Democracy Spraffa

8 Risk Register and App 1

North Ayrshire Council · 2 December 2022
Back to Ayrshire Shared Services Committee — 2 December 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
2 December 2022  
Report by the Interim Head of Roads - Ayrshire Roads Alliance     
_________________________________________________________________ 
AYRSHIRE ROADS ALLIANCE
RISK REPORT AND REGISTER    
_________________________________________________________________ 
PURPOSE OF REPORT 
1. The purpose of this Report is to advise the Joint Committee on the management
of risk associated with the Ayrshire Roads Alliance. 
RECOMMENDATIONS 
2. It is recommended that the Joint Committee: 
i. Notes the risk register presented in this report; 
ii. Continues to receive updates on progress; and 
iii.  Otherwise, notes the content of the report.
BACKGROUND 
3. A report detailing the general approach to the Risk Report and Risk Register was
presented to the Joint Committee on 21 August 2014, where it was agreed that
the Risk Report and Risk Register would be a standing item on the agenda.  This
would ensure that the risks are monitored and scrutinised at a minimum of a
quarterly basis.     
MAIN REPORT/MAIN ISSUES 
4. The management of risk aims to enable confident decision taking on risk and
innovation, reduce waste and inefficiency, and lead to fewer unanticipated
problems and crises that could undermine the performance and operation of the
Ayrshire Roads Alliance.
5. The Risk Register is now in a new and improved format which will make it easier
to review the individual risks which are now in a colour coded format. 
6. The resulting revised risk register is contained in Appendix 2.  
There have been no changes to the Risk Register since the last Joint Committee.

Page 2

The revised risk register illustrates the red, amber and green status and also
illustrates whether the risk severity relates to time, indicated by [T] or cost,
indicated by [C]. 
POLICY/COMMUNITY PLAN IMPLICATIONS 
7. A well maintained road network will contribute to achieving the Community Plan
objectives in relation to Economy & Skills and Safer Communities to maintain
good access to our communities within East Ayrshire. 
8. The matters referred to in this report contribute to South Ayrshire Council
strategic objective of ‘Enhanced Environment through Social, Cultural and
Economic Activities’ and within that to the outcome ‘Work with partners to
improve roads and other infrastructure, to encourage house building and
business investment that sustains local communities’. 
LEGAL IMPLICATIONS 
9. The Risk Register is a management tool and this will not replace the existing
statutory returns for risk and performance related information. 
HUMAN RESOURCES IMPLICATIONS 
10. The Risk Register has no direct impact on human resources. 
EQUALITY IMPACT IMPLICATIONS 
11. The Risk Register complements the Equality Impact Assessment by ensuring
that any issues arising are adequately prioritised, managed and either eliminated
or mitigated. 
FINANCIAL IMPLICATIONS 
12. The Risk Register facilitates the existing scrutiny arrangements to manage,
prioritise, and review the budget provided by East Ayrshire Council and South
Ayrshire Council to the Ayrshire Roads Alliance. 
RISK IMPLICATIONS 
13. The Risk Register assists in the prioritisation of risks that need to be mitigated
by the Ayrshire Roads Alliance in order to reduce the overall risk to either Council
and to comply with the Community Plan/Council Plan in both partner bodies.  
TRANSFORMATION STRATEGY 
14. This Report aligns with the following design principle stated in the
“Transformation Strategy 2017-2022”.

Page 3

• “Maximum value for our communities”, by ensuring the various elements
of the Ayrshire Roads Alliance improves transport provision throughout
East Ayrshire. 
Kevin Braidwood
Head of Roads – Ayrshire Roads Alliance
21 November 2022 
BACKGROUND PAPERS 
None 
LIST OF APPENDICES 
1. Risk Register Scoring Matrix
2. Ayrshire Roads Alliance Risk Register 
Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org 
Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads
Alliance 
Tel No. 01563 503164  
E-mail: kevin.braidwood@ayrshireroadsalliance.org

Page 4

Appendix 1: Risk Register Scoring Matrix 
The Risk Matrix for deciding each of the risk factors (Likelihood x Severity) in a 5 by 5
matrix are illustrated in Table 1 below: 
Table 1: Risk Factors in Practical Form 
Following on from Table 1, the following Summary Risk Profile is colour coded to highlight
the risk classification: 
Table 2: Summary Risk Profile 
Assessed
Risk (LxS) Action Required
Low Risk: 
1 to 4 
Acceptable/ can be accepted provided risk is
managed.
Medium Risk: 
5 to 12
Undesirable/ must be avoided if reasonably
practicable.
High Risk: 15
to 25 
Unacceptable risk - must be eliminated or moved to
a lower level. 
Rare (1) Unlikely
(2)
Possible
(3)
Likely
(4)
Almost
Certain
(5)
Catastrophic
(5) 5 10 15 20 25
Very Serious
(4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Insignificant
(1) 1 2 3 4 5
Risk Likelihood
Risk Severity

Page 5

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
NOTE:
The Risk rating will be influenced by considering a combination of event effects
Such as associated cost, event duration, and organisational reputation.   
The table below will provide some assistance with risk rating. 
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
1 
Personnel
Shortage due
to:
Pandemic
Event
Loss of trained and competent
personnel from all sections
within ARA due to pandemic
event. 
Business continuity plans in place
(BUS-12, 13, & 14) to manage all
ARA mission critical activities.   
Number of employees working from
home significantly increased to
minimise medium / long term
disruption of service.   Operational
Personnel - re-assigned to other
duties within the Council.   Relaxing
of UK driving regulations to maximise
decreased LGV driver numbers. 
Additional usage of external
contractors to ensure essential
services / works programme targets
are met.   Covid safe workplaces /
sites established to accommodate
reduced number of staff. Further
mitigation measures developed as
national guidance information
becomes available.   
3 4  12 [T]
All Service
Managers
Head of Roads
– Ayrshire
Roads Alliance
Further control measures to
be developed/implemented
as situation develops.  21/11/22 
2 
Fuel Shortage Loss or restriction due to relief
events.  Relief Event: Any
event that has an effect on the
cost of performing the
Services, or the date of their
completion, including the
occurrence of risks both
foreseen and unforeseen e.g.
industrial action.
Mitigation measures in place to
prioritise front line services as
detailed in the specific Business
Continuity Plans for offices and
depots. 
3 3  9 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continuation of public
support will be dependent on
outcomes, though expect
some mixed reaction. 
21/11/22 
To calculate the risk rating, multiply the 
Likelihood x Severity.    Example….   
Possible (3) X Significant (3) = Medium Risk 
Critical (5) 
Severe (4) 
Significant (3) 
Marginal (2) 
Insignificant  (1)      
SEVERITY INDEX 
LIKELIHOOD
INDEX 
Highly probable (5) 25 20 15 10 5
Probable (4) 20 16 12 8 4
Possible (3) 15 12 9 6 3
Unlikely (2) 10 8 6 4 2
Very Unlikely (1) 5 4 3 2 1 
Incident Severity Cost (£) [C] Time [T] Reputation
Min Max Min Max 
Insignificant (1) £0 £10,000 0 1 day Councillors/CEO
Marginal (2) £10,001 £50,000 1 day 2 weeks Local Media Facebook etc.
Significant (3) £50,001 £500,000 2 weeks 1 month Local Newspaper
Severe (4) £500,001 £1,000,000 1 month 3 months National Newspaper
Catastrophic (5) £1,000,001  >£1,000,001 3 months     > 6 months National News (TV)
KEY
High Risk (16 – 25) Risks are not acceptable under any circumstances. Immediate action required
Medium Risk (8 – 15) Additional controls measures may be required.
Low Risk (1 – 6) Continue to monitor as part of review process or where changes occur.

Page 6

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
3 
Failure to align
with Budget
requirements
Level of investment required in
road repairs and resurfacing
and resulting cost of treatment
higher than anticipated. 
Reduced budget could lead to
the deterioration in the roads
network, an increase in
accidents, and insurance
costs.
Loss of parking income as a
result of changing behaviour /
work patterns due to Covid.
Uniform claims handling system
aligned with the Roads Inspection
and Maintenance policy.    
Appropriate financial and
performance monitoring
arrangements in place to mitigate the
risk.  Regular meetings with and
within partners Councils to advice on
further resource and funding
requirements. 
2 4  8 [C]
Business
Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
Adequate control measures
are in place, specifically,
monthly meetings held with
budget holders to review
revenue budget and take
appropriate corrective
actions to bring budgets
within tolerance limits. 
Monthly meeting with service
managers to review capital
budgets and programmes. 
21/11/22 
4
Adverse
Weather
Lack of trained and competent
personnel including operatives
and drivers to provide full
complement required to fulfil
all gritting routes due to lack of
volunteers for existing staff, flu
pandemic, mass resignation,
strike action and breach of
Working Time Directive and
Driver Hours Legislation. 
Procedures in place to manage a
short / medium disruption of Driver /
Operative Personnel including
banking workers and overtime
working as required.  Over the long
term there would be recruitment /
procurement of the necessary
experience to fill the gaps. 
2 4  8 [C]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
Rolling programme
established to ensure
ongoing Health and Safety
training.  Appropriate and
applicable checks are
conducted on all new drivers
to ensure that all reasonable
precautions are taken to
safeguard the ‘O’ licence,
insurance payments and
reputation.  The service has
extended the use of external
companies to provide the
winter service to increase
resilience 
21/11/22 
5 
Loss of Street
Lighting &
Traffic Signals
Extended loss of Public
Electricity supply creating
issues with Street Lighting and
Traffic Signals
Some temporary traffic signals will be
provided at key locations determined
by the Traffic Management Section
should these issues arise. 
Temporary traffic signals deployed by
RMU.  Contingency measures
detailed in Business Continuity
Plans. 
3 3  9 [T]  Traffic & Road
Safety Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider that the overall
risk is low due to the
mitigation measures that are 
in place 
21/11/22 
6
Transfer of
Shared
Services –
Ayrshire
Roads Alliance
Any failure in Service provision
would adversely affect the
resilience of the Roads
services.
Extensive negotiations have taken
place to ensure that the proposed
joint service meets stakeholders
needs 
2 2  4 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The new service is over five
years old and it is considered
that the initial transfer of the
shared service has been
completed.  Nevertheless
there will always remain
issues on transfer issues
which may still arise. 
21/11/22 
7
Council’s
Waste
Transfer
Licence
Loss off / restrictions on waste
transfer licence for all depots
Robust management systems and
procedures in place to comply with
Environmental legislation, permit
conditions and health and safety 
2 3  6 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider the overall risk
is low, due to the current
waste management systems
in operation. 
21/11/22 
8
Failure to
provide an
adequate
Failure to provide an adequate
Risk based approach and 
Inspection System in
accordance with the approved,
There are procedures in place to
manage this process:  2  4  8 [T]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Following implementation of
the  Inspection Manual: Road
Safety Inspections and
defect categorisations from 
21/11/22

Page 7

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
Roads
Inspection
System
Inspection Manual: Road
Safety Inspections and defect
categorisations.in accordance
with the Well-Managed
Highway Infrastructure:
A Code of Practice.
1. Short term by prioritising and
reducing other works activities
and realigning budgets;
2. Medium / long term there would
be a request for additional
budgets;
3. Operatives can be assigned from
other duties and overtime
working approved.
1st April 2019 in accordance
with the Well-Managed
Highway Infrastructure:
A Code of Practice the
Ayrshire Roads Alliance 
a) Inspects the entire road
network within East
Ayrshire and South
Ayrshire, with
performance in relation
to the percentage of
safety inspections carried
out within the timescale
being reported to the
Joint Committee under
the Performance
Scorecard standing item
on the agenda. 
b) Categorise defects in
accordance with a risk
based approach ranking
defects one to four as
detailed in the Inspection
Manual: Road Safety
Inspections and defect
categorisations 
c) Issue repair lines for
defects on carriageways
and footways with target
response times
determined by the
category of defect, as
identified in the
Inspection Manual: Road
Safety Inspections and
defect categorisations 
d) Complete the vast
majority of Category 1
defects within the target
response time of two
hours. 
9
Personnel
Shortage
Loss of trained and competent
professional staff, through
retirement.
Procedures are in place to manage
short term issues by prioritising and
reducing other works activities and
realigning budgets. 
2 3  6 [T]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
The staff numbers are
reviewed whenever there are
significant changes in staffing
level.  The Ayrshire Roads
Alliance has Modern
Apprentices who are
providing a strong foundation
for future staffing levels. 
21/11/22 
10 
Personnel
Shortage due
to:
Loss of trained and competent
personnel including operatives
and drivers due to mass
resignation, strike action and
Procedures are in place to manage a
short / medium disruption of
Technical / Supervisory / operational
Personnel including re-assignment of 
1 4  4 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
We consider overall risk is
low due to a combination of
recruitment and selection to
fill existing vacancies.  In

Page 8

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
 Strike
Action
 Driver
hour
restrictions
breach of Driver Hours
Legislation 
duties and controlled overtime
working as required.  Over long term
there would be recruitment /
procurement of the necessary
experience to fill the gaps.
addition there is increased
resilience form the external
service providers for winter  21/11/22 
11 
Adverse
Weather
Reduction and /or loss of salt
stock materials for Winter
Service operations.
There is adequate salt stock
resilience and conservation control
measures.  Transport Scotland has
strategic salt stock piles. 
1 4  4 [T]
Strategic
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Service has a framework
salt supplier with a 14 day
call down delivery.  There is
a joint agreement with other
Councils to share available
salt stocks.  The existing
weather service provides
long term forecast indicating
extreme and prolonged
weather conditions. 
21/11/22 
12
Business
Continuity /
Emergency
Planning
Incident affecting one or more
of the Ayrshire Roads Alliance
service functions (including
ICT Failure).
Business continuity plans developed
for: Roads Maintenance (including
the Winter Gritting Programme);
Lighting Maintenance Unit; Network;
Design and Traffic and Road Safety
facilities within East Ayrshire and
South Ayrshire. 
2 4  8 [T]
Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
The overall risk is high due to
the unknown nature of such
an incident and because of
the potential reputational
damage and adverse effect
on the service delivery,
including discharge of
statutory responsibilities. 
21/11/22 
13
Benefits
Realisation
Ayrshire Roads Alliance does
not deliver the expected
benefits outlined in the
Detailed Business Case of
June 2013.
Benefit Realisation Plan to track the
delivery of each benefit and take
corrective action where appropriate it
has been developed. 
2 3  6 [C] 
Service Managers Head of Roads
– Ayrshire
Roads Alliance
The overall risk is medium
due to the various reviews
outlined in the Benefits
Realisation Strategy and
Plan now progressing
towards fruition.  Internal
management reports to be
prepared reflecting on
progress against Benefits
Realisation Strategy.  As at 1
April 2018 had realised
budget savings of £2.031m
against a target of £1.510m 
21/11/22 
14
Performance Performance Metrics are
missed.
A standardised operational process
and procedures has been developed
to ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Performance metrics are
reviewed and developed with
the Pentana System being
used to review performance. 
Performance is reviewed at
every Management meeting. 
21/11/22 
15
Procurement Insufficient due diligence
carried out by the Ayrshire
Roads Alliance in the
procurement of goods and
services.
Standardised processes and
procedures have been developed to
ensure efficient and effective
processes and verification measures
are in place. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
16
Programme
Management
Programme scope, schedule,
objectives, cost and
deliverables are not clearly
defined or understood.
Clear definition of scope, schedule,
objectives, cost, and deliverables
through Service Improvement Plan,
Benefits Realisation Strategy & Plan,
and Customer Service Strategy. 
1 4  4 [C]
Service Managers Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22

Page 9

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
17
Programme
Management
Estimating and / or scheduling
errors.
A Programme Plan has been
developed which illustrates key
activities, team, timing, milestones,
and delivery of products. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
18
Programme
Management
Unplanned work that must be
accommodated.
Incorporate unplanned work within
Programme Plan and minimise
impact on delivery of products
through parallel processes when
feasible. 
1 4  4 [C]     Business Support
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
19
Programme
Management
Lack of co-ordination /
communication
Programme co-ordination and
communication conducted in
accordance with Programme
governance structure and in
accordance with PRINCE 2
principles. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
20
Programme
Management
Underestimated support
resources or overly optimistic
delivery schedule.
Support resources and delivery
schedule developed from robust
Programme Plan and previous
experience of similar Programmes. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Introduction of the
appropriate Project
Management software to
deliver a unified programme
across the Ayrshire Roads
Alliance whilst utilising plant /
resources efficiently. 
21/11/22 
21
Programme
Management
Unresolved Programme
conflicts not escalated in a
timely manner.
Programme conflicts recorded in
Issues Log and progressed in
accordance with reporting
arrangements for project team. 
2 4  8 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
22
Programme
Management
Unanticipated escalation in
Programme costs as a result
of uncontrolled changes or
continuous inflation of a
project’s scope beyond initial
remit.
Escalation of Programme costs
addressed through appropriate and
applicable corrective actions and
control measures. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
23
Programme
Management
Unanticipated delays in
Programme timescale as a
result of uncontrolled changes
or continuous inflation of a
project’s scope beyond initial
remit.
Delay of Programme timescale
addressed through appropriate and
applicable corrective actions and
control measures. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22

Page 10

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
24
Programme
Management
Delay in earlier Programme
phases jeopardises ability to
meet programmed delivery
commitment.
Incorporate delays within updated
Programme Plan and minimise
impact on delivery of products
through parallel processes when
feasible. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
25
Programme
Management
Communication Strategy to
engage public awareness not
planned on a joint Ayrshire
basis
Ensure that a robust Communication
Strategy and response network is
developed during planning stages of
Programme which incorporates
sufficient key review stages to ensure
effective communication of key
messages regarding deliverables and
progress. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed risk, hence
reducing.  21/11/22 
26
Programme
Management
Unforeseen agreements
required to proceed with or
conclude Programme.
Engage all appropriate and
applicable requirements to ensure
that amicable arrangements are put
in place. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
27
Programme
Management
Priorities change on existing
service delivery.
Ensure that changes on existing
service delivery are communicated in
accordance with the existing Service
Level Agreement, namely that all
parties agree and will abide by the
philosophy of operating as a whole
under the principle of what is best for
the Council Tax payer, not
necessarily the individual authority. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
28
Programme
Management
Inconsistent cost, time, scope
and quality objectives resulting
in time delays and further
costs.
Ensure that cost, time, and scope
estimates along with quality
objectives are evidence based on
experience from previous
comparable Programmes. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk. 
21/11/22 
29
Programme
Management
Affordability of future service
payments.
Ensure that East Ayrshire Council
and South Ayrshire Council are fully
aware of the budgetary implications
required to meet the on-going cost of
service provision, as detailed in the
DBC, and have fully committed
sufficient financial resources
following Business Case sign-off. 
2 4  8 [C]
Head of Roads –
Ayrshire Roads
Alliance
East Ayrshire
Council and
South Ayrshire
Council
Continue to present revenue
financial monitoring report to
Joint Committee.  Four
weekly meetings are held to
discuss revenue and capital
position of the Ayrshire
Roads Alliance. 
21/11/22 
30
Programme
Management
Councils withdraw or cannot
provide sufficient support, or
agreed level of input is not
provided resulting in
Programme delays
Early identification of problems, and
dialogue with Council.  1  4  4 [T]
Head of Roads –
Ayrshire Roads
Alliance
East Ayrshire
Council and
South Ayrshire
Council
Managed Risk. 
21/11/22 
31
Council’s
Operators
Licence (‘O’
Licence)
Loss off / restrictions on
Council’s ‘O’ Licence.
There are the correct management
controls in place, and these are
robust and appropriate.  Paperwork  2  4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Continue to work with fleet
service in East Ayrshire
Council.  21/11/22

Page 11

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
issued to Road Traffic Commissioner
for transfer of ‘O’ Licence. 
32
Health &
Safety / Risk &
Insurance
Insufficient investment,
resources and on-going
maintenance to resolve issues
identified in Health & Safety
surveys of depots are on-
going. This also includes
ensuring security is adequate.
New harbour facility was
constructed along with
additional fencing, gates and
stillage for timber.  Dredging is
carried out bi-annually.  Works
have been completed at
lifeboat station and new sheet
piling to be installed along
timber jetty. The Ayrshire
Roads Alliance operates from
and manage risk of
enforcement action and
penalties should HSE become
involved.
Issues identified in Health and Safety
Surveys are recorded on Issues Log
along with corrective actions to rectify
/ bring up to the required standard. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
South Ayrshire Council
continues to have ownership
for and maintenance of
depots/harbour within their
area.  Responsibility of
funding the various mitigation
actions identified in the
Issues Log sits solely within
the control of South Ayrshire
Council.  East Ayrshire
Council has ownership and
responsibility for their depots. 
21/11/2 
33
Development
Control –
Road Bonds
Inadequate coupon values of
Road Bonds exposes the
Roads Authority to a potential
shortfall if the roads works
have to be completed by them
in the event that a developer
defaults.
The coupon value of Road Bonds
that are more than three years old
are reviewed to determine their
adequacy.  Where a shortfall is
identified, the developer will be
advised to increase the value of the
Road Bond held when an application
is made for an extension to the Road
Construction Consent (RCC), which
is normally valid for three years. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
If the road authority is
required to complete a
development road then only
the cost up to the value of
the Road Bond can be
recovered from the provider. 
Any shortfall has to be met
by the roads authority.  A
complete review of the
process of delivering road
bonds has been completed 
21/11/22 
34
Connect
Roads 
Residential loss of income to
the Ayrshire Roads Alliance
and expenditure incurred as a
lighting maintenance
subcontractor to Connect
Roads on the M77/Southern
Orbital, amount of exposure for
Ayrshire Roads Alliance is up
to £50,000 per year for the
main contractor.
Ayrshire Roads Alliance will reduce
exposure by limiting the amount
owing to us at any one time. 
Ayrshire Roads Alliance will insist on
payment by contractual terms or stop
doing the work. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
35
Bridges and
Structures
Inadequate inspection of
bridges and culverts for
deterioration due to aging,
increased live loads, cracking,
corrosion, environmental
effects (freeze and thaw
cycles) and fatigue
All principal bridge inspections
currently up to date in South
Ayrshire, with a rolling programme
being developed for East Ayrshire
along with additional resource for
principal inspection work.  All
General Bridge inspections are up to
date across both East Ayrshire and 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Bridges and culverts are
defined as structures with a
span in excess of 900mm.  21/11/22

Page 12

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
South Ayrshire.  Weak bridges are
monitored on a regular basis.  The
Ayrshire Roads Alliance provides
increased resilience in this matter. 
36
Bridges and
Structures
Inadequate maintenance of
structures, bridges and
culverts due to aging,
increased live loads, cracking
corrosion, environmental
effects (freeze and thaw
cycles) and fatigue
Rolling programme of repair,
rehabilitation or replacement (for
weak bridges) through Council
Capital Budgets. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Bridges and culverts are
defined as structures with a
span in excess of 900mm.  21/11/22 
37
Flooding Potential loss of all Grant
Aided Expenditure funding for
flooding mitigation schemes
administered by SEPA.
Seek capital funding from Council(s)
for priority flooding mitigation
schemes declared in Flood Risk
Management Plan. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Councils have a legal
duty under the Flood Risk
Management (Scotland) Act
2009 to implement flooding
mitigation schemes declared
in the Flood Risk
Management Plan. 
21/11/22 
38
Flooding Receipt of less Grant Aided
Expenditure funding than
anticipated for flooding
mitigation schemes
administered by SEPA.
Seek capital funding from Council(s)
to bridge funding gap for flooding
mitigation schemes declared in Flood
Risk Management Plan. 
2 4  8 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
The Councils have a legal
duty under the Flood Risk
Management (Scotland) Act
2009 to implement flooding
mitigation schemes declared
in the Flood Risk
Management Plan. 
21/11/22 
39
Flooding Potential lack of sufficient
funding for flooding mitigation
schemes if cost of schemes
exceeds Grant Aided
Expenditure (GAE) due to
Relief Events or Force
Majeure.
Seek capital funding from Council(s)
to bridge funding gap for flooding
mitigation schemes declared in Flood
Risk Management Plan. 
3 2  6 [C]
Bridges & Design
Manager
Head of Roads
– Ayrshire
Roads Alliance
Only 80% of principal funding
for flooding mitigation
scheme.  However increased
costs due to relief events or
force majeure is not funded. 
21/11/22 
40
Financial Potential swift decline in value
of Pound Sterling due to Force
Majeure or material adverse
change resulting in increased
costs in terms of fuel prices,
interest rates and insurance
premiums.
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business
Continuity Plans for office, depot and
harbour, as applicable 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
21/11/22 
41
Contractual
Agreement
Potential swift decline in value
of Pound Sterling followed by
market volatility over the short
to medium term resulting in
suppliers and contractors
terminating agreements due to
Force Majeure or material
adverse change.
Mitigation measures would be put in
place to prioritise front line services
as detailed in the specific Business
Continuity Plans for office, deport
and harbour, as applicable. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk.  The impact
of the United Kingdom exit
from the European Union has
still to be evaluated.  On-
going discussions with
Transport Scotland, COSLA
and Ayrshire Roads Alliance
on the impacts on the
transport network. 
21/11/22

Page 13

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
42
GDPR  The existing Data Protection
Act 2018 was brought about by
the General Data Protection
Regulation (GDPR) which is
an EU Regulation that sets out
the changes that the UK will
implement in a new Data
Protection Act.
Follow Corporate Procedures 
3 3  9 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
43
Presence of
Coal Tar within
the
carriageway
network
Coal Tar is a known material
used in the construction of
carriageways until the mid-80s
and is now known as a
carcinogen and hazardous
waste material.
Reduce the level of risk by coring all
works prior to design.
Ensure an appropriate solution within
the design is prepared which is either
to retain in-situ and record presence,
or remove and dispose of in
accordance with current guidelines. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed Risk; Ayrshire
Roads Alliance has a duty of
care to all employees in
accordance with the Health
and Safety at Work Act
1974,Construction Design
and Management
Regulations 2015 and the
disposal of hazardous waste. 
21/11/22 
44
Service The impact of the United
Kingdom exit from the
European Union
Mitigation measures are in place to
prioritise front line services as
detailed in the specific Business
Continuity Plans for office, depot and
harbour as applicable. 
4 3  12 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Managed risk.  Ongoing
discussions with Transport
Scotland, COSLA and
Ayrshire Roads Alliance on
the impacts on the transport
network. 
21/11/22 
45
Transport Increased cost of vehicle
maintenance due to lack of
investment in fleet
replacement
To mitigate the risk of increased
maintenance costs through lack of
fleet investment a comprehensive
maintenance programme is in place
for all vehicles in addition to a vehicle
replacement programme developed
to identify the optimum life cycle for
fleet. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
46
Transport Workshop performance and
training levels
Without appropriate level of
performance and training provision
there is a risk to operational
performance for management of the
fleet.
To address this, performance levels
are monitored on a daily and weekly
basis and ongoing training is
provided to staff for refresher training
as well as familiarisation training on
new fleet and plant vehicles. 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
47
Transport Loss of trained and competent
professional staff through
retirement or turnover
The movement of staff always has a
chance of happening but to ensure
the impact of this is minimised, an
ongoing apprenticeship programme
is in place with 2 apprentices in
transport being trained in all aspects
of fleet maintenance and repair. 
3 4  12 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Due to retirements and staff
leaving for better paid
mechanic roles elsewhere
the number of mechanics
has fallen from 10 to 7.
Multiple attempts have been
made to recruit replacement
mechanics with no success 
21/11/22

Page 14

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review 
so far. Changes have been
made to the recruitment
process in terms of
information being made
available as well as channels
used to advertise such as a
higher number of social
media websites. This issue is
being closely monitored and
further action may be
required. 
48
Transport Loss of restriction of fuel due
to any event that has an effect
on the Services provision of
fuel to departments, including
the occurrence of risks both
foreseen and unforeseen e.g.
industrial action
To mitigate the impact of losing
access or having a restricted access
to fuel, a contingency plan has been
established which sets out the
emergency management actions that
will be taken that include designated
fuelling stations and the prioritisation
of fleet, putting non-essential
vehicles off the road. 
2 4  8 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance
Further mitigation measures
have recently been put in
place to allow for fuel to be
drawn manually should there
be a prolonged loss of
electrical supply to the fuel
pumps. 
21/11/22 
50
Transport Loss off / restrictions on
Councils O Licence 
A comprehensive maintenance
regime has been established that
follows all guidance from DVSA and
the Traffic Commissioner to ensure
that the O-Licence is protected.
In addition, compliance activities are
established and in place and a
regular external audit is carried out
by the Freight Transport Association
every 2 years to ensure that all
processes are performing to the
required standard. 
1 5  5 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
51
Transport Loss of operational base for
any reason (Crookedholm
Depot)
To mitigate the impact of the loss of
the transport depot and garage,
business contingency plans have
been developed that highlight how
and where office based staff will work
in addition to the steps to ensure that
maintenance is undertaken, which
would be to activate external
maintenance frameworks. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
52
Transport Savings targets not achieved
(as per the Best Value Service
Review)
To mitigate the impact of the loss of
the transport depot and garage,
business contingency plans have
been developed that highlight how
and where office based staff will work
in addition to the steps to ensure that
maintenance is undertaken which 
1 3  3 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22

Page 15

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
would be to activate external
maintenance frameworks. 
53
Transport IT systems loss from any
cause for an extended period
may potentially effect the
operations of the transport
service which in turn will affect
service delivery and may
cause reputational damage to
the Council.
To prevent fallout from IT system
failure, a business contingency plan
has been developed as well as a
back up process to revert to paper
based recording systems for fleet
management and maintenance. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
54
Transport Failure to comply with Health
and Safety duties
To ensure that Health and Safety
processes are always followed, this
is a standing agenda item held at
monthly management meetings.  In
addition to a separate H&S group
that meets on a quarterly basis with
the H&S Officer.  Risk assessments
and safe systems of work have also
been developed and are in place with
H&S assistance. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   
21/11/22 
55
Transport Loss of utilities for an extended
time
Business continuity plans are in
place to allow for the whole service to
continue to function in the case that
utilities are lost for an extended
period of time. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
56
Transport Loss of confidential information
and appropriate handling of
information will lead to
breaches of data protection
and potential significant
financial penalties being
incurred by the Council
All staff that handle personal details
have undertaken e-learning to advise
of appropriate data protection steps
required and where appropriate
electronic systems are in place for
recording and management of
personal data to avoid paper being
lost or misplaced. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
57
Transport Passenger transport – late /
non-attendance / vehicle
breakdown by pick up vehicle
– Failure of service as Service
as user would miss Transport
link connection / arrives late at
destination activity / part
activity
The delivery of passenger transport
is managed on the Council’s behalf
by SPT.
If there is an issue where there is a
failure in service provision SPT would
be required to organise a
replacement service, working in
conjunction with Officer locally within
EAC. 
2 2  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
58
Transport Passenger transport – escort
not in attendance ASN
contracts / Council owned
vehicles service failure. 
Service not able to be provided
until escort arrives.  Server
Should an escort not be available
H&SC services would arrange to
provide another responsible
individual available to ensure that the
service can be delivered. 
1 4  4 [T]
Strategic      
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22

Page 16

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
user misses ac  tivity / part
activity  
In the unlikely case this cannot be
accommodated, the parent would be
notified and alternative arrangements
made for the transport of the child to
the school. 
59
Transport No driver available to deliver
service due to annual leave /
sickness absence. Service not
able to be provided service
user misses activity / part
activity
Any shortage of driver would result in
arranging for an alternative qualified
individual within transport services to
drive, or to work with Coalfield
Community Transport to deliver the
service. 
1 3  3 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
60
Transport Passenger transport :
Emergency closure of schools
and contractors unable to
provide transport within
relevant timescales
Should schools need to close
unexpectedly, all parents will be
contacted to request that children are
collected ASAP.  Teachers will
remain with children until the last one
has been collected safely by a
parent. 
1 4  4 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
61
Transport Passenger Transport:
Documentation out of date risk
to service users.  Potentially
inappropriate individuals,
inappropriate vehicles used
being used to provide service
Documentation is reviewed and
approved on an annual basis to
ensure that the correct data is held
for pupils, parents, schools and
transport operator information.  1  5  5 [T]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
62
Transport Passenger Transport:
Contractor unable to fulfil
obligations due to bankruptcy
etc.  Service failure not able to
be provided until alternative
arrangements made.  Server
user misses activity / part
activity
SPT manage all transport on behalf
of EAC.  In the case of a contractor
going out of business, an alternative
contractor will be sought.  Where this
cannot be provided, parents will be
contacted and alternative
arrangements may need to be made
for the provision of transporting
school children such as providing a
mileage allowance to parents until an
alternative solution can be
implemented. 
1 4  4 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22 
63
Transport Failure to mitigate the potential
impacts of BREXIT including a
worst case scenario “no deal”
withdrawal
There remains a significant number
of unknown issues surrounding Brexit
as no trade deals have been struck
with the EU yet.  It is possible that
there will be impacts on time and
cost in relation to delivery of vehicles
and parts from the EU but this
remains unknown.
The service has engaged with all
suppliers to obtain up to date
information on any potential issues
that may be known and this will 
3 3  9 [C]
Strategic   
Manager
Head of Roads
– Ayrshire
Roads Alliance   21/11/22

Page 17

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
remain an ongoing process until the
final details of Brexit emerges.
64 Material
Shortages and
Price
Increases
Steel products, timber,
electrical equipment and
aggregates have seen a price
increase with aggregates
prices falling back in the
spring.
This is as a result of COVID19
affecting suppliers, supply
chains, shipping and
transportation. Construction
activity rose rapidly after
lockdown.
Increased admin at UK ports
due to EU Trade Cooperation
has resulted in increased
transportation costs and
surcharges. 
Where there are problems we are
working with supplier to optimise
deliveries to get procure best value
under the circumstances.
4 3 12 [C] Strategic
Manager
Head of Service
– Ayrshire
Roads Alliance
This will be under constant
review with contractors. 
21/11/22
65 Storage
Related Risks
Theft / Damage of Stores Risk is very low as there are many
measures that have been put in
place.  For example – CCTV
cameras, secure entry to the depots,
insurance covers all depots for theft /
damage, robust store person / key
holder procedures in place
1 4 4 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
21/11/22
66 Ash Die Back Potential for death or injury as
a result of ash dieback related
accidents, both to
professionals working on trees,
and to the general public
Increased safety issues due to
declining ash trees on roads,
owned and managed land
such as in county parks,
housing, estates, schools,
routes to school, active travel
routes and other well-used
paths
Risks to statutory functions or
service delivery such as
retaining safe schools, public
open spaces or roads
Risks to staff and community
from trees on adjacent land
falling into your estate 
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   
21/11/22

Page 18

APPENDIX 2: AYRSHIRE ROADS ALLIANCE RISK REGISTER                                                                                                                                                                                                                                                                       
Risk ID Risk Category Risk Description Risk Mitigation Actions Likelihood Severity Risk Rating after
Mitigation measures
Responsible for
managing the risk
Risk Owner Additional Comments Date of last
review
67  Ukrainian Crisis 
Increasing cost of bitumen and
the potential of short supply
due to Russian sanctions and
increased costs.
Pre-programming with suppliers and
contractors.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   21/11/22
68  Impact on Fuel
No longer permitted to use red
diesel within construction
vehicles. This has an impact
on project costs and the
overall programme.
Reviewing alternative forms of fleet,
however, this brings additional cost.
4 3 12 [C] Strategic
Manager
Head of Service
Ayrshire Roads
Alliance   21/11/22