure 0.550 0.948 0.398 0.000 0.398 (v)
Capital Financing 26.270 23.834 (2.436) (2.372) (0.064) (vi)
Gross Expenditure 66.026 62.554 (3.472) (2.161) (1.311)
Income (66.026) (66.496) (0.470) (0.164) (0.306) (vii)
Net Expenditure 0.000 (3.942) (3.942) (2.325) (1.617)
16

Page 17

The movement is due to an increase in the bad debt provision. 
(vi) Capital Financing Costs – underspend of £2.436m, a movement of (£0.064m)
from the previously reported position 
The movement is primarily related to revised loan charges reflecting the revised
profile of capital project delivery, leading to a lower level of in-year borrowing.
These funds will be required to support the HRA capital programme in future
years. 
(vii) Income – over recovery of £0.470m, a movement of (£0.306m) from the
previously reported position 
The movement is primarily related to an over-recovery in Council House rents
(£0.147m) and other income (£0.157m). 
3. Proposals 
3.1 It is proposed that Cabinet agrees to: 
(a) note the information and financial outturn position outlined in the report; 
(b) approve the earmarking of £7.691m identified at 2.4 to meet future year
commitments in accordance with funding requirements;
(c) note the financial performance for the Health and Social Care Partnership
highlighted at 2.5; and
(d) approve the virements detailed in Appendix 8. 
4. Implications/Socio-economic Duty 
Financial 
4.1 General Services
The final outturn position for the year is a net underspend of (£2.014m) after transfers
to and from earmarked reserves. 
Housing Revenue Account
The final outturn position for the year is a net underspend of (£3.942m). 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None.
17

Page 18

Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Mark Boyd, Head of Service (Finance), on 01294
324560. 
Background Papers
Revenue Budget 2025/26: Financial Performance to 31 January 2026 – Cabinet 17 March
2026
18

Page 19

NORTH AYRSHIRE COUNCIL
15 June 2026                                                                                                                                                            
Audit and Scrutiny Committee
Title: Call In: Revenue Budget 2025/26: Financial Performance to
31 March 2026
Purpose: To allow the Committee to consider a call-in request in respect
of the decision taken by Cabinet at its meeting on Tuesday 2
June 2026 advising of the financial performance for the Council
for 2025/26.
Recommendation: That the Committee considers the terms of the call-in and agrees,
or otherwise, to make a recommendation to Cabinet.
1. Executive Summary
1.1   In terms of the Scheme of Administration (Section 5), the Audit and Scrutiny Committee
has a remit to consider call-in requests and invite at least one of the Members who has
requested the reference to call-in to attend the Committee to explain the request.
1.2 This report sets out the background to a call-in request in respect of the decision
taken by Cabinet at its meeting on 2 June 2026 in relation to the report on the
financial performance for the Council 2025/26.
2. Background
2.1 The Cabinet, at its meeting on 2 June 2026, considered a report on the financial
performance for Council 2025/26. Cabinet amended the recommendation to the report
by determining to allocate £1.496m of underspend to the 26/27 revenue budget with
the funds to be used to create an Our Places, Our Communities fund designed to
benefit all North Ayrshire communities with details of the fund being brought to council
on the 24th of June for debate and approval.
2.2 A request was received in terms of the call-in procedure set out in the Council's
Scheme of Administration and Standing Orders, that the Audit and Scrutiny
Committee examine the decision taken by the Cabinet.
2.3 The call-in request, which was signed by Councillors Cullinane, Foster and
Montgomerie is in the following terms: -
Reason for call-in
“In passing its budget, the Council set Council Tax bands at a level required to fund its
APPENDIX 2
19

Page 20

expenditure requirements, including prioritising investment in areas such as education
and roads. 
The £1.496million underspend should therefore not be spent on another of the
administrations pet projects, particularly when the evidence of the last four years
shows that these pots of money are not used in a timeous manner. 
Instead, the underspend should be returned to council taxpayers.” 
Desired Outcome 
“That the £1.496million allocated to an ‘Our Places, Our Communities fund’ be re-
allocated to provide a Council Tax rebate, reflecting the fact that our expenditure
requirements for 2026/27 have already been funded. 
Although this outcome proposes a Council Tax rebate, we acknowledge officers'
advice that as matters relating to setting Council Tax levels are reserved to Council
and that for this outcome to be implemented it will require a decision of Full Council,
including the suspension of 15.5 and 25.1 of Standing Orders Relating to Meetings
and Proceedings of the Council, as Council Tax was set within the last six months.
The Audit & Scrutiny Committee is asked to accept the call in and recommend that the
matter is referred by Cabinet to Council for further consideration and determination.” 
2.4 A copy of the original report presented to Cabinet on 2 June 2026 and the relevant
extract of the minute are attached as Appendix 1 to this report. A briefing note has
been provided by the Head of Service (Finance) and is attached at Appendix 2. 
2.5 The call-in request is valid for consideration by the Committee. The request was
received within the appropriate timescale, it was requested by three Elected Members
and details were provided on both the reason for the call-in and the desired outcome. 
2.6 The Elected Members who have submitted the call-in will be invited to address the
Committee to explain the respective call-in request.  The appropriate Cabinet Member
will then be invited to clarify the reasons for the decision. The relevant senior officer
will also be present to provide information on the report presented to Cabinet and on
issues raised by the call-in received. The Committee will have an opportunity to ask
questions of both parties and of those officers in attendance. 
2.7 The Committee will then debate the call-in request and decide whether or not it agrees
with the decision of the Cabinet. 
2.8    The Audit and Scrutiny Committee:- 
i) decides if it agrees or not with the decision of the Cabinet; and
ii) if it does not agree with the decision, considers what alternative action the
Committee would recommend to the Cabinet. 
2.9   If the Committee supports the decision of Cabinet and does not accept the call-in, the
original decision of Cabinet remains in effect, and no further procedure is required. 
20

Page 21

2.10 If the Committee accepts the call-in, the matter is referred to Cabinet with a
recommendation. When the matter is considered by the Cabinet, the Chairperson or
another member of the Audit and Scrutiny Committee will have the right to attend the
Cabinet and speak in support of any recommendation. 
2.11 In the event that Cabinet declines to accept the recommendation from the Audit and
Scrutiny Committee, the matter will be referred to Council for determination. The
decision of the Council will be final. 
3. Proposals 
3.1 It is proposed that the Committee considers the call-in request. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the Revenue Budget 2025/26: Financial
Performance to 31 March 2026 report attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the Revenue Budget 2025/26:
Financial Performance to 31 March 2026 report attached at Appendix 1. 
Legal 
4.3 The legal implications are outlined in the Revenue Budget 2025/26: Financial
Performance to 31 March 2026 report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the Revenue Budget
2025/26: Financial Performance to 31 March 2026 report attached at Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the Revenue Budget
2025/26: Financial Performance to 31 March 2026 report attached at Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the Revenue Budget 2025/26: Financial Performance
to 31 March 2026 report attached at Appendix 1. 
Community Wealth Building 
4.7 Any community wealth building implications are outlined in the Revenue Budget
2025/26: Financial Performance to 31 March 2026 report attached at Appendix 1. 
21

Page 22

Islands Communities Impact Assessment (ICIA) 
4.8 Any ICIA implications are outlined in the Revenue Budget 2025/26: Financial
Performance to 31 March 2026 report attached at Appendix 1. 
United Nations Rights of the Child (UNCRC) 
4.9 Any UNCRC implications are outlined in the Revenue Budget 2025/26: Financial
Performance to 31 March 2026 report attached at Appendix 1. 
Consumer Duty 
4.10 Any consumer duty implications are outlined in the Revenue Budget 2025/26:
Financial Performance to 31 March 2026 report attached at Appendix 1. 
5. Consultation 
5.1 None concerning this report. 
Craig Hatton
Chief Executive 
For further information please contact Shannon Wilson, Committee Services Officer, on
shannonwilson@north-ayrshire.gov.uk. 
Background Papers 
N/A
22

Page 23

NORTH AYRSHIRE COUNCIL
2 June 2026                                                                                  
Cabinet
Title: Revenue Budget 2025/26 : Financial Performance to 31
March 2026
Purpose: To advise Cabinet of the financial performance for the Council
for 2025/26.
Recommendation: That Cabinet agrees to:
(a) note the information and financial outturn position outlined
in the report;
(b) approve the earmarking of £7.691m identified at 2.4 to
meet future year commitments in accordance with funding
requirements;
(c) note the financial performance for the Health and Social
Care Partnership highlighted at 2.5; and
(d) approve the virements detailed in Appendix 8.
1. Executive Summary
1.1 The General Services Revenue Estimates for 2025/26 were approved by Council on
26 February 2025. The Housing Revenue Account (HRA) Revenue Budget for
2025/26 was approved by Council on 12 February 2025.
1.2  As part of the monitoring procedures to keep the Cabinet informed of the financial
performance of the Council, financial performance reports are presented on a regular
basis. This is the fourth report for 2025/26 and covers the period to the end of March
2026 (Period 12). Projections have been made to the year-end. This is the final
financial performance information on which the annual accounts for the Council will be
prepared.
1.3  At Period 12 the General Fund is reporting a net in-year underspend of (£2.014m),
(0.4%), after transferring resources to/from earmarked reserves This is an
improvement of (£0.334m) from that reported at Period 10 and is primarily related to
additional income, lower than anticipated employee costs within the Facilities
Management and Streetscene linked to staff turnover levels and lower than
anticipated utilisation of inflationary related provisions during the year. In recognising
that there continues to be volatility across certain areas of spend, linked to current
global events, this improved position has been partially offset by additional requests
for earmarking to meet anticipated cost pressures in 2026/27. The underspend will be
added to the General Fund Unearmarked Reserves which would increase the
Appendix 1
23

Page 24

available balance to 2.3% the revised General Services Revenue Budget which is
within the recommended range of 2 – 4%.  From the underspend, a total of £0.518m
is required to ensure unearmarked reserves are retained at a minimum level of 2%
within this range. Whilst the current level of unearmarked reserves remains at the
lower end of good practice, this still reflects a prudent position to help address areas
of significant risk to the Council through 2026/27, most notably through the financial
performance of the HSCP.
1.4  The Housing Revenue Account is reporting a net in-year underspend of (£3.943m),
(6.0%). This is a movement of (£1.617m) from the previously reported underspend at
Period 10. The movement is primarily related to reduced expenditure on property
costs and increased income. The underspend will be added to the HRA earmarked
balances to support service delivery in future years.
1.5  Work is ongoing to confirm the final Health and Social Care Partnership out-turn
position for the year, and the final confirmation of the NHS budget outturn is awaited.
The final outturn for the Council services element has been confirmed as an
underspend of £1.818m.  From this, £1.359m will be earmarked to meet future costs.
This leaves a £0.459m surplus to be added to the HSCP’s unearmarked reserves
bringing the reported position to a net break-even position. This is an improvement
of £1.941m from the previously reported Council services position.  A further report
will follow from the HSCP in the new year.
1.6 Management action is ongoing to address absence levels across services. However,
employee absence rates remain above targets, and there has been a marginal 0.9%
increase in days lost during the period when compared to the same period last year.
2. Background
General Fund
2.1   The Council set a balanced budget for 2025/26. In addition to the budget approved on
26 February 2025, earmarked funds of £85.088m were carried forward from 2024/25
for service expenditure in 2025/26 and beyond. These funds are reflected in the
figures within the 2025/26 financial performance reports as they are drawn down.
2.2 A net in-year underspend of £2.014m is reported, net of transfers to/from reserves.
The undernoted table details the final position on a service-by-service basis.
Service Expenditure
App
No.
Annual
Budget
£ million
Actual
Expenditure
to 31 March
2026
£ million
Variance
for year
(Fav)/Adv
£ million
Requests
for Carry
Forwards
£ million
Variance
after
Carry
Forward
(Fav)/Adv
£ million Note
Corporate Services 1 22.748 21.767 (0.981) 0.186 (0.795) (i)
Education 2 191.980 192.050 0.070 (0.193) (0.123) (ii)
Place 3 60.889 58.371 (2.518) 3.363 0.845 (iii)
Communities &
Housing 4 17.116 16.344 (0.772) 0.233 (0.539) (iv)
Other Corporate Items 5 15.971 10.781 (5.190) 3.357 (1.833) (v)
Sub Total 308.704 299.313 (9.391) 6.946 (2.445)
24

Page 25

Health and Social
Care Partnership 9 142.676 140.858 (1.818) 1.818 0.000
Balance for Services 451.380 440.171 (11.209) 8.764 (2.445)
Financing Charges 6 13.751 13.751 0.000 0.000 0.000
Contribution to Loans
Fund Reserve 6 10.187 10.187 0.000 1.500 1.500 (vi)
Total Planned
Expenditure 475.318 464.109 (11.209) 10.264 (0.945)
Aggregate External
Finance 6 (394.613) (394.637) (0.024) 0.000 (0.024)
Council Tax 6 (71.939) (72.984) (1.045) 0.000 (1.045) (vii)
Use of Earmarked
Funds 6 (8.766) (8.766) 0.000 0.000 0.000
Total Planned
Income (475.318) (476.387) (1.069) 0.000 (1.069)
Net Expenditure/
(Income) 0.000 (12.278) (12.278) 10.264 (2.014)
2.3 The reported Aggregate External Finance within Planned Income includes several
adjustments to Scottish Government funding from that reported at Period 10, as
detailed in the following table:
Movements on Planned Income
General
Revenue
Grant
£ million
Non
Domestic
Rates
£ million
Specific
Grants
£ million
TOTAL
AEF
£ million
Revised Budget at P10 (342.866) (42.606) (8.101) (393.573)
Pupil Equity Fund C/F 0.655 0.655
Discretionary Housing Payment
Undistributed (0.781) (0.781)
Teacher Pay Award (0.756) (0.756)
CSC Pay Uplift Adjustment 0.083 0.083
Revised Planned Income (344.320) (42.606) (7.446) (394.372)
2.4 Commentary on Significant Movements from Period 10
The Council's overall financial forecast against the revised budget is an improvement
of (£0.334m) from the previously reported position. A brief explanation of the
significant movements at a service level are outlined as follows:
(i) Corporate Services – underspend of (£0.795m), an improvement of
(£0.200m) from the previously reported underspend
The movement is primarily related to:
• Vacancy management across the services;
• Revisions to Statutory additions (£0.070m);
• Lower than anticipated ICT contract costs in-year (£0.067m).; and
• Underspend in Election costs (£0.081m)
25

Page 26

This has been offset by a request to Earmark £0.283m in relation to anticipated
ICT contract inflation in 26/27 (£0.138m), resources to support the outcome of a
Service review (£0.060m) and the carry forward of Election resources to support
the democratic process (£0.085m).
(ii) Education – underspend of £0.123m, a favourable movement of (£0.724m)
from the previously reported position
The movements are primarily related to:
• Increase in the underspend within Facilities management of £0.679m primarily
relating to vacancy management and reduced expenditure across supplies and
services.
• Reduction in the overspend within ASN of £0.402m as a result of reduced day
placement costs and a reduction in external residential placement numbers and
associated costs, through the work of the Brighter Pathways programme.
This has been offset by increased teacher costs across Primary and Secondary
Schools.
It is requested that £0.010m is earmarked to meet costs in relation to Furniture and
updated equipment for the Visual Impairment team in ASN.
(iii) Place – overspend of £0.845m, an increase of £0.434m from the previously
reported overspend
The movement is primarily related to:
• Funds received from the Extended Producer Responsibility Payment
(£1.087m) in accordance with the payment schedule.
• Increased underspend within Transport of £0.310m due to reduced
expenditure on repairs and maintenance, fuel and additional income.
• A favourable movement within Streetscene of £0.196m largely due to a
reduction in staff costs and increased income
• An over-recovery of Largs car park income as a result of the new pricing
structure.
This is offset by requests to earmark £1.939m, further to the £1.424m previously
approved, to support anticipated additional expenditure during 2026/27 in relation
to:
• Waste pressures and investments in accordance with Extended Producer
Responsibility funding requirements, £0.950m
• Programme of Fire risk Assessments and essential works, £0.400m
• Programme of Water Quality Assessments and essential works, £0.100m
• Largs Car Park income to be retained in Largs Car Park Fund, £0.104m
• Anticipated Fuel cost pressures in view of current global events, £0.274m
• Investment in Car parking infrastructure, £0.076m
• Provision for the Making Waves Festival, £0.035m
26

Page 27

Virements in relation to the realignment of budgets within Roads and
Employability have been included within Appendix 8.
(iv) Communities and Housing – underspend of £0.539m, an improvement of
(£0.139m) from the previously reported underspend
The movement is primarily related to:
• Increase in the underspend within Housing of £0.197m largely relating to
reduced Bad debt provision and write off costs.
• Reduced expenditure within connected communities of £0.261m relating to
lower than anticipated storm damage costs and service management of
budget lines to offset the impact of delay in implementing previously approved
libraries savings.
• Additional income within protective services of £0.255m
• Reduced expenditure on employee costs due to ongoing service redesign of
£0.094m
• An underspend due to the reprofiling of the local development plan into 2026-
27
• A surplus of £0.057m within Building services.
This has been partially offset by :
• An overspend of £0.314m in relation to demolition costs as a result of
significant fire damage at the Forum Centre Irvine.
• Requests to earmark £0.463m to support anticipated additional expenditure
during 2026/27 in relation to:
 Further anticipated costs in relation to the demolition of the Forum
centre following the major fire damage, £0.400m
 Local Development Plan, £0.043m
 Holiday Playschemes and Activities budget as part of a delivery
programme of activities in Summer 2026, £0.020m
(v) Other Corporate Items – underspend of £1.833m, an increase of (£0.757m)
from the previously reported underspend
The movement is primarily related to:
• Centrally held provisions not drawndown during the year, including pay
inflation, energy sustainability funding and energy cost provisions which have
been subject to ongoing volatility, even after allowing for a proportion of
advanced purchasing arrangements, (£2.041m)
• Workforce Planning cost provisions not required in year including Severance
costs and Equal pay £1.257m
• Funding to support ongoing Transformation activity secured as part of the
2025/26 Budget, not utilised in year £0.750m
This is offset by :
27

Page 28

• An overspend on insurance reflecting high level of excesses largely relating to
storm damage. £1.106m
• Requests to earmark £3.496m to support anticipated additional expenditure
during 2026/27 in relation to:
o Equal Pay Provision required to help address future risks, £0.494m
o Workforce Planning and Transformation resources required to
support ongoing programme £1.732m
o Property – Energy sustainability funding to address current volatility,
£0.500m
o DWP Housing Benefit Accuracy award, £0.018m
o Rapid Rehousing Transition Plan rolling programme £0.024m
o SG Resettlement programme funding £0.095m
o SG Nature Restoration funding £0.073m
o SG Island support funding £0.288m
o On-going Service re-design costs £0.031m
o SG NDR Empty Property Relief funding £0.241m
(vi) Contribution to Loans Fund Reserve – Overspend of £1.500m, an increase of
£1.500m from the previously reported position
In view of the current conflict in the middle east and the anticipated inflationary
impacts, the Bank of England forecast for interest rates now reflects an increase
from the current base rate of 3.75% up to 5.25% potentially during 2026/27. In
order to address the impact this will have on borrowing costs through 2026/27, it
is requested that £1.500m is earmarked and transferred to the Loans Fund
reserve.
(vii)Council Tax – over-recovery of (£1.045m), an increase of £0.448m from the
previously reported over-recovery
The movement reflects growth in the Council Tax base from additional new builds,
properties previously registered as self-catering holiday units for NDR purposes
that have come onto the Council tax register, and the impact of the application of
100% premium on Council tax for second homes when measured against the
original financial planning assumptions.
Health and Social Care Partnership
2.5 The final HSCP financial performance report for the year will be presented to the
Integration Joint Board on 18 June 2026 and will outline the 2025/26 financial
performance in more detail. Work is ongoing to confirm the final outturn position for
the year and the HSCP is awaiting final confirmation of the NHS budget outturn. The
final outturn for the Council services element has been confirmed as an underspend
of £1.818m.  £1.359m is to be earmarked to meet costs in relation to ADP, Whole
Family Wellbeing Fund, Community alarms, Magic Notes and Adult Social work
Restructure costs. This leaves a £0.459m surplus which is to be added to the
HSCP’s unearmarked reserves bringing the reported position to a net break-even
position.  This is an improvement of £1.941m from the previously reported Council
services position. A further report will follow from the HSCP in the new year.
28

Page 29

Absence Management 
2.6 The programme of work to monitor absence levels and effectively implement relevant
policies has been ongoing and initially resulted in a significant reduction in reported
absence levels across the Council. However, the year-end position shows a marginal
increase in days lost during 2025/26 when compared to 2024/25 i.e. 12.87 days lost
compared to 12.76 in 2024/25. The absence levels for the year exceed the target of
10.22 days. Within the Education Service, the number of days lost for teaching staff
has reduced by almost 8% when compared to the previous year (5.78 days compared
to 6.25 last year). The HSCP and the Communities and Housing directorate’s number
of days lost have increased by 20% and 4% respectively, with the Place directorate
showing a 14% improvement for the period. 
Risks 
2.7 Due to the anticipated outturn position of the HSCP in 2025/26, from the Council
services element, the level of HSCP unearmarked reserves will increase by £0.459m.
Moving forward into 2026/27, under the terms of the Health and Social Care
Integration Scheme, a recovery plan is required in order to address any projected
shortfalls in future years. There is a risk that, if the recovery plan is not successful, this
would have an impact on the level of financial contributions from the funding parties.
In such a circumstance the Council would be asked to make interim funds available.
The funding could be made available for repayment by the HSCP across a period of
future years or as an additional contribution. This HSCP position will continue to be
monitored through 2026/27, however, in view of the level of pressures faced by the
HSCP and the scale of savings required in 2026/27 to operate within available
resources, there is a risk that spend will exceed available resources. It is recognised
the Council’s underspend position 2025/26 will help provide a level of financial
mitigation to this risk. The other main risks are linked to current global events and the
potential impacts on inflation and interest rates through 2026/27. Again, to address
these, further mitigations through the earmarking of financial resources have been
included in the year end position. 
Housing Revenue Account 
2.8  The Housing Revenue Account budgeted for a breakeven position in 2025/26.  An
underspend of (£3.942m), net of transfers to/from reserves, has been reported. This is
an improvement of (£1.617m) from the previously reported position and is
summarised in the following table with further details provided in Appendix 7. The
underspend will be added to the HRA earmarked balances to support delivery of the
HRA Business Plan. 
29

Page 30

2.9 Commentary on Significant Movements from Period 10 
A brief explanation of the significant movements from the previous forecasts is
outlined as follows: 
(i) Property Costs – underspend of £1.092m, a favourable movement of 
(£1.250m) from the previously reported position
The movement is primarily related to reduced expenditure on Aids and
Adaptation, (£0.191m), Void Repairs (£0.276m), Planned and Cyclical
Maintenance (£0.466m) and Other Property Costs (£0.293m). 
(ii) Administration Costs – underspend of £0.212m, a movement of (£0.208m)
from the previously reported position 
The movement is primarily related to reduced expenditure on legal fees
(£0.103m), Central Recharges (£0.053m) and Insurances (£0.025m) 
(iii) Third Party Payments – underspend of £0.061m, a favourable movement of
(£0.122m) from the previously reported position
The movement is primarily related to reduced recharges from other Council
departments. 
(iv) Transfer payments – underspend of £0.053m, a movement of (£0.053m) from
the previously reported position
The movement is due to an underspend in disturbance allowances. 
(v) Other Expenditure – overspend of £0.398m, a movement of £0.398m from
the previously reported position
Housing Revenue
Account
Annual
Budget
£ million
Actual
Expenditure
to  31 March
2026
£ million
Variance for
year
(Fav)/Adv
£ million
Projected
Variance at
P10 
(Fav)/Adv
£ million Movement Note
Employee Costs 5.294 5.294 0.000 0.002 (0.002)
Property Costs 25.628 24.536 (1.092) 0.158 (1.250) (i)
Supplies and Services 2.145 2.130 (0.015) (0.006) (0.009) (ii)
Transport and Plant Costs 0.016 0.015 (0.001) 0.000 (0.001)
Administration Costs 2.114 1.902 (0.212) (0.004) (0.208) (iii)
Third Party Payments 3.832 3.771 (0.061) 0.061 (0.122) (iv)
Transfer Payments 0.177 0.124 (0.053) 0.000 (0.053)
Other Expenditure 0.550 0.948 0.398 0.000 0.398 (v)
Capital Financing 26.270 23.834 (2.436) (2.372) (0.064) (vi)
Gross Expenditure 66.026 62.554 (3.472) (2.161) (1.311)
Income (66.026) (66.496) (0.470) (0.164) (0.306) (vii)
Net Expenditure 0.000 (3.942) (3.942) (2.325) (1.617)
30

Page 31

The movement is due to an increase in the bad debt provision. 
(vi) Capital Financing Costs – underspend of £2.436m, a movement of (£0.064m)
from the previously reported position 
The movement is primarily related to revised loan charges reflecting the revised
profile of capital project delivery, leading to a lower level of in-year borrowing.
These funds will be required to support the HRA capital programme in future
years. 
(vii) Income – over recovery of £0.470m, a movement of (£0.306m) from the
previously reported position 
The movement is primarily related to an over-recovery in Council House rents
(£0.147m) and other income (£0.157m). 
3. Proposals 
3.1 It is proposed that Cabinet agrees to: 
(a) note the information and financial outturn position outlined in the report; 
(b) approve the earmarking of £7.691m identified at 2.4 to meet future year
commitments in accordance with funding requirements;
(c) note the financial performance for the Health and Social Care Partnership
highlighted at 2.5; and
(d) approve the virements detailed in Appendix 8. 
4. Implications/Socio-economic Duty 
Financial 
4.1 General Services
The final outturn position for the year is a net underspend of (£2.014m) after transfers
to and from earmarked reserves. 
Housing Revenue Account
The final outturn position for the year is a net underspend of (£3.942m). 
Human Resources 
4.2 None. 
Legal 
4.3 None. 
Equality/Socio-economic 
4.4 None.
31

Page 32

Climate Change and Carbon 
4.5 None. 
Key Priorities 
4.6 This report directly supports the Council Plan 2023 to 2028 by maximising financial
flexibility to support the delivery of our priorities. 
Community Wealth Building 
4.7 None. 
Islands Communities Impact Assessment (ICIA) 
4.8 None. 
United Nations Rights of the Child (UNCRC) 
4.9 None. 
Consumer Duty 
4.10 None. 
5. Consultation 
5.1 Progress as outlined in this report has been approved by Executive Directors. 
Mark Boyd
Head of Service (Finance) 
For further information please contact Mark Boyd, Head of Service (Finance), on 01294
324560. 
Background Papers
Revenue Budget 2025/26: Financial Performance to 31 January 2026 – Cabinet 17 March
2026
32

Page 33

Appendix 1
CORPORATE SERVICES
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS TO 31 MARCH 2026
Objective Summary
Annual
Budget
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
Note
No
£000 £000 £000
Chief Executive's Office
Chief Executive's Office 197 214 17 9%
Total for Chief Executive's  Office 197 214 17
Financial Services
Change Programme 283 283 0 0%
Audit, Fraud, Safety & Insurance 701 688 (13) -2%
Corporate Procurement 815 566 (249) -31% 1        
Financial Services 1,749 1,634 (115) -7% 2        
Revenues (459) (546) (87) 19% 3        
Transformation 795 817 22 3%
Total for Financial Services 3,884 3,442 (442)
People & ICT
Employee Services 946 865 (81) -9% 4        
HR & Organisational Development 1,229 1,193 (36) -3% 5        
ICT 5,605 5,431 (174) -3% 6        
Business Support 1,594 1,554 (40) -3% 7        
Customer Services 4,759 4,700 (59) -1% 8        
Total for People & ICT 14,133 13,743 (390)
Democratic Services
Legal & Licensing 791 823 32 4%
Policy, Performance & Democracy 539 516 (23) -4%
Communications 503 507 4 1%
Civil Contingencies 60 59 (1) -2%
Committee Services 443 372 (71) -16% 9        
Member Services 1,560 1,528 (32) -2%
Information Governance 577 524 (53) -9% 10      
Ayrshire Area Support Team 61 39 (22) -36%
Total for Democratic Services 4,534 4,368 (166)
Net Totals 22,748 21,767 (981) -4%
Transfer to/ (from) Earmarked Reserves 97 283 186
Net Total 22,845 22,050 (795) -3%
33

Page 34

Appendix 1
Subjective Summary
Annual
Budget
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
£000  £000  £000
Employee Costs 18,290         17,858         (432)               -2%
Property Costs 85                118              33                  39%
Supplies and Services 3,462           3,174           (288)               -8%
Transport and Plant Costs 23                13                (10)                 -43%
Administration Costs 1,653           1,569           (84)                 -5%
Other Agencies & Bodies 2,274           2,209           (65)                 -3%
Transfer Payments 867              866              (1)                   0%
Other Expenditure -                   -                   -                     -
Capital Financing -                   -                   -                     -
Gross Expenditure 26,654         25,807         (847)               -3%
Income (3,906)          (4,040)          (134)               3%
Net Expenditure 22,748         21,767         (981)               -4%
34

Page 35

Appendix 1a
CORPORATE SERVICES
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS TO 31 MARCH 2026
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Finance - Corporate Procurement
Movement: There has been a favourable movement of (£0.091m) since P10 mainly due to continued forecasted
underspends in employee costs and overrecovery of income.
815 (167)              -20% Employee costs: There is an underspend of £0.167m due to vacancy management.
(100) (60)                -7% Income: £0.060m overrecovery of income from Procurement cards and rebates from Scotland Excel contracts.
(22)                -3% Other minor movements.
(249)             
Note 2 Finance - Financial Services
Movement: There has been a favourable movement of (£0.066m) since P10 mainly due to an over recovery of
£0.052m in staff recharges.
1,456 (45)                -3% Employee Costs: Underspend of £0.045m mainly due to vacancy management.
(108) (53)                Income: £0.053m over recovery of staff recharges.
(17)                Other minor movements.
(115)             
Note 3 Finance - Revenues
Movement: There has been a favourable movement of (£0.070m) since P10 largely due to revisions to statutory
additions.
(1,385) (48)                3% Income: There is an overall increase in statutory additions of £0.048m.
(39)                Other minor movements.
(87)               
Note 4 People & ICT - Employee Services
Movement: There has been a favourable movement of (£0.010m) since P10 due to vacancy management.
900 (78)                -9% Employee Costs: There is an underspend of £0.078m due to vacancy management.
(3)                  Other minor movements.
(81)               
Note 5 People & ICT - HR & Organisational Development
Movement: There has been no significant movement from P10.
413 (35)                -8% Third Party Payments: There is an underspend of £0.035m due to Occupational Health charges.
(1)                  Other minor movements.
(36)               
Note 6 People & ICT - ICT
Movement: There has been a favourable movement of (0.067m) since P10 due to contract costs being less, Co-
Pilot trial being funded from change fund and Wi-Fi support not being completed.
5,605 (179)              -3%
Supplies and Services: There is an underspend of £0.205m due to contract costs being less than expected, Wi-Fi
support not completed in September due to negotiations of new product offset with a £0.010m overspend in WAN
cicuits due to increase in contract prices and £0.016m overspend in other supplies in services due to no computer
disposals.
5                   Other minor movements.
It is requested to earmark £0.138m underspend in software licenses and support. This funding would be used to
offset the unforeseen and significant increase in charges under the current WAN contract, estimated at £0.138m.
Earmarking these underspends will allow the service to manage this in-year budget pressure within existing ICT
resources, while progressing the planned procurement of a replacement WAN contract
(174)             
35

Page 36

Appendix 1a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 7 People & ICT - Business Support
Movement: There has been no significant movement from P10.
1,583 (36)                -2% Employee Costs: There is an underspend of £0.036m due to vacancy management.
(4)                  Other minor movements.
(40)               
Note 8 People & ICT - Customer Services
Movement: There has been no significant movement from P10.
3,069 (78)                -3% Employee Costs: There is an underspend of £0.078m due to vacancy management.
19                  Other minor movements.
It is requested to earmark £0.060m for service review costs in 2026/27.
(59)               
Note 9 Democratic Services - Committee Services
Movement: There has been a favourable movement of (£0.081m) since P10 mainly due to underspend in Election
Costs.
443 (85)                -19% Election Costs: There is an underspend of £0.085m in relation to Election Costs for 2025/26.
14                  3% Other minor movements.
It is requested to earmark  £0.085m for future Election commitments.
(71)               
Note 10 Democratic Services - Information Governance
Movement: There has been a small favourable movement of (£0.007m) from P10.
571 (60)                -11% Employee Costs: Underspend of £0.060m due to vacancy management.
7                   Other minor movements.
(53)               
36

Page 37

Appendix 2
EDUCATION
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS TO 31 MARCH 2026
Objective Summary
Annual
Budget
Final Year
End Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
Note
No
£000 £000 £000
Early Years Education 21,528           20,868           (660)              -3% 1
Primary Education 55,635           56,447           812               1% 2
Secondary Education 67,948           69,278           1,330            2% 3
Additional Support Needs 17,754           18,725           971               5% 4
Central Education 4,980             4,581             (399)              -8% 5
Scottish Equity Fund 152                152                -                    0%
Pupil Equity Fund 4,074             4,074             -                    0%
Facilities Management 19,909           17,925           (1,984)           -10% 6
191,980         192,050         70                
Transfer to/(from) Earmarked Reserves 203                10                  (193)             
Net Total 192,183         192,060         (123)             
Subjective Summary
Annual
Budget
Final Year
End Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs - Teachers 108,021         109,763         1,742            2%
Employee Costs - Non Teachers 53,190           51,976           (1,214)           -2%
Property Costs 1,921             1,803             (118)              -6%
Supplies and Services 25,328           24,797           (531)              -2%
Transport and Plant Costs 160                187                27                 17%
Administration Costs 827                845                18                 2%
Other Agencies & Bodies 10,017           11,059           1,042            10%
Transfer Payments 580                426                (154)              -27%
Other Expenditure 1                    1                    -                    0%
Capital Financing 71                  84                  13                 18%
Gross Expenditure 200,116         200,941         825               0%
Income (8,136)           (8,891)           (755)              9%
Net Expenditure 191,980         192,050         70                 0%
-                    -                    -                   
37

Page 38

Appendix 2a
EDUCATION
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS TO 31 MARCH 2026
Budget
£000
Projected
Variance
£000
Variance
as % of
budget Section
Note 1 Early Years Education
Movement : There has been an unfavourable movement of £0.041m since P10 mainly due to an increase of £0.058m in
employee costs.
15,895 (485) -3% Employee Costs: Overall an underspend of (£0.544m).
- Teachers:- underspend of (£0.055m.)
- Non Teachers:- underspend of (£0.430m) as a result of vacancy management after accounting for budgeted turnover.
5,341 (151) -3%
Third Party Payments: There are underspends of (£0.165m) in payments to funded providers due to a lower than
forecasted uptake of hours and a change in the charging model for cross boundary costs, partially offset by an
overspend of £0.024m in Speech Therapy costs.
(24) Other minor movements
(660)
Note 2 Primary Education
Movement : There has been an unfavourable movement of £0.162m since P10 mainly due to increased teacher costs
53,155 784 1%
Employee Costs : Overall an overspend of £0.784m
- Teachers:- overspend of £0.758m   Pressures on this line include teacher absence cover, budgeted turnover and
teacher salary pay levels
- Non Teachers:- underspend of (£0.027m) after accounting for budgeted turnover.
28 Other minor movements.
812
Note 3 Secondary Education
Movement : There has been a unfavourable movement of £0.219m since P10 mainly due to increased teacher costs
51,940 1,412 3%
Employee Costs : Overall an overspend of £1.412m
- Teachers:- overspend of £1.289m. Pressures on this line include teacher absence cover, budgeted turnover and
teacher salary pay levels
- Non Teachers:- overspend of £0.123m after accounting for budgeted turnover.
15,834 (109) -1% Supplies and Services: forecasted underspend in PPP unitary charge mostly due to a reduction in energy costs
27 Other minor movements.
1,330
Note 4 ASN
Movement: There has been a favourable movement of (£0.402m) since P10. (£0.207m) of this favourable movement is
in Day Placements as a result of the level of assessed needs varying for some young people, transport costs were less
than projected and rates for one provider were lower than projected. There has been a (£0.117m) favourable movement
in Residential Placements as there are less children in Residential Placements compared to P10, and there has been a
decrease in rates from P10 projection. There has also been a favourable movement of (£0.067m) in Employee Costs.
16,034 (321) -2%
Employee Costs :  Overall underspend of (£0.321m)
- Teachers:- underspend of (£0.246m). Pressures on this line include teacher absence cover, budgeted turnover and
teacher salary pay levels
- Non Teachers:- underspend of (£0.075m) reflecting the level of turnover within the service.
268 (32) -12% There is an underspend of (£0.032m) on payments to Other Local Authorities due to a reduction in the number of NAC
children accessing placements in their establishments.
1,310 (83) -6% Underspend of (£0.083m) on external day placements. Currently there are 31 children in day placement provision. This
service will continue to be monitored as options for alternative service provision are developed.
38

Page 39

Appendix 2a
Budget
£000
Projected
Variance
£000
Variance
as % of
budget Section
499 1,414 283%
There is an overspend of £1.414m on external specialist residential placements. Currently there are 9 children in
accommodation. Increased pressures on internal care settings, as well as changing needs of children and young people,
have resulted in an increase in the need for external residential settings. Joint working is ongoing with HSCP on the
Brighter Pathways Programme to ensure that all options are fully explored to retain young people within their local
community where possible. Where this is not possible, a forum has been set up to further discuss those young people
who will require care and education provision to support them appropriately.
(7) Other minor movements.
It is requested to earmark £0.010m to purchase furniture and updated equipment for the Visual Impairment team.
971
Note 5 Central Education
Movement:  There has been a favourable movement of (£0.075m) since P10.
4,015 40 1% Employee Costs: There is an overspend of £0.040m mainly due to unachieved turnover.
(1,407) (431) 31% Income:  There is an over-recovery of PPP insurance rebate of (£0.285m) and PPP deductions of (£0.156m) in excess of
budget.
(8) Other minor movements
(399)
Note 6 Facilities Management
Movement: There has been a favourable movement of (£0.679m) since P10.  This is mainly due to further employee
cost underspends and further underspends across supplies and services lines
15,642 (901) -6% Employee Costs: There is an underspend of (£1.232m) primarily due to previous vacancy management, offset by a
budgeted turnover target of £0.331m resulting in a net underspend of (£0.901m)
1,612 (58) -4% Property Costs: There is an underspend of (£0.058m) across cleaning materials budget lines
5,434 (445) -8%
Supplies and services: There is an underspend of (£0.445m). This comprises of underspends in kitchen equipment of
(£0.376m) and other supplies and services of (£0.160m) which is offset slightly by an overspend on food costs of
£0.138m.
2,892 (625) -22%
Income: There is an over recovery in Commercial Catering of (£0.191m). A targeted approach over the last few years
has seen this outturn position change from a significant under recovery in income to the favourable position shown this
year. Over recovery in Cleaning/janitorial income of (£0.218m) and school meals income of (£0.215m) linked to an
uptake in paid meals within secondary schools
45 Other minor movements
(1,984)
Note 7 General
Teacher absence levels are subject to regular review across the service and appropriate actions are being taken to
maximise attendance. Average days lost per FTE is 8.82 for the period April-March.  Average days lost per FTE for same
period last year was 9.33.  This reflects an improved position for the year.
39

Page 40

Appendix 3
PLACE
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Objective Summary
Annual
Budget
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
Note
No
£000 £000 £000
Directorate and Support 995 836             (159)              (16%) 1    
Neighbourhood Services
Roads 8,109 8,034          (75) (1%) 2    
Streetscene 5,875 5,753          (122)              (2%) 3    
Waste Resources 8,199 6,545          (1,654)           (20%) 4    
Municipalisation Advertising (73)             (29)              44 (60%)
Total for Neighbourhood Services 22,110       20,303        (1,807)          
Economic Development, Growth & Regeneration
Economic Policy 337 261             (76) (23%) 5    
Employability and Skills 2,274 2,274          - 0%
Regeneration 702 703             1 0%
Business 954 556             (398)              (42%) 6    
Growth & Investment 287 277             (10) (3%) 7    
Total for Economic Development, Growth &
Regeneration 4,554 4,071          (483)             
Sustainability, Transport and Corporate Property
Property Management & Investment 2,129 2,132          3 0% 8    
Housing Assets & Investment 95 - (95) (100%) 9    
Property Maintenance 4,709 4,848          139 3% 10  
Property Running Costs 6,653 7,287          634 10% 11  
Energy and Sustainability 7,679 7,679          - 0%
Internal Transport 11,965       11,215        (750)              (6%) 12  
Total for Sustainability, Transport and Corporate
Property 33,230       33,161        (69)
Net Total 60,889       58,371        (2,518)           (4%)
Transfer to Earmarked Reserves 3,363          3,363           
Net Total 60,889       61,734        845
40

Page 41

Appendix 3
Subjective Summary
Annual
Budget
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 31,558       32,297        739 2%
Property Costs 24,583       24,722        139 1%
Supplies and Services 4,548 4,634          86 2%
Transport and Plant Costs 10,638       10,997        359 3%
Administration Costs 703 933             230 33%
Other Agencies & Bodies 21,044       19,834        (1,210)           (6%)
Transfer Payments - - - 0%
Other Expenditure 78 90 12 15%
Capital Financing 26 26 - 0%
Gross Expenditure 93,178       93,533        355 0%
Income (32,289)      (35,162)       (2,873)           9%
Net Expenditure 60,889       58,371        (2,518)           (4%)
41

Page 42

Appendix 3a
PLACE
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Directorate and Support
Movement: There has been a favourable movement of (£0.104m) since P10. This relates to Largs Car Park, with
increased income and a decrease in operating costs.
981 (56) (6%) Employee Costs: There is an underspend due to vacancy management.
(212) (85) 40% Income: £0.085m over recovery of income in Largs Car Park, as a new pricing structure was introduced in 2025/26.
(18) Other minor movements.
There is an underspend of £0.104m in Largs Car Park and this will be retained for the Largs Car Park fund, to be used in
future years.
(159)
Note 2 Roads
Movement: There has been a favourable movement of (£0.075m) since P10 primarily due to a reduction in forecasted
winter and energy costs within supplies and services of £0.108m and additional over recovery of income of £0.181m. This
is partially offset by an adverse movement of £0.138m in third party costs due to reactive emergency unplanned
maintenance costs and £0.093m in employee costs.
4,877 58 1% Employee Costs: £0.058m overspend due to additional overtime.
31 91 294% Transport Costs: £0.090m overspend mainly due to hire charges in particular of a gully unit.
2,828 (115) (4%) Supplies & Services: Underspends of £0.100m in winter salt/grit costs and £0.052m in electrical power, partially offest by
overspends of £0.026m in materials and £0.017m in software licence costs.
1,070 144 13% Third Party Payments: overspend of £0.091m within Engineering Services due to reactive emergency unplanned costs
together with £0.040m Winter overspend due to weighbridge replacement costs and Millport gritting contract.
(1,631) (226) 14% Income: £0.163m over recovery of design fees income mainly due to project management fees for Road Safety
Improvement Funds and 20mph projects and £0.076m over recovery in Decriminalised Parking Enforcement income.
(27) Other minor movements.
It is requested to earmark £0.076m, the DPE net income, which will be reinvested in the car parking infrastructure.
(75)
Note 3 Streetscene
Movement: There has been a favourable movement of (£0.196m) since P10. Vacant posts and a reduction in overtime and
casual staff costs have contributed to a favourable movement of £0.130m in Employee Costs. Income has seen a
favourable movement of £0.052m, with increased income from other departments, interment and memorial permit income.
There has also been a favourable movement of £0.012m in Supplies and Services.
7,712 (285) (4%) Employee Costs: £0.285m underspend due to vacancy management. Management are currently recruiting to fill vacant
posts in 2026/27.
455 66 15% Supplies and Services: £0.066m overspend includes £0.041m for storm rectification works, £0.011m overspend on tools
and machinery and £0.014m overspend on PPE.
(2,886) 77 (3%) Income: £0.077m under recovery of income, which includes £0.050m under recovery of interment income and £0.022m
under recovery of memorial permit income.
20 Other minor movements.
(122)
42

Page 43

Appendix 3a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 4 Waste Services
Movement: There has been a favourable movement of (£0.951m) since P10 due to £1.087m of funds received from the
Extended Producer Responsibility payment, partially offset by additional costs within supplies & services of £0.127m which
includes £0.082m of trade effluent costs.
5,616            799 14%
Employee costs: Current sickness absence rates for April 2025 to March 2026 are 20.26 days per employee, a reduction of
10.15 days per employee when compared to the same period last year. A robust absence monitoring process is in place
and a dedicated resource has been recruited to monitor and review the absence management process in Waste, through
assisting supervisors with absence management meetings, referrals to occupational health etc and to support employees
return to work. The statutory nature of the service requires additional resources and/or overtime to cover unforeseen
absences resulting in additional costs. To help mitigate against this, resources out-with Waste Collections have received
HGV training to help provide cover for collections.  An overall review of the Waste service in light of legislative changes
and current service demands is ongoing. The absence rates reflect an improving position, however they are still above
target rates.
245            368 150% Transport Costs: Additional vehicles are currently in place to deal with ongoing pressures and demands.  Transport needs
are continuously under review and flexed depending on the operational needs of the service.
671 10 1%
Supplies & Services: Overspends in trade effluent of £0.082m, software and computer equipment costs of £0.018m, and
materials/tools and implements of £0.011m have been partially offset by underspends in refuse containers of £0.055m and
leachate of £0.052m.
6,896          (125) (2%)
Third Party Payments: Underspends mainly from diverted waste of £0.114m due to a reduction in tonnages as a result of
the implementation of the HWRC booking system, the recyclables contract of £0.046m, the organics contract of £0.048m,
and the Clyde Valley Contract of £0.025m, this is partially offset by an overspend in Special Uplift processing costs of
£0.093m due to increased costs for POPs waste.
(5,413)        (2,679) 49%
Income:  Income from the Extended Producer Responsibility (£4.350m) for packaging funds currently exceeds the amount
included in the Budget by £2.843m. These funds were received in 3 tranches from November 2025 and have been
allocated to cover chargeable disposal costs. In 2025/26 these funds helped address the pressures faced by the service
and supported further investment to meet operational needs and deliver service improvements. These funds together with
an over recovery in special uplifts income of £0.077m, sale of scrap of £0.023m, and the sale of vouchers of £0.019m, is
partially offset by an under-recovery in purple bin contract income of £0.175m due to reductions in recyclate market prices,
commercial refuse charges of £0.074m and sale of bins of £0.035m.
(27) Other minor movements.
A further request to earmark funds of £0.950m is made to the P10 request of £0.703m (total £1.653m), these funds will be
utilised to support waste pressures and investments in accordance with EPR funding requirements.
43

Page 44

Appendix 3a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
(1,654)
Note 5 Economic Policy
Movement: There has been a favourable movement of (£0.021m) since P10.
347 (84) (24%) Employee Costs: Underspend of £0.084m due to vacancy management and maximising available external funding.
8 Other minor movements.
(76)
Note 6 Business
Movement: There has been an unfavourable movement of £0.012m since P10.
975 (400) (41%) Income: £0.400m received from Business Loans Scotland for contributions to the West Of Scotland Loans Fund.
2 0% Other minor movements.
(398)
Note 7 Growth & Investment
Movement: There has been a favourable movement of (£0.010m) since P10.
193 (10) (5%) Third Party Payments: Underspend of £0.010m in budget for Events.
It is requested to earmark £0.035m to support the Making Waves festival 2027 to support an event of sufficient scale and
quality to promote the Great Harbour programme.
(10)
Note 8 Property Management and Investment
Movement: There has been adverse movement of £0.120m since largely due to an under recovery in project income
(£0.171m), partially offset by an increase in the employee costs underspend (£0.081m) due to vacancy management.
2,733 (253) (9%) Employee Costs: There is an underspend of £0.253m primarily due to vacancy management.
(1,263) 211           (17%) Income: There is an under-recovery of fee income of £0.211m which is primarily related to projects.
45             Other minor movements.
3
Note 9 Housing Assets and Investments
Movement: There has been a favourable movement of (£0.095m) since P10 mainly due to increased income offset by
increased employee costs. This is now reported as on budget.
(2,204) (86) 4% Income: Increased income from HRA.
(9) Other minor movements
(95)
Note 10 Property Maintenance
Movement: There has been an adverse movement of £0.139m since P10 mainly due to insurance works (£0.272m),
partially offset by a reduction in spend in relation to security costs and Rationalisation.
0 272 Administration Costs: An overspend of £0.272m in relation to insurance works.
8,071 (92) (1%) Property Costs: An underspend of £0.092m largely relating to lower than anticipated security costs and reduced
expenditure within the rationalisation budget.
(41) Other minor movements.
It is requested to earmark £0.500m to undertake programmes of Fire and Water Quality Risk Assessments and essential
works which arise from these assessments.
139
44

Page 45

Appendix 3a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 11 Property Running Costs
Movement: There has been a minor favourable movement of (£0.019m) since P10 due to a reduction in under-recovery of
income £0.101m, partially offset by increased overspends within property costs in relation to service charges and condition
surveys.
7,975 253 3%
Property Costs: Overspend of £0.100m due to Non Domestic Rates costs relating to the following properties: Moorpark
Primary which is scheduled for demolition, and Annickbank Innovation Campus which now has a lease agreed. The NDR
liability for Annickbank relates to the period it is unoccupied. There are also £0.058m of additional costs due to condition
surveys for the commercial estate and higher service charges of £0.072m.
(1,907) 376 (20%)
Income: Under-recovery of income £0.375m largely related to rental property income linked to market pressures, the
commercial property review is ongoing and we anticipate improvement in this position through recently agreed leases
which will fully come into effect in 2026/27 along with anticipated future pipeline of income from the capital investment
programme. 
5 Other minor movements.
634
Note 12 Internal Transport
Movement: There has been a favourable movement of (£0.310m) since P10, this is mainly due to an increased
underspend in Fuel of £0.076m, lower than projected costs for Software Licences of £0.026m, lower than projected Hires
costs of £0.019m, lower than projected overspend in Repairs and maintenance of £0.053m, an increase in Internal Pool
Vehicle Income of £0.042m and an increase in projected Bus Income of £0.060m.
1,714 (274) (16%)
Fuel: There is an underspend in fuel of £0.274m due to the current mix in fleet; HVO roll out, Electric Vehicles being
operated and fuel price volatility
5,513 (302) (5%)
Pupil Transport:  There is an underspend of £0.302m this was mainly due to changes from SPT as a result of expired
contracts with no renewal and savings on renewed contracts, linked to reduced levels of inflation, as well as in-house
operational efficiencies.
630 (61) (10%)
External Hires: There is a projected underspend in Roads Plant Hire of £0.103m due to works being allocated to capital. 
This is partially offset by an overspend of £0.061m mainly within Care at Home due to replacement vehicles to cover
extensive Vehicle Off Road time due to age of the current fleet and not having suitable zero emission alternatives readily
available. 
1,363 172 13%
Repairs & Maintenance: There is an overspend of £0.172m due to additional repairs being outsourced as a result of
difficulties recruiting Motor Mechanics (now resolved) during the first two quarters of the year along with maximising the life
of assets due to the availability of suitable replacements.  Automotive parts and third party labour cost continues to
increase.
(170) (241) 142%
Income: There is an over-recovery of £0.144m in bus transport income and an over-recovery of £0.121m in hire of pool
vehicle income which will support overspends in repairs and maintenance as end of life vehicles in pool are being retained
for longer, offset with a previously reported under recovery in Enterprise Cars Income.
(44) Other minor movements.
It is requested to earmark £0.274m in view of current global events to help address fuel cost pressures in 2026/27.
(750)
45

Page 46

Appendix 4
COMMUNITIES AND HOUSING
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Objective Summary
Annual
Budget
Projected 
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
Variance
Note
No
£000 £000 £000
Directorate and Support 262            249             (13)                (5%)
Housing and Public Protection
Building Services (2,565)        (2,622)         (57)                2% 1    
Works Scoping and Quality Assurance -                 -                  -                    0%
Property Governance -                 -                  -                    0%
Planning Services 257            112             (145)              (56%) 2    
Protective Services 2,167         2,008          (159)              (7%) 3    
Other Housing 2,790         2,501          (289)              (10%) 4    
Total for Housing and Public Protection 2,649         1,999          (650)             
Connected Communities 14,205       14,096        (109)              (1%) 5    
Net Total 17,116       16,344        (772)              (0)          
Transfer to/ (from) Earmarked Reserves 230            463             233              
Net Total 17,346       16,807        (539)             
Subjective Summary
Annual
Budget
Year End
Outturn
Annual
Variance
Adverse or
(Favourable)
%
variance
£000  £000  £000
Employee Costs 26,854       28,360        1,506            6%
Property Costs 4,603         5,129          526               11%
Supplies and Services 7,051         6,335          (716)              (10%)
Transport and Plant Costs 969            1,070          101               10%
Administration Costs 332            278             (54)                (16%)
Other Agencies & Bodies 12,527       12,531        4                   0%
Transfer Payments -                 -                  -                    0%
Other Expenditure 286            67               (219)              (77%)
Capital Financing -                 -                  -                    0%
Gross Expenditure 52,622       53,770        1,148            2%
Income (35,506)      (37,426)       (1,920)           5%
Net Expenditure 17,116       16,344        (772)              (5%)
46

Page 47

Appendix 4a
COMMUNITIES AND HOUSING
FINANCIAL PERFORMANCE 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 1 Building Services
Movement: There has been a favourable movement of £0.057m since Period 10.
10,792 (329) (3%)
Employees: an underspend in employee costs of £0.379m. This is due to vacancy management.
4,584 (570) (12%) Supplies & Services: an underspend in supplies and services of £0.570m. This is primarily as a result of an underspend in
materials due to changes in the income profile detailed below.
884 80 9% Transport: an overspend of £0.080m in transport costs primarily due to scaffolding costs linked to increased number of
factoring jobs received and some additional transport related costs.
3,287 184 6%
Third party payments: an overspend in third party payments of £0.184m. This is due to an overspend in payment to
contractors of £0.220m as a result of a carry forward of storm damage works from the previous financial year. This is partially
offset by an underspend of £0.036m in Agency costs.
(23,265) 614 -3%
Income: an under recovery in income of £0.614m. This is due to a reduction of £0.425m in voids works and £0.599m in
Projects, mainly due to a reduction in demand for replacement bathrooms and wetrooms at void stage as well as a reduction
in buybacks and the separation of communal windows from the window programme. There is also a reduction of £0.276m in
Aids & Adaptations. This is partially offset by an increase in Responsive Repairs income of £0.240m as a result of an
increase in storm damage works carried forward from last financial year partially offset by a reduction in other responsive
repairs and a 5% productivity efficiency. There is also an increase of £0.358m in Planned repairs due to increased timber and
damp works and an additional £0.096m in income mainly due to additional Estates Based Regeneration Programme fencing
works.
(36) Other minor movements
(57)
Note 2 Planning Services
Movement: There has been a favourable movement of (£0.031m) since Period 10, this is mainly due to underspend in Other
Supplies and Services of £0.043m.
100 (42) Supplies & Services: There is an underspend in Supplies & Services of £0.042m, mainly due to reprofiling of the  Local
Development Plan into 2026-27.
(684) (83) 12% Income: There is an over-recovery of £0.083m for additional planning fee application income.
(20) Other minor movements
It is requested to Earmark £0.043m of underspends which relate to the Local Development Plan
(145)
Note 3 Protective Services
Movement: There has been a favourable movement of (£0.043m) since P10, this is mainly due to a reduction in projected
emp costs of £0.094m due to ongoing service redesign, an increase in the over-recovery of Building Warrant income of
£0.155m and an over-recovery of income from HRA of £0.100m, offset with an overspend in Property costs of £0.314m due
to Forum fire
2,731 (189) (7%) Employee Costs:  There is an underspend of £0.180m, this is primarily due to a delayed implementation in the Scheme of
Delegation.
247 315 128% Property Costs:  There is an overspend of £0.314m, this is due to costs associated with making site safe following the Forum
fire of £0.300m and other minor variances
(1,233) (337) 27% Income: There is an over-recovery of £0.195m for additional Building Warrant income, an over-recovery of £0.100m in
income from HRA and other minor variances
52 Other minor movements
It is requested to Earmark £0.400m for further costs in relation to the demolition of the Forum Centre following the major fire
damage.
(159)
47

Page 48

Appendix 4a
Budget
£000
Projected
Variance
£000
Variance as
% of budget Section
Note 4 Other Housing
Movement: There has been a favourable movement of (£0.197m) since P10. This is mainly due to due to lower than
anticipated bad debt provision and write off costs.
3,524 (169) (5%) Employee Costs: There is an underspend of £0.169m due to vacancy management.
3,350 111 3%
Property Costs: An overspend of £0.166m mainly due to additional maintenance costs to be addressed at the void stage in
relation to homeless furnished units, partially offset by undersend in property repair costs of £0.027m and small variances
across other property costs.
55 (40) (73%) Administration Costs: Underspend due to lower staff training costs of £0.018m and legal expenses of £0.018m.
286 (220) (77%) Other Expenditure: underspend of £0.220m due to lower than anticipated bad debt provision and write off costs.
(7,016) 61 (1%) Income: There is an under-recovery mainly due to temporary furnished accomodation and hostel rents.
(32) Other minor movements
(289)
Note 5 Connected Communities
Movement: There has been favourable movement of (£0.261m) since P10.  This is due to a favourable movement of
£0.119m in property costs following less than anticipated costs in relation to Storm Eowyn and service management of
budget lines to offset the impact of revised programming of implementation of the libraries 20% reduction efficiencies target.
7,508 (5) (0%)
Employee Costs: There is a projected overspend of £0.098m related to the revised programming of implementation of the
approved saving for the libraries 20% reduction efficiencies target with work ongoing as part of the Land and Property review.
This is offset by management of other lines to reduce the impact, including an underspend of £0.103m across the service
primarily due to vacancy management.
767 66 9% Property Costs: An overspend of £0.106m due to storm damage repairs at Eglinton Country Park offset against an
underspend of £0.045m in library fixtures and fittings.
890 (70) (8%) Supplies and Services: There was an underspend of £0.070m primarily due to reduced spend within libraries.
(2,205) (95) 4% Income: There was an over recovery of Harbour Arts Centre income of £0.049m and Arran Outdoor income of £0.044m.
(5) Other minor movements.
It is requested that we earmark the Holiday Playschemes and Activites budget of £0.020m as part of delivery of a programme
of activities in summer 2026.
(109)
48

Page 49

Appendix 5
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2025/26
REPORT FOR THE 12 MONTHS TO 31 MARCH 2026
Objective Summary Annual Budget Final Outturn
Annual
Variance
Adverse or
(Favourable) % Variance Note No
£000 £000 £000
Strathclyde Passenger Transport 2,261 2,254 (7) 0%
SPT Concessionary Fares 291 291 - 0%
Ayrshire Joint Valuation Board 1,002 1,002 - 0%
3,554 3,547 (7) 0% 1               
Other Corporate Costs
Pension Costs 2,157 2,157 - 0%
Central Telephones 133 133 - 0%
Other Corporate Items (incl Transformation Costs, Bad
Debt Provision, External Audit fees and other centrally
held funding.)
7,509 1,024 (6,485)              -86% 2               
Insurance Account -1033 73 1,106               -107% 3               
Housing Benefit 3,651 3,847 196 5% 4               
-
Net Total 15,971 10,781 (5,190)              (32%)
Transfer to/ (from) Earmarked Reserves 139 3,496 3,357              
Net Total 16,110 14,277 (1,833) (11%)
49

Page 50

Appendix 5a
OTHER CORPORATE ITEMS
BUDGETARY CONTROL 2025/26
REPORT FOR THE 12 MONTHS TO 31 MARCH 2026
Budget
£000
Outturn
Variance
£000
Variance as
% of budget Section
Note 1 Joint Boards
No signficant movements since P10
3,554             (7) 0% Projected underspend of (£0.008m) due tp confirmation of annual requisitions and applicable refunds.
(7)                 
Note 2 Other Corporate Items
There has been an favourable movement of £6.485m since P10 primarily related to centrally held inflationary and othe budget
pressures not required in year.
7,268             (6,244)          (86%) An underspend of £6.485m in relation to centrally held inflationary and other budget pressures not required to be drawndown in
year.
(6,244)
Note 3 Insurance
There has been an adverse movement of £1.106m since P10 as a result of year end allocations of Insurance premiums and Excesses
(1,033)            1,106           -107% An overspend on insurance reflecting high level of excesses largely relating to recent storm damages.
1,106          
Note 4 Housing benefit
There has been a favourable movement of (£0.094m) since Period 10 in relation to the year end Housing Benefit submission to the
DWP.
3,651 196               5% Overspend of £0.040m due to the provision of Housing Benefits, reduced Bad Debt Provisions and additional overpayment recovery
196
50

Page 51

Appendix 6
MISCELLANEOUS ITEMS
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS TO 31 MARCH 2026
Objective Summary
Annual
Budget
Projected
Outturn
Annual
Variance
Adverse or
(Favourable) % variance Note No
£000 £000 £000
Financing Charges 13,751 13,751 - -
Contribution to Loans Fund Reserve 10,187 10,187 - -
Scottish Government Funding (394,613) (394,637) (24) 0%
Council Tax (71,939) (72,984) (1,045) 1% 1
Use of Earmarked Funds (8,766) (8,766) - -
Net Total (451,380) (452,449) (1,069) 0%
Transfer toEarmarked Reserves 1,500 1,500                   2
Net Total (451,380) (450,949) 431 (0%)
Note 2 Transfer to Earmarked Reserves
In view of the current conflict in the middle east and the anticipated inflationary impacts, the Bank of England
forecast for interest rates now reflects an increase from the current base rate of 3.75% up to potentially 5.25%
during 2026/27. In order to address the impact this will have on borrowing costs through 2026/27, it is requested
that £1.500m is earmarked and transferred to the Loans Fund reserve. 
The projected over recovery reflects growth in the Council Tax base from additional new builds, properties
previously registered as self-catering holiday units for NDR purposes that have come onto the Council tax register,
and the impact of the application of 100% premium on Council tax for second homes which has exceeded original
financial planning assumptions.
Note 1 Council Tax
There has been a favourable movement of £1.045m since P10 due to updated Council tax projections.
51

Page 52

Appendix 7
HOUSING REVENUE ACCOUNT
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Budget P12 outturn
Year End
variance
%
Variance Note No
£  £  £
Employee Costs 5,294 5,294 0 0%
Property Costs
Responsive Repairs 7,406 6,714 (692) (9%)
Void Repairs 4,656 4,348 (309) (7%)
Planned and Cyclical Maintenance 6,047 6,197 150 2%
Aids and Adaptions 1,792 1,342 (450) (25%)
Other property costs 5,726 5,935 209 4%
Total for Property Costs 25,627 24,536 (1,092) (4%) 1
Supplies & Services 2,145 2,130 (15) (1%)
Transport Costs 16 15 (1) (6%)
Administration Costs 2,114 1,902 (211) (10%) 2
Third Party Payments 3,832 3,771 (61) (2%) 3
Transfer Payments 177 124 (53) (30%) 4
Other Expenditure 550 948 398 72% 5
Capital Financing Costs 26,270 23,834 (2,437) (9%) 6
Gross Expenditure 66,026 62,555 (3,472) (5%)
Income
Council House Rents (62,592) (62,740) (147) 0%
Other Rents (541) (358) 183 (34%)
Recharges (1,212) (1,505) (292) 24%
Other Income (959) (1,174) (214) 22%
Transfer from HRA Balances (722) (722) 0 0%
Total Income (66,026) (66,497) (470) 1% 7
Net Expenditure (0) (3,942)           (3,942)          
52

Page 53

Appendix 7a
HRA
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
Budget
£000
Variance
£000 Variance as % of budget
Note 1
25,627 (1,092) -4%
(1,092)
Note 2
2,114 (211) -10%
(211)
Note 3
3,832 (61) -2%
(61)
Note 4
177 (53) -30%
(53)
Note 5
550 398 72%
398
Note 6
26,270 (2,437) -9%
(2,437)
Note 7
(66,026) (470) 0.7%
(470)
An over-recovery in income of £0.469m due to an over-recovery of £0.147m in Council House Rents, £0.292m in
Recharges primarily due to insurance recoveries and £0.214m in other income in relation to additional grants. This is
partially offset by an under-recovery of £0.184m in Other Rents as result of rent refunds and ex tenant arrears.
Income
Movement: There has been a favourable movement of £0.306m since Period 10.
Capital Financing Costs
Movement: there has been a favourable movement of £0.065m since Period 10.
An underspend of £2.437m in capital financing costs which reflects a continuing strategy to delay new external borrowing
by utilising cash balances, resulting in savings on external interest costs, changes in the profile of the capital programme
and projected investment income returns.
An underspend of £0.053m in Transfer payments due to a lower volume of disturbance allowances than anticipated when
the budget was set.
Other Expenditure
Movement: there has been an adverse movement of £0.398m since Period 10.
An overspend of £0.398m in Other Expenditure due to a review of the level/ methodology for calculation of the bad debt
provision.
Movement: there has been a favourable movement of £0.122m since Period 10.
An underspend of £0.061m in Third party payments due to an underspend in internal recharges.
Transfer Payments
Movement: there has been a favourable movement of £0.053m since Period 10.
Administration costs
Movement: there has been a favourable movement of £0.207m since Period 10.
An underspend of £0.211m in Administration costs. This is primarily due to lower than anticipated expenditure on external
legal fees (£0.103m), central recharges (£0.053m) and insurances (£0.025m).
Third Party Payments
Section
Property Costs
Movement: there has been a favourable movement of £1.250m since period 10. This is due to favourable movements of
£0.191m in Aids and Adaptations, £0.024m in Responsive Repairs, £0.276m in Void Repairs, £0.466m in Planned and
Cyclical Maintenance, and £0.293 in Other Property costs
An underspend of £1.092m in Property costs. This is due to an underspend of £0.692m in Responsive Repairs, primarily
as a result of an underspend of £0.162m in Emergency Repairs, £0.436m in Planned Repairs and £0.177m in RTR, an
underspend in Void Repairs of £0.309m and £0.450m in Aids & Adaptations. An element of the Voids and Aids and
Adaptations underspends, in particular, are attributable to the ongoing Housing Transformation Programme. These
underspends are partially offset by an overspend of £0.150m in Planned and Cyclical Maintenance and £0.209m in other
Property costs due to void rent loss.
53

Page 54

Appendix 7a
HRA
BUDGETARY CONTROL 2025/26
REPORT FOR THE TWELVE MONTHS ENDED 31 MARCH 2026
B/fwd from
2024/25
Transfer to /
from
Reserves
Use of
Earmarked
Sums
Earmarking of in
year surplus
Funding of
Capital Projects Reallocation
Balance at
31/03/26
£m £m £m £m £m £m
13.213 3.942 (0.227) 16.928
5.000 (0.495) 4.505
2.000 (0.213) 1.787
Unearmarked 1.758 0.170 1.928
0.170 (0.170) -
22.141 - - 3.729 (0.722) - 25.148
Housing Services Transformation Programme
Tenant led budget
Council House Building Fund
Sustainability Fund
HRA reserves and balances
54

Page 55

Appendix 8
Place
Employability - Employee Costs T 0.405
Employability - Income T 0.245
Employability - Transport Costs T 0.004
Employability - Third Party Payments T -0.612
Employability - Supplies and Services T -0.022
Employability - Admin Costs T -0.020
Roads - Employee Costs T -0.027
Roads - Supplies & Services T -0.073
Roads - Third Party Payments T 0.376
Roads - Income T -0.276
0.000
Perm (P) /
Temp(T)
Virement £m
Directorate
Total £m
Budget Management - 31 March 2026
Virement/Budget Adjustment Requests
2025/26
55

Page 56

OFFICIAL INFORMATION
OFFICIAL INFORMATION
Cabinet
2 June 2026
At a Meeting of the Cabinet of North Ayrshire Council at 2.30 p.m. involving a
combination of participation by remote electronic means and physical attendance within
the Council Chambers, Irvine
Present (Physical Participation)
Tony Gurney, Christina Larsen, Eleanor Collier, Alan Hill, Margaret Johnson, and for
consideration of Education Authority Business Elizabeth Turbet and Jacqui MacKenzie.
Present (Remote Participation)
Chloé Robertson.
In Attendance
C. Hatton, Chief Executive; S. Anson, Executive Director, A. McClelland, Head of
Service and L. Kayes, Policy Officer (Child Poverty); R. McCutcheon, Executive
Director, L. Cree, Head of Service (Sustainability, Transport and Corporate Property), L.
Kirk, Director (Regional Economy), D. McDowall, Head of Service (Ayrshire Growth
Deal) and S. Baird, Senior Officer (Islands) (Place); D. Hammond, Executive Director, Y.
Baulk, Head of Service (Housing and Public Protection), F. Ellis, Senior Manager
(Housing Strategy & Development), L. Forsyth, Senior Manager (Information and
Culture), J. Greenlees, Senior Manager (Connected Communities) and S. McKenzie,
Senior Manager (Protective Services) (Communities and Housing); C. Cameron,
Director (Health and Social Care Partnership); M. Boyd, Head of Service (Finance); F.
Walker, Head of Service (People & ICT); R. Lynch, Senior Manager (Legal Services), J.
Hutcheson, Senior Communications Officer (Media and Internal Communications) and
C. Stewart, Committee Services Officer (Democratic Services) (Corporate Services).
Chair
Tony Gurney in the Chair.
1. Declarations of Interest
There were no declarations of interest by Members in terms of Standing Order 11 and
Section 5 of the Code of Conduct for Councillors.
2. Minutes
The Minutes of the Meeting of the Cabinet held on 28 April 2026 were confirmed and
the Minutes signed in accordance with Paragraph 7 (1) of Schedule 7 of the Local
Government (Scotland) Act 1973.
3. Planned temporary closure of educational provisions
Submitted a report by the Executive Director (Education) outlining a standardised
procedure in connection with the planned temporary closure of educational provisions,
compliant with updated Scottish Government Guidance, attached at Appendix 1 to the
report.
56

Page 57

OFFICIAL INFORMATION
OFFICIAL INFORMATION
Officers responded to Members’ questions and the Cabinet agreed (a) to note the
decisions taken, which resulted in the temporary closure of two early years’ classes for
session 2026-27; (b) to approve the adoption of the proposed policy for future
temporary closures, in line with updated Scottish Government Guidance subject to the
addition of “trade unions” in Section 3.2 of the policy and (c) to the submission of an
annual report to Cabinet summarising any proposed temporary closures for future
sessions.
4. Review of ELC Sustainable Rates for Funded Providers
Submitted a report by the Executive Director (Education) seeking approval from Cabinet
to increase the sustainable rate of payment to funded providers of early learning and
childcare (ELC) in North Ayrshire who are contracted by the Council to deliver funded
ELC to eligible 2-5-year-olds. 
Officers responded to Members’ questions and the Cabinet agreed (a) an increase of
6.2% in the current hourly rate paid by the Council to funded providers, backdated to 1
April 2026; (b) to an increase to all funded providers (including childminders) in the
amount paid per meal to £3.22, and for this to be backdated to 1 April 2026; and (c) to
receive a further report at the time of the next annual review of the sustainable rate for
funded providers.
5. School Leavers’ Attainment and Achievement 2025
Submitted a report by the Executive Director (Education) on the overall performance of
the 2024-25 cohort of North Ayrshire Council school leavers. The glossary of key terms
used in the report was attached at Appendix 1.
Officers responded to Members’ questions and the Cabinet agreed to (a) note the
content of the report, including the achievements of school leavers in qualifications in
2025; and (b) note the measures being taken to make further improvements to
attainment and achievement levels across NAC Secondary schools.
6. Care Experienced School Leavers’ Attainment and Achievement2024-25
Submitted a report by the Executive Director (Education) on the overall performance of
the 2024-25 cohort of care experienced school leavers in North Ayrshire. The glossary
of key terms used in the report was attached at Appendix 1.
Officers responded to Members’ questions and the Cabinet agreed (a) to note the
content of the report, including the achievements of care experienced school leavers in
qualifications in 2025; and (b) to note the continued focus on improving outcomes for
care experienced learners in North Ayrshire.
7. School Holiday Calendar – Academic Session 2027-28
Submitted a report by the Executive Director (Education) informing Cabinet of changes
to the school holiday calendar from academic session 2027-28, attached at Appendix 1
to the report. It was noted that there had been a correction, in the version of the
calendar that had been issued, and the revised calendar had been uploaded to the
Council’s website.
57

Page 58

OFFICIAL INFORMATION
OFFICIAL INFORMATION
The Cabinet agreed (a) to note the significant level of engagement and consultation
with key stakeholders; and (b) to note the resultant agreed changes to the school
holiday calendar, to be implemented from session 2027-28 onwards.
8. Child Poverty Action Plan Progress Report 2025-26
Submitted a report by the Executive Director (Education) requesting approval of the
Child Poverty Action Plan Progress Report 2025-26, attached at Appendix 1 to the
report.
Officers responded to Members’ questions and the Cabinet agreed to publication of
the Child Poverty Action Plan Progress Report 2025-26 provided at Appendix 1 to the
report and its submission to the Scottish Government. 
9. Children’s Services Performance Report 2025/26
Submitted a report by the Director (HSCP) seeking approval for the North Ayrshire
Children’s Services Plan Performance Report 2025/26. The Children’s Services Plan
Action Update 2025-26 and the Children’s Services Plan Performance Indicators 2025-
26 were attached at Appendices 1 and 2, respectively, to the report.
The Cabinet agreed (a) to approve the North Ayrshire Children’s Services Plan
Performance Report 2024/26; and (b) to note the update in relation to the new Children
and Families Plan 2026-2029.
The following item is subject to the call-in procedure per the Council's Scheme of
Administration and will be considered at a Special meeting of Audit & Scrutiny
Committee.
10. Revenue Budget 2025/26: Financial Performance to 31 March 2026
Submitted a report by the Head of Finance advising Cabinet of the financial
performance for the Council for 2025/26.
Officers responded to Members’ questions and Councillor Larsen, seconded by
Councillor Gurney, moved as follows:
“That the Cabinet supports the recommendations set out in the report, subject to the
amendment below:
Approve subject to the movement of £1.496m of underspend to the 26/27 revenue
budget. These funds to be used to create an Our Places, Our Communities fund
designed to benefit all North Ayrshire communities. The administration will bring details
of this fund to council on the 24th of June for debate and approval.”
There being no amendment, the motion was declared carried.
Accordingly, the Cabinet agreed as follows:
58

Page 59

OFFICIAL INFORMATION
OFFICIAL INFORMATION
To (a) note (i) the information and financial outturn position outlined in the report; (ii) the
financial performance for the Health and Social Care Partnership highlighted at 2.5 of
the report; and (b) approve (i) the earmarking of £7.691m identified at 2.4 of the report
to meet future year commitments in accordance with funding requirements; and (ii) the
virements detailed in Appendix 8 to the report.
Approve subject to the movement of £1.496m of underspend to the 26/27 revenue
budget. These funds to be used to create an Our Places, Our Communities fund
designed to benefit all North Ayrshire communities. The administration will bring details
of this fund to council on the 24th of June for debate and approval.
11. Capital Programme Performance to 31 March 2026
Submitted a report by the Head of Finance advising Cabinet of progress in delivering
the Capital Investment Programme 2025/26.
Officers responded to Members’ questions and the Cabinet agreed (a) to approve the
virement proposal noted within the HRA programme detailed in Appendix 2 to the
report; (b) note (i) the revisions to budgets outlined in the report; (ii) the General
Services and HRA revised budgets at 31 March 2026; and (iii) the net expenditure to 31
March 2026.
12. Community Asset Transfer – Blacklands Hall, Kilwinning
Submitted a report by the Executive Director (Communities and Housing) seeking
approval for the transfer of ownership of Blacklands Hall (and adjacent land), Abbots
Avenue, Kilwinning to the Kilwinning Community Shed. The location plan was attached
at Appendix 1 to the report.
Officers responded to Members’ questions and Cabinet agreed (a) to the asset transfer
of Blacklands Hall and the adjacent land from North Ayrshire Council to the Kilwinning
Community Shed; (b) to approve the recommended terms of transfer on this occasion at
5% of the property valuation of £85,000 (totalling £4,250); and (c) to authorise officers to
conclude the associated legal and community asset transfer processes for Blacklands
Hall and adjacent land.
13. Community Asset Transfer – Auld Dirrans Resource Centre, Kilwinning
Submitted a report by the Executive Director (Communities and Housing) seeking
approval for the transfer of ownership of Auld Dirrans Resource Centre, 70 Dirrans
Terrace, Kilwinning to Irvine Elite Boxing Club. It was noted that a revised copy of the
location plan, attached at Appendix 1 to the report, had been uploaded to the Council’s
website showing the correct location.
Officers responded to Members’ questions and Cabinet agreed (a) to the asset transfer
of Auld Dirrans Resource Centre from North Ayrshire Council to Irvine Elite Boxing Club;
(b) to approve the recommended terms of transfer on this occasion at 5% of the
property valuation of £85,000 (totalling £4,250); and (c) to authorise officers to conclude
the associated legal and community asset transfer processes for Auld Dirrans Resource
Centre.
59

Page 60

OFFICIAL INFORMATION
OFFICIAL INFORMATION
14. Proposals for Community Investment Fund (CIF) Expenditure
Submitted a report by the Executive Director (Communities and Housing) to determine
applications by Locality Partnerships to allocate CIF funding to proposed projects. The
application from Dalry Community Sports Club was attached at Appendix 1 to the report.
Officers responded to Members’ questions and the Cabinet (a) reviewed the application
from Garnock Valley Locality Partnership in line with CIF criteria; and (b) agreed to
approve the CIF application in relation to Dalry Community Sports Club (Appendix 1 to
the report).
15. Use of Animals at Public Events
Submitted a report by the Executive Director (Communities and Housing) seeking
Cabinet approval of Guidelines and Policy relating to the use of animals at public
events, attached at Appendix 1 to the report.
The Cabinet agreed to approve the Guidelines and Policy relating to the use of animals
at public events detailed in Appendix 1 to the report.
The following item is subject to the call-in procedure per the Council's Scheme of
Administration and will be considered at a Special meeting of Audit & Scrutiny
Committee.
16. North Ayrshire Housing Acquisition Strategy
Submitted a report by the Executive Director (Communities and Housing) seeking
Cabinet approval of the proposed Housing Acquisition Strategy 2026-2031, attached at
Appendix 1 to the report.
Officers responded to Members’ questions and Cabinet agreed to approve the proposed
North Ayrshire Housing Acquisition Strategy detailed in Appendix 1 to the report.
The following item is subject to the call-in procedure per the Council's Scheme of
Administration and will be considered at a Special meeting of Audit & Scrutiny
Committee.
17. Ardrossan Campus - Project Update
Submitted a report by the Executive Director (Place) providing Cabinet with an update
on the current progress of the Ardrossan Campus project, including current projections
in relation to costs and programme.
Officers responded to Members’ questions and Cabinet agreed (a) to note the content of
this report, including the current progress of work on site; (b) to note the revised project
completion date of 26 May 2028, with anticipated occupation from August 2028; and (c)
to note the additional estimated cost of £9.97 million (8.74%) associated with
addressing the contamination will be met from approved capital flexibility funding.
60

Page 61

OFFICIAL INFORMATION
OFFICIAL INFORMATION
18. Ayrshire Growth Deal: International Marine Science and Environment
Progress (IMSE) Update
Submitted a report by the Executive Director (Place) on progress on the International
Marine Science and Environment project and seeking approval for the strategic direction
and to note the development of a Collaboration Agreement with partners Field Studies
Council and Community of Arran Seabed Trust to support the further development of
the project.
The Cabinet agreed to (a) note the progress to date and approves the strategic direction
for the International Marine Science and Environment project; (b) notes the
development of a Collaboration Agreement with the Field Studies Council and the
Community of Arran Seabed Trust to progress the project and develop the full business
case; and (c) notes the progression of the change management requirements and
Outline Business Case for the project, informed by feedback from the Scottish and UK
Governments.
19. Flexible Advanced Manufacturing Space, i3 Irvine: Phase 2, Full Business
Case
Submitted a report by the Executive Director (Place) seeking endorsement of the Full
Business Case for Phase 2 of the Flexible Advanced Manufacturing Space Project at i3,
Irvine, attached at Appendix 1 to the report.
The Cabinet agreed (a) to endorse the Full Business Case for Phase 2 of the Flexible
Advanced Manufacturing Space project at i3, Irvine, subject to feedback from Scottish
and UK Governments and the successful outcome of the tender process; (b) that
authority be delegated to the Executive Director (Place) to update the Full Business
Case to reflect the feedback and outcome of the tender process; and (c) to approve the
submission of the Full Business Case to the Ayrshire Economic Joint Committee. 
20. National Islands Plan and North Ayrshire Islands Programme Update
Submitted a report by the Executive Director (Place) on the North Ayrshire Islands
Programme and the new National Islands Plan and outlining proposed next steps. The
North Ayrshire Islands Programme Achievements 2022 to 2025 was attached at
Appendix 1 to the report.
Officers responded to Members’ questions and Cabinet agreed (a) to note (i) the
progress of the North Ayrshire Islands Programme and achievements to date, (ii) the 
publication of the National Islands Plan 2026 to 2031 and associated investment in
2026/27; (b) to the refresh and refinement of the current Local Island Plans and
associated delivery plans and their intended reporting; and (c) to the finalisation and
submission of the proposed funding applications to the Scottish Government’s Islands
Programme.
61

Page 62

OFFICIAL INFORMATION
OFFICIAL INFORMATION
21. Regeneration Delivery Plan Funding Proposals Update 2026/27
Submit a report by the Executive Director (Place) on progress of the Regeneration
Delivery Plan and seeking approval for proposed funding allocations in 2026/27. The
Regeneration Funding Proposals and the Project Updates were set out in Appendices 1
and 2, respectively, to the report.
The Cabinet agreed (a) to approve (i) the Regeneration funding proposals as detailed at
Appendix 1 to the report; and (ii) the proposed delegated authority changes following
service restructure; (b) to note (i) the progress made on the implementation of the
Regeneration Delivery Plan; and (ii) the update on previously secured or applied for
funds provided at Appendix 2 to the report; and (c) that delegated authority be granted
to the Executive Director (Housing and Communities) to agree changes to the funding
allocations in Appendices 1 and 2 in the report, in consultation with the Portfolio Lead as
required.
22. Fleet Decarbonisation
Submitted a report by the Executive Director (Place) on progress made to date with
decarbonisation of the Council Fleet and providing details of the further proposed
decarbonisation-first approach work going forward.
Officers responded to Members’ questions and Cabinet agreed (a) the decarbonisation-
first approach for fleet replacement outlined at paragraph 2.17 of the report; (b) note (i)
the progress made to date in decarbonising the fleet, and against the actions set out in
the May 2023 Cabinet paper, and (ii) that the Council’s current fleet decarbonisation
actions would continue to evolve to reflect the Scottish Government’s refreshed Climate
Change Plan 2026-2040 and the awaited public sector fleet decarbonisation action plan.
23. Urgent Items
There were no urgent items.
The meeting ended at 4.45 p.m.
The full meeting proceedings can be viewed at
https://north-ayrshire.public-i.tv/core/portal/home
62

Page 63

Revenue Budget 2025/26: Financial Performance to 31 March 2026
Briefing Note:-
Mark Boyd (Head of Service – Finance)
The Revenue Budget report to the 31 March 2026 was presented at Cabinet on 2 June
2026 and outlined the final reported position for the 2025/26 financial year. This position
will be reflected in the Council’s Unaudited accounts due for presentation at Council on
the 24 June 2026.
The General Fund reported a net in-year underspend of £2.014m for the year. This is the
net position after transferring resources to and from earmarked reserves. This is an
improvement of £0.334m from that reported at period 10. This underspend will be
added to the General Fund Unearmarked reserves which would increase the available
balance to 2.3% of the General Services Revenue Budget which is within the
recommended range of 2% to 4%. The level of General Fund Unearmarked Reserves at
31 March 2026 is £11.195m. This is £1.496m above the 2% lowest Reserves threshold of
£9.699m. Whilst the current level of Unearmarked Reserves remains at the lower end of
good practice, this still reflects a prudent position to help address areas of significant
risk to the Council through 2026/27, most notably through the financial performance of
the HSCP, this being set within the context of the savings the HSCP require to deliver to
remain within available resources during 2026/27.
The report also references the improved position of the Health and Social Care
Partnership (HSCP) for the year 2025/26 i.e. the final outturn for the Council Services
element of the HSCP is a net underspend of £0.459m after earmarking resources. This
is an improvement of £1.941m from that reported at period 10. The £0.459m will be
added to the HSCP’s Unearmarked Reserves. This will help address pressures through
2026/27, however, as referenced above the HSCP requires to make significant savings
through 2026/27.
An Amendment was made to this report as follows:-
That the Cabinet supports the recommendations set out in the report, subject to the
amendment below:-
“Approve subject to the movement of £1.496m of underspend to the 26/27 revenue
budget. These funds to be used to create an Our Places, Our Communities fund
designed to benefit all North Ayrshire communities. The administration will bring details
of this fund to council on the 24th of June for debate and approval.”
The financial effect of this Amendment is to utilise, in 2026/27, the level of
Unearmarked reserves, being the difference between 2.3% reserves and 2%
Unearmarked reserves for the stated purpose. Whilst this is still within the Council’s
reserves policy, it is at the lowest end. Further, as the utilisation of reserves relates to
Appendix 2
63

Page 64

2026/27, this does not change the Council’s reported out-turn or reserves position at 31
March 2026, therefore the Council’s unaudited Accounts are unaffected and will be
submitted to Council for approval on 24 June 2026 as planned.   
64

Page 65

Audit and Scrutiny Committee
15 June 2026 
At a Special Meeting of the Audit and Scrutiny Committee of North Ayrshire Council
at 10.00 a.m. involving participation by remote electronic means and physical
attendance within the Council Chambers, Irvine. 
Present (Physical Participation)
John Bell, Cameron Inglis, Tom Marshall, Matthew McLean, Donald Reid, Donald L
Reid and John Sweeney. 
Present (Remote Participation)
Davina McTiernan and Shaun Macaulay. 
In Attendance 
D. Hammond, Executive Director and K. Bell, Team Manager (Housing Strategy)
(Communities and Housing); S. Anson, Executive Service (Education) M. Boyd,
Head of Service (Finance); L. Cree, Head of Service (Sustainability, Transport &
Corporate Property) (Place); A. Craig, Head of Service, C. Stewart, Committee
Services Officer, and H. Young, Senior Committee Services Office (Democratic
Services) (Corporate Services). 
Also in Attendance
Eleanor Collier, Joe Cullinane, Robert Foster, Christina Larsen, Jim Montgomerie
and Ian Murdoch. 
Chair
Councillor Bell in the Chair. 
1. Declarations of Interest 
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors. 
2.  Call In: Revenue Budget 2025/26: Financial Performance to 31 March 2026 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026
advising of the financial performance for the Council for 2025/26. The original
Cabinet report and minute from the Cabinet meeting which took place on Tuesday 2
June 2026 was attached at Appendix 1 to the report. Appendix 2 to the report
contained a briefing note provided by the Head of Finance in response to the matters
raised in the call-in request form. 
The Cabinet, on 2 June 2026, considered a report on the financial performance for
Council 2025/26. Cabinet amended the recommendation to the report by determining
to allocate £1.496m of underspend to the 26/27 revenue budget with the funds to be
used to create an Our Places, Our Communities fund designed to benefit all North
65

Page 66

Ayrshire communities with details of the fund being brought to council on the 24th of
June for debate and approval. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“In passing its budget, the Council set Council Tax bands at a level required to fund
its expenditure requirements, including prioritising investment in areas such as
education and roads. 
The £1.496million underspend should therefore not be spent on another of the
administrations pet projects, particularly when the evidence of the last four years
shows that these pots of money are not used in a timeous manner. 
Instead, the underspend should be returned to council taxpayers.” 
Desired Outcome 
“That the £1.496million allocated to an ‘Our Places, Our Communities fund’ be re-
allocated to provide a Council Tax rebate, reflecting the fact that our expenditure
requirements for 2026/27 have already been funded.  
Although this outcome proposes a Council Tax rebate, we acknowledge officers'
advice that as matters relating to setting Council Tax levels are reserved to Council
and that for this outcome to be implemented it will require a decision of Full Council,
including the suspension of 15.5 and 25.1 of Standing Orders Relating to Meetings
and Proceedings of the Council, as Council Tax was set within the last six months.
The Audit & Scrutiny Committee is asked to accept the call in and recommend that
the matter is referred by Cabinet to Council for further consideration and
determination.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request and
was heard in response to Members’ questions. 
The Chair then invited Councillor Larsen, as the Cabinet Member for Finance, to
address the meeting. Councillor Larsen explained the reasoning for the Cabinet
decision and referred to a briefing note from the Head of Finance provided at
Appendix 2 to the report. She was also heard in answer to Members’ questions. 
The Head of Finance was then heard in relation to the report presented to Cabinet
and on issues raised by the call-in. 
Councillors Cullinane and Larsen were heard in summing up. 
66

Page 67

Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration, with the recommendation that the matter is referred to
Council to determine the use of the underspend and that Council suspends Standing
Orders to consider the proposal regarding a Council Tax rebate. 
As an amendment, Councillor Macaulay, seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
There followed questions, debate and summing up on the motion and amendment
presented for consideration. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Macaulay and McTiernan (2) and for the motion, Councillors Bell, D.
Reid, Inglis, Marshall, McLean, D.L Reid and Sweeney (7). The motion was declared
carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b) that the
matter be referred to Cabinet for further consideration, with the recommendation that
the matter is referred to Council to determine the use of the underspend and that
Council suspends Standing Orders to consider the proposal regarding a Council Tax
rebate. 
3.  Call In: North Ayrshire Housing Acquisition Strategy 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 on
the proposed Housing Acquisition Strategy 2026- 2031. The original Cabinet report
was attached at Appendix 1 to the report. Appendix 2 to the report contained a
briefing note provided by the Executive Director (Communities and Housing) in
response to the matters raised in the call-in request form. 
The Cabinet, on 2 June 2026, considered a report on the proposed Housing
Acquisition Strategy 2026-2031. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“It is wrong to suggest this policy will have no impact on the Council’s Community
Wealth Building (CWB) strategy. A key component of the strategy is to increase
procurement spend with North Ayrshire, and Ayrshire, businesses creating economic
and socio benefits from investing in the local economy. The fact that Ayrshire based
companies have won our council house building contracts has made a significant
contribution to us achieving the initial procurement targets set out in the first CWB
strategy published in 2020. 
This policy is the opposite of this approach. It will see a significant proportion of our
investment in Council housing, the majority of which comes from the Council with the
67

Page 68

rest from Holyrood, be transferred to private housing developers, many of which are
large national developers. It will see that investment extracted from the Ayrshire
economy. 
We remain as committed to Community Wealth Building as were in 2020. We
therefore reject this policy.” 
Desired Outcome 
“That the Council reaffirms its commitment to Community Wealth Building by
rejecting this policy and redoubling our efforts to ensure that Ayrshire based
companies can bid for, and win, the contracts to build the next generation of Council
houses in North Ayrshire.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request. 
In the absence of Councillor Hill, as the Cabinet Member for Communities, Housing
and the Islands, the Chair then invited Councillor Collier to address the meeting. She
was also heard in answer to Members’ questions. 
The Executive Director and the Team Manager (Housing Strategy) (Communities
and Housing) were heard in response to Members’ questions. 
Councillors Cullinane and Collier were heard in summing up. 
Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration with the recommendation that the policy be rejected. 
As an amendment, Councillor Macaulay seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Inglis, Macaulay, Marshall, McTiernan and D.L Reid (5) and for the
motion, Councillors Bell, D. Reid. McLean and Sweeney (4) and amendment was
declared carried. 
Accordingly, the Committee agreed not to support the call-in request and that the
decision of Cabinet should stand. 
68

Page 69

4. Call In: Ardrossan Campus Project Update 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 to
note the current progress of the Ardrossan Campus project, including current
projections in relation to costs and programme. The original Cabinet report was
attached at Appendix 1 to the report. 
The Cabinet, on 2 June 2026, considered an update report on the current progress
of the Ardrossan Campus project, including current projections in relation to costs
and programme. 
Subsequently, a call-in request was received from Councillors Stalker, Murdoch and
Stephen in the following terms:-   
Reason for Call-In 
“This decision is being called in because there are some real concerns about how
the Ardrossan Campus project is progressing. The report shows a significant cost
increase of around £10 million, along with delays pushing completion back to May
2028. 
There are also questions about how risks have been handled, especially around
ground contamination and the challenges of building on a contaminated site. It’s not
clear if these issues were fully understood early on, or if more could have been done
to avoid the impact they have had. On top of that, using additional capital funding to
cover the extra costs raises concerns about what this means for and the overall
budget of the campus and what more flexibility funding will be made available in
future budgets. 
Overall, this call-in is about getting reassurance that the project is still under control,
that risks are being properly managed, and that it continues to represent good value
for the Council and local communities.” 
Desired Outcome 
“To provide assurance on and seek greater information on the cost, programme, risk
management, governance and wider capital implications of the Ardrossan Campus
project, ensuring it remains deliverable, financially sustainable and represents value
for money.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Murdoch addressed the Committee in support of the call-in request and
was also heard in response to Members’ questions. 
As a point of clarification it was confirmed that the decision of Cabinet was to note
the update provided in the report presented. 
69

Page 70

The Chair then invited Councillor Collier, as the Cabinet Member for Green
Environment and Economy, to address the meeting. Councillor Collier explained the
reasoning for the Cabinet decision and was also heard in answer to Members’
questions. 
The Executive Director (Education) and the Head of Service (Sustainability,
Transport & Corporate Property) (Place) were heard in answer to Members’
questions. 
Councillors Cullinane and Collier were heard in summing up.  
Councillor Inglis, seconded by Councillor McLean, moved that the Committee agree
to accept the terms of the call-in request with a recommendation that a progress
report is taken to a future meeting of Council in six months for consideration. There
being no amendment the motion was declared carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b)
recommended to Cabinet that an update report is taken to a future meeting of
Council in six months. 
The meeting ended at 12.10 p.m. 
The full meeting proceedings can be viewed at
https://north-ayrshire.public-i.tv/core/portal/home 
70

Page 71

NORTH AYRSHIRE COUNCIL 
19 June 2026 
Cabinet 
Title:    Ardrossan Campus Project Update 
Purpose:  To inform Cabinet of the decision of the Audit & Scrutiny
Committee following a call-in of the Cabinet decision of 2 June
2026 which noted the current progress of the Ardrossan Campus
project, including current projections in relation to costs and
programme. 
Recommendation:  That Cabinet considers the decision and recommendation from
the Audit & Scrutiny Committee and determines: 
(a) whether to accept the recommendation of the Audit &
Scrutiny Committee and amend its original decision
accordingly; or 
(b) if it does not accept the recommendation, to refer the matter
to Council for final determination. 
1. Executive Summary 
1.1 At its meeting on 2 June 2026, Cabinet considered a report and noted the current
progress of the Ardrossan Campus project, including current projections in relation to
costs and programme. 
1.2 Subsequent to the decision taken by Cabinet to note the update, a call-in request was
received from Councillors Stalker, Murdoch and Stephen which was referred to the
Audit & Scrutiny Committee for consideration. 
1.3 At its meeting on 15 June 2026, the Audit and Scrutiny Committee agreed to accept
the call-in request and referred the matter back to Cabinet for further consideration
with the recommendation that a future update report is brought to Council in 6 months. 
1.4 Accordingly, Cabinet is asked to consider the decision and recommendation from the
Audit & Scrutiny Committee and determine: 
a) whether to accept the recommendation of the Audit & Scrutiny Committee and
amend its original decision accordingly; or 
b) if it does not accept the recommendation, to refer the matter to Council for final
determination.
Agenda Item 3
71

Page 72

2. Background 
2.1 The Cabinet, at its meeting on 2 June 2026, considered a report on the current
progress of the Ardrossan Campus project, including current projections in relation to
costs and programme. A copy of the original report presented to Cabinet on 2 June
2026 is attached as Appendix 1. 
2.2 Subsequently, a call-in request was received in terms of the call-in procedure set out
in the Council’s Standing Orders. The report to the Audit & Scrutiny Committee in
relation to the call-in is attached at Appendix 2. 
2.3 The Audit & Scrutiny Committee at its meeting on 15 June 2026 heard from Councillor
Murdoch in relation to the call-in. The Committee also heard from Councillor Collier,
Cabinet Member for Green Environment and Economy, in response to the call-in. The
Executive Director (Education) and the Head of Service (Sustainability, Transport &
Corporate Property) were also present to provide information on the Cabinet report
and on issues raised by the call-in received. The Committee subsequently agreed to
accept the call-in and referred the matter back to Cabinet for further consideration with
the recommendation that a future update on the progress of the Project is brought to
Council in 6 months. The Minutes of the meeting of the Audit & Scrutiny Committee
are attached at Appendix 3. 
3. Proposals 
3.1 Cabinet is recommended to consider the decision and recommendation from the Audit
& Scrutiny Committee and determine: 
a) whether to accept the recommendation of the Audit & Scrutiny Committee and
amend its original decision accordingly; or 
b) if it does not accept the recommendation, to refer the matter to Council for final
determination. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the Cabinet report attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the Cabinet report attached at
Appendix 1. 
Legal 
4.3 The legal implications are outlined in the Cabinet report attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the Cabinet report attached
at Appendix 1.
72

Page 73

Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the Cabinet report
attached at Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the Cabinet report attached at Appendix 1. 
Community Wealth Building 
4.7 The community wealth building implications are outlined in the Cabinet report attached
at Appendix 1. 
Islands Communities Impact Assessment (ICIA) 
4.8 Any ICIA implications are outlined in the Cabinet report attached at Appendix 1. 
United Nations Rights of the Child (UNCRC) 
4.9 Any UNCRC implications are outlined in the Cabinet report attached at Appendix 1. 
Consumer Duty 
4.10 Any consumer duty implications are outlined in the Cabinet report attached at
Appendix 1. 
5. Consultation 
5.1 None concerning this report. 
Aileen Craig
Head of Service (Democratic) 
For further information please contact Craig Stewart, Committee Services Officer, on 
01294 324130 or by email, craigstewart@north-ayrshire.gov.uk 
Background Papers
N/A
73

Page 74

NORTH AYRSHIRE COUNCIL
2 June 2026
Cabinet
Title: Ardrossan Campus – Project Update
Purpose: To provide Cabinet with an update on the current progress of
the Ardrossan Campus project, including current projections in
relation to costs and programme.
Recommendation: Cabinet is asked to:
1. Note the content of this report, including the current progress
of work on site.
2. Note the revised project completion date of 26 May 2028,
with anticipated occupation from August 2028.
3. Note the additional estimated cost of £9.97 million (8.74%)
associated with addressing the contamination will be met
from approved capital flexibility funding.
1. Executive Summary
1.1 The Ardrossan Coastal Quarter programme represents a transformational vision for
the area which includes the provision of new housing and commercial uses, providing
ambitious transformational regeneration of a vacant and derelict site on land within
one of North Ayrshire’s most deprived communities. A key component of this vision is
a new educational and community campus. 
1.2 The contract to construct the new Ardrossan Campus Project commenced on site in
July 2025, with the first stage focusing on the excavation of foundations and the
swimming pool tank. In September 2025, asbestos and hydrocarbon contamination
was identified during construction. Appropriate Safe Systems of Work were then
implemented by the main contractor (Morgan Sindall), with an independent review
confirming these measures to be proportionate and compliant.
1.3 The contractual and programme implications were subsequently assessed by our cost
consultant, resulting in an additional cost of £9.97 million (8.74%) and an extension of
the completion date to 26 May 2028.
1.4 The overall Campus project budget will therefore increase to £124,558,600, with the
additional funding to be met from the Council’s capital flexibility fund approved in
February 2026.
APPENDIX 1
74

Page 75

1.5 An independent external review of the enabling works has been commissioned, with
an initial assessment received and currently under consideration. 
1.6 The safe systems of work which have been required since encountering the
contamination have now ceased. Works are progressing unhindered by these
additional measures and the project has now reached a significant milestone on the
construction process as steel work is now rapidly being erected on-site. 
1.7 Stakeholder engagement will now be undertaken to communicate the revised delivery
arrangements and support appropriate mitigation of the impacts arising from the
extended programme. 
2. Background 
2.1 Two separate contracts relating to the delivery of the Ardrossan Coastal Quarter
were undertaken commencing in June 2023 and January 2024 respectively. The
purpose of these projects was to deliver a new revetment (Sea-Wall) coastal
defence, an extension of the coastal path, remediate contamination and to install
site-wide infrastructure to enable future development. 
2.2 Remediation strategy involved treating contaminated soil on location, removing
hydrocarbons, and reusing suitable treated material in the works. The strategy also
included installing 600mm stone cap across the site to provide a protective barrier as
all contamination would not be removed. The remediation was independently
monitored and verified to ensure it met all required standards. 
2.3 Subsequent to that, construction work on the new Ardrossan Campus commenced in
July 2025, with initial works focusing on the formation of foundations and excavation
of the swimming pool. 
2.4 As works progressed on site, an in accordance with the agreed methodology for
progressing the works, testing of excavated materials continued in order to ensure
all health and safety standards were maintained. In September 2025, asbestos and
hydrocarbon contamination was identified as a result of that testing. Appropriate
Safe Systems of Work were immediately implemented by the main contractor
(Morgan Sindall), with an independent review confirming these measures to be
proportionate and compliant
Programme Development
2.5 The Ardrossan Coastal Quarter site was selected in 2018-2019 as the preferred
location for the new Campus, reflecting its capacity, regeneration potential, and
alignment with the Council’s Local Development Plan priorities. The wider vision
includes residential and commercial development to support regeneration and align
with the Local Development Plan.
2.6 The “Ardrossan North Shore Development Framework”, prepared by external
consultants (Stallan Brand), was approved in April 2021 and set the strategic context
for redevelopment. Subsequently, In June 2021, the Council agreed remediation and
75

Page 76

site infrastructure works to achieve economies of scale and improve the site’s
attractiveness for future investment. 
2.7 In the prevailing market conditions, a single contract for the complete programme of
work was not considered the most deliverable option, and the chosen approach
provided a practical route to securing progress. Market feedback indicated that
including the Campus within those packages would have been less attractive to
bidders. This was reaffirmed when the subsequent Campus tender process only
attracted two bids.
2.8 Following market engagement on the enabling works tender issued in November
2021, the procurement approach was refined in response to no compliant bids being
received through the original process, with the works restructured into two packages
and successfully retendered in 2023 and 2024. 
2.9 Due to the phasing of the separate projects, the enabling works were more
advanced than the Campus design, and the revetment had to be completed first. In
the context of a volatile market, maintaining separate elements of delivery helped
support programme progress and provided a more manageable basis for pricing. 
2.10 It should be noted that the enabling works, as separate contracts with different
contractors, were not the first stage of the construction contract to deliver the
Campus. These were discrete pieces of work, intended to enable development
across the wider Ardrossan Coastal Quarter site. Although the advance enabling and
remediation works provided an appropriate and proactive route to delivery, the use
of three separate contracts meant that interface risks were recorded and remained
an inherent feature of the overall programme.
2.11 The Campus design was successfully finalised while the advance works were
progressing, with the projects coordinated to support overall delivery. Although the
advance works project was not intended to deliver Campus construction works, this
approach helped maintain progress, while market feedback confirmed that separate
contractual responsibilities remained the more practical route. 
2.12 Recognising the challenges being experienced in delivering the wider programme of
works, with a focus on ensuring the Campus could be delivered as soon as possible,
a review was conducted with the support of external consultants (Ironside Farrar) in
February 2024. This confirmed the inherent risks of brownfield remediation, buried
structures, coastal conditions and sequential working, with further contamination
assessed at that stage as an amber risk.
2.13 As Morgan Sindall had no control over the enabling works contract, it confirmed prior
to Financial Close that it would not accept contamination risk within the Campus
contract, the contract therefore acknowledged this risk and relied on the contingency
allocation to address any arising issues. 
2.14 A report was submitted to Council on 26 June 25, confirming the revised budget and
programme for the project. A number of key remaining risks were also highlighted in
the report. Included within those was the potential to discover contaminated material
76

Page 77

in the deep excavations below the remediated level, and the impact this could have
on costs and programme. 
2.15 To estimate the potential cost, prior to entering the construction contract the
assessment associated with this risk estimated that around 13,280m³ of excavation
would extend below the 3.5m remediation depth. Utilising market rates for disposal,
a potential worst case disposal exposure of £6.64m was assessed. Because overlap
between known contamination and deep excavations appeared limited, an overall £5
million contingency was considered realistic and included within the project budget. 
2.16 The Scottish Futures Trust (SFT) have worked in partnership with the Council
throughout the development phases of the project, including providing financial
support thought the Scottish Government’s Learning Estate Investment Programme.
The project allocation was increased to reflect the challenging conditions around the
delivery of the project. 
2.17 Verification reports in respect of the enabling works contract were received,
satisfying the Planning Conditions required to allow works to commence on site. 
Campus Construction Phase 
2.18 In September 2025, asbestos and hydrocarbon contamination was encountered
during deep excavations. Elected Members and the local community were
proactively informed shortly thereafter. 
2.19 As a result of this, and to ensure works could progress in a safe manner, Morgan
Sindall introduced Safe Systems of Work, including exclusion zones and specialist
controls. 
2.20 An external specialist engineering advisor independently reviewed the Safe Systems
of Work on the Council’s behalf and found them to be both proportionate and
compliant. 
2.21 Our cost consultants, Atkins Realis, have assessed the contractual impact of the
appropriate treatment of the contaminants via the safe system of work as an
additional £9.97 million. The programme impact has also resulted in an extension of
time to the contract to 26 May 2028. This has been formally confirmed through the
contractual change control process. 
2.22 This figure represents a significant betterment than the original proposal by the
contractor following robust review and challenge by the Campus project team and
external advisors. 
2.23 Addressing the contamination issue will result in the Campus project budget rising to
£124,558,600. This increase will be addressed through the Council’s capital flexibility
fund approved by Council in February 2026. 
2.24 A report by independent specialist engineers has been commissioned, with input
from the appropriate consultant teams, to ensure the reasons for the current issues
are properly understood. An initial assessment has been provided and is being
reviewed to determine the next steps. 
77

Page 78

2.25 Separate delivery of the enabling works and the Campus has also required ongoing
management of wider interface risks; however, these matters are being actively
managed through cross-service coordination to ensure that appropriate mitigation
measures are identified and allocated. 
2.26 Under the NEC4 contract, the Council’s exposure to additional cost arising from
systemic supply chain issues arising from the current conflict in the Middle East is
limited, with broader liability arising mainly where contract terms or future legislative
changes require it.
2.27 As the cost and programme implications arising from encountering contamination are
now understood, the overall construction programme has been updated, and the
Project Team will undertake stakeholder engagement to advise on the new
timetable. This engagement will include: elected members; the school community;
neighbours and the Ardrossan community; and Scottish Futures Trust. 
2.28 The negative impacts of the delay will be most keenly felt by the by the school
community being unable to access the new facility when planned and the
neighbouring properties experiencing direct disruption caused by construction
activities. 
2.29 Stakeholder engagement will recognise these negative impacts, and the project team
will continue to explore practical mitigations to the issues posed by the extended
programme. 
2.30 With the safe systems of work around contamination removal now being complete,
works are progressing unhindered by these additional measures and the project has
now reached a significant milestone on the construction process as steel work is now
rapidly being erected on-site and concrete floor slabs are being poured. 
3. Proposals 
3.1 It is proposed that Cabinet:
• Notes the content of this report, including the current progress of works on site.
• Notes the revised completion date of 26 May 2028, with anticipated occupation from
August 2028. 
• Notes the additional estimated cost of £9.97 million (8.74%) associated with
addressing the contamination will be met from approved capital flexibility and
borrowing. 
4. Implications/Socio-economic Duty 
Financial 
4.1 An additional £9.97 million (8.74%) has been identified as necessary to address the
contamination issues associated with Compensation Events relating to the
contamination as outlined in this report. This requirement will be met through the
approved capital flexibility budget agreed by Council on 25 February 2026. 
78

Page 79

It is anticipated that additional contingency funding may be required to address any
remaining risks which arise during the remainder of the construction period. 
In parallel, a further review of the Council’s Capital Investment Programme will be
undertaken covering the period 2026/27 to 2033/34, to ensure that the revised
programme remains prudent, affordable and sustainable. This review will include long-
term projections of borrowing and interest rate assumptions, assessment of
expenditure profiles, capital receipt forecasts, anticipated capital grant funding, and
the planned use of the loans fund reserve. 
Scottish Futures Trust has been approached to explore whether any additional
support may be available. However, the Scottish Government has confirmed, that in
accordance with the agreed LEIP funding principles, the inflationary risk associated
with project delays rests with the local authority. 
Human Resources 
4.2 None 
Legal 
4.3 Legal Services will be asked to comment on the report noted at item 2.24. 
Equality/Socio-economic 
4.4 The construction of the new Campus, as a key component of the wider
transformational regeneration of the Ardrossan Coastal Quarter will have significant
direct and wider socio-economic benefits. 
Climate Change and Carbon 
4.5 Ardrossan Campus has been designed to be highly energy-efficient and to meet the
LEIP in-use energy requirements of between 67-83KWh/m²/annum. The contract
design shows a predicted attainment of 71KWh/m²/annum. A sustainability
responsibility matrix has been developed and incorporated into the contractual
agreement to deliver facilities that will contribute to the Council’s climate change
priorities. 
Key Priorities 
4.6 The project supports the following Council priorities: 
Wellbeing 
• Developing appropriate skills for the local and regional economy 
• Using our assets to support wellbeing in local communities Improving educational
attainment and achievement and closing the attainment gap 
• Developing the young workforce and ensuring positive destinations for school
leavers 
• Providing lifelong learning opportunities for individuals and organisations including
digital literacy 
79

Page 80

• Improving outcomes for care-experienced young people including implementation
of The Promise 
• Ensure our places and spaces where we live, work and visit are well maintained
and accessible. 
• Support KA Leisure’s leadership of North Ayrshire’s Health and Wellbeing Alliance 
• Through the Health and Social Care Partnership Strategic Plan we will protect and
provide care and support for those in need. 
Communities and Local Democracy 
• Developing partnerships with the third and voluntary sector 
• Placemaking, including creation of locality action plans. 
• Accessible public services, both digitally and locally. 
Climate Change 
• Embedding our net-zero ambition in all democratic decision-making. 
• Reducing the carbon footprint of our estate and taking a fabric first and low carbon
energy generation approach to homes and buildings 
• Promoting new woodland creation and protecting our green spaces to provide a
natural resource for carbon sequestration. 
Community Wealth Building 
4.7 A suite of community benefits has been developed through the design and
construction phases of the project. The commitments from Morgan Sindall which are
defined in the SCAPE framework agreement have been incorporated into the
contractual requirements for the project. 
Islands Communities Impact Assessment (ICIA) 
4.8 None 
United Nations Rights of the Child (UNCRC) 
4.9 The development of the Campus fully supports these rights. 
Consumer Duty 
4.10 The project will deliver on these through the Stakeholder Reference Group and Client
Planning workstreams. 
5. Consultation 
5.1 Consultation has been undertaken with Education, Economic Development Growth &
Regeneration, and Finance. 
RUSSELL McCUTCHEON
Executive Director (Place) 
For further information please contact Laurence Cree, Head of Service Sustainability,
Transport & Corporate Property, on 01292 324514. 
80

Page 81

Background Papers
0 
81

Page 82

NORTH AYRSHIRE COUNCIL
15 June 2026                                                                                                                                                            
Audit and Scrutiny Committee
Title: Call In: Ardrossan Campus Project Update
Purpose: To allow the Committee to consider a call-in request in respect
of the decision taken by Cabinet at its meeting on Tuesday 2
June 2026 to note the current progress of the Ardrossan
Campus project, including current projections in relation to costs
and programme.
Recommendation: That the Committee considers the terms of the call-in and agrees,
or otherwise, to make a recommendation to Cabinet.
1. Executive Summary
1.1    In terms of the Scheme of Administration (Section 5), the Audit and Scrutiny Committee
has a remit to consider call-in requests and invite at least one of the Members who has
requested the reference to call-in to attend the Committee to explain the request.
1.2 This report sets out the background to a call-in request in respect of the decision
taken by Cabinet at its meeting on 2 June 2026 in relation to the report on the current
progress of the Ardrossan Campus project, including current projections in relation to
costs and programme.
2. Background
2.1 The Cabinet, at its meeting on 2 June 2026, considered a report on the current
progress of the Ardrossan Campus project, including current projections in relation to
costs and programme.
2.2 A request was received in terms of the call-in procedure set out in the Council's
Scheme of Administration and Standing Orders, that the Audit and Scrutiny
Committee examine the decision taken by the Cabinet.
2.3 The call-in request, which was signed by Councillors Stalker, Murdoch and Stephen is
in the following terms: -
Reason for call-in
“This decision is being called in because there are some real concerns about how
the Ardrossan Campus project is progressing. The report shows a significant cost
increase of around £10 million, along with delays pushing completion back to May
APPENDIX 2
82

Page 83

2028. 
There are also questions about how risks have been handled, especially around
ground contamination and the challenges of building on a contaminated site. It’s
not clear if these issues were fully understood early on, or if more could have
been done to avoid the impact they have had. On top of that, using additional
capital funding to cover the extra costs raises concerns about what this means
for and the overall budget of the campus and what more flexibility funding will be
made available in future budgets. 
Overall, this call-in is about getting reassurance that the project is still under
control, that risks are being properly managed, and that it continues to represent
good value for the Council and local communities.” 
Desired Outcome 
“To provide assurance on and seek greater information on the cost,
programme, risk management, governance and wider capital implications of the
Ardrossan Campus project, ensuring it remains deliverable, financially
sustainable and represents value for money.” 
2.4 A copy of the original report, prepared by the Executive Director of Place and
presented to Cabinet on 2 June 2026 is attached as Appendix 1 to this report. 
2.5 The call-in request is valid for consideration by the Committee. The request was
received within the appropriate timescale, it was requested by three Elected Members
and details were provided on both the reason for the call-in and the desired outcome. 
2.6 The Elected Members who have submitted the call-in will be invited to address the
Committee to explain the respective call-in request.  The appropriate Cabinet Member
will then be invited to clarify the reasons for the decision. The relevant senior officer
will also be present to provide information on the report presented to Cabinet and on
issues raised by the call-in received. The Committee will have an opportunity to ask
questions of both parties and of those officers in attendance. 
2.7 The Committee will then debate the call-in request and decide whether or not it agrees
with the decision of the Cabinet. 
2.8    The Audit and Scrutiny Committee:- 
i) decides if it agrees or not with the decision of the Cabinet; and
ii) if it does not agree with the decision, considers what alternative action the
Committee would recommend to the Cabinet. 
2.9   If the Committee supports the decision of Cabinet and does not accept the call-in, the
original decision of Cabinet remains in effect and no further procedure is required. 
2.10 If the Committee accepts the call-in, the matter is referred to Cabinet with a
recommendation. When the matter is considered by the Cabinet, the Chairperson or
another member of the Audit and Scrutiny Committee will have the right to attend the
Cabinet and speak in support of any recommendation. 
83

Page 84

2.11 In the event that Cabinet declines to accept the recommendation from the Audit and
Scrutiny Committee, the matter will be referred to Council for determination. The
decision of the Council will be final. 
3. Proposals 
3.1 It is proposed that the Committee considers the call-in request. 
4. Implications/Socio-economic Duty 
Financial 
4.1 The financial implications are outlined in the Ardrossan Campus Project Update report
attached at Appendix 1. 
Human Resources 
4.2 The human resource implications are outlined in the Ardrossan Campus Project
Update report attached at Appendix 1. 
Legal 
4.3 The legal implications are outlined in the Ardrossan Campus Project Update report
attached at Appendix 1. 
Equality/Socio-economic 
4.4 The equality/social-economic implications are outlined in the Ardrossan Campus
Project Update report attached at Appendix 1. 
Climate Change and Carbon 
4.5 The climate change and carbon implications are outlined in the Ardrossan Campus
Project Update report attached at Appendix 1. 
Key Priorities 
4.6 The key priorities are outlined in the Ardrossan Campus Project Update report
attached at Appendix 1. 
Community Wealth Building 
4.7 Any community wealth building implications are outlined in the Ardrossan Campus
Project Update report attached at Appendix 1. 
Islands Communities Impact Assessment (ICIA) 
4.8 Any ICIA implications are outlined in the Ardrossan Campus Project Update report
attached at Appendix 1. 
84

Page 85

United Nations Rights of the Child (UNCRC)
4.9 Any UNCRC implications are outlined in the Ardrossan Campus Project Update report
attached at Appendix 1.
Consumer Duty
4.10 Any consumer duty implications are outlined in the Ardrossan Campus Project Update
report attached at Appendix 1.
5. Consultation
5.1 None concerning this report.
Craig Hatton
Chief Executive
For further information please contact Shannon Wilson, Committee Services Officer, on
shannonwilson@north-ayrshire.gov.uk.
Background Papers
N/A
85

Page 86

NORTH AYRSHIRE COUNCIL
2 June 2026
Cabinet
Title: Ardrossan Campus – Project Update
Purpose: To provide Cabinet with an update on the current progress of
the Ardrossan Campus project, including current projections in
relation to costs and programme.
Recommendation: Cabinet is asked to:
1. Note the content of this report, including the current progress
of work on site.
2. Note the revised project completion date of 26 May 2028,
with anticipated occupation from August 2028.
3. Note the additional estimated cost of £9.97 million (8.74%)
associated with addressing the contamination will be met
from approved capital flexibility funding.
1. Executive Summary
1.1 The Ardrossan Coastal Quarter programme represents a transformational vision for
the area which includes the provision of new housing and commercial uses, providing
ambitious transformational regeneration of a vacant and derelict site on land within
one of North Ayrshire’s most deprived communities. A key component of this vision is
a new educational and community campus. 
1.2 The contract to construct the new Ardrossan Campus Project commenced on site in
July 2025, with the first stage focusing on the excavation of foundations and the
swimming pool tank. In September 2025, asbestos and hydrocarbon contamination
was identified during construction. Appropriate Safe Systems of Work were then
implemented by the main contractor (Morgan Sindall), with an independent review
confirming these measures to be proportionate and compliant.
1.3 The contractual and programme implications were subsequently assessed by our cost
consultant, resulting in an additional cost of £9.97 million (8.74%) and an extension of
the completion date to 26 May 2028.
1.4 The overall Campus project budget will therefore increase to £124,558,600, with the
additional funding to be met from the Council’s capital flexibility fund approved in
February 2026.
Appendix 1
86

Page 87

1.5 An independent external review of the enabling works has been commissioned, with
an initial assessment received and currently under consideration. 
1.6 The safe systems of work which have been required since encountering the
contamination have now ceased. Works are progressing unhindered by these
additional measures and the project has now reached a significant milestone on the
construction process as steel work is now rapidly being erected on-site. 
1.7 Stakeholder engagement will now be undertaken to communicate the revised delivery
arrangements and support appropriate mitigation of the impacts arising from the
extended programme. 
2. Background 
2.1 Two separate contracts relating to the delivery of the Ardrossan Coastal Quarter
were undertaken commencing in June 2023 and January 2024 respectively. The
purpose of these projects was to deliver a new revetment (Sea-Wall) coastal
defence, an extension of the coastal path, remediate contamination and to install
site-wide infrastructure to enable future development. 
2.2 Remediation strategy involved treating contaminated soil on location, removing
hydrocarbons, and reusing suitable treated material in the works. The strategy also
included installing 600mm stone cap across the site to provide a protective barrier as
all contamination would not be removed. The remediation was independently
monitored and verified to ensure it met all required standards. 
2.3 Subsequent to that, construction work on the new Ardrossan Campus commenced in
July 2025, with initial works focusing on the formation of foundations and excavation
of the swimming pool. 
2.4 As works progressed on site, an in accordance with the agreed methodology for
progressing the works, testing of excavated materials continued in order to ensure
all health and safety standards were maintained. In September 2025, asbestos and
hydrocarbon contamination was identified as a result of that testing. Appropriate
Safe Systems of Work were immediately implemented by the main contractor
(Morgan Sindall), with an independent review confirming these measures to be
proportionate and compliant
Programme Development
2.5 The Ardrossan Coastal Quarter site was selected in 2018-2019 as the preferred
location for the new Campus, reflecting its capacity, regeneration potential, and
alignment with the Council’s Local Development Plan priorities. The wider vision
includes residential and commercial development to support regeneration and align
with the Local Development Plan.
2.6 The “Ardrossan North Shore Development Framework”, prepared by external
consultants (Stallan Brand), was approved in April 2021 and set the strategic context
for redevelopment. Subsequently, In June 2021, the Council agreed remediation and
87

Page 88

site infrastructure works to achieve economies of scale and improve the site’s
attractiveness for future investment. 
2.7 In the prevailing market conditions, a single contract for the complete programme of
work was not considered the most deliverable option, and the chosen approach
provided a practical route to securing progress. Market feedback indicated that
including the Campus within those packages would have been less attractive to
bidders. This was reaffirmed when the subsequent Campus tender process only
attracted two bids.
2.8 Following market engagement on the enabling works tender issued in November
2021, the procurement approach was refined in response to no compliant bids being
received through the original process, with the works restructured into two packages
and successfully retendered in 2023 and 2024. 
2.9 Due to the phasing of the separate projects, the enabling works were more
advanced than the Campus design, and the revetment had to be completed first. In
the context of a volatile market, maintaining separate elements of delivery helped
support programme progress and provided a more manageable basis for pricing. 
2.10 It should be noted that the enabling works, as separate contracts with different
contractors, were not the first stage of the construction contract to deliver the
Campus. These were discrete pieces of work, intended to enable development
across the wider Ardrossan Coastal Quarter site. Although the advance enabling and
remediation works provided an appropriate and proactive route to delivery, the use
of three separate contracts meant that interface risks were recorded and remained
an inherent feature of the overall programme.
2.11 The Campus design was successfully finalised while the advance works were
progressing, with the projects coordinated to support overall delivery. Although the
advance works project was not intended to deliver Campus construction works, this
approach helped maintain progress, while market feedback confirmed that separate
contractual responsibilities remained the more practical route. 
2.12 Recognising the challenges being experienced in delivering the wider programme of
works, with a focus on ensuring the Campus could be delivered as soon as possible,
a review was conducted with the support of external consultants (Ironside Farrar) in
February 2024. This confirmed the inherent risks of brownfield remediation, buried
structures, coastal conditions and sequential working, with further contamination
assessed at that stage as an amber risk.
2.13 As Morgan Sindall had no control over the enabling works contract, it confirmed prior
to Financial Close that it would not accept contamination risk within the Campus
contract, the contract therefore acknowledged this risk and relied on the contingency
allocation to address any arising issues. 
2.14 A report was submitted to Council on 26 June 25, confirming the revised budget and
programme for the project. A number of key remaining risks were also highlighted in
the report. Included within those was the potential to discover contaminated material
88

Page 89

in the deep excavations below the remediated level, and the impact this could have
on costs and programme.
2.15 To estimate the potential cost, prior to entering the construction contract the
assessment associated with this risk estimated that around 13,280m³ of excavation
would extend below the 3.5m remediation depth. Utilising market rates for disposal,
a potential worst case disposal exposure of £6.64m was assessed. Because overlap
between known contamination and deep excavations appeared limited, an overall £5
million contingency was considered realistic and included within the project budget.
2.16 The Scottish Futures Trust (SFT) have worked in partnership with the Council
throughout the development phases of the project, including providing financial
support thought the Scottish Government’s Learning Estate Investment Programme.
The project allocation was increased to reflect the challenging conditions around the
delivery of the project. 
2.17 Verification reports in respect of the enabling works contract were received,
satisfying the Planning Conditions required to allow works to commence on site.
Campus Construction Phase
2.18 In September 2025, asbestos and hydrocarbon contamination was encountered
during deep excavations. Elected Members and the local community were
proactively informed shortly thereafter. 
2.19 As a result of this, and to ensure works could progress in a safe manner, Morgan
Sindall introduced Safe Systems of Work, including exclusion zones and specialist
controls.
2.20 An external specialist engineering advisor independently reviewed the Safe Systems
of Work on the Council’s behalf and found them to be both proportionate and
compliant.
2.21 Our cost consultants, Atkins Realis, have assessed the contractual impact of the
appropriate treatment of the contaminants via the safe system of work as an
additional £9.97 million. The programme impact has also resulted in an extension of
time to the contract to 26 May 2028. This has been formally confirmed through the
contractual change control process. 
2.22 This figure represents a significant betterment than the original proposal by the
contractor following robust review and challenge by the Campus project team and
external advisors. 
2.23 Addressing the contamination issue will result in the Campus project budget rising to
£124,558,600. This increase will be addressed through the Council’s capital flexibility
fund approved by Council in February 2026.
2.24 A report by independent specialist engineers has been commissioned, with input
from the appropriate consultant teams, to ensure the reasons for the current issues
are properly understood. An initial assessment has been provided and is being
reviewed to determine the next steps. 
89

Page 90

2.25 Separate delivery of the enabling works and the Campus has also required ongoing
management of wider interface risks; however, these matters are being actively
managed through cross-service coordination to ensure that appropriate mitigation
measures are identified and allocated. 
2.26 Under the NEC4 contract, the Council’s exposure to additional cost arising from
systemic supply chain issues arising from the current conflict in the Middle East is
limited, with broader liability arising mainly where contract terms or future legislative
changes require it.
2.27 As the cost and programme implications arising from encountering contamination are
now understood, the overall construction programme has been updated, and the
Project Team will undertake stakeholder engagement to advise on the new
timetable. This engagement will include: elected members; the school community;
neighbours and the Ardrossan community; and Scottish Futures Trust. 
2.28 The negative impacts of the delay will be most keenly felt by the by the school
community being unable to access the new facility when planned and the
neighbouring properties experiencing direct disruption caused by construction
activities. 
2.29 Stakeholder engagement will recognise these negative impacts, and the project team
will continue to explore practical mitigations to the issues posed by the extended
programme. 
2.30 With the safe systems of work around contamination removal now being complete,
works are progressing unhindered by these additional measures and the project has
now reached a significant milestone on the construction process as steel work is now
rapidly being erected on-site and concrete floor slabs are being poured. 
3. Proposals 
3.1 It is proposed that Cabinet:
• Notes the content of this report, including the current progress of works on site.
• Notes the revised completion date of 26 May 2028, with anticipated occupation from
August 2028. 
• Notes the additional estimated cost of £9.97 million (8.74%) associated with
addressing the contamination will be met from approved capital flexibility and
borrowing. 
4. Implications/Socio-economic Duty 
Financial 
4.1 An additional £9.97 million (8.74%) has been identified as necessary to address the
contamination issues associated with Compensation Events relating to the
contamination as outlined in this report. This requirement will be met through the
approved capital flexibility budget agreed by Council on 25 February 2026. 
90

Page 91

It is anticipated that additional contingency funding may be required to address any
remaining risks which arise during the remainder of the construction period. 
In parallel, a further review of the Council’s Capital Investment Programme will be
undertaken covering the period 2026/27 to 2033/34, to ensure that the revised
programme remains prudent, affordable and sustainable. This review will include long-
term projections of borrowing and interest rate assumptions, assessment of
expenditure profiles, capital receipt forecasts, anticipated capital grant funding, and
the planned use of the loans fund reserve.
Scottish Futures Trust has been approached to explore whether any additional
support may be available. However, the Scottish Government has confirmed, that in
accordance with the agreed LEIP funding principles, the inflationary risk associated
with project delays rests with the local authority.
Human Resources
4.2 None
Legal
4.3 Legal Services will be asked to comment on the report noted at item 2.24.
Equality/Socio-economic
4.4 The construction of the new Campus, as a key component of the wider
transformational regeneration of the Ardrossan Coastal Quarter will have significant
direct and wider socio-economic benefits.
Climate Change and Carbon
4.5 Ardrossan Campus has been designed to be highly energy-efficient and to meet the
LEIP in-use energy requirements of between 67-83KWh/m²/annum. The contract
design shows a predicted attainment of 71KWh/m²/annum. A sustainability
responsibility matrix has been developed and incorporated into the contractual
agreement to deliver facilities that will contribute to the Council’s climate change
priorities.
Key Priorities 
4.6 The project supports the following Council priorities:
Wellbeing
• Developing appropriate skills for the local and regional economy
• Using our assets to support wellbeing in local communities Improving educational
attainment and achievement and closing the attainment gap
• Developing the young workforce and ensuring positive destinations for school
leavers
• Providing lifelong learning opportunities for individuals and organisations including
digital literacy
91

Page 92

• Improving outcomes for care-experienced young people including implementation
of The Promise
• Ensure our places and spaces where we live, work and visit are well maintained
and accessible.
• Support KA Leisure’s leadership of North Ayrshire’s Health and Wellbeing Alliance
• Through the Health and Social Care Partnership Strategic Plan we will protect and
provide care and support for those in need.
Communities and Local Democracy
• Developing partnerships with the third and voluntary sector
• Placemaking, including creation of locality action plans.
• Accessible public services, both digitally and locally.
Climate Change
• Embedding our net-zero ambition in all democratic decision-making.
• Reducing the carbon footprint of our estate and taking a fabric first and low carbon
energy generation approach to homes and buildings
• Promoting new woodland creation and protecting our green spaces to provide a
natural resource for carbon sequestration.
Community Wealth Building
4.7 A suite of community benefits has been developed through the design and
construction phases of the project. The commitments from Morgan Sindall which are
defined in the SCAPE framework agreement have been incorporated into the
contractual requirements for the project.
Islands Communities Impact Assessment (ICIA)
4.8 None
United Nations Rights of the Child (UNCRC)
4.9 The development of the Campus fully supports these rights.
Consumer Duty
4.10 The project will deliver on these through the Stakeholder Reference Group and Client
Planning workstreams.
5. Consultation
5.1 Consultation has been undertaken with Education, Economic Development Growth &
Regeneration, and Finance.
RUSSELL McCUTCHEON
Executive Director (Place)
For further information please contact Laurence Cree, Head of Service Sustainability,
Transport & Corporate Property, on 01292 324514. 
92

Page 93

Background Papers
0 
93

Page 94

Audit and Scrutiny Committee
15 June 2026
At a Special Meeting of the Audit and Scrutiny Committee of North Ayrshire Council
at 10.00 a.m. involving participation by remote electronic means and physical
attendance within the Council Chambers, Irvine.
Present (Physical Participation)
John Bell, Cameron Inglis, Tom Marshall, Matthew McLean, Donald Reid, Donald L
Reid and John Sweeney.
Present (Remote Participation)
Davina McTiernan and Shaun Macaulay.
In Attendance
D. Hammond, Executive Director and K. Bell, Team Manager (Housing Strategy)
(Communities and Housing); S. Anson, Executive Service (Education) M. Boyd,
Head of Service (Finance); L. Cree, Head of Service (Sustainability, Transport &
Corporate Property) (Place); A. Craig, Head of Service, C. Stewart, Committee
Services Officer, and H. Young, Senior Committee Services Office (Democratic
Services) (Corporate Services).
Also in Attendance
Eleanor Collier, Joe Cullinane, Robert Foster, Christina Larsen, Jim Montgomerie
and Ian Murdoch.
Chair
Councillor Bell in the Chair.
1. Declarations of Interest
There were no declarations of interest by Members in terms of Standing Order 11
and Section 5 of the Code of Conduct for Councillors.
2. Call In: Revenue Budget 2025/26: Financial Performance to 31 March 2026
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026
advising of the financial performance for the Council for 2025/26. The original
Cabinet report and minute from the Cabinet meeting which took place on Tuesday 2
June 2026 was attached at Appendix 1 to the report. Appendix 2 to the report
contained a briefing note provided by the Head of Finance in response to the matters
raised in the call-in request form.
The Cabinet, on 2 June 2026, considered a report on the financial performance for
Council 2025/26. Cabinet amended the recommendation to the report by determining
to allocate £1.496m of underspend to the 26/27 revenue budget with the funds to be
used to create an Our Places, Our Communities fund designed to benefit all North
Appendix 3
94

Page 95

Ayrshire communities with details of the fund being brought to council on the 24th of
June for debate and approval. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“In passing its budget, the Council set Council Tax bands at a level required to fund
its expenditure requirements, including prioritising investment in areas such as
education and roads. 
The £1.496million underspend should therefore not be spent on another of the
administrations pet projects, particularly when the evidence of the last four years
shows that these pots of money are not used in a timeous manner. 
Instead, the underspend should be returned to council taxpayers.” 
Desired Outcome 
“That the £1.496million allocated to an ‘Our Places, Our Communities fund’ be re-
allocated to provide a Council Tax rebate, reflecting the fact that our expenditure
requirements for 2026/27 have already been funded.  
Although this outcome proposes a Council Tax rebate, we acknowledge officers'
advice that as matters relating to setting Council Tax levels are reserved to Council
and that for this outcome to be implemented it will require a decision of Full Council,
including the suspension of 15.5 and 25.1 of Standing Orders Relating to Meetings
and Proceedings of the Council, as Council Tax was set within the last six months.
The Audit & Scrutiny Committee is asked to accept the call in and recommend that
the matter is referred by Cabinet to Council for further consideration and
determination.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request and
was heard in response to Members’ questions. 
The Chair then invited Councillor Larsen, as the Cabinet Member for Finance, to
address the meeting. Councillor Larsen explained the reasoning for the Cabinet
decision and referred to a briefing note from the Head of Finance provided at
Appendix 2 to the report. She was also heard in answer to Members’ questions. 
The Head of Finance was then heard in relation to the report presented to Cabinet
and on issues raised by the call-in. 
Councillors Cullinane and Larsen were heard in summing up. 
95

Page 96

Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration, with the recommendation that the matter is referred to
Council to determine the use of the underspend and that Council suspends Standing
Orders to consider the proposal regarding a Council Tax rebate. 
As an amendment, Councillor Macaulay, seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
There followed questions, debate and summing up on the motion and amendment
presented for consideration. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Macaulay and McTiernan (2) and for the motion, Councillors Bell, D.
Reid, Inglis, Marshall, McLean, D.L Reid and Sweeney (7). The motion was declared
carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b) that the
matter be referred to Cabinet for further consideration, with the recommendation that
the matter is referred to Council to determine the use of the underspend and that
Council suspends Standing Orders to consider the proposal regarding a Council Tax
rebate. 
3.  Call In: North Ayrshire Housing Acquisition Strategy 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 on
the proposed Housing Acquisition Strategy 2026- 2031. The original Cabinet report
was attached at Appendix 1 to the report. Appendix 2 to the report contained a
briefing note provided by the Executive Director (Communities and Housing) in
response to the matters raised in the call-in request form. 
The Cabinet, on 2 June 2026, considered a report on the proposed Housing
Acquisition Strategy 2026-2031. 
Subsequently, a call-in request was received from Councillors Cullinane, Foster and
Montgomerie in the following terms:-   
Reason for Call-In 
“It is wrong to suggest this policy will have no impact on the Council’s Community
Wealth Building (CWB) strategy. A key component of the strategy is to increase
procurement spend with North Ayrshire, and Ayrshire, businesses creating economic
and socio benefits from investing in the local economy. The fact that Ayrshire based
companies have won our council house building contracts has made a significant
contribution to us achieving the initial procurement targets set out in the first CWB
strategy published in 2020. 
This policy is the opposite of this approach. It will see a significant proportion of our
investment in Council housing, the majority of which comes from the Council with the
96

Page 97

rest from Holyrood, be transferred to private housing developers, many of which are
large national developers. It will see that investment extracted from the Ayrshire
economy. 
We remain as committed to Community Wealth Building as were in 2020. We
therefore reject this policy.” 
Desired Outcome 
“That the Council reaffirms its commitment to Community Wealth Building by
rejecting this policy and redoubling our efforts to ensure that Ayrshire based
companies can bid for, and win, the contracts to build the next generation of Council
houses in North Ayrshire.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Cullinane addressed the Committee in support of the call-in request. 
In the absence of Councillor Hill, as the Cabinet Member for Communities, Housing
and the Islands, the Chair then invited Councillor Collier to address the meeting. She
was also heard in answer to Members’ questions. 
The Executive Director and the Team Manager (Housing Strategy) (Communities
and Housing) were heard in response to Members’ questions. 
Councillors Cullinane and Collier were heard in summing up. 
Councillor Sweeney, seconded by Councillor D. Reid, moved that the Committee
agree to accept the terms of the call-in request and refer the matter to the Cabinet
for further consideration with the recommendation that the policy be rejected. 
As an amendment, Councillor Macaulay seconded by Councillor McTiernan moved
that the Committee agree not to support the call-in request and that the decision of
Cabinet should stand. 
Thereafter, on a division and a roll call vote, there voted for the amendment,
Councillors Inglis, Macaulay, Marshall, McTiernan and D.L Reid (5) and for the
motion, Councillors Bell, D. Reid. McLean and Sweeney (4) and amendment was
declared carried. 
Accordingly, the Committee agreed not to support the call-in request and that the
decision of Cabinet should stand. 
97

Page 98

4. Call In: Ardrossan Campus Project Update 
Submitted report by the Head of Democratic Services to consider a call-in request in
respect of the decision taken by Cabinet at its meeting on Tuesday 2 June 2026 to
note the current progress of the Ardrossan Campus project, including current
projections in relation to costs and programme. The original Cabinet report was
attached at Appendix 1 to the report. 
The Cabinet, on 2 June 2026, considered an update report on the current progress
of the Ardrossan Campus project, including current projections in relation to costs
and programme. 
Subsequently, a call-in request was received from Councillors Stalker, Murdoch and
Stephen in the following terms:-   
Reason for Call-In 
“This decision is being called in because there are some real concerns about how
the Ardrossan Campus project is progressing. The report shows a significant cost
increase of around £10 million, along with delays pushing completion back to May
2028. 
There are also questions about how risks have been handled, especially around
ground contamination and the challenges of building on a contaminated site. It’s not
clear if these issues were fully understood early on, or if more could have been done
to avoid the impact they have had. On top of that, using additional capital funding to
cover the extra costs raises concerns about what this means for and the overall
budget of the campus and what more flexibility funding will be made available in
future budgets. 
Overall, this call-in is about getting reassurance that the project is still under control,
that risks are being properly managed, and that it continues to represent good value
for the Council and local communities.” 
Desired Outcome 
“To provide assurance on and seek greater information on the cost, programme, risk
management, governance and wider capital implications of the Ardrossan Campus
project, ensuring it remains deliverable, financially sustainable and represents value
for money.” 
The Head of Democratic Services summarised the procedure for considering the
call-in request in terms of Standing Orders and referred to the Cabinet decision. 
Thereafter, the Members who had requested the call-in were invited to speak and
Councillor Murdoch addressed the Committee in support of the call-in request and
was also heard in response to Members’ questions. 
As a point of clarification it was confirmed that the decision of Cabinet was to note
the update provided in the report presented. 
98

Page 99

The Chair then invited Councillor Collier, as the Cabinet Member for Green
Environment and Economy, to address the meeting. Councillor Collier explained the
reasoning for the Cabinet decision and was also heard in answer to Members’
questions. 
The Executive Director (Education) and the Head of Service (Sustainability,
Transport & Corporate Property) (Place) were heard in answer to Members’
questions. 
Councillors Cullinane and Collier were heard in summing up.  
Councillor Inglis, seconded by Councillor McLean, moved that the Committee agree
to accept the terms of the call-in request with a recommendation that a progress
report is taken to a future meeting of Council in six months for consideration. There
being no amendment the motion was declared carried. 
Accordingly, the Committee agreed (a) to support the call-in request; and (b)
recommended to Cabinet that an update report is taken to a future meeting of
Council in six months. 
The meeting ended at 12.10 p.m. 