AYRSHIRE SHARED SERVICE JOINT COMMITTEE
10 MARCH 2023
Report by the Head of Roads - Ayrshire Roads Alliance     
_________________________________________________________________
AYRSHIRE ROADS ALLIANCE
IMPROVEMENT ACTION PLAN
________________________________________________________________
PURPOSE OF REPORT
1. The purpose of this Report is to advise the Joint Committee on the management
of the Improvement Action Plan with the Ayrshire Roads Alliance.
RECOMMENDATIONS
2. It is recommended that the Joint Committee:
i. Notes the Improvement Action Plan presented in this report;
ii. Continues to receive updates on progress; and
iii. Otherwise, notes the content of the report.
BACKGROUND
3. The purpose of the report is to provide regular updates on the Improvement
Action Plan.  This would ensure that the actions are monitored and scrutinised at
a minimum of a quarterly basis and is contained in Appendix 1.
MAIN REPORT/MAIN ISSUES
4. This Improvement Action Plan is collated by the Business Support Manager
and used to:
• monitor the progress in meeting the Ayrshire Roads Alliance’s
objectives;
• help managers to continually review the actions and progress to date;
and
• identify any risk / problem areas that need addressed regarding the
Improvement Action Plan.
5. The Scottish Government has published the final STPR2 report, details were
presented to both Cabinets. The final delivery programme of projects for the
next 20 years is due for publication Spring 2023.
6. ARA has received feedback from UK Government on its Levelling up bids
associated with Bellfield Interchange and Active Travel Prestwick to Ayr.

Page 2

7. Both bids received positive feedback with the potential to re-submit under
cycle 3.
8. Ayrshire Roads Alliance has taken over delivery of the AGD Roads Project
Prestwick and now meet colleagues in SAC on a regular reporting cycle to
update progress.
9. The Road Asset Proposals for East Ayrshire was presented to Cabinet on 8
March 2023 and the Road Improvement Plan for South Ayrshire will be
presented to South Ayrshire Cabinet on 25 April 2023.
POLICY/COMMUNITY PLAN IMPLICATIONS
10. A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire.
11. The matters referred to in this report contribute to South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’.
LEGAL IMPLICATIONS
12. The Risk Register is a management tool and this will not replace the existing
statutory returns for risk and performance related information.
HUMAN RESOURCES IMPLICATIONS
13. The Risk Register has no direct impact on human resources.
EQUALITY IMPACT IMPLICATIONS
14. The Risk Register complements the Equality Impact Assessment by ensuring
that any issues arising are adequately prioritised, managed and either eliminated
or mitigated.
FINANCIAL IMPLICATIONS
15. The Risk Register facilitates the existing scrutiny arrangements to manage,
prioritise, and review the budget provided by East Ayrshire Council and South
Ayrshire Council to the Ayrshire Roads Alliance.
RISK IMPLICATIONS

Page 3

16. The Risk Register assists in the prioritisation of risks that need to be mitigated
by the Ayrshire Roads Alliance in order to reduce the overall risk to either Council
and to comply with the Community Plan/Council Plan in both partner bodies.
TRANSFORMATION STRATEGY
14. This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”.
• “Maximum value for our communities”, by ensuring the various elements
of the Ayrshire Roads Alliance improves transport provision across both
networks.
Kevin Braidwood
Head of Roads – Ayrshire Roads Alliance
24 February 2023
BACKGROUND PAPERS 
Ayrshire Roads Alliance Service Plan 2022/23
LIST OF APPENDICES 
1. Ayrshire Roads Alliance Action Plan
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance
Tel No. 01563 503164 
E-mail: kevin.braidwood@ayrshireroadsalliance.org
Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164 
E-mail: kevin.braidwood@ayrshireroadsalliance.org

Page 4

AYRSHIRE ROADS ALLIANCE IMPROVEMENT ACTION PLAN 2022/23 – MARCH UPDATE
Action Success Criteria/
Desired Outcome Responsible Timescale Details
1 Continue to use the integrated
Roads Asset Management
Plan across the Ayrshire
Roads Alliance.
There is one Asset Plan for the
Service delivering a risk based
approach for full service
delivery
Head of Service March 2023. SCOTS RAMP Project.  Development work
has been extended with staff attending various
external workshops to progress this work.  
2 Continue to prepare details for
developing an integrated Local
Transport Strategy.
A Strategy covering both
Council areas, which will
involve consultation with
stakeholders.  Information will
be gathered to inform the
future Local Transport
Strategy.  
Continue to contribute to the
Scottish National Transport
Strategy, Regional Transport
Strategy and Strategic
Transport Projects Review
work.
Head of Service  March 2023 The Regional Transport Strategy, through
SPT, has just commenced on which the
Alliance has Board membership.  The Local
Strategy will be created as an appendix to the
Draft RTS when this is published in June 
2022
3 Action the Flood Risk
Management Plan
Complete schemes and
undertake studies.  Inform the
next national cycle of potential
flood risk management
schemes beyond 2022.
Head of Service Complete Continue with construction of new Cumnock
Phase 2.  Continue design work on the Irvine
Valley Work.  Continue with flood study works
for the River Ayr, River Doon and in Girvan.
Continue to engage with SEPA with the final
document due for publication Autumn 2022
reports brought to committees within East
Ayrshire February 2023 and South Ayrshire
April 2023.
Appendix 1

Page 5

Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
4 Improve the condition of the
road network. 
Improve annual roads survey
results which are part of the
SRMCS work.  Ensure the
Alliance undertakes more
proactive maintenance. 
Head of Service Site works will be
undertaken
throughout
2022/23.
Key dependencies are the Road Improvement
Plans approved by the relevant Committees in
East Ayrshire and South Ayrshire in spring
2022.  Progress is provided to members, and
relevant Committees .Currently reviewing
capital spend as a result of increased costs. 
5 Ensure the road network
remains safe through raising
awareness and improving road
safety through education,
engineering and enforcement. 
Reduce road accidents in line
with government targets. 
Provide appropriate traffic
management schemes and
initiatives.
Strategic Manager
Roads and
Transportation 
March 2023 Scottish Government and SCOTS guidance is
used.  A key dependency is the Road
Improvement Plans which are presented to
Cabinet and Leadership each year. 
6 Improve the condition of the
bridge stock. 
Improve bridge condition index. 
Reduce the number of weight
restricted bridges.  Complete
all general, special and
principal bridge inspections.   
Design &
Environment
Manager
March 2023 Through the Road Asset Management Plan. 
Key dependencies are Road Improvement
programmes approved by Committees in East
Ayrshire and South Ayrshire in spring 2022.   
Deliver the capital and revenue programmes. 
7 Manage and improve the
street lighting asset and install
energy efficient lighting
schemes. 
Maintain high standard of fixing
dark street lights.  Complete
the LED lighting replacement
programme in both East
Ayrshire and South Ayrshire. 
Head of Service October 2023 Through the Road Asset Management Plan,
with additional funding being provided to
commence the LED programme. 
At present performance is 86.2% of streets
lights are now LED in EAC; and 99% in SAC.
On target for completion within timescales. 
8 Maximise and deliver
externally funded sources of
work 
Identify external funding
sources and deliver work on
time and on budget.  Improve
infrastructure; and contribute to
improving the condition of the
network.
Head of Service Works will be
undertaken
throughout the
2022/23.
External sources, including Timber Transport,
SUSTRANS, SPT - Regional Transport
Partnership, CWSS - Cycling Walking and
Safer Streets. Scottish Government Bridge
Fund.SFT

Page 6

Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
9 Implementation of Parking
Strategy
Develop Head of Service Works will be
undertaken
through 2022/23
Amendments to TRO’s, lining, signing and
residential parking permits and implementing
an improved process using digital technology.
10 Prepare Service Plan  Publish  Head of Service  Annual  East Ayrshire Council Community Plan. South
Ayrshire - Local Outcomes Improvement Plan
and Local Place Plans.  Draft Plan to be
submitted to Joint Committee in December
2022. 
11 Continue to review insurance
costs and insurance issues. 
Review current practices to
minimise insurance costs. 
Head of Service Complete Ayrshire Roads Alliance Monthly Insurance
Report. 
There is good dialogue with the Risk &
Insurance to ensure our work improves the
number of repudiated claims.  The number of
claims has greatly reduced due to the
implementation of the new Code of Practice. 
12 Review Depots and
Accommodation 
Continue to review in 2022/23
from initial work was completed
in 2017 as a result of amended
working practices.  
Head of Service March 2023 Joint Committee Reports of November 2016.  
Although initial work has been completed we
continue to strive to make depot and
accommodation cost savings. Further work
will continue on this as a result of COVID and
the return to office space during 2022/23. 
13 Review vehicle and plant costs Continue to review in 2021/22
from initial work that was
completed in 2017. 
Head of Service  March 2023 Joint Committee Reports of June 2016 
The service continues to review fleet
requirements with the most recent
improvement being on the management of
vehicle utilisation, electric vehicles and
Telematics.

Page 7

Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
14 Monitor and exercise Business
Continuity Plans
Improved resilience.  Business Support
Manager
Complete  Existing East Ayrshire and South Ayrshire
Council plans are all revised and up to date. 
15 Continue to use the Roads
Costing System to its full
potential. 
Improve service performance
from both an on-site and
financial perspective. 
Business Support
Manager
May 2023 Revised roads costing system was fully
operational from November 2018. 
The system continues to be used to monitor
performance and work is ongoing to
implement digital timesheets linked to the
Roads Costing System. 
16 Support and contribute to the
Ayrshire Growth Deal 
Transport Summit has taken
place and outcomes are
included in the National
Transport Strategy, Regional
Transport Strategy and the
Strategic Transport Projects
Review.   
Head of Service Complete  The Transport Appraisal being led by
Transport Scotland commenced in January
2019.  We continue to engage with Transport
Scotland to ensure the Ayrshire Growth Deal
transportation work is included in Strategic
Transport Projects Review 2 work. 
17 Regional Transport Strategy Successfully contribute to the
preparation of this work being
led by SPT.  The Alliance has
Board representation. 
Head of Service Complete
Complete
SPT documents and existing Regional
Transport Strategy 
the draft RTS was  published June 2022.ARA
will respond to the consultation by the
deadline of October 2022 
18 Regional Transport Appraisal Ensure the various projects
identified as part of this work
are included in the Strategic
Transport Projects Review.  
Head of Service Complete Transport Scotland documents 
Work is on-going with the completion date for
the STPR2 of October 2022,published 8
December 2022.
19 National Transport Strategy East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure the
Head of Service October 2023 In recognition of the anticipated increase in
Active Travel work, it is proposed that a

Page 8

Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details 
sustainable transport hierarchy
and sustainable investment
hierarchy are delivered.  
member of staff is dedicated directly to this
work. 
20 National Transport Strategy –
review of Governance 
East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure that the
outcome/output meets the
needs of the road
users/communities in both
Council areas.
Head of Service March 2023 National Transport Strategy 
21 Transport (Scotland) Bill -  East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure the work
provides the best outcome for
road users in both Council
areas.
Head of Service Complete Transport (Scotland) Bill received Royal
Assent 15 November 2019.
22 Transport (Scotland) Bill -  East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure a
pragmatic approach is taken in
delivering the pavement
parking ban in both Council
areas.
Head of Service March 2023 Transport (Scotland) Bill and Transport
Scotland Parking Standards working group
still awaiting guidance from Transport
Scotland.
23 Levelling Up Fund East Ayrshire and South
Ayrshire Councils contribute to
this process to ensure that the
outcome/output meets the
needs of the road
users/communities 
Head of Service Complete Levelling Up Fund bids will be submitted June
2022.
Feedback has been received for EAC and
SAC bids with potential for re-submitting 3rd
cycle.

Page 9

East Ayrshire Council Strategic Priorities 2022/23 
Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
1 Progress and complete the
New Cumnock Flood
Protection Project 
Complete the flood prevention
projects at the Leggate and
beside the Afton Water. 
Head of Service March 2023 East Ayrshire Council and Scottish Government
funding.  The Leggat stage of the works was
completed in August 2018 with the Afton Water
phase commenced May 2021 with an 18 month
contract duration.Project currently 2 months
behind programme.
2 Develop Projects approved
from the Flood Risk
Management Plan  
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022. 
Head of Service Ongoing  East Ayrshire Council and Scottish Government
Funding.  Continue with work on studies for the
Irvine Valley, Dalrymple, Catrine and
Dalmellington through the financial year.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth
concerns.  Contribute to
infrastructure projects which are
being developed through the
Regional Transport Appraisal
work being led by Transport
Scotland. 
Head of Service Complete  The all Ayrshire Transport Appraisal being led
by Transport Scotland commenced in January
2019. We will continue to engage with Transport
Scotland to ensure the Ayrshire Growth Deal
transportation work is included in Strategic
Transport Projects Review work.
4 Transformation 
Strategy 2 
Continue to provide a high
quality roads service within
decreasing available budgets. 
Includes service re-design work.
Head of Service Complete East Ayrshire Council reports to various
Committees. 
Work commenced and was completed by March
2022 including a full revision of ARA structure.
5 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network and East Ayrshire
Network
Head of Service Complete  A full review of active travel provision in East
Ayrshire has been undertaken and this will be
presented to the relevant East Ayrshire Council
Committee Summer 2022.

Page 10

Action  Success Criteria/
Desired Outcome  Responsible  Timescale  Details
6 EV Strategy  Develop EV strategy across
East Ayrshire Network
Head of Service March 2023 A full review of EV provision in East Ayrshire has
been undertaken at present and this will be
presented to the relevant East Ayrshire Council
Committee with further work being carried out in
partnership with Scottish Futures Trust to
assess public charging funding models.
7 Levelling Up Fund Completion and Submission of
Bid for improvements to Bellfield
Interchange
Head of Service Complete Design and modelling work to improve Bellfield
to increase capacity and open up development
opportunities. Feedback received from UK Gov
8 Ash Die back Strategy Develop a risk based strategy
for the management of Ash Die
Back.
Head of Service Complete Develop a risk based approach to the
management of Ash Die Back.

Page 11

South Ayrshire Council Strategic Priorities 2022/23 
Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details
1 Implementation of car parking
strategy for South Ayrshire. 
Complete this work with
improved parking provision and
management. 
Head of Service  Complete A full review of car parking provision in South
Ayrshire is being undertaken at present and this
will be presented to the relevant South Ayrshire
Council Committee. 
2 Develop Projects approved
from the Flood Risk
Management Plan  
Progress relevant studies and
inform the developing list of
schemes for cycle two of the
national protection schemes to
be delivered from 2022. 
Head of Service April 2023 Flood study work in the Girvan area is
progressing and a report will be presented to the
relevant South Ayrshire Council Committee.
3 Support and contribute to the
Ayrshire Growth Deal
Stimulate economic growth and
address inclusive growth
concerns.  Contribute to
infrastructure projects which are
being developed through the
Regional Transport Appraisal
work being led by Transport
Scotland. 
Head of Service Complete The all Ayrshire Transport Appraisal being led
by Transport Scotland commenced in January
2019. We will continue to engage with Transport
Scotland to ensure the Ayrshire Growth Deal
transportation work is included in Strategic
Transport Projects Review work.
4 20mph speed restrictions in
villages
Progress with the 20mph speed
restrictions in all villages. 
Maintain engagement with the
local communities. 
Head of Service March 2022 phase
1&2 Complete 
March 2023 
phase 3
Completed phase 1 and 2.
Design work and consultation phase 3 
Responses received from two CC’s with further
design work required. 
5 Anticipated Budget Reductions
in 2022/23
Continue to provide a high
quality roads service within
decreasing available budgets.
Includes service re-design work.
Head of Service March 2023 Reports to various Committees.

Page 12

Action  Success Criteria/
Desired Outcome 
Responsible  Timescale  Details 
6 Active Travel Strategy Develop active strategy for
travel across South Ayrshire
Network
Head of Service Complete A full review of active travel provision in South
Ayrshire has been undertaken and was
presented to Leadership Panel. Strategy to be
published.
7 EV Charging Strategy  Develop further the  EV strategy
for South Ayrshire Network
Head of Service April 2023 A full review of EV provision in South Ayrshire
was being undertaken and approved by
Leadership Panel. This will be reviewed as a
result of work with Scottish Futures Trust to
assess public charging funding models.
8 Levelling Up Fund Submission of Active Travel bid Head of Service  Complete Joint bid with NAC for active travel route Ayr to
Irvine
9 Levelling Up Fund Submission of A70 Improvement
Package.Deferred 
Submission of Active Travel Bid
Prestwick to Ayr
Head of Service 
Head of Service
June 2022 
Complete
Bid submission for A70 improvements.Deferred. 
Bid Submitted Feedback Received from UK
Gov.
10 Motorhome Trials Develop Campervan sites along
the coastline.
Head of Service Complete  Formalisation of two temporary sites at Girvan
and Ayr and additional trials at Ballantrae,
Maidens, Prestwick and Troon.Progress paper
to be brought to cabinet February 2023 with
additional Troon paper March 2023.Progress
update Autumn 2023.
11 Strategic Economic Impact
Assessment A75/A77
There is a growing desire to
understand the importance /
effectiveness of the
improvements outlined along the
A75 and A77.
Head of Service Complete Public consultation / survey covering
communities throughout Ayrshire (North, South
and East) and Dumfries & Galloway is currently
being undertaken. To date there has been
approximately 600 responses, with more
responses expected as the survey is promoted
on social media and the radio. Final report
complete for reporting July 2022.To be signed
off by D&G and SAC.