Risk Register Report September 2022
North Ayrshire Council · 2 September 2022
Back to Ayrshire Shared Services Committee — 2 September 2022 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.
Page 1
AYRSHIRE SHARED SERVICE JOINT COMMITTEE 2 SEPTEMBER 2022 Report by the Head of Roads - Ayrshire Roads Alliance ________________________________________________________________ _ AYRSHIRE ROADS ALLIANCE RISK REPORT AND REGISTER ________________________________________________________________ _ PURPOSE OF REPORT 1. The purpose of this Report is to advise the Joint Committee on the management of risk associated with the Ayrshire Roads Alliance. RECOMMENDATIONS 2. It is recommended that the Joint Committee: i. Notes the risk register presented in this report; ii. Continues to receive updates on progress; and iii. Otherwise, notes the content of the report. BACKGROUND 3. A report detailing the general approach to the Risk Report and Risk Register was presented to the Joint Committee on 21 August 2014, where it was agreed that the Risk Report and Risk Register would be a standing item on the agenda. This would ensure that the risks are monitored and scrutinised at a minimum of a quarterly basis. MAIN REPORT/MAIN ISSUES 4. The management of risk aims to enable confident decision taking on risk and innovation, reduce waste and inefficiency, and lead to fewer unanticipated problems and crises that could undermine the performance and operation of the Ayrshire Roads Alliance. 5. The Risk Register is now in a new and improved format which will make it easier to review the individual risks which are now in a colour coded format. 6. The resulting revised risk register is contained in Appendix 2. Since the last Joint Committee, the following risk has been added: 67 – Ukrainian Crisis - Increasing cost of bitumen and the potential of short supply due to Russian sanctions and increased costs. 68 – Fuel Crisis - No longer permitted to use red diesel within construction vehicles. This has an impact on project costs and the overall programme
Page 2
The revised risk register illustrates the red, amber and green status and also illustrates whether the risk severity relates to time, indicated by [T] or cost, indicated by [C]. POLICY/COMMUNITY PLAN IMPLICATIONS 7. A well maintained road network will contribute to achieving the Community Plan objectives in relation to Economy & Skills and Safer Communities to maintain good access to our communities within East Ayrshire. 8. The matters referred to in this report contribute to South Ayrshire Council strategic objective of ‘Enhanced Environment through Social, Cultural and Economic Activities’ and within that to the outcome ‘Work with partners to improve roads and other infrastructure, to encourage house building and business investment that sustains local communities’. LEGAL IMPLICATIONS 9. The Risk Register is a management tool and this will not replace the existing statutory returns for risk and performance related information. HUMAN RESOURCES IMPLICATIONS 10. The Risk Register has no direct impact on human resources. EQUALITY IMPACT IMPLICATIONS 11. The Risk Register complements the Equality Impact Assessment by ensuring that any issues arising are adequately prioritised, managed and either eliminated or mitigated. FINANCIAL IMPLICATIONS 12. The Risk Register facilitates the existing scrutiny arrangements to manage, prioritise, and review the budget provided by East Ayrshire Council and South Ayrshire Council to the Ayrshire Roads Alliance. RISK IMPLICATIONS 13. The Risk Register assists in the prioritisation of risks that need to be mitigated by the Ayrshire Roads Alliance in order to reduce the overall risk to either Council and to comply with the Community Plan/Council Plan in both partner bodies.
Page 3
TRANSFORMATION STRATEGY 14. This Report aligns with the following design principle stated in the “Transformation Strategy 2017-2022”. • “Maximum value for our communities”, by ensuring the various elements of the Ayrshire Roads Alliance improves transport provision across our networks. Kevin Braidwood Head of Roads – Ayrshire Roads Alliance 19 August 2022 BACKGROUND PAPERS None LIST OF APPENDICES 1. Risk Register Scoring Matrix 2. Ayrshire Roads Alliance Risk Register Person to contact: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail: kevin.braidwood@ayrshireroadsalliance.org Implementation officer: Kevin Braidwood, Head of Roads - Ayrshire Roads Alliance Tel No. 01563 503164 E-mail: kevin.braidwood@ayrshireroadsalliance.org
Page 4
Appendix 1: Risk Register Scoring Matrix The Risk Matrix for deciding each of the risk factors (Likelihood x Severity) in a 5 by 5 matrix are illustrated in Table 1 below: Table 1: Risk Factors in Practical Form Following on from Table 1, the following Summary Risk Profile is colour coded to highlight the risk classification: Table 2: Summary Risk Profile Assessed Risk (LxS) Action Required Low Risk: 1 to 4 Acceptable/ can be accepted provided risk is managed. Medium Risk: 5 to 12 Undesirable/ must be avoided if reasonably practicable. High Risk: 15 to 25 Unacceptable risk - must be eliminated or moved to a lower level. Rare (1) Unlikely (2) Possible (3) Likely (4) Almost Certain (5) Catastrophic (5) 5 10 15 20 25 Very Serious (4) 4 8 12 16 20 Moderate (3) 3 6 9 12 15 Minor (2) 2 4 6 8 10 Insignificant (1) 1 2 3 4 5 Risk Likelihood Risk Severity
Page 5