04 Roads Programme Report
North Ayrshire Council · 19 May 2023
Back to Ayrshire Shared Services Committee — 19 May 2023 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 19 MAY 2023 Report by the Head of Ayrshire Roads Alliance ______________________________________________________________ SUBJECT: ROADWORKS PROGRAMME 2023/24 ______________________________________________________________ PURPOSE OF REPORT 1. The purpose of this report is to advise the Joint Committee on the progress of work through the roads improvement programmes within East Ayrshire and South Ayrshire for financial year 2023 to 2024. RECOMMENDATIONS 2. It is recommended that Joint Committee: (i) Notes, the Ayrshire Roads Alliance programmed works 2023/24 (ii) Otherwise, notes the contents of this Report. BACKGROUND 3. The budget allocation for East and South Ayrshire Councils Roads Investment Programme for FY 2023/24 can be seen in tables 1 and 2 below respectively. Programme Area Budget (£m) Carriageway Resurfacing 3.240 Footway Resurfacing 0.250 Environmental Improvements 0.015 Street Lighting 0.250 Multi Storey 0.030 Structures (Bridges & Culverts) 4.100 Flood Prevention 2.666 Kilmarnock Car Parks 2.719 Browns Road 0.220 EV Charging 0.100 Active Travel 0.100 Other Works 0.080 Total £14.040 External Funding SPT – Park & Ride £0.020 SPT - Bus Station Improvements £1.800 Cycling, Walking & Safer Routes £0.779 Smarter Choices, Smarter Places 0.170 (tbc) Sustrans 0.030 (tbc) Road Safety Improvement Fund 0.150 prospective bid Active Travel Transformation fund 1.800 (tbc)
Page 2
Total £2.599 confirmed Table 1: East Ayrshire Council Roads Investment Programme 2023/24 Programme Area Budget (£m) Carriageway & Footway Resurfacing 2.812 Structures (Bridges & Culverts) 0.410 Street Lighting 0.250 Traffic Signals 0.290 Girvan Harbour 0.502 Slope Stabilisation 0.216 EV charging 0.190 Tourist and visitor Facilities 0.150 Total £4.946 External Funding Cycling, Walking & Safer Routes 0.718 Smarter Choices, Smarter Places 0.101 (tbc) Sustrans 2.715 (tbc) SPT 0.800 Regional Active Travel Grant 0.800tbc Road Safety Improvement Fund 0.150 (prospective bid) Active Travel transformation fund 1.200 Total £2.718m confirmed Table 2: South Ayrshire Council Roads Investment Programme 2023/24 DETAIL 4. The programmes for FY 23/24 are contained within Appendices One and Two. Resurfacing 5. Road improvement programmes in East Ayrshire Council for FY 23/24 commenced April 2023 and in South Ayrshire Council commencing May 2023 with some early improvement works complete. The price of road material and fuel has not subsided, the focus this year will be to limit outsourcing works to external contractors, which will be achieved by combining and upskilling our workforce. 6. Early planning meetings with Team Leaders, Depot Coordinators and our Roadwork Coordinator has concluded and will continue throughout the year to monitor budget, progress and move resources as required. 7. As previously reported at our last joint committee, Ayrshire Roads Alliance has submitted bids to Scottish Timber Transport for both East and South Ayrshire to the value of £286k and £630k respectively. Communication has been received
Page 3
confirming they are currently reviewing our applications with a decision expected towards end of May/beginning of June. 23. 8. Due to an early low temperature forecast received, winter operations was extended for a week ending 1st May 2023. Summer standby has now commenced with Ayrshire Roads Alliance responding to incidents on the network. 9. At the end of winter our salt stocks are 2257tonnes in East Ayrshire Council and 2239tonnes in South Ayrshire Council with resilience levels at 4,400tonnes. 10. A lessons learned workshop is planned which will be attended by Winter Controllers and Winter Supervisors to discuss 22/23 winter operations and take forward areas of improvement for winter 23/24. Route optimisation of our gritting routes is at the early stages with discussions progressing with specialist Contractors.. Street Lighting 11. Street lighting teams continue to focus on cyclic maintenance faults and statutory electrical test and inspection. 12. Utilising the external Contractor LED lighting installations continue to progress as detailed in Appendix 1 and 2. Electric Vehicle Infrastructure 13. The Electric Vehicle Infrastructure Fund (EVIF programme) has been included within Appendix three for South and East Ayrshire respectively, with the number of public chargers installed to date is included at Appendix 3. 14. New EV chargers have been commissioned at Cumnock Community Hospital, with installations proceeding at Sturrock Street (East), Car Park and at Rosebank Resource Centre (both Kilmarnock). 15. PAN Ayrshire Public Electric Vehicle Charging Strategy has been approved by all three authorities with Ayrshire Roads Alliance taking the lead. Work has commenced but it is at very stages of development. Structures 16. Many of the bridge projects that we undertake requires works to be undertaken within the watercourse and depending on what the works involve it can often take up to 4months for the SEPA licence to be obtained with other constraints, such as the fish spawning season which typically runs from end October to end April restricting work in the watercourse. 17. Appendix B details East Ayrshire Council Bridges Capital programme with three projects, Queens Crescent Retaining Walls, Newmillns and B741 Coal Glen
Page 4
Embankment Slip, near Dalmellington issued for tender with a remaining seven projects nearing tender ready with a combined estimated value of £3.62m. 18. Land acquisition and/or access agreements are often required for bridge related projects and can cause delay to the projects. A number of projects are currently near tender ready but are being delayed due to land related issues. ARA are actively working with the Council’s Estates and Legal teams in all of these projects but land acquisition can be a very challenging and resource intense activity for ARA, Estates and Legal sections. Again, where possible, projects that do not require land acquisition or formal legal access agreements are being brought forward. 19. ARA representing South Ayrshire Council as a coastal authority participate as one of four Local Authorities on the Coastal Adaptation Budget Group which has representation from Scottish Government, Nature Scot, SEPA and Local Authorities. The group is currently considering the model for allocation of the year 3 funding for the coastal change adaptation fund. 20. The business case for Ballantrae was accepted by the Coastal Adaption Budget Group and £180,000 will be included for this project in the Scottish Government General Capital Grant for South Ayrshire Council in 2023/24. The onsite start up meeting took place on the 21st April and the project is now live. 21. The business case for Girvan Golf course was not accepted for funding, however positive feedback on the objective was received and encouragement given to submit the case study for future funding taking note of the feedback provided. The opportunity to use dredge material from Girvan Harbour to replenish the Girvan Golf Course beach is being investigated as part of the future dredging planned without access to this funding. Traffic & Transportation 22. Agreement has been reached where necessary to roll grant funding provision into the new financial year to complete projects. The focus of these projects will continue to be improvements to our roads and infrastructure to improve journeys and increase safety measures where required. At present, grant award confirmation has been received from Strathclyde Partnership for Transport (SPT) and Cycling, Walking, Safer Routes (CWSR), whilst we continue to await conformation from various others including Sustrans, Smarter Choices, Smarter Places (SCSP), the Active Travel Transformation Fund (ATTF), the Regional Active Travel Grant (RATG) and the Road Safety Improvement Fund (RSIF). 23. The Active Travel Strategy for East Ayrshire will shortly be undergoing a final public consultation review – as previously agreed at EAC Cabinet the final version of the Strategy can be signed off by the Leader and Cabinet Member for Roads without the need to return to a future Cabinet meeting. The Active Travel Strategy for South Ayrshire has now been published.
Page 5
APSE Highways, Street Lighting and Winter Maintenance Innovation Awards 2023 24. Ayrshire Roads Alliance were announced as the winners of the Highways Maintenance innovation category for our Temporary Traffic Regulation Order (TTRO) digitalisation submission at an awards dinner on Thursday 23 March 2023 in Blackpool. POLICY/COMMUNITY PLANNING ISSUES 25. A well -maintained road network will contribute to achieving the Community Plan objectives in relation to Economy & Skills and Safer Communities to maintain good access to our communities within East Ayrshire. 26. The matters referred to in this report contribute to the South Ayrshire Council strategic objective of ‘Enhanced Environment through Social, Cultural and Economic Activities’ and within that to the outcome of ‘Work with partners to improve roads and other infrastructure, to encourage house building and business investment that sustains local communities’ LEGAL IMPLICATIONS 27. By virtue of the relevant statutory provisions, principally detailed within the Roads (Scotland) Act 1984, the Council as local roads authority is required to manage and maintain all publicly adopted roads within its area other than those which are maintained and managed by the Scottish Ministers. HUMAN RESOURCES IMPLICATIONS 28. The work programmes have direct impact on human resources and the Alliance will ensure all works are suitably resourced to maintain satisfactory progress. EQUALITY IMPACT IMPLICATIONS 29. An equality impact assessment is not needed because the proposal does not have a differential impact on any of the protected characteristics. FINANCIAL IMPLICATIONS 30. The Ayrshire Roads Alliance will deliver the strategic and local services as stated in the Service Plan. The budget is provided by East Ayrshire Council, South Ayrshire Council, and other external organisations. Appropriate scrutiny arrangements are in place to manage these budgets. RISK IMPLICATIONS 31. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every joint Committee.
Page 6
32. The Works Programmes, Service Plan and the Risk Register do not expose either Council to an increased risk as they have been developed from existing budgets and existing service commitment. TRANSFORMATION STRATEGY 33. This Report aligns with the following design principle stated in the “Transformation Strategy 2017-2022”. Maximum value for our communities; by ensuring the road network is maintained. BACKGROUND PAPERS East Ayrshire Council Cabinet Report – 2023/24 Roads Asset Management Plan – Investment and Programme - 8 March 2023 South Ayrshire Council Leadership Report Road Improvement Plan 2023/24 -25 April 2023 LIST OF APPENDICES Appendix 1 - South Ayrshire Council Programme of Works 2023/24 Appendix 2 - East Ayrshire Council Programme of Works 2023/24 Appendix 3 – EV Public Chargers Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail: kevin.braidwood@ayrshireroadsalliance.org Implementation Officer: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail: kevin.braidwood@ayrshireroadsalliance.org
Page 7
Appendix 1 South Ayrshire Council – Programme of Works 2023/24 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2022 to 2024 Route No Town Road Name Works Description Scheme Score Estimated Cost Comments Variance +/- B734 Old Dailly Barr Old Dailly Old Dailly to Penkill + drainage improvements N/A £108,000 B7035 By Girvan Glendoune Houdston Road (Coalpots) Braetoll South + S Power shut down N/A £200,000 B743 By Mossblown Ayr / Mossblown? West from Brocklehill Farm 53 £270.668 C37 Auchincruive Barrackhall Gibbsyard TBC 48 £118,347 Uncl Tarbolton Springfield Road Garden Street to No 50 46 £28,523 B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton By Holebogs, S bend 59 £48,000 B742 By Coylton B742 Council Boundary - A70/Hillhead, Coylton From A70 at Hillhead south to C21 Craigs Road junction 56 £55,000
Page 8
B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton From Meadowhead Depot entrance south-wards 55 £97,500 B744 Annbank Weston Brae Full Length 53 £59,000 B744 Annbank Browns Crescent Weston Avenue Full Length Craighall Way to 101 Weston Avenue 53 56 £93,000 B742 By Coylton B742 A70 Hillhead - B744 Jcn N Of Annbank, Coylton Bridge of Coyle to C2 52 £190,500 U77 By Coylton Hole Road Full Length 46 £65,911 B7023 Maybole Crosshill Road Full Length 56 £74,687 B7023 Maybole St Cuthbert's Road Full Length 53 £30,669 B7024 Maybole Alloway Road Redbrae to Bypass 51 £55,922 C122 By Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole C122 Gardenrose Path/Maybole - School Road/Minishant, Maybole School to new Bypass Ladycross to new Bypass 50 £60,134
Page 9
B7023 Maybole Maybole Crosshill 30mph Maybole to jcn C58 72 £162,720 U52 Pinwherry Muck road Various TBC 52 £71,978 B7023 Maybole Ballochbroe to Crosshill Dalhowan to C58 £275,435 A719 PH 2 By Maidens By Dunure Pennyglen/B7023 - Kirkoswald Road/Maidens, Maidens A719 Smithy Bridge/Dunure - Croy Brae, Dunure B7023 Enoch Lodge - Caravan Park Cemetery to Drumshang 67 £353,083 A719 PH 1 By Maidens Pennyglen/B7023 - Kirkoswald Rd & Turnberry Rd /Maidens, Turnberry Morriston Farm to Jct Blawearie Maidens to Turnberry 56 £552,084 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget allocation Uncl Ayr Saltpans Road North from Glebe Road 46 £48,750 Uncl Prestwick Morris Road Full Road 43 £34,320 Uncl Ayr Saltpans Road North from Glebe Road 46 £48,750 Uncl Prestwick Morris Road Full Road 43 £34,320
Page 10
Uncl Ayr Green Street Waggon Road to Crown Street 42 £67,760 Uncl Prestwick Craigie Street Full length 39 £11,638 C74 By Ayr Macnairston Road C105 to B742 Junction 52 £92,960 Uncl Ayr Saltpans Road North from Glebe Road 46 £48,750 Uncl Prestwick Morris Road Full Road 43 £34,320 Uncl Ayr Green Street Waggon Road to Crown Street 42 £67,760 Uncl Prestwick Craigie Street Full length 39 £11,638 C74 By Ayr Macnairston Road C105 to B742 Junction 52 £92,960 B744 By Annbank B744 Belston/A70 - Weston Avenue/Annbank, Ayr Auchincruive Junction to Glenview 52 £91,250 Uncl Ayr Ellisland Square Full Length 42 £58,806 Uncl Ayr Chapel Park Road Full Length 40 £53,319 B742 By Maybole B742 Jcn Of A77(T) Ne Of Maybole - Council Boundary S Of Dalrymple, Maybole From B7045 junction westwards N/A £66,845 A719 By Dunure A719 Smithy Bridge/Dunure - Croy Brae, Dunure By Humeston, Castlehill woods to Pennyglen 70 To be measured
Page 11
Ayrshire Roads Alliance – Surface Dressing works – Sites identified for future budget allocation U72 By Dundonald Crooks Full Length N/A U99 By Symington Dundonald Symington C32 to U98 Corraith N/A C115 By Tarbolton Parkmill Road Parkmill to C114 N/A C114 By Tarbolton Largie Road 2 sections N/A B744 By Tarbolton Tarbolton/Crosshands C114 to Auchinweet N/A C74 By Ayr Macnairston Road Macnairston to Lochfergus N/A C60 By Maybole Ladycross Full Length N/A C39 By Ayr Corton Road A77 to Equestrian Centre N/A U2 By Maybole Auchencross C29 to Railway Bridge N/A U25 By Dailly Delamford B741 to Hadyard Hill N/A U56 Girvan Golf Course Road Newton Kennedy Br. to Knockvalley Cottages N/A C102 By Kirkoswald Balvaird Full Length N/A
Page 12
Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2022 to 2024 C17 Tarbolton Westport Footway North side 28 £17,370 Uncl Mossblown Martin Avenue 28 £15,300 Uncl Prestwick Hunters Avenue South from Heathfield Road, west side 23 £7,500 Uncl Maybole Hicks Avenue No 2 to No 94 30 £28,980 C151 Dailly Woodside Both sides from Back St and Hadyard Terr 30 £20,400 Uncl Crosshill Newton Street Church Side of road 30 £15,795 Uncl Dailly Hadyard Terrace Inside footway + part outer section 28 £54,400 Uncl Maybole Ashgrove Avenue Full Length To be measured Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget allocation Uncl Troon Fullarton Drive No 19 to No 37 30 £16,500 B730 Dundonald Drybridge Road Bowling Green to Kilnford Dr 28 £14,500
Page 13
B730 Dundonald Drybridge Road Kilnford Drive to A759 28 £33,600 C492 Troon Bentinck Drive No 97 to No 121 28 £20,000 Uncl Prestwick Outdale Avenue F/path Sherwood Road side , both sides 30 £38,300 B743 Mossblown Mauchline Road Fourways to Railway Bridge North side 28 £15,300 Uncl Ayr Content Avenue South Side full length (College Side) 28 £8,400 Uncl Ayr Bellevue Crescent 34 £37,800 Uncl Ayr Hawthorn Drive 30 £62,000 B742 Annbank Weston Brae 28 £10,700 Uncl Maidens Ardlochan Road 30 £20,000 Uncl Maybole Queens Terrace No 17 to No 39 + cway see separate entry 28 £18,000 Uncl Maybole Kingcraig Avenue No 2 to No 32 + cway see separate entry 28 £22,800
Page 14
Uncl Ayr Lochpark slab replacement 23 £20,425 Uncl Dailly Church Crescent Odd number side full length 30 £16,000 Ayrshire Roads Alliance - Lighting Programme 2023/24 Town Location Work Type No of columns Estimated Programme Cost Comments Variance +/- Ayr Castlehill (Larchwood Road, Hawthorn Drive and Area) Mix of steel and concrete columns SAC cabling and 5th Core 17 £60,000 Start Date 9 May 23 Ayr Belmont Crescent Poor lighting & 5th Core supplies 13 £30,000 Scheduled June 23 Girvan Elder Avenue and Area Old steel columns, poor lighting levels 31 £60,000 Scheduled June 23 Prestwick Mossbank (Phase 2) Old steel columns and 5th Core supplies (ongoing section faults) 35 £60,000 Started 2 May 23 Troon South of town centre area Concrete column replacements (Scottish Power services) 50 £40,000 Scheduled July 23 £250,000 Ayrshire Roads Alliance - LED Lighting Programme 2023/24 Town Description Remaining Ayr - 11
Page 15
Ayrshire Roads Alliance - Traffic and Transportation Programme 2023/24 Calculated Funding Totals Sub-Bid Match Detail Total Bids Project Description Comments Variance +/- SPT £39,000 Match £800,000 Access for All Review Coylton Works underway on site £100,000 Match Alloway to Burton Construction Works underway – contractor started on site 13/02 £450,000 Match Dundonald to Barassie Link Ph1 Construction Currently on hold as we await confirmation of land acquisition £50,000 Match Loans to Troon Railway Station (Phase 3) Currently awaiting confirmation of Sustrans match funding £61,000 Match Active Travel Strategy projects – details TBC Various works – all will be completed by financial year end £100,000 No Match SQP Various Projects Various works – all will be completed by financial year end Sustrans – Places for Everyone £114,926 Match £2,714,926 Access for All Review Coylton Currently awaiting formal grant award
Page 16
Calculated Funding Totals Sub-Bid Match Detail Total Bids Project Description Comments Variance +/- £400,000 Match Alloway to Burton Construction Works underway – contractor started on site 13/02. Funding includes additional works including new SUDS feature with biodiversity enhancements £2,100,000 Match Dundonald to Barassie Link Ph1 Construction Currently on hold as we await confirmation of land acquisition. Funding unconfirmed at this time. £100,000 Match Loans to Troon Railway Station (Phase 3) Currently awaiting formal grant award Regional Active Travel Grant (RATG) £800,000 No Match £800,000 Dalmellington to Ayr active travel route - design Currently awaiting formal award Road Safety Improvemen t Fund £150,000 No Match £150,000 Various road safety improvements - tbc Fund will open to bids shortly – bid currently being prepared
Page 17
Calculated Funding Totals Sub-Bid Match Detail Total Bids Project Description Comments Variance +/- SCSP £100,800 Hub Match £100,800 Active Travel Hub Ayr Ongoing Project delivery – awaiting confirmation of funding – announcement has been delayed on multiple occasions CWSR £50,000 Match £718,000 Access for All Review Coylton Works underway on site £200,000 Match Alloway to Burton Construction Works underway – contractor started on site 13/02 £100,000 Match Active Travel Strategy projects – details TBC Detail TBC – will be programmed and delivered in current FY. £200,000 Match Dundonald to Barassie Link Ph1 Construction On hold - Awaiting confirmation of land acquisition and Sustrans funding element £8,000 Match Loans to Troon Railway Station (Phase 3) Awaiting Sustrans award confirmation for match
Page 18
Calculated Funding Totals Sub-Bid Match Detail Total Bids Project Description Comments Variance +/- £160,000 Hub Match Various projects to provide match for the SCSP funding – active travel infrastructure imps Detail TBC – will be programmed and delivered in current FY. Active Travel Transformat ion Fund (ATTF) £500,000 No Match £1,200,000 Culzean Way – optioneering and outline design ATTF fund is currently oversubscribed, therefore it is very unlikely that a full grant award based on our submission will be successful. £200,000 No Match Heathfield active travel route – optioneering and outline design £200,000 No Match Ayr Hospital active travel route – optioneering and outline design £200,000 No Match Carrick Connections – optioneering and outline design £100,000 No Match Dundonald to Crosshouse – optioneering and outline design Total £6,483,726
Page 19
Calculated Funding Totals Sub-Bid Match Detail Total Bids Project Description Comments Variance +/- ARA New Signals £290,000 No Match £290,000 Signalisation of A759/B730, Dundonald, and signalisation of Doonfoot Rd/Greenfield Ave, Ayr Works to be designed, costed, programmed and installed in current FY. Total £6,773,726 Ayrshire Roads Alliance - Traffic and Transportation Signal Replacement 2023/24 Signal No Town Description Work Type Estimated Programmed Cost Comments Variance +/- SAS1 Ayr Racecourse Road/ Doonfoot Road Junction Replacement £60,000 Design to be undertaken, costed, and works programmed SA17 Ayr Whitletts Road/ Mainholm Road Junction Replacement £60,000 Design to be undertaken, costed, and works programmed SAP15 Ayr Ped Crossing – Whitletts Road corridor Pedestrian Crossing Replacement £40,000 Design to be undertaken, costed, and works programmed
Page 20
Total £160,000 Ayrshire Roads Alliance - Structures Capital Programme 2023/24 Description Work Type Estimated Programme Cost Comments Variance +/- A79-30 Victoria Bridge Joint Replacement and waterproofing £15,000 On Site -£15,000 A79-30 Victoria Bridge Concrete Repairs and Painting £490,571 Design Ongoing. Construction planned 2023/24 -£488,403.12 C12 Dunure Station Road Dunure, Slope Stabilisation £193,346 Design Ongoing, Construction Planned 2023/24 -£185,681.63 U49 Littleton Farm Littleton Farm, Slope Stabilisation £23,000 Ground Invetigation and Design. -£23,000 Girvan Harbour Girvan Harbour South Pier Repairs £136,000 Design -£136,000 Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £587,380.03 Design -£587,380.03 Collennan Reservoir Troon Valve tower access access gantry installation. £70,000 Design and Tender -£70,000 £1,515,297.03
Page 21
Appendix 2 East Ayrshire Council – Programme of Works 2023/24 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme [Works carried over from 2022/23] ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment A71 Main Street Darvel £121,875.00 A735 U26 to past C7 Junction £155,250.00 B743 Strathaven Road Muirkirk 950m to South Lanarkshire Boundary £93,600.00 C134 Rural Sections £28,800.00 U760 Dalcairnie Full Length £122,400.00 U26 Dunlop Full Length £43,200.00 Ellis Street Kilmarnock Full Length £18,900.00 Howard Street Kilmarnock Full Length £85,680.00 Seaford Street Kilmarnock Full Length £134,640.00 Dundonald Road Kilmarnock Smillie Place to Seaford Street £112,00.00 Meiklewood Road Kilmarnock No1 to No 31 £33,000.00 Shortlees Crescent Kilmarnock Rathlin Avenue to Shortlees Road £44,000.00 Old Street Kilmarnock Academy Street to Campbell St £37,800.00 Stoneyhill Avenue Kilmarnock Full Length £22,000.00 Turner Place Kilmarnock Full Length £32,000.00 Craufurdland Road Kilmarnock No87 to No145 £24,000.00 Old Mill Road kilmarnock Lawson Street to Saturrock Street £64,000.00 Grassyards Road Kilmarnock Kennedy Drive to C10 £48,000.00
Page 22
Mansfield Road New Cumnock A76 to Top Corner/ Junction £287,100.00 Blaney Avenue Patna Full Length £33,000.00 Crougar Road Crookedholm Full Length £69,300.00 Meadowside Crookedholm Full Length £7,500.00 High Street Newmilns Full Length £45,000.00 East Donnington Street Darvel Full Length £30,600.00 Burn Road Darvel Various Sections £88,000.00 Campbell Street Darvel Full Length £28,050.00 Glen Terrace Darvel Full Length £30,000.00 Fleming Drive Stewarton Full Length £13,970.00 Lothian Road Stewarton Full Length £55,000.00 Cutsburn Road Stewarton Full Length £88,000.00 Irvine Road Kilmaurs Full Length £25,300.00 Newmill Road Dunlop Rural Section £81,000.00 Middlefield Drive Muirkirk Full Length £14,450.00 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme 2023/24 – New sites A77 Underneath Flyover £41,400.00 A70 South of Muirkirk at B743 Junction £189,750.00 A70 West of Ochiltree £86,250.00 A713 Patna £92,000.00 B743 Mauchline – Mary Morrison Drive to Hill Top £105,300.00 B705 2 Sections from 30mph to Glenshamrock Road £117,000.00 C3 C82 to Stair £129,600.00
Page 23
C11 Patna – Dallowie Farm to Dalvennan £45,000.00 U55 Galston – Various Sections £27,000.00 Furnace Road Muirkirk Furnace Bridge to Golf Course £40,000.00 Main Street Ochiltree A70 to Gallowlee Avenue £104,000.00 Blackwood Avenue Catrine Full Length £27,600.00 Fourfields Catrine Full Length £39,600.00 John Allan Drive Cumnock Full Length £48,000.00 Duncan Court Cumnock Full Length £12,000.00 James Young Avenue Cumnock Full Length £13,000.00 Burnside Road Caponacre Full Length £70,000.00 Riecawr Avenue Bellsbank Full Length £45,600.00 Shalloch Place Bellsbank Full Length £32,400.00 Garden Street Dalrymple Full Length £32,400.00 Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget allocation Hughfield Road Mauchline Full Length £55,500.00 Carrick View Mauchline Full Length £41,250.00 Beechwood Road Mauchline Full Length £69,500.00 Jean Armour Drive Mauchline Full Length £112,500.00
Page 24
Ayrshire Roads Alliance - Footway Structural Maintenance Programme 2023/24 [Works carried over from 2022/23] FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment Riverbank Place Kilmarnock No 3 to No 9 £2,880.00 Burn Road Darvel A71 to West Donnington Street £4,032.00 Mauchline Road Auchinleck Merlin Park to Merlin Garage £18,900.00 Kings Drive Holmhead Cumnock Full Length 1 Side £18,900.00 Broomfield Avenue Holmhead Cumnock Full Length 1 Side £10,080.00 Netherhill Crescent Patna Full Length 1 Side £18,900.00 A713 Dalmellington Road Patna Dalharco Avenue to Doonbank Crescent £30,240.00 Taiglum Drongan Full Length 1 Side £5,670.00 Cessnock Road Hurlford Full Length 1 Side £17,640.00 Homes Road Galston Full Length 1 Side £12,600.00 Rysland drive Fenwick Full Length 1 Side £20,790.00 Bowes Rigg Stewarton Full Length 1 Side £25,200.00 James Young Avenue Netherthird Full Length Both Sides £16,380.00 Western Road Kilmarnock Lewis Drive Side £9,450.00 Knowhead Road Kilmarnock Full Length 1 Side £28,350.00 Castle terrace Kilmarnock Full Length 1 Side £10,368.00
Page 25
Ayrshire Roads Alliance - Environmental Improvement Programme Year Project Description of Works Benefit Estimated Cost Future Years Hayhill, by Drongan, Environmental Improvement Kerb, upgrade verge and form parking bay Improve environment in village and road safety by formalising parking area. £15,000 Future Years Craigie Avenue, Kilmarnock Form Lay-by - street parking bays Improve environment and road safety by reducing on street parking problems. £15,000 Future Years Wellpark Crescent Kilmarnock, widen road. Re-kerb and widen over- run grassed area Improve environment and road safety by reducing on street parking problems. £7,000 Future Years Kilmarnock Rd Service Rd Crosshouse, widen road. Re-kerb and widen over- run grassed area Improve environment and road safety by reducing on street parking problems. £8,000 Future Years Hillcrest, Bellsbank, Dalmellington Parking Bays Form 6 No Off-Street parking bays Improve environment and safety by reducing on street parking problems. £15,000 Future Years North Hamilton Place Kilmarnock, parking bays. Additional Parking Area Improve environment and road safety by reducing on street parking problems. £8,000 Future Years Gateside Road, Galston, widen road. Re-kerb and widen over- run grassed area Improve environment and road safety by reducing on street parking problems. £7,000
Page 26
Ayrshire Roads Alliance - Lighting Capital Programme 2023/24 Town Location Work Type Estimated Cost Comments Variance +/- Galston Cairn Terrace, Cairn View and Cairn Place 5th Core supplies and concrete columns £50,000 Scheduled November 23 Kilmarnock Bridgehousehill Road 5th Core supplies and deteriorated columns £60,000 Scheduled September 23 Muirkirk Garpel Ave, Smallburn Dr Area Ph2 5th Core supplies and concrete columns £75,000 Scheduled October 23 New Cumnock Dalhanna Drive, Mounthope Terrace, Lochbrowan Crescent 5th Core supplies and concrete columns £65,000 Scheduled July 23 £250,000 Ayrshire Roads Alliance - LED Lighting Programme Update 2023/24 [Works carried over from 2022/23] Town Lantern Amount Status Delivery / start install Install complete by Kilmarnock - North East 1135 Complete Dec-21 90% Complete Kilmarnock - Central 1400 On site Aug-23 East Ayrshire - Decorative 350 75% complete tender to be issued for next stage Aug-23 Logan, Lugar, Cronberry & Muirkirk 390 On site Oct-22 May-23 Stewarton, Kilmaurs, Fenwick, Dunlop & Lugton 1420 On site Oct-22 May-23 Current Status Programme completed conversions to date 12,696 Replacement programme 90% complete Overall LED units completed 19,125 LEDs now 90.8% of total EAC inventory
Page 27
Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 [Works carried over from 2022/23] During our design works for our LED conversions, we have identified a number of older installations in East Ayrshire where it is not practicable to simply replace the existing discharge lighting with LED lanterns. Consequently, the following full lighting replacement projects have been programmed and will be funded from the LED replacement budget. Town Location Estimated Cost Scheduled Comments Galston Orchard Street £35,000 Nov-22 90% Complete Kilmarnock Samson Ave, Linfern Ave Areas £95,000 27-Feb-23 40% Complete Stewarton Clerkland Road Area £70,000 27-Feb-23 40% Complete Kilmarnock Glasgow Road B7038 £45,000 27-Mar-23 90% Complete Kilmarnock Forest Grove and Woodlands Grove £85,000 03-Mar-23 40% Complete 2022/23 Total £425,000 Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 Town Location Estimated Cost Scheduled Comments Kilmarnock Woodstock Street & Area £60,000 12-Jun-23 Kilmarnock Gibson St and Carmel Ave Areas £110,000 2-Jun-23 Kilmarnock Wilson Ave, Greenan Rd, Dunure Rd Area £120,000 15-May-23 Stewarton Annick Crescent & Area £75,000 3-Apr-23 10% Complete Fenwick Maunsheugh Road £50,000 May-23 Fenwick Skernieland Road £30,000 Jul-23 Kilmarnock Bonnyton Road £20,000 Jul-23 2023/24 Total £465,000
Page 28
Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2023/24 [Ongoing and identified works] Bridge Strengthening and Replacement Structure Reference Structure Name Proposed Works Project cost estimate Spend to-date Comment Status U22/10 Burnfoot Bridge, near Darvel Replacement – Near tender ready. Land acquisition outstanding £440,000 £5,250 Ground Investigation completed. Land acquisition ongoing with Estates/Legal . SEPA CAR Licence received Design & tender docs C127/10 Low Ashyard Bridge Infilling of bridge by Historical Railways Estate. EAC part contribution £5,000 £0 HRE has funded the installation of temporary supports and working up design to sleeve the structure Programmed Funding discussions ongoing with HRE U26/10 West Clerkland Bridge, near Stewarton Replacement – currently closed to traffic; near tender ready. CPO required to obtain land acquisition. Construction likely to be in future year programme £12,000 £389 Land acquisition stalled due to landowner. CPO reqd. Bridge completely closed to veh & peds. With Legal working on CPO. Tender ready B730/10 Littlemill Bridge, near Rankinston Replacement - near tender ready; land acquisition to be concluded; construction likely to be in future year programme £6,000 £3,442 Land acquisition near complete. Advance electricity diversion complete. Near Tender ready. Works in 2023/24 A71/280/C8 0 Mathews Burn Culvert, West Donnington St, Darvel Replace section of culvert below West Donnington Street; design on going and near tender ready, land acquisition to be concluded. £149,000 £0 SEPA Licence obtained. Land acquisition with Legal to conclude. Design/Tender
Page 29
B713 B713 Road Slip south of Sorn Detailed design and construct sheet piled wall £312,000 £2,450 Consultant working up detailed design & tender documents Near tender ready B705 B705 Road Slip centre of Catrine Detailed design £18,000 £0 No progress B705 B705 Road Slip north of Catrine Detailed design £18,000 £0 No progress Various Investigative works Topographical surveys, paint surveys, etc £6,000 £1,350 Package of topos awarded A735/130/C 58 Gills Burn Culvert, Dunlop Part deck replacement and Retaining Wall Repairs - design in 2022/23 and construction in future year programme £10,000 £0 On hold (as part of F&PM wider ECC build) U751/10 Crossflats Bridge Replacement – design by consultant £60,000 £0 No progress Consultant to be appointed for design via SXL U760/00/C93 Glenhead Culvert Replacement £42,000 £0 Design ongoing U740/10 Barbieston Bridge Boundary Bridge Replacement – design by consultant £24,000 £0 No progress U44/10 Bruntland Bridge Strengthen and refurbish £24,000 £0 No progress Upgrade Works identified from inspections B705/10/C9 1 Cowan Place Culvert, Catrine Masonry repairs/scour repairs £24,000 £0 Site visit undertaken and preliminary design Preliminary design B705/20 Shellies Bridge, Catrine Scour repairs; masonry training wall repairs and culvert extension – Consultant appointed to undertake design & works ongoing; land acquisition Construction in future year programme £6,000 £1,538 Consultant design ongoing. Land acquisition to be determined Design
Page 30
A71/300 Priestland Bridge Retaining Wall strengthening – finalise design, conclude land acquisition/servitude and construct.Tender evaluation. £120,000 £48,301 Works ongoing Site U764/10 Glenmuir Bridge Scour repairs £42,000 £0 No progress A70/130/W3 1 Thornwood Wall, Lugar Replacement - Consultant appointed to undertake design which is ongoing; land acquisition required. Construction in future year programme £6,000 £1,538 Consultant design ongoing and site investigation complete. Sheet pile option developed but conflict with O/H power cables being investigated Design Queens Crescent, Newmilns Replace riverbank retaining wall.tender being evaluated. £325,000 £10,000 Tender delayed until Spring 2023 due to fish spawning issues with river working. Advance tree, vegetation clearance undertaken. Tender ready B741 Coal Glen Embankment Slip, near Dalmellington Ground investigation complete. Consultant finalizing design & tender package. Land acquisition required. Construction potentially in 2022/23. £384,000 £14,000 (Tenders returned and being evaluated) Tender Stage A713/60/C6 1 Polnessan Upper Bridge Extension of culvert. Design and land acquisition in 2022/23. Construction in future year programme. £24,000 £0 No progress C90/35/CG0 2 Cattle Grid Replacement of cattle grid and bypass improvement. Extent of works increased. £30k Wind Farm contribution £136,725 Site works ongoing On Site A736/60/C8 4 Lochridge Culvert Masonry and drainage repairs £60,000 £0 Near ready for tender issue Design F/LUGA/10 Logan to Park Terrace Footbridge, Lugar Replacement of footbridge deck.on refurbished abutments. Consultant design ongoing £150,000 £1,538 Deck replacement and scour protection – design ongoing Design
Page 31
B705/20/C6 8 Smithy’s Culvert, near Catrine Replace with box units - future year programme £0 No progress B741/40/C7 9 Polmathburn Bridge, near Dalmellington Replace damaged deck slabs - future year programme £0 No progress A71 Dundonald Rd Bridge Refurbish – replace expansion joints, waterproofing, drainage, surfacing – design. Construction in future year programme. £36,000 £14,074 Consultant appointed and design ongoing Design A71 Riccarton Viaduct Refurbish – paint, replace expansion joints, waterproofing, drainage, surfacing – design. Construction in future year programme. £36,000 £11,414 Consultant appointed and design ongoing Design A71 River Irvine Bridge Refurbish – paint, replace expansion joints, waterproofing, drainage, surfacing - design. Construction in future year programme. £336,000 £11,414 Consultant appointed and design ongoing Design B741/50 Nith Lodge Bridge Replacement. Appoint consultant for design and construction in future year £54,000 £0 Consultant to be appointed for design via SXL Held pending possible WF proposals Programmed Annick Water, Stewarton Replacement of collapsing gabion training wall. Detailed design by consultant and construction £378,000 £8,713 Draft tender documents being reviewed by ARA Design U/LOGA/10 Old Lugar Bridge Strengthening, masonry repairs and scour protection £300,000 £5,797 Early stages of design Design C85/10 Fenwick Bridge Masonry refurbishment £24,000 £0 Preliminary design. Trial pit investigation ongoing Design B7036/10 Lugar Bridge, Ochiltree Major refurbishment – design in FY 2022/23, construction in future year £24,000 £0 No progress U/KMCK/20 West Shaw Street Bridge Strengthen and Refurbishment £0 No progress
Page 32
C135/20 Avon Bridge Masonry and scour repairs £36,000 £0 No progress U736/10/C6 5 Sykeside Bridge Scour repair £24,000 £0 No progress U729/00/C6 4 Hayhiolm Bridge Masonry and Scour repairs £36,000 £0 No progress U729/00/C7 1 Barry Burn Culvert Masonry and Scour repairs £36,000 £0 No progress U730/00/C3 7 Culvert Masonry and Scour repairs £36,000 £0 No progress C36/10 Nith Bridge Masonry parapet rebuild and repairs to commence end of August 2022 £60,000 £25,242 Site works ongoing Site A70/100 Gatehouse Bridge Parapet heighten, scour repairs & masonry repairs £24,000 £0 No progress A70/110/C4 6 Rose Burn Bridge Masonry and scour repairs £24,000 £0 No progress Broomknowe Retaining Wall Design in 2022/23, construction in future years £24,000 £0 No progress W/MUIR/20 Muirkirk Shops Retaining Wall Design in 2022/23, construction in future years £24,000 £0 Topo survey. Trial pit investigation works awarded Parapet Upgrades A70/70 Burnock Bridge, Ochiltree Parapet and other masonry repairs £216,000 £5,545 £196,496 Contract awarded, start date TBC. Further Ecology surveys being undertaken Site A713/90 Dunaskin Bridge, Waterside Widening to create footway and replace both masonry parapets - design ongoing. £70,000 £1,480 Out to Tender Tender Stage
Page 33
B743/80 Cleuch Bridge, Sorn Upgrade of parapets and install footway £90,000 £0 Design ongoing. Further ecology surveys being undertaken Programmed C134/10 Ranoldcoup Bridge, Darvel Masonry repairs and heighten parapets £264,000 £0 No progress B769/40 Corsehill Mill Bridge Parapet replacement – design in FY 2021/22 £12,000 £0 No progress B7082/10 Townhead Bridge Parapet replacement £150,000 £0 Trial pit investigation works awarded B743/135/C 50 Beacon Hill Culvert Headwall Repairs £0 No progress W/NCUMN/1 0 Burnside Retaining Wall Replacement £36,000 £0 Preliminary Design Design Rail Incursion C23/10 Rigg Road Rail Bridge, Cumnock Safety fencing - future year programme £0 No progress Non ARA Council Footbridges Various sites Design, investigation £120,000 £2,196 Minor repairs ongoing F/HURL/10 Portland Brae Footbridge Load Assessment, paint and replace concrete planks £230,000 £22,687 Consultant completed structural assessment and strengthenin g options. Detailed design cost fee being reviewed by ARA. Design F/CATR/20 Institute Ave Footbridge, Catrine Refurbishment £72,000 £0 No progress A71/190 River Irvine Emergency repairs to expansion joint. Scheme transferred from Revenue to Capital £28,794
Page 34
Principal Inspections Various Principal Inspections of bridge stock by consultant and in-house staff £216,000 £0 No progress Capital staff fees Staff fee already included in above estimates £260,000 Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2023/24 (i) Road Safety Programme Town/Route Location Proposed Scheme Kilmarnock A71 / Campbell Street Off Slip Signalisation Hurlford A71/B7073 roundabout AIP junction assessment Dunlop Lugton Road Pedestrian crossing Dunlop Main Street HGV route assessment Lugton A735/A736 Anti-skid surfacing and traffic sign review B741 Dalmellington to New Cumnock Road safety route review B7034 Hollybush Speed limit review A713 Waterside Speed limit review B730 Drongan Speed limit review Auchinleck Various General review of parking restrictions Mauchline Various General review of parking restrictions Patna Doon Bridge Signalisation and associated safety improvement works
Page 35
(ii) Safer Neighborhoods Town Location Proposed Scheme Galston Cessnock Road at Bowling Club Pedestrian build-out Stewarton Various roads 20mph speed limit orders amendments Kilmarnock Whatriggs Road Parking review Cumnock Glaisnock Street Possible speed reduction measures Various Various locations Vehicle activated signs upgrade Crookedholm Grougar Road Pedestrian crossing and road widening Sinclairston B7046 Traffic calming (iii) Rural Route Action Plans Route Proposed Scheme B778 B778 Fenwick to Stewarton Route Study (iv) Cycling, Walking and Safer Routes (CWSR) Town Location Proposed Scheme Kilmarnock Grassyards Road Cycle route enhancement scheme Kilmarnock Annahill Park to B7073 Cycle route Fenwick Kirkton Rd/Main St – Fenwick PS Pedestrian safety improvements Mauchline Loudoun Street Pedestrian crossing Kilmaurs Main Street Traffic modelling for improved pedestrian facilities Kilmaurs Townhead Pedestrian crossing Crosshouse Crosshouse-Dundonald Cycle route feasibility study Newmilns Loudoun Road Pedestrian Crossing Investigation
Page 36
Darvel East Main St/Murdoch Road Junction sightline improvement Kilmarnock Green Infinity Loop Design process for cycle path network (v) Strathclyde Partnership for Transport (SPT) Location Project Kilmarnock Phase 3 refurbishment of Kilmarnock bus station to upgrade concourse and stance areas. Kilmarnock Glasgow Road bus park & ride (vi) SUSTRANS Location Project Hurlford Hurlford Street Design Project Appendix 3 Ayrshire Roads Alliance - EV Public Chargers EAST AYRSHIRE CPS ID Type Make Location 51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 50821 22kw eVolt Multi Storey Car Park, Kilmarnock, KA1 1LU 51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH 52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU 52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
Page 37
52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB 51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU 52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ 50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW 51170 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP 60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR 52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU 52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE 52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG 52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS 52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB 52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY 51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL 52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ 52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB 52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ 52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
Page 38
52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ 52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH 52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY 52962 Rapid eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 52963 22kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU 53080 7kw eVolt Netherthird Community Centre, 65 Ryderston Drive, Cumnock, KA18 3AR 53778 Rapid eVolt Main Street Car Park, Muirkirk 53775 22kw eVolt Rose Reilly Sports Centre, Stewarton 53776 7kw eVolt Standalane Car Park, Stewarton 60786 7kW eVolt Academy Street, Hurlford 60732 22kW eVolt Drongan Centre car park, Mill of Shield Road 51210 22kW eVolt Carnshalloch Avenue car park, Patna 60924 7kW eVolt Queen Street car park, Kilmarnock 60250 22kW eVolt New Cumnock Outdoor Swimming Pool car park 60955 22kW eVolt Gatehead Road car park, Crosshouse 61021 7kW eVolt East Ayrshire Community Hospital, Cumnock 61022 7kW eVolt East Ayrshire Community Hospital, Cumnock 61983 7kW eVolt Morton Place car park, Kilmarnock 61984 7kW eVolt Morton Place car park, Kilmarnock 61985 7kW eVolt Morton Place car park, Kilmarnock SOUTH AYRSHIRE CPS ID Type Make Location 51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW 51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU 51535 Rapid eVolt Burns Statue Square, Ayr, KA7 UT 52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN 52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT 52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
Page 39
51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY 50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ 50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF 52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG 50816 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG 52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR 52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH 52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU 52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE 52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW 52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL 53774 Rapid eVolt Academy Street, Troon 53773 Rapid eVolt Lodge Road Car Park, Turnberry 53777 22kw eVolt Burnside Road, Monkton 60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly 60081 22kw eVolt Inches Close car park, Maybole 61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton 61986 22kw eVolt Dundonald Primary School car park, Dundonald 60086 22kw eVolt Mossblown Activity Centre car park, Mossblown 60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald 61979 7kW eVolt Chalmers Arcade car park, Girvan 61980 7kW eVolt Chalmers Arcade car park, Girvan 61981 7kW eVolt Chalmers Arcade car park, Girvan Awaiting CPS number 22kW eVolt Barrhill Community car park, Main Street, Barrhill