THE AYRSHIRE SHARED SERVICE JOINT COMMITTEE 
4tth NOVEMBER 2022 
AYRSHIRE ROADS ALLIANCE
REVENUE FINANCIAL MONITORING REPORT 
Report by Chief Financial Officer & Head of
Finance & ICT 
PURPOSE OF REPORT 
1 The purpose of this Report is to update the Joint Committee on the revenue
budget monitoring position for the year to 31st July 2022, for the Ayrshire Roads
Alliance. 
2 It is recommended that the Joint Committee 
(i) Note the financial management position of the Ayrshire Roads
Alliance.
(ii) Requests a further financial update at the next meeting of the Joint
Committee.
(iii) Otherwise, notes the content of this Report 
REVIEW OF FUNDING MECHANISM 
3 The Joint Committee approved a Report on 23 May 2014 describing the budget
monitoring arrangements for the Ayrshire Roads Alliance. 
4 As part of the Detailed Business Case the service budget is split between
strategic service delivery and local service delivery.  This separates out the
core/recurring costs of service delivery from the local service costs at a single
Council level.  This ensures that decisions on the level of local spend remain
with local Members, and ensures that the local Members retain control of their
local roads budgets.  Appendix 1 provides a breakdown of this split. 
5 At its meeting of 19th February 2016, Committee agreed a change to how
Strategic Service Delivery would be allocated between the two Councils. A
smaller group of core Strategic Delivery staff have been identified and their
costs continue to be split equally. The remaining Strategic Delivery costs would
be apportioned in line with Local Delivery budget inputs plus actual capital
expenditure in-year.

Page 2

CLASSIFICATION: PUBLIC 
BUDGET MONITORING POSITION 
6 The overall outturn for 2022-23 is anticipated to be £0.399m less than budget. 
7 Strategic Delivery estimated out-turn is £0.324m less than budget. 
Strategic Service Delivery Combined
(£m)
Initial Budget 3.822
Probable Outturn 3.498
Probable Variance (0.324) 
8 East Ayrshire Local Delivery projected out-turn is £0.141m less than budget
and South Ayrshire Local Delivery £0.066m greater than budget. 
9 Summary information is provided in the table below. A full budget monitoring
statement, including reasons for major variances is attached at Appendix 2.    
Service Division
Annual Estimate
2022/23           
£m
Projected
Actual to 31/3/23            
£m
Variance
(Favourable) /
Adverse       
£m
STRATEGIC DELIVERY 3.822 3.498 (0.324)
LOCAL DELIVERY - EAST AYRSHIRE 4.227 4.086 (0.141)
LOCAL DELIVERY - SOUTH AYRSHIRE 4.472 4.538 0.066
TOTAL 12.521 12.122 (0.399) 
10 The position for each Council is shown below: 
EAC
(£m)
SAC
(£m)
TOTAL
(£m)
Strategic Delivery (0.118) (0.206) (0.324)
Local Delivery (0.141) 0.066 (0.075)
2022-23 Variance (0.259) (0.140) (0.399) 
FINANCIAL IMPLICATIONS 
11 The available revenue budget for the Ayrshire Roads Alliance for 2022-23 is
£12.521m. The budget will continue to be monitored and reported to the 
Joint Committee. 
TIMBER TRANSPORT 
12 At the meeting of the Joint Committee on 23rd June 2017, further information
was requested in relation to timber transport funding. The undernoted table

Page 3

CLASSIFICATION: PUBLIC 
provides an analysis of relevant project and Timber Transport contributions for
2022-23 to date. 
2022-23
Actual to
date
(£m)
2022-23
Probable
Outturn(£m)
South Ayrshire  
Expenditure on Projects 0.100 0.255
Timber Transport
Contribution
0.148 0.148 
LEGAL IMPLICATIONS 
13 The work of the Ayrshire Roads Alliance is undertaken in accordance with 
relevant legislation. 
HUMAN RESOURCES IMPLICATIONS 
14 The establishment of the Ayrshire Roads Alliance is dependent on the available
budget. Available budget and human resource requirements will be reviewed
as part of budget monitoring. 
COMMUNITY / COUNCIL PLAN IMPLICATIONS 
15 The work undertaken by the Ayrshire Roads Alliance aligns with the Community
Plan for East Ayrshire Council; and the Council Plan for South Ayrshire Council. 
RISK MANAGEMENT IMPLICATIONS
16 Appropriate financial monitoring arrangements are in place to mitigate risk.  This
is included in the Ayrshire Roads Alliance Risk Register.  Regular meetings are
held between relevant finance staff and the Ayrshire Roads Alliance. 
LIST OF APPENDICES 
Appendix One - Split between Strategic and Local Service Delivery
Appendix Two - Financial Monitoring Report 
BACKGROUND PAPERS 
None 
For further information on this report, please contact Kevin Braidwood, Head of Roads
- Ayrshire Roads Alliance on 01563 503164

Page 4

CLASSIFICATION: PUBLIC 
Implementation Officer: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance
on 01563 503164

Page 5

CLASSIFICATION: PUBLIC 
Appendix 1 – Split Between Strategic and Local Service Delivery
Strategic Service Delivery Local Service Delivery
Transportation, Development Control
and Road Safety
Local Transport Strategy; Transportation
Policy; Road Safety Plan; Travel Planning,
Cycling Strategy; Planning Applications;
Road Construction Consents; Development
Planning, Council/Partner  Liaison, Section
75 Agreements;  Road Safety Schemes;
Road Safety Audits;  School Travel Plans;
School Crossing Patrol; Road Safety
Education. 
Transportation, Development
Control and Road Safety
Maintenance of Bus Shelters; Split
Cycle Offset Optimisation Technique
(SCOOT) systems (an adaptive
control system for controlled road
crossings); Development Control;
Bus Shelter Advertising;
Shopmobility; Construction of Road
Safety Schemes. 
Asset, Traffic and Parking
Asset Management Plan; Roads
Improvement Plan; Infrastructure Surveys;
Inventory Management; Scottish Roadworks
Register; Issue of Permits; Performance
Monitoring; Accident Investigation and
Prevention; Traffic Orders; Traffic Counts;
and Parking Strategy. 
Asset, Traffic and Parking
Maintenance of Traffic signals, traffic
signs, Car Park Maintenance and
Parking Enforcement.
Design and Environment
Flood Risk Management Strategy; Flood
Risk Management Plans; Watercourses;
Flood Mitigation; Coastal Protection;
Inspection  of Piers & Harbours; Bridge
Inspections and Maintenance; Structural
Assessments; Technical Approval; 
Abnormal Load Routing; and Design of
Major and Minor Road Schemes and
Improvements. 
Design and Environment
Maintenance of Watercourses,
Bridges, Retaining Walls, Piers and
Harbours. 
Operations
Carriageway Inspections; Winter Service
Planning; Programming of Proactive,
Reactive and Cyclic Maintenance; Street
Lighting Design and Management; and
Festive Lighting.
Operations
Proactive, Reactive, Cyclic
Maintenance of Roads and
Footways; Winter and Weather
Emergency Service; Proactive and
Reactive Maintenance of Streetlights;
Electricity costs for streetlights. 
Support Services        
HR, Finance, ICT, and Administrative
Support.

Page 6

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4 NOVEMBER 2022
2022/23 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY
CLASSIFICATION: OFFICIAL-PROTECT 
SERVICE SUMMARY - OVERVIEW POSITION 
It is anticipated that Ayrshire Roads Alliance will outturn £0.399m less than budget. 
Actual
Expenditure
as at P4           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Service Division Annual
Estimate
2022/23           
£m
Projection to
31/3/23            
£m
Variance
(Favourable) /
Adverse       
£m
1.119 29.3% STRATEGIC DELIVERY 3.822 3.498 (0.324)
1.803 42.7% LOCAL DELIVERY - EAST AYRSHIRE 4.227 4.086 (0.141)
1.964 43.9% LOCAL DELIVERY - SOUTH AYRSHIRE 4.472 4.538 0.066
4.886 39.0% TOTAL 12.521 12.122 (0.399)    
PROPOSED REDUCTION FOLLOWING LINE BY LINE 0.000 0.000 0.000    
TOTAL FOLLOWING LINE BY LINE REVIEW 12.521 12.122 (0.399)    
EARMARKED FUNDS TO BE CARRIED FORWARD 0.000 0.000 0.000
4.886 39.0% TOTAL INCLUDING EARMARKED FUNDS 12.521 12.122 (0.399) 
STRATEGIC DELIVERY 
This variance mainly reflects staff turnover savings due to vacant posts (£0.243m) and
reduced insurance costs relating to ARA South (£0.087m), along with additional income
(£0.039m). This is partly offset by additional expenditure on computing (£0.020m), road
safety training materials (£0.010m) and other supplies and services (£0.012m). 
LOCAL DELIVERY – EAST AYRSHIRE
This variance mainly reflects vacancies and turnover (£0.444m) particularly within Roads
Maintenance. This is partly offset by a shortfall in on-street parking income (£0.103m),
additional expenditure on Supplies & Services (£0.143m) and additional fuel costs
(£0.062m) reflecting price increases. 
LOCAL DELIVERY – SOUTH AYRSHIRE
This variance mainly reflects additional expenditure on supplies and services (£0.112m)
and fuel price increases (£0.030m). This is partly offset by a saving on employee costs
(£0.081m) mainly as a result of vacancies.

Page 7

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4 NOVEMBER 2022
2022/23 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY
CLASSIFICATION: OFFICIAL-PROTECT 
STRATEGIC DELIVERY 
Actual
Expenditure
as at P4           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Service Division
Annual
Estimate
2022/23           
£m
Projection to
31/3/23            
£m
Variance
(Favourable) /
Adverse       
£m
0.973 26.0% EMPLOYEE COSTS 3.742 3.501 (0.241)
0.015 41.7% PREMISES COSTS 0.036 0.036 0.000
0.006 26.1% TRANSPORT COSTS 0.023 0.024 0.001
0.125 15.0% SUPPLIES & SERVICES 0.836 0.791 (0.045)
0.000 0.0% THIRD PARTY PAYMENTS 0.000 0.000 0.000
0.000 0.0% DEBT CHARGES 0.015 0.015 0.000
1.119 24.1% TOTAL EXPENDITURE 4.652 4.367 (0.285)
-0.357 43.0% INCOME -0.830 -0.869 (0.039)
0.762 19.9% NET EXPENDITURE 3.822 3.498 (0.324)    
PROPOSED REDUCTION FOLLOWING LINE BY LINE 0.000 0.000 0.000    
TOTAL FOLLOWING LINE BY LINE REVIEW 3.822 3.498 (0.324)    
EARMARKED FUNDS TO BE CARRIED FORWARD   0.000 0.000
0.762 19.9% TOTAL INCLUDING EARMARKED FUNDS 3.822 3.498 (0.324)

Page 8

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2021
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at     
31 March
2021
(£m)
Strategic Delivery
(0.241) 
(0.045) 
(0.039) 
0.001 
Employee Costs
This saving reflects turnover savings vacant posts and turnover savings
(£0.243m). This is partly offset by additional training costs (£0.002m). 
Supplies & Services
This variance mainly reflects a saving on South Ayrshire insurance
charges (£0.087m). This is partly offset by expenditure on computing
(£0.020m), road safety training materials (£0.010m) and a number of
small variances (£0.012m). 
Income
This variance reflects additional income from capital programmes
(£0.030m), and Cycling Scotland grant income (£0.009m). 
Other Variances
This represents other non-material variances within Strategic Delivery.
(0.324) Total reported variance

Page 9

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2021
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2021 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
LOCAL DELIVERY – EAST AYRSHIRE 
Actual
Expenditure
as at P4           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Detail Annual
Estimate
2022/23           
£m
Projection to
31/3/23            
£m
Variance
(Favourable) /
Adverse       
£m
0.730 23.2% EMPLOYEE COSTS 3.147 2.672 (0.475)
0.070 21.5% PREMISES COSTS 0.325 0.329 0.004
0.345 52.0% TRANSPORT COSTS 0.663 0.725 0.062
0.479 23.0% SUPPLIES & SERVICES 2.080 2.223 0.143
0.786 60.4% THIRD PARTY PAYMENTS 1.302 1.438 0.136
0.054 18.2% DEBT CHARGES 0.296 0.296 0.000
2.464 31.5% TOTAL EXPENDITURE 7.813 7.683 (0.130)
(0.661) 18.4% INCOME (3.586) (3.597) (0.011)
1.803 42.7% NET EXPENDITURE 4.227 4.086 (0.141)    
PROPOSED REDUCTION FOLLOWING LINE BY LINE 0.000 0.000 0.000    
TOTAL FOLLOWING LINE BY LINE REVIEW 4.227 4.086 (0.141)    
EARMARKED FUNDS TO BE CARRIED FORWARD 0.000 0.000 0.000
1.803 42.7% TOTAL INCLUDING EARMARKED FUNDS 4.227 4.086 (0.141)

Page 10

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2022
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at   
31 March
2021
(£m)
Local Delivery - East Ayrshire 
(0.475)                 
0.062         
0.143                     
0.136 
(0.011) 
0.004 
Employee Costs
This variance mainly reflects staff turnover due to vacant posts (£0.444m), an
employee recharge in respect of cross boundary working (£0.015m) and the
temporary removal of summer standby (£0.010m) partly offset by additional
training costs (£0.005m). 
Transport Costs
This variance mainly reflects increased expenditure on fuel as a result of price
increases 
Supplies & Services
This variance mainly reflects additional IT costs (£0.071m), particularly
in relation to, additional expenditure on roads maintenance materials
(£0.032m), consultancy costs in relation to two car parks within
Newmilns artificial intelligence surveying within roads (£0.018m) along
with a number of small variances across various headings (0.021m). 
Third Party Payments
This variance mainly reflects additional sub-contractor costs within
Traffic (£0.118m) which will mostly be offset by additional income, Street
Lighting (£0.007m) and Flood Prevention (£0.010m) 
Income
This variance mainly reflects additional Traffic income – see Third Party
Payments above (£0.114m), partly offset by a shortfall in on-street parking
income (£0.103m). 
Other Variances
This variance reflects non-material variances within Local Delivery –
East Ayrshire 
(0.141) Total reported variance

Page 11

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2022
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
LOCAL DELIVERY – SOUTH AYRSHIRE 
Actual
Expenditure
as at P4           
£m
Actual
Expenditure
as % of
Ann. Est.         
£m
Detail Annual
Estimate
2022/23           
£m
Projection to
31/3/23            
£m
Variance
(Favourable) /
Adverse       
£m
0.607 27.4% EMPLOYEE COSTS 2.217 2.136 (0.081)
0.078 46.4% PREMISES COSTS 0.168 0.181 0.013
0.419 45.8% TRANSPORT COSTS 0.915 0.957 0.042
0.772 43.9% SUPPLIES & SERVICES 1.758 1.870 0.112
1.039 74.4% THIRD PARTY PAYMENTS 1.397 1.681 0.284
0.000 0.0% DEBT CHARGES 0.106 0.106 0.000
2.915 44.4% TOTAL EXPENDITURE 6.561 6.931 0.370
-0.951 45.5% INCOME -2.089 -2.393 (0.304)
1.964 43.9% NET EXPENDITURE 4.472 4.538 0.066    
PROPOSED REDUCTION FOLLOWING LINE BY LINE 0.000 0.000 0.000    
TOTAL FOLLOWING LINE BY LINE REVIEW 4.472 4.538 0.066    
EARMARKED FUNDS TO BE CARRIED FORWARD 0.000 0.000 0.000
1.964 43.9% TOTAL INCLUDING EARMARKED FUNDS 4.472 4.538 0.066

Page 12

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2022
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT 
Projected
Variance at   
31 March
2021
(£m) 
Local Delivery - South Ayrshire 
(0.081) 
0.013 
0.042 
0.112 
0.284 
(0.304) 
Employee Costs
This variance mainly reflects staff turnover due to vacancies (£0.127m),
mainly within Roads Maintenance partly offset by an employee recharge
in relation to cross boundary working (£0.044m). 
Premises Costs
This variance mainly reflects non-domestic rates charges in relation to
bus shelters. 
Transport Costs 
This variance mainly reflects increased expenditure on fuel as a result of price
increases (£0.030m) and the hire of campervans (£0.011m), the latter
being offset by additional income. 
Supplies & Services
This variance mainly reflects additional roads maintenance materials (£0.026m),
computing costs (£0.074m) particularly in relation to artificial intelligence
surveying within roads along with a number of small variances across
various headings (£0.012m). 
Third Party Payments
This variance mainly reflects additional sub-contractor costs within Traffic
(£0.260m) and Design (£0.005m), which will mostly be offset by additional
income, along with coastal protection works (£0.019m). 
Income
This variance mainly reflects additional design income (£0.066m) and Traffic
income (£0.237m) – see Third Party Payments and Transport Costs. 
0.066 Total reported variance

Page 13

APPENDIX 2
AYRSHIRE SHARED SERVICES JOINT COMMITTEE
4th NOVEMBER 2022
2021/22 GENERAL SERVICES REVENUE BUDGET
AS AT 31 JULY 2022 – PERIOD 4
AYRSHIRE ROADS ALLIANCE
FINANCIAL PERFORMANCE SUMMARY 
CLASSIFICATION: OFFICIAL-PROTECT