North Ayrshire Council, Cunninghame House, Irvine KA12 8EE         
Ayrshire Shared Services Committee 
A Meeting of the Ayrshire Shared Services Committee will be held in the William
Murdoch Room, East Ayrshire Council Headquarters, London Road,
Kilmarnock,  on Friday, 19 May 2023 at 10:00 to consider the undernoted business. 
Meeting Arrangements - Hybrid Meetings
This meeting will be held on a predominantly physical basis but with
provision, by prior notification, for remote attendance by Elected
Members in accordance with the provisions of the Local Government
(Scotland) Act 2003.  
The proceedings will not be live-streamed to the internet, but a physical
public gallery will be available to the press and public. 
1 Apologies 
2 Declarations of Interest
Members are requested to give notice of any declarations of interest in
respect of items of business on the Agenda. 
3 Previous Minutes
The accuracy of the Minutes of the last meeting of the Joint Committee
held on 10 March 2023 will be confirmed and the Minutes signed in
accordance with Paragraph 7(1) of Schedule 7 of the Local Government
(Scotland)
Act 1973. 
4 Ayrshire Roads Alliance - Update on Performance Scorecard
Submit report by the Head of Roads (Ayrshire Roads Alliance) on
progress made to date against the Performance Scorecard (copy
enclosed).
1

Page 2

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
5 Ayrshire Roads Alliance - Risk Report and Register
Submit report by the Head of Roads (Ayrshire Roads Alliance) on the
management of risk associated with the Ayrshire Roads Alliance (copy
enclosed). 
6 Ayrshire Roads Alliance - Service Plan 2023/24
Submit report by the Head of Roads (Ayrshire Roads Alliance) seeking
approval for the Ayrshire Roads Alliance Service Plan for 2023/24 (copy
enclosed). 
7 Roadworks Programme 2023/24
Submit report by the Head of Ayrshire Roads Alliance on the progress of
work through the roads improvement programmes within East Ayrshire
and South Ayrshire for financial year 2023/24 (copy enclosed). 
8 Rotation of Joint Committee
The Joint Committee is invited to note that the chairing and administration
of its meetings will, in terms of the Minute of Agreement, rotate to East
Ayrshire Council from June 2023 
9 Urgent Items
Any items which the Chair considers to be urgent. 
2

Page 3

North Ayrshire Council, Cunninghame House, Irvine KA12 8EE 
Ayrshire Shared Services Committee Sederunt 
North Ayrshire Council
Marie Burns
Joe Cullinane
Scott Davidson
Tom Marshall
East Ayrshire Council
Neal Ingram
Barry Douglas
Douglas Reid
Neill Watts
South Ayrshire Council
Alec Clark 
William Grant
Bob Pollock
Philip Saxton 
Chair: 
Apologies: 
Attending: 
3

Page 4

4

Page 5

Ayrshire Shared Services Joint Committee
10 March 2023 
At a Meeting of Ayrshire Shared Services Joint Committee at 10.00 a.m. involving a
combination of participation by remote electronic means and physical attendance within
the Council Chambers, East Ayrshire Council Headquarters, Kilmarnock 
Present (Physical Participation)
Councillors Douglas Reid and Neal Ingram (East Ayrshire Council); and Councillor
Philip Saxton (South Ayrshire Council). 
Present (Remote Electronic Participation)
Councillors Barry Douglas and Neil Watts (East Ayrshire Council) and William Grant
and Bob Pollock (South Ayrshire Council).
In Attendance (Physical Participation)
K. Braidwood, Head of Roads, C. Knape, Strategic Manager Network and Transportation
and T. Mackin, Strategic Manager Business Support (Ayrshire Roads Alliance); P. Whip,
Group Finance Manager and ICT and S. Nelson, Committee Services Officer (East
Ayrshire Council); and M. Anderson, Senior Manager (Committee and Member Services)
(North Ayrshire Council). 
In Attendance (Remote Electronic Participation)
K. Kelly, Depute Chief Executive (East Ayrshire Council). 
Chair
Councillor Douglas Reid in the Chair. 
Apologies
Councillors Marie Burns, Joe Cullinane, Scott Davidson and Tom Marshall (North
Ayrshire Council) and Alec Clark (South Ayrshire Council). 
1. Introductory Remarks 
In the absence of the Chair, and given that there were no items of business on the
agenda for which North Ayrshire Council Elected Members were required to attend,
Councillor Douglas Reid was appointed to chair the meeting. 
2.  Declarations of Interest 
There were no declarations of interest in terms of Standing Order 11 and Section 5 of
the Councillors' Code of Conduct. 
Agenda Item 3
5

Page 6

3. Temporary Traffic Regulation Orders 
The Committee received a presentation by the Head of Roads and the Strategic
Manager Business Support (Ayrshire Roads Alliance) on a new digital platform
developed by the ARA with True View Visuals for processing requests for Traffic
Regulation Orders and Notices. 
The presentation highlighted: 
• the benefits of this unique online system in terms of streamlining processes,
generating public notices and mapping, and tracking the status of requests; 
• other potential applications of the platform, such as skip permits;
• potential income generation arising from marketing the system to other agencies;
and 
• the ARA’s success in being named as finalists in the APSE Highway Maintenance
Innovation category 
Members asked questions, and received clarification, on the following: 
• anticipated changes in the role of local newspapers, with a trend towards titles
moving online;
• the scope to develop the platform for use with other types of permit;
• the current status of the platform, which went ‘live’ in November 2022; and
• planned refinements to the mapping tool, to take account of one-way systems
when setting diversions and allow for the identification of secondary diversions. 
Noted. 
4. Ayrshire Roads Alliance – Revenue Financial Monitoring Report 
Submitted report by the Chief Financial Officer and Head of Financial and ICT on the
Ayrshire Roads Alliance revenue budget monitoring position for the year to 31
December 2022.  Appendices 1 and 2 to the report provided the split between strategic
and local service delivery and the financial monitoring report, respectively. 
Members asked questions, and received clarification, on the following; 
• whether additional funding identified in East Ayrshire Council’s recent budget-
setting had been taken into account, or if this would be reflected in future reporting;
• anticipated changes in respect of contract costs; and
• the COSLA position in terms of parking fine levels; 
It was agreed (a) to note the financial management position of the Ayrshire Roads
Alliance; (b) to request a further financial update at the next meeting of the Joint
Committee; and (c) otherwise, to note the content of the report. 
6

Page 7

5. Ayrshire Roads Alliance – Risk Report and Register 
Submitted report by the Head of Roads (Ayrshire Roads Alliance) on the management
of risk associated with the Ayrshire Roads Alliance.  The risk Scoring Matrix and
Ayrshire Roads Alliance Risk Register were set out at Appendices 1 and 2 to the report,
respectively. 
It was agreed (a) to note the risk register presented at Appendix 2 to the report; (b) to
continue to receive updates on progress; and (c) otherwise, to note the content of the
report.  The risk scoring matrix and Ayrshire Roads Alliance Risk Register were set out
at Appendices 1 and 2 to the report, respectively. 
6. Ayrshire Roads Alliance – Improvement Action Plan 
Submitted report by the Head of Roads (Ayrshire Roads Alliance) on the management
of the Improvement Action Plan with the Ayrshire Roads Alliance.  The Improvement
Action Plan was set out at Appendix 1 to the report. 
Members asked questions, and received clarification, on the following: 
• whether the support of Transport Scotland could be sought for the Bellfield
Interchange and Active Travel Prestwick projects, which had received positive
feedback from the Scottish Government and could the subject of bids to the next
cycle of Levelling Up funding, but which had not been successful under STPR2;
• the position with regard to the A70 and A71, which were designated as local
routes, notwithstanding their strategic importance to Ayrshire;
• recent discussion at the Ayrshire Regional Economic Joint Committee on the
importance of transportation and infrastructure to economic strategy; and
• the value of the three Ayrshire authorities working together to look at transport
links (including roads, ports and rail) and present a business case for Ayrshire
Growth Deal support  
The Head of Roads (Ayrshire Roads Alliance) undertook to write to Transport Scotland
on behalf of the Committee in support of the Bellfield Interchange and Active Travel
Prestwick projects. 
It was agreed (a) to note the Improvement Action Plan set out at Appendix 1 to the
report; (b) to continue to receive updates on progress; and (c) otherwise, to note the
content of the report.  
7

Page 8

7. Roadworks Programme 2022/23 
Submitted report by the Head of Roads (Ayrshire Roads Alliance) on the progress of
work through the roads improvement programmes within East Ayrshire and South
Ayrshire for the financial year 2022/23.  The South and East Ayrshire Council
Programmes of Works 2022/23 were set out at Appendices 1 and 2 to the report,
respectively.  Appendix 3 provided information on EV Infrastructure. 
Members asked questions, and received clarification, on the following; 
• the impact of budget constraints on road improvements/repairs and the need for
reassurance that project which had been delayed in previous years would be
progressed as a priority; and
• work to identify more effective materials for use in patch repairs and the
challenges around this, in terms of the overall condition of roads 
It was agreed (a) to note the Ayrshire Roads Alliance works completed in 2022/23 as
set out in the report and its appendices; and (b) otherwise, to note the content of the
report. 
8. Ayrshire Roads Alliance – Update on Performance Scorecard 
Submitted report by the Head of Roads (Ayrshire Roads Alliance) on the progress made
to date against the Performance Scorecard.  The detailed Performance Scorecard
monitoring report was set out at Appendix 1 to the report. 
A Member referred to the discount scheme recently introduced by South Ayrshire
Council to promote the early payment of invoices and received clarification that work
was underway to explore the scope for the ARA to introduce a similar scheme.   
It was agreed (a) to note the Performance Scorecard information presented in the report
and its appendix; (b) to continue to receive the Performance Scorecard updates; and (c)
otherwise, to note the content of the report. 
9. Date of Next Meeting 
The Senior Manager (Committee and Member Services) (North Ayrshire Council)
invited the Committee to consider rescheduling the next meeting due to take place on
28 April 2023, in order to accommodate a meeting of the COSLA Leaders. 
The Committee agreed that the next meeting be re-scheduled to take place at 10.00
a.m. on Friday 19 May 2023. 
The Meeting ended at 11.10 a.m.
8

Page 9

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
19 May 2023 
Report by the Head of Roads - Ayrshire Roads Alliance   
_____________________________________________________________ 
SUBJECT: AYRSHIRE ROADS ALLIANCE
UPDATE ON PERFORMANCE SCORECARD
______________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to advise the Joint Committee regarding the
progress made to date against the Performance Scorecard. 
RECOMMENDATIONS 
2.   It is recommended that the Joint Committee: 
i Notes the performance scorecard presented in this report; 
ii Continues to receive the performance scorecard updates; and 
iii  Otherwise, notes the content of the report.
BACKGROUND 
3  The purpose of the performance management and benchmarking is to work
collaboratively to deliver tangible and sustained improvements within the
Ayrshire Roads Alliance in order to manage the on-going development and
delivery of benchmarking frameworks. 
4. Improved performance management is fundamental to supporting the Ayrshire
Roads Alliance.  This drives change and improvement within the fully integrated
roads service and support improved outcomes, better performance, and more
effective use of resources.   
5. The Performance Indicators are regularly refreshed when new useful
performance measures are introduced by the Ayrshire Roads Alliance or there
is an agreement to include a specific indicator.  This will be a regular item for
the Ayrshire Shared Service Joint Committee to review. 
MAIN REPORT/MAIN ISSUES 
6. This scorecard is collated by the Business Support Manager and used to: 
• monitor the progress in meeting the Ayrshire Roads Alliance’s
objectives;
Agenda Item 4
9

Page 10

• help managers to have performance-related conversations with staff;
and 
• identify any problem areas that need addressed. 
7. Some indicators are collated at different frequencies and so these will be
included as appropriate. 
8. The Performance Scorecard is presented in Appendix 1.  Commentary against
the specific red and amber performance measures are included in Appendix 1.
There are a number of green performance measures which should be
highlighted, especially: 
• Finance with respect to the percentage of invoices paid within 30 calendar
days.  This is currently at 99% for this financial year. 
• Priority 1 and Priority 2 Faults – with respect to the percentage of priority
1 and 2 faults completed within timescale.  This is currently above target
for this financial year. 
• Safety Inspections – with respect to the percentage of safety inspections
completed within the timescale.  The service has achieved an average of
98% for this financial year. 
9. The Process Improvement and Integration Plan continues to identify
improvements to a number of existing processes for re-design within The
Ayrshire Roads Alliance. 
POLICY/COMMUNITY PLAN IMPLICATIONS 
10.   A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
11.   The matters referred to in this report contribute to South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’. 
LEGAL IMPLICATIONS 
12 The Performance Scorecard summarises the pertinent Statutory Performance
Indicators and this does not replace the existing statutory returns for
performance information. 
HUMAN RESOURCES IMPLICATIONS 
13 The Performance Scorecard has no direct impact on human resources. 
10

Page 11

EQUALITY IMPACT IMPLICATIONS 
14 The Performance Scorecard complements the Equality Impact Assessment by
ensuring that any issues arising are adequately prioritised, managed and either
eliminated or mitigated. 
FINANCIAL IMPLICATIONS 
15 The Performance Scorecard facilitates the existing scrutiny arrangements to
manage, prioritise, and review the budget provided by East Ayrshire Council
and South Ayrshire Council to the Ayrshire Roads Alliance. 
RISK IMPLICATIONS 
16.    The Performance Scorecard assists in the prioritisation of risks that need to be
mitigated by the Ayrshire Roads Alliance in order to reduce the overall risk to
either Council and to comply with the Community Plan/Council Plan in both
partner bodies. 
TRANSFORMATION STRATEGY 
17 This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”. 
• “Maximum value for our communities”, by ensuring the various elements
of the Ayrshire Roads Alliance improves transport provision throughout
East Ayrshire. 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
11

Page 12

2014/16 2015/17 2016/18 2017/19 2018/20 2019/21 2021/22 2013/15 2014/16 2015/17 2016/18 2017/19 2018/20 2019/21 2021/22
2014 2015 2016 2017 2018 2019 2020 2021 % of A Class roads that should be considered for
maintenance 27.06% 21.30% 19.10% 19.80% 21.20% 23% 22.10% 17.20% 42.20% 40.50% 38.60% 38.20% 36.10% 34.40% 34.10% 28.90%
Number of people killed or seriously injured in road
accidents per 100,000 population 25 29 29 33 59 46 36 36 % of B Class roads that should be considered for
maintenance 31.89% 34.20% 34.00% 35.70% 32.20% 32.50% 32.60% 26.80% 50.40% 48.90% 43.90% 40.70% 38.10% 36.90% 37.30% 34.40%
Number of slightly injured casualties per 100,000
population 147 176 138 150 181 86 65 49 % of C Class roads that should be considered for
maintenance 34.22% 40.30% 38.50% 40.50% 40.60% 38.80% 33.50% 29.50% 49.50% 43.90% 40.20% 41.40% 42.40% 42.20% 40.80% 37.90%
% of unclassified roads that should be considered for
maintenance 39.84% 44.90% 45.60% 44.00% 43.70% 42.10% 42.30% 40.90% 42.00% 43.30% 43.30% 41.40% 42.90% 42.30% 43.30% 42.90%
Overall % of road network that should be considered
for maintenance - 39.40% 39.10% 39.00% 38.40% 37.80% 36.80% 33.80% 45.00% 44.10% 42.30% 41% 41.30% 37.80% 40.90% 34.20%
MONTHLY PERFORMANCE INDICATORS APSE
Average Target Current
Status Mar MONTHLY PERFORMANCE INDICATORS APSE
Average Target Current
Status Mar
No of invoices paid within 30 days 1689 Average days lost per employee - - 1.34
No of Invoices Received 1705
% of invoices paid within 30 days 99% Visits to the ARA Website every month -
49,000
per
annum 
9,641
Average Year to date of Number of Invoices paid
within 30 days 99% No of Twitter Followers every month -  4,431
Monthly visits to the website from social media - 1,800 per
annum           986
Number of ARA Safety Inspections Completed within
Timescale 47
Number of ARA Safety Inspections Scheduled 47
% of ARA Safety Inspections Completed within
timescale 100%
Number of Health and Safety Incidents Reported to the
Health and Safety Section 4
Average Number of days to report an incident to the
Health and Safety Section 2
Target Current
Status Mar Target Current
Status Mar Comments Target Current
Status Mar Target Current
Status Mar
Number of Public Liability claims closed 16 9
Number of Public Liability claims received 10 8
Total number of open claims 49 43
Number of Public Liability Claims that were successful 1 0
% of Public Liability Claims that were successful 6% 0% Number of Principal Bridge Inspections - 0 0 0 3
Number of Priority 1 Road Emergency defect repairs
made safe within 2 hours 2 12 Number of Street Lighting repairs completed within 7
working days 87 71
Number of Priority 1 Repair Lines issued 2 16 Number of Street Lighting Repair Lines Issued 90 71
AYRSHIRE ROADS ALLIANCE PERFORMANCE SCORECARD DETAILED MONITORING REPORT
UPDATE : JOINT COMMITTEE  - 19 MAY 2023
There will be
occasions when
there are more
Inspections
completed in one
month than another
but over the year the
service is still on
target.
WELL ENGAGED
APSE
Average
ABSENCE MONITORING
36 36
62
- 100%
AYRSHIRE ROADS ALLIANCE
SOUTH AYRSHIRE COUNCIL
Comments
STREET LIGHTING
100%
ROADWORKS PROGRAMME
BRIDGES
Physical % of Roadworks Programme Completed 100% 100%
95%
62
EAST AYRSHIRE COUNCIL SOUTH AYRSHIRE COUNCIL
APSE
Average MONTHLY PERFORMANCE INDICATORS
26
FINANCE
ANNUAL PERFORMANCE INDICATORS
(CALENDAR YEAR)
ANNUAL PERFORMANCE INDICATORS                                                                                              
(FINANCIAL YEAR)
98%
AYRSHIRE ROADS ALLIANCE
-
Comments
AYRSHIRE ROADS ALLIANCE
Comments
EAST AYRSHIRE COUNCIL
2
63 37 
95% 88%75%
100%
-
PUBLIC LIABILITY CLAIMS
MONTHLY PERFORMANCE INDICATORS APSE
Average
- -
FACETIME
PRIORITY 1 FAULTS
-
Number of General Bridge Inspections
Number of Special Bridge Inspections
-
-
-
HEALTH AND SAFETY
92.02%
- -
100%
EAST AYRSHIRE COUNCIL
75%
--
91.20%
Number of staff who have received annual FACETIME
review 21% 5%
SOUTH AYRSHIRE COUNCIL
-
X0A1HX0A3HX0A4H
12

Page 13

Target Current
Status Mar Target Current
Status Mar Comments Target Current
Status Mar Target Current
Status Mar Comments
EAST AYRSHIRE COUNCIL SOUTH AYRSHIRE COUNCIL
APSE
Average MONTHLY PERFORMANCE INDICATORSMONTHLY PERFORMANCE INDICATORS APSE
Average
EAST AYRSHIRE COUNCIL SOUTH AYRSHIRE COUNCIL
% of Priority 1 Road Emergency defect repairs made
safe within 2 hours 100% 75% % Street Lighting repairs completed within 7 working
days 97% 100%
Number of Priority 2 Road Emergency defect repairs
made safe within 5 working days 11 55 Number of Traffic light repairs completed within 48
hours 12 23
Number of Priority 2 Repair Lines issued 14 89 Number of Traffic light repair lines issued 12 23
% of Carriageway Priority 2 Defects repaired within 5
working days 79% 62% % of Traffic light repairs completed within 48 hours 100% 100%
Number of Stage 1 Complaints responded to within
allotted timescales 0 0 Number of enquiries responded to within allotted
timescales 48 16
Numer of Stage 1 Complaints received 0 0 Number of enquiries received 53 31
% of Stage 1 Complaints responded to within allotted
timescales - - % of enquiries responded to within allotted timescales 90% 52%
Number of Stage 2 complaints responded to within
allotted timescales - 0 0
Number of Stage 2 complaints received 0 0 Number of FOI & EIR requests responded to within 20
working days 14 9
% of Stage 2 complaints responded to within allotted
timescales - - Number of FOI & EIR requests received 14 9
% of FOI & EIR requests responded to within 20
working days 100% 100%
Number of parking appeals accepted 41 56
Number of parking appeals received 95 132
% of parking appeals accepted 43% 42%
Officers are
reminded of the
importance of
responding to
enquiries within
timescales
TRAFFIC
100%
88.23% 95% 95%
80%- 100%
ENQUIRIES
83.44% 80%
88.52% 100%
FREEDOM OF INFORMATION
COMPLAINTS
PRIORITY 2 FAULTS
100%
76.23% 50%50%
PARKING
- ----
100% 100%
X0A0HX0A2HX0A5HX0A6H
X0A7H
13

Page 14

14

Page 15

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
19 May 2023  
Report by the Interim Head of Roads - Ayrshire Roads Alliance     
_________________________________________________________________ 
AYRSHIRE ROADS ALLIANCE
RISK REPORT AND REGISTER    
_________________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to advise the Joint Committee on the management
of risk associated with the Ayrshire Roads Alliance. 
RECOMMENDATIONS 
2. It is recommended that the Joint Committee: 
i. Notes the risk register presented in this report; 
ii. Continues to receive updates on progress; and 
iii.  Otherwise, notes the content of the report.
BACKGROUND 
3. A report detailing the general approach to the Risk Report and Risk Register was
presented to the Joint Committee on 21 August 2014, where it was agreed that
the Risk Report and Risk Register would be a standing item on the agenda.  This
would ensure that the risks are monitored and scrutinised at a minimum of a
quarterly basis.     
MAIN REPORT/MAIN ISSUES 
4. The management of risk aims to enable confident decision taking on risk and
innovation, reduce waste and inefficiency, and lead to fewer unanticipated
problems and crises that could undermine the performance and operation of the
Ayrshire Roads Alliance.
5. The Risk Register is now in a new and improved format which will make it easier
to review the individual risks which are now in a colour coded format. 
6. The resulting revised risk register is contained in Appendix 2.  
There has been one update to the Risk Register since the last Joint Committee. 
69 – Avian Flu - Supporting SAC in lifting bird carcasses. 
Agenda Item 5
15

Page 16

The revised risk register illustrates the red, amber and green status and also
illustrates whether the risk severity relates to time, indicated by [T] or cost,
indicated by [C]. 
POLICY/COMMUNITY PLAN IMPLICATIONS 
7. A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
8. The matters referred to in this report contribute to South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’. 
LEGAL IMPLICATIONS 
9. The Risk Register is a management tool and this will not replace the existing
statutory returns for risk and performance related information. 
HUMAN RESOURCES IMPLICATIONS 
10. The Risk Register has no direct impact on human resources. 
EQUALITY IMPACT IMPLICATIONS 
11. The Risk Register complements the Equality Impact Assessment by ensuring
that any issues arising are adequately prioritised, managed and either eliminated
or mitigated. 
FINANCIAL IMPLICATIONS 
12. The Risk Register facilitates the existing scrutiny arrangements to manage,
prioritise, and review the budget provided by East Ayrshire Council and South
Ayrshire Council to the Ayrshire Roads Alliance. 
RISK IMPLICATIONS 
13. The Risk Register assists in the prioritisation of risks that need to be mitigated
by the Ayrshire Roads Alliance in order to reduce the overall risk to either Council
and to comply with the Community Plan/Council Plan in both partner bodies.  
TRANSFORMATION STRATEGY 
14. This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”. 
16

Page 17

• “Maximum value for our communities”, by ensuring the various elements
of the Ayrshire Roads Alliance improves transport provision throughout
East Ayrshire. 
Kevin Braidwood
Head of Roads – Ayrshire Roads Alliance
4 May 2023 
BACKGROUND PAPERS 
None 
LIST OF APPENDICES 
1. Risk Register Scoring Matrix
2. Ayrshire Roads Alliance Risk Register 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
17

Page 18

Appendix 1: Risk Register Scoring Matrix 
The Risk Matrix for deciding each of the risk factors (Likelihood x Severity) in a 5 by 5
matrix are illustrated in Table 1 below: 
Table 1: Risk Factors in Practical Form 
Following on from Table 1, the following Summary Risk Profile is colour coded to highlight
the risk classification: 
Table 2: Summary Risk Profile 
Assessed
Risk (LxS) Action Required
Low Risk: 
1 to 4 
Acceptable/ can be accepted provided risk is
managed.
Medium Risk: 
5 to 12
Undesirable/ must be avoided if reasonably
practicable.
High Risk: 15
to 25 
Unacceptable risk - must be eliminated or moved to
a lower level. 
Rare (1) Unlikely
(2)
Possible
(3)
Likely
(4)
Almost
Certain
(5)
Catastrophic
(5) 5 10 15 20 25
Very Serious
(4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Insignificant
(1) 1 2 3 4 5
Risk Likelihood
Risk Severity
18

Page 19

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER
NOTE:
The Risk rating will be influenced by considering a combination of event effects
Such as associated cost, event duration, and organisational reputation.   
The table below will provide some assistance with risk rating. 
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
1
Personnel
Shortage due
to:
Pandemic
Event
Loss of trained and competent
personnel from all sections
within ARA due to pandemic
event.
Business continuity plans in place
(BUS-12, 13, & 14) to manage all
ARA mission critical activities.   
Number of employees working from
home significantly increased to
minimise medium / long term
disruption of service.   Operational
Personnel - re-assigned to other
duties within the Council.   Relaxing
of UK driving regulations to maximise
decreased LGV driver numbers. 
Additional usage of external
contractors to ensure essential
services / works programme targets
are met.   Covid safe workplaces /
sites established to accommodate
reduced number of staff. Further
mitigation measures developed as
national guidance information
becomes available.  
3 4 12 [T]
All Service
Managers
Head of Roads
– Ayrshire
Roads Alliance
Further control measures to
be developed/implemented
as situation develops.  4/5/23
2
Fuel Shortage Loss or restriction due to relief
events.  Relief Event: Any
event that has an effect on the
cost of performing the
Services, or the date of their
completion, including the
occurrence of risks both
foreseen and unforeseen e.g.
industrial action.
Mitigation measures in place to
prioritise front line services as
detailed in the specific Business
Continuity Plans for offices and
depots.
3 3 9 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continuation of public
support will be dependent on
outcomes, though expect
some mixed reaction.
4/5/23 
To calculate the risk rating, multiply the 
Likelihood x Severity.    Example…. 
Possible (3) X Significant (3) = Medium Risk
Critical (5)
Severe (4)
Significant (3)
Marginal (2)
Insignificant  (1)  
SEVERITY INDEX
LIKELIHOOD
INDEX
Highly probable (5) 25 20 15 10 5
Probable (4) 20 16 12 8 4
Possible (3) 15 12 9 6 3
Unlikely (2) 10 8 6 4 2
Very Unlikely (1) 5 4 3 2 1 
Incident Severity Cost (£) [C] Time [T] Reputation
Min Max Min Max
Insignificant (1) £0 £10,000 0 1 day Councillors/CEO
Marginal (2) £10,001 £50,000 1 day 2 weeks Local Media Facebook etc.
Significant (3) £50,001 £500,000 2 weeks 1 month Local Newspaper
Severe (4) £500,001 £1,000,000 1 month 3 months National Newspaper
Catastrophic (5) £1,000,001  >£1,000,001 3 months  > 6 months National News (TV)
KEY
High Risk (16 – 25) Risks are not acceptable under any circumstances. Immediate action required
Medium Risk (8 – 15) Additional controls measures may be required.
Low Risk (1 – 6) Continue to monitor as part of review process or where changes occur.
Appendix 2
19

Page 20

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
3 
Failure to align
with Budget
requirements
Level of investment required in
road repairs and resurfacing
and resulting cost of treatment
higher than anticipated. 
Reduced budget could lead to
the deterioration in the roads
network, an increase in
accidents, and insurance
costs.
Loss of parking income as a
result of changing behaviour /
work patterns due to Covid.
Uniform claims handling system
aligned with the Roads Inspection
and Maintenance policy.    
Appropriate financial and
performance monitoring
arrangements in place to mitigate the
risk.  Regular meetings with and
within partners Councils to advice on
further resource and funding
requirements. 
2 4  8 [C]
Business
Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
Adequate control measures
are in place, specifically,
monthly meetings held with
budget holders to review
revenue budget and take
appropriate corrective
actions to bring budgets
within tolerance limits. 
Monthly meeting with service
managers to review capital
budgets and programmes. 
4/5/23 
4
Adverse
Weather
Lack of trained and competent
personnel including operatives
and drivers to provide full
complement required to fulfil
all gritting routes due to lack of
volunteers for existing staff, flu
pandemic, mass resignation,
strike action and breach of
Working Time Directive and
Driver Hours Legislation. 
Procedures in place to manage a
short / medium disruption of Driver /
Operative Personnel including
banking workers and overtime
working as required.  Over the long
term there would be recruitment /
procurement of the necessary
experience to fill the gaps. 
2 4  8 [C]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
Rolling programme
established to ensure
ongoing Health and Safety
training.  Appropriate and
applicable checks are
conducted on all new drivers
to ensure that all reasonable
precautions are taken to
safeguard the ‘O’ licence,
insurance payments and
reputation.  The service has
extended the use of external
companies to provide the
winter service to increase
resilience 
4/5/23 
5 
Loss of Street
Lighting &
Traffic Signals
Extended loss of Public
Electricity supply creating
issues with Street Lighting and
Traffic Signals
Some temporary traffic signals will be
provided at key locations determined
by the Traffic Management Section
should these issues arise. 
Temporary traffic signals deployed by
RMU.  Contingency measures
detailed in Business Continuity
Plans. 
3 3  9 [T]  Traffic & Road
Safety Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider that the overall
risk is low due to the
mitigation measures that are 
in place 
4/5/23 
6
Transfer of
Shared
Services –
Ayrshire
Roads Alliance
Any failure in Service provision
would adversely affect the
resilience of the Roads
services.
Extensive negotiations have taken
place to ensure that the proposed
joint service meets stakeholders
needs 
2 2  4 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The new service is over five
years old and it is considered
that the initial transfer of the
shared service has been
completed.  Nevertheless
there will always remain
issues on transfer issues
which may still arise. 
4/5/23 
7
Council’s
Waste
Transfer
Licence
Loss off / restrictions on waste
transfer licence for all depots
Robust management systems and
procedures in place to comply with
Environmental legislation, permit
conditions and health and safety 
2 3  6 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider the overall risk
is low, due to the current
waste management systems
in operation. 
4/5/23 
8
Failure to
provide an
adequate
Failure to provide an adequate
Risk based approach and 
Inspection System in
accordance with the approved,
There are procedures in place to
manage this process:  2  4  8 [T]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Following implementation of
the  Inspection Manual: Road
Safety Inspections and
defect categorisations from 
4/5/23
20

Page 21

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
Roads
Inspection
System
Inspection Manual: Road
Safety Inspections and defect
categorisations.in accordance
with the Well-Managed
Highway Infrastructure:
A Code of Practice.
1. Short term by prioritising and
reducing other works activities
and realigning budgets;
2. Medium / long term there would
be a request for additional
budgets;
3. Operatives can be assigned from
other duties and overtime
working approved.
1st April 2019 in accordance
with the Well-Managed
Highway Infrastructure:
A Code of Practice the
Ayrshire Roads Alliance 
a) Inspects the entire road
network within East
Ayrshire and South
Ayrshire, with
performance in relation
to the percentage of
safety inspections carried
out within the timescale
being reported to the
Joint Committee under
the Performance
Scorecard standing item
on the agenda. 
b) Categorise defects in
accordance with a risk
based approach ranking
defects one to four as
detailed in the Inspection
Manual: Road Safety
Inspections and defect
categorisations 
c) Issue repair lines for
defects on carriageways
and footways with target
response times
determined by the
category of defect, as
identified in the
Inspection Manual: Road
Safety Inspections and
defect categorisations 
d) Complete the vast
majority of Category 1
defects within the target
response time of two
hours. 
9
Personnel
Shortage
Loss of trained and competent
professional staff, through
retirement.
Procedures are in place to manage
short term issues by prioritising and
reducing other works activities and
realigning budgets. 
2 3  6 [T]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
The staff numbers are
reviewed whenever there are
significant changes in staffing
level.  The Ayrshire Roads
Alliance has Modern
Apprentices who are
providing a strong foundation
for future staffing levels. 
4/5/23 
10 
Personnel
Shortage due
to:
Loss of trained and competent
personnel including operatives
and drivers due to mass
resignation, strike action and
Procedures are in place to manage a
short / medium disruption of
Technical / Supervisory / operational
Personnel including re-assignment of 
1 4  4 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider overall risk is
low due to a combination of
recruitment and selection to
fill existing vacancies.  In 
21

Page 22

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
 Strike
Action
 Driver
hour
restrictions
breach of Driver Hours
Legislation 
duties and controlled overtime
working as required.  Over long term
there would be recruitment /
procurement of the necessary
experience to fill the gaps.
addition there is increased
resilience form the external
service providers for winter  4/5/23 
11 
Adverse
Weather
Reduction and /or loss of salt
stock materials for Winter
Service operations.
There is adequate salt stock
resilience and conservation control
measures.  Transport Scotland has
strategic salt stock piles. 
1 4  4 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Service has a framework
salt supplier with a 14 day
call down delivery.  There is
a joint agreement with other
Councils to share available
salt stocks.  The existing
weather service provides
long term forecast indicating
extreme and prolonged
weather conditions. 
4/5/23 
12
Business
Continuity /
Emergency
Planning
Incident affecting one or more
of the Ayrshire Roads Alliance
service functions (including
ICT Failure).
Business continuity plans developed
for: Roads Maintenance (including
the Winter Gritting Programme);
Lighting Maintenance Unit; Network;
Design and Traffic and Road Safety
facilities within East Ayrshire and
South Ayrshire. 
2 4  8 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The overall risk is high due to
the unknown nature of such
an incident and because of
the potential reputational
damage and adverse effect
on the service delivery,
including discharge of
statutory responsibilities. 
4/5/23 
13
Benefits
Realisation
Ayrshire Roads Alliance does
not deliver the expected
benefits outlined in the
Detailed Business Case of
June 2013.
Benefit Realisation Plan to track the
delivery of each benefit and take
corrective action where appropriate it
has been developed. 
2 3  6 [C] 
Service Managers Head of Roads
– Ayrshire
Roads Alliance
The overall risk is medium
due to the various reviews
outlined in the Benefits
Realisation Strategy and
Plan now progressing
towards fruition.  Internal
management reports to be
prepared reflecting on
progress against Benefits
Realisation Strategy.  As at 1
April 2018 had realised
budget savings of £2.031m
against a target of £1.510m 
4/5/23 
14
Performance Performance Metrics are
missed.
A standardised operational process
and procedures has been developed
to ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Performance metrics are
reviewed and developed with
the Pentana System being
used to review performance. 
Performance is reviewed at
every Management meeting. 
4/5/23 
15
Procurement Insufficient due diligence
carried out by the Ayrshire
Roads Alliance in the
procurement of goods and
services.
Standardised processes and
procedures have been developed to
ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
16
Programme
Management
Programme scope, schedule,
objectives, cost and
deliverables are not clearly
defined or understood.
Clear definition of scope, schedule,
objectives, cost, and deliverables
through Service Improvement Plan,
Benefits Realisation Strategy & Plan,
and Customer Service Strategy. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23
22

Page 23

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
17
Programme
Management
Estimating and / or scheduling
errors.
A Programme Plan has been
developed which illustrates key
activities, team, timing, milestones,
and delivery of products. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
18
Programme
Management
Unplanned work that must be
accommodated.
Incorporate unplanned work within
Programme Plan and minimise
impact on delivery of products
through parallel processes when
feasible. 
1 4  4 [C]     Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
19
Programme
Management
Lack of co-ordination /
communication
Programme co-ordination and
communication conducted in
accordance with Programme
governance structure and in
accordance with PRINCE 2
principles. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
20
Programme
Management
Underestimated support
resources or overly optimistic
delivery schedule.
Support resources and delivery
schedule developed from robust
Programme Plan and previous
experience of similar Programmes. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Introduction of the
appropriate Project
Management software to
deliver a unified programme
across the Ayrshire Roads
Alliance whilst utilising plant /
resources efficiently. 
4/5/23 
21
Programme
Management
Unresolved Programme
conflicts not escalated in a
timely manner.
Programme conflicts recorded in
Issues Log and progressed in
accordance with reporting
arrangements for project team. 
2 4  8 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
22
Programme
Management
Unanticipated escalation in
Programme costs as a result
of uncontrolled changes or
continuous inflation of a
project’s scope beyond initial
remit.
Escalation of Programme costs
addressed through appropriate and
applicable corrective actions and
control measures. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
23
Programme
Management
Unanticipated delays in
Programme timescale as a
result of uncontrolled changes
or continuous inflation of a
project’s scope beyond initial
remit.
Delay of Programme timescale
addressed through appropriate and
applicable corrective actions and
control measures. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
23

Page 24

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
24
Programme
Management
Delay in earlier Programme
phases jeopardises ability to
meet programmed delivery
commitment.
Incorporate delays within updated
Programme Plan and minimise
impact on delivery of products
through parallel processes when
feasible. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
25
Programme
Management
Communication Strategy to
engage public awareness not
planned on a joint Ayrshire
basis
Ensure that a robust Communication
Strategy and response network is
developed during planning stages of
Programme which incorporates
sufficient key review stages to ensure
effective communication of key
messages regarding deliverables and
progress. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed risk, hence
reducing.  4/5/23 
26
Programme
Management
Unforeseen agreements
required to proceed with or
conclude Programme.
Engage all appropriate and
applicable requirements to ensure
that amicable arrangements are put
in place. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
27
Programme
Management
Priorities change on existing
service delivery.
Ensure that changes on existing
service delivery are communicated in
accordance with the existing Service
Level Agreement, namely that all
parties agree and will abide by the
philosophy of operating as a whole
under the principle of what is best for
the Council Tax payer, not
necessarily the individual authority. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
28
Programme
Management
Inconsistent cost, time, scope
and quality objectives resulting
in time delays and further
costs.
Ensure that cost, time, and scope
estimates along with quality
objectives are evidence based on
experience from previous
comparable Programmes. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
4/5/23 
29
Programme
Management
Affordability of future service
payments.
Ensure that East Ayrshire Council
and South Ayrshire Council are fully
aware of the budgetary implications
required to meet the on-going cost of
service provision, as detailed in the
DBC, and have fully committed
sufficient financial resources
following Business Case sign-off. 
2 4  8 [C]
Head of Roads –
Ayrshire Roads
Alliance
East Ayrshire
Council and
South Ayrshire
Council
Continue to present revenue
financial monitoring report to
Joint Committee.  Four
weekly meetings are held to
discuss revenue and capital
position of the Ayrshire
Roads Alliance. 
4/5/23 
30
Programme
Management
Councils withdraw or cannot
provide sufficient support, or
agreed level of input is not
provided resulting in
Programme delays
Early identification of problems, and
dialogue with Council.  1  4  4 [T]
Head of Roads –
Ayrshire Roads
Alliance
East Ayrshire
Council and
South Ayrshire
Council
Managed Risk. 
4/5/23 
31
Council’s
Operators
Licence (‘O’
Licence)
Loss off / restrictions on
Council’s ‘O’ Licence.
There are the correct management
controls in place, and these are
robust and appropriate.  Paperwork  2  4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continue to work with fleet
service in East Ayrshire
Council.  4/5/23
24

Page 25

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
issued to Road Traffic Commissioner
for transfer of ‘O’ Licence. 
32
Health &
Safety / Risk &
Insurance
Insufficient investment,
resources and on-going
maintenance to resolve issues
identified in Health & Safety
surveys of depots are on-
going. This also includes
ensuring security is adequate.
New harbour facility was
constructed along with
additional fencing, gates and
stillage for timber.  Dredging is
carried out bi-annually.  Works
have been completed at
lifeboat station and new sheet
piling to be installed along
timber jetty. The Ayrshire
Roads Alliance operates from
and manage risk of
enforcement action and
penalties should HSE become
involved.
Issues identified in Health and Safety
Surveys are recorded on Issues Log
along with corrective actions to rectify
/ bring up to the required standard. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
South Ayrshire Council
continues to have ownership
for and maintenance of
depots/harbour within their
area.  Responsibility of
funding the various mitigation
actions identified in the
Issues Log sits solely within
the control of South Ayrshire
Council.  East Ayrshire
Council has ownership and
responsibility for their depots. 
4/5/23 
33
Development
Control –
Road Bonds
Inadequate coupon values of
Road Bonds exposes the
Roads Authority to a potential
shortfall if the roads works
have to be completed by them
in the event that a developer
defaults.
The coupon value of Road Bonds
that are more than three years old
are reviewed to determine their
adequacy.  Where a shortfall is
identified, the developer will be
advised to increase the value of the
Road Bond held when an application
is made for an extension to the Road
Construction Consent (RCC), which
is normally valid for three years. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
If the road authority is
required to complete a
development road then only
the cost up to the value of
the Road Bond can be
recovered from the provider. 
Any shortfall has to be met
by the roads authority.  A
complete review of the
process of delivering road
bonds has been completed 
4/5/23 
34
Connect
Roads 
Residential loss of income to
the Ayrshire Roads Alliance
and expenditure incurred as a
lighting maintenance
subcontractor to Connect
Roads on the M77/Southern
Orbital, amount of exposure for
Ayrshire Roads Alliance is up
to £50,000 per year for the
main contractor.
Ayrshire Roads Alliance will reduce
exposure by limiting the amount
owing to us at any one time. 
Ayrshire Roads Alliance will insist on
payment by contractual terms or stop
doing the work. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
35
Bridges and
Structures
Inadequate inspection of
bridges and culverts for
deterioration due to aging,
increased live loads, cracking,
corrosion, environmental
effects (freeze and thaw
cycles) and fatigue
All principal bridge inspections
currently up to date in South
Ayrshire, with a rolling programme
being developed for East Ayrshire
along with additional resource for
principal inspection work.  All
General Bridge inspections are up to
date across both East Ayrshire and 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Bridges and culverts are
defined as structures with a
span in excess of 900mm.  4/5/23
25

Page 26

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
South Ayrshire.  Weak bridges are
monitored on a regular basis.  The
Ayrshire Roads Alliance provides
increased resilience in this matter. 
36
Bridges and
Structures
Inadequate maintenance of
structures, bridges and
culverts due to aging,
increased live loads, cracking
corrosion, environmental
effects (freeze and thaw
cycles) and fatigue
Rolling programme of repair,
rehabilitation or replacement (for
weak bridges) through Council
Capital Budgets. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Bridges and culverts are
defined as structures with a
span in excess of 900mm.  4/5/23 
37
Flooding Potential loss of all Grant
Aided Expenditure funding for
flooding mitigation schemes
administered by SEPA.
Seek capital funding from Council(s)
for priority flooding mitigation
schemes declared in Flood Risk
Management Plan. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Councils have a legal
duty under the Flood Risk
Management (Scotland) Act
2009 to implement flooding
mitigation schemes declared
in the Flood Risk
Management Plan. 
4/5/23 
38
Flooding Receipt of less Grant Aided
Expenditure funding than
anticipated for flooding
mitigation schemes
administered by SEPA.
Seek capital funding from Council(s)
to bridge funding gap for flooding
mitigation schemes declared in Flood
Risk Management Plan. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Councils have a legal
duty under the Flood Risk
Management (Scotland) Act
2009 to implement flooding
mitigation schemes declared
in the Flood Risk
Management Plan. 
4/5/23 
39
Flooding Potential lack of sufficient
funding for flooding mitigation
schemes if cost of schemes
exceeds Grant Aided
Expenditure (GAE) due to
Relief Events or Force
Majeure.
Seek capital funding from Council(s)
to bridge funding gap for flooding
mitigation schemes declared in Flood
Risk Management Plan. 
3 2  6 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Only 80% of principal funding
for flooding mitigation
scheme.  However increased
costs due to relief events or
force majeure is not funded. 
4/5/23 
40
Financial Potential swift decline in value
of Pound Sterling due to Force
Majeure or material adverse
change resulting in increased
costs in terms of fuel prices,
interest rates and insurance
premiums.
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business
Continuity Plans for office, depot and
harbour, as applicable 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
4/5/23 
41
Contractual
Agreement
Potential swift decline in value
of Pound Sterling followed by
market volatility over the short
to medium term resulting in
suppliers and contractors
terminating agreements due to
Force Majeure or material
adverse change.
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business
Continuity Plans for office, deport
and harbour, as applicable. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
4/5/23
26

Page 27

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
42
GDPR  The existing Data Protection
Act 2018 was brought about by
the General Data Protection
Regulation (GDPR) which is
an EU Regulation that sets out
the changes that the UK will
implement in a new Data
Protection Act.
Follow Corporate Procedures 
3 3  9 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
43
Presence of
Coal Tar within
the
carriageway
network
Coal Tar is a known material
used in the construction of
carriageways until the mid-80s
and is now known as a
carcinogen and hazardous
waste material.
Reduce the level of risk by coring all
works prior to design.
Ensure an appropriate solution within
the design is prepared which is either
to retain in-situ and record presence,
or remove and dispose of in
accordance with current guidelines. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk; Ayrshire
Roads Alliance has a duty of
care to all employees in
accordance with the Health
and Safety at Work Act
1974,Construction Design
and Management
Regulations 2015 and the
disposal of hazardous waste. 
4/5/23 
44
Service The impact of the United
Kingdom exit from the
European Union
Mitigation measures are in place to
prioritise front line services as
detailed in the specific Business
Continuity Plans for office, depot and
harbour as applicable. 
4 3  12 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed risk.  Ongoing
discussions with Transport
Scotland, COSLA and
Ayrshire Roads Alliance on
the impacts on the transport
network. 
4/5/23 
45
Transport Increased cost of vehicle
maintenance due to lack of
investment in fleet
replacement
To mitigate the risk of increased
maintenance costs through lack of
fleet investment a comprehensive
maintenance programme is in place
for all vehicles in addition to a vehicle
replacement programme developed
to identify the optimum life cycle for
fleet. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
46
Transport Workshop performance and
training levels
Without appropriate level of
performance and training provision
there is a risk to operational
performance for management of the
fleet.
To address this, performance levels
are monitored on a daily and weekly
basis and ongoing training is
provided to staff for refresher training
as well as familiarisation training on
new fleet and plant vehicles. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
47
Transport Loss of trained and competent
professional staff through
retirement or turnover
The movement of staff always has a
chance of happening but to ensure
the impact of this is minimised, an
ongoing apprenticeship programme
is in place with 2 apprentices in
transport being trained in all aspects
of fleet maintenance and repair. 
3 4  12 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Due to retirements and staff
leaving for better paid
mechanic roles elsewhere
the number of mechanics
has fallen from 10 to 7.
Multiple attempts have been
made to recruit replacement
mechanics with no success 
4/5/23
27

Page 28

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
so far. Changes have been
made to the recruitment
process in terms of
information being made
available as well as channels
used to advertise such as a
higher number of social
media websites. This issue is
being closely monitored and
further action may be
required. 
48
Transport Loss of restriction of fuel due
to any event that has an effect
on the Services provision of
fuel to departments, including
the occurrence of risks both
foreseen and unforeseen e.g.
industrial action
To mitigate the impact of losing
access or having a restricted access
to fuel, a contingency plan has been
established which sets out the
emergency management actions that
will be taken that include designated
fuelling stations and the prioritisation
of fleet, putting non-essential
vehicles off the road. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Further mitigation measures
have recently been put in
place to allow for fuel to be
drawn manually should there
be a prolonged loss of
electrical supply to the fuel
pumps. 
4/5/23 
50
Transport Loss off / restrictions on
Councils O Licence 
A comprehensive maintenance
regime has been established that
follows all guidance from DVSA and
the Traffic Commissioner to ensure
that the O-Licence is protected.
In addition, compliance activities are
established and in place and a
regular external audit is carried out
by the Freight Transport Association
every 2 years to ensure that all
processes are performing to the
required standard. 
1 5  5 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
51
Transport Loss of operational base for
any reason (Crookedholm
Depot)
To mitigate the impact of the loss of
the transport depot and garage,
business contingency plans have
been developed that highlight how
and where office based staff will work
in addition to the steps to ensure that
maintenance is undertaken, which
would be to activate external
maintenance frameworks. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
52
Transport Savings targets not achieved
(as per the Best Value Service
Review)
To mitigate the impact of the loss of
the transport depot and garage,
business contingency plans have
been developed that highlight how
and where office based staff will work
in addition to the steps to ensure that
maintenance is undertaken which 
1 3  3 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23
28

Page 29

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
would be to activate external
maintenance frameworks. 
53
Transport IT systems loss from any
cause for an extended period
may potentially effect the
operations of the transport
service which in turn will affect
service delivery and may
cause reputational damage to
the Council.
To prevent fallout from IT system
failure, a business contingency plan
has been developed as well as a
back up process to revert to paper
based recording systems for fleet
management and maintenance. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
54
Transport Failure to comply with Health
and Safety duties
To ensure that Health and Safety
processes are always followed, this
is a standing agenda item held at
monthly management meetings.  In
addition to a separate H&S group
that meets on a quarterly basis with
the H&S Officer.  Risk assessments
and safe systems of work have also
been developed and are in place with
H&S assistance. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   
4/5/23 
55
Transport Loss of utilities for an extended
time
Business continuity plans are in
place to allow for the whole service to
continue to function in the case that
utilities are lost for an extended
period of time. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
56
Transport Loss of confidential information
and appropriate handling of
information will lead to
breaches of data protection
and potential significant
financial penalties being
incurred by the Council
All staff that handle personal details
have undertaken e-learning to advise
of appropriate data protection steps
required and where appropriate
electronic systems are in place for
recording and management of
personal data to avoid paper being
lost or misplaced. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
57
Transport Passenger transport – late /
non-attendance / vehicle
breakdown by pick up vehicle
– Failure of service as Service
as user would miss Transport
link connection / arrives late at
destination activity / part
activity
The delivery of passenger transport
is managed on the Council’s behalf
by SPT.
If there is an issue where there is a
failure in service provision SPT would
be required to organise a
replacement service, working in
conjunction with Officer locally within
EAC. 
2 2  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
58
Transport Passenger transport – escort
not in attendance ASN
contracts / Council owned
vehicles service failure. 
Service not able to be provided
until escort arrives.  Server
Should an escort not be available
H&SC services would arrange to
provide another responsible
individual available to ensure that the
service can be delivered. 
1 4  4 [T]
Strategic      
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23
29

Page 30

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
user misses ac  tivity / part
activity  
In the unlikely case this cannot be
accommodated, the parent would be
notified and alternative arrangements
made for the transport of the child to
the school. 
59
Transport No driver available to deliver
service due to annual leave /
sickness absence. Service not
able to be provided service
user misses activity / part
activity
Any shortage of driver would result in
arranging for an alternative qualified
individual within transport services to
drive, or to work with Coalfield
Community Transport to deliver the
service. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
60
Transport Passenger transport :
Emergency closure of schools
and contractors unable to
provide transport within
relevant timescales
Should schools need to close
unexpectedly, all parents will be
contacted to request that children are
collected ASAP.  Teachers will
remain with children until the last one
has been collected safely by a
parent. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
61
Transport Passenger Transport:
Documentation out of date risk
to service users.  Potentially
inappropriate individuals,
inappropriate vehicles used
being used to provide service
Documentation is reviewed and
approved on an annual basis to
ensure that the correct data is held
for pupils, parents, schools and
transport operator information.  1  5  5 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
62
Transport Passenger Transport:
Contractor unable to fulfil
obligations due to bankruptcy
etc.  Service failure not able to
be provided until alternative
arrangements made.  Server
user misses activity / part
activity
SPT manage all transport on behalf
of EAC.  In the case of a contractor
going out of business, an alternative
contractor will be sought.  Where this
cannot be provided, parents will be
contacted and alternative
arrangements may need to be made
for the provision of transporting
school children such as providing a
mileage allowance to parents until an
alternative solution can be
implemented. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23 
63
Transport Failure to mitigate the potential
impacts of BREXIT including a
worst case scenario “no deal”
withdrawal
There remains a significant number
of unknown issues surrounding Brexit
as no trade deals have been struck
with the EU yet.  It is possible that
there will be impacts on time and
cost in relation to delivery of vehicles
and parts from the EU but this
remains unknown.
The service has engaged with all
suppliers to obtain up to date
information on any potential issues
that may be known and this will 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   4/5/23
30

Page 31

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
remain an ongoing process until the
final details of Brexit emerges.
64 Material
Shortages and
Price
Increases
Steel products, timber,
electrical equipment and
aggregates have seen a price
increase with aggregates
prices falling back in the
spring.
This is as a result of COVID19
affecting suppliers, supply
chains, shipping and
transportation. Construction
activity rose rapidly after
lockdown.
Increased admin at UK ports
due to EU Trade Cooperation
has resulted in increased
transportation costs and
surcharges. 
Where there are problems we are
working with supplier to optimise
deliveries to get procure best value
under the circumstances.
4 3 12 [C] Strategic
Manager
Head of Service
– Ayrshire
Roads Alliance
This will be under constant
review with contractors. 
4/5/23
65 Storage
Related Risks
Theft / Damage of Stores Risk is very low as there are many
measures that have been put in
place.  For example – CCTV
cameras, secure entry to the depots,
insurance covers all depots for theft /
damage, robust store person / key
holder procedures in place
1 4 4 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
4/5/23
66 Ash Die Back Potential for death or injury as
a result of ash dieback related
accidents, both to
professionals working on trees,
and to the general public
Increased safety issues due to
declining ash trees on roads,
owned and managed land
such as in county parks,
housing, estates, schools,
routes to school, active travel
routes and other well-used
paths
Risks to statutory functions or
service delivery such as
retaining safe schools, public
open spaces or roads
Risks to staff and community
from trees on adjacent land
falling into your estate
Ash Trees within the public network
with a fall range will be inspected and
prioritised.
P1 Immediate Felling
P2 Monitor and Fell if moved to P1
P3 Monitor and Fell if moved to P1
Private landowners will be advised of
any trees within their land which
could impact on the public network.
Under Road Scotland Act 1984 ARA
have the authority to pursue
landowners and remove diseased
trees and recharge
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
4/5/23
31

Page 32

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
67  Ukrainian Crisis 
Increasing cost of bitumen and
the potential of short supply
due to Russian sanctions and
increased costs.
Pre-programming with suppliers and
contractors.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   4/5/23
68  Impact on Fuel
No longer permitted to use red
diesel within construction
vehicles. This has an impact
on project costs and the
overall programme.
Reviewing alternative forms of fleet,
however, this brings additional cost.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   4/5/23
69 Avian Flu Supporting SAC in lifting bird
carcasses.
Appropriate disposable PPE and
Face fit masks
4 3 12(R) Strategic
Manager
Head of
Ayrshire Roads
Alliance 
4/5/23 
32

Page 33

THE AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
19 MAY 2023 
Report by the Head of Roads - Ayrshire Roads Alliance 
AYRSHIRE ROADS ALLIANCE 
SERVICE PLAN 2023/24 
PURPOSE OF REPORT 
1 The purpose of this Report is to seek the Joint Committee approval for the Ayrshire
Roads Alliance Service Plan for 2023/24. 
RECOMMENDATIONS 
2 It is recommended that the Joint Committee: 
i. Approves the Ayrshire Roads Alliance Service Plan for 2023/24,
ii. Notes the confirmed finance budgets for 2023/24
iii. Notes the Performance Scorecard for 2022/23
iv. Requests that progress updates are provided to future meetings of the
Joint Committee,
v. Otherwise, notes the content of this Report. 
MAIN REPORT/MAIN ISSUES 
3 The first Ayrshire Roads Alliance Service Plan for 2014/15 was approved by Joint
Committee on 23 May 2014.  As part of all Service Plans it was agreed that the draft
Service Plan is approved prior to submission to both East Ayrshire Council and
South Ayrshire Council. 
4 The service plan included in Appendix One provides detail on the current operating
position of the Ayrshire Roads Alliance and indicates the position where the Service
will be by March 2024.   
Details are provided for the activities to be undertaken to achieve these goals
through: 
• The ten year review;
• the Performance Management Framework as approved and updated at every
Joint Committee;  
• the Risk Register and Report which has established a method of effective
management of risk to ensure service improvement through better service
delivery; increased certainty and fewer surprises; more effective and efficient
Agenda Item 6
33

Page 34

management of resources; reduced waste; and better management at all
levels through improved decision-making; and
• the Benefits Realisation Strategy and Plan which sets out how benefits will be
tracked and controlled across the fully integrated Roads service and which
was approved by the Joint Committee in on 1 May 2015. 
5 The Service Plan describes the challenges and the targets for the service. 
6 In addition to Revenue Budgets, the Ayrshire Roads Alliance receives budgets from
other sources including capital, and grants from the Scottish Government,
Strathclyde Partnership for Transport; and other organisations including both
external to the Council and Council Departments. 
POLICY/COMMUNITY PLAN IMPLICATIONS 
8 A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain good
access to our communities within East Ayrshire. 
9 The matters referred to in this report contribute to Priority 1 of the Council Plan: 
Spaces and Places/ Moving around and the environment (Outcome 1). 
LEGAL IMPLICATIONS 
10 The work of the Ayrshire Roads Alliance is undertaken in accordance with relevant
legislation. 
HUMAN RESOURCES IMPLICATIONS 
11 The Service Plan has no direct impact on human resources.  However, as the
Improvement Action Plan work develops, and reviews are completed, it is expected
that some impact on human resources will arise. 
EQUALITY IMPACT IMPLICATIONS 
12 The Risk Register complements the Equality Impact Assessment by ensuring that
any issues arising are adequately prioritised, managed and either eliminated or
mitigated. 
34

Page 35

FINANCIAL IMPLICATIONS 
13 The Ayrshire Roads Alliance delivers the strategic and local services as stated in the
Service Plan.  The budget is provided by East Ayrshire Council, South Ayrshire
Council, and other external organisations.  Appropriate scrutiny arrangements are in
place to manage these budgets. 
RISK IMPLICATIONS 
14 The Risk Register assists in the prioritisation of risks that need to be mitigated by the
Ayrshire Roads Alliance in order to reduce the overall risk to either Council and to
comply with the Community Plan/Council Plan in both partner bodies. 
TRANSFORMATION STRATEGY 
15 This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”. 
• “Maximum value for our communities”, by ensuring the various elements of
the Transport (Scotland) Bill enacted will improve Transport provision
throughout East Ayrshire.
BACKGROUND PAPERS 
1 Benefits Realisation Strategy And Plan  - 1 May 2015 – Joint Committee 
LIST OF APPENDICES 
1 The Ayrshire Roads Alliance Service Plan - 2023/24 
2 Ayrshire Roads Alliance Performance Scorecard 2022/23 
Kevin Braidwood
Head of Roads - Ayrshire Roads Alliance 
03 May 2023 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org
35

Page 36

1
Service Plan 2023-2024
May 2023
A Partnership between East Ayrshire Council and South Ayrshire Council
Appendix
36

Page 37

2
Table of Contents
INTRODUCTION ............................................................................................................................................ 3
STRATEGIC CONTEXT .................................................................................................................................. 14
SERVICE PERFORMANCE FRAMEWORK ...................................................................................................... 15
RISK, OPPORTUNITIES and CHALLENGES .................................................................................................... 18
PROFILE OF SAVINGS AND COSTS OVER THE FIRST 10 YEARS .................................................................... 22
AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2023/24........................................................ 24
APPENDIX 1 – ORGANISATIONAL CHART ................................................................................................... 33
APPENDIX 2-STRATEGIC AND LOCAL DELIVERY SPLIT SPLIT……………………………………………………………………35
37

Page 38

3 
INTRODUCTION 
The Ayrshire Roads Alliance is a shared integrated roads and transportation service
which provides the roads service for East Ayrshire Council and South Ayrshire Council. 
The Service is delivered with the overall objective of improving the road and
transportation service in the East Ayrshire and South Ayrshire areas to move the
Ayrshire Roads Alliance to a position that will deliver at least £8.634 million of savings
by 2024.   
The Ayrshire Roads Alliance is governed by the Ayrshire Shared Service Joint
Committee.  The Joint Committee has responsibility for all shared Council services in
Ayrshire.   
The Shared Services Minute of Agreement describes the functions of the Joint
Committee as follows: 
• making decisions within the confines of the service budget, 
• developing and implementing a strategic policy framework,
• co-ordinating, monitoring and reviewing service performance,
• monitoring budget spend,
• considering and approving an annual Service Plan. 
In addition, the "Joint Committee Arrangements for the Ayrshire Roads Alliance"
document covers those issues that are specific to the Ayrshire Roads Alliance. 
The two Councils involved in the Ayrshire Roads Alliance have each appointed four
Elected Members to the Joint Committee.  Meetings take place as often as required to
conduct business, but at least twice per year in line with the terms of the Minute of
Agreement.   
The Alliance is responsible for all the roads and transportation activities listed in
Appendix 2, split between strategic and local delivery, that are the responsibility of East
Ayrshire Council and South Ayrshire Council.  Both Authorities retain the role of Roads
Authority under the Roads (Scotland) Act 1984 - Section 1.   
38

Page 39

4 
East Ayrshire Council - Strategic Issues 
The East Ayrshire Community Plan is the sovereign and overarching planning
document for the East Ayrshire area, providing the strategic policy framework for the
delivery of public services by all local Partners.  The Plan is the Council’s Corporate
Plan and covers the 15 years from 2015 to 2030. 
The Vision contained within the Community Plan is shared by all Partners and states
that: 
“East Ayrshire is a place with strong, safe, vibrant communities where
everyone has a good quality of life and access to opportunities, choices
and high quality services which are sustainable, accessible and meet
people’s needs.”
The Community Plan is implemented through three thematic Delivery Plans - Economy
and Skills, Safer Communities and Wellbeing.  The Plan is also implemented through
the day to day work carried out by services across the Council. 
East Ayrshire Council Strategic Plan 2022-2027 
This plan sets out our priorities for the communities of East Ayrshire over the next five
years and describes the context in which our services will work collaboratively with
each other, our communities and our partners to drive forward the actions needed to
achieve our aims. This will include prioritising the resources that are entrusted to us and
continuing to find new and innovative ways of working, to ensure the delivery of
services that are affordable, sustainable and which best meet the needs of those we
serve. The Plan recognises the strengths and assets that exist within East Ayrshire and
highlights the ambitions we have for our communities. However, it is written against a
backdrop of what are unprecedented challenges for both our Council and for those we
serve. These challenges include: 
• Rising inflation and increases in the cost of living 
• Increased demand for services 
• Restrictions in funding
• Pandemic Recovery and Renewal 
• Public Sector Reform 
• The impact of EU Exit 
The Strategic Plan priorities take account of the communities we serve, including local
needs, circumstances and aspirations; the current internal and external context in which
the Council operates; national and local drivers for change, including risks, challenges
and opportunities; governance arrangements; programme management and
performance measurement. Our priorities build on the work of our previous two
Transformation Strategies and our Covid-19 Recovery and Renewal Dynamic Action
Plan. It is important to recognise that there are commonalities and interdependencies
across and between our priorities. 
• Building a Fairer Economy
39

Page 40

5 
• Tackling Poverty and Inequality
• Improving Community Wellbeing
• Supporting Children and Young People
• Delivering a Clean, Green East Ayrshire
• Ensuring Financial Sustainability and Resilience 
Service Improvement Plans are an essential element of the Council’s performance
management and improvement framework.  They set out the key issues for
delivering services in support of the Community Plan Vision and priorities, provide a
focus on performance improvement aligned to the Single Outcome Agreement and
describe the service specific risks that may impact on the delivery of the Service. 
The diagram below provides a graphic representation of the Council’s Policy Planning
Framework and shows the strategic context within which the Service Improvement
Plans sit.  In addition it shows the wider Performance Management and Improvement
Framework which the Council has adopted to ensure the rigorous scrutiny of
performance and drive service improvement across the Council. 
40

Page 41

6 
South Ayrshire Council - Strategic Issues 
The Council Plan 2023-2028 sets out the Council’s vision for the next five years, with a
focus on “Our Pupose”,Our Vision”,”Our Values”.  The Plan details the high-level
objectives and outcomes to be achieved by 2028. 
The Council’s priorities and outcomes place an emphasis on the connection between
our places and the wellbeing of our communities and environment. The place-based
approach recognises that every area has a different blend of physical, social, and
economic characteristics that influence each other and aims to address complex
problems that no service alone can solve. The priorities provide a common framework,
aimed at promoting a shared understanding that encourages services and partners to
work collaboratively to achieve improved outcomes and wellbeing for our communities. 
• Priority One Spaces and Places
• Priority Two Live, Work, Learn
• Priority Three Civic and Community Pride 
The Ayrshire Regional Growth Deal 
The three Ayrshire Councils have worked in partnership with other agencies,
communities and businesses to secure the first Regional Growth Deal in Scotland.  This
will see £251.5 million of investment in key assets and key sectors across Ayrshire,
underpinned by an ambition to facilitate economic growth across the region.  The
projects within the Growth Deal offer the best opportunity to attract private sector
investment into Ayrshire and to transform the area.  It is considered that the various
interventions in the Growth Deal will unlock £300 million of private investment and
deliver around 7,000 new jobs across a wide range of sectors. 
The vision is for Ayrshire to be “a vibrant, outward looking, confident region,
attractive to investors and visitors, making a major contribution to Scotland’s
growth and local well-being, and leading the implementation of digital
technologies and the next generation of manufacturing.” 
Project proposals and associated outline business cases have been prepared,
reviewed, assessed and refined following feedback received from policy leads with the
United Kingdom and Scottish Government and these now form the overall programme
business case. 
The Heads of Terms for the Ayrshire Growth Deal were signed on 8 March 2019. 
Partners are now working with Governments to agree the profiling and phasing of
projects and the development of full business cases for those projects.   
The figure below illustrates how the Ayrshire Growth Deal programme links to the
Governments’ objectives of increased growth and prosperity.  The programme is based
on the achievement of economic growth and inclusive growth with a clear focus on
addressing the issues of innovation and productivity, and inequality across the regional
economy. 
41

Page 42

7 
There are no transport projects within the current Ayrshire Growth Deal proposals
outwith the areas where development is proposed.  Connectivity and accessibility are
key tenets of the Deal, and transport infrastructure will be essential to securing
Ayrshire’s economic growth. 
Funding for Prestwick Transport Infrastructure will create an effective network of
internal roads to enable the creation of high specification industrial and office spaces,
while supporting our sustainable transport aims. This investment will meet the needs of
the growing aerospace sector, advanced manufacturing units, spaceport and launch
operator infrastructure.
There are three elements to this project as follows:
• Work package 1 – Prestwick East Aerospace Park Link Road – a new and
upgraded road infrastructure to link the B739 Station Road from a redesigned
roundabout junction on the A79 to the Prestwick East Aerospace Park. This
includes Spirit Campus and the airport development land to the north of the main
runway, by-passing Monkton village.
• Work package 2 – A new route corridor to extend the link road infrastructure from
Prestwick East Aerospace Park to the northern edge of the airport site and connect
the Gannet site.
• Work package 3 – A new road infrastructure to service Spaceport and further
aerospace development land from Sandyford Toll roundabout and link to Prestwick
East Aerospace Park.
This project will be funded by £12 million from the Scottish Government, and £5 million
from South Ayrshire Council. 
Ayrshire Roads Alliance will deliver these projects for South Ayrshire Council.
42

Page 43

8 
STPR2 
Ayrshire’s key transport routes (road, rail, sea and air) are critical for businesses to
enable goods to get to market, our communities to employment and for training
opportunities.  A number of key route improvements have been identified. 
The current Strategic Transport Projects Review for the 20 year period from 2012 deals
with just road and rail modes of transport.  The new Strategic Transport Projects
Review was published in December 2022 and included all modes of travel including
active travel and public transport.  In addition, this work will develop transport projects
outputs at a national, regional and local level. 
Due to Covid-19, Transport Scotland restructured the STPR2 into two phases. Phase 1 
focussed on the short-term (up to 5 years) with a view to identifying interventions which
can be accelerated to support a green economic recovery from Covid-19, and also
those which embed, support and extend any increase in travel by sustainable travel
modes, including positive behaviour change seen during the pandemic. Phase 2
completed the review and the report was published in December 2022, giving Scottish
Ministers a programme of potential transport investment opportunities for the period
2022-2042.A delivery programme is yet to be published. 
Levelling Up Fund 
The Fund provides £4.8bn capital investment allocated through a competitive bid
process that will operate from 2021/22 through to 2024/25.  Total funding of £800m
from the quantum has been allocated to Scotland, Wales and Northern Ireland 
with Scotland guaranteed to receive at least 9% (£432m) of the overall UK total.  The
fund will be jointly managed by the Ministry of Housing, Communities and Local
Government (MHCLG), the Department for Transport (DfT) and HM Treasury. 
Ayrshire Roads Alliance submitted two bids on behalf of East Ayrshire and South
Ayrshire Council. 
• Bellfield Interchange Improvement 
• Active Travel Route Ayr to Prestwick 
Both bids were unsuccessful in Round 2 however it is proposed that these will form part
of our round 3 submission. 
43

Page 44

9 
Our Current Service Resources 
Table 1 – The Ayrshire Roads Alliance Assets (as at 31 March 2022)
Asset Inventory Data as of 31st March 2022
Asset Type Units East Ayrshire
Council
South Ayrshire
Council
Totals
Carriageway km 1,222 1,182 2,404
Footways & Footpaths km 1,028 940 1,915
Street Lighting Columns No. 20,436 19,612 40,048
Illuminated Signs &
Bollards
No. 1,442 1,110 2,552
Structures  No. 618 369 987
Retaining Walls km 7 3 10
Length of Sea Defences km 0 24 24
Piers and Harbours No 0 1 1
Cattle Grids No. 11 34 45
Traffic Signals No. of Sets 79 74 153
Variable Message Signs No. 125 10 135
Vehicle Activated Signs No. 154 57 211
Real Time Passenger
Information
No. 66 48 114
Gullies No. 27,257 26,350 53,607
Grit Bins No. 593 259 852
Weather Stations No. 3 1 4
EV Dual Chargers No 54 36 90
Depots No 1 2 3
44

Page 45

10 
Staff in the Ayrshire Roads Alliance 
Staff, Property and Fleet 
The Ayrshire Roads Alliance has depots located at Gauchalland in Galston;
Meadowhead in Coylton and Grangestone in Girvan.  Offices are located in Kilmarnock,
Ayr and at Girvan Harbour.  We also have extensive vehicles, plant and equipment to
allow our service to be delivered.   
There will be an ongoing need for property and accommodation across the area for the
Ayrshire Roads Alliance; for vehicle and equipment storage; and maintenance and staff
facilities.  It is important that property and accommodation is safe, secure, fit for
purpose, and strategically placed to minimise the time spent travelling from depot to
workplace to maintain the road asset, minimise the associated vehicle wear and tear,
and emissions. 
From April 2014, the following actions have been taken in relation to property and
accommodation: 
• Gauchalland Depot - Street lighting operations have moved from Munro Place in
Kilmarnock to Galston. 
Head
of Service
Strategic
Manager
Strategic  
Manager
• Traffic & Road Safety
• Transportation
• Roads & Structures
Design
• Environmental
• Asset Management
• Development Control
• Parking
• Roadworks Co-ordination
• Street Lighting Network
• Network East
• Network South
• Structural Road Maintenance
• Routine and Cyclic
Maintenance
• Winter & other Civil
Emergency Provision
• Piers and Harbours
• Support Services
• Finance
• IT support
45

Page 46

11 
• The street lighting technical team is located at the Johnnie Walker Bond in
Kilmarnock which now provides a more centralised service.  This involved some
staff transferring from Burns House in Ayr.
• The closure of the Underwood Depot in Cumnock has seen staff re-located to the
Gauchalland Depot in Galston.
• All salt for the Ayrshire Roads Alliance previously stored in the Underwood Depot
is now distributed from the Meadowhead Depot in Coylton.  
• A rationalisation of fleet across the Ayrshire Roads Alliance has taken place
resulting in a reduction in cost. 
Further office developments include staff transferring from the Johnnie Walker Bond to
the Opera House in Kilmarnock and from Burns House to Wellington Square and Town
Hall in Ayr which was restricted due to COVID guidance. 
Staff have now returned to the Opera House Kilmarnock on a rota based model with
posts designated as fixed, flexible and mobile. 
Staff returned to County Buildings and Ayr Town Hall in June 2022 on a rota hybrid
model. 
Depots at Galston, Ayr and Girvan are fully operational 
Our key messages from this work include:
The Ayrshire Roads Alliance completed an organisational review which delivers the
current management structure which has generated £326,000 of revenue savings per
year.  This will contribute £2.242 million towards the Business Case savings target of
£8.634 million.  The Joint Committee agreed to this review on 1 April 2016, and the
work was completed during 2017/18.  In accordance with good management practice
the Alliance continued to review staff provision, and completed the service re-design
during 2021/22 with management actions realising a saving of £190,000,parking
£86,000 and £293,000 in South Ayrshire. 
The Ayrshire Roads Alliance completed a depot review which will result in £404,362 of
revenue savings by 2024.  This included the closure of the Underwood Depot with staff
transferring to Gauchalland Depot; and the Munro Place Street Lighting Depot with all
street lighting staff now being based in Gauchalland.  In accordance with good
management practice the Alliance will continue to review depot and accommodation
provision. 
The Ayrshire Roads Alliance has completed the fleet review which will result in
£1,350,699 of revenue savings by 2024.  In accordance with good management
practice the Alliance will continue to review fleet and plant provision. 
Budgets
The Ayrshire Roads Alliance delivers the strategic and local services as stated in this
Service Plan and listed in Appendix 2.   
46

Page 47

12 
The budget to deliver these services is provided from East Ayrshire Council, South
Ayrshire Council, and other external organisations. 
budgets for 2023/24 are confirmed and this is reflected in Tables 1 and 2. 
Table 1 - Budgets 2023/24  
Council Revenue  Non - Revenue Total (£m)
East
Ayrshire
Council 6.286 14.040 20.326
South
Ayrshire
Council 
6.284 4.464 10.748
Total 12.570 18.504 31.074 
Table 2 provides the current non-revenue budgets for 2023/24 
Table 2- Non-Revenue Budgets 
Funding Source Type/Level of Funding Annual Budget 2023/24
East Ayrshire Council
Carriageway, 
Footway 
Street Lighting.
Traffic, Transportation &
Road Safety. 
Bridges & Culvert
Replacement.
Other works 
Kilmarnock Car Parks
School Streets
EV Charging 
£3.240m
£0.250m
£0.250m
£0.315m 
£4.100m 
£0.080m
£2.939m
£0.100m
£0.100m 
Current approved budget
£14.040m at Cabinet
meeting of 8 March 2023.  
Scottish Government Cycling Walking and Safer Streets.
Smarter Choices, Smarter Places.
Deliver the Local Flood Risk
Management Plan.
New Cumnock.  Grant funding
equivalent to 80% of scheme
estimate of £6.29 million. 
£3.375m
Strathclyde Partnership
for Transport
General funding  £1.82m
Sustrans Projects  TBC
SFT Funding for Strategic Strategy for
Public charging
£0.060m 
Scottish Timber Transport Projects TBC 
47

Page 48

13 
Group
LED Street Lighting
Replacement 
LED Replacement £3.650m 
Funding Source Type/Level of Funding Annual Budget 2023/24
South Ayrshire Council 
Roads Improvement Plan
Bridge Works 
Street Lighting 
Traffic Signals
Girvan Harbour
EV Charging 
£2.812m
£0.410m
£0.250m
£0.290m
£0.569m
£0.190m 
£4.464m (Confirmed at
Cabinet meeting on 25
April 2023)
Scottish Government Cycling Walking and Safer Streets. 
Smarter Choices, Smarter Places.
Deliver the Local Flood Risk
Management Plan. 
£2.418m 
Strathclyde Partnership
for Transport
General funding  £700,000
Sustrans Projects  £1.300m
SFT Funding for Strategic Strategy for
Public charging 
£0.060m
Scottish Timber
Transport Group
Projects TBC
48

Page 49

14 
STRATEGIC CONTEXT 
EAST AYRSHIRE COUNCIL 
The Community Plan 2015 - 2030 includes a Safer Communities Delivery Plan, which
sets out the key actions to be undertaken and also measures progress.  The Delivery
Plan contains three distinct strategic priorities, all of which will be influenced by the
activities undertaken by the Ayrshire Roads Alliance. These are: 
• Make East Ayrshire a safe, secure and attractive place to live, work and visit.
• Improve community safety in neighbourhoods and homes and protect and
support our most vulnerable individuals and families.
• Promote our vibrant communities by encouraging active and responsible
citizenship. 
Single Outcome Agreement (SOA)
The SOA was reviewed and developed as a key element of the comprehensive review
of the Community Plan to ensure alignment with strategic priorities and high level
local outcomes.  There are a number of National Outcomes which are supported by
the activities undertaken by the Ayrshire Roads Alliance.  The Community Planning
Partnership receives an annual report in September each year at which they are advised
of progress against the local outcomes previously agreed. 
SOUTH AYRSHIRE COUNCIL – 
The Local Outcomes Improvement Plan and Local Place Plans were introduced in
2017.  The plan focuses on two strategic themes which emerged from the development
process.  
• Closing the poverty-related outcomes gap for children and young people in 
South Ayrshire 
• Supporting older people to live in good health 
The Plan is supported by a partnership wide focus on four priority areas  
• Improving outcomes for looked after children and care leavers 
• Providing support for young people who are carers 
• Reducing social isolation and loneliness 
• Support for people living with dementia and their carers 
There will be an effort to improve outcomes for children and older people particularly in
the Ayr North and Girvan Glendoune areas, and to identify transferable good practice to
be used to support outcomes improvement in other parts of South Ayrshire.  The work
on progressing this work is taking place within the auspices of the Integrated Children’s
Services Strategic Delivery Partnerships and the Health and Social Care Partnership
and this is supported by appropriate partnership work.  
49

Page 50

15 
SERVICE PERFORMANCE FRAMEWORK 
PERFORMANCE AND BENCHMARKING 
The Councils’ performance management frameworks operate on a number of
levels providing detail on strategic priorities, operational priorities and day to day
management information.  Within the Ayrshire Roads Alliance, the approach is fully
integrated and aligned with the corporate frameworks. 
• Strategic (Community Plan and Single Outcome Agreement; and Local
Outcomes Improvement Plan)
• Operational Priorities (Council performance indicators)
• Management information (operational statistics, corporate measures of
performance) 
Strategic Issues
East Ayrshire Community Plan 2015-30.  The Community Plan includes three
Delivery Plans, which set out the key actions to be undertaken and measures to
progress against them.  The Delivery  Plans  contains  distinct  strategic  priorities, 
which  will  be  influenced  by  the  activities undertaken by the Ayrshire Roads
Alliance Service. 
Single Outcome Agreement.  The single outcome agreement has been reviewed and
developed as a key element of the comprehensive review of the Community Plan in
2014/15 to ensure alignment with strategic priorities and high level local outcomes. 
Operational Issues
Council Performance Indicators.   
The Ayrshire Roads Alliance reports on a number of performance indicators through an
electronic Performance Management System.  A management framework has been
developed, which has been approved by the Joint Committee.  The data includes both
contextual and performance information thereby allowing statutory returns to be made
facilitate benchmarking provide each Council and the Joint Committee with the
information they require to monitor performance. 
A performance scorecard is produced as an integral part of the Ayrshire Roads Alliance
which is reviewed at the monthly Ayrshire Roads Alliance Management Team meetings
and reported to every Joint Committee. 
This scorecard is used to:
• monitor the progress in meeting the Ayrshire Roads Alliance’s objectives;
• help managers to have performance-related conversations with staff; 
• identify any problem areas that need addressed. 
50

Page 51

16 
Performance Management System
Relevant information contained within the Performance Management System is
provided for each four week period in a scorecard which is used by the Depute
Chief Executive (Safer Communities) and the Head of Service to monitor
performance activity and improvement within their respective management team
meetings. 
SCOTS/APSE Benchmarking Framework 
The Society of Chief Officers of Transportation in Scotland (SCOTS) and the
Association for Public Sector Excellence (APSE) have developed a series of indicators
to utilise SCOTS definitions using a single template. 
The Alliance participates in the SCOTS/APSE benchmarking framework through the
APSE Annual Return; the SCOTS/Institution of Civil Engineers “state of the network”
annual return; and the Scottish Road Maintenance Condition Survey. 
Local Government Benchmarking Framework  
The Local Government Benchmarking Framework (LGBF) collates information from
the APSE Annual Return that is published by the Improvement Service with specific
actions to improve performance. 
Monitoring and Review 
Monitoring of the service plan is the responsibility of the Joint Committee.  An annual
review will be completed and reported to the Joint Committee and both Councils.  The
Joint Committee will receive a six monthly update on the Service Plan progress.  In
addition, separate monthly meetings are held with the Depute Chief Executive
responsible for the provision of the roads service within East Ayrshire Council; and the
Executive Director responsible for the provision of the roads service within South
Ayrshire Council. 
Scrutiny in respect of the Joint Committee is undertaken by both Councils in
accordance with their own processes as set out within their respective Corporate
Governance arrangements.  Matters in relation to service performance will be closely
monitored by both Councils through the Joint Committee.   
QUALITY MANAGEMENT AND ASSESSMENT
European Foundation for Quality Management (EFQM) Excellence Model
The European Foundation for Quality Management (EFQM) Excellence Model is a
practical self-assessment tool designed to promote continuous improvement within
organisations by assessing their performance against concepts of tested and
recognised good management practice.  The EFQM Model is the cornerstone of Best
Value.  The service also has an externally accredited Quality Management System. 
51

Page 52

17 
ENGAGEMENT WITH SERVICE USERS 
The Ayrshire Roads Alliance will continue to undertake engagement with relevant
service users.  This engagement will take a number of forms through informing,
consulting, involving, collaborating or empowering our service users. 
Through 2023/24 we will continue engagement with our customers to ensure we
maximise the involvement of our service users. 
The Association for Public Service Excellence (APSE) who work with over 300 Councils
through the UK to promote excellence in the delivery of frontline services to our local
communities have developed the Scotland Roads Survey in conjunction with the
Society of Chief Officers of Transportation in Scotland (SCOTS). 
The Survey will be used to gauge customer service customer service and user
experience/satisfaction of winter gritting, road works, road safety and other road
maintenance related matters within East Ayrshire Council and South Ayrshire Council. 
The information gathered from the survey will help shape future service delivery and
inform on performance. 
APSE will administer the survey on our behalf and it is expected that the first results will
be published in the 2024 Roads Asset Management Plan (RAMP) update. 
The link on the Ayrshire Roads Alliance website to the East Ayrshire Council and the
South Ayrshire Council survey forms is below 
https://www.ayrshireroadsalliance.org/Information-On/Consultations/the-association-for-
public-service-excellence-apse-road-condition-survey.aspx 
CONSULTATION WITH EMPLOYEES 
Employee Engagement 
The Employee Attitude Survey identified a number of issues to be addressed.  
Employee engagement will continue through 2023/24 and this will take many forms
including management meetings; team meetings and staff forums.  The staff forums will
take place when important Council or service information requires to be provided to
staff.  One of the main issues for 2021/22 was the transformation strategy for Ayrshire
Roads Alliance and implemented April 2022. 
Trade Union Meetings 
The Alliance will continue to engage with the Trade Unions through the established JCC
process which involves meetings at a Corporate; Service and work specific level.   
52

Page 53

18 
RISK, OPPORTUNITIES and CHALLENGES 
Risk 
The Ayrshire Roads Alliance records risk using a “five by five” scoring matrix, for the
risks identified which quantifies the assessment of the likelihood and severity of a
particular risk occurring.  This information is hosted on the Performance Management
System and it is used to understand the impact of proposed controls and mitigations on
the overall risk profile.  This is a widely used tool in risk management.   
The service risk register, and the Corporate Risk Registers, are aligned to the approach
of identifying and recording risk, which ensures a consistent approach to service level
risk recording.  This allows service objectives and priorities, performance measures and
service risks to be captured in a single document.  These areas are closely aligned, and
this approach offers benefits in business planning, service delivery, and performance
and risk management. 
The risk register for the Ayrshire Roads Alliance is presented to every meeting of the
Joint Committee. 
There continues to be a number of opportunities and challenges which the Ayrshire
Roads Alliance faces over the next twelve months. 
Opportunities  
The opportunities include the following 
• Although the Organisational Review was approved by Joint Committee on 1 April
2016 and implemented during 2017/18, we continued to review staff provision
during 2020/21 as part of service re-design reported and approved by Cabinet 23
February 2022 the transformation and redesign was implemented from 1 April
2022. 
• The Plant & Fleet review from June 2016 was implemented immediately. 
However, with new technology and the need to increase the number of electric
vehicles then all plant and fleet will continue to be reviewed during 2022/23. 
• The property and accommodation review from November 2016 and all the
actions have been implemented.  Nevertheless, with more agile and remote
working, the Alliance will continue to review these issues during 2022/23, as part
of the service re-design. 
• The opportunity to continue to make significant revenue budget savings through
the replacement of existing street lighting units with LED units cannot be
understated.  Work commenced in 2018/19 with work programmed to be
completed in 2021/22, however completion has been delayed due to COVID and
the impact of material shortages...  It was expected that street lighting revenue
delivery cost would reduce by more than 50%, however, the current challenge
53

Page 54

19 
against this, is the current rising energy costs as a result of wider economic
issues. 
• Use of Digital software to improve our gully, culvert, and harbour infrastructure 
management 
• Moving all our permits over to a digital platform and our TTRO process was
recognised in March 2023 at APSE Innovation awards. 
• Ten year review of the business plan. 
Challenges 
There are a number of challenges the Ayrshire Roads Alliance will face in 2023/24
which include the following.
External
• There is the potential to increase the utilisation of electric cars and vans to
comply with emission standards and the Scottish Government decision to ensure
that all new cars and vans are not powered through fossil fuel means by 2030. 
This will result in the reduction in harmful emissions, and an improvement to air
quality. 
• The Transport (Scotland) Bill places increased emphasis on low emission zones;
smarter ticketing arrangements; the increased role and powers for the
Roadworks Commissioner; the ban on pavement and double parking; the
workplace parking levy and the ability for Councils to run public bus services. 
• The National Transport Strategy will focus on sustainable, inclusive and
accessible transport systems to promote prosperity, health and fairness.  The
Sustainable Transport Hierarchy will be used to inform budgetary decisions
with walking first; then cycling; public transport; taxis and shared transport and
then the private car.  There is a need on many levels for more active travel and
public transport use across Scotland.  The Sustainable Investment Hierarchy
will be used to inform budgetary decisions – reduce the need to travel; maintain
existing assets; make better use of existing capacity; and finally targeted
infrastructure improvements. 
• The National Transport Strategy has identified the need to focus on increased
collaboration, and this was considered through the Roles and Responsibilities
Working Group which made recommendations to the Scottish Ministers including
that future transport governance arrangements should be on the basis of some
form of regional model allowing for variations in approach between different
geographic regions; and 
• There is the potential for continuous increases in the unit costs of electricity due
to on-going energy costs.  The Department of Energy and Climate Change has
predicted that electricity prices are likely to double within the next ten years.
54

Page 55

20 
SCOTS reported a 20% increase in energy costs with a further increases
expected in 2023/24. 
• However, provided the programme for LED lights is completed then the impact of
this specific challenge may be reduced.   
• Ensure the current Regional Transport Appraisal work aligns with the needs of
East Ayrshire and South Ayrshire Council. 
• Rising costs of oil based products and construction materials as a result of
ongoing world issues with Bitumen and coated road stone increasing by 12%. 
• Rising costs and shortage of general construction materials, steel, and high
value electrical products. 
• Changes to the use of rebated fuel (Red Diesel) for construction plant has seen
an increase in overall fuel costs. 
Internal
• There are increased austerity measures resulting in need to drive further
efficiency savings over and above the £8.634m identified in the Benefits
Realisation Strategy & Plan which was presented to Joint Committee on 1 May
2015. 
• The need to increase the level of mobile working across the Ayrshire Roads
Alliance workforce as a direct result of implementing the Roads Asset
Management Plan and the impact of COVID.  This has resulted in an increase in
mobile technology, full use of the WDM Roads Maintenance and Management
System, Artificial Intelligence and the decrease in the demand for desk and office
space. As a result of COVID many of the aforementioned have been accelerated
by the service in particular reduced desk space, mobile technology and the
implementation of Artificial Intelligence, training has been delivered on this
particular element for operational use from April 2022. 
• The rise in demand for electricity charging points as a direct result of the greater
number of electric vehicles and the Scottish Government initiative to ban the sale
of new fossil fuel powered cars and vans from 2030. 
• The impact of an ageing workforce and the need to ensure an appropriate
knowledge transfer and succession planning; and service re-design. Work
around this was carried out over 21/22 with a greater emphasis on the service
being more resilient with an amended structure to be more community focused
along with Modern Apprenticeships and trainee opportunities. 
55

Page 56

21 
Resilience
• Continue to engage with community councils and community groups to improve
local winter and flooding resilience.  This allows these groups to take ownership
of gritting the footpaths and minor roads; and attend minor flooding events and
report them directly to the Alliance for action.  The uptake to date has been
encouraging and risen to 160 groups. This resilience work was recognised by the
National Highways Industry in October 2021 and APSE in March 2022. 
• Decreasing requirements for desk and office space due to the increase in
mobilisation of workforce from the developing Roads Asset Management Plan
using the WDM system and working patterns amended due to COVID will see an
increase in ‘hot desking’ and access to welfare facilities at key strategic locations
throughout the geographical area of the Ayrshire Roads Alliance, through service
re-design. 
• Improved adverse weather resilience during periods of heavy rain, and severe
snow conditions. 
• Ensuring improved resilience as a measure of our ability to successfully absorb
future  changes; to reshape ourselves; and a strategic capability to thrive.  
56

Page 57

22 
PROFILE OF SAVINGS AND COSTS OVER THE FIRST 10 YEARS 
The Ayrshire Roads Alliance will achieve savings of £8.634 million by 2024.   
This represents a saving on the costs to deliver the service when comparing the first
year with later years.  Table 3 has been extracted from the Detailed Business Case,
and this shows the various costs/savings to be delivered.  The reason for the variations
in year one to year four is due to set up costs.  In practice, these set up costs may be
spread over a longer period to mitigate any operational risks.  This may impact on when
consequential savings are realised.   
Continual updates on progress and targets will be contained within the service plan,
and reported to the Joint Committee when required.   
This savings will enable Councils to take individual decisions, either to bank their share
of the savings, or to invest some or all in additional roads maintenance.   
Strategic Delivery Savings for each Council are now calculated by considering a
smaller group of core strategic delivery staff and that their costs are apportioned on a
budget spend profile basis, in line with local delivery budget spend plus the actual
capital expenditure in that specific year.   
Local Delivery Savings are pro rata to the existing budgets.   
Table 3 – Ayrshire Roads Alliance Total Revenue Savings 
Year
1
Year
2
Year
3
Year
4
Year
5
Year
6
Year
7
Year 8 Year 9 Year 10 Total 
14/15 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 
Proposed
Savings
Benefits
realisation(£
m)  0.696 -0.426 -0.730 -1.049 -1.187 -1.188 -1.187 -1.188 -1.187 -1.188 -8.634
Budget 14.683 14.813 14.006 13.823 13.551 12.695 12.294 11.992 12.278 12.582 132.717
Savings to
date (£m) 0.696 -0.441 -0.971 -1.315 -1.768 -2.515 -3.067 -3.636 -3.828 -4.454 
Cumulative
Budget
14.683 29.496 43.502 57.325 70.876 83.571 95.865 107.857 120.135 132.717 
Cumulative
Savings to
date (£m)
0.696 0.255 -0.715 -2.031 -3.799 -6.314 -9.381 -13.017 -16.845 -21.299 
57

Page 58

23 
The Benefits and Realisation Strategy provided a framework for achieving cumulative
savings of £8.634m between 2014/15 and 2023/24. However, during this time additional
savings have been achieved due to prevailing economic conditions and their impact on
public sector funding. This has resulted in cumulative expenditure reductions of
£21.299m over the life of ARA. This is significantly in excess of the £8.634m originally
envisaged
The Benefits Realisation Strategy and Plan
• Ensures benefits are identified and also defined at the outset, and appropriately
linked to the East Ayrshire and South Ayrshire Council’s strategic objectives. 
• Ensures relevant business areas are prepared to realising their defined benefits. 
• Reduces the risk of unrealistic optimism in the Detailed Business Case and
subsequent benefits realisation dilution or delay during or after potential
implementation. 
• Drives the process of realising benefits, including benefits measurement,
tracking and recording benefits as they are realised. 
• Uses the defined, expected benefits as a roadmap for the programme, providing
a focus for delivering change.
58

Page 59

24 
AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2023/24 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
1 Continue to use the integrated
Roads Asset Management
Plan across the Ayrshire
Roads Alliance. 
There is one Asset Plan for the
Service delivering a risk based
approach for full service
delivery 
Head of Service Draft Completed Document will be presented to Joint
committee and will be reviewed annually.
2 Continue to prepare details for
developing an integrated Local
Transport Strategy. 
A Strategy covering both
Council areas, which will
involve consultation with
stakeholders.  Information will
be gathered to inform the
future Local Transport
Strategy.   
Continue to contribute to the
Scottish National Transport
Strategy, Regional Transport
Strategy and Strategic
Transport Projects Review
work. 
Head of Service Ongoing The Regional Transport Strategy, through
SPT, has just commenced on which the
Alliance has Board membership.  The Local
Strategy will be created as an appendix to the 
Draft RTS when this is published. 
Await publication of the STPR2 Delivery
programme.
3 Action the Flood Risk
Management Plan 
Inform the next national cycle
of potential flood risk
management schemes beyond
2022. 
Complete schemes and
undertake studies.  
Head of Service  Complete 
April 2023 
March 2024 
Reports submitted to both Cabinets Early
2023 
New Cumnock Flood Defences Complete 
Continue Design Work on the Irvine Valley
Continue with flood study works for the river
Ayr,Doon sand Girvan
59

Page 60

25 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
4 Improve the condition of the
road network. 
Improve annual roads survey
results which are part of the
SRMCS work.  Ensure the
Alliance undertakes more
proactive maintenance. 
Head of Service Site works will be
undertaken
throughout
2023/24.
Key dependencies are the Road Improvement
Plans approved by the relevant Committees in
East Ayrshire and South Ayrshire in spring
2023.  Progress is provided to members, and
relevant Committees. 
5 Ensure the road network
remains safe through raising
awareness and improving road
safety through education,
engineering and enforcement. 
Reduce road accidents in line
with government targets. 
Provide appropriate traffic
management schemes and
initiatives.
Strategic Manager
Roads and
Transportation 
March 2024 Scottish Government and SCOTS guidance is
used.  A key dependency is the Road
Improvement Plans which are presented to
Cabinet each year. 
6 Improve the condition of the
bridge stock. 
Improve bridge condition index. 
Reduce the number of weight
restricted bridges.  Complete
all general, special and
principal bridge inspections.   
Design &
Environment
Manager
March 2024 Through the Road Asset Management Plan. 
Key dependencies are Road Improvement
programmes approved by Committees in East
Ayrshire and South Ayrshire in spring 2023.   
Deliver the capital and revenue programmes. 
7 Manage and improve the
street lighting asset and install
energy efficient lighting
schemes. 
Maintain high standard of fixing
dark street lights.  Complete
the LED lighting replacement
programme in both East
Ayrshire and South Ayrshire. 
Head of Service October 2024 Through the Road Asset Management Plan,
with additional funding being provided to
commence the LED programme. 
At present performance is 86% of streets
lights are now LED in EAC; and 99% in SAC.
On target for completion within timescales. 
8 Maximise and deliver
externally funded sources of
work 
Identify external funding
sources and deliver work on
time and on budget.  Improve
infrastructure; and contribute to
improving the condition of the
network. 
Head of Service Works will be
undertaken
throughout the
2023/24.
External sources, including Timber Transport,
SUSTRANS, SPT - Regional Transport
Partnership, CWSS - Cycling Walking and
Safer Streets. Scottish Government Bridge
Fund.SFT
60

Page 61

26 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
9 Implementation of Parking
Strategy
Develop Head of Service Works will be
undertaken
through 2023/24
Amendments to TRO’s, lining, signing and
residential parking permits and implementing
an improved process using digital technology.
10 Prepare Service Plan  Publish  Head of Service  Annual  East Ayrshire Council Community Plan. South
Ayrshire - Local Outcomes Improvement Plan
and Local Place Plans.  Draft Plan to be
submitted to Joint Committee in December
2022. 
11 Continue to review insurance
costs and insurance issues. 
Review current practices to
minimise insurance costs. 
Head of Service Complete Ayrshire Roads Alliance Monthly Insurance
Report. 
There is good dialogue with the Risk &
Insurance to ensure our work improves the
number of repudiated claims.  The number of
claims has greatly reduced due to the
implementation of the new Code of Practice. 
12 Review Depots and
Accommodation 
Continue to review in 2022/23
from initial work was completed
in 2017 as a result of amended
working practices.  
Head of Service Complete Joint Committee Reports of November 2016.  
Although initial work has been completed we
continue to strive to make depot and
accommodation cost savings. Further work
will continue on this as a result of COVID and
the return to office space during 2022/23. 
13 Review vehicle and plant costs Continue to review in 2021/22
from initial work that was
completed in 2017. 
Head of Service  March 2024 Joint Committee Reports of June 2016 
The service continues to review fleet
requirements with the most recent
improvement being on the management of
vehicle utilisation, electric vehicles and
Telematics.
14 Monitor and exercise Business Improved resilience.  Business Support Review and Existing East Ayrshire and South Ayrshire
61

Page 62

27 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
Continuity Plans Manager update following
relevant local and
national events. 
Council plans 
15 Continue to use the Roads
Costing System to its full
potential. 
Improve service performance
from both an on-site and
financial perspective. 
Business Support
Manager
August  2024 Revised roads costing system was fully
operational from November 2018. 
The system continues to be used to monitor
performance and work is ongoing to
implement digital timesheets linked to the
Roads Costing System. 
16 Support and contribute to the
Ayrshire Growth Deal 
Project Management of Roads
Delivery Projects.
Head of Service Ongoing Deliver the three work packages for the AGD.
17 Regional Transport Strategy Successfully contribute to the
preparation of this work being
led by SPT.  The Alliance has
Board representation. 
Head of Service Complete SPT documents and existing Regional
Transport Strategy 
ARA responded to Consultation and await
publication of the final document. 
18 Regional Transport Appraisal Ensure the various projects
identified as part of this work
are included in the Strategic
Transport Projects Review.  
Head of Service Complete Transport Scotland has published the final
STPR2 with delivery programme to be
published. 
19 National Transport Strategy East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure the
sustainable transport hierarchy
and sustainable investment
hierarchy are delivered.   
Head of Service October 2023 In recognition of the anticipated increase in
Active Travel work, it is proposed that a
member of staff is dedicated directly to this
work. 
20 National Transport Strategy –
review of Governance
East Ayrshire and South
Ayrshire Councils contribute to
Head of Service Complete National Transport Strategy
62

Page 63

28 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
this process to ensure that the
outcome/output meets the
needs of the road
users/communities in both
Council areas. 
21 Transport (Scotland) Bill -  East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure the work
provides the best outcome for
road users in both Council
areas. 
Head of Service Complete Transport (Scotland) Bill received Royal
Assent 15 November 2019.
22 Transport (Scotland) Bill -  East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure a
pragmatic approach is taken in
delivering the pavement
parking ban in both Council
areas.
Head of Service March 2024 Transport (Scotland) Bill and Transport
Scotland Parking Standards working group
still awaiting guidance from Transport
Scotland.
23 Levelling Up Fund East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure that the
outcome/output meets the
needs of the road
users/communities 
Head of Service TBC Levelling Up Fund bids will be re-submitted
Summer 2023
63

Page 64

29 
East Ayrshire Council Strategic Priorities 2023/24 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Progress and complete the
New Cumnock Flood
Protection Project 
Complete the flood prevention
projects at the Leggate and
beside the Afton Water. 
Head of Service Complete East Ayrshire Council and Scottish Government
funding.  The Leggat stage of the works was
completed in August 2018 with the Afton Water
phase commenced May 2021 with an 18 month
contract duration.Contract delayed due to
material shortages.
2 Develop Projects approved
from the Flood Risk
Management Plan  
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022. 
Head of Service March 2024 East Ayrshire Council and Scottish Government
Funding.  Continue with work on studies for the
Irvine Valley, Dalrymple, Catrine and
Dalmellington through the financial year.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth
concerns.  Contribute to
infrastructure projects which are
being developed through the
Regional Transport Appraisal
work being led by Transport
Scotland. 
Head of Service Complete The all Ayrshire Transport Appraisal being led
by Transport Scotland commenced in January
2019. We will continue to engage with Transport
Scotland to ensure the Ayrshire Growth Deal
transportation work is included in Strategic
Transport Projects Review work.
4 Transformation 
Strategy 2 
Continue to provide a high
quality roads service within
decreasing available budgets. 
Includes service re-design work.
Head of Service Complete East Ayrshire Council reports to various
Committees. 
Work commenced and was completed by March
2022 including a full revision of ARA structure.
5 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network and East Ayrshire
Network
Head of Service Complete  A full review of active travel provision in East
Ayrshire has been undertaken and this will be
presented to the relevant East Ayrshire Council
Committee Summer 2022.
64

Page 65

30 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
6 EV Strategy  Develop EV strategy across
East Ayrshire Network
Head of Service March 2025  A full review of EV provision in East Ayrshire has
been undertaken at present and this was
presented to East Ayrshire Council Cabinet with
further work being carried out in partnership with
Scottish Futures Trust to assess public charging
funding models.
7 Levelling Up Fund Completion and Submission of
Bid for improvements to Bellfield
Interchange
Head of Service TBC Design and modelling work to improve Bellfield
to increase capacity and open up [development
opportunities.
8 Ash Die back Strategy Develop a risk based strategy
for the management of Ash Die
Back.
Head of Service Complete Develop a risk based approach to the
management of Ash Die Back.
9 152nd Open Championship Delivery of Event Traffic and
Transport Management 
Head of Service July 2024 ARA will chair the transport delivery team for the
Open Championship Troon.
65

Page 66

31 
South Ayrshire Council Strategic Priorities 2023/24 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
1 Implementation of car parking
strategy for South Ayrshire. 
Complete this work with
improved parking provision and
management. 
Head of Service  Complete A full review of car parking provision in South
Ayrshire is being undertaken at present and this
will be presented to the relevant South Ayrshire
Council Committee. 
2 Develop Projects approved
from the Flood Risk
Management Plan  
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022. 
Head of Service March 2024 Flood study work in the Girvan area is
progressing and a report will be presented to the
relevant South Ayrshire Council Committee.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth
concerns.  Contribute to
infrastructure projects which are
being developed through the
Regional Transport Appraisal
work being led by Transport
Scotland. 
Head of Service October 2022 The all Ayrshire Transport Appraisal being led
by Transport Scotland commenced in January
2019. We will continue to engage with Transport
Scotland to ensure the Ayrshire Growth Deal
transportation work is included in Strategic
Transport Projects Review work.
4 20mph speed restrictions in
villages
Progress with the 20mph speed
restrictions in all villages. 
Maintain engagement with the
local communities. 
Head of Service March 2022 phase
1&2 Complete 
October 2023
phase 3
Completed phase 1 and 2.
Design work and consultation phase 3 
Responses from Community Councils
5 Anticipated Budget Reductions
in 2022/23
Continue to provide a high
quality roads service within
decreasing available budgets.
Includes service re-design work. 
Head of Service March 2024 Reports to various Committees. 
66

Page 67

32 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
6 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network
Head of Service Complete A full review of active travel provision in South
Ayrshire has been undertaken and was
presented to Leadership Panel. Strategy to be
published.
7 EV Charging Strategy  Develop further the  EV strategy
for South Ayrshire Network
Head of Service March 2025 A full review of EV provision in South Ayrshire
was being undertaken and approved by Cabinet.
This will be reviewed as a result of work with
Scottish Futures Trust to assess public charging
funding models.
8 Levelling Up Fund Submission of Active Travel bid Head of Service  TBC Joint bid with NAC for active travel route Ayr to
Irvine
9 Levelling Up Fund Submission of A70 Improvement
Package
Head of Service TBC Bid submission for A70 improvements.
10 Motorhome Trials Develop Campervan sites along
the coastline.
Head of Service March 2024 Formalisation of two temporary sites at Girvan
and Ayr and additional trials at Ballantrae,
Maidens, Prestwick and Troon.
11 Strategic Economic Impact
Assessment A75/A77
There is a growing desire to
understand the importance /
effectiveness of the
improvements outlined along the
A75 and A77.
Head of Service Complete Public consultation / survey covering
communities throughout Ayrshire (North, South
and East) and Dumfries & Galloway is currently
being undertaken. To date there has been
approximately 600 responses, with more
responses expected as the survey is promoted
on social media and the radio. Final report
complete for reporting July 2022.
67

Page 68

33 
APPENDIX 1 – ORGANISATIONAL CHART 
Chair
Joint Committee
Chief Executive of
South Ayrshire Council 
Chief Executive of  
East Ayrshire Council 
Director of Place
Depute Chief Executive
Strategic Lead: Safer
Communities   
Head of Roads
Strategic Manager  Strategic Manager 
• Traffic, Parking & Road Safety
• Transportation & Flooding
• Roads & Structures Design     
• Finance & Admin Support
• Reviews of service activities
• Business Continuity 
• Street Lighting 
• Roads Maintenance Unit
• Girvan Harbour 
68

Page 69

34 
69

Page 70

35 
APPENDIX 2 – STRATEGIC AND LOCAL DELIVERY SPLIT
TABLE 1 - PROPOSED SPLIT BETWEEN STRATEGIC AND LOCAL DELIVERY
Strategic Service Delivery Local Service Delivery
Asset and Performance
Local Transport Strategy; Transportation Policy;
Road Safety Plan; Cycling Strategy
Council/Partner Liaison; 
Transportation, Development Control and
Road Safety
Maintenance of Bus Shelters; Split Cycle
Offset Optimisation Technique (SCOOT)
systems (an adaptive control system for
controlled road crossings); Development
Control; Bus Shelter Advertising;
Shopmobility; Travel Planning; Planning
Applications; Development Planning;
Section 75 Agreements; Road Safety Audits;
School Travel Plans; School Crossing
Patrol; Road Safety Education.
Maintenance of Traffic signals, traffic signs,
Traffic Orders; Traffic Counts, Accident
Investigation and Prevention; 
Asset and Performance
Asset Management Plan; Performance
Monitoring; Parking Strategy.
Scottish Roadworks Register
Asset, Traffic and Parking Car Park
Maintenance and Parking Enforcement.
Roads Improvement Plan; Infrastructure
Surveys; Inventory Management; Issue of
Permits; Accident Investigation and
Prevention; 
Asset and Performance
Flood Risk Management Strategy; Flood Risk
Management Plans;
Design and Environment
Maintenance of Watercourses, Bridges,
Retaining Walls, Piers and Harbours.
Watercourses; Flood Mitigation; Coastal
Protection; Inspection of Piers & Harbours;
Bridge Inspections and Maintenance;
Structural Assessments; Technical Approval;
Abnormal Load Routing; and Design of
Major Road Schemes and Improvements.
Road Construction Consents 
Construction and Roads Maintenance
Winter Service Planning; Street Lighting
Management; 
Operations
Proactive, Reactive, Cyclic Maintenance of
Roads and Footways; Winter and Weather
Emergency Service; Proactive and Reactive
Maintenance of Streetlights; Electricity costs
for streetlights. Carriageway Inspections;
Programming of Proactive, Reactive and
Cyclic Maintenance; Street Lighting Design;
Festive Lighting, Construction of Road
Safety Schemes; Design of Minor Road
Schemes.EV Charging.
70

Page 71

36 
Strategic Service Delivery Local Service Delivery 
Business Operations 
Scottish Roadworkers National Training
Programme
New Business opportunities 
Support Services        
HR, Finance, ICT, and Administrative Support. 
TABLE 2 - CURRENT SPLIT BETWEEN STRATEGIC AND LOCAL DELIVERY
Strategic Service Delivery Local Service Delivery
Transportation, Development Control and
Road Safety
Local Transport Strategy; Transportation Policy;
Road Safety Plan; Travel Planning, Cycling
Strategy; Planning Applications; Road
Construction Consents; Development Planning,
Council/Partner Liaison, Section 75 Agreements;
Road Safety Schemes; Road Safety Audits;
School Travel Plans; School Crossing Patrol;
Road Safety Education. 
Transportation, Development Control and
Road Safety
Maintenance of Bus Shelters; Split Cycle
Offset Optimisation Technique (SCOOT)
systems (an adaptive control system for
controlled road crossings); Development
Control; Bus Shelter Advertising;
Shopmobility; Construction of Road Safety
Schemes. 
Asset, Traffic and Parking
Asset Management Plan; Roads Improvement
Plan; Infrastructure Surveys; Inventory
Management; Scottish Roadworks Register;
Issue of Permits; Performance Monitoring;
Accident Investigation and Prevention; Traffic
Orders; Traffic Counts; and Parking Strategy. 
Asset, Traffic and Parking
Maintenance of Traffic signals, traffic signs,
Car Park Maintenance and Parking
Enforcement.
Design and Environment
Flood Risk Management Strategy; Flood Risk
Management Plans; Watercourses; Flood
Mitigation; Coastal Protection; Inspection of Piers
& Harbours; Bridge Inspections and Maintenance;
Structural Assessments; Technical Approval;
Abnormal Load Routing; and Design of Major and
Minor Road Schemes and Improvements. 
Design and Environment
Maintenance of Watercourses, Bridges,
Retaining Walls, Piers and Harbours. 
Operations
Carriageway Inspections; Winter Service
Planning; Programming of Proactive, Reactive
and Cyclic Maintenance; Street Lighting Design
and Management; and Festive Lighting.
Operations
Proactive, Reactive, Cyclic Maintenance of
Roads and Footways; Winter and Weather
Emergency Service; Proactive and Reactive
Maintenance of Streetlights; Electricity costs
for streetlights. 
71

Page 72

37 
72

Page 73

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
19 MAY 2023 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: ROADWORKS PROGRAMME 2023/24
______________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this report is to advise the Joint Committee on the progress of
work through the roads improvement programmes within East Ayrshire and
South Ayrshire for financial year 2023 to 2024. 
RECOMMENDATIONS 
2. It is recommended that Joint Committee: 
(i) Notes, the Ayrshire Roads Alliance programmed works 2023/24
(ii) Otherwise, notes the contents of this Report. 
BACKGROUND 
3. The budget allocation for East and South Ayrshire Councils Roads Investment
Programme for FY 2023/24 can be seen in tables 1 and 2 below respectively. 
Programme Area Budget (£m)
Carriageway Resurfacing 3.240
Footway Resurfacing 0.250
Environmental Improvements  0.015
Street Lighting 0.250
Multi Storey 0.030
Structures (Bridges & Culverts) 4.100
Flood Prevention 2.666
Kilmarnock Car Parks 2.719
Browns Road 0.220
EV Charging 0.100
Active Travel 0.100
Other Works 0.080
Total £14.040
External Funding 
SPT – Park & Ride £0.020 
SPT - Bus Station Improvements £1.800
Cycling, Walking & Safer Routes £0.779
Smarter Choices, Smarter Places 0.170 (tbc)
Sustrans 0.030 (tbc)
Road Safety Improvement Fund 0.150 prospective bid
Active Travel Transformation fund 1.800 (tbc)
Agenda Item 7
73

Page 74

Total £2.599 confirmed   
Table 1: East Ayrshire Council Roads Investment Programme 2023/24 
Programme Area Budget (£m)
Carriageway & Footway Resurfacing 2.812
Structures (Bridges & Culverts) 0.410
Street Lighting 0.250
Traffic Signals 0.290
Girvan Harbour 0.502
Slope Stabilisation 0.216
EV charging  0.190
Tourist and visitor Facilities 0.150
Total £4.946
External Funding 
Cycling, Walking & Safer Routes 0.718
Smarter Choices, Smarter Places 0.101 (tbc)
Sustrans 2.715 (tbc)
SPT 0.800
Regional Active Travel Grant 0.800tbc
Road Safety Improvement Fund 0.150 (prospective bid)
Active Travel transformation fund 1.200
Total £2.718m confirmed 
Table 2: South Ayrshire Council Roads Investment Programme 2023/24 
DETAIL 
4. The programmes for FY 23/24 are contained within Appendices One and Two. 
Resurfacing 
5. Road improvement programmes in East Ayrshire Council for FY 23/24
commenced April 2023 and in South Ayrshire Council commencing May 2023
with some early improvement works complete.  The price of road material and
fuel has not subsided, the focus this year will be to limit outsourcing works to
external contractors, which will be achieved by combining and upskilling our
workforce. 
6. Early planning meetings with Team Leaders, Depot Coordinators and our
Roadwork Coordinator has concluded and will continue throughout the year to
monitor budget, progress and move resources as required. 
7. As previously reported at our last joint committee, Ayrshire Roads Alliance has
submitted bids to Scottish Timber Transport for both East and South Ayrshire to
the value of £286k and £630k respectively.  Communication has been received
74

Page 75

confirming they are currently reviewing our applications with a decision expected
towards end of May/beginning of June. 23. 
8. Due to an early low temperature forecast received, winter operations was
extended for a week ending 1st May 2023.  Summer standby has now
commenced with Ayrshire Roads Alliance responding to incidents on the
network. 
9. At the end of winter our salt stocks are 2257tonnes in East Ayrshire Council and
2239tonnes in South Ayrshire Council with resilience levels at 4,400tonnes. 
10. A lessons learned workshop is planned which will be attended by Winter
Controllers and Winter Supervisors to discuss 22/23 winter operations and take
forward areas of improvement for winter 23/24.  Route optimisation of our gritting
routes is at the early stages with discussions progressing with specialist
Contractors.. 
Street Lighting 
11. Street lighting teams continue to focus on cyclic maintenance faults and statutory
electrical test and inspection. 
12. Utilising the external Contractor LED lighting installations continue to progress
as detailed in Appendix 1 and 2. 
Electric Vehicle Infrastructure 
13. The Electric Vehicle Infrastructure Fund (EVIF programme) has been included
within Appendix three for South and East Ayrshire respectively, with the number
of public chargers installed to date is included at Appendix 3. 
14. New EV chargers have been commissioned at Cumnock Community Hospital,
with installations proceeding at Sturrock Street (East), Car Park and at Rosebank
Resource Centre (both Kilmarnock). 
15. PAN Ayrshire Public Electric Vehicle Charging Strategy has been approved by
all three authorities with Ayrshire Roads Alliance taking the lead.  Work has
commenced but it is at very stages of development. 
Structures 
16. Many of the bridge projects that we undertake requires works to be undertaken
within the watercourse and depending on what the works involve it can often take
up to 4months for the SEPA licence to be obtained with other constraints, such
as the fish spawning season which typically runs from end October to end April
restricting work in the watercourse. 
17. Appendix B details East Ayrshire Council Bridges Capital programme with three
projects, Queens Crescent Retaining Walls, Newmillns and B741 Coal Glen
75

Page 76

Embankment Slip, near Dalmellington issued for tender with a remaining seven
projects nearing tender ready with a combined estimated value of £3.62m. 
18. Land acquisition and/or access agreements are often required for bridge related
projects and can cause delay to the projects. A number of projects are currently
near tender ready but are being delayed due to land related issues. ARA are
actively working with the Council’s Estates and Legal teams in all of these
projects but land acquisition can be a very challenging and resource intense
activity for ARA, Estates and Legal sections. Again, where possible, projects that
do not require land acquisition or formal legal access agreements are being
brought forward. 
19. ARA representing South Ayrshire Council as a coastal authority participate as
one of four Local Authorities on the Coastal Adaptation Budget Group which has
representation from Scottish Government, Nature Scot, SEPA and Local
Authorities. The group is currently considering the model for allocation of the year
3 funding for the coastal change adaptation fund. 
20.    The business case for Ballantrae was accepted by the Coastal Adaption Budget               
Group and £180,000 will be included for this project in the Scottish Government    
General Capital Grant for South Ayrshire Council in 2023/24.  The onsite start up
meeting took place on the 21st April and the project is now live. 
21. The business case for Girvan Golf course was not accepted for funding, however
positive feedback on the objective was received and encouragement given to
submit the case study for future funding taking note of the feedback provided.
The opportunity to use dredge material from Girvan Harbour to replenish the
Girvan Golf Course beach is being investigated as part of the future dredging
planned without access to this funding. 
Traffic & Transportation 
22. Agreement has been reached where necessary to roll grant funding provision
into the new financial year to complete projects. The focus of these projects will
continue to be improvements to our roads and infrastructure to improve journeys
and increase safety measures where required. At present, grant award
confirmation has been received from Strathclyde Partnership for Transport (SPT)
and Cycling, Walking, Safer Routes (CWSR), whilst we continue to await
conformation from various others including Sustrans, Smarter Choices, Smarter
Places (SCSP), the Active Travel Transformation Fund (ATTF), the Regional
Active Travel Grant (RATG) and the Road Safety Improvement Fund (RSIF). 
23. The Active Travel Strategy for East Ayrshire will shortly be undergoing a final
public consultation review – as previously agreed at EAC Cabinet the final
version of the Strategy can be signed off by the Leader and Cabinet Member for
Roads without the need to return to a future Cabinet meeting. The Active Travel
Strategy for South Ayrshire has now been published. 
76

Page 77

APSE Highways, Street Lighting and Winter Maintenance Innovation Awards 2023 
24. Ayrshire Roads Alliance were announced as the winners of the Highways
Maintenance innovation category for our Temporary Traffic Regulation Order
(TTRO) digitalisation submission at an awards dinner on Thursday 23 March
2023 in Blackpool. 
POLICY/COMMUNITY PLANNING ISSUES 
25. A well -maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
26. The matters referred to in this report contribute to the South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome of ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’ 
LEGAL IMPLICATIONS 
27. By virtue of the relevant statutory provisions, principally detailed within the Roads
(Scotland) Act 1984, the Council as local roads authority is required to manage
and maintain all publicly adopted roads within its area other than those which are
maintained and managed by the Scottish Ministers. 
HUMAN RESOURCES IMPLICATIONS 
28. The work programmes have direct impact on human resources and the Alliance  
will ensure all works are suitably resourced to maintain satisfactory progress. 
EQUALITY IMPACT IMPLICATIONS 
29. An equality impact assessment is not needed because the proposal does not
have a differential impact on any of the protected characteristics. 
FINANCIAL IMPLICATIONS 
30. The Ayrshire Roads Alliance will deliver the strategic and local services as stated
in the Service Plan. The budget is provided by East Ayrshire Council, South
Ayrshire Council, and other external organisations. Appropriate scrutiny
arrangements are in place to manage these budgets. 
RISK IMPLICATIONS 
31. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every 
joint Committee. 
77

Page 78

32. The Works Programmes, Service Plan and the Risk Register do not expose
either Council to an increased risk as they have been developed from existing
budgets and existing service commitment. 
TRANSFORMATION STRATEGY 
33. This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”. 
Maximum value for our communities; by ensuring the road network is maintained. 
BACKGROUND PAPERS 
East Ayrshire Council Cabinet Report – 2023/24 Roads Asset Management Plan
– Investment and Programme - 8 March 2023 
South Ayrshire Council Leadership Report Road Improvement Plan 2023/24 -25
April 2023   
LIST OF APPENDICES 
Appendix 1 - South Ayrshire Council Programme of Works 2023/24 
Appendix 2 - East Ayrshire Council Programme of Works 2023/24
Appendix 3 – EV Public Chargers 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation Officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org
78

Page 79

Appendix 1 
South Ayrshire Council – Programme of Works 2023/24 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2022 to 2024 
Route
No
Town Road Name Works
Description
Scheme
Score
Estimated
Cost
Comments Variance +/-
B734 Old Dailly Barr Old Dailly Old Dailly to
Penkill +
drainage
improvements
N/A £108,000  
B7035 By Girvan Glendoune Houdston
Road (Coalpots)
Braetoll South
+ S Power
shut down
N/A £200,000  
B743 By
Mossblown
Ayr / Mossblown? West from
Brocklehill
Farm
53 £270.668  
C37 Auchincruive Barrackhall Gibbsyard TBC 48 £118,347  
Uncl Tarbolton Springfield Road Garden Street
to No 50
46 £28,523  
B742 By Coylton B742 Council
Boundary -
A70/Hillhead, Coylton
By Holebogs,
S bend
59 £48,000  
B742 By Coylton B742 Council
Boundary -
A70/Hillhead, Coylton
From A70 at
Hillhead
south to C21
Craigs Road
junction
56 £55,000  
79

Page 80

B742 By Coylton B742 A70 Hillhead -
B744 Jcn N Of
Annbank, Coylton
From
Meadowhead
Depot
entrance
south-wards
55 £97,500  
B744 Annbank Weston Brae Full Length 53 £59,000  
B744 Annbank Browns Crescent 
Weston Avenue
Full Length
Craighall Way
to 101
Weston
Avenue
53
56
£93,000  
B742 By Coylton B742 A70 Hillhead -
B744 Jcn N Of
Annbank, Coylton
Bridge of
Coyle to C2
52 £190,500  
U77 By Coylton Hole Road Full Length 46 £65,911  
B7023 Maybole Crosshill Road Full Length 56 £74,687  
B7023 Maybole St Cuthbert's Road Full Length 53 £30,669  
B7024 Maybole Alloway Road Redbrae to
Bypass
51 £55,922  
C122 By Maybole  C122 Gardenrose
Path/Maybole -
School
Road/Minishant,
Maybole 
C122 Gardenrose
Path/Maybole -
School
Road/Minishant,
Maybole
School to new
Bypass 
Ladycross to
new Bypass
50  £60,134  
80

Page 81

B7023 Maybole Maybole Crosshill 30mph
Maybole to
jcn C58
72 £162,720  
U52 Pinwherry Muck road Various TBC 52 £71,978  
B7023 Maybole Ballochbroe to
Crosshill
Dalhowan to
C58 
£275,435  
A719
PH 2
By Maidens 
By Dunure
Pennyglen/B7023 -
Kirkoswald
Road/Maidens,
Maidens 
A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
B7023 Enoch
Lodge -
Caravan Park 
Cemetery to
Drumshang
67 £353,083  
A719
PH 1
By Maidens  Pennyglen/B7023 -
Kirkoswald Rd & 
Turnberry Rd
/Maidens, Turnberry
Morriston
Farm to Jct
Blawearie 
Maidens to
Turnberry
56  £552,084  
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget
allocation 
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320  
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320  
81

Page 82

Uncl Ayr Green Street Waggon
Road to
Crown Street
42 £67,760  
Uncl Prestwick Craigie Street Full length 39 £11,638  
C74 By Ayr Macnairston Road C105 to B742
Junction
52 £92,960  
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320  
Uncl Ayr Green Street Waggon
Road to
Crown Street
42 £67,760  
Uncl Prestwick Craigie Street Full length 39 £11,638  
C74 By Ayr Macnairston Road C105 to B742
Junction
52 £92,960  
B744 By Annbank B744 Belston/A70 -
Weston
Avenue/Annbank, Ayr
Auchincruive
Junction to
Glenview
52 £91,250  
Uncl Ayr Ellisland Square Full Length 42 £58,806  
Uncl Ayr Chapel Park Road Full Length 40 £53,319  
B742 By Maybole B742 Jcn Of A77(T)
Ne Of Maybole -
Council Boundary S
Of Dalrymple,
Maybole
From B7045
junction
westwards
N/A £66,845  
A719 By Dunure A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
By Humeston,
Castlehill
woods to
Pennyglen 
70 To be
measured  
82

Page 83

Ayrshire Roads Alliance – Surface Dressing works – Sites identified for future budget allocation 
U72 By
Dundonald
Crooks Full Length N/A   
U99 By
Symington
Dundonald Symington C32 to U98
Corraith
N/A   
C115 By
Tarbolton
Parkmill Road Parkmill to
C114
N/A   
C114 By
Tarbolton
Largie Road 2 sections N/A   
B744 By
Tarbolton
Tarbolton/Crosshands C114 to
Auchinweet
N/A   
C74 By Ayr Macnairston Road Macnairston
to Lochfergus
N/A   
C60 By Maybole Ladycross Full Length N/A   
C39 By Ayr Corton Road A77 to
Equestrian
Centre
N/A   
U2 By Maybole Auchencross C29 to
Railway
Bridge
N/A   
U25 By Dailly Delamford B741 to
Hadyard Hill
N/A   
U56 Girvan Golf Course Road Newton
Kennedy Br.
to
Knockvalley
Cottages
N/A   
C102 By
Kirkoswald
Balvaird  Full Length N/A   
83

Page 84

Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2022 to 2024 
C17 Tarbolton Westport Footway
North side
28 £17,370  
Uncl Mossblown Martin Avenue  28 £15,300  
Uncl Prestwick Hunters Avenue South from
Heathfield
Road, west
side
23 £7,500  
Uncl Maybole Hicks Avenue No 2 to No 94 30 £28,980  
C151 Dailly Woodside Both sides
from Back St
and Hadyard
Terr
30 £20,400  
Uncl Crosshill Newton Street Church Side
of road
30 £15,795  
Uncl Dailly Hadyard Terrace Inside
footway +
part outer
section
28 £54,400  
Uncl Maybole Ashgrove Avenue Full Length  To be
measured 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget
allocation 
Uncl Troon Fullarton Drive  No 19 to No
37
30 £16,500  
B730 Dundonald Drybridge Road Bowling
Green to
Kilnford Dr
28 £14,500  
84

Page 85

B730 Dundonald Drybridge Road Kilnford Drive
to A759
28 £33,600  
C492 Troon Bentinck Drive No 97 to No
121
28 £20,000  
Uncl Prestwick Outdale Avenue F/path
Sherwood
Road side ,
both sides
30 £38,300          
B743 Mossblown Mauchline Road Fourways to
Railway
Bridge North
side
28 £15,300  
Uncl Ayr Content Avenue South Side
full length
(College
Side)
28 £8,400                  
Uncl Ayr Bellevue Crescent  34 £37,800  
Uncl Ayr Hawthorn Drive  30 £62,000  
B742 Annbank Weston Brae  28 £10,700  
Uncl Maidens Ardlochan Road  30 £20,000          
Uncl Maybole Queens Terrace No 17 to No
39 + cway
see separate
entry
28 £18,000  
Uncl Maybole Kingcraig Avenue No 2 to No 32
+ cway see
separate
entry
28 £22,800  
85

Page 86

Uncl Ayr Lochpark slab
replacement
23 £20,425  
Uncl Dailly Church Crescent Odd number
side full
length
30 £16,000   
Ayrshire Roads Alliance - Lighting Programme 2023/24 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Ayr Castlehill (Larchwood Road,
Hawthorn Drive and Area)
Mix of steel and
concrete columns SAC
cabling and 5th Core
17 £60,000 Start Date
9 May 23 
Ayr Belmont Crescent Poor lighting & 5th
Core supplies 13 £30,000 Scheduled
June 23 
Girvan Elder Avenue and Area Old steel columns, poor
lighting levels 31 £60,000 Scheduled
June 23 
Prestwick Mossbank (Phase 2)
Old steel columns and
5th Core supplies
(ongoing section faults)
35 £60,000 Started 
2 May 23 
Troon South of town centre area
Concrete column
replacements (Scottish
Power services)
50 £40,000
Scheduled
July 23 
£250,000   
Ayrshire Roads Alliance - LED Lighting Programme 2023/24 
Town Description Remaining
Ayr - 11
86

Page 87

Ayrshire Roads Alliance - Traffic and Transportation Programme 2023/24 
Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/- 
SPT £39,000 Match £800,000 Access for All
Review Coylton
Works underway
on site 
£100,000  Match
Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02 
£450,000  Match
Dundonald to
Barassie Link
Ph1 Construction
Currently on hold
as we await
confirmation of
land acquisition 
£50,000 Match Loans to Troon
Railway Station
(Phase 3)
Currently
awaiting
confirmation of
Sustrans match
funding 
£61,000  Match
Active Travel
Strategy projects
– details TBC
Various works –
all will be
completed by
financial year end 
£100,000  No
Match 
SQP Various
Projects
Various works –
all will be
completed by
financial year end 
Sustrans –
Places for
Everyone 
£114,926  Match
£2,714,926  Access for All
Review Coylton
Currently
awaiting formal
grant award 
87

Page 88

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
£400,000 Match Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02. Funding
includes
additional works
including new
SUDS feature
with biodiversity
enhancements 
£2,100,000 Match Dundonald to
Barassie Link
Ph1 Construction
Currently on hold
as we await
confirmation of
land acquisition.
Funding
unconfirmed at
this time. 
£100,000 Match Loans to Troon
Railway Station
(Phase 3)
Currently
awaiting formal
grant award 
Regional
Active
Travel Grant
(RATG)
£800,000 No
Match
£800,000 Dalmellington to
Ayr active travel
route - design
Currently
awaiting formal
award 
Road Safety
Improvemen
t Fund
£150,000 No
Match
£150,000 Various road
safety
improvements -
tbc
Fund will open to
bids shortly – bid
currently being
prepared 
88

Page 89

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
SCSP £100,800 Hub
Match
£100,800 Active Travel Hub
Ayr
Ongoing Project
delivery –
awaiting
confirmation of
funding –
announcement
has been delayed
on multiple
occasions 
CWSR  £50,000 Match £718,000 Access for All
Review Coylton
Works underway
on site 
£200,000 Match Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02 
£100,000 Match Active Travel
Strategy projects
– details TBC
Detail TBC – will
be programmed
and delivered in
current FY. 
£200,000 Match Dundonald to
Barassie Link
Ph1 Construction
On hold -
Awaiting
confirmation of
land acquisition
and Sustrans
funding element 
£8,000 Match Loans to Troon
Railway Station
(Phase 3)
Awaiting
Sustrans award
confirmation for
match 
89

Page 90

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
£160,000 Hub
Match
Various projects
to provide match
for the SCSP
funding – active
travel
infrastructure
imps
Detail TBC – will
be programmed
and delivered in
current FY. 
Active
Travel
Transformat
ion Fund
(ATTF)
£500,000 No
Match
£1,200,000 Culzean Way –
optioneering and
outline design 
ATTF fund is
currently
oversubscribed,
therefore it is very
unlikely that a full
grant award
based on our
submission will
be successful. 
£200,000 No
Match
Heathfield active
travel route –
optioneering and
outline design 
£200,000 No
Match
Ayr Hospital
active travel route
– optioneering
and outline
design 
£200,000 No
Match
Carrick
Connections –
optioneering and
outline design 
£100,000 No
Match
Dundonald to
Crosshouse –
optioneering and
outline design 
Total £6,483,726   
90

Page 91

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
ARA New
Signals £290,000 No
Match
£290,000 Signalisation of
A759/B730,
Dundonald, and
signalisation of
Doonfoot
Rd/Greenfield Ave,
Ayr
Works to be
designed, costed,
programmed and
installed in current
FY. 
Total £6,773,726   
Ayrshire Roads Alliance - Traffic and Transportation Signal Replacement 2023/24 
Signal
No Town  Description  Work
Type
Estimated Programmed
Cost 
Comments Variance
+/-
SAS1 Ayr
Racecourse
Road/
Doonfoot Road
Junction
Replacement £60,000
Design to be
undertaken,
costed, and
works
programmed 
SA17 Ayr
Whitletts Road/
Mainholm
Road
Junction
Replacement £60,000
Design to be
undertaken,
costed, and
works
programmed 
SAP15 Ayr
Ped Crossing –
Whitletts Road
corridor
Pedestrian
Crossing
Replacement
£40,000
Design to be
undertaken,
costed, and
works
programmed 
91

Page 92

Total    £160,000   
Ayrshire Roads Alliance - Structures Capital Programme 2023/24 
Description   Work Type Estimated
Programme Cost 
Comments Variance
+/-
A79-30 Victoria Bridge Joint Replacement and waterproofing £15,000 On Site -£15,000 
A79-30 Victoria Bridge Concrete Repairs and Painting £490,571 Design
Ongoing.
Construction
planned
2023/24
-£488,403.12
C12 Dunure Station Road Dunure, Slope Stabilisation £193,346 Design
Ongoing,
Construction
Planned
2023/24
-£185,681.63
U49 Littleton
Farm
Littleton Farm, Slope Stabilisation  £23,000 Ground
Invetigation
and Design.
-£23,000
Girvan Harbour Girvan Harbour South Pier Repairs £136,000 Design  -£136,000
Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £587,380.03 Design  -£587,380.03
Collennan
Reservoir Troon
Valve tower access access gantry installation. £70,000 Design and
Tender
-£70,000  
£1,515,297.03   
92

Page 93

Appendix 2 
East Ayrshire Council – Programme of Works 2023/24 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme [Works carried over from 2022/23] 
ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment
A71 Main Street Darvel £121,875.00   
A735 U26 to past C7 Junction £155,250.00   
B743 Strathaven
Road Muirkirk 950m to South Lanarkshire Boundary £93,600.00   
C134 Rural Sections £28,800.00   
U760 Dalcairnie Full Length £122,400.00   
U26 Dunlop Full Length £43,200.00   
Ellis Street
Kilmarnock Full Length £18,900.00   
Howard Street
Kilmarnock Full Length £85,680.00   
Seaford Street
Kilmarnock Full Length £134,640.00   
Dundonald Road
Kilmarnock Smillie Place to Seaford Street £112,00.00   
Meiklewood Road
Kilmarnock No1 to No 31 £33,000.00   
Shortlees Crescent
Kilmarnock Rathlin Avenue to Shortlees Road £44,000.00   
Old Street
Kilmarnock Academy Street to Campbell St £37,800.00   
Stoneyhill Avenue
Kilmarnock Full Length £22,000.00   
Turner Place
Kilmarnock Full Length £32,000.00   
Craufurdland Road
Kilmarnock No87 to No145 £24,000.00   
Old Mill Road
kilmarnock Lawson Street to Saturrock Street £64,000.00   
Grassyards Road
Kilmarnock Kennedy Drive to C10 £48,000.00   
93

Page 94

Mansfield Road
New Cumnock A76 to Top Corner/ Junction £287,100.00   
Blaney Avenue
Patna Full Length £33,000.00   
Crougar Road
Crookedholm Full Length £69,300.00   
Meadowside
Crookedholm Full Length £7,500.00   
High Street
Newmilns Full Length £45,000.00   
East Donnington
Street Darvel Full Length £30,600.00   
Burn Road Darvel Various Sections £88,000.00   
Campbell Street
Darvel Full Length £28,050.00   
Glen Terrace
Darvel Full Length £30,000.00   
Fleming Drive
Stewarton Full Length £13,970.00   
Lothian Road
Stewarton Full Length £55,000.00   
Cutsburn Road
Stewarton Full Length £88,000.00   
Irvine Road
Kilmaurs Full Length £25,300.00   
Newmill Road
Dunlop Rural Section £81,000.00   
Middlefield Drive
Muirkirk Full Length £14,450.00   
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme 2023/24 – New sites 
A77 Underneath Flyover £41,400.00   
A70 South of Muirkirk at B743 Junction £189,750.00   
A70 West of Ochiltree £86,250.00   
A713 Patna £92,000.00   
B743 Mauchline – Mary Morrison Drive to Hill Top £105,300.00   
B705 2 Sections from 30mph to Glenshamrock Road £117,000.00   
C3 C82 to Stair £129,600.00   
94

Page 95

C11 Patna – Dallowie Farm to Dalvennan £45,000.00   
U55 Galston – Various Sections £27,000.00   
Furnace Road
Muirkirk Furnace Bridge to Golf Course £40,000.00   
Main Street
Ochiltree A70 to Gallowlee Avenue £104,000.00   
Blackwood Avenue
Catrine Full Length £27,600.00   
Fourfields Catrine Full Length £39,600.00   
John Allan Drive
Cumnock Full Length £48,000.00   
Duncan Court
Cumnock Full Length £12,000.00   
James Young
Avenue Cumnock Full Length £13,000.00   
Burnside Road
Caponacre Full Length £70,000.00   
Riecawr Avenue
Bellsbank Full Length £45,600.00   
Shalloch Place
Bellsbank Full Length £32,400.00   
Garden Street
Dalrymple Full Length £32,400.00   
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget allocation 
Hughfield Road
Mauchline Full Length £55,500.00   
Carrick View
Mauchline Full Length £41,250.00   
Beechwood Road
Mauchline Full Length £69,500.00   
Jean Armour Drive
Mauchline Full Length £112,500.00   
95

Page 96

Ayrshire Roads Alliance - Footway Structural Maintenance Programme 2023/24 [Works carried over from 2022/23] 
FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment
Riverbank Place
Kilmarnock No 3 to No 9 £2,880.00   
Burn Road Darvel A71 to West Donnington Street £4,032.00   
Mauchline Road
Auchinleck Merlin Park to Merlin Garage £18,900.00   
Kings Drive
Holmhead
Cumnock
Full Length 1 Side £18,900.00 
Broomfield Avenue
Holmhead
Cumnock
Full Length 1 Side £10,080.00 
Netherhill Crescent
Patna Full Length 1 Side £18,900.00   
A713
Dalmellington
Road Patna
Dalharco Avenue to Doonbank Crescent £30,240.00 
Taiglum Drongan Full Length 1 Side £5,670.00   
Cessnock Road
Hurlford Full Length 1 Side £17,640.00   
Homes Road
Galston Full Length 1 Side £12,600.00   
Rysland drive
Fenwick Full Length 1 Side £20,790.00   
Bowes Rigg
Stewarton Full Length 1 Side £25,200.00   
James Young
Avenue
Netherthird
Full Length Both Sides £16,380.00 
Western Road
Kilmarnock  Lewis Drive Side £9,450.00   
Knowhead Road
Kilmarnock Full Length 1 Side £28,350.00   
Castle terrace
Kilmarnock Full Length 1 Side £10,368.00   
96

Page 97

Ayrshire Roads Alliance - Environmental Improvement Programme 
Year Project Description of Works Benefit Estimated
Cost 
Future Years Hayhill, by Drongan, Environmental
Improvement
Kerb, upgrade verge
and form parking bay
Improve environment in village
and road safety by formalising
parking area.  £15,000 
Future Years  Craigie Avenue, Kilmarnock Form Lay-by - street
parking bays
Improve environment and road
safety by reducing on street
parking problems.  £15,000 
Future Years Wellpark Crescent Kilmarnock, widen
road.
Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £7,000 
Future Years  Kilmarnock Rd Service Rd Crosshouse,
widen road. 
Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £8,000 
Future Years Hillcrest, Bellsbank, Dalmellington
Parking Bays
Form 6 No Off-Street
parking bays
Improve environment and safety by
reducing on street parking
problems.  £15,000 
Future Years  North Hamilton Place Kilmarnock, parking
bays.  Additional Parking Area
Improve environment and road
safety by reducing on street
parking problems.  £8,000 
Future Years  Gateside Road, Galston, widen road. Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £7,000 
97

Page 98

Ayrshire Roads Alliance - Lighting Capital Programme 2023/24 
Town Location Work Type Estimated Cost Comments Variance +/-
Galston Cairn Terrace, Cairn View and Cairn
Place
5th Core supplies and
concrete columns £50,000 Scheduled
November 23 
Kilmarnock Bridgehousehill Road 5th Core supplies and
deteriorated columns £60,000 Scheduled
September 23 
Muirkirk Garpel Ave, Smallburn Dr Area Ph2 5th Core supplies and
concrete columns £75,000 Scheduled
October 23 
New Cumnock Dalhanna Drive, Mounthope
Terrace, Lochbrowan Crescent
5th Core supplies and
concrete columns £65,000 Scheduled 
July 23 
£250,000 
Ayrshire Roads Alliance - LED Lighting Programme Update 2023/24 [Works carried over from 2022/23] 
Town Lantern
Amount Status
Delivery /
start
install
Install
complete
by
Kilmarnock - North East 1135 Complete Dec-21 90%
Complete
Kilmarnock - Central 1400 On site  Aug-23
East Ayrshire - Decorative 350 75% complete 
tender to be issued for next stage  Aug-23
Logan, Lugar, Cronberry & Muirkirk 390 On site Oct-22 May-23
Stewarton, Kilmaurs, Fenwick, Dunlop & Lugton 1420 On site Oct-22 May-23 
Current Status 
Programme completed conversions to
date
12,696 Replacement programme 90% complete
Overall LED units completed 19,125 LEDs now 90.8% of total EAC inventory 
98

Page 99

Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 [Works carried over from 2022/23] 
During our design works for our LED conversions, we have identified a number of older installations in East Ayrshire where it is not practicable to
simply replace the existing discharge lighting with LED lanterns. Consequently, the following full lighting replacement projects have been
programmed and will be funded from the LED replacement budget.
Town Location Estimated
Cost Scheduled Comments
Galston Orchard Street £35,000 Nov-22 90% Complete
Kilmarnock Samson Ave, Linfern Ave Areas £95,000 27-Feb-23 40% Complete
Stewarton Clerkland Road Area £70,000 27-Feb-23 40% Complete
Kilmarnock Glasgow Road B7038 £45,000 27-Mar-23 90% Complete
Kilmarnock Forest Grove and Woodlands Grove £85,000 03-Mar-23 40% Complete
2022/23 Total £425,000   
Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 
Town Location Estimated
Cost Scheduled Comments
Kilmarnock Woodstock Street & Area £60,000 12-Jun-23  
Kilmarnock Gibson St and Carmel Ave Areas £110,000 2-Jun-23 
Kilmarnock Wilson Ave, Greenan Rd, Dunure Rd Area £120,000 15-May-23 
Stewarton Annick Crescent & Area £75,000 3-Apr-23 10% Complete 
Fenwick Maunsheugh Road £50,000 May-23  
Fenwick Skernieland Road £30,000 Jul-23  
Kilmarnock Bonnyton Road £20,000 Jul-23 
2023/24 Total £465,000     
99

Page 100

Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2023/24 [Ongoing and identified works] 
Bridge Strengthening and Replacement
Structure
Reference Structure Name Proposed Works
Project
cost
estimate 
Spend
to-date   Comment  Status 
U22/10  Burnfoot Bridge, near
Darvel
Replacement – Near tender ready. Land
acquisition outstanding  £440,000  £5,250
Ground
Investigation
completed. Land
acquisition
ongoing with
Estates/Legal .
SEPA CAR
Licence received
Design &
tender docs 
C127/10  Low Ashyard Bridge
Infilling of bridge by Historical Railways
Estate. EAC part contribution  £5,000  £0
HRE has funded
the installation of
temporary
supports and
working up
design to sleeve
the structure
Programmed 
Funding
discussions
ongoing with
HRE 
U26/10
West Clerkland Bridge,
near Stewarton
Replacement – currently closed to traffic;
near tender ready.  CPO required to obtain
land acquisition. Construction likely to be
in future year programme 
£12,000  £389
Land acquisition
stalled due to
landowner. CPO
reqd.
Bridge completely
closed to veh &
peds. With Legal
working on CPO. 
Tender ready 
B730/10
Littlemill Bridge,
near Rankinston
Replacement - near tender ready; land
acquisition to be concluded; construction
likely to be in future year programme
£6,000  £3,442
Land acquisition
near complete.
Advance
electricity
diversion
complete.
Near Tender
ready. Works in
2023/24 
A71/280/C8
0
Mathews Burn Culvert,
West Donnington St,
Darvel
Replace section of culvert below West
Donnington Street; design  on going and
near tender ready, land acquisition to be
concluded.
£149,000  £0
SEPA Licence
obtained.  Land
acquisition with
Legal to
conclude. 
Design/Tender 
100

Page 101

B713  B713 Road Slip south of
Sorn 
Detailed design and construct sheet piled
wall
£312,000  £2,450
Consultant
working up
detailed design &
tender documents 
Near tender
ready 
B705  B705 Road Slip centre of
Catrine  Detailed design £18,000  £0  No progress 
B705  B705 Road Slip north of
Catrine  Detailed design £18,000  £0  No progress 
Various  Investigative works  Topographical surveys, paint surveys, etc £6,000  £1,350  Package of topos
awarded 
A735/130/C
58  Gills Burn Culvert, Dunlop
Part deck replacement and Retaining
Wall Repairs - design in  2022/23 and
construction in future year programme  £10,000 £0 
On hold (as
part of F&PM
wider ECC
build)
U751/10 Crossflats Bridge Replacement – design by consultant  £60,000 £0  No progress
Consultant
to be
appointed
for design
via SXL
U760/00/C93 Glenhead Culvert Replacement £42,000 £0 Design ongoing 
U740/10 Barbieston Bridge Boundary Bridge Replacement – design by
consultant £24,000 £0 No progress 
U44/10 Bruntland Bridge Strengthen and refurbish £24,000 £0 No progress 
Upgrade Works identified from inspections 
B705/10/C9
1
Cowan Place Culvert,
Catrine Masonry repairs/scour repairs £24,000 £0
Site visit
undertaken and
preliminary
design
Preliminary
design 
B705/20  Shellies Bridge, Catrine
Scour repairs; masonry training wall repairs
and culvert extension – Consultant
appointed to undertake design & works
ongoing; land acquisition
Construction in future year programme
£6,000 £1,538
Consultant
design ongoing.
Land acquisition
to be determined 
Design 
101

Page 102

A71/300  Priestland Bridge
Retaining Wall strengthening – finalise
design, conclude land
acquisition/servitude and
construct.Tender evaluation.
£120,000 £48,301 Works ongoing  Site
U764/10 Glenmuir Bridge Scour repairs £42,000 £0 No progress 
A70/130/W3
1 Thornwood Wall, Lugar
Replacement - Consultant appointed to
undertake design which is ongoing; land 
acquisition required. Construction in future
year programme
£6,000 £1,538
Consultant design
ongoing and site
investigation
complete. Sheet
pile option
developed but
conflict with O/H
power cables
being investigated
Design 
Queens Crescent,
Newmilns 
Replace riverbank retaining wall.tender
being evaluated. 
£325,000 £10,000
Tender delayed
until Spring 2023
due to fish
spawning issues
with river working.
Advance tree,
vegetation
clearance
undertaken.
Tender ready 
B741 Coal Glen
Embankment Slip, near
Dalmellington
Ground investigation complete. Consultant
finalizing design & tender package. Land
acquisition required. Construction
potentially in 2022/23.
£384,000  £14,000
(Tenders returned
and being
evaluated) 
Tender Stage
A713/60/C6
1 Polnessan Upper Bridge
Extension of culvert. Design and land
acquisition in 2022/23. Construction in
future year programme.
£24,000 £0 No progress 
C90/35/CG0
2 Cattle Grid
Replacement of cattle grid and bypass
improvement. Extent of works increased.
£30k Wind Farm contribution
£136,725  Site works
ongoing
On Site
A736/60/C8
4 Lochridge Culvert  Masonry and drainage repairs £60,000 £0
Near ready for
tender issue
Design 
F/LUGA/10
Logan to Park Terrace
Footbridge, Lugar
Replacement of footbridge deck.on
refurbished abutments. Consultant design
ongoing  £150,000  £1,538
Deck replacement
and scour
protection – design
ongoing 
Design
102

Page 103

B705/20/C6
8
Smithy’s Culvert, near
Catrine
Replace with box units - future year
programme  £0 No progress 
B741/40/C7
9
Polmathburn Bridge, near
Dalmellington
Replace damaged deck slabs - future year
programme  £0 No progress 
A71  Dundonald Rd Bridge
Refurbish –  replace expansion joints,
waterproofing, drainage, surfacing – design.
Construction in future year programme.
£36,000  £14,074
Consultant
appointed and
design
ongoing
Design 
A71  Riccarton Viaduct
Refurbish – paint, replace expansion joints,
waterproofing, drainage, surfacing – design.
Construction in future year programme.
£36,000  £11,414
Consultant
appointed
and design
ongoing
Design 
A71  River Irvine Bridge
Refurbish – paint, replace expansion joints,
waterproofing, drainage, surfacing - design.
Construction in future year programme.
£336,000  £11,414
Consultant
appointed
and design
ongoing
Design 
B741/50 Nith Lodge Bridge
Replacement. Appoint consultant for
design and construction in future
year  £54,000  £0
Consultant to be
appointed for
design via SXL
Held pending
possible WF
proposals
Programmed 
Annick Water, Stewarton
Replacement of collapsing gabion
training wall. Detailed design by
consultant and construction
£378,000  £8,713
Draft tender
documents
being
reviewed by
ARA 
Design
U/LOGA/10 Old Lugar Bridge Strengthening, masonry repairs and
scour protection £300,000 £5,797 Early stages
of design
Design 
C85/10 Fenwick Bridge Masonry refurbishment £24,000 £0
Preliminary
design. Trial
pit
investigation
ongoing 
Design
B7036/10 Lugar Bridge, Ochiltree Major refurbishment – design in FY
2022/23, construction in future year £24,000 £0 No progress 
U/KMCK/20 West Shaw Street Bridge Strengthen and Refurbishment  £0 No progress 
103

Page 104

C135/20 Avon Bridge Masonry and scour repairs £36,000 £0 No progress 
U736/10/C6
5
Sykeside Bridge Scour repair £24,000 £0 No progress 
U729/00/C6
4
Hayhiolm Bridge Masonry and Scour repairs £36,000 £0 No progress 
U729/00/C7
1 
Barry Burn Culvert Masonry and Scour repairs £36,000 £0 No progress 
U730/00/C3
7
Culvert Masonry and Scour repairs £36,000 £0 No progress 
C36/10 Nith Bridge Masonry parapet rebuild and repairs
to commence end of August 2022 £60,000 £25,242 Site works
ongoing
Site 
A70/100 Gatehouse Bridge Parapet heighten, scour repairs &
masonry repairs £24,000 £0 No progress 
A70/110/C4
6
Rose Burn Bridge Masonry and scour repairs £24,000 £0 No progress 
Broomknowe Retaining
Wall
Design in 2022/23, construction in
future years £24,000 £0 No progress 
W/MUIR/20 Muirkirk Shops
Retaining Wall Design in 2022/23, construction in future
years
£24,000 £0 Topo survey.
Trial pit
investigation
works
awarded 
Parapet Upgrades 
A70/70  Burnock Bridge, Ochiltree  Parapet and other masonry repairs  £216,000
£5,545
£196,496
Contract
awarded,
start date
TBC.
Further
Ecology
surveys
being
undertaken
Site 
A713/90  Dunaskin Bridge,
Waterside  Widening to create footway and replace
both masonry parapets - design ongoing. 
£70,000 £1,480 Out to Tender
Tender Stage
104

Page 105

B743/80 Cleuch Bridge, Sorn Upgrade of parapets and install footway  £90,000 £0 
Design ongoing.
Further ecology
surveys being
undertaken
Programmed
C134/10 Ranoldcoup Bridge, Darvel  Masonry repairs and heighten parapets  £264,000  £0  No progress 
B769/40 Corsehill Mill Bridge Parapet replacement – design in FY 2021/22  £12,000  £0 No progress 
B7082/10 Townhead Bridge Parapet replacement £150,000 £0
Trial pit
investigation
works
awarded 
B743/135/C
50 Beacon Hill Culvert Headwall Repairs  £0 No progress 
W/NCUMN/1
0 Burnside Retaining Wall Replacement £36,000 £0 Preliminary
Design
Design 
Rail Incursion 
C23/10 Rigg Road Rail
Bridge, Cumnock Safety fencing - future year programme  £0 No progress 
Non ARA  Council Footbridges 
Various sites Design, investigation £120,000 £2,196 Minor repairs
ongoing 
F/HURL/10 Portland Brae Footbridge Load Assessment, paint and replace
concrete planks £230,000 £22,687
Consultant
completed
structural
assessment
and
strengthenin
g options.
Detailed
design cost
fee being
reviewed by
ARA.
Design
F/CATR/20 Institute Ave Footbridge,
Catrine Refurbishment £72,000 £0 No progress 
A71/190 River Irvine Emergency repairs to expansion joint.
Scheme transferred from Revenue to Capital  £28,794   
105

Page 106

Principal Inspections 
Various Principal Inspections of bridge stock by
consultant and in-house staff £216,000 £0 No progress 
Capital staff fees
Staff fee already
included in above
estimates
£260,000         
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2023/24
(i) Road Safety Programme 
Town/Route Location Proposed Scheme
Kilmarnock A71 / Campbell Street Off Slip Signalisation
Hurlford A71/B7073 roundabout AIP junction assessment
Dunlop Lugton Road Pedestrian crossing
Dunlop Main Street HGV route assessment
Lugton A735/A736 Anti-skid surfacing and traffic sign review
B741 Dalmellington to New Cumnock Road safety route review
B7034 Hollybush Speed limit review
A713 Waterside Speed limit review
B730 Drongan Speed limit review
Auchinleck Various General review of parking restrictions
Mauchline Various General review of parking restrictions
Patna Doon Bridge Signalisation and associated safety improvement works
106

Page 107

(ii) Safer Neighborhoods 
Town Location Proposed Scheme
Galston Cessnock Road at Bowling Club Pedestrian build-out
Stewarton Various roads 20mph speed limit orders amendments
Kilmarnock Whatriggs Road Parking review
Cumnock Glaisnock Street Possible speed reduction measures
Various Various locations Vehicle activated signs upgrade
Crookedholm Grougar Road Pedestrian crossing and road widening
Sinclairston B7046 Traffic calming 
(iii) Rural Route Action Plans 
Route Proposed Scheme
B778 B778 Fenwick to Stewarton Route Study 
(iv) Cycling, Walking and Safer Routes (CWSR) 
Town Location Proposed Scheme
Kilmarnock Grassyards Road Cycle route enhancement scheme
Kilmarnock Annahill Park to B7073 Cycle route
Fenwick Kirkton Rd/Main St – Fenwick PS Pedestrian safety improvements
Mauchline Loudoun Street Pedestrian crossing
Kilmaurs Main Street Traffic modelling for improved pedestrian facilities
Kilmaurs Townhead Pedestrian crossing
Crosshouse Crosshouse-Dundonald Cycle route feasibility study
Newmilns Loudoun Road Pedestrian Crossing Investigation
107

Page 108

Darvel East Main St/Murdoch Road Junction sightline improvement
Kilmarnock Green Infinity Loop Design process for cycle path network 
(v) Strathclyde Partnership for Transport (SPT) 
Location Project
Kilmarnock Phase 3 refurbishment of Kilmarnock bus station to upgrade concourse and stance areas.
Kilmarnock Glasgow Road bus park & ride 
(vi) SUSTRANS 
Location Project
Hurlford Hurlford Street Design Project 
Appendix 3 
Ayrshire Roads Alliance - EV Public Chargers 
EAST AYRSHIRE 
CPS ID Type Make Location
51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
50821 22kw eVolt Multi Storey Car Park, Kilmarnock, KA1 1LU
51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH
52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
108

Page 109

52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW
51170 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP
60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR
52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE
52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG
52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS
52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB
52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ
52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB
52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
109

Page 110

52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY
52962 Rapid eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
52963 22kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
53080 7kw eVolt Netherthird Community Centre, 65 Ryderston Drive, Cumnock, KA18 3AR
53778 Rapid eVolt Main Street Car Park, Muirkirk
53775 22kw eVolt Rose Reilly Sports Centre, Stewarton
53776 7kw eVolt Standalane Car Park, Stewarton
60786 7kW eVolt Academy Street, Hurlford
60732 22kW eVolt Drongan Centre car park, Mill of Shield Road
51210 22kW eVolt Carnshalloch Avenue car park, Patna
60924 7kW eVolt Queen Street car park, Kilmarnock
60250 22kW eVolt New Cumnock Outdoor Swimming Pool car park
60955 22kW eVolt Gatehead Road car park, Crosshouse
61021 7kW eVolt East Ayrshire Community Hospital, Cumnock
61022 7kW eVolt East Ayrshire Community Hospital, Cumnock
61983 7kW eVolt Morton Place car park, Kilmarnock
61984 7kW eVolt Morton Place car park, Kilmarnock
61985 7kW eVolt Morton Place car park, Kilmarnock
SOUTH AYRSHIRE
CPS ID Type Make Location
51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW
51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU
51535 Rapid eVolt Burns Statue Square, Ayr, KA7 UT
52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN
52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 110

Page 111

51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY
50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ
50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF
52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG
50816 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG
52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR
52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH
52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU
52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL
53774 Rapid eVolt Academy Street, Troon
53773 Rapid eVolt Lodge Road Car Park, Turnberry
53777 22kw eVolt Burnside Road, Monkton
60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly
60081 22kw eVolt Inches Close car park, Maybole
61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton
61986 22kw eVolt Dundonald Primary School car park, Dundonald
60086 22kw eVolt Mossblown Activity Centre car park, Mossblown
60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald
61979 7kW eVolt Chalmers Arcade car park, Girvan
61980 7kW eVolt Chalmers Arcade car park, Girvan
61981 7kW eVolt Chalmers Arcade car park, Girvan
Awaiting CPS number 22kW eVolt Barrhill Community car park, Main Street, Barrhill 