AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
19 MAY 2023 
Report by the Head of Ayrshire Roads Alliance
______________________________________________________________ 
SUBJECT: ROADWORKS PROGRAMME 2023/24
______________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this report is to advise the Joint Committee on the progress of
work through the roads improvement programmes within East Ayrshire and
South Ayrshire for financial year 2023 to 2024. 
RECOMMENDATIONS 
2. It is recommended that Joint Committee: 
(i) Notes, the Ayrshire Roads Alliance programmed works 2023/24
(ii) Otherwise, notes the contents of this Report. 
BACKGROUND 
3. The budget allocation for East and South Ayrshire Councils Roads Investment
Programme for FY 2023/24 can be seen in tables 1 and 2 below respectively. 
Programme Area Budget (£m)
Carriageway Resurfacing 3.240
Footway Resurfacing 0.250
Environmental Improvements  0.015
Street Lighting 0.250
Multi Storey 0.030
Structures (Bridges & Culverts) 4.100
Flood Prevention 2.666
Kilmarnock Car Parks 2.719
Browns Road 0.220
EV Charging 0.100
Active Travel 0.100
Other Works 0.080
Total £14.040
External Funding 
SPT – Park & Ride £0.020 
SPT - Bus Station Improvements £1.800
Cycling, Walking & Safer Routes £0.779
Smarter Choices, Smarter Places 0.170 (tbc)
Sustrans 0.030 (tbc)
Road Safety Improvement Fund 0.150 prospective bid
Active Travel Transformation fund 1.800 (tbc)

Page 2

Total £2.599 confirmed   
Table 1: East Ayrshire Council Roads Investment Programme 2023/24 
Programme Area Budget (£m)
Carriageway & Footway Resurfacing 2.812
Structures (Bridges & Culverts) 0.410
Street Lighting 0.250
Traffic Signals 0.290
Girvan Harbour 0.502
Slope Stabilisation 0.216
EV charging  0.190
Tourist and visitor Facilities 0.150
Total £4.946
External Funding 
Cycling, Walking & Safer Routes 0.718
Smarter Choices, Smarter Places 0.101 (tbc)
Sustrans 2.715 (tbc)
SPT 0.800
Regional Active Travel Grant 0.800tbc
Road Safety Improvement Fund 0.150 (prospective bid)
Active Travel transformation fund 1.200
Total £2.718m confirmed 
Table 2: South Ayrshire Council Roads Investment Programme 2023/24 
DETAIL 
4. The programmes for FY 23/24 are contained within Appendices One and Two. 
Resurfacing 
5. Road improvement programmes in East Ayrshire Council for FY 23/24
commenced April 2023 and in South Ayrshire Council commencing May 2023
with some early improvement works complete.  The price of road material and
fuel has not subsided, the focus this year will be to limit outsourcing works to
external contractors, which will be achieved by combining and upskilling our
workforce. 
6. Early planning meetings with Team Leaders, Depot Coordinators and our
Roadwork Coordinator has concluded and will continue throughout the year to
monitor budget, progress and move resources as required. 
7. As previously reported at our last joint committee, Ayrshire Roads Alliance has
submitted bids to Scottish Timber Transport for both East and South Ayrshire to
the value of £286k and £630k respectively.  Communication has been received

Page 3

confirming they are currently reviewing our applications with a decision expected
towards end of May/beginning of June. 23. 
8. Due to an early low temperature forecast received, winter operations was
extended for a week ending 1st May 2023.  Summer standby has now
commenced with Ayrshire Roads Alliance responding to incidents on the
network. 
9. At the end of winter our salt stocks are 2257tonnes in East Ayrshire Council and
2239tonnes in South Ayrshire Council with resilience levels at 4,400tonnes. 
10. A lessons learned workshop is planned which will be attended by Winter
Controllers and Winter Supervisors to discuss 22/23 winter operations and take
forward areas of improvement for winter 23/24.  Route optimisation of our gritting
routes is at the early stages with discussions progressing with specialist
Contractors.. 
Street Lighting 
11. Street lighting teams continue to focus on cyclic maintenance faults and statutory
electrical test and inspection. 
12. Utilising the external Contractor LED lighting installations continue to progress
as detailed in Appendix 1 and 2. 
Electric Vehicle Infrastructure 
13. The Electric Vehicle Infrastructure Fund (EVIF programme) has been included
within Appendix three for South and East Ayrshire respectively, with the number
of public chargers installed to date is included at Appendix 3. 
14. New EV chargers have been commissioned at Cumnock Community Hospital,
with installations proceeding at Sturrock Street (East), Car Park and at Rosebank
Resource Centre (both Kilmarnock). 
15. PAN Ayrshire Public Electric Vehicle Charging Strategy has been approved by
all three authorities with Ayrshire Roads Alliance taking the lead.  Work has
commenced but it is at very stages of development. 
Structures 
16. Many of the bridge projects that we undertake requires works to be undertaken
within the watercourse and depending on what the works involve it can often take
up to 4months for the SEPA licence to be obtained with other constraints, such
as the fish spawning season which typically runs from end October to end April
restricting work in the watercourse. 
17. Appendix B details East Ayrshire Council Bridges Capital programme with three
projects, Queens Crescent Retaining Walls, Newmillns and B741 Coal Glen

Page 4

Embankment Slip, near Dalmellington issued for tender with a remaining seven
projects nearing tender ready with a combined estimated value of £3.62m. 
18. Land acquisition and/or access agreements are often required for bridge related
projects and can cause delay to the projects. A number of projects are currently
near tender ready but are being delayed due to land related issues. ARA are
actively working with the Council’s Estates and Legal teams in all of these
projects but land acquisition can be a very challenging and resource intense
activity for ARA, Estates and Legal sections. Again, where possible, projects that
do not require land acquisition or formal legal access agreements are being
brought forward. 
19. ARA representing South Ayrshire Council as a coastal authority participate as
one of four Local Authorities on the Coastal Adaptation Budget Group which has
representation from Scottish Government, Nature Scot, SEPA and Local
Authorities. The group is currently considering the model for allocation of the year
3 funding for the coastal change adaptation fund. 
20.    The business case for Ballantrae was accepted by the Coastal Adaption Budget               
Group and £180,000 will be included for this project in the Scottish Government    
General Capital Grant for South Ayrshire Council in 2023/24.  The onsite start up
meeting took place on the 21st April and the project is now live. 
21. The business case for Girvan Golf course was not accepted for funding, however
positive feedback on the objective was received and encouragement given to
submit the case study for future funding taking note of the feedback provided.
The opportunity to use dredge material from Girvan Harbour to replenish the
Girvan Golf Course beach is being investigated as part of the future dredging
planned without access to this funding. 
Traffic & Transportation 
22. Agreement has been reached where necessary to roll grant funding provision
into the new financial year to complete projects. The focus of these projects will
continue to be improvements to our roads and infrastructure to improve journeys
and increase safety measures where required. At present, grant award
confirmation has been received from Strathclyde Partnership for Transport (SPT)
and Cycling, Walking, Safer Routes (CWSR), whilst we continue to await
conformation from various others including Sustrans, Smarter Choices, Smarter
Places (SCSP), the Active Travel Transformation Fund (ATTF), the Regional
Active Travel Grant (RATG) and the Road Safety Improvement Fund (RSIF). 
23. The Active Travel Strategy for East Ayrshire will shortly be undergoing a final
public consultation review – as previously agreed at EAC Cabinet the final
version of the Strategy can be signed off by the Leader and Cabinet Member for
Roads without the need to return to a future Cabinet meeting. The Active Travel
Strategy for South Ayrshire has now been published.

Page 5

APSE Highways, Street Lighting and Winter Maintenance Innovation Awards 2023 
24. Ayrshire Roads Alliance were announced as the winners of the Highways
Maintenance innovation category for our Temporary Traffic Regulation Order
(TTRO) digitalisation submission at an awards dinner on Thursday 23 March
2023 in Blackpool. 
POLICY/COMMUNITY PLANNING ISSUES 
25. A well -maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
26. The matters referred to in this report contribute to the South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome of ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’ 
LEGAL IMPLICATIONS 
27. By virtue of the relevant statutory provisions, principally detailed within the Roads
(Scotland) Act 1984, the Council as local roads authority is required to manage
and maintain all publicly adopted roads within its area other than those which are
maintained and managed by the Scottish Ministers. 
HUMAN RESOURCES IMPLICATIONS 
28. The work programmes have direct impact on human resources and the Alliance  
will ensure all works are suitably resourced to maintain satisfactory progress. 
EQUALITY IMPACT IMPLICATIONS 
29. An equality impact assessment is not needed because the proposal does not
have a differential impact on any of the protected characteristics. 
FINANCIAL IMPLICATIONS 
30. The Ayrshire Roads Alliance will deliver the strategic and local services as stated
in the Service Plan. The budget is provided by East Ayrshire Council, South
Ayrshire Council, and other external organisations. Appropriate scrutiny
arrangements are in place to manage these budgets. 
RISK IMPLICATIONS 
31. The Ayrshire Roads Alliance Risk Register is reviewed and presented at every 
joint Committee.

Page 6

32. The Works Programmes, Service Plan and the Risk Register do not expose
either Council to an increased risk as they have been developed from existing
budgets and existing service commitment. 
TRANSFORMATION STRATEGY 
33. This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”. 
Maximum value for our communities; by ensuring the road network is maintained. 
BACKGROUND PAPERS 
East Ayrshire Council Cabinet Report – 2023/24 Roads Asset Management Plan
– Investment and Programme - 8 March 2023 
South Ayrshire Council Leadership Report Road Improvement Plan 2023/24 -25
April 2023   
LIST OF APPENDICES 
Appendix 1 - South Ayrshire Council Programme of Works 2023/24 
Appendix 2 - East Ayrshire Council Programme of Works 2023/24
Appendix 3 – EV Public Chargers 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation Officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org

Page 7

Appendix 1 
South Ayrshire Council – Programme of Works 2023/24 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme over two years 2022 to 2024 
Route
No
Town Road Name Works
Description
Scheme
Score
Estimated
Cost
Comments Variance +/-
B734 Old Dailly Barr Old Dailly Old Dailly to
Penkill +
drainage
improvements
N/A £108,000  
B7035 By Girvan Glendoune Houdston
Road (Coalpots)
Braetoll South
+ S Power
shut down
N/A £200,000  
B743 By
Mossblown
Ayr / Mossblown? West from
Brocklehill
Farm
53 £270.668  
C37 Auchincruive Barrackhall Gibbsyard TBC 48 £118,347  
Uncl Tarbolton Springfield Road Garden Street
to No 50
46 £28,523  
B742 By Coylton B742 Council
Boundary -
A70/Hillhead, Coylton
By Holebogs,
S bend
59 £48,000  
B742 By Coylton B742 Council
Boundary -
A70/Hillhead, Coylton
From A70 at
Hillhead
south to C21
Craigs Road
junction
56 £55,000

Page 8

B742 By Coylton B742 A70 Hillhead -
B744 Jcn N Of
Annbank, Coylton
From
Meadowhead
Depot
entrance
south-wards
55 £97,500  
B744 Annbank Weston Brae Full Length 53 £59,000  
B744 Annbank Browns Crescent 
Weston Avenue
Full Length
Craighall Way
to 101
Weston
Avenue
53
56
£93,000  
B742 By Coylton B742 A70 Hillhead -
B744 Jcn N Of
Annbank, Coylton
Bridge of
Coyle to C2
52 £190,500  
U77 By Coylton Hole Road Full Length 46 £65,911  
B7023 Maybole Crosshill Road Full Length 56 £74,687  
B7023 Maybole St Cuthbert's Road Full Length 53 £30,669  
B7024 Maybole Alloway Road Redbrae to
Bypass
51 £55,922  
C122 By Maybole  C122 Gardenrose
Path/Maybole -
School
Road/Minishant,
Maybole 
C122 Gardenrose
Path/Maybole -
School
Road/Minishant,
Maybole
School to new
Bypass 
Ladycross to
new Bypass
50  £60,134

Page 9

B7023 Maybole Maybole Crosshill 30mph
Maybole to
jcn C58
72 £162,720  
U52 Pinwherry Muck road Various TBC 52 £71,978  
B7023 Maybole Ballochbroe to
Crosshill
Dalhowan to
C58 
£275,435  
A719
PH 2
By Maidens 
By Dunure
Pennyglen/B7023 -
Kirkoswald
Road/Maidens,
Maidens 
A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
B7023 Enoch
Lodge -
Caravan Park 
Cemetery to
Drumshang
67 £353,083  
A719
PH 1
By Maidens  Pennyglen/B7023 -
Kirkoswald Rd & 
Turnberry Rd
/Maidens, Turnberry
Morriston
Farm to Jct
Blawearie 
Maidens to
Turnberry
56  £552,084  
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget
allocation 
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320  
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320

Page 10

Uncl Ayr Green Street Waggon
Road to
Crown Street
42 £67,760  
Uncl Prestwick Craigie Street Full length 39 £11,638  
C74 By Ayr Macnairston Road C105 to B742
Junction
52 £92,960  
Uncl Ayr Saltpans Road North from
Glebe Road
46 £48,750  
Uncl Prestwick Morris Road Full Road 43 £34,320  
Uncl Ayr Green Street Waggon
Road to
Crown Street
42 £67,760  
Uncl Prestwick Craigie Street Full length 39 £11,638  
C74 By Ayr Macnairston Road C105 to B742
Junction
52 £92,960  
B744 By Annbank B744 Belston/A70 -
Weston
Avenue/Annbank, Ayr
Auchincruive
Junction to
Glenview
52 £91,250  
Uncl Ayr Ellisland Square Full Length 42 £58,806  
Uncl Ayr Chapel Park Road Full Length 40 £53,319  
B742 By Maybole B742 Jcn Of A77(T)
Ne Of Maybole -
Council Boundary S
Of Dalrymple,
Maybole
From B7045
junction
westwards
N/A £66,845  
A719 By Dunure A719 Smithy
Bridge/Dunure - Croy
Brae, Dunure
By Humeston,
Castlehill
woods to
Pennyglen 
70 To be
measured

Page 11

Ayrshire Roads Alliance – Surface Dressing works – Sites identified for future budget allocation 
U72 By
Dundonald
Crooks Full Length N/A   
U99 By
Symington
Dundonald Symington C32 to U98
Corraith
N/A   
C115 By
Tarbolton
Parkmill Road Parkmill to
C114
N/A   
C114 By
Tarbolton
Largie Road 2 sections N/A   
B744 By
Tarbolton
Tarbolton/Crosshands C114 to
Auchinweet
N/A   
C74 By Ayr Macnairston Road Macnairston
to Lochfergus
N/A   
C60 By Maybole Ladycross Full Length N/A   
C39 By Ayr Corton Road A77 to
Equestrian
Centre
N/A   
U2 By Maybole Auchencross C29 to
Railway
Bridge
N/A   
U25 By Dailly Delamford B741 to
Hadyard Hill
N/A   
U56 Girvan Golf Course Road Newton
Kennedy Br.
to
Knockvalley
Cottages
N/A   
C102 By
Kirkoswald
Balvaird  Full Length N/A

Page 12

Ayrshire Roads Alliance - Footway Structural Maintenance Programme over two years 2022 to 2024 
C17 Tarbolton Westport Footway
North side
28 £17,370  
Uncl Mossblown Martin Avenue  28 £15,300  
Uncl Prestwick Hunters Avenue South from
Heathfield
Road, west
side
23 £7,500  
Uncl Maybole Hicks Avenue No 2 to No 94 30 £28,980  
C151 Dailly Woodside Both sides
from Back St
and Hadyard
Terr
30 £20,400  
Uncl Crosshill Newton Street Church Side
of road
30 £15,795  
Uncl Dailly Hadyard Terrace Inside
footway +
part outer
section
28 £54,400  
Uncl Maybole Ashgrove Avenue Full Length  To be
measured 
Ayrshire Roads Alliance - Footway Structural Maintenance Programme – sites identified for future budget
allocation 
Uncl Troon Fullarton Drive  No 19 to No
37
30 £16,500  
B730 Dundonald Drybridge Road Bowling
Green to
Kilnford Dr
28 £14,500

Page 13

B730 Dundonald Drybridge Road Kilnford Drive
to A759
28 £33,600  
C492 Troon Bentinck Drive No 97 to No
121
28 £20,000  
Uncl Prestwick Outdale Avenue F/path
Sherwood
Road side ,
both sides
30 £38,300          
B743 Mossblown Mauchline Road Fourways to
Railway
Bridge North
side
28 £15,300  
Uncl Ayr Content Avenue South Side
full length
(College
Side)
28 £8,400                  
Uncl Ayr Bellevue Crescent  34 £37,800  
Uncl Ayr Hawthorn Drive  30 £62,000  
B742 Annbank Weston Brae  28 £10,700  
Uncl Maidens Ardlochan Road  30 £20,000          
Uncl Maybole Queens Terrace No 17 to No
39 + cway
see separate
entry
28 £18,000  
Uncl Maybole Kingcraig Avenue No 2 to No 32
+ cway see
separate
entry
28 £22,800

Page 14

Uncl Ayr Lochpark slab
replacement
23 £20,425  
Uncl Dailly Church Crescent Odd number
side full
length
30 £16,000   
Ayrshire Roads Alliance - Lighting Programme 2023/24 
Town Location Work Type No of
columns
Estimated
Programme Cost
Comments Variance +/-
Ayr Castlehill (Larchwood Road,
Hawthorn Drive and Area)
Mix of steel and
concrete columns SAC
cabling and 5th Core
17 £60,000 Start Date
9 May 23 
Ayr Belmont Crescent Poor lighting & 5th
Core supplies 13 £30,000 Scheduled
June 23 
Girvan Elder Avenue and Area Old steel columns, poor
lighting levels 31 £60,000 Scheduled
June 23 
Prestwick Mossbank (Phase 2)
Old steel columns and
5th Core supplies
(ongoing section faults)
35 £60,000 Started 
2 May 23 
Troon South of town centre area
Concrete column
replacements (Scottish
Power services)
50 £40,000
Scheduled
July 23 
£250,000   
Ayrshire Roads Alliance - LED Lighting Programme 2023/24 
Town Description Remaining
Ayr - 11

Page 15

Ayrshire Roads Alliance - Traffic and Transportation Programme 2023/24 
Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/- 
SPT £39,000 Match £800,000 Access for All
Review Coylton
Works underway
on site 
£100,000  Match
Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02 
£450,000  Match
Dundonald to
Barassie Link
Ph1 Construction
Currently on hold
as we await
confirmation of
land acquisition 
£50,000 Match Loans to Troon
Railway Station
(Phase 3)
Currently
awaiting
confirmation of
Sustrans match
funding 
£61,000  Match
Active Travel
Strategy projects
– details TBC
Various works –
all will be
completed by
financial year end 
£100,000  No
Match 
SQP Various
Projects
Various works –
all will be
completed by
financial year end 
Sustrans –
Places for
Everyone 
£114,926  Match
£2,714,926  Access for All
Review Coylton
Currently
awaiting formal
grant award

Page 16

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
£400,000 Match Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02. Funding
includes
additional works
including new
SUDS feature
with biodiversity
enhancements 
£2,100,000 Match Dundonald to
Barassie Link
Ph1 Construction
Currently on hold
as we await
confirmation of
land acquisition.
Funding
unconfirmed at
this time. 
£100,000 Match Loans to Troon
Railway Station
(Phase 3)
Currently
awaiting formal
grant award 
Regional
Active
Travel Grant
(RATG)
£800,000 No
Match
£800,000 Dalmellington to
Ayr active travel
route - design
Currently
awaiting formal
award 
Road Safety
Improvemen
t Fund
£150,000 No
Match
£150,000 Various road
safety
improvements -
tbc
Fund will open to
bids shortly – bid
currently being
prepared

Page 17

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
SCSP £100,800 Hub
Match
£100,800 Active Travel Hub
Ayr
Ongoing Project
delivery –
awaiting
confirmation of
funding –
announcement
has been delayed
on multiple
occasions 
CWSR  £50,000 Match £718,000 Access for All
Review Coylton
Works underway
on site 
£200,000 Match Alloway to Burton
Construction
Works underway
– contractor
started on site
13/02 
£100,000 Match Active Travel
Strategy projects
– details TBC
Detail TBC – will
be programmed
and delivered in
current FY. 
£200,000 Match Dundonald to
Barassie Link
Ph1 Construction
On hold -
Awaiting
confirmation of
land acquisition
and Sustrans
funding element 
£8,000 Match Loans to Troon
Railway Station
(Phase 3)
Awaiting
Sustrans award
confirmation for
match

Page 18

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
£160,000 Hub
Match
Various projects
to provide match
for the SCSP
funding – active
travel
infrastructure
imps
Detail TBC – will
be programmed
and delivered in
current FY. 
Active
Travel
Transformat
ion Fund
(ATTF)
£500,000 No
Match
£1,200,000 Culzean Way –
optioneering and
outline design 
ATTF fund is
currently
oversubscribed,
therefore it is very
unlikely that a full
grant award
based on our
submission will
be successful. 
£200,000 No
Match
Heathfield active
travel route –
optioneering and
outline design 
£200,000 No
Match
Ayr Hospital
active travel route
– optioneering
and outline
design 
£200,000 No
Match
Carrick
Connections –
optioneering and
outline design 
£100,000 No
Match
Dundonald to
Crosshouse –
optioneering and
outline design 
Total £6,483,726

Page 19

Calculated
Funding
Totals 
Sub-Bid Match
Detail
Total Bids Project
Description
Comments Variance
+/-
ARA New
Signals £290,000 No
Match
£290,000 Signalisation of
A759/B730,
Dundonald, and
signalisation of
Doonfoot
Rd/Greenfield Ave,
Ayr
Works to be
designed, costed,
programmed and
installed in current
FY. 
Total £6,773,726   
Ayrshire Roads Alliance - Traffic and Transportation Signal Replacement 2023/24 
Signal
No Town  Description  Work
Type
Estimated Programmed
Cost 
Comments Variance
+/-
SAS1 Ayr
Racecourse
Road/
Doonfoot Road
Junction
Replacement £60,000
Design to be
undertaken,
costed, and
works
programmed 
SA17 Ayr
Whitletts Road/
Mainholm
Road
Junction
Replacement £60,000
Design to be
undertaken,
costed, and
works
programmed 
SAP15 Ayr
Ped Crossing –
Whitletts Road
corridor
Pedestrian
Crossing
Replacement
£40,000
Design to be
undertaken,
costed, and
works
programmed

Page 20

Total    £160,000   
Ayrshire Roads Alliance - Structures Capital Programme 2023/24 
Description   Work Type Estimated
Programme Cost 
Comments Variance
+/-
A79-30 Victoria Bridge Joint Replacement and waterproofing £15,000 On Site -£15,000 
A79-30 Victoria Bridge Concrete Repairs and Painting £490,571 Design
Ongoing.
Construction
planned
2023/24
-£488,403.12
C12 Dunure Station Road Dunure, Slope Stabilisation £193,346 Design
Ongoing,
Construction
Planned
2023/24
-£185,681.63
U49 Littleton
Farm
Littleton Farm, Slope Stabilisation  £23,000 Ground
Invetigation
and Design.
-£23,000
Girvan Harbour Girvan Harbour South Pier Repairs £136,000 Design  -£136,000
Girvan Harbour Girvan Harbour Timber Jetty Sheet Piles £587,380.03 Design  -£587,380.03
Collennan
Reservoir Troon
Valve tower access access gantry installation. £70,000 Design and
Tender
-£70,000  
£1,515,297.03

Page 21

Appendix 2 
East Ayrshire Council – Programme of Works 2023/24 
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme [Works carried over from 2022/23] 
ROAD LOCATION Estimated Cost Cost to Date variance +/- Comment
A71 Main Street Darvel £121,875.00   
A735 U26 to past C7 Junction £155,250.00   
B743 Strathaven
Road Muirkirk 950m to South Lanarkshire Boundary £93,600.00   
C134 Rural Sections £28,800.00   
U760 Dalcairnie Full Length £122,400.00   
U26 Dunlop Full Length £43,200.00   
Ellis Street
Kilmarnock Full Length £18,900.00   
Howard Street
Kilmarnock Full Length £85,680.00   
Seaford Street
Kilmarnock Full Length £134,640.00   
Dundonald Road
Kilmarnock Smillie Place to Seaford Street £112,00.00   
Meiklewood Road
Kilmarnock No1 to No 31 £33,000.00   
Shortlees Crescent
Kilmarnock Rathlin Avenue to Shortlees Road £44,000.00   
Old Street
Kilmarnock Academy Street to Campbell St £37,800.00   
Stoneyhill Avenue
Kilmarnock Full Length £22,000.00   
Turner Place
Kilmarnock Full Length £32,000.00   
Craufurdland Road
Kilmarnock No87 to No145 £24,000.00   
Old Mill Road
kilmarnock Lawson Street to Saturrock Street £64,000.00   
Grassyards Road
Kilmarnock Kennedy Drive to C10 £48,000.00

Page 22

Mansfield Road
New Cumnock A76 to Top Corner/ Junction £287,100.00   
Blaney Avenue
Patna Full Length £33,000.00   
Crougar Road
Crookedholm Full Length £69,300.00   
Meadowside
Crookedholm Full Length £7,500.00   
High Street
Newmilns Full Length £45,000.00   
East Donnington
Street Darvel Full Length £30,600.00   
Burn Road Darvel Various Sections £88,000.00   
Campbell Street
Darvel Full Length £28,050.00   
Glen Terrace
Darvel Full Length £30,000.00   
Fleming Drive
Stewarton Full Length £13,970.00   
Lothian Road
Stewarton Full Length £55,000.00   
Cutsburn Road
Stewarton Full Length £88,000.00   
Irvine Road
Kilmaurs Full Length £25,300.00   
Newmill Road
Dunlop Rural Section £81,000.00   
Middlefield Drive
Muirkirk Full Length £14,450.00   
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme 2023/24 – New sites 
A77 Underneath Flyover £41,400.00   
A70 South of Muirkirk at B743 Junction £189,750.00   
A70 West of Ochiltree £86,250.00   
A713 Patna £92,000.00   
B743 Mauchline – Mary Morrison Drive to Hill Top £105,300.00   
B705 2 Sections from 30mph to Glenshamrock Road £117,000.00   
C3 C82 to Stair £129,600.00

Page 23

C11 Patna – Dallowie Farm to Dalvennan £45,000.00   
U55 Galston – Various Sections £27,000.00   
Furnace Road
Muirkirk Furnace Bridge to Golf Course £40,000.00   
Main Street
Ochiltree A70 to Gallowlee Avenue £104,000.00   
Blackwood Avenue
Catrine Full Length £27,600.00   
Fourfields Catrine Full Length £39,600.00   
John Allan Drive
Cumnock Full Length £48,000.00   
Duncan Court
Cumnock Full Length £12,000.00   
James Young
Avenue Cumnock Full Length £13,000.00   
Burnside Road
Caponacre Full Length £70,000.00   
Riecawr Avenue
Bellsbank Full Length £45,600.00   
Shalloch Place
Bellsbank Full Length £32,400.00   
Garden Street
Dalrymple Full Length £32,400.00   
Ayrshire Roads Alliance - Carriageway Structural Maintenance Programme – Sites identified for future budget allocation 
Hughfield Road
Mauchline Full Length £55,500.00   
Carrick View
Mauchline Full Length £41,250.00   
Beechwood Road
Mauchline Full Length £69,500.00   
Jean Armour Drive
Mauchline Full Length £112,500.00

Page 24

Ayrshire Roads Alliance - Footway Structural Maintenance Programme 2023/24 [Works carried over from 2022/23] 
FOOTWAY LOCATION Estimated Cost Cost to Date variance +/- Comment
Riverbank Place
Kilmarnock No 3 to No 9 £2,880.00   
Burn Road Darvel A71 to West Donnington Street £4,032.00   
Mauchline Road
Auchinleck Merlin Park to Merlin Garage £18,900.00   
Kings Drive
Holmhead
Cumnock
Full Length 1 Side £18,900.00 
Broomfield Avenue
Holmhead
Cumnock
Full Length 1 Side £10,080.00 
Netherhill Crescent
Patna Full Length 1 Side £18,900.00   
A713
Dalmellington
Road Patna
Dalharco Avenue to Doonbank Crescent £30,240.00 
Taiglum Drongan Full Length 1 Side £5,670.00   
Cessnock Road
Hurlford Full Length 1 Side £17,640.00   
Homes Road
Galston Full Length 1 Side £12,600.00   
Rysland drive
Fenwick Full Length 1 Side £20,790.00   
Bowes Rigg
Stewarton Full Length 1 Side £25,200.00   
James Young
Avenue
Netherthird
Full Length Both Sides £16,380.00 
Western Road
Kilmarnock  Lewis Drive Side £9,450.00   
Knowhead Road
Kilmarnock Full Length 1 Side £28,350.00   
Castle terrace
Kilmarnock Full Length 1 Side £10,368.00

Page 25

Ayrshire Roads Alliance - Environmental Improvement Programme 
Year Project Description of Works Benefit Estimated
Cost 
Future Years Hayhill, by Drongan, Environmental
Improvement
Kerb, upgrade verge
and form parking bay
Improve environment in village
and road safety by formalising
parking area.  £15,000 
Future Years  Craigie Avenue, Kilmarnock Form Lay-by - street
parking bays
Improve environment and road
safety by reducing on street
parking problems.  £15,000 
Future Years Wellpark Crescent Kilmarnock, widen
road.
Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £7,000 
Future Years  Kilmarnock Rd Service Rd Crosshouse,
widen road. 
Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £8,000 
Future Years Hillcrest, Bellsbank, Dalmellington
Parking Bays
Form 6 No Off-Street
parking bays
Improve environment and safety by
reducing on street parking
problems.  £15,000 
Future Years  North Hamilton Place Kilmarnock, parking
bays.  Additional Parking Area
Improve environment and road
safety by reducing on street
parking problems.  £8,000 
Future Years  Gateside Road, Galston, widen road. Re-kerb and widen over-
run grassed area
Improve environment and road
safety by reducing on street
parking problems.  £7,000

Page 26

Ayrshire Roads Alliance - Lighting Capital Programme 2023/24 
Town Location Work Type Estimated Cost Comments Variance +/-
Galston Cairn Terrace, Cairn View and Cairn
Place
5th Core supplies and
concrete columns £50,000 Scheduled
November 23 
Kilmarnock Bridgehousehill Road 5th Core supplies and
deteriorated columns £60,000 Scheduled
September 23 
Muirkirk Garpel Ave, Smallburn Dr Area Ph2 5th Core supplies and
concrete columns £75,000 Scheduled
October 23 
New Cumnock Dalhanna Drive, Mounthope
Terrace, Lochbrowan Crescent
5th Core supplies and
concrete columns £65,000 Scheduled 
July 23 
£250,000 
Ayrshire Roads Alliance - LED Lighting Programme Update 2023/24 [Works carried over from 2022/23] 
Town Lantern
Amount Status
Delivery /
start
install
Install
complete
by
Kilmarnock - North East 1135 Complete Dec-21 90%
Complete
Kilmarnock - Central 1400 On site  Aug-23
East Ayrshire - Decorative 350 75% complete 
tender to be issued for next stage  Aug-23
Logan, Lugar, Cronberry & Muirkirk 390 On site Oct-22 May-23
Stewarton, Kilmaurs, Fenwick, Dunlop & Lugton 1420 On site Oct-22 May-23 
Current Status 
Programme completed conversions to
date
12,696 Replacement programme 90% complete
Overall LED units completed 19,125 LEDs now 90.8% of total EAC inventory

Page 27

Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 [Works carried over from 2022/23] 
During our design works for our LED conversions, we have identified a number of older installations in East Ayrshire where it is not practicable to
simply replace the existing discharge lighting with LED lanterns. Consequently, the following full lighting replacement projects have been
programmed and will be funded from the LED replacement budget.
Town Location Estimated
Cost Scheduled Comments
Galston Orchard Street £35,000 Nov-22 90% Complete
Kilmarnock Samson Ave, Linfern Ave Areas £95,000 27-Feb-23 40% Complete
Stewarton Clerkland Road Area £70,000 27-Feb-23 40% Complete
Kilmarnock Glasgow Road B7038 £45,000 27-Mar-23 90% Complete
Kilmarnock Forest Grove and Woodlands Grove £85,000 03-Mar-23 40% Complete
2022/23 Total £425,000   
Ayrshire Roads Alliance - LED Programme Funded Replacement Works 2023/24 
Town Location Estimated
Cost Scheduled Comments
Kilmarnock Woodstock Street & Area £60,000 12-Jun-23  
Kilmarnock Gibson St and Carmel Ave Areas £110,000 2-Jun-23 
Kilmarnock Wilson Ave, Greenan Rd, Dunure Rd Area £120,000 15-May-23 
Stewarton Annick Crescent & Area £75,000 3-Apr-23 10% Complete 
Fenwick Maunsheugh Road £50,000 May-23  
Fenwick Skernieland Road £30,000 Jul-23  
Kilmarnock Bonnyton Road £20,000 Jul-23 
2023/24 Total £465,000

Page 28

Ayrshire Roads Alliance - Bridge and Culvert Strengthening Programme 2023/24 [Ongoing and identified works] 
Bridge Strengthening and Replacement
Structure
Reference Structure Name Proposed Works
Project
cost
estimate 
Spend
to-date   Comment  Status 
U22/10  Burnfoot Bridge, near
Darvel
Replacement – Near tender ready. Land
acquisition outstanding  £440,000  £5,250
Ground
Investigation
completed. Land
acquisition
ongoing with
Estates/Legal .
SEPA CAR
Licence received
Design &
tender docs 
C127/10  Low Ashyard Bridge
Infilling of bridge by Historical Railways
Estate. EAC part contribution  £5,000  £0
HRE has funded
the installation of
temporary
supports and
working up
design to sleeve
the structure
Programmed 
Funding
discussions
ongoing with
HRE 
U26/10
West Clerkland Bridge,
near Stewarton
Replacement – currently closed to traffic;
near tender ready.  CPO required to obtain
land acquisition. Construction likely to be
in future year programme 
£12,000  £389
Land acquisition
stalled due to
landowner. CPO
reqd.
Bridge completely
closed to veh &
peds. With Legal
working on CPO. 
Tender ready 
B730/10
Littlemill Bridge,
near Rankinston
Replacement - near tender ready; land
acquisition to be concluded; construction
likely to be in future year programme
£6,000  £3,442
Land acquisition
near complete.
Advance
electricity
diversion
complete.
Near Tender
ready. Works in
2023/24 
A71/280/C8
0
Mathews Burn Culvert,
West Donnington St,
Darvel
Replace section of culvert below West
Donnington Street; design  on going and
near tender ready, land acquisition to be
concluded.
£149,000  £0
SEPA Licence
obtained.  Land
acquisition with
Legal to
conclude. 
Design/Tender

Page 29

B713  B713 Road Slip south of
Sorn 
Detailed design and construct sheet piled
wall
£312,000  £2,450
Consultant
working up
detailed design &
tender documents 
Near tender
ready 
B705  B705 Road Slip centre of
Catrine  Detailed design £18,000  £0  No progress 
B705  B705 Road Slip north of
Catrine  Detailed design £18,000  £0  No progress 
Various  Investigative works  Topographical surveys, paint surveys, etc £6,000  £1,350  Package of topos
awarded 
A735/130/C
58  Gills Burn Culvert, Dunlop
Part deck replacement and Retaining
Wall Repairs - design in  2022/23 and
construction in future year programme  £10,000 £0 
On hold (as
part of F&PM
wider ECC
build)
U751/10 Crossflats Bridge Replacement – design by consultant  £60,000 £0  No progress
Consultant
to be
appointed
for design
via SXL
U760/00/C93 Glenhead Culvert Replacement £42,000 £0 Design ongoing 
U740/10 Barbieston Bridge Boundary Bridge Replacement – design by
consultant £24,000 £0 No progress 
U44/10 Bruntland Bridge Strengthen and refurbish £24,000 £0 No progress 
Upgrade Works identified from inspections 
B705/10/C9
1
Cowan Place Culvert,
Catrine Masonry repairs/scour repairs £24,000 £0
Site visit
undertaken and
preliminary
design
Preliminary
design 
B705/20  Shellies Bridge, Catrine
Scour repairs; masonry training wall repairs
and culvert extension – Consultant
appointed to undertake design & works
ongoing; land acquisition
Construction in future year programme
£6,000 £1,538
Consultant
design ongoing.
Land acquisition
to be determined 
Design

Page 30

A71/300  Priestland Bridge
Retaining Wall strengthening – finalise
design, conclude land
acquisition/servitude and
construct.Tender evaluation.
£120,000 £48,301 Works ongoing  Site
U764/10 Glenmuir Bridge Scour repairs £42,000 £0 No progress 
A70/130/W3
1 Thornwood Wall, Lugar
Replacement - Consultant appointed to
undertake design which is ongoing; land 
acquisition required. Construction in future
year programme
£6,000 £1,538
Consultant design
ongoing and site
investigation
complete. Sheet
pile option
developed but
conflict with O/H
power cables
being investigated
Design 
Queens Crescent,
Newmilns 
Replace riverbank retaining wall.tender
being evaluated. 
£325,000 £10,000
Tender delayed
until Spring 2023
due to fish
spawning issues
with river working.
Advance tree,
vegetation
clearance
undertaken.
Tender ready 
B741 Coal Glen
Embankment Slip, near
Dalmellington
Ground investigation complete. Consultant
finalizing design & tender package. Land
acquisition required. Construction
potentially in 2022/23.
£384,000  £14,000
(Tenders returned
and being
evaluated) 
Tender Stage
A713/60/C6
1 Polnessan Upper Bridge
Extension of culvert. Design and land
acquisition in 2022/23. Construction in
future year programme.
£24,000 £0 No progress 
C90/35/CG0
2 Cattle Grid
Replacement of cattle grid and bypass
improvement. Extent of works increased.
£30k Wind Farm contribution
£136,725  Site works
ongoing
On Site
A736/60/C8
4 Lochridge Culvert  Masonry and drainage repairs £60,000 £0
Near ready for
tender issue
Design 
F/LUGA/10
Logan to Park Terrace
Footbridge, Lugar
Replacement of footbridge deck.on
refurbished abutments. Consultant design
ongoing  £150,000  £1,538
Deck replacement
and scour
protection – design
ongoing 
Design

Page 31

B705/20/C6
8
Smithy’s Culvert, near
Catrine
Replace with box units - future year
programme  £0 No progress 
B741/40/C7
9
Polmathburn Bridge, near
Dalmellington
Replace damaged deck slabs - future year
programme  £0 No progress 
A71  Dundonald Rd Bridge
Refurbish –  replace expansion joints,
waterproofing, drainage, surfacing – design.
Construction in future year programme.
£36,000  £14,074
Consultant
appointed and
design
ongoing
Design 
A71  Riccarton Viaduct
Refurbish – paint, replace expansion joints,
waterproofing, drainage, surfacing – design.
Construction in future year programme.
£36,000  £11,414
Consultant
appointed
and design
ongoing
Design 
A71  River Irvine Bridge
Refurbish – paint, replace expansion joints,
waterproofing, drainage, surfacing - design.
Construction in future year programme.
£336,000  £11,414
Consultant
appointed
and design
ongoing
Design 
B741/50 Nith Lodge Bridge
Replacement. Appoint consultant for
design and construction in future
year  £54,000  £0
Consultant to be
appointed for
design via SXL
Held pending
possible WF
proposals
Programmed 
Annick Water, Stewarton
Replacement of collapsing gabion
training wall. Detailed design by
consultant and construction
£378,000  £8,713
Draft tender
documents
being
reviewed by
ARA 
Design
U/LOGA/10 Old Lugar Bridge Strengthening, masonry repairs and
scour protection £300,000 £5,797 Early stages
of design
Design 
C85/10 Fenwick Bridge Masonry refurbishment £24,000 £0
Preliminary
design. Trial
pit
investigation
ongoing 
Design
B7036/10 Lugar Bridge, Ochiltree Major refurbishment – design in FY
2022/23, construction in future year £24,000 £0 No progress 
U/KMCK/20 West Shaw Street Bridge Strengthen and Refurbishment  £0 No progress

Page 32

C135/20 Avon Bridge Masonry and scour repairs £36,000 £0 No progress 
U736/10/C6
5
Sykeside Bridge Scour repair £24,000 £0 No progress 
U729/00/C6
4
Hayhiolm Bridge Masonry and Scour repairs £36,000 £0 No progress 
U729/00/C7
1 
Barry Burn Culvert Masonry and Scour repairs £36,000 £0 No progress 
U730/00/C3
7
Culvert Masonry and Scour repairs £36,000 £0 No progress 
C36/10 Nith Bridge Masonry parapet rebuild and repairs
to commence end of August 2022 £60,000 £25,242 Site works
ongoing
Site 
A70/100 Gatehouse Bridge Parapet heighten, scour repairs &
masonry repairs £24,000 £0 No progress 
A70/110/C4
6
Rose Burn Bridge Masonry and scour repairs £24,000 £0 No progress 
Broomknowe Retaining
Wall
Design in 2022/23, construction in
future years £24,000 £0 No progress 
W/MUIR/20 Muirkirk Shops
Retaining Wall Design in 2022/23, construction in future
years
£24,000 £0 Topo survey.
Trial pit
investigation
works
awarded 
Parapet Upgrades 
A70/70  Burnock Bridge, Ochiltree  Parapet and other masonry repairs  £216,000
£5,545
£196,496
Contract
awarded,
start date
TBC.
Further
Ecology
surveys
being
undertaken
Site 
A713/90  Dunaskin Bridge,
Waterside  Widening to create footway and replace
both masonry parapets - design ongoing. 
£70,000 £1,480 Out to Tender
Tender Stage

Page 33

B743/80 Cleuch Bridge, Sorn Upgrade of parapets and install footway  £90,000 £0 
Design ongoing.
Further ecology
surveys being
undertaken
Programmed
C134/10 Ranoldcoup Bridge, Darvel  Masonry repairs and heighten parapets  £264,000  £0  No progress 
B769/40 Corsehill Mill Bridge Parapet replacement – design in FY 2021/22  £12,000  £0 No progress 
B7082/10 Townhead Bridge Parapet replacement £150,000 £0
Trial pit
investigation
works
awarded 
B743/135/C
50 Beacon Hill Culvert Headwall Repairs  £0 No progress 
W/NCUMN/1
0 Burnside Retaining Wall Replacement £36,000 £0 Preliminary
Design
Design 
Rail Incursion 
C23/10 Rigg Road Rail
Bridge, Cumnock Safety fencing - future year programme  £0 No progress 
Non ARA  Council Footbridges 
Various sites Design, investigation £120,000 £2,196 Minor repairs
ongoing 
F/HURL/10 Portland Brae Footbridge Load Assessment, paint and replace
concrete planks £230,000 £22,687
Consultant
completed
structural
assessment
and
strengthenin
g options.
Detailed
design cost
fee being
reviewed by
ARA.
Design
F/CATR/20 Institute Ave Footbridge,
Catrine Refurbishment £72,000 £0 No progress 
A71/190 River Irvine Emergency repairs to expansion joint.
Scheme transferred from Revenue to Capital  £28,794

Page 34

Principal Inspections 
Various Principal Inspections of bridge stock by
consultant and in-house staff £216,000 £0 No progress 
Capital staff fees
Staff fee already
included in above
estimates
£260,000         
Ayrshire Roads Alliance - Traffic, Transportation and Road Safety Programmes 2023/24
(i) Road Safety Programme 
Town/Route Location Proposed Scheme
Kilmarnock A71 / Campbell Street Off Slip Signalisation
Hurlford A71/B7073 roundabout AIP junction assessment
Dunlop Lugton Road Pedestrian crossing
Dunlop Main Street HGV route assessment
Lugton A735/A736 Anti-skid surfacing and traffic sign review
B741 Dalmellington to New Cumnock Road safety route review
B7034 Hollybush Speed limit review
A713 Waterside Speed limit review
B730 Drongan Speed limit review
Auchinleck Various General review of parking restrictions
Mauchline Various General review of parking restrictions
Patna Doon Bridge Signalisation and associated safety improvement works

Page 35

(ii) Safer Neighborhoods 
Town Location Proposed Scheme
Galston Cessnock Road at Bowling Club Pedestrian build-out
Stewarton Various roads 20mph speed limit orders amendments
Kilmarnock Whatriggs Road Parking review
Cumnock Glaisnock Street Possible speed reduction measures
Various Various locations Vehicle activated signs upgrade
Crookedholm Grougar Road Pedestrian crossing and road widening
Sinclairston B7046 Traffic calming 
(iii) Rural Route Action Plans 
Route Proposed Scheme
B778 B778 Fenwick to Stewarton Route Study 
(iv) Cycling, Walking and Safer Routes (CWSR) 
Town Location Proposed Scheme
Kilmarnock Grassyards Road Cycle route enhancement scheme
Kilmarnock Annahill Park to B7073 Cycle route
Fenwick Kirkton Rd/Main St – Fenwick PS Pedestrian safety improvements
Mauchline Loudoun Street Pedestrian crossing
Kilmaurs Main Street Traffic modelling for improved pedestrian facilities
Kilmaurs Townhead Pedestrian crossing
Crosshouse Crosshouse-Dundonald Cycle route feasibility study
Newmilns Loudoun Road Pedestrian Crossing Investigation

Page 36

Darvel East Main St/Murdoch Road Junction sightline improvement
Kilmarnock Green Infinity Loop Design process for cycle path network 
(v) Strathclyde Partnership for Transport (SPT) 
Location Project
Kilmarnock Phase 3 refurbishment of Kilmarnock bus station to upgrade concourse and stance areas.
Kilmarnock Glasgow Road bus park & ride 
(vi) SUSTRANS 
Location Project
Hurlford Hurlford Street Design Project 
Appendix 3 
Ayrshire Roads Alliance - EV Public Chargers 
EAST AYRSHIRE 
CPS ID Type Make Location
51171 7kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
50821 22kw eVolt Multi Storey Car Park, Kilmarnock, KA1 1LU
51324 22kw eVolt Titchfield Street Car Park, Kilmarnock, KA1 1PH
52474 22kw eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52470 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52471 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52472 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU
52473 Rapid eVolt Ayrshire Athletics Arena EV Hub, Queens Drive, Kilmarnock, KA1 1HU

Page 37

52020 Rapid eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52021 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52022 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
52023 7kw eVolt East George Street Car Park, Kilmarnock, KA1 1GB
51233 22kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52035 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52036 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52037 7kw eVolt EAC Headquarters, London Road, Kilmarnock, KA3 7BU
52026 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52027 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52028 7kw eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
52025 Rapid eVolt Waterside Street Car Park, Kilmarnock, KA1 1RJ
50819 22kw eVolt Beechwood Avenue Car Park, Beechwood Avenue, Auchinleck, KA18 2AW
51170 Rapid eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
50507 22kw eVolt Avenue Square Car Park, Stewarton, KA3 5AP
60301 Rapid eVolt Castle Car Park, New Cumnock, KA18 4AR
52024 Rapid eVolt Ranouldcoup Road, Darvel, KA17 0JU
52042 Rapid eVolt Loudoun Street Car Park, Mauchline, KA5 5BE
52018 Rapid eVolt Tanyard Car Park, Cumnock, KA18 1BG
52034 22kw eVolt Glaisnock Street Car Park, Cumnock, KA18 1JS
52017 Rapid eVolt Mill Bank Car Park, Mill Bank, Cumnock, KA18 1AB
52039 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52040 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
52041 7kw eVolt Townhead Street Car Park, Cumnock, KA18 1LY
51792 22kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52966 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52967 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52968 7kw eVolt Area Office, 33 Main Street, Dalmellington, KA6 7QL
52972 7kw eVolt Saint Germain Street Car Park, Catrine, KA5 6RQ
52969 22kw eVolt Dean Castle Country Park, Dean Road, Kilmarnock, KA3 1XB
52970 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52971 7kw eVolt Fenwick Road Car Park, Fenwick Road, Kilmaurs, KA3 2RQ
52953 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ

Page 38

52954 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52955 7kw eVolt Northwest Area Centre, Western Road, Kilmarnock, KA3 1NQ
52956 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52957 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52958 7kw eVolt Rothesay House, Greenholm Road, Cumnock, KA18 1LH
52965 22kw eVolt Morton Place Car Park, Morton Place, Kilmarnock, KA1 2AY
52962 Rapid eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
52963 22kw eVolt Queens Street Car Park, Queen Street, Kilmarnock, KA1 1LU
53080 7kw eVolt Netherthird Community Centre, 65 Ryderston Drive, Cumnock, KA18 3AR
53778 Rapid eVolt Main Street Car Park, Muirkirk
53775 22kw eVolt Rose Reilly Sports Centre, Stewarton
53776 7kw eVolt Standalane Car Park, Stewarton
60786 7kW eVolt Academy Street, Hurlford
60732 22kW eVolt Drongan Centre car park, Mill of Shield Road
51210 22kW eVolt Carnshalloch Avenue car park, Patna
60924 7kW eVolt Queen Street car park, Kilmarnock
60250 22kW eVolt New Cumnock Outdoor Swimming Pool car park
60955 22kW eVolt Gatehead Road car park, Crosshouse
61021 7kW eVolt East Ayrshire Community Hospital, Cumnock
61022 7kW eVolt East Ayrshire Community Hospital, Cumnock
61983 7kW eVolt Morton Place car park, Kilmarnock
61984 7kW eVolt Morton Place car park, Kilmarnock
61985 7kW eVolt Morton Place car park, Kilmarnock
SOUTH AYRSHIRE
CPS ID Type Make Location
51930 7kw eVolt Barns Crescent Car Park, Ayr, KA7 2BW
51793 7kw eVolt Mill Brae Car Park, Ayr, KA7 2HU
51535 Rapid eVolt Burns Statue Square, Ayr, KA7 UT
52029 22kw eVolt Belleisle Park, Ayr, KA7 4BN
52030 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52031 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT
52032 7kw eVolt Castlehill Road Car Park, Ayr, KA7 2HT

Page 39

51325 22kw eVolt Cromwell Road Car Park, Ayr, KA7 1DY
50818 22kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
50817 22kw eVolt Jubilee Road, Troon Swimming Pool, Troon, KA10 6XQ
50290 22kw eVolt South Beach Road Car Park, Troon, KA10 6EF
52033 22kw eVolt Girvan Harbour, Girvan, KA26 9AG
50816 Rapid eVolt Girvan Harbour, Girvan, KA26 9AG
52038 22kw eVolt Harbour Road Car Park, Maidens, KA26 9NR
52019 Rapid eVolt The Vennel, Ballantrae, KA26 0NH
52975 Rapid eVolt Mill Brae Car Park, Ayr, KA7 2HU
52974 7kw eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52973 Rapid eVolt New Road Car Park, New Road, Ayr, KA8 8HE
52959 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52960 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52961 7kw eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
53555 Rapid eVolt Bellevue Car Park, Bellevue Road, Prestwick, KA9 1NW
52976 Rapid eVolt Coylton Activity Centre, Hole Road, Coylton, KA6 6JL
53774 Rapid eVolt Academy Street, Troon
53773 Rapid eVolt Lodge Road Car Park, Turnberry
53777 22kw eVolt Burnside Road, Monkton
60793 22kw eVolt Dailly Activity Centre, Victory Crescent, Dailly
60081 22kw eVolt Inches Close car park, Maybole
61982 22kw eVolt Tarbolton Community Campus car park, Tarbolton
61986 22kw eVolt Dundonald Primary School car park, Dundonald
60086 22kw eVolt Mossblown Activity Centre car park, Mossblown
60082 22kw eVolt Kirkoswald Main Street car park, Kirkoswald
61979 7kW eVolt Chalmers Arcade car park, Girvan
61980 7kW eVolt Chalmers Arcade car park, Girvan
61981 7kW eVolt Chalmers Arcade car park, Girvan
Awaiting CPS number 22kW eVolt Barrhill Community car park, Main Street, Barrhill